tangguh lng project e&s external panel ii (2011-2016) · requirements of the amdal as evidence...
TRANSCRIPT
Tangguh LNG Project E&S External Panel II
(2011-2016)
4th Operational Compliance Monitoring Report
July 2015
BP Berau - Project Financiers
CONFIDENTIAL
335508 PHR ENS 4 D
-
22 July 2015
Tangguh LNG Project E&S External Panel II (2011-2016)
4th Operational Compliance Monitoring Report
Tangguh LNG Project E&S External Panel II (2011-2016)
4th Operational Compliance Monitoring Report
July 2015
BP Berau - Project Financiers
CONFIDENTIAL
Mott MacDonald, Graha CIMB Niaga 16th Floor,
Jl. Jenderal Sudirman Kav.58, Jakarta, 12190, Indonesia
T +62 21 252 6588 F +62 21 252 6592 W www.mottmac.com
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
335508/PHR/ENS/4/D 22 July 2015 -
Revision Date Originator Checker Approver Description Standard
A 11.05.14 Tom Streather, Nanang Ananto, Jacqueline Hamadi Laura Jones, Anhar Kramadasistra
Marielle Rowan Simon Lidell 1st draft
B 12.06.15 Tom Streather, Nanang Ananto, Jacqueline Hamadi Laura Jones, Anhar Kramadasistra
Simon Lidell Simon Lidell 2nd
draft addressing client comments
C 10.07.15 Tom Streather Simon Lidell Simon Lidell 3rd draft addressing client
comments
D 22.07.15 Tom Streather Simon Lidell Simon Lidell Final draft
Issue and revision record
This document is issued for the party which commissioned it and for specific purposes connected with the above-captioned project only. It should not be relied upon by any other party or used for any other purpose.
We accept no responsibility for the consequences of this document being relied upon by any other party, or being used for any other purpose, or containing any error or omission which is due to an error or omission in data supplied to us by other parties.
This document contains confidential information and proprietary intellectual property. It should not be shown to other parties without consent from us and from the party which commissioned it.
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
335508/PHR/ENS/4/D 22 July 2015 -
Chapter Title Page
Acronyms & Abbreviations i
Executive Summary iii
1 Introduction 1
1.1 Overview _________________________________________________________________________ 1 1.2 Tangguh LNG & Tangguh Expansion Project (TEP) Descriptions ______________________________ 1 1.3 Scope of EPII Monitoring _____________________________________________________________ 3 1.3.1 Overview _________________________________________________________________________ 3 1.3.2 Changes to EPII’s Social Monitoring Scope from the New AMDAL _____________________________ 4 1.3.3 Changes to EPII’s Environmental Monitoring Scope from the New AMDAL _______________________ 6 1.4 Activities & Information Sources for 4
th EPII Monitoring Audit _________________________________ 7
1.5 Overview of Project Performance and Key Developments in 2015 _____________________________ 8 1.6 Limitations of the Fourth EPII Monitoring Audit ___________________________________________ 10
2 Non-Compliance (NC) Review 11
2.1 Overview ________________________________________________________________________ 11 2.2 Approach to Non-Compliance (NC) Assessment __________________________________________ 11 2.3 Non Compliances Identified in EPII 4
th Monitoring Audit ____________________________________ 12
3 Review of Monitoring & Reporting 13
3.1 Overview ________________________________________________________________________ 13 3.2 Environmental Monitoring and Reporting ________________________________________________ 13 3.2.1 Environmental Monitoring Requirements ________________________________________________ 13 3.2.2 Amdal Reporting ___________________________________________________________________ 13 3.2.3 Emissions to Water_________________________________________________________________ 14 3.2.4 Emissions to Air ___________________________________________________________________ 14 3.3 Social Monitoring and Reporting ______________________________________________________ 15 3.3.1 Social Monitoring & Reporting Requirements _____________________________________________ 15 3.3.2 Comment on Social Monitoring and Reporting in 2014 _____________________________________ 15 3.3.3 Grievance Log Review ______________________________________________________________ 20 3.3.4 2014 Social Budget Realization Review _________________________________________________ 20
4 Other Issues and Suggestions 22
4.1 Overview ________________________________________________________________________ 22 4.2 Environmental Management Issues and Challenges _______________________________________ 22 4.2.1 Invasive Species Management ________________________________________________________ 22 4.2.2 Food Waste Composting ____________________________________________________________ 22 4.2.3 Biodiesel Production ________________________________________________________________ 23 4.2.4 Storage of Waste __________________________________________________________________ 23 4.2.5 Erosion Control ____________________________________________________________________ 24 4.2.6 Hazardous Waste Permit ____________________________________________________________ 24
Contents
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
335508/PHR/ENS/4/D 22 July 2015 -
4.3 Social Management Issues and Challenges ______________________________________________ 25 4.3.1 Overview ________________________________________________________________________ 25 4.3.2 Ongoing Issues and Challenges _______________________________________________________ 25 4.3.3 Newly Identified Issues and Future Challenges ___________________________________________ 30
5 Concluding Comments 33
Appendices 34
Appendix A. ADB, JBIC Policies & Equator Principles Relevant to the Original AMDAL ______________________ 35 Appendix B. Key Documents Reviewed ___________________________________________________________ 36 Appendix C. Stakeholders Consulted _____________________________________________________________ 39
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
i 335508/PHR/ENS/4/D 22 July 2015 -
Acronyms & Abbreviations
Acronym Description
ADB Asian Development Bank
AGI Acid Gas Incinerator
AIS Alien Invasive Species
BC British Council (BP’s main Education Programme partner)
BOD Biological Oxygen Demand
CA Corrective Action
CAPs Community Action Plans
C&EA Communications & External Affairs
CEMS Continuous Emissions Monitoring System
CFO Community Financial Officer
CFR Case Fatality Rate
Co-op Cooperative
DAFW Days Away From Work
DAV Directly Affected Villages
DF Dimaga Foundation
EMP |Environmental Management Plan
EMS Environmental Management System
EP External Panel
E&S Environmental and Social
FEED Front End Engineering Design
GoI Government of Indonesia
Gvt. Government
H&S Health and Safety
IAV Indirectly Affected Villages
ICBS Integrated Community Based Security
IPIECA International Petroleum Industry Environmental Conservation Association
IPSI Indigenous Peoples and Social Issues
ISO International Standards Organisation
ISP Integrated Social Programme
JBIC Japan Bank for International Cooperation
JNCC Joint Nature Conservation Committee
KK Kepala Kampung (Village Leader)
KPI Key Performance Indicator
LARAP Land Acquisition and Resettlement Plan
LAT Lowest Astronomical Tide
LNG Liquefied Natural Gas
MoE Ministry of Environment
MoU Memorandum of Understanding
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
ii 335508/PHR/ENS/4/D 22 July 2015 -
Acronym Description
MCC Mediatama Ciptacitra (BP’s main Health Programme partner)
NC Non Compliance
NOX Nitrogen Oxides
OB Onar Baru
OL Onar Lama
PV Photovoltaic
QPR Quarterly Performance Review
RAV Resettlement Affected Villages
RIF Recordable Incident Frequency
SO2 Sulphur Dioxide
SOP Standard Operating Procedure
STP Sewage treatment Plant
TIAP Tangguh Independent Advisory Panel
TMB Tanah Merah Baru
TSDP Tangguh Sustainable Development Project
UGM Universitas Gajah Mada (BP’s main Governance Programme partner)
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
iii 335508/PHR/ENS/4/D 22 July 2015 -
Executive Summary
Introduction
The Tangguh LNG Project (the Project) operated by BP is situated on the south
shore of Bintuni Bay, Teluk Bintuni Regency, Papua Barat Province, Indonesia.
The Project is extracting natural gas from large offshore reservoirs and piping it to
an onshore LNG plant for conversion to LNG.
The External Panel Second Iteration (EPII) has been appointed to undertake
independent monitoring of the project’s compliance environmental and social
(E&S) requirements during the operational period between 2011 and 2016. E&S
requirements are defined in Lenders’ policies, finance agreements and statutory
AMDAL (Indonesian Environmental Impact Assessment) commitments.
This report is EPII’s fourth (E&S) Compliance Monitoring Report covering the
2014 reporting period.
Non Compliance Assessment Findings
EPII identified no level one or level two non complainces (NC1s and NC2s
respectively).
Review of Monitoring and Reporting
The project demonstrates general compliance with Permit requirements and the
requirements of the AMDAL as evidence by outcomes of 2014 PROPER audit
which categorised the Project with a ‘blue’ rating, meaning that the Project is
considered in compliance with its AMDAL and the applicable environmental
requirements.
An appropriate level of environmental and social monitoring is carried out by BP
and third parties and BP is considered to be generally in compliance with its
monitoring and reporting requirements.
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
iv 335508/PHR/ENS/4/D 22 July 2015 -
Other Comments & Suggestions
We have also made some suggestions as to areas where the Project may wish to
focus continuous improvement efforts in recognition of the future development of
Train 3. These relate to common activities and identify where there may be
opportunities to bring those activities in line with current international Lender
standards and guidelines. Areas of focus include invasive species management,
food and waste composting, storage of waste and erosion control.
The Social Programme continues to be well resourced and implemented. It is
resulting in sustainable development outcomes and community benefit sharing.
Key achievements for 2014 include the health programme embedding services
within the local government health department; and BP providing 4MW of
electricity for the rural electrification of local villages. BP is aware of, and is
continuing to tackle ongoing challenges related to balancing demand for
community produce with supply, livelihood market dependency, revenue sharing,
industrial development within the area and the effect that all of this has on
community relations.
Concluding Comments
In conclusion, EPII finds the Project to be compliant with Project requirements. No
critical or significant environmental and social risks have been identified in relation
to compliance with Project requirements. EPII would like to acknowledge the
openness and assistance of BP’s team leaders and the Lenders’ Consultants in
providing information and explanation and facilitating the monitoring visit.
335508/PHR/ENS/4/D 22 July 2015 1
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
1.1 Overview
This report is the External Panel Second Iteration’s (EPII) annual operational monitoring report of the
Tangguh Liquified Natural Gas facility (Tangguh LNG or the Project). EPII has been appointed to
undertake independent environmental and social (E&S) monitoring of the Project’s compliance with project
requirements during the operational period between 2011 and 2016. This is the fourth annual monitoring
report of EPII, and the eleventh EP compliance monitoring report overall, following the seven reports
produced by EPI between 2005 and 2010. This report covers Project performance from April 2014 to April
2015.
1.2 Tangguh LNG & Tangguh Expansion Project (TEP) Descriptions
Tangguh LNG is situated on the south shore of Bintuni Bay, Kabupaten Teluk Bintuni, Papua Barat
Province (formerly part of the Papua Province), Indonesia (see Figure 1.1). Tangguh LNG is extracting
natural gas from large offshore reservoirs and piping it to an onshore LNG plant for conversion to LNG,
after which it is exported by shipping tanker to markets in the Asia-Pacific region and beyond. Construction
commenced in 2005 and the first cargo of LNG was shipped in the second quarter 2009. Tangguh LNG is
anticipated to have an operational lifespan of more than 20 years with the potential for expansion
depending on reservoir performance and proofing of additional reserves.
Figure 1.1: Tangguh LNG Project Locations and Affected Communities (according to original 2003 Amdal)
Indirectly Affected Villages far from the project =
Indirectly Affected Villages near the project =
Directly Affected Villages (DAV) =
1 Introduction
335508/PHR/ENS/4/D 22 July 2015 2
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
The Tangguh LNG Environmental and Social (E&S) Project follows on from the AMDAL (Indonesian
statutory Environmental Impact Assessment) commitments and the international project finance
agreements between the Lenders and BP made in 2003. In accordance with these requirements, prior to
and throughout construction, BP has developed and implemented a number of environmental and social
management and monitoring plans, most notably: Environmental Management System (EMS); Land
Acquisition and Resettlement Plan (LARAP); Indigenous Peoples Development Framework (IPDF); and
Integrated Social Programme 1 (ISP1) 2005 -2010, which incorporated an Indigenous Peoples
Development Plan (IPDP) in accordance with the requirements of the IPDF.
Following completion of construction and the commencement of the operational phase of the Tangguh
LNG facility, ISP1 was revised to become the Community Investment Programme (CIP) 2011-2015 which
was published at the end of 2011 in advance of the first EPII monitoring audit in 2011.
All of the aforementioned documents were reviewed in detail by EPII in advance of the first audit in
November 2011 and are key reference documents for this and all future EPII audits. The additional
documents and data reviewed for this audit are listed in Appendix A.
Figure 1.2: LNG tanker moored at the site.
Source: Mott MacDonald
In 2015 the Engineering, Procurement and Construction (EPC) Contract will be awarded for the
construction of third train (Train 3), two more offshore platforms, a new receiving facility, a second LNG
jetty and other associated infrastructure: this is known as the Tangguh Expansion project (TEP). The TEP
is expected to be commissioned in 2020. The TEP will result in additional and new environmental and
social impacts and therefore it has required a new AMDAL process which was completed, approved and
came into effect in July 2014. The effect of this new AMDAL on the scope of EPII’s monitoring is discussed
in the next section.
335508/PHR/ENS/4/D 22 July 2015 3
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
1.3 Scope of EPII Monitoring
1.3.1 Overview
The detailed scope of EPII Operational Monitoring was outlined in the first annual monitoring report issued
in February 2012. In summary, the overall objectives and functions of EPII are to assess the compliance of
operational activities of the Project with the Project’s requirements:
Applicable Asian Development Bank (ADB) and Japan Bank for International Cooperation (JBIC)
policies and the Equator Principles (see Appendix A)
Production Sharing Contract (PSC) Parties and Loan Agreements
AMDAL documentation and requirements of the:
– 2002 AMDAL for Trains 1 & 2 (hereafter refered to as the old AMDAL)
– 2014 AMDAL for Trains 3 & 4 (hereafter refered to as the new AMDAL), approved July 2014
Specific statutory requirements laid out in permits
Environmental and social management plans developed by BP
EPII’s primary role is the identification of areas of non-compliance (NC) with the Project requirements.
Where NCs are identified, EPII provides practical recommendations as to how NCs can be addressed by
BP. EPII also identifies other risks and important issues that are not specifically NCs, but that EPII
suggests are addressed by BP in accordance with good international industry practice (GIIP).
In relation to topics where NC or risk findings are not presented in this report, the Project can be
considered to be fully compliant in these areas. Although this approach and this report do not aim to
identify all of the examples of GIIP and effective project performance, some such examples are highlighted
in various sections of the report. It should be noted that whilst the report focuses on areas of poor
performance, the overall conclusions of EPII after this third audit are that the Project continues to be well
resourced, appropriately managed, and is resulting in beneficial sustainable development outcomes.
Although BP is required to address NCs identified by EPII according to the project finance agreements, it is
not a project requirement for BP to follow the specific recommendations of EPII. BP formulates detailed
action plans and measures to address NC and other important issues using its own experience and
expertise. Actions recommended by EPII are suggestions aimed to assist BP in improving performance.
The EPII team hopes to add value to the environmental and social sustainability management of the
Tangguh LNG Project.
The new AMDAL resulted in some new compliance requirements coming in to effect. The ways in which
these new requirements have changed to social and environmental monitoring scope of EPII are
summarised in the following sub-sections.
335508/PHR/ENS/4/D 22 July 2015 4
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
1.3.2 Changes to EPII’s Social Monitoring Scope from the New AMDAL
Most of the changes in Project’s social requirements and comitments as a result of the TEP and the new
AMDAL comitments will result from change villages being supported by BPs social programmes resulting
from:
An increase in the size of the area and the number of communities affected by project activities, largely
as a result of the drilling new wells for train 4 in the Kokas area to the west of the Project site; and
The sub-divison of many of the villages targeted in the original AMDAL into smaller villages (due to
population growth and for political reasons1).
Now 62 ‘villages surrounding the Tangguh LNG project’ will be supported by BP programmes to varying
degrees, but the previous programmes will not be replicated in all of these villages to the same extent as
the was the case for the original 14 Directly Affected Villages (DAVs) and Indirectly Affected Villages
(IDAVs) (hereafter refered to as ‘old AMDAL’ villages).
EPII’s scope will not be affected by this change and we continue to only monitor activities in the 14 old
AMDAL villages as located in Figure 1.1.
In addition to changes to the coverage area, there has also been changes to the content, objectives and
focus of BP’s social AMDAL comitments and programmes which affect EPII’s scope. The operational
phase social requirements for the old AMDAL were translated into the Community Investment Programme
(CIP, originally referred to as the Integrated Social Programme 2: 2011-2015). EPII has been monitoring
against the CIP over the previous three audits and we undertook a mid-term evaluation of its progress in
2014.
Many of the old AMDAL requirements have been carried over into the new AMDAL, whereas some
requirements are completely new. Reporting requirements aginst the new AMDAL requirements came into
effect in January 2015. These requirements have been translated into the draft Tangguh Sustainable
Development Programme (TSDP), which is expected to be finalised and approved in June 2015. As such,
complaince against the TSDP will be considered in the fifth audit in 2016.
The CIP programmes are compared with those of the new draft TSDP in Table 1.1, overleaf, which also
provides an overview of how this effects EPII’s scope for this and future audits.
1 Fourteen viallges are required to establish a District. Districts receive more finance from the Government. Thereore, this approach of
sub-dividing villages is known in Indonesia to obtain more government finances.
335508/PHR/ENS/4/D 22 July 2015 5
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
Table 1.1: Overivew of CIP and new draft TSDP programmes and the effect on EPII’s monitoring scope
CIP/ISP2 Programmes
New draft TSDP Programmes Overview of changes to EPII monitoring scope
(from July 2014 onwards)
1. Governance No substantive change of objectives or EPII's scope
2. Communications and external affairs
3. Community health
4. Education and training 5 flagships schools required but locations still to be determined; if in 14 old AMDAL villages will affect EPII’s scope for future audits – for this audit, scope remains the same
5. Livelihoods 5. Local Economic Development Program (LED)
CIP agriculture and fisheries livelihood support programmes continuing, but new emphasis on Papuan business development. Longer time requirement to place non-hydrocarbon businesses outside of site fence into some of the 14 old AMDAL villages, but not applicable for this audit.
6. Workforce & Papuan Development
This supersedes the requirements of the original Indigenous Peoples’ Development Framework and is a now stand-alone programme2. The previous target of 85% of Papuan workforce by 2029, but this is now subdivided further into three groups which will means a slight variation to EPs scope.
7. Integrated Community based Security (ICBS)
Now stand alone programme3. No substantive change in objectives or EPII’s scope.
8. Environmental Protection Awareness
New programme with the objective of increasing local awareness, capacities, and participation related to environmental issues & applicable management practices. Applicable to 14 old AMDAL villages and therefore is included in EPII scope.
This program is not an AMDAL commitment or Lenders requirements but is an additional program in TSDP. Thus, the review on this is not of Compliance Review, but to see the output and outcome of this program on the 14 old AMDAL villages.
9. Tangguh Sustainable Project (TSP – North Shore Housing and 4+4 Mw Electricity Project
New programme with the objective of supporting and increasing communities’ standard of living in Teluk Bintuni by providing reliable energy sources and improving housing. North shore housing affects 2 of the 14 old AMDAL villages of the Weriagar and Tomu Districts, and therefore is within EPII’s scope. EPII will focus on the impact and any social risks of this project implementation on the 14 old AMDAL villages. The TSP project management itself is outside EPII scope as the project is funded by Tangguh Expansion Project and not by Lenders.
In conclusion, the most substantive changes to EPII’s social monitoring scope relate to different definitions
of indigenous peoples (IP) groups and their respective workforce targets; and,three new programmes
related to environmental protection awareness , TSP and the IEDP. Comment on BP’s progress in meeting
the old and the new requirements, and the quality of BPs internal monitoring against these requirements, is
provided in section Review of Monitoring & Reporting.
2 Under the original 2004 Amdal, this was a requirement of HR rather than ISP/CIP.
3 Previously within the CIP this was contained within the Governance programme.
335508/PHR/ENS/4/D 22 July 2015 6
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
1.3.3 Changes to EPII’s Environmental Monitoring Scope from the New AMDAL
The new AMDAL has resulted in a number of changes to environmental management at Tangguh,
principally for environmental monitoring. The new AMDAL requirements have been translated into the
Environmental Management Plan (RKL) and the Environmental Monitoring Plan (RPL) for the integrated
activities of the Tangguh Expansion Project. A summary of the key changes is set out below in Table 1.2.
Table 1.2: Old AMDAL 2002 and new AMDAL TEP 2014 and the effect on EPII’s monitoring scope
AMDAL 2002 AMDAL TEP 2014 Relevance EPII 2014 Audit
RKL-RPL refers to relevant Indonesian regulation and international requirement at that period.
Updated reference regulation, both Indonesian regulation and international requirement (IFC 2012, Equator Principles 3, ADB).
The RKL/RPL produced for the AMDAL TEP sets out the requirements for Tangguh LNG, applicable Indonesian and IFC standards and the standard for the TEP (the most stringent of the aforementioned).
The requirements and limits are set out in the Environmental Permit issued following approval of the AMDAL.
Audit has referred to the emission limits included in the new AMDAl which are in compliance with MoE Regulation no. 19/2009 on Stationary Emission Standards for Oil and Gas Business/Activity & IFC 2012
Parameter and location of management and monitoring activity as agreed in RKL-RPL 2002.
A number of the sampling locations and parameters relating to the existing Tangguh plant have changed following the updated AMDAL and water quality discharge permits.
Changes relate/ will relate to:
Surface water
Groundwater
Ambient seawater
Seabed Sediment
Ambient air
Air Emission
Changes came into effect following the approval of the AMDAL in July 2014. As such the reporting for April – Dec 2014 includes a combination of reporting against the old and new AMDALs.
Water supply only from desalination.
Included the addition of a groundwater option to replace or supple for desalination, and to reduce volumes of brine water reject.
If groundwater is used, management and monitoring plans for trains 1 and 2 will also be updated.
No effect on EPII scope for this audit.
Wastewater discharge point at -13 m LAT.
Wastewater discharge point at -6 m LAT.
During the reporting period, water quality continued to be monitored from wastewater discharge point at -13 m LAT.
The discharge point -13 m LAT in LNG jetty 1 will still be used until operation of Train 3 commences.
CEMS only installed on CEMS will be installed for all stacks in process CEMS is currently installed on two AGIs
335508/PHR/ENS/4/D 22 July 2015 7
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
AMDAL 2002 AMDAL TEP 2014 Relevance EPII 2014 Audit
stacks with significant impact, i.e. AGI and gas turbine.
area (i.e. AGI, boiler, gas turbine) with capacity >25 MW.
and two gas turbines. The results of monitoring data from the Lenders Report dated April 2014 – March 2015 have been reviewed as part of this audit.
CEMs will be installed on the new AGI, boilers and gas turbines as part of the TEP.
No effect on EPII scope for this audit.
No hazardous waste incinerator during operation stage.
Hazardous waste incinerator will be installed for operation.
Not currently applicable. It will be applicable upon commencement of TEP.
Activities at Babo not included.
Activities at Babo included within the new AMDAL.
Activities at Babo are not internationally financed and as such are not included within the EPII scope.
Comments on BP’s compliance with both the old and new requirements, and the quality of BP’s internal
monitoring against these requirements, is provided in Chapter 3.
1.4 Activities & Information Sources for 4th
EPII Monitoring Audit
The EPII team undertook its fourth annual monitoring audit between the 30th March and 13
th April 2015.
The first few days of the audit was spent in Jakarta in BP’s central offices to review the project
documentation and to participate in presentations by BP project personnel. The following week was spent
at the Tangguh LNG Facility to review the site and surrounding community conditions. Interviews were
undertaken with project and external stakeholders and focus group discussions were held in some villages
(see Figure 1.3).
Figure 1.3: Focus group discussion in Onar Baru Village
Source: Mott MacDonald Source: Mott MacDonald
335508/PHR/ENS/4/D 22 July 2015 8
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
The locations visited within and outside of the project site are presented in Table 1.3 beow. The audit
concluded with a close out meeting in Jakarta on 13th April 2015 to present the findings outlined in this
report.
Table 1.3: Locations visited
Locations visited within the Project site Locations visited outside the Project site
LNG Plant Area Arguni and Taver Villages
Combo Jetty Onar Lamu and Onar Baru Villages
Wastewater Treatment Plant Bintuni Town
Permanent Sewage Treatment Plant (STP) facility Weriagar
Plant construction phase lay-down area Tanah Merah Baru (TMB) & Saengga Villages
Central Waste Accumulation Area Babo Town
Hazardous waste storage area Manggosa Pathway
Sewage treatment plants (A, C1, C2) New Genting Oil Road linking TMB and Tofoi
Reverse Osmosis Plant
New Sanitary landfill
Existing inert landfill site
Existing organic waste landfill site and associated leachate pond
Production laboratory
Log pond and perimeter fence
Perimeter fence (including managed access point)
PLN Substation
The key types of project and external stakeholders interviewed were:
BP Jakarta-based and site personnel
Government officials at the regency and village level
Project affected people and community and Adat leaders in the Directly Affected Villages (DAVs)
BP’s Implementing partners
The full list of documents reviewed is presented in Appendix B and the full list of stakeholders that EPII met
is presented in Appendix C.
1.5 Overview of Project Performance and Key Developments in 2015
The project performed extremely well in technical terms in 2014 with a record 117 cargoes delivered. The
same can be said of environmental, health and safety performance with key achievements including:
In December 2014, the Project retained its ‘blue’ rating in its Ministry of Environment (MOE) PROPER
audit for the third year in a row, meaning that the Project is considered in compliance with its AMDAL
and the applicable environmental requirements. BP have an official objective to maintain its blue rating
in 2015, whilst striving to obtain a green rating.
335508/PHR/ENS/4/D 22 July 2015 9
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
Ongoing improvements around flaring resulted in a 25% reduction in 2014 from 2013 .
GHG emissions for 2014 were 4.73 million tonnes (mt), demonstrating a decrease in GHG emissions of
4.77mt in 2013 despite increased LNG production. The reduction in GHG emissions produced was a
result of reduced flaring and completion of a program to replace diesel power generation with electricity
from a plant at the camp area. This reduced 1000 tonnes/quarter of CO2 emission.
Strong performance in health and safety with only one recordable injury representing a 0.03%
recordable incident frequency (RIF)4. One medical treatment was reported, for which BP undertook a
detailed investigation and a review of corrective actions. No ‘day away from work’ (DAFW) cases were
reported.
In 2014 the Project implemented a four point safety intervention case to improve the occupational
health and safety statistics. The STOP Card system (CARE) (see Figure 1.4) was introduced which
encourages employees to speak up if they observe unsafe acts.
Figure 1.4: BP's STOP Card System (CARE)
Source: BP
Key social development contributions in 2014 included:
The health programme embedding services within the local government health department
representing a state of ‘development with the community’ as opposed to ‘development for the
community’.
The education programme achieving a student passing rate of 100% for elementary and junior high
and 99% in senior high.
BP providing 4MW of electricity to a substation at the site perimeter which is sold to the state electricity
utility PLN. In 2014, PLN constructed infrastructure to connect Tanah Merah Baru, Saenga and other
villages that are receiving electricity around the clock.
BP achieving the very challenging workforce targets for indigenous peoples and Papuans.
4 Recordable Injury frequency is defined as number of incidents per 200,000 man-hours.
335508/PHR/ENS/4/D 22 July 2015 10
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
These and other achievements are discussed in further detail in Chapter 3.
1.6 Limitations of the Fourth EPII Monitoring Audit
Consultation fatigue was identified as an issue by EPII during the 2013 audit and this has continued in
2014 as a result of the Amdal process. There has also been some tension with communities who have
expressed their dissatisfaction with unresolved issues related to Adat revenue sharing claims to the
government. As a result of this, it was agreed with BP that EPII would hold fewer community meetings, and
instead would focus on key informant interviews involving a smaller range of stakeholders. Despite the
above approach, one security incident occurred during consultations resulting in a security stand down, as
discussed further in section 4.3.2.5. Hence, a day of EPII community consultation activities for the audit
was lost.
335508/PHR/ENS/4/D 22 July 2015 11
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
2.1 Overview
This section presents findings of the non-compliance assessment. Its key objective is the identification of
areas where the Project is not in compliance with the Project/Lenders’ requirements. The approach to the
assessment and the categorisations used by EPII as well as the results and recommendations are
presented in the sub-sections below.
2.2 Approach to Non-Compliance (NC) Assessment
All of the information and evidence gathered from the site visit activities and information sources has been
used by EPII to identify areas of non-compliance (NC) with Project requirements. The following two levels
of NC are defined in the Project finance agreements:
a. “Level 1 [hereafter referred to as NC1] means any failure to comply with, or any action or
omission which is inconsistent with, any Environmental and Social Requirement, but which
failure, action, or omission does not constitute a Level 2 E&S Non Compliance”;
b. “Level 2 [hereafter referred to as NC2] means any failure to comply with, or any action or
omission which is inconsistent with, any Environmental and Social Requirement, but which
failure, action, or omission (considered either on its own or in conjunction with any other one or
more such failure(s), action(s) or omission(s)):
i. Has resulted in or is reasonably likely to result in material damage or harm to, or a
material and adverse impact on, the environment;
ii. Constitutes or is reasonably likely to constitute a “significant impact” for the purposes of
and as defined in the Indonesian Decree Concerning Guidelines for the Determination of
Significant Impacts (BAPEDAL Decree No. KEP-056/1994);
iii. Has resulted in or is reasonably likely to result in material damage or harm to, or a
material and adverse impact on, the lives, livelihood, quality of life, health, safety, security,
property or cultural heritage of affected people; or
iv. Has resulted in or is reasonably likely to result in the revocation of, or the refusal to grant,
any approval, consent, permit or other authorisation required for the implementation of the
Tangguh E&S Project (but only to the extent that such approval, consent, permit or other
authorisation is required for implementation of the Tangguh E&S Project at that time).”
EPII has endeavoured to apply these definitions as literally as possible, presenting conclusions supported
with evidence. Where evidence is not clear-cut and professional judgement has been used, this has been
clearly explained and justified with reasoned arguments.
Where NCs have been identified, corrective actions have been recommended to address them. EPII has
aimed to be practical with consideration of costs and constraints faced by BP, actual or predicted change
in circumstances, likelihood of effectiveness of corrective actions and where appropriate, key performance
indicators (KPIs) that can be used to measure success.
2 Non-Compliance (NC) Review
335508/PHR/ENS/4/D 22 July 2015 12
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
2.3 Non Compliances Identified in EPII 4th
Monitoring Audit
In the third annual audit EPII identified no non compliances (NC1 or NC2).
335508/PHR/ENS/4/D 22 July 2015 13
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
3.1 Overview
This section presents the findings of EPII’s review of BP’s internal and external monitoring, continuous
improvement planning, and reporting to lenders, communities and other external stakeholders in
accordance with Project requirements.
3.2 Environmental Monitoring and Reporting
3.2.1 Environmental Monitoring Requirements
BP is required to carry out regular monitoring and reporting as well as occasional studies and surveys. The
commitments arise from:
The 2002 AMDAL
The 2014 AMDAL (and associated Environmental Permit (Izin Lingkungan) No. 02.37.07 Year 2014
Dated 24 July 2014)
The PSC Parties Agreements signed in 2003
The International Standards Organisation (ISO) 14001 certified EMS: although it is not legally binding,
failure to comply could result in the loss of certification
Environmental permits issued by government authorities
Permits from the environmental authorities, in particular the Ministry of Environment including an
environmental management plan (RKL) and monitoring plan (RPL) which become statutory
requirements following their approval by the authorities.
It should be noted that additional Project activities not covered in the original AMDAL (such as dredging
work or helipad construction) have only required Environmental Management Effort and Environmental
Monitoring Effort (UKL/UPL) studies.
Where applicable to the existing Project, the environmental monitoring requirements of the new
Environmental Permit came into effect in July 2014 following approval of the new AMDAL. This relates to a
change of sampling points for surface water monitoring.
Compliance with these requirements and the results of environmental monitoring are discussed in the
following sub-sections.
3.2.2 Amdal Reporting
The AMDAL report for April to December 2014 did not contain the quarterly surface water monitoring
results obtained in June 2014 in accordance with the requirements of the 2002 AMDAL. It was noted that
there was no exceedances in the monitoring data. EPII raised this issue with BP, who confirmed that there
had been verbal agreement with the MOE that the reporting period,and the monitoring and reporting
requirements would change to follow the new AMDAL. However, there was no documented evidence of
this discussion to confirm the revised approach for reporting has been agreed. We have since been
provided with confirmation from the MOE contact. EPII recommends that written records of all verbal
3 Review of Monitoring & Reporting
335508/PHR/ENS/4/D 22 July 2015 14
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
discussions relating to permitting matters be maintained. Furthermore, monitoring and reporting
procedures should be updated to show a change in process.
To effectively manage future communications with government departments, BP has established a
governmental liaison role. EPII consider that this is a suitable approach which will formalise discussions
held and recommends that records need to be maintained of communications relating to permitting
matters.
3.2.3 Emissions to Water
In July and September 2014, the ammonia concentration of produced water reached 8.46mg/l and
8.03mg/l exceeding the 5 mg/l concentration standard in the wastewater effluent permit 125/2013. This is
an exceedance rather than a non-compliance. Permit 125/2013 includes limits on monthly loading (kg) as
well as concentrations (mg/l) and based on the wording of the permit, the non-compliance only applies
when both parameters are exceeded.
It is understood that on a number of occasions in 2014 when exceedances were identified, the water was
recirculated in the system and not discharged via the -13m LAT common outfall. Discharges to the outfall
only occurred on occasions where the water treatment system was at capacity.
On both occasions that there were exceedances in 2014, BP notified the MoE of the exceedance and
noting measures being taken to reduce ammonia concentrations from produced water. Further, BP should
be commended for going beyond the legal notification requirements and reporting to the MoE in November
2014 that there could be an exceedance based on the trends that were observed through internal water
quality monitoring5.
These exceedances represent ongoing difficulties BP has experienced in achieving the ammonia
concentration standard for produced water. BP has established a strategic action plan with the objective of
identifying methods to improve the performance of waste water treatment. Options for pre-treatment of
water are being considered and a university and research center has been appointed to lead the ongoing
investigation. EPII look forward to a resolution being reached on this point by the next annual visit in 2016.
3.2.4 Emissions to Air
There were no exceedances of external emissions to air limits within the reporting period.
5 External produced water quality monitoring results in November 2014 showed no exceedance of ammonia.
335508/PHR/ENS/4/D 22 July 2015 15
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
3.3 Social Monitoring and Reporting
3.3.1 Social Monitoring & Reporting Requirements
The CIP translates the monitoring and reporting requirements stipulated by the old AMDAL6 and the PSC
Parties Agreements into a CIP monitoring, evaluation and reporting framework. Namely:
Internal monthly programme tracking and reporting - to collect data and information to develop
preliminary findings on the progress of activities;
Internal Quarterly Performance Review (QPR) – to review the targets of activities to identify the
problems and challenges;
External bi-annual AMDAL and lenders reports7 – to monitor the progress of stated results and
commitments and to formulate recommendation; and
Annual Performance Review – to review the progress and achievement of activities, formulate
refinement and adaptation to actual context.
As well as social programme performance, one of the key parameters required to be monitored and
reported by BP is community grievances.
The old Amdal requirements for BP’s internal monitoring and reporting activities were defined in the CIP
which was applicable until January 2015, after which the new AMDAL and TSDP monitoring requirements
came into effect. Precise key performance indicators (KPIs) were still being defined by BP at the time of
the audit.
Compliance with these requirements and EPII’s opinions on the quality and outcomes of the monitoring is
discussed in the following sub-sections.
3.3.2 Comment on Social Monitoring and Reporting in 2014
Overall, EPII is of the opinion that the internal monitoring and reporting approach and systems continue to
be adequate and effective, and that BP is meeting its internal and external reporting commitments in line
with Project requirements.
The monitoring findings identified by BP in relation to each of their social programmes during the reporting
period – including the new TSDP programmes relevant since January 2015 - are summarised in Table 3.1
overleaf, along with EPII’s comments on the monitoring approach.
6 The AMDAL contains 222 social commitments for the operational phase of the project and approximately 22 of these include
specific monitoring requirements. BP informed EPII during the site visit that not all of the AMDAL social commitments were included in the scope of EPII, however it was not clarified which items were included and which weren’t. This issue will require clarification prior to the next EPII monitoring visit.
7 These reports are requirements of the PSC parties agreements lender monitoring and reporting requirements.
335508/PHR/ENS/4/D 22 July 2015 16
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
Table 3.1: Overview of BP social programme monitoring findings and EPII comment
CIP/TSDP programme
Overarching objectives Selected BP monitoring findings and plans EPII comment
1. Governance Contribution to the improvement of governance of government and civil society in accordance with transparency, accountability, and participation principles.
The Programme was largely on hold during 2014 as partnership agreements came to an end and its scope was revisited. Achievements in 2014 included:
Use of radio in Bintuni for public monitoring and
citizen oversight of budgetary spending
Development of networks between local and
central government to address specific issues
such as revenue sharing and remote community
transportation
A gap analysis of the governance programme is expected to be complete by June 2015. This will be followed by a workshop with UNDP and government, SKKMigas, to redefine the programme. Genting and Eni will be invited so that governance can be looked at holistically among the various oil projects.
The achievements reported in the April to December 2014 monitoring report provide some information on increasing civil society organisation participation levels and participatory planning.
This is understandable in light of the scale back of the programme.
However, the local election for Bupati Bintuni will happen in December 2015 where during the period before and after, the local government will be focusing on politics/election. The program will start when new Bupati is in office early 2016.
2. External Relations Promotion of mutual respect and constructive relationship between Tangguh LNG and its local stakeholders in West Papua.
In addition to ongoing grievance management,
Community Action Planning and reporting to
communities via the ‘Kadate’ newsletter, in 2014 BP
provided:
Visits for Onar and Tanah Merah Baru residents to
restricted access cemeteries
Support for several social and religious events in
the villages such as Independence Day
commemoration, Ramadan Eid and Chistmas
celebrations.
BP recognises the issue of consultation fatigue and is actively trying to manage it by not visiting the same village in the same month. In previous audits EPII flagged up that consultation fatigue may be exacerbated because the M&E and study results are not routinely fed back to the communities and stakeholders who provide the data and opinions, other than through the Kadate community newsletter, which does not go into much depth.
We previously recommended that BP finds ways to communicate these results, for instance through non-technical summaries. These recommendations still stand. However it is noted that BP did share the education results from the survey during program discussions with Fakfak and Bintuni local governments and education stakeholders.
3 Community health Supporting local government and local community to improve health quality / accessibility of services.
BP states that in 2014 local health providers achieved
a new level of empowerment as the implementing
partner YSA was fully embedded in local government
and all programmes have budget sharing. The BP’s
health staff is now monitoring from Jakarta. Key
achievements include:
Completed emergency maternity services in the
Babo Puskesmas (health clinic) and a referral
The health programme continues to be a success story for BP and BP is commended for reaching a state of integration of services with the local government.
EPII identified that there were 110 births in Babo Puskesmas in 2014 compared with 37 in 2013 which shows a local culture shift from use of traditional birth attendants, as explained at the Posyandu (see Figure 3.1).
BP reported zero cases of malaria in 2014 but EPII consultation with
335508/PHR/ENS/4/D 22 July 2015 17
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
CIP/TSDP programme
Overarching objectives Selected BP monitoring findings and plans EPII comment
service for high risk mothers established
The head of the local health department of Bintuni
regency and BP programme manager were invited
to present the malaria programme to the national
Civil Servant Empowerment ministry as a capacity
building activity.
the Puskesmas as a result of local transmission. However, 14 cases found among Genting oil workers, who had apparently been infected as a result of malaria being introduced into the area by migrant construction workers.
Lack of transport from remote villages to maternal health facilities such as that in Babo and for serious cases, to Bintuni hospital, continues to be the key challenge.
A key achievement identified by EPII is that in TMB there were zero cases of mother and child malnutrition in in 2014.
4. Education and training
Supporting local government and local community efforts to achieve an educated and skilled local population.
In 2014 the contract with the education partner British Council was completed and the partnership arrangement was re-tendered. The prequalification process failed because only one applicant passed the BP’s HSE requirements, so the process is being repeated. If the process fails for a second time, a direct appointment can be undertaken according to SKKMigas rules. Despite this, key achievements and findings in 2014 include:
Student passing rate of 100% for elementary and
junior high, and 99% in senior high.
Recruitment of 35 full time teachers paid by BP to
support elementary and high school programmes
in villages
Provisions of scholarships
Upon returning to the high school in Babo EPII were pleased to hear that in 2014 visits were facilitated to the LNG facility for school children (this was requested to EPII via the previous audit) which was well received by students and teachers alike, who found it inspiring.
The Indigenous Enterprise Development Programme (IEDP) team (see the next row) took a coordinated approach with the education teams to ensure that the education programmes are aligned with the long term objective of increasing the IP workforce on the Project and promoting Papuan businesses.
The education team has developed shcolarship database that define the beneficiaries as well as their origin and type of scholarship received.
Adult literacy and commitment to children’s education is still a key constraint to realising education objectives, and efforts in these programmes should be stepped up. However, the Education program has developed an initial literacy program in the village through PPL (field program provided by UNCEN) in 2014. This is an effort to improve community capacity in literacy as well as among the students. The literacy issues still become a challenge due to cultural constraint.
5. Livelihoods / Local Economic Development
Improving capacity of households in local community to create diversified and sustainable income sources, and empowerment of indigenous Papuan contractors to be competitive.
Under the TSDP, there is new emphasis on Papuan business development; also, there is a
2014 saw a decline in the total amount of agriculture produce supplied to Tangguh catering (provided by Indocater) as a result of a reduction in demand due to the reduction in the number of workers on site. Efforts continue to open up alternative markets. Key achievements identified by BP monitoring include:
New outlet opened in Fak Fak in Nov 2014
282 tonnes of agricultural and fisheries products
supplied to Tangguh catering from 7 stocking
points in 14 old Amdal villages - $694,000.
New cooperatives with local women to sew
During this audit many of the challenges and issues unidentified by EPII related to the agricultural programmes and these are discussed in more detail in section 4.
A suggestion for BP to improve its monitoring and reporting is to measures consumption of fisheries and agricultural produce by Tangguh LNG not according to volume, but percentage of total purchase, in order to demonstrate the trends, aiming for increased percentages of the total coming from the local communities and IPs.
There is high demand for new livelihood streams and the cooperatives in Babo expressed excitement at the opportunity offered to them for assistance with developing a fisheries and crab
335508/PHR/ENS/4/D 22 July 2015 18
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
CIP/TSDP programme
Overarching objectives Selected BP monitoring findings and plans EPII comment
requirement to place non-hydrocarbon businesses outside of the site fence.
uniforms – first uniforms in August (in wider
villages beyond DAVs)
New livelihood programmes: mangrove syrup,
fresh water fisheries.
fattening business. They have prepared the land in readiness.
New programmes under the TSDP – came into effect since January 2015 (monitoring approach still being defined)
6. Workforce & Papuan Development
Empowerment and skills development of Papuan peoples. The previous target of 85% of workforce being Papuan by 2029 still stands.
BP has developed a MoU with the local government to
improve the local Polytechnic in Fak Fak and SMK
Bintuni. 2014 achievement include
Target for 2015 was 51.5% of the workforce being
Papuan and the actual achievement was 52.1%,
so BP is on track.
Key challenge is to identify indigenous enterprise
outside the fence, to support low tech activities
9 batches of site apprenticeship programme were
completed and 40% are now working in the
Tangguh facilities
Meeting the extremely challenging workforce targets every year continues to be a commendable achievement by BP. This will get increasingly challenging as the requirement to have higher percentages of indigenous and Papuan peoples in technical and managerial roles begins.
Going forward it will be critical that the Indigenous Enterprise Development, Workforce and Education teams take a coordinated approach to achieve these objectives.
7. Integrated Community based Security (ICBS)
This is now a standalone programme8. .
Key achievements include:
Joint exercise involving police and BP
ICBS evaluation was undertaken in late 2014 (still
awaiting findings)
BP is aware of and monitoring the impact of other operators in the area, for example, Genting oil was previously using the military for security creating local tensions.
8. Environmental Protection Awareness
Increasing local awareness, capacities, and participation related to environmental issues & applicable management practices.
At the time of the audit this programme was yet to start and as such no monitoring data was available.
To be reviewed in the fifth audit in 2015.
9. Tangguh Sustainable Project (TSP – North Shore Housing and 4+4 Mw Electricity Project)
Supporting and increasing communities’ standard of living in Teluk Bintuni by:
Providing reliable energy
source through rural
electrification Supporting the
government’s north shore
housing project to protect
villages from erosion
BP provides 4MW of electricity which is distributed
to TMB, Saenga and other villages. BP states that
affordability is not a problem but willingness to pay
is. In Taroy people refused to pay because they
feel they have an entitlement as they own the gas
being used to generate the electicity. This is
another manifestation of the unresolved revenue
sharing issue.
North shore housing project major achievements
Previously electricity was only available for six hours per day via
use of gensets in the villages closest to the site, now the
villages are permanently connected. This is a great
achievement and should be commended as lack of electricity is
repeatedly identified as key constraints to health, education and
livelihoods within the affected villages. The Onar villages are
expected to be connected next, and distribution poles have
already been erected.
Some stakeholders consulted by EPII stated that they knew that
8 Previously within the CIP this was contained within the Governance programme.
335508/PHR/ENS/4/D 22 July 2015 19
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
CIP/TSDP programme
Overarching objectives Selected BP monitoring findings and plans EPII comment
. in 2014 include appointment of a feasibility
consultant, a site survey and pre-feasibility study
the North Shore Housing project is an AMDAL commitment, but
had not heard anything about it. Requests were raised for a
socialisation on the topic, which BP has agreed to do alongside
the local government once the revenue sharing issue is further
resolved.
335508/PHR/ENS/4/D 22 July 2015 20
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
Figure 3.1: Babo Posyandu (maternal health clinic)
Source: <ott MacDonald site visit 2015
3.3.3 Grievance Log Review
EPII’s review of the grievance log showed that although there were 38 entries in 2014 from seven different
villages, none were actual grievances about project performance or impacts. Rather, all communications
recorded were comments about the social programmes and requests for information, jobs or investment.
This is a satisfying achievement, and reflects the duty of care that BP is talking in relation to community
operations.
One of the people who had lodged some comments was the same individual who was responsible for the
security incident discussed further in Section 4.3.2.5. Discussions with BP’s community relations teams
revealed that this individual, and others, were known dissenters. It was recommended that in the future
when comments or communications are raised from these ‘high risk’ individuals, this is flagged to ensure
that extra care is taken when responding to not exacerbate any bad feelings or catalyse any incidents or
attacks.
3.3.4 2014 Social Budget Realization Review
Upon reviewing the 2014 budget and expenditure EPII finds that the ISP2 programme continues to be well
resourced and that the budget is largely appropriate in terms of continuing to meet Project requirements.
2014 saw the introductions of a new budget line focussing on Papuan development in accordance with
EPII’s previous recommendations and the requirements of the new Amdal.
335508/PHR/ENS/4/D 22 July 2015 21
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
The 2014 budget absorption was 73.1% with underspends in all budget lines except in education and
vocational training. This was as a result of the primary focus being on the Amdal for the TEP, and the
context of wider economic constraints resulting from the reduction in oil prices.
335508/PHR/ENS/4/D 22 July 2015 22
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
4.1 Overview
This chapter identifies other environmental and social issues identified as part of the audit and offers
suggestions for continual improvement.
4.2 Environmental Management Issues and Challenges
4.2.1 Invasive Species Management
Since the last EPII audit visit, an increased prevalence of Mimosa, an invasive species (but not considered
by BP to be an Alien Invasive Species (AIS) was noted on site, leading to concerns that the increased
abundance of this species is adversely affecting the natural habitat. It is understood that the flora and
fauna survey, which is currently out for tender and will be undertaken in late 2015/early 2016, will include a
review of invasive species on site. It is recommended that following the survey, a weed and pest
management programme is developed and implemented for the control of invasive species.
Figure 4.1: Evidence of Mimosa at the onsite log pile
Source: Mott MacDonald
4.2.2 Food Waste Composting
The onsite food waste composter operated for one month in 2014 before being shut down due to a
breakdown of an electrical component of the plant. Previously, the composter had been shut down for
more than two years while agreement for sourcing a replacement part was agreed with the authorities.
These shutdown periods resulted in unprocessed food waste going directly to the organic waste landfill,
which is against the GIIP ‘4Rs’ (reduce, reuse, recycle and recovery of waste). The use of the composter
4 Other Issues and Suggestions
335508/PHR/ENS/4/D 22 July 2015 23
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
to reduce the amount of waste going to landfill would assist BP to achieve a green ranking in the PROPER
audit, where efforts for waste minimisation are a ranking consideration.
EPII consider that in future BP should adopt a more proactive approach to avoid similar delays. It is
recommended that the preventative management programme for the composter is reviewed to increase
the frequency of maintenance periods, to identify spare parts which should be procured, and to lessen the
duration of any future outage periods. Once the composter returns to operation, it is recommended that BP
identify local villages that would benefit from receiving a proportion of the compost produced.
4.2.3 Biodiesel Production
Previously EPII reported on the success of the laboratory trials held at Tangguh to convert used cooking
oils to biodiesel for use in onsite vehicles (see Figure 4.2). Whilst there have been some delays in
establishing the full biodiesel production programme on site, tenders for a biodiesel mini pilot plant with a
capacity of 100 litres/batch will be commissioned by the end of 2015. This will not only reduce the use of
conventional fuel used by on-site vehicles, it will also reduce transportation and disposal costs of waste
cooking oils which currently are sent to West Java for disposal.
Figure 4.2: Laboratory trials of biodiesel
Source: Mott MacDonald
4.2.4 Storage of Waste
During the visit to the reverse osmosis (RO) plant, it was noted that several drums of waste, including
waste oil (hazardous), were labelled and stored incorrectly on the edge of the bund wall. In the event of a
spillage there is a risk that it would not be contained. It is understood that the contractor responsible for the
RO plant was waiting for the waste to be removed. Regardless, waste should have been stored correctly. It
is important that BP ensure that all contractors are made fully aware of the procedures for waste handling,
storage and disposal. The EPII does not consider this to represent a significant issue, but does highlight
the need for regular site inspections and training of contractors. This is particularly pertinent given the
future works planned.
335508/PHR/ENS/4/D 22 July 2015 24
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
4.2.5 Erosion Control
During the visit to the new inert and organic waste landfill site, evidence of soil erosion was observed. A
number of gullies have formed on land adjacent to the landfill area (as shown in Figure 4.3), with soil runoff
going into a drainage channel and in the direction of the natural waterway at the site boundary.
Furthermore, it was noted that the drainage channel does not extend as far as the site boundary resulting
in further erosion channels developing at the outfall of the drainage channel (refer to Figure 4.4). As a first
step, it is recommended that the erosion control berms are installed in areas where rill erosion is occurring
and the area of bare earth is re-vegetated. The drainage channel termination should also be reviewed with
a suitable collection sump or tie into any existing drainage network.
Figure 4.3: Evidence of erosion on land adjacent to the
new landfill site
Figure 4.4: Erosion channels from the drainage channel
outfall in the direction of the natural water way
Source: Mott MacDonald Source: Mott MacDonald
4.2.6 Hazardous Waste Permit
The EPII report 2014 reported that BP had not obtained a hazardous waste permit, as a result
longstanding issue that is related to third party administrative function outside the control of BP. A
hazardous waste permit (188.4.5/A-39) has now been obtained from the Bintuni Regency for the temporary
storage of hazardous waste at site, which allows hazardous waste to be stored for a maximum of 90 days
on site.
335508/PHR/ENS/4/D 22 July 2015 25
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
4.3 Social Management Issues and Challenges
4.3.1 Overview
4.3.1.1 Overview
The sub-section below discusses a number of ongoing issues identified in previous EP audits and already
recognised by BP, namely challenges faced by the livelihood programmes, and issues of community
dependency, revenue sharing, transport and community relations challenges. A number of new issues are
identified relating to the potential resettlement of the Onar villages, risks resulting from the area opening
up, oil price fluctuations and the change in government in 2015.
4.3.2 Ongoing Issues and Challenges
4.3.2.1 Balancing Livelihood Programme Supply with Project Demand for Produce
The ongoing challenge of balancing the Project’s need for agriculture and fisheries products (see Figure
4.5) with the supply from the communities persists. This issue has been identified previously by EPII and is
considered very important because Indocater, the site produce supplier, is the main and in many cases the
only market outlet for local communities who are largely dependent on the company for their agriculture
production income.
Figure 4.5: Fisheries Livelihood programme Produce
Source: Mott MacDonald
335508/PHR/ENS/4/D 22 July 2015 26
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
4.3.2.2 Communities’ Market Dependence on BP
Addressing this issue is critical to the success of BP’s livelihood programmes. This can be seen though
examples of failed initiatives such as the agricultural cooperative in Onar Baru that disbanded a few years
ago due to demand not matching supply and loss of motivation in the village. There are now only three
active farmers in Onar Baru which would make the reestablishment of a cooperative challenging.
The importance of ’local content’ (in this case, procurement of local produce) to the sustainability of the
Tangguh Project is recognised in the new Amdal which includes the target of 65% of agriculture and
fisheries produce being consumed by the Project as coming from the local communities after train 3 is
operational in 2020. EPII noted to BP that only the total tonnage of produce that is consumed from the
local communities is being reported, rather than the percentage of the total consumption by Indocater
coming from the communities. Therefore, it is difficult to monitor progress in reaching this target. It was
suggested to BP that the monitoring and reporting approach is revised to address this As of December
2014 they were at 25% of fisheries produce and 17% of agricultural produce coming from the local
communities.
EPII village consultation identified a number of cases of over-production in the communities. Some
frustration was expressed by cooperatives that both fisheries and agricultural produce was not being
purchased and as such was being wasted. Farmers and fishers indicated this was adversely affecting
livelihoods in cases where producers did not receive economic return for their labour. There appears to be
four main challenges causing this, as outlined below, along with EPII suggestions to consider overcoming
them:
1. Minimum consumption contracts: it became apparent through community consultation that BP has
agreed contracts with a number of cooperatives guaranteeing a minimum purchase (tonnage) per
week.9. EPII suggests that in light of demand varying from month to month, it does not make sense to
have minimum purchase agreements and these should be revised. Furthermore, there needs to be
more regular and timely communication to communities about changing demand levels as was
specifically requested by some communities consulted by EPII.
2. Meeting minimum produce quality requirements: producers must meet the strict regulatory and
Project produce quality requirements relating to sanitation, hygiene, produce type and size. Produce is
inspected at the stocking points and if requirements are not met, it cannot be purchased. Overcoming
this is challenging and BP’s agriculture team is diligently working to raise production standards on an
ongoing basis.
3. Adverse weather and produce transport challenges: sometimes the produce collection boat cannot
travel to the stocking points to collect the produce before it has perished and cannot meet the quality
criteria. EPII, BP and the local government recognise that this issue of transport is a cross-cutting
challenge which affects many aspects of daily life.
9 EPII has reviewed a sample of one of these contracts and can verify the claims made by communtiies of a guaranteed minimum
purchase.
335508/PHR/ENS/4/D 22 July 2015 27
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
One solution proposed by cooperatives in Tanah Merah Baru who have requested that BP to allow
delivery of produce by land through the site fence. BP is looking in to this, but it may not be possible for
security reasons. BP is also investigating the opportunity to upgrade the boats so they have higher
capacity for produce storage.
4. Communities’ market dependency on BP: BP is fully aware that the overarching and longer term
issue is the communities’ market dependency on BP, as discussed in more detail in the following
section.
BP has stated that its livelihoods team will work on a strategy with the Project logistics team to overcome
the challenges that the EP has identified in order to increase local production and purchases.
BP are considering a number of options to open up alternative markets for agriculture and fisheries
produce in the Bintuni and Fak Fak regencies and beyond, including:
Discussing opportunities to supply a shipping company in Babo with crab and agricultural produce.
There has also been interest and demand expressed from traders from Kokas and Bintuni, however
the cost of transport is making this prohibitive at present.
The Mayri Cooperative has plans to develop a village outlet in TMB to sell excess supplies.
Discussions with local government about a joint strategy to penetrate markets further afield in Java and
beyond.
EPII feels that, when considering new livelihood initiatives such as the crab cultivation scheme being
conceived in 2015, greater consideration should be given to market penetration strategies early in the
planning process. If schemes are to be sustainable, efforts should be made to ensure that schemes are
designed not only to provide services to the Project in the short term, but also to gain access external
markets and demand for produce and services.
One example where this was not done was the bicycle repair business established in Babo in 2012. The
business progress was noted in previous EP audit reports. The livelihood team provided training, business
support and inputs to a team of local people to set up a workshop to provide bicycle repair services to
Project workers and community members. However, in Q2 2014 when BP stopped sending bicycles to
Babo for repair, the business quickly ceased to operate. This demonstrates the market dependence of the
initiative on the Project.
BP states that the failure of the bicycle repair business is also due to the greater availability and use of
motorcycles in recent years, a trend which EPII feels could have been identified at inception of the
livelihood scheme.
EPII suggests that lessons could possibly be learnt from Onar Tengah (‘Centre Onar’), the recent village
that has come into existence through economic migrants who have travelled to the area to pursue shrimp
and fisheries opportunities. They appear to be independently running successful enterprises and have
access to other markets. Whilst it is recognised that they are more experienced and established fishermen
with additional skills and resources for transporting produce to market and providing credit, opportunities
335508/PHR/ENS/4/D 22 July 2015 28
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
could be considered to learn from them in relation to market diversification and business
professionalisation.
4.3.2.3 Effective Functioning of Cooperatives and Jealousy over Stocking Point Locations
Some Onar Baru farmers stated that payment from the Mayri Cooperative10
in Tanah Merah Baru often
takes one or two months after produce is delivered. Some Onar Lama farmers claim that the cooperative is
two years behind with payments and it owes six million rupiah to farmers in the village. The Mayri
cooperative acknowledged to EPII that there are often delays in payment. The cited reasons related to
weather and tidal conditions, transport challenges, and also their inexperience with accounting. Whilst last
year farmers received support from Bina Swadaya in improving production, they stated that they did not
receive any business mentoring and that they need this to function more effectively.
Both Onar villages have requested assistance from BP with establishing their own cooperative, rather than
having to transport their produce to Tanah Merah Baru stocking point. This would save them the expense
of transport and could prevent the long waits for payment. They want to be able to sell produce directly to
Indocator and have a stocking point established in the Onar villages. In Weriagar too, there were
complaints to EPII that stocking point management needs improvement with better communications about
collections.
As noted previously, earlier efforts at establishing cooperatives in the Onar villages failed partly due to
supply and demand issues. However, in both Onar villages it was widely acknowledged that the UBSP
women’s savings and loans schemes were the most successful operational institutions. One option to
reduce dependence on the Mayri Cooperative could be to use UBSP’s capital to establish a new Onar
cooperative.
4.3.2.4 Revenue Sharing and its Effect on Community Relations
The socialisation activities to present the new Amdal to the communities have been delayed due to the
lack of resolution regarding revenue sharing and the north shore Adat communities’ claims for 54 billion
rupiah from the local government. This has resulted in some tensions with the local communities who hold
BP partly responsible, despite the fact that this issue is the responsibility of the government.
EPII commends BP for its efforts to facilitate the resolution of this issue through, for example, continuing
advocacy for a ‘Perdasus’ (special bylaw) mechanism so that revenue is not just shared at regency level,
but flows down to local Adat community leaders. Efforts are ongoing to get the draft regulation enacted. BP
also facilitated a workshop in February 2015 to introduce oil and gas industry revenue sharing to house
representatives of Teluk Bintuni regency, NGOs and university representatives.
In addition, EPII suggests that BP repeats the community socialisations held previously in 2014 on revenue
sharing, to explain that it is not BP’s responsibility to enact Perdasus, but that BP is doing what it can to
push the government towards resolving the issue. This would go some way to addressing misinformation
10
The Mayri cooperative in TMB has 80 farmers (up from 70 in 2014) from TMB, Tofoi, Saenga and Onar Lama and onar Baru.
335508/PHR/ENS/4/D 22 July 2015 29
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
in the communities. For example one of the Kepala Kampungs of consulted in the North Shore villages
stated a common north shore perception that the benefits of the oil and gas revenue to the provincial and
regional government were in the region of twelve trillion per year, and there is little evidence of it trickling
down to small communities.11
4.3.2.5 Community Relations
Community frustration continues threaten community relations manifested in security incidents that lead to
‘safety stand downs’ (temporary withdrawal of staff from villages). There were two security stand downs in
2014. Both were the result of boat detentions (obstruction). Such incidents disrupt the Project’s social
programmes.
During the audit on Sunday 5th April the EP and the Lenders Consultant’s team experienced one such
incident when its boat was attacked and a window was smashed (see figure. Upon investigation this was
caused by one agitator acting alone rather than an organised action. It was concluded that he did not have
a valid grievance, but it meant that there was a security stand down in the village which was to the
detriment of the community.
EPII recognises that such incidents can never be completely avoided and believes that overall BP has
fostered good community relations to date, in light of high expectations and dissatisfaction with the
government. Continuing to monitor and analyse grievances closely, especially from known agitators as
discussed earlier, is important to maintain the harmonious relations and manage any dissent. This is
especially relevant as BP informed EPII that recently a community threatened to undertake a sit-down
protest on an LNG jetty unless BP resolves the revenue sharing issue and pays the 54 billion rupiahs. BP
states that if this happens, the military will have to be called in as a last resort to prevent Project operations
being disrupted.
4.3.2.6 Coordination with Local Government
Whilst in some areas BP has achieved great success in coordinating its programmes with local
government (Pemda) in 2014, for example in health, Pemda repeated comments made to EPII in previous
audits that there could be more regular communication to better align some programmes. BP responded
that its implementing partners regularly communicate with Pemda, although it was acknowledged that the
new Amdal process has delayed meetings with local government in 2014 and that this will be stepped up in
2015. A significant coordination and collaboration also happened in agriculture program. Tangguh
Livelihood team fully supported the local government program on its rice plantation project in Bintuni
during end of 2014. Tangguh provided technical assistance and expertese while the project was lead by
the local government.
The last meeting between BP and Pemda was held in January 2015 to synchronise the timing of planning
and budget expenditure. The next one is planned in August to support the development of Bintuni RPJMD
(5 year plan 2016-2020). Also, there were smaller meetings between TSDP program staff with the relevant
11
He stated that his information source was the local newspaper.
335508/PHR/ENS/4/D 22 July 2015 30
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
departments in the regency governments based on programs needs. There is also Bintuni 12th
anniversary event on 9th June, 2015 where BP management will meet with Bupati Bintuni as well as
exhibition booth at the government’s event in Bintuni town.
EPII suggests that consideration is given to holding quarterly meetings to share results and scheduling.
EPII feels that a key objective should be for the government to be seen to have an equal presence in the
villages as BP and its partners12
, to counter the culture of villages being dependent on BP for social
services.
4.3.3 Newly Identified Issues and Future Challenges
4.3.3.1 Potential Resettlement of the Onar Villages
The location of the Onar villages has tentatively been identified by the government as an industrial
development area where a downstream petrochemical production is to be located. This is likely to result in
the resettlement of the villages.
Many of the villagers in Onar Baru have not yet received their land ownership certificates from the
government following their resettlement from Onar Lama. The certificates cannot be issued by BP until the
land status is converted by the government from ‘Productive Forest’ to ‘Land for ‘Specific Use’. Without
these land certificates, residents do not have legal entitlements to compensation for loss of land as a result
of future resettlement to facilitate this planned industrial development.
The new petrochemical plans pose potential impoverishment risks to the Onar communities and
reputational risk to the Project and BP resulting from resettlement of the Onar communities for a second
time. BP recognises this, and although it is not BP’s formal responsibility to convert the status of the land,
BP continues to make considerable efforts to resolve the land registration issue, and to obtain more
information about potential displacement.
4.3.3.2 Economic Development of the Area
The aforementioned petrochemical economic development plans are indicative of the area opening up to
industrial and commercial development. As normal, the development poses risks and opportunities and will
require coordinated management. In 2014 Genting oil completed construction of a highway linking Tanah
Merah Baru and Tofoi villages just a few metres from the Mangossa pathway and the Project’s perimeter
fence (see Figure 4.6). Apparently there are plans to extend the highway to Saenga.
12
Some villagers stated to EPII that they only saw BP in the villages, not government officers.
335508/PHR/ENS/4/D 22 July 2015 31
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
Figure 4.6: New Genting Oil Highway adjacent to the Project site perimeter
Source: Mott MacDonald
Risks may occur from the influx of other oil and gas companies. There are likely to be economic migrants
with related influx problems, some of which are already being seen. For instance, malaria was reintroduced
into Tanah Merah Baru from Genting Oil construction labour forces. Other cumulative impacts include
environmental degradation, dilution of traditional culture, and disruption of community relations as a result
of the differing approaches of companies operating in the area.
4.3.3.3 Oil Price Fluctuations and Budget Reductions in 2015
Due to the recent reduction in oil prices there are expected to be budgetary cuts to BP’s social
programmes over the next monitoring period. This may pose constraints on meeting programme objectives
and achieving outcomes and process efficiency improvements could be explored.
4.3.3.4 The Change in Government in 2015
The 2014 presidential elections mean new political bodies and a new house of representatives at the
provincial and regency levels. BP has had to divert resources to efforts to form new relationships with
government, and this will continue following the local elections in 2015. In addition, some programs,
especially the governance program, will slow down in 2015 due to the election activities by the local
government, until the new Bupati is in office.
335508/PHR/ENS/4/D 22 July 2015 32
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
Figure 4.7: EPII, Lenders’ Consultant and BP team with Onar Baru villagers
Source: Mott MacDonald
335508/PHR/ENS/4/D 22 July 2015 33
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
Tangguh LNG continues to demonstrate a high level of project compliance with environmental and social
requirements. No environmental or social non-compliances have been identified.
EPII finds that the Project continues to operate a well-defined Environmental Management System and
that key issues are identified and dealt with adequately. Going forward, a key action will be disseminating
the new requirements of the AMDAL to all employees, particularly to contractors.
The Social Programme continues to be well resourced and implemented. It is resulting in sustainable
development outcomes and community benefit sharing. Key achievements for 2014 include the health
programme embedding services within the local government health department; and, BP providing 4MW of
electricity for the rural electrification of local villages. BP is aware of, and is doing a good job of tackling
ongoing challenges related to livelihood dependency, revenue sharing and industrial development within
the area.
In conclusion, EPII finds the Project to be compliant with Project requirements. No critical or significant
environmental and social risks have been identified in relation to compliance with Project requirements.
EPII would like to acknowledge the openness and assistance of BP’s team leaders and the Lenders’
Consultants in providing information and explanation and facilitating the monitoring visit.
5 Concluding Comments
335508/PHR/ENS/4/D 22 July 2015 34
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
Appendices
Appendix A. ADB, JBIC Policies & Equator Principles Relevant to the Original AMDAL ______________________ 35 Appendix B. Key Documents Reviewed ___________________________________________________________ 36 Appendix C. Stakeholders Consulted _____________________________________________________________ 39
335508/PHR/ENS/4/D 22 July 2015 35
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
Policy
ADB Tranche Lender JBIC
Equator Principles & associated policies
Environment, health and safety
Environment Policy of the Asian Development Bank (ADB document no. R154-02, November 2002)
JBIC Guidelines for Confirmation of Environmental and Social Considerations of April 2002 (but excluding any portion thereof relating solely to (i) the disclosure of information regarding confirmation of environmental and social considerations to concerned organizations, stakeholders and other third parties, and (ii) the submission to JBIC by concerned organizations and stakeholders of objections relating to the non-compliance of the Tangguh Project with JBIC’S stated policies) (the JBIC Guidelines)
The World Bank Pollution Prevention and Abatement Handbook 1998 incorporating Industry Sector Guidelines for Oil & Gas Development (Onshore)
International Finance Corporation (IFC) Operational Policy for Environmental Assessment (OP 4.01), October 1998
IFC Environmental, Health and Safety Guidelines for Oil and Gas Development (Offshore)
IFC Operational Policy for Natural Habitats (OP 4.04), November 1998
IFC Operational Policy Note for Management of Cultural Property (OPN 11.03) of September 1986
The Equator Principles, June 2003.
IFC Operational Policy 4.01 Environmental Assessment (October 1998)
IFC Operational Policy 4.04 Natural Habitats (November 1998)
IFC Operational Policy 4.09 Pest Management (November 1998)
IFC Operational Policy 4.36 Forestry (November 1998)
IFC Operational Policy 7.50 International Waterways (November 1998)
IFC Operational Policy Note 11.03 Management of Cultural Property (September 1986)
The World Bank Pollution Prevention and Abatement Handbook 1998 incorporating Industry Sector Guidelines for Oil & Gas Development (Onshore)
IFC Environmental, Health and Safety Guidelines for Oil and Gas Development (Offshore)
Involuntary resettlement
Involuntary Resettlement (ADB document no. R179-95, August 1995)
The JBIC Guidelines
IFC Operational Policy for Environmental Assessment (OP 4.01), October 1998
IFC Operational Policy for Involuntary Resettlement (OP 4.30) of June 1990
IFC Operational Policy Note for Management of Cultural Property (OPN 11.03) of September 1986
The Equator Principles, June 2003.
IFC Operational Policy for Environmental Assessment (OP 4.01), October 1998
IFC Operational Policy for Involuntary Resettlement (OP 4.30) of June 1990
IFC Operational Policy Note for Management of Cultural Property (OPN 11.03) of September 1986
Indigenous peoples
Policy on Indigenous Peoples (ADB document no. R55-98, April 1998)
The JBIC Guidelines
IFC Operational Policy for Environmental Assessment (OP 4.01), October 1998
IFC Operational Directive for Indigenous Peoples (OD 4.20), September 1991
IFC Operational Policy Note for Management of Cultural Property (OPN 11.03) of September 1986
The Equator Principles, June 2003.
IFC Operational Policy for Environmental Assessment (OP 4.01), October 1998
IFC Operational Directive for Indigenous Peoples (OD 4.20), September 1991
IFC Operational Policy Note for Management of Cultural Property (OPN 11.03) of September 1986
Others Public Communications Policy (March 2005)
Child and Forced Labour Policy Statement (March 1998)
Appendix A. ADB, JBIC Policies & Equator Principles Relevant to the Original AMDAL
335508/PHR/ENS/4/D 22 July 2015 36
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
The first EPII monitoring report (January 2012) listed all of the key contextual documents reviewed
including the PSC Parties Agreements, the AMDAL documentation, the Land Acquisition and Resettlement
Action Plan (LARAP), the Indigenous People’s Development Framework (IPDF), the Integrated Social
Program (ISP) I and the Community Investment Programme (CIP), amongst others. Those documents
have been returned to as key compliance reference points for this audit. Table B.1 lists the new documents
reviewed.
Table B.1: Documents reviewed
Type of Document Document Title Author
PPT. Update Presentations to EPII in April 2015
Joint Lenders EP and Consultant Visit, March 2015 – Tangguh Environmental Programs
BP
HSE overview (dated 31 March 2015) BP
Environmental and social sensitivity map of Bintuni – Berau Bay, west Papua (March 2015)
BP
Tangguh Sustainable Program BP
Tangguh Update (30 March 2015) BP
Community Relation (CAT) Program and Yayasan Dimaga BP
TangguhSocial Program Update BP
Amdal 2002 vs Amdal 2014 (September 2014) BP
Education Program Update - Growth and develop together in West Papua, 3 April 2015
BP
Governance Program Update -Growth and develop together in West Papua
BP
Papuan Capability BP
Papuan Development, External Panel – 31 March 2015 BP
Lenders External Panel Visit - Health Overview, 1st 2015, March31st,2015
BP
Integrated Community-Based Security BP
AMDAL / Environmental Monitoring documentation
AMDAL Report April – Dec 2014 BP
CEMs Emissions Report (Jan - March 2014) BP
CEMs Emissions Report (April – June 2014) BP
CEMs Emissions Report (July – September 2014) BP
Flaring Implementation Report at Tangguh LNG (Jan – June 2014) BP
Hazardous and toxic waste management implementation report (Jan – March 2014)
BP
Hazardous and toxic waste management implementation report (July - Sept 2014)
BP
011-ISP-WP-7003 (J714019) Fugitive Emissions ORF Overall BP
Surface Water Monitoring Points (old and new AMDAL) BP
Environmental Management Plans (2014) (set of 13) BP
Environmental Management Plans (2015) (set of 15) BP
Environmental Aspects Impact dentification (EAI 2014) BP
Appendix B. Key Documents Reviewed
335508/PHR/ENS/4/D 22 July 2015 37
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
Type of Document Document Title Author
Environmental Aspects Impact dentification (EAI 2015) BP
Hazardous Waste Permit (Indonesian) BP
Wastewater Discharge Permit BP
PRC-EN-2325 Environmental Sampling and Anaysis Protocol for External lab
BP
900-PRC-EN-2337 Environmental Audit Procedure BP
900-PRC-EN – 2320 Environmental Monitoring BP
900-PRC-EN – 2331 Non hazardous solid waste procedure BP
900-PRC-EN – 2324 Wastewater Management procedure BP
900-PRC-EN – 2326 – Environmental Communication BP
900-PRC-EN - 2329 – Marine Mammals and sea reptiles protection BP
900-PRC-EN – 2330 – Flora and Fauna Protection Procedure BP
900-PRC-EN – 2333 – Environmental aspect and impact identification
BP
920-MAN-EN – 2301 – EMS manual BP
900-PRC-HE – 1001 – HSE Training procedure BP
900-PRC-HE – 2750 – HSE Document Record Control process BP
920-PRC-HS-2245 HSE Regulatory Compliance Management BP
920 – WIS – HS-2432-03 Temporary Secondary Containment. BP
PROPER Certificate 2013 BP
Wastewater discharge activity to sea (Jan – March 2014) BP
Wastewater discharge activity to sea (Apr – June 2014) BP
Wastewater discharge activity to sea (July – Sept 2014) BP
Operators EHS Report (Oct 2013 – March 2014) BP
ANDAL chapter 2 – Environmental Baseline (Feb 2015) BP
Project Executiion Plant – Transfer wooden logs from log pond to TMB village (June 2014)
BP
Weekly Monitoring (2014) BP
CEMS reporting data – January to December 2013 BP
Internal Production daily report (2014) BP
Notice of exceedence of Ammonia (8 July 2014) BP
Notice of exceedence of Ammonia (7 Sept 2014) BP
Notice of potential exceedence of Ammonia (15 November 2014) BP
GHG Workbook BP
Biodiesel presentation (March 2014) BP
900-PRC-CM-1001 Oil Spill Continency Plan BP
Personal Benzene Monitoring 2013 BP
Energy Efficiency Review BP
Operator’s Environmental, Health and Safety Report BP
335508/PHR/ENS/4/D 22 July 2015 38
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
Type of Document Document Title Author
Tangguh LNG, April 2014 – December 2014 (issued to Lenders)
Tangguh Operation Monthly Report Dec 2014 BP
Tangguh Operation Monthly Report Jan 2015 BP
Tangguh Operation Monthly Report Feb 2015 BP
Tangguh LNG Produced Water Management Update. Notice of Exceedance Dated 08 July 2014
BP
Tangguh LNG Produced Water Management Update. Notice of Exceedance Dated 07 September 2014
BP
External surface water monitoring results (June 2014) BP
Tangguh LNG Produced Water Management Update. Dated 15 November 2014
BP
Environmental management plan (RKL) and Environmental Monitoring Plan (RPL) Integrated activities of the Tangguh LNG Expansion Project, Taluk Bintinu and Fakfak Regencies, Papua Barat Province (August 2014) including Appendix 1: Relevant Environmental Standards.
BP
Greenhouse Gas Workbook BP
Biosludge Report update (Indonesian). BP
Tangguh Waste Biodiesel 25 March 2014 BP
Grievance log BP.
BP Partner reports /evaluations in Bahassa
Introduction of Oil and Gas Industry socialization and DBH To the Legislative and Local Government Staff Teluk Bintuni
The Board of Research , Study and Development of Legal Aid, LP3BH Manokwari
UPAYA MELESTARIKAN BAHASA DAN KESENIAN LOKAL MASYARAKAT ADAT SUMURI, KEMBERAN DAN NDAMBAN
(EFFORTS TO PRESERVE LANGUAGE AND ARTS, LOCAL COMMUNITY, ADAT wells , Kember AND Ndamba
Tim Peneliti, STUDY CENTER Melanesian
UNIVERSITY CENDERAWASIH, JAYAPURA
2014
CAPs evaluation study Institute for Research and Community Services, Cendrawasih Uni.
335508/PHR/ENS/4/D 22 July 2015 39
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
Table C.1 and Table C.2 below list the stakeholders interviewed by EPII, and some of this consultation is
depicted in Figure C.1 to Figure C.5 overleaf.
Table C.1: External Stakeholders Consulted
Stakeholder Location Date
King (traditional leader) Kepala Kampung (village head) of Arguni Arguni & Taver Villages (New Amdal villages)
Saturday 4th April
Head of Fisheries Cooperative
Deputy Kepala Kampung (village head)
Adat leaders
Male and Female SD (primary) school teachers
Onar Baru (new) Village
Monday 6th April
Kepala Kampung (village head)
Head of Onar Lama UBSP Savings and Loan Cooperative
YSA Health Programme Cadres
Onar Lama (old) village
Meeting with Bintuni Regency Government representatives including from the Bapeda (planning), Trade and Cooperatives, Fisheries, Infrastructure, Health and Education departments
Bintuni Town Tuesday 7th April
Meeting with Weriagar District Head and heads of the Kepala Kampungs of the six villages in the dirstrict
Head of Puskesmas
Weriagar Village Wednesday 8th April
Kepala Kampung (village head)
Head of Mayri (Agriculture) Coperative
Sampoerna FoundationsSchool Head and teachers
Head of Puskesmas
Tanah Merah Baru village
Thursday 9th April
Babo Stocking Point crab fattening Cooperative Heads (x 2)
Babo High School Head, teachers and students
Head of Puskesmas and Posyandu
Babo Iratutu III Village
Friday 10th April
Appendix C. Stakeholders Consulted
335508/PHR/ENS/4/D 22 July 2015 40
Tangguh LNG Project E&S External Panel II (2011-2016) 4th Operational Compliance Monitoring Report
CONFIDENTIAL
Figure C.1: Meeting with the King of Arguni Figure C.2: Woman’s focus group discussion in Onar
Lama
source: Mott MacDonald source: Mott MacDonald
figure C.3: Meeting with the Kepala Kampung of Tanah
Merah Baru
Figure C.4: Meeting with the Sampoerna Foundation
model-) School in Tanah Mera Baru
Source: Mott MacDonald
Figure C.5: Meeting with the Weriagar District and the village heads
Source: Mott MacDonald