TAXIWAY ALPHA REHABILITATION
Ashton B. Watson, P.E., C.M., ACE
Airport Engineer
![Page 2: TAXIWAY ALPHA REHABILITATION · •Closing 5/23 as a runway •Press Release and Council Manager Memo •Coordination with FAA, AAL, FedEx, UPS •7460 Permits •NCDENR. Value Engineering](https://reader035.vdocuments.us/reader035/viewer/2022071214/60429452549a305792295e01/html5/thumbnails/2.jpg)
Pavement Management Plan
![Page 3: TAXIWAY ALPHA REHABILITATION · •Closing 5/23 as a runway •Press Release and Council Manager Memo •Coordination with FAA, AAL, FedEx, UPS •7460 Permits •NCDENR. Value Engineering](https://reader035.vdocuments.us/reader035/viewer/2022071214/60429452549a305792295e01/html5/thumbnails/3.jpg)
Pavement Management Plan
![Page 4: TAXIWAY ALPHA REHABILITATION · •Closing 5/23 as a runway •Press Release and Council Manager Memo •Coordination with FAA, AAL, FedEx, UPS •7460 Permits •NCDENR. Value Engineering](https://reader035.vdocuments.us/reader035/viewer/2022071214/60429452549a305792295e01/html5/thumbnails/4.jpg)
Capital Investment Program
![Page 5: TAXIWAY ALPHA REHABILITATION · •Closing 5/23 as a runway •Press Release and Council Manager Memo •Coordination with FAA, AAL, FedEx, UPS •7460 Permits •NCDENR. Value Engineering](https://reader035.vdocuments.us/reader035/viewer/2022071214/60429452549a305792295e01/html5/thumbnails/5.jpg)
Consultant Selection and Negotiation
• RFQ for General Engineering Services
• Pool of firms to chose from
• Scope and Fee
• Geotech, Surveying, Utility locates, Design,
Bidding, Electrical, SRM, Construction
Admin, Materials Testing
• Independent Fee Estimate
• Negotiation
• Procurement and City Council Approval
• Above is about 9 month process
![Page 6: TAXIWAY ALPHA REHABILITATION · •Closing 5/23 as a runway •Press Release and Council Manager Memo •Coordination with FAA, AAL, FedEx, UPS •7460 Permits •NCDENR. Value Engineering](https://reader035.vdocuments.us/reader035/viewer/2022071214/60429452549a305792295e01/html5/thumbnails/6.jpg)
Design Schedule
![Page 7: TAXIWAY ALPHA REHABILITATION · •Closing 5/23 as a runway •Press Release and Council Manager Memo •Coordination with FAA, AAL, FedEx, UPS •7460 Permits •NCDENR. Value Engineering](https://reader035.vdocuments.us/reader035/viewer/2022071214/60429452549a305792295e01/html5/thumbnails/7.jpg)
Intersection Geometry of TWY A,G,R
*Hot Spot 1
![Page 8: TAXIWAY ALPHA REHABILITATION · •Closing 5/23 as a runway •Press Release and Council Manager Memo •Coordination with FAA, AAL, FedEx, UPS •7460 Permits •NCDENR. Value Engineering](https://reader035.vdocuments.us/reader035/viewer/2022071214/60429452549a305792295e01/html5/thumbnails/8.jpg)
Other Design Considerations
• Shoulders
• Asphalt vs. Concrete
• Future Concourse and Ramp Expansion
• Underdrains
• Lighting systems
• Regulator at East Lighting Vault
• 2.5% Longitudinal Taxiway Grade
• Modification of Standards
• Oil-Water Separators
![Page 9: TAXIWAY ALPHA REHABILITATION · •Closing 5/23 as a runway •Press Release and Council Manager Memo •Coordination with FAA, AAL, FedEx, UPS •7460 Permits •NCDENR. Value Engineering](https://reader035.vdocuments.us/reader035/viewer/2022071214/60429452549a305792295e01/html5/thumbnails/9.jpg)
Other Design Considerations
![Page 10: TAXIWAY ALPHA REHABILITATION · •Closing 5/23 as a runway •Press Release and Council Manager Memo •Coordination with FAA, AAL, FedEx, UPS •7460 Permits •NCDENR. Value Engineering](https://reader035.vdocuments.us/reader035/viewer/2022071214/60429452549a305792295e01/html5/thumbnails/10.jpg)
Construction Safety and Phasing Plan
![Page 11: TAXIWAY ALPHA REHABILITATION · •Closing 5/23 as a runway •Press Release and Council Manager Memo •Coordination with FAA, AAL, FedEx, UPS •7460 Permits •NCDENR. Value Engineering](https://reader035.vdocuments.us/reader035/viewer/2022071214/60429452549a305792295e01/html5/thumbnails/11.jpg)
Safety Risk Management (SRM) Workshop
• Foreign Object Debris/Damage
• Contractor Vehicle Deviation/Loss of Situational
Awareness
• Pedestrian Loss of Situational
Awareness/Pedestrian Deviation
• Pilot Loss of Direction/Pilot Confusion
• Debris damage tow workers and equipment
caused by jet blast
• Head-to-Head taxiing aircraft at AAL Maintenance
Ramp
![Page 12: TAXIWAY ALPHA REHABILITATION · •Closing 5/23 as a runway •Press Release and Council Manager Memo •Coordination with FAA, AAL, FedEx, UPS •7460 Permits •NCDENR. Value Engineering](https://reader035.vdocuments.us/reader035/viewer/2022071214/60429452549a305792295e01/html5/thumbnails/12.jpg)
Safety Risk Management (SRM) Workshop
![Page 13: TAXIWAY ALPHA REHABILITATION · •Closing 5/23 as a runway •Press Release and Council Manager Memo •Coordination with FAA, AAL, FedEx, UPS •7460 Permits •NCDENR. Value Engineering](https://reader035.vdocuments.us/reader035/viewer/2022071214/60429452549a305792295e01/html5/thumbnails/13.jpg)
Safety Risk Assessment (SRA) Workshop
![Page 14: TAXIWAY ALPHA REHABILITATION · •Closing 5/23 as a runway •Press Release and Council Manager Memo •Coordination with FAA, AAL, FedEx, UPS •7460 Permits •NCDENR. Value Engineering](https://reader035.vdocuments.us/reader035/viewer/2022071214/60429452549a305792295e01/html5/thumbnails/14.jpg)
Public Contact
• Closing 5/23 as a runway
• Press Release and Council Manager Memo
• Coordination with FAA, AAL, FedEx, UPS
• 7460 Permits
• NCDENR
![Page 15: TAXIWAY ALPHA REHABILITATION · •Closing 5/23 as a runway •Press Release and Council Manager Memo •Coordination with FAA, AAL, FedEx, UPS •7460 Permits •NCDENR. Value Engineering](https://reader035.vdocuments.us/reader035/viewer/2022071214/60429452549a305792295e01/html5/thumbnails/15.jpg)
Value Engineering
• Original Estimate = $12,534,360
• Bid Opening = $13,454,449
• Negotiated Price = $12,823,949 (2.3% over)
• Value Engineering Items:
• Contractor Retain Millings
• Cement-Treated Base instead of P-403
• Liquid AC type: PG64-22 instead of PG76-22
• Removal of Glasgrid Interlayer
![Page 16: TAXIWAY ALPHA REHABILITATION · •Closing 5/23 as a runway •Press Release and Council Manager Memo •Coordination with FAA, AAL, FedEx, UPS •7460 Permits •NCDENR. Value Engineering](https://reader035.vdocuments.us/reader035/viewer/2022071214/60429452549a305792295e01/html5/thumbnails/16.jpg)
UPS Change Order
![Page 17: TAXIWAY ALPHA REHABILITATION · •Closing 5/23 as a runway •Press Release and Council Manager Memo •Coordination with FAA, AAL, FedEx, UPS •7460 Permits •NCDENR. Value Engineering](https://reader035.vdocuments.us/reader035/viewer/2022071214/60429452549a305792295e01/html5/thumbnails/17.jpg)
CLT Airport: Building an Airport for the Future!