technical manager’s report september 2005. telescope activities primary mirror hardpoint repair...
TRANSCRIPT
Technical manager’s report
September 2005
Telescope activities
• Primary mirror hardpoint repair
• New mirror actuator controls
• Collimation analysis
• F/5 secondary mirror aspherized
Instrument activities
• CorMASS visiting instrument
• POETS visiting instrument
• GLAO observing
• F/5 instrument cart delivered
SAO F/5 instrument cart
Instrument activities
• LDSS wheel encoders, cable wrap
• Iodine cell remote control
• MagIC upgrade tests
• IMACS cooler repair
• IMACS CCD repair
Instrument activities
• New instrument components– LDP & 150 l/mm grism for IMACs– VPH-ALL for LDSS– GISMO for IMACS– ugriz & Hα filters for IMACS– LDSS filters– MMTF
Infrastructure activities
• Serial-on-fiber lightning protection– Control computers to telescope hardware
cable runs to be replaced with fiber optics
Instrument meetings
Meetings with:– FIRE– FourStar– PFS– MIRAC4– MMIRS
– MegaCAM– F/5 secondary– F/5 WFC– AO secondary
Staffing – Chile(budgeted level plus ATE)
• We are at full staffing
• Two new instrument
specialists (one
promoted from TO)
• New programmer
(promoted from TO)
• Two new telescope
operators
Job Effort
Asst. telescope engineer 1.0
Electronics engineer 3.0
Instrument specialist 4.0
Machinist assistant 2.0
Mechanical technician 2.0
Programmer 2.0
Telescope operator 6.0
Total 20.0
Staffing – Pasadena(budgeted level minus ATE)
Job Effort Job Effort
Accounting assistant 0.10 Manager tech group 0.80
Asst business manager 0.20 Mechanical engineer 0.50
Buyer 0.15 Postdoc 0.66
Controller 0.20 Programmer 0.90
Electronics engineer 1.00 Purchasing manager 0.15
Electronics technician 1.00 Shipping clerk 0.10
Instrument scientist 1.00 Technical manager 0.50
Machinist 0.50 Total 7.76
Computer networking
• Network administration was a 10% effort from
Magellan programmer
• New instruments require more support
• LCO arranged for CTIO management– More IP addresses– Adds routers and firewall– Connects to CTIO network
Clean room for large IR instruments
• MMIRS and FourStar are large (3x3x10 feet)
• Detectors need protection from static
electricity and particulate contamination
• Detectors are expensive ($2.5M for FourStar)
• Undisturbed workspace needed for long
periods for assembly and repairs
Clean room for large IR instruments
• Clean room is required to support large
infrared instruments
• Proposal development in progress
Carnegie shop
• New purchases– CNC lathe– CNC mill
• Increases production throughput
Instruments
• Assume we can support six facility
instruments
• How to handle incoming 7+ instruments
• Plus new telescope subsystems (new
secondaries, AO, etc.)
Instruments – page 1
Instrument Science rank Effort
IMACS F/2 3.0 High
IMACS F/4 2.8 High
MIKE 2.8 Low
FourStar 2.6 High
PANIC 2.5 Low
LDSS 2.2 Low
MagIC 2.0 Low
F/11 AO 2.0 High+
Instruments – page 2
Instrument Science rank Effort
MMIRS 1.9 High
MMFS 1.9 High
MIRAC/AO 1.8 High
MegaCAM 1.6 High
MagE 1.6 Lo
MMTF 1.5 High
GISMO 1.4 Medium
MOE 1.4 Low
Instruments
• Instruments can displace similar equipment
(trade PANIC for FourStar)
• User status (PI or other expert required on
every observing run)
• Mothball (minimum 18 months) to
accommodate the new
• Decommission