Overview
Planning, organization, setup (Michael) Component procurement (Trey) Gyrobot construction (Rod) Base construction (Rob) Programming (Quy) Troubleshooting, future plans (Quy)
![Page 3: Team A ECE 496: Gyrobot Michael Tan Trey Moran Rod Petak Rob Slater Quy Quan](https://reader035.vdocuments.us/reader035/viewer/2022062805/5697bfaa1a28abf838c9a651/html5/thumbnails/3.jpg)
PlanningPersonal involvement: Michael
![Page 4: Team A ECE 496: Gyrobot Michael Tan Trey Moran Rod Petak Rob Slater Quy Quan](https://reader035.vdocuments.us/reader035/viewer/2022062805/5697bfaa1a28abf838c9a651/html5/thumbnails/4.jpg)
OrganizationPersonal involvement: Michael
Assigning tasks Supervising and providing support Weekly report Website
![Page 5: Team A ECE 496: Gyrobot Michael Tan Trey Moran Rod Petak Rob Slater Quy Quan](https://reader035.vdocuments.us/reader035/viewer/2022062805/5697bfaa1a28abf838c9a651/html5/thumbnails/5.jpg)
SetupPersonal involvement: Michael
Configuring software Testing servotogo breakout board
![Page 6: Team A ECE 496: Gyrobot Michael Tan Trey Moran Rod Petak Rob Slater Quy Quan](https://reader035.vdocuments.us/reader035/viewer/2022062805/5697bfaa1a28abf838c9a651/html5/thumbnails/6.jpg)
Component ProcurementPersonal involvement: Trey
Motor/Encoder Combo Shaft Encoder Bearings and Housing Shaft and Lock Collar
![Page 7: Team A ECE 496: Gyrobot Michael Tan Trey Moran Rod Petak Rob Slater Quy Quan](https://reader035.vdocuments.us/reader035/viewer/2022062805/5697bfaa1a28abf838c9a651/html5/thumbnails/7.jpg)
Motor-Encoder ComboPersonal involvement: Trey
Pittman 9237S011 24Vdc High
Torque/Weight Ratio
500 CPR encoder Tried and True
![Page 8: Team A ECE 496: Gyrobot Michael Tan Trey Moran Rod Petak Rob Slater Quy Quan](https://reader035.vdocuments.us/reader035/viewer/2022062805/5697bfaa1a28abf838c9a651/html5/thumbnails/8.jpg)
Shaft EncoderPersonal involvement: Trey
US Digital E3 Optical Encoder 2048 CPR Quadrature Type 5/8” Shaft Diameter Hole Option Tool Option Cable Option
![Page 9: Team A ECE 496: Gyrobot Michael Tan Trey Moran Rod Petak Rob Slater Quy Quan](https://reader035.vdocuments.us/reader035/viewer/2022062805/5697bfaa1a28abf838c9a651/html5/thumbnails/9.jpg)
Bearings and HousingPersonal involvement: Trey
Dayton-1F636/36/12 Ultra-High Molecular
Weight Polyethylene 5/8” Bore Very Low Friction Self Aligning Inexpensive
![Page 10: Team A ECE 496: Gyrobot Michael Tan Trey Moran Rod Petak Rob Slater Quy Quan](https://reader035.vdocuments.us/reader035/viewer/2022062805/5697bfaa1a28abf838c9a651/html5/thumbnails/10.jpg)
Shaft and Lock Collar Personal involvement: Trey
Shaft Purchased 5/8” x 36” Cut to 5/8” x 18”
Lock Collar Necessary to Lock the shaft in place Design Utilizes only one
![Page 11: Team A ECE 496: Gyrobot Michael Tan Trey Moran Rod Petak Rob Slater Quy Quan](https://reader035.vdocuments.us/reader035/viewer/2022062805/5697bfaa1a28abf838c9a651/html5/thumbnails/11.jpg)
Hardware construction(Machined Parts)
Personal involvement: Rod
Courtesy of:
Custom Equipment (Greenville, SC)
![Page 12: Team A ECE 496: Gyrobot Michael Tan Trey Moran Rod Petak Rob Slater Quy Quan](https://reader035.vdocuments.us/reader035/viewer/2022062805/5697bfaa1a28abf838c9a651/html5/thumbnails/12.jpg)
Hardware construction(Link)
Personal involvement: Rod
Drawing changes and omissions No extra holes No black anodize Motor mounting modification
Coupler Designed Join link to 5/8” shaft
![Page 13: Team A ECE 496: Gyrobot Michael Tan Trey Moran Rod Petak Rob Slater Quy Quan](https://reader035.vdocuments.us/reader035/viewer/2022062805/5697bfaa1a28abf838c9a651/html5/thumbnails/13.jpg)
Hardware construction(Flywheel)
Personal involvement: Rod
Drawing changes and omissions Steel Vs. Brass
Material DensityTotal Price
Motor Coupling Pressed fit vs. Set Screw fit
![Page 14: Team A ECE 496: Gyrobot Michael Tan Trey Moran Rod Petak Rob Slater Quy Quan](https://reader035.vdocuments.us/reader035/viewer/2022062805/5697bfaa1a28abf838c9a651/html5/thumbnails/14.jpg)
Base constructionPersonal involvement: Rob
Design Goals Stabilization Zero impedance of flywheel and link Safe for test phase
![Page 15: Team A ECE 496: Gyrobot Michael Tan Trey Moran Rod Petak Rob Slater Quy Quan](https://reader035.vdocuments.us/reader035/viewer/2022062805/5697bfaa1a28abf838c9a651/html5/thumbnails/15.jpg)
Base construction(Stabilization)
Personal involvement: Rob
Initial design Platform with extension C clamps
Final Design Smaller Platform Incorporating interface
wiring
![Page 16: Team A ECE 496: Gyrobot Michael Tan Trey Moran Rod Petak Rob Slater Quy Quan](https://reader035.vdocuments.us/reader035/viewer/2022062805/5697bfaa1a28abf838c9a651/html5/thumbnails/16.jpg)
Base construction(Low Impedance)
Personal involvement: Rob
Wire length Enough for test phase Keeping the wires neat
Problems and Solutions Wires were sporadic, tie wraps Wires caught end of platform extension, location
of wraps Gyrobot could malfunction, kill switch
![Page 17: Team A ECE 496: Gyrobot Michael Tan Trey Moran Rod Petak Rob Slater Quy Quan](https://reader035.vdocuments.us/reader035/viewer/2022062805/5697bfaa1a28abf838c9a651/html5/thumbnails/17.jpg)
Base construction(Final design)
Personal involvement: Rob
![Page 18: Team A ECE 496: Gyrobot Michael Tan Trey Moran Rod Petak Rob Slater Quy Quan](https://reader035.vdocuments.us/reader035/viewer/2022062805/5697bfaa1a28abf838c9a651/html5/thumbnails/18.jpg)
Programming(Control)
Personal involvement: Quy
Swing up control Balancing control
![Page 19: Team A ECE 496: Gyrobot Michael Tan Trey Moran Rod Petak Rob Slater Quy Quan](https://reader035.vdocuments.us/reader035/viewer/2022062805/5697bfaa1a28abf838c9a651/html5/thumbnails/19.jpg)
Programming(Swing up Control)Personal involvement: Quy
Non-collocated Collocated Sinusoidal
Not exceed +-10V at any angle Maximum effort near rest position Minimum effort through inverted position
![Page 20: Team A ECE 496: Gyrobot Michael Tan Trey Moran Rod Petak Rob Slater Quy Quan](https://reader035.vdocuments.us/reader035/viewer/2022062805/5697bfaa1a28abf838c9a651/html5/thumbnails/20.jpg)
Programming(Balancing Control)Personal involvement: Quy
PID (Proportional, Integral, & Derivative) PD (Proportional & Derivative)
Simplest control for inverted pendulum
![Page 21: Team A ECE 496: Gyrobot Michael Tan Trey Moran Rod Petak Rob Slater Quy Quan](https://reader035.vdocuments.us/reader035/viewer/2022062805/5697bfaa1a28abf838c9a651/html5/thumbnails/21.jpg)
Troubleshooting
Problem Mandrel has too
much friction
Solution Used polyethylene
bearings instead
Problem The motor encoder
was not providing correct output
Solution Found that GND
and +5 pins are switched
![Page 22: Team A ECE 496: Gyrobot Michael Tan Trey Moran Rod Petak Rob Slater Quy Quan](https://reader035.vdocuments.us/reader035/viewer/2022062805/5697bfaa1a28abf838c9a651/html5/thumbnails/22.jpg)
Current Progress
One week behind schedule More time will have to be spent on
programming to catch up to deadline
![Page 23: Team A ECE 496: Gyrobot Michael Tan Trey Moran Rod Petak Rob Slater Quy Quan](https://reader035.vdocuments.us/reader035/viewer/2022062805/5697bfaa1a28abf838c9a651/html5/thumbnails/23.jpg)
Future plans
Prepare balancing system for Bonus Day Optimize program for Competition Day