KING ABDULAZIZ CITY FOR SCIENCE AND TECHNOLOGYGENERAL DIRECTORATE OF FACILITIES AND PROJECTS
Construction of Solar Panel Storage Buildingat KACST Al-Uyaynah Research Station
TECHNICAL REPORTContractor Name: Saad Bin Abdullah Bin Naji Contracting Est.
Date: 09.11.1436 (25.08.2015)____________________________________________________________________________
a. Electrical
Electrical Manhole not yet finished and no cables installed.
![Page 2: Technical Report Electrical Rev](https://reader034.vdocuments.us/reader034/viewer/2022051100/577c78451a28abe0548f5c74/html5/thumbnails/2.jpg)
KING ABDULAZIZ CITY FOR SCIENCE AND TECHNOLOGYGENERAL DIRECTORATE OF FACILITIES AND PROJECTS
Construction of Solar Panel Storage Buildingat KACST Al-Uyaynah Research Station
TECHNICAL REPORTContractor Name: Saad Bin Abdullah Bin Naji Contracting Est.
Date: 09.11.1436 (25.08.2015)____________________________________________________________________________
Electrical Room , No panelboard and main cable installed
.
Grounding Rod with Bare Copper outside the Building
![Page 3: Technical Report Electrical Rev](https://reader034.vdocuments.us/reader034/viewer/2022051100/577c78451a28abe0548f5c74/html5/thumbnails/3.jpg)
KING ABDULAZIZ CITY FOR SCIENCE AND TECHNOLOGYGENERAL DIRECTORATE OF FACILITIES AND PROJECTS
Construction of Solar Panel Storage Buildingat KACST Al-Uyaynah Research Station
TECHNICAL REPORTContractor Name: Saad Bin Abdullah Bin Naji Contracting Est.
Date: 09.11.1436 (25.08.2015)____________________________________________________________________________
Disconnecting Switches for ACCU
Electrical Recessed Indoor Luminaire on Mezzanine
![Page 4: Technical Report Electrical Rev](https://reader034.vdocuments.us/reader034/viewer/2022051100/577c78451a28abe0548f5c74/html5/thumbnails/4.jpg)
KING ABDULAZIZ CITY FOR SCIENCE AND TECHNOLOGYGENERAL DIRECTORATE OF FACILITIES AND PROJECTS
Construction of Solar Panel Storage Buildingat KACST Al-Uyaynah Research Station
TECHNICAL REPORTContractor Name: Saad Bin Abdullah Bin Naji Contracting Est.
Date: 09.11.1436 (25.08.2015)____________________________________________________________________________
Electrical Pendant Highbay Industrial Luminaire Installed on Main Storage Area
Surface Mounted Luminaires in Electrical and Communication Room
![Page 5: Technical Report Electrical Rev](https://reader034.vdocuments.us/reader034/viewer/2022051100/577c78451a28abe0548f5c74/html5/thumbnails/5.jpg)
KING ABDULAZIZ CITY FOR SCIENCE AND TECHNOLOGYGENERAL DIRECTORATE OF FACILITIES AND PROJECTS
Construction of Solar Panel Storage Buildingat KACST Al-Uyaynah Research Station
TECHNICAL REPORTContractor Name: Saad Bin Abdullah Bin Naji Contracting Est.
Date: 09.11.1436 (25.08.2015)____________________________________________________________________________
Outdoor Luminaire
WC Downlight Luminaire
![Page 6: Technical Report Electrical Rev](https://reader034.vdocuments.us/reader034/viewer/2022051100/577c78451a28abe0548f5c74/html5/thumbnails/6.jpg)
KING ABDULAZIZ CITY FOR SCIENCE AND TECHNOLOGYGENERAL DIRECTORATE OF FACILITIES AND PROJECTS
Construction of Solar Panel Storage Buildingat KACST Al-Uyaynah Research Station
TECHNICAL REPORTContractor Name: Saad Bin Abdullah Bin Naji Contracting Est.
Date: 09.11.1436 (25.08.2015)____________________________________________________________________________
Pendant Mounted Indoor Luminaire Installed on Loading/Unloading Area
Exit Lights Installed on all Exit Doors
![Page 7: Technical Report Electrical Rev](https://reader034.vdocuments.us/reader034/viewer/2022051100/577c78451a28abe0548f5c74/html5/thumbnails/7.jpg)
KING ABDULAZIZ CITY FOR SCIENCE AND TECHNOLOGYGENERAL DIRECTORATE OF FACILITIES AND PROJECTS
Construction of Solar Panel Storage Buildingat KACST Al-Uyaynah Research Station
TECHNICAL REPORTContractor Name: Saad Bin Abdullah Bin Naji Contracting Est.
Date: 09.11.1436 (25.08.2015)____________________________________________________________________________
Floor Mounted Socket Installed at Mezzanine
Switches and Sockets
![Page 8: Technical Report Electrical Rev](https://reader034.vdocuments.us/reader034/viewer/2022051100/577c78451a28abe0548f5c74/html5/thumbnails/8.jpg)
KING ABDULAZIZ CITY FOR SCIENCE AND TECHNOLOGYGENERAL DIRECTORATE OF FACILITIES AND PROJECTS
Construction of Solar Panel Storage Buildingat KACST Al-Uyaynah Research Station
TECHNICAL REPORTContractor Name: Saad Bin Abdullah Bin Naji Contracting Est.
Date: 09.11.1436 (25.08.2015)____________________________________________________________________________
On/Off Pushbutton Switch for Highbay Lightings
Dip Switch
![Page 9: Technical Report Electrical Rev](https://reader034.vdocuments.us/reader034/viewer/2022051100/577c78451a28abe0548f5c74/html5/thumbnails/9.jpg)
KING ABDULAZIZ CITY FOR SCIENCE AND TECHNOLOGYGENERAL DIRECTORATE OF FACILITIES AND PROJECTS
Construction of Solar Panel Storage Buildingat KACST Al-Uyaynah Research Station
TECHNICAL REPORTContractor Name: Saad Bin Abdullah Bin Naji Contracting Est.
Date: 09.11.1436 (25.08.2015)____________________________________________________________________________
Duplex Socket Outlet at Main Storage Area
380 Volts Industrial Outlet Sample on Site
![Page 10: Technical Report Electrical Rev](https://reader034.vdocuments.us/reader034/viewer/2022051100/577c78451a28abe0548f5c74/html5/thumbnails/10.jpg)
KING ABDULAZIZ CITY FOR SCIENCE AND TECHNOLOGYGENERAL DIRECTORATE OF FACILITIES AND PROJECTS
Construction of Solar Panel Storage Buildingat KACST Al-Uyaynah Research Station
TECHNICAL REPORTContractor Name: Saad Bin Abdullah Bin Naji Contracting Est.
Date: 09.11.1436 (25.08.2015)____________________________________________________________________________
Wall Mounted Duplex Socket in Rooms
Disconnecting Switch and Push Button for Roll up Shutter
![Page 11: Technical Report Electrical Rev](https://reader034.vdocuments.us/reader034/viewer/2022051100/577c78451a28abe0548f5c74/html5/thumbnails/11.jpg)
KING ABDULAZIZ CITY FOR SCIENCE AND TECHNOLOGYGENERAL DIRECTORATE OF FACILITIES AND PROJECTS
Construction of Solar Panel Storage Buildingat KACST Al-Uyaynah Research Station
TECHNICAL REPORTContractor Name: Saad Bin Abdullah Bin Naji Contracting Est.
Date: 09.11.1436 (25.08.2015)____________________________________________________________________________