technical losses in pea
TRANSCRIPT
Provincial Electricity AuthorityProvincial Electricity Authority11
TECHNICAL LOSSES TECHNICAL LOSSES of of
PEA DISTRIBUTION PEA DISTRIBUTION SYSTEMSYSTEM
Provincial Electricity AuthorityProvincial Electricity AuthorityThailandThailand
Provincial Electricity AuthorityProvincial Electricity Authority22
- OVERVIEWS OF PEAOVERVIEWS OF PEA
OUTLIOUTLINESNES
- PEA’S DISTRIBUTION PEA’S DISTRIBUTION NETWORK PROFILENETWORK PROFILE- PEA’S LOSSES PEA’S LOSSES
COMPUTATION & COMPUTATION & ACCOUNTINGACCOUNTING
- PEA’S OVERALL - PEA’S OVERALL TECHNICAL LOSSES TECHNICAL LOSSES
MANAGEMENT MANAGEMENT PROGRAMPROGRAM
- - CONCLUSICONCLUSI
ONSONS
Provincial Electricity AuthorityProvincial Electricity Authority33
Provincial Electricity Provincial Electricity Authority (PEA) is a Authority (PEA) is a
government enterprise government enterprise under the Ministry of under the Ministry of
Interior. It was Interior. It was established under established under 19601960 act by the Royal Decree act by the Royal Decree executed on September executed on September 20,196020,1960, then published , then published
in the Government in the Government Gazette on September Gazette on September
27,196027,1960
OVERVIEWS OVERVIEWS OF PEA OF PEA
Provincial Electricity AuthorityProvincial Electricity Authority44
The service area of The service area of the PEA is the PEA is approximately approximately 510,000510,000 kmkm22, accounting for , accounting for 928928 PEA’s sub - office PEA’s sub - office scattered throughout scattered throughout the country, rendering the country, rendering service to their service to their customers. The customers. The PEAPEA has has grouped its services area grouped its services area into 4 regions.into 4 regions.
PEA Service PEA Service Area Area
Provincial Electricity AuthorityProvincial Electricity Authority55
Chiang MaiChiang Mai
PhitsanulokPhitsanulok
Lop BuriLop BuriNokhon RatchasimaNokhon Ratchasima
Ubon Rat.Ubon Rat.
Udon ThaniUdon Thani
Ayutthaya
Chon Buri
Nakhorn Prathom
PetchaburiPetchaburi
Nakhon Sri ThammaratNakhon Sri Thammarat
YalaYala
Provincial Electricity AuthorityProvincial Electricity Authority66
DISTRIBUTION DISTRIBUTION NETWORK PROFILE NETWORK PROFILE
PEA classifies PEA classifies distribution voltage level distribution voltage level into into 3 levels : 3 levels :
- High voltage level - High voltage level : : 115, 69 kV115, 69 kV
- Medium voltage - Medium voltage level level :: 22, 33 kV 22, 33 kV- - Low voltage levelLow voltage level
: 400/230 : 400/230 VV
Provincial Electricity AuthorityProvincial Electricity Authority77
PEPEA use the various A use the various type of conductors for type of conductors for MV. The standards MV. The standards according to according to TISTIS and and IECIEC..
STANDARDIZE STANDARDIZE Conductor size for Conductor size for MV MV (I)(I)
Provincial Electricity AuthorityProvincial Electricity Authority88
STANDARDIZE STANDARDIZE Conductor size for Conductor size for MV MV (II)(II)
Bare Conductor Current Bare Conductor Current RatingsRatingsCross Cross
section section (mm(mm22))5050
9595185185
Current Current Rating Rating
(Amperes(Amperes))
225225340340520520
Provincial Electricity AuthorityProvincial Electricity Authority99
STANDARDIZE STANDARDIZE Conductor size for Conductor size for MV MV (III)(III)
Cross Cross section section (mm(mm22))5050
185185
Current Current Rating Rating
(Amperes(Amperes))
185185425425
Partially Insulated Cable Partially Insulated Cable Current RatingsCurrent Ratings
Provincial Electricity AuthorityProvincial Electricity Authority1010
STANDARDIZE STANDARDIZE Conductor size for Conductor size for MV MV (IV)(IV)
Cross Cross section section (mm(mm22))5050
185185
Current Current Rating Rating
(Amperes(Amperes))
180180410410
Spaced Aerial Cable Current Spaced Aerial Cable Current RatingsRatings
Provincial Electricity AuthorityProvincial Electricity Authority1111
STANDARDIZE STANDARDIZE Conductor size for Conductor size for MV MV (V)(V)
Underground Cable Current Underground Cable Current Ratings : Ratings : 240240 mm mm22
TotTotal al CirCircuicuitt
1122334455
400400337337298298272272251251
Current Current Rating Rating
(Amperes(Amperes))
Provincial Electricity AuthorityProvincial Electricity Authority1212
STANDARDIZE STANDARDIZE Conductor size for Conductor size for LV LV
Cross Cross section section (mm(mm22))3535
50509595
Current Current Rating Rating
(Amperes(Amperes))
152152194194295295
Aluminum Conductor Aluminum Conductor Current RatingsCurrent Ratings
Provincial Electricity AuthorityProvincial Electricity Authority1313
PEA’s Substation PEA’s Substation TransformerTransformer (I) (I)
The substation The substation transformers shall transformers shall have ratings as have ratings as follow :follow :
Rated power output : Rated power output : 30/40/50 MVA30/40/50 MVA and and 15/20/25 15/20/25 MVAMVARated primary voltage :Rated primary voltage : 115 kV115 kVOn load tapping voltage :On load tapping voltage : +10%+10% to - to -10%10% of of 115 kV115 kV, , 1.25%1.25% in each step. in each step.
Provincial Electricity AuthorityProvincial Electricity Authority1414
PEA’PEA’ss Substation Substation Transformer Transformer (II)(II)
HV/MVHV/MV Substation Substation TransformerTransformer
NNoo
1122
TransforTransformermer
RatingRating50502525
TransforTransformation mation voltagevoltage115/2115/2
2-332-33115/2115/22-332-33
Provincial Electricity AuthorityProvincial Electricity Authority1515
PEA’PEA’ss Substation Substation Transformer Transformer (II)(II)
MV/LVMV/LV Substation Substation TransformerTransformer
NNoo
11
22
TransforTransformermer
RatingRating (kVA)(kVA)
50, 100, 50, 100, 160, 250, 160, 250, 315, 400, 315, 400,
50050010, 20, 10, 20,
3030
TransforTransformation mation voltagevoltage22-22-
33kV/33kV/400-230 400-230
VV
22-22-33kV/230 33kV/230
VV
PhPhasease
3 3 phaphasese
1 1 phaphasese
Provincial Electricity AuthorityProvincial Electricity Authority1616
INSTALLATION INSTALLATION STANDARDSTANDARD
22-33 kV 22-33 kV Aerial Aerial Cable Cable
Feeder & Feeder & Bare Bare
ConductoConductor Feederr Feeder
Provincial Electricity AuthorityProvincial Electricity Authority1717
Provincial Electricity AuthorityProvincial Electricity Authority1818
Meter Meter InstallatInstallat
ionion
Provincial Electricity AuthorityProvincial Electricity Authority1919
CAPACITOCAPACITOR R (I)(I)
Provincial Electricity AuthorityProvincial Electricity Authority2020
CAPACITOCAPACITOR R (II)(II)
Provincial Electricity AuthorityProvincial Electricity Authority2121
LOSSES LOSSES COMPUTATION & COMPUTATION &
ACCOUNTING ACCOUNTING
Energy PurchasedEnergy PurchasedEnergy GeneratedEnergy Generated
Energy SalesEnergy SalesFree of ChargeFree of Charge
Percentage Percentage of Losses of Losses
(% (% Losses)Losses)
== Energy Energy Losses Losses Energy Energy
RequiremRequirementent
xx1100
00
Energy Losses = Energy Energy Losses = Energy Requirement - Energy Requirement - Energy
ConsumptionConsumption
The methodology to The methodology to calculate losses of PEA calculate losses of PEA ::
Provincial Electricity AuthorityProvincial Electricity Authority2222
Methodology for Methodology for Distribution Distribution LossesLosses Computation Computation (I)(I)
Key Key variablvariabl
ee/unit/unit
SymSymbolbol
Actual Actual readingreading
//EstimateEstimate
dd
Variable Variable used in used in losses losses
computaticomputationon
Imported energy Imported energy through through
transmission transmission main intake main intake
substation (kWh)substation (kWh)Imported energy Imported energy
from utility from utility owned owned
distributed distributed generationgeneration (kWh)(kWh)Imported energy Imported energy from utility non-from utility non-
owned owned distributed distributed
generationgeneration (kWh)(kWh)
AA
BB
CC
Actual Actual readingreading
Actual Actual readingreading
Actual Actual readingreading(include(include
d A)d A)
YesYes
YesYes
YesYes
Provincial Electricity AuthorityProvincial Electricity Authority2323
Key Key variablvariabl
ee/unit/unit
SymSymbolbol
Actual Actual readingreading
//EstimateEstimate
dd
Variable Variable used in used in losses losses
computaticomputationon
Total metered Total metered sales for all sales for all
LV/MV customers LV/MV customers (kWh)(kWh)
Internally used Internally used energyenergy (kWh)(kWh)
HV tariff sales HV tariff sales (kWh)(kWh)
Free of chargeFree of charge (kWh)(kWh)
DD
EE
FFGG
Actual Actual readingreading
Actual Actual readingreading
Actual Actual readingreadingActual Actual
readingreading& &
EstimatEstimateded
YesYes
YesYes
YesYesYesYes
Methodology for Methodology for Distribution Distribution LossesLosses Computation Computation (II)(II)
Provincial Electricity AuthorityProvincial Electricity Authority2424
According to the According to the variable in the table variable in the table above, we can find the above, we can find the formula for the formula for the computation of computation of distribution system losses distribution system losses as follow : as follow :
Energy Losses (kWh) = Energy Energy Losses (kWh) = Energy Requirement - Energy Requirement - Energy ConsumptionConsumption
= (A+B+C) – = (A+B+C) – (D+E+F+G)(D+E+F+G)
Energy Losses (%) =Energy Losses (%) = 1- 1- (D+E+F+G)/(A+B+C) (D+E+F+G)/(A+B+C) xx 100% 100%
Provincial Electricity AuthorityProvincial Electricity Authority2525
Metering locations Metering locations and reading and reading frequencyfrequency
Key Key variablvariabl
ee/unit/unit
Imported Imported energy energy through through
transmission transmission main intake main intake substation substation
(kWh)(kWh)Imported Imported
energy from energy from utility owned utility owned distributed distributed generationgeneration
(kWh)(kWh)Imported Imported
energy from energy from utility non-utility non-
owned owned distributed distributed generationgeneration
(kWh)(kWh)
SymSymbolbol
MeteMetering ring locatlocationion
Manual Manual Reading Reading or AMRor AMRAA
BB
CC
HV HV sideside
HV HV sideside
HV HV sideside
ManualManual
ManualManual
ManualManual
SyncSync..
readreadingingYeYess
YeYess
YeYess
ReaReadingdingfreq.freq.End End
of of momonthnth
End End of of momonthnth
End End ofofmomonthlnthl
yy
Remark : Sync. Reading Remark : Sync. Reading : Auto reset meter: Auto reset meter
Provincial Electricity AuthorityProvincial Electricity Authority2626
Key Key variablvariabl
ee/unit/unit
SymSymbolbol
MeteMetering ring locatlocationion
Manual Manual reading reading or AMRor AMRTotal metered Total metered
sales for all sales for all LV/MV LV/MV
customers customers (kWh)(kWh)
Internally Internally used energyused energy
(kWh)(kWh)HV tariff sales HV tariff sales
(kWh)(kWh)
Free of chargeFree of charge (kWh)(kWh)
DD
EE
FF
GG
HV HV sideside
HV HV sideside
HV HV sideside
LV LV sideside
ManualManual
ManualManual
ManualManual
ManualManual
SynSync. c. reareadindingg
YeYes & s & NoNo
NoNo
YeYess
NoNo
ReaReadingdingfreq.freq.1515thth--44thth & & 2525thth--2626thth
every every montmont
hh2525thth - -2626thth
every every montmont
hhEnd End of of
montmonthh
25th -25th -26th 26th every every montmont
hh
Remark : Sync. Reading Remark : Sync. Reading : Auto reset meter: Auto reset meter
Provincial Electricity AuthorityProvincial Electricity Authority2727
Cust.Cust.
MMFF, synch. meter class 0.2, synch. meter class 0.2Record : at 0.00 am., at theRecord : at 0.00 am., at the end of every month.end of every month.
MMA,B,CA,B,C, synch. meter class 0.2 or 0.5, synch. meter class 0.2 or 0.5Record : at 0.00 am., at the end Record : at 0.00 am., at the end
of every month.of every month.
Cust. >1 MBahtCust. >1 MBaht
MMD1D1, synch. TOU meter, synch. TOU meterRecord : at 0.00 am., at the Record : at 0.00 am., at the end of every month.end of every month.
Large Cust. Large Cust. energy >energy >30 kW 30 kW MMD2D2, meter class 0.5, meter class 0.5
Record : on 25Record : on 25thth -26 -26thth of of every month.every month.
Internal Internal usedused MMEE, meter class 0.5, meter class 0.5
Record : on 25Record : on 25thth -26 -26thth of every month.of every month.
MMD3D3, meter class 0.1, meter class 0.1Record : on 25Record : on 25thth -26 -26thth of every month.of every month.
Large Cust. Large Cust. 30 kW < energy < 6630 kW < energy < 66 kVA kVA
Cust.Cust.MMD4D4, meter class 0.1, meter class 0.1Record : on 15Record : on 15thth -24 -24thth of every month.of every month.
1515thth-18-18thth :40% :40%1818thth-21-21thth :30% :30%2121thth-24-24thth :30% :30%
EGAT PEA115 kV115 kV22/33 kV22/33 kV
22/33 kV22/33 kV
400/230 400/230 kVkV
Provincial Electricity AuthorityProvincial Electricity Authority2828
12 region offices of 12 region offices of PEA report losses data PEA report losses data to PEA head office to PEA head office every every monthmonth, the billing system , the billing system (meter reading) and (meter reading) and software analysis are software analysis are used.used.
Provincial Electricity AuthorityProvincial Electricity Authority2929
This is the technical This is the technical losses data of year losses data of year 2004.2004.
Energy Energy Purchased Purchased (kWh)(kWh)
77,921,877,921,878.37278.372
Energy Energy GeneratedGenerated (kWh)(kWh)Energy Sales Energy Sales (kWh)(kWh)
Losses Losses (kWh)(kWh)Losses Losses (%)(%)
41,875,341,875,38484
73,124,273,124,233,64833,648
Free of chargeFree of charge (kWh)(kWh)
995,987,995,987,988988
3,843,533,843,532,1202,1204.934.93
A, CA, C
BB
D, E, FD, E, F
GG
--
--
Provincial Electricity AuthorityProvincial Electricity Authority3030
Losses Evaluation in Losses Evaluation in 2004 by formula is:2004 by formula is:
Energy Losses (kWh) = Energy Losses (kWh) = (A+B+C) – (D+E+F+G)(A+B+C) – (D+E+F+G)
Energy Losses (%) = 1- Energy Losses (%) = 1- (D+E+F+G)/(A+B+C) (D+E+F+G)/(A+B+C) xx 100% 100%
Energy Losses (kWh) = Energy Losses (kWh) = (77,921,878,372(77,921,878,372 + 41,875,384) – + 41,875,384) –
(73,124,233,648 + 995,987,988) (73,124,233,648 + 995,987,988) kWhkWh
= 3,843,532,120 = 3,843,532,120 kWhkWh
Energy Losses (%) = 1- Energy Losses (%) = 1- (D+E+F+G)/(A+B+C) (D+E+F+G)/(A+B+C) xx 100% 100%
= 1-= 1-(74,120,221,636/77,963,753,756) (74,120,221,636/77,963,753,756) x 100%x 100%
= 4.93%= 4.93%
Provincial Electricity AuthorityProvincial Electricity Authority3131
Historical MW Historical MW Demand growthDemand growth
YearYearMW MW at at distribution leveldistribution level% growth% growth
20002000
8,7248,724
5.815.81
20012001
9,4569,456
8.398.39
20022002
9,9629,962
5.355.35
20032003
10,63910,639
679.679.
20042004
11,72111,721
10.1710.17
Provincial Electricity AuthorityProvincial Electricity Authority3232
Historical Historical Distribution Distribution Losses Level Losses Level (I)(I)
Fiscal yearFiscal year
Energy Energy Purchase & Purchase & Energy Energy Generate Generate (MWh)(MWh)Energy Energy Sales Sales (MWh)(MWh)Free of Free of Charge Charge (MWh)(MWh)Losses Losses (MWh)(MWh)Losses (%)Losses (%)
20020000
56,256,29292
52,352,37070
6656653,253,25
775.795.79
20200101
60,60,414144
56,56,484822
646433
3,43,492925.75.788
20200202
64,64,343400
60,60,232399
757588
3,73,715155.75.777
20200303
70,70,222288
65,65,494977
868677
3,83,864645.55.500
20200404((SeSept0pt044))
58,58,404044
54,54,606088
757577
3,03,039395.25.200
Provincial Electricity AuthorityProvincial Electricity Authority3333
Historical Historical Distribution Losses Distribution Losses Level Level (II)(II)
Provincial Electricity AuthorityProvincial Electricity Authority3434
Historical Historical Distribution Losses Distribution Losses Level Level (III)(III)Fiscal yearFiscal year
Distribution Distribution losses (%)losses (%)HV HV network network (cct-km)(cct-km)MV MV network network (cct-km)(cct-km)LV LV network network (cct-km)(cct-km)Total KVA of Total KVA of Distribution Distribution transformer transformer (MVA)(MVA)
20200000
5.75.799
3,83,80909
243243,82,8244
338338,49,4944
37,37,511511
20200101
5.75.788
4,64,62525
244244,61,6188
344344,44,4499
37,37,668668
20200202
5.75.777
5,25,28686
252252,61,6144
354354,65,6599
38,38,465465
20020033
5.55.500
6,06,07979
260260,71,7144
368368,47,4777
37,37,401401
20020044
((SeSept0pt044))5.25.200
6,66,60000
265265,90,9011
388388,83,8300
42,42,052052
Provincial Electricity AuthorityProvincial Electricity Authority3535
PEA’s Energy PEA’s Energy Forecast Forecast (I)(I)
YEARYEAR
Energy requirementEnergy requirement(GWh)(GWh)Peak demandPeak demand(MW)(MW)
20052005
83,52883,528
12,61512,615
20062006
90,814 90,814
13,68513,685
20072007
98,455 98,455
1414,806,806
20082008
106,148106,148
15,94715,947
20092009
114,263 114,263
17,15117,151
20102010
123,066 123,066
18,45118,451
Provincial Electricity AuthorityProvincial Electricity Authority3636
OVERALL OVERALL TECHNICAL LOSSES TECHNICAL LOSSES
MANAGEMENT MANAGEMENT PROGRAM PROGRAM (I)(I)
1. System 1. System Planning Planning DesignDesign The criteria of The criteria of substation and distribution substation and distribution system of PEA are :system of PEA are :
Provincial Electricity AuthorityProvincial Electricity Authority3737
Substation’Substation’s Criterias Criteria
1)1) Transformer Transformer capacity : capacity : 25 MVA25 MVA or or 50 MVA50 MVA
2) 2) Transformer max. Transformer max. loading capacity :loading capacity :- - 56%56% of rating of rating capacity for capacity for N-1N-1 criteriacriteria- - 75%75% of rating of rating capacity for capacity for N-0 N-0 criteriacriteria
33 )) Breaker rating Breaker rating (IC)(IC) : :- - 31.5 31.5 kA for kA for 115115 kV kV- - 2525 kA for kA for 22/3322/33 kV kV
Provincial Electricity AuthorityProvincial Electricity Authority3838
MV MV (22/33 kV)(22/33 kV) Distribution’s Distribution’s Criteria Criteria (I)(I)
1)1) Voltage drop at peak Voltage drop at peak load :load :- 5% - 5% for normal conditionfor normal condition- 10% - 10% for emergency for emergency conditioncondition
2) 2) Line loading capacity:Line loading capacity:- - 8 MVA 8 MVA fofor 22 kV r 22 kV system, system, no more than 18 kmno more than 18 km..- 12 MVA - 12 MVA forfor 33 kV 33 kV system, system, no more than 27 kmno more than 27 km..
33 ) Conductor size : ) Conductor size : 185185 mmmm22 aluminum in main aluminum in main feedersfeeders
Provincial Electricity AuthorityProvincial Electricity Authority3939
4)4) Types of conductors : Types of conductors :- - Bare conductors for clear Bare conductors for clear area, rural area.area, rural area.- - Spaced aerial cable for Spaced aerial cable for cities, industrial area and cities, industrial area and
lines under 115 kV lines under 115 kV transmission lines.transmission lines.- Underground cable for in - Underground cable for in front of substation andfront of substation and
environment protected environment protected area.area.
5) 5) Adequacy for transferring Adequacy for transferring load from nearby load from nearby substation.substation.
Provincial Electricity AuthorityProvincial Electricity Authority4040
LV LV (400/230 V)(400/230 V) Distribution’s Distribution’s CriteriaCriteria1)1) Voltage drop at peak Voltage drop at peak
load :load :- 5% - 5% for normal conditionfor normal condition- 10% - 10% for emergency for emergency conditioncondition
2) 2) Line loading capacity:Line loading capacity:- - 80% 80% of line, transformer, of line, transformer, no more than 1 kmno more than 1 km
33 ) Conductor size : ) Conductor size : 95, 50, 95, 50, 35 mm35 mm22 aluminum aluminum
Provincial Electricity AuthorityProvincial Electricity Authority4141
The Standard The Standard Power Factor Power Factor (I)(I)
1) Standard Power Factor 1) Standard Power Factor ofof PEA-EGAT : PEA-EGAT :- Power factor - Power factor >> 0.8750.875 lagging at each delivery lagging at each delivery pointpoint
((EGATEGAT Substation) Substation)- Power factor <- Power factor < 0.875 0.875 lagging must pay for lagging must pay for penalty penalty
about 5 about 5 baht/kbaht/kVARVAR/month of the /month of the different kdifferent kVARVAR
between original and between original and 0.8750.875 power factor. power factor.
Provincial Electricity AuthorityProvincial Electricity Authority4242
2) Standard of HV 2) Standard of HV Capacitor Bank :Capacitor Bank :- - 5, 10, 20, 305, 10, 20, 30 and and 7575 k kVARVAR 33 phase phase LVLV capacitor. capacitor.- Fixed 3x100 and - Fixed 3x100 and 6x100 6x100 kVARkVAR..- - VARVAR control, time control control, time control of of 15x100 kVAR15x100 kVAR switched switched
capacitor.capacitor.- Power factor control - Power factor control 7.2 7.2 MVARMVAR indoor capacity indoor capacity bank bank
((33steps steps x x 2.4 MVAR2.4 MVAR) ) substation installation substation installation only.only.
Provincial Electricity AuthorityProvincial Electricity Authority4343
3) Standard Power Factor 3) Standard Power Factor of PEA Customer :of PEA Customer :- Only - Only 3030 k kWW up demand up demand customer is responsible customer is responsible forfor
keeping power factor keeping power factor not less than not less than 0.850.85 lagging. lagging.- Power factor < - Power factor < 0.850.85 lagging, the customer lagging, the customer must pay must pay
for penalty about for penalty about 55 Baht/kBaht/kVARVAR/month./month.
Provincial Electricity AuthorityProvincial Electricity Authority4444
OVERALL OVERALL TECHNICAL LOSSES TECHNICAL LOSSES
MANAGEMENT MANAGEMENT PROGRAMPROGRAM (II)(II)
2. Equipment Design 2. Equipment Design & Specifications& Specifications The The PEAPEA’s listings of ’s listings of
MV&LVMV&LV conductors with conductors with technical parameters and technical parameters and transformers with load & transformers with load & no load losses and no load losses and impedance are :impedance are :
Provincial Electricity AuthorityProvincial Electricity Authority4545
CONDUCTOR designs CONDUCTOR designs & specifications& specifications (I)(I)
CondConductoructorTypeType185A185A185P185P
ICIC50SA50SA
CC185S185SACAC
RR11
(ohm(ohm/km)/km)0.170.176464
0.210.210707
0.820.821919
0.210.210707
XX11
(ohm(ohm/km)/km)0.4090.409
110.4140.414
440.3390.339
550.2980.298
66
RR00
(ohm(ohm/km)/km)0.400.400505
0.350.355454
1.101.109393
0.440.446262
XX00
(ohm(ohm/km)/km)1.5981.598
991.6441.644
881.8971.897
551.8311.831
00
Provincial Electricity AuthorityProvincial Electricity Authority4646
CONDUCTOR designs CONDUCTOR designs & specifications & specifications (II)(II)
CondConductoructorTypeType185A185A185P185P
ICIC50SA50SA
CC185S185SACAC
GG11
(uS/(uS/km)km)
00000000
BB11
(uS/(uS/km)km)
3.5323.53200
3.6363.63600
5.1225.12200
5.9515.95100
GG00
(uS/(uS/km)km)
00000000
BB00
(uS/(uS/km)km)
1.9371.93700
1.3641.36400
1.3951.39500
1.5221.52200
Provincial Electricity AuthorityProvincial Electricity Authority4747
TRANSFORMER losses TRANSFORMER losses & impedance& impedance
TransformTransformer Rating er Rating
(MVA)(MVA)30/4030/40
/50/5015/2015/20
/25/25
No Load No Load LossLoss(kW)(kW)
Load Load LossLoss(kW)(kW)Up to Up to
25.525.5Up to Up to 15.015.0
Up to Up to 150150
Up to Up to 100100
Provincial Electricity AuthorityProvincial Electricity Authority4848
OVERALL OVERALL TECHNICAL TECHNICAL LOSSES LOSSES MANAGEMENT MANAGEMENT PROGRAMPROGRAM (III)(III)
3. System Operation 3. System Operation & Maintenance& Maintenance-Loading monitoring Loading monitoring programprogram : : *for HV - record at *for HV - record at substation monthly.substation monthly. *for LV - record at *for LV - record at distribution transformer distribution transformer yearly. yearly.
Provincial Electricity AuthorityProvincial Electricity Authority4949
3. System Operation 3. System Operation & Maintenance& Maintenance (cont.)(cont.)
- - PEAPEA uses on load tap uses on load tap change transformers change transformers ((OLTC)OLTC) to to manage voltage profile manage voltage profile at at HV/MVHV/MV substations. For substations. For MV/LVMV/LV substation, we substation, we analyze load in each area analyze load in each area andand change the tap of change the tap of transformers to the transformers to the proper tap.proper tap.
Provincial Electricity AuthorityProvincial Electricity Authority5050
-Feeder balancing program Feeder balancing program :: StandardStandard : : unbalance unbalance current current << 10%10%
Monitoring ProcedureMonitoring Procedure : : by reading incoming & by reading incoming & outgoing feeder at outgoing feeder at substation every month substation every month andand measured measured distribution transformer’s distribution transformer’s load once load once a year.a year.
3. System Operation 3. System Operation & Maintenance& Maintenance (cont.)(cont.)
Provincial Electricity AuthorityProvincial Electricity Authority5151
Load unbalance Load unbalance ImprovingImproving : : UnbalanciUnbalancing > ng > 10%10%
1-phase 1-phase branches& branches&
1-phase 1-phase transformerstransformers
&&1-phase 1-phase
customer customer shall be shall be
reconnected reconnected to to
the proper the proper phasesphases
1-1-phase phase branches’ branches’
load load > > 150 150 kkVAVAUpgraded Upgraded
to to 3-phase3-phase
Provincial Electricity AuthorityProvincial Electricity Authority5252
-Power factor correction :Power factor correction : Monitoring ProcedureMonitoring Procedure : : Power factor at substation Power factor at substation shall be checked from meter shall be checked from meter reading MW and MVARreading MW and MVAR
3. System Operation 3. System Operation & Maintenance& Maintenance (cont.)(cont.)
Provincial Electricity AuthorityProvincial Electricity Authority5353
Power Factor ImprovingPower Factor Improving : :- Find optimal capacitor - Find optimal capacitor location using computer location using computer software.software.- Check real current and - Check real current and power factor from meters in power factor from meters in
existing system.existing system.- Obtain the optimal - Obtain the optimal location.location.- Install LV fixed capacitor at - Install LV fixed capacitor at 100 kVA or more distribution 100 kVA or more distribution
transformer. (kVAR = 10% transformer. (kVAR = 10% of transformer Rating)of transformer Rating)
Provincial Electricity AuthorityProvincial Electricity Authority5454
OVERALL OVERALL TECHNICAL LOSSES TECHNICAL LOSSES
MANAGEMENT MANAGEMENT PROGRAMPROGRAM (IV)(IV)
4. Technical Losses 4. Technical Losses Assessment Assessment MethodologyMethodology PEA uses computer PEA uses computer software such as PSS/Adept software such as PSS/Adept to calculate distribution to calculate distribution losses. This soft-ware needs losses. This soft-ware needs Single Single line diagram that contains the line diagram that contains the database as follow :database as follow :
- Daily Load - Daily Load (MW)(MW)
- Length of - Length of feedersfeeders
- Power - Power factorfactor
- Type and - Type and characteristic ofcharacteristic of Distribution Distribution transformerstransformers
- No. and type - No. and type of customersof customers
Provincial Electricity AuthorityProvincial Electricity Authority5555
OVERALL OVERALL TECHNICAL LOSSES TECHNICAL LOSSES
MANAGEMENT MANAGEMENT PROGRAMPROGRAM (V)(V)
5. Overall technical losses 5. Overall technical losses optimization, issues andoptimization, issues and learning pointslearning points * MVAR program or * MVAR program or capacitor placement programcapacitor placement program
- The fix capacitors are - The fix capacitors are installed in every feeders. The installed in every feeders. The capacitor rated is about 10% capacitor rated is about 10% of each feeder’s load.of each feeder’s load.
- The installation of - The installation of switching capacitors depends switching capacitors depends on daily load curve.on daily load curve.
Provincial Electricity AuthorityProvincial Electricity Authority5656
5. Overall technical losses 5. Overall technical losses optimization, issues andoptimization, issues and learning pointslearning points (cont.)(cont.) * Voltage profile * Voltage profile improvement programimprovement program PEA has installed SCADA PEA has installed SCADA system to monitor and manage system to monitor and manage the equipments in distribution the equipments in distribution systems and also control systems and also control voltage in system by switching voltage in system by switching capacitor. But SCADA isn’t capacitor. But SCADA isn’t reach full efficiency now, we reach full efficiency now, we have to improve it to handle all have to improve it to handle all function of program.function of program.
Provincial Electricity AuthorityProvincial Electricity Authority5757
5. Overall technical losses 5. Overall technical losses optimization, issues andoptimization, issues and learning pointslearning points (cont.)(cont.) * Loading profile * Loading profile improvement programimprovement program - For distribution - For distribution transformers, we have to transformers, we have to manage the existing manage the existing transformers and install new transformers and install new transformers or change to transformers or change to high rated transformer for high rated transformer for increasing load.increasing load. - The load monitoring - The load monitoring at substations are at substations are programmed monthly to programmed monthly to manage load profile.manage load profile. -- PEA has plan to reduce PEA has plan to reduce capacitor of transformers, If capacitor of transformers, If the transformers supply load the transformers supply load less than 30% of rated.less than 30% of rated.
Provincial Electricity AuthorityProvincial Electricity Authority5858
PEA’s realized PEA’s realized that the meter reading that the meter reading error such as the overlap error such as the overlap reading date is the reading date is the function of loss analysis’s function of loss analysis’s error so the 50,000 AMR error so the 50,000 AMR meters was planed to meters was planed to install within year 2007.install within year 2007.
Year 2004200520062007Total
.No of AMR 5,00015,00015,00015,00050,000
Ratio to Total Per Year10% 30% 30% 30%100%
Accumulate10% 40% 70%100%100%
CONCLUSICONCLUSIONSONS
Provincial Electricity AuthorityProvincial Electricity Authority5959
CONCLUSICONCLUSIONS ONS (II)(II) To improve the To improve the
technical losses analysis, technical losses analysis, PEA has employed the PEA has employed the consultant to :consultant to :- research, specify and - research, specify and improve the methodology improve the methodology of lossesof losses analysis and forecast.analysis and forecast.- develop the software for - develop the software for capacitor installation. capacitor installation. - distribution transformer - distribution transformer criteria in distribution criteria in distribution system.system.
The pilot area of this project is The pilot area of this project is the feeder the feeder
in the central area.in the central area.
Provincial Electricity AuthorityProvincial Electricity Authority6060
CONCLUSICONCLUSIONS ONS (III)(III)
And the last, PEA And the last, PEA set up the losses set up the losses optimization committee. optimization committee. The staffs are from PEA The staffs are from PEA head office and region head office and region office in order to manage office in order to manage and find the and find the methodology to optimize methodology to optimize losses.losses.
Provincial Electricity AuthorityProvincial Electricity Authority6161
The losses evaluation of The losses evaluation of the central area in year the central area in year 2004.2004.HV systemHV system
MV systemMV systemLV systemLV systemPower Power TransformerTransformerDistribution Distribution TransformerTransformer
0.270.27%%
2.442.44%%
4.344.34%%
0.170.17%%
2.372.37%%
Provincial Electricity AuthorityProvincial Electricity Authority6262
THANK YOUTHANK YOUfor your for your
attentionattention