teamwork in the design phase ‐ integrating design and construction forecasting for value

68
Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value John Mack and Jesse Whalen Herrero Contractors, Inc Balfour Beatty

Upload: ora

Post on 11-Jan-2016

43 views

Category:

Documents


0 download

DESCRIPTION

Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value. John Mack and Jesse Whalen. Herrero Contractors, Inc Balfour Beatty Construction. VDC / BIM Department Manager at Herrero Contractors, Inc. 26 years in the construction industry - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for

Value

John Mack and Jesse Whalen

Herrero Contractors, Inc

Balfour Beatty Construction

Page 2: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

John Mack

• VDC / BIM Department Manager at Herrero Contractors, Inc.

• 26 years in the construction industry• Last 3.5 as a general contractor• Previous 22.5 years in the mechanical and plumbing

industry• Doing BIM/VDC for 18 years

– Union trained plumber– Ran detailing department for two large mechanical

contractors– Helped design software for third party AutoCAD and

Project Management programs• Been involved with Lean Construction for 7+ years.• Participate with Lean Construction Institute (LCI),

Center for Integrated Facility Engineering (CIFE) and Project Production Systems Laboratory (P2SL).

• President of the San Francisco Navisworks User Group (SFNUG).

Page 3: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

• Established 1955

• Second Generation Family Owned Business

• Areas of Operation: Northern California and anywhere else our customers take us

• Construction Employers Association’s safety award for the past four years

• Primary focus is Integrated Lean Project Delivery

• Providing Preconstruction and Construction Services

• All Projects Done Using VDC

• Full Time VDC Employees

Higher Education

For Other Examples Visit Our Website at www.herrero.com

K-12 Schools

Healthcare

Hospitality

Historical Restoration and Renovation Affordable Housing

Residential

Retail

Tenant Improvement

Page 4: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

Jesse Whalen

• Manager of Technology & Process Development (TPD)– Project BIM Execution Support– Pursuit BIM Planning and Execution– R&D / Process Development– Knowledge Sharing / Training

• Bach. Arch. Eng. Penn State University (Construction Mgmt.)

• Eight years with Balfour Beatty– Last four with TPD group– First four in Operations

• Hospital Project Engineer• Prison Asst. Project Manager• Art Museum Asst. Superintendent

Fairfax, VA

Pittsburgh, PA

Page 5: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

North

SoutheastSouth Central

Southwest

BBC HSW

Page 6: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

North

SoutheastSouth Central

Southwest

BBC HSW

Multi-Family Residential Public

Assembly

TransportationMission Critical

Research Labs

Military Housing

Hospitality Education

Healthcare

Criminal Justice

Corporate

Civic

Page 7: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

North

SoutheastSouth Central

Southwest

BBC HSW

TPD

National BIM Workgroup

Page 8: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

The Evolving Landscape

• Tools and Technologies

• Processes and Behaviors

• Information Flow

• Revit / BIM

• Opportunity to Collaborate

Page 9: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

The Evolving LandscapeInformation Flow

DESIGN CONSTRUCT OPERATE

Owner

GC

Architect

Consultants

Subs

Fabricators

Engineers

End User

Operator

L O N G

I N E F F I C I E N T

Page 10: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

The Evolving LandscapeInformation Flow

Page 11: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

The Evolving Landscape

Design Construct Design Construct

Design Construct

Hand Drafting Computer Drafting

Building Information Modeling

Page 12: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

Why We Are Here

• Opportunity to Collaborate

• Promote Understanding

• Fears and Perceptions

Page 13: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

Agenda

• Revit without Integration – The Blind Handoff

• Revit with Integration – Case Studies

• Questions and Discussion

Page 14: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

The Blind HandoffGet to know the model Get to know the content

• In what version of Revit was this model created?– Do I need to upgrade my Revit?

– Will I ever transfer this back to the designer?

– Should I upgrade the model or work back in the earlier version?

Page 15: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

The Blind HandoffGet to know the model Get to know the content

• Has the model been workshared?– No? Good, move on.

– Yes? Should I keep it workshared? Detach and preserve?

• What am I looking to do with this model?

• Will I have multiple modelers working in this model? Does worksharing make sense for me?

• What do the worksets look like?

• Should I un-workshare? Detach and preserve? Detach and discard?

Page 16: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

The Blind HandoffGet to know the model Get to know the content

• What errors and warnings do I get when I open the file?

Page 17: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

The Blind HandoffGet to know the model Get to know the content

• What errors and warnings do I get from Manage – Warnings?

Page 18: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

The Blind HandoffGet to know the model Get to know the content

• Are there linked Revit files?– No? Good, move on.

– Yes?

• What’s in these linked Revit models? Do I need that content?

• Do I have these Revit models?

• Should I try to obtain them?

• Should I unlink them?

Page 19: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

The Blind HandoffGet to know the model Get to know the content

• Are there linked CAD files?– No? Good, move on.

– Yes?

• What’s in these linked CAD files? Do I need to see that content?

• Do I have these CAD files?

• Should I try to obtain them?

• Should I unlink them?

Page 20: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

The Blind HandoffGet to know the model Get to know the content

• How is the project browser organized?– Is it intuitive?

– Does it work for how I want to use the model?

– Do I need a new browser organizational scheme?

Page 21: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

The Blind HandoffGet to know the model Get to know the content

• Did the author use Design Options?– No? Good, move on.

– Yes? Alright, let’s have a look.

• Are they legitimate design options I need to know about?

• Are they named intuitively?

• How will they affect my use of the model?

• Check them out individually when I’m getting to know the content.

Page 22: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

The Blind HandoffGet to know the model Get to know the content

• Did the author use Phases?– No? Good, move on.

– Yes? Alright, let’s have a look.

• Do the Phases really represent periods in time, or were they just a means to control visibility?

• Are the Phases named intuitively?

• Are the Phase Filters named intuitively?

• Are the views named accurately to match their phase and filter?

• How will they affect my use of the model?

• Check them out individually when I’m getting to know the content.

Page 23: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

The Blind HandoffGet to know the model Get to know the content

• Project location, coordinates, orientation?– Any changes to default?

– Are there multiple projects I need to align?

• Do I need them to align in Revit?

• Do I need them to align in Navisworks?

Page 24: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

The Blind HandoffGet to know the model Get to know the content

• How do the Family Names look?– Intuitive?

– Well described?

– Do they fit their categories?

Page 25: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

The Blind HandoffGet to know the model Get to know the content

• The 3D view Host-Only Revit-Only content check

1. Manage – Manage Links

• Revit links – unload or remove

• CAD links – unload or remove

2. Visibility Graphics

• Imported categories – all off

• Model categories – all on

• Filters – none applied

• Worksets – all show

3. 3D View Properties

• Crops and section box off

• Phase Filter set to None

Page 26: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

The Blind HandoffGet to know the model Get to know the content

• The 3D view Host-Only Revit-Only content check

4. Select all objects

5. Check the filter

6. Look for red flags

• Generic Models – what are they?

• Model Groups – what do they contain?

• Specialty Equipment – what are they?

• Lines – they don’t represent objects to be constructed

• Openings, shafts, reveals, etc. – they are invisible and represent voids

Page 27: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

The Blind HandoffGet to know the model Get to know the content

• The 3D view Host-Only Revit-Only content check

7. Isolate and evaluate one category at a time

• Will I get reliable quantities from these objects?

• Can I use these objects for 4D simulation?

• Can I use these objects for coordination?

Page 28: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

The Blind HandoffGet to know the model Get to know the content

• The schedule view Host-Only Revit-Only content check

1. One category at a time, build a quantity schedule

2. Phase Filter – set to None

3. Compare objects in quantity schedule to objects in 3D view

• Do the quantities match?

Page 29: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

The Blind HandoffGet to know the model Get to know the content

• Evaluate Design Options

1. One Option Set at a time, activate and evaluate the options• Are they legitimate design options?

• For my intended purpose, what option do I care about?

Page 30: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

The Blind HandoffGet to know the model Get to know the content

• Evaluate Phases

1. Build condition isolating phase filters

2. One phase at a time, one filter at a time, isolate and evaluate

• Do the phases really represent phases in time?

• How are the objects falling across the phases?

• How do the phases and object distribution affect what I’m trying to do with the model?

Page 31: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

Partnering with Architects

• Case 1: UCSF HSE-15

• Case 2: St Mary’s School

• Case 3: Kaiser San Rafael

• Case 4: Cathedral Hill Hospital (CHH)

• Case 5: St Luke’s Hospital (STL)

Page 32: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

UCSF HSE-15 Project

Page 33: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

UCSF HSE-15 Project Background

• Craniofacial and Mesenchymal Biology Program Lab

• Single story tenant improvement renovation in an exist ing building

• 13,500± sf

• Lab space

• Owner: UCSF

• GC: Herrero Contractors, Inc.

• Architect: BlakeDrucker Architects

Page 34: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

• Started construction 3 months after owners intended start.

Finish 1 month early

• Early identification of as built conditions with the design that

were solved before construction– Pipes serving other floors not in walls

– Lights into the fireproofing on the steel

• Gained early trust between architect

and GC

UCSF HSE-15 Story

Page 35: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

St Mary’s School

Page 36: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

St Mary’s School Project Background

• New gymnasium, play area and classrooms

• 4 stories, plus roof top play area, over existing parking

• 40,000 ± sf

• Owner: Archdiocese of San Francisco

• Construct ion cost: 14M

• GC: Herrero Contractors, Inc.

• Architect: WRNS

Page 37: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

St Mary’s School Story• All documents came from 2D AutoCAD• Herrero recognized the need for a 3D architectural model

– We were resource stricken

• Approached architect to build the initial construction model the building in Revit using the architectural documents.

• One week in, we get a phone call, “how do you people build off what we draw?”

• This process eliminated 100’s of RFI’s that would have ben generated in the field

• Gained trust between the architect and GC.• Allowed us to use hand sketches in meeting to resolve issues.

– Example was a 30 minutes session to resolve a beam penetration

Page 38: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

Kaiser San Rafael

Page 39: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

Kaiser San Rafael Project Background

• New Ground up ED and New Mechanical Yard separate from building

• Single Story

• 17,500± sf

• Construct ion cost: $6M

• Owner: Kaiser Permanente

• GC: Herrero Contractors, Inc.

• Architect: Lionakas

Page 40: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

Kaiser San Rafael StoryInconsistency of Walls Example

Page 41: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

Kaiser San Rafael Story• Placed a Herrero person at architects office for 1 week

– Person was well received. In fact they gave him one of their workstations, a company login and access the central model.

– Treated like one of their own employees

• Objective was for the contractor to work with the architect in the architect central model to rebuild partitions and ceilings as a team.– Provide document needs and constructability needs from the same model.

• Outcome– Walls and wall details match– Wall families have contractor information for 5D and total station layout.– Ceilings match details– Ceilings families have contractor information for 5D and total station layout

Page 42: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

Cathedral Hill Project, aka CHH

Page 43: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

Cathedral Hill Project Background

• New Acute Care Hospital to be Constructed in San Francisco

• 16 Stories, +2.5 Stories Underground Parking

• 1,000,000± sf

• 555 Patient Beds

• Fully glazed enclosure, green roof

• Breaking ground: Fall 2012

• Construction cost: $1 billion

• Owner: CPMC/Sutter Health

• GC: HerreroBoldt Partnership

• Architect: Smith Group JJR

Page 44: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

CHH Story: Integrated Project Delivery

• Enables team collaboration.• Promotes a coordinated Building Information Model.• A culture of sharing expertise, resources and experience to solve problems. • IPD agreement allows for shared risks and profits.• Co-location.

Page 45: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

CHH Story:Current State of Model-based QTO • Lacking a full understanding of the technology and its integration into the industry

• Minimum communication and understanding between Modelers and the Estimators

• BIM expectations, process and model end-goals not pre-planned and mapped out early in the project

• Subjective trust / faith in the model and its quantity reports

• Not everything can be takeoff from the model

Page 46: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

CHH Story: Addressing challengesVD

CEs

timat

ors

A / E

/ Tr

ade

Partn

ers

Design in 3D

Establish Modeling Standards

Specify Types and Format for

Quantity Take-off

Extract Data from Model

Set up Models to Facilitate QTO and Estimating

Export 2D Drawings from

3D Models

Take-off Quantities from 2D Drawings

Final Quantity Validation and

Estimating

Data Analysis

Continuous Team Collaboration

Page 47: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

CHH Story: Interior EMP

No Room Finish Data in the model

Page 48: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

CHH Story: Interior EMP

BIM

Lin

k

Floor Typology

Wall Typology

Ceilings Typology

Wall Protection Typology

Finish Schedule in Excel

Updated Finish Schedule for EMP

Arch

/TP/

GC

inpu

ts

2D Drawings

Page 49: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

CHH Story: Interior EMP

Room Finish Data is in the model and drives color coded plans

Page 50: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

CHH Story: Interior EMP

Page 51: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

CHH Story: Interior EMP

Page 52: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

CHH Story: Interior EMP

Page 53: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

CHH Story: Interior EMP

Page 54: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

CHH Story: Interior EMP

BIMLink to synchronize model data and Excel Finish schedule

Page 55: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

CHH Story: Interior EMP

An accurate/updated Finish schedule in Excel for EMP

Page 56: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

The Replacement Hospital at St. Luke’s Campus

Page 57: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

St Luke’s Hospital Project Backgroundaka. STL• Acute Care Hospital to be Constructed in San Francisco

• 5 Stories

• 185000± sf

• 80 Patient Beds

• Breaking ground: Fall 2012

• Construction cost: $272M

• Owner: CPMC/Sutter Health

• GC: HerreroBoldt Partnership

• Architect: Smith Group JJR and Boulder Associates, Inc.

Page 58: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

STL Story: The Models

• Site, campus • Curtain wall • GFRC • Sheet metal

• Stud framing • Structure

• Ceilings, walls, floors … stuff

• Equipment & Furniture

• Lighting • Ductwork • Security• IT• Pneumatic Tube• Unistrut support

Page 59: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

STL Story: Weekly hotspots report

Page 60: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

STL: Weekly model change report

Page 61: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

STL Story: BIM for Exterior Collaboration

Page 62: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

STL Story: Collaborative BIM Details

Page 63: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

STL: Collaborative BIM Details

Page 64: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

STL Story: Working with Dry Wall

Page 65: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

STL Story: Working with Dry Wall

Page 66: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

Summary

• Invite the GC’s and Trade Partners to join in early on projects

• Use the GC and Trade Partners for their building knowledge

• Be innovative to create better quality documents for

construction

• Improve on each project

• Creating this behavior and environment is contagious to all

• Test in small controlled batches before applying to everything

Page 67: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

Take Away Session

Page 68: Teamwork in the Design Phase ‐ Integrating Design and Construction Forecasting for Value

Questions?

John MackJesse Whalen

Herrero Contractors, Inc

Balfour Beatty Construction