team p12442 marissa blockus, brandon harbridge, …edge.rit.edu/edge/p12442/public/system design...
TRANSCRIPT
Next Generation Charcoal Stove for Haiti
Team P12442
Marissa Blockus, Brandon Harbridge, Sam Huynh, Brianna Stephenson-Vallot, Dustin Tyler
Team Members
• Brandon Harbridge (IE) – Team Lead, Test Technician
Stove Team • Samantha Huynh (ME) – Lead Engineer
• Brianna Stephenson-Vallot (ME) – Team Engineer,
Purchaser Thermoelectric Team
• Marissa Blockus (ME) – Team Facilitator
• Dustin Tyler (ME) – Team Engineer, EE Liaison
Purpose of Review
• Demonstrate the group’s progress in accepting the tasks involved in creating two functioning Haitian cook stoves
• To gain feedback on the group’s current path to verify that the team has a complete understanding of the project
• Finalize customer Needs/Specs
• To obtain constructive criticism in order to improve as young engineers
Customer Needs-Stove
Need Importance Description Notes
1 9* Affordable (initial cost <$10 at high production) 1-10K Production
2 9 Requires less fuel for same cooking tasks
3 9 Reduced CO emissions
4 9 Safe to operate
5 9 Same or improved cooking controls
6 9 Able to be fabricated and assembled using Haitian artisan practices
7 3 Obtain rapid boil quickly and then bring to simmer
8 3 Easy to operate (l ittle user interaction and intuitive processes)
9 3 Transportable (able to be moved by a single Haitian adult 500 m)
10 3 Rugged (can handle being dropped and withstand harsh conditions)
11 3 Durable - l ifetime of five or more years Used twice a day
12 3 Have simple, cheap and easily replaceable parts
13 3 Reduced PM emissions
Importance Scale: 1 - low importance, 3 moderate importance, 9 high importance
* items are most critical
Engineering Specs-Stove
Eng Spec Description Importance Units Marginal Value Ideal Value
Relates to Customer
Need(s) Notes
1 Cost 9 $ <$15 <$10 1
2 Assembly time 3 hrs < 4 < 2 12,8
3 Fuel reduction 9 kg 50% >50% 2,3
Compared to Haitian
Rebar Stove, WBT and
Simmer
4 CO reduction 9 g 25% >50% 3
Compared to Haitian
Rebar Stove, WBT and
Simmer
5 PM reduction 3 g 25% >55% 4
Compared to Haitian
Rebar Stove, WBT and
Simmer
6 Time to boil 9 min 22.5 <22.5 7
7 Maximum Surface Temperature 1 °C < °50 C < °40 C 13
8 Time to boil for Modified WBT 3 min < 15 < 8 7,6
9 Range of heat output 3 kW 1 - 6 .8 - 6.2 7
10 Capable pot diameters 3 cm 20 - 60 15 - 65 5,6
11 Withstand pot mass 9 kg 25 30 5,6
12 Five or less tasks to maintain fire 3 tasks 5 < 5 5,6
13 Replacement: Part cost 3 $ 3 < 3 12
14 Replacement: Time required 1 min 60 < 60 8,12
15 Replacement: Tools required 3 - - - 8 Simple Haitian hand tools
16 Stove overall mass 3 kg 8 8 9
17 Stove volume 1 m^3 0.2 < 0.2 1
18 Stove construction 9 - - - 9 Simple Haitian hand tools
19 Survive 20 X 2-meter drop tests 3 drop tests 20 20 10,11
Importance Scale: 1 - low importance, 3 moderate importance, 9 high importance
Customer Needs-TEG
Need Importance Description Notes
1 9* Thermoelectric module will not fail
High temperature
gradients as well
as mechnanical
failure
2 9* Maintain appropriate temperature gradient across thermoelectric module
3 9 Safe to operate
4 9 Durable - l ifetime of five or more years Used twice a day
5 3 Rugged (can handle being dropped and withstand harsh conditions)
6 3 Have simple, cheap and easily replaceable parts
7 3 Achieve Desired temperature gradient quickly
TE Team
Importance Scale: 1 - low importance, 3 moderate importance, 9 high importance
* items are most critical
Engineering Specs-TEG
Eng Spec Description Importance Units
Marginal
Value Ideal Value
Relates to
Customer Need(s) Notes
1 Survive 20 X 2-meter drop tests 3 drop tests 20 20 1,2
2
Minimum temperature gradient
across Thermonanic TE 9 °C 200 200 6 Under peak conditions
3 Quickly reach temperature gradient 9 min 20 15 7
4 Stove electrical consumption 9 W .6 - 1 <.9 4
5
Maximum thermoelectric
temperature on hot side 9 °C 380 (400) 380 6
380°C continuously and
400°C intermittently
6
Maximum thermoelectric
temperature on cold side 9 °C
(Value from
EE Team) 200 6
7
Thermoelectric module is
mechanically loaded evenly and 9 - - - 6
8 Cost 9 $ <$10 <$10 3,5
TE Team
Importance Scale: 1 - low importance, 3 moderate importance, 9 high importance
System Energy Flow-Stove
System Map
Start-Up Flow Diagram
Start fire
Enough power
stored in battery to
run fan
Harvest heat from
combustion chamber to
power TEG
No power stored to
run fan
Convert power
produced by TEG
to power fan
Battery power to
aux device
Turn on fan
Store TEG power
produced in
battery
Process
Takes
longer
Harvest heat from
combustion chamber to
power TEG
Store power to
operate fan at next
start up
Stove/TEG team
EE Team
TEG Diagram 1
TFIRE
Thermoelectric Harvester Heat Sink Thermoelectric Unit (TEG)
W=q1-q2
TH-TC=200°C
α=0.0346 V/K
TEG
qLOSS Re=2.745 Ω
RTH=1.376 K/W
TEG Diagram 2
Delta T 200 degrees C
Tc (C) 100 110 120 130 140 150 160 170 180
Th (C) 300 310 320 330 340 350 360 370 380
Imax 1.26
qh (W) 156.25 156.69 157.12 157.56 158.00 158.43 158.87 159.30 159.74
qc (W) 151.89 152.33 152.76 153.20 153.64 154.07 154.51 154.94 155.38
W (W) 4.36 4.36 4.36 4.36 4.36 4.36 4.36 4.36 4.36
At a temperature difference other than 200C
Delta T 125 degrees C
Tc (C) 100 110 120 130 140 150 160 170 180
Th (C) 225 235 245 255 265 275 285 295 305
Imax 0.788
qh (W) 96.12 96.40 96.67 96.94 97.21 97.49 97.76 98.03 98.30
qc (W) 94.42 94.69 94.97 95.24 95.51 95.78 96.06 96.33 96.60
W (W) 1.70 1.70 1.70 1.70 1.70 1.70 1.70 1.70 1.70
Delta T 150 degrees C
Tc (C) 100 110 120 130 140 150 160 170 180
Th (C) 250 260 270 280 290 300 310 320 330
Imax 0.945
qh (W) 115.96 116.29 116.62 116.94 117.27 117.60 117.92 118.25 118.58
qc (W) 113.51 113.84 114.16 114.49 114.82 115.14 115.47 115.80 116.13
W (W) 2.45 2.45 2.45 2.45 2.45 2.45 2.45 2.45 2.45
Delta T 175 degrees C
Tc (C) 100 110 120 130 140 150 160 170 180
Th (C) 275 285 295 305 315 325 335 345 355
Imax 1.103
qh (W) 136.00 136.39 136.77 137.15 137.53 137.91 138.29 138.68 139.06
qc (W) 132.67 133.05 133.43 133.81 134.19 134.57 134.96 135.34 135.72
W (W) 3.34 3.34 3.34 3.34 3.34 3.34 3.34 3.34 3.34
qh = α*Th*I + K*(Th-Tc) - 1/2*Re*I^2 qc = α*Tc*I + K*(Th-Tc) + 1/2*Re*I^2
Imax = α*(Th-Tc)/(2*Re) W = qh-qc
α 0.035 V/K
Re 2.745 ohms
Rth 1.376 K/W
K 0.7267 W/K
Governing Equations
Measured Constants
What this shows… The heat conduction required from the fire to achieve the hot side temperature as well as the cooling required to maintain the cold side temperature. Though this is a crude representation, it represents a basis for further study.
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
4.5
5.0
0 50 100 150 200 250
Po
we
r P
rod
uce
d (
W)
Delta T (C)
Power Produced Vs. Delta Temp
Morphological Chart
Functions Option 1 Option 2 Option 3 Option 4
Provide heat to pot Direct Contact Skirt
Combustion chamber
shape/size
Provide complete combustion Fan Swirl Chamber
Combustion chamber
shape/size
Convert heat into electricity TEG
Provide air to stove fire 1 Fan Multiple Fan Compressed air source Natural Draft
Control air flow Fan Speed Adjustable bypass Duct sizing Throttling
Provide heat to hot side of TEG Direct contact Extended metal surface Contact Block Radiative
Control temp at the hot side of the TEG Fan control Extended metal surface sizing Insulate around TEG
Provide cooling to cold side of TEG Heat sink Forced Convection (fan) Liquid Cooling
Control temp at the cold side of the TEG Sizing of heat sink Fan control Type of liquid used Fan overall size
Control temp gradient across TEG Modify extended surface Direct mount
Achieve temp difference within 20 min Extended surface sizing Fan control (or number of fans)
Extended surface location
within combustion chamber
Connect/disconnect harvester from stove Bolts Dowels
Associated Risks
System, Materials and Manufacturing, TEG, Fan and Conducting Rod Risks
ID Risk Item Effect Cause
Lik
elih
oo
d
Sev
erit
y
Imp
ort
an
ce
Action to Minimize Risk Owner
Describe the risk briefly
What is the effect on any or all
of the project deliverables if the
cause actually happens?
What are the possible
cause(s) of this risk?L*S
What action(s) will you take (and by when) to
prevent, reduce the impact of, or transfer the
risk of this occurring?
Who is
responsible for
following
through on
mitigation?
1 Stove not easily repaired. Life of stove can be altered.Designed as a one piece
system.2 1 2
Design pieces with a high potential of breaking
to be easily removed.Bri
2Does not meet emissions
goal.Cannot be used indoors. Insufficient stove design. 2 3 6
Ensure complete combustion of fuel is
obtained.Sam
3Does not meet high efficiency
goal.Stove needs to be redesigned. Insufficient stove design. 2 3 6 Heat transfer to pot must be maximized. Bri/Sam
4Insufficient interaction with
electrical team.
Stove does not meet needs or
specs.
Don't consult the other
team.2 2 4
Maintain consistent communication with the
other team.Dustin
5Heat output by stove is not
adjustable.
Stove will resemble current
stoves.
Did not take customer
needs into consideration.3 2 6
Ensure there is a means of adjusting the flow
(i.e. flap, fan).Bri
6 Inaccurate testing data.Insufficient redesign of areas in
need.
Data does not collect or
does not match last
year's.
3 2 6
Test until appropriate data is received.
Contact previous year group members if
issues continue to occur.
Brandon
7 Transient modeling.Forced induction may fail at
start-up/batter is drained.
Insufficient transient heat
transfer modeling.
Insufficient energy
storage capabilities
3 2 6
Rigorous transient heat transfer analysis.
Careful selection of heat transfer method.
Extensive testing.
Bri/Sam
8Casing conducts too much
heat.Jeopardize user safety Insufficient insulation 2 3 6
Testing of radiant and conductive heat transfer
in casing.Brandon
Risks Associated with System/Project Management
1-low likelihood/severity, 2-moderate likelihood/severity, 3-high likelihood/severity
ID Risk Item Effect Cause
Lik
elih
oo
d
Sev
erit
y
Imp
ort
an
ce
Action to Minimize Risk Owner
9 Material cost is too high.
Will not be able to be
manufactured or marketed in
Haiti.
Designed with resources
unavailable to Haitians.
Excessive component
costs.
3 2 6 Ensure materials are locally available in Haiti. Sam
10Stove too heavy and not
mobile.Cannot be marketed to vendors.
Overlooked customer
mobility need.2 3 6 Final product must be made of light materials Sam
11Cannot be manufactured
within Haitian abilities.Stove cannot be built in Haiti.
Complex components and
exotic manufacturing
methods (CNC).
2 3 6Consider means of production when in design
process.Sam
12Materials unavailable for
prototype stove.
Cannot build or test a stove
with the correct materials.
Materials are unavailable
to us or are ordered too
late. In sufficient
consideration given to
lead times.
2 3 6Do not delay in ordering the materials. Plan
ahead for lead times.Bri
Risks Associated with Materials and Manufacturing
1-low likelihood/severity, 2-moderate likelihood/severity, 3-high likelihood/severity
ID Risk Item Effect Cause
Lik
elih
ood
Sev
erit
y
Imp
ort
an
ce
Action to Minimize Risk Owner
13 TEG Overheat. Total system failure.Inadequate heat transfer
control.2 3 6
In-depth heat transfer analysis including FEM
and testing.
Marissa/
Dustin
14 Insufficient TEG cooling. Unsustainable operation.Heating up of TEG cold
side.2 2 4 In-depth heat transfer analysis of heat sink.
Marissa/
Dustin
15Inability to accurately model
TEG
Optimal power output not
realized.
TEG model changes with
heat and current. Load
resistance is effected.
2 2 4In depth analysis of the TEG unit as well as
modeling and testing.
Marissa/
Dustin
16Insufficient TEG power
production capability.Underpowered system.
Unable to meet required
temperature difference
across TEG. TEG
maximum output too
small
2 3 6In depth heat transfer analysis and testing of
TEG system.
Marissa/
Dustin
17
Temperature gradient across
hot side of the thermoelectric
unit.
Underpowered system.
Low conduction material
used. Insufficient analysis
done of the rod.
3 2 6Detailed heat transfer analysis of the rod
holding the TEG. Add an angle down the rod.Marissa
18Inaccurate benchmarking at
the thermoelectric region.
Insufficient data used as a
reference to redesign the
thermoelectric region
Thermocouples not
placed appropriately.3 2 6
Contact the old team to understand their
placement. Add more thermocouples in the
appropriate locations to collect better data.
Dustin/Brandon
Risks Associated with Thermoelectric (TEG)
1-low likelihood/severity, 2-moderate likelihood/severity, 3-high likelihood/severity
ID Risk Item Effect Cause
Lik
elih
oo
d
Sev
erit
y
Imp
ort
an
ce
Action to Minimize Risk Owner
19
Fan does not supply
sufficient supply of air.
Insufficient pressure drop
produced.
Force air system will not work/
reach combustion chamber.
Analysis of air flow was
incorrect. Poor modeling/
testing.
1 3 3Theoretical airflow analysis must include
potential losses. Marissa
20 Fan melts. Loss of airflow. System failure.
Fan placed too close to
stove. Underestimation of
stove temperature.
1 3 3Testing/benchmarking to correctly estimate
temperatures at proposed locations.
Dustin/
Brandon
21 Fan requires too much power
Fan will drain power from
battery. TEG will be unable to
provide enough power and
system will fail.
Poor fan selection or
design. Lack of
communication with
Electrical team.
1 2 2Contact electrical team to ensure selected fan
fits within their proposed system.Dustin
Risks Associated with Fan
1-low likelihood/severity, 2-moderate likelihood/severity, 3-high likelihood/severity
ID Risk Item Effect Cause
Lik
elih
oo
d
Sev
erit
y
Imp
ort
an
ce
Action to Minimize Risk Owner
22Heat conduction rod/ device
melting.
Possible loss of heat conduction
to TEG.
Inadequate analysis of
stove temperatures and
material properties.
2 3 6
Analyze stove operating temperatures. Select
materials to suit/withstand those
temperatures.
Marissa/Dustin
23
Heat conduction device
conducts too much/too little
heat.
Overheating of TEG or
insufficient power generation.
Inadequate heat transfer
analysis.2 3 6
Complete analysis of heat transfer
characteristics of device. Average stove
operating temps should be considered.
Marissa/Dustin
24Rod takes too long to heat
up.
Improper system function. Fan
may not operate at start-up.
Inadequate heat transfer
analysis. Inadequate
understanding of transient
temperatures in
combustion chamber.
2 2 4
Test stove to gain understanding of transient
temperatures. Complete transient modeling of
rod. Potentially move rod closer to fire/higher
up.
Dustin/
Brandon
Risks Associated with Conduction Rod
1-low likelihood/severity, 2-moderate likelihood/severity, 3-high likelihood/severity
Pugh Charts
Stove Team
CriteriaDirect
Contact
Skirt
(reference)
Combustion
Chamber
Size/Shape
Cost 0 0 0
Complexity + 0 -
Life-Span + 0 +
Durability - 0 +
Safety - 0 0
Efficiency - 0 0
Functionality - 0 0
Net Score -2 0 1
Use? No Yes Potentially
Provide Heat to Pot
CriteriaSwirl
Chamber
Fan
(reference)
Combustion
Chamber
Size/Shape
Cost + 0 +
Complexity - 0 -
Life-Span 0 0 0
Durability 0 0 0
Safety 0 0 0
Efficiency - 0 0
Functionality 0 0 0
Net Score -1 0 0
Use? No Yes Potentially
Provide Complete Combustion
Pugh Charts
TE Team
Criteria1 Fan
(reference)Multiple Fans
Compressed Air
Source
Cost 0 - -
Complexity 0 - -
Life-Span 0 0 -
Durability 0 0 -
Safety 0 0 -
Efficiency 0 - 0
Functionality 0 0 0
Net Score 0 -3 -5
Use? Yes Potentially No
Provide Air to Stove Fire
Criteria Fan Speed
Adjustable
Bypass
(reference)
Duct Sizing Throttling
Cost - 0 0 -
Complexity - 0 0 -
Life-Span 0 0 + -
Durability 0 0 0 -
Safety 0 0 + -
Efficiency + 0 + +
Functionality 0 0 0 +
Net Score -1 0 3 -3
Use? No Yes Yes No
Control Air Flow
CriteriaDirect
Contact
Extended
Metal Surface
(reference)
Contact Block Radiative
Cost + 0 + +
Complexity - 0 - -
Life-Span - 0 - 0
Durability 0 0 0 0
Safety 0 0 0 0
Efficiency + 0 + 0
Functionality - 0 - -
Net Score -1 0 -1 -1
Use? No Yes No No
Provide heat to hot side of TEG
Criteria Fan Control
Extended
Metal Surface
Sizing
(reference)
Insulate Around
TEG
Cost - 0 -
Complexity - 0 0
Life-Span 0 0 -
Durability 0 0 0
Safety - 0 0
Efficiency + 0 0
Functionality 0 0 +
Net Score -2 0 -1
Use? No Yes Potentially
Control temp at the hot side of TEG
CriteriaHeat Sink
(reference)
Forced
Convection
(reference)
Liquid Cooling
Cost 0 0 -
Complexity 0 0 -
Life-Span 0 0 -
Durability 0 0 0
Safety 0 0 0
Efficiency 0 0 +
Functionality 0 0 0
Net Score 0 0 -2
Use? Yes Yes No
Provide cooling to cold side TEG
CriteriaSizing of Heat
SinkFan Control Type of Liquid Used
Sizing of
Fan
(reference)
Cost 0 - - 0
Complexity 0 - - 0
Life-Span + 0 0 0
Durability + 0 0 0
Safety 0 - 0 0
Efficiency + + + 0
Functionality + 0 0 0
Net Score 4 -2 -1 0
Use? Yes No No Yes
Control temp at the cold side of TEG
Criteria
Modify
Extended
Surface
Direct Mount
Cost + +
Complexity + +
Life-Span + +
Durability 0 0
Safety + -
Efficiency + +
Functionality 0 0
Net Score 5 3
Use? Yes No
Control Temp Gradient Across TEG
Criteria
Extended
Surface
Sizing
Fan Control (or
Number of
Fans)
Extended Surface
Location within
Combustion
Chamber
Cost + 0 +
Complexity + - +
Life-Span + 0 +
Durability 0 0 0
Safety + - +
Efficiency + + +
Functionality 0 0 0
Net Score 5 -1 5
Use? Yes No Yes
Achieve Temp Difference within 20 min
Project Plan
Task Start Finish Predecessor Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10
Generate Preliminary Work Break Down 12/5/2011 12/9/2011 N/A
Plan for Weeks 3,4,5 12/5/2011 12/9/2011 N/A
Identify Customer Needs 12/5/2011 12/9/2011 N/A
Identify Engineering Specs 12/5/2011 12/9/2011 N/A
Generate Block Diagram/System
Configuration12/5/2011 12/9/2011 N/A
Identify Top 10 Risks 12/5/2011 12/9/2011 N/A
Test Rebar Stove 12/8/2011 12/8/2011 N/A
Test Rebar Stove Again 12/11/2011 12/11/2011 5
Test Last Years Stove 12/14/2011 12/14/2011 6
Learn about Post Processing 12/9/2011 1/1/2012 N/A
Read All Info 11/29/2011 1/1/2012 N/A
Present Planning Presentation 12/9/2011 12/16/2011 1,2,3,4
Generate Concept Development 12/9/2011 12/9/2011 3
Complete Peer Evaluation 1 12/15/2011 12/16/2011 N/A
Update and map Needs/Specs 12/15/2011 12/15/2011 2
Update Block Diagram 12/15/2011 12/15/2011 3
Update Risks/Mitigations 12/15/2011 12/16/2011 4
Generate Concept Matrix 12/15/2011 12/16/2011 11
Identify Key Functions 12/15/2011 12/16/2011 14
Evaluate/Generate Risk Assessment 12/17/2011 1/12/2012 11,12
Morphographical Chart/ Function
Breakdown Chart1/12/2012 1/13/2012
Update Block Diagram 1/12/2012 1/13/2012
Update Needs/ Specs Relationship 1/12/2012 1/12/2012 13
Present Practice System Design
Review1/13/2012 1/13/2012 10
Present System Design Review 1/20/2012 1/20/201218, 19, 10,
23
Complete any action items from system
design review and continue working on
flow diagrams
1/20/2012 6.7
Select Final Concept 11
Evaluate Risk Management 19
Develop and Follow Through with Test
Plans21
Create Bill of Materials 22
Present Detailed Design Review20, 22, 23,
24, 25
Work Breakdown Structure
Brandon Harbridge:
Project Manager,
Edge Guy
|
Sam Huynh: Lead
Engineer, Design
Specialist
/ | \
Marissa Blockus:
Team Facilitator,
3D Modeling
Dustin Tyler: Pairing
with EE Team (Fan
& Thermoelectrics)
Brianna
Stephenson- Vallot:
Testing Guru,
Purchaser
Stove Team
TEG Team
Future Plans
• Detailed heat transfer analysis of proposed heat harvesting
system to determine appropriate heat sink and conduction rod
sizing.
• Calculate all percentage heat losses within the stove system to
better optimize future designs.
• Analyzing the need for a change in combustion chamber
geometry.
• Test existing RIT stove to compare empirical data with
theoretical models and determine overall efficiency of the
system.
Questions?