technical manager’s report september 2005. telescope activities primary mirror hardpoint repair...

18
Technical manager’s report September 2005

Upload: elisabeth-griffin

Post on 11-Jan-2016

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Technical manager’s report September 2005. Telescope activities Primary mirror hardpoint repair New mirror actuator controls Collimation analysis F/5

Technical manager’s report

September 2005

Page 2: Technical manager’s report September 2005. Telescope activities Primary mirror hardpoint repair New mirror actuator controls Collimation analysis F/5

Telescope activities

• Primary mirror hardpoint repair

• New mirror actuator controls

• Collimation analysis

• F/5 secondary mirror aspherized

Page 3: Technical manager’s report September 2005. Telescope activities Primary mirror hardpoint repair New mirror actuator controls Collimation analysis F/5

Instrument activities

• CorMASS visiting instrument

• POETS visiting instrument

• GLAO observing

• F/5 instrument cart delivered

Page 4: Technical manager’s report September 2005. Telescope activities Primary mirror hardpoint repair New mirror actuator controls Collimation analysis F/5

SAO F/5 instrument cart

Page 5: Technical manager’s report September 2005. Telescope activities Primary mirror hardpoint repair New mirror actuator controls Collimation analysis F/5

Instrument activities

• LDSS wheel encoders, cable wrap

• Iodine cell remote control

• MagIC upgrade tests

• IMACS cooler repair

• IMACS CCD repair

Page 6: Technical manager’s report September 2005. Telescope activities Primary mirror hardpoint repair New mirror actuator controls Collimation analysis F/5

Instrument activities

• New instrument components– LDP & 150 l/mm grism for IMACs– VPH-ALL for LDSS– GISMO for IMACS– ugriz & Hα filters for IMACS– LDSS filters– MMTF

Page 7: Technical manager’s report September 2005. Telescope activities Primary mirror hardpoint repair New mirror actuator controls Collimation analysis F/5

Infrastructure activities

• Serial-on-fiber lightning protection– Control computers to telescope hardware

cable runs to be replaced with fiber optics

Page 8: Technical manager’s report September 2005. Telescope activities Primary mirror hardpoint repair New mirror actuator controls Collimation analysis F/5

Instrument meetings

Meetings with:– FIRE– FourStar– PFS– MIRAC4– MMIRS

– MegaCAM– F/5 secondary– F/5 WFC– AO secondary

Page 9: Technical manager’s report September 2005. Telescope activities Primary mirror hardpoint repair New mirror actuator controls Collimation analysis F/5

Staffing – Chile(budgeted level plus ATE)

• We are at full staffing

• Two new instrument

specialists (one

promoted from TO)

• New programmer

(promoted from TO)

• Two new telescope

operators

Job Effort

Asst. telescope engineer 1.0

Electronics engineer 3.0

Instrument specialist 4.0

Machinist assistant 2.0

Mechanical technician 2.0

Programmer 2.0

Telescope operator 6.0

Total 20.0

Page 10: Technical manager’s report September 2005. Telescope activities Primary mirror hardpoint repair New mirror actuator controls Collimation analysis F/5

Staffing – Pasadena(budgeted level minus ATE)

Job Effort Job Effort

Accounting assistant 0.10 Manager tech group 0.80

Asst business manager 0.20 Mechanical engineer 0.50

Buyer 0.15 Postdoc 0.66

Controller 0.20 Programmer 0.90

Electronics engineer 1.00 Purchasing manager 0.15

Electronics technician 1.00 Shipping clerk 0.10

Instrument scientist 1.00 Technical manager 0.50

Machinist 0.50 Total 7.76

Page 11: Technical manager’s report September 2005. Telescope activities Primary mirror hardpoint repair New mirror actuator controls Collimation analysis F/5

Computer networking

• Network administration was a 10% effort from

Magellan programmer

• New instruments require more support

• LCO arranged for CTIO management– More IP addresses– Adds routers and firewall– Connects to CTIO network

Page 12: Technical manager’s report September 2005. Telescope activities Primary mirror hardpoint repair New mirror actuator controls Collimation analysis F/5

Clean room for large IR instruments

• MMIRS and FourStar are large (3x3x10 feet)

• Detectors need protection from static

electricity and particulate contamination

• Detectors are expensive ($2.5M for FourStar)

• Undisturbed workspace needed for long

periods for assembly and repairs

Page 13: Technical manager’s report September 2005. Telescope activities Primary mirror hardpoint repair New mirror actuator controls Collimation analysis F/5

Clean room for large IR instruments

• Clean room is required to support large

infrared instruments

• Proposal development in progress

Page 14: Technical manager’s report September 2005. Telescope activities Primary mirror hardpoint repair New mirror actuator controls Collimation analysis F/5

Carnegie shop

• New purchases– CNC lathe– CNC mill

• Increases production throughput

Page 15: Technical manager’s report September 2005. Telescope activities Primary mirror hardpoint repair New mirror actuator controls Collimation analysis F/5

Instruments

• Assume we can support six facility

instruments

• How to handle incoming 7+ instruments

• Plus new telescope subsystems (new

secondaries, AO, etc.)

Page 16: Technical manager’s report September 2005. Telescope activities Primary mirror hardpoint repair New mirror actuator controls Collimation analysis F/5

Instruments – page 1

Instrument Science rank Effort

IMACS F/2 3.0 High

IMACS F/4 2.8 High

MIKE 2.8 Low

FourStar 2.6 High

PANIC 2.5 Low

LDSS 2.2 Low

MagIC 2.0 Low

F/11 AO 2.0 High+

Page 17: Technical manager’s report September 2005. Telescope activities Primary mirror hardpoint repair New mirror actuator controls Collimation analysis F/5

Instruments – page 2

Instrument Science rank Effort

MMIRS 1.9 High

MMFS 1.9 High

MIRAC/AO 1.8 High

MegaCAM 1.6 High

MagE 1.6 Lo

MMTF 1.5 High

GISMO 1.4 Medium

MOE 1.4 Low

Page 18: Technical manager’s report September 2005. Telescope activities Primary mirror hardpoint repair New mirror actuator controls Collimation analysis F/5

Instruments

• Instruments can displace similar equipment

(trade PANIC for FourStar)

• User status (PI or other expert required on

every observing run)

• Mothball (minimum 18 months) to

accommodate the new

• Decommission