Tafila Wind Farm Jordan Wind Project Company PSC EIB Investments in Renewable Energy outside EU By: Samer S. Judeh, Chairman 26 th April, 2017

Upload: others

Post on 05-May-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Tafila Wind Farm · 2019-03-20 · Timeline Q2 2011 MOU Signed with GOJ Q4 2013 PPA / EPC / Finance Docs signed Q2 2014 Commenced site works (21 month construction period) Q1 2015

Tafila Wind FarmJordan Wind Project Company PSC

EIB Investments in Renewable Energy outside EU

By: Samer S. Judeh, Chairman26th April, 2017

Page 2: Tafila Wind Farm · 2019-03-20 · Timeline Q2 2011 MOU Signed with GOJ Q4 2013 PPA / EPC / Finance Docs signed Q2 2014 Commenced site works (21 month construction period) Q1 2015

Jordan Wind Project Company

A Success Story - First Commissioned Wind Project in Jordan/Region

Page 3: Tafila Wind Farm · 2019-03-20 · Timeline Q2 2011 MOU Signed with GOJ Q4 2013 PPA / EPC / Finance Docs signed Q2 2014 Commenced site works (21 month construction period) Q1 2015

Sponsors Lenders

Participants- Sponsors & Lenders

Page 4: Tafila Wind Farm · 2019-03-20 · Timeline Q2 2011 MOU Signed with GOJ Q4 2013 PPA / EPC / Finance Docs signed Q2 2014 Commenced site works (21 month construction period) Q1 2015

Legal Engineering Accounting, Tax

InsuranceAccount Banks

Advisory & Service Providers

Page 5: Tafila Wind Farm · 2019-03-20 · Timeline Q2 2011 MOU Signed with GOJ Q4 2013 PPA / EPC / Finance Docs signed Q2 2014 Commenced site works (21 month construction period) Q1 2015

Timeline

Q2 2011 MOU Signed with GOJ

Q4 2013 PPA / EPC / Finance Docs signed

Q2 2014 Commenced site works (21 month construction period)

Q1 2015 Turbine erection commenced

9/2015 Commercial Operations Start (20 yrs)

Total Project Cost: $287m

Lenders: International Finance Corporation (IFC), European Investment Bank (EIB), Netherlands Development Finance Company (FMO), Europe Arab Bank (EAB), OPEC Fund for International Development (OFID), Danish Export Credit Agency (EKF) 77% of funding ($221m)

Sponsors: Inframed Infrastructure, Masdar Power, EP Global Energy Ltd. 23% of funding($66M)

Jordan Wind Project Company

Page 6: Tafila Wind Farm · 2019-03-20 · Timeline Q2 2011 MOU Signed with GOJ Q4 2013 PPA / EPC / Finance Docs signed Q2 2014 Commenced site works (21 month construction period) Q1 2015

IFC: Mandated bank

EIB:

Loan:

Largest lender at $72m

Repayments: Three to date

Lenders

Page 7: Tafila Wind Farm · 2019-03-20 · Timeline Q2 2011 MOU Signed with GOJ Q4 2013 PPA / EPC / Finance Docs signed Q2 2014 Commenced site works (21 month construction period) Q1 2015

Required studies received input from lender technical / legal advisor throughout the process

▪ Environmental & Social Impact Assessment

▪ Baseline Environmental Surveys

▪ Avifauna surveys & reporting

▪ Wind measurement & reporting

▪ Topographic study

▪ Geotechnical study

▪ Grid Impact Study

▪ Transport study

▪ Preliminary Design works

Required Studies

Development Process

Page 8: Tafila Wind Farm · 2019-03-20 · Timeline Q2 2011 MOU Signed with GOJ Q4 2013 PPA / EPC / Finance Docs signed Q2 2014 Commenced site works (21 month construction period) Q1 2015

Development:

▪ Land Acquisition & Title Documentation

▪ Tax Framework

▪ Project Documents▪ PPA / TCA

▪ Financing Docs

▪ EPC (DBOM) Contract

▪ Environmental (Avian monitoring / risk assessment)

▪ Permitting

Development / Implementation Challenges

Page 9: Tafila Wind Farm · 2019-03-20 · Timeline Q2 2011 MOU Signed with GOJ Q4 2013 PPA / EPC / Finance Docs signed Q2 2014 Commenced site works (21 month construction period) Q1 2015

▪ GOJ Guarantee on NEPCO Obligations

▪ Lender direct agreements (GOJ, Contractor, etc)

▪ PPA – currency adjustment provision

▪ Security Provisions (onshore / offshore assets)

▪ Due Diligence / KYC

▪ Strict environmental mitigation / monitoring program

▪ Bankable studies and contracts

De-risking (Bankability)

Page 10: Tafila Wind Farm · 2019-03-20 · Timeline Q2 2011 MOU Signed with GOJ Q4 2013 PPA / EPC / Finance Docs signed Q2 2014 Commenced site works (21 month construction period) Q1 2015

- First privately sponsored utility scale wind farm in the Middle East

- First non recourse project finance renewable deal in Middle East

- First utility scale renewable plant in Jordan - First renewable PPA and Generation License in Jordan- Middle East Renewable Deal of the Year 2013 –

Project Finance magazine- First successfully commissioned RE project onto the

NEPCO grid in September 2015

Accomplishments

Page 11: Tafila Wind Farm · 2019-03-20 · Timeline Q2 2011 MOU Signed with GOJ Q4 2013 PPA / EPC / Finance Docs signed Q2 2014 Commenced site works (21 month construction period) Q1 2015

- Government Agreements, Financing Docs, DBOM Contract signed simultaneously

- December 2013 year end conditions satisfaction (DBOM)

- Deal of the Year Award 2013

Closing

Page 12: Tafila Wind Farm · 2019-03-20 · Timeline Q2 2011 MOU Signed with GOJ Q4 2013 PPA / EPC / Finance Docs signed Q2 2014 Commenced site works (21 month construction period) Q1 2015

▪ Roads

▪ Crane pads

▪ Foundations

▪ Turbines

▪ Cabling

▪ Substation (MV / HV)

▪ Warehouse & Control building

▪ Permanent wind measurement mast

▪ Sections of roads and crane pads

▪ Construction compound & storage area

▪ Some road entrances

▪ Temporary wind measurement masts

Permanent

Temporary

PROJECT COMPONENTS

Page 13: Tafila Wind Farm · 2019-03-20 · Timeline Q2 2011 MOU Signed with GOJ Q4 2013 PPA / EPC / Finance Docs signed Q2 2014 Commenced site works (21 month construction period) Q1 2015

Slide 13

Vestas V112 Turbine (Qty 38)

• 3.075 MW rated capacity• 112m rotor diameter• 94m tower height• 3 – 25 m/s operating range• Fully automated

Towers: SpainNacelle: DenmarkGearbox: GermanyBlades: USA, Denmark

~400GWH / Year CF @ 39%Class II site

PROJECT COMPONENTS

Page 14: Tafila Wind Farm · 2019-03-20 · Timeline Q2 2011 MOU Signed with GOJ Q4 2013 PPA / EPC / Finance Docs signed Q2 2014 Commenced site works (21 month construction period) Q1 2015

Construction:

▪ Customs / Importation / Transport

▪ Wind conditions during turbine erection

▪ Crane logistics

Development / Implementation Challenges

Page 15: Tafila Wind Farm · 2019-03-20 · Timeline Q2 2011 MOU Signed with GOJ Q4 2013 PPA / EPC / Finance Docs signed Q2 2014 Commenced site works (21 month construction period) Q1 2015

Slide 15

HM the King landing onsite to inaugurate the wind farm project.

PROJECT COMPONENTS

Page 16: Tafila Wind Farm · 2019-03-20 · Timeline Q2 2011 MOU Signed with GOJ Q4 2013 PPA / EPC / Finance Docs signed Q2 2014 Commenced site works (21 month construction period) Q1 2015

16

PROJECT COMPONENTS

Page 17: Tafila Wind Farm · 2019-03-20 · Timeline Q2 2011 MOU Signed with GOJ Q4 2013 PPA / EPC / Finance Docs signed Q2 2014 Commenced site works (21 month construction period) Q1 2015

Slide 17

JWPC and NEPCO substation

PROJECT COMPONENTS

Page 18: Tafila Wind Farm · 2019-03-20 · Timeline Q2 2011 MOU Signed with GOJ Q4 2013 PPA / EPC / Finance Docs signed Q2 2014 Commenced site works (21 month construction period) Q1 2015

18Transformer Transport and Installation

PROJECT COMPONENTS

Page 19: Tafila Wind Farm · 2019-03-20 · Timeline Q2 2011 MOU Signed with GOJ Q4 2013 PPA / EPC / Finance Docs signed Q2 2014 Commenced site works (21 month construction period) Q1 2015

Slide 19

Snow storm on site

PROJECT COMPONENTS

Page 20: Tafila Wind Farm · 2019-03-20 · Timeline Q2 2011 MOU Signed with GOJ Q4 2013 PPA / EPC / Finance Docs signed Q2 2014 Commenced site works (21 month construction period) Q1 2015

Slide 20

Roads / Crane Pads

Foundation excavation

Completed site road

Completed crane pad

PROJECT COMPONENTS

Page 21: Tafila Wind Farm · 2019-03-20 · Timeline Q2 2011 MOU Signed with GOJ Q4 2013 PPA / EPC / Finance Docs signed Q2 2014 Commenced site works (21 month construction period) Q1 2015

Slide 21

PROJECT COMPONENTS

Page 22: Tafila Wind Farm · 2019-03-20 · Timeline Q2 2011 MOU Signed with GOJ Q4 2013 PPA / EPC / Finance Docs signed Q2 2014 Commenced site works (21 month construction period) Q1 2015

Slide 22

MV Cable works

33kV cable works

Cable drum storage

PROJECT COMPONENTS

Page 23: Tafila Wind Farm · 2019-03-20 · Timeline Q2 2011 MOU Signed with GOJ Q4 2013 PPA / EPC / Finance Docs signed Q2 2014 Commenced site works (21 month construction period) Q1 2015

Slide 23

Foundations

Completed Foundation ready for backfilling

Foundation reinforcement works

Backfilled foundation

PROJECT COMPONENTS

Page 24: Tafila Wind Farm · 2019-03-20 · Timeline Q2 2011 MOU Signed with GOJ Q4 2013 PPA / EPC / Finance Docs signed Q2 2014 Commenced site works (21 month construction period) Q1 2015

Slide 24

PROJECT COMPONENTS

Page 25: Tafila Wind Farm · 2019-03-20 · Timeline Q2 2011 MOU Signed with GOJ Q4 2013 PPA / EPC / Finance Docs signed Q2 2014 Commenced site works (21 month construction period) Q1 2015

Unloading & Transport

Component unloading in Aqaba

PROJECT COMPONENTS

Page 26: Tafila Wind Farm · 2019-03-20 · Timeline Q2 2011 MOU Signed with GOJ Q4 2013 PPA / EPC / Finance Docs signed Q2 2014 Commenced site works (21 month construction period) Q1 2015

Slide 26Pictures from the construction

PROJECT COMPONENTS

Page 27: Tafila Wind Farm · 2019-03-20 · Timeline Q2 2011 MOU Signed with GOJ Q4 2013 PPA / EPC / Finance Docs signed Q2 2014 Commenced site works (21 month construction period) Q1 2015

Slide 27

PROJECT COMPONENTS

Page 28: Tafila Wind Farm · 2019-03-20 · Timeline Q2 2011 MOU Signed with GOJ Q4 2013 PPA / EPC / Finance Docs signed Q2 2014 Commenced site works (21 month construction period) Q1 2015

Slide 28

PROJECT COMPONENTS

Page 29: Tafila Wind Farm · 2019-03-20 · Timeline Q2 2011 MOU Signed with GOJ Q4 2013 PPA / EPC / Finance Docs signed Q2 2014 Commenced site works (21 month construction period) Q1 2015

Slide 29

View from the permanent met mast during the maintenance

Inspection of the top cooler at WTG

PROJECT COMPONENTS

Page 30: Tafila Wind Farm · 2019-03-20 · Timeline Q2 2011 MOU Signed with GOJ Q4 2013 PPA / EPC / Finance Docs signed Q2 2014 Commenced site works (21 month construction period) Q1 2015

Completed WTG

Completed WTG

Page 31: Tafila Wind Farm · 2019-03-20 · Timeline Q2 2011 MOU Signed with GOJ Q4 2013 PPA / EPC / Finance Docs signed Q2 2014 Commenced site works (21 month construction period) Q1 2015

31View from WTG 24

PROJECT COMPONENTS

Page 32: Tafila Wind Farm · 2019-03-20 · Timeline Q2 2011 MOU Signed with GOJ Q4 2013 PPA / EPC / Finance Docs signed Q2 2014 Commenced site works (21 month construction period) Q1 2015

Slide 32

Summary:

• The wind farm is operating at full installed capacity of

117MW

• The availability / performance of the turbines is very good

(97.37% after TOC)

• Turbines do not have any major technical issues

• Cooperation with NEPCO is without any problems

• ESMMP tasks are being carried out in line with requirements

Operations Overview

Page 33: Tafila Wind Farm · 2019-03-20 · Timeline Q2 2011 MOU Signed with GOJ Q4 2013 PPA / EPC / Finance Docs signed Q2 2014 Commenced site works (21 month construction period) Q1 2015

Slide 33

Regular JWPC site team activities:• Weekly inspections of substation electrical equipment• Weekly inspections of the buildings and site roads• Monthly inspections on the spare parts• Monitoring Vestas activity• Regular WTGs inspection• Monitoring WF performance – evaluation of the data from the WTGs• Reporting – weekly internal reports, monthly reports• Billing• Monitoring H&S on site

• Environmental activities:• Carcass searching on weekly basis (dropping to 2 x month in winter)• Bird monitoring• Monthly inspection of the site in terms of environmental.

O&M Activities - Ongoing

Page 34: Tafila Wind Farm · 2019-03-20 · Timeline Q2 2011 MOU Signed with GOJ Q4 2013 PPA / EPC / Finance Docs signed Q2 2014 Commenced site works (21 month construction period) Q1 2015

Slide 34

HSE Statistics – Since Taking Over

Month Events for the month Total

OHS Near Misses First Aid Injury Lost Time Injury

12/2015 0 1* 0 1

1/2016 0 0 0 0

2/2016 0 0 0 0

3/2016 0 0 0 0

4/2016 0 0 0 0

5/2016 0 0 0 0

6/2016 0 0 0 0

7/2016 0 0 0 0

8/2016 0 0 0 0

9/2016 0 0 0 0

10/2016 0 0 0 0

11/2016 0 0 0 0

12/2016 0 0 0 0

01/2017 0 0 0 0

HSE Statistics – Since Taking Over

Page 35: Tafila Wind Farm · 2019-03-20 · Timeline Q2 2011 MOU Signed with GOJ Q4 2013 PPA / EPC / Finance Docs signed Q2 2014 Commenced site works (21 month construction period) Q1 2015

Slide 35

Thank you very much