Technical Assistance Consultant’s Report Project Number: 45280 June 2012 Socialist Republic of Viet Nam: Support to Improve Portfolio Performance and Aid Effectiveness (Financed by ADB’s Technical Assistance Special Fund) Inception Report (June 2012) Prepared by Nguyen Viet Dung Institutional Development Specialist/Team Leader For Asian Development Bank This consultant’s report does not necessarily reflect the views of ADB or the Government concerned, and ADB and the Government cannot be held liable for its contents. (For project preparatory technical assistance: All the views expressed herein may not be incorporated into the proposed project’s design.

Upload: dinhkien

Post on 01-Jan-2017

221 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: TACR: Viet Nam: Support to Improve Portfolio Performance and Aid

Technical Assistance Consultant’s Report

Project Number: 45280

June 2012

Socialist Republic of Viet Nam: Support to Improve Portfolio Performance and Aid Effectiveness (Financed by ADB’s Technical Assistance Special Fund)

Inception Report (June 2012)

Prepared by Nguyen Viet Dung

Institutional Development Specialist/Team Leader

For Asian Development Bank

This consultant’s report does not necessarily reflect the views of ADB or the Government concerned, and ADB and

the Government cannot be held liable for its contents. (For project preparatory technical assistance: All the views

expressed herein may not be incorporated into the proposed project’s design.

Page 2: TACR: Viet Nam: Support to Improve Portfolio Performance and Aid

TA 8034-VIE: Support to Improve Portfolio Performance

and Aid Effectiveness

INCEPTION REPORT

Prepared by NGUYEN VIET DUNG

Consultant Team Leader

Viet Nam Resident Mission

Ha Noi, June 2012

Page 3: TACR: Viet Nam: Support to Improve Portfolio Performance and Aid

ABBREVIATIONS

AA - Advance Actions

ADB -

Asian Development Bank

EA -

Executing Agency

DMF -

Design and Monitoring Framework

FERD -

Foreign Economic Relation Department

FS -

Feasibility Study

IA -

Implementing Agency

IMTF -

Inter-Ministerial Task Force

JAP -

Joint Action Plan

JPPR -

Joint Portfolio Performance Review

MOF -

Ministry of Finance

MONRE -

Ministry of Natural Resource and Environment

MPI -

Ministry of Planning and Investment

PDO -

Project Detailed Outline

PMU -

Project Management Unit

PPSSF -

Project Preparation Support Facility

TA -

Technical Assistance

i

Page 4: TACR: Viet Nam: Support to Improve Portfolio Performance and Aid

TABLE OF CONTENTS

ABBREVIATIONS ……………………………………………………………………………………………………………………………………..i

TABLE OF CONTENTS ………………………………………………………………………………………………………………………………ii

I. INTRODUCTION ........................................................................................................................................ 1

II. TECHNICAL ASSISTANCE DETAILS ............................................................................................................ 1

A. TA duration: . ...................................................................................................................................... 1

B. TA Impact and Outcomes .................................................................................................................. 1

C. TA Outputs and Activities .................................................................................................................. 2

Output 1: Harmonization of ODA Procedure ...................................................................................... 2

Output 2: Achievement of Project start-up compliance ..................................................................... 2

Output 3: Strengthening of Institutional mechanism for join portfolio management ....................... 3

Output 4: Strengthening of capacity for ODA project management .................................................. 4

Output 5: Institutionalization and implementation of results of dialogues on ODA effectiveness .... 5

D. TA Resources ........................................................................................................................................ 5

E. Implementation Arrangements ........................................................................................................... 5

III.TA START-UP ACTIVITIES .......................................................................................................................... 6

IV. IMPLEMENTATION APPROACH AND METHODOLOGY .......................................................................... 6

A. Consultation and Collaboration among TA project Stakeholders ...................................................... 6

B. Facilitate and enhance ongoing policy dialogues ............................................................................... 7

C. Result-based management with indicators ........................................................................................ 7

V. IMPLEMENTATION PLAN ........................................................................................................................ 8

VI. MONITORING, REPORTING AND EVALUATION...................................................................................... 9

VII. FINANCIAL AND BUDGET PLAN ............................................................................................................. 9

VIII. CONSULTANT PERSONNEL PLAN ........................................................................................................ 10

ATTACHMENTS

Attachment 1. Implementation Plan .......................................................................................................... 11

Attachment 2. Training Plan ………………………………………………………………………………………………….………………14

Attachment 3. Procurement Plan ............................................................................................................... 15

Attachment 4. Personnel Schedule ............................................................................................................. 16

Attachment 5. Updated Design and MonitoringFramework ...................................................................... 17

ii

Page 5: TACR: Viet Nam: Support to Improve Portfolio Performance and Aid

1

I. INTRODUCTION

1. Official Development Assistance (ODA) has been an important catalyst for Viet Nam’s

rapid economic development since resumed ODA assistance from international development

partners in 1993. However, portfolio performance as reflected in indicators such as

disbursement, project start-up compliance and average loan extension has deteriorated in 2004

and improved in 2009, but slid back in 2010. Some portfolio performance indicators in Viet Nam

are worst than those of other Southeast Asia countries. This situation requires that ODA

utilization and management in Viet Nam needs to be improved toward contribution to better

aid effectiveness.

2. ADB’s portfolio performance review in 2010 and 2011 identified main constraints that

need to be solved for improvement of portfolio and aid effectiveness, which among others

include (i) lack of harmonized procedures on ODA project management, (ii) project start-up

delays, (iii) limited effectiveness of joint portfolio performance management mechanism, (iv)

project management capacity constraints, and (v) delays in institutionalization of results of

dialogue between Government and development partners on aid effectiveness.

3. The Government highly appreciates and requests supports to improve portfolio

performance and aid effectiveness from the international development partners in general and

the Six Banks in particular. In response to Government request, the first ADB technical

assistance (TA) to enhance ODA absorptive capacity and efficiency was implemented from

October 2007 to August 2011. As continuation of ADB support, this TA, which is financed by

ADB, will provide consultancy services, both international and national, to support the

Government in improvement of portfolio performance and aid effectiveness focusing on

dealing with the above mentioned constraints. This TA will not only build on results achieved in

previous TA, but will further institutionalize the outcomes of the policy dialogue between

Government and the Six Banks, especially Joint Action Plan 2 (JAP 2) and dialogue results

thereafter.

4. The purpose of this report is to set out clear approach and methodology to implement the

TA; present implementation plan, activities, timeframe and resources to implement the TA

assignment.

II. TECHNICAL ASSISTANCE DETAILS

A. Duration

5. The TA will be implemented from 1 June 2012 to 30 November 2014.

B. Impact and Outcomes

6. The TA impact will be effective utilization of ODA resources. The outcome will be

improved portfolio performance of ADB-financed projects in Viet Nam.

Page 6: TACR: Viet Nam: Support to Improve Portfolio Performance and Aid

2

C. Outputs and Activities

7. The TA will produce the following outputs and activities:

Output 1: Harmonization of ODA Procedures (Jun – Oct 2012)

(i) Activity 1: Propose provisions relating to advance actions (AA) and project detailed

outlines (PDO), among others, to new Decree/Circular on ODA (Jun-Jul 2012). This includes preparation of legal provisions regarding AA and PDO to be included in the new

decree and circular on ODA being prepared under other TA. This Activity will be done in three sub-

activities below.

• Prepare provisions of AA and PDO in new Circular on ODA

• Obtain comments from ADB and the Ministry of Planning and Investment (MPI)

• Finalize the AA and PDO provisions based on comments received

(ii) Activity 2: Update the Blue Book following issuance of new decree on ODA

management and utilization (Aug-Oct 2012) The task includes updating the current Handbook on Processing and Implementation of ADB-

Financed Projects in Viet Nam (the Blue Book) published in 2009 incorporating new provisions of

ADB’s related guidelines and Government’s regulations on ODA including ADB’s Streamlined

Business Process and Government’s new Decree on ODA. This activity will be done in three sub-

activities below.

• Update the Blue Book

• Obtain comments from MPI and ADB

• Finalize the Blue Book based on comments received

Output 2: Achievement of Project start-up compliance (Jun 2012- Nov 2014,

Intermittent)

(i) Activity 1: Prepare guideline for AA implementation in ADB-financed projects (Jul

2012) The consultant task is to prepare guideline for implementation of AA by executing and

implementing agencies and other related bodies. The guideline will guide to identify AAs, and

include procedure for implementation.

(ii) Activity 2: Identifying AAs for projects to be approved from 2012 onward (Jul-Sep

2012) The activity includes working with ADB and Government’s projects implementing agencies to

identify projects financed by ADB from 2012 onward, preparation of specific AAs that may apply

for each of those projects, and support Government’s project implementation agencies in

preparing AA implementation plans. This task will be done in two sub-activities below.

• Work with ADB officer to identify the projects to be processed in 2012, 2013 and

2014

• Work with executing agencies (EAs) and project management units (PMUs) to

prepare AAs and their implementation plans for each of these projects.

Page 7: TACR: Viet Nam: Support to Improve Portfolio Performance and Aid

3

(iii) Activity 3: Monitoring the implementation of AA projects (Aug 2012- Nov 2014,

Intermittent)

The activity includes supporting Government project implementation agencies in

monitoring and evaluation of AAs implementation, and reporting progress to ADB and

MPI. This activity will be done in two sub-activities below.

• Support in monitoring the AA implementation in accordance with approved

implementation plan

• Report on AA implementation monitoring

(iv) Activity 4: Support and facilitate preparation of PDO and FS for PPSSF project, which

will speed up preparation and start-up of ADB financed projects (Jun-Jul 2012)

The activity includes supporting MPI in preparation of PDO and feasibility study (FS) for

the Project Preparation and Support Facility (PPSSF) project, which will support

Government executing agencies and implementing agencies in improvement of

Government capacity to fast-track the preparation and implementation of ODA-financed

projects in Viet Nam, including capacity building for executing and implementing

agencies and project management units, improved quality at entry and shortened

project preparation and implementation start-up periods of ADB-financed projects in

Viet Nam. This activity will be done with three sub-activities below.

• Support the Foreign Economic Relations Department (FERD) of MPI to prepare

PDO and FS

• Review and comment by MPI

• Finalization and submission for approval PDO (by Government) and FS (by MPI)

Output 3: Strengthening of Institutional mechanism for joint portfolio management

(i) Activity 1: Conduct periodically project site inspection and systematic quarterly

portfolio performance review meetings on problematic projects (Aug 2012- Nov

2014, Intermittent). The activity is to support MPI in monitoring problematic projects, including travelling, to

problematic projects for inspection with MPI staff and conduction of meetings with participation

of concerned agencies to solve the problems of those projects. This activity will be done with

three sub-activities below.

• Support MPI in Identifying problematic projects

• Support in finding remedy measures for each of problematic projects, and

prepare reports/materials as needed

• Support in conducting quarterly portfolio performance review meetings on these

projects

(ii) Activity 2: Conduct annual and midterm country portfolio review in 2012, 2013 and

2014 to review ADB portfolio performance (Dec 2012- Nov 2014, Intermittent)

(iii) Activity 3: Follow-up on JPPR VII and JPPR VIII in Jun 2013, including monitoring

status of JAP2 implementation focusing on AA (Oct 2012- Nov 2014, Intermittent).

Page 8: TACR: Viet Nam: Support to Improve Portfolio Performance and Aid

4

Since 1999 the Government and the Six Banks have met every two years which is called Joint

Portfolio Performance Review meeting (JPPR) to discuss the status of overall ODA assistance,

including the review of projects and programs, implementation, and measures to overcome

difficulties and bottlenecks in ODA management. As result of these discussions, Joint Action Plans

(JAPs) has been agreed between both sides. During JPPR VI in 2009, JAP2 was agreed by both

sides, and the Government through issuance of Decision 747/2010/QD-BKH on 28 May 2010 has

institutionalized this JAP to implement this action plan. JPPR VII was organized in 2011 and JPPR

will be organized in 2013. The Consultant’s task is to follow-up on these JAPs focusing on

monitoring AA.

(iv) Activity 4: Consolidate targeted sector outputs results framework and Update sector

result framework monitoring matrix (Sep 2012) ADB’s Country Partnership Strategy (CPS) set out the outputs for specific sectors of the country.

Consultant task is to consolidate sector outputs results framework and update available sector

result framework monitoring matrix.

(v) Activity 5: Monitor the achievement of targeted sector outputs using result

framework (Oct 2012- Nov 2014, Intermittent)

(vi) Activity 6: Develop and maintain an Excel- based database in MPI (Sep 2012) FERD is focal agency of MPI in ODA portfolio management of the country. Currently, FERD does

not have computer-based management tool to help them fulfill their responsibility. Consultant will

support FERD to develop a simple database at FERD which is based on Microsoft Excel application.

Output 4: Strengthening of capacity for ODA project management (Jul 2012- Nov 2014,

Intermittent)

(i) Activity 1: Conduct training and capacity building needs assessment (Jul 2012) Project management capacity constraints is one of the main reasons that cause delay in project

implementation in Viet Nam. Consultant team will work with each of ADB-financed project

implementation agencies to identify their need of training and capacity building. To identify

training needs, training courses received, training demand and the gaps at implementation

agencies/ PMUs will be defined (refer to Annex1 for details). Interview and questionnaire will be

used as method to collect data and information.

(ii) Activity 2: Develop training program (training for EAs/IAs/PMUs staff) and training

materials (Aug-Oct 2012) Training material will be prepared separately for specific topics relating to project cycle

management and indicating time duration for the training courses corresponding to number of

topics needed by project management agencies (see Annex 2 for details).

(iii) Activity 3: Conduct quarterly trainings up to 2014 (Sep 2012-Sep 2014, Intermittent) The training will be carried out for every quarter of the years, from September 2012 to November

2014. Training for project implementation agencies will be in form of the followings.

• Project management training courses

• Consultation workshops

Page 9: TACR: Viet Nam: Support to Improve Portfolio Performance and Aid

5

(iv) Activity 4: Evaluation of training program Evaluation report will be submitted at the end of the training program. The report covers number

of training courses organized, trainees participated, evaluation as to whether objectives have

been achieved, lessons learn etc.

Output 5: Institutionalization and implementation of results of dialogues on ODA

effectiveness (Aug 2012- Nov 2014, Intermittent)

(i) Activity 1: Prepare reports for consultative group meetings in December 2012, 2013

(Dec 2012- Jun 2014, Intermittent) Consultant team will support MPI in preparation of reports for consultative group meetings in

December 2012 and 2013. The report preparation is done in close cooperation with MPI’s related

offices and staffs.

(ii) Activity 2: Develop Post-Busan Monitoring Framework (Sep 2012) International high level forum in aid effectiveness was organized in Korea in 2011. Consultant

team will support MPI in developing monitoring framework to follow-up on the results of this

forum.

(iii) Activity 3: Prepare the survey on Aid Effectiveness (Aug 2012)

D. TA Resources

8. The TA will require the following resources:

(i) Individual Consultants

(ii) Equipment and office supplies

(iii) Training, seminars, and conferences

(iv) Miscellaneous administration and support costs

E. Implementation Arrangements

9. MPI will be Executing Agency of the TA. MPI will set up a TA project management unit

within PERD to manage daily implementation of the TA. The TA will work closely with Inter-

ministerial Task Force (IMTF) to make sure that government agencies are involved with TA

implementation. To this end, some ones who are member of the IMTF and concurrently

participate in PMU will contribute much benefit for the TA implementation.

10. The TA implementation will be supported by a team of individual international and

national consultants, totaling 43 person-months, in expertise of institutional development,

portfolio management, capacity building and economics. The individual consultants will be

selected by ADB in accordance with ADB Guidelines on the Use of Consultants.

11. The TA expected outcomes will be jointly monitored and evaluated by the MPI and ADB

during TA inception, midterm, and final review missions. TA progress will be made on a

quarterly basis and discussed semi-annually between ADB with MPI and other relevant

Government agencies. Baseline data on portfolio performance such as contract awards,

disbursement rate, start-up compliance, and number of projects at risk will be monitored

during the course of the TA.

Page 10: TACR: Viet Nam: Support to Improve Portfolio Performance and Aid

6

III. TA START-UP ACTIVITIES

12. Team Leader has been recruitment as advance action and he will serve from beginning of

the TA

13. Some discussions among TA Consultant, ADB and MPI with regard to required outputs,

setting-up TA office and implementation plan have been taken place. As a result, there were

some changes to activities estimated at the time of TA preparation.

14. Office space needs to be provided by MPI as soon as possible. Administration assistants

and office equipment also need to be procured in July 2012 to enable operation of the

consultant team.

IV. IMPLEMENTATION APPROACH AND METHODOLOGY

A. Consultation and Collaboration among TA project Stakeholders

15. Working closely among ADB, other Development Donors, MPI as Government’s TA

Executive Agency and EAs/IAs/PMUs of ADB financed projects is important for the success of TA

implementation.

16. Following current arrangement, ODA Portfolio performance management at the policy

level involves mainly with MPI and the Donors, and also with other Government’s relevant

ministries such as MOF, SBV, and MONRE. At project level, sector ministries, provinces and

other project stakeholders are also involved in portfolio management.

17. Portfolio management and aid effectiveness issues have been concerned by the

Government and international donors for many years. These issues have been dialogued

frequently at Consultative Group meetings, Aid Effectiveness Forums such as Joint Portfolio

Performance Review, Inter-Ministerial Task Force meeting with the Six Banks. The Government

highly appreciates and utilizes the results of these discussions as inputs for adjusting and

finalization of its laws, decrees, and circulars.

18. This TA is designed based on not only recommendation of ADB’s portfolio performance

review but also results of Government and International partners dialogues. The

implementation of the TA’s activities, therefore, needs to be in collaboration and consultation

with the above mentioned agencies. Due to consultation and collaboration process, consensus

on targets, timing, action plan etc. will be obtained among stakeholders involved. This is very

important factors for consultant performance success.

19. The focal agencies/ organizations that the consultant team needs to consult and

collaborate during performance of the assignments are:

(i) Government: PMU (under FERD), MPI, IMTF, EAs/IAs/PMUs of problematic projects

and ADB- financed projects

(ii) International Development Partners: the Six Banks, especially ADB

Page 11: TACR: Viet Nam: Support to Improve Portfolio Performance and Aid

7

B. Facilitate and enhance ongoing policy dialogues

20. As presented above the TA impact, outcomes, outputs and activities are designed based

on present constraints found at Government and the Six Banks dialogues. Implementation of

activities under the TA is expected to solve these constraints, and therefore improve aid

effectiveness in Viet Nam. Any activities and initiatives carried out under the TA must target to

facilitation and enhancement of ongoing dialogues between the Government and the Six Banks.

21. Since 1999 the Government and the Six Banks have met every two years to discuss the

status of overall ODA assistance, including the review of projects and programs,

implementation, and measures to overcome difficulties and bottlenecks in ODA management.

In 2004 the Government established the IMTF to assist the Government, in cooperation with

the Six Banks, to effectively manage ODA. As an outcome of the Fifth JPPR (JPPR-V) between

IMTF and the Six Banks, which was conducted in May 2007, a Joint Action Plan (JAP-1) was

developed. Implementation of JAP-1 was officially instructed by Government Decision

883/2008/QD-BKH dated 14 July 2008 for the 2008-2009 period which comprised: (i)

harmonization of the Government’s PDO and the donor’s Project Concept Paper; (ii) use of

Common Feasibility Study Guidelines as instructed by Decision 48/2008/QD-TTg on 3 April

2008; (iii) implementation of Advance Action; (iv) Procurement Reform and Harmonization; (v)

reform of Cost Norms system; (vi) improvement of Payment & Disbursement procedures, and

Budget Management; (vii) use of Aligned Monitoring Tools for project reporting as instructed by

Decision 803/2007/QD-BKH on 30 July 2007; (viii) reform of legal framework on Project

Management Units (PMU); and (ix) harmonization of Resettlement and Environment Impact

Assessment policies and procedures.

22. In October 2009 the Sixth Joint Portfolio Performance Review (JPPR-VI) was held to

discuss the issues addressed in JPPR-V and reinforcement of JAP-1 to include two additional

items, namely: (i) improvement of Contract Management; and (ii) improvement of procedures

for making adjustments and changes of scope during project implementation. Subsequently the

Six Banks proposed the second Joint Action Plan (JAP-2), which was adopted by the

Government through issuance of Decision 747/2010/QD-BKH on 28 May 2010 for the 2010-

2011 stage.

23. In Dec 2011 the Seventh Joint Portfolio Performance Review (JPPR-VII) was held. As result

of the dialogue, the next JAP has been agreed. The Government is now preparing new Decision

which cover mutual agreement on the meeting. JPPR VIII is scheduled to be held in June 2013.

24. One of the Consultant tasks under the TA is to follow-up on JPPR VII and JPPR VIII in Jun

2013, including monitoring status of JAP 2 implementation focusing on AA.

C. Result-based management with indicators

25. The TA scope is large and its intervention nature is comprehensive. The TA will address

both management and operational levels of Government’s ODA management arrangement,

cover aspects of institution, procedure, and capacity. The TA stakeholders include Government

Page 12: TACR: Viet Nam: Support to Improve Portfolio Performance and Aid

8

agencies that are at policy making levels and project operational level, the Six Banks, civil social

organizations etc.

26. Portfolio performance management has been discussed for many years and there have

been some technical assistance that more or less relate to this TA, and have contributed to

improve portfolio performance in Viet Nam. As a tool for monitoring and evaluation of this TA

implementation, a detailed design and monitoring framework will be set up and implemented.

This is crucial for monitoring as to whether the TA objectives have been achieved.

V. IMPLEMENTTATION PLAN

27. The TA will be implemented within two and half years, from June 2012 to November

2014. In line with the above approach and methodology, the TA implementation plan will

describe detailed actions to be carried out for each month of the TA life and is structured

according to outcomes, outputs and activities described above. In summary, the TA will be

implemented by year as follows:

Year 1 (June 2012 to June 2013)

(i) Setting up Executing Agency’s PMU and the TA office

(ii) Procurement of office equipments: Desktop: 01; Laptop: 01; Laser Printer: 01;

Photocopier: 01; LCD Projector and screen: 01 (refer to Attachment 2- Procurement

Plan for details)

(iii) Selection of individual consultants (refer to Attachment 2- Procurement Plan for

details)

(iv) Review the TA documents and prepare Inception Report including approach and

implementation plan to implement the tasks

(v) Conduct works relating to harmonization of procedures in connection with ongoing

revision of ODA legal framework of the Government, which are:

• Advance actions

• PDO

• Updating the Hand book on Project Processing and Implementation for ADB-

financed Projects in Viet Nam (the Blue Book)

(vi) Conduct assessment of training and capacity building needs and develop the training

program

(vii) Evaluation of advance action implementation in ADB financed pilot project

(viii) Support in develop Excel-based database

(ix) Conduct annual (Dec 2012) and midterm country portfolio review (Jun 2013)

(x) Conduct site inspection and systematic quarterly portfolio review meetings on

problematic projects

(xi) Follow-up on JPPR VII and VIII, focusing on advance actions

(xii)Support MPI in developing post Busan monitoring framework

(xiii) Reporting:

• Annually report (Dec 2012)

Page 13: TACR: Viet Nam: Support to Improve Portfolio Performance and Aid

9

• Quarterly reports (September 2012, Mar 2013, Jun 2013)

Year 2 (Jul 2013 to June 2014)

(i) Conduct training courses

(ii) Test and finalize Excel-based database

(iii) Conduct annual (Dec 2013) and midterm country portfolio review (Jun 2014)

(iv) Conduct site inspection and systematic quarterly portfolio review meetings on

problematic projects

(v) Follow-up on JPPR VII and VIII, focusing on advance actions

(vi) Reporting

• TA Interim report (Jul 2013)

• Quarterly reports (September 2013, Mar 2014, Jun 2014)

• Annually report (Dec 2013)

Year 3 (Jul 2014 to November 2014)

(i) Conduct training courses and evaluation of training program

(ii) Conduct project site inspections and systematic quarterly portfolio review meetings

on problematic projects

(iii) Follow-up on JPPR VII and VIII, focusing on advance actions

(iv) Reporting:

• Quarterly reports (September 2014)

• Draft final report (31 Oct 2014)

• Final report (30 Nov 2014)

(Refer to Attachment 1 for TA Implementation Plan in form of diagram showing activities

versus timeframe, Attachment 2 for the training plan and Attachment 3 for the

Procurement Plan).

VI. MONITORING, REPORTING AND EVALUATION

28. At the time of TA preparation, a design and monitoring framework (DMF) has been

prepared. In this Inception Report the DMF will be updated taking into account discussions

among TA consultants, ADB and MPI. DMF is important to monitoring and evaluation of TA

performance. DMF presents the impact, outcomes, outputs, activities and resources in a box

matrix where the boxes are linked logically together. Each activity will have its own

performance target and indicator with baselines to check if it has completed or not. The DMF

follows result-based management method required by the ADB.

(Refer to Attachment 5 for updated DMF)

Page 14: TACR: Viet Nam: Support to Improve Portfolio Performance and Aid

10

VII. FINANCIAL AND BUDGET PLAN

F. ADB finance

29. ADB will provide financing for:

(i) Individual Consultants

(ii) Equipment and office supplies

(iii) Training, seminars, and conferences

(iv) Miscellaneous administration and support costs

(v) Contingencies

G. Government contribution

30. Government contributions comprise counterpart support in form of counterpart staff

remuneration and office spaces.

VIII. CONSULTANT PERSONNEL PLAN

31. Consultant team includes 4 local individual consultants and 2 international individual

consultants, totaling 43 persons-months, recruited by ADB. Service timings for each of the

consultant are as follows:

International:

(i) Institutional Development Specialist: 5 months

(ii) Portfolio Management Specialist: 3 months

National:

(i) Team Leader/Institutional Development Specialist: 20 months

(ii) Portfolio Management Specialist: 10 months

(iii) Economist: 04 months

(vi) Capacity Building Specialist: 01 month

32. In line with implementation plan presented in item V above, the Personnel- Schedule that

show detailed service timings of each individual consultant for the whole TA period is presented

in Attachment 4 attached.

33. The plan has taken into consideration of minimizing number of international consultant

service sessions to save international travelling costs.

Page 15: TACR: Viet Nam: Support to Improve Portfolio Performance and Aid

11

ATTACHMENT 1: IMPLEMENTATION PLAN

Table 1.1 Overall Implementation Plan

Activity/Output 2012 2013 2014

J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

1.Procedures for ODA management harmonized

1.1 Advance actions (AA)

- Assessment

- Preparation of AA in new circular

- Preparation of AA guidelines

1.2 Project Detailed Outline (PDO)

- Preparation of PDO in new circular

1.3 Revision to Blue Book

2. Project startup compliance

2.1Prepare guideline for AA implementation in ADB-financed projects

2.2Identifying AAs for projects from 2012 onward

2.3 Monitoring and evaluation of AA

2.4Support preparation of PDO and FS for PPSSF

3. Institutional mechanism for join portfolio management

3.1 Portfolio performance review meetings on problematic projects

3.2 Conduct annual and midterm country portfolio review 2012- 2014

iii. Follow-up on JPPR VII and JPPR VIII, including monitoring of JAP 2 3.3 Follow-up on JPPR VII and JPPR VIII, including monitoring of JAP 2

v. Set up M&E, and monitor the achievement of targeted sector outputs 3.4 Consolidate targeted sector outputs results framework

ii. Conduct annual and midterm country portfolio review in 2012, 2013 3.5 Monitor the achievement of 3.4 using result framework

iv. Consolidate targeted sector outputs results framework 3.6 Develop and maintain an Excel- based database in MPI

4. Capacity for ODA project management strengthened

4.1 Conduct training and capacity building needs assessment

4.2 Develop training program (EA staff) and training materials

4.3 Conduct quarterly trainings up to 2014

5. Results of dialogues on ODA effectiveness institutionalized

5.1 Prepare reports for CG meetings in 2012, 2013.

5.2. Develop Post Busan Monitoring Framework

5.3. Prepare the survey on Aid Effectiveness

Page 16: TACR: Viet Nam: Support to Improve Portfolio Performance and Aid

12

Table 1.2 Annual Implementation Plan (June 2012- June 2013)

Outputs

Activities

Time

Frame

Done

By

Jun Ju

l

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Ju

n

1.Procedures for

ODA management

are harmonised

1.1 Propose provisions relating to AAs and PDO:

a. Assess pilot AA

b. Prepare provisions of AA and PDO in new Circular

c. Get comments from MPI, donors and finalize AA

and PDO

Jun- Jul2012

Jun 2012

Jun 2012

Jul 2012

TL;NPMS

TL

TL;

TL,NPMS

1.2 Update the Blue Book:

a. Prepare updated “Blue Book”

b. Get comments from MPI and ADB, and finalize it

Aug-Oct 2012

Aug-Sep 2012

Sep- Oct 2012

TL

TL,

TL,

2. Project start-up

compliance achieved

2.1Prepare guideline for AA implementation in ADB-

financed projects

Jul 2012 TL

2.2 Identifying AAs for projects to be approved from 2012

onward:

a. Identify the projects to be prepared

b. Work with EAs/PMUs, prepare AAs and get

approval on AAs

Jun-Sep 2012

Jun-Jul 2012

Jul-Sep 2012

TL;

ADB team

TL,

ADB team

TL; NPMS

2.3 M&E of AAs

Aug 2012-

Jun 2013

TL; NPMS

2.4 Support and facilitate preparation of PDO and FS for

PPSSF project

Jun- Jul 2012

TL

3. Institutional

mechanism for join

portfolio

management

strengthened

3.1 Conduct quarterly portfolio performance review

meetings on problematic projects:

a. Identify problematic projects

b. Project site Inspections

c. Conduct quarterly portfolio performance review

meetings

Aug 2012-

Jun 2013;

Aug 2012

Aug 2012- Jun

2013

III, IV, 2012;

I,II 2013

IPMS, NPMS,

TL.

NPMS,TL

NPMS,NPMS,

IPMS,PMS,TL

3.2 Conduct annual and midterm country portfolio review

in 2012, 2013

Dec 2012-

June 2013

IIDS; IPMS;

NE,TL

3.3 Follow-up on JPPR VII and JPPR VIII in Jun 2013,

including monitoring status of JAP 2 implementation

Sep 2012-

June 2013

TL; IPMS;

NPMS, NE

Page 17: TACR: Viet Nam: Support to Improve Portfolio Performance and Aid

13

Notes:

TL: Team Leader/National Institutional Development Specialist;

IIDS: Inter Institutional Development Specialist;

IPMS: International Portfolio Management Specialist

NPMS: National Portfolio Management Specialist;

NCBS: National Capacity Building Specialist

NE: National Economist

focusing on AA.

3.4 Consolidate targeted sector outputs results

framework and update sector result framework

monitoring matrix

Nov 2012 NPMS,

NE

3.5 Monitor the achievement of targeted sector outputs

using result framework

Dec 2012

- Jun 2013

IPMS, NPMS,

NE

3.6 Act.6: Develop and maintain an Excel- based

database in MPI

Aug-Oct 2012 IPMS; NPMS

4. Capacity for ODA

project

management

strengthened

4.1 Conduct training and capacity building needs

assessment (Annex 1)

Jul-Aug 2012 NCBS

4.2 Develop training program and training materials

(Annex 2)

a. Project management

b. Consultation workshops

Sep- Oct 2012 TL; LCBS

4.3 Conduct quarterly trainings up to Jun 2013 Sep 2012-

Nov 2014

TL;IIDS, NCBS

5. Results of

dialogues on ODA

effectiveness

institutionalized

and implemented

5.1 Prepare reports for consultative group meetings in

2012, 2013.

5.2 Develop Post Busan Monitoring Framework

5.3 Prepare the survey on Aid Effectiveness

Dec 2012

Jun 2013

Sep 2012

Aug 2012

TL; IIDS,

IPMS, NE

TL, NE

TL;IIDS, IPMS

Page 18: TACR: Viet Nam: Support to Improve Portfolio Performance and Aid

14

ATTACHMENT 2. TRAINING PLAN

Table 2.1. Assessment of Training needs

No.

Agencies

Review of training received and demand Gap and Training need indentified

Trainings received Training demand Gaps Training Needs

1 TBD TBD TBD TBD TBD

2 TBD TBD TBD TBD TBD

3 TBD TBD TBD TBD TBD

(Note of TBD: To be determined after carrying out of training needs assessment).

Table 2.2. Tentative Training Program

No.

Project management/Consultative

Workshop

Objective # of

Training

Trainee

s

Place Time Budget

1 ODA, Planning, and Project cycle Understand overall ODA management TBD TBD TBD 1 day TBD

2 Project Preparation/Design (PDO, FS) Provide skills in design of project TBD TBD TBD 2 days TBD

3 Project Start-up and Advance Actions Understanding importance of project

start-up, AA and implementation

TBD TBD TBD 2 days TBD

4 Project Implementation and

Administration

Provide overall tasks during

implementation of project

TBD TBD TBD 2 days TBD

5 Financial Management /Accounting

and Disbursement

Provide skills in financial management

accounting and disbursement

TBD TBD TBD 1 days TBD

6 Project M&E Provide skills in monitoring, reporting

and evaluation in ODA project

TBD TBD TBD 1 day TBD

7 Procurement Provide skills in procurement of

works/goods and Consultant selection.

TBD TBD TBD 2 days TBD

8 Contract Management and design

change

Provide skills in management of a certain

contract, including variation of contract

due to change of design.

TBD TBD TBD 1 days TBD

(Note of TBD: To be determined after carrying out of training needs assessment).

Page 19: TACR: Viet Nam: Support to Improve Portfolio Performance and Aid

15

ATTACHMENT 3: PROCUREMENT PLAN

No. Packages No. of

package

Procurement Method Selection Time

I Office Equipments

1 01 Desktop; 01 Laptop; 01 Laser Printer; 01

Photocopier; and 01 LCD Projector and

screen.

1 Shopping Jul - Aug 2012

II Individual Consultants

International

1 Institutional Dev. Specialist (IIDS), 5 months 1 ADB’s Individual Consultant Selection Nov- Dec 2012

2 Portfolio/ODA Management Specialist (IPMS),

3 months

1 ADB’s Individual Consultant Selection Nov-Dec 2012

National

3 Institutional Dev. Specialist/T. Leader (TL), 20

months

1 ADB’s Individual Consultant Selection May-Jun 2012

4 Portfolio Management Specialist (LPMS), 10

months

1 ADB’s Individual Consultant Selection Jul-Aug 2012

5 Economist (LE), 4 months 1 ADB’s Individual Consultant Selection Aug-Sep 2012

6 Capacity Building Specialist (LCBS), 1 month 1 ADB’s Individual Consultant Selection Jun-Jul 2012

Page 20: TACR: Viet Nam: Support to Improve Portfolio Performance and Aid

16

ATTACHMENT 4. PERSONNEL SCHEDULE

Name of Expert 2012 2013 2014

J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

International

1. Institutional Dev. Specialist (5 months)

2. Portfolio Management Specialist (3 months)

National

3. Team Leader/NIDS(20 months)

4. Portfolio Management Specialist (10 m)

5. Economist (4 months)

6. Capacity Building Specialist (1 month)

Page 21: TACR: Viet Nam: Support to Improve Portfolio Performance and Aid

17

ATTACHMENT 5: UPDATED DESIGN AND MONITORING FRAMEWORK

Design Summary Performance Target and Indicators Data Sources and Reporting

Mechanism

Assumptions and Risks

Impact:

Effective utilization of

ODA resources by the

Government

ODA disbursement ratio, currently 20%,

on par with international average by

2018

Start-up time currently 8 months, on par

with international average by 2018

Completion of ODA funded projects,

currently 8 years, on par with

international average 2018

Aid effectiveness forum reports

Government statistics on the MPI

website

Assumption:

Government support for framework

to harmonize its procedures with

ODA procedures

Risk:

Rapid changes in the development

context in Viet Nam affect the

expected impacts of ODA projects in

Viet Nam

Outcomes:

Improved portfolio

performance of ADB-

financed projects in Viet

Nam.

Increased cumulative disbursement ratio

from 20% to 30% by 2014

Reduced time elapsed:

(i) Loan approval to effectiveness from

8 months (2010) to 6 months (2014)

(ii) Loan approval to first contract from

16 months (2010) to 11 months

(2014)

Reduced loan extensions to 10% of

ongoing portfolio by 2014

ADB quarterly country portfolio

performance review

COSO country portfolio review data

and SERD Operations Dashboard

COSO country portfolio review data

and SERD Operations Dashboard

Assumptions:

More dedicated capacity building

support to line agencies

Proposals on harmonized

procedures for project preparation

an start-up will be institutionalized

in the Vietnamese legal framework

for ODA management

Outputs:

1. ODA harmonized

Procedures

Refined procedures for PDO ready for

inclusion into the Gov’s proposed decree

on ODA by Q2, 2012

AAs incorporated into Gov’s

decree/circular on ODA by Q2 2012

The Blue Book updated by Q3 2012

New decree and circular on

management and utilization of ODA

Six Banks monthly meeting minutes

Assumption:

GOV allocates sufficient financial

and human resources for portfolio

management; relevant and active

participation of GOV officials in

training programs

Risk:

Delays in the GOV adoption of new

decree on ODA management

Page 22: TACR: Viet Nam: Support to Improve Portfolio Performance and Aid

18

Design Summary Performance Target and Indicators Data Sources and Reporting

Mechanism

Assumptions and Risks

2. Achievement of Project

start-up compliance

• AAs for projects to be approved from

2012 onward are implemented

• PMUs are able to monitor the AAs

implementation

Mission memorandum of

understanding or aide-memoire

Country portfolio performance and

mission reviews

Approved PDO and FS by the

Government and MPI

3. Strengthening of

Institutional

mechanism for join

portfolio management

• 3.1 Recommendations from portfolio

performance monitoring reviews

adopted:

• One annual country portfolio review,

four quarterly tripartite portfolio

reviews conducted annually, one joint

portfolio performance review with the

Six Banks held every 2 years.

• Alignment of portfolio performance

with the results framework specified

in ADB’s Strategy 2020.

ADB annual reports

The Six Banks bi-annual joint portfolio

performance review reports

MPI’s ODA management reports

4. Strengthening of

capacity for ODA

project management

Demand-driven training programs on

project management skills developed and

implemented for 60% of ongoing projects

including of gender-disaggregated

indicators for training.

TA Implementation reports

Training evaluation sheets

5. Institutionalization and

implementation of

results of dialogues on

ODA effectiveness

Recommendations from ODA

effectiveness forums, including CG

meetings, adopted.

Knowledge products developed and

disseminated by Q1 2014.

Consultative Group proceedings

Page 23: TACR: Viet Nam: Support to Improve Portfolio Performance and Aid

19

Activities:

1.1 Provisions relating to AA and PDO, among others, to be included in new Decree/ Circular on ODA.

1.2 The updated Blue Book

2.1 Prepare AA guideline

2.2 AAs for projects to be approved from 2012 onward are identified.

2.3 The implementation of AA projects is monitored.

2.4 PDO and FS for PPSSF project are prepared

3.1 Systematic quarterly portfolio performance review meetings on problematic projects are conducted.

3.2 Annual and midterm country portfolio review in 2012, 2013 and 2014 are conducted.

3.3 JPPR VII and JPPR VIII in Jun 2013, including monitoring status of JAP 2 implementation, focusing on AA are

followed.

3.4 Targeted sector outputs results framework is consolidated and Update sector result framework monitoring

matrix is updated.

3.5 The achievement of targeted sector outputs using result framework is monitored.

3.6 An Excel- based database in MPI is developed and maintained.

4.1 Training and capacity building needs assessment is conducted.

4.2 Training program (training for EAs/IAs/PMUs staff) and training materials are prepared.

4.3 Quarterly trainings up to 2014 are conducted.

4.4 Evaluation of training program

5.1 Reports for consultative group meetings are prepared.

5.2 Post Busan Monitoring Framework is developed.

5.3 The survey on Aid Effectiveness is prepared.

Inputs:

ADB $ 800,000.

Consulting services: 377,000

Equipment: 10,000

Training/workshops: 267,000

Miscellaneous Adm. 77,000

Contingency: 60,000

The Government will provide

counterpart support in form of

counterpart staff remuneration and

office spaces.