tanzania north west grid (400 kv nyakanazi kigoma ... · tanesco’s energy production in...

43
AFRICAN DEVELOPMENT BANK TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA TRANSMISSION LINE) RDGE/PESD/COTZ DEPARTMENTS July 2018 Public Disclosure Authorized Public Disclosure Authorized

Upload: others

Post on 13-Apr-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

AFRICAN DEVELOPMENT BANK

TANZANIA

NORTH WEST GRID

(400 KV NYAKANAZI – KIGOMA TRANSMISSION LINE)

RDGE/PESD/COTZ DEPARTMENTS

July 2018

P

ubli

c D

iscl

osu

re A

uth

ori

zed

P

ubli

c D

iscl

osu

re A

uth

ori

zed

Page 2: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

TABLE OF CONTENTS

CURRENCY EQUIVALENTS - June 2018 ............................................................................ i

FISCAL YEAR .......................................................................................................................... i

WEIGHTS AND MEASURES ................................................................................................. i

ACRONYMS AND ABBREVIATIONS ................................................................................ ii

PROJECT INFORMATION SHEET......................................................................................iii

PROJECT SUMMARY ............................................................................................................ v

ANTICIPATED RESULTS BASED LOGICAL FRAMEWORK ......................................... vii

PROJECT IMPLEMENTATION SCHEDULE ..................................................................... ix

1. STRATEGIC THRUST AND RATIONALE ................................................................... 1 1.1 Project Linkages with Country Strategy and Objectives ............................................ 1

1.2 Rationale for Bank Involvement ................................................................................. 1

1.3 Donor Coordination..................................................................................................... 2

2. PROJECT DESCRIPTION ................................................................................................ 3 2.1 Project Objectives and Components ........................................................................... 3

2.2 Technical Solution Adopted and Alternative Considered ........................................... 4

2.3 Project Type ................................................................................................................ 5

2.4 Project Cost and Financing Arrangements .................................................................. 5

2.5 Project’s target and population .................................................................................... 7

2.6 Bank Group Experience and Lessons Reflected in Project Design ............................ 7

2.7 Key Performance Indicators ........................................................................................ 8

3. PROJECT FEASIBILITY ................................................................................................. 9 3.1 Financial and Economic Performance......................................................................... 9

3.2 Environmental, Social Impact and Climate Change ................................................ 12

4. IMPLEMENTATION ...................................................................................................... 14 4.1 Implementation Arrangements .................................................................................. 14

4.2 Procurement Arrangements ....................................................................................... 15

4.3 Financial Management Arrangements ...................................................................... 16

4.4 Monitoring and Evaluation........................................................................................ 17

4.5 Governance................................................................................................................ 17

4.6 Sustainability ............................................................................................................. 18

4.7 Risk Management ...................................................................................................... 18

4.8 Knowledge Building and Inclusivity......................................................................... 18

5. LEGAL INSTRUMENTS AND AUTHORITY ............................................................. 19 5.1 Legal Instrument ....................................................................................................... 19

5.2 Conditions associated with the Bank’s proposed Financing ..................................... 19

5.3 Other Conditions ....................................................................................................... 19

5.4 Undertakings ............................................................................................................. 20

5.5 Compliance with the Bank’s Policy .......................................................................... 20

6. RECOMMANDATIONS ................................................................................................ 20

Page 3: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

APPENDIX I: COMPARATIVE SOCIO-ECONOMIC INDICATORS

APPENDIX II: MAP OF PROJECT AREA (NYAKANAZI – KIGOMA; 280 KM)

APPENDIX III: ENERGY BRIEF

APPENDIX IV: MAPPING THE COUNTRY DP FOCUS AREAS VS FYDP II

APPENDIX V: JUSTIFICATION OF ADB FINANCING OF MORE THAN 50%0

APPENDIX VI: ADB PORTFOLIO

APPENDIX VII: HIGHLIGHTS ON TANESCO FINANCIAL SUSTAINABILTIY

ACTION PLAN

APPENDIX VIII: PROJECT RISKS

Page 4: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

i

CURRENCY EQUIVALENTS - June 2018

1 UA = 1.42 USD

1 UA = 3203.88 TSH

FISCAL YEAR

1 July – 30 June

WEIGHTS AND MEASURES

1 metric tonne = 2204 pounds (lbs)

1 kilogramme (kg) = 2.200 lbs

1 metre (m) = 3.28 feet (ft)

1 millimetre (mm) = 0.03937 inch (“)

1 kilometre (km) = 0.62 mile

1 hectare (ha) = 2.471 acres

m Metre KOE kilogram of oil equivalent

cm centimetre = 0.01 metre kV kilovolt = 1,000 volts

mm millimetre = 0.001 metre kVA kilovolt ampere (1,000 Va)

km kilometre = 1,000 metres kW kilowatt = 1,000 Watts

m² square meter GW gigawatt (1,000,000 kW or 1,000

MW)

cm² square centimetre MW megawatt (1,000,000 W or 1,000 kW

km² square kilometre = 1,000,000

m² kWh kilowatt hour (1,000 Wh)

ha hectare = 10,000 m² MWh megawatt hour (1,000 kWh)

t (t) metric tonne (1,000 kg) GWh gigawatt hour (1,000,000 kWh)

Page 5: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

ii

ACRONYMS AND ABBREVIATIONS

AC Alternating Current MoEM Ministry of Energy & Minerals

ACFA Accelerated Co-financing Facility for Africa MoFP Ministry of Finance and Planning

AfDB African Development Bank MTR Medium Term Review

ADF African Development Fund NAPA National Adaptation Programme for Action

AFD Agence Française De Développement NEMC National Environment Management Council

AfIF

APP

African Investment Facility

Annual Procurement Plan

NWG North West Grid

BoQs Bills of Quantities NELSAP Nile Equatorial countries Subsidiary Action

Program

BPS Borrower’s Procurement System NPV Net present value

CAG Controller & Auditor General O&M Operational & Maintenance

CDM Clean Development Mechanism PAR Project Appraisal Report

CPAR Country Procurement Assessment Report PAPs Project Affected Persons

CPIA Country Policy and Institutional Assessment PCR Project Completion Report

CRB Contractor Registration Board PFM Public Financial Management

CSRF Corporate Social Responsibility Fund PIDA Programme for Infrastructure Development in

Africa

CSP Country Strategy Paper PIT Project Implementation Teams

DP

DRC

Development Partner

Democratic Republic of Congo

RMC Regional Member Country

EAPP Eastern Africa Power Pool RoW Right of Way

EDCF Korea Economic Development Co-operation Fund PE Procurement Entity

EDPG

EIB

EIRR

Energy Development Partner Group

European Investment Bank

Economic Rate of Return

PMP Procurement Methods and Procedure

ENPV Economic Net Present Value PMU Procurement Management Unit

EoI Expression of Interest PRCA Procurement Risk & Capacity Assessment

EPC Engineering Procurement & Construction PP Procurement Plan

PPAs Power Purchase Agreement (s)

ERB Engineers Registration Board PPA Public Procurement Act

E&S Environment and Social PPAA Public Procurement Appeals Authority

ESI Electricity Supply Industry PPPD Public Procurement Policy Division

ESIA Environmental and Social Assessment PPRA Public Procurement Regulatory Authority

ESMP Environmental and Social management plan PPRR Project Procurement Risk Rating

EWURA Energy and Water Utilities Regulatory Authority PSPTB Procurement and Supplies Professionals and

Technicians Board

EU European Union

FC Foreign Currency PSA Power Sales Agreement

FIRR Financial Internal rate of return PURA Petroleum Upstream Regulatory Authority

FM Financial Management QCBS Quality and Cost based Selection

FNPV Financial Net Present Value RISP Regional Integration Strategy Paper

FY Financial Year REA Rural Energy Agency

FYDP Five Year Development Plan RAP Resettlement Action Plan

GPD Gross Domestic Product RfP Request for Proposal

GHG Greenhouse Gas Emissions RMC

SAPP

Regional Member Country

Southern African Power Pool

GPN General Procurement Notice SBD Standard Bidding Document

GPSA Government Procurement Service Agency SEP Stakeholder Engagement Plan

GoT Government of the United Republic of Tanzania SIDA

SME

Swedish International Development Agency

Small-Medium Enterprises

HFO Heavy Fuel oil SPN Specific Procurement Notice

Hi-5s High Fives SREP Scaling-Up Renewable Energy Program

HPP Hydropower plant TANESCO Tanzania Electric Supply Company Limited

INDC Intended Nationally Determined Contributions TDV Tanzania Development Vision

JICA Japan International Cooperation Agency TYS Ten Year Strategy 2013 - 2022

LC Local Currency ToRs Terms of Reference

MD Managing Director UA Units of Accounts

MDB Multinational Development Bank UK DFID

UNCITRAL

United Kingdom Department for International

Development

United National Commission on International

Trade Law

MoE Ministry of Energy USAID

WB

United States Agency for International

Development

World Bank

Page 6: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

iii

PROJECT INFORMATION SHEET

CLIENT’S INFORMATION

BORROWER United Republic of Tanzania (GoT)

EXECUTING AGENCY Ministry of Energy (MoE)

IMPLEMENTING AGENCY Tanzania Electric Supply Company Limited (TANESCO)

FINANCING PLAN

Sources Amount

(USD million)

Instrument

African Development Bank (ADB) 123.39 Loan

South Korea Economic Development Co-

operation Fund (EDCF) 44.19 Loan

Government of the United Republic of

Tanzania (GoT) 18.54 Counterpart

Total Financing 186.12

TIME FRAME – KEY MILESTONES

Concept Note Approval September 2017

Board Approval July 2018

Loan signing September 2018

Launching October 2018

Effectiveness December 2018

Closing Date December 2023

Project Completion Report June 2024

ADB KEY FINANCING INFORMATION

Loan Currency United-States Dollars (USD)

Loan Type Fully Flexible Loan

Tenor 24 years inclusive of Grace Period

Grace period 5 years

Average Loan Maturity* 14.75 years

Repayments Equal and consecutive semi-annual payments after Grace Period

Interest Rate Base Rate +Funding Cost Margin+ Lending Margin + Maturity

Premium

This Interest Rate will be floored to zero

Base Rate

Floating Base Rate ( 6-month USD LIBOR reset each 1st February

and 1st august)

A free option to fix the Base Rate is available

Funding Cost Margin The Bank funding cost margin as determined each 1st January and

1st July and applied to the Base Rate each 1st February and 1st

August

Lending Margin 80 basis points (0.8%) per annum

Maturity Premium 10 basis points (0.1%) per annum

Front-end fees 0.25% of the total amount of the Loan shall be due on entry into

force of the Loan, and payable at the earliest of, (i) up to 60 days

Page 7: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

iv

from the Date of entry into force of the Loan, or (ii) at the time of

first disbursement.

Commitment fees 0.25% per annum of the undisbursed amount. Commitment fees

start accruing 60 days after signature of the loan agreement and are

payable on Payment Dates

Option to convert the Base

Rate**

In addition to the free option to fix the floating Base Rate, the

Borrower may reconvert the fixed rate to floating or refix it on part

or full the disbursed amount.

Transaction fees are payable.

Option to cap or collar the

Base Rate**

The Borrower may cap or set both cap and floor on the Base Rate

to be applied on part or the full-disbursed amount.

Transaction fees are payable.

Option to convert loan

currency**

The Borrower may convert the loan currency for both undisbursed

and disbursed amounts in full or part to another approved lending

currency of the Bank.

Transaction fees are payable.

Page 8: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

v

PROJECT SUMMARY

Project

Overview

The North West Grid (NWG) 400 kV Nyakanazi - Kigoma Transmission

Line Project comprises: (i) Construction of a 280 km power line running

from Nyakanazi to Kigoma in the northwestern part of Tanzania; (ii)

Extension of Nyakanazi substation & construction of a new substation at

Kidahwe near Kigoma town; (iii) Integration of existing Kigoma &Kasulu

33 kV distribution networks to the main grid including supply of last-mile

connection materials to serve at-least 10,000 potential consumers in Kigoma

Region; (iv) Consultancy Services; (v) Audit Services and (vi)

Compensation and/or resettlement of project affected persons.

The Project’s overall cost is estimated at USD 186.12 million to be covered

by the African Development Bank (AfDB herein referred to as the Bank –

using ADB loan), South Korea Economic Development Co-operation Fund

(EDCF) and the Government of the United Republic of Tanzania (GoT)

contributing USD 123.39 million (i.e. 66%), USD 44.19 million (i.e. 24%)

and USD 18.54 million (i.e. 10%) respectively. The Tanzania Electric

Supply Company Limited (TANESCO) will be the Implementing Agency

on behalf of GoT and the Project is expected to be completed in 2023.

The upstream main grid extensions to Nyakanazi have already commenced

under two transmission line projects namely: (i) 220 kV Regional Rusumo

hydropower - Nyakanazi financed by the Bank and (ii) 220 kV Geita –

Nyakanazi jointly funded by Agence Française de Développement (AFD)

and KfW Development Bank. The expected commissioning date of the

upstream grid extensions is 2020.

The Project (i.e. Nyakanazi – Kigoma of 280 km) will form part of the

proposed 1,080 km NWG stretching from Nyakanazi (via Kigoma, Mpanda,

Sumbawanga and Tunduma) to Mbeya. The World Bank (WB), in

conjunction with AFD, is handling the grid extension from Iringa to Mbeya

including Tunduma – Sumbawanga which was approved by the WB Board

on 18th June 2018.

The remaining portion (i.e. Kigoma - Mpanda - Sumbawanga) of the NWG

is still at preparatory phase by the Bank and TANESCO.

Needs

Assessment

The Project will provide affordable and reliable main grid access to already

electrified but isolated grids and, therefore, replace the expensive diesel-

based power generating plants in Kigoma and Kasulu towns. In addition, the

Project will evacuate power from the proposed renewable generation plants

in Kigoma Region including the multinational Rusumo hydropower plant

(HPP).

In line with the Government’s Five Year Development Plan (FYDP II)

2016/17 - 2020/21, the Project will provide transmission line infrastructure

to address bottlenecks in the energy sector in order to promote socio-

economic transformation and nurture industrialization.

Page 9: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

vi

Project

Outcomes

The Project will contribute to: (i) improved power supply through provision

of main grid electricity (ii) lower operation & maintenance {O&M} costs of

TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation

and (iv) reduction in greenhouse gas {GHG} emissions.

Bank’s

added value

The Bank is one of the Development Partners (DPs) playing a leading role

in financing infrastructure projects at both national and region level with

positive impacts on the socio-economic development of the country.

Therefore, the Nyakanazi - Kigoma Project is expected to make a similar

contribution towards the economic transformation of Tanzania.

In particular, the Project will provide a backbone fostering electricity access

in Kigoma Region whose household connectivity rate is less than 20% as

per the Energy Access Situation Report, 2016 of mainland Tanzania.

Also, the Bank has mobilised additional funding from EDCF (estimated at

USD 44.19 million and covering 24% of the Project overall costs) to

implement the transmission line associated to substations at Nyakanazi and

Kigoma.

Institutional

development

and

knowledge

building

The proposed Project is in line with the ongoing Bank’s energy interventions

in Tanzania. Therefore, lessons learnt in reference to (i) advance contracting

(ii) co-financing (iii) last-mile connectivity and (iv) realistic implementation

schedule, among other things, have been incorporated into the proposed

Nyakanazi - Kigoma Project.

Furthermore, in line with other Bank-funded energy operations, all

Engineering Procurement & Construction (EPC) contracts as well as

Consultancy services under the Project shall include specific provisions for

capacity building offering customised training to Operational staff covering

technical, legal, commercial and safeguard aspects in regard to new Plant &

Equipment.

Lastly, the skills and knowledge gained from Nyakanazi - Kigoma Project

will be used by the Bank to inform future investment lending operations of

the NWG Kigoma - Mpanda - Sumbawanga transmission line as well as

other similar projects in Regional Member Countries (RMCs). The “lessons

learnt’ will be disseminated through sharing findings of Supervision

Missions and the Project Completion Report (PCR).

Page 10: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

vii

ANTICIPATED RESULTS BASED LOGICAL FRAMEWORK

Country and project name: Tanzania; North West Grid (400 kV Nyakanazi – Kigoma Transmission Line)

Purpose of the project: To improve supply, reliability and affordability of electricity in Kigoma Region by providing main grid access and consequently contributing to socioeconomic transformation of Tanzania.

RESULTS CHAIN

PERFORMANCE INDICATORS

MEANS OF VERIFICATION RISKS/MITIGATION MEASURES Indicator

(including CSI)

Baseline

(2016) Target (2024)

IMP

AC

T

Increased access to electricity in northwestern

Tanzania

Households connected to electricity

in Kigoma Region

Female-headed households connected

to electricity in Kigoma Region

Demand growth in Kigoma Region

16.2%

17.2%

11.25 MW

20%

20%

38 MW

National Bureau of Statistics reports

(e.g. Energy Access Situation Reports);

Country Strategic Paper 2021 – 2025;

EWURA & TANESCO Annual

Reports;

Power System Master Plan (Updates).

Risk: At Country level, TANESCO’s financial

sustainability remains a concern and may jeopardize

provision of adequate, reliable and affordable electricity

access.

Mitigation: The Bank and other DPs will continue

engagement with GoT through policy dialogue to support

power sector reforms to improve TANESCO’s financial

performance.

OU

TC

OM

ES

Outcome 1

Improved power supply through provision of main

grid reliable and affordable electricity

Availability of supply 69% 95%

TANESCO & EWURA Annual reports;

Project Completion Report (PCR);

TANESCO Audited Accounts;

Consultant’s supervision reports;

Supervision Mission Reports.

Risk:

TANESCO Financial Management issues,;

Protracted procurement processes;

Poor performance of EPC contractors;

Delay in release of counterpart funds;

Delay in implementation of upstream infrastructure.

Mitigation:

Appoint a qualified Accountant as part of the Project

Implementation Team (PIT);

Use of Advance Contracting;

Raise performance guarantees;

Engage GoT early enough to ensure timely

availability of funds and that upstream transmission

infrastructure is completed on time.

Outcome 2

Lower energy production costs

Annual financial resources spent on

O&M of diesel-power plants in

Kigoma & Kasulu towns

~USD 9.44

million

~ 0

Outcome 3

Enhance job creation

Number of temporary and permanent

jobs created

0 600 (temporary) & 50

(permanent)

disaggregated by

gender and at-least

33% allocated to

women.

Outcome 4

Reduction in GHG emissions

GHG Emissions from TANESCO

Kigoma/Kasulu diesel generation

plants

~ 18,895 tons

per annum

~ 0

Page 11: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

viii

Outcome 5

Support development of renewable energy

Number of renewable energy power

facilities installed

0 2 TANESCO & EWURA Annual

Reports;

Power Purchase Agreements

(PPAs) signed

Risk:

Delay project implementation;

Complex & lengthy PPA negotiations.

Mitigation

Appointment of skilled PIT;

TANESCO has appropriate skills to

handle PPAs;

Additional support from Africa Legal

Support Facility.

OU

TP

UT

S

Component A: 400 kV Nyakanazi - Kigoma

transmission line

- Length (in km) 0 280 Consultant’s Supervision Reports;

Bank Supervision Mission Reports;

Bank Disbursement Statements;

TANESCO Financial Statements;

TANESCO Annual Reports;

PCR.

Risk: Project completion delay and cost overruns.

Mitigation 1: Closely supervise the Project (through

Bank Task Team, Project Supervision Consultant and

Project Implementation Team).

Mitigation 2: Implement the Project through EPC

contracts to ensure minimum variance in costs

Component B: 400/220/132/33 Substations - Number of new substations

0

2

Component C: Distribution Network -Number of last-mile connections;

-Length (in km) of Medium

Voltage network;

-Length (in km) of LV lines;

-Number of ready boards

32,176

465

1,202

0

42,176

535

1302

7,500

Component D: Consultancy Services -Number supervision reports

(Nyakanazi - Kigoma)

-Number of Design Studies

(Kigoma - Mpanda -

Sumbawanga)

0

0

10

1

Component E : Annual Audit Number of Audit Reports 0 5

Component F: Compensation & Resettlement - Acres affected

- No. of PAPs

0

0

3,937

2,548

Project Cost

1. Component A : USD 106.96 2. Component B : USD 44.19 3. Component C : USD 7.88 4. Component D : USD 8.35 5. Component E : USD 0.20 6. Component F : USD 18.54 7. Overall Cost : USD 186.12

Page 12: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

ix

PROJECT IMPLEMENTATION SCHEDULE

N

o

Description Year 2017 2018 2019 2020 2021 2022 2023 2024

Quarter 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

1 Concept Note Approval

2 Appraisal

3 Advance Contracting

4 Board Approval

5 Effectiveness

6 Conclude Selection of

Consultants

7 Bid Preparation

8 Bidding period

9 Evaluation and Contract Award

10 Mobilization and Construction

11 Commissioning

12 Operational Acceptance

13 Closing Date

14 Preparation of PCR

Page 13: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

1

REPORT AND RECOMMENDATION OF MANAGEMENT TO THE BOARD OF DIRECTORS

ON PROPOSED ADB LOAN TO THE UNITED REPUBLIC OF TANZANIA FOR THE NORTH

WEST GRID (400 kV NYAKANAZI – KIGOMA TRANSMISSION LINE) PROJECT

Management submits the following Report and Recommendations on the proposed ADB loan of USD

123.39 million to the United Republic of Tanzania (GoT) for the Northwest Grid (NWG) 400 kV Nyakanazi

- Kigoma Transmission Line Project.

1. STRATEGIC THRUST AND RATIONALE

1.1 Project Linkages with Country Strategy and Objectives

1.1.1 The Bank’s Tanzania Country Strategic Paper (CSP) 2016 - 2020 is based on two strategic pillars

namely (i) infrastructure development and (ii) strengthening governance and accountability. In regard to

infrastructure development, the Bank’s interventions are focused on improving both domestic and regional

transport connectivity as well as access to electricity. The NWG is one of the interventions mentioned in

the CSP to meet the country’s development goal of enhancing energy transmission to increase electricity

access. Also, the CSP is aligned with the Country’s national development strategies of achieving sustainable

economic transformation as per the Tanzania Development Vision (TDV) 2025. One of the strategies of

achieving the Vison is through Infrastructure Development comprising, among other things, investment in

energy, water and telecommunications. The Vision 2025 is implemented through multiple medium term

plans.

1.1.2 The current Five Year Development medium term Plan II (FYDP II 2016/17 – 2020/21) under the

theme “Nurturing Industrialization for Economic Transformation and Human Development” takes note that

energy infrastructure development is crucial for promoting socio-economic transformation1 and obtaining

a Gross Domestic Product (GDP) growth rate commensurate with a middle-income country. The NWG

project is mentioned in FYDP II and the Power System Master Plan (PSMP Update 2016) as one of the

important infrastructure projects to provide reliable power supply crucial for industrial development in

Kigoma, Katavi, Rukwa and Mbeya regions. Also, the NWG Project will provide one of the avenues

through which the country will implement some of its energy-related Intended Nationally Determined

Contributions (INDCs) for reducing greenhouse gas emissions (GHG) in line with the 2015 United Nations

Climate Change Conference (i.e. COP 21/CMP 11).

1.2 Rationale for Bank Involvement

1.2.1 The rationale for the Bank’s involvement is to: (i) complement the ongoing Bank-funded 220 kV

Rusumo - Nyakanazi interconnection project to provide additional evacuation facilities for the 80 MW

Regional Rusumo Falls HPP2 and (ii) connect the isolated Kigoma/Kasulu grids to replace the associated

expensive diesel-based plants. A map of the Project area (i.e. Nyakanazi – Kigoma transmission line) is

shown in Appendix II including Rusumo HPP.

1.2.2 By replacing the expensive diesel-based power plants in Kigoma/Kasulu with a cleaner energy mix

from the main grid, the Project supports the Bank’s Climate Change Action Plan (2016 – 2020) to mitigate

GHG emissions as well as the Bank’s Energy Sector Policy (2012) whose goals are: (i) to support Regional

Member Countries {RMCs} in efforts to provide their populations & productive sectors with access to

1 The country’s socio-economic indicators (as of June 2017) in comparison with Africa, Developing Countries and Developed Countries are shown in

Appendix I. The information is available at the Bank’s Statistics Department. 2 Construction works (funded by WB and implemented by NELSAP) are ongoing and the expected commissioning date is 2021. Also, the 80 MW resource

will be shared equally among Tanzania, Burundi & Rwanda.

Page 14: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

2

modern, affordable & reliable energy services; and (ii) to help RMCs develop their energy sectors in a

socially, economically and environmentally sustainable manner.

1.2.3 Though the NWG Nyakanazi - Kigoma Project is wholly located within Tanzania, it will provide an

anchor point for regional power trade with Rwanda & Burundi (through the 220 kV Rusumo - Nyakanazi)

thus contributing to the objectives of the Eastern Africa Power Pool (EAPP).

1.2.4 Since the NWG is an infrastructure development project, it is aligned with the Bank’s Ten-year

Strategy (TYS 2013-2022) focussing on two objectives to improve the quality of Africa’s growth: (i)

inclusive growth and (ii) transition to green growth; elaborated below.

1.2.5 The Project is directly aligned with one of the Bank’s five priority areas (commonly known as High

5s or Hi-5s) of “Light up & power Africa” which is interlinked with other Hi-5s including the United Nations

Sustainable Development Goals (SDGs). Furthermore, the Project takes into consideration the Bank’s

Gender Strategy (2014 - 2018) as discussed in paragraphs 3.2.9 – 3.2.12 below since sustainable

development must be inclusive in terms of gender, age and geographical location, among other things.

1.2.6 In reference to the New Deal on Energy for Africa, the Project cross-cuts the following flagship

programmes: (i) renewable energy – through providing additional evacuation facilities for Rusumo HPP

& other renewable power projects including an Independent Power Producer developing a 5 MW solar

plant in Kigoma (ii) bottom of the pyramid electricity access – through provision of last-mile connections

and (iii) regional infrastructure development – through linkages with the transmission line to

Rwanda/Burundi.

1.3 Donor Coordination

1.3.1 In Tanzania, the Ministry of Finance & Planning (MoFP) oversees the activities of the Development

Partner Group (DPG). The Energy Development Partner Group (EDPG) is one of the many technical arms

of DPG. The EDPG primarily focuses on energy issues by coordinating Development Partner (DP) activities

in liaison with the Ministry of Energy (MoE). The DP interventions in energy include, among others,

physical infrastructure development, on-grid & off-grid energy access, renewable energy & energy

efficiency, power sector reforms, promotion of private sector investments, capacity building and energy

diversification. Appendix III gives a brief on the Tanzania energy sector while Appendix IV shows a

summary of the various DP interventions in the country including energy.

1.3.2 The Bank, being a member of EDPG, closely collaborates with other Group members composed of

multilaterals {European Union (EU), World Bank (WB) and European Investment Bank (EIB)} and

bilateral institutions {United Kingdom Department for International Development (UK DFID), Swedish

International Development Agency (SIDA), Japan International Cooperation Agency (JICA), South Korea

Economic Development Cooperation Fund (EDCF), Embassy of Norway, Agence Française De

Développement (AFD), United States Agency for International Development (USAID) and KfW

Development Bank. The EDPG chairs for the period 2017/8 are EU/Sweden.

1.3.3 In particular to the NWG preparation, the Bank in conjunction with EDCF held several meetings

with AFD, WB, EU and KfW to harmonize the development of the Project with other energy transmission

infrastructure extensions in western and northwestern Tanzania such as: (i) ongoing 220 kV Geita -

Nyakanazi and (ii) proposed 400 kV inter-connections namely Tanzania - Uganda & Tanzania - Zambia.

Page 15: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

3

2. PROJECT DESCRIPTION

2.1 Project Objectives and Components

2.1.1 In addition to significantly contributing to socio-economic transformation of Tanzania in line with

FYDP II, the ultimate development objectives of the Project comprise: (i) improve power supply through

provision of main grid reliable and affordable electricity (ii) lower energy production costs by

decommissioning the expensive diesel power plants in Kigoma & Kasulu (iii) enhance job creation (iv)

reduce GHG emissions3 and (v) provide power evacuation facilities for the Rusumo HPP and other

renewables.

2.1.2 Presently, Kigoma region is supplied by three isolated diesel generators at Kigoma town (6.25 MW),

Kasulu (2.5 MW) and Kibondo (2.5 MW). The Nyakanazi - Kigoma Project will provide main grid access

to Kigoma/Kasulu and consequently the associated diesel plants will be decommissioned. It is expected that

the Kibondo diesel power plant will be taken out of service upon commissioning of the ongoing 220 kV

Geita - Nyakanazi project funded by AFD/KfW. The diesel power plants in the region are operated at a load

factor of 75% which is relatively high implying that the demand is firm. However, the supply is very erratic

and load shedding is a common occurrence (with a plant availability factor of 69%). With access to the

main grid, the availability of supply in Kigoma will improve to at-least 95% given the fact that the Rusumo

80 MW HPP (and the associated 220 kV transmission line to Nyakanazi from Rusumo) will be operational

at the time of commissioning the Nyakanazi - Kigoma Project.

2.1.3 In addition to power rationing, growth in electricity demand from Small-Medium Enterprises

(SMEs) including households is constrained due to lack of distribution line materials and accessories to

service new customers. Also, several potential industrial-based businesses such as water filtration, fish

processing, palm oil processing and salt mining & processing, among others, have not been developed due

to lack of adequate supply in the region. The PSMP (Update 2016) demand forecast (i.e. base case scenario)

for Kigoma Region is 38 MW (in 2023 at commissioning of the Project) and 101 MW after ten years.

Furthermore, it is envisaged that an aggregated demand of at-least 645 MW will be served by the whole

1,080 km NWG covering regions of Kagera, Kigoma, Katavi, Rukwa and Mbeya by the year 2032 in

addition to providing evacuation facilities to new generation plants with a combined installed capacity of

285 MW in Katavi/Kigoma regions.

2.1.4 In context, TANESCO (i.e. Implementing Agency) engaged a Consultant4 in 2007 to undertake a

“study of transmission and sub-transmission system and alternative supply options for western & north-

western Tanzania.” Taking into account the planned generation sources in the western part of the country

and in addition to increasing reliability of the 400 kV network, TANESO re-engaged the Consultant to

upgrade the feasibility study from 220 kV to 400 kV (herein referred to as NWG). The revised 400 kV study

was completed in November 2016.

2.1.5 Further to the above studies, TANESCO prepared Environmental & Social Impact Assessment

(ESIA) studies as well as the 400 kV Nyakanazi - Kigoma transmission line Resettlement Policy Framework

(RPF) and a Resettlement Action Plan (RAP).

3 The net benefit of the Project is displacement of at-least 18,895 tons of GHG per annum produced by Kigoma and Kasulu TANESCO-owned diesel

generators. The emissions associated with the diesel power plants will reduce to zero since the plants will be taken out of service in 2023 upon commissioning

of the NWG Nyakanazi – Kigoma Project. The emissions figure is based on a grid emission factor of 0.586 tCO2/MWh for TANESCO generation published

Green Resources period 2006 – 2008. 4 SWECO International in Joint Venture with Norconsult

Page 16: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

4

2.1.6 The revised 400 kV study of 2016 proposed a phased approach of implementing the NWG in three

parts namely: (i) Mbeya - Tunduma - Sumbawanga5 (ii) Nyakanazi - Kigoma - Mpanda and (iii)

Sumbawanga - Mpanda. The AfDB/EDCF and WB/AFD6 will finance the Nyakanazi - Kigoma and Mbeya

- Tunduma - Sumbawanga projects respectively. The remaining portion Kigoma - Mpanda - Sumbawanga

is still under preparatory phase by the Bank and TANESCO.

2.1.7 The Project components are summarized in Table 2.1 including at-least 10,000 last-mile connections

to address the backlog of SME and household service connection applications mentioned in paragraph 2.1.3

above as well as other potential consumers in Kigoma region.

Table 2.1: Project Components

Component Name Component Description

Component A: 400 kV

Transmission Line

Construction of a 280 km double-circuit 400 kV rated

transmission from Nyakanazi to Kigoma.

Component B : Substations Extension of 400/220 kV Nyakanazi substation and

construction of a new 400/132/33 kV Kigoma (Kidahwe)

substation.

Component C: Distribution

Networks including last-mile

connections

Construction of approx. 70 km medium voltage distribution

networks including 100 km of low voltage reticulations and

supply of 10,000 last-mile connection materials and 7,500

ready boards for Kigoma Region.

Component D: Consultancy

Services

Consultancy firms will be engaged to undertake: (i) Project

Supervision & Management of transmission lines and

distribution networks including ESMP Implementation and

(ii) Design for Kigoma - Sumbawanga including RAP and

economic/financial analysis.

Component E Annual Audit Project Audits for 2019 – 2023.

Component F: Compensation

and Resettlement

Compensation and Resettlement for Project Affected

Persons (PAPs)

2.2 Technical Solution Adopted and Alternative Considered

2.2.1 The optional alternatives of the NWG including supply to Kigoma are elaborated in the studies

mentioned in paragraph 2.1.4 above.

2.2.2 Though a radial 132 kV transmission line was the least-cost supply option in 2007, the cost variance

(i.e. between 132 kV and 220 kV) was insignificant in comparison to the benefits7 accrued by supplying

Kigoma using a 220 kV network line from Geita/Nyakanazi. Furthermore, the 220 kV ring option from

Geita/Nyakanazi to Mbeya via Kigoma/Mpanda presented significant loss savings but required a substantial

investment cost in addition to reinforcement of Iringa - Singida to realize a reliable robust grid.

5 This component will be implemented concurrently with Iringa – Mbeya as part of the Tanzania – Zambia Interconnection project and was approved by the

WB Board on 18 June 2018. 6 The AFD package is likely to include Grant Financing from the EU Africa Investment Facility (AfIF). 7 The benefits include (i) Increased power carrying capacity with less technical losses (ii) Enhanced compatibility with future inter-connection projects to

Tabora and Mbeya.

Page 17: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

5

2.2.3 Taking into account ongoing 400 kV projects {such as the Iringa - Shinyanga via Dodoma/Singida

Backbone Transmission Investment Project (BTIP)8 & Kenya-Tanzania Power Interconnection

Transmission Project (KTPIP9)} and the planned Tanzania - Zambia (i.e. Iringa - Mbeya - Tunduma -

Nakonde) including future generation developments (i.e. Rusumo HPP, Songwe HPP and the Mbeya

Geothermal plants), the revised NWG study of 2016 recommended upgrading the voltage level from 220

kV to 400 kV. Also, as already mentioned in paragraph 2.1.6 above, the study proposed implementation of

the project in a phased-approach in tandem with the various commissioning dates of ongoing and planned

transmission and generation projects. Therefore, in consideration of the long term load forecast presented

in the PSMP (Update 2016), the Nyakanazi - Kigoma Project will be designed and operated as a 400 kV

double-circuit transmission line. Table 2.2 shows the alternatives considered and the respective reasons for

rejection.

Table 2.2: Alternatives Considered and Reasons for Rejection

# Alternative and Description Reasons for Rejection

1. 2007 Study: 132 kV network

Least cost supply option to

supply to supply Kigoma

Taking into account future inter-connections to Tabora

and Mbeya regions, the 132 kV line from

Geita/Nyakanazi to Kigoma would cause high technical

losses in addition to having a limited power carrying

capacity.

2. 2016 Study: 220 kV network The study, taking into account the planned generation

sources in the north-western part of the country,

concluded that a 220 kV network was not compatible (in

terms of power transfer capabilities) with the ongoing

BTIP and KTPIP as well as other regional inter-

connection 400 kV lines.

2.3 Project Type

The proposed intervention is a standalone investment project using ADB loan and with parallel co-

financing from EDCF. The funds from EDCF are a result of the tripartite designation to cooperate in

financing the 400 kV North-West Transmission Line Project signed on 25 October 2016 by AfDB, Ministry

of Strategy & Finance (Republic of South Korea) and MoFP.

2.4 Project Cost and Financing Arrangements

2.4.1 The overall Project cost, estimated at USD 186.12 million, is shown in Table 2.3, including

contingencies of 10% (i.e. physical contingency of 5% and price contingency of 5%) is. It also includes

the cost breakdown in both foreign currency (FC) and local currency (LC).

2.4.2 The cost per source of funding is shown in Table 2.4 including respective percentage contributions10.

The Bank’s cost breakdown per category and financing expenditure (2019 - 2023) are shown in Table 2.5

and Table 2.6 respectively.

8 Co-financed by AfDB/WB/EIB/JICA & EDCF 9 Co-financed by AfDB/JICA 10 The justification of an ADB contribution of more than 50% of the Project cost is provided in Appendix V.

Page 18: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

6

Table 2.3: Project costs by Component & Category

# Component/Category In Million USD

FC LC Total

1 Works

1.1 Component A: 400 kV Transmission Lines 85.57 21.39 106.96

1.2 Component B: Substations 35.35 8.84 44.19

1.3 Component C - 1: Distribution Networks 3.14 1.34 4.48

1.4 Sub-total 1 124.06 31.57 155.63

2 Goods

2.1 Component C - 2: Supply of Last-mile connections 3.00 0.40 3.40

2.2 Sub-total 2 3.00 0.40 3.40

3 Services

3.1

Component D: Consultancy services for (i) Nyakanazi –

Kigoma project management & supervision and (ii) design

studies for Kigoma - Mpanda - Sumbawamga. 2.78 5.57 8.35

3.2 Component E: Annual Audits 0.00 0.20 0.20

3.3 Sub-total 3 2.78 5.77 8.55

4 Others

4.1 Component F: Compensation & Resettlement Costs 0.00 18.54 18.54

4.2 Sub-total 4 0.00 18.54 18.54

5 Overall Project Cost 129.84 56.28 186.12

Table 2.4: Project costs by Sources of financing

No. Financer In Million USD

% FC LC Total

1 AfDB 94.49 28.90 123.39 66

2 EDCF 35.35 8.84 44.19 24

3 GoT11 0.00 18.54 18.54 10

4 Overall Project Cost 129.84 56.28 186.12 100

Table 2.5: AfDB Project costs per category

Category In Million USD

FC LC Total

Works 88.71 22.73 111.44

Goods 3.00 0.40 3.40

Services 2.78 5.77 8.55

Total for ADB financing 94.49 28.90 123.39

Table 2.6: AfDB Project financing plan 2019 – 2023

Source Year, Million USD

2019 2020 2021 2022 2023 Total

ADB 2.47 22.21 43.19 30.85 24.68 123.39

11 The Government’s contribution will cover compensation and Resettlement Costs including land acquisitions, customs and

duties.

Page 19: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

7

2.5 Project’s target and population

2.5.1 As already mentioned, the transmission line will traverse approximately 280 km from Nyakanazi to

Kidahwe at the outskirts of Kigoma town12. Nyakanazi (in Kagera region) is a few kilometres outside

Kigoma region near the four-way highway junction from Dodoma (in the East), Rwanda/Burundi (in the

West), Uganda via Bukoba (in the North) and Kigoma town (in the southern direction). Kigoma region,

one of the administrative regions of Tanzania, is sub-divided into District Councils of Kibondo, Kasulu,

Kigoma, Kigoma Ujiji, Uvinza, Buhingwe, Kakonko and Kasulu Mjini covering a total area of 45,066 sq.

km with a population of 2,028,82713. The region has about 483,363 households of which 16.2%14 are

connected to electricity. Also, Kigoma is one of the regions in the country where the number of female-

headed households connected to electricity is higher than that of male-headed homes at 17.2% and 15.8%

respectively. It is noted that the number of households in mainland Tanzania is 11,454,818 of which 32.8%

are connected to electricity. Overall, the connectivity of female-headed and male-headed households is

32.3% and 32.9% respectively on mainland Tanzania.

2.5.2 In view of the above, the Project will provide reliable main-grid electricity to existing connections

in Kigoma region including households, social amenities, SMEs and large electricity consumers in addition

to targeting a connectivity rate of at-least 20% (in 2023) with associated increase for female-headed homes.

In order to achieve 20% connectivity, at-least 18,368 new connections (taking into consideration population

increase) are required of which the Project will provide 10,000. The remaining 8,368 will be provided via

Government interventions in collaboration with other stakeholders including individual household efforts

and off-grid solutions. Based on the existing number of households and connectivity rate, the potential

number of new connections in Kigoma region is at-least 405,000.

2.6 Bank Group Experience and Lessons Reflected in Project Design

2.6.1 The Bank is actively involved in country’s energy sector as shown in Appendix VI (i.e. Portfolio as

of April 2018). In summary, the ongoing operations of the energy portfolio include Iringa - Shinyanga BTIP

(approved in 2011; UA 45.36 million), Regional Rusumo HPP - Nyakanazi transmission line (approved in

2013; UA 22.41 million), KTPIP (approved in 2015; UA 75.29 million), Scaling-Up Renewable Energy

Program {SREP} Grant (approved in 2013; UA 0.7 million). Two multi-sectoral operations relating to

energy sector are: (i) Kikonge Multipurpose dam for irrigation & hydropower generation and (ii)

Institutional support project for domestic resources mobilisation & natural resources governance.

2.6.2 There were cases of slow disbursements in 2016 and 2017 mainly due to protracted procurement

delays and non-availability of counterpart funds. Nonetheless, the issues have been sorted out and

disbursements are expected to significantly improve in Quarter four (i.e. Q4) of 2018.

2.6.3 The most recently completed operation in the energy sector is Electricity V (UA 28.7 million, which

was approved in 2007 and closed 2015). It was rated satisfactorily in regard to both Development Objectives

and Implementation Progress as per the PCR finalised in December 2017. In regard to the multi-sectoral

Power Sector Reform & Governance Support Program, the PCR will be completed by August 2018.

12 Kigoma town, a port on Lake Tanganyika, is the regional headquarters of Kigoma Region. 13 Energy Access Situation Report 2016; published in February 2017 by the National Bureau of Statistics (NBS) and Rural Energy Agency (REA). 14 Kigoma is one of the few regions in the country with a household connectivity rate of less than 20%. The 16.2% includes electrification from TANESCO

isolated grids and off-grid solutions such as solar home systems

Page 20: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

8

2.6.4 Also, it is noted that the original scope of the BTIP (i.e. 217 km 400 kV Dodoma - Singida

transmission line) was completed satisfactorily in December 2016 utilising about 45% of the original loan

amount. The loan saving of about UA 24.95 million was approved, in conjunction with JICA, for the 400

kV substation upgrade at Dodoma/Singida and the EPC contract was signed in December 2017.

2.6.5 A number of important lessons can be drawn from both the Bank’s past and ongoing operations

mainly related to: (i) procurement delays including protracted tender evaluation processes (ii) delay in

implementation of RAP due to non-availability of counterpart funds (iii) poor performance of contractors

and (v) slow project start-up due to use of conventional & traditional topographic survey techniques.

2.6.6 In most cases, the challenges mentioned above have resulted into long periods of no disbursements

forcing the Bank to issue Cancellation Notices in line with the Presidential Directive (PD 02/2015).

Therefore, the lessons learnt have been taken into account in the design of the proposed Project notably

through: (i) Advance contracting in addition to ensuring that the Project Management & Supervision

Consultancy entails procurement support (ii) Use of National Procurement Systems for a few selected

Project Components elaborated in paragraph 4.2 below (iii) Regular dialogue meetings with relevant

Government Ministries regarding availability of counterpart funds (iv) Enhanced due diligence to avoid

financially constrained Contractors and (v) Use of modern Airborne LiDAR15 survey techniques to reduce

the amount of time spent in design review data collection.

2.6.7 To avoid having significant un-utilised loan amounts similar to the situation described in paragraph

2.6.4 above, the cost estimate for the Nyakanazi - Kigoma Project has been critically reviewed to ensure

that it is realistic. However, in the event that there are any significant loan savings, decisions will be made

well in advance to ensure timely usage in order to avoid un-necessary extensions of the loan closing date.

2.6.8 Also, in regard to “lessons learnt” under co-financing, the good attributes of the ongoing BTIP and

KTPIP will be employed by the proposed AfDB/EDCF parallel co-financing arrangements for the

Nyakanazi - Kigoma Project. This will include holding joint AfDB/EDCF supervision missions in addition

to having one overall TANESCO Project Coordinator. However, one of the Conditions Precedent (CPs) to

first disbursement shall be securing funds for the substation component by GoT. This is not expected to be

a major issue due to the fact that EDCF already committed to provide funding as explained in paragraph

2.3 above.

2.7 Key Performance Indicators

2.7.1 The proposed key performance indicators that will be used to measure the impacts, outcomes and

outputs of the Project have been discussed with the Implementing Agency; details of which are presented

in the Results Based Logical Framework and summarized below.

2.7.2 The performance of the Project will be measured in relation to: last-mile connectivity (gender

disaggregated), demand, availability of supply, energy production costs, job creation, GHG emission

reductions resulting from decommissioning the diesel power plants, length/number of plant & equipment

and number of supervision mission reports etc. using a baseline of 2016.

15 LiDAR: Light Detection and Ranging

Page 21: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

9

2.8 Participatory Process

2.8.1 The preparation activities of the NWG Nyakanazi - Kigoma Project comprised extensive

consultation at both local/national and regional levels including DPs namely WB, KfW, EDCF and AFD.

At the regional perspective, discussions were held with KfW and WB/AFD to harmonize the development

of the NWG with the planned 400 kV Tanzania - Uganda16 and Tanzania - Zambia17 transmission lines

respectively.

2.8.2 The concerns and opinions of the DPs, in regard to TANESCO’s financial sustainability, are

addressed in paragraph 3.1 below. In addition, the Government has developed an elaborate Action Plan to

significantly improve TANESCO’s financial sustainability. In a nutshell, the project will improve

TANESCO’s positive cash flows by reducing the energy supply costs which will be further enhanced by

cheaper renewable sources such as Rusumo HPP.

2.8.3 At national level, consultations were held with both MoE and MoFP including key stakeholder

institutions namely REA, Energy & Water Utilities Regulatory Authority (EWURA) and the National

Environmental Management Council (NEMC). Also, as part of stakeholder engagement, the Bank Task

Team including Environmental & Safeguard staff undertook a field visit to the Project area in May 2017

and participated in meetings between TANESCO/Local Authorities and potential PAPs including women.

3. PROJECT FEASIBILITY

3.1 Financial and Economic Performance

3.1.1 A financial/economic analysis of the NWG was conducted based on the least-cost options in the

aforementioned feasibility studies in paragraph 2.2 above. However, revised analyses have been undertaken

for the stand-alone Nyakanazi - Kigoma Project taking into account the deliberate efforts to foster demand

through expansion of the distribution network and associated increase in last-mile connections as well as

the envisaged improvement in availability of supply.

3.1.2 The region is presently supplied from diesel power plants with high O&M costs driven by volatile

foreign exchange rates and high cost of spare parts, tools & consumables including expensive fuel road

transportation means from Dar es Salaam. The ever increasing energy production costs have adversely

impacted TANESO’s financial performance. As an example, TANESCO spent approximately USD 9.44

million (i.e. USD 0.33 per kwh) in 201618 to run the diesel power plants of Kigoma and Kasulu but received

revenues worth USD 3.26 million from the total of 28,542,24219 kWh units of energy sold in Kigoma region.

In light of such operational issues, the existing isolated grid facilities cannot be expanded to accommodate

the huge suppressed demand mentioned in paragraphs 2.1.2 & 2.1.3 above without serious financial and

environmental consequences

3.1.3 The updated financial assessment presented in the PAR is based on incremental impact between

“with project” and “without project” scenarios. In the “without project” scenario, Kigoma region will

16 KfW has provided grant to undertake a feasibility study to interconnect Masaka (in Uganda) to Mwanza (in Tanzania) via Nyakanazi. 17 WB/AFD is in advanced stages completing the preparatory activities to finance the Tanzanian component of the Tanzania – Zambia interconnection

including the NWG Mbeya - Tunduma - Subawanga. 18 It is expected that the Utility will spend about USD23.60 million to run these diesel plants but collect revenues worth USD 7.0 million in 2023 at the time of

commissioning the NWG Nyakanazi – Kigoma transmission line project. Howver, this figure will be slightly lower because Kibondo will be grid connected

earlier than Kigoma & Kasulu. 19 This is to number of kWh sold from Kigoma, Kasulu and Kibondo diesel power plants.

Page 22: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

10

continue to be served by the expensive diesel-based power generators or other improvised off-grid facilities

in order to conduct economic activities in addition to having unreliable supply and suppressed demand. In

the “with project” scenario, the new infrastructure will provide Kigoma region with cheaper supply from

the main grid and renewable power plants.

3.1.4 A summary of the financial and economic analyses is shown in Table 3.1 where the project is

financially sustainable and economically viable to justify use of the country’s resources for the investment.

A loan tenor of 24 years was used in the analysis taking into account a conservative lifespan of 25 years for

the transmission line. The assumed average end-user tariff and long-run cost of hydro generation are USD

0.12/kWh and USD 0.07/kWh respectively.

3.1.5 To assess the financial viability of the project with a conservative approach, the analysis considers

the benefits and costs in the project area only20. Its financial internal rate of return (FIRR) is estimated at

18% (real) while the financial net present value (FNPV), discounted at a weighted average cost of capital

(WACC) of 13%, is USD 68 million.

3.1.6 The FNPV is calculated using a relatively high discount rate, equal to TANESCO’s WACC, and is

expected to positively contribute to TANESCO sustainability given that the interest rate of the project’s

concessional financing is considerably lower than the entity WACC.

3.1.7 In regard to economic analysis, an integrated approach was used where by the assessment was based

on the financial cash flows of the Project. Once the transmission line is in place, the existing TANESCO

diesel-based generators including off-grid privately-owned diesel sets will be displaced by the reliable and

affordable main grid electricity21. Therefore, the value of the local diesel power plants was used to estimate

the economic benefits of the NWG Nyakanazi - Kigoma Project. Shadow prices, reflecting foreign

exchange premiums on imported items for the Project as well as local economy distortions, were applied to

project cost items to derive resource outflows. The project will yield a high economic internal rate of return

(EIRR) of 27% (real) and an economic net present value (ENPV) discounted at the opportunity cost of

capital of 12% (real), estimated at US$ 388 million.

3.1.8 A sensitivity analysis was also performed against the key risks identified including increase in costs

associated with generation, investment and O&M. The highlights of the sensitivity analysis are shown in

Table 3.2 indicating that the financial and economic outcomes are robust under adverse conditions related

to end-user tariff reduction and energy cost increase. The main reason of the robustness arises from the

significant cost savings of replacing the diesel power plants.

20 Other benefits in regard to regional interconnectivity, with Zambia and Burundi, will be considered during Kigoma – Mpanda – Sumbawanga transmission

line Project Appraisal in 2021. 21 The cost of energy is expected to significantly drop at commissioning of the 80 MW Rusomo HPP. Furthermore, the security of supply will be boosted from

the 87 MW Kakono HPP whose construction is expected to commence not later than 2020.

Page 23: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

11

Table 3.1: Main Financial and Economic Indicators

PARAMETERS VALUES

FIRR 18%

FNPV (@13%) USD 68 million

EIRR 27%

ENPV (@12%) USD 388million

Table 3.2: Sensitivity Analysis

Assumption

Change in

Assumption

(%)

FNPV @

13% DR,

real million

USD

FIRR

ENPV @ 12%

DR, real

million USD

EIRR

Base Case 68 18% 388 527%

Tariff Escalation

-1 17 14 377 28

Energy Cost

increase

5 56 17% 377 27%

10 44 16% 366 27%

15 32 15% 355 27%

Operation and

Maintenance Cost

10 63 17% 384 27%

25 62 17% 383 27%

Increase in

Investment Costs

15 49 16% 367 25%

20 37 15% 353 24%

3.1.9 In regard to the financial performance of the Implementing Agency (i.e. TANESCO), the Company

is in a financially weak position as observed from the Liquidity, Solvency and Activity ratios in one of the

ongoing Audits commissioned by GoT22. The electricity supply crisis of 2011 – 2012 was primarily

responsible for the present financial issues. The country was heavily dependent on hydro power generation

whose capacity was curtailed due to poor hydrological regimes in 2011 forcing TANESCO to engage

expensive Emergency Power Plants (EPPs) based on liquid fuels. The high generation costs weren’t fully

reflected in the end-user tariffs consequently leading to TANESCO’s financial woes. Other issues such as

high commercial losses and expensive O&M costs associated with running at-least eighteen (18) liquid

diesel-powered isolated plants23 have also significantly contributed to TANESCO’s financial problems.

3.1.10 However, the financial situation is expected to improve once the reforms that will be based on the

ongoing study conducted by Ernst & Young (E&Y), commissioned by WB/GoT and supervised by

Controller & Auditor General (CAG), are substantially implemented. On this note, GoT (through MoFP)

submitted a Financial Sustainability Action Plan to the Bank in June 2018 outlining steps that will be

undertaken to improve TANESCO’s profitability24. The NWG project, which is in line with the

Government’s Action Plan highlighted in Appendix VII, will particularly relieve TANESCO of an

estimated financial burden of USD 9.44 million spent annually on running Kigoma and Kasulu diesel power

plants. Therefore, the project will have a strong positive impact on TANESCO’s financial statement by

22 This information was obtained from the tripartite meeting among the Bank, E&Y and CAG held at the Bank offices in Dar es

Salaam in Oct 2017. 23 The estimated installation capacity of the 18 off-grid plants is 25.25 MW 24 In addition, the Government will seek support from the Africa Legal Facility in form of Advisory Services & Capacity

Building to handle IPP commercial negotiations.

Page 24: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

12

generating positive cash flows over the project lifetime (from electricity sales in Kigoma region) illustrated

in Chart 3.3 below.

Table 3.3: Cash flow over the project lifetime excluding the five year grace period.

3.2 Environmental, Social Impact and Climate Change

3.2.1 As already mentioned, the Project comprises implementation of a 280 km transmission line of 400

kV from Nyakanazi to Kigoma, substations at Nyakanazi & Kigoma and distribution networks in Kigoma

region as well as last-mile connections. The Project is classified as Category 1 because the potential

environmental & social impacts are significant and required adequate mitigation measures to be identified

through detailed ESIA studies. Furthermore, the proposed transmission infrastructure could result in

displacement of more than 200 PAPs and/or assets. The major impacts include: (i) land uptake since no

settlements will be permitted within the wayleave corridor of the transmission infrastructure (ii) interference

with avian migration routes (iii) waste generation due to construction related activities and (iv) occupational

health & safety risks associated with tower erection & working at heights. Also, a few impacts were

identified concerning the operational phase such as chemical/mechanical control of vegetation in the right

of way (RoW). Furthermore, Category 1 clarification is justified because the Project was found to trigger

all the Operational Safeguards (OS) under the Bank’s Integrated Safeguards System (ISS).

3.2.2 The ESIA studies identified a range of mitigation measures to address the key impacts including

arrangements to compensate PAPs before works are undertaken on any given sections of the transmission

infrastructure. The measures include, among others: (i) clearing of vegetation to be limited to the wayleave

corridor as much as possible (ii) ensuring availability of emergency accident response in regard to tower

erection/stringing & other general occupational hazards (iii) ensuring that contractors prepare waste

management plans and (iv) installation of transmission line reflectors to deter bird collisions.

3.2.3 Summaries of the ESIA & RAP for the Nyakanazi and Kigoma proposed substations including the

280 km 400 kV transmission line elaborating the above-mentioned mitigation measures were disclosed on

the Bank website on 9th August 201725. A total of 3,937 acreage of land will be affected corresponding to

approximately 2,548 PAPs. Compensation of the PAPs will be implemented before commencement of

works on any section of the transmission line as required by both National and Bank policies. The

25 The RAP for the 400 kV Nyakanazi – Kigoma transmission line was completed on 28 February 2018. To this end, an

Addendum to the documentation of 9th Aug 2017 was posted on the Bank’s website.

-

20

40

60

80

100

120

140

160

180

2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042

USD

Mill

ion

Project generating profit

Finance cost

Page 25: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

13

Environment & Social Management Plan (ESMP) costs, estimated at USD 11 million, will be covered under

the project management & supervision consultancy services as well as the EPC Contracts. In regard to the

400 kV transmission line RAP implementation, the cost estimate is TSH 5,923,850,579 excluding

Nyakanazi/Kigoma substations whose land was already acquired by TANESCO.

3.2.4 As part of the ESIA process, a socio-economic survey was conducted with the purpose of obtaining

a clear representation of the characteristics of population within the Project area and soliciting information

on standards of living. As much as possible, the transmission infrastructure will be routed through areas

with limited settlements to reduce compensation-related costs as well as minimize social disturbance to

ensure consistency with the mitigation hierarchy. To facilitate further stakeholder engagement, TANESCO

prepared a Stakeholder Engagement Plan (SEP) to guide managing and facilitating engagements with

communities throughout the various stages of the Project life cycle.

3.2.5 In line with the SEP implementation, consultations were conducted at all levels comprising

interviews and meetings involving Local Authority Officials such as District Commissioners & Executive

Directors, Ward & Village leaders and with potential PAPs (including women) whose land will be directly

affected by the transmission infrastructure. At village level, the Project was viewed positively in regard to

job creation and provision of electricity to households. At district level, the Project was welcomed in regard

to job creation and growth of secondary economic activities related to the Project.

3.2.6 From the climate change perspective, Tanzania is committed to reducing its GHG emissions as

stated in paragraph 1.1.2 above. The country’s INDC commits to reducing GHG emissions by a range of

measures including increased modern energy access.

3.2.7 The Project will contribute to climate change adaptation by helping to strengthen the economy in

Kigoma region by supplying main grid reliable & cheaper electricity. However, the more obvious benefits

will come from the emission reductions arising from the decommissioning of the existing diesel-powered

plants. On the basis of these emissions reductions and according to the 2015 Joint Report on Multilateral

Development Banks’ Climate Finance (i.e. Annex 3 List of Activities Eligible for Classification as Climate

Mitigation Finance; activity 2.1 Transmission and Distribution Systems), the Project is considered to be

100% climate mitigation finance and should be counted towards the Bank’s target of climate finance

accordingly.

3.2.8 In compliance to the Bank’s Climate Safeguards System, the Project was screened for climate

change impacts and classified as Category 2. Unlike generation facilities, the Project’s vulnerability to

climate risk, as well as its contribution to climate change, is considered minimal. Nevertheless, the Project

will take appropriate measures to mitigate climate change-related risks that could occur in the long-run.

Specifically, the Project Supervision Consultant and EPC Contractors will take into account flood-prone26

areas during the selection of tower & substation locations in order to avoid damage to the infrastructure as

a result of flooding and/or poor drainage. Also, clearing of vegetation before construction of the line will

be restricted within the 50 m wide wayleave corridor.

3.2.9 In regard to social aspects, the communities in the Project area will benefit from the ESMP budget

of USD 11 million, mentioned in paragraph 3.2.3 above, aimed at addressing development inclusion, social

protection, gender inequality and livelihood support. The demographic characteristics show that the region

has a young population indicative of youth in-migration from other regions and rural areas. The 2012

26 Information regarding flood-prone areas is available at the Ministry of Water & Irrigation as well as Local Authorities and Lake Tanganyika Basin

Authorities and NEMC.

Page 26: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

14

Census revealed that about 49% of the population constituted the young population below 15 years of age

and only 4% of the population aged 65 years and above. The Kigoma’s age dependency ratio was 110,

implying that there were 100 people in age 15 - 64 supporting 110 persons in age groups 0 - 14 and 65 years

and above. The region is largely agro-based with the majority of the population (i.e. 76.35%) engaged in

subsistence farming. The low agricultural production coupled with high expenditure on social services is

an indicator of high poverty levels in the region. Also, kerosene and firewood are the most common sources

of energy for lighting and cooking respectively.

3.2.10 In regard gender, the country policy is progressive27, however, disparities still exist with negative

impacts on development efforts. The recently published Energy Access Situation Report 2016 states that

“nearly in all regions of Tanzania, the burden to collect firewood is more borne by females than males as

measured by length of time used to collect firewood.”

3.2.11 In view of the above, though the Nyakanazi - Kigoma Project comprises largely of transmission line

infrastructure, it has a component for last-mile connections particularly related to provision of pre-payment

energy meters as well as ready boards targeting low income earners including female-headed households.

Use of ready boards will enhance access to electricity through provision of a “plug & play” low-cost but

quality solution in comparison with expensive conventional house wiring. Also, the pre-payment system

will ensure that households manage their consumption and thus avoid debt. As part of the ESMP,

TANESCO will carry out a public Awareness Campaigns regarding house wiring, demand-side

management as well as benefits of electrification.

3.2.12 In addition to the last-connection strategy towards gender and vulnerable groups, the community

and SEP will increase participation of women-owned businesses such as food vending during Project

Implementation. Also, trainings will be conducted with the aim of reducing the incidence of sexual

exploitation, abuse & violence and sexually transmitted diseases, including HIV/AIDS as well as

unsupported parenthood that may result from the high influx of male workers into communities during

Project Implementation.

4. IMPLEMENTATION

4.1 Implementation Arrangements

4.1.1 In reference to institutional arrangements, GoT through MoFP shall be the Borrower of the loan.

The Executing and Implementing Agencies will be MoE and TANESCO respectively. TANESCO has

demonstrated adequate technical and managerial ability to implement the Project through the completion

of a similar 670 km 400 kV Iringa - Shinyanga BTIP jointly co-financed by ADF/JICA and GoT including

parallel co-financing from WB, EIB and EDCF.

4.1.2 The Project will be implemented by a Project Implementation Team (PIT) comprising key

TANESCO staff namely: Project Coordinator, Transmission Line Engineer, Distribution Engineer, Civil

Engineer, Procurement Expert, Accountant, Environmental Expert and Social Expert. In addition, a

Consultancy Firm will be recruited to handle project management and supervision aspects of the Project,

including ESMP Implementation, in liaison with PIT. Furthermore, the PIT will coordinate the NWG

substation component in liaison with the financier EDCF including MoE and MoFP.

27 Evidenced by the National Gender and Sustainable Energy Network collaboration with the Ministry of Energy

Page 27: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

15

4.2 Procurement Arrangements

4.2.1 The procurement of goods (including non-consultancy services), works and consultancy services,

financed by the Bank, will be carried out in accordance with the Bank’s “Procurement Policy for Bank

Group Funded Operations” dated October 2015 in line with the provisions stated in the Financing

Agreement.

4.2.2 In particular, the procurement will be based on the following procurement methods and procedures

(PMP):

i. Borrower Procurement System (BPS) comprising its Laws & Regulations (i.e. Public Procurement

Act, 2011 revised 2016 and its Regulations) using the national Standard Bidding Documents (SBDs)

or other Solicitation Documents.

ii. Bank Procurement System using the relevant Standard Solicitation Documents for contracts that are

above certain financial thresholds.

4.2.3 A Procurement Risks and Capacity Assessment (PRCA) at Country, Sector and Project level

including Implementing Agency was conducted and the findings have been taken into account during the

Nyakanazi – Kigoma Project preparation.

4.2.4 The assessment of the Implementing Agency and its Procurement Management Unit (PMU),

responsible for handling and following up procurement activities in TANESCO, showed that the

organization has a system in place and trained staff competent to handle large contracts. Also, the PMU has

practical experiences and exposures in the working procedures of Bilateral and Multilateral Financing

Institutions including the Bank.

4.2.5 In addition, the assessment revealed increasing trends in the level of participation in public

procurement by both private sector local & international contractors, suppliers and consultants either as sole

entities or in form of joint-ventures and sub-contracting.

4.2.6 The major procurement packages under the Nyakanazi - Kigoma Project comprise six categories

namely: (i) supply & installation of a 280 km 400 kV Nyakanazi - Kigoma transmission line - 2 Lots; (ii)

Supply of last-mile connection materials - 1 Lot; (iii) Consultancy Services - 1 Lot; (iv) Supply &

installation of distribution networks - 2 Lots; (v) Selection of a consultant to carry out annual financial

audit of the Project accounts - 1 Lot; and (vi) Supply & Installation of substations.

4.2.7 The procurement packages (i) – (iii) and (iv) – (v) will be procured based on the Bank28 and

Borrower PMP respectively. The supply & installation of substations will be procured using Third Party

PMP agreed upon between the Borrower and EDCF.

4.2.8 In light of paragraph 2.6.6 on lessons learnt related to advance contracting, TANESCO submitted

an Official Request to the Bank, taking into account appropriate safeguards, to start the procurement process

28 The Quality & Cost Based Selection method will be used to procure Consultancy Services while Open Competitive Bidding will be utilized for the 400 kV

transmission lines as well as supply of last-mile connection materials.

Page 28: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

16

prior to Board Approval of the Project. On this note, the Bank granted no-objections and accordingly the

procurement process of Project Management & Supervision Consultancy Services for Nyakanzi – Kigoma

was launched in April 2018..

4.3 Financial Management Arrangements

4.3.1 An assessment of Financial Management System (FMS) of the Implementing Agency (i.e.

TANESCO) was conducted based on Bank’s Financial Management (FM) Implementation Guidelines

2014. The assessment concluded that the overall risk is “Substantial” with issues such as (i) delays in

submitting annual audit reports; and (ii) ineffective budget monitoring tools. Accordingly, the Project has

been designed with a conditionality comprising: (i) assigning a Project Accountant, as part of the PIT, with

qualifications & experience acceptable to the Bank (ii) preparation & submission of quarterly performance

reports, Annual Work Plan & Procurement Plan and (iii) preparing annual audits in accordance to the

Bank’s guidelines described in below.

4.3.2 Furthermore, the Government is committed to undertaking reforms in the Energy Sector with

particular emphasis on TANESCO’s financial sustainability including FM. As already mentioned in

paragraph 3.1, there is an ongoing WB-funded E&Y financial audit, supervised by CAG, which will be

used as a key input to undertaking reforms in TANESCO. Also, coupled with the ongoing initiatives of

paying off arrears and reduction of receivables, it is expected that the revenues will improve significantly

and TANESCO will became profitable within the next few years.

4.3.3 In view of the above mitigation measures, the Project will substantially use the TANESCO FMS.

The overall responsibility of the FM (including Budgeting, Accounting System, Internal Control, Treasury

Management/Funds Flow, Financial Reporting and External Audit arrangements) rests with the TANESCO

Management under the Managing Director (MD). Since the Project FM function will be implemented within

the existing structure of TANESCO, it will be under the responsibility of the Chief Finance Officer (CFO)

who will supervise the Project Accountant. In addition, the TANESCO Internal Audit Department will, as

part of its routine, undertake regular audits of the Project financial transactions which will be shared with

the Bank during the bi-annual Project Supervision Missions.

4.3.4 The audit arrangement of the Project entails that financial statements are prepared and submitted

within three (3) months after the closure of every financial year. The Project Audit will be conducted by

either CAG or a Private Audit firm appointed by CAG in line with the Bank approved audit terms of

reference (ToRs). The audit report, complete with a Management Letter, will be submitted to the Bank not

later than six months after the end of the financial year. As already mentioned in paragraph 4.2, the cost of

the audit shall be borne by the Project in the event that it is conducted by a Private Audit Firm.

4.3.5 In regard to Disbursement Arrangements, the Project will use the Direct Payment Method to

Contractors/Suppliers/Consultants. Other methods may be used when need arises and upon prior approval

by the Bank. The four disbursement methods are described in the AfDB Disbursement Handbook available

on the Bank’s website. The Bank issued a draft Disbursement Letter for discussion, during loan

negotiations, providing specific guidelines on key disbursement procedures and practices.

Page 29: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

17

4.4 Monitoring and Evaluation

4.4.1 The performance of the 400 kV NWG Nyakanazi - Kigoma Project will be monitored through

submission of quarterly progress reports to both Bank Senior Management and the Board. This will be

conducted through the established performance indicators and budgets against which actual reporting is

done including detailed explanations of any significant variances. The reports will show cash receipts by

source and expenditure (i.e. services/works/goods) including linking physical implementation progress to

disbursed amounts. In addition, the report will highlight issues requiring Bank’s intervention. The Project

performance indicators are presented in the Results Basic Logical Framework in the introductory section

of the PAR.

4.4.2 The Project will be launched in the 4th quarter of 2018 and will be monitored through Field

Supervision Missions from the Bank’s Headquarters in Abidjan, Regional Offices in Nairobi and the

Tanzania Country Office at least twice a year from 2019 until 2023. The Missions will be conducted in

liaison with EDCF, MoE, TANESCO and MoFP. However, the Task Manager will undertake monthly desk

reviews of the Project and hold ad-hoc meetings with the Project Coordinator to ensure that the Project is

completed on schedule within the available budget.

4.4.3 The PIT, assisted by the Project Management & Supervision Consultant, is primarily responsible

for monitoring implementation and fulfilling TANESCO’s reporting obligations to the Bank, including

preparation and submission of quarterly reports and annual audit reports.

4.4.4 In addition to the bi-annual Supervision Missions, the Bank will undertake a Mid-Term Review

(MTR) of the Project not later than 30 months after the loan approval, which shall inform any adjustments

to the Project design to ensure that Project objectives are achieved. Besides regular monthly and quarterly

project progress reporting, the Project Management & Supervision Consultant shall be required to prepare

and submit a report to the Implementing Agency upon completion of the consultancy assignment. The

Consultant’s Report will form the basis upon which TANESCO will prepare and submit a Completion

Report to the Bank. Upon receipt of both reports, the Bank will, in consultation with MoFP/MoE and

EDCF/TANESCO prepare its own PCR.

4.4.5 The Project will be implemented over a period of five (5) years, as shown in the PAR introductory

sections, starting 2019 and closing not later than 31 December 2023..

4.5 Governance

4.5.1 The Implementing Agency TANESCO is a (limited company) fully government-owned utility under

the MoE and duly registered under the amended Companies Act Cap 12. The Company is responsible for

generation, transmission and distribution of electricity on mainland Tanzania and is regulated under the

Electricity Act No. 10 of 2008. Though TANESCO is vertically integrated, it is not a monopoly following

the amendment of Section 41(6) of the Electricity Act 2008. TANESCO is headed by the MD who reports

to the Board of Directors. The PIT will be under the direct supervision of the Deputy MD - Investment.

Also, TANESCO has a Company Secretariat Division dealing with all legal matters within the organisation.

The Secretariat handles, among other things, issues pertaining to risk management and good governance,

corruption and fraud including physical protection of company property and assets.

4.5.2 In reference to the approved Electricity Supply Industry (ESI) Reform Strategy & Roadmap 2014 -

2025, TANESCO will be un-bundled in the long run into generation, transmission and distribution

Page 30: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

18

segments. It is envisaged that in the event unbundling takes place during implementation, PIT will most

likely be transferred to the Transmission Segment.

4.6 Sustainability

4.6.1 The Project is technically, economically and financially sustainable. In addition, the Government is

committed to implementing the NWG Project in order to contribute towards realizing TDV 2025.

4.6.2 Technical sustainability is guaranteed due to the fact that the Project will be implemented based on

proven worldwide technology common in the country. In addition, the Project has been designed taking

into account compatibility with future infrastructure namely: (i) Tanzania - Uganda & Tanzania - Zambia

regional interconnections and (ii) Rusumo HPP and other renewable power plants. Also, the supply &

installation contracts as well as Project Management & Supervision will include relevant on-the-job training

aspects to ensure that the plant & equipment are operated in a sustainable manner where at-least one third

of the training opportunities will be allocated to women.

4.6.3 In regards to economic and financial sustainability, the Project will provide reliable main-grid

supply to Kigoma Region thereby promoting economic activities in the area. From an operational point of

view, TANESCO’s high O&M costs will drastically reduce as a result of commissioning the transmission

line and decommissioning the diesel power plant in Kigoma and Kasulu. Therefore, the Project will

significantly contribute towards addressing the TANESCO’s financial woes.

4.7 Risk Management

4.7.1 The Project involves some degree of risks, in addition to the fiduciary-related issues mentioned in

paragraph 4.3 above, such as: (i) Poor performance of contractors (ii) Delay in releasing counterpart funds

(iii) Delay in implementation of Nyakanazi/Kigoma substations and upstream infrastructure transmission

projects and (iv) Social issues related to large influx of “foreign” workforce in Kigoma region. The major

risks and mitigation measures are shown in Appendix VIII, nonetheless, the overall Project risk is rated as

moderate.

4.8 Knowledge Building and Inclusivity

4.8.1 The Nyakanazi - Kigoma Project will provide on-the-job training opportunities to TANESCO staff

particularly in 400 kV-rated transmission infrastructure which is fairly new to the country.

4.8.2 As mentioned in paragraph. 4.2.7 above, at-least two Project components (i.e. distribution networks

and Audit services) will be procured using the Country’s public procurement system and will, therefore,

attract participation from local Service Providers, Suppliers and Contractors.

4.8.3 In addition, the Bank will use the “lessons learnt” under the Project to inform future energy

operations in Tanzania and other RMCs. Also, if the Project is successfully implemented, it will build a

long lasting partnership between the Bank, GoT and EDCF in energy-related operations.

Page 31: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

19

5. LEGAL INSTRUMENTS AND AUTHORITY

5.1 Legal Instrument

ADB Loan Agreement will be signed between the Borrower and the Bank.

5.2 Conditions associated with the Bank’s proposed Financing

5.2.1 Entry into Force

The entry into force of the Loan Agreement shall be subject to the fulfilment by the Borrower, of the

conditions set forth in Section 12.01 of the General Conditions Applicable to the Bank’s Loan Agreements

and Guarantee Agreements (Sovereign Entities).

5.2.2 Conditions Precedent to First Disbursements

5.2.2.1 Disbursement for Goods and Services - The obligation of the Bank to disburse the proceeds of the

Loan for Goods and Services shall be conditional upon entry into force of the Loan Agreement, and the

fulfilment by the Borrower, in form and substance satisfactory to the Bank, of the following conditions:

(i) Either the parallel co-financier (EDCF) has approved its financing for the Substations at

Nyakanazi/Kigoma or the Borrower has made appropriate arrangements to cover any financing

gap resulting from failure to obtain EDCF’s financing under the Project;

(ii) Conclusion of a Subsidiary Financing Agreement with TANESCO for on-lending or on-granting

the proceeds of the loan to TANESCO on terms and conditions acceptable to the Bank;

(iii) Appointment of the Project Implementation Team;

(iv) Submission of a Works and Compensation Schedule detailing (a) sections into which civil works

under the Project will be divided and (b) time frame for compensation and resettlement of all

Project Affected Persons (PAPs) in respect of each section, in accordance with the Resettlement

Action Plan (RAP).

5.2.2.2 Disbursement for Works – The obligation of the Bank to disburse the proceeds of the Loan for

Works shall be conditional upon the fulfilment of the Conditions Precedent to First Disbursement for Goods

and Services, and the fulfilment by the Borrower, in form and substance satisfactory to the Bank, of the

following condition:

(i) Compensation and/or resettlement of all PAP in accordance with the RAP, in at least the first

affected section of the civil works under the Works and Compensation Schedule of the Project.

5.3 Other Conditions

The Borrower shall provide evidence, in form and substance satisfactory to the Bank, confirming that prior

to commencement of construction on any affected section of the civil works under the Works and

Compensation Schedule of the Project, all PAPs have been compensated and/or resettled in accordance with

the RAP.

Page 32: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

20

5.4 Undertakings

The Borrower undertakes, in form and substance satisfactory to the Bank, to:

i. Ensure that co-financing and counterpart funds are availed for Project Implementation;

ii. Fully implement the Environmental and Social Impact Assessment (ESIA), the Environmental and

Social Management Plan (ESMP) and the RAP of the Project, as may be updated, and

comprehensively report to the Bank on the said implementation on a quarterly basis;

iii. Submit Annual Reports approved by the relevant authorities on ESMP and Occupational Health

and Safety (OSHA) compliance and

iv. Make timely provisions in the Borrower’s annual budgets for the funds required as the

Borrower’s counterpart contribution to the cost of implementation of the Project so as to avoid

Project implementation delays.

5.5 Compliance with the Bank’s Policy

This project complies with all applicable Bank policies.

6. RECOMMANDATIONS

Management recommends that the Board of Directors approves the proposed ADB Loan of USD 123.39

million to the United Republic of Tanzania for the financing of the North West Grid (400 kV Nyakanazi -

Kigoma transmission line) Project, subject to the terms and conditions stipulated in this report.

Page 33: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

I

APPENDIX I: COMPARATIVE SOCIO-ECONOMIC INDICATORS

Page 34: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

II

APPENDIX II: MAP OF PROJECT AREA (NYAKANAZI – KIGOMA; 280 KM)

Page 35: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

III

APPENDIX III: ENERGY BRIEF

The Energy Sector on mainland Tanzania is under the direct supervision of MoE based on the Tanzania

National Energy Policy (NEP) 2015. The legal framework is governed by various Acts of Parliament

including (i) Electricity Act 2008 (ii) EWURA Act 2001. On the regulatory side, the EWURA Act

(2001) and the Petroleum Act (2015) empowers EWURA with the responsibilities to regulate the

midstream/downstream petroleum (including natural gas) subsector and the electricity/water utilities

respectively for mainland Tanzania excluding Zanzibar. The upstream activities are regulated by

Petroleum Upstream Regulatory Authority (PURA).

Institutionally, the key organisation include MEM, EWURA, REA, TANESCO (i.e. NWG

Implementing Agency), TPDC and IPPs, etc. TANESCO is a government owned utility under MoE.

Its principal activities include generation, transmission, distribution and energy sales on mainland

Tanzania. It also sells power in bulk to Zanzibar and Kenya; and imports from Kenya, Uganda and

Zambia. In addition to the main grid, TANESCO owns and operates about 18 isolated diesel-powered

grids.

In line with NEP, there are ongoing reforms to address challenges in the electricity sub-sector in order

to provide the country with adequate, reliable, affordable and environmentally friendly supply to

realise the targets of TDV 2025. The reforms are articulated in the Electricity Supply Industry Reform

Strategy & Roadmap (2014 - 2025). It is envisaged that TANESCO will be un-bundled into generation,

transmission and with several regional distribution companies.

In addition, the Power Sector Master Plan (PSMP) was updated 2016 re-assessing the short-term (2016

- 2020), mid-term (2021 - 2025) & long-term (2026 - 2040) generation and transmission plan

requirements of the country, among other things, in order to attain stable supply to achieve economic

growth, energy security and environmental protection.

The country’s installed capacity is approximately1,500 MW comprising both main grid and isolated

grids including imports & exports. The isolated grids operated by TANESCO account for about 127.5

MW. The installed capacity of the main grid is approximately 1366.6 MW comprising hydro (567.70

MW - 41.54%), natural gas (615 MW - 45%), liquid fuel (173.4 MW - 12.69%) and biomass (10.5

MW 0.77%) with a maximum demand of about 1051 MW. The 2020, 2025, 2030, 2035 and 2040

domestic demand forecast (base-case scenario) is 2190 MW, 3659 MW, 5872 MW, 9351 MW and

14332 MW respectively. Therefore, the Country ensure that new plants are brought on line as soon as

possible to realise secure supply in the near future. The transmission losses are estimated at 5.92% as

of June 2017. On the distribution side, Automated Meter Reading (AMR) and pre-paid energy meters

are being installed at large power users and SME/households to reduce commercial loses.

In regard to electrification, about 32.8% of households on mainland Tanzania are connected to

electricity as of 2016. Of the electrified households, 74.9% are grid-connected while 24.7% use solar

power and 0.3% utilise other means. Also, the connection rate of rural and urban households is 34.5%

and 96.4% respectively.

The key challenges presently faced in the electricity sub-sector include (i) low private sector

participation in large scale generation (ii) over-reliance on few generation sources (iii) unreliable and

expensive energy supply (iv) low access to modern energy services and (v) TANESCO financial

sustainability issues, among other things. In addition to the Action Plan prepared to tackle TANESCO’s

financial problems, the Government is expected to seek assistance from the Africa Legal Support

Facility to manage IPP commercial related transactions.

Page 36: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

IV

APPENDIX IV: MAPPING THE COUNTRY DP FOCUS AREAS VS FYDP II

Page 37: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

V

APPENDIX V: JUSTIFICATION OF ADB FINANCING OF MORE THAN 50%0

Based on the Bank’s policy on Expenditure Eligible for the Bank Group, this operation is proposing

government financial contribution of less than 50%, justified as follows:

1. Country Commitment to Implement its Overall Development Program:

Tanzania’s development framework and long-term development goals are laid out in the National

Vision 2025 (TDV 2025), with the aspirations to transform the country into a middle income and

semi-industrialized economy by 2025. The Vision has the following three targets: (i) a high quality

livelihood for all citizens, (ii) good governance and rule of law, and (iii) a strong and competitive

economy, including through the development of infrastructure. The Government’s medium term

development agenda is outlined in the recently launched Five Year Development Plan (FYDP II:

2016/17-2020/21) with a strong focus on industrialization. The ambitious FYDP II, which bears

the theme – “Nurturing Industrialization for Economic Transformation and Human Development”

– focuses on: (1) growth and industrialization (2) human development and social transformation;

(3) business environment strengthening; and (4) ensuring implementation effectiveness and

efficiency. The Plan aspires to raise annual real GDP growth to 10% by 2021 (from 7% in 2015),

per capita income to US$ 1,500 (from US$ 1,043 in 2014) and reduce poverty rate to 16.7% in

2021 from 28.2% recorded in 2011/12.

2. Financing Allocated by the Country to Sectors Targeted by Bank Assistance:

Infrastructure development remains a top priority in Tanzania’s plans and strategies. The share of

infrastructure (transport and energy) spending in the total budget is around 26%, and there are

several multi-year master-plans and programs in place, but funding remains a challenge. With

regard to energy sector, the Government’s Five Year Development Plan (FYDP II: 2016/17-

2020/21) aspires to increase electricity generation from 1,501 MW in 2015 to 4,915 MW by 2020,

and increase electricity connections from an estimated 36% 2015 to 60% of the population. According

to the Power System Master-Plan, total investment needs to achieve these targets are estimated at about

US$ 11.6 billion (equivalent to an average annual budget of about US$ 2.3 billion). However,

financing remains a major challenge, and for fiscal years 2016/17 and 2017/18, budget allocations for

energy sector were merely about US$ 510 million and US$ 540 million respectively. The shares of

energy sector in the budget are indicated in table 1.

TABLE 1: INFRASTRUCTURE FINANCING IN TANZANIA

2016/2017 Budget 2017/2018 Budget

Financing allocated to infrastructure UA 2089 Million UA 2184 Million

Share of infrastructure (energy and transport) in

the budget 26% 26%

Financing allocated to energy sector UA 358 Million UA 380 Million

Share of energy budget in infrastructure budget 17% 17%

Source: Ministry of Finance

3. Country Budget Situation and Debt Level: In June 2017, the Government unveiled a

TZS 31.7 trillion (approx. USD 14.1 billion) budget for FY 2017/18. The overall budgeted

expenditure is about 26.2% of GDP, slightly higher than the 24.2% of GDP expected outturn for

FY 2016/17. Domestic revenues are projected to increase from likely outturn of 15.3% of GDP in

Page 38: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

VI

FY 2016/17 to 16.0% of GDP in FY 2017/18. The budget situation is summarized in Table 2,

which highlights the challenges the Government faced in securing external financing for it

FY2016/17 budget to support the development agenda. The share of foreign loans and grants

declined from a budgeted 12.2% of the 2016/17 Budget, to an expected 8.7%. This is expected to

pick up to 12.5% in the 2017/18 Budget. Net domestic financing is planned at around 1.5% of

GDP in line with International Monetary Fund’s Program – the Policy Support Instrument (PSI).

Tanzania’s public debt stands at around 37% of GDP, and the IMF’s most recent debt sustainability

analyses (DSA) in mid-2016 indicates that Tanzania could expand its fiscal deficit up to 4.5% of

GDP for a few years and still maintain a low risk of debt distress.

TABLE 2: BUDGET SITUATION

2016/17 Budget 2016/17 Likely 2017/18 Budget

Total Expenditure as % of GDP 27.0% 24.2% 26.2%

Domestic Revenues as % of GDP 16.3% 15.3% 16.0%

Share of Foreign Loans and Grants in total Budget 12.2% 8.7% 12.5%

Share of General Budget Support in total Budget 1.6% 1.2% 3.0%

Foreign Loans and Grants as % of GDP 3.3% 2.1% 3.3% Source: Ministry of Finance

4. Country Initiatives: Recent initiatives by the Government in the energy sector include the

ongoing implementation of ambitious rural electrification program, estimated to cost about UA

290 million – funded from the Government’s own resources. By March 2017, about 17,740 kms

of distribution network, inclusive networks in areas that will be serviced by the NWG, had been

constructed resulting in 153,821 new connections. Also, the construction of 240 MW Kinyerezi 2

gas-fired plant which started in 2016 is in advanced stages, and is expected to be completed in

2018. The estimated cost of Kinyerezi 2 is about UA 220 million.

5. Conclusion: In view of the dwindling ADF resources, it is justified to have an ADB

window contribution of more than 50% in order to support the Government of Tanzania to meet

its development objectives given the fact that the Country has undertaken several own-funded

energy investments in line with the NWG objectives.

Page 39: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

VII

APPENDIX VI: ADB PORTFOLIO

SN

1 Marketing Infrastructure, Value Addition and

Rural Finance Program

ADF Loan 29-Jun-2011 30-Sep-2018 40.00 35.75 89.4 6.9

2 Agriculture Development Bank ADF Loan 13-Dec-2016 31-Dec-2018 67.27 33.64 50.0 1.4

SUB-TOTAL 107.27 69.39 64.7 4.15

3 Tanzania Road Sector Support Project I ADF Loan 2-Dec-2009 15-Dec-2018 152.00 135.00 88.82 8.4

4 Tanzania Road Sector Support Project II ADF Loan 5-Apr-2012 31-Dec-2018 140.00 122.00 87.14 6.0ADB Loan 30-Sep-2015 31-Dec-2020 71.60 0.86 1.20 2.6

AGTF Loan 30-Sep-2015 31-Dec-2020 32.60 0.20 0.62 2.6

ADB Loan 26-Nov-2015 30-Oct-2021 199.20 20.21 10.15 2.5

ADF Loan 26-Nov-2015 30-Oct-2021 54.00 4.65 8.61 2.5

SUB-TOTAL 649.40 282.92 43.57 4.88

7 Zanzibar Urban Water & Sanitation ADF Loan 19-Dec-2012 31-Dec-2018 14.00 6.86 49.00 5.4

ADB Loan 16-Sep-2015 31-Dec-2020 105.60 5.18 4.91 2.6

ADF Loan 16-Sep-2015 31-Dec-2020 18.00 2.10 11.67 2.6

AGTF Loan 16-Sep-2015 31-Dec-2020 30.90 1.04 3.37 2.6

SUB-TOTAL 168.50 15.18 9.01 4.00

9 Iringa-Shinyanga Transmission Line ADF Loan 26-Oct-2010 31-Oct-2018 45.36 24.50 54.01 7.5

10 Scaling-Up Renewable Energy Program SCF Grant 20-Dec-2013 30-Jun-2018 0.50 0.50 100.53 4.4

SUB-TOTAL 45.86 25.00 54.52 5.95

11 Alternative Learning and Skills Development ADF Loan 29-Jun-2011 15-Dec-2018 15.00 5.17 34.47 6.9

12 Support to Technical Vocational Education and

Training & Teacher Education

ADF Loan 2-Apr-2014 31-Dec-2019 34.00 3.43 10.09 4.1

SUB-TOTAL 49.00 8.60 17.55 5.50

13 Institutional Support Project for Good

Governance III

ADF Loan 3-Feb-2016 31-Dec-2018 12.00 4.11 34.25 2.3

14 Institutional Support Project for DRM and

Natural Resources Govermance

ADF Loan 31-Mar-2017 31-Dec-2019 19.58 0.21 1.07 1.2

15 Kikonge Multipurpose Dam, HEP and Irrigation

Feasiblity Study

TF 27-Jun-2016 31-Dec-2018 1.60 0.00 0.0 1.9

16 Humanitarian Emmergency Assistance for Kagera

Earth Quake

ADF Grant 12-Jan-2017 31-Mar-2018 0.70 0.70 100.00 1.4

33.88 5.02 14.82 1.36

FINANCE

17 TZS Line of Credit to FNB Subsidiary in TZ ADB Loan 12-Dec-2012 31-Dec-2017 31.05 14.32 46.12 5.3

Line of Credit to CRDB Bank Ltd ADB Loan 18-May-2016 1-Aug-2024 11.00 0.00 0.00 2.0

Line of Credit to CRDB Bank Ltd ADB Loan 18-May-2016 30-Nov-2017 88.20 66.15 75.00 2.0

SUB-TOTAL 130.25 80.47 61.78 2.43

NATIONAL Operations 1184.16 486.59 41.09 4.71

19 Arusha-Holili/Taveta-Voi Road Project ADF Loan 16-Apr-2013 31-Dec-2018 79.90 39.00 48.8 5.1

20 Regional Rusumo Hydropower ADF Loan 27-Nov-2013 31-Aug-2019 22.41 0.86 3.84 4.5

21 EAC Centres of Excellence for Skills and

Tertiary Education

ADF Loan 3-Oct-2014 31-Dec-2019 6.25 1.35 21.60 3.5

22 Kenya -Tanzania Interconnection ADF Loan 18-Feb-2015 31-Dec-2019 75.29 10.41 13.83 3.2

23 Lake Victoria Maritime and Transport Project ADF Loan 24-Oct-2016 31-Dec-2019 3.77 0.56 14.85 1.6

SUB TOTAL 187.62 52.18 27.81 3.6

1371.8 538.8 39.3 4.0

8

5 Dar es Salaam Rapid Bus Transit Project

Transport Sector Support Program6

ENERGY

WATER SUPPLY/SANITATION

Arusha Urban Water Supply Improvement

Porject

SOCIAL

AGE (

Yrs)

DISB RATE

(%)

AGRICULTURE

A. NATIONAL OPERATIONS:

18

TRANSPORT

DISBURSED

AMOUNT

(MUA)

MULTISECTORAL

NATIONAL + MULTINATIONAL

B. MULTINATIONAL OPERATIONS:

SUB TOTAL

APPROVE

D

AMOUNT

CLOSING

DATE

APPROVAL

DATE

TANZANIA: PORTFOLIO BASIC DATA, 30 APRIL 2018

SECTOR

SOURCE

OF

FINANCE

Page 40: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

VIII

SN1 Marketing Infrastructure, Value Addition and Rural Finance Program ADF Loan 29-Jun-2011 31-Dec-2017 40.00 30.23 75.6 6.2

2 Agriculture Development Bank ADF Loan 13-Dec-2016 31-Dec-2018 67.27 33.64 50.0 0.7

SUB-TOTAL 107.27 63.87 59.5 3.45

3 Tanzania Road Sector Support Project I ADF Loan 2-Dec-2009 15-Dec-2017 152.00 130.91 86.13 7.7

4 Tanzania Road Sector Support Project II ADF Loan 5-Apr-2012 31-Dec-2018 140.00 102.59 73.28 5.4

ADB Loan 30-Sep-2015 31-Dec-2020 71.60 0.46 0.64 1.9

AGTF Loan 30-Sep-2015 31-Dec-2020 32.60 0.17 0.54 1.9

ADB Loan 26-Nov-2015 30-Oct-2021 199.20 0.08 0.04 1.8

ADF Loan 26-Nov-2015 30-Oct-2021 54.00 0.95 1.76 1.8

SUB-TOTAL 649.40 235.16 36.21 4.20

7 Zanzibar Urban Water & Sanitation ADF Loan 19-Dec-2012 31-Dec-2017 14.00 5.77 41.21 4.7

ADB Loan 16-Sep-2015 31-Dec-2020 105.60 0.56 0.53 2.0

ADF Loan 16-Sep-2015 31-Dec-2020 18.00 1.24 6.89 2.0

AGTF Loan 16-Sep-2015 31-Dec-2020 30.90 0.32 1.04 2.0

SUB-TOTAL 168.50 7.89 4.68 3.35

9 Iringa-Shinyanga Transmission Line ADF Loan 26-Oct-2010 31-Oct-2018 45.36 20.31 44.78 6.8

10 Scaling-Up Renewable Energy Program SCF Grant 20-Dec-2013 15-Sep-2017 0.50 0.03 5.41 3.7

SUB-TOTAL 45.86 20.34 44.35 5.25

11 Alternative Learning and Skills Development ADF Loan 29-Jun-2011 31-Dec-2017 15.00 4.10 27.33 6.2

12 Support to Technical Vocational Education and Training & Teacher

Education

ADF Loan 2-Apr-2014 31-Dec-2019 34.00 2.31 6.79 3.4

SUB-TOTAL 49.00 6.41 13.08 4.80

13 Institutional Support Project for Good Governance III ADF Loan 3-Feb-2016 31-Dec-2018 12.00 2.66 22.17 1.6

14 Power Sector Reform Program and Governance Support programADF Loan 15-Dec-2016 31-Dec-2017 50.00 50.0 100.00 0.7

15 Kikonge Multipurpose Dam, HEP and Irrigation Feasiblity Study TF 27-Jun-2016 31-Dec-2018 1.60 0.00 0.0 1.2

16 Humanitarian Emmergency Assistance for Kagera Earth Quake ADF Grant 12-Jan-2017 30-Sep-2017 0.70 0.70 100.00 0.5

17 Institutional Support Project for DRM and Natural Resources

Govermance

ADF Loan 31-Mar-2017 31-Dec-2017 19.58 0.0 0.00 0.5

83.88 53.36 63.61 0.90

FINANCE

18 TZS Line of Credit to FNB Subsidiary in TZ ADB Loan 12-Dec-2012 31-Dec-2017 31.05 14.32 46.12 4.7

19 Partial Credit Guarantee for TMRC ADB Loan 4-May-2016 Not signed 2.82 0.00 0.00 1.3

Line of Credit to CRDB Bank Ltd ADB Loan 18-May-2016 30-Nov-2017 11.00 0.00 0.00 1.2

Line of Credit to CRDB Bank Ltd ADB Loan 18-May-2016 30-Nov-2017 88.20 66.15 75.00 1.3

SUB-TOTAL 133.07 80.47 60.472.43

NATIONAL Operations 1236.98 467.49 37.79 4.06

21 Arusha-Holili/Taveta-Voi Road Project ADF Loan 16-Apr-2013 31-Dec-2018 79.90 27.01 33.8 4.4

22 Regional Rusumo Hydropower ADF Loan 27-Nov-2013 31-Aug-2019 22.41 0.44 1.96 3.8

23 EAC Centres of Excellence for Skills and Tertiary Education ADF Loan 3-Oct-2014 31-Dec-2019 6.25 0.94 15.04 2.8

24 Kenya -Tanzania Interconnection ADF Loan 18-Feb-2015 31-Dec-2019 75.29 9.75 12.95 2.5

25 Lake Victoria Maritime and Transport Project ADF Loan 24-Oct-2016 31-Dec-2019 3.77 0.00 0.00 0.9

SUB TOTAL 187.62 38.14 20.33 2.0

1424.6 505.6 35.5 3.2NATIONAL + MULTINATIONAL

B. MULTINATIONAL OPERATIONS:

AGRICULTURE

A. NATIONAL OPERATIONS:

ENERGY

WATER SUPPLY/SANITATION

Arusha Urban Water Supply Improvement Porject

SOCIAL

8

5

6

DISBURSED

AMOUNT (MUA)

APPROVED

AMOUNT (MUA )CLOSING DATEAPPROVAL DATE

PORTFOLIO BASIC DATA, 31 AUGUST 2017

SECTORSOURCE OF

FINANCEAGE ( Yrs)DISB RATE (%)

20

Dar es Salaam Rapid Bus Transit Project

Transport Sector Support Program

MULTISECTORAL

TRANSPORT

SUB TOTAL

Page 41: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

IX

APPENDIX VII: HIGHLIGHTS ON TANESCO FINANCIAL SUSTAINABILTIY ACTION

PLAN

Tanzania Electric Supply Company Ltd. (TANESCO) is credited for the country’s rapid economic

development that is among the fastest on the continent. The power utility has also a highly skilled

labor force that compares favorably well in the East Africa region, and has access to a vast and

diverse endogenous energy resource base. These factors, and its location at the intersection of the

Eastern Africa and Southern Africa Power Pool presents TANESCO with great opportunities

arising from regional power trade.

However, in the recent past TANESCO’s financial sustainability has faced serious challenges from

huge losses driven by the electricity supply crisis in 2011-2013. The crisis was mainly due to; i)

high dependence on hydropower generation and ii) inadequate forecast system for investments to

meet the rapidly increasing electricity demand. In 2010, the hydro generation represented 52% of

total capacity. The hydropower production capacity was seriously curtailed by poor hydrological

regime and the ensuing supply shortage that hit the country in 2011 forced TANESCO to enter

into short-term contract with expensive private Emergency Power Plants (EPPs). In addition, the

isolated diesel power plants have contributed significantly to TANESCO’s financial woes due to

their high maintenance and operational costs.

Since the 2011-13 electricity supply crisis, TANESCO has improved its financial performance

though tariff increases, improved hydrology, and the phase-out of EPPs. In addition, the collection

rate has increased by 50% and the Transmission & Distribution losses has reduced to 17% in 2017

from 22% in 2011. The aforementioned operation efficiency improvement has contributed to a

gross margin increase of 3% in 2017 from -53% in 2013. Although TANESCO’s cash flow is not

sufficient to meet the investment target, TANESCO has remained in positive operating cash flow

since 2014. According to the “Financial Viability of Electricity Sectors in Sub-Saharan Africa”

published by World Bank in 2016, Tanzania is in a relatively better position compared to other

African countries in terms of the recovery ratio (i.e. tariff collected /generation cost).

Despite of the current recovery, TANESCO still has cash deficit arising from larger cash outflows

than cash inflows. In order to address its financial challenges, TANESCO has planned to invest in

hydrological risks reduction through energy production diversification, implementing regional

transmission line, increasing access rates as well as enhancing grid extensions with the objective

of replacing expensive isolated diesel power plants. Accordingly, the Government submitted to

the Bank an Action Plan, summarized in the table below, to address TANESCO’s financial

sustainability challenges.

The North West Grid transmission line project (including Nyakanazi – Kigoma) will directly

contribute to the Action Plan through:

Realizing the crucial investments in the country’s Power System Master Plan;

Support Generation mix by providing evacuation lines for hydropower generation and

other renewable sources in the North Western Tanzania;

Page 42: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

X

Increase TANESCO Customer base in North Western Tanzania;

Displace Diesel Power Plants in North West Tanzania;

Enhance TANESCO’s revenue through provision of pre-paid energy meters;

Improve stability and reliability of the Power Grid in the North West Region;

Address the missing links in the Tanzania Backbone grid system that has attracted several

Development Partners including the World Bank, KfW, AfD, South Korea among others.

Highlights of TANESCO Financial Sustainability Action Plan 3 – 12 Months Planning

Horizon

Objective Strategic goal Activity

Improve

Operational

Efficiency

Reducing system energy losses - Install regional boundary meters

- Introduce Meter Register to track lifetime of meters

Enhancing revenue collection - Reinforce Revenue Protection measures

- Perform meter inspections

Streamlining processes to improve

efficiency and reduce operational

costs

- Installation of the CMS

- Comply to the Customer Service Charter (CSC)

Adoption of cost saving

technologies - Research for new technologies

Design &

Implement a

new investment

strategy

Implement project as per the Power

System Master Plan (PSMP)

- Implement projects using least cost order

- Follow the recommended generation mix

Procure projects that have Value for

Money

- Encourage private participation by procuring projects

that are easy to implement (No obligation of GoT and

TANESCO)

- Obtain projects through International Competitive

Bidding

Develop

sustainable debt

management

strategy

Enhance financial stability of the

company

- Identify genuine debts through special audit by Control

Audit General (CAG)

- Apply for a concession loan to pay for all outstanding

debts

- Extend payment period to suppliers from 30 days to 90

days

Increase customer base - Electricity Urban Areas

Implement

efficient Cost-

Based Tariffs

Implement cost-based tariff,

including a reasonable return on

capital

- Apply for tariff review after EWURA has completed

Cost of Service Study

Implement full pass-through of non-

manageable costs - Apply for quarterly Automatic Adjustment

Improving risk

management

Mitigate Foreign Exchange risks

- Service and goods providers to charge in local

currency, such as Small Power Projects (SPP) tariffs and

Gas price

- Budget to factor such costs

Establish Stabilization fund Modalities to establish special fund to cater for

unforeseen events like disasters such as draught etc.

Page 43: TANZANIA NORTH WEST GRID (400 KV NYAKANAZI KIGOMA ... · TANESCO’s energy production in Kigoma/Kasulu towns (iii) job creation and (iv) reduction in greenhouse gas {GHG} emissions

XI

APPENDIX VIII: PROJECT RISKS

Risk Description Rating Mitigations

TANESCO

Financial

sustainability

TANESCO is in a financially weak

position.

M Efforts are underway by both GoT

and DP to improve TANESCO’s

financial performance.

Financial

Management

- Delays in preparation of audit

reports;

- Ineffective budget monitoring tools.

M - Assign a Project Accountant

- Annual audits conducted in line

with Bank guidelines.

Protracted

procurement

Bidders’ queries regarding:

- Quality of tender documents;

- Outcome of bid evaluation.

M An international reputable firm

will be recruited to prepare the

tender document & participate in

the bid evaluation process.

Poor

performance

of contractors

In the recent past, a contractor handling

a large transmission line delayed

delivery due to financial constraints.

M - Consider raising performance

guarantees to 15 – 20%;

- Split the transmission line and

distribution works into 2 Lots

each;

- Ensure use of qualified sub-

contractors;

- Align project cash flow with

implementation milestones;

- Consider prequalification of

EPC Contractors.

Counterpart

funds

Delay in mobilising counterpart funds

for compensation and RAP cost.

M Engage GoT early enough to

ensure timely availability of funds

Delay in

implementati

on of EDCF

funded

substations

and/or

upstream

Geita –

Nyakanazi &

Rusumo –

Nyakanazi.

The 400 kV Nyakanazi – Kigoma

transmission line is not a stand-alone

project. It is dependent on the

implementation of upstream

infrastructure.

M - Approval of EDCF funding for

the substation will be a CP to

first disbursement;

- AfDB and KfW/AFD and GoT

are committed to implementing

the Rusumo – Nyakanazi &

Geita – Nyakanazi lines.

Negative

environmenta

l & social

impacts

Large influx of “foreign” workers from

outside Kigoma Region

H - The ESMP will include social

issues such as HIV/AIDs

campaign.

L: Low; M: Moderate; H: High