technical appendix a - iaa.gov.il...iaa tender for a-vdgs version 1.0 appendix a – technical...
TRANSCRIPT
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 1 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
Technical Appendix A -
The A-VDGS
System Requirement Definition
Chapter 7
Scope of Work and Bidder’s Details
Amendment Record
Issue Date Reasons For
Change
Section
Amended Author Remarks
Version 1.0 16.8.2016 IAA
References and Related Documents Document Description
IAA_A-VDGS - Appendix A - Technical
Requirements - Glossary
Abbreviations and Terms
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 2 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
Table of Contents
7. The Project's Scope of Work (SOW) .............................................................................. 3
7.1 Background and Highlights .......................................................................................... 3 7.1.1 Chapter Objectives .......................................................................................................................... 3 7.1.2 Overview of the Project's Objectives ............................................................................................... 3 7.1.3 Overview of the Project's Implementation ..................................................................................... 3 7.1.4 The A-VDGS Project Interrelation with Other Ongoing Projects ..................................................... 4 7.1.4.1 Setting-Up Concourse E: Current Status & Major Relevant Milestones .......................................... 4 7.1.4.2 Setting-Up Concourse Passengers Loading Bridges of Concourse E: Current Status & Major Relevant Milestones ...................................................................................................................................... 5 7.1.5 Major Future Expansion Options ..................................................................................................... 5 7.1.5.1 Option1 – Expanding the system to Concourse A (O) ..................................................................... 5 7.1.5.2 Option 2 – Expanding the system to Remote (Hard) Stands (O) ..................................................... 5
7.2 The Bidder, Project Team & Organization – Reference Model .................................. 6 7.2.1 Involved Parties (Including Subcontractors) .................................................................................... 6 7.2.1.1 The Bidder's and Subcontractors Details (Q) ................................................................................... 6 7.2.2. Project's Organization.................................................................................................................... 13 7.2.3. Bidder's Project Team .................................................................................................................... 15
7.3. Project's Implementation Process ............................................................................... 19 7.3.1. Introduction ................................................................................................................................... 19 7.3.2. Setting Up the Basic System / Project Plan – Overview ................................................................ 19 7.3.2.1. Setting Up the WP#CS Central System / Project Plan – Overview ................................................. 19 7.3.2.2. Setting Up the WP#BCD System / Project Plan – Overview .......................................................... 23 7.3.2.3. Setting Up the WP#E System / Project Plan – Overview ............................................................... 25 7.3.3. Setting up Future Options ............................................................................................................. 26 7.3.4. Formal Reviews .............................................................................................................................. 27 7.3.5. Major Sub- Stages – Activities and Deliverables Overview ........................................................... 28 7.3.6. Project Plan .................................................................................................................................... 46 7.3.7. Tests ............................................................................................................................................... 49 7.3.8. Training ........................................................................................................................................ 59 7.3.9. Documentation ............................................................................................................................. 62 7.3.10. Involvement of the Bidder in the CFE activities ............................................................................. 64 7.3.11. Installation Requirements ............................................................................................................. 65
7.4. Project Management / Governance – Reference Procedures .................................... 68 7.4.1. Introduction ................................................................................................................................... 68 7.4.2. Managerial Procedure Objectives ................................................................................................. 68 7.4.3. Forums & Meetings ....................................................................................................................... 69 7.4.4. Reviews .......................................................................................................................................... 73 7.4.5. Reports .......................................................................................................................................... 74 7.4.6. Deliverable Management .............................................................................................................. 75 7.4.7. Quality Assurance .......................................................................................................................... 76 7.4.8. Risk Management .......................................................................................................................... 77
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 3 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
7. The Project's Scope of Work (SOW)
7.1 Background and Highlights
7.1.1 Chapter Objectives
1. This chapter describes the Project's Scope of Work (SOW) and provides
requirements for the implementation project, including tasks, outputs, principles
and project management methodology that the Supplier shall undertake during the
Contract Period.
2. The requirements in this chapter aim to minimize potential discrepancies of
expectations between the IAA and the Bidder. These requirements should enable
the Bidder to assess the scope and the depth of the response expected from it;
however, IAA shall endeavor that the actual execution of the Project will be made
as close as possible to the Bidder's best practices, standards, working procedures,
etc.
3. Section 2 above is subjected to IAA’s approval as stipulated in the Contract
regarding the 'Approved Project Execution Plan' and to the Revised Requirements
Definition (RRD) stage as stipulated in Section 7.3.5.3.17.3.5.3 Error! Reference
source not found.Error! Reference source not found.below.
7.1.2 Overview of the Project's Objectives
1. The IAA requests for Proposals for a complete integrative solution for A-VDGS
(Advanced Visual Docking Guidance System) solution as a Turnkey Firm Fixed
Price Project with as many COTS components as possible.
2. The Project’s Business Objectives and Goals and Project’s Schedule are concisely
described in Chapter 1 of the Technical Appendix A (The Technical Requirements),
in Section 1.1
3. The A-VDGS System’s Implementation Concept appear in Chapter 2, Section 2.4
of the Technical Appendix of the RFP.
7.1.3 Overview of the Project's Implementation
1. Please refer to Chapter 1, Section 1.5 and Chapter 2, Section 2.4 of the Technical
Appendix of the RFP.
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 4 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
7.1.4 The A-VDGS Project Interrelation with Other Ongoing Projects
1. In parallel with the A-VDGS project, IAA implements a few other significant
projects:
a. Setting Up Concourse E.
b. Setting Up the Passengers Loading Bridges (PLB) of Concourse E.
2. The Bidder shall fully cooperate throughout the term of the either the Supplier's
Selection Process (of the PLB’s) and/or the Contract with either the Bidders and/or
the Supplier of any existing or future system.
7.1.4.1 Setting-Up Concourse E: Current Status & Major Relevant Milestones
1. Timetable of Setting-Up Concourse E Project will be shared with the Awarded
Bidder at a later stage.
# Status Due
Date
Comments
1. Infrastructure
Readiness
Power Supply, Communication
Network, Civil Engineering
infrastructure are ready be tested by
the Selected Supplier.
2. Electronic Equipment
Installation Readiness
Dust free, Vibrations free, air-
conditioning, fire protection
approval, steady power supply, …
3. Calibration readiness All the Construction works have
been concluded, all temporary
obstacles, fences, etc. has already
been removed, all the Aprons are
paved and painted, and As Made
Surveyed Maps have been
submitted to the Selected Supplier.
4. Test Runs
5. Operational Activation 8/2017
2. The Bidder shall consider the above timetable in its Work Plan.
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 5 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
7.1.4.2 Setting-Up Concourse Passengers Loading Bridges of Concourse
E: Current Status & Major Relevant Milestones
1. IAA has not yet selected a supplier for the Passengers Loading Bridge. Information
shall be provided when available.
7.1.5 Major Future Expansion Options
1. The entire list of the Contract’s Options appears at Chapter 9 of the Technical
Appendix of the RFP.
2. The Bidder shall be aware that any item in the BOQ can be purchased during the
lifecycle of the system. This includes the DSS unit, training, WS, Spare parts, etc.
3. Following are major Options which are based on the price of a single DSS unit.
7.1.5.1 Option1 – Expanding the system to Concourse A (O)
1. For this option, The Bidder shall propose a complete and integral future expansion
of the A-VDGS System with Concourse A.
2. The Bidder should propose the Project as extension of the TLV AP solution.
3. The Bidder should assume that for the Concourse A the quantities as quoted in
Chapter 9.
4. Commercial issues are detailed in Section 9.8 in Chapter 9 of the Technical
Appendix. It is highly recommended to read Section 9.8 in order to realize the terms
and conditions of this Option.
5. The Concourse A Option shall be an option for IAA which may be implemented at
any time during the life cycle of the system.
7.1.5.2 Option 2 – Expanding the system to Remote (Hard) Stands (O)
1. For this option, The Bidder shall propose a complete and integral future expansion
of the A-VDGS System with Remote (Hard) Stands.
2. The Bidder should propose the Project as extension of the TLV AP solution.
3. The Bidder should assume that for the Remote (Hard)) Stands the quantities as
quoted in Chapter 9.
4. As mentioned in Section 9.9 of the Technical Requirements, the implementation of
remote (hard) stands shall be based on the price for a single DSS.
5. The Remote (hard) Stands Option shall be an option for IAA, which may be
implemented at any time and any quantity during the life cycle of the system.
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 6 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
7.2 The Bidder, Project Team & Organization – Reference
Model
7.2.1 Involved Parties (Including Subcontractors)
7.2.1.1 The Bidder's and Subcontractors Details (Q)
1. The Bidder shall fill in the required information in the following table within the
following sub-sections.
# Party Company Contact
Person
Phone, Fax &
1 Supplier / Integrator
Subcontractor 1
…
Subcontractor n
Local Support
Commercial representative
2. Local Subcontractor for the DSS’s Installation
a. The Bidder may have in-house all the capabilities and supplies required
by this Bid including support services; However the Bidder may, at its
sole discretion, to complement its capabilities, qualifications, products
and such using highly skilled Local Subcontractor with proven
successful experience in supplying services and goods as required in this
bid for de-installation of the existing DSS’s and installation of the new
DSS’s.
b. The Israeli Subcontractor for installation of DSS’s (hereinafter: The
Local Installation Subcontractor and / or LIS) shall comply with the
following requirements:
c. The LIS has participated in processes of supply and installation,
commencing from the year 2012, of at least 50 electronic devices (such
as: display signs, cameras, antennas, …), located at outdoors
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 7 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
environment, requires Height Work Permits and approved by Civil
Engineering Constructor(s) and an Electrical Engineer.
d. The LIS has supplied and installed such electronic devices, to at least 3
customers.
e. The LIS has employed at least 5 employees during the past 3 years with
an experience in the aforementioned installation processes.
f. The LIS is certified for a Quality Control system in accordance with the
ISO 9001:2000, or equivalent standards.
g. The following shall be considered as an advantage: (Q)
i. The LIS has acquired experience in working in an operational
airport at its airside.
ii. The LIS shall appoint a suitably qualified and experienced Project
Coordinator for the duration of the Installation Phase of this
project, hereinafter referred to as the ‘Local’ Project Coordinator.
iii. The ‘Local’ Project Coordinator is expected to be in Israel for the
whole duration of the Installation Phase of the Project.
iv. The ‘Local’ Project Coordinator may be either Israeli or foreign,
and must be able to converse fluently in the English language. It
is an advantage, but not a requirement, for the ‘Local’ Project
Coordinator to speak Hebrew.
3. For each of the involved parties (The Bidder and Subcontractors / local
support), the Bidder shall provide information according to the following
form. The Bidder may add as many copies as needed for the following form.
The Bidder shall provide information about all the involved parties and for
each party in a separated table. If the Bidder has provided that information in
Appendix C (the Bidder Statement) of the Invitation, a reference to the
appropriate form is needed.
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 8 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
Details Required Information #
Registered office address 1.
Company’s registration number, registration date,
country of registration
2.
Number of years under the same Corporate name 3.
Web Address 4.
Name of Owners (whether a company or an
individual)
5.
Name of CEO and tenure in this position 6.
Names of directors 7.
Free text information
such as: public or
private company,
branches etc.
Description of Company 8.
Number of years of experience as a Prime Contractor
in A-VDGS related projects:
9.
In Own Country
Internationally
Number of years of experience as a subcontractor in
A-VDGS related projects:
10.
In Own Country
Internationally
2015 2014 2013 2012 2011 Number of operational A-VDGS Clients:
As a prime contractor?
11.
In Own Country
Internationally
2015 2014 2013 2012 2011 Number of employees 12.
For each of the operational Systems as mentioned above in entry 11
as of year 2013, As a prime contractor, The Bidder is requested to
attach a copy of the Site Acceptance Tests.
13.
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 9 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
7.2.1.2. Division of Roles between the Involved Parties (Q)
1. The Bidder shall describe the parties involved in the implementation of the A-
VDGS project, and the division of Roles/Tasks.
7.2.1.3. Previous Cooperation between the Involved Parties (Q)
1. The bidder shall describe previous cooperation between the involved parties: (Q)
Involved parties Type and nature of joint activity
Customer Year Principal
contractor
1st sub-
contractor …
Local
Supp
ort
Proposal
to Tender Pilot
Operational
system
Current
Maint.
Other,
specify:
7.2.1.4. Subcontractors Management
1. The Bidder shall describe any Subcontractors involved during the project's
implementation and future options, as well as for the project's Warranty, Service
and Maintenance stages.
2. The Bidder shall describe the subcontractors' experience concerning with the
aforementioned activities. (Q)
3. The Bidder shall provide information as to the management methodology
concerning subcontractors/suppliers. The description shall include quality control,
risk analysis and a detailed description of the replacement strategy for the case
where the subcontractor failed in the execution of the work according to the
required standards. (Q)
4. The Bidder shall provide a Letter of authorization from the sub-contractor to the
Bidder allowing the Bidder to propose the sub-contractor’s services for this Tender.
7.2.1.5. Experience, Goodwill and Customers
1. The information provided by the Bidder in response to this section shall have
significant impact on the quality evaluation of the Bidder's Proposal. An advantage
in quality evaluation will be given to:
a. Operational provability (The more the offered A-VDGS is in
operational use, in as many Airports, longer duration in use, etc.).
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 10 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
b. Quantities supplied of the same or equivalent Systems such as offered
in the Bidder's Proposal.
c. Compliance with the related functional, performance and maintenance
requirements listed within this RFP.
2. Relevant Projects Completed (Q)
a. The Bidder shall provide information about both A-VDGS projects
completed by the Bidder (as a prime contractor), where the system had
been fully accepted by the client over the past five years (2011, 2012,
2013, 2014 and 2015) in the following table format.
b. In particular, The Bidder shall describe in detail one site, with similar
characteristics and complexities to those required for the A-VDGS
System in Israel, thus demonstrating the Bidder’s ability to deliver a
complete solution as required under this Tender's Document.
c. The Bidder shall fully describe in details a case study of a complete
Project in operation, most similar to the A-VDGS, including but not
limited to: Centralized System, Obstacle Detection and Alert Module,
the architecture, BOM, challenges, solutions, deployment time,
example documents of FAT and SAT (also of the COTS components),
lessons learnt, etc.
d. The Bidder should emphasize and detail any difference in
capabilities/technologies/bugs fixes between the future A-VDGS
Version and the described project. Also, if there are any major
changes, the Bidder shall explain how these are intended to be tested.
# Subject Remarks
1 Name of customer Add airport info:
Num of movements, number of passenger, layout,
number of gates, …
2 Current status Pilot, During Qualification Process, Operational,
Not In Use, … and Further business engagement
since originally signing the contract
3 Contact person details Information concerning the references shall
include at least the following information: name
of contact person, function, term of acquaintance,
nature of acquaintance, contact details (phone,
fax, email) and a written document that shall be
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 11 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
# Subject Remarks
signed by the contact person expressing that
he/she is aware that IAA may contact him/her for
this purpose.
4 Type of contract Main Contractor, Subcontractor (if so, to whom)
5 A-VDGS solution
project major
milestones
Project's Starting Date, Project's Acceptance's
Date, System Handover Date
6 Description of the A-
VDGS
Please refer Section c’ above.
10 System limitations and
constraints
11 Interfaces Such as A-SMGCS, Flight Plan info, Airport Info,
Electronic Flight Strip, others. Name the specific
system.
Certification /
Acceptance
Please provide information such as: System
certification date, who certified the system, how
long it took, Division of roles among the supplier,
the client and certifying body, content of examined
elements, whether it was necessary to certify the
Operational Staff as well, whether it was
necessary to certify the Technical Staff as well,
etc. The Bidder may attach the relevant
certificates to its Proposal.
Reference Letters The information concerning the references shall
include the following at least: name of the
company, name of reference, function, term of
acquaintance, nature of acquaintance, contact
details (phone, fax, email) and a written document
that shall be signed by the reference expressing
that he/she is aware that IAA may contact him/her
for this purpose.
*Additional pages may be added for more than one project.
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 12 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
3. All Projects in Progress
a. The Bidder shall provide information about all of its related projects that are
presently in progress, including those where the Bidder has received a letter
of intent, but a formal contract has not yet been awarded and/or entered into
force, in the format specified at Section 7.2.1.5
4. Experience: Geographical Spread (Q)
a. The Bidder shall provide information about all countries in which works
similar to the A-VDGS projects have been undertaken, in the last five years
(2011-2015):
# Country Details*
1
2
… … …
*Bidder is required to provide details of the project such as year of installation,
location where the System resides, operational status, further engagements
since the 1st installation, etc.
5. The Bidder shall elaborate about procedures to verify customer’s satisfaction (such
as surveys for examples) during the Project and afterwards during the Maintenance
and Operational Term and Future Expansions. The Bidder shall provide its
methodology, its forms and at least 2 recent forms (for each of the 3 activities that
are mentioned above: the Project, the Maintenance and Operational Term and
Future Expansions) that were filled by the Bidder's clients. (Q)
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 13 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
7.2.2. Project's Organization
7.2.2.1. Project Team Highlights
1. The Bidder shall refer to the following highlights while introducing the proposed key
persons for IAA's project (see clauses: 7.2.3.2, 7.2.3.3, 7.2.3.4, etc.). (Q)
2. The Selected Bidder is required to provide a Project Team (PT) fully capable of
managing, supervising and successfully executing the A-VDGS project – to provide
a comprehensive, integrative and seamless solution as required by this Tender. The
Bidder is required to present proven methodologies for the planning execution,
monitoring and control of similar previous projects. The methodologies shall include
all phases of the project lifecycle, such as starting with sites' surveys, update of
requirement definitions, design, execution, through acceptance tests and assimilation.
The Bidder is required to present its internal monitoring methodologies to ensure
accomplishment of the plan's objectives (such as internal follow up meetings, internal
review for the meaningful milestones, other channels of communication with the
participating parties, monitoring client's awareness and satisfaction, etc.) throughout
the project's lifecycle. The Bidder shall present its methodologies and best practices
for managing projects with remote international locations. (Q)
3. The PT shall include experts from different disciplines as required for such a project
with proven ability to handle the challenges in the following domains: (Q)
a. Management of a multi-disciplinary project endeavor.
b. Assembling a pragmatic and applicable technological solution.
c. Coordinated teamwork with subcontractors from Israel (if there are such
subcontractors) and abroad.
d. Interfacing with IAA external suppliers, equipment that shall be executed
in a harsh environment - at an operational airport.
e. Providing warranty, service and maintenance support for the A-VDGS
solution spanning over a long period of time.
4. The PT is expected to have thorough professional familiarity and experience with the
main supply components in the project, such as: A-VDGS, Infrastructure design and
execution and service and maintenance for a critical operational system requiring
maximal availability. (Q)
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 14 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
5. The PT members shall be first-class, motivated and responsible professionals who
are willing to engage in strenuous work, in possibly different time zones, maintain
maximal availability and be capable of delivering the required tasks under tight
schedules. They shall have full access to all relevant expertise and knowledge base
of the Bidder's group. They shall also be capable of interacting smoothly and
coordinating with IAA entities and suppliers. (Q)
6. IAA expects the Bidder to provide a formal authorization confirming that the PT
members are trained, skilled, qualified for their role in the Project and kept constantly
up to date with the best practices in their field of expertise, major suppliers and
products, solutions applied in other organizations (A-VDGS installations in other
airports), as well as having high level acquaintances in their field of expertise,
participate in relevant professional forums, etc. IAA expects to gain real added value
from highly competent professionals who stand in the forefront of world technology.
(Q)
7. The Bidder is required to have adequate operational backup capabilities to allow for
an efficient response to possible overloads (e.g. quantities/locations) that are
expected in such a project. (Q)
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 15 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
7.2.3. Bidder's Project Team
7.2.3.1. The Bidder's Proposed Project Team and Project Organization
Structure
1. All the details requested below shall be completed for all the team members involved
in project, including subcontractors (Q)
#
Work
er’s
Nam
e
Role in
the P
roject
Pro
fession
% Position Allotted to
IAA Project Expertise –
No. of
Projects
Seniority
in the
Field
Experience
in the Field Setting
Up the
System
Maintenance
Stage
2. The Bidder shall append an organizational chart, which must include all personnel
and lines of responsibilities of the IAA's Project (Q)
3. During the Supplier's selection process, IAA shall approve all personnel proposed by
the Bidder and have the right to interview key personnel and discuss changes if the
Bidder's choice is deemed unsuitable. (Q)
4. The following requirements for destined Key Persons in the projects depicts IAA’s
understanding of a suitable staffing for such a project; however, if the Bidder's
common / best practice is different, the Bidder should not restrict itself to the
following key persons and may offer its best staffing. (Q)
7.2.3.2. Details on the Project Executive
1. The Bidder shall appoint to the A-VDGS Project an Executive who will be the project
sponsor. The Executive will ensure the project's success and will be authorized to
make decisions and commitments on behalf of the Bidder Executive Management.
The Executive will be also an escalation contact for any major issues. The Executive
will be in direct contact with the Project Manager and with the Bidder’s top
management. (Q)
2. The Bidder’s A-VDGS Project Executive shall be able to communicate fluently in
the English language (written and oral) (P).
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 16 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
3. The Bidder shall provide a relevant CV of the Project Executive– this shall include
at a minimum: (Q)
a. Personal details (name, contact details).
b. Formal education, training and qualifications.
c. Position in the Company.
d. Relevant experience as a project manager / project executive of similar
projects.
e. Two references from the past 5 years while acting in similar capacity
(preferred if applicable)
f. Availability.
7.2.3.3. Details on the A-VDGS Project Manager
1. The Bidder shall appoint a suitably qualified and experienced Project Manager for
the duration of this project hereinafter referred to as the Bidder’s A-VDGS Project
Manager. (Q)
2. The Bidder’s A-VDGS Project Manager shall meet the requirements that are depicted
in Section 5.2 of the Contract – “The Supplier's Representative”
3. The Bidder’s A-VDGS Project Manager shall be assigned fully and solely to the
IAA’s A-VDGS Project (Q)
4. However, if the Bidder’s response to Section 2’ above is partially compliant, IAA’s
Project shall be the A-VDGS Project Manager principle occupation and not less than
80% of a full time job.
5. The Bidder’s A-VDGS Project Manager shall be able to communicate fluently in the
English language (written and oral).
6. The Bidder’s A-VDGS Project Manager is expected to be in Israel as needed during
the duration of the project, at least once a month or as per the project stages criticality
and steering committee meetings. (Q)
7. The Bidder shall provide a relevant CV of the destined Bidder’s A-VDGS Project
Manager – this shall include at a minimum: (Q)
a. Personal details (name, contact details).
b. Formal education, training and qualifications.
c. Relevant experience in Project Managing of A-VDGS related projects.
d. Two references from the past 5 years.
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 17 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
e. Availability.
f. Compliance with clause 7.2.2.1 – Project Team Highlights.
8. The IAA shall reserve the right to interview the Bidder’s A-VDGS Project Manager.
This interview will take place in person at IAA premises.
9. If the Bidder’s A-VDGS Project Manager is replaced by the Bidder during the setting
up period of the Complete System, a notice period of 30 days must be given to the
IAA, which in turn reserves the right to interview and approve the replacement. The
replacement must spend at least 15 days in Israel with the incumbent Bidder’s A-
VDGS Project Manager to accomplish a full handover.
10. IAA reserves the right to request the replacement the Bidder’s A-VDGS Project
Manager at its discretion with a notice period of 30 days. The IAA shall reserve the
right to interview and approve the new Bidder’s A-VDGS Project Manager. The
replacement must spend 15 days in Israel with the incumbent Bidder’s A-VDGS
Project Manager to accomplish a full handover.
7.2.3.4. Details of the Senior Technical Manager
1. The Bidder shall appoint a suitably qualified and experienced Senior Technical
Manager for at least the duration of the Set-Up of Complete System project,
hereinafter referred to as the project A-VDGS Senior Technical Manager. (Q)
2. The A-VDGS Senior Technical Manager is expected to be in Israel as much as
needed during the duration of the aforementioned project, in particular during the
RRD and Design, Installation and Commissioning, Integration and Tests phases of
the project. (Q)
3. The A-VDGS Senior Technical Manager shall be able to converse fluently in the
English language.
4. The Senior Technical Manager shall at all times be under the direction of the Bidder's
Technical Executive Director (or CTO).
5. The Bidder shall provide a relevant CV of the A-VDGS Senior Technical Manager
– this shall include at a minimum: (Q)
a. Personal details (name, contact details).
b. Formal education, training and qualifications.
c. Relevant experience in Project Managing of A-VDGS projects which
include a complete integrative solutions.
d. Two references from the past 5 years.
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 18 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
6. The Bidder shall provide a relevant CV of the Chief Technology Officer – this shall
include at a minimum: (Q)
a. Personal details (name, contact details).
b. Formal education, training and qualifications.
c. Relevant experience in project managing of similar A-VDGS projects or
IT Implementation projects.
7. The IAA shall reserve the right to interview the A-VDGS Senior Technical Manager.
8. If the IAA’s A-VDGS Senior Technical Manager is replaced during the project term,
a notice period of 30 days must be given to the IAA, which reserves the right to
interview the replacement.
7.2.3.5. Details of the Installation Team Manager
1. The Bidder shall appoint a suitably qualified and experienced field engineer to
manage IAA’s installations during the Set Up of the Complete System Project. (Q)
2. The Installations and Technicians Team Manager shall be able to converse fluently
in the English Language.
3. The Installations and Technicians Team Manager is expected to be in Israel as needed
during the relevant Stages.
4. The Bidder shall provide a relevant CV of the Installations and Technicians Team
Manager – this shall include at a minimum: (Q)
a. Personal details (name, contact details).
b. Formal education, training and qualifications.
c. Relevant experience in managing A-VDGS solution Installations.
d. Two references from the past 5 years.
5. The IAA shall reserve the right to interview the Installations and Technicians Team
Manager.
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 19 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
7.3. Project's Implementation Process
7.3.1. Introduction
1. Section 7.3 intends to provide information about the project's major stages, timetable,
major activities and deliverables.
2. The project life cycle in this chapter is presented as the minimal scope of
requirements. The Bidder is entitled and encouraged to propose enhancements and/or
slight amendments based on the Bidder's best practice, as well as to present examples
of deliverables similar to those requested during the various stages of the Project to
depict its abilities and execution practices (Q)
3. The above mentioned shall not derogate from the full and complete responsibility of
the Bidder for the performance of the Project in compliance with the System
Requirements as stipulated in chapters 1-9 and compliance with the provisions of the
Contract and completed within the defined timetable.
7.3.2. Setting Up the Basic System / Project Plan – Overview
7.3.2.1. Setting Up the WP#CS Central System / Project Plan – Overview
1. Refer to Clause 1.5.2 Implementation Major Stages, at Chapter 1 of the Technical
Appendix of the RFP.
2. The following table provides more details to the major stages and milestones as well
as expected time table that IAA requires for the Complete WP#CS System
Implementation. [The high-level project plan is as specified in this section, and it
includes a separate SAT for WP#BCD (A-VDGS in Concourses B, C & D) and
WP#E (A-VDGS in Concourse E). The Bidder is requested to provide a Project Plan
as requested in this Technical Appendix of the RFP. However, the Bidder may add
an elective option of a different outline for the Project Implementation. A
comparative review of both concepts will be warmly welcomed. For avoidance of a
doubt it is clarified, that the outline as stipulated by IAA is the one that will oblige
the Bidder and that the cost in the Price Proposal Form should refer to IAA's outline.]
3. The Bidder shall insert its planned timeframe (number of months from ARO)
wherever this was not specified by IAA. (Q)
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 20 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
4. The Bidder is requested to distinguish between a formal Payment Milestone – in
which the Bidder should comply with IAA’s requirements (such as the HLD for both
stages) – and Informal Stages – which stands for expectations’ coordination solely.
5. The Completion of the Central system is a pre-requisite to any DSS in concourses B
C D and E. The Final Central System SAT shall be combined with the SAT of either
WP#BCD or WP#E whichever commenced last. Thus the total A-VDGS system SAT
shall be commenced when All DSSs are installed in B C D and E.
6. The commencement of the Soak Period of the Central system shall be combined with
the commencement of the SOAK period of either WP#BCD or WP#E whichever
commences last. Thus the total A-VDGS system SOAK shall be commenced when
All DSSs are installed in B C D and E.
7. Setting Up the WP#CS table:
Stage /
Milestone #
Stage / Sub-Stage
[Section number]
Due Date for
Finalizing The
Stage / Sub-
Stage (ARO
+# Months)
Comments
0. Signing the Contract ARO
Receipt of Order.
A payment milestone
1. Kick-Off
TBD By the
Bidder
A Draft Site Survey Plan,
Draft PEP’s Updates and
Draft RRD are expected 5
working days before the
Kick-off Meeting.
1.1. Sites Survey
1.2. Project Execution Plan (PEP)
Updates
If needed.
1.3. Revised Requirement Definition
(RRD) 7.3.5.3.1.
All other aspects but the
Technical Portion that has
already been done during the
Contract Signature’s Term.
2. System Design Review (Central
System, and Concourses B C D and
E)
TBD By the
Bidder
The Bidder shall submit all
the documents that will be
reviewed (see 2.1 – 2.6
below) at least 5 business
days before the Review.
2.1. High Level Design for the Central
System and both WP#BCD System
and WP#E 7.3.5.5.27.3.5.5.2
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 21 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
Stage /
Milestone #
Stage / Sub-Stage
[Section number]
Due Date for
Finalizing The
Stage / Sub-
Stage (ARO
+# Months)
Comments
2.2. Architecture 7.3.5.5.17.3.5.5.1
2.3. WP#CS, 7.3.5.5.37.3.5.5.3
2.4. WP#CS System – Site Engineering
Report. 7.3.5.4.17.3.5.4.1
2.5. WP#BCD System – FAT & SAT
Plan and Procedures
2.6. Presenting the System Maintenance
Program SMP
3. Setting-up WP#CS Central System
3.1. Manufacturing / Purchasing /
Development / Integration 7.3.5.6
3.2. FAT for Central System
Components 7.3.5.7
TBD By the
Bidder A payment milestone,
together with the IRR (See
entry 3.3 in this table).
3.3. Formal Review: IRR (Installation
Readiness Review): The Supplier
Accepts IAA’s Supplies. 7.3.5.7
TBD By the
Bidder A payment milestone,
together with the FAT (See
entry 3.2 in this table).
3.4. Delivering the System Components
to Israel 0
3.5. Setting Up the Central
System 7.3.5.9
3.6. Central System Preliminary
Acceptance Test (simulated data) ARO + 4m See Critical Mile Stone for
WP#BCD. The Central
System must be ready
before testing any DSS at B
C or D.
4. System and Service Acceptance
Tests
4.1. Final SAT Commencement of
AVDGS Central System 7.3.5.11
The CS Final SAT shall be
combined either the Final
SAT of WP#BCD, or WP#E
whichever will commence
later.
4.2. WP#CS System's Final SAT
Completion
TBD By the
Bidder
Overall System Acceptance
Formal Review: SAT.
A payment milestone
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 22 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
Stage /
Milestone #
Stage / Sub-Stage
[Section number]
Due Date for
Finalizing The
Stage / Sub-
Stage (ARO
+# Months)
Comments
4.3. Commencement of the Soak Period
and Activation of the System as
Fully Operational
Not Later
than ARO+10
Months
4.4. Soak Test Completion [7.3.5.12]
This is also the completion of Soak
Test for BCD and E as well. * Soak test as stipulated at the
aforementioned Sections is 3 periods of one
month (total of 3 months) for each stage of
the project separately. However, the final
duration for each soak test will be
discussed with the selected bidder based on
its best practice, subject to the IAA's
approval.
Ends with issuing a Final
Certificate of Acceptance
(COA) for WP#CS and
WP#BCD and WP#E A-
VDGS System by IAA
A payment milestone
5. Warranty, Service and maintenance
Period for WP#CS System 7.3.5.13]
5.1. Warranty, Period for WP#CS
System starts [Error! Reference
source not found.7.3.5.12]
Starts at the Commencement
of the First DSS Gate
Acceptance Tests either in B
C D or E
5.2. Service and Maintenance Period for
WP#CS WP#BCD and WP#E
System starts
Warranty period ends 24
months after the Supplier has
received from IAA the
Certificate Of Acceptance of
WP#CS and WP#BCD. The
Warranty for WP#E shall be
no less than 1 year. Please
refer to the Contract.
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 23 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
7.3.2.2. Setting Up the WP#BCD System / Project Plan – Overview
1. Refer to Clause 1.5.2 Implementation Major Stages, at Chapter 1 of the
Technical Appendix of the RFP.
2. The following table provides more details to the major stages and milestones
as well as expected time table that IAA requires for the Complete WP#BCD
System Implementation. [The high-level project plan is as specified in this
section, and it includes a separate SAT for WP#BCD (A-VDGS in
Concourses B, C & D) and WP#E (A-VDGS in Concourse E). The Bidder is
requested to provide a Project Plan as requested in this Technical Appendix
of the RFP. However, the Bidder may add an elective option of a different
outline for the Project Implementation. A comparative review of both
concepts will be warmly welcomed. For avoidance of a doubt it is clarified,
that the outline as stipulated by IAA is the one that will oblige the Bidder and
that the cost in the Price Proposal Form should refer to IAA's outline.]
3. The Bidder shall insert its planned timeframe (number of months from ARO)
wherever this was not specified by IAA. (Q)
4. The Bidder is requested to distinguish between a formal Payment Milestone
– in which the Bidder should comply with IAA’s requirements (such as the
HLD for both stages) – and Informal Stages – which stands for expectations’
coordination solely.
5. The SAT for WP#BCD shall commence only after completing the
Preliminary SAT of the CS. See WP#CS Project plan.
6. Setting Up the WP#BCD Table:
Stage /
Milestone
#
Stage / Sub-Stage
[Section number]
Due Date for
Finalizing The
Stage / Sub-
Stage (ARO
+# Months)
Comments
1. Setting-up WP#BCD System
1.1. Manufacturing / Purchasing /
Development / Integration 7.3.5.6
1.2. FAT 7.3.5.7 TBD By the
Bidder
A payment milestone, together
with the IRR (See entry 1.3 in this
table).
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 24 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
Stage /
Milestone
#
Stage / Sub-Stage
[Section number]
Due Date for
Finalizing The
Stage / Sub-
Stage (ARO
+# Months)
Comments
1.3. Formal Review: IRR (Installation
Readiness Review): the Supplier Accepts
IAA’s Supplies. 7.3.5.7
TBD By the
Bidder A payment milestone, together
with the FAT (See entry 1.2 in this
table).
1.4. Delivering the System Components to
Israel 07.3.5.8
1.5. Equipment for at least 2 Concourses is
stored at BGN Airport ready to be installed ARO + 5m
A Critical Milestone
1.6. Central system is ready for the first test of
DSS
See WP#CS [7.3.2.1]
1.7. Gates' Installation, Commissioning and
Acceptance 0
May last for a few weeks. One by
one replacement.,
Warranty, Starts for each Gate
separately.
2. System and Service Acceptance Tests
2.1. WP#BCD System's Final SAT
Commencement 7.3.5.11
2.2. WP#BCD System's Final SAT Completion TBD By the
Bidder
B C D gates. System Acceptance
Formal Review: SAT.
A payment milestone
2.3. Commencement of the Soak Period for
BCD and Activation of the System as
Fully Operational System (shutting down
the old system)
Not Later
than
ARO+10
Months
2.4. Soak Test Completion [7.3.5.12] * Soak test as stipulated at the aforementioned
Sections is 3 periods of one month (total of 3
months) for each stage of the project separately.
However, the final duration for each soak test will
be discussed with the selected bidder based on its
best practice, subject to the IAA's approval.
Ends with issuing a Final
Certificate of Acceptance (COA)
WP#BCD System by IAA
A payment milestone
3. Warranty, Service and maintenance Period
for WP#BCD System
3.1. Warranty, Period for WP#BCD System
starts [7.3.5.13]
Starts at the Commencement of
each Gate Acceptance Tests
3.2. Service and Maintenance Period for
WP#BCD System ends
Warranty period ends 24 month
after the Supplier has received from
IAA the Certificate Of Acceptance
of WP#BCD for all gates.
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 25 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
7.3.2.3. Setting Up the WP#E System / Project Plan – Overview
1. Refer to Clause Error! Reference source not found.7.3.2.3 – WP#E System –
Implementation major milestones.
2. Setting Up the WP#E Table:
Stage /
Milestone
#
Stage / Sub-Stage
[Section number]
Due Date for
Finalizing The
Stage / Sub-
Stage (ARO
+# Months)
Comments
1. Setting-up WP#E System
1.1. Manufacturing / Purchasing / Development /
Integration 7.3.5.6
1.2. FAT 7.3.5.7 TBD By the
Bidder A payment milestone,
together with the IRR (See
entry 1.3 in this table).
1.3. Formal Review: IRR (Installation Readiness
Review): The Supplier Accepts IAA’s
Supplies. 7.3.5.7
TBD By the
Bidder A payment milestone,
together with the FAT
(See entry 1.2 in this
table).
1.4. Delivering the System Components to Israel 0
1.5. Central system is ready for the first test of
DSS
See WP#CS
1.6. Gates' Installation, Commissioning and
Acceptance 0
Installation of all 8 gates
2. System and Service Acceptance Tests
2.1. WP#E System's Final SAT
Commencement 7.3.5.11
2.2. WP#E System's Final SAT Completion TBD By the
Bidder
System Acceptance for
all 8 gates
Formal Review: SAT.
Note that if SAT of
WP#E commences after
SAT WP#BCD, this SAT
is actually the Final A-
VDGS system SAT.
A payment milestone
2.3. Commencement of the Soak Period and
Activation of the Gate E as Fully Operational
Not Later
than ARO + 6
Months
Warranty Starts after
SAT COA.
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 26 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
Stage /
Milestone
#
Stage / Sub-Stage
[Section number]
Due Date for
Finalizing The
Stage / Sub-
Stage (ARO
+# Months)
Comments
2.4. Soak Test Completion [7.3.5.12]
* Soak test as stipulated at the aforementioned Sections
is 3 periods of one month (total of 3 months) for each
stage of the project separately. However, the final
duration for each soak test will be discussed with the
selected bidder based on its best practice, subject to the
IAA's approval.
Ends with issuing a Final
Certificate of Acceptance
(COA) WP#E System by
IAA. Note that if WP#W
ends after WP#BCD than
it is the Final Soak of A-
VDGS system.
A payment milestone
3. Warranty, Service and maintenance Period for
WP#E System
3.1. Warranty, Period for WP#E System starts
[7.3.5.13]
Starts at each tested gates
3.2. Service and Maintenance Period for WP#E
System starts
Warranty period ends 24
months after the Supplier
has received from IAA the
Certificate Of Acceptance
of WP#BCD and WP#CS;
However, minimal term
for the Warranty shall not
be less than 12 months.
7.3.3. Setting up Future Options
1. For each options listed in the corresponding clauses - in chapter 9, the Bidder shall
describe a tentative Project Plan and timetable for implementation (according the
example above at section 7.3.2 Setting Up the Option 1/2/… System / Project Plan –
Overview
The suggested format is the following table:
# Stage / Sub-Stage
Due Date for
Finalizing The Stage /
Sub-Stage (ARO + M)
Comments / details
1
2
.. … … …
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 27 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
2. Each option and proceeding in this respect shall be implemented in the manner
stipulated in the provisions regarding "Variations" in the Contract. However, the
prices stipulated for each option shall include all managerial tasks and statement of
work necessary to implement the option.
3. For options 1 and 2, each shall be considered as a Project in itself.
4. IAA shall be entitled to activate each option any time during the Contract Period.
5. The Bidder shall stipulate for each option all the relevant details required for the
implementation of each option as stipulated at 7.1.5.1 above.
6. For the avoidance of doubt, it is hereby clarified that for the performance of each
Option by the Bidder, the Bidder shall be entitled only to the sum stipulated by it for
the relevant Option in its Price Proposal.
7. The Bidder’s proposal shall refer to all the above. (Q)
7.3.4. Formal Reviews
1. This Section specifies the formal reviews that shall be executed throughout the
project. The schedule for the reviews shall be set in the project's Gantt chart as a
single milestone or a series of milestones (e.g. the SAT, Sites and Production
Readiness Reviews) as needed.
2. All the Reviews will be held in Israel in Ben Gurion Airport unless IAA approved in
writing another location.
3. The Bidder shall list and describe any additional recommended reviews as per its best
practice.
4. In addition, the Bidder and IAA can initiate technical design reviews (DR) or
managerial reviews (PMR) when and if needed, in order to attend unexpected or
special issues that might arise throughout the project. The following is valid for each
stage.
5. The Review Procedure is described in Section 7.4.4 below
6. List of Formal Reviews:
# Name Estimated
Schedule Responsibility
(1) RRD and PEP Review The Bidder
(2) High Level Design Review (PDR) The Bidder
(3) Installation Readiness Review (IAA’s
Supplies Readiness Review (per each site))
IAA
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 28 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
# Name Estimated
Schedule Responsibility
(4) SAT Readiness Review The Bidder
(5) SAT Review The Bidder
(6) Soak Readiness Review The Bidder
(7) Soak Review The Bidder
7.3.5. Major Sub- Stages – Activities and Deliverables Overview
7.3.5.1. General
1. The following list of major sub-stages shall not be considered to be exhaustive; some
of the sub-stages are not mentioned at all; however, the Bidder shall accept the
following milestones, responsibilities and elaborate in an equivalent manner all the
proposed sub-stages. (Q)
2. The Bidder shall describe the following:
a. The Bidder shall describe the involvement of the Bid Manager and the
Bid team in Setting-Up the WP#CS, WP#BCD and/or WP#E System.
IAA relates high importance to the Bid Manager's involvement at least
until completion and approval of the RRD stage. (Q)
b. The Bidder shall describe the proposed Executive Project Manager, The
Proposed Project Manager, the Proposed Technical Manager and other
key staff proposed (upon Bidder's discretion) in preparing and
approving the Proposal. (Q)
c. The handover / overlapping between the Bid Manager and the A-VDGS
/ A-VDGS Project Manager. (Q)
7.3.5.2. IAA's Approval for Each Stage
1. The Bidder shall accept that each stage is concluded only upon IAA's Approval of
completion. For example, the revised Requirement Definition stage is concluded by
IAA's approval of the RRD Summary document.
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 29 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
2. The Bidder shall accept that IAA's Approval, for each stage as described below, is a
threshold condition for proceeding to next stage and/or for a payment milestone, in
compliance with Section 11 and 20 in the Contract.
7.3.5.3. Kick-Off Meeting
1. On-Site Kick-Off Meeting (hereinafter KOM) would be held in Israel in order to
define and finalize technical and administrative issues of the Contract. The visit shall
last as many days as required to be able to include Approved Project Plan and the
RRD in the Contract.
2. Following are major activities and deliverables for the Kick-Off Stage:
# Activities Deliverables Responsibility
1. High Level Project Plan for
Executive
PEP Presentation
High Level Project Plan
Project Steering Committee
Defining the Review process
The Bidder
2. Project Work Plan Review
(PEPR)
Detailed Project Execution Plan.+
Baseline Freeze
The Bidder
PEPR – Summary document The Bidder
3. IAA's approval to Project
Execution Plan
PEP Approval document + Baseline
Freeze
IAA
4. Revised Requirement
Definition (a) Requirements'
Freezing.
Revised Requirement Definition
document
The Bidder
5. System Requirements
Review
RRD – Summary document The Bidder
6. IAA's approval of the RRD
Summary document
RRD Approval document IAA
7.3.5.3.1. KOM – The Approved Project Plan and RRD
1. The Contract, entitles the Awarded Bidder to submit a formal Project Execution Plan,
subjected to the terms and conditions in the aforementioned Contract’s Section. The
idea behind this plan is to try to find the “golden path” between IAA’s initial
requirements and procedures and the Bidder’s best practices. The Project Execution
Plan is a formal Annex of the Contract – Annex “C3”. Lineup – The RRD Technical
Portion
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 30 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
2. The RRD Document shall be derived from the IAA's Technical Requirements, the
Selected Bidder’s Proposal, the various clarifications that were submitted by the
Selected Bidder during the Bidder’s Selection Process and necessary updates to the
aforementioned documents that may have been created due to the long period that
has elapsed since originally writing these documents until their implementation.
3. Following is a ”Blocks Diagram” that illustrated the aforementioned text:
Figure 1 - Overview of the RRD Stage
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 31 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
4. Following is an example (from another Tender) for a single requirement during the
RRD stage:
5. For avoidance of a doubt, IAA explicitly declares that the RRD stage shall neither
influence nor change either the final cost or the timetable in any way. The meetings
are intended merely to "fine-tune" the requirements within the basic scope of the
project that shall serve the Contract and Project implementation.
7.3.5.4. Kick-Of Meeting (KOM), Site Survey and Site Engineering Report
1. On-Site Kick-off Meeting would be held in Israel in order to define and finalize
technical and administrative issues of the project. The visit may last for a few days,
which shall include the Official and Final Site Survey according to the Supplier's
methodology. The Bidder shall refer to the Contract for further details relating to the
Official and Final Site Survey.
2. A Draft Site Survey Plan is expected 5 working days before the Kick-off Meeting.
3. In general, the KOM is an opportunity for the Awarded Bidder to gather all the
information it needs for the design phase (for example: information about interfacing
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 32 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
system, etc.). The Bidder is most welcome to add activities to the KOM Plan upon
its experience and best practices (Q).
7.3.5.4.1. The Site Survey and the Site Engineering Report
1. The Sight Engineering Report (SER) should incorporate the following activities and
information:
a. Finalizing all System’s Components that should reside in IAA premises.
b. The Supplier should well define each component that requires supplies by IAA
such as: Space, Power Supply, and Communication Network, for all required
activities such as: locating, installation, commissioning, operating, maintenance,
etc.
c. IAA will decide the components exact locations.
d. During the Site Survey, the Supplier shall be acquainted with the existing and
planned conditions.
e. Shortly after the Site Survey, the Supplier is expected to send IAA a draft with
all needed preparation for locating, installing, commissioning, operating and
maintaining each component. That should include information such as:
i. Components’ Requirements.
ii. Existing Conditions.
iii. Required Site Preparations.
iv. Sharing the Preparations’ roles among the Supplier and IAA including
the desired timetable.
v. High level design of the connection / integration between the Supplier’s
supplies and IAA supplies, including demarcation points and acceptance
tests by the supplier to IAA’s supplies.
vi. Site Preparations should incorporate themes such as: removal of existing
equipment, space, power supply, communication network, access
control, air condition, furniture, demarcation points, etc.
vii. IAA will study the report and will comment on it to the Supplier.
viii. The Supplier shall amend its report until IAA’s approval.
f. During the Supplier’s Selection Process IAA will provide the Bidders a list of
Supplies that are available for the System / Project. IAA prefers that the Bidders
will adapt their solution to IAA’s constraints; however, if the Bidder needs
extra’s it should write it in its proposal. Meeting IAA constraints may contribute
to facilitate IAA’s preparation, which might be expressed in savings of time and
money. Hence, the closer the Bidder will be to IAA’s constraints, the higher
potential for quality grade that it will receive.
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 33 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
g. Timetable for providing the SER and its approval is crucial to IAA in order to
meet its desired due dates.
h. The Bidder is requested to elaborate in its response how it is about to meet IAA’s
challenge as depicted above (Q).
7.3.5.5. Design
1. Following are the Design Phase Characteristics / Highlights:
a. Architecture and High Level Design (as described below) shall be done for all
WP#CS, WP#BCD and WP#E.
b. IAA has no objection that the HLD and the DLD shall be joint to one phase.
c. Following are activities and deliverables for: Architecture, High Level Design
and Detailed Design.
7.3.5.5.1. Architecture / High Level Design for Both Stages
1. Architecture / High Level Design table:
# Activities Deliverables Responsibility
1 Defining System Logical
Architecture
Defining System Modules and
Functionality
Defining System's Physical
Configuration
Defining System Sizing
System Architecture Document The Bidder
2 Analyzing the environment in which
The System shall be installed (see
note (a) below)
Site Engineering Report -
Required Infrastructure for the
System's installation, operation
and maintenance
The Bidder
3 Formation of System Interfaces
Specification
System Interfaces
Specification's document.
The Bidder
4 Specification of 3rd parties products
to be integrated in The System
3rd Party Products –
Specification for Purchase.
The Bidder
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 34 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
# Activities Deliverables Responsibility
5 Formation of Administrative
Management Concept
A document, referring to
various issues, such as:
monitoring functionality, alert
levels, special site specific
principles, HMI, etc.
The Bidder
6 Formation of a Conceptual Test Plan
(see clause 7.3.7)
Conceptual Test Plan doc.
(STP)
The Bidder
8 Formation of a Conceptual Quality
Plan (see clause 0)
Conceptual Quality Plan doc.
(QAP)
The Bidder
9 Risk Identification and Analysis Risk Analysis and Mitigation
Plan Document
The Bidder
10 Updating the Project's Work plan Updated Project's Work plan
approved by IAA
The Bidder
11 System Architecture Review (SAR) SAR– Summary document The Bidder
12 IAA's approval to SAR SAR Approval document IAA
2. The Required infrastructure (table entry #2 above) shall refer, inter alia, to power
supply requirements, passive communication network, floating floor, survivability
requirements, air conditioning, floor space, height, access control, recommended
furniture both for operation and storage, lighting, separation of areas, windows, etc.
For more details, see 7.3.5.4 (SER).
7.3.5.5.2. High Level Design (for each Work Package separately)
1. High Level Design Activity Table:
# Activities Deliverables Responsibility
1 Formation of a configuration
for each Working Positions for
the phase
Working Positions' Configuration
document
The Bidder
2 System Interfaces High Level
Specification
System Interfaces High Level
Specification's document
The Bidder
3 Design of HMI principles and
interaction flow
HMI Principles document The Bidder
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 35 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
# Activities Deliverables Responsibility
4 Design of IAA’s specific
Requirements - High Level
Specification
IAA Specific Requirements -
High Level Specification
Document
The Bidder
5 Defining System Tests Description of all the System tests
(STD)
The Bidder
6 Formation of a Preliminary
Installation Plan
Preliminary Installation Plan
document
The Bidder
7 Formation of a Preliminary
Training and Assimilation Plan
Preliminary Training and
Assimilation Plan document
The Bidder
8 High Level Design Review
(PDR)
PDR– Summing Up document The Bidder
9 IAA's approval to PDR PDR Approval document
IAA
7.3.5.5.3. Detailed Design (for ALL Work Packages)
1. In this phase, IAA would not need to approve some of the deliverables of this stage. IAA
would merely approve receipt of the deliverables, but not their content. All deliverables
that do not need to be approved by IAA are marked – Not a formal deliverable. For the
avoidance of doubt, it is hereby clarified that the abovementioned shall not derogate
from the full and complete responsibility of the Selected Bidder for the performance of
the Project in compliance with all of the Functional Requirements and any other and/ or
additional requirement as stipulated in the Contract.
2. Detail Design Activity Table:
# Activities Deliverables Responsibility
1. Detailed Specification for each
Working Position for the phase
Detailed Specification for each
Working Positions document –
The Bidder
2. Detailed system Architecture Detailed system architecture
including network and end
devices
The Bidder
3. Detailed Design of the System
Data Model (especially for new
developed items such as IAA’s
Specific Requirements)
Detailed Design of the System
Data Model document – Not a
formal deliverable
The Bidder
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 36 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
# Activities Deliverables Responsibility
4. System Interfaces Detailed
Specification
System Interfaces Detailed
Specification's document
The Bidder
5. Detailed Design of The System
HMI
Detailed Design of The System
HMI document
The Bidder
6. Detailed Maintenance Plan Including maintenance procedure,
repair procedure, use cases
The Bidder
7. Defining System Tests
Scenarios
Test Cases Scenarios document
(TCS)
The Bidder
8. Preparing a Validation Matrix
("VRTM") [see 7.3.7.2 below]
VM document for IAA's
approval.
The Bidder
9. Detailed Design of an
Installation Plan
Detailed Design of an Installation
Plan document
The Bidder
10. Detailed Design of Training
and Assimilation Plan
Detailed Design of Training and
Assimilation Plan document
The Bidder
11. Detailed Design Review (DDR) CDR Summary document The Bidder
Note: IAA reserves the right to review and comment the CDR document, addressing The
Bidder's attention to potential design issues.
7.3.5.6. Manufacturing / Purchasing / Development / Integration
1. Manufacturing / Purchasing / Development / Integration Activity Table:
# Activities Deliverables Responsibility
1. Manufacture / Develop / Purchase of
all the Work Packages components
(including interfaces)
The Bidder
2. Unit Test to each of the
aforementioned System Components
(IAA is entitled to review the
deliverables upon its sole discretion)
Unit Test Summary
document – Not a formal
deliverable
The Bidder
3. Integration of all the System
components (including interfaces)
The Bidder
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 37 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
# Activities Deliverables Responsibility
4. Integration Test for the phase (IAA is
entitled to review the deliverables
upon its sole discretion)
Unit Test Summary
document – Not a formal
deliverable
The Bidder
5. FAT environment / Site Preparation FAT site ready for use The Bidder
6. Training Courses Adaptation Training Materials The Bidder
7. Sanity Test for the Stage Sanity Test Summary
document
The Bidder
8. Bidder’s approval to the Stage
readiness for FAT
A Stage ready for FAT The Bidder
7.3.5.7. FAT & IRR
1. An important activity at this step is testing and approving IAA’s supplies according to
the agreed method as stipulated in the approved SER.
2. FAT & IRR Activity Table:
# Activities Deliverables Responsibility
1. FAT document preparation FAT document The Bidder
2. FAT document approval FAT document approval IAA
3. Basic training to IAA's FAT's
witnessing group in case they
attend the FAT
The Bidder
4. FAT for the version (including
interfaces)
The Bidder
5. FAT Review FAT Results – Summary document The Bidder
6. IAA Approval of FAT Review Approval of FAT Review
document
IAA
7. Formal version ready for shipping
to IAA
The Bidder
8. IAA’s Supplies Acceptance
Tests document preparation
CFE AT document The Bidder
9. CFE AT document approval CFE AT document approval IAA
10. CFE AT Execution The Awarded Bidder is welcome to
witness
IAA
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 38 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
# Activities Deliverables Responsibility
1. FAT document preparation FAT document The Bidder
2. FAT document approval FAT document approval IAA
11. CFE AT Review CFE AT Results – Summary
document
IAA
12. IAA Approval of CFE AT
Review
Approval of CFE AT Review
document
The Bidder
7.3.5.8. Delivering the System Components to Israel (Q)
1. The Bidder shall define, in the same manner as the tables above, all activities upon its
discretion.
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 39 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
7.3.5.9. Setting Up the Central System (Q)
1. Installation, Commissioning and Training are major activities during this stage.
2. Following are major activities and deliverables for this stage:
# Activities Deliverables Responsibility
1. Preparation of Up-to-date Plan
for Setting up the Central
System
Plan for Setting Up the Central
System including Tests Plan and
Procedures
The Bidder
2. Setting Up and Tests
Documents approval
Approval of the aforementioned
Plans
IAA
3. Setting the Central System and
the Test Environment in both
Core rooms
The Bidder
4. Setting the interfaces to AODB
and DCRS
Test environment and preparing for
the operational environment
5. Conducting the Bidder’s
Internal Tests
The Bidder
6. Coordinating with all External
Interfacing Systems for
individual testing
The Bidder +
IAA
7. Training Courses Both for the Technicians and the
Operational Staff
The Bidder +
IAA
8. Conducting the Central System
Tests – Preliminary CS SAT.
Preliminary Test. This test can be
integrated with the SAT tests of
WP#E. It is a pre-requisite to
WP#BCD.
The Bidder +
IAA
9. Preparing Central System Tests
Report
Central System Tests Results – The
entire report
The Bidder
10. Central System Tests Review Central System Tests Results –
Summary document
The Bidder +
IAA
11. IAA Approval of Central
System Tests Report
Approval of Central System Tests
Report document
IAA
12. Formal version ready for Gates’
Installation
The Bidder
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 40 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
7.3.5.10. Gates’ Docking Sub Systems Installation, Commissioning and
Acceptance (Q)
1. The Bidder shall define all activities for commissioning the Gate’s Docking Sub
System’s Acceptance Tests.
2. The Bidder must plan carefully the installation of the DSSs at gates B C D, with the
coordination and approval of IAA, since it has a great influence on the business
continuity of the A-VDGS / VDGS services in TLV airport. The Bidder shall submit
as part of this proposal its proposed plan for the transition from the old system to the
new one.
3. During the installation of DSSs in concourses B C D, the Operators in the Tower will
work with two systems in parallel, the old VDGS system and the new A-VDGS
system.
4. In this transition Interim period, the DSSs shall be replaced one by one utilizing the
new infrastructure (Fiber optic passive network, Dedicated Core rooms etc.). Thus, the
commissioning of each DSS for B C D shall be planned carefully and with minimum
down time. The transition must include the dismounting of the old PDU and mounting
the new DSS on the existing poles, and perform acceptance test in order to return the
gate into operational mode as soon as possible. The expected down time for each gate
shall be no more than 24 hours.
5. When dismounting the old PDU it is essential to reconnect the f/o ring cable in order
to retain the redundancy operation of the old system.
6. The installation stage for Concourse E shall not influence the Current VDGS system.
It will be depended on the concourse E readiness (a new concourse).
7. The Gates' DSS Acceptance tests shall be conducted only after complete acceptance
of the Central A-VDGS System.
8. Each Gate DSS Installation, Activation, Calibration and Acceptance Tests shall be
executed within up to 24 consecutive hours.
9. Once IAA approves a Gate’s Docking Sub System’s acceptance, the Bidder shall
commence the Warranty period according to the SLA (Chapter 8).
10. The following table depicts major activities for each Gate’s DSS acceptance..
# Activities Deliverables Responsibility
1 Up-to-date Setting up
Gate’s DSS Plan document
preparation
Plan for Setting Up the Gates DSS
Tests Plan and Procedures.
The Bidder
2 Setting Up and Tests
Documents approval
Approval of the aforementioned
Plans.
IAA
4 Setting the Gates’ DSS’s For BCD: careful planning according
to IAA approval. Replacing the old
PDU one by one with minimum
influence on the current system
The Bidder
with IAA
approval
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 41 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
# Activities Deliverables Responsibility
5 Conducting the Tests The Bidder +
IAA
6 Gates’ DSS’s Tests
Review
Gates’ DSS’s Tests Results –
Summary document
The Bidder
7 IAA Approval of Sites
Review
Approval of Gates’ DSS’s Tests
Review document
IAA
8 Formal version ready for Overall
System’s Final SAT
The Bidder
7.3.5.11. SAT
1. Following is the SAT Activities table:
# Activities Deliverables Responsibility
1. SAT document preparation SAT document The Bidder
2. SAT document approval SAT document approval IAA
3. SAT Readiness Review Version Document Description
(VDD) for the SAT.
The Bidder
SAT Readiness Review - Summary
document
The Bidder
4. SAT for the formal System
Version
The final SAT for the CS shall be
combined with the final SAT of
BCD or E whichever starts later.
The Bidder
5. SAT report preparation SAT report The Bidder
6. SAT Review SAT Results – Summary document. The Bidder
7. IAA Approval of SAT
Results
Approval of SAT Results document IAA
8. Formal Version ready for Soak Test The Bidder
7.3.5.12. Soak Test
1. During this stage, IAA will study and review both the System Performance and the
Management Application(s) suitability to IAA needs.
a. The Supplier's specialist shall accompany this stage at IAA facilities in Israel
during the SOAK Period for at least two weeks with optional extension of
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 42 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
two more weeks. During this period the Supplier's specialists shall perform
All Maintenance procedures with the IAA relevant involved bodies.
b. During this stage, status meeting shall be held twice a month at IAA facility
in order to report and verify various relevant issues.
c. The SOAK of the Central system is combined with the SOAK of WP#BCD
or WP#E whichever starts later.
d. IAA aims to cover a wide spectrum of the A-VDGS services and scenarios.
e. At the end of this stage, based on the success of the soak period, the system
shall be announced ready for Operational Use.
f. The Bidder shall prepare a Soak Readiness Review (SORR) checklist that
will contain all pre-requisite tasks of both the Bidder and IAA responsibilities.
The SORR Checklist shall be coordinated and approved by IAA.
g. The SORR process shall follow the process described in section 7.3.4.
h. A document containing a list of anomalies / mal-functions and follow-up on
their repair shall be kept by the Bidder. IAA users or the Bidder will be able
to open entries in this table. This document will be reviewed periodically (by
meetings, conference call, and special visit by Bidder's engineers – all
according to the severity of the issues being addressed).
i. System adaptation issues shall be listed and fixed by the Bidder mainly during
the first half of the SOAK period. The timing of the System adaptation should
enable IAA a sufficient time to evaluate it. [IAA’s intention is that most fixes
will be done at the 1st half of the Soak period, which will enable IAA sufficient
time to evaluate the fixes contribution.]
j. Repairing anomalies / mal-functions that were found before or during the
SOAK period should be corrected during that period and are a prime
condition for a successful completion of the SOAK stage, and with it the
completion of the A-VDGS Project.
k. The Bidder shall pay attention to the activity in entry #6 in the table below.
The Soak incorporates 3 one month periods. Hopefully, both parties will be
able to execute it sequentially, however, if the fixes won’t suffice IAA and /
or the System will not be available for a significant period and / or the services
by the System will be unacceptable the Soak process will be halt and it will
resume upon resolving the issues that caused the halt.
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 43 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
7.3.5.12.1. A Possible Procedure for Anomalies reporting by IAA and Anomalies
Resolution by the Awarded Bidder (Q)
1. The Bidder shall introduce its proposed method to handle anomalies during the
Soak. The Bidder should note that IAA refers a very high importance to the Soak
Period, since it was proved to minimize / bridge the gaps between the written
requirement and the day to day needs to operate a the Message handling system in
the Israel. (Q)
2. The following procedure description is for expectations' coordination:
a. IAA will use a spreadsheet to report about anomalies.
b. The spreadsheet shall be managed by the Awarded Bidder.
c. The spreadsheet shall have 2 basic portions:
i. One that shall be filled by IAA.
ii. Another one that shall be filled by the Awarded Bidder.
d. IAA's portion shall incorporate all kinds of information that shall provide the
Awarded Bidder sufficient information to analyze the anomaly, to look into
the system logs, to select a solution path, to implement the solution and to test
its effectiveness in order that IAA will be able to close the anomaly.
e. IAA's portion shall include information such as:
# Information Item Description
1. Anomaly ID Unique identifier to each anomaly.
2. Severity 1 – Does not prevent SOAK continuing.
2 – Urgent; may prevent SOAK continuing.
3. Anomaly Status Open or Closed
4. Date Reported by
IAA
5. Contact Person to
discuss the
anomaly
6. Anomaly Type Such as: International Communication Line,
Interface …
7. Time UTC
8. A-VDGS System
Components
Involved
Such as: Server, Splitter, …
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 44 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
# Information Item Description
9. Description of the
anomaly
Free Text
10. Additional
Information as
needed
Such as referring to photograph and / or a
document etc.
11. Possible Relevant
Environmental
Circumstances
Such as Power Outage, Air-conditioning
Outage, IAA's Communication Network
disruptions etc.
12. Others (Q) Upon the Bidder's discretion
f. The Awarded Bidder's portion shall include information such as:
# Information Item Description
1. The Awarded
Bidder Anomaly
Label
According to its acquaintance with the
system's internal components.
2. The Awarded
Bidder Action Plan
For the various activities such as: data
gathering, analyzing the data, formation of a
conceptual solution …
3. The Awarded
Bidder Requests
from IAA
Such as: access to the Test or the Production
System, special inputs from interfacing
systems, etc.
4. Expected Next
Update to the
Action Plan
At that date IAA expects a status report about
the anomaly.
5. Others (Q) Upon the Bidder's discretion.
g. The Awarded Bidder's responsibilities are as follows:
i. Review the daily reports submitted from the IAA. The Awarded Bidder
will group and evaluate the anomalies.
ii. Will report to the IAA within 3-5 business days the next steps for
evaluation. This is to allow The Awarded Bidder to evaluate any
emerging patterns of system performance. This communication will be
performed via emails and conference calls as necessary.
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 45 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
7.3.5.12.2. Table of Relevant Activities, Deliverables and Responsibilities
1. SOAK Period Activities Table:
# Activities Deliverables Responsibility
1 Soak Readiness Review (SORR)
checklist document preparation
Soak Readiness Review (SORR)
checklist document
The Bidder
2 SORR document approval SORR document IAA
3 Trial run of the system Periodical system approval and/or
punch list of problems
IAA
4 Status meeting in Israel with the
Supplier’s specialists onsite
Status meeting – Summary
document (including a list of those
problems that must be fixed +
schedule)
The Bidder &
IAA
5 Fix problems Fixed problems report
Open problems report
The Bidder
6 Reviewing the Fixed problems
and open problems reports
Soak test continuity approval IAA
7 Soak Period completion meeting Completion meeting – Summary
document
The Bidder
8 Completion of soak Period Completion of soak test approval -
issuing a Final Acceptance
Certificate
IAA
7.3.5.13. Go Live Period - System is ready for Operational Use
# Activities Deliverables Responsibility
1 SLA period commencement
(See Chapter 8 of the Technical
Requirements)
Starts when the first DSS is
operational (in BCD or E)
The Bidder
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 46 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
7.3.6. Project Plan
7.3.6.1. Principles and Guidelines
1. The Project work plan shall refer to IAA's requirements as stipulated in
clauses 7.3.2 above.
2. The project work plan shall include all the stages / sub-stages of the project
as mentioned in clause 7.3.3. The plan shall be built in such a way that
clarifies for each milestone the activities that are prerequisites to the full
completion thereof. (Q)
3. The project work plan shall include all the formal reviews of the project and
also the reviews that will be defined during the project, as mentioned in the
Proposal.
7.3.6.2. Work Plan for Setting up the WP#CS WP#BCD and/or WP#E
System
1. Within the Bidder’s integrated project plan, the Bidder shall provide the
following:
a. A project plan detailing the tasks, sub-tasks, dependencies,
resources and timeframes, deliverables, etc. for each stage.
b. The Bidder shall explicitly specify all the tasks that are within
IAA’s “court” for each activity, as well as the timeframe it
allocated to each of IAA’s tasks.
c. For avoidance of a doubt, IAA states that the Bidder would not
assume that IAA would supply any equipment for the project’s
purposes, other than those that are explicitly declared in the tender
documents.
2. The Bidder shall gather all the above-mentioned IAA’s tasks into one
Appendix - "IAA's Activity/Tasks" that shall be submitted as part of the
Proposal. This appendix shall contain a complete list of all IAA's tasks
a. This Appendix shall be valid only after a written approval by
IAA. IAA's approval shall be an integral part of the Technical
Specification approval as stipulated in the Contract.
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 47 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
b. This Appendix shall be the sole source for any of IAA's tasks
within the Project. Any task and /or activity and /or work and / or
service and / or a Component etc., that are not mentioned in this
Appendix, and are required for the successful completion of the
Project, shall be deemed as The Selected Supplier's obligation
whatsoever.
c. For each task, the Bidder shall elaborate as follows:
# The
Task
Reference
within the
Bid
Relevant
Stage of the
Project
Due
date for
delivery
Reference to
a sample (if
applicable)
1
2
..
d. For avoidance of a doubt, IAA declares, that a task within the Bid
that is associated with IAA but is not included in this appendix,
shall not oblige the IAA.
e. Each of IAA’s tasks will be inspected by the Selected Bidder and
will be approved / commented in writing. The inspection /
approval shall be done prior to the installation of the relevant
Systems’ components.
f. The number of tasks and their impact on IAA's obligations shall
have significant impact on the technical evaluation of the Bidder's
response. (Q)
3. A Gantt chart of the project shall be submitted along with the Bidder’s
Proposal, as an MS-Project file and in Excel and PDF files. IAA encourages
the Bidder to use its own templates for the Gantt Charts. IAA described the
Project Major Stages through the timeline / phases of the Project; however,
the Bidder may use its standard template with the required adaptations. (Q)
4. Following is an example for illustration purposes solely:
a. A-VDGS Gantt (Partial Sample): Level 1 and 2
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 48 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
b. A-VDGS Gantt / Tests (Partial Sample): Level 3
c. A-VDGS Gantt / Installation (Partial Sample): Level 3
5. Any delay in the execution of any activity or milestone shall be announced in
writing to IAA.
6. The re-scheduling of a delayed activity/milestone shall be approved by IAA;
otherwise the original schedule of the activity/milestone shall remain valid.
7. Every new revision of the plan approved by IAA shall be set as a new baseline
for tracking and reporting purposes. The Bidder shall keep the history of all
the baseline plans and not override them.
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 49 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
7.3.7. Tests
1. The Bidder shall introduce its proposed test methodology, test plan, test
activities and deliverables throughout the whole lifecycle of the Project (Q).
2. The Test Program shall refer to IAA's requirement below (P).
7.3.7.1. General
1. The test program stands to prove that the A-VDGS system delivered by the
Bidder is fully compliant with the Bidder’s proposal and IAA Requirements.
2. Tests shall refer to:
a. Central System, HMI and interfaces.
b. Gates’ DSS’s Acceptance.
c. Overall System Acceptance (Successful SAT).
d. Overall Service Acceptance (SOAK Completion).
3. The Subsystems / Components Acceptance and the overall System
Acceptance tests are the sole responsibility of the Selected Bidder's.
4. The final system acceptance shall be based upon the successful execution of
functionality and performance tests. If the System fails to meet (for example)
the expected performance, it shall be the Bidder's obligation to correct and/or
to add components and/or to enhance the configuration etc. to meet the
required functionality and performance.
5. Note that the Final Acceptance Tests for the Central System is combined with
either WP#BCD or WP#E whichever starts last.
6. The Overall Service Acceptance / the Soak Test would be led by IAA;
however, the Selected Bidder shall accompany this phase.
7. Regarding the Overall System Acceptance, some parameters, particularly
those concerning system reliability, availability, and continuity of service,
shall need to be tested over an extended period of time. This may impose
constraints on the initial operational use of the system until adequate
statistical evidence has been obtained to provide the necessary degree of
confidence.
8. Subsystems / Components Acceptance tests shall include (for all Work
Packages where applicable):
a. The Central System (functionality, redundancy, HMI, interfaces
etc.).
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 50 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
b. IAA Specific Requirements.
c. Communication Network
d. Gates’ DSS’s.
e. Other, upon the Bidder's discretion.
9. System Acceptance tests shall include but not limited to:
a. Functional tests of A-VDGS operational process in the central
system
b. Functional tests of A-VDGS process at the DSS level (local and
connected)
c. Functional tests of the Technical CMM (Control Monitoring and
Management) application (including maintenance procedures,
reports, logs, information security etc.)
d. AODB interface test
e. DCRS interface test
f. NTP interface tests
g. Redundancy tests (servers (SW and HW, Data base, network, WS,
interfaces)
h. Performance and capacity tests
i. Network testing
j. Reliability and maintainability tests (e.g., replacing LRU, detecting
faults etc.)
k. Working position HMI and functions for each of the system roles
l. More tests as required by the VRTM document (see next clause)
7.3.7.2. Verification Requirements Table Matrix
1. The purpose of the Verification Requirements Table Matrix ("VRTM") is to
define for each RRD requirement its validation (testing / proving) method,
and the relevant phase(s) in the Program in which it is going to be conducted.
Composing a VRTM is part of the Program CDR.
2. The Bidder shall submit for IAA's approval a final VRTM well before the
beginning of the Acceptance tests, and before submission of the Test Plan
documents.
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 51 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
3. Each and every requirement in the RRD document should occupy a line in
the VRTM table with complete data to enable IAA to review it. In the
reviewing process IAA should be able to easily trace for each requirement
when it is going to be tested and the exact testing procedure / step designed
to prove it. (In case the VRTM is submitted before final test plan documents
are completed, IAA will verify the general validation method, and only later
the actual test procedures when submitted to IAA).
4. The following are considered to be the most important fields for the above-
mentioned tractability approval:
Requirement
ID
Validation Method Project stage
(e.g. SAT,
Sub-SAT,
etc.)
Procedure
document
name
Section Test
Case
Name /
step
testing, inspection,
demonstration,
analysis, etc.
These 3 fields are the ID of
the testing procedure / step
The combination <Procedure document name, Section, Test Case
Name/step> defines the exact procedure/step(s) designed to prove the specific
requirement.
5. Verification Method is how the requirement is going to be tested / proved /
demonstrated. To mention a few:
a. Product Qualification Tests
b. Test during FAT, Sub-SAT, SAT, SOAK
c. Laboratories tests
d. Compliance certificates with standards (such as FCC for
example)
e. Winning Bidder's declaration (to be minimized)
f. Written statement by a 3rd party vendor
g. Inspection / demonstration during training
h. Mathematical / Theoretical analysis
i. Real Field Measurements
j. Other
6. It should be noted that IAA has to approve the System Requirements
Validation as proposed by the Bidder. This may be done in two stages: First
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 52 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
IAA reviews and approves the VRTM: that all the RRD requirements are
addressed (completeness), the method of verification (i.e. testing, inspection,
demonstration, analysis, etc.) and at what stage(s) of the project this
validation shall be done. The second stage is to review and approve the actual
Test Plan documents which inter alia detail the exact test procedures or other
validation procedures.
7. Following is a “Block Diagram” illustrating an Overview of the VRTM:
7.3.7.3. IAA Expectation from a FAT / SAT / Sub SAT document
1. The Bidder shall provide IAA with a FAT / SAT document that shall cover,
at least, the following subjects (the following requirements intend to enlarge
the requirements in other Chapters, such as Chapter 5 rather than narrowing
them):
a. Test Environment: Hardware, Software, Other Test Equipment, Pre
AT (Acceptance Tests) conditions, Test data and data generation tools,
participants, Precautions, etc.
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 53 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
b. Safety Precautions
c. Test Forms: That shall incorporate, inter-alia the test procedures, the
steps in them, the expected results for each procedure / step.
d. Test Work Plan: Formatted Acceptance Test (AT) Documents which
shall specify at least the following:
i. What is going to be tested, when and under which
conditions?
ii. Who will participate in each test
iii. Timetable for results submission, presenting and discussing
the results with IAA, result approval by IAA, correcting
issues by the supplier.
iv. Retesting and Regression’s tests.
7.3.7.4. Factory Acceptance Test (FAT)
1. The purpose of the FAT is to demonstrate that all items of the intended A-
VDGS are correctly manufactured, or developed, and meet their individual
requirements.
2. The required FAT shall be performed and documented before shipment to
site.
3. The Bidder shall present to IAA in the FAT Test Plan document the intended
test, and define for each of the tests:
a. Test purpose – description of the system feature or requirement to be
tested.
b. Test Equipment –
i. Description of any test equipment and conditions needed to
perform the test.
ii. If proprietary test equipment is used, IAA would like The
Bidder to introduce it to IAA in order that IAA will gain
confidence in this test tool.
iii. For non-proprietary test equipment, IAA would like the
Bidder to attach the laboratory certificates that verify that the
test equipment is valid at the time of conducting the test.
c. Test Procedure - description of test method, including analysis of test
data.
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 54 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
4. IAA reserves the right to attend and witness the FAT execution.
5. Should problems materialize during the FAT or should the FAT results be
deemed unsatisfactory in any way by IAA, the problems shall be corrected
after (not during) the test and the status shall be solely defined by IAA.
6. The System Supplier shall take full economic responsibility for any required
retesting program. If during the test, additional tests become necessary, IAA
has the right to request their execution.
7.3.7.5. Site Acceptance Test (SAT)
1. The SAT shall prove that all System/Subsystem requirements at their site
specific installation and location are met.
2. The Bidder shall prepare a SAT Readiness Review (SARR) checklist
containing all SAT pre-requisite tasks with clearly defined division of roles
between the Bidder and IAA. The SARR Checklist shall be coordinated and
approved by IAA.
3. The SARR Review process shall follow the process described in section 7.3.4.
4. The SAT shall be carried out in IAA's facilities in accordance with SAT
Specification.
5. The SAT shall make use of both simulations and real data recordings as input,
if so required.
6. The Bidder shall provide IAA with the SAT documentation for approval prior
to SAT execution.
7. IAA representative(s) shall witness the SAT.
8. As the SAT shall include a number of live trials, IAA is prepared to provide
for the environment for such trials and operational/technical staff to perform
specified actions.
9. Before starting the SAT, all non-conformances and reservations recorded in
the FAT report shall be removed.
10. The SAT schedule shall be specified in the project work plan.
11. The Bidder shall provide the SAT report as scheduled in the project work
plan.
12. Results of each single test shall be mutually verified; however the PASS /
FAIL evaluation shall be approved solely by IAA.
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 55 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
13. Should problems materialize during the SAT or should the SAT results be
deemed unsatisfactory in any major way by IAA, the problems shall be
corrected after (not during) the test and the status shall be solely defined by
IAA.
14. The Bidder shall take full economic responsibility for any required retesting
programs. If during the test, additional tests become necessary, IAA has the
right to request their execution.
15. The Bidder shall provide a concise description for the SAT (Q)
7.3.7.6. SAT Closure
1. The Supplier shall fill for all failed test and / or for each anomaly occurred
and/or for each known bug / deficiency at SAT commencement the table
below:
2. The Correction Path Table:
# VRTM
Identifier
Problem /
Issue
Description
Reason
/
Theory
Proposed
Corrective
Action
Estimated
Contribution
to SAT
Results
Verification
Method
Verification
Due Date
Reference
to the Test
Case
Correction
Plan
Activities
Comments
3. A Waiver / Deviation Request shall incorporate the following information as
a minimum:
Req. # Contract
Paragraph Requirement Event
Procedure
Document
Test Case
Name
Product Test
Report
7.3.7.7. System Overall Acceptance Tests, Minimal Scope - Highlights
1. The following list of tests elaborates on some requested tests mentioned
at 7.3.7.1, and shall enlarge the Selected Bidder's test obligations rather than
reduce them.
2. The following not inclusive test types and areas shall be included in the SAT
plan proposed by the Bidder. Final test procedure shall be determined at the
detail design reviews.
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 56 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
7.3.7.7.1. General Tests
1. Start-up Time
2. Switch Over Time
3. Maximum Working Positions capacity
4. Maximum DSS capacity
5. Response time in various system tasks
6. Administration capabilities
7. Archive and data backup
8. Processing Delay
9. Common repair tasks (for testing MTTR of LRUs)
10. Stress Tests - including high loading, failure scenarios, wrong inputs, non-
valid values for system configurable items, etc.
11. The Bidder shall provide a concise description for the General Tests (Q)
7.3.7.7.2. Human – Machine Interface Tests
1. Special attention shall be made to testing HMI features that are not part of the
generic product, and were developed/ configured / adopted per IAA's
requirements.
7.3.7.7.2.1. General
1. HMI parameters & performance.
2. Multiple working position tests (e.g. various authorizations, etc.).
3. WP functionality.
4. Operational Data Management WP functionality.
5. Roles and authorization
6. Test environment mode
7. The Bidder shall provide a concise description for the HMI Tests (Q)
7.3.7.7.2.2. Maintenance working management positions
1. Please refer to the functionality described in Chapter 3
2. System components status and maintenance info display and reports
(Situation awareness picture, alerts, events, tasks etc.)
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 57 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
3. System performance degradation alerts and information display
4. System’s components configuration and management tools
5. System’s Events and Audible alerts management
6. Users and roles management
7. The Bidder shall provide a concise description for the Maintenance
Functionality Tests (Q)
7.3.7.7.3. Interfaces to Existing Airport Systems Tests
1. Per the requirements in Chapter 5.
2. Redundancy tests for interfaces
3. Interfacing to Test environment
4. The Bidder shall provide a concise description for the Interface to External
Airport Systems (Q)
7.3.7.7.4. System Availability Tests
1. Server redundancy tests
2. Network redundancy tests
3. Power failure and cold start-up
4. Work positions failure
5. The Bidder is encouraged to detail about other tests based on the proposed
architecture
6. The Bidder shall provide a concise description for the System Availability
Tests (Q)
7.3.7.7.5. DSS Tests
1. Detecting the A/C in straight and curved line
2. Detecting the A/C with obscure regions (like the Bridge)
3. Wrong A/C is approaching
4. A/C is not aligned to center line
5. The accuracy of the display reading compared to actual position of the A/C
6. Moving too SLOW or too Fast on the center line
7. STOP too Far conditions
8. On/OFF block messages to AODB
9. Obstacle detection tests
10. Repeating the tests for night, dawn, twilight, strong day light conditions
11. OCU tests
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 58 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
12. Local / connected mode tests
13. Other functional tests
14. Environmental Conditions Tests
15. The Bidder shall provide a Test plan of each DSS for a period of minimum
two weeks and at least 50 parking operations (Q). The aforementioned plan
shall cater for evaluation purposes solely.
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 59 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
7.3.8. Training
7.3.8.1. General
1. Training shall accompany, as an integral part of the project plan, each product,
module, sub-system or system that shall be delivered to the IAA. (PQ)
2. All training shall be performed either at IAA Premises in Israel or at the
Bidder's premises, according to IAA sole discretion. (PQ)
3. The bidder shall certify Technical-Users that participated in the technical
courses to perform system maintenance procedures. (PQ)
4. Practical training shall take place in class rooms which shall be equipped with
operational A-VDGS / A-VDGS end stations. (PQ)
5. The Bidder shall describe whether the class room will be part of the
operational A-VDGS / A-VDGS system or a standalone system with the same
capabilities for the training. (Q)
6. Both configurations shall not affect the operational system and disrupt its
performance and availability. (P)
7. All training shall include a theoretical and a practical part. (PQ)
8. The courses syllabus shall be coordinated with IAA and adapted to IAA
specific needs. (PQ)
9. The practical part shall include a real life system for the operational use. (Q)
10. The Bidder shall conduct a competency based training program to IAA's
Operational staff in accordance with the Project Plan at schedule. (Q)
11. The Bidder's trainers shall have formal training qualification and appropriate
experience. (PQ)
12. The Bidder shall issue a certificate of competency to each trainee that
successfully completes the training program. (PQ)
13. The bidder shall provide training courses in any case of a major system
change/update that affects the Technical and/or the Operational procedures.
(PQ)
7.3.8.2. Training Material
1. The Bidder shall provide course materials (manuals, drawings, presentations,
handouts, etc.) for each of the trainees. These materials shall cover all aspects
of the IAA system. (PQ)
2. The Bidder shall coordinate with IAA the exact amount of training material
hard copies at least one month prior to the planned training courses. (P)
3. In addition, all training materials shall be supplied to IAA in soft copies
(using removable media device – e.g. CD, DOK etc.). (PQ)
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 60 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
4. The Bidder shall provide the soft copies training material at least one month
prior to the planned training courses. (P)
5. Training material format shall be produced according to Documentation
format requirements as specified in section 7.3.10.7. (P)
7.3.8.3. Type of Courses
1. There are four categories of training courses: (Q)
a. Operational End Users training: System Operational use for all the A-
VDGS users. Including central system and OCU operation.
b. System Operational Managers/Experts training: That should
incorporate the operational management capabilities.
c. System Technical Users training: That should incorporate the entire
technical user’s capabilities.
d. System Technical Managers training: That should incorporate the entire
technical management capabilities.
2. The Supplier shall obligate to be able to provide certification / training course
for the system during the lifetime of the system. (PQ)
3. The A-VDGS Supplier shall provide the following training courses [The
selected bidder shall suggest the location for each course and/or merging
courses based on added value of such act and IAA approval]:
# of Cycles Location Schedule Participants Course Name #
1 Bidder’s
Premises
Prior to FAT Up to 6 Operational End
Users (1)
1 Bidder’s
Premises
Prior to FAT Up to 6 System technical
Users (2)
5 Israel Prior to 1st DSS
Acceptance
6 - 13 Operational End
Users (3)
1 Bidder’s
Premises
Prior to 1st DSS
Acceptance
Up to 6 System technical
Users (4)
1 Bidder’s
Premises
Prior to SAT 3 System technical
Management
(advanced
training)
(5)
1 Bidder’s
Premises
Prior to SAT 4 Operational
managers
/experts
(6)
4. Operational users’ courses duration shall be coordinated with IAA. For
courses that will be held in Israel, their duration should not exceed two
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 61 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
consecutive days due to operational constraints (shifts rosters). In case of
operational users’ courses longer than two days, IAA may require to split the
courses. (Q)
7.3.8.4. Expected Response
1. For each training course included in the Proposal, the following details shall
be included: (Q)
a. Course name.
b. Course syllabus
c. Course teacher name, profession and experience.
d. Course objectives, including the skills to be taught as well as how the
course participants will be examined on all aspects covered.
e. Course level, prerequisites and intended audience.
f. Course duration and schedule, including detailed timetable for each
day.
g. Course materials to be handed out to each one of the participants.
h. Recommended / maximum number of participants (included in the
Proposal).
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 62 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
7.3.9. Documentation
7.3.9.1. Details of documentation (PQ)
1. The Bidder is required to provide the necessary documentation for the safe
operation of The A-VDGS.
2. The Bidder shall undertake to revise the documentation with every upgrade
of The A-VDGS and/or peripheral hardware.
3. The documentation shall be tracked with version control mechanism.
4. The documentation shall be open to inspection by the IAA at any time.
5. The documentation shall be updated once a year as part of the Maintenance
Services
7.3.9.2. Specific requirements (Q)
1. Configuration documentation of the A-VDGS system.
2. Operational manuals
3. Bill of quantities
4. Spare part and consumable list
5. Site operating procedures, including change management, homologation
processes
6. Health and safety policy manuals
7. Operating and maintenance manuals
8. Service Level Agreement (SLA) & Service Delivery Plan (SDP)
9. ICD for data and / or services exchange with external information systems.
7.3.9.3. End User Manuals
1. Complete guides to the safe use of the A-VDGS system end devices and
peripherals for End-Users
2. Quick Reference Guides
3. Abbreviated version of the manuals for End-Users to include troubleshooting
of peripherals
4. The Bidder shall list all other documentation, which will be provided as part
of its basic Proposal. (Q)
7.3.9.4. Quantities
1. Note: The documentation shall be provided in the English Language. A soft
copy either on CD-ROM or another removable media device shall also be
provided to allow IAA to make additional copies for End-Users. (PQ)
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 63 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
7.3.9.5. Documentation List – Concentrated
1. The following table incorporates all requested documents as appear through
the Tender Documents. The list is introduced solely for tracking convenience
of all the involved parties.
2. The Documentation List:
Requirements
Documents
System
Application
Documents
Test
Documents
Project Management
Documents
Operations and
Maintenance
Documents
Revised
Requirement
Definition
(RRD)
System
Architecture
Conceptual
Test Plan
Program
Management Plan
Operational
User’s Manuals
Verification
Requirements
Table Matrix
(VRTM)
Site Engineering
Report
FAT
Procedure
and Plan
QA Plan and other
documents
Technicians
User’s Manual
System
Interfaces
Specifications
Installation Plan FAT Report Risk Management
Plan and other
documents
Version
Description
Document
HMI
Specifications
Inspection of the
Installed Base
Pre-SAT
Procedures
and Plan
Monthly reports
Interface Control
Document(s)
[ICD(s)] to the A-
VDGS / A-VDGS
sub-systems
Pre-SAT
Report
Steering Committee
Agenda and Report
Reviews Agenda and
Report
7.3.9.6. Other Documentation
1. The Bidder shall list all other documentation, which will be provided as part
of the System. (Q)
7.3.9.7. Documentation Format (P)
1. The Project's documents will be produced with MS Office (2010 version of
higher) tools (such as: MS Word, MS Excel, PowerPoint, Visio, etc.).
2. The Bidder shall submit PDF copies in addition to the Office documents, if
IAA asks for it.
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 64 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
3. All diagrams will be submitted in Visio or in AutoCAD format, or both, as
set by the IAA.
4. Gantt charts shall be submitted in all the following formats: MS Project, MS
Excel and PDF.
7.3.10. Involvement of the Bidder in the CFE activities
1. Following is a description regarding the Involvement of the Bidder in
Accompanying, Guiding and Controlling of other IAA's Contractors /
Interfacing Systems' contact persons
2. The Bidder shall support the IAA Infrastructure setup executed either by IAA
and / or by other IAA contractors, as follows:
# Stage Description of involvement
a. Requirements
definition
Provide the requirements definition document to the
design and/or executing entity in the station.
Work meetings for clarification of the requirements
definition (one or two meetings).
b. Assistance in
design
Telephone response to questions.
Work meetings.
c. Reviewing the
detailed plan
Reviewing the detailed plan.
Passing the comments document.
A work meeting aimed at clarification of comments
Reviewing the amended version of the detailed plan.
d. Purchasing,
execution,
installations
Telephone response to questions.
One or two on-site visits at the start of and during the
works.
e. Acceptance tests Full involvement in the tests.
f. Approval of the
infrastructures
Full and final approval of the infrastructures, verifying full
compliance and adequacy for the intended A-VDGS
System.
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 65 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
7.3.11. Installation Requirements
1. The Bidder shall describe in details his compliance with the requirements in
Sections 7.3.11.1, 7.3.11.2, 7.3.11.3 below. (Q)
7.3.11.1. General Characteristics of the required services
1. Variability Among Deployment Sites
a. In planning, execution and installation of all the relevant equipment and
supporting infrastructure (hereinafter the Element), the Bidder shall
take into account possible variations between the different positioning
sites, including such constraints as: positioning space constraints,
sources of electricity and data feed, temperatures and ventilation,
induction, service access, requirements dictated by other equipment
installed in the area, textures and structures of ceilings / walls / other
supporting infrastructures, method of mounting (wall mount, ceiling
mount, pole mount etc.), maximal accessibility for service personnel,
minimal disturbance to traffic in proximity of the Element, prevention
of direct lighting and other reflections and so forth.
b. For avoidance of any doubt, it is clarified hereby that no extra payments
whatsoever shall be paid to the selected Bidder due to the
aforementioned variability among deployment sites.
2. Planning and Construction Law
The Bidder must operate according to the Planning and Construction Law,
Israeli Standard 5435 and other official regulations.
3. Safety
The Bidder shall be aware of the existing hazards during the execution of
works on the airside and in the proximity of airplanes and other vehicles and
operate according to IAA's safety regulations.
4. Sub-Project
a. Each physical site in which the services and the goods specified in the
Technical Appendixes shall be required – shall be characterized as a
separate sub-project, including: capacity of work, time schedules etc.
b. The Bidder shall adjust to the required nature of work in IAA and
supply optimal response to such needs as:
i. Simultaneous execution of a number of sub-projects.
ii. Significantly reduced time-to-operation from raising a need to a
fully operational Element.
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 66 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
iii. Compliance with the actual target schedules as required in the
Project.
iv. Around the clock work and/or working during hours in which the
airport does not provide customer services and according to safety
regulations.
5. Execution Schedule
a. The Bidder shall work during hours that do not collide / conflict with
services for customers and/or movement of airplanes and/or other
works.
b. If the need arises, IAA at its sole, absolute discretion may order the
Bidder to work on Saturdays, Sundays, holidays, etc. (excluding Day of
Atonement). If there is a specific day on which the Bidder team cannot
work, it shall inform IAA in writing at least two months ahead of that
day.
7.3.11.2. Installation responsibilities
1. The Bidder shall carry out the installation of the Element in accordance with
its procedures as submitted to IAA for review.
2. The Bidder shall submit drawings to IAA for approval of any temporary
works, major equipment, etc. that it requires on site in the execution of the
Contract's Services.
3. During the installation, the Bidder shall coordinate its works with other
Subcontractors working in the same and adjoining areas, so as to ensure that
no delays are caused to work of others.
4. The Supplier shall review with IAA the installation sequence schedule prior
to starting the installation.
5. All mounting elements/brackets, either mounted on the wall or hanged from
the ceiling, shall be produced at a workshop prior to delivery to the site.
6. The mounting method to any building's element shall be reviewed, in
advance, by the building's constructor.
7. The selected Bidder shall verify the leveling of all elements in the horizontal
plan and in the vertical plan.
8. Upon completion of each task, the delivered equipment and working areas
shall be clean and in a working state and/or ready for immediate use.
9. The delivered equipment shall be protected against any damage until entering
into operation.
10. Throughout the installation period, the Bidder shall ensure that an appropriate
number of full time site supervisors are present at the site to ensure proper
installation of the System.
11. The installation work shall be executed in cooperation with the IAA.
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 67 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
12. All works shall be installed strictly in accordance with approved drawings,
specifications and procedures.
13. The Bidder shall provide and install all necessary equipment in connection
with the Element in order to ensure the correct and proper functionality. This
includes cabling, cable trays, supports, mountings, interface equipment with
networks or other systems, etc.
14. These associated deliveries or works shall be included in the Contract, unless
explicitly stated otherwise.
15. The Bidder shall inform IAA about the power consumption of all hardware
parts to be installed in order to allow IAA to provide either standard mains
voltage or guaranteed power using on-line UPSs.
16. The System Supplier shall be responsible for the ICD specification and
integration.
7.3.11.3. Installation Priorities and Considerations
1. The System Supplier, in cooperation with IAA and IAA’s designated
authorized representatives, shall investigate in detail and define solutions on
operational, functional or technical problems that may arise due to the
installation and operation of the equipment.
2. Whenever it is possible, the Bidder shall involve IAA personnel in installation
and preparation works.
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 68 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
7.4. Project Management / Governance – Reference Procedures
7.4.1. Introduction
1. This Section specifies the control and reporting tools and also additional rules
that shall serve as a basis for the management concepts to be implemented
throughout the execution of the project.
2. The Bidder may attach its own procedures for the Managerial Procedures. (Q)
7.4.2. Managerial Procedure Objectives
1. The management of the project shall be based upon the following managerial
elements:
2. Forums & Meetings
a. Steering Committee
b. Project Directorate (PD)
c. Technical Board
3. Procedures:
a. Project Management reviews (PMR)
b. Quality Reviews
c. Formal Reports
d. Risk Management
e. Quality Management
f. Test Management
4. The Bidder shall present its proposed Project Management / Governance
Procedures, which it trusts to be effective in bringing the A-VDGS Project to
completion, successfully, on time, on scope, on quality and on budget. (Q)
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 69 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
7.4.3. Forums & Meetings
7.4.3.1. General
1. After each meeting / forum the Bidder’s A-VDGS Project Manager shall be
responsible to deliver the minutes, including any relevant written materials,
in an official document that shall become formal once it is approved by IAA.
2. It is preferable that a meeting minutes draft is prepared during the meeting by
the Bidder's leader of the meeting, and is reviewed and agreed between both
parties during, or at the end of the meeting. The draft shall include the issues
that were discussed, agreements, resolutions, action items, risk and mitigation
thereof.
7.4.3.2. Steering Committee
1. The steering committee is a decision making forum who:
a. Receives and approves a consolidated status report prepared by the
project management team
b. Outlines strategic directions
c. Resolves high-priority and escalated issues
d. Directs and prioritizes activities at the operational and tactical levels
2. The steering committee is a joint IAA and Bidder’s Executive Level Forum
that is authorized to make decisions as described above. The committee shall
be convened and chaired by IAA’s Executive or anyone on his behalf, and
shall consists of:
a. IAA's management representatives and relevant stakeholders
b. Bidder’s Executive Manager
c. IAA’s Project Manager
d. Bidder’s Project Manager
e. Bidder’s Senior Technical Manager
3. The participation in the Steering Committee is mandatory. Any waiver shall
be coordinated and given with the prior consent of the Chairperson up to 5
days before the planned date of the Steering Committee. The Bidder’s
executive manager shall be responsible to nominate an appropriate
replacement and advise the Steering Committee forum in case of absence.
4. It shall be the Bidder’s A-VDGS Project Manager’s responsibility to prepare
an agenda and presentation documents (Microsoft Office format) prior to the
Steering Committee in coordination with the IAA’s Project Manager, and
distribute these files not later than 48-72 hours prior to the meeting.
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 70 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
5. Additional participants can be invited to the Steering Committee with the
prior consent of the chairperson.
6. The committee shall convene every 3 months in Israel or earlier upon a
specific need - on a schedule agreed with the Selected Bidder.
7.4.3.2.1. Minutes of the Steering Committee Meetings
1. The minutes of meeting shall be prepared by the Bidder's Project Manager
and approved by the IAA’s Project Manager prior to their distribution.
2. The Bidder's Project Manager shall prepare and publish after IAA approval,
up to 5 days after each meeting, a Word document titled "A-VDGS Steering
Committee – Meeting Minutes <date>".
3. The Minutes of Meeting shall include the following items:
a. Meeting Owner
b. Invitees
c. Participants
d. Unattended Invitees
e. Agenda – a predefined agenda shall be concluded between the
Bidder's Project Manager and the IAA’s Project Manager upon the
project line-up period
f. Meeting Decisions
g. Action Items - including the responsible person and the due date for
each item. These action items shall be tracked until closure and
reported on the subsequent Steering Committee.
h. Attachments – including the meeting status review report and any
other relevant materials.
7.4.3.3. Project Directorate (PD)
1. The mission of the PD is to enable effective coordination between all the
involved parties in the project both from IAA and among the Bidder's team
and subcontractors and also to enable control over the progress of the project.
2. The PD forum shall include:
a. Chairperson – the Bidder’s A-VDGS Project Manager
b. Bidder’s participants - Bidder’s A-VDGS Senior Technical
Manager and any other relevant team member(s) determined by the
A-VDGS Project Manager.
c. IAA’s participants - IAA’s Project Manager and additional
representatives on behalf of IAA determined by IAA’s Head of
Electricity Division Manager and Project Manager.
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 71 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
3. It will be possible, in coordination with IAA’s Project Manager, subject to
suitable security clearance, to invite additional participants to meetings of the
directorate.
4. The PD shall convene regularly on a weekly or a bi-weekly basis by
conference call, and every 6 weeks by a meeting at IAA. The responsibility
for the invitation of the PD is of the Bidder's A-VDGS Project Manager.
7.4.3.3.1. Minutes of the Project Directorate Meetings and / or Conference Calls
1. The minutes of the PD Meetings shall be prepared by the Bidder's A-VDGS
Project Manager and approved by the IAA’s Project Manager prior to
distribution.
2. The Bidder’s A-VDGS Project Manager shall prepare a detailed report with
the main management and technical subjects of the project, and submit it to
the PD 48-72 hours prior to the meeting, so the forum can review it before the
meeting.
3. Immediately after each meeting, the Bidder's A-VDGS Project Manager shall
prepare and publish, a Word document titled "A-VDGS Project Directorate –
Meeting Minutes <date>".
4. Each summary of the meetings shall include at least the following subjects:
a. Major comments made by the IAA’s Project manager
b. Major comments made by the Bidder’s Project Manager
c. Meeting Decisions
d. Work Plan Highlights for the near future
e. Main risks and concluded mitigation plan
f. New tasks or Action Items (including the responsible person and due
date for each item)
7.4.3.4. Technical Board
1. The technical board goal is to discuss and address imminent technical issues,
and escalate to the Project Directorate any unresolved issues.
2. A technical board shall be founded for the project to include:
a. Chairperson – Bidder’s Senior Technical Manager
b. Bidder’s Participants – relevant team members determined by the
Bidder’s Senior Technical Manager.
c. IAA’s participants - relevant technical experts determined by IAA’s
IAA Telecommunication Manager and Project Manager.
d. Optional participants - IAA’s Project Manager, Bidder’s A-VDGS
Project Manager
3. Additional participants may be invited to the technical board meetings in
coordination and with the prior consent of the IAA’s Project Manager.
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 72 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
4. The technical board shall convene every 6 weeks in a meeting at IAA, and by
conference call on a weekly basis or as necessary. The technical forum shall
be scheduled prior to the weekly PD forum meeting.
5. The initiative for a technical board meeting can be triggered by both IAA and
the Bidder, including the IAA’s Project Manager, and the Bidder’s A-VDGS
Project Manager or Senior Technical Manager. The responsibility for the
invitation of the forum shall be that of the Bidder’s Senior Technical
Manager.
7.4.3.4.1. Minutes of the Project's Technical Board Meetings
1. The minutes of these meetings shall be prepared by the Bidder’s Senior
Technical Manager and approved by the IAA Technical Manager prior to
their distribution.
2. The Bidder's Senior Technical Manager shall prepare and publish,
immediately after each meeting, a Word document titled "A-VDGS Technical
Board – Meeting Minutes <date>".
3. A summary of the meeting shall include at least the following subjects:
a. Previous meeting’s Action Items status
b. Made Decisions
c. List of newly opened issues and their status
d. Issue Highlights of the Work Plan for the near future
e. Identified risks and concluded mitigation plan
f. New tasks or Action Items (including responsible person and due
date for each item)
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 73 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
7.4.4. Reviews
7.4.4.1. Review Procedure
1. All the formal reviews shall be registered, as aforesaid, as a single milestone
or a series of milestones in the Project Management Plan including the
necessary precedent activities in the Gantt chart. All the technical and
managerial reviews that are to be established during the project shall also be
updated in the project plan.
2. Five (5) business days prior to the review, unless otherwise agreed upon
between the parties, the Bidder shall submit to IAA all the documentation
accompanying the review and the basis for their approval.
3. After the review, the Bidder shall prepare and publish a document titled
"<topic> Review Summary" (‘topic’ refers to each of the formal reviews
listed in the table above), and present it for the approval of IAA. The summary
shall include updates to the accompanying documentation of the review.
4. In case the review is associated with a milestone, its existence does not
constitute automatic approval of the milestone. Only after the review has
ended successfully and has been approved by IAA, the milestone will be
considered approved. IAA will approve the review, if the conditions for it are
matured, within 5 working days after its completion.
7.4.4.2. Readiness Review Procedure
1. The Bidder shall plan and create a comprehensive checklist, for each of the
readiness review activities and milestones that must be accomplished to
ensure the timely readiness of the relevant milestone.
2. This checklist shall include the list of the Bidder and IAA’s prerequisite tasks
/ actions, whose responsibility, due date, progress status and Red / Yellow /
Green (RYG) indicator for quick status visibility and tracking purposes. The
Bidder shall send the checklists for the review and approval of IAA.
3. The Review procedure of the Readiness activity shall be according to the
Review Procedure detailed in the previous clause.
4. The Bidder is requested to describe in its response how it is planning to meet
all the requirements above (1, 2 and 3) if he will be the selected Bidder (Q).
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 74 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
7.4.5. Reports
7.4.5.1. General
1. The Bidder is welcome to propose and introduce its reports that have been
successful in past projects. (Q)
7.4.5.2. Monthly Progress Report of the Project
1. By no later than the 5th of each month, the Bidder’s A-VDGS Project
Manager shall prepare and publish, with reference to the previous month, a
Word document titled: "A-VDGS Monthly Progress Report <- mmm-yyyy>"
and submit it for review and approval of the IAA’s Project Manager.
2. The report shall include at least the following clauses:
a. Executive Summary containing the status of the project in general, a
concise report in view of the progress time axis of the project, a report
on the main events during the previous month and details of the main
issues that require attention.
b. References to the main up-to-date Managerial Documents of the
project, with emphasis on an up-to-date Project Plan (Gantt), with clear
marking of any change from previous version, or deviation of actual vs.
plan, Customer (IAA) tasks, action Items status
c. Project risks and their mitigation plan, with emphasis on newly
observed risks.
d. Details of the main activities for the next month.
e. Staffing status, including but not limited to changes made and planned.
f. Procurement status of third party products.
g. Development status in view of subjects and components.
h. Status of formal deliverables.
i. Outstanding issues and recommended action plan.
7.4.5.3. Steering Committee Status Report
1. The Bidder’s A-VDGS Project Manager shall be responsible to prepare in
coordination and approval of the IAA’s Project Manager a Word document
titled: "A-VDGS Steering Committee status report”.
2. The Bidder’s A-VDGS Project Manager shall distribute the report no later
than 48-72 hours before the scheduled steering committee meeting.
3. The report shall include at least the following topics: (Q)
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 75 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
a. Goals (from previous meeting) status
b. Major and/or significant achievements accomplished during the
reporting period
c. Major Milestones Status – Actual vs. Plan
d. Action Items Status (from previous Steering Committee)
e. Outstanding Risks along with suggested Mitigation Plan to be
approved
f. Outstanding Open Issues along with suggested decision to be made
g. Production Readiness Status – Actual vs. Plan (when it becomes
relevant)
h. Main Change Request Status
i. Next Steps and/or Goals for the next period
7.4.6. Deliverable Management
7.4.6.1. General
1. The components / items that will be delivered within the project are defined
in Chapter 9 - BOQ to this technical appendix.
7.4.6.2. Method of Management
1. The various documents to be prepared within the project (including those for
analysis, design, testing, documentation, status reports etc.) shall be written
according to the standards defined in the Proposal. In special cases when
required, the Bidder can request to write a certain document according to
another standard that shall be presented to IAA for approval.
2. The table of contents and the template of each document included in the list
of the products of the project shall be presented to IAA, to the extent possible,
prior to the start of the work upon it and no later than 10 working days before
the time of its submission.
3. Submission of any formal document, including status reports, formal
products, formal addressing etc., shall be considered as having been carried
out if and only if this document was delivered in one, or more "hard copy"
(paper) and "soft copy" (CD) to IAA as agreed, and the IAA’s Project
Manager has confirmed their receipt.
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 76 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
7.4.7. Quality Assurance
1. The Bidder shall describe in its response how it complies with the
requirements in this section (Q)
7.4.7.1. General
1. Throughout the project, the Bidder shall take all measures in order to assure
that the supplied system and all the other products, including documents,
conform to the requirements detailed in the agreement and are of high quality,
according to the standards detailed in the documents of the agreement.
2. The Bidder shall implement a "quality assurance program" within the project
framework according to industry standards and the Bidder’s own QA
procedures and everywhere required as customary in the relevant field
internationally and based on "best practice" principles.
7.4.7.2. Organization and Responsibility
1. The Supplier shall assume sole responsibility for all issues of quality
assurance in the project, including implementation of the quality assurance
program of the project.
2. The Supplier shall appoint a quality assurance manager who shall be
responsible for the quality assurance processes that shall be applied in the
project.
3. In addition, one member of the project team shall be nominated as a quality
assurance monitor and shall serve as the quality assurance manager
representative in the project team.
7.4.7.3. Quality Assurance Plan
1. The Bidder shall prepare a quality assurance plan for the project, which shall
function as a tool for tracking and controlling quality assurance activities that
shall be carried out throughout the project.
2. The supplier shall make its best effort so that the quality assurance plan shall
include and address at least the following subjects:
a. Definition of quality assurance assignments and outputs in each
phase of the project's lifecycle.
b. Definition of the procedures and the standards by which the
system shall be developed.
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 77 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
c. Definition of the quality metrics (technical and managerial) that
shall allow for tracking the quality of the product and the progress
of the project.
d. Definition of the way in which data shall be collected as regards
to the quality metrics that were defined.
e. Definition of contents and times to perform the project's internal
quality audits.
f. Follow-up of essential issues such as: risk management and the
test plan.
7.4.7.4. Quality Audits
1. During the project, the supplier shall execute internal quality audits in order
to assure conformance to the quality requirements and plan.
2. At least one internal quality audit shall be made before each formal milestone.
The quality audits shall be indicated in the Gantt chart.
3. Following each quality audit, a report that summarizes the audit shall be
published.
7.4.8. Risk Management
1. The Bidder shall describe in its response how it complies with the
requirements in this section (Q)
2. The Bidder shall demonstrate its Risk Management Methodology by
analyzing the top 5 risks of IAA’s A-VDGS Project as it sees them (Q)
7.4.8.1. General
1. "Risk management" is intended to help in locating weak links, risk factors
and potential failures that may cause significant delays in schedules, cost
overruns and the contents downgrade of the project.
2. Throughout the project, a "Risk management" process shall be realized under
the full responsibility of the Bidder and according to the specifications,
meanings and contents detailed in this chapter.
3. Risk management shall include at least activities of: identification,
assessment, mitigation plan and performance tracking and repeat
measurement.
Version 1.0 IAA Tender For A-VDGS
Chapter 7 – SOW & Bidder’s Details Appendix A – Technical Requirements
Page 78 of 78 File Name: IAA_A-VDGS-RFP-Appendix-A__Chapter 7 - SOW and Bidder Details
Saved: August 28, 2016
4. The Bidder’s A-VDGS Project Manager and IAA’s Project Manager shall
agree on all issues that require further clarification concerning the
methodology by which the risk management is to be realized.
7.4.8.2. Risk Management Methodology
1. The process of the risk management, as mentioned above, shall be based
mainly on a designated "risks forum" that shall be established to execute the
mission.
2. The risks forum shall include at least the following roles: the A-VDGS Project
Manager, the system engineer, the development manager, the tests manager,
IAA’s Project Manager and IAA QA Manager.
3. The Bidder’s A-VDGS Project Manager shall head the risk forum.
4. The risk forum shall convene each month in arrangement between the A-
VDGS Project Manager and IAA’s Project Manager.
5. Meeting minutes shall be written under the responsibility of the Bidder's
project manager.
6. The Bidder shall be responsible for maintaining a chart of detailed risks that
shall be updated continuously and on a timely manner that shall ensure the
risks mitigation or elimination. The structure of the chart shall be as detailed
in clause 7.4.8.3 below. The up-to-date chart shall be prepared and published,
each month, within 2 working days from day of the risk forum meeting.
7. The project risks and the mitigation plan shall be presented to the project
steering committee by the Bidder’s project manager.
7.4.8.3. Structure of the Risk Chart
1. The Risk chart shall include the following fields:
a. Risk Identification factors – risk identification number, type,
description, initiator, identification date.
b. Risk analysis factors – impacted areas/key success factors, risk
materialized date (the date in which the risk become real if not
addressed or mitigated), Severity, Probability, risk rank(*)
c. Risk Mitigation Plan – risk owner, mitigation plan, planned due date
(for mitigation), revised and actual due dates, and status report.