tbm presentation-bld 560
TRANSCRIPT
TUNNEL BORING MACHINE (TBM) METHOD OF
CONSTRUCTIONCASE STUDY :
KOWLOON SOUTHERN LINK RAILWAY
PREPARED BY :
FARRIS IZZAT BIN RAZALI2010229528RAMBA UGAK 2010413758NOR BAIZURA BINTI MAHMUD2010431768SAFWANAH BT MOHD SUKRI2010806896NUR AFIFAH BINTI ABDUL RAHIM2010460356
CHECKED BY:MDM.FARRAH NORRIZZAH YUSOFF
CLASS : AP226 4B
BACKGROUND PROJECT
PROJECT TITLE : CENTRAL KOWLOON ROUTE
NAME OF PROJECT PROPONENT : HIGHWAY DEPARTMENT , HKSAR GOVERNMENT
PROJECT DURATION : 2005-2009
COST OF PROJECT : HK$ 2 MILLIONS
LINE LENGTH : 3.8 KM
NO OF STATION : 3
TYPE : HEAVY RAIL
TBM : METHOD OF CONSTRCUTION
CRANE –TO ASSEMBLY THE
TBM
Component of TBM
This method starts by excavating a trench to provide a space for assembly the TBM components. The trench is reinforced with
diaphragm walls and steel struts.
Trench
The TBM components is placing down into the trench using a crane
TBM work under the flyover
Tunnel track under the flyover
Tunnel segment installation
During the drilling process, the assemble of components is doing at the same time.
Segment installation
While the drilling works are carried out near the building, surveys will be conducted to monitor for any settlement that
may occur in any nearest buildings during the work.
TBM work
Survey work
At the end of the point, the trench will be excavate similar with the start point as a receiver trench for the TBM. Upon arrival, the TBM is
then dismantled and brought upon to the surface
Lastly, the tunnel is done when all the appliances is completely installed.
PROBLEM DURING TUNNELING WORK
PROBLEM :
Noise & vibration nearest building
EFFECT :
Disruption to nearest premise
SOLUTION :
Strictly control the
noise & vibration
PROBLEM :
Geotechnical environment
1
2EFFECT :
Drilling different type of soil
(from hard rock to soft soil)
SOLUTION :
Using slurry types of TBM
VIDEO : TBM CONSTRUCTION
THANK YOU