technical meeting on the country nuclear power profiles · the nuclear law was modified in 2007...
TRANSCRIPT
Jordan Atomic Energy Commission
Technical Meeting on the Country Nuclear Power Profiles
Jordan’s Nuclear Energy Programme
Yasmin Majali
Jordan Atomic Energy Commission
10-13 May 2016
0
Jordan Atomic Energy Commission
Jordan’s Country Profile
Total Area: 89,213 Km2
Sea Port: Aqaba
Coastline: 26 Km
Population: 9.5 million (2015)
Climate: Mediterranean & Arid Desert
GDP: US$35.6 billion (2014)
Jordan Atomic Energy Commission
Jordan’s Electricity Supply
Currently: >98% of electricity generation based on imported fossil fuels
2% 6%
92%
1%
33%
13%
43%
10%
37%
20%
28%
15%
Local Gas Oil Shale Nuclear Renewable Imported Gas Imported Fuel Oil
2014 2020 2040
Imported Fossil Fuel
Jordan Atomic Energy Commission
Challenges Facing Jordan
Small economy - 70% of GDP/service sector.
Need for Mega projects - high capital investment.
Energy crisis - translated to a severe economic crisis.
Limited energy resources - 97% imported.
Single Source of imported Natural Gas - more than 85% of total
generation.
High electricity demand growth.
Political situation in the Middle East (security, refugees, loss of export
markets and energy sources, etc….).
Jordan Atomic Energy Commission
Jordan Nuclear Power Plant Challenges
Very limited coast line (26 km), High seismicity, Grid issues NPP Siting
Water Supply
Political
HRD
Financing
Public
Opposition
Scarcity of water
Turmoil in region
Lack of competent staff (owner, regulator, stakeholders)
Size of the Project, credit rating of Jordan and Limited
Government financing
Safety and environmental concerns after Fukushima Daiichi
Jordan Atomic Energy Commission
Nuclear Cooperation Agreements
Signature Country
30 May, 2008 France
19 August, 2008 China
1 December, 2008 South Korea
17 February, 2009 Canada
22 May, 2009 Russian Federation
22 June, 2009 UK
22 September, 2009 Argentina
20 January, 2010 Spain
10 September, 2010 Japan
9 January, 2011 Romania
14 February, 2011 Italy
17 February, 2011 Turkey
22 January, 2014 Saudi Arabia
29 October, 2014 Armenia
Jordan Atomic Energy Commission
The Nuclear Law was modified in 2007 resulting in splitting the Jordan
Nuclear Energy Commission (JNEC) into two independent commissions:
Jordan Atomic Energy Commission (JAEC)
Jordan Nuclear Regulatory Commission (JNRC)
Initiating a Nuclear Power Program in Jordan
JNEC
JNRC JAEC
EMRC
Jordan Atomic Energy Commission
Status of Implementing Nuclear Power in Jordan
Established Key Bodies:
Nuclear Regulator – JNRC {now EMRC}
Nuclear Procurement Agency – JAEC
Utility estabished-JNPC
Building the Infrastructure
Identification of suitable NPP site
Establishment of applicable laws and regulations
Tapping into Jordan’s higher education institutions
Forging International Cooperation: IAEA, Peer Groups, Nuclear Cooperation
Agreements
Technology Selection
Detailed process using IAEA methodology and supported by experienced advisors
Technology selected
Identification of the Investor/Operator Partner
Selected
Jordan Atomic Energy Commission
JAEC’s Current Activities
Jordan’s Nuclear Projects
Uranium Exploration
HRD Nuclear
Power Plant Project
Education
Research Reactor
Subcritical Assembly
Jordan Atomic Energy Commission
Jordan Research and Training Reactor (JRTR)
Construction Permit issued by JNRC in August 2013
Operating License Application submitted in December 2014 to EMRC
Subcritical Assembly
Commissioned in June 2013
Provides for 9+ first principle nuclear experiments for nuclear engineering students
Operation and staffing are under the auspices of Jordan University for Science and Technology (JUST)
Nuclear Research Facilities
Jordan Atomic Energy Commission
Education & Training
JUST established a nuclear engineering dept. to graduate future
reactor operators holding a B.Sc. degree in nuclear engineering.
UJ, YU and BAU have established M.Sc. programs in nuclear
physics & students are trained in SESAME.
A total of 95 students have been sent on scholarships abroad
for M.Sc. and Ph.D. degrees in nuclear engineering and related
fields, as well as specialized degrees.
So far 28 engineers and technicians were trained at KAERI on
aspects related to JRTR (Operation, Supervision, Monitoring
and Maintenance).
Jordan Atomic Energy Commission
NPP Technology Selection
JAEC has been mandated to implement the Nuclear Energy
Strategy including the selection of plant vendor and Investor/
Operator for Jordan.
JAEC elected to arrive at a design/vendor selection process for
construction of the first nuclear power plant through an
Engineering, Procurement and Construction (EPC) contract.
It was intended that the plant would consist of a Generation III or
III+ unit with an option for second unit with a capacity ranging
from 700 to 1,200 MWe per unit.
Jordan Atomic Energy Commission
Technologies
The final seven vendors plant technologies responses received were, namely:
APR-1000 from KEPCO in Korea
ATMEA1 from AREVA in France
EC6 from AECL in Canada
VVER-1000 version A91 (AES-91) - AtomStroyExport of Russia
VVER-1000 version A92 (AES-92) - AtomStroyExport of Russia
AES-2006 Leningrad versions - AtomStroyExport of Russia
AES-2006 Novo Voronezh - AtomStroyExport of Russia
Jordan Atomic Energy Commission
Technology Bid Evaluation Approach
The differences between technologies and their impact on Jordan was
assessed through rigorous evaluation methodologies designed to bring
full visibility and transparency:
Assessment of the vendor technology towards Key Factors (important for Jordan)
Exclusionary Topics
Evaluation Matrix
Best-in-Class for each evaluation criteria
Other Topics
Price under competitive environment
Jordan Atomic Energy Commission
Results of the Selection
The following two nuclear power plant types were
selected:
AES-92 (VVER/PWR by AtomStroyExport)
ATMEA1 (PWR by Areva/Mitsubishi)
Jordan Atomic Energy Commission
NPP Model
Our NPP is an inland NPP that will rely on reclaimed, treated waste
water as its cooling water
This is very similar Palo Verde/USA use of waste water for cooling
Jordan Atomic Energy Commission
Government of Jordan (GoJ) Cabinet Decision (Aug. 25, 2013)
1
• To adopt Nuclear Energy as one of the alternatives to producing electricity in the overall energy mix in Jordan
2
• To establish a company that is fully owned by the Government to manage the Project
3
• To select Amra site as the preferred site and carry out site characterization for the construction of the JNPP
Jordan Atomic Energy Commission
GoJ Cabinet Decision (Oct. 27, 2013)
1
• To select Rosatom as the Preferred Bidder based upon the integrated approach consisting of ASE as the EPC contractor and Rusatom Overseas as the strategic partner (Investor/Operator)
2 • To implement the project through a two-phased approach
3
• To designate JAEC to negotiate with the Russian side the implementation of the Project
Jordan Atomic Energy Commission
Project Development Agreement (PDA)
The PDA is a project level agreement that defines the activities and
responsibilities required by both parties in the Pre-Investment Phase – Phase I.
Activities included in this Phase under the PDA: Site Characterization,
Environmental Impact Assessment, Off-Site Infrastructure Studies, Water
Requirements, Securing of Financing and Preparation of the Bankable
Feasibility Study.
Following this, and as part of the Pre-Investment Phase, Project Agreements
(PPA, EPC, O&M, SPA, SHA, FSA) will be negotiated and signed to proceed
with Phase II (project implementation and construction phase).
The PDA has been approved by the Ministerial Cabinet of Jordan (Decision No.
5100, 6/8/2014) and signed by JAEC and RAOS on September 22, 2014.
Jordan Atomic Energy Commission
Inter-Governmental Agreement (IGA)
The IGA is a government level agreement that lays the framework and
understanding in relation to the cooperation on the implementation of
the Project between the Government of the Jordan and the Russian
Federation.
Governmental support.
Guarantee both parties obligations in the Project.
Tax exemptions.
Guarantee the Fuel Supply.
Guarantee Spent Nuclear Fuel return to Russia.
The IGA has been approved by the Ministerial Cabinet of Jordan on
March 8th , 2015 (Decision No. 8495) and signed on March 24th, 2015.
Jordan Atomic Energy Commission
Project Phases
Implementation Phase
Phase I 1. Conducting the required Site Characterization,
Environmental Impact Assessment, Grid Study, Electricity
Market Study, Offsite Infrastructure and Water & Cooling
Study for the Site/Project.
2. Preparing and finalizing the Bankable Feasibility Study
with the Investor/Operator and Investors for the project
along with other all required studies.
3. Securing the Financing for the project and Finalizing all
Phase II related Project Agreements.
Pre-Investment Phase (Development Phase)
Phase II
1. Power Plant Construction
2. Power Plant Commissioning and Operation
Jordan Atomic Energy Commission
23
The GoJ established in October 2015 the JNPC a state-owned company to
manage the Pre-Investment Phase.
Implementation of the Pre-Investment Phase (Phase I) of Jordan Nuclear Power
Project according to the PDA and IGA to achieve a Positive Investment
Decision. Concluding of Project Agreements (EPC, PPA, FSA,…)
Construction/Owner/Operator of the Project (Phase II).
Jordan Nuclear Power Company (JNPC)
Jordan Atomic Energy Commission
Owner/
Operator
Company JNPC
JAEC
Government of Jordan
EMRC
Project Implementation
Jordan Atomic Energy Commission
Next Steps for Jordan NPP
Technology Vendor
PDA
Feasibility Study
Establish Utility JNPC
Licensing
Infrastructure Development
EPC Contract
Engagement with Financial Community
Site Characterization Ongoing
Partners
Jordan Atomic Energy Commission
International Advisory Group
An International Advisory Group (IAG) has been formed of world
experts on nuclear power, nuclear safety, its regulation and other
nuclear activities, to provide independent advice to the Royal
Court and the GoJ on the Jordan Nuclear Energy Programme.
Report will be ready by the end of May 2016.
Jordan Atomic Energy Commission
Public Communications
JAEC has developed a strategy for stakeholder involvement, which
includes 3 phases:
Build awareness, inform and educate
Engage different stakeholders
Empower them to advocate the project
Public information activities including public awareness campaigns,
interviews, scholarships, meeting with media representatives, and
initiatives supported by JAEC.
JAEC used students and nuclear graduates to communicate with the
large youth population.
An opinion poll will be conducted by end of this year.