table of contents introduction -...
TRANSCRIPT
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Table of Contents
INTRODUCTION .....................................................................................................................8
1.1. Purpose of the Report.............................................................................................................8
1.2. Profile of Project Proponent ...................................................................................................8
1.3. Contact Details of the Project Proponent...............................................................................9
1.4. Project Implementing Organization........................................................................................9
1.5. Project Consultants .................................................................................................................9
1.6. Description of Land ...............................................................................................................10
1.7. Environmental Regulations Applicable to the Project ..........................................................10
1.7.1. Environmental Regulations of Government of India ....................................................10
1.7.2. Environmental Regulations of State Government ........................................................11
1.8. National Environmental Standards Relevant to the Project.................................................11
1.9. Details of Litigations Pending against the Project ................................................................15
PROJECT DESCRIPTION......................................................................................................16
2.1. Objective of the Project ........................................................................................................16
2.2. Significance of the Project ....................................................................................................16
2.3. Overall Suitability of Site.......................................................................................................16
2.4. Need for the Study................................................................................................................17
2.5. Project Location ....................................................................................................................17
2.5.1. Description of Environmental Sensitive Areas around Project Site..............................24
2.6. Land Use Profile of Project Region........................................................................................26
2.7. Topographical Features of the Proposed Site.......................................................................26
2.8. Project Description................................................................................................................28
2.8.1. Administrative Block .....................................................................................................32
2.8.2. Second Block .................................................................................................................35
2.8.3. Restaurant Building.......................................................................................................35
2.8.4. Other Supporting Facilities ...........................................................................................39
2.8.4.1. Badminton Court...................................................................................................39
2.8.4.2. Pool .......................................................................................................................41
2.8.4.3. Boat Jetty ..............................................................................................................42
2.8.4.4. Parking Facilities....................................................................................................42
2.8.4.5. Landscape..............................................................................................................42
2.8.4.6. Sewage Treatment ................................................................................................43
1
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
2.8.5. Natural Resources Requirement...................................................................................47
2.8.6. Manpower Requirement...............................................................................................48
2.8.7. Project Implementation Schedule ................................................................................48
DESCRIPTION OF THE ENVIRONMENT ..........................................................................51
3.1. Study Area.............................................................................................................................51
3.2. Baseline Environmental Profile of Project Region ................................................................53
3.2.1. Land Environment.........................................................................................................53
3.2.1.1. Physiography.........................................................................................................53
3.2.1.2. Soil.........................................................................................................................56
3.2.2. Water Environment.......................................................................................................57
3.2.2.1. Drainage ................................................................................................................57
3.2.2.2. Hydrogeology ........................................................................................................57
3.2.2.3. Seismicity ..............................................................................................................60
3.2.3. Air Environment ............................................................................................................61
3.2.3.1. Rainfall and Climate ..............................................................................................61
3.2.3.2. Temperature .........................................................................................................62
3.2.3.3. Relative Humidity..................................................................................................63
3.2.3.4. Wind Speed and Wind Direction...........................................................................63
3.2.3.5. Ambient Air Quality...............................................................................................63
3.2.4. Noise Environment........................................................................................................64
3.2.5. Biological Environment .................................................................................................64
3.2.6. Socio Economic Environment .......................................................................................65
3.2.7. Solid Waste ...................................................................................................................66
IMPACT ANALYSIS AND MITIGATION MEASURES.....................................................67
4.1. Activities during Construction Phase ....................................................................................67
4.2. Activities during Operation Phase ........................................................................................67
4.3. Identification of Impacts of Onsite Activities on Various Environmental Attributes............67
4.3.1. Land Environment.........................................................................................................68
4.3.2. Water Environment.......................................................................................................69
4.3.3. Air Environment ............................................................................................................73
4.3.4. Noise Environment........................................................................................................74
4.3.5. Biological Environment .................................................................................................75
4.3.6. Socio Economic Environment .......................................................................................76
4.3.7. Solid Waste Management.............................................................................................77
2
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
4.4. Identification of Impacts of Offsite Activities ............................................................................78
ALTERNATIVE TECHNOLOGIES ......................................................................................80
ENVIRONMENTAL MONITORING PLAN.........................................................................81
6.1. Block Cost Estimate for Implementing EMP .........................................................................83
ADDITIONAL STUDIES .......................................................................................................86
7.1. Introduction ..........................................................................................................................86
7.2. Disaster Management Plan in India ......................................................................................86
7.3. Disaster Management for Almas ..........................................................................................88
7.3.1. Risk Assessment ............................................................................................................88
7.3.2. Objective of Disaster Management Plan ......................................................................89
7.3.3. Various Stakeholders in Disaster Management............................................................90
7.3.4. Institutional Responsibility............................................................................................90
7.3.5. Institutional Arrangements...........................................................................................91
7.3.5.1. Pre-Disaster Preparedness....................................................................................91
7.3.5.2. Emergency Management System during Disaster ................................................92
7.3.5.3. Post Disaster Management...................................................................................97
7.3.6. Plan update and Review................................................................................................97
7.3.7. Training & Drills.............................................................................................................97
PROJECT BENEFITS .............................................................................................................98
ENVIRONMENTAL MANAGEMENT PLAN....................................................................100
SUMMARY AND CONCLUSIONS ....................................................................................114
DECLARATION BY EXPERTS ..........................................................................................116
ANNEXURES .......................................................................................................................126
Annexure I. Soil Monitoring Results .......................................................................................127
Annexure II. Water Quality Monitoring Results .....................................................................130
Annexure III. Air Quality Monitoring Results ...........................................................................135
AnnexureIV. Noise Quality Monitoring Results .......................................................................138
3
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
List of Tables
Table 1.1. Details of the Project Proponent ........................................................................................9Table 1.2. Details of the EIA consultancy Organization.......................................................................9Table 1.3. Details of Land Proposed for Development of Resort ......................................................10Table 1.4. Rules and Acts Applicable to the Proposed Project..........................................................10Table 1.5. Ambient Air Quality Standards .........................................................................................11Table 1.6. Ambient Noise Quality Standards .....................................................................................12Table 1.7. Indian Standard Specifications for Drinking Water...........................................................12Table 1.8. General Standards for Discharge of Environmental Pollutants ........................................13Table 2.1. Administrative Setting of Proposed Ayurvedic Resort Location.......................................18Table 2.2. CRZ Categorization of Project Area...................................................................................24Table 2.3 Area Statement for the Resort..........................................................................................30Table 2.4. List of Facilities Provided in the Administrative Block ......................................................32Table 2.5. Area Statement for Proposed Administrative Block .........................................................32Table 2.6. List of facilities provided in Second Block .........................................................................35Table 2.7. Area Statement of Proposed Second Block ......................................................................35Table 2.8. Area Statement of Proposed Restaurant..........................................................................35Table 2.9. Characteristics of Combined Raw Sewage and Treated Water ........................................43Table 2.10. Water and Material Quantity during Construction Phase ............................................47Table 2.11. Abstract of Manpower Requirement for Construction Phase ......................................48Table 2.12. Abstract of Manpower Requirement for Operation Phase ..........................................48Table 3.1. Description of Monitoring Locations ................................................................................53Table 3.2. Soil Quality Monitoring Result ..........................................................................................57Table 3.3. Water Monitoring Results.................................................................................................59Table 3.4. Ambient Air Quality Monitoring Results ...........................................................................63Table 3.5 Noise Monitoring results...................................................................................................64Table 3.6. Vegetation Cover Observed in Project Area .....................................................................64Table 4.1. Proposed Solid Waste Handling Plan for Construction and Operation Phases ................77Table 4.2. Environmental Factors Affected and Outcome of the Proposed Project Site ..................79Table 6.1. Environmental Monitoring Plan........................................................................................81Table 6.2. Cost Estimate of Implementing Environmental Monitoring for Construction and InitialThree Years of Operation......................................................................................................................83Table 6.3. Block Cost Estimate for Implementing EMP .....................................................................85Table 7.1. Proposed Emergency Management Team for Almas Resort ............................................93Table 7.2. Emergency Contact List to be maintained by Resort........................................................96Table 9.1. Environmental Management Plan ..................................................................................102
4
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
List of Figures
Figure 2.1. Location Map of the Proposed Ayurvedic Resort .........................................................18Figure 2.2. Project Site with Immediate Surroundings ...................................................................19Figure 2.3. View of the Project Site from the North West Corner..................................................19Figure 2.4. View of the Project Site from the South West Corner..................................................20Figure 2.5. View of the Project Site from the Centre to the Eastern Side ......................................20Figure 2.6. View of the river from the South East Corner...............................................................21Figure 2.7. View of the Project Site from the North East Corner ...................................................21Figure 2.8. View of the Project Site from the South East Corner....................................................22Figure 2.9. CRZ Map of Project Area prepared by NIES, Trivandrum .............................................23Figure 2.10. Map showing the sensitive areas around the 1km of the project boundary ...............25Figure 2.11. Land Use Map of the Project Area ................................................................................26Figure 2.12. Contour Map of Proposed Location..............................................................................27Figure 2.13 Layout of Proposed Resort............................................................................................29Figure 2.14 Area Occupied by Various Components of Resort........................................................31Figure 2.15. Elevation and Ground Floor Plan of Proposed Administrative Block. ..........................33Figure 2.16. Section and First Floor Plan of Proposed Administrative Block....................................34Figure 2.17. Section Plan of Proposed Second Block ........................................................................36Figure 2.18. Section and Ground Floor Plan of the Proposed Restaurant........................................37Figure 2.19. Elevation and First Floor Plan of the Proposed Restaurant ..........................................38Figure 2.20. Sectional View and Plan ofProposed Badminton Court................................................40Figure 2.21. Front View, Sectional View and Plan Proposed Swimming Pool ..................................41Figure 2.22. Elevation and Plan of Proposed Boat Jetty ...................................................................42Figure 2.23. Flow Diagram of Proposed STP .....................................................................................45Figure 2.24 Proposed Rain Water Harvesting Facility......................................................................47Figure 2.25. Project Schedule of the Construction of the Proposed Ayurvedic Resort ....................50Figure 3.1. Google Map showing 500 mRadius of the Proposed Site.............................................52Figure 3.2. MonitoringLocations in the Proposed Site ...................................................................53Figure 3.3. Relief and Slope of the Project location at Purathur ....................................................55Figure 3.4. Soils of the Project Location at Purathur ......................................................................56Figure 3.5. Irrigation and Hydrogeology of the Project Location at Purathur ................................58Figure 4.1. Water Balance Statement for Construction Phase .......................................................70Figure 4.2. Water Balance Statement for Operation Phase ...........................................................71Figure 7.1. Structure of Emergency Management Team................................................................93Figure 7.2. Responsibility Allocation within EMT during Emergency .............................................95
5
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
ABBREVIATIONS
BOD - Biochemical Oxygen Demand
COD - Chemical Oxygen Demand
CPCB - Central Pollution Control Board
CRZ - Coastal Regulation Zone
dB - Decibel
DG - Diesel Generator
DMP - Disaster Management Plan
EGSB - Expanded Granular Sludge Bed
EIA - Environmental Impact Assessment
EMC - Electronic Manufacturing Cluster
EMP - Environmental Management Plan
EMT - Emergency Management Team
ERC - Emergency Response Center
GRIHA - Green Rating for Integrated Habitat Assessment
HTL - High Tide Line
KSEB - Kerala State Electricity Board
KSPCB - Kerala State Pollution Control Board
kV - Kilo Volt
MoEF - Ministry of Environment and Forests
NDMA - National Disaster Management Authority
NDZ - Non development Zone
PCB - Pollution Control Board
PIO - Project Implementing Organization
PIZ - Project Impact Zone
PUC - Pollution- under –check
R.O - Reverse Osmosis Plant
6
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
RCC - Reinforced Cement Concrete
RWH - Rain Water Harvest
SPCB - State Pollution Control Board
STP - Sewage Treatment Plant
7
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
INTRODUCTION1.1. Purpose of the Report
Almas Ayurvedic Hospitals and Research Center Private Ltd., with head quarters at Kottakkal,
Malappuram district, Kerala, proposes to develop a resort in their available land of 2.1ha at Purathur
Grama Panchayath, Tirur, Malappuram District. The land parcel is ideally suited for developing a
resort within a village setting having direct access to back water and the sea shore in close proximity.
The project proposal is to establish a resort with facilities for rejuvenation for the inmates in the
Ayurvedic system. Though the project involves development of buildings of 5056.87sqm with a total
capacity of 138 inmates and staff at a time, the construction and operation phase can have direct and
indirect impacts on the environment. Since the project area falls within Coastal Regulation Zone III,
as per the CRZ Notification 2011, S.O .19 (E), an environmental impact assessment study is carried
out to support the application for environmental clearance under the said notification.
The main objectives of the EIA Report are as below:
To document the baseline environmental and social profile of the Project Impact Zone (PIZ)based on primary and secondary data.
To identify and evaluate the impacts on the baseline environmental and social profile of theProject Impact Zone due to the proposed project activities during pre-construction,construction and operation phases.
To identify the requirements of various environmental regulations applicable to the project.
To prepare an Environmental Management Plan (EMP) to mitigate or minimize the adverseimpacts of the project and an Environmental Monitoring Plan to quantify the impacts duringconstruction and operation.
1.2. Profile of Project Proponent
M/s. Almas Ayurvedic Hospitals and Research Center is a Private Limited company having its Head
Office at Kottakkal, Malappuram district, Kerala, is the project proponent. The project proponent has
been in the services with health care sector and has established a hospital at Kottakkal. The existing
hospital at Kottakkal has both the facilities for Allopathic and Ayurvedic Treatment. Taking in to
consideration of the increased choice of the visitors from abroad for holidaying in Kerala, and looking
1
8
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
for traditional herbal wellness centers, M/s. Almas proposes to develop a resort in the available land
in Purathur Grama Panchayath.
M/s KITCO Ltd, an accredited organization under QCI-NABET MoEF is entrusted by M/s. Almas,
the task of carrying out Environmental scheme and Social Impact Assessment for the proposed
Ayurvedic Resort.
1.3. Contact Details of the Project Proponent
The proposed project is at Malappuram District in Kerala. The proponent has registered office atKottakkal, Malappuram.
Table 1.1. Details of the Project ProponentSl. No. Particulars Description1 Contact Address Dr.AhamedKabeer
Chairman &Managing Director# 1/215 D,Al Madeena Institute of Medical Science,Changuvetty, Kottakkal (P.O)Malappuram district676503
2 Phone 0483-28091003 E-mail ID [email protected]
1.4. Project Implementing Organization
The project proponent will act as the Project Implementing Organization (PIO) in this project. As this
is a resort project which takes only about two years to complete, the proponent will assign the work to
local contractors who can complete the construction work of buildings and related facilities.
1.5. Project Consultants
KITCO Ltd. is the consultancy organization for conducting an EIA study for obtaining clearance
under CRZ Notification, 2011for the project. Table1.2provides the contact details of the project
consultant.
Table 1.2. Details of the EIA consultancy OrganizationSl. No. Particulars Description1 Contact Address KITCO Ltd,
Femith’s, P.B No:4407,Puthiya Road, NH Bypass,Vennala,Kochi-682028
2 Phone (0484) 41290003 Fax (0484) 28050664 E-mail ID [email protected]
9
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
1.6. Description of Land
Land details as per the revenue records are presented in Table 1.3.
Table 1.3. Details of Land Proposed for Development of ResortSl.No Item Details1. Survey Numbers 8/1A9, 8/1A10, 8/1B22. Village Purathur3. Tehsil Tirur4. District Malappuram5. State Kerala6. Total area of land 2.1ha7. GPS Coordinates of Boundaries NW Corner 10°49’30.71” N, 75°54’17.02”E
SW Corner 10°49’27.55”N, 75°54’17.65” ENE Corner 10°49’31.39”N, 75°54’24.45” ESE Corner 10° 49’29.89”N, 75°54’25.96”E
1.7. Environmental Regulations Applicable to the Project
A review of the project relevant legal policies, regulations and institutions relevant to the project at
National and State levels are presented in this Section. Applicable clearances required for the project
under various regulations and role of various institutions in implementing various regulations and
environmental management measures are enlisted.
1.7.1. Environmental Regulations of Government of India
The Indian constitution makes environmental protection an explicit duty for every citizen by the
statement, “It shall be duty of every citizen of India to protect and improve the environment including
forests, lakes, rivers, wild life, etc. and to have compassion for living creatures”. In addition,
Government of India has laid out various policy guidelines, acts and regulations pertaining to
sustenance of environment. As per the Indian environmental acts and regulations, following acts and
regulations are applicable for the project.
Acts such as The Forest (Conservation) Act, 1980, Wetland Conservation Act 2010 and EIA
Notification, 2006 are not applicable to this project. The Acts and Regulations applicable are enlisted
in Table 1.4.
Table 1.4. Rules and Acts Applicable to the Proposed ProjectSl.No Applicability of Acts / Guidelines Compliance Criteria1. Coastal Regulation Zone
Notification, 2011Prior clearance to be obtained from MoEFthrough recommendation from Kerala StateCoastal Zone Management Authority.
2. The Water (Prevention & Control ofPollution) Act, 1974
Consent to Establish and Consent to Operate tobe obtained from Kerala State Pollution
10
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Sl.No Applicability of Acts / Guidelines Compliance CriteriaControl Board
3. The Air (Prevention & Control ofPollution) Act, 1981
-do-
The other legislations relevant to the project include Noise Pollution (Regulation and Control) Rules,
2000, The Motor Vehicles Act, 1988, Workmen Compensation Act, 1923, The Public Liability
Insurance Act, 1991, Contract Labour (Regulation & Abolition) Act, 1970, Minimum Wages Act,
1948, Payment of Wages Act, 1936, Equal Remuneration Act, 1979, Child Labour (Prohibition &
Regulation) Act, 1986, The Building & Other Construction Workers (Regulation of Employment &
Conditions of Service) Act, 1996 and the Cess Act of 1996.
1.7.2. Environmental Regulations of State Government
Kerala Building Rules and provisions are applicable to this project.
1.8. National Environmental Standards Relevant to the Project
The standards providing acts under various environmental acts and rules are applicable to the project.
Table 1.5. Ambient Air Quality StandardsPollutants Time
weightedaverage
Concentration in ambient air Method ofmeasurementSensitive of
AreaIndustrial
AreaResidential,Rural &Other areas
SulphurDioxide(SO2)
AnnualAverage*
15 µg/m3 80 µg/m3 60 µg/m3 Improved West andGreek Method
24 hours** 30 µg/m3 120 µg/m3 80 µg/m3 UltravioletFluorescence
Oxide ofNitrogen asNO2
Annual* 15 µg/m3 80 µg/m3 60 µg/m3 Jacob &Ochheisermodified (Na-Arsenite) Method
24 hours** 30 µg/m3 120 µg/m3 80 µg/m3 Gas PhaseChemilumloescence
SuspendedParticulateMatter (SPM)
Annual 70 µg/m3 360 µg/m3 140 µg/m3 High volumesampling. (Averageflow rate not lessthan 1.1m3/minute)
24 hours** 100 µg/m3 500 µg/m3 200 µg/m3
RespirableParticulatematter(RPM),(sizeless than10µm)
Annual 50 µg/m3 120 µg/m3 60 µg/m3 Respirableparticulatemattersampler
24 hours** 75 µg/m3 150 µg/m3 100 µg/m3
Lead (Pb) Annual 0.50 µg/m3 1.0 µg/m3 0.75 µg/m3 ASS Method aftersampling usingEPM 2000 orequivalent Filter
24 hours** 0.75 µg/m3 1.5 µg/m3 1.00 µg/m3
11
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Pollutants Timeweightedaverage
Concentration in ambient air Method ofmeasurementpaper
CarbonMonoxide(CO)
8 hours** 1.0 µg/m3 5.0 µg/m3 2.0 µg/m3 Non dispersiveinfra redSpectroscopy
1 hour 2.0 µg/m3 10.0 µg/m3 4.0 µg/m3
* Annual Arithmetic mean of minimum 104 measurements in a year taken twice a week 24 hourly
at uniform interval.
** 24 hourly/8 hourly values should be met 98 % of the time in a year. However, 2 %of the time, it
may exceed but not on two consecutive days.
Table 1.6. Ambient Noise Quality StandardsCategory of Area / Zone Category of Area / ZoneRural 25-35Sub Urban 30-40Residential(Urban) 35-45Urban(Residential& Business 40-50City 45-50Industrial 50-60
Table 1.7. Indian Standard Specifications for Drinking WaterSl.NO. Parameter Requirement desirable
LimitRemarks
1. Colour 5 May be extended up to50 if toxic substancesare suspected
2. Turbidity 10 May be relaxed up to 25in the absence ofalternate
3. pH 6.5 to 8.5 May be relaxed up to9.2 in the absence
4. Total Hardness 300 May be extended up to600
5. Calcium as Ca 75 May be extended up to200
6. Magnesium as Mg 30 May be extended up to100
7. Copper as Cu 0.05 May be relaxed up to1.5
8. Iron 0.3 May be extended up to1
9. Manganese 0.1 May be extended up to0.5
10. Chlorides 250 May be extended up to1000
11. Sulphates 150 May be extended up to400
12. Nitrates 45 No relaxation
12
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Sl.NO. Parameter Requirement desirableLimit
Remarks
13. Fluoride 0.6 to 1.2 If the limit is below 0.6water should berejected, Max. Limit isextended to 1.5
14. Phenols 0.001 May be relaxed up to0.002
15. Mercury 0.001 No relaxation16. Cadmium 0.01 No relaxation17. Selenium 0.01 No relaxation18. Arsenic 0.05 No relaxation19. Cyanide 0.05 No relaxation20. Lead 0.1 No relaxation21. Zinc 5.0 May be extended up to
10.022. Anionic
detergents(MBAS)0.2 May be relaxed up to 1
23. Chromium as Cr+6 0.05 No relaxation24. Poly nuclear aromatic
Hydrocarbons-- --
25. Mineral Oil 0.01 May be relaxed up to0.03
26. Residual free Chlorine 0.2 Applicable only whenwater is Chlorinated
27. Pesticides Absent --28. Radio active -- --
Table 1.8. General Standards for Discharge of Environmental Pollutants
Sl.No. Parameter
StandardsInlandSurface water
PublicSewers
Land ofirrigation
Marine/Costalareas
1. Colour 5
Above 5,consumeracceptancedecreases
25
2 Odour Unobjectionable -- --
3 Suspended solidsmg/1,max. 100 600 200
a. Forprocess wastewater 100b. b. Forcooling watereffluent10 percent abovetotalsuspendedmater ofinfluent
4 Particle size ofsuspended solids
Shallpass850micronIS Sieve
--a. Floatablesolids, solidsmax. 3 mm
13
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Sl.No.
Parameter Standardsb.Settleablesolids. Max856 microns
5 pH value 5.5 to 9.0 5.5 to9.0 5.5 to 9.0 5.5 to 9.0
6 Temperature
Shall notexceed 5oCabove thereceivingwatertemperature
-- --
Shall notexceed5oCabove thereceivingwatertemperature
7 Oil and grease,mg/1max. 10 20 10 20
8 Total residualchlorine, mg/1 max 1.0 -- -- 1.0
9 Ammonical nitrogen(as N), mg/l, max. 50 50 -- 50
10 Total nitrogen(asN),mg/l,max. 100 -- -- 100
11 Free ammonia(asNH3), mg/l,max 5.0 -- -- 5.0
12Biochemicaloxygendemand (3 days at27oC), mg/l, max
30 350 100 100
13Chemicaloxygendemand,mg/l, max
250 -- -- 250
14 Arsenic (as As)mg/l,max 0.2 0.2 0.2 0.2
15 Mercury (asHg),mg/l, max 0.01 0.01 -- 0.01
16 Lead (as Pb),mg/l,max 0.1 0.1 -- 2.0
17 Cadmium (as Cd),mg/l, max 2.0 1.0 -- 2.0
18Hexavalentchromium (asCr+6),mg/l, max
0.1 2.0 -- 1.0
19 Total chromium(asCr), mg/l, max 2.0 2.0 -- 2.0
20 Copper (as Cu),mg/l,max 3.0 3.0 -- 30
21 Zinc (as Zn),mg/l,max 5.0 15 -- 15
22 Selenium (asSe),mg/l, max 0.05 0.05 -- 0.05
23 Nickel (as Ni),mg/l,max 3.0 3.0 -- 50
24 Cyanide (as CN), g/l,max 0.2 2.0 0.2 0.2
25 Fluoride (as F),mg/l,max 2.0 15 -- 15
26 Dissolved 5.0 -- -- --
14
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Sl.No.
Parameter Standardsphosphates (as P),mg/l, max
27 Sulphide (as S),mg/l,max 2.0 -- -- 5.0
28 Manganese (as Mn) 2 mg/l 2 mg/l 2 mg/l 2 mg/l29 Iron (as Fe) 3 mg/l 3 mg/l 3 mg/l 3 mg/l30 Vanadium (as V) 0.2 mg/l 0.2 mg/l -- 0.2 mg/l31 Nitrate Nitrogen 10 mg/l -- -- 20 mg/l
1.9. Details of Litigations Pending against the Project
No litigations are pending against the project.
15
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
PROJECT DESCRIPTION
The project envisages establishing a world class resort with herbal wellness guidelines based on
Ayurveda.
2.1. Objective of the Project
M/s. Almas Hospital and Research Center has already set up a hospital for allopathic treatment at
Kottakkal. During the course of time, it was observed that foreigners are interested to get ayurvedic
treatment for its rejuvenation values. M/s. Almas has already set up an ayurvedic hospital in their
hospital premises at Kottakkal.
With this background, the objective of the project is to set up an Ayurvedic Resort at Purathur Grama
Panchayath. The location with a beach and estuary in the vicinity offers a serene natural setting.
2.2. Significance of the Project
Ayurveda is not simply a health care system, but a form of lifestyle adopted to maintain perfect
balance and harmony within a human existence. With the success rate of the ayurvedic treatment,
there is an increased demand for the same sector especially from people abroad.
The location due to poor access and low diversity in resources remains economically backward.
Activities of the proposed resort will result in an increase in the income level of people through
employment.
2.3. Overall Suitability of Site
The proposed site is a strip of land between the beach line and back water in a pristine village setting
with virtually no developmental activities. The land is occupied by end of life coconut trees and
cashew trees and no other major crops are cultivated due to the sandy nature of the soil, poor soil
fertility and seasonal intrusion of saline water in the estuary.
The village has no approved development plan proposed by State Planning Department The site
identified for the resort is already identified as a destination for tourism development which is evident
from the fact that a Government of Kerala initiative in this regard through Kerala Tourism
2
16
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Development Corporation for setting up of a Beach resort is under progress at about 4 km from the
proposed location.
As the proposed location falls under the purview of CRZ Notification, 2011, the only commercial
activity that can be done is setting up of resort for temporary occupancy by tourists on the site. This
type of green project is feasible in this area.
2.4. Need for the Study
The proposed site for Almas Ayurvedic Resort lies in the CRZ III, within in the limit of restricted
development as per setting of CRZ Notification, 2011 S.O 19 (E) of MoEF which requires a CRZ
clearance from the Kerala Coastal Zone Management Authority and MoEF. As a part of the clearance
procedure, Rapid Environmental Impact Assessment Report is mandatory.
The purpose of REIA is to understand the project activities and analyze its impact (positive and
negative) on the baseline environmental setting of the project region (physical, biological and socio-
economic settings) and to formulate measures to minimize negative impacts and maximize positive
ones.
The EIA study comprised the following steps.
Understanding the project activities.
Analysis of baseline conditions of project area specifically any environmental or socioeconomic sensitivities through review of literature, field studies and reconnaissancesurveys.
Identification of potential impacts of the project and suggesting appropriate mitigationmeasures.
Preparation of an Environmental Management Plan (EMP) and EnvironmentalMonitoring Schedules and defining Environmental Monitoring Cell (EMC) structure forexecuting EMP.
2.5. Project Location
The project location of the site is shown in Figure 2.1
17
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Figure 2.1. Location Map of the Proposed Ayurvedic Resort
The site is a parcel of land of 2.1 ha and form part of the landform falling between the Arabian Sea
and Tirur Estuary. The Estuary is the boundary of the site on eastern side. Further downstream at
about 3.7 km, the Tirur Estuary joins Bharathapuzha River which drains out to Arabian Sea. The site
is having direct access with Padinjarekkara-Kuttayi Beach Road which is connecting the proposed
Coastal Highway connecting Ponnani and Vengalam. The administrative setting of the land for resort
development is presented in Table 2.1.
Table 2.1. Administrative Setting of Proposed Ayurvedic Resort Location
Village Purathur Grama Panchayath PurathurTaluk Tirur Block Panchayath TirurDistrict Malappuram Jilla Panchayath Malappuram
The proposed site is located about 49 kilometers from the Calicut International Airport (Karippur) and
114 kilometers from Cochin International Airport (Nedumbassery) and about 5 km away from the
Ponnani Harbor. The nearest railway station is Tirur, located at approx. 13 km from the project site.
Figure 2.2 presents the site with its immediate surroundings and Figure 2.3 to Figure 2.8 shows the
present status of the land.
18
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Figure
2.2. Project Site with Immediate Surroundings
Figure 2.3. View of the Project Site from the North West Corner
19
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Figure 2.4. View of the Project Site from the South West Corner
Figure 2.5. View of the Project Site from the Centre to the Eastern Side
20
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Figure 2.6. View of the river from the South East Corner
Figure 2.7. View of the Project Site from the North East Corner
21
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Figure 2.8. View of the Project Site from the South East Corner
The aerial distance of the site is about 280 m away from the Ponnani beach. As the site falls within
500m from the HTL of Arabian Sea at Ponnani beach, it falls under the purview of CRZ Notification,
2011. Further with confluence of Tirur Puzha with Bharathapuzha which subsequently drain to
Arabian Sea, tidal action is prominent in Tirur Puzha which is abutting the project site.
As per CRZ Notification, 2011
As per section 1, sub section (i), the project area fall under the Coastal Regulation Zone sincebeing falling within 500m from HTL.
As per the section 1, sub section (ii), considering the tidal action from Tirur Puzha, 100 m ofthe site from HTL of puzha is falling under the purview of CRZ Notification.
Since the is in a village setting, falling under CRZ III, setting up of Hotels and beach resorts isa permitted activity as per the Clause No 8.i.III.B(i) of CRZ Notification, 2011. The CRZmapping of the proposed site was done by Centre for Earth Science Studies (CESS/NIES).Themap is presented in Figure 2.9.
22
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Figure 2.9. CRZ Map of Project Area prepared by NIES, Trivandrum
23
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Categorization of land as per CRZ notification is presented in Table 2.2 below.
Table 2.2. CRZ Categorization of Project AreaSl.No Description of land Area of Land (m2)1 CRZ landward side of HTL from open sea-CRZ III 21084.19 (Total area of the
proposed site)2 In between 200 m and 500 m CRZ line (with respect to
the HTL of Lakshadweep Sea)21084.19
3 Between HTL (with respect to the Tirur River) and CRZline for rivers or Backwater(NDZ)
8834.59
4 Between the 200 m CRZ line (with respect to the HTLof the Lakshadweep Sea) and CRZ with respect to theTirur River
12249.60
2.5.1. Description of Environmental Sensitive Areas around Project Site
The list of sensitive areas presented as per defined in the Form I of EIA Notification, 2006 within 15
km of the project location is presented in Figure 2.10
24
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Figure 2.10. Map showing the sensitive areas around the 1km of the project boundary
25
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
There are no major environmental sensitive features within the close proximity of project location.
2.6. Land Use Profile of Project Region
Figure 2.11. Land Use Map of the Project Area
2.7. Topographical Features of the Proposed Site
The proposed site occupies the eastern portion of a sand bar between the sea and the northern part of
the Ponnani-Tirur River with very gentle slope (around 1%) towards the east, i.e. to the Puzha Side.
The site is a part of a very gently sloping terrain lying to the east of the sandbar ridge which is half
way between the sea and the estuary. The site is within the physiographic unit “Coastal Plains and
Lagoons” falling under 0-10m altitudinal range. The beach near the site is protected with seawall in
order to protect the seashore. Figure 2.12 presents the contour map of the project location.
26
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Figure 2.12. Contour Map of Proposed Location
27
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
2.8. Project Description
The project aims at setting up of an Ayurvedic resort with five star facilities. The project aims to
integrate resort facility with the various leisure options such as pool, Badminton Court, library, open
area for cultural programmes and a boat jetty to facilitate boating.
The facility will have qualified and trained personnel in hospitality and ayurvedic treatment.
Layout of the proposed resort is presented as Figure 2.13
28
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Figure 2.13 Layout of Proposed Resort
29
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
The building structure for the proposed resort include an Administrative Block and a second block,
with supporting facilities such as restaurant, pool, badminton court and open cultural area, ample car
parking facilities in line with the mandatory requirements, provision for rain water harvesting with
186 cum capacity along with an STP of capacity 20 cum/day is also integrated within the project.
There is a proposal for construction of a Jetty for provision for boat services in the backwater. The
land area occupied by various facilities for the resort with respect to the total land available is
presented in Table 2.4 followed by Figure 2.14 below. As the 100 m from the Tirur Puzha is under
the purview of CRZ Notification, 2011, no permanent structures are proposed and essentially the area
is proposed to retain with an open area and walkway maintained and landscaping.
Table 2.3 Area Statement for the Resort
SlNo: Components of the resort Area (m2)
1 Main Block 1548.372 Second Block 656.533 Restaurant 362.694 Landscape 10698.75 STP 546 Rainwater Harvesting Tank 457 Pool 1448 Open Area for cultural Programmes 7669 Badminton Court 25610 Walk way 281211 Parking area 1698
30
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Figure 2.14 Area Occupied by Various Components of Resort
31
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Description of the facilities in detail is followed.
2.8.1. Administrative Block
Table 2.4. List of Facilities Provided in the Administrative BlockSl.no Facilities Number1 Porch 12 Reception 13 Recreation room 34 Administration 15 Yoga hall 26 Lobby 27 Library 28 Gymnasium 29 Dining hall 110 Majilis 211 Lift 212 Bed rooms 2113 Staff room 1
The area statement for the Administrative Block is presented as Table 2.5 and plan and profile of the
Block are presented in Figures 2.15 and 2.16.
Table 2.5. Area Statement for Proposed Administrative BlockFloor Plinth Area (m2) Floor Area (m2) Carpet Area (m2)Ground 1548.37 1548.37 1238.69First 1470.06 1470.06 1176.04Total 3018.43 3018.43 2414.73
32
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Figure 2.15. Elevation and Ground Floor Plan of Proposed Administrative Block.
33
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Figure 2.16. Section and First Floor Plan of Proposed Administrative Block
34
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
2.8.2. Second Block
Table 2.6. List of facilities provided in Second BlockSl No. Facilities Numbers1 Reception lobby 12 Administrative office 13 Jacuzzi rooms 24 Steam rooms 25 Lift 16 Utility rooms 77 Treatment rooms 158 Guest rooms 109 Bed rooms 2010 Staff room 111 Staff accommodation 2
The Area Statement of the proposed building is presented in Table 2.7 followed by the plan and
profile in Figure 2.17
Table 2.7. Area Statement of Proposed Second BlockFloor Plinth Area (m2) Floor Area (m2) Carpet Area(m2)Ground 656.53 656.53 525.22First 656.53 656.53 525.22Total 1313.06 1313.06 4045.44
2.8.3. Restaurant Building
An independent building is proposed for the restaurant which has direct access from the entrance of
the resort. The dining facilities, a common kitchen to cater to the need of the inmates along with
storage facilities, wash rooms is provided in the restaurant building.
The first floor of the restaurant is meant as rest rooms of restaurant staff such. The area statement for
proposed restaurant building is presented in Table 2.9 below and the plan and profile is presented in
Figure 2.9.
Table 2.8. Area Statement of Proposed RestaurantFloor Plinth Area (m2) Floor Area (m2) Carpet Area (m2)Ground 362.69 362.69 290.15First 362.69 362.69 290.15Total 725.38 725.38 580.30
35
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Figure 2.17. Section Plan of Proposed Second Block
36
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Figure 2.18. Section and Ground Floor Plan of the Proposed Restaurant
37
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Figure 2.19. Elevation and First Floor Plan of the Proposed Restaurant
38
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
2.8.4. Other Supporting Facilities
The supporting facilities which form part of the resort include a Badminton Court, Pool and Boat
Jetty, and Parking facilities. The details of the same are as presented below.
2.8.4.1. Badminton Court
A badminton court is proposed on the northern side of the site behind the Administrative Block. The
section and plan of the proposed badminton court is shown in Figure 2.20.
39
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Figure 2.20. Sectional View and Plan ofProposed Badminton Court
40
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
2.8.4.2. Pool
A swimming pool with shower room is proposed in front of the Second Block. The shower room
consists of wash room and toilet. The sectional and front view of the swimming pool is shown in
Figure 2.21.
Figure 2.21. Front View, Sectional View and Plan Proposed Swimming Pool
41
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
2.8.4.3. Boat Jetty
The resort has the facility for landing house boats. The boat jetty is proposed on the bank of the river.
The boat jetty will be of temporary nature. The section and elevation plan of the boat jetty is show in
Figure 2.22.
Figure 2.22. Elevation and Plan of Proposed Boat Jetty
2.8.4.4. Parking Facilities
Car parking facilities are provided in front of the Administrative Block adjacent to the entry. Open
parking area is allotted for 23 cars among which 2 slots are for disabled parking.
2.8.4.5. Landscape
42
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
A landscape plan is proposed for the resort exclusive with indigenous species found in the site.
Existing vegetation will be retained in those areas which are not disturbed by any construction
activities. The landscape will enhance the aesthetic beauty of the site and also act as a natural
cleanser. A total area of 10699sqm is proposed for the landscape of the resort.
2.8.4.6. Sewage Treatment
PROCESS DESCRIPTION
CHARACTERISTICS OF COMBINED RAW SEWAGE
The characteristics of combined raw sewage adopted for design and characteristics of treated water
are presented in Table 2.8
Table 2.9. Characteristics of Combined Raw Sewage and Treated WaterSl No. Parameter Combined Raw Sewage Treated Water1 pH 6.5 – 7.5 6.5 – 82 SS 250 – 400 mg/l < 100 mg/l3 B.O.D 300 – 400 mg/l < 30 mg/l4 C.O.D 450 – 650 mg/l <250 mg/l5 Oil & Grease 100-150mg/l <5 mg/l
The total quantity of combined raw sewage and laundry from hospital is estimated as 19 cum/day.
VARIOUS UNITS AND EQUIPMENT OF STP
The various units in the existing system are the following:
Grit Chamber/ Oil Trap
Collection Tank
Expanded Granular Sludge Bed(EGSB) reactor
Aeration tank with aerators
Clarifier
Filter Feed Tank
Pressure Sand filter
Activated Carbon Filter
Treated water tank
Sludge Digestor
Filter feed pump
Chemical dosing pump
BRIEF DESCRIPTION OF THE TREATMENT PROCESS
43
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
The sewage and sullage generated from resort blocks and restaurant will be transported to the Sewage
Treatment Plant (STP) through a sewer lines network. Sewage will be collected in the collection tank
after passing through preliminary treatment units (Grit Chamber/Oil trap). From the collection tank,
sewage will be pumped at a uniform rate to the Expanded Granular Sludge Bed (EGSB) reactor.
EGSB reactor is a variant for the UASB reactor for the anaerobic treatment of sewage. The overflow
from the EGSB reactor will be collected in the aeration tank where it is aerated using a diffused
aeration system. The overflow from the aeration tank is let into the clarifier. A portion of bio-sludge
gets settles at the bottom of the clarifier from where it is removed periodically to the sludge digestor.
The overflow from clarifier will be directed to filter feed tank by gravity. The semi-treated water from
filter feed tank is pumped at a uniform rate to a pressure sand filter to remove fine suspended solids
followed by an activated carbon adsorber for removing the traces of BOD, COD, colour, odour etc.
Outlet from the carbon adsorber will be disinfected and collected in the treated water collection tank
before using it for gardening.
44
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Figure 2.23. Flow Diagram of Proposed STP
45
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
2.8.4.7. Solid Waste Management Facility
The solid waste produced during the operation phase can be classified into four.
1. Biodegradable
2. Non biodegradable
3. Recyclable
4. Oil contaminated
The biodegradable solid wastes which include the food waste from the restaurant and other
biodegradable waste from other buildings shall be collected in garbage Collection Bins will be placed
at different locations in the resort. The non biodegradable solid wastes will be collected in different
Garbage Collection bins and will be sold to vendors. The Recyclable materials will be collected and
sent to recycle units.
The oil contaminated solid wastes will be collected from the wellness facility and will be treated
separately using bulking agents (saw dust, waste paper and nutrient mixture) and composted
aerobically to form manure.
2.8.4.8. Power and Water Supply Management
A 250 kVA power supply from KSEB will serve the power requirement during operation phase. DG
sets of 200kVA will be provided as a backup for the entire project.
During operation phase, water will be drawn from the river with the consent of the authority.
2.8.4.9. Rain Water Harvesting
A roof top rain water harvesting facility is integrated with the project and a rainwater storage tank of
capacity 186 m3 is proposed. The rainwater will be lead into a filter unit and stored in ground level
tank. From the storage tank, overflow will be lead into percolation pit/well to recharge groundwater.
The schematic diagram of Rain Water Harvesting tank is presented in Figure 2.24.
46
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Figure 2.24 Proposed Rain Water Harvesting Facility
2.8.5. Natural Resources Requirement
Table 2.10. Water and Material Quantity during Construction PhaseSlNo.
Material Quantity(m3)
CementQuantity(Tonnes)
WaterRequirement(m3)
Volume ofwater forCuring (m3)
1 PCC 1:4:8 672.26 121.01 100.84 242.012 RCC 1 1564.08 547.43 234.61 563.073 RCC 2 109.55 60.25 16.43 39.444 Tile work (Cement
mortar) 1:31826.17 47.94 18.26 18.26
5 Cement plaster 1:6 13911.82 62.60 41.74 111.296 Cement plaster 1:3 4040.57 32.12 12.12 32.327 masonry 1287.45 96.56 64.37 64.378 Total quantity in Lit 488.37 1070.779 Total quantity in million
liters1559.149
The total water demand for construction of the project period of 24 months is approximately 1.6 ML
47
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
2.8.6. Manpower Requirement
The construction of the resort is proposed to be completed within 2 years and the manpower
requirement for the construction phase is presented below in Table 2.10. and the various labour rule
in force which would attract the provisions for the construction labours are presented below.
Table 2.11. Abstract of Manpower Requirement for Construction Phase
Sl. No ACTIVITY TOTALMandays
Construction Phase1 Civil /mechanical/piping work 231182 Electrical work 1263
Total man days 24381Expected number of working days 450Average labour requirement 55Peak labour requirement 110
Proposed manpower requirement for the operation phase of the project is as presented in Table
2.11below.
Table 2.12. Abstract of Manpower Requirement for Operation PhaseSl.No ACTIVITY TOTAL staff
requirementOperation Phase1 Number of rooms for inmates 412 Staff requirement per room 2
Total staff required per day 82Staff requirement during day time 62Staff requirement for night 20
2.8.7. Project Implementation Schedule
The major activities in the construction phase and implementation schedule are presented as Figure
2.25 is as follows.
Preliminary activities
Setting out the building
Clearing of site
Earthwork excavations and foundations
Superstructure works
Finishing works
Electrical works
Plumping works
48
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Painting works
Install doors and windows
Interior finishes
Equipments
Clean ups
The construction is proposed to be completed within 2 years and Figure 2.25 presents the project
implementation schedule for the proposed resort.
49
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Figure 2.25. Project Schedule of the Construction of the Proposed Ayurvedic Resort
50
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
DESCRIPTION OF THE ENVIRONMENT
The environmental attributes, which can be impaired or modified by the proposed construction
activities, include land, air, water, noise and socio economic aspects. In order to understand the
impact of the project on existing environmental attributes, a study of the baseline environmental
setting has been carried out through, reconnaissance survey, environmental monitoring and analysis.
This chapter below presented in details the studies undertaken and the baseline environmental profile
of project setting where the resort is proposed to come up.
3.1. Study Area
The project site is located in a pristine coastal village with no industries or major human activities in
the immediate surroundings. Considering that the proposed activity is falling within 2.1 ha of the land
in a village setting, essentially constituting buildings and green activities, detailed studies were carried
out within 500m of the project location while secondary data on the project setting availed
considering the 1km around the project site. Figure 3.1 below presents the environmental setting with
a radius of 500m from the project site.
3
51
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Figure 3.1. Google Map showing 500 m Radius of the Proposed Site
From Figure 3.1, it can be seen that the proposed location form a patch of land in between the sea and
estuarine part of a river. In order to analyze the environmental impact due to the proposed project
activities, it is essential that the baseline environmental setting of the project area need to be analyzed
and understood with the proposed developmental activities. The ambient environmental sampling and
analysis of the various environmental attributes such as air, water, and soil and noise quality was an
integral part of EIA Study. The selected monitoring locations are shown in Figure 3.2. The
environmental monitoring results are presented in the respective sections.
52
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Figure 3.2. Monitoring Locations in the Proposed Site
Table 3.1. Description of Monitoring Locations
3.2. Baseline Environmental Profile of Project Region
3.2.1. Land Environment
3.2.1.1. Physiography
Geomorphologically the Malappuram district can be divided into three viz. coastal plain(less than 7.5
m AMSL) mid land (7.5-75 m AMSL) and highland (above 75 m AMSL). The coastal plain extends
Locationcode Environmental Attributes Name of location GPS
CoordinatesDescriptionof Location
AQ1 Ambient Air QualityMain Gate of ProposedProject Site (WestBoundary)
10o 49.482’ N75o 54.289’ E
ResidentialArea
AQ2Ambient Air Quality Near MMHSS Koottayi
(1.5 Km from Project Site)
10o 50.190’ N75o 54.160’ E
SensitiveArea
AQ3Ambient Air Quality River Side Boundary of
Proposed ProjectSite(East Boundary)
10o 49.513’ N75o 54.394’ E
Project Area
SW1 Surface WaterMonitoring River side 10o 49.512’ N
75o 54.406’ ENear theProject Area
GW1 Ground Water Bore well inside theproposed site
10o 49.461’ N75o 54.306’ E
Project Area
S1 Soil Quality At the gate of theproposed site
10o 49.479’ N75o 54.292’ E
Near theProject Area
S2 Soil Quality River Side 10o 49.503’ N75o 54.417’ E
Project Area
NQ Ambient Noise Level Main Gate of theproposed site
10o 49.482’ N75o 54.289’ E
Project Area
53
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
as a narrow stretch of land lying along the coast from Kadalundi Nagaram in the north to Ponnani in
the south.
The proposed site occupies the eastern portion of a sand bar between the Arabian Sea and the northern
part of the Ponnani-Tirur estuary with very gentle slope (around 1%) towards the east, i. e. to the Tirur
estuarine side. The site is part of a very gently sloping terrain lying to the east of the sand bar ridge
which is half way between the sea and the estuary and is within the physiographic unit “Coastal plains
and lagoons” falling under 0 - 10 m altitudinal range. Level difference between the eastern and
western sides is only 2.7 meter. The soil type is modified beach sand.
54
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
.
Source:District Planning map Series, Survey of India, 1995
Figure 3.3. Relief and Slope of the Project location at Purathur
55
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
3.2.1.2. Soil
The soil profile of the project area is generally sandy by nature. The site is a former coconut
plantation with surviving end of life trees and cashew trees.
Source: District Planning map Series, Survey of India, 1995
Figure 3.4. Soils of the Project Location at Purathur
56
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Further, in order to ascertain the soil quality to understand its agrarian property, the soil quality was
monitored within the project location and the results of the same are presented in Table 3.2 below and
attached as ANNEXURE I
Soil samples were collected from two locations of the proposed site.
Table 3.2. Soil Quality Monitoring ResultSlno: Parameter Unit Method S1 S2
1 Texture - Sand % -- 79 462 Texture - Silt % -- 13 163 Texture - Clay % -- 3.0 8.04 Soil Type -- -- Sandy Sandy clay5 Colour -- -- Yellowish
greyDark brown
6 Moisture Content % IS 2720(Pt 2)-1973 3.25 7.497 Conductivity at 250C (1:5
soil extract)mmhos/cm IS 14767:2000 0.07 0.06
8 pH at 300C -- IS 2720(Pt 26)-1987 6.61 6.599 Organic carbon mg/100gm IS 2720(Pt 22)-1972 389 143010 Total Nitrogen as N mg/100gm IS 14684-1999 28 34.3111 Phosphorus mg/100gm IS 10158-1982 49.65 34.0912 Chlorides mg/100gm USEPA 9212 3.62 6.5313 Sodium mg/100gm USEPA 3050B 14.99 19.3814 Sodium Absorption Ratio --- USEPA 3050B 2.75 3.9215 Bulk Density g/cm3 USEPA 3050B 1.64 1.4216 Water Holding Capacity % ASTM D 425 3.90 9.4117 Infiltration Capacity cm/hr ASTM D 3385 77.60 29.4118 Cation Exchange
Capacitymeq/100g IS 2720 (Pt 24)-1976 2.27 2.63
19 Cadmium as Cd mg/kg USEPA 3050B BDL (MDL-0.1)
BDL(MDL-0.1)
20 Chromium as Cr mg/kg USEPA 3050B 11.79 19.9621 Copper as Cu mg/kg USEPA 3050B 1.35 3.2022 Iron as Fe mg/kg USEPA 3050B 6121.63 10293.5523 Manganese as Mn mg/kg USEPA 3050B 22.99 35.3624 Lead as Pb mg/kg USEPA 3050B 9.99 24.2225 Zinc as Zn mg/kg USEPA 3050B 7.15 8.7226 Nickel as Ni mg/kg USEPA 3050B 4.19 7.75
3.2.2. Water Environment
3.2.2.1. Drainage
The site discharges and drains to Tirur Puzha.
3.2.2.2. Hydrogeology
57
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Source: District Planning map Series, Survey of India, 1995
Figure 3.5. Irrigation and Hydrogeology of the Project Location at Purathur
Surface and groundwater characteristics and flows were assessed using field investigations as well as
maps, and data from the ground water department, Kerala. The site is sandwiched between the sea and
the estuary. Deeper sedimentary formations are absent. Ground water potential therefore is confined
to very limited occasional patches with silty formations. It is understood that the ground water is
confined in silty base. A number of wells are in use in the locality nearby the proposed site.
Baseline water quality of the project area was established with the ground and surface water quality
monitoring in the project location. The results of surface water quality and ground water quality
monitoring are presented in Table 3.3 and attached as ANNEXURE II
58
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
The surface water was collected from the River and marked (SW1)
The ground water sample was collected from the Bore well inside the project Site (GW1)
Table 3.3. Water Monitoring ResultsSlno: Parameters Unit Method SW1 GW1
1 pH at 320C --- Cl.2 of IS 3025 (Pt11):1983, Reaff. 2006 6.77 7.45
2 Color Hazen units Cl. 2 of IS 3025 (Pt4):1983, Reaff. 2006 4.0 4.0
3 Turbidity NTU IS 3025 (Pt 10):1984,Reaff. 2006 1.30 BDL (MDL-0.5)
4 Total dissolvedsolids mg/l IS 3025(Pt 16):1984,
Reaff. 2006 760 692
5 Total solids mg/l IS 3025 (Pt 15):1984,Reaff. 2009 764 692
6 Total Hardness asCaCO3
mg/l Cl. 2 of IS 3025(Pt21):1983, Reaff. 2002 161.68 363
7 Chloride as Cl mg/l Cl. 2 of IS 3025(Pt32):1988, Reaff. 2009 296.26 20.70
8 Sulphate as SO4 mg/l Cl. 4 ofIS 3025(Pt24):1986, Reaff. 2009 70.01 288.15
9 Fluoride as F mg/l Cl. 5 of IS 3025(Pt60):2008
BDL(MDL-0.1) BDL (MDL-0.1)
10 Alkalinity asCaCo3 mg/l Cl. 8.1 of IS 3025(Pt
23):1986,Reaff. 2009 116.48 180.60
11 Iron as Fe mg/l Cl. 6 of IS 3025 (Pt53):2003,Reaff. 2009 0.10 0.14
12 Nitrate as NO3 mg/l Cl. 3 of IS 3025(Pt34):1988, Reaff. 2009 0.33 0.15
13 Nitrite as NO2 mg/l Cl. 4 of IS 3025(Pt34):2005, Reaff. 2009 0.01 BDL(MDL-0.01)
14 Copper as Cu mg/l Cl. 6 of IS 3025(Pt42):1992, Reaff. 2009
BDL(MDL-0.01) BDL(MDL-0.01)
15 Nickel as Ni mg/l IS 13428: 2005Annex L, Reaff. 2009
BDL(MDL-0.01) BDL(MDL-0.01)
16 Mercury as Hg mg/l Cl. 5 of IS 3025 (Pt48):1994, Reaff. 2009
BDL(MDL-0. 0005)
BDL(MDL-0.0005)
17 Cadmium as Cd mg/l Cl. 6 of IS 3025(Pt41):1992, Reaff. 2009
BDL(MDL-0.001)
BDL(MDL-0.001)
18 Calcium as Ca mg/l Cl. 5 of IS 3025(Pt40):1991, Reaff. 2009 22.61 131.86
19 Magnesium as Mg mg/l Cl. 6 of IS 3025(Pt46):1994, Reaff.2009 25.58 34.26
20 Manganese as Mn mg/l Cl. 5 of IS 3025(Pt59):2006 0.069 BDL(MDL-0.05)
21PhenolicCompounds asC6H5OH
mg/l Cl. 6 of IS 3025 (Pt43):1992, Reaff. 2009
BDL(MDL-0.0005)
BDL(MDL-0.0005)
22 Zinc as Zn mg/l Cl. 5 of IS 3025(Pt 0.098 BDL(MDL-0.05)
59
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
49):1994
23 Sodium as Na mg/l Cl. 5 of IS 3025 (Pt45):1993, Reaff. 2009 240 35
24 Potassium as K mg/l Cl. 5 of IS 3025 (Pt45):1993, Reaff. 2009 14 3.0
25 Total Chromiumas Cr mg/l IS 13428: 2005
Annex J, Reaff. 2009BDL(MDL-0.01) BDL(MDL-0.01)
26 Lead as Pb mg/l Cl. 8 of IS 3025(Pt47):2005, Reaff. 2009
BDL(MDL-0.005)
BDL(MDL-0.005)
27 Conductivity µs IS 3025 (Pt 14):1984,Reaff. 2006 1240 1120
28 Total nitrogen asN mg/l Cl. 5.2 of IS 3025 (Pt
34):1988, Reaff. 2009 30.80 16.80
29 Dissolved Oxygen mg/lCl. 4.1 & 4.2 of IS3025 (Pt 38):1989,Reaff. 2009
6.30 4.10
30 Chemical Oxygendemand mg/l IS 3025(Pt 58) : 2006 10 8.0
31Biochemicaloxygen demand @27°C for 3 days
mg/l IS 3025(Pt 44):1993,Reaff. 2009 4.0 3.0
32 Oil & Grease mg/l Cl. 5 of IS 3025(Pt39): 2009 0.20 BDL(MDL-0.05)
33 Temperature 0C APHA 2550-B 29 29
34 Phosphate as PO42- mg/l Cl. 4 of IS 3025 (Pt
31):1988, Reaff. 2009 0.12 BDL(MDL-0.05)
35 Total SuspendedSolids mg/l IS 3025 (Pt 17):1984,
Reaff. 2006 3.80 BDL(MDL-1.0)
36 TotalColiforms/100ml
IS 1622:1981,REAFF.2003 500 23 Total
Coliforms/100ml
37 FaecalColiforms/100ml
IS 1622:1981,REAFF.2003
220 <2 FaecalColiforms/100ml
Note: BDL: Below Detection Limit
MDL: Minimum detection Limit
The water sampling parameters for bore well water is within the recommended range of portable
water as per WHO standards.
3.2.2.3. Seismicity
As per National Earthquake Zonation map of India, in Figure 3.6, Kerala falls in Zone III where
earthquake of magnitude 6 on Richter scale is a probability
60
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Figure 3.6. Seismic Map of the Project Area
The map shows that Kerala falls in Zone III which is prone to earthquake below magnitude 6. The site
is located in the landward side beyond the ridge of the sand bar. The vegetation the HTL to 250m
zone protects the site from the vulnerability to tsunami.
3.2.3. Air Environment
3.2.3.1. Rainfall and Climate
61
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
The district has dry season from December to February and hot season from March to May. The
South-West monsoon prevails from June to September and the North-East Monsoon from October to
December. The average annual rainfall of the district during the last five years is about 2800mm. Out
of this, major rainfall contribution is from SW monsoon followed by the NE. the SW monsoon
contributes nearly 73.5% of the rainfall. NE monsoon contributes nearly 16.4% and March to May
summer rain contributes nearly 9.9% and the balance 0.2% is accounted for January and February
months.
Source: District Planning map Series, Survey of India, 1995
Figure 3.7. Climatic Conditions of the Project Location
3.2.3.2. Temperature
62
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
The climate is generally hot and humid. March and April months are the hottest January and February
months are the coldest. The maximum temperature ranges from 28.9 to 36.2°C and the minimum
temperature ranges from 17.0 to 23.4°C. The temperature starts rising from January and reaches the
peak in the month of March and April and then decreases during the monsoon month and again rising
from September onwards.
3.2.3.3. Relative Humidity
The relative humidity ranges from 84 to 94% during morning hours. The humidity is more during the
peak monsoon months from June to September.
3.2.3.4. Wind Speed and Wind Direction
The wind is predominant from east as well as west during morning and evening hours. The wind
speed is more during December to February months. It ranges from 2.9 to 7.2 km per hour.
3.2.3.5. Ambient Air Quality
In order to establish the baseline ambient air quality of the project surroundings, environmental
monitoring was carried out within the proposed location for the criteria pollutants. The details of the
monitoring locations along with results of environmental monitoring with standard prescribed for the
location are presented in Table 3.4and attached as ANNEXURE III
Table 3.4. Ambient Air Quality Monitoring ResultsParameters Unit Intervals Value Reported NAAQ Standards
AQ1 AQ2 AQ3 Ecosensitiveareas
Otherarea
Particulate matter ofsize less than 2.5 µm(PM10)
µg/ m3 I 52.6 57.3 39.5 100 100
Particulate matter ofsize less than 2.5 µm(PM2.5)
µg/ m3 I 19.3 21.4 10.7 60 60
80Sulphur Dioxide(SO2)
µg/ m3 I 7.6 9.6 6.3 80 80II 6.9 7.9 6.1III 7.1 8.3 6.4
Nitrogen Dioxide(NOx)
µg/ m3 I 8.3 10.1 8.3 80 80II 8.7 8.7 7.1III 8.1 8.8 7.2
Carbon Monoxide (CO)8 Hrs
mg/m3 I 0.8 0.9 0.7 2 2II 0.9 1.0 0.8III 0.8 0.8 0.8
63
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
All the Air Quality parameters are far below the maximum levels permitted.
3.2.4. Noise Environment
The project location being in a calm village setting, without much developmental activities close by,
the traffic operating through the Tippu Sultan road is the contributing factor for noise level of project
region. Baseline data on the ambient noise environment is ascertained through noise monitoring. The
noise monitoring locations details along with the analysis of the observed data is presented in Table
3.5 and attached as ANNEXURE IV
Table 3.5 Noise Monitoring resultsNoise level values dB (A) CPCB Standard Leq
dB (A)L10 L50 L90 LDn LDay LNight Day Night54.3 47.8 40.8 50.0 51.5 42.8 55 45
3.2.5. Biological Environment
There is no national park and wildlife sanctuary within 40km from the project site. The land is in the
midst of a coastal village with scattered settlements and coconut and cashew plantations as economic
crops suitable to beach side sandy soil. The coconut trees on the project site are end of life trees.
Denatured vegetation consists of Calophyllum inophyllum (Alexandrian laurel/Punna), Lannea
coromandelica (Uthi), Cordia obliqua (Pasakkamaram), Acacia auriculiformis (Acacia), Anacardium
occidentale (Cashew nut), Alstonia scholars (Ezhilampala) and Azadirachta indica (Aryaveppu).
Table 3.6 presents the list of vegetation observed in the site.
Table 3.6. Vegetation Cover Observed in Project Area
Sl no Scientific Name Family Common/Local Name Habit
1 Abrus precatorius L. Fabaceae Kunni Climber2 Abutilon indicum (L.) Sweet Malvaceae Kattooram Shrub3 Acacia auriculiformisA.
Cunn.exBenth.Mimosaceae Acacia Tree
4 Ageratum conyzoides L. Asteraceae Appa Herb5 Alstonia scholaris(L.) R.Br. Apocynaceae Ezhilampala Tree6 Anacardium occidentale L. Anacardiaceae Cashew nut tree Tree7 Anamirta cocculus (L.) Wight
&Arn.Menispermaceae Nanchuvalli Climber
8 Calophyllum inophyllum L. Clusiaceae Punna Tree9 Calotropis gigantea (L.) R.Br. Asclepiadaceae Erukku Shrub10 Canthium rheedei DC.
EndemicRubiaceae Kattara Shrub
11 Chlori sbarbata Sw. Poaceae Kodappullu Herb12 Chromolaena odorata (L.) King
& Robins.Asteraceae Comminist-pacha Shrub
64
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Sl no Scientific Name Family Common/Local Name Habit
13 Chrysopogon acciculatus (Retz.)Trin.
Poaceae Snehappullu Herb
14 Citrulus lanatus (Thunb.)Matsumara&Nakai
Cucurbitaceae Thannimathan Climber
15 Clitorea ternatea L. Fabaceae Sankhupushpam Climber16 Cocos nuciferaL. Arecaceae Thengu Tree17 Cyperus rotundusL. Cyperaceae Muthanga Herb18 Eleucine indica (L.) Gaertn. Poaceae Herb19 Evolvulus alsinoides (L.) L. Convolvulaceae Vishnukranthi Herb20 Gliricidia sepium (Jacq.) Kunth
ex WalpFabaceae Seemakkonna Tree
21 Lannea coromandelica (Houtt.)Merr.
Anacardiaceae Uthi Tree
22 Leea indica (Burm.f.) Merr. Leeaceae Chorianthali Shrub23 Leucas aspera (Willd.) Link Lamiaceae Thumba Herb24 Leucas lavendulifolia J.E. Smith Lamiaceae Thumba Herb25 Macaranga peltata (Roxb)
Muell.-Arg.Euphorbiaceae Vatta Tree
26 Morinda citrifolia L. Rubiaceae Cherumanjanathi Tree27 Oldenlandia herbacea (L.) Roxb. Rubiaceae Nonganampullu Herb28 Pedalium murex L. Pedaliaceae Kakkamullu Herb29 Phyllanthus aery-shawii Brunel
RouxEuphorbiaceae Keezharnelli Herb
30 Physalis minima L. Solanaceae Njottanjodiyan Herb31 Premna serratifolia L. Verbenaceae Munja Shrub32 Ricinus communis L. Euphorbiaceae Aavanakku Shrub33 Sida acutaBurm.f Malvaceae Anakurunthotti Shrub34 Sida rhomboideaRoxb. ex
FlemingMalvaceae Kurumthotti Shrub
35 Thespesia lampas (Cav.) Dalz.&Gibs.
Malvaceae Kattupruthi Shrub
36 Triumphetta rhomboideaJecq. Tiliaceae Oorppam Shrub37 Vernonia cinerea (L.) Less Asteraceae Poovankurunthal Herb38 Ziziphus oenoplia (L.) Mill. Rhamnaceae Cheruthudali Shrub
Being lined by Tirur Puzha, about 5.0 km upstream of its confluence with the estuary, the adjoining
areas of the eastern boundary of the project site show occurrence of a few mangroves. Avicennia
officinalis (Uppatti), Rhizophora mucronata (Panchikandal) and Acanthus ilicifolius (Chullikkandal)
are the true mangroves and Calophyllum inophyllum (Punna), Clerodendrum inerme (Cheru-chinna),
Derris trifoliata (Kammattivalli) and Premna serratifolia (Munja) represent mangrove associates.
3.2.6. Socio Economic Environment
According to 2011 census, Government of India, Malappuram district has a population of 4,110,956.
This gives it a ranking of 50th in India (out of a total of640).The district has a population density of
1,158 inhabitants per square kilometer (3,000/sq mi). The population growth rate over the decade
65
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
2001-2011 was 13.39%.Malappuram has a sex ratio of 1096femalesfor every 1000 males, and a
literacy rate of 93.55%.Malappuram has the highest fertility rate in Kerala.
The population of the Purathur village is 31915 which comprises of 15062 males and 16853 females.
The literacy rate of the village is 78.41%, which is far below the district average.
Most of the population in this area depends on the sea for their livelihood. Koottayi fishing harbor is
just 1.5 km away from the proposed project site. After implementation of the resort, in the long run,
there is a possibility to increase the floating population and it will lead to the areas development in
terms of small business units and others .In such condition the residing population will get
employment opportunities
3.2.7. Solid Waste
The proposed site is within a village setting with predominantly residential belt along the beach side
with a few schools and mosques. Being outside the municipal limit, there is no systematic solid waste
management system in function in the project location.
The proposed site is devoid of any type of construction. Hence there is no issue of demolition waste
being generated at the site. During construction phase, the solid waste generated includes construction
debris which will be collected by proper means. During the operation phase solid waste generated will
be collected and treated according to the norms and conditions of KSPCB.
66
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
IMPACT ANALYSIS AND MITIGATION MEASURES
Any developmental activities invariably bring changes in the ambient setting of the project region
which can have positive and negative impact on the environment and community. Sustainable
development ensures maximizing the potential benefits of the developmental activity and ensuring
that the negative impacts are avoided minimized or mitigated. The positive and negative impacts
could be direct, indirect or cumulative, and also the impacts could be long term, or short term and also
permanent or temporary by nature. By understanding the environmental setting of the project site and
its surroundings and by reviewing the proposed development plan, the probable impacts due to the
proposed development can be delineated and appropriate measures shall be proposed to avoid,
minimize and mitigate impacts. The activities during the construction and operation phase of the
project are critically reviewed to understand the resultant impact due to the same and this section
identifies the potential impacts, and suggests the various mitigation measures related to the Ayurvedic
Resort.
4.1. Activities during Construction Phase
The various activities during the construction phase include leveling of site, clearing of trees and
shrubs, increased vehicular movement for transit of men and material, storage of construction
materials, operation of construction machineries, increased influx of labours to the area, construction
work includes excavation, filling, foundation works, structural works and finishing works. While the
major construction activities are located in the project location, the supportive facilities such as quarry
and crusher at areas located offsite where also changes are happening due to proposed project
development. Quarried materials will be procured only from licensed quarries and crusher units.
4.2. Activities during Operation Phase
During the operation of the resort, there will be increased influx of visitors to the project area and
operation of resort, restaurant, and house boat operation ayurvedic treatment facilities for the inmates.
4.3. Identification of Impacts of Onsite Activities on Various Environmental
Attributes
4
67
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
The probable impacts due to the proposed construction activities on the various environmental
attributes for the construction and operation phase of the projects are discussed below.
4.3.1. Land Environment
The proposed site is for Almas Ayurvedic Resort is presently almost a plain land with small
undulation with major crop as coconut. No major excavation, filling and leveling the site is required
for implementation of the proposed resort. The soil formation is dominated by beach sand with high
percolation risk. Drainage pattern of the proposed area would be slightly disturbed during the
construction phase; however, proper drainage is planned for operational phase. The resort proposal
involves restoration of the trees within the plot to maximum possible. With existing compound wall in
place, the construction materials and debris reaching the nearby area is not anticipated.
Onsite Activities
Anticipated impacts during Construction Phase
Top soil will get compacted during the movement of people and machinery, vehicles,throughout construction phase.
Site clearance may lead to the soil erosion of the said area and which may pollute the watercourse existing close by.
Storage of construction materials may pollute soil and there by impact the agriculturalproperty at the site due to mixing with concrete, cement construction waste etc.
Soil pollution can occur due to spillage of fuel/lubricants used in construction machineriesand vehicles during site clearance, cleaning of vehicles/machineries used and also with themixing of materials used such as paints during the painting process.
Mitigation Measures
Top soil up to a depth of 30 cm from building foot print shall be stripped out and stored asheaps with proper geotextile covering.
The construction machineries shall be placed only in designated locations and internalmovement shall be planned in such a way to limit the movement in non construction areas.
Site clearance activities shall be carried out in a non rainy season with disturbing thevegetation only in the areas where construction needs to be initiated.
The construction material shall be stored in a specified location with proper covering.
It shall be ensured that no construction spoils of any unsuitable material are disposed ofoffsite or any other place in the project area.
Machineries and vehicles shall be properly maintained to avoid fuel leakage.
Designated areas shall be arranged for parking and fuelling and cleaning of the constructionvehicles such that the spillage if any will not be lead to soil pollution.
68
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Anticipated Impacts during Operational Phase
During operation phase, waste management if not executed properly shall pollute the land
environment; however, this impact is not anticipated since the proposal involves establishing an
efficient waste management system in place. The sludge will be used as manure for the landscape.
4.3.2. Water Environment
Construction and operational phases of the project can influence the water environment of the project
setting. The water consumption during construction phase is estimated as 8.42 KLD and for operation
phase as 35.5 KLD. . Source of water
Water balance estimated for the project for both construction and operation phase is presented in
Figure 4.1 and Figure 4.2.
69
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
WATER BALANCE STATEMENT FOR ALMAS AYURVEDIC RESORT-CONSTRUCTION PHASE
Figure 4.1. Water Balance Statement for Construction Phase
Labour Requirement
4.95 KLD
Total WaterDemand
8.42 KLD
Source
Bore well
Tube well
Supply fromprivate parties
ConstructionRequirement
3.47 KLD
Drinking-0.55 KLD
Non Drinking-4.40KLD
Curing-2.39 KLD
Concreting andfinishing-1.08 KLD
70
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
WATER BALANCE STATEMENT FOR ALMAS AYURVEDIC RESORT- OPERATION PHASE
Figure 4.2. Water Balance Statement for Operation Phase
Fresh Water35.5KLD
Recycled Water –15.5 KLD
Sludge and EvaporationLoss 0.5 KLD
Sewage 16 KLD
Treated Water – 15.5KLD
Irrigation for Landscaping32KLD
Drinking 19KLD
71
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Considering the proposed development plan, increased water demand during the construction phase,
pollution of nearby water courses due to soil erosion from the proposed site, disposal of untreated
waste water or solid waste in the water body shall lead to pollution of water courses.
Anticipated Impacts during Construction Phase
Meeting the increased water demand for the construction phase from water bodies withcompeting users can have impact on community especially during drought seasons.
During excavation process, surface runoff of the excavated earth will lead to partial orcompletely filling of water bodies and also to enhance the turbidity of water to unacceptablelevels for the intended uses and also to the loss of aquatic flora and fauna.
Surface drainage from the temporary material stock yard can lead to pollution of watercourses.
During site clearance, fuels/lubricants used in site can pollute water courses if the find its wayto the water courses
Cleaning of construction machineries if carried out near the water courses, can lead topollution of water courses during site clearance.
Disposal of waste or un treated sewage in to the water courses of mixing with the groundwater can have impact on ground water and surface water resources of project region.
Pollution of common water resources can have impact on the community.
Mitigation Measures
It shall be ensured that excavation activities are taken up during non rainy season and thetemporary detention pond if necessary shall be provided for the entire construction period forthe project site to avoid direct discharge of turbid water to nearby water course.
Dumping of waste in the water course shall be completely prohibited.
Construction waste generated shall be reused for laying foundation of walkways and roads.
Anticipated Impacts during Operation Phase
During the operation phase of the project, water would be required for domestic purpose, landscaping,
drinking etc. The water demand for the operation phase is presented in Figure 4.2.
It is proposed to recycle 15.5 KLD of water during operation phase and the recycled water would be
utilized for irrigation, flushing etc.
During the operation phase, if water withdrawn from the intake point is more than thereplenishable capacity of the resource, significant impact will be resulted for the competingusers.
Disposal of untreated/partially treated sewage can result in pollution of surface and groundwater courses.
Mitigation Measures
72
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
As mentioned, it is proposed to recycle 15.5 KLD of water during operation phase, which willcater to 43.6% of daily water demand.
Rainwater harvesting is integrated in the project design with a proposed storage capacity theunderground tank is 186.5 m3 and the same shall be used for various operational requirementsof Resort.
Efficiency of operation of Sewage Treatment Plant would be ensured in such a way to ensurethat the treated water meets the standard prescribed by KSPCB. Routine checking of outletquality of the STP shall be made to ensure the treatment capacity to the satisfactory limit.
4.3.3. Air Environment
During the construction phase of the project, the site clearance activities would lead to dust emissions
here would be increased traffic in the project area due the man and material transit. Spillage of
construction materials such as sand, gravel, earth etc. during transit can lead to dust emission both
along the way and at construction site. Material handling at the project site and operation of
construction machineries based on petroleum fuels remain are sources of air pollution during
construction phase.
Anticipated Impacts during Construction Phase
During site clearance, excavation and leveling can lead to dust generation
Loading, unloading and material transit such as aggregates and cements during the siteclearance and excavation generates dust.
Operation of construction machineries such as excavator, loader, transit vehicles leads to dustemission and pollutants due to fuel burning.
The movement of transit vehicles and the spillage during the material transit will lead to dustemission if loose soil is transported without covering
Cement handling will give out fugitive emissions for plastering works and ceiling works
Mitigation Measures
Considering that the project area is not close of any thickly populated belt and also the soil is sandy by
nature, the dust emission would be comparatively less during the construction phase. Considering the
magnitude of machineries to be deployed it can be inferred that with sound construction practices
such as proper maintenance of machineries and use of standard fuel can control the vehicle related
emission to a great extend.
Sprinklers shall be installed in areas of regular vehicular movement and along access ofconstruction site. .
While the compound wall will act as the barrier towards spreading of dust from constructionactivities, temporary sheidling of the project area shall be to a height of 3m out to avoidspreading of dust
73
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Vehicles transporting all construction materials will be covered en-route.
Spill proof packing and containers will be used for the transportation of the fine materials.
All vehicles and machineries shall be properly maintained to control air emission.
Valid Pollution Under Control Certificate shall be made mandatory for all the constructionvehicles and machineries employed.
Clean fuel shall be used by the vehicles and machineries to reduce the emission of pollutants.
DG set employed in construction phase shall comply with the CPCB norms on air emissions.
Solid waste burning shall be strictly prohibited and proper waste management system in placeto be ensured.
The construction vehicles used shall have facility for tyre washing before leaving the sourcingarea and project location so as to avoid material spillage leading to dust emission on the way.
Anticipated Impacts during Operation Phase
During the operational phase of project, significant air polluting activities are expected. There is a
proposal for a stand by DG set of capacity 250 kVA, which will be operating during power failure.
DG set complying with the CPCB guidelines would be installed. Green belt development with tree
species of perennial foliage is expected to have positive impacts in the ambient air quality around the
site.
4.3.4. Noise Environment
The increased traffic due to operation of vehicles and construction machinery can increase the
ambient environmental setting of project region.
Anticipated Noise Impacts during Construction Phase
Operation of excavator, loader, crane and transporting vehicles, loading and unloading ofmaterials, lead to increased ambient noise level
During construction, work involving use of concrete mixer and vibrator can lead to increasednoise level.
Noise pollution due to wood cutting, plaining machine, drilling machine, welding machine,gas cutter / electrical cutter etc. during joinery works
Mitigation Measures
All construction activities involving used of machinery shall be carried out during day timeonly.
Servicing of all construction vehicles and machinery shall be done regularly and duringroutine servicing operations, the effectiveness of exhaust silencers shall be checked and
Vehicles used for transportation of construction materials at site shall conform to the noiseand exhaust emission standards and shall be operated only during non-peak traffic hours..
74
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Perimeter noise monitoring is recommended during the construction phase.
DG set used in construction phase shall capacity with CPCB standard DG set
Anticipated Impacts during Operation phase
Considering the project activities during operation phase, there is no major noise emitting activities
envisaged. Operation of DG set, pump sets used in RO Plant and STP will have noise emission and
the emission levels is not expected have a marginal increase in ambient noise level of project region
provided routine maintenance is ensured.
4.3.5. Biological Environment
The project location is dominated by Coconut plantation and common shrubs. The vegetation standing
on the foot print of the proposed structures would be cleared .
Anticipated Impacts during Construction Phase
Site clearance can lead to loss of terrestrial and fauna.
The top soil transported to the construction site may contain invasive plant species affectingthe nearby agricultural lands
Contamination of soil or nearby water course if any can lead to impact in terrestrial andaquatic flora and fauna during, RCC roofing, column construction, etc.
Mitigation measures
The land foot prints of the buildings, roads and parking contributes only 33.5% of total land.
However, the landscape up to 50.74% of total land of development is proposed, where native species
are proposed. Total number of trees to be felled to clear the foot print is 48. Compensatory plantation
shall be carried out with thrice the number of trees felled with inclusion of native species as part of
landscape development. Considering that the project form part of agricultural land and doesn’t have
any endemic or endangered species involved, the project is not expected to have significant impact on
the biological environment. The following mitigation measures shall be done during construction
phase.
Site clearance shall be limited to the minimum area and also the existing trees in the site shallbe retained as much as possible.
Trees that to be transplanted would be shifted to appropriate locations.
Construction material shall be properly stored without draining out to the nearby land or watercourse and there by polluting the said environment.
Landscaping by accommodating native species will improve the vegetative cover and add toair shed purification functions. Vegetation planned for landscaping buffers and for aestheticappeal should be maintained, and a maintenance programme should be established andimplemented.
75
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Along the river side site boundary except for access to the jetty shall be developed withappropriate bio-fencing to maintain continuity with the riparian belt.
A green belt herbal garden (medicinal plant conservatory), aesthetically designed lawns,miniature gardens, topiary, etc. shall be developed within the project area in the postestablishment phase.
Anticipated Impacts during Operation Phase
During the operation phase of resort, the project will not have any significant negative impact on the
biological environment.
Of this, 100 trees are end of life and unyielding. Two hundred indigenous trees would be planted as
part of landscape and green belt development.
4.3.6. Socio Economic Environment
The construction and operation phase of the project shall positively affect the socio economic setting
of the project region. The project would trigger the local economic growth with increased temporary
employment during construction. As the project is expected to have high income group visitors from
abroad and the local population would get an opportunity to explore the tourism potential of project
region through selling of handicrafts, stage shows of traditional art forms, back water tourism,
popularizing ethnic food.
During the construction phase, there will be increased traffic operation due to man and material
transit. With migrant labours contributing to majority of the construction requirements of State, an
interaction of natives with people from a culturally different domain would result in. The essential
safety aspects and basic facilities for the labours during the construction phase need to be ensured.
Anticipated Impacts during Construction Phase
Increased dust emission from the construction site will affect the health of local population.
Material transit if done during the peak hours can lead to inconvenience to commuters
Spillage of materials on its way and transit of materials without covering would lead to dustemission along the transit way and also cause accident risk to the commuters.
Improper solid waste management and sanitation facilities for the construction labours willpollute the land and water environment of project region and check unsanitary conditions.
Unhealthy solid waste and sanitary management in the construction site can lead to pollutionof land, air and water of the project setting leading to conflict between the natives andconstruction labours.
Mitigation Measures
Whenever possible, local laborers will be employed for construction work.
76
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
During construction phase, proper drainage management shall be ensured within the site withchanges as appropriate according to the progress of the work so as to avoid draining of soil anconstruction material to nearby land and water body and there by polluting the environment.
Man and material transit shall be scheduled to non peak hours to avoid inconvenience to thecommuters.
Construction activities shall be planned in such a way to avoid simultaneous operation ofnoisy machineries. No noisy construction shall be executed during night hours (10.00 PM –6.00 AM)
The work forces would be accommodated offsite. Basic facilities or the labours shall beensured with provision of clean drinking water, quality food and adequate number ofdecentralized latrines and urinals for use during working hours.
An adequate solid waste management system in place with segregation and collection ofwaste and handling the same through recycling or treatment and disposal.
Labours shall be provided with Personnel Protective Equipments (PPEs) such as hard hats,safety goggles, face shields, masks, ear plug/ear muff, gloves, safety belt, boots, etc. It shallbe ensured that the labours are wearing the necessary PPEs during the construction phase.
Electrical connections shall be routinely checked and maintained to avoid short circuits.
Flammable materials (if any) shall be stored with clear indication on its characteristicsthrough Material Safety Data Sheet.
Guarding all parts of dangerous machinery
Maintaining hoists and lifts, lifting machines, chainages, ropes, and other lifting tackles ingood condition to avoid accident risks.
First aid facilities shall be set up in the construction site with people provided with essentialtraining.
Anticipated Impacts during Operation Phase
There will be increased influx of visitors into the project region for occupying in the resort. The local
economic growth can be triggered due to increased business opportunities with commercial
establishments and exploring the tourism potential of project region with back water tourism, cultural
exchanges through traditional art forms, selling of handicrafts, stage shows of traditional art forms,
back water based tourism, popularizing ethnic food varieties etc.
4.3.7. Solid Waste Management
As presented in Table 4.1 below.
Table 4.1. Proposed Solid Waste Handling Plan for Construction and Operation PhasesItem Mode of HandlingA. At Project SiteConstruction Debris such as cement,brick, concrete, cut pieces etc.
Shall be used for leveling of walkways andlandscape areas.
77
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Biodegradable waste such as food waste Shall be collected and processed in the biogas plant.Paper, plastic, cartons etc. Shall be recycled.B. GarbageBiodegradable waste Shall be collected and processed in the biogas plant.Paper, plastic, clothes, bottles etc. Shall be recycled.
Site clearance generates waste including pieces of trees, rags such as paper/glass etc, whichwere present in site
There is no surplus earth on site
Surplus concrete has to be chiselled and disposed off properly during construction of column,RCC Roofing. These will be used in laying foundation of walk way.
Wood dust/pieces/glass pieces / Aluminium fabrication pieces would be generated during thejoinery works.
Waste materials will be generated as part of plastering works and ceiling works.
If false ceiling is done, waste pieces of thermo coal, gypsum, PVC etc. will be generated aswaste materials
The manure generated from the STP has to be utilized for soil conditioning /disposed offsuitably during the operation of STP-
Waste will be generated during quarrying which could not be used for the constructionpurpose. It shall be insisted that material should be procured only form environmentalresponsible sides and organizations
4.4. Identification of Impacts of Offsite Activities
Being a building project with limited construction activities, the project doesn’t warrant establishment
of an independent quarry of crusher. The offsite environmental management for the quarry and
crusher shall be regulated by the concerned authorities through necessary statutory clearances.
However, the following aspects shall be complied in quarries, crushers and earth sourcing areas for
better environmental management in offsite activities.
Anticipated impacts during Construction Phase
There is no borrow soil requirement, hence offsite impact from borrow soil mining will notoccur.
During the storage of explosives for quarrying, if explosives get mixed with the surface runoff or mixed with water courses, the receiving water bodies will get contaminated
During the operation of crusher, growth of plants will be restricted due to dust accumulationalong the leaves (offsite)
Dust emission from the borrow areas, quarry and crusher and material spillage enroute canlead to pollution of land parcels, dust disturbance to the public and increasing the accidentrisk in roads.
78
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Labours employed in the Quarry and Crusher units are exposed to high risk with explosivesand
Haul roads shall be selected in such a way that the busiest corridors are avoided and the haulroads should be maintained to avoid travel discomfort to the public.
Borrow areas and quarries pose accident risk for human and animals.
Mitigation Measures
No borrow soil is required except for making pottery mixture for nursery. Procurement ofpotting mixture would be sub contracted.
Material transit should be in properly sealed vehicles and covered to avoid spillage ofconstruction materials along the way affecting the land parcels enroute.
All machineries and construction vehicles used shall have valid Pollution Under Control(PUC) Certificate.
Table 4.2. Environmental Factors Affected and Outcome of the Proposed Project SiteSlno:
Environmental factors Outcome
1 Sensitive areas, natural habitats,other state declared sensitiveareas
Around the 15 km radius of the project boundary, there isno such sensitive area like Wildlife Sanctuary, Nationalpark, Biosphere reserve.
2 Change in land use and drainagepattern
The project involves the construction of buildings withoutmuch change in the land use. The proposed buildings donot alter the drainage pattern of the area.
3 Inadequate sanitation, safety andhealth issues
Proper sanitation facilities are provided during constructionand operation phases. There will be no such inadequatesanitation issue. Besides, the project proposes STP for thetreatment of liquid waste generated during the operationphase.
4 Impact on river water quality The project does not involve any such continuous processwhich would have chance to deteriorate river water quality.
5 Impact on Environmentalaesthetics
There will be no impact on the environmental aesthetic dueto the proposed activities and buildings. The proposedproject is an Ayurvedic Resort which does not disturb thenatural beauty of the site. Beside, the project proposeslandscape with indigenous flora which will enhance theaesthetic beauty of the site. The visual quality of the sitewill be enhanced through systematic planting andlandscaping
6 Impact on natural habitat As the project comes under the purview of CRZ, thebuildings and activities are proposed at a setback distancefrom the river. Hence there will be no impact on naturalhabitat.
7 Loss of livelihood As such the project does not affect any livelihood. In fact itwill open the occupational chances of the local people,which will enhance the chance for more livelihoods nearthe project site.
The project is envisaged to have a range of positive environmental impact and social impacts.
79
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
ALTERNATIVE TECHNOLOGIES
During the construction period, the best management practices will be adopted which emphasis
reduction of water and energy conservation. Besides, the construction materials available locally will
be purchased from the local market.
Water demand during the construction will be reduced by use of pre-mixed concrete, curing agents
and other best practices will be followed. Also, fixture of showers, toilet flushing and drinking should
be of low either by use of aerators of pressure reducing devices or sensor based control.
Energy conservation is the other method adopted during the construction. Use of glass may be
reduced by up to 40% to reduce the electricity consumption and load on air conditioning. If necessary,
high quality double glass with special reflecting coating in windows will be used. Opaque wall will be
meeting the perspective requirement as per Energy Conservation Building Code which is proposed to
be mandatory for all air conditioned spaces while it is aspirational for non-air conditioned spaces by
use of appropriate thermal insulation material to fulfill requirement.
Besides, the project has provision for Rain Water Harvest which reduces the usage of ground water
and surface water during the operation phase. The project aims to achieve a GRIHA Rating of three
stars for the project.
5
80
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
ENVIRONMENTAL MONITORING PLAN
With proper implementation of the various mitigation measures as proposed in EMP, the
environmental setting of the project area could be developed in a sustainable manner. It is required
that the critical environmental attributes which are indicative of environmental performance of the
project should be periodically monitored and analyzed during the construction and operation stages of
the project. Environmental Monitoring Plan (EMP) for each of the environmental components
specifies the technical aspects of monitoring like locations of monitoring; frequency of monitoring
and duration, sampling method, parameters to be monitored, and standards to be monitored in
analyzing. The monitoring plan also specifies the applicable standards, and implementation and
supervising responsibilities. The environmental monitoring plan is presented in Table 6.1.
Table 6.1. Environmental Monitoring PlanAir Quality Monitoring
Project stage Construction StageParameter PM10, PM 2.5, SO2, NOx, COSampling Method High volume air sampler to be located 50 m from the source of pollution in
the downwind direction. Method specified by CPCB for analysis shall befollowed.
Standards Revised National Ambient Air Quality (NAAQ) Standards set by CPCBFrequency Once in every season for three seasons (except monsoon) per year for every
year of construction.Once in a year for the initial 3 years of operation phase.
Duration Continuous 24 hours / or for 1 full working dayLocations One location within the project location with two locations outside the
periphery along the predominant wind direction near sensitive areas duringconstruction phase.
One location within the project site with two locations outside the peripheryalong the predominant wind direction near sensitive areas during operationphase.
Measures Wherever air pollution parameters increase above specified standards, theroot cause analysis has to be carried out appropriate additional measures shallbe carried out to avoid exceeding the standard.
Implementation Project Implementation Team through NABL Approved LaboratoriesSupervision Environmental Management Cell for the ProjectWater quality MonitoringProject stage Construction and Operation stage
6
81
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Parameter pH, Colour (Hazen), Temperature(°C), Electrical Conductivity (mmhos/cm),Turbidity (NTU), Total Solids (mg/l), Suspended Solids (mg/l), TotalDissolved Solids (mg/l), Dissolved oxygen (mg/l), BOD (mg/l), COD (mg/l),Alkalinity as CaCO3 (mg/l), Total Hardness as CaCO3 (mg/l), Chlorides(mg/l), Fluorides (mg/l), Sodium (mg/l), Potassium (mg/l), Calcium (mg/l),Magnesium (mg/l), Sulphates (mg/l), Nitrates (mg/l), Nitrites (mg/l), TotalNitrogen (mg/l), Phosphates (mg/l), Phenols (mg/l), Iron as Fe (mg/l),Mercury (mg/l), Zinc (mg/l), Copper (mg/l), Nickel (mg/l), Cadmium (mg/l),Chromium (mg/l), Manganese (mg/l), Lead (mg/l), Oil and Grease (mg/l),Total Coliform (MPN/100ml), Faecal Coliform (MPN/100ml).
Sampling Method Grab sample collected and analysis as per Standard Methods for Examinationof water and Waste water
Standards Indian standards for Inland Surface Water (IS; 2296, 1982) and for Drinkingwater (IS; 10500,1991)
Frequency Once in a season (except monsoon season) during the entire Constructionperiod for surface and ground water samples.Once in a season (except monsoon seasons) during the entire Operationperiod for ground water sample and outlet of STP and WTP
Duration One-time grab samplingLocation Three samples, one up stream and one downstream and one near the project
location drainage pattern to Tirur Puzha and one sample from the existingwell within the premises during construction phase.
One sample from the existing well within the premises, outlet of STP andWTP for the initial 3 years of operation phase.
Measures At locations of increased water pollution towards downstream, all inflowchannels shall be checked and adequate pre treatment measures shall beinstalled to control pollution input in to the water body.
Implementation Project Implementation Team through NABL Approved LaboratoriesSupervision Environmental Management Cell for the ProjectNoise Level MonitoringProject stage Construction and Operation stagesParameter Noise level on dB (A) scaleSampling Method Measure equivalent noise levels using an integrated noise level meter kept at
a distance of 15m from edge of the pavementStandards Noise Pollution (Regulation and Control) Rules, 2000Frequency Once in every seasons (except monsoon) for each year of construction.Duration Reading to be taken at 15 seconds interval for 15 minutes every hour for 24
hours and then average will be taken.Location One location within the project site and second location near the nearest
human settlement during construction phase.Measures In case of noise levels causing disturbance to the sensitive receptors,
management measures as suggested in the EMP shall be carried out.Implementation Project Implementation Team through NABL Approved LaboratoriesSupervision Environmental Management Cell for the ProjectSoil Quality MonitoringProject stage ConstructionParameter Monitoring of Colour, texture, water holding capacity, pH, Potassium,
Sodium, Cation exchange capacitySampling Method Sample of soil collected to be acidified and analyzed using absorption
spectrophotometerStandards Threshold for each contaminant set by IRIS database of USEPA until national
standards are promulgatedFrequency During the pre monsoon and post monsoon seasons in each year for the entire
82
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
construction periodDuration One-time grab samplingLocation One location within the project site along the modified contour pattern of
project site towards slope.Measures At location of increased pollution levels, source shall be identified and
measures shall be taken to control the pollution.Implementation Project Implementation Team through NABL Approved LaboratoriesSupervision Environmental Management Cell for the Project
6.1. Block Cost Estimate for Implementing EMP
The proposed environmental monitoring programme and cost involved for the same is as presented in
Table 6.2.below.
Table 6.2. Cost Estimate of Implementing Environmental Monitoring for Construction andInitial Three Years of Operation
Sl.No EnvironmentalAttributes
Parameters to beAnalysed
Frequency ofMonitoring
No ofLocations
Cost (Rs)
Construction Phase – 2 Years1 Ambient Air
QualityMonitoring
PM10 (µg/m3), PM 2.5(µg/m3),
Once in everyseason for threeseasons (exceptmonsoon) per yearfor every year ofconstruction.
3 1,94,400.00
SO2 (µg/m3), NOX(µg/m3), CO (mg/m3)
Once in everyseason for threeseasons (exceptmonsoon) per yearfor every year ofconstruction.
3 1,45,800.00
2 Ground waterQualityMonitoring
pH, temperature,turbidity, magnesiumhardness, totalalkalinity, chloride,sulphate, nitrate,fluoride, sodium,potassium, salinity, totalnitrogen , totalphosphorous, DO, BOD,COD, Heavy metals[Silver, Selenium,Arsenic, Mercury, Zinc,Copper, Nickel,Cadmium, Chromium,Manganese, Lead],Total coliforms, faecalcoliforms,phytoplankton
Once in a season(except monsoonseason) during theentire Constructionperiod for surfaceand ground watersamples.
1 48,600.00
Surface waterqualityMonitoring
3 1,45,800.00
3 Ambient NoiseLevelMonitoring
Noise Level (dB) inL10, L50, L90, Leq,Leqday, Leqnight,
Once in everyseasons (exceptmonsoon) for each
2 1,14,000.00
83
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Sl.No EnvironmentalAttributes
Parameters to beAnalysed
Frequency ofMonitoring
No ofLocations
Cost (Rs)
Leqdn year of construction4 Soil quality
monitoringTexture - Sand (%), Silt(%), Clay (%), SoilType, Colour, MoistureContent (%), ElectricalConductivity (1:5 SoilExtract) (mmhos/cm),pH, Organic Carbon(mg/100gm), Nitrogenas N (mg/100gm),Phosphorus as P(mg/100gm), Chlorides(mg/100gm), Sodium(mg/100gm), SodiumAbsorption Ratio(SAR), Bulk Density(g/cm3), Water HoldingCapacity (%) ,Infiltration (cm/hr),Cation ExchangeCapacity (meq/100gm),Cadmium as Cd(mg/kg), Chromium asCr (mg/kg), Copper asCu (mg/kg), Iron as Fe(mg/kg), Manganese asMn (mg/kg), Lead as Pb(mg/kg), Zinc as Zn(mg/kg), Nickel as Ni(mg/kg).
During the premonsoon and postmonsoon seasons ineach year for theentire constructionperiod
1 36,000.00
5 Mobilization Charges - Lumpsum 21,000.00Total Cost for Construction Period of 2 Years 7,05,600.001 Ambient Air
QualityMonitoring
PM10 (µg/m3), PM 2.5(µg/m3),
Once in a year forthe initial 3 years ofoperation phase.
3 97,200.00
SO2 (µg/m3), NOX(µg/m3), CO (mg/m3)
Once in a year forthe initial 3 years ofoperation phase.
3 72,900.00
2. Ground WaterQualityMonitoring
pH, temperature,turbidity, magnesiumhardness, totalalkalinity, chloride,sulphate, nitrate,fluoride, sodium,potassium, salinity, totalnitrogen , totalphosphorous, DO, BOD,COD, Heavy metals[Silver, Selenium,Arsenic, Mercury, Zinc,Copper, Nickel,
Once in a season(except monsoonseasons) during theinitial 3 years ofoperation phase.
1 72,900.00
84
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Sl.No EnvironmentalAttributes
Parameters to beAnalysed
Frequency ofMonitoring
No ofLocations
Cost (Rs)
Cadmium, Chromium,Manganese, Lead],Total coliforms, faecalcoliforms,phytoplankton
Outlet of STPand WTP
Once in a season 2 1,45,800.00
3. Mobilization Charges - Lumpsum 21,000.00Total Cost for Initial 3 Years of Operation Phase 409800.00
The block estimate for the implementation of EMP for the construction period of 2 years and
operation period of 3 years is as presented in the Table 6.3below.
Table 6.3. Block Cost Estimate for Implementing EMPItem Assumptions Cost in Rs.Construction Phase - 2 YearsEnvironmental Monitoring 7,05,600.00Dust Suppression 2,92,000.00Total cost 9,97,600.00Operation Phase – Initial 3 yearsEnvironmental Monitoring 409800.00
85
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
ADDITIONAL STUDIES7.1. Introduction
A disaster is a sudden, calamitous phenomenon that can cause damage to life and property and destroy
the economic, social and cultural life of people. Though often caused by nature, disasters can have
human origins. Disaster management is the discipline of dealing with and avoiding both natural and
manmade disasters. It involves preparedness, response and recovery in order to lessen the impact of
disasters.
As the proposed resort will serve as the location for holidaying mostly, foreigners from Middle East
countries a risk assessment for the operation stage and preparation of a disaster management plan is
essential. This chapter covers the risk assessment, disaster management plan along with natural
resource conservation plan. As the project does not involve any resettlement and rehabilitation of
people, the resettlement and rehabilitation plan is excluded from the scope of the studies.
7.2. Disaster Management Plan in India
National Disaster Management Act (NDMA), came in to force on 23rd December 2005 envisages
disaster preparedness facilities at national level, state level, district level and local level to combat on
emergencies with designated members responsible with institutions having the flexibility to design
their own plan based on the availability of manpower and operational pattern.
State Disaster Management Authority shall function as the apex decision-making body and
facilitate, co-ordinate, review and monitor all disaster related activities in the state including capacity
building. The Authority shall lay down the State Disaster Management policy and guidelines to be
followed by the government departments and approve the State Disaster Management Plan and
Departmental plans. The Authority shall be provided with statutory powers to facilitate, coordinate
and monitor the activities related to disaster management utilizing the resources and expertise of
relevant Government departments, district administration, local authorities, non-governmental
organizations, the public sector, international development agencies, donors and the community. It
shall also exercise the powers and functions as laid down in the national Disaster Management Act,
2005 and in the notification of Kerala State Disaster Management Authority vide G.O (p) No.
154/2007/DMD.
7
86
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
The State Government, by notification, has established and constituted District Disaster Management
Authorities in all fourteen districts as per the provisions of National Disaster Management Act, 2005.
The District Authority shall act as the district planning; coordinating and implementing body for
disaster management and take all measures for the purposes of disaster management in the district in
accordance with the guidelines laid down by the National Authority and the State Authority.
The State Government will ensure an appropriate chain of command whereby the Kerala State
Disaster Management Authority at the State level and District Disaster Management Authorities
headed by District Collectors at the district level are empowered to coordinate disaster management
activities and mobilize resources of all relevant Departments at their level. Similar institutional
arrangements fixing responsibilities, administrative mechanism and procedures shall also be made
down line at Taluk and Village levels.
The Department of Revenue and Disaster Management will be the nodal department for
management of all types of natural disasters that include water and climate related disasters and
geological disasters. The scope of Department of Revenue has been enhanced to include prevention,
mitigation and preparedness aspects of Disaster
Management apart from its traditional responsibility of relief and rehabilitation and renamed as
Department of Revenue and Disaster Management. The Principal Secretary to government will act as
the State Relief Commissioner. The organizational structure of the Department dealing with disaster
management will be so tailored as to reflect the change in focus from post-disaster relief and
rehabilitation to prevention, mitigation and preparedness in addition to relief and rehabilitation.
The Department of Home shall be the nodal department for management of manmade and human
induced disasters including air and rail accidents. The Department of Public Health shall be the nodal
department for chemical, biological (health related), radiological and nuclear disasters. The Factories
and Broilers Department shall be the nodal department for industrial accidents and the department
shall work in tandem with Industries Department in the event of a disaster. While Agricultural
Department deals with pest attacks; cattle epidemics shall be handled by Animal Husbandry
Department. Irrigation and Public Works Departments shall be the lead agencies for disasters related
to dam bursts and major building collapse respectively. Forest Department shall be the nodal
department for disasters like forest fire.
A well-coordinated and unified response of various state departments and agencies appropriate to the
proportion and demand of the crisis situation will be ensured by the state government to improve the
process of recovery through rapid dissemination of information, quick response and effective decision
making. An institutional mechanism distinguished as ‘Crisis Management Group’ under the
87
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
chairmanship of Chief Secretary with representatives of Department of Home including Police,
Department of Revenue and Disaster Management and Department of Health will function at the state
level as a nerve center to support, coordinate and monitor crisis management activities related to
natural disasters, manmade / accident related disasters and chemical / biological / radiological /
nuclear disasters. Accordingly, ‘Crisis Management Plans’ that clearly define response roles and
responsibilities of government agencies, facilitate communication across agencies, specify protocols
and procedures, and detail actions to be taken by government departments shall be prepared and made
operational by the state government. As and when a grave crisis situation develops, the District
Collector as Chairman of ‘District Crisis Management Committee’ will send the ‘first information’ to
the state level ‘Crisis Management Group’.
At the institutional level, the disaster management plan proposed for Almas Resort is presented
below.
7.3. Disaster Management for Almas
The disaster management policy statement for Almas Resort is as presented below.
Almas resort is committed for ensuring a comfortable, relaxing and safe holidaying in the resort for
which all necessary safety aspects have been integrated in the design and operation of resort. This
disaster management plan identifies the possible risks, the safety aspects integrated and which will be
periodically reviewed and updated for ensuring the safety and satisfaction of the customer.
7.3.1. Risk Assessment
Considering the location of the resort, activities to come up in the operation phase, the possible
disasters could be mainly of two types – natural and manmade. The most probable disasters are
briefed below.
Natural Disasters
Flood
Earthquake
Cyclone
Storm
Landslides
Volcanic eruptions
Lightning
88
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Tsunami
Manmade Disasters
Fire
o Fire due to short circuit
o Fire due to gas or oil leakage
o Fire due to improper handling/storage
o Fire due to human activity
Explosion
Terrorist attack
Wars, Riots
Accidents
From the analysis of the various natural disasters, flooding of the project area may be expected due
towards the river side due to heavy rainfall since in proximity to the river existing along the boundary
of the proposed project site. As the structures are designed with the maximum flood probability for
the 100 years, any impact on the proposed structures are considerably reduced.
As per the National Earthquake Zonation Map, Kerala state falls under Zone III. Though the area does
not fall where there is most probability of occurrence of earth quake, it is required that all the
structures constructed should be able to withstand the probability if any. Incorporating the input of the
relevant Indian standard IS: 1893:2002 - criteria for earthquake resistant design of structures shall be
incorporated to reduce the impact on structures and related damages due to earth quake.
Considering the historical profile as well as the location specificity, the area is not likely to be
affected by storm and cyclone, volcanic eruption, and landslides.
Fire related risks due to short circuit, gas leakage, improper handling/storage; human activities etc. are
high for resorts. A proper fire fighting system shall be in place with regular mock drills done for
ensuring that the system can function as per the requirement.
7.3.2. Objective of Disaster Management Plan
The objectives of the Disaster Management Plan (DMP) id to maximize human safety and survival,
preserve property, minimize danger and restore normal activities. In case of disaster in the various
categories the concerned departments/officials should be intimated immediately so as to put them into
action. Since they are already authorized to involve incase of such a disaster as per the Kerala disaster
89
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
management policy, they can trigger into action without waiting for any written order. This will save
much time in decision making.
7.3.3. Various Stakeholders in Disaster Management
The various stakeholders who are part of any disaster management are presented below and the
general profile of the actions and the responsible officers from the statutory bodies are presented in
Table 7.1.
Kerala State Disaster Management Authority
State and Central Government departments
District Disaster Management Authorities
Local authorities including Municipal Corporations/Municipalities, District/block/GramaPanchayaths, taluk/village officers etc,.
Voluntary and civil society organizations
Red Cross, multinational aid agencies and UN agencies
Community-village disaster management committees, task forces
Public sector undertakings
Private sector undertakings
Army, navy, air force, coast guard, airport authority, national disaster response force etc.
Table 7.1. Actions during Disaster Management and Responsible Statutory AuthorityAction points Responsible Statutory AuthorityEvacuation of people Army, Police, Civil Defence, Fire Brigade, and
Linkage TeamRecovery of dead bodies and their disposal Police, Civil Defence and Linkage TeamMedical care for the injured District Medical and Health OfficerSupply of food and water and restoration ofwater supply lines
Executive Engineer, Water Authority, DeputyDirector of Supply and Relief Team
Restoring lines of communication andinformation
Communication, District Information Officer.
Quick assessment of damage and demarcationof damaged areas according to grade of damage
Emergency Operating Centre, PWD and BlockDevelopment Officer concerned
Cordoning off severely damaged structuresliable to collapse during aftershocks
Police, Fire Brigade, Home guards
7.3.4. Institutional Responsibility
An Emergency Response Centre (ERC) should be maintained and put in action within the Resort
which would co-ordinate with various state departments to ensure planning, response and recovery.
As the owner, M/s. Almas shall be responsible for
90
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Planning, Monitoring and Evaluation of disaster management practices.
Review, adoption of appropriate laws, rules, codes and other measures to increase disastermanagement at all levels
Incorporating disaster management aspects in normal developmental activities
Provide financial assistance
Building of Inventories
Gathering support from Government / other departments to train department officials from theState Headquarters and districts, members from the community and other stakeholdersthrough a participatory approach
Documentation of incident records, lessons learnt etc.
To maintain Support in Relief and rescue operation.
7.3.5. Institutional Arrangements
Institutional arrangements for an emergency management include pre-disaster preparedness, during
disaster and post disaster management.
7.3.5.1. Pre-Disaster Preparedness
Pre-disaster preparedness include disaster preventive measures related with setting up of the resort
with design and construction of all buildings as per the approved national and international code of
practice and ensuring that the routine maintenance requirements are complied in all respects for the
same. Incorporation of adequate access ways/walk ways for the movement of equipment and
personnel’s, preparation of adequate number of escape route plan and providing escape routes to
ensure evacuation within the shortest span of time, pre planning of assembly points at the event of any
emergency, training of the inmates for dos as don’ts during an emergency and safe evacuation
practices, ensuring routine mock drill operations etc. would be an important step towards controlling
the damage due to any disaster. The project is incorporated with escape routes, emergency alarm, a
dedicated fire fighting facilities and common assembly point has been fixed at the parking lot of the
resort and the details are presented in Figure 7.1, 7.2 7.3.etc.
Provision of an exit at the back side of the resort shall be provided as an additional escape route,
which could be operational only during an emergency and employees within the resort, shall be
familiarized with the disaster management procedures during their induction period of employment
itself. Considering the floating population visiting the resort, it shall be made mandatory by M/s.
Almas that the information on the disaster management aspects are duly shared with the inmates
preferably in their individual rooms in the language familiar to them with clear display of escape
routes and guidance for safe exit.A centralized facility with regular record on the number of inmates
including the employees at any time within the resort with visitors’ details with emergency contact
91
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
details shall be maintained for assessing the probability of actual person affected during any
emergency in any unit and also to ease contacting with the relatives of the diseased.
For better preparedness, the administrative office as well as the parent organization running the
resort shall have an updated ready to reference record on the number of people within the resort with
essential details of site layout, building layout with details of equipments, storage details for raw
materials especially the inflammable chemicals, details on the man, machinery, details of fixed and
movable assets, including the flexibility for its mobility, storage of solid/liquid waste etc .in place
which will ease the priority of protection in the event of any emergency. This may help in saving the
very important machineries as well as avoiding contamination of chemicals with the soil/nearest water
body. A list of emergency contact numbers shall be kept ready to refer while dealing with any
emergency.
An in house arrangement for managing any disaster shall be set by M/s. Almas as part of the project.
The essential institutional arrangements need to be made is to set up Emergency Control Room and
ensuring that the Emergency Management Team is available throughout the shift.
7.3.5.2. Emergency Management System during Disaster
Emergency Control Room
Emergency control room activates in case of an emergency to direct and co ordinate the operation to
handle emergency. The control room shall have well trained personal and facilities for
communication, co ordination etc. The following facility shall be made mandatory for the ECR.
Site Plan showing all emergency exits, fire escapes, assembly point, sources of safetyequipments
External & Internal telephone connections.
List of Key persons and their addresses, and essential telephone numbers displayed on board.
Operating point for public addressing systems
Loud speaker
Torches
Alarm Systems
In case of an emergency, the first step to be initiated by the ECR is to disseminate information by
blowing siren or signal for the company people as well as for the outside people of the campus.
Emergency Management Team (EMT)
92
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
The Emergency Management Team shall be constituted as per the structure presented below to
combat on emergencies. A 3 tier team shall be maintained for the resort with trained manpower as
presented in Figure 7.1. On an incident reporting Site Incident Manager has to primarily investigate
the situation and appraise to Works Main Controller. Works Main Controller will be the overall
responsible officer for assessing and declaring an emergency, analyzing the progress of combat
operation and also to ensure availing the services of various stakeholders involved. Site Incident
Manager would be directly in touch with the operation team and would facilitate their operation,
closely monitor the progress and report the same to Works Main Controller. The operation teams
consisting of Combat Team, Rescue Team and Auxiliary Team would be dealt with actual
operation in site and SIC and WMC would be supporting the operation team with appropriate input,
decision and ensuring that the services of various stakeholders involved are availed for combating
with the situation.
Figure 7.1. Structure of Emergency Management Team
During an emergency, the whole team would be put in to action and the general responsibility
allocation within the emergency management team is presented in Figure 7.2.below. The Emergency
Management Team proposed for the resort is presented in Table 7.1
Table 7.1. Proposed Emergency Management Team for Almas ResortSl.No Proposed Position Details of Personnel1. Works Main Controller Dr Ahmed Kabeer , Chairman, Almas Ayurvedic Resorts
Limited2. Site Incident Controller Resort Administrator3. Combat team leader Resort Manager4. Rescue Team leader Resort Security Officer5. Auxiliary Team leader Public Relations Officer
Works Main Controller
Site Incident Controller
Combat Team Rescue Team Auxiliary Team
93
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Note: The team leaders of combat team, rescue team and auxiliary team would be supported with
adequate number of members for the operation during an emergency.
94
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Figure 7.2. Responsibility Allocation within EMT during Emergency
Incident Reporting(Any source)
Assess Situation Appraise WMC Analyse Situation Declare Emergency
Blow Siren
ExternalCommunication
Facilitate Conveyanceand Coordination of
stakeholderinvolvement
Communication withRelatives
Arrange for sendingcausalities andoccupants to
hospitals/residences
Evacuate Non EssentialPerson to Assembly Point
Head Count
Engage Medical Team for
Shifting of causalities andoccupants from site
Utilise trained persons on duty
Controlling emergency forarresting leakage/fire and provide
first aid for combating
Attend emergencyrepair/installation of pumps and
other supportive equipments
Take measures to minimisedamages through segregation,
covering, salvaging, diverting fireetc.
Support for Identifying saferoute for fire fighting,
ambulance, medical teametc
Updates to WMC
Technical Support for regulatoryauthorities for their operation
95
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
The emergency contact list to be maintained by the resort is presented in Table 7.2.
Table 7.2. Emergency Contact List to be maintained by ResortSr. No. Contact PointInternal Contact Numbers1. Dr. Ahmed Kabeer, Chairman2. Almas Hospital, Changuvetty, Kottakkal3. Resort Administrator4. Resort Manager5. EmployeesExternal Contact Numbers1. District Administration
District CollectorThahasildarVillage OfficerTirur MunicipalityCorporationDistrict PanchayathBlock PanchayathGrama Panchayath
2. Fire ServicesChief Fire Officer of nearby stations
3. PolicePolice Commissioner
4. Medical FacilitiesAll government hospitals/private and clinics community health centers, primary healthcentres etc.Ambulance ServicesBlood bank facilities
5. State Electricity Board Office6. Fisheries department
Fisherman association/societies7. Transport Services
Road Transport Officer, TirurKSRTC Station, TirurPrivate Bus Stand TirurPonnani Port
8. District Public Relations Officer9. District Agriculture Officer10. Educational institutes for acting as shelter
All schools and colleges, play schools etc11. Press media for information dissemination
DoordarshanAll India RadioMathrubhumi DailyMalayala Manorama DailyTimes of IndiaThe HinduAsianet
96
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Sr. No. Contact PointReporterIndiavisionAmruthaJeevanKairaliSurya
7.3.5.3. Post Disaster Management.
Damage Assessment and Estimation of Funds
A detailed assessment must be conducted before commencing rehabilitation and reconstruction
activities. Project proponent along with the officials from statutory authorities should undertake
detailed assessments at their respective level for damages sustained. Based on detailed damage
assessment, it is required to finalize estimation of funds required and fund generation mechanisms.
Assistance from national and international organizations shall also be sought, if required.
7.3.6. Plan update and Review
This disaster management plan shall be reviewed once in a year and shall be updated as per the
operational requirements.
7.3.7. Training & Drills
The key personnel to act on emergencies shall be provided with basis training for handling any
emergency. Mock drill exercises shall be done once in a month (10.00 AM – 11.30 AM on
4thSaturday) to ensure that the employees and inmates are aware of the measures to be undertaken
during an emergency
97
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
PROJECT BENEFITS
Kerala regarded as “gods own country” with its natural beauty being the trademark for the tourism
attraction has been included in the list of the ten must-see destinations by the National Geographic
Traveler. The proposed resort is planned in a location where the natural beauty is blessed with
backwater and beach in close proximity. Being a relatively undisturbed landscape with only without
having residential areas in close proximity to the proposed location, the resort will provide a perfect
calm holidaying location for people.
While providing the ayurvedic rejuvenation support in the resort, the proposed project of Almas
Ayurvedic Resort can boost the possibilities of medical tourism in the state. Ayurveda which is the
part of Indian culture will get a good exposure from this proposed project. Ayurvedic resorts have
become popular destinations for relaxation and rejuvenation in India. The Almas Ayurveda presently
has their hospital in Kottakkal which clearly describes their experience in the field of Ayurvedic
treatment. The resort thus offers its visitors quality service for rejuvenation while holidaying.
As the project is proposed to be developed by maintaining 72% of total land without permanent
construction, the resort will attract its visitors with a feeling of “living with nature”. The backwater
tourism potential of the project location gives an excellent opportunity for the visitors to enjoy the
serene beauty of the village and landscape of the state.
The proposed project of Almas Ayurvedic Resort has benefits in various ways.
Tourism Development: Almas is expecting more visitors from Middle East Countries as guests in
their resort. The project would attract visitors due to the calm environment surrounding being in the
village setting with proximity to sea shore as well as back water, proximity to ferry operation along at
Ponnani and Purathur Padinjarekkara-Azhimukham Beach at about 3.5 km from the proposed site
would attract its visitors.
Promotion to Medical Tourism: Kerala government is already on a move to promote the medical
tourism potential of the state through being the facility integrates the rejuvenation for its inmates in an
Ayurvedic support; the project will promote the medical tourism sector for the state.
Regional Development: The project activities would support employment generation during the
construction and operation phase of the project. Since the visitors would be of predominantly from
8
98
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
the Middle East Countries, the local traditional art forms, handicrafts etc could have a better business
market along with native food varieties, which will lead to socio economic and development of a
region as a whole. The proposed project will increase the number of tourists visiting the region and
thereby support the regional economic development through new business opportunities
.
99
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
ENVIRONMENTAL MANAGEMENT PLAN
Considering the extend of construction proposed and the activities during the operation phase of the
project, it was understood that by a careful planning and execution of the construction activities and
following the widely adopted good practices, the negative impacts of the construction projects could be
far outweighed with the positive impacts. The likely adverse environmental impacts during the
construction phase of the project will degradation of soil, soil erosion, pollution due to improper disposal
of excavated materials and construction waste; spillage of oil and other substances from the construction
equipment and vehicles during the construction; pollution of water resources and soil by construction run-
offs; temporary air pollution related to increased traffic during the construction, release of dust from
digging-loading works and heavy machinery operation; noise and vibration disturbances; safety hazards
during implementation of construction works. The likely adverse environmental impacts during the
operation phase include waste disposal issues associated with improper categorization and
utilization/disposal of waste generated from the restaurant and utility rooms of the proposed resort and
sewage treatment aspects.
The long term positive socio economic impact of the operation of a new Ayurvedic Resort with five star
facilities in Purathur is expected to be significant, since the project provide employment opportunities to
the local and such a facility will enhance the local development of the area in terms of revenue and
income. This type of resort will increase the chance of foreign income
The project is not expected to have any significant or irreversible negative environmental impacts neither
at the construction, nor at operation phases. Impacts of the construction phase will be typical for all
medium scale construction activities, short-term and limited to the project sites. In this case care has to be
taken as the site shares its boundary with the Tirur-Ponnani River. The construction material, debris or
anything must not pollute the river and its flora and fauna and the natural beauty. Control of dust and
noise becomes crucial during construction phase.
The management measures to mitigate the impacts during the construction & operation phase have been
presented in the foregoing section. During both phases the management will involve segregated
9
100
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
collection, storage minimizing open/ ground level dumping. on/off-site reuse, recycle, treatment and final
disposal. Most of the construction waste can be reused and recycled.
Air & noise pollution are the adverse impacts mainly during construction Phase. Dust suppression
measures will be done aimed at prevention of air pollution through watering of access roads and
construction site. During construction, air pollution levels will be increased mostly by machine operations
for earthwork and construction. The main pollutants caused by these operations include exhaust gases
emitted by machines and dust caused by the earthwork. Regular sprinkling of water during construction
works will depress the dust, thus reducing impact on workers. Additional measures planned to maintain
air quality include locating concrete mixing plant and stockpiles in isolated area, as well as confining
working vehicles to designated routes only following the established schedule. Trucks loaded with loose
construction materials (such as gravel, sand, soil, etc.) shall be covered to minimize dust emissions during
transportation. Vehicles and machinery should be fitted with effective exhaust silencers and maintained in
good and efficient working order. Machinery in intermittent use should be shut down or throttled down to
a minimum when not in use.
Operational phase generates solid waste. The recyclable and reusable portion of the waste could be
separated and processed and the biodegradable waste shall be processed in the biogas plant and the fuel
shall be utilized for the operation of restaurant.
The predicted environmental impact during both phases, suggested mitigation measures are summarized
in Table 9.1.
101
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Table 9.1. Environmental Management PlanSlNo:
Activity EnvironmentalAttributes
Potential Impact Management Measures ImplementingAgency
MonitoringAgency
I Pre-construction Phase1. Land
AcquisitionLand As there is no land acquisition
proposed for this project, there areno impacts envisaged.
No management measuresneeded.Water
AirNoiseBiologicalSocio-EconomicSolid wasteManagementGeology
2. SoilInvestigation-Bore Hole
LandWater Liquid/mud contamination Collect liquid mud in pits allow
setting and preventing directcontamination of water body
ProjectConsultants/Contractors
AlmasManagement
Air Temporary/low – air pollution dueto dust /airborne litter
Screening the area , sprinklingwater to minimize dustgeneration
Noise noise due to drilling Use well maintained drillingequipments ,
BiologicalSocio-EconomicSolid wasteManagementGeology Partial compaction of the top
sandy soil layerVery insignificant that nomanagement measure is needed
II. Construction PhaseII A. Onsite Activities3. Site Clearance Land Top soil gets compacted with the
movement of vehicles, man andmachineries.
Top soil needs to be stripped outand preserved in heaps undercover which is to be restoredback to the areas proposed for
ProjectConsultants/Contractors
AlmasManagement
102
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
SlNo:
Activity EnvironmentalAttributes
Potential Impact Management Measures ImplementingAgency
MonitoringAgency
green belt and landscaping.Soil pollution can occur due tospillage of fuel/lubricants used inconstruction machineries andvehicles.
Proper maintenance of vehiclesand construction machineriesshould be done.The construction machineriesand vehicles should be inspectedperiodically for the detection ofleaks and spillages.The maintenance and inspectionof vehicles should be confinedto designated paved areas only.
The activity increases the soilerosion probability of said area.
The site clearance should not beinitiated during or prior to heavymonsoon season.
Water If site clearance is done duringrainy season, surface run off willlead to contamination of waterbodies.
The site clearance should not beinitiated during or prior to heavymonsoon season.The construction should not beprolonged too much after siteclearance.
ProjectConsultants/Contractors
AlmasManagement
Fuels/lubricants used in site canpollute water courses if it find itsway to the water courses
The construction machineriesand vehicles should be inspectedperiodically for the detection ofleaks and spillages.The maintenance and inspectionof vehicles should be confinedto designated paved areas only.The oily surface run off shouldbe collected for treatment anddisposed off.
Cleaning of constructionmachineries if carried out near thewater courses, can lead to
Confined area which is situatedaway from the water bodiesshould be allotted for cleaning
103
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
SlNo:
Activity EnvironmentalAttributes
Potential Impact Management Measures ImplementingAgency
MonitoringAgency
pollution of water courses. for construction machineries.Air Excavation leads to dust
generation.The site is already demarcatedwith high compound wallswhich prevents the dust reachingthe nearby resident areas andother sites.
Operation of excavator, l, vehiclesleads to air emissions due to fossilfuel burning
Pollution- under –check (PUC)should be made mandatory forall vehicles used forconstruction activities.Regular maintenance andinspection of the machineriesshould be conducted.The excavators, vehicles, shouldbe operated only well within thedemarcated area of the projectsite.
Movement of transport vehiclesleads to dust generation
Water should be sprinkledperiodically to suppress the dustgeneration.Personnel masks should beprovided to workers.The tyres of the transportvehicles have to be washedbefore leaving the constructionsite.The material transport vehiclesshould be adequately covered.
Operation of DG set inconstruction site results in airemissions.
The DG should be operated onlyon standby mode.Periodic emission test should beconducted.The stack height of the DG set
104
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
SlNo:
Activity EnvironmentalAttributes
Potential Impact Management Measures ImplementingAgency
MonitoringAgency
has to be in conformance withthe CPCB guidelines. .
Noise Operation of tree cutter,excavator, loader, DG, crane andtransporting vehicles lead toincreased ambient noise level.
Diesel generator should havenoise control measures to meetthe noise standards set byCentral Pollution Control Board(75 dB(A) at 1 m from theenclosure surface for generatorswith integral acoustic enclosure.Acoustic enclosure forgenerators without integralacoustic enclosure shall bedesigned for minimum 25 dB(A)insertion loss or for meeting theambient noise standards,whichever is on the higher sideat 0.5 m from the enclosure).Workers shall not be exposed tosound of more than 85 – 90 dBfor more than eight hours a dayand shall be provided with earplugs.Noise quality monitoring shallbe conducted as perEnvironmental Monitoring Planto detect noise pollution.Noise level of vehicles used forconstruction activities shouldmeet the noise standards set byCentral Pollution Control Board(maximum 80 dB(A) )Construction contract shallclearly specify the use of
ProjectConsultants/Contractors
AlmasManagement
105
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
SlNo:
Activity EnvironmentalAttributes
Potential Impact Management Measures ImplementingAgency
MonitoringAgency
equipment emitting noise of notgreater than 90 dB (A) for theeight hour operation shift.
Biological Site clearance leads to loss ofterrestrial and aquatic flora andfauna. The impact could be severeif protected or endangered speciesare affected.
Compensatory plantation has tobe carried out with thrice thenumber of trees to be cut forproposed project. No protectedor endangered species arereported in the project area.
ProjectConsultants/Contractors
AlmasManagement
Socio-Economic Labour involved in the siteclearance is exposed to dust andincreased ambient noise level.
Water should be sprinkledperiodically to suppress the dustgeneration.Personal protective equipmentssuch as ear plugs, helmets,goggles, gloves, boots etc.should be made mandatory forthe construction workers.Other provisions to ensureworker’s safety shall befollowed as per rules in force.
Safety risk includes the attack ofvenomous species, or injuries dueto glass pieces, metals or anyother sharp materials.
Personal protective equipmentssuch as ear plugs, helmets,goggles, gloves, boots etc.should be made mandatory forthe construction workers.Trained personnel for first aid
should be available at site. Firstaid kit at site and on-callaccident support agreement withan approved hospital should bemade.
Immediate surroundings of the Noisy construction shall be
106
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
SlNo:
Activity EnvironmentalAttributes
Potential Impact Management Measures ImplementingAgency
MonitoringAgency
project site and the transport routefor the project purposeexperiences nuisance due to dustemissions and increased ambientnoise level. The magnitude ofimpact increases if theconstruction works are extendedto night hours including the use offlood light.
stopped between 10:00 pm and6:00 am.
Flood lights would be properlyshaded without affecting thesurrounding
Solid wasteManagement
Site clearance generates wasteincluding pieces of trees, ragssuch as paper/glass etc, whichwere present in site.
The construction waste shouldbe disposed off properly by theconstruction contractor.
ProjectConsultants/Contractors
AlmasManagement
Geology Landscape alteration, drainagealteration
Nominal slope may bemaintained to retain the naturaldrainage direction,Cleared top sandy layer may bestacked separately for landscaperenovation plan towardscompletion of the project
Risk/Hazard Site clearance generates wasteincluding pieces of trees, ragssuch as paper/glass etc, whichwere present in site.
The construction waste shouldbe disposed off properly by theconstruction contractor.
4. Land Loss of topsoil Top soil conservation measuresshould be adopted.
ProjectConsultants/Contractors
AlmasManagement
Water Surface runoff of the excavatedearth will lead to partial orcompletely filling of water bodiesand also to enhance the turbidityof water to unacceptable levels forthe intended uses and also to theloss of aquatic flora and fauna.
Excavated earth should bestored properly and re used forleveling and filling., The surplusearth should be stored in such away that the surface run offfrom the construction site willnot lead to nearby water courses.
107
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
SlNo:
Activity EnvironmentalAttributes
Potential Impact Management Measures ImplementingAgency
MonitoringAgency
Air Excavation work especially alongthe loose soil areas releases largeamount of dust.
Water should be sprinkleperiodically to suppress the dustgeneration.The construction area should betemporarily fenced to avoiddispersion of dust from the samearea.
ProjectConsultants/Contractors
AlmasManagement
Operation of fossil fuelledvehicles and machineries will leadto emissions due to fossil fuelburning.
Pollution- under –check (PUC)should be made mandatory forall vehicles used forconstruction activities.Stack height of Generator andemission level of vehicles andmachineries should meet therelevant SPCB guidelines.Fuel adulteration should not bepermitted for any constructionmachineries.
Leveling of site, loading andunloading of excavated earthreleases significant amount ofdust
Water should be sprinkledperiodically to suppress the dustgeneration.Compound wall constructedaround the site will controldispersion of dust to aconsiderable extend.
Noise Operation of heavy dutymachineries such as excavators,loaders and frequent uses oftransit vehicles such as lorry,tractor etc leads to increasedambient noise level in projectarea.
Workers shall not be exposed tosound of more than 85 – 90 DBfor more than eight hours a dayand shall be provided with earplugs.Noise quality monitoring shallbe conducted as per
ProjectConsultants/Contractors
AlmasManagement
108
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
SlNo:
Activity EnvironmentalAttributes
Potential Impact Management Measures ImplementingAgency
MonitoringAgency
Environmental Monitoring Planto detect noise pollution.Noise level of vehicles used forconstruction activities shouldmeet the noise standards set byCentral Pollution Control Board(maximum 80 dB(A) )Construction contract shallclearly specify the use ofequipment emitting noise of notgreater than 90 dB (A) for theeight hour operation shift.
Biological NIL NIL ProjectConsultants/Contractors
AlmasManagementSolid waste
ManagementDebris and the extra excavatedearth
The waste materials will have tobe properly disposed off toauthorized dumping areas.Proper disposal measure ofdebris and excavated earth hasto be undertaken by thecontractor.
Geology Breach in ground water table,instability of the excavationperiphery.
Excavation periphery may besealed to avoid breach in groundwater table. By maintainingappropriate slope on the cuttingface and by placing buttresses,instability of the excavationperiphery can be avoided.
Risk Hazards Occupational health and safetyimpacts for workers
Provisions to ensure worker’ssafety shall be followed as perthe rule in force.
5. Foundations,Columns,joinery Works,
Land Top soil gets compacted with themovement of vehicles, man andmachineries.
Top soil conservation measuresshould be adopted.
ProjectConsultants/Contractors
AlmasManagement
109
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
SlNo:
Activity EnvironmentalAttributes
Potential Impact Management Measures ImplementingAgency
MonitoringAgency
Roofing,Ceiling,Plastering,Painting
Soil pollution can occur due tospillage of fuel/lubricants used inconstruction machineries.
Machinery and equipments aremaintained and refilled in such afashion that fuel spillage doesnot contaminate the soil.Soil quality monitoring shall beconducted as per EnvironmentalMonitoring Plan to ascertainlevel of contamination.Maintenance should be carriedout on impervious platformswith spill collection provisionsand oil traps.All spills shall be disposed offas desired and the site shall befully cleaned before handingover.
Soil pollution can occur along rawmaterial storage area, concretemixing area and along the transitpoints and construction sites dueto spillage.
The materials would be storedproperly and all transit should bewithout spillage and in vehiclesunder cover.
Water Contamination of water coursewith construction materials arepossible if the construction is nearto water courses or the surfacerunoff of the construction sitereaches the water course.
Proper covering to be given towater bodies inside the location.Construction during heavy rainydays should be avoided.No construction yard should beset up near water courses.Surface run off should beallowed for detention within theyard so as to avoid reaching thewater courses.
ProjectConsultants/Contractors
AlmasManagement
Air Use of DG set in the constructionsite can lead to air pollutants
The DG should be operated onstandby mode.
110
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
SlNo:
Activity EnvironmentalAttributes
Potential Impact Management Measures ImplementingAgency
MonitoringAgency
emission. Periodic emission test should beconducted.The stack height of the DG sethas to be adequate.Stack height and emission levelof hot mix plant and dieselgenerator should meet therelevant SPCB
Dust emission will be resulted dueto transit of construction vehiclesand concrete mixer.
Water should be sprayed atregular intervals.Tyres of the vehicles should bewashed before leavingconstruction site.The materials being transportedshould be adequately covered.Pollution- under –check (PUC)should be conducted for vehiclesin every three months.
Noise Operation of transport vehiclesand construction machineriesespecially Concrete transferpump, Jack hammer, vibrator etc.Leads to increased ambient noiselevel.
Noise quality monitoring shallbe conducted as perEnvironmental Monitoring Planto detect noise pollution.Noise level of vehicles used forconstruction activities shouldmeet the noise standards set byCentral Pollution Control Board(maximum 80 dB(A) )Construction contract shallclearly specify the use ofequipment emitting noise of notgreater than 90 dB (A) for theeight hour operation shift.The tools deployed for vibration
ProjectConsultants/Contractors
AlmasManagement
111
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
SlNo:
Activity EnvironmentalAttributes
Potential Impact Management Measures ImplementingAgency
MonitoringAgency
will have optimal power ratingconfined to daytime.The vibrators would be mountedon vibration damping mountingsrecommended for machines.
Noise pollution due to woodcutting, planing machine, drillingmachine, welding machine, gascutter / electrical cutter etc. duringjoinery works
As only fitting needs to be doneat site, noise will be minimum.The work has to be done withinthe noise barrier zone
Biological Terrestrial / aquatic flora andfauna in the immediatesurroundings of project locationaffected if the soil / water isseverely contaminated withconstruction materials/chemicalused.
As the construction is confinedwithin the compound wall,possibility of contamination ofwater body is less.Green belt should be plantedprior to construction activitieswith indigenous species havingcanopy to so as to avoiddispersion of pollutants to theimmediate surroundings.
ProjectConsultants/Contractors
AlmasManagement
Socio-Economic The immediate surroundings ofthe project location and transportroutes experiences increasedtraffic, dust and noise levels dueto transfer of constructionmachineries /labour force.
Material transit should beconfined non peak hours andhaul roads should be thoughroads having less traffic. Allmaterial transit should be madeunder cover without chances ofdust dispersion.
Solid wasteManagement
Waste concrete and slurry wouldbe generated as waste.Waste materials will be generatedas part of plastering works. Iffalse ceiling is done, waste piecesof thermo coal, gypsum, PVC etc.
The waste concrete removed hasto be disposed off by thecontractor.
112
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
SlNo:
Activity EnvironmentalAttributes
Potential Impact Management Measures ImplementingAgency
MonitoringAgency
will be generated as wastematerials.
Geology NIL NILII. Operational phase
Land Risk of contamination from thecareless disposal of waste fromthe restaurant and other buildingsfor treatment in the resorts
A well-managed waste disposalscheming in accordance withmunicipal waste Managementwill be adopted.
ProjectConsultants/Contractors
AlmasManagement
Risk of disposal of sludge fromthe STP
The sludge generated will beused for manuring the gardenplants after sludge stabilization.
Water Withdrawal of water more thanthe replenishable capacity of thesource can deplete the sourceduring the operation of WTP
Water recharging facilities willbe provided at site. Maximumusage of rainwater is alsoenvisaged for the project.
Impacts associated with liquideffluents (sewage)
The liquid effluent will betreated in the STP before usingit for irrigation.
Air Emission of pollutants fromvehicular movements and DG setsand negligible emissions fromsewage and solid waste handlingand disposal
A strong vegetation belt whichinvolves evergreen trees andpollution suppressing plants willbe maintained in the plot inorder to minimize the airpollution from the pollutantemissions.DG sets comply with MoEFnorms of emissions will be usedVehicles with pollution undercontrol certificate may beallowed to ply.
Socio economic Employment opportunities to thelocal people
113
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
SUMMARY AND CONCLUSIONS
The Almas Ayurvedic Hospitals and Research Center is proposing an Ayurvedic Resort at Purathur in
Tirur taluk, Malappuram District. The proposed project is a five star Ayurvedic Resort which offers
the blended treatment of Ayurveda and Allopathy to the patients coming. The proposed site is
adjacent to the Tirur-Ponnani River and only about 280 meters away from the sea coast. Thus the site
comes under the purview of Coastal Regulation Zone Notification (CRZ), 2011.
According to the CRZ map of the proposed area, the site comes under CRZ III. As the proposed site
shares its boundary with Tirur-Ponnani River, which is tidal influenced water body, 100 meters area
comes under the Non Development Zone (NDZ) according to the CRZ Notification 2011. No
activities can be proposed in the NDZ area except boat jetty.
The proposed site has a total area of 21081.19sqm and the total plinth area of the proposed buildings
is 5056.87sqm (less than 20,000sqm) which does not require Environmental Clearance from the State
Environmental Impact Assessment Authority. Since the Site comes under the purview of CRZ
notification, 2011, the proposed project requires clearance from the Kerala state Coastal Zone
Management Authority and Ministry of Environment and Forests (MoEF).
The proposed project includes three main buildings-Administrative block, Second Block and
Restaurant. Besides, the project has facilities including:
1. Ample Car Parking
2. Sewage Treatment Plant
3. Biogas plant
4. Water Treatment Plant
5. Rainwater Harvesting Tank
6. R.O Plant
7. Boat Jetty
8. Open theatre for Cultural Programs
9. Swimming Pool
All the activities are proposed in the area sparing the NDZ applicable to the site. Only boat jetty and
open theatre for cultural programmes are proposed in the NDZ.
10
114
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
The proposed project does not alter the Physiography of t he area. And it does not alter the land use of
the area. As the proposed project is a Resort having five star facilities, it will ensure the natural beauty
and aesthetic of the site without altering the existing features. The landscape proposed by the project
will enhance the biological diversity of the area and increase the aesthetic beauty. The local people
will have employment opportunities as a result of this proposed project.
The sensitive areas near the project boundary include schools, hospitals, community facilities, beach
etc. which does not have any impact due to this project.
The potential impacts are measured for both the construction and operation phase. The impacts have
been analyzed in the context of significant positive or negative; direct or indirect; long term or short
term impacts. The impacts during the operation phase include: Degradation of soil and water,
pollution of nearby land and water sources by the careless disposal of construction debris, air and
noise pollution as a result of increased traffic.etc.
The impacts during the operation phase include the positive impacts such as long term positive impact
on the socio economy of the area. Besides there are negative impacts such as: risk of disposal of
sludge from STP, impacts associated with liquid effluents such as storm water & sewage, emissions
from vehicular movements and DG sets, etc.
Proper mitigation measures are suggested to mitigate the negative impacts produced during both the
construction and operation phase.
As the proposed project is an ayurvedic resort, which is eco friendly, there will be less impact on the
surrounding environment and local people. The project has several benefits in terms of foreign
exchange and local area development. The other benefits include: the development of health tourism,
exposure of Ayurveda to the Middle East and other foreign countries, employment opportunities to
the local people, socio economic development f the area etc.
115
116
117
118
119
120
121
122
123
124
125
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
ANNEXURES
126
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Annexure I. Soil Monitoring Results
127
128
129
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Annexure II. Water Quality Monitoring
Results
130
131
132
133
134
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
Annexure III. Air Quality Monitoring Results
135
136
137
REIA Report for Almas Ayurvedic Resort, Purathur
\\Datalibrary-1\2014-15\DP-753
AnnexureIV. Noise Quality Monitoring Results
138
139
140