team introduction

59

Upload: kelly-schwartz

Post on 03-Jan-2016

17 views

Category:

Documents


1 download

DESCRIPTION

Team Introduction. construction manager Kit Fleming. architect Xiang Liu. engineer Peng Li. owner Hans Verheij. Collaboration in Cyberspace. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Team Introduction
Page 2: Team Introduction

construction manager Kit Fleming

engineer Peng Li

architect Xiang Liu

owner Hans Verheij

Collaboration in Cyberspace

E X P R E S S T E A M 2 0 0 2 . C E E 2 2 2 . A E C G L O B A L T E A M C L A S S 2 0 0 2

Team Introduction

Page 3: Team Introduction

• Multi-disciplinary, collaborative teamwork in a building project

• Apply discipline knowledge and technologies.

• Knowledge management.

• The year is 2015

• A 3-story building

• Total fund, $5,500,000

• Maintain the footprint of the existing buildings

• A collection of rare cactus varieties about 16,000 square feet is protected by the “Society Environmental Desert Studies.”

Requirements

Project Goal

Page 4: Team Introduction

The campus map of Express University

The site map of new engineering school

Location

Express University is located in Phoenix, Arizona.

Climate/Weather

Annual average temperature is 61F.

Annual rainfall is 7.6 inch

Site Map

Page 5: Team Introduction

The site map of new engineering school

• Good use of materials

• Insulation Concerns

• Aesthetic taste to enrich environment

Analysis of Context

Page 6: Team Introduction

The site map of new engineering school

• Cactus, a typical plant in a desert environment

• A collection of rare cactus varieties between two footprints

• Other green plants on campus

Analysis of Landscape

Page 7: Team Introduction

A collection of cactus

Outside public space

Entrance to each footprint

Subdivided roads

Main roads

Analysis of Circulation

Page 8: Team Introduction

static dynamic

Design Concept

Page 9: Team Introduction

• static status

• regular geometric forms

• solid exterior look

• symmetrical layout

conversation

The silent conversation between desert and architecture

static

Design I Concept

Page 10: Team Introduction

The relationship of three layers of lines along X, Y, Z axis 21 3

2

Vertical circulation of the building

The first layer of lines is along the footprint.

The second layer of lines reveals the horizontal lines along X, Y axis.

The third layer of lines displays the relationship between horizontal and vertical lines.

1

3

Design I Analysis

Page 11: Team Introduction

Auditorium, technical supportSmall classroomInstructional lab

MEP

The First Floor Plan

-7’-1’ 0’

14’

27’

40’

58’

116’

58’

Design I Drawings & Models

Page 12: Team Introduction

Student office

SeminarBig classroomStorage

Computer machine roomSmall classroom

The Second Floor Plan

Winterthur Museum of Art Extension

West Elevation

Design I Drawings

N

Page 13: Team Introduction

Faculty officeFaculty loungeMEPChair’s office Secretaries Senior admin. office

The Third Floor Plan

0’

14’

27’

40’

Design I Drawings & Details

Page 14: Team Introduction

• Climate

39 °FLow temperature in Jan

105 °FHigh temperature in July

0.1”Annual snow fall

7.6”Average rain

61°FAverage temperature

• Soil conditions

Bearing capacity: 5ksf

No expansive soil

• Earthquake free

Site Issues

Earthquake Locations

Page 15: Team Introduction

Gravity Loads

Page 16: Team Introduction

Gravity load path——Steel Braced frames

Gravity load path——Two way slabs

Gravity Loads

Page 17: Team Introduction

Lateral Loads

Wind Zone Map

Page 18: Team Introduction

Lateral load path —— Concrete MRF

Lateral Loads

Lateral load path —— Braced frames

Page 19: Team Introduction

“Simplicity and functionality through early collaboration and exchange of ideas, inspirations and constraints.”

• Simple

• Regular

• Least intrusive structural system

• Constructability

• Lower budget

Design Goals

Page 20: Team Introduction

Option 1 -- Framing

Framing Plan

Laterally Braced Frame

• 2VLI20 composite deck with 2.5” light weight concrete slab

• Beam & Girder: full composite with slab

• 6”x6” HSS shape braces

• Column size: W14x68

• 10” concrete walls

Page 21: Team Introduction

Structural Options

• Composite floor system

• Laterally braced frame

• Cast-in-place concrete walls in elevator shaft

• Spread footings

Option 1: Option 2:• Concrete frame

• One-way slab

• Waffle slab in auditorium

Page 22: Team Introduction

Option 1

entrance

main entrance

First floor

Second floor

Third floor

Matching The Architectural Plan

Page 23: Team Introduction

Option 1 -- Sizes

Typical Sizes:

2VLI20, 2.5”

W18x119

W16x40

W21x48

W21x48

10” wall

Page 24: Team Introduction

Option 1 -- Foundation

Foundation Plan

Foundation Plan:

• Shallow foundation

• Spread footing under columns, with size of 8’x8’

• Strip footing under concrete walls, with a width of 4’

Page 25: Team Introduction

Option 1 -- Connection

Typical connections

Beam-Girder

Girder-Column webGirder-Column flange

Beam Splice

Page 26: Team Introduction

Option 2 -- Framing

1st Floor Framing Plan 2nd and 3rd Floor Framing Plan

Framing Plan——Concrete Frame:

Page 27: Team Introduction

Option 2 -- SizesTypical Element Sizes:

•One way slab

Depth: 7”

Steel: #3@6”

3@3=9"2.5" 2.5"2.5"

2.5"

16.5"#3@10"

Beam Column section

2@4=8"3"

3"

3"

12"#3@14"

3"

Beam Section Column Section

•Beams

14” x 21.5”

6#7 bars

#3@10” Ties

•Columns

18” x 18”

6#7 bars

#3@14” Ties

Page 28: Team Introduction

Option 2 -- Waffle Slab

Waffle Slab:

Waffle slab

•4.5” slab

•Total depth: 22.5”

•30”x30” voids

•6” ribs

Top View

Page 29: Team Introduction

Option 2 -- Foundation

A A

Raft Footing

A - A

Page 30: Team Introduction

Pros and Cons

Options Pros Cons

Steel Braced FrameSpread Footing

•Regular framing plan•Simple connection•Easy construction•Inexpensive•Simple foundation

• Large and heavy beams in auditorium

• Exterior brace conflicts with architect’s vision

• Possible differential settlement

Concrete FrameRaft Footing

• Pre-cast• No differential

settlement• More redundant in

LFR system

• More form work on waffle slab

• Thick footing and more reinforcement

• More expensive

Page 31: Team Introduction

Layout1

Design I Static

Material Lay down

Cactus

Crane

Wash Out/Pump Area

Material Lay Down

Parking

Trailers

Page 32: Team Introduction

Design I Concept

Alternative 1- Steel Brace Frame

Alternative 2- MRF Pre-Cast

Waffle Slab

Design I Static

Cost Analysis

$3,672,990 Total

$122/SF

$4,126,376 Total

$137/SF

Page 33: Team Introduction

Alternative 2- MRF Pre-Cast

Waffle SlabAlternative 1- Steel Brace

Frame

Design I StaticCost

Breakdown

$24,087 $255,264

$923,099

$580,683

$232,753

$549,857

$82,345

$713,715

$22,869$217,788

$445,503

$547,950

$278,553

$532,027

$81,570

$690,045

Page 34: Team Introduction

Design I Static

Alt 1- Steel

Start- 9/2/14

Occupancy- 7/11/16

Alt 2-MRF Pre-Cast

Occupancy June 3th ‘16

Occupancy July 11th ‘16

Foundation Complete 10/11/15

3rd Floor Steel Complete

11/5/16

Building Enclosed 1/14/16

Foundation Complete 10/16/15

Waffle Slab Complete 11/9/15

Building Enclosed 1/29/16

Schedule Comparison

Page 35: Team Introduction

Design I ConceptDesign I Static

Alternative 1- Steel Brace Frame

Alternative 2- MRF Pre Waffle Slab

Pros and Cons

•Fast Construction

•Cheap

•Simple Layout

Pro:

Con:•Site Access

•Heavy Beams in Auditorium

Pro:

Con:•Waffle Slab

•Expensive

•Uniform Members

•Speed of Erection

Page 36: Team Introduction

conversation

The echo of conversation between desert and architecture

dynamic

• Dynamic status

• Façade

• Colors

• Angled partition walls

• Irregular circulation

Design II Concept

Page 37: Team Introduction

21 3

Vertical circulation of the building

The first dynamic element is the form.

The second dynamic element is partition angled walls.

The third dynamic element is the color.

Three dynamic elements

2

1

3

Design II Analysis

Page 38: Team Introduction

why architects love colors ?

Chapel of St. Ignatius by Steven HollBerlin IBA housing by Zaha Hadid

Kamioka Town Hall by Arata Isozaki

Shukosha Building by Arata Isozaki

Sports Center Davos by Annette Gigon + Mike Guyer

Colors represent nature

Colors light the space

Colors may function as landmark

Colors have symbolic meaning

Colors lift spirit

Design II Color Coding

Page 39: Team Introduction

Auditorium, technical supportSeminar

Instructional lab

MEP

The First Floor Plan

Small classroom

West Elevation

38’ 76’

114’

Design II Drawings & Models

N

Page 40: Team Introduction

Big classroomStudent officeComputer machine room

The Second Floor Plan

SeminarMEPSmall classroom

0’

14’

27’

43’

-4’ -1’

Design II Drawings & Models

Page 41: Team Introduction

Faculty office

Chair’s office, Secretary, Senior admin. office

Faculty lounge

The Third Floor Plan

MEPSmall courtyard

0’

14’

27’

40’

-6’ -1’

Hamburg Music School A House by Morphosis

Design II Drawings & Details

Page 42: Team Introduction

Angled walls and colors imply movement

Sequential spatial layout

Design II Movement

Page 43: Team Introduction

Structural Options

• Composite floor system

• Steel MRF

• Concrete walls in elevator shaft

• Strip footings

Option 1: Option 2:• Cast-In-Place Concrete frame

• Flat slab

• Strip footing along exterior columns

Page 44: Team Introduction

Option 1 -- Framing

Moment Resistant Frame

W14x26

W16x50

W18x50

2VLI20, 2.5”

W14x68 column

Page 45: Team Introduction

Option 1

First floor

Second floor

Third floor

Matching The Architectural Plan

Page 46: Team Introduction

Option 1 -- Foundation

Foundation Plan

Foundation Plan:

• Shallow foundation

• Spread footing under interior columns, 8’x8’

• Strip footing under external columns, with a width of 4’

Page 47: Team Introduction

Option 2 -- Framing

Framing Plan

12”x18” beam

8” two way slab

10” concrete wall

14”x14” column

Page 48: Team Introduction

Option 2 -- Two-way slab

Slab

Column

Shear reinforcing

Flat slab with drop panel

Typical span: 25’x25’

Page 49: Team Introduction

Pros and Cons

Options Pros Cons

Steel MRF

• Prefabrication possible

• Inexpensive• Simple foundation, no

much excavation work

• Complex moment resistant connection

• Less space for MEP

Concrete Frame

• Large clear space for MEP system

• Less concrete and reinforcing

• Simple foundation

• Cast-In-Place concrete

• More form work

Page 50: Team Introduction

Layout 2

Cactus

Trailers

Crane

Material Lay Down

Material Lay down

Parking

Wash Out/Pump Area

Parking

Design II Dynamic

Page 51: Team Introduction

Alternative 1- MRF Steel Alternative 2- Flat Slabs

Cost Analysis

$3,715,073 Total

$125/SF

$3,846,427 Total

$129/SF

Design II Dynamic

Page 52: Team Introduction

Alternative 1- MRF Steel Alternative 2- Flat Slabs

Design II Dynamic

$23,936 $229,392

$628,224

$622,325

$284,511

$590,195

$85,345

$713,175

$23,817$228,901

$487,601

$628,205

$283,956

$581,075

$85,345

$709,609

Cost Breakdown

Page 53: Team Introduction

Schedule Comparison

Alt 1- MRF Steel

Alt 2-Flat Slabs

Start- 9/2/14

End- 7/29/15

Occupancy June 15th ‘15

Foundation Complete 10/16/14

3rd Floor Steel Complete 11/17/15

Building Enclosed

2/2/15

Structural System

Complete 12/15/14

Building Enclosed 2/19/15

Foundation Complete 10/17/14 Occupancy July29th ‘15

Design II DynamicSchedule

Comparison

Page 54: Team Introduction

Design I Concept

Pros and Cons

•Fast Construction

•Simple Foundation

Pro:

Con:•Difficult Connections

•More Expensive

Pro:

Con:•Longer Schedule

•Less Pre-Fabrication

•No Beams

•Site Access

Design II Dynamic

Alternative 1- MRF Steel Alternative 2- Flat Slabs

Page 55: Team Introduction

Decision Matrix

CONCEPT 1

+ PROS - CONS

A

E

C

• Regular framing

• Simple connection

• Large and heavy beams

• Unsymmetric

• Easy accessibility

• Big public open space

• Interesting details

• Unexciting interior space

• Less active in existing environment

• Simple connection/framing

• Cheap, Fast Schedule

• Waffle Slab, Expensive

• Site Access

Page 56: Team Introduction

Decision Matrix

CONCEPT 2

+ PROS - CONS

A

E

C

• Larger space for MEP

• Symmetric

• Irregular overhanging

• More form work

• More difficult connection

• Playing active role

• Concerning movements

• Interesting interior space

• No big open space

• Potential conflict to MEP system

• Site Access

• Smaller Beam Sizes

• More Expensive, Longer Construction

• Irregular 3rd Floor

Page 57: Team Introduction

Valuable Lessons

• Do not wait until last minutes!!!

• Team iteration is critical to achieve a better structural design.

• Be prepared before discussion.

Page 58: Team Introduction

Improvements

• More contact with owner and mentors.

• Faster and more frequent iteration.

• Learn more about other disciplines.

• Early sharing of information, even if incomplete

Page 59: Team Introduction

Thanks

Thanks to Mentors and Owner

Special thanks to all AEC classmates