technical note - tn 082: 2016 - transport for nsw · and is the network design and standards...

26
Technical Note - TN 082: 2016 © State of NSW through Transport for NSW Page 1 of 1 Superseded by T HR CI 12180 ST v2.0, 02/09/2019 Technical Note - TN 082: 2016 Subject: Revised reference to risk criteria Issued date: 21 December 2016 For queries regarding this document [email protected] www.asa.transport.nsw.gov.au This technical note has been issued by the Asset Standards Authority (ASA) to notify the following. The risk criteria to be used by the Authorised Engineering Organisations (AEOs) providing engineering services to TfNSW are contained in T MU MD 20002 ST Risk Criteria for Organisations Providing Engineering Services, version 1.0. 30-ST-164 TfNSW Enterprise Risk Management (TERM) Standard provides the risk criteria to be used by TfNSW. All references to the TERM standard in this document, where applicable to AEOs, shall read as T MU MD 20002 ST. Authorisation: Technical content prepared by Checked and approved by Interdisciplinary coordination checked by Authorised for release Signature Date Name Richard Adams Andy Tankard Andy Tankard Graham Bradshaw Position Manager Safety and Risk Assurance Principal Manager SQER Principal Manager SQER Director Network Standards and Services

Upload: others

Post on 08-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Technical Note - TN 082: 2016 - Transport for NSW · and is the network design and standards authority for defined NSW transport assets. The ASA is responsible for developing engineering

Technical Note - TN 082: 2016

© State of NSW through Transport for NSW Page 1 of 1

Sup

erse

ded

by T

HR

CI 1

2180

ST

v2.0

, 02/

09/2

019

Technical Note - TN 082: 2016

Subject: Revised reference to risk criteria

Issued date: 21 December 2016

For queries regarding this document [email protected]

www.asa.transport.nsw.gov.au

This technical note has been issued by the Asset Standards Authority (ASA) to notify the

following.

• The risk criteria to be used by the Authorised Engineering Organisations (AEOs) providing

engineering services to TfNSW are contained in T MU MD 20002 ST Risk Criteria for

Organisations Providing Engineering Services, version 1.0.

• 30-ST-164 TfNSW Enterprise Risk Management (TERM) Standard provides the risk criteria

to be used by TfNSW.

• All references to the TERM standard in this document, where applicable to AEOs, shall read

as T MU MD 20002 ST.

Authorisation:

Technical content prepared by

Checked and approved by

Interdisciplinary coordination checked by

Authorised for release

Signature

Date

Name Richard Adams Andy Tankard Andy Tankard Graham Bradshaw

Position Manager Safety and Risk Assurance

Principal Manager SQER

Principal Manager SQER

Director Network Standards and Services

Page 2: Technical Note - TN 082: 2016 - Transport for NSW · and is the network design and standards authority for defined NSW transport assets. The ASA is responsible for developing engineering

Sup

erse

ded

by T

HR

CI 1

2180

ST

v2.0

, 02/

09/2

019

Active Transport Links on the Rail Corridor

T HR CI 12180 ST

Standard

Version 1.0

Issued date: 05 May 2015

Important Warning

This document is one of a set of standards developed solely and specifically for use on public transport assets which are vested in or owned, managed, controlled, commissioned or funded by the NSW Government, a NSW Government agency or a Transport Agency (as defined in the Asset Standards Authority Charter). It is not suitable for any other purpose.

You must not use or adapt it or rely upon it in any way unless you are authorised in writing to do so by a relevant NSW Government agency. If this document forms part of a contract with, or is a condition of approval by a NSW Government agency, use of the document is subject to the terms of the contract or approval.

This document may not be current. Current standards are available for download from the Asset Standards Authority website at www.asa.transport.nsw.gov.au.

© State of NSW through Transport for NSW

Page 3: Technical Note - TN 082: 2016 - Transport for NSW · and is the network design and standards authority for defined NSW transport assets. The ASA is responsible for developing engineering

T HR CI 12180 ST Active Transport Links on the Rail Corridor

Version 1.0 Issued date: 05 May 2015

Standard governance

Owner: Lead Civil Engineer, Asset Standards Authority

Authoriser: Chief Engineer Rail, Asset Standards Authority

Approver: Director, Asset Standards Authority on behalf of the ASA Configuration Control Board

Document history

Version Summary of Changes

1.0 First issue

For queries regarding this document, please email the ASA at [email protected] or visit www.asa.transport.nsw.gov.au

© State of NSW through Transport for NSW

Sup

erse

ded

by T

HR

CI 1

2180

ST

v2.0

, 02/

09/2

019

Page 4: Technical Note - TN 082: 2016 - Transport for NSW · and is the network design and standards authority for defined NSW transport assets. The ASA is responsible for developing engineering

T HR CI 12180 ST Active Transport Links on the Rail Corridor

Version 1.0 Issued date: 05 May 2015

Preface The Asset Standards Authority (ASA) is an independent unit within Transport for NSW (TfNSW)

and is the network design and standards authority for defined NSW transport assets.

The ASA is responsible for developing engineering governance frameworks to support industry

delivery in the assurance of design, safety, integrity, construction, and commissioning of

transport assets for the whole asset life cycle. In order to achieve this, the ASA effectively

discharges obligations as the authority for various technical, process, and planning matters

across the asset life cycle.

The ASA collaborates with industry using stakeholder engagement activities to assist in

achieving its mission. These activities help align the ASA to broader government expectations

of making it clearer, simpler, and more attractive to do business within the NSW transport

industry, allowing the supply chain to deliver safe, efficient, and competent transport services.

The ASA develops, maintains, controls, and publishes a suite of standards and other

documentation for transport assets of TfNSW. Further, the ASA ensures that these standards

are performance-based to create opportunities for innovation and improve access to a broader

competitive supply chain.

This standard specifies the technical requirements for the installation of active transport links. It

has been developed from RailCorp standard ESC 530 Cycleways on the Rail Corridor,

Version 1.1.

ESC 530 is withdrawn with the publication of this standard.

This standard is a first issue.

© State of NSW through Transport for NSW Page 3 of 25

Sup

erse

ded

by T

HR

CI 1

2180

ST

v2.0

, 02/

09/2

019

Page 5: Technical Note - TN 082: 2016 - Transport for NSW · and is the network design and standards authority for defined NSW transport assets. The ASA is responsible for developing engineering

T HR CI 12180 ST Active Transport Links on the Rail Corridor

Version 1.0 Issued date: 05 May 2015

Foreword This standard is intended to be used by competent personnel engaged in the provision of

services relating to rail infrastructure. Compliance with the requirements in this standard will

not, by itself, be sufficient to ensure that satisfactory outcomes will be produced. Personnel

providing services based on the standard need to bring appropriate expertise to the matters

under consideration.

In addition to the requirements of this standard, asset decisions shall take into account the life

cycle cost considerations specified in T MU AM 01001 ST Life Cycle Costing.

If, when using the standard, it is considered that the intent of the stated requirements is not

clear, a clarification should be sought from the ASA.

© State of NSW through Transport for NSW Page 4 of 25

Sup

erse

ded

by T

HR

CI 1

2180

ST

v2.0

, 02/

09/2

019

Page 6: Technical Note - TN 082: 2016 - Transport for NSW · and is the network design and standards authority for defined NSW transport assets. The ASA is responsible for developing engineering

T HR CI 12180 ST Active Transport Links on the Rail Corridor

Version 1.0 Issued date: 05 May 2015

Table of contents 1. Introduction .............................................................................................................................................. 6

2. Purpose .................................................................................................................................................... 6 2.1. Scope ..................................................................................................................................................... 6 2.2. Application ............................................................................................................................................. 6

3. Reference documents ............................................................................................................................. 7

4. Terms and definitions ............................................................................................................................. 8

5. Safety requirements ................................................................................................................................ 9

6. Heritage requirements ............................................................................................................................ 9

7. General requirements ........................................................................................................................... 10

8. Urban design considerations ............................................................................................................... 11

9. Design requirements – Type 1 ATLs ................................................................................................... 11 9.1. Location for Type 1 ATLs ..................................................................................................................... 14 9.2. Drainage for Type 1 ATLs .................................................................................................................... 14 9.3. Fences for Type 1 ATLs ...................................................................................................................... 14 9.4. Access gates for Type 1 ATLs ............................................................................................................. 15 9.5. Lighting for Type 1 ATLs ...................................................................................................................... 15 9.6. Electrolysis – Type 1 ATL .................................................................................................................... 15 9.7. Services affected by Type 1 ATLs ....................................................................................................... 16 9.8. Signage for Type 1 ATLs ..................................................................................................................... 16 9.9. Sustainability of Type 1 ATLs .............................................................................................................. 16

10. Design requirements – Type 2 ATLs ................................................................................................... 17 10.1. Location of Type 2 ATLs .................................................................................................................. 20 10.2. Drainage for Type 2 ATLs ................................................................................................................ 20 10.3. Fences for Type 2 ATLs .................................................................................................................. 20 10.4. Access gates for Type 2 ATLs ......................................................................................................... 21 10.5. Lighting for Type 2 ATLs .................................................................................................................. 21 10.6. Electrolysis – Type 2 ATL ................................................................................................................ 21 10.7. Services affected by Type 2 ATLs ................................................................................................... 21 10.8. Signage for Type 2 ATLs ................................................................................................................. 22 10.9. Sustainability of Type 2 ATLs .......................................................................................................... 22

11. Design and documentation .................................................................................................................. 22 11.1. Design stage documentation ........................................................................................................... 23 11.2. Work-as-executed drawings ............................................................................................................ 24 11.3. Deed ................................................................................................................................................ 24

12. Construction .......................................................................................................................................... 24 12.1. Protection of rail infrastructure ......................................................................................................... 24

13. Maintenance ........................................................................................................................................... 25

14. Decommissioning or disposal ............................................................................................................. 25

© State of NSW through Transport for NSW Page 5 of 25

Sup

erse

ded

by T

HR

CI 1

2180

ST

v2.0

, 02/

09/2

019

Page 7: Technical Note - TN 082: 2016 - Transport for NSW · and is the network design and standards authority for defined NSW transport assets. The ASA is responsible for developing engineering

T HR CI 12180 ST Active Transport Links on the Rail Corridor

Version 1.0 Issued date: 05 May 2015

1. Introduction Active transport links (ATL) include footpaths, cycleways, and shared walking and cycle paths.

In certain locations, the rail corridor could provide an opportunity to develop active transport

facilities.

2. Purpose This standard specifies the design, construction, maintenance and disposal or decommissioning

requirements of active transport links within the TfNSW heavy rail corridor.

2.1. Scope This standard specifies the design requirements for two types of ATLs for use within the TfNSW

heavy rail corridor:

• Type1 – ATLs that are separated from the activities of the railway maintainer and the

railway operator

• Type 2 – ATLs that are not separated from the activities of the railway maintainer and the

railway operator

2.2. Application This standard applies to the design of new ATLs on the TfNSW heavy rail corridor.

The requirements of this standard are applicable to all parties involved in the design of ATLs.

If, when using the standard, it is considered that the intent of the stated requirements is not

clear, a clarification should be sought from the Asset Standards Authority (ASA).

© State of NSW through Transport for NSW Page 6 of 25

Sup

erse

ded

by T

HR

CI 1

2180

ST

v2.0

, 02/

09/2

019

Page 8: Technical Note - TN 082: 2016 - Transport for NSW · and is the network design and standards authority for defined NSW transport assets. The ASA is responsible for developing engineering

T HR CI 12180 ST Active Transport Links on the Rail Corridor

Version 1.0 Issued date: 05 May 2015

3. Reference documents The following documents are cited in the text. For dated references, only the cited edition

applies. For undated references, the latest edition of the referenced document applies.

Australian standards

AS 5100 Bridge design

Transport for NSW standards

ESC 215 Transit Space

ESC 420 Track Drainage

ESC 510 Boundary Fences

T HR CI 12105 ST Vegetation Hazard Management in the Rail Corridor

T HR CI 12200 ST Access Roads

T HR EL 12002 GU Electrolysis from stray DC current

T MU AM 01001 ST Life Cycle Costing

T MU AM 01003 ST Development of Technical Maintenance Plans

TMD 0001 CAD and drafting manual – All design areas – Sections 1 and 2

TMD 0002 CAD and drafting manual – Civil design – Section 3

TS 20001 System Safety Standard for New or Altered Assets

30-ST-164 TfNSW Enterprise Risk Management Standard (available on request from

[email protected])

Legislation

Heritage Act 1977 (NSW)

Other reference documents

Austroads 2009, Guide to Road Design Part 6A: Pedestrian and Cyclist Paths, pub.

AGRD06A-09

Austroads 2009, Guide to Road Design Part 6B: Roadside Environment, pub. AGRD06B-09

NSW Heritage Office 2005, State Agency Heritage Guide, pub. HO05/01

Roads and Traffic Authority 2003, NSW Bicycle Guidelines, RTA, pub. 03.286

© State of NSW through Transport for NSW Page 7 of 25

Sup

erse

ded

by T

HR

CI 1

2180

ST

v2.0

, 02/

09/2

019

Page 9: Technical Note - TN 082: 2016 - Transport for NSW · and is the network design and standards authority for defined NSW transport assets. The ASA is responsible for developing engineering

T HR CI 12180 ST Active Transport Links on the Rail Corridor

Version 1.0 Issued date: 05 May 2015

4. Terms and definitions The following terms and definitions apply in this document:

ATL active transport link. An ATL is a footpath, cycleway, or a shared walking and cycle path.

AEO Authorised Engineering Organisation

ASA Assets Standards Authority

CPTED crime prevention through environmental design

OHW overhead wiring

OHWS overhead wiring structure

RCMG Rail Corridor Management Group

RIM Rail Infrastructure Manager. In relation to rail infrastructure of a railway, means the

organisation that has effective control and management of the rail infrastructure, whether or not

the organisation:

• owns the rail infrastructure; or

• has a statutory or contractual right to use the rail infrastructure or to control, or provide,

access to it

service requirement is the clearance beyond the safety clearance margin that enables defined

service tasks to be undertaken

SFAIRP so far as is reasonably practicable

TfNSW Transport for New South Wales

Type 1 ATLs are ATLs that are separated from the operations and maintenance activities of the

railway

Type 2 ATLs are ATLs that share the rail corridor access roads with the operator or maintainer

of the railway

© State of NSW through Transport for NSW Page 8 of 25

Sup

erse

ded

by T

HR

CI 1

2180

ST

v2.0

, 02/

09/2

019

Page 10: Technical Note - TN 082: 2016 - Transport for NSW · and is the network design and standards authority for defined NSW transport assets. The ASA is responsible for developing engineering

T HR CI 12180 ST Active Transport Links on the Rail Corridor

Version 1.0 Issued date: 05 May 2015

5. Safety requirements The design of active transport links (ATLs) shall take into account safety considerations for

construction, operational, maintenance and decommissioning workers; and, for the potential

users of the ATL.

The Authorised Engineering Organisation (AEO) shall establish and implement a design

process system that manages safety across the full life cycle of the structure. The design

process system shall be developed with reference to TS 20001 System Safety Standard for

New or Altered Assets.

6. Heritage requirements The design of ATLs shall be compliant with the necessary heritage regulations as mandated by

the Heritage Act 1977 (NSW).

Where items of heritage significance will be affected by the design of an ATL, the following

requirements shall apply:

• the provisions of the Heritage Act for all items listed on the State Heritage Register

• the provisions of the State Agency Heritage Guide for all items listed on the state agency

Section 170 Heritage and Conservation Register

Identification and assessment of impacts to potential heritage items shall be obtained early in

the scoping and design stage of a project.

Designs for ATLs at or in the vicinity of heritage-listed precincts shall be developed in

consultation with the relevant approval authorities, including the nominated operator and

maintainer, the relevant RIM, and regulatory authorities.

The design of ATLs shall demonstrate how identified heritage elements have been considered

in the design before the construction stage. Consultation with local community groups may also

be warranted in particular circumstances.

© State of NSW through Transport for NSW Page 9 of 25

Sup

erse

ded

by T

HR

CI 1

2180

ST

v2.0

, 02/

09/2

019

Page 11: Technical Note - TN 082: 2016 - Transport for NSW · and is the network design and standards authority for defined NSW transport assets. The ASA is responsible for developing engineering

T HR CI 12180 ST Active Transport Links on the Rail Corridor

Version 1.0 Issued date: 05 May 2015

7. General requirements All applications for development within TfNSW rail corridors shall be made through the Rail

Corridor Management Group (RCMG). An information and application package and the relevant

guidelines can be accessed via the TfNSW website.

The rail infrastructure manager (RIM) shall be consulted during the development of the

proposed ATL to ensure that:

• appropriate measures are included in the ATL to manage risks around the safety of the

users of the ATL

• appropriate provision is made for rail operations and maintenance

Impediments to railway operations shall be minimised as far as practicable. The interface with

railway operations, such as maintenance activities, generally requires complex management

arrangements in order to deal with safety issues.

ATLs within the rail corridor should be designed to be Type 1 ATLs, wherever possible.

The optimum arrangement is a Type 1 ATL located at the boundary of the rail corridor and the

boundary fence relocated to be on the trackside edge of the ATL.

An ATL can be fully Type 1; fully Type 2; or, a combination of Type 1 and Type 2 sections. The

extent of any Type 2 ATL sections shall be minimised.

In general, ATLs shall be constructed at grade. It is possible for structures such as bridges and

culverts to also be required. ATLs may be attached to existing bridges. These shall be designed

and constructed in accordance with the relevant transport standards as published on the ASA

website.

The configuration and operation plan for a Type 2 ATL, or an ATL incorporating sections of

Type 2 ATL, shall ensure that the users of the ATL are appropriately protected from the

activities of the maintainer or operator. This may result in disruption to the use of the ATL if it is

required by the RIM.

© State of NSW through Transport for NSW Page 10 of 25

Sup

erse

ded

by T

HR

CI 1

2180

ST

v2.0

, 02/

09/2

019

Page 12: Technical Note - TN 082: 2016 - Transport for NSW · and is the network design and standards authority for defined NSW transport assets. The ASA is responsible for developing engineering

T HR CI 12180 ST Active Transport Links on the Rail Corridor

Version 1.0 Issued date: 05 May 2015

8. Urban design considerations Urban design shall be considered as part of the design of ATLs.

Examples of urban design aspects to consider include:

• accessible and safe circulation routes

• crime prevention through environmental design (CPTED) principles

• maximise usage and activity to populate and activate spaces

• provision of logical links to existing transport infrastructure and facilities, including to other

ATLs and bicycle storage facilities (consideration should be given to the potential for future

links through consultation with local and state government authorities)

• minimisation of environmental impacts, including potential for the inclusion of alternative

energy sources

• consideration of local qualities and character, including but not limited to local heritage,

landscape, public art, and community involvement

• promotion of infrastructure design that pursues an agenda of design excellence

• landscaping shall not be in conflict with the requirements set out in T HR CI 12105 ST

Vegetation Hazard Management in the Rail Corridor

9. Design requirements – Type 1 ATLs The design of a Type 1 ATL within the rail corridor shall comply with the guidelines of the Roads

and Maritime Services publication, NSW Bicycle Guidelines; and, the Austroads publication,

Guide to Road Design Part 6A: Pedestrian and Cycle Paths. Any proposed departure from

these guidelines shall be documented by the applicant and included in the proposal to TfNSW

via the RCMG.

A Type 1 ATL occupies the area adjacent to the rail lines and does not infringe on the

infrastructure service requirements as set out in ESC 215 Transit Space, which ensures access

to the railway infrastructure by rail, police and emergency personnel, and their vehicles and

equipment. This access is required for maintenance activities and emergency purposes and

shall be unobstructed at all times; that is, 24 hours a day, 7 days a week.

Depending on the site specific requirements of the RIM, this access may be provided on one

side of the rail corridor and to particular items of infrastructure rather than being continuous

along the corridor.

Refer to Figure 1 for details of the zone reserved exclusively for infrastructure service

requirements and Figure 2 for examples of possible arrangements for Type 1 ATLs at cuttings

and embankments.

© State of NSW through Transport for NSW Page 11 of 25

Sup

erse

ded

by T

HR

CI 1

2180

ST

v2.0

, 02/

09/2

019

Page 13: Technical Note - TN 082: 2016 - Transport for NSW · and is the network design and standards authority for defined NSW transport assets. The ASA is responsible for developing engineering

T HR CI 12180 ST Active Transport Links on the Rail Corridor

Version 1.0 Issued date: 05 May 2015

A minimum clearance of 1 metre shall be provided from the ATL to the edge of embankment

and toe of cutting to allow for maintenance access. This dimension shall be increased as

necessary to provide for drainage. Refer to ESC 420 Track drainage for drainage requirements.

© State of NSW through Transport for NSW Page 12 of 25

Sup

erse

ded

by T

HR

CI 1

2180

ST

v2.0

, 02/

09/2

019

Figure 1 – Type 1 ATL

Page 14: Technical Note - TN 082: 2016 - Transport for NSW · and is the network design and standards authority for defined NSW transport assets. The ASA is responsible for developing engineering

T HR CI 12180 ST Active Transport Links on the Rail Corridor

Version 1.0 Issued date: 05 May 2015

© State of NSW through Transport for NSW Page 13 of 25 S

uper

sede

d by

T H

R C

I 121

80 S

T v2

.0, 0

2/09

/201

9

Figure 2 – Type 1 ATL at cuttings and embankments

Page 15: Technical Note - TN 082: 2016 - Transport for NSW · and is the network design and standards authority for defined NSW transport assets. The ASA is responsible for developing engineering

T HR CI 12180 ST Active Transport Links on the Rail Corridor

Version 1.0 Issued date: 05 May 2015

9.1. Location for Type 1 ATLs The location of Type 1 ATLs shall not infringe the infrastructure service requirements set out in

ESC 215, unless approved by the Lead Civil Engineer, ASA.

On level ground, the trackside fence of a proposed Type 1 ATL shall not be less than 6.2 m

from the centreline of the nearest track. This minimum distance shall be increased as necessary

at cuttings, on embankments, and where vehicle turning and material storage areas are

required by the RIM.

Where it is possible (for example, if access to railway services is not affected) the Type 1 ATL

shall be located adjacent to the railway corridor boundary.

In train examination areas with a parallel access road, the minimum distance shall be increased

to 7.8 m.

The design of the ATL shall comply with safety clearances to live electrical infrastructure.

The Type 1 ATL shall be clear of the following:

• catchpoint derailment landing areas

• cable routes

• structures and buildings

9.2. Drainage for Type 1 ATLs Appropriate drainage systems shall be designed for the Type 1 ATL which shall ensure that

stormwater run-off is not concentrated and then directed onto the rail lines or other railway

infrastructure. The drainage systems shall be designed to be compatible with the existing

drainage along the rail corridor and cesses, and where possible should direct run-off away from

the track drainage system.

9.3. Fences for Type 1 ATLs The Type 1 ATL shall be fenced on the side adjacent to the track and shall comply with

ESC 510 Boundary Fences. Where the Type 1 ATL is located at the corridor boundary, the

boundary fence may be removed subject to approval from TfNSW.

© State of NSW through Transport for NSW Page 14 of 25

Sup

erse

ded

by T

HR

CI 1

2180

ST

v2.0

, 02/

09/2

019

Page 16: Technical Note - TN 082: 2016 - Transport for NSW · and is the network design and standards authority for defined NSW transport assets. The ASA is responsible for developing engineering

T HR CI 12180 ST Active Transport Links on the Rail Corridor

Version 1.0 Issued date: 05 May 2015

The minimum requirement is a 1.8 m high chain-link fabric fence along the full length of the

ATL, except for the following locations, where the minimum requirement is a 2.4 m high fence

with 600 mm high concertina short barbed tape:

• where the fence line is less than 3 m from overhead wiring structures, power poles or

signalling equipment

• where an ATL is to be located on the shoulder of a cutting

The height of the fence is measured from the top surface of the ATL.

9.4. Access gates for Type 1 ATLs To provide access for authorised rail infrastructure vehicles and equipment into the

infrastructure service area, access gates with railway security locks shall be provided in the side

fences of a proposed Type 1 ATL. The RIM shall specify the location and spacing of the gates

for the proposed ATL. Gates shall comply with ESC 510.

Where appropriate, the access points shall include laybacks in adjoining road kerbing and

removable bollards. If bollards are to be used, they shall be signed, marked and illuminated in

accordance with the NSW Bicycle Guidelines.

9.5. Lighting for Type 1 ATLs Lighting of a proposed Type 1 ATL shall comply with the Austroads publication Guide to Road

Design Part 6B: Roadside Environment. The design and location of the lighting shall meet the

following requirements:

• avoid glare or reflections to the eyes of train drivers

• avoid being confused with railway signals

• minimise the impact on residents of adjoining properties

9.6. Electrolysis – Type 1 ATL Electrolysis occurs in the electrified areas of the railway corridors. The issue of potential

corrosion shall be taken into account where metallic products, for example metal fencing or

bridges, are proposed to be utilised as part of the ATL.

For further technical information and guidance, reference shall be made to T HR EL 12002 GU

Electrolysis from Stray DC Current.

© State of NSW through Transport for NSW Page 15 of 25

Sup

erse

ded

by T

HR

CI 1

2180

ST

v2.0

, 02/

09/2

019

Page 17: Technical Note - TN 082: 2016 - Transport for NSW · and is the network design and standards authority for defined NSW transport assets. The ASA is responsible for developing engineering

T HR CI 12180 ST Active Transport Links on the Rail Corridor

Version 1.0 Issued date: 05 May 2015

9.7. Services affected by Type 1 ATLs Appropriate measures shall be designed, where necessary, to protect (or relocate) any existing

above ground or below ground services affected by the proposed ATL. Railway services shall

be located within the infrastructure service area and shall be protected from damage and

unauthorised access.

9.8. Signage for Type 1 ATLs Signage for Type 1 ATL shall be provided in accordance with the requirements of NSW Bicycle

Guidelines.

9.9. Sustainability of Type 1 ATLs The design of Type 1 ATLs shall consider environmental impacts and sustainability

opportunities during investigation, design, construction and operational activities.

The design shall consider sustainability over the life cycle of the asset. Considerations relating

to Type 1 ATLs include the following:

• embodied energy in construction materials

• protection or enhancement of biodiversity, including weed management

• stormwater management

• air quality, especially from dust

• noise and vibration

• traffic impacts

• visual impact and amenity

• resilience to climate change

• disposal and reuse at life cycle end

© State of NSW through Transport for NSW Page 16 of 25

Sup

erse

ded

by T

HR

CI 1

2180

ST

v2.0

, 02/

09/2

019

Page 18: Technical Note - TN 082: 2016 - Transport for NSW · and is the network design and standards authority for defined NSW transport assets. The ASA is responsible for developing engineering

T HR CI 12180 ST Active Transport Links on the Rail Corridor

Version 1.0 Issued date: 05 May 2015

10. Design requirements – Type 2 ATLs The design of a Type 2 ATL within the rail corridor shall comply with the requirements of the

NSW Bicycle Guidelines, the Guide to Road Design Part 6A: Pedestrian and Cyclists Paths and

T HR CI 12200 ST Access Roads. Any proposed departure from these requirements shall be

documented by the applicant and included in the proposal to TfNSW via the RCMG.

The RIM requires access to railway infrastructure by rail personnel, their vehicles and

equipment. This access is required for maintenance activities (for example access to points,

power poles, OHWS) and is generally provided by the access road. Access is also required for

emergency purposes (for example detraining passengers from a disabled train). In general, the

access arrangements shall be determined on a case by case basis with the RIM.

Depending on the site specific requirements of the RIM, this access may be provided on one

side of the rail corridor and to particular items of infrastructure. Depending on site conditions,

provision of walking access up to 300 m from a maintenance vehicle may be considered.

The Type 2 ATL shall be configured so that access for these activities can be readily arranged

as required by the RIM. This access may be necessary at any time during the day or night.

Refer to Figure 3 for details of the zone reserved exclusively for infrastructure service

requirements and Figure 4 for examples of possible arrangements for Type 2 ATLs at cuttings

and embankments.

A minimum clearance of 1 metre shall be provided from the ATL to the edge of embankment

and toe of cutting to allow for maintenance access. This dimension shall be increased as

necessary to provide for drainage. Refer to ESC 420 for drainage requirements.

© State of NSW through Transport for NSW Page 17 of 25

Sup

erse

ded

by T

HR

CI 1

2180

ST

v2.0

, 02/

09/2

019

Page 19: Technical Note - TN 082: 2016 - Transport for NSW · and is the network design and standards authority for defined NSW transport assets. The ASA is responsible for developing engineering

T HR CI 12180 ST Active Transport Links on the Rail Corridor

Version 1.0 Issued date: 05 May 2015

© State of NSW through Transport for NSW Page 18 of 25

Sup

erse

ded

by T

HR

CI 1

2180

ST

v2.0

, 02/

09/2

019

Figure 3 – Type 2 ATL

Page 20: Technical Note - TN 082: 2016 - Transport for NSW · and is the network design and standards authority for defined NSW transport assets. The ASA is responsible for developing engineering

T HR CI 12180 ST Active Transport Links on the Rail Corridor

Version 1.0 Issued date: 05 May 2015

© State of NSW through Transport for NSW Page 19 of 25 S

uper

sede

d by

T H

R C

I 121

80 S

T v2

.0, 0

2/09

/201

9

Figure 4 – Type 2 ATL at cuttings and embankments

Page 21: Technical Note - TN 082: 2016 - Transport for NSW · and is the network design and standards authority for defined NSW transport assets. The ASA is responsible for developing engineering

T HR CI 12180 ST Active Transport Links on the Rail Corridor

Version 1.0 Issued date: 05 May 2015

10.1. Location of Type 2 ATLs The location of Type 2 ATLs shall not infringe the infrastructure service requirements set out in

ESC 215, unless approved by the Lead Civil Engineer, ASA.

On level ground, the trackside fence of a proposed Type 2 ATL shall not be less than 5 m from

the centreline of the nearest track. This minimum distance shall be increased as necessary at

cuttings; on embankments; and where vehicle turning and material storage areas are required

by the RIM.

The design of the ATL shall comply with safety clearances to live electrical infrastructure.

The ATL shall be clear of the following:

• catchpoint derailment landing areas

• cable routes

• structures and buildings

10.2. Drainage for Type 2 ATLs Appropriate drainage systems shall be designed for the Type 2 ATL which shall ensure that

stormwater run-off is not concentrated and then directed onto the rail lines or other railway

infrastructure. The drainage systems shall be designed to be compatible with the existing

drainage along the rail corridor and cesses and where possible should direct run-off away from

the track drainage system.

10.3. Fences for Type 2 ATLs The Type 2 ATL shall be fenced on both sides. Where possible the outer fence should be the

rail corridor boundary fence. The fences shall comply with ESC 510.

The minimum requirement is a 1.8 m high chain-link fabric fence along both sides for the full

length of the ATL.

The minimum requirement for the trackside fence is a 2.4 m high fence with 600 mm high

concertina short barbed tape at the following locations:

• where the fence line is less than 3 m from overhead wiring structures; power poles; or

signalling equipment

• where a Type 2 ATL is to be located on the shoulder of a cutting

Fence height is measured from the top surface of the ATL.

© State of NSW through Transport for NSW Page 20 of 25

Sup

erse

ded

by T

HR

CI 1

2180

ST

v2.0

, 02/

09/2

019

Page 22: Technical Note - TN 082: 2016 - Transport for NSW · and is the network design and standards authority for defined NSW transport assets. The ASA is responsible for developing engineering

T HR CI 12180 ST Active Transport Links on the Rail Corridor

Version 1.0 Issued date: 05 May 2015

10.4. Access gates for Type 2 ATLs To provide access for authorised rail infrastructure vehicles and equipment into the

infrastructure service area, access gates with railway security locks shall be provided in the side

fences of a proposed Type 2 ATL. The RIM shall specify the location and spacing of the gates

for the proposed ATL. Gates shall comply with the requirements of ESC 510.

Where appropriate, the access points shall include laybacks in adjoining road kerbing and

removable bollards. If bollards are to be used, they shall be signed and marked and lit in

accordance with the NSW Bicycle Guidelines.

Fence and gate arrangements shall make provision for safely restricting access for the users of

the ATL when the Type 2 ATL is being used for rail activities and may include the following:

• full closure, including an appropriately signed and marked detour

• path narrowing with appropriate advance warning and work zone protection

10.5. Lighting for Type 2 ATLs Lighting of a proposed Type 2 ATL shall comply with the NSW Bicycle Guidelines. The design

and location of the lighting shall also meet the following requirements:

• avoid glare or reflections to the eyes of train drivers

• avoid being confused with railway signals

• minimise the impact on residents of adjoining properties

10.6. Electrolysis – Type 2 ATL Electrolysis occurs in the electrified areas of the railway corridors. The issue of potential

corrosion shall be taken into account where metallic products (for example metal fencing) are

proposed to be utilised as part of the ATL.

For further technical information and guidance, reference shall be made to T HR EL 12002 GU.

10.7. Services affected by Type 2 ATLs Appropriate measures shall be designed, where necessary, to protect (or relocate) any existing

above ground or below ground services affected by the proposed Type 2 ATL. Railway services

shall be located within the infrastructure service area and shall be protected from damage and

unauthorised access.

© State of NSW through Transport for NSW Page 21 of 25

Sup

erse

ded

by T

HR

CI 1

2180

ST

v2.0

, 02/

09/2

019

Page 23: Technical Note - TN 082: 2016 - Transport for NSW · and is the network design and standards authority for defined NSW transport assets. The ASA is responsible for developing engineering

T HR CI 12180 ST Active Transport Links on the Rail Corridor

Version 1.0 Issued date: 05 May 2015

10.8. Signage for Type 2 ATLs Signage for a Type 2 ATL shall be provided in accordance with the requirements of the NSW

Bicycle Guidelines. Additional signage shall be provided as required to ensure the safe

operation of the ATL, particularly when the Type 2 ATL is being used for railway activities.

10.9. Sustainability of Type 2 ATLs The design of the Type 2 ATL shall consider environmental impacts and sustainability

opportunities during investigation, design, construction and operational activities.

The design shall consider sustainability over the life cycle of the asset. Considerations relating

to Type 2 ATLs include the following:

• embodied energy in construction materials

• protection or enhancement of biodiversity, including weed management

• stormwater management

• air quality, especially from dust

• noise and vibration

• traffic impacts

• visual impact and amenity

• resilience to climate change

• disposal and reuse at life cycle end

11. Design and documentation The following documents are required to be submitted as part of the application to the RCMG

for proposed ATLs:

• documentation required during design stage, such as detailed technical specifications, and

maintenance plans

• work-as-executed drawings

• the appropriate deed

Documentation requirements are detailed in Section 11.1, Section 11.2 and Section 11.3.

© State of NSW through Transport for NSW Page 22 of 25

Sup

erse

ded

by T

HR

CI 1

2180

ST

v2.0

, 02/

09/2

019

Page 24: Technical Note - TN 082: 2016 - Transport for NSW · and is the network design and standards authority for defined NSW transport assets. The ASA is responsible for developing engineering

T HR CI 12180 ST Active Transport Links on the Rail Corridor

Version 1.0 Issued date: 05 May 2015

11.1. Design stage documentation ATLs shall be designed by an AEO.

Crossings supporting the ATL shall be designed in accordance with AS 5100 Bridge Design.

The detailed drawings shall comply with TMD 0001 CAD and Drafting Manual, in particular

Section 1, 2 and 3. The drawings shall be provided by the applicant as part of the planning and

design process.

General requirements include a detailed site topographic survey and scaled drawings that detail

the following:

• the proposed location in plan view and railway kilometrages of the ATL, relative to the

railway boundary, tracks and other adjacent railway infrastructure

• the proposed reduced levels of the ATL, relative to the ground, track and other

infrastructure

• the details of the proposed ATL formation, pavement design, running surface, drainage,

fencing, access gates, pavement marking, signage and lighting

• the details of existing underground services as identified in the Services Search and any

proposed protective measures where applicable

• the location of all access gates and crossings

The applicant shall prepare and submit a detailed technical specification for the proposed works

for approval by TfNSW.

In the case of a Type 2 ATL or an ATL containing Type 2 ATL sections, the submission shall

also include a detailed risk assessment, an operation plan describing how the ATL will function

and the specification of responsibilities for ensuring safety of the various users. The risk

assessment shall assess risk against the risk criteria defined in 30-ST-164 TfNSW Enterprise

Risk Management Standard.

The applicant shall also prepare and submit the maintenance requirements for the ATL in the

form of a technical management plan, for approval by TfNSW, including periodic inspections of

fencing, pavement and drainage systems. The maintenance plan shall include a clear statement

nominating the responsibilities of the external party and the RIM for inspection and

maintenance. The requirements and high-level processes for the development of technical

maintenance plans are detailed in T MU AM 01003 ST Development of Technical Maintenance

Plans.

Maintenance and operational plans shall include the specification of arrangements for any

necessary pedestrian and cyclist detours including temporary way finding requirements.

© State of NSW through Transport for NSW Page 23 of 25

Sup

erse

ded

by T

HR

CI 1

2180

ST

v2.0

, 02/

09/2

019

Page 25: Technical Note - TN 082: 2016 - Transport for NSW · and is the network design and standards authority for defined NSW transport assets. The ASA is responsible for developing engineering

T HR CI 12180 ST Active Transport Links on the Rail Corridor

Version 1.0 Issued date: 05 May 2015

11.2. Work-as-executed drawings Work-as-executed drawings shall be prepared and submitted to TfNSW by the applicant on the

completion of a new ATL. Any variations to the approved design drawings shall be clearly

marked.

All work-as-executed drawings shall be lodged in the TfNSW Plan Room.

11.3. Deed All approved ATLs shall be covered by an appropriate deed. The deed shall include all relevant

information including approved easements and construction and maintenance agreements.

12. Construction The construction of an ATL shall be undertaken in accordance with the approval granted by

TfNSW and the relevant engineering standards.

Construction of an ATL shall consider the effects the construction will have on existing railway

infrastructure.

12.1. Protection of rail infrastructure Particular care shall be taken during the construction of an ATL to ensure that adjacent rail

infrastructure is not disturbed or damaged. Potential construction issues include the following:

• track subsidence

• excavation at the base of railway embankments, which might lead to destabilisation and

failure of the embankment

• disturbance to drainage systems over railway cuttings, which might lead to failure of the

cutting slopes or fouling of the tracks below

• undercutting of the base of railway cuttings

• damage to railway cess drains and disturbance to the flow of stormwater runoff

• damage to train examination or staff walkway areas

• excavation adjacent to building, bridges or other structures that might undermine or

destabilise the foundations

• damage to above ground railway equipment such as signalling infrastructure

• damage to existing above ground or below ground services

• working in proximity to overhead wiring (OHW)

© State of NSW through Transport for NSW Page 24 of 25

Sup

erse

ded

by T

HR

CI 1

2180

ST

v2.0

, 02/

09/2

019

Page 26: Technical Note - TN 082: 2016 - Transport for NSW · and is the network design and standards authority for defined NSW transport assets. The ASA is responsible for developing engineering

T HR CI 12180 ST Active Transport Links on the Rail Corridor

Version 1.0 Issued date: 05 May 2015

13. Maintenance The applicant shall implement the maintenance plan for the ATL in accordance with the deed

requirements. A copy of all inspection and repair reports shall be forwarded by the applicant, or

nominated maintenance party, to the relevant RIM.

14. Decommissioning or disposal Decommissioning is the final process of withdrawing an asset from active service on the

network.

Disposal is the process of removing an asset from the network. For example demolition of an

overbridge followed by removal and recycling.

The decommissioning or disposal of an asset is the final stage of the asset life cycle. Proper

planning of this part of the life cycle is an integral part of the strategic life cycle process.

The process to be undertaken for the disposal of an active transport link on the rail corridor shall

be as follows:

i) A report shall be produced to confirm that the asset is surplus to the requirements of the

rail network or it is life expired.

ii) The report shall identify the benefits including financial costs arising from the proposed

decommissioning or disposal.

iii) The report shall confirm stakeholder engagement regarding the proposed action. Such

engagement shall include, but not be limited to heritage, council and environmental body

consultation.

iv) The means of decommissioning or disposal shall be a risk based decision carried out in

accordance with the TfNSW safety management system. Refer to 30-ST-164 TfNSW

Enterprise Risk Management Standard for requirements regarding the mitigation of risk so

far as is reasonably practical (SFAIRP).

v) The report shall include a decommissioning or disposal plan for implementation.

vi) Following decommissioning or disposal, the asset database shall be updated to reflect

network changes.

95% of construction and demolition waste by weight of the decommissioned asset shall be

diverted from landfill.

© State of NSW through Transport for NSW Page 25 of 25

Sup

erse

ded

by T

HR

CI 1

2180

ST

v2.0

, 02/

09/2

019