tabel rab john ahs 2012

160
TABEL PERHITUNGAN VOLUME PEKERJAAN PERSIAPAN TIMESING DIMENSION SQUARING DESCRIPTION 1 18.00 11.00 198.00 m2 PEMBERSIHAN LAPANGAN TIMESING DIMENSION SQUARING DESCRIPTION .2/1/ 18.00 BOWPLANK ( LIHAT GAMBAR ) 11.00 58.00 m TIMESING DIMENSION SQUARING DESCRIPTION 2 18.00 0.03 uk papan bowplank 25x3 cm panj 4m 0.25 0.27 m3 Panjang tiang =1 m 2 11.00 Jarak tiang ke tiang =1m 0.03 ukuran tiang 5/7 cm 0.25 0.17 m3 Banyak tiang =62/2=31 31 1.00 0.05 0.07 0.11 m3 0.54 m3 Volume Bowplank TIMESING DIMENSION SQUARING DESCRIPTION 1 2.00 direksi keet uk 2 x 2 m 2.00 4.00 m2 TIMESING DIMENSION SQUARING DESCRIPTION 1 5.00 los kerja uk 5x2 m 2.00 10.00 m2 TIMESING DIMENSION SQUARING DESCRIPTION 1 0.80 papan nama proyek uk 80 x 40 cm 0.40 0.32 m2

Upload: riyadi-ztcohs

Post on 06-Aug-2015

141 views

Category:

Documents


6 download

TRANSCRIPT

Page 1: TABEL  RAB john AHS 2012

TABELPERHITUNGAN VOLUME PEKERJAAN PERSIAPAN

TIMESING DIMENSION SQUARING DESCRIPTION 1 18.00

11.00 198.00 m2 PEMBERSIHAN LAPANGAN TIMESING DIMENSION SQUARING DESCRIPTION

.2/1/ 18.00 BOWPLANK ( LIHAT GAMBAR ) 11.00 58.00 m

TIMESING DIMENSION SQUARING DESCRIPTION 2 18.00

0.03 uk papan bowplank 25x3 cm panj 4m 0.25 0.27 m3 Panjang tiang =1 m

2 11.00 Jarak tiang ke tiang =1m0.03 ukuran tiang 5/7 cm0.25 0.16 m3 Banyak tiang =62/2=31

31 1.000.050.07 0.11 m3

0.54 m3 Volume BowplankTIMESING DIMENSION SQUARING DESCRIPTION

1 2.00 direksi keet uk 2 x 2 m 2.00 4.00 m2

TIMESING DIMENSION SQUARING DESCRIPTION 1 5.00 los kerja uk 5x2 m

2.00 10.00 m2TIMESING DIMENSION SQUARING DESCRIPTION

1 0.80 papan nama proyek uk 80 x 40 cm 0.40 0.32 m2

Page 2: TABEL  RAB john AHS 2012

TIMESING DIMENSION SQUARING DESCRIPTION 1 58.00

2.00 116 m2 pagar Proyek tinggi 2m dan keliling proyek 66 m

Page 3: TABEL  RAB john AHS 2012

TABELPERHITUNGAN VOLUME PEKERJAAN TANAH

TIMESING DIMENSION SQUARING DESCRIPTION

1 1.40 Luas Trapesium Galian Tanah Untuk Pondasi tipe1 (Pondasi Penuh)

1.00 Lebar Atas 1.4m Lebar Bawah 1.0m

1.00 1.201 0.95 Luas Trapesium Galian Tanah Untuk Pondasi tipe 2 (Pondasi 1/2 Penuh)

0.75 Lebar Atas 0.95m Lebar Bawah 0.75m

1.00 0.851 0.48 Luas trapesium galian tanah untuk pondasi tipe 3 (Pondasi teras)

0.40 lebar atas 0.48m lebar bawah 0.40m

0.65 0.291 0.60 luas trapesium galian tanah untuk pondasi tipe 4( Pondasi setempat)

0.90 lebar atas 0.6m lebar bawah 0.9m

1.50 0.81TIMESING DIMENSION SQUARING DESCRIPTION

1 1.20 volume galian untuk pondasi tipe 1

70.1 84.11 0.85 volume galian untuk pondasi tipe 2

34.5 29.31 0.29 volume galian untuk pondasi tipe 3

7.40 21 0.81

volume galian untuk pondasi tipe 412.00 10

125TIMESING DIMENSION SQUARING DESCRIPTION

1 70.10 urugan pasir di bawah pondasi 5 cm Type 1 (pondasi Penuh)0.050.80 2.80 m3

1 34.50 urugan pasir di bawah pondasi 5 cm Type 2 (pondasi 1/2 Penuh)0.050.80 1.38 m3

1 7.40 urugan pasir di bawah pondasi 5 cm Type 3(pondasi teras)0.050.35 0.13 m3

4.31 m3

TIMESING DIMENSION SQUARING DESCRIPTION 1 125.28

urugan tanah kembali 1/3 dari seluruh vol. galian41.76

m2

m2

m2

m2

m3

m3

m3

m3

m3

m3

Page 4: TABEL  RAB john AHS 2012

TABELPERHITUNGAN VOLUME PEKERJAAN PONDASI

TIMESING DIMENSION SQUARING DESCRIPTION

1 1.00 Luas Aanstamping Pondasi Type 1

0.15 0.15 Panjang 1.0m Lebar 0.15m

1 0.15 Volume Aanstamping Type 1

70.1 10.51

1 0.75 Luas Aanstamping Pondasi Type 2

0.15 0.11 Panjang 0.75m Lebar 0.15m

1 0.11 Volume Aanstamping Type 234.5 3.88

TIMESING DIMENSION SQUARING DESCRIPTION

1 0.30 Luas Trapesium Pondasi Type 1 (Pondasi Penuh)0.80 lebar Atas 0.30m lebar Bawah 0.80m

0.80 0.44

1 70.1 Volume Pondasi Batu Kali Type 1 (Pondasi Penuh)0.44 30.84

1 0.30 Luas Trapesium Pondasi Type 2 (Pondasi 1/2 Penuh)0.60 lebar Atas 0.3 m lebar Bawah 0.6 m

0.80 0.36

1 34.5 Volume Pondasi Batu Kali Type 2 (Pondasi 1/2 Penuh)0.36 12.42

1 0.25 Luas Trapesium Pondasi Type 3(Pondasi Teras)0.35 lebar Atas 0.25m lebar Bawah 0.35 m

0.63 0.19

1 7.4 Volume Pondasi Batu Kali Type 3 (Pondasi Teras )0.19 1.40

TIMESING DIMENSION SQUARING DESCRIPTION 1 1.40 luas pondasi telapak tipe 1

0.60 dengan lebar atas 0.2 m dan lebar bawah 0.6 m0.20 0.56 m2

1 1.40 luas pondasi telapak tipe 20.60 dengan lebar atas 0.2 m dan lebar bawah 0.6m0.20 0.56 m2

TIMESING DIMENSION SQUARING DESCRIPTION 12 0.90 volume pondasi telapak tipe 1 tipe 2

0.56 6.05 m38 0.90

0.56 4.03 m3

m2

m2

m2

m2

m2

m3

m2

m3

m2

m3

Page 5: TABEL  RAB john AHS 2012

TABELPERHITUNGAN VOLUME BETON

TIMESING DIMENSION SQUARING DESCRIPTION 1 0.15 sloof berdimensi 15/30,

0.30 0.05 Luas sloof1 0.045 dengan panjang Sloof 121 m

121 5.44 Volume beton sloof PxLUAS1 0.15 Sloof gantung 15/30,

0.30 0.05 Luas sloof gantung1 0.045 dengan panjang sloof 25 m

25 1.13 Volume sloof gantungTIMESING DIMENSION SQUARING DESCRIPTION

34 0.15 Diketahui : kolom praktis ukuran 15x150.15 34 buah tinggi kolom = 7,20 m7.20 5.51 Volume I

28 0.15 Diketahui : kolom praktis ukuran 15x150.15 28 buah tinggi kolom =3,60 m3.60 2.27 Volume II

24 0.15 Diketahui : kolom struktur ukuran 15x300.30 volume III7.20 7.78 24 buah tinggi kolom = 7,20 m

TIMESING DIMENSION SQUARING DESCRIPTION 1 0.15 Ring Balk ukuran 15 x 20 cm dengan panjang 15 m

0.2015 0.45 m3

TIMESING DIMENSION SQUARING DESCRIPTION 1 0.15 Balok ukuran 15 x 25 cm dengan panjang 11 m

0.2511 0.41 m3

1 0.15 Balok ukuran 15 x 30 cm dengan panjang 70 m0.3070 3.15 m3

1 0.15 Balok ukuran 15 x 35 cm dengan panjang 38 m0.3538 1.99 m3

TIMESING DIMENSION SQUARING DESCRIPTION 1 142.5 volume plat lantai

0.12 17.10 m3 luas plat lantai 142.5TIMESING DIMENSION SQUARING DESCRIPTION

18 0.175 volume tangga0.30 t (antreade) 0.3 m, t (optrade) 0.175 m0.90 0.43 m3 lebar tangga 0.9 m

1 0.15

m2

m3

m2

m3

m3

m3

m3

Page 6: TABEL  RAB john AHS 2012

0.900.90 0.06 m3

0.49 m3 Volume total tangga

Page 7: TABEL  RAB john AHS 2012

TABELPERHITUNGAN VOLUME DINDING

TIMESING DIMENSION SQUARING

4 27.00 108

3 1.152 3.456

104.54

117.279

4 196.20

784.80

1 1.416 1.42

1 6.9825 6.98

3 1.5872 4.76

1 2.3796 2.38

1 3.1908 3.19

6 0.7488 4.49

5 1.5408 7.70

6 0.8496 5.10

4 0.816 3.26

1 1.1984 1.20

5 0.2688 1.34

41.83

784.80

41.83 742.97TIMESING DIMENSION SQUARING

0.015

847.51 12.710.005

12.71 0.06

12.78

m2

m2

m3

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m3

m3

m3

Page 8: TABEL  RAB john AHS 2012

TABELPERHITUNGAN VOLUME DINDING

DESCRIPTION

Volume dinding tanpa kusenpanjang dinding 1:3 = 27 m (3+3+1,5+1,5+1,5+1,5+1,5+1,5+1,5+1,5+1,5+1,5+1,5+1,5+1,5+1,5)

Total dinding 1:3Luas Type kusen P2 ( 1,80 mx 0,64m=1,152 m2)

total kusen

Volume dinding 1:3Panjang dinding 1:5 Panjang lantai 1= 117,2 m (11+4+3+4+3+4+3,5+3+4+2,5+3+1,2+3+18+6+1,5+4,5+0,5+2,5+0,5+15+1,5+18)Panjang lantai 2 = 79 m ( 3+4,5+1+6+3+3+3+15+14+3+2,5+3+1,5+3+4+6,5+3)

Total panjang

Total dinding 1:5

Luas Kusen Type PU= 1,416m2 ( (1,77x0,8)+(0,4x0,8))

Luas kusen Type PG= 6,9825m2 (2,45x2,85)

Luas Kusen P1 = 1,5872 m2 (( 1,76 x 0,72) + (0,4 x 0,8))

Luas Kusen PJ1 = 2,3796 m2 ((0,4x1,23)+(0,51x1,16)+(1,8x0,72))

Luas Kusen PJ2 = 3,1908 m2 ((0,72x1,8)+(0,4x1,75)+(1,03x1,16))

Luas Kusen Type J1 = 0,7488 m2 ((0,48x1,16)+(0,4x0,48))

Luas Kusen Type J2 = 1,5408 m2 ((0,36x1,07)+(1,08x1,07))

Luas Kusen Type J3 = 0,8496 m2 ((0,4x0,36)+(0,36x1,96))

Luas Kusen Type J4 = 0,816 m2 ( 2,04x0,4)

Luas Kusen Type J5 = 1,1984 m2 ( 1,12x1,07)

Luas Kusen Type BV = 0,2688 m2 (0,48x0,56)

Total luas kusen keseluruhan

Volume dinding 1:5 DESCRIPTION

Plesteran tebal 0,015 m

Volume plesteranAcian tebal 0,005 m

Volume acian

Page 9: TABEL  RAB john AHS 2012

TABELPERHITUNGAN VOLUME KUSEN

TIMESING DIMENSION SQUARING DESCRIPTION 1 0.8 Kusen Type PU Pintu Lebar 0,80 m tinggi 1,72 m

1.72 1.38 Volume Pintu1 0.8 Lebar kusen pintu 0,8 m tinggi kusen 1,68 m2 1.68 4.16 Panjang kusen

0.12 lebar 0,12 m tebal 0,04 m0.4 0.20 Volume kusen type PU

2 0.8 Kusen Jendela Lebar 0,80 m tinggi 0,40 m2 0.40 2.40 Panjang kusen jendela

0.12 lebar 0,12 m tebal 0,04 m0.04 0.01

2 0.72 Ventilasi pintu lebar 0,72 m tinggi 0,32 m2 0.32 2.08 volume ventilasi pintu

0.56 Jendela kaca lebar 0,56 m tinggi 0,16m0.16 0.09 volume jendela kaca

TIMESING DIMENSION SQUARING DESCRIPTION 3 0.64 Kusen Type P1 Pintu Lebar 0,64 m tinggi 1,76 m

1.72 3.30 Volume Pintu1 0.72 Lebar kusen pintu 0,72 m tinggi kusen 1,68 m2 1.72 4.16 Panjang kusen3 0.12 lebar 0,12 m tebal 0,04 m

0.04 0.06 Volume kusen type PU2 0.72 Kusen Jendela Lebar 0,72 m tinggi 0,40 m2 0.40 2.24 Panjang kusen jendela

0.12 lebar 0,12 m tebal 0,04 m0.04 0.01

6.40 m total panjang kusen keseluruhan0.64 Jendela kaca 3 buah lebar 0,64 m tinggi 0,32

3 0.32 0.61 volume jendela kacaTIMESING DIMENSION SQUARING DESCRIPTION

2 0.56 Kusen Type P2 Pintu Lebar 0,56 m tinggi 1,76 m1.72 1.93 Volume Pintu

1 0.64 Lebar kusen pintu 0,64 m tinggi kusen 1,72m2 1.72 4.08 Panjang kusen2 0.12 lebar 0,12 m tebal 0,04 m

0.04 0.04 Volume kusen type P2TIMESING DIMENSION SQUARING DESCRIPTION

m2

m2

m3

m2

m3 Volume kusen jendela type PU

m3

m3

m2

m2

m3

m2

m3 Volume kusen jendela type P1

m3

m2

m2

m3

Page 10: TABEL  RAB john AHS 2012

0.3 Kusen Type PJ10.46 Jendela kaca lebar 0,30 m; 0,46 m; 0,30m0.30.14 tinggi 0,14 m; 0,14 m; 0,91 m0.14

0.91 0.38 Volume jendela kaca

0.46 lebar frame 0,46 m ; 0,62 m; 0,46 m0.620.46

2 0.3 Tinggi frame 0,30 m ; 0,30 m ;1,07 m2 0.3

2 1.07 6.42 Volume frame jendela0.64 Lebar pintu 0,64 m tinggi 1,72 m1.72 1.10 volume pintu

1 0.72 lebar kusen pintu 0,72 m tinggi kusen pintu 1,80 m2 1.8 4.32 panjang kusen pintu

0.12 lebar 0,12 m tebal 0,04 m0.04 0.02 Volume kusen pintu

2 0.51 Kusen jendela2 1.23 lebar kusen jendela 0,51 m ; 1,23 m2 1.16 Tinggi kusen jendela 1,16 m; 0,40 m2 0.4

2 1.07 8.74 Panjang kusen jendela0.12 lebar 0,12 m tebal 0,04 m0.04 0.04 Volume kusen pintu

TIMESING DIMENSION SQUARING DESCRIPTION 0.46 Kusen Type PJ20.3 Jendela kaca lebar 0,46 m; 0,30 m;0,30 m;0,30m ;0,30m0.30.3

0.30.14 tinggi 0,14 m ; 0,14 m ;0,14m ; 0,91 m; 0,91 m

0.140.140.91

0.91 0.69 volume jendela kaca

0.62 lebar frame 0,62 m ; 0,47 m; 0,47 m;0,47 m; 0,47 m0.470.470.47

m3

m3

m2

m3

m3

m3

m3

m3

Page 11: TABEL  RAB john AHS 2012

0.472 0.3 Tinggi frame 0,30 m ; 0,30 m ;0,30 m;1,07m;1,07 m2 0.32 1.07

2 1.07 11.08 Volume frame jendela0.64 pintu Lebar 0,64 m tinggi 1,72 m1.72 1.10 volume pintu

1 0.72 Kusen pintu lebar 0,72 m tinggi 1,80 m2 1.8 4.32 panjang kusen pintu

0.12 lebar 0,12 m tebal 0,04 m0.04 0.02 Volume kusen pintu

2 0.51 kusen jendela lebar 0,51m;1,23m2 1.232 1.16 tinggi 1,16 m;0,40 m2 0.4 6.6 Panjang kusen jendela

0.12 lebar 0,12 m tebal 0,04 m0.04 0.03 Volume kusen type PJ2

TIMESING DIMENSION SQUARING DESCRIPTION 0.4 Kusen Type J1 0.40 lebar frame 0,40 m;0,40m

2 0.32 Tinggi frame 0,32 m;1,56 m2 1.56 24.96 Volume frame jendela 6 buah

0.24 Jendela kaca lebar 0,24 m ;0,24 m0.240.16 tinggi 0,16 m; 1,40 m1.4 2.05 volume jendela kaca

2 0.48 Kusen jendela lebar 0,48 m;0,48 m2 0.482 0.40 tinggi 0,40 m ;1,64m2 1.64 6 panjang kusen jendela

0.12 lebar 0,12 m tebal 0,04 m6 0.04 0.17 Volume kusen jendela

TIMESING DIMENSION SQUARING DESCRIPTION 0.48 Kusen Type J2 5 buah0.48 lebar frame 0,48 m;0,48m

2 0.28 Tinggi frame 0,28 m;1,00 m2 1.00 16.32 Volume frame jendela

0.35 jendela kaca Lebar 0,35 m;0,35m0.350.28 tinggi 0,28 m;0,87 m

m3

m2

m3

m3

m2

m3

m3

m3

m2

m3

m3

Page 12: TABEL  RAB john AHS 2012

6 0.87 1.93 volume jendela kaca2 1.07 kusen jendela lebar 1,07 m ;1,07 m2 1.072 0.36 tinggi 0,36m;1,08m2 1.08 7.16 Panjang kusen jendela

0.12 lebar 0,12 m tebal 0,04 m6 0.04 0.21 Volume kusen type J2

TIMESING DIMENSION SQUARING DESCRIPTION 0.28 Kusen Type J3 6 buah0.28 lebar jendela kaca 0,28 m;0,28 m0.32 Tinggi jendela kaca 0,32 m; 1,56 m

6 1.56 2.71 Volume frame jendela2 0.36 Kusen jendela Lebar 0,36m;0,36m2 0.362 0.4 tinggi 0,40 m;1,64m2 1.64 5.52 panjang kusen pintu

0.12 lebar 0,12 m tebal 0,04 m6 0.04 0.16 Volume kusen jendela

TIMESING DIMENSION SQUARING DESCRIPTION 4 0.32 Kusen Type J4 jendela kaca lebar 0,32 m tinggi 1,96 m

1.96 2.51 volume jendela kaca2 0.4 Kusen jendela Lebar 0,40 m tinggi 2,04 m2 2.04 4.88 panjang kusen jendela

0.12 lebar 0,12 m tebal 0,04 m4 0.04 0.09 Volume kusen jendela

TIMESING DIMENSION SQUARING DESCRIPTION 2 0.99 Kusen Type J5 lebar frame 0,99 tinggi 0,33

0.33 2.64 Volume frame jendela0.83 jendela kaca Lebar 0,83 m;0,99m0.990.17 tinggi 0,17 m;0,33m0.33 0.47 volume jendela kaca

2 1.07 kusen jendela lebar 1,07 m tinggi 1,12 m2 1.12 4.38 Panjang kusen jendela

0.12 lebar 0,12 m tebal 0,04 m0.04 0.02 Volume kusen type J5

TIMESING DIMENSION SQUARING DESCRIPTION 0.48 Kusen Type BV 5 buah lebar frame 0,48 m tinggi 0,40 m0.40 8.8 volume frame jendela0.35 Jendela kaca lebar 0,35 m tinggi 0,27 m 5 buah

m3

m2

m3

m3

m3

m3

m3

m2

m3

m3

m3

m2

m3

Page 13: TABEL  RAB john AHS 2012

0.27 0.47 Volume jendela kaca2 0.56 Kusen jendela kaca Lebar 0,56 m tinggi 0,48 m2 0.48 2.08 panjang kusen jendela

0.12 lebar 0,12 m tebal 0,04 m5 0.04 0.05 Volume kusen type BV

TIMESING DIMENSION SQUARING DESCRIPTION 27 1 27 bh Pas. Engsel Pintu39 1 39 bh Pas. Engsel Jendela Kupu-Kupu1 1 1 bh Pas. Kunci Tanam Pintu Biasa3 1 3 bh Pas. Kunci Tanam KM/ WC8 1 8 bh Pas. Kunci Selot

m3

m2

m3

Page 14: TABEL  RAB john AHS 2012

14.291.118.81

72.93

82.84

Page 15: TABEL  RAB john AHS 2012

TABELPERHITUNGAN VOLUME ATAP & PLAFOND

TIMESING DIMENSION SQUARING DESCRIPTION

Pekerjaan Atap Type K1Jumlah kuda-kuda 2 buahjarak antar kuda-kuda 3 mjarak antar kaso 50cm,maka jumlah kaso (300/50)+1 = 7 bhJumlah reng 4m+4m = 8 m, maka jumlah reng 800/25=32 buahjumlah balok apit 2 buah

5.2 Panjang balok tarik 8/12= 5,2 m (5m+1cm+1cm)1.76 Panjang balok tiang gantung 8/12 = 1,76 m5.46 Panjang balok kaki kuda-kuda 8/12 = 5,46 m((1,79 +0,94)x2)1.64 Panjang balok sokong 8/12=1,64m (0,82x2)

1 Panjang balok kunci 8/12 = 1m15.06 m V1 jumlah balok 8/12

0.08 Dimensi 8/120.12 0.14 Volume Kuda-kuda (V1)

TIMESING DIMENSION SQUARING DESCRIPTION 10 Panjang gording 6/12 = 10 m ((3+1+1)x2buah)5 Panjang balok bubungan 6/12 = 5m (3+1+1)

10 Panjang balok tembok = 10m ((3+1+1)x2buah) 25.00 m Jumlah balok 6/12

0.06 Dimensi 6/120.12 0.18 Volume gording & nok (V2) Type K1

TIMESING DIMENSION SQUARING DESCRIPTION 32 5 Panjang reng 3/4 = 5m (3+1+1)

160.00 m total Panjang reng 0.03 Dimensi 3/40.04 0.19 Volume Kaso (V3)56 Panjang kaso 5/7 = 56 m ((4mx2m)x7buah)

0.05 Dimensi 5/70.07 0.20 Volume Reng (V4) Type K1

TIMESING DIMENSION SQUARING DESCRIPTION 24 Panjang listpank = 24m ((5+1+1)x2)+(3+1=1)x2)

5.00 Panjang ruiter = 5m (3+1+1)29.00 m Jumlah papan 2/20

0.02 Dimensi 2/20

0.20 0.12 Volume Lisplank (V5) Type K1TIMESING DIMENSION SQUARING DESCRIPTION

4.003.00

2.00 24.00 Volume atap genteng (V6)

m3

m3

m3

m3

m3

m3

Page 16: TABEL  RAB john AHS 2012

0.27

0.35 0.09 Luas 1 genteng

254.0 bh Banyaknya genteng yang dibutuhkan Type K1TIMESING DIMENSION SQUARING DESCRIPTION

Pekerjaan Atap Type K2Jumlah kuda-kuda 2 buahjarak antar kuda-kuda 3mjarak antar kaso 50cm, maka jumlah kaso (300/50)+1 = 7 bhJumlah reng 465+462=927cm, maka jumlah reng 927/25 = 37 bh

6.2 Panjang balok tarik 8/12= 6,2 m (6m+1cm+1cm)1.71 Panjang balok tiang gantung 8/12 = 1,71 m

6.88 Panjang balok kaki kuda-kuda 8/12 = 6,88 m((1,72+1,72)x2)3 Panjang balok sokong 8/12=3m (1,5x2)1 Panjang balok kunci 8/12 = 1m

18.79 m V1 jumlah balok 8/120.08 Dimensi 8/120.12 0.18 Volume Kuda-kuda (V1)

TIMESING DIMENSION SQUARING DESCRIPTION 10 Panjang gording 6/12 = 10 m ((3+1+1)x2buah)5 Panjang balok bubungan 6/12 = 5m (3+1+1)

10 Panjang balok tembok = 10m ((3+1+1)x2buah) 25.00 m Jumlah balok 6/12

0.06 Dimensi 6/120.12 0.18 Volume gording & nok (V2) Type K2

TIMESING DIMENSION SQUARING DESCRIPTION 37 5 Panjang reng 3/4 = 5m (3+1+1)

185.00 m total Panjang reng 0.03 Dimensi 3/40.04 0.22 Volume Kaso (V3)65.1 Panjang kaso 5/7 = 65,1 m (9,3mx7buah)0.05 Dimensi 5/70.07 0.23 Volume Reng (V4) Type K2

TIMESING DIMENSION SQUARING DESCRIPTION 26 Panjang listpank = 26m ((6+1+1)x2)+(3+1=1)x2)

5.00 Panjang ruiter = 5m (3+1+1)31.00 m Jumlah papan 2/20

0.02 Dimensi 2/20

0.20 0.12 Volume Lisplank (V5) Type K2TIMESING DIMENSION SQUARING DESCRIPTION

4.653.00

2.00 27.90 Volume atap genteng (V6)

0.27

m2

m3

m3

m3

m3

m3

m3

Page 17: TABEL  RAB john AHS 2012

0.35 0.09 Luas 1 genteng

295 bh Banyaknya genteng yang dibutuhkan Type K2TIMESING DIMENSION SQUARING DESCRIPTION

Pekerjaan Atap Type K3Jumlah kuda-kuda 2 buahjarak antar kuda-kuda 3,5 mjarak antar kaso 50cm, maka jumlah kaso (350/50)+1 = 8 bhjumlah reng 490+490= 928cm, maka jumlah reng 928/25 = 38 bh

6.7 Panjang balok tarik 8/12= 6,7 m (6,5m+1 cm+1cm)2.00 Panjang balok tiang gantung 8/12 = 2,00 m7.2 Panjang balok kaki kuda-kuda 8/12 = 7,2 m ((1,8+1,8)x2)3.36 Panjang balok sokong 8/12=3,36m (1,68x2)

1 Panjang balok kunci 8/12 = 1m20.26 m V1 jumlah balok 8/12

0.08 Dimensi 8/120.12 0.19 Volume Kuda-kuda (V1)

TIMESING DIMENSION SQUARING DESCRIPTION 11 Panjang gording 6/12 = 11 m ((3,5+1+1)x2buah)5.5 Panjang balok bubungan 6/12 = 5m (3,5+1+1) 11 Panjang balok tembok = 11m ((3,5+1+1)x2buah)

27.50 m Jumlah balok 6/120.06 Dimensi 6/120.12 0.20 Volume gording & nok (V2) Type K3

TIMESING DIMENSION SQUARING DESCRIPTION 38 5.5 Panjang reng 3/4 = 5,5m (3,5+1+1)

209.00 m total Panjang reng 0.03 Dimensi 3/40.04 0.25 Volume Kaso (V3)78.4 Panjang kaso 5/7 = 78,4 m ((4,9mx2m)x8buah)0.05 Dimensi 5/70.07 0.27 Volume Reng (V4) Type K3

TIMESING DIMENSION SQUARING DESCRIPTION 28 Panjang listpank = 28m ((6,5+1+1)x2)+(3,5+1=1)x2)

5.50 Panjang ruiter = 5m (3,5+1+1)33.50 m Jumlah papan 2/20

0.02 Dimensi 2/20

0.20 0.13 Volume Lisplank (V5) Type K3TIMESING DIMENSION SQUARING DESCRIPTION

4.903.50

2.00 34.30 Volume atap genteng (V6)

0.27

0.35 0.09 Luas 1 genteng

m2

m3

m3

m3

m3

m3

m3

m2

Page 18: TABEL  RAB john AHS 2012

363.0 bh Banyaknya genteng yang dibutuhkan Type K3TIMESING DIMENSION SQUARING DESCRIPTION

Pekerjaan Plafond15.00 panjang 15 m lebar 11m

11.00 165.00 Luas lantai 1 12.00 panjang 12 m lebar 11m

11.00 132.00 Luas lantai 2

297.00 Luas total yang akan di plafond 1.20 Plafond jenis GRC 120 x 240 cm

2.40 2.88 luas 1 plafond297.002.88 103.13 bh Jumlah plafond yang akan digunakan

TIMESING DIMENSION SQUARING DESCRIPTION

1.002.00 2.00 m Kerangka plafond kayu borneo 5/7

297.002.00 148.50 m luas kerangka plafond

0.12 240.12 260.13 280.37 78

m2

m2

m2

m2

Page 19: TABEL  RAB john AHS 2012

TABELPERHITUNGAN VOLUME LANTAI

TIMESING DIMENSION SQUARING DESCRIPTION 295.00

0.15 44.25 m2 Pek.Tanah urug bawah lantai 15 cmTIMESING DIMENSION SQUARING DESCRIPTION

295.000.1 29.50 m2 Pek.pasir urug 10 cm

TIMESING DIMENSION SQUARING DESCRIPTION

Menggunakan keramik ukuran 30 x 30 DN4.5 Ruang keluarga lebar 4,5m x 4,5 m1.5 panjang 1,5m x 4 m4.54.00 24.75 m2 luas ruang keluarga0.3 275.00 bh keramik yang dibutuhkan dengan ukuran 30cm x 30cm DN

TIMESING DIMENSION SQUARING DESCRIPTION

Menggunakan keramik ukuran 30 x 30 DN6.5 Ruang tamu panjang 6,5 m x 2,5 m x 1,2 m2.5 lebar 3 m x 3m x 0,5m1.233

1.5 28.80 m2 Luas ruang tamu0.3 320.00 bh keramik yang dibutuhkan dengan ukuran 30cm x 30cm DN

TIMESING DIMENSION SQUARING DESCRIPTION

Menggunakan keramik ukuran 30 x 30 DN2.4 m Ruang Teras panjang 2,4 m lebar 1,46 m1.46 3.50 Luas ruang teras0.3 38.93 bh keramik yang dibutuhkan dengan ukuran 30cm x 30cm DN

TIMESING DIMENSION SQUARING DESCRIPTION

Menggunakan keramik ukuran 30 x 30 DN3.00 Kamar tidur lantai 1.1 panjang 3 m x 0,6 m0.60 lebar 2,9 m x 2,5 m2.902.50 10.20 m2 Luas kamar tidur Lantai 1.10.3 113.33 bh keramik yang dibutuhkan dengan ukuran 30cm x 30cm DN4.00 Kamar tidur lantai 1.2 panjang 4 m lebar 4,5 m4.50 18.00 m2 Luas kamar tidur lantai 1.20.3 200.00 bh keramik yang dibutuhkan dengan ukuran 30cm x 30cm DN

TIMESING DIMENSION SQUARING DESCRIPTION Menggunakan keramik ukuran 30 x 30 DN

5.00 Ruang Makan panjang 5 m lebar 3 m

3.00 15.00 Luas ruang makanm2

Page 20: TABEL  RAB john AHS 2012

0.3 166.67 bh keramik yang dibutuhkan dengan ukuran 30cm x 30cm DNTIMESING DIMENSION SQUARING DESCRIPTION

Menggunakan keramik ukuran 30 x 30 DN3.00 Kamar tidur lantai 2.2 panjang 3 m lebar 3 m3.00 9.00 m2 Luas kamar tidur lantai 2.20.3 100.00 bh keramik yang dibutuhkan dengan ukuran 30cm x 30cm DN

TIMESING DIMENSION SQUARING DESCRIPTION

Menggunakan keramik ukuran 30 x 30 DN3.00 Kamar tidur lantai 2.3 panjang 3 m lebar 5 m5.00 15.00 m2 Luas kamar tidur lantai 2.30.3 166.67 bh keramik yang dibutuhkan dengan ukuran 30cm x 30cm DN

TIMESING DIMENSION SQUARING DESCRIPTION

Menggunakan keramik ukuran 30 x 30 DN3.00 Kamar tidur lantai 2.4 panjang 3 m lebar 4 m4.00 12.00 m2 Luas kamar tidur lantai 2.40.3 133.33 bh keramik yang dibutuhkan dengan ukuran 30cm x 30cm DN

TIMESING DIMENSION SQUARING DESCRIPTION 24.75 Luas dengan menggunakan keramik 30 x 30 DN28.803.50

10.2018.0015.009.00

15.0012.00 136.25 m2 Total luas ruang yang menggunakan keramik 30 x 30 DN

TIMESING DIMENSION SQUARING DESCRIPTION 275.00 keramik yang dibutuhkan dengan ukuran 30cm x 30cm DN320.0038.93113.33200.00166.67100.00166.67133.33 1514 bh Total seluruh keramik 30 x 30 DN yang diperlukan

151.39 kot Total kotak keramik ukuran 30 x 30 DNTIMESING DIMENSION SQUARING DESCRIPTION

Menggunakan keramik ukuran 30 x 30 DN polos6 Dapur 1.1 panjang 6 m lebar 3 m3 18.00 m2 luas dapur 1.1.

0.3 200.00 bh keramik yang dibutuhkan dengan ukuran 30cm x 30cm DN polos1.5 Dapur 1.2 panjang 1,5m x 1,5m1.5 lebar 3 m x 1,5 m

Page 21: TABEL  RAB john AHS 2012

31.5 6.75 m2 Luas dapur 1.20.3 75.00 bh keramik yang dibutuhkan dengan ukuran 30cm x 30cm DN polos

TIMESING DIMENSION SQUARING DESCRIPTION

Menggunakan keramik ukuran 30 x 30 DN polos3 Taman panjang 3 m lebar 0,98 m

0.98 2.94 m2 luas taman0.3 32.67 bh keramik yang dibutuhkan dengan ukuran 30cm x 30cm DN polos

TIMESING DIMENSION SQUARING DESCRIPTION

Menggunakan keramik ukuran 30 x 30 DN polos3 Garasi panjang 3 m lebar 6,67 m

6.67 20.01 m2 luas garasi0.3 222.33 bh keramik yang dibutuhkan dengan ukuran 30cm x 30cm DN polos

TIMESING DIMENSION SQUARING DESCRIPTION

Menggunakan keramik ukuran 30 x 30 DN polos3 Carpot panjang 3 m lebar 3 m3 9.00 m2 luas carpot

0.3 100.00 bh keramik yang dibutuhkan dengan ukuran 30cm x 30cm DN polosTIMESING DIMENSION SQUARING DESCRIPTION

Menggunakan keramik ukuran 30 x 30 DN polos3 Kamar tidur pembantu panjang 3 m lebar 2,5 m

2.5 7.50 m2 luas kamar tidur pembantu0.3 83.33 bh keramik yang dibutuhkan dengan ukuran 30cm x 30cm DN polos

TIMESING DIMENSION SQUARING DESCRIPTION

Menggunakan keramik ukuran 30 x 30 DN polos3 Mushola panjang 3 m lebar 2,5 m

2.5 7.50 m2 luas mushola0.3 83.33 bh keramik yang dibutuhkan dengan ukuran 30cm x 30cm DN polos

TIMESING DIMENSION SQUARING DESCRIPTION

Menggunakan keramik ukuran 30 x 30 DN polos6.5 Ruang belajar / R. Duduk 1 panjang 6,5 m lebar 1,5 m1.5 9.75 m2 luas Ruang belajar / R. Duduk 10.3 108.33 bh keramik yang dibutuhkan dengan ukuran 30cm x 30cm DN polos

TIMESING DIMENSION SQUARING DESCRIPTION

Menggunakan keramik ukuran 30 x 30 DN polos4.5 Ruang belajar / R. Duduk 2 panjang 4,5 m x 3,05 m3.05 lebar 8 m x 3,05 m

83.05 45.30 m2 luas Ruang belajar / R. Duduk 20.3 503.36 bh keramik yang dibutuhkan dengan ukuran 30cm x 30cm DN polos

TIMESING DIMENSION SQUARING DESCRIPTION

Menggunakan keramik ukuran 30 x 30 DN polos5 Ruang belajar / R. Duduk 3 panjang 5 m lebar 3 m3 15.00 m2 luas Ruang belajar / R. Duduk 3

Page 22: TABEL  RAB john AHS 2012

0.3 166.67 bh keramik yang dibutuhkan dengan ukuran 30cm x 30cm DN polosTIMESING DIMENSION SQUARING DESCRIPTION

Menggunakan keramik ukuran 30 x 30 DN polos1 Ruang belajar / R. Duduk 4 panjang 1 m lebar 3,93 m

3.93 3.93 m2 luas Ruang belajar / R. Duduk 4 0.3 43.67 bh keramik yang dibutuhkan dengan ukuran 30cm x 30cm DN polos

TIMESING DIMENSION SQUARING DESCRIPTION

Menggunakan keramik ukuran 30 x 30 DN polos3 Ruang belajar / R. Duduk 5 panjang 3 m lebar 2,5 m

2.5 7.50 m2 luas Ruang belajar / R. Duduk 50.3 83.33 bh keramik yang dibutuhkan dengan ukuran 30cm x 30cm DN polos

TIMESING DIMENSION SQUARING DESCRIPTION 18.00 Luas dengan menggunakan keramik 30 x 30 DN polos 6.752.94

20.019.007.507.509.75

45.3015.003.937.50 153.18 m2 Total luas ruang yang menggunakan keramik 30 x 30 DN polos

TIMESING DIMENSION SQUARING DESCRIPTION 200.00 keramik yang dibutuhkan dengan ukuran 30cm x 30cm DN polos75.0032.67222.33100.0083.3383.33108.33503.36166.6743.6783.33 1435 bh Total seluruh keramik 30 x 30 DN polos yang diperlukan

143.54 kot Total kotak keramik ukuran 30 x 30 polosTIMESING DIMENSION SQUARING DESCRIPTION

Menggunakan keramik ukuran 20 x 20 bercorak0.7 Kamar mandi 1 panjang 0,7 m lebar 0,65 m d 0,470.65 panjang 1,5m x 4 m0.47 0.28 m2 luas kamar mandi 10.2 7.04 bh keramik yang dibutuhkan dengan ukuran 20cm x 20cm bercorak

Page 23: TABEL  RAB john AHS 2012

TIMESING DIMENSION SQUARING DESCRIPTION

Menggunakan keramik ukuran 20 x 20 bercorak0.78 m Kamar mandi 2 panjang 0,78 m lebar 1,35 m1.35 1.05 Luas kamar mandi 20.2 26.33 bh keramik yang dibutuhkan dengan ukuran 20cm x 20cm bercorak

TIMESING DIMENSION SQUARING DESCRIPTION

Menggunakan keramik ukuran 20 x 20 bercorak0.65 m Kamar mandi 3 panjang 0,65 m lebar 0,65 m0.65 0.42 Luas kamar mandi 30.2 10.56 bh keramik yang dibutuhkan dengan ukuran 20cm x 20cm bercorak

TIMESING DIMENSION SQUARING DESCRIPTION 0.28 Luas kamar mandi Lantai 21.05

0.42 1.76 Total luas kamar mandi lantai 2

TIMESING DIMENSION SQUARING DESCRIPTION 7.04

26.3310.56 43.92 bh keramik yang dibutuhkan dengan ukuran 20cm x 20cm bercorak

2.20 kot Total kotak keramik ukuran20 x20 bercorakTIMESING DIMENSION SQUARING DESCRIPTION

Menggunakan keramik ukuran 20 x 20 bercorak1.76 m2 Kamar mandi lantai 1.1 sama dengan total kamar mandi lantai 20.2 43.92 bh keramik yang dibutuhkan dengan ukuran 20cm x 20cm bercorak

TIMESING DIMENSION SQUARING DESCRIPTION

Menggunakan keramik ukuran 20 x 20 bercorak0.71 m Kamar mandi Lantai 1.2 R 1 panjang 0,71 m x 0,4 m0.4 lebar 0,82 m x 0,69m0.820.69 0.31 Luas kamar mandi 0.2 7.65 bh keramik yang dibutuhkan dengan ukuran 20cm x 20cm bercorak

TIMESING DIMENSION SQUARING DESCRIPTION

Menggunakan keramik ukuran 20 x 20 bercorak0.82 m Kamar mandi R 2 panjang 0,82 m lebar 0,79 m

0.79 0.65 Luas kamar mandi 0.2 16.19 bh keramik yang dibutuhkan dengan ukuran 20cm x 20cm bercorak

TIMESING DIMENSION SQUARING DESCRIPTION

Menggunakan keramik ukuran 20 x 20 bercorak1.9 m Kamar mandi R 3 panjang 1,9 m lebar 1,5 m1.5 2.85 Luas kamar mandi 0.2 71.25 bh keramik yang dibutuhkan dengan ukuran 20cm x 20cm bercorak

TIMESING DIMENSION SQUARING DESCRIPTION 1.76 Luas kamar mandi0.31

m2

Page 24: TABEL  RAB john AHS 2012

0.65

2.85 5.56 Total luas kamar mandi

TIMESING DIMENSION SQUARING DESCRIPTION 43.927.65

16.1971.25 139.02 bh keramik yang dibutuhkan dengan ukuran 20cm x 20cm bercorak

6.95 kot Total kotak keramik ukuran20 x20 bercorak

m2

Page 25: TABEL  RAB john AHS 2012

136.25153.18

5.56

Page 26: TABEL  RAB john AHS 2012

TABELPERHITUNGAN PEKERJAAN INSTALASI LISTRIK

TIMESING DIMENSION SQUARING DESCRIPTION 23 1.00 23 bh Lampu TL2 1.00 2 bh Lampu Taman2 1.00 2 bh Lampu Gantung

14 1.00 14 bh Saklar tunggal4 1.00 4 bh Saklar ganda 5 1.00 5 bh Stop Kontak1 1.00 1 bh Sekring1 1.00 1 bh KWH

Page 27: TABEL  RAB john AHS 2012

TABELPERHITUNGAN PEKERJAAN SANITASI

TIMESING DIMENSION SQUARING DESCRIPTION 1 1 1 bh Mesin pompa air1 19.68 19.68 m Pipa air bersih dia 3/4"1 1.00 1 bh Kloset Jongkok Porselen1 53.12 53.12 m Pipa air kotor dia 4 "1 1.00 1 bh Kloset duduk / Monoblock1 1.00 1 bh Wastafel3 1.00 3 bh Bak Mandi Fiberglass, Kap 0,30 m31 1.00 1 bh Bath Tube2 1.00 2 bh Bak Cuci Piring1 1.00 1 bh Bak Kontrol6 1.00 6 bh Kran Air1 1.00 1 unit Septitank dan Rembesan3 1.00 3 unit Floor Drain

Page 28: TABEL  RAB john AHS 2012

TABELPERHITUNGAN PEKERJAAN PENGECATAN

TIMESING DIMENSION SQUARING DESCRIPTION 2

847.51 1695.03 pengecatan dindingTIMESING DIMENSION SQUARING DESCRIPTION

1

297.00 297 Pengecatan PlafondTIMESING DIMENSION SQUARING DESCRIPTION

2

82.84 166 Pengecatan Kusen

m2

m2

m2

Page 29: TABEL  RAB john AHS 2012

TABELPERHITUNGAN PEKERJAAN LAIN-LAIN

TIMESING DIMENSION SQUARING DESCRIPTION

1 30.03 31.03 Pek. Pegangan tanggam2

Page 30: TABEL  RAB john AHS 2012

DATA UMUM PROYEK

Nama Proyek

Lokasi Proyek

Pemilik ProyekNama Kontraktor

Luas Bangunan

Luas Tanah

SPESIFIKASI

Jenis BangunanFungsi BangunanPondasiDindingRangka AtapPenutup AtapLisplankLantaiLantai KM/WCKusenPlafonSanitasi dan Instalasi Air

Listrik

Page 31: TABEL  RAB john AHS 2012

: Rumah Tinggal 2 Lantai

: Perumahan Cibeureum Regency Blok, Kelurahan Cibeureum, Kecamatan Sukaraja, Sukabumi: PT Putra Papan Seruni: PT Adhie Tamtam Putra

: Struktur Beton bertulang 2 lantai: Rumah tinggal: Pas. Batu Kali 1:2, dan Pondasi Telapak: Pasangan Bata Merah yang diplester dan diaci: Kuda-kuda Kayu Jati: Genting Glazuur: Kayu Kamper: Keramik bercorak

: Pintu, Jendela, Telinga Kusen, Angker: Gypsum: Septictank, Rembesan, Pipa PVC, kran air, floor drain, kloset duduk,kloset jongkok, wastafel, : Box panel, stop kontak, saklar ganda, saklar tunggal, fitting lampu, lampu

: 138 m2 ( Lantai 1 ), 144 m2 ( Lantai 2 )

: 198 m2

Page 32: TABEL  RAB john AHS 2012

WORK BREAKDOWN STRUCTURE

1 Pekerjaan Persiapan

2 Pekerjaan Tanah

3 Pekerjaan Pondasi

4 Pekerjaan Beton

5 Pekerjaan Dinding

6 Pekerjaan Pintu dan Jendela

7 Pekerjaan Atap dan Plafond

8 Pekerjaan Lantai

10 Pekerjaan Sanitasi

11 Pekerjaan Pengecatan

1.1 Pembersihan Lapangan

1.2 Bowplank

1.3 Direksi Keet

1.4 Los Kerja

2.3 Urugan Tanah

2.1 Galian Tanah

1.6 Pagar Proyek

1.5 Papan Nama Proyek

3.1 Pekerjaan Pondasi Batu Kali

3.1.2 Pemasangan Batu Kali

3.1.1 Aanstamping

4.6 Tangga

4.5 Plat Lantai

4.4 Balok

4.2 Kolom

4.1 Sloof

5.1 Pasangan Bata Merah 5.1.1 Plesteran dan Acian

6.1. Pekerjaan Kusen

6.3 Pemasangan Aksesoris

6.2 Pemasangan Kaca

7.1 Pek. Kuda-kuda

7.2 Pek. Rangka Plafond

7.1.1 Pek. Rangka Atap

9 Pekerjaan Elektrikal

11.2 Pengecatan Plafond

11.1. Pengecatan Dinding

Pekerjaan Rumah Tinggal 2 lantai

3.2 Pekerjaan Pondasi Telapak

2.2 Urugan Pasir DibawahPondasi

3.2.2 Pondasi TelapakSetengah

3.2.1 Pondasi Telapak Penuh

11.3 Pengecatan Kusen

11.4 Pengecatan Lisplank

8.1 Pek. Keramik 30 x 30

8.2 Pek. Keramik 20 x 20

4.3 Ring Balk

Page 33: TABEL  RAB john AHS 2012

WORK BREAKDOWN STRUCTURE

1 Pekerjaan Persiapan

2 Pekerjaan Tanah

3 Pekerjaan Pondasi

4 Pekerjaan Beton

5 Pekerjaan Dinding

6 Pekerjaan Pintu dan Jendela

7 Pekerjaan Atap dan Plafond

8 Pekerjaan Lantai

10 Pekerjaan Sanitasi

11 Pekerjaan Pengecatan

1.1 Pembersihan Lapangan

1.2 Bowplank

1.3 Direksi Keet

1.4 Los Kerja

2.3 Urugan Tanah

2.1 Galian Tanah

1.6 Pagar Proyek

1.5 Papan Nama Proyek

3.1 Pekerjaan Pondasi Batu Kali

3.1.2 Pemasangan Batu Kali

3.1.1 Aanstamping

4.6 Tangga

4.5 Plat Lantai

4.4 Balok

4.2 Kolom

4.1 Sloof

5.1 Pasangan Bata Merah 5.1.1 Plesteran dan Acian

6.1. Pekerjaan Kusen

6.3 Pemasangan Aksesoris

6.2 Pemasangan Kaca

7.1 Pek. Kuda-kuda

7.2 Pek. Rangka Plafond

7.1.1 Pek. Rangka Atap

9 Pekerjaan Elektrikal

11.2 Pengecatan Plafond

11.1. Pengecatan Dinding

Pekerjaan Rumah Tinggal 2 lantai

3.2 Pekerjaan Pondasi Telapak

2.2 Urugan Pasir DibawahPondasi

3.2.2 Pondasi TelapakSetengah

3.2.1 Pondasi Telapak Penuh

11.3 Pengecatan Kusen

11.4 Pengecatan Lisplank

8.1 Pek. Keramik 30 x 30

8.2 Pek. Keramik 20 x 20

4.3 Ring Balk

Page 34: TABEL  RAB john AHS 2012

WORK BREAKDOWN STRUCTURE

1 Pekerjaan Persiapan

2 Pekerjaan Tanah

3 Pekerjaan Pondasi

4 Pekerjaan Beton

5 Pekerjaan Dinding

6 Pekerjaan Pintu dan Jendela

7 Pekerjaan Atap dan Plafond

8 Pekerjaan Lantai

10 Pekerjaan Sanitasi

11 Pekerjaan Pengecatan

1.1 Pembersihan Lapangan

1.2 Bowplank

1.3 Direksi Keet

1.4 Los Kerja

2.3 Urugan Tanah

2.1 Galian Tanah

1.6 Pagar Proyek

1.5 Papan Nama Proyek

3.1 Pekerjaan Pondasi Batu Kali

3.1.2 Pemasangan Batu Kali

3.1.1 Aanstamping

4.6 Tangga

4.5 Plat Lantai

4.4 Balok

4.2 Kolom

4.1 Sloof

5.1 Pasangan Bata Merah 5.1.1 Plesteran dan Acian

6.1. Pekerjaan Kusen

6.3 Pemasangan Aksesoris

6.2 Pemasangan Kaca

7.1 Pek. Kuda-kuda

7.2 Pek. Rangka Plafond

7.1.1 Pek. Rangka Atap

9 Pekerjaan Elektrikal

11.2 Pengecatan Plafond

11.1. Pengecatan Dinding

Pekerjaan Rumah Tinggal 2 lantai

3.2 Pekerjaan Pondasi Telapak

2.2 Urugan Pasir DibawahPondasi

3.2.2 Pondasi TelapakSetengah

3.2.1 Pondasi Telapak Penuh

11.3 Pengecatan Kusen

11.4 Pengecatan Lisplank

8.1 Pek. Keramik 30 x 30

8.2 Pek. Keramik 20 x 20

4.3 Ring Balk

Page 35: TABEL  RAB john AHS 2012

WORK BREAKDOWN STRUCTURE

1 Pekerjaan Persiapan

2 Pekerjaan Tanah

3 Pekerjaan Pondasi

4 Pekerjaan Beton

5 Pekerjaan Dinding

6 Pekerjaan Pintu dan Jendela

7 Pekerjaan Atap dan Plafond

8 Pekerjaan Lantai

10 Pekerjaan Sanitasi

11 Pekerjaan Pengecatan

1.1 Pembersihan Lapangan

1.2 Bowplank

1.3 Direksi Keet

1.4 Los Kerja

2.3 Urugan Tanah

2.1 Galian Tanah

1.6 Pagar Proyek

1.5 Papan Nama Proyek

3.1 Pekerjaan Pondasi Batu Kali

3.1.2 Pemasangan Batu Kali

3.1.1 Aanstamping

4.6 Tangga

4.5 Plat Lantai

4.4 Balok

4.2 Kolom

4.1 Sloof

5.1 Pasangan Bata Merah 5.1.1 Plesteran dan Acian

6.1. Pekerjaan Kusen

6.3 Pemasangan Aksesoris

6.2 Pemasangan Kaca

7.1 Pek. Kuda-kuda

7.2 Pek. Rangka Plafond

7.1.1 Pek. Rangka Atap

9 Pekerjaan Elektrikal

11.2 Pengecatan Plafond

11.1. Pengecatan Dinding

Pekerjaan Rumah Tinggal 2 lantai

3.2 Pekerjaan Pondasi Telapak

2.2 Urugan Pasir DibawahPondasi

3.2.2 Pondasi TelapakSetengah

3.2.1 Pondasi Telapak Penuh

11.3 Pengecatan Kusen

11.4 Pengecatan Lisplank

8.1 Pek. Keramik 30 x 30

8.2 Pek. Keramik 20 x 20

4.3 Ring Balk

Page 36: TABEL  RAB john AHS 2012

WORK BREAKDOWN STRUCTURE

1 Pekerjaan Persiapan

2 Pekerjaan Tanah

3 Pekerjaan Pondasi

4 Pekerjaan Beton

5 Pekerjaan Dinding

6 Pekerjaan Pintu dan Jendela

7 Pekerjaan Atap dan Plafond

8 Pekerjaan Lantai

10 Pekerjaan Sanitasi

11 Pekerjaan Pengecatan

1.1 Pembersihan Lapangan

1.2 Bowplank

1.3 Direksi Keet

1.4 Los Kerja

2.3 Urugan Tanah

2.1 Galian Tanah

1.6 Pagar Proyek

1.5 Papan Nama Proyek

3.1 Pekerjaan Pondasi Batu Kali

3.1.2 Pemasangan Batu Kali

3.1.1 Aanstamping

4.6 Tangga

4.5 Plat Lantai

4.4 Balok

4.2 Kolom

4.1 Sloof

5.1 Pasangan Bata Merah 5.1.1 Plesteran dan Acian

6.1. Pekerjaan Kusen

6.3 Pemasangan Aksesoris

6.2 Pemasangan Kaca

7.1 Pek. Kuda-kuda

7.2 Pek. Rangka Plafond

7.1.1 Pek. Rangka Atap

9 Pekerjaan Elektrikal

11.2 Pengecatan Plafond

11.1. Pengecatan Dinding

Pekerjaan Rumah Tinggal 2 lantai

3.2 Pekerjaan Pondasi Telapak

2.2 Urugan Pasir DibawahPondasi

3.2.2 Pondasi TelapakSetengah

3.2.1 Pondasi Telapak Penuh

11.3 Pengecatan Kusen

11.4 Pengecatan Lisplank

8.1 Pek. Keramik 30 x 30

8.2 Pek. Keramik 20 x 20

4.3 Ring Balk

Page 37: TABEL  RAB john AHS 2012

WORK BREAKDOWN STRUCTURE

1 Pekerjaan Persiapan

2 Pekerjaan Tanah

3 Pekerjaan Pondasi

4 Pekerjaan Beton

5 Pekerjaan Dinding

6 Pekerjaan Pintu dan Jendela

7 Pekerjaan Atap dan Plafond

8 Pekerjaan Lantai

10 Pekerjaan Sanitasi

11 Pekerjaan Pengecatan

1.1 Pembersihan Lapangan

1.2 Bowplank

1.3 Direksi Keet

1.4 Los Kerja

2.3 Urugan Tanah

2.1 Galian Tanah

1.6 Pagar Proyek

1.5 Papan Nama Proyek

3.1 Pekerjaan Pondasi Batu Kali

3.1.2 Pemasangan Batu Kali

3.1.1 Aanstamping

4.6 Tangga

4.5 Plat Lantai

4.4 Balok

4.2 Kolom

4.1 Sloof

5.1 Pasangan Bata Merah 5.1.1 Plesteran dan Acian

6.1. Pekerjaan Kusen

6.3 Pemasangan Aksesoris

6.2 Pemasangan Kaca

7.1 Pek. Kuda-kuda

7.2 Pek. Rangka Plafond

7.1.1 Pek. Rangka Atap

9 Pekerjaan Elektrikal

11.2 Pengecatan Plafond

11.1. Pengecatan Dinding

Pekerjaan Rumah Tinggal 2 lantai

3.2 Pekerjaan Pondasi Telapak

2.2 Urugan Pasir DibawahPondasi

3.2.2 Pondasi TelapakSetengah

3.2.1 Pondasi Telapak Penuh

11.3 Pengecatan Kusen

11.4 Pengecatan Lisplank

8.1 Pek. Keramik 30 x 30

8.2 Pek. Keramik 20 x 20

4.3 Ring Balk

Page 38: TABEL  RAB john AHS 2012

TABEL 2

DAFTAR HARGA SATUAN BAHAN

NO Jenis Bahan Bangunan Sat.Harga Satuan

Rp.

1 2 3 4

Bahan - Bahan Yang Dipakai

1 kayu kaso, albasia m3 Rp1,500,000.00 2 paku 5 - 12 cm kg Rp13,000.00 3 kayu papan 3/20 m3 Rp1,500,000.00 4 batu belah 15/20 cm m3 Rp200,000.00 5 semen portland kg Rp1,120.00 6 pasir pasang m3 Rp175,000.00 7 bata merah bh Rp750.00 8 kayu borneo balok m3 Rp4,250,000.00 9 kayu borneo papan m3 Rp3,500,000.00 10 paku 1 - 3 cm kg Rp20,000.00 11 triplek 4mm lembar Rp55,000.00 12 lem kayu liter Rp12,000.00 13 kaca 3mm m2 Rp55,000.00 14 kaca 5mm m2 Rp75,000.00 15 engsel pintu buah Rp20,000.00 16 engsel jendela buah Rp7,500.00 17 kunci tanam besar buah Rp125,000.00 18 kunci tanam KM buah Rp35,000.00 19 spring knip buah Rp8,050.00 20 genteng bubung peletong buah Rp2,500.00 21 genteng peletong buah Rp1,800.00 22 list kayu 1 x 5 cm m Rp15,000.00 23 seng plat 7,5 x 15 cm lembar Rp17,500.00 24 meni besi kg Rp25,500.00

25 batu pecah mesin 1/2 m3 Rp250,000.00

26 pasir beton m3 Rp165,000.00

27 split m3 Rp147,500.00 28 besi beton polos kg Rp7,000.00 29 kawat beton kg Rp14,000.00 30 minyak bekisting liter Rp5,000.00 31 kayu terentang albasia m3 Rp1,500,000.00 32 triplek 9mm lembar Rp115,000.00 33 dolken kayu alam 8-10/400 batang Rp16,250.00 34 keramik putih 30 x 30 cm buah Rp2,545.00 35 semen warna ( putih ) kg Rp5,000.00 36 keramik warna 20 x 20 cm buah Rp1,600.00 37 floor drain buah Rp24,750.00 38 kran air buah Rp27,500.00 39 seal tape buah Rp2,000.00 40 dempul jadi kg Rp40,000.00 41 minyak cat liter Rp18,500.00 42 batu apung kg - 43 kape kayu buah Rp5,000.00 44 plamuur tembok kg Rp40,000.00

Page 39: TABEL  RAB john AHS 2012

45 kertas amplas lembar Rp2,650.00 46 plamuur kayu kg Rp40,000.00 47 cat dasar kg Rp50,000.00 48 cat penutup kg Rp32,000.00 49 kwas 3 buah Rp12,000.00 50 meni kayu kg Rp17,250.00 51 cat penutup 2 kali kg Rp32,000.00 52 politur liter Rp27,850.00 53 politur jadi liter Rp28,750.00 54 residu liter Rp3,150.00 55 roll cat buah Rp15,000.00

56 Pegangan tangga ( balustrade ) profil jati Rp107,300.00

57 Bak Fiberrglass Kap.0,30 M3 Buah Rp147,500.00 58 Bak Fiberrglass Kap.1 M3 Buah Rp168,000.00

59 Gypsum Rp63,600.00

60 Kabel Rp7,000.00

61 Kloset Duduk/Monoblock Buah Rp1,025,126.00 62 Kloset Jongkok Porselen Buah Rp335,400.00 63 Kunci Selot Buah Rp7,500.00 64 Lampu Gantung Buah Rp145,000.00 65 Lampu Neon 20 Watt Buah Rp53,300.00 66 Lampu Taman Buah Rp165,000.00 67 Lampu TL Buah Rp73,700.00 68 Sakelar Ganda Buah Rp18,500.00 69 Saklar Tunggal Buah Rp12,000.00 70 Wastafel Buah Rp256,800.00

71 Reng uk. 2/3 kayu borneo super Rp1,600.00

72 Reng uk. 3/4 kayu borneo super Rp1,900.00

73 Pipa PVC 3/4" Batang Rp3,500.00 74 Pipa PVC 4" Batang Rp31,250.00 75 Lampu Pijar 25 watt s/d 100 watt Buah Rp8,200.00 76 Lampu Neon TL 20 watt Buah Rp53,300.00 77 Lampu Neon TL 40 watt Buah Rp73,700.00

78 Lampu Taman 1 Buah + Tiang Buah Rp302,200.00

M1

M3

M1

M1

M1

Page 40: TABEL  RAB john AHS 2012

TABEL 2

DAFTAR HARGA SATUAN BAHAN

Jenis Bahan Bangunan Sat.Harga Satuan

Rp.

1 2 345.000

30.000

90.000

175.000

165.000

165.000

200.000

250.000

200.000

185.000

155.000

90.000

56.000

5.000

5.000

5.000

40.000

35.000

33.000

750

850

1.200

2.000

3.250

38.000

2.500

9.000

9.000

9.000

9.000

9.000

9.000

9.000

9.000

9.000

9.000

9.500

9.500

9.500

10.000

10.000

9.500

17.500

17.000

45.000

1. Tanah Urug/Setempat m³

2. Tanah merah/ yang didatangkan dari luar lokasi m³

3. Pasir urug m³

4. Pasir pasang m³

5. Pasir Beton m³

6. Pasir batu ( sirtu ) m³

7. Batu belah pondasi m³

8. Batu pecah mesin 1/2 m³

9. Batu pecah mesin 2/3 m³

10. Batu pecah mesin 3/5 m³

11. Batu pecah mesin 5/7 m³

12. Batu templek hitam m²

13. Semen Tiga Roda (50 Kg) zak

14. Semen putih kg

15. Semen warna muda kg

16. Semen warna tua kg

17. Lem kuning kg

18. Lem putih fox kg

19. Lem Vinil kg

1. Bata merah bh

2. Batako kecil uk. 10 x 20 x 8 bh

3. Batako besar uk. 20 x 30 x 8 bh

4. Bata terawang / rooster bh

5. Beton rooster, uk. 20 x 20 cm bh

6. Batacote kg

I j u k ( 20 kg / m2 ) kg

1. Besi beton U-24, uk. Dia 8 mm (SII) Kg

2. Besi beton U-24, uk. Dia 10 mm (SII) Kg

3. Besi beton U-24, uk. Dia 12 mm (SII) Kg

4. Besi beton U-24, uk. Dia 16 mm (SII) Kg

5. Besi beton U-24, uk. Dia 19 mm (SII) Kg

6. Besi beton U-24, uk. Dia 22 mm (SII) Kg

7. Besi beton ulir, uk. Dia 12 mm (SII) Kg

8. Besi beton ulir, uk. Dia 16 mm (SII) Kg

9. Besi beton ulir, uk. Dia 19 mm (SII) Kg

10. Besi beton ulir, uk. Dia 22 mm (SII) Kg

11. Besi profil siku, uk. 5 x 5 x 5 (SII) kg

12. Besi profil siku, uk. 3 x 3 x 3 (SII) kg

13. Besi profil IWF, ex DN-SII kg

14. Besi kanal "C" s/d. 150.65.20.3,2 kg

15. Besi kanal "C" 200.75.20.3,2 kg

16. Besi Strip, uk. 3 x 30 mm x 6 m ( 4,21 Kg ) Kg

17. Seng BJLS 0.20, l = 55 cm ( 1 rol = 50 m' ) m'

18. Seng BJLS 0.30, l = 55 cm ( 1 rol = 50 m' ) m'

19. Seng plat BJLS 25 uk. 90 x 180 cm lbr

Page 41: TABEL  RAB john AHS 2012

65.000

40.000

35.000

14.000

30.000

20.000

10.000

8.500

7.500

8.500

25.000

25.000

10.000

75.000

50.000

125.000

60.000

119.000

75.000

35.000

10.000

175.000

55.000

75.000

75.000

75.000

95.000

80.000

3.400

15.000

30.000

35.000

45.000

20.000

12.000

13.000

25.000

25.000

25.000

12.500

20. Seng plat BJLS 30 uk. 90 x 180 cm lbr

21. Seng gelombang BJLS 25 uk. 0.90 x 1.80 m lbr

22. Seng gelombang BJLS 30 uk. 0.90 x 1.80 m lbr

23. Kawat beton kg

1. Engsel pintu nylon besar psg

2. Engsel pintu nylon kecil psg

3. Engsel jendela biasa psg

4. Grendel jendela ( spring knip ) bh

5. Grendel jendela biasa bh

6. Grendel pintu biasa ( selot ) bh

7. Grendel tanam pintu ganda ( espagnolet ) bh

8. Hak angin stainless bh

9. Hak angin kait biasa bh

10. Kunci pintu Union Type besar, 2 slaage bh

11. Kunci pintu Union Type kecil 2 slaage bh

12. Kunci pintu Cap KUDA TERBANG Type besar 2 slaage bh

13. Kunci pintu Cap KUDA TERBANG Type kecil 2 slaage bh

14. Kunci pintu SEIS Type besar bh

15. Kunci pintu SEIS Type kecil bh

16. Kunci pintu KM/WC, ALPHA bh

17. Kunci pintu Lemari bh

18. Rel pintu dorong Marathon ( 1 pintu ) unit

19. Kaca polos 3 mm m²

20. Kaca polos 5 mm m²

21. Kaca raybend 3 mm m²

22. Kaca raybend 5 mm m²

23. Kaca es 3 mm m²

24. Kaca es 5 mm m²

24. Kawat duri ( 1 rol = 25 m' ) m'

25. Kawat raam m²

26. Kawat elektrode kg

27. Almunium plat 0,25 mm ( 1.00 x 2.00 ) lbr

28. Almunium plat 0,30 mm ( 1.00 x 2.00 ) lbr

29. Paku 1 - 3 cm kg

30. Paku uk. 5 - 12 cm kg

31. Paku uk. 7,5 - 15 cm kg

32. Paku seng kg

33. Hak kait asbes 7 cm lengkap bh

34. Paku gipsump ( 20.00 m2 / kg ) kg

35. Paku sekrup bh

1. Kayu balok Albasia uk. 5/7, 5/10, 6/12, 8/12, 8/15 m³ 1,500,000

2. Kayu papan Albasia uk 2/20 m³ 1,500,000

3. Kayu papan Albasia uk 3/30 m³ 1,500,000

4. Kayu balok Borneo 5/7, 5/10, 6/12, 8/12, 8/15 m³ 3,750,000

5. Kayu papan Borneo, uk. 2/20 cm m³ 3,500,000

6. Kayu papan Borneo, uk. 3/30 cm m³ 3,500,000

7. Kayu balok Borneo super ( Meranti ) uk. 5/7, 5/10, 6/12, 8/12, 8/15 m³ 4,250,000

8. Kayu papan Borneo super ( Meranti ) uk. 2/20 cm m³ 4,350,000

9. Kayu papan Borneo super ( Meranti ) uk. 3/30 cm m³ 4,500,000

10. Kayu balok kamper Medan ( kruing ) uk. 5/7, 5/10, 6/12, 8/12, 8/15 m³ 5,250,000

11. Kayu balok kamper Banjar uk. 5/7, 5/10, 6/12, 8/12, 8/15 m³ 6,500,000

12. Kayu papan kamper Banjar, uk. 2/20 cm m³ 7,000,000

Page 42: TABEL  RAB john AHS 2012

1.400

2.900

2.750

1.800

2.750

3.500

5.000

3.000

3.000

2.500

2.500

4.200

6.100

6.600

3.400

5.200

20.500

17.900

40.000

55.000

75.000

107.000

150.000

200.000

235.000

85.000

75.000

75.000

10.000

16.000

55.000

253.000

379.000

14.000

15.000

45.000

47.500

10.000

12.500

15.000

17.500

10.000

10.000

15.000

49.300

42.200

13. Kayu papan kamper Banjar, uk. 3/30 cm m³ 8,000,000

14. Kayu balok kamper Samarinda uk. 5/7, 5/10, 6/12, 8/12, 8/15 m³ 7,975,000

15. Kayu papan kamper Samarinda, uk. 2/20 cm m³ 9,500,000

16. Kayu papan kamper Samarinda, uk. 3/30 cm m³ 9,500,000

1. Genteng kodok natural, ex jatiwangi bh

2. Genteng kodok glazuur, ex jatiwangi bh

3. Genteng palentong natural, ex Jatiwangi bh

4. Genteng palentong glazuur, ex Jatiwangi bh

5. Genteng palentong super / besar natural, ex Jatiwangi bh

6. Genteng palentong super / besar glazuur, ex Jatiwangi bh

7. Genteng beton natural, Rengganis bh

8. Genteng beton warna, Rengganis bh

9. Genteng Morando natural ex Jatiwangi bh

10. Genteng Morando glazuur ex Jatiwangi bh

11. Genteng bubung segi tiga / bulat, natural bh

12. Genteng bubung segi tiga / bulat, glazuur bh

13. Genteng bubung beton natural Rengganis bh

14. Genteng bubung beton warna Rengganis bh

15. Genteng bubung natural Morando bh

16. Genteng bubung glazuur Morando bh

17. Kayu kaso Borneo uk. 5/7 - 4. 00 m' m³ 3,000,000

18. Dolken dia 5 s/d 7 cm btg

19. Dolken dia 8 s/d 10 cm btg

20. Triplek 3 mm, uk. 1,20 x 2,40 lbr

21. Triplek 4 mm, uk. 1,20 x 2,40 lbr

22. Triplex 6 mm, uk. 1,20 x 2,40 lbr

23. Multiplek 9 mm, uk. 1,20 x 2,40 lbr

24. Multiplek 12 mm, uk. 1,20 x 2,40 lbr

25. Multiplek 15 mm, uk. 1,20 x 2,40 lbr

26. Multiplek 18 mm, uk. 1,20 x 2,40 lbr

27. Teakwood 4 mm, uk. 1,20 x 2,40 lbr

28. Melamin 4 mm, uk. 1,20 x 2,40 lbr

29. Formika putih polos, uk. 1,20 x 2,40 lbr

30. Reng uk. 2/3 kayu Borneo Super ( Meranti ) btg

31. Reng uk. 3/4 kayu Borneo Super ( Meranti ) btg

32. Gipsum Jayaboard, uk. 1,20 x 2,40 lbr

33. Dome Gipsump type Merak dia 85 cm lbr

34. Dome Gipsump type Bunga dia 90 cm bh

35. Eternit cap Bola Dunia bh

36. Eternit cap dua gajah lbr

37. Eternit hardflex 3 mm, uk. 1.20 x 2.40 lbr

38. Eternit hardflex 5 mm, uk. 1.20 x 2.40 lbr

39. List profil 2 x 2 cm btg

40. List Profil 1 x 3 cm btg

41. List Profil 1 x 5 cm btg

42. List Kayu 1 x 4 cm btg

43. List Kayu 1 x 5 cm btg

44. List Gipsump 7 cm m'

45. List Gipsump 10 cm m'

1. Keramik dinding 20/25, putih polos, Roman m²

2. Keramik dinding 20/25, putih polos, Mulya m²

Page 43: TABEL  RAB john AHS 2012

45.000

39.000

46.000

28.000

37.000

38.000

59.100

45.000

43.700

42.600

56.700

41.800

35.000

45.000

9.000

17.000

22.500

27.500

50.000

17.000

25.900

34.100

38.000

45.000

38.500

36.000

75.000

35.000

40.000

25.000

45.000

25.000

20.000

50.000

22.500

17.500

30.000

1.000

18.000

13.000

25.000

250.000

27.500

25.000

5.000

10.000

12.000

15.000

62.800

90.400

116.200

222.600

3. Keramik dinding 20/25, warna muda / corak, Roman m²

4. Keramik dinding 20/20, warna muda / corak, Mulya m²

5. Keramik lantai 30 x30, putih polos Roman m²

6. Keramik lantai 30 x30, putih polos Mulya m²

7. Keramik lantai 30 x30, warna polos Roman m²

8. Keramik lantai 30 x30, warna polos Mulya m²

9. Keramik lantai 30 x30 warna muda /corak Roman m²

10. Keramik lantai 30 x30 warna/corak Mulya m²

11. Keramik lantai 20 x 20, warna polos Roman m²

12. Keramik lantai 20 x 20, warna polos Mulya m²

13. Keramik lantai 20 x 20, warna/corak Roman m²

14. Keramik lantai 20 x 20, warna/corak Mulya m²

15. Paving block natural, t = 6 cm. m²

16. Paving block warna, t = 6 cm. m²

17. Kaansteen uk. 6 x 15 x 40 cm bh

18. Kaansteen uk. 10 x 20 x 40 cm bh

19. Kaansteen uk. 15 x 40 x 60 cm bh

20. Kaansteen uk. 17 x 28 x 60 cm bh

1. Cat dasar tembok, Indo 9000 Sealer Water Base kg

2. Cat tembok Sanlex ltr

3. Cat tembok Sanlex Wonder kg

4. Cat tembok Vinilex kg

5. Cat tembok Wiratex kg

6. Cat kayu / besi Seiv kg

7. Cat kayu / besi Avian kg

8. Meni kayu / besi Bola mas kg

9. Cat sinchromate Bola mas kg

10. Plint coat ltr

11. Dempul tembok ( plamuur ) Sanlex kg

12. Dempul kayu cap kucing kg

13. Dempul halus Impra kg

14. Dempul lilin kg

15. Terpentin ( minyak cat ) ltr

16. Solignem ( 1 blek = 10 liter ) ltr

17. Thiner A ltr

18. Thiner B ltr

19. Oker kg

20. Oten ( pewarna plituran ) bks

21. Sirlak ex India kg

22. Spirtus ltr

23. Politur ltr

24. Politur jadi Ultran ltr

25. V e r n i s ltr

26. Kertas amplas kayu / tembok Lbr

27. Kape kayu 2" Bh

28. Kape tembok Bh

29. kwas 3" - 4" Bh

30. Roll cat Bh

1. Pipa hitam klas Medium dia 1 " btg

2. Pipa hitam klas Medium dia 1 1/4 " btg

3. Pipa hitam klas Medium dia 1 1/2 " btg

4. Pipa hitam klas Medium dia 2 " btg

Page 44: TABEL  RAB john AHS 2012

257.400

361.800

389.600

440.000

410.000

5. Pipa hitam klas Medium dia 2 1/2 " btg

6. Pipa hitam klas Medium dia 3 " btg

7. Pipa hitam klas Medium dia 4 " btg

8. Pipa hitam klas Medium dia 5 " btg

9. Pipa hitam klas Medium dia 6 " btg

Page 45: TABEL  RAB john AHS 2012

TABEL 3 TABEL 3

DAFTAR UPAH DAFTAR UPAH

No. Jenis Pekerja Satuan Harga Keterangan No.1 Pekerja terampil hari Rp39,600.00 8 jam kerja 12 Tukang Batu terampil hari Rp49,500.00 8 jam kerja 23 Kepala tukang Batu hari Rp59,400.00 8 jam kerja 34 Tukang Kayu Terampil hari Rp49,500.00 8 jam kerja 45 Kepala tukang Kayu hari Rp59,400.00 8 jam kerja 56 Tukang Cat Terampil hari Rp49,500.00 8 jam kerja 67 Kepala Tukang Cat hari Rp59,400.00 8 jam kerja 78 Tukang Besi Terampil hari Rp49,500.00 8 jam kerja 89 Kepala Tukang Besi hari Rp59,400.00 8 jam kerja 9

10 Tukang Las hari Rp49,500.00 8 jam kerja 1011 Kepala Tukang Las hari Rp59,400.00 8 jam kerja 1112 Pekerja hari Rp39,600.00 8 jam kerja 1213 Pekerja setengah terampil hari Rp30,000.00 8 jam kerja 1314 Mandor hari Rp64,400.00 8 jam kerja 1415 tukang kayu 1/2 terampil hari Rp30,000.00 8 jam kerja 15

16 Tukang besi 1/2 terampil hari Rp30,000.00 8 jam kerja 16

17 Tukang batu 1/2 terampil hari Rp30,000.00 8 jam kerja

Page 46: TABEL  RAB john AHS 2012

TABEL 3

DAFTAR UPAH

Jenis Pekerja Satuan Harga39.600

49.500

59.400

49.500

59.400

49.500

59.400

49.500

59.400

49.500

59.400

49.500

59.400

49.500

59.400

64.400

1. P e k e r j a Oh

2. Tukang Batu Oh

3. Kepala Tukang batu Oh

4. Tukang Kayu Oh

5. Kepala Tukang Kayu Oh

6. Tukang Besi profil / Tukang Las Oh

7. Kepala Tukang Besi Profil / Tukang Las Oh

8. Tukang Besi Beton Oh

9. Kepala Tukang Besi Beton Oh

10. Tukang Cat Oh

11. Kepala Tukang Cat Oh

12. Tukang Gali Oh

13. Kepala Tukang Gali Oh

14. Tukang Pipa Oh

15. Kepala Tukang Pipa Oh

16. M a n d o r Oh

Page 47: TABEL  RAB john AHS 2012

TABEL 4

HARGA PERALATAN

NO JENIS PERALATAN SAT HARGA

1 Palu 0,5 kg bh Rp49,300.00 2 Cangkul bh Rp71,700.00 3 Singkup bh Rp58,900.00 4 Sekrop bh Rp84,500.00 5 Pengki bh Rp2,800.00 6 Linggis bh Rp56,300.00 7 Rol meter 30 meter bh Rp169,000.00 8 Rol meter 5 meter - 10 meter bh Rp56,300.00 9 Slang plastik untuk waterpasss diameter 0,5 cm m' Rp2,000.00 10 Waterpass alumunium 60 cm bh Rp140,800.00

11 Roda dorong bh Rp320,100.00

Page 48: TABEL  RAB john AHS 2012

TABEL 5

ANALISA HARGA SATUAN

No. Uraian Jenis pekerjaan Sat. Koeff.

Harga Sat. Jumlah Harga Jumlah Harga

Bahan / Upah Bahan Upah Bahan + Upah

Rp. Rp. Rp. Rp.

1 2 3 4 5 6 7 8

1. PEKERJAAN PERSIAPAN

1.1 1M2 PEK. PEMBERSIHAN DAN PENGUKURAN KEMBALI (SITE)Pekerja Terampil org 0.020 Rp40,000.00 Rp800.00

Alat Bantu ls 1.000 Rp1,000.00 Rp1,000.00

Tukang Batu Terampil org 0.010 Rp40,000.00 Rp400.00

Jumlah Rp2,200.00 Rp2,200.00

Jumlah Rp2,200.00

No. Uraian Jenis pekerjaan Sat. Koeff.

Harga Sat. Jumlah Harga Jumlah Harga

Bahan / Upah Bahan Upah Bahan + Upah

Rp. Rp. Rp. Rp.

1 2 3 4 5 6 7 8

1.2 1M' PEK. PASANGAN BOUWPLANK

Kayu Borneo Super 0.010 Rp3,232,300.00 Rp32,323.00

Kayu Papan Albasia 0.007 Rp900,000.00 Rp6,300.00

Paku 5-7 kg 0.038 Rp12,900.00 Rp490.20

Ongkos Pasang ls 1.000 Rp2,500.00 Rp2,500.00

Jumlah Rp39,113.20 Rp2,500.00 Rp41,613.20

Jumlah Rp41,613.20

No. Uraian Jenis pekerjaan Sat. Koeff.

Harga Sat. Jumlah Harga Jumlah Harga

Bahan / Upah Bahan Upah Bahan + Upah

Rp. Rp. Rp. Rp.

1 2 3 4 5 6 7 8

1.3 1M2 PEK. DIREKSI KEET

Kayu Borneo Super 0.072 Rp3,232,300.00 Rp232,725.60

Paku kg 0.250 Rp12,900.00 Rp3,225.00

Seng Glb BJLS 25 (80X180)cm lbr 1.100 Rp35,750.00 Rp39,325.00

Tripleks 3mm lbr 0.500 Rp62,100.00 Rp31,050.00

Semen PC Zak 0.100 Rp50,000.00 Rp5,000.00

Pasir Pasang org 0.250 Rp108,000.00 Rp27,000.00

Bata Merah bh 70.000 Rp500.00 Rp35,000.00

Ongkos Pasang ls 1.000 Rp45,000.00 Rp45,000.00

Jumlah Rp373,325.60 Rp45,000.00 Rp418,325.60

Jumlah Rp418,325.60

No. Uraian Jenis pekerjaan Sat. Koeff.

Harga Sat. Jumlah Harga Jumlah Harga

Bahan / Upah Bahan Upah Bahan + Upah

Rp. Rp. Rp. Rp.1 2 3 4 5 6 7 8

1.4 1M2 LOS KERJA /GUDANG

Kayu Borneo Super 0.100 Rp3,232,300.00 Rp323,230.00

Paku kg 0.250 Rp12,900.00 Rp3,225.00

Seng Glb BJLS 25 lbr 1.100 Rp35,750.00 Rp39,325.00

Triplex 3mm lbr 0.500 Rp62,100.00 Rp31,050.00

Ongkos Pasang ls 1.000 Rp2,500.00 Rp2,500.00

Jumlah Rp396,830.00 Rp2,500.00 Rp399,330.00

Jumlah Rp399,330.00

No. Uraian Jenis pekerjaan Sat. Koeff.

Harga Sat. Jumlah Harga Jumlah Harga

Bahan / Upah Bahan Upah Bahan + Upah

Rp. Rp. Rp. Rp.

1 2 3 4 5 6 7 8

1.5. Papan Nama Proyek5 1 M2 PAPAN NAMA PROYEK

Bahanpapan albasia 3/30 M3 0.18 Rp900,000.00 Rp162,000.00

kayu boneo 5/7 m3 0.06 Rp3,232,300.00 Rp193,938.00

Paku biasa 2", 5" Kg 0.25 Rp12,900.00 Rp3,225.00

Cat kayu DULUX,warna standar ltr 0.10 Rp42,000.00 Rp4,200.00

Tenaga KerjaPekerja Oh 0.10 Rp30,000.00 Rp3,000.00

Jumlah Rp363,363.00 Rp3,000.00 Rp 366,363.00

No. Uraian Jenis pekerjaan Sat. Koeff.

Harga Sat. Jumlah Harga Jumlah Harga

Bahan / Upah Bahan Upah Bahan + Upah

Rp. Rp. Rp. Rp.

1 2 3 4 5 6 7 8

1.6 Pembuatan pagar seng gelombang

Kayu Borneo Super 0.036 Rp3,232,300.00 Rp116,362.80

Paku kg 0.020 Rp12,900.00 Rp258.00

Seng Gelombang BJLS 25 lbr 1.430 Rp35,750.00 Rp51,122.50

Pengecatan dg Cat Minyak 2x ltr 1.800 Rp25,350.00 Rp45,630.00

Ongkos Pasang ls 1.000 Rp25,000.00 Rp25,000.00

Jumlah Rp213,373.30 Rp25,000.00 Rp238,373.30

Jumlah Rp238,373.30

NO PEKERJA DAN BAHAN KOEF SAT HARGA SATUAN JUMLAH HARGA JUMLAH HARGA

BAHAN UPAH BAHAN UPAH BAHAN+UPAH

1 2 3 4 5 6 7 8 9

m3

m3

m3

m3

m3

Page 49: TABEL  RAB john AHS 2012

2. PEKERJAAN TANAH

2.1 1 M3 PEK.GALIAN TANAH PONDASI Pekerja Setengah Terampil 0.400 org Rp35,000.00 Rp14,000.00

Mandor 0.040 org Rp45,000.00 Rp1,800.00

Alat Bantu 1.000 LS Rp1,000.00 Rp1,000.00

Jumlah Rp16,800.00 Rp16,800.00

Jumlah Rp16,800.00

NO PEKERJA DAN BAHAN KOEF SAT HARGA SATUAN JUMLAH HARGA JUMLAH HARGA

BAHAN UPAH BAHAN UPAH BAHAN+UPAH

1 2 3 4 5 6 7 8 9

2.2 1M3 URUGAN PASIR BAWAH PONDASI

Pasir Urug 1.20 Rp90,000.00 Rp108,000.00

Pekerja 0.15 org Rp30,000.00 Rp4,500.00

Mandor 0.05 org Rp45,000.00 Rp2,250.00

Alat Bantu (Stample) 1.00 ls Rp1,000.00 Rp1,000.00

Jumlah Rp108,000.00 Rp7,750.00 Rp115,750.00

Jumlah Rp115,750.00

NO PEKERJA DAN BAHAN KOEF SAT HARGA SATUAN JUMLAH HARGA JUMLAH HARGA

BAHAN UPAH BAHAN UPAH BAHAN+UPAH

1 2 3 4 5 6 7 8 9

2.3 1M3 URUGAN KEMBALI TANAH Pekerja Terampil 0.192 org Rp40,000.00 Rp7,680.00

Mandor 0.400 org Rp45,000.00 Rp18,000.00

Alat Bantu 1.000 ls Rp1,000.00 Rp1,000.00

Jumlah Rp26,680.00 Rp26,680.00

Jumlah Rp26,680.00

NO PEKERJA DAN BAHAN KOEF SAT HARGA SATUAN JUMLAH HARGA JUMLAH HARGA

BAHAN UPAH BAHAN UPAH BAHAN+UPAH

1 2 3 4 5 6 7 8 9

3. PEKERJAAN PONDASI

3.1.1 1M3 PASANGAN ANSTAMPING BATU BELAH

Batu Kali 1.20 Rp102,500.00 Rp123,000.00

Pekerja 1.50 org Rp30,000.00 Rp45,000.00

Pasir Urug 0.40 Rp90,000.00 Rp36,000.00

Tukang Batu 1/2 Terampil 0.75 org Rp30,000.00 Rp22,500.00

Kep. Tukang Batu 0.01 org Rp42,500.00 Rp425.00

Mandor 0.08 org Rp45,000.00 Rp3,375.00

Jumlah Rp159,000.00 Rp71,300.00 Rp230,300.00

Jumlah Rp230,300.00

NO PEKERJA DAN BAHAN KOEF SAT HARGA SATUAN JUMLAH HARGA JUMLAH HARGA

BAHAN UPAH BAHAN UPAH BAHAN+UPAH

1 2 3 4 5 6 7 8 9

3.1 1 M3 PONDASI BATU KALI 1 : 5

Batu Kali 1.20 Rp102,500.00 Rp123,000.00

PC (50kg) 2.16 zak Rp50,000.00 Rp108,000.00

Pasir Pasang 0.43 Rp108,000.00 Rp46,440.00

Pekerja 3.00 org Rp30,000.00 Rp90,000.00

Tk. Batu Terampil 1.50 org Rp40,000.00 Rp60,000.00

Kep. Tukang Batu 0.15 org Rp42,500.00 Rp6,375.00

Mandor 0.05 org Rp45,000.00 Rp2,250.00

Jumlah Rp277,440.00 Rp158,625.00 Rp436,065.00

Jumlah Rp436,065.00

* 1 M3 PEK.GALIAN TANAH PONDASI SETEMPATPekerja Setengah Terampil 0.400 org Rp35,000.00 Rp14,000.00

Mandor 0.040 org Rp45,000.00 Rp1,800.00

Alat Bantu 1.000 LS Rp1,000.00 Rp1,000.00

Jumlah Rp-00 Rp16,800.00 Rp16,800.00

Jumlah Rp16,800.00

NO PEKERJA DAN BAHAN KOEF SAT HARGA SATUAN JUMLAH HARGA JUMLAH HARGA

BAHAN UPAH BAHAN UPAH BAHAN+UPAH

1 2 3 4 5 6 7 8 9

3.2 PONDASI TELAPAK SETEMPAT TIPE P1* 1 M3 COR BETON SITE MIX K-225

Semen PC (50 Kg) 7.90 zak Rp50,000.00 Rp394,800.00

Batu Pecah Mesin 2/3 0.81 Rp153,500.00 Rp124,335.00

Pasir Beton 0.49 Rp138,500.00 Rp67,865.00

Pekerja 3.00 org Rp30,000.00 Rp90,000.00

Tk Batu 1/2 Terampil 0.50 org Rp30,000.00 Rp15,000.00

Kepala Tk. Batu 0.05 org Rp42,500.00 Rp2,125.00

Mandor 0.01 org Rp45,000.00 Rp450.00

Jumlah Rp587,000.00 Rp107,575.00 Rp694,575.00

Jumlah Rp694,575.00

* 1 M2 BEKISTING DENGAN PAPAN

Kaso 5/7 borneo 0.02 Rp3,232,300.00 Rp27,474.55

Papan Terentang 0.02 Rp1,800,000.00 Rp32,400.00

Paku 0.40 kg Rp12,900.00 Rp5,160.00

Pekerja 0.12 org Rp30,000.00 Rp3,600.00

Tk. Kayu 1/2 terampil 0.15 org Rp30,000.00 Rp4,500.00

Kepala Tk. Kayu 0.15 org Rp45,000.00 Rp6,750.00

Mandor 0.05 org Rp45,000.00 Rp2,250.00

Tk .Kayu 1/2 terampil (bongkar cetakan) 0.12 org Rp30,000.00 Rp3,600.00

m3

m3

m3

m3

m3

m3

m3

m3

m3

Page 50: TABEL  RAB john AHS 2012

Jumlah Rp65,034.55 Rp20,700.00 Rp85,734.55

Jumlah Rp85,734.55

* 1 KG BESI BETON TERPASANG U-24Besi Beton Rata-rata 1.05 Kg Rp9,300.00 Rp9,765.00

Kawat Beton 0.01 Kg Rp17,700.00 Rp177.00

Peralatan Spenser 1.00 ls Rp225.00 Rp225.00

Tk. Besi Beton 1/2 Terampil 0.03 org Rp30,000.00 Rp750.00

Tk. Besi Beton Terampil 0.02 org Rp42,500.00 Rp637.50

Kepala Tk. Besi Beton 0.01 org Rp45,000.00 Rp495.00

Mandor 0.01 org Rp45,000.00 Rp225.00

Jumlah Rp10,167.00 Rp2,107.50 Rp12,274.50

Jumlah Rp12,274.50

NO PEKERJA DAN BAHAN KOEF SAT HARGA SATUAN JUMLAH HARGA JUMLAH HARGA

BAHAN UPAH BAHAN UPAH BAHAN+UPAH

1 2 3 4 5 6 7 8 9

3.1 1 BUAH PONDASI TELAPAK SETEMPAT TIPE P1

Cor Beton 0.26 Rp587,000.00 Rp107,575.00 Rp153,940.75 Rp28,211.54 Rp182,152.29

Bekisting 0.95 m2 Rp65,034.55 Rp20,700.00 Rp61,457.65 Rp19,561.50 Rp81,019.15

Besi Tulangan 44.68 Kg Rp10,167.00 Rp2,107.50 Rp454,281.89 Rp94,167.32 Rp548,449.21

Jumlah Biaya Pekerjaan 1 buah Pond Telapak Setempat Rp669,680.29 Rp141,940.36 Rp811,620.65

3.2 PONDASI TELAPAK SETEMPAT TIPE P2* 1 M3 COR BETON SITE MIX K-225

Semen PC (50 Kg) 7.90 zak Rp50,000.00 Rp394,800.00

Batu Pecah Mesin 2/3 0.81 Rp153,500.00 Rp124,335.00

Pasir Beton 0.49 Rp138,500.00 Rp67,865.00

Pekerja 3.00 org Rp30,000.00 Rp90,000.00

Tk Batu 1/2 Terampil 0.50 org Rp30,000.00 Rp15,000.00

Kepala Tk. Batu 0.05 org Rp42,500.00 Rp2,125.00

Mandor 0.01 org Rp45,000.00 Rp450.00

Jumlah Rp587,000.00 Rp107,575.00 Rp694,575.00

Jumlah Rp694,575.00

* 1 M2 BEKISTING DENGAN PAPAN

Kaso 5/7 borneo 0.02 Rp3,232,300.00 Rp27,474.55

Papan Terentang 0.02 Rp1,800,000.00 Rp32,400.00

Paku 0.40 kg Rp12,900.00 Rp5,160.00

Pekerja 0.12 org Rp30,000.00 Rp3,600.00

Tk. Kayu 1/2 terampil 0.15 org Rp30,000.00 Rp4,500.00

Kepala Tk. Kayu 0.15 org Rp45,000.00 Rp6,750.00

Mandor 0.05 org Rp45,000.00 Rp2,250.00

Tk .Kayu 1/2 terampil (bongkar cetakan) 0.12 org Rp30,000.00 Rp3,600.00

Jumlah Rp65,034.55 Rp20,700.00 Rp85,734.55

Jumlah Rp85,734.55

* 1 KG BESI BETON TERPASANG U-24Besi Beton Rata-rata 1.05 Kg Rp9,300.00 Rp9,765.00

Kawat Beton 0.01 Kg Rp17,700.00 Rp177.00

Peralatan Spenser 1.00 ls Rp225.00 Rp225.00

Tk. Besi Beton 1/2 Terampil 0.03 org Rp30,000.00 Rp750.00

Tk. Besi Beton Terampil 0.02 org Rp42,500.00 Rp637.50

Kepala Tk. Besi Beton 0.01 org Rp45,000.00 Rp495.00

Mandor 0.01 org Rp45,000.00 Rp225.00

Jumlah Rp10,167.00 Rp2,107.50 Rp12,274.50

Jumlah Rp12,274.50

NO PEKERJA DAN BAHAN KOEF SAT HARGA SATUAN JUMLAH HARGA JUMLAH HARGA

BAHAN UPAH BAHAN UPAH BAHAN+UPAH

1 2 3 4 5 6 7 8 9

3.2 1 BUAH PONDASI TELAPAK SETEMPAT TIPE P2

Cor Beton 0.12 Rp587,000.00 Rp107,575.00 Rp68,825.75 Rp12,613.17 Rp81,438.92

Bekisting 0.95 m2 Rp65,034.55 Rp20,700.00 Rp61,457.65 Rp19,561.50 Rp81,019.15

Besi Tulangan 31.11 Kg Rp10,167.00 Rp2,107.50 Rp316,290.29 Rp65,563.27 Rp381,853.56

Jumlah Biaya Pekerjaan 1 buah Pond Telapak Setempat Rp446,573.69 Rp97,737.94 Rp544,311.63

NO PEKERJA DAN BAHAN KOEF SAT HARGA SATUAN JUMLAH HARGA JUMLAH HARGA

BAHAN UPAH BAHAN UPAH BAHAN+UPAH

1 2 3 4 5 6 7 8 9

4. PEKERJAAN BETON

* 1 M3 COR BETON SITE MIX K-225Semen PC (50 Kg) 8.90 zak Rp50,000.00 Rp445,000.00 Rp445,000.00

Batu Pecah Mesin 2/3 0.12 Rp140,000.00 Rp16,800.00 Rp16,800.00

Pasir Beton 0.49 Rp138,500.00 Rp67,865.00 Rp67,865.00

Pekerja 3.00 org Rp30,000.00 Rp90,000.00 Rp90,000.00

Tk Batu 1/2 Terampil 0.50 org Rp30,000.00 Rp15,000.00 Rp15,000.00

Kepala Tk. Batu 0.05 org Rp42,500.00 Rp2,125.00 Rp2,125.00

Mandor 0.01 org Rp45,000.00 Rp450.00 Rp450.00

Jumlah Rp529,665.00 Rp107,575.00 Rp637,240.00

Jumlah Rp637,240.00

* 1 M2 BEKISTING DENGAN PAPAN

Kaso 5/7 borneo (2x Pakai) 50% 0.02 Rp3,232,300.00 Rp54,949.10 Rp54,949.10

Papan Terentang (2x Pakai) 75% 0.02 Rp1,800,000.00 Rp43,200.00 Rp43,200.00

Paku 0.40 kg Rp12,900.00 Rp5,160.00 Rp5,160.00

Pekerja 0.12 org Rp30,000.00 Rp3,600.00 Rp3,600.00

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

Page 51: TABEL  RAB john AHS 2012

Tk. Kayu 1/2 terampil 0.15 org Rp30,000.00 Rp4,500.00 Rp4,500.00

Kepala Tk. Kayu 0.15 org Rp45,000.00 Rp6,750.00 Rp6,750.00

Mandor 0.05 org Rp45,000.00 Rp2,250.00 Rp2,250.00

Tk .Kayu 1/2 terampil (bongkar cetakan) 0.12 org Rp30,000.00 Rp3,600.00 Rp3,600.00

Jumlah Rp103,309.10 Rp20,700.00 Rp124,009.10

Jumlah Rp124,009.10

* 1 KG BESI BETON TERPASANG U-24Besi Beton Rata-rata 1.05 Kg Rp9,300.00 Rp9,765.00 Rp9,765.00

Kawat Beton 0.01 Kg Rp17,700.00 Rp177.00 Rp177.00

Peralatan Spenser 1.00 ls Rp225.00 Rp225.00 Rp225.00

Tk. Besi Beton 1/2 Terampil 0.03 org Rp30,000.00 Rp750.00 Rp750.00

Tk. Besi Beton Terampil 0.02 org Rp42,500.00 Rp637.50 Rp637.50

Kepala Tk. Besi Beton 0.01 org Rp45,000.00 Rp495.00 Rp495.00

Mandor 0.01 org Rp45,000.00 Rp225.00 Rp225.00

Jumlah Rp10,167.00 Rp2,107.50 Rp12,274.50

Jumlah Rp12,274.50

* 1 M2 PAS. BEKISTING DENGAN MULTIPLEX 9MMMultiplex 9 mm 0.35 lbr Rp146,200.00 Rp50,731.40 Rp50,731.40

Kaso-kaso Borneo 0.02 Rp3,232,300.00 Rp54,949.10 Rp54,949.10

Paku 0.40 kg Rp12,900.00 Rp5,160.00 Rp5,160.00

Pekerja 0.12 org Rp30,000.00 Rp3,600.00 Rp3,600.00

Tk.kayu 1/2 terampil 0.15 org Rp30,000.00 Rp4,500.00 Rp4,500.00

Kepala tukang kayu 0.15 org Rp45,000.00 Rp6,750.00 Rp6,750.00

Mandor 0.05 org Rp45,000.00 Rp2,250.00 Rp2,250.00

Tk.kayu 1/2 terampil (bongkar cetakan) 0.12 org Rp30,000.00 Rp3,600.00 Rp3,600.00

Jumlah Rp110,840.50 Rp20,700.00 Rp131,540.50

Jumlah Rp131,540.50

NO PEKERJA DAN BAHAN KOEF SAT HARGA SATUAN JUMLAH HARGA JUMLAH HARGA

BAHAN UPAH BAHAN UPAH BAHAN+UPAH

1 2 3 4 5 6 7 8 9

4. PEKERJAAN BETON

4.1 1 M3 SLOOF BETON BERTULANG K-225 15/30

COOR BETON K-225 1.00 Rp529,665.00 Rp107,575.00 Rp529,665.00 Rp107,575.00 Rp637,240.00

BEKISTING DENGAN PAPAN 10.57 Rp103,309.10 Rp20,700.00 Rp1,092,421.42 Rp218,888.01 Rp1,311,309.43

BESI TERPASANG U-24 38.65 kg Rp10,167.00 Rp2,107.50 Rp392,974.88 Rp81,459.09 Rp474,433.97

JUMLAH Rp2,015,061.30 Rp407,922.10 Rp2,422,983.40

NO PEKERJA DAN BAHAN KOEF SAT HARGA SATUAN JUMLAH HARGA JUMLAH HARGA

BAHAN UPAH BAHAN UPAH BAHAN+UPAH

1 2 3 4 5 6 7 8 9

PEKERJAAN KOLOM4.2 1 M3 KOLOM STRUKTUR BETON BERTULANG K-225 15/30

COOR BETON K-225 1.00 Rp529,665.00 Rp107,575.00 Rp529,665.00 Rp107,575.00 Rp637,240.00

BEKISTING DENGAN MULTIPLEK 20.00 Rp110,840.50 Rp20,700.00 Rp2,216,810.00 Rp414,000.00 Rp2,630,810.00

BESI TERPASANG U24 210.32 kg Rp10,167.00 Rp2,107.50 Rp2,138,323.44 Rp443,249.40 Rp2,581,572.84

JUMLAH Rp4,884,798.44 Rp964,824.40 Rp5,849,622.84

NO PEKERJA DAN BAHAN KOEF SAT HARGA SATUAN JUMLAH HARGA JUMLAH HARGA

BAHAN UPAH BAHAN UPAH BAHAN+UPAH

1 2 3 4 5 6 7 8 9

4.2 1 M3 KOLOM BETON BERTULANG K-225 15/15

COOR BETON K-225 1.00 Rp529,665.00 Rp107,575.00 Rp529,665.00 Rp107,575.00 Rp637,240.00

BEKISTING DENGAN PAPAN 26.67 Rp103,309.10 Rp20,700.00 Rp2,755,253.70 Rp552,069.00 Rp3,307,322.70

BESI TERPASANG U24 299.15 kg Rp10,167.00 Rp2,107.50 Rp3,041,437.72 Rp630,454.41 Rp3,671,892.13

JUMLAH Rp6,326,356.41 Rp1,290,098.41 Rp7,616,454.82

NO PEKERJA DAN BAHAN KOEF SAT HARGA SATUAN JUMLAH HARGA JUMLAH HARGA

BAHAN UPAH BAHAN UPAH BAHAN+UPAH

1 2 3 4 5 6 7 8 9

4.3 1 M3 RING BALK BETON BERTULANG K-225 15/20

COOR BETON K-225 1.00 Rp529,665.00 Rp107,575.00 Rp529,665.00 Rp107,575.00 Rp637,240.00

BEKISTING DENGAN PAPAN 14.48 Rp103,309.10 Rp20,700.00 Rp1,495,812.46 Rp299,715.30 Rp1,795,527.76

BESI TERPASANG U24 116.77 kg Rp10,167.00 Rp2,107.50 Rp1,187,231.09 Rp246,099.10 Rp1,433,330.19

JUMLAH Rp3,212,708.55 Rp653,389.40 Rp3,866,097.95

NO PEKERJA DAN BAHAN KOEF SAT HARGA SATUAN JUMLAH HARGA JUMLAH HARGA

BAHAN UPAH BAHAN UPAH BAHAN+UPAH

1 2 3 4 5 6 7 8 9

4.4 1 M3 BALOK BETON BERTULANG K-225 20/40

COOR BETON K-225 1.00 Rp529,665.00 Rp107,575.00 Rp529,665.00 Rp107,575.00 Rp637,240.00

BEKISTING DENGAN PAPAN 11.99 Rp103,309.10 Rp20,700.00 Rp1,238,469.49 Rp248,151.60 Rp1,486,621.09

BESI TERPASANG U24 33.03 kg Rp10,167.00 Rp2,107.50 Rp335,805.84 Rp69,608.62 Rp405,414.46

JUMLAH Rp2,103,940.33 Rp425,335.22 Rp2,529,275.55

4.4 1 M3 BALOK BETON BERTULANG K-225 25/45COOR BETON K-225 1.00 m3 Rp529,665.00 Rp107,575.00 Rp529,665.00 Rp107,575.00 Rp637,240.00

BEKISTING DENGAN PAPAN 10.28 m2 Rp103,309.10 Rp20,700.00 Rp1,062,430.78 Rp212,878.80 Rp1,275,309.58

BESI TERPASANG U24 48.05 kg Rp10,167.00 Rp2,107.50 Rp488,493.85 Rp101,259.05 Rp589,752.90 JUMLAH Rp2,080,589.63 Rp421,712.85 Rp2,502,302.49

PEKERJA DAN BAHAN KOEF SAT HARGA SATUAN JUMLAH HARGA JUMLAH HARGA

BAHAN UPAH BAHAN UPAH BAHAN+UPAH1 2 3 4 5 6 7 8 9

4.4 1 M3 BALOK BETON BERTULANG K-225 15/25COOR BETON K-225 1.00 m3 Rp529,665.00 Rp107,575.00 Rp529,665.00 Rp107,575.00 Rp637,240.00

m3

m3

m2

m3

m2

m3

m2

m3

m2

m3

m2

Page 52: TABEL  RAB john AHS 2012

BEKISTING DENGAN PAPAN 17.33 m2 Rp103,309.10 Rp20,700.00 Rp1,790,656.63 Rp358,793.10 Rp2,149,449.73

BESI TERPASANG U24 44.40 kg Rp10,167.00 Rp2,107.50 Rp451,404.63 Rp93,570.89 Rp544,975.53

JUMLAH Rp2,771,726.26 Rp559,938.99 Rp3,331,665.26

NO PEKERJA DAN BAHAN KOEF SAT HARGA SATUAN JUMLAH HARGA JUMLAH HARGA

BAHAN UPAH BAHAN UPAH BAHAN+UPAH

1 2 3 4 5 6 7 8 9

4.4 1 M3 BALOK BETON BERTULANG K-225 15/30COOR BETON K-225 1.00 m3 Rp529,665.00 Rp107,575.00 Rp529,665.00 Rp107,575.00 Rp637,240.00

BEKISTING DENGAN PAPAN 16.67 m2 Rp103,309.10 Rp20,700.00 Rp1,722,162.70 Rp345,069.00 Rp2,067,231.70

BESI TERPASANG U24 42.96 kg Rp10,167.00 Rp2,107.50 Rp436,769.24 Rp90,537.15 Rp527,306.38

JUMLAH Rp2,688,596.93 Rp543,181.15 Rp3,231,778.08

PEKERJA DAN BAHAN KOEF SAT HARGA SATUAN JUMLAH HARGA JUMLAH HARGA

BAHAN UPAH BAHAN UPAH BAHAN+UPAH1 2 3 4 5 6 7 8 9

4.4 1 M3 BALOK BETON BERTULANG K-225 15/35COOR BETON K-225 1.00 m3 Rp529,665.00 Rp107,575.00 Rp529,665.00 Rp107,575.00 Rp637,240.00

BEKISTING DENGAN PAPAN 15.94 m2 Rp103,309.10 Rp20,700.00 Rp1,646,747.05 Rp329,958.00 Rp1,976,705.05

BESI TERPASANG U24 41.52 kg Rp10,167.00 Rp2,107.50 Rp422,133.84 Rp87,503.40 Rp509,637.24

JUMLAH Rp2,598,545.89 Rp525,036.40 Rp3,123,582.29

4.4 1 M3 BALOK BETON BERTULANG K-225 15/20COOR BETON K-225 1.00 m3 Rp529,665.00 Rp107,575.00 Rp529,665.00 Rp107,575.00 Rp637,240.00

BEKISTING DENGAN PAPAN 17.50 m2 Rp103,309.10 Rp20,700.00 Rp1,807,909.25 Rp362,250.00 Rp2,170,159.25

BESI TERPASANG U24 46.82 kg Rp10,167.00 Rp2,107.50 Rp475,968.11 Rp98,662.61 Rp574,630.72

JUMLAH Rp2,813,542.36 Rp568,487.61 Rp3,382,029.97

4.4 1 M3 BALOK BETON BERTULANG anak K-225 15/20COOR BETON K-225 1.00 m3 Rp529,665.00 Rp107,575.00 Rp529,665.00 Rp107,575.00 Rp637,240.00

BEKISTING DENGAN PAPAN 18.33 m2 Rp103,309.10 Rp20,700.00 Rp1,893,655.80 Rp379,431.00 Rp2,273,086.80

BESI TERPASANG U24 47.83 kg Rp10,167.00 Rp2,107.50 Rp486,257.11 Rp100,795.40 Rp587,052.51

JUMLAH Rp2,909,577.91 Rp587,801.40 Rp3,497,379.31

PEKERJA DAN BAHAN KOEF SAT HARGA SATUAN JUMLAH HARGA JUMLAH HARGA

BAHAN UPAH BAHAN UPAH BAHAN+UPAH

1 2 3 4 5 6 7 8 9

4.5 1 M3 PLAT LANTAI BETON BERTULANG K-225

COOR BETON K-225 1.00 Rp529,665.00 Rp107,575.00 Rp529,665.00 Rp107,575.00 Rp637,240.00

BEKISTING DENGAN MULTIPLEK 8.67 Rp110,840.50 Rp20,700.00 Rp960,772.10 Rp179,428.84 Rp1,140,200.95

BESI TERPASANG U24 139.29 kg Rp10,167.00 Rp2,107.50 Rp1,416,124.22 Rp293,545.96 Rp1,709,670.18

JUMLAH Rp2,906,561.32 Rp580,549.80 Rp3,487,111.13

PEKERJA DAN BAHAN KOEF SAT HARGA SATUAN JUMLAH HARGA JUMLAH HARGA

BAHAN UPAH BAHAN UPAH BAHAN+UPAH

1 2 3 4 5 6 7 8 9

4.6 1 M3 TANGGA BETON K225

COOR BETON K-225 1.00 Rp529,665.00 Rp107,575.00 Rp529,665.00 Rp107,575.00 Rp637,240.00

BEKISTING DENGAN MULTIPLEK 17.17 Rp110,840.50 Rp20,700.00 Rp1,903,619.08 Rp355,510.08 Rp2,259,129.16

BESI TERPASANG U24 126.12 kg Rp10,167.00 Rp2,107.50 Rp1,282,223.41 Rp265,789.89 Rp1,548,013.30

JUMLAH Rp3,715,507.49 Rp728,874.97 Rp4,444,382.46

No. Uraian Jenis pekerjaan Sat. Koeff.

Harga Sat. Jumlah Harga Jumlah Harga

Bahan / Upah Bahan Upah Bahan + Upah

Rp. Rp. Rp. Rp.

1 2 3 4 5 6 7 8

5 PEKERJAAN DINDING

5.1 1 M² PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC. : 3 PS. ( SNI. Edisi Rev. 2002 )

Bahan : Bata Merah Bh 70 Rp425.00 Rp29,750.00 -

Semen Portland Kg 14.37 Rp850.00 Rp12,214.50 -

Pasir Pasang M³ 0.04 Rp108,000.00 Rp4,320.00 -

Tenaga Kerja :Pekerja Oh 0.32 Rp30,000.00 - Rp9,600.00

Tukang Batu Oh 0.1 Rp40,000.00 - Rp4,000.00

Kepala Tukang Batu Oh 0.01 Rp42,500.00 - Rp425.00

Mandor Oh 0.015 Rp90,000.00 - Rp1,350.00

Jumlah Rp46,284.50 Rp15,375.00 Rp61,659.50

Dibulatkan Rp61,650.00

5.1 1 M² PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC. : 5 PS. ( SNI. Edisi Rev. 2002 )

Bahan : Bata Merah Bh 70 Rp425.00 Rp29,750.00 -

Semen Portland Kg 9.68 Rp850.00 Rp8,228.00 -

Pasir Pasang M³ 0.045 Rp108,000.00 Rp4,860.00 -

Tenaga Kerja :Pekerja Oh 0.32 Rp30,000.00 - Rp9,600.00

Tukang Batu Oh 0.1 Rp40,000.00 - Rp4,000.00

Kepala Tukang Batu Oh 0.01 Rp42,500.00 - Rp425.00

Mandor Oh 0.015 Rp90,000.00 - Rp1,350.00

Jumlah Rp42,838.00 Rp15,375.00 Rp58,213.00

Dibulatkan Rp58,210.00

No. Uraian Jenis pekerjaan Sat. Koeff.

Harga Sat. Jumlah Harga Jumlah Harga

Bahan / Upah Bahan Upah Bahan + Upah

Rp. Rp. Rp. Rp.

1 2 3 4 5 6 7 8

5.2 1M2 PLESTERAN DINDING + ACIAN

m3

m2

m3

m2

Page 53: TABEL  RAB john AHS 2012

PC (50kg) zak 0.1 Rp44,000.00 Rp4,400.00

Pasir Pasang m3 0.019 Rp108,000.00 Rp2,052.00

Pekerja Terampil org 0.35 Rp35,000.00 Rp12,250.00

Tk. Batu Terampil org 0.24 Rp40,000.00 Rp7,200.00

Kep. Tukang Batu org 0.021 Rp42,500.00 Rp630.00

Mandor org 0.01 Rp90,000.00 Rp450.00

Jumlah Rp6,452.00 Rp20,530.00 Rp 26,982.00

No. Uraian Jenis pekerjaan Sat. Koeff.

Harga Sat. Jumlah Harga Jumlah Harga

Bahan / Upah Bahan Upah Bahan + Upah

Rp. Rp. Rp. Rp.

1 2 3 4 5 6 7 8

6 PEKERJAAN KAYU

1 1 M3 PASANGAN KUSEN PINTU & JENDELA, (SNI. Edisi Rev. 2002)

Bahan :Kayu kamper, Balok M3 1.1 Rp3,232,300.00 Rp3,555,530.00

Paku Kg 2.5 Rp12,900.00 Rp32,250.00

Lem kayu Fox Kg 1 Rp14,800.00 Rp14,800.00

Tenaga Kerja:Pekerja Oh 6 Rp30,000.00 Rp180,000.00

Tukang Kayu Oh 20 Rp42,500.00 Rp850,000.00

Kepala Tukang Kayu Oh 2 Rp45,000.00 Rp90,000.00

Mandor Oh 0.3 Rp90,000.00 Rp27,000.00

Jumlah Rp3,602,580.00 Rp1,147,000.00 Rp4,749,580.00

Dibulatkan Rp4,749,580.00

2 1M2 PASANG PINTU PANIL , KAYU kamper

Bahan :Kayu kamper, Papan M3 0.04 Rp3,232,300.00 Rp129,292.00

List kayukamper Profil M1 4 Rp7,500.00 Rp30,000.00

Lem kayu Fox Kg 0.75 Rp14,800.00 Rp11,100.00

Tenaga Kerja:Pekerja Oh 1 Rp30,000.00 Rp30,000.00

Tukang Kayu Oh 2.5 Rp42,500.00 Rp106,250.00

Kepala Tukang Kayu Oh 0.25 Rp45,000.00 Rp11,250.00

Mandor Oh 0.05 Rp90,000.00 Rp4,500.00

Jumlah Rp170,392.00 Rp152,000.00 Rp322,392.00 Dibulatkan Rp322,390.00

3 1 M2 DAUN JENDELA KACA (TANPA KACA )

Bahan :

Rangka Kayu Borneo m3 0.017 Rp3,232,300.00 Rp54,949.10

Lem Putih Fox kg 0.3 Rp14,800.00 Rp4,440.00

List Kayu 1 x 2 cm m3 4 Rp2,200.00 Rp8,800.00

Tenaga Kerja :

Pekerja org 0.3 Rp30,000.00 Rp9,000.00

Tukang Kayu org 1.2 Rp42,500.00 Rp51,000.00

Kepala Tukang Kayu org 0.12 Rp45,000.00 Rp5,400.00

Mandor org 0.012 Rp90,000.00 Rp1,080.00

Jumlah Rp68,189.10 Rp66,480.00 Rp134,669.10

Dibulatkan Rp134,660.00

4 1 M2 PASANGAN KACA, T= 5 MM (SNI. EDISI REV. 2002)

Bahan: Kaca M2 1.1 Rp86,900.00 Rp95,590.00

Tenaga Kerja:Pekerja Oh 0.02 Rp30,000.00 . Rp600.00

Tukang Kayu Oh 0.15 Rp42,500.00 . Rp6,375.00

Kepala Tukang Kayu Oh 0.02 Rp45,000.00 . Rp900.00

Mandor Oh 0.0008 Rp45,000.00 . Rp36.00

Jumlah Rp95,590.00 Rp7,911.00 Rp103,501.00

Dibulatkan Rp103,500.00

No. Uraian Jenis pekerjaan Sat. Koeff.Harga Sat. Jumlah Harga Jumlah Harga Bahan / Upah Bahan Upah Bahan + UpahRp. Rp. Rp. Rp.

1 2 3 4 5 6 7 8

1 BUAH PASANG ENGSEL PINTU ( SNI. Edisi Rev .2002)

Bahan :Engsel pintu lbr 1 Rp6,500.00 Rp6,500.00 -

Tenaga kerja:Pekerja Oh 0.015 Rp30,000.00 - Rp450.00

Tukang kayu Oh 0.15 Rp42,500.00 - Rp6,375.00

Kepala tukang kayu Oh 0.015 Rp45,000.00 - Rp675.00

Mandor Oh 0.0008 Rp90,000.00 - Rp72.00

Jumlah Rp6,500.00 Rp7,572.00 Rp14,072.00

dibulatkan Rp14,070.00

1 BUAH PASANG ENGSEL JENDELA KUPU-KUPU (SNI. Edisi Rev. 2002)

Bahan :Engsel jendela Bh 1 Rp6,500.00 Rp6,500.00 -

Tenaga Kerja :Pekerja Oh 0.01 Rp30,000.00 - Rp300.00

Tukang kayu Oh 0.1 Rp42,500.00 - Rp4,250.00

Kepala tukang kayu Oh 0.01 Rp45,000.00 - Rp450.00

Mandor Oh 0.0005 Rp90,000.00 - Rp45.00

Jumlah Rp6,500.00 Rp5,045.00 Rp11,545.00

dibulatkan Rp11,540.00

Page 54: TABEL  RAB john AHS 2012

1 BUAH PASANG KUNCI TANAM BIASA ( SNI. Edisi Rev. 2002)

Bahan :Kunci tanam biasa Bh 1 Rp67,500.00 Rp67,500.00 -

Tenaga kerja :Pekerja Oh 0.01 Rp30,000.00 - Rp300.00

Tukang kayu Oh 0.5 Rp42,500.00 - Rp21,250.00

Kepala tukang kayu Oh 0.01 Rp45,000.00 - Rp450.00

Mandor Oh 0.005 Rp90,000.00 - Rp450.00

Jumlah Rp67,500.00 Rp22,450.00 Rp89,950.00

dibulatkan Rp89,950.00

1 BUAH PASANG KUNCI TANAM KAMAR MANDI (SNI. Edisi Rev, 2002)

Bahan :Kunci Tanam Kamar Mandi Bh 1 Rp90,000.00 Rp90,000.00 -

Tenaga Kerja :Pekerja Oh 0.005 Rp30,000.00 - Rp150.00

Tukang Kayu Oh 0.5 Rp42,500.00 - Rp21,250.00

Kepala Tukang Kayu Oh 0.005 Rp45,000.00 - Rp225.00

Mandor Oh 0.0025 Rp90,000.00 - Rp225.00

Jumlah Rp90,000.00 Rp21,850.00 Rp111,850.00

Dibulatkan Rp111,850.00

1 BUAH PASANG KUNCI SELOT (SNI. Edisi Rev. 2002)

Bahan :Kunci selot Bh 1 Rp7,500.00 Rp7,500.00 -

Tenaga Kerja :Pekerja Oh 0.02 Rp30,000.00 - Rp600.00

Tukang kayu Oh 0.2 Rp42,500.00 - Rp8,500.00

Kepala tukang kayu Oh 0.02 Rp45,000.00 - Rp900.00

Mandor Oh -00 Rp90,000.00 - Rp45.00

Jumlah Rp7,500.00 Rp10,045.00 Rp17,545.00

dibulatkan Rp17,540.00

No. Uraian Jenis pekerjaan Sat. Koeff.

Harga Sat. Jumlah Harga Jumlah Harga

Bahan / Upah Bahan Upah Bahan + Upah

Rp. Rp. Rp. Rp.

1 2 3 4 5 6 7 8

8. PEKERJAAN LANTAI

8.1 1 M3 URUGAN TANAH DIBAWAH LANTAIPekerja 1/2Terampil org 0.650 Rp35,000.00 Rp22,750.00

Pekerja Terampil org 0.500 Rp40,000.00 Rp20,000.00

Mandor org 0.050 Rp45,000.00 Rp2,250.00

Alat Bantu ls 1.000 Rp1,000.00 Rp1,000.00

Jumlah Rp46,000.00 Rp46,000.00 Jumlah Rp46,000.00

8.2 1 M3 PASIR URUG LANTAIPasir Urug 1.200 Rp90,000.00 Rp108,000.00 Pekerja Terampil org 0.150 Rp40,000.00 Rp6,000.00

Mandor org 0.050 Rp45,000.00 Rp2,250.00

Sewa Alat Pemadat ls 1.000 Rp-00

Jumlah Rp108,000.00 Rp8,250.00 Rp116,250.00

Jumlah Rp116,250.00

No. Uraian Jenis pekerjaan Sat. Koeff.Harga Sat. Jumlah Harga Jumlah Harga Bahan / Upah Bahan Upah Bahan + UpahRp. Rp. Rp. Rp.

1 2 3 4 5 6 7 88.3 1 M2 PASANGAN LANTAI KERAMIK , UK. 30x30 CM ( SNI. Edisi Rev. 2002 )

Bahan :Ubin Keramik, uk. 30x30 cm Bh 11.87 Rp4,490.31 Rp53,299.98 - Semen Portland Kg 11.38 Rp850.00 Rp9,673.00 -

Pasir Pasang M3 0.042 Rp108,000.00 Rp4,536.00 - Semen Warna ( putih ) Kg 1.5 Rp2,000.00 Rp3,000.00 - Tenaga Kerja :Pekerja Oh 0.62 Rp30,000.00 - Rp18,600.00

Tukang Batu Oh 0.35 Rp40,000.00 - Rp14,000.00

Kepala Tukang Batu Oh 0.035 Rp42,500.00 - Rp1,487.50

Mandor Oh 0.03 Rp90,000.00 - Rp2,700.00

Jumlah Rp70,508.98 Rp36,787.50 Rp107,296.48

Dibulatkan Rp107,290.00

No. Uraian Jenis pekerjaan Sat. Koeff.Harga Sat. Jumlah Harga Jumlah Harga Bahan / Upah Bahan Upah Bahan + UpahRp. Rp. Rp. Rp.

1 2 3 4 5 6 7 8

8.4 1 M2 PASANGAN LANTAI KERAMIK , UK. 20x20 CM ( SNI. Edisi Rev. 2002 )

Bahan :Ubin Keramik, uk. 20x20 cm Bh 25 Rp2,144.00 Rp53,600.00 -

Semen Portland Kg 9.3 Rp850.00 Rp7,905.00 -

Pasir Pasang M3 0.018 Rp108,000.00 Rp1,944.00 -

Semen Warna Kg 1.5 Rp6,200.00 Rp9,300.00 -

Tenaga Kerja :Pekerja Oh 0.6 Rp30,000.00 - Rp18,000.00

Tukang Batu Oh 0.45 Rp40,000.00 - Rp18,000.00

Kepala Tukang Batu Oh 0.045 Rp42,500.00 - Rp1,912.50

Mandor Oh 0.03 Rp90,000.00 - Rp2,700.00

Jumlah Rp72,749.00 Rp40,612.50 Rp113,361.50

Dibulatkan Rp113,360.00

m3

Page 55: TABEL  RAB john AHS 2012

No. Uraian Jenis pekerjaan Sat. Koeff.Harga Sat. Jumlah Harga Jumlah Harga Bahan / Upah Bahan Upah Bahan + UpahRp. Rp. Rp. Rp.

9 PEKERJAAN ELEKTRIKAL

1 Lampu TL Bh 1 Rp6,000.00 Rp6,000.00

Kabel m1 41.51 Rp7,000.00 Rp290,570.00

PekerjaOngkos Pasang Oh 1 Rp35,000.00 Rp35,000.00

Jumlah Rp296,570.00 Rp35,000.00 Rp331,570.00

Dibulatkan Rp331,570.00

2 Lampu Taman Bh 1 Rp165,000.00 Rp165,000.00

Kabel m1 8.85 Rp7,000.00 Rp61,950.00

PekerjaOngkos Pasang Oh 1 Rp35,000.00 Rp35,000.00

Jumlah Rp226,950.00 Rp35,000.00 Rp261,950.00

Dibulatkan Rp261,950.00

3 Lampu Gantung Bh 1 Rp145,000.00 Rp145,000.00

Kabel m1 4.38 Rp7,000.00 Rp30,660.00

PekerjaOngkos Pasang Oh 1 Rp45,000.00 Rp45,000.00

Jumlah Rp175,660.00 Rp45,000.00 Rp220,660.00

Dibulatkan Rp220,660.00

4 Saklar Tunggal Bh 1 Rp12,000.00 Rp12,000.00

Kabel m1 12 Rp7,000.00 Rp84,000.00

PekerjaOngkos Pasang Oh 1 Rp25,000.00 Rp25,000.00

Jumlah Rp96,000.00 Rp25,000.00 Rp121,000.00

Dibulatkan Rp121,000.00

5 Sakelar Ganda Bh 1 Rp18,500.00 Rp18,500.00

Kabel m1 14.25 Rp7,000.00 Rp99,750.00

PekerjaOngkos Pasang Oh 1 Rp25,000.00 Rp25,000.00

Jumlah Rp118,250.00 Rp25,000.00 Rp143,250.00

Dibulatkan Rp143,250.00

6 Stop Kontak Bh 1 Rp13,500.00 Rp13,500.00

Kabel m1 13.56 Rp7,000.00 Rp94,920.00

PekerjaOngkos Pasang Oh 1 Rp25,000.00 Rp25,000.00

Jumlah Rp108,420.00 Rp25,000.00 Rp133,420.00

Dibulatkan Rp133,420.00

Sekring Bh 1 Rp105,000.00 Rp105,000.00

7 Sekring Bh 1 105000 105000

PekerjaOngkos Pasang Oh 1 15000 15000

Jumlah 318,420.00 15,000.00 333,420.00

Dibulatkan 333,420.00

Rp333,420.00

8 KWH Bh 1 Rp285,000.00 Rp285,000.00

Kabel m1 5.23 Rp7,000.00 Rp36,610.00

PekerjaOngkos Pasang Oh 1 Rp30,000.00 Rp30,000.00

Jumlah Rp321,610.00 Rp30,000.00 Rp351,610.00

Dibulatkan Rp351,610.00

No. Uraian Jenis pekerjaan Sat. Koeff.Harga Sat. Jumlah Harga Jumlah Harga Bahan / Upah Bahan Upah Bahan + UpahRp. Rp. Rp. Rp.

10 PEKERJAAN SANITASI

1 M3 GALIAN TANAH BIASA KEDALAMAN 1M' ( SNI.edisi Rev. 2002)

Tenaga kerja :Pekerja Oh 0.4 Rp30,000.00 - Rp12,000.00

Mandor Oh 0.04 Rp90,000.00 - Rp3,600.00

Jumlah Rp15,600.00 Rp15,600.00

Dibulatkan Rp15,600.00

1M3 PASANGAN BATU BELAHBatu Belah 1.2 Rp102,500.00 Rp123,000.00

Pasir Urug 0.1 Rp90,000.00 Rp9,000.00

Pekerja org 1.25 Rp30,000.00 Rp37,500.00 Tukang Batu Setengah Terampil org 0.675 Rp35,000.00 Rp23,625.00 Kep. Tukang Batu org 0.2 Rp42,500.00 Rp8,500.00 Mandor org 0.01 Rp90,000.00 Rp900.00 Jumlah Rp132,000.00 Rp70,525.00 Rp202,525.00 Dibulatkan Rp202,520.00

URUGAN PASIR

Bahan :Pasir Urug m3 1.2 Rp90,000.00 Rp108,000.00 -

Tenaga kerja :Pekerja Oh 0.3 Rp30,000.00 - Rp9,000.00

Mandor Oh 0.01 Rp90,000.00 - Rp900.00

m3

m3

Page 56: TABEL  RAB john AHS 2012

Jumlah Rp108,000.00 Rp9,900.00 Rp117,900.00

Dibulatkan Rp117,900.00

1 M3 PASANGAN LAPISAN IJUK ( SNI.edisi Rev. 2002)

Bahan :ijuk m3 1.2 Rp1,600,000.00 Rp1,920,000.00 -

Tenaga kerja :Pekerja Oh 0.15 Rp30,000.00 - Rp4,500.00

Mandor Oh 0.015 Rp90,000.00 - Rp1,350.00

Jumlah Rp1,920,000.00 Rp5,850.00 Rp1,925,850.00

Dibulatkan Rp1,925,850.00

1 M² PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC. : 3 PS. ( SNI. Edisi Rev. 2002 )

Bahan : Bata Merah Bh 70 Rp425.00 Rp29,750.00 -

Semen Portland Kg 14.37 Rp850.00 Rp12,214.50 -

Pasir Pasang M³ 0.04 Rp108,000.00 Rp4,320.00 -

Tenaga Kerja :Pekerja Oh 0.32 Rp30,000.00 - Rp9,600.00

Tukang Batu Oh 0.1 Rp40,000.00 - Rp4,000.00

Kepala Tukang Batu Oh 0.01 Rp42,500.00 - Rp425.00

Mandor Oh 0.02 Rp90,000.00 - Rp1,350.00

Jumlah Rp46,284.50 Rp15,375.00 Rp61,659.50

Dibulatkan Rp61,650.00

1 M2 PLESTERAN DINDING 1PC : 3PS ; TEB. 15 MM (SNI. Edisi Rev. 2002)

Bahan : Semen Portland Kg 6.48 Rp850.00 Rp5,508.00

Pasir Pasang M3 0.019 Rp108,000.00 Rp2,052.00

Tenaga Kerja : Pekerja Oh 0.2 Rp30,000.00 Rp6,000.00

No Uraian Jenis pekerjaan Sat. Koeff.Harga Sat. Jumlah Harga Jumlah Harga Bahan / Upah Bahan Upah Bahan + UpahRp. Rp. Rp. Rp.

1 2 3 4 5 6 7 8

Tukang Batu Oh 0.15 Rp40,000.00 Rp6,000.00

Kepala Tukang Batu Oh 0.015 Rp42,500.00 Rp637.50

Mandor Oh 0.01 Rp90,000.00 Rp900.00

Jumlah Rp7,560.00 Rp13,544.50 Rp21,104.50

Dibulatkan Rp21,100.00

1 KG TULANGAN BETON DENGAN BESI POLOS / ULIR (SNI Edisi Rev. 2002)

Bahan:Besi Beton Polos Kg 1.05 Rp9,300.00 Rp9,765.00 -

Kawat Beton Kg 0.015 Rp17,700.00 Rp265.50 -

Tenaga Kerja:Pekerja Oh 0.007 Rp30,000.00 - Rp210.00

Tukang Batu Oh 0.007 Rp40,000.00 - Rp280.00

Kepala Tukang Batu Oh 0.0007 Rp42,500.00 - Rp29.75

Mandor Oh 0.0003 Rp90,000.00 - Rp27.00

Jumlah Rp10,030.50 Rp546.75 Rp10,577.25

Dibulatkan Rp10,570.00

No Uraian Jenis pekerjaan Sat. Koeff.Harga Sat. Jumlah Harga Jumlah Harga Bahan / Upah Bahan Upah Bahan + UpahRp. Rp. Rp. Rp.

1 2 3 4 5 6 7 8

MEMASANG 1 BUAH KLOSET DUDUK / MONOBLOCK (SNI. Edisi Rev. 2002)

Bahan :Kloset Duduk / Monoblock Bh 1 Rp967,100.00 Rp967,100.00

Perlengkapan (6% x Harga Kloset) Ls 1 Rp58,026.00 Rp58,026.00

Tenaga kerja :Pekerja Oh 3.3 Rp30,000.00 Rp99,000.00

Tukang Batu Oh 1.1 Rp40,000.00 Rp44,000.00

Kepala Tukang Batu Oh -00 Rp42,500.00 Rp-00

Mandor Oh 0.02 Rp90,000.00 Rp1,800.00

Jumlah Rp1,025,126.00 Rp144,800.00 Rp1,169,926.00

Dibulatkan Rp1,169,920.00

MEMASANG 1 BUAH KLOSET JONGKOK PORSELEN (SNI. Edisi Rev. 2002)

Bahan :Kloset Jongkok Porselen Bh 1 Rp335,400.00 Rp335,400.00

Semen Portland Kg 6 Rp850.00 Rp5,100.00

Pasir Pasang Ls 0.01 Rp108,000.00 Rp1,080.00

Tenaga kerja :Pekerja Oh 1 Rp30,000.00 Rp30,000.00

Tukang Batu Oh 1.5 Rp40,000.00 Rp60,000.00

Kepala Tukang Batu Oh 1.5 Rp42,500.00 Rp63,750.00

Mandor Oh 0.16 Rp90,000.00 Rp14,400.00

Jumlah Rp341,580.00 Rp168,150.00 Rp509,730.00

Dibulatkan Rp509,730.00

MEMASANG 1 BUAH BAK MANDI FIBREGLASS, KAP. 0,30 M3 ( SNI. Edisi Rev. 2002)

Bahan :Bak Fibreglass Bh 1 Rp125,000.00 Rp125,000.00

Pelengkapan ( 185 x Harga Bak ) Kg 1 Rp22,500.00 Rp22,500.00

Tenaga Kerja :Pekerja Oh 1.8 Rp30,000.00 Rp54,000.00

Page 57: TABEL  RAB john AHS 2012

Tukang Batu Oh 2.7 Rp40,000.00 Rp108,000.00

Kepala Tukang Batu Oh 0.54 Rp42,500.00 Rp22,950.00

Mandor Oh 0.11 Rp90,000.00 Rp9,900.00

Jumlah Rp147,500.00 Rp194,850.00 Rp342,350.00

Dibulatkan Rp342,350.00

MEMASANG 1 BUAH BAK MANDI FIBREGLASS, KAP. 1,00 M3 ( SNI. Edisi Rev. 2002)

Bahan :Bak Fibreglass Bh 1 Rp150,000.00 Rp150,000.00

Pelengkapan ( 12% x Harga Bak ) Ls 1 Rp18,000.00 Rp18,000.00

Tenaga Kerja :Pekerja Oh 3 Rp30,000.00 Rp90,000.00

Tukang Batu Oh 4.5 Rp40,000.00 Rp180,000.00

Kepala Tukang Batu Oh 0.9 Rp42,500.00 Rp38,250.00

Mandor Oh 0.9 Rp90,000.00 Rp81,000.00

Jumlah Rp168,000.00 Rp389,250.00 Rp557,250.00

Dibulatkan Rp557,250.00

MEMASANG 1 BUAH WASTAFEL ( SNI. Edisi Rev. 2002)

Bahan :Wastafel Bh 1 Rp256,800.00 Rp256,800.00

No Uraian Jenis pekerjaan Sat. Koeff.Harga Sat. Jumlah Harga Jumlah Harga Bahan / Upah Bahan Upah Bahan + UpahRp. Rp. Rp. Rp.

1 2 3 4 5 6 7 8

Perlengkapan ( 12% x Harga Wsatafel ) Ls 1 Rp30,816.00 Rp30,816.00

Semen Portland Kg 6 Rp850.00 Rp5,100.00

Pasir Pasang M3 0.01 Rp10,800.00 Rp108.00

Tenaga Kerja :Pekerja Oh 1.2 Rp30,000.00 Rp36,000.00

Tukang Batu Oh 1.45 Rp40,000.00 Rp58,000.00

Kepala Tukang Batu Oh 0.15 Rp42,500.00 Rp6,375.00

Mandor Oh 0.1 Rp90,000.00 Rp9,000.00

Jumlah Rp292,830.00 Rp109,375.00 Rp402,205.00

Dibulatkan Rp402,200.00

MEMASANG 1 BH. FLOOR DRAIN (SNI Edisi Rev. 2002)

Bahan :Floor Drain Bh 1 Rp25,000.00 Rp25,000.00 -

Tenaga Kerja :Pekerja Oh 0.01 Rp30,000.00 - Rp300.00

Tukang Pipa Oh 0.1 Rp40,000.00 - Rp4,000.00

Kepala Tukang Pipa Oh 0.01 Rp42,500.00 - Rp425.00

Mandor Oh 0.005 Rp90,000.00 - Rp450.00

Jumlah Rp25,000.00 Rp5,175.00 Rp30,175.00

Dibulatkan Rp30,170.00

MEMASANG 1 BH BAK CUCI PIRING STAINLESS STEELBak Cuci Piring Stainless Steel m' 1.00 Rp211,500.00 Rp211,500.00

Water Drain + Asesoris Set 1.00 Rp25,380.00 Rp25,380.00

Pekerja Oh 0.03 Rp30,000.00 Rp900.00

Tukang Pipa Oh 0.30 Rp40,000.00 Rp12,000.00

Kepala Tukang Pipa Oh 0.03 Rp42,500.00 Rp1,275.00

Mandor Oh 0.02 Rp45,000.00 Rp675.00

Jumlah Rp236,880.00 Rp14,850.00 Rp251,730.00

Jumlah Rp251,730.00

MEMASANG 1 BUAH BATH TUBEBarh Tube Bh 1.00 Rp1,500,000.00 Rp1,500,000.00

Perlengkapan ( 20 % x Harga Bath Tube ) Ls 1.00 Rp300,000.00 Rp300,000.00

Tukang Batu Oh 0.75 Rp40,000.00 Rp30,000.00

Kepala Tukang Batu Oh 0.08 Rp42,500.00 Rp3,187.50

Mandor Oh 0.25 Rp45,000.00 Rp11,250.00

Jumlah Rp1,800,000.00 Rp44,437.50 Rp1,844,437.50

Jumlah Rp1,844,500.00

No. Uraian Jenis pekerjaan Sat. Koeff.Harga Sat. Jumlah Harga Jumlah Harga Bahan / Upah Bahan Upah Bahan + UpahRp. Rp. Rp. Rp.

1 2 3 4 5 6 7 8

7 PEKERJAAN ATAP

1 M3 Kuda - Kuda Bahan :Balok kayu borneo super M3 1.1 Rp3,232,300.00 Rp3,555,530.00 -

Besi strip Kg 15 Rp6,050.00 Rp90,750.00 -

Paku biasa 2" . 5" Kg 0.8 Rp12,900.00 Rp10,320.00 -

Tenaga kerja :Pekerja Oh 4 Rp30,000.00 - Rp120,000.00

Tukang kayu Oh 12 Rp42,500.00 - Rp510,000.00

Kepala tukang kayu Oh 1.2 Rp45,000.00 - Rp54,000.00

Mandor Oh 0.2 Rp90,000.00 - Rp18,000.00

Jumlah Rp3,656,600.00 Rp702,000.00 Rp4,358,600.00

dibulatkan Rp4,358,600.00

Pek. Pas. Gording 6/12kayu kamper banjar m3 1.1 Rp4,900,000.00 Rp5,390,000.00

Paku kg 0.128 Rp12,900.00 Rp1,651.20

Pekerja org 0.35 Rp30,000.00 Rp10,500.00

Tukang Kayu Org 0.035 Rp42,500.00 Rp1,487.50

Page 58: TABEL  RAB john AHS 2012

Kep. Tk. Kayu Org 0.015 Rp45,000.00 Rp675.00

Mandor Org 0.005 Rp90,000.00 Rp450.00

Jumlah Rp5,391,651.20 Rp13,112.50 Rp5,404,763.70

Rp5,404,760.00

No. Uraian Jenis pekerjaan Sat. Koeff.Harga Sat. Jumlah Harga Jumlah Harga Bahan / Upah Bahan Upah Bahan + UpahRp. Rp. Rp. Rp.

1 2 3 4 5 6 7 8

Pek. 1 m2 Pas. Rangka Atap (kaso&Reng)Bahan :kayu kamper banjar M3 0.014 Rp4,900,000.00 Rp68,600.00 -

Paku biasa 2" . 5" Kg 0.15 Rp12,900.00 Rp1,935.00 -

Tenaga kerja :Pekerja Oh 0.1 Rp30,000.00 - Rp3,000.00

Tukang kayu Oh 0.1 Rp42,500.00 - Rp4,250.00

Kepala tukang kayu Oh 0.01 Rp45,000.00 - Rp450.00

Mandor Oh 0.005 Rp90,000.00 - Rp450.00

Jumlah Rp70,535.00 Rp8,150.00 Rp78,685.00

dibulatkan Rp78,680.00

No. Uraian Jenis pekerjaan Sat. Koeff.Harga Sat. Jumlah Harga Jumlah Harga Bahan / Upah Bahan Upah Bahan + UpahRp. Rp. Rp. Rp.

1 2 3 4 5 6 7 8

1 M2 PASANG LISPLANK 2 x ( 2 x 20 cm ) , KAYU KAMPER ( SNI.Edisi Rev.2002 )Bahan :Kayu Kamper, Papan M3 0.0086 Rp4,900,000.00 Rp42,570.00 -

Paku biasa 2" - 5" kg 0.06 Rp12,900.00 Rp774.00 -

Tenaga Kerja :Pekerja Oh 0.1 Rp30,000.00 - Rp3,000.00

Tukang Kayu Oh 0.1 Rp42,500.00 - Rp4,250.00

Kepala Tukang Kayu Oh 0.01 Rp45,000.00 - Rp450.00

Mandor Oh 0.05 Rp90,000.00 - Rp2,250.00

Jumlah Rp43,344.00 Rp9,950.00 Rp53,294.00

Dibulatkan Rp53,290.00

No. Uraian Jenis pekerjaan Sat. Koeff.Harga Sat. Jumlah Harga Jumlah Harga Bahan / Upah Bahan Upah Bahan + UpahRp. Rp. Rp. Rp.

1 2 3 4 5 6 7 8

Pek. 1 m" Pas. Papan Ruiter dan Balok BubunganBalok 8/12 Borneo Super 0.010 m3 Rp3,232,300.00 Rp31,030.08

Papan 2/20 Borneo Super 0.004 m3 Rp3,232,300.00 Rp12,929.20

Paku 0.128 Kg Rp9,500.00 Rp1,215.05

Pekerja 0.115 Org Rp30,000.00 Rp3,456.00

Tk.Kayu Terampil 0.346 Org Rp42,500.00 Rp14,688.00

Kep. Tukang Kayu 0.035 Org Rp45,000.00 Rp1,557.00

Mandor 0.006 Org Rp90,000.00 Rp522.00

Jumlah Rp45,174.33 Rp20,223.00 Rp65,397.33

Dibulatkan Rp65,390.00

No. Uraian Jenis pekerjaan Sat. Koeff.Harga Sat. Jumlah Harga Jumlah Harga Bahan / Upah Bahan Upah Bahan + UpahRp. Rp. Rp. Rp.

1 2 3 4 5 6 7 8

1 M2 PASANG ATAP GENTENG KODOK / GLAZUUR ( SNI. Edisi Rev. 2002)Bahan :genteng kodok Bh 25 Rp1,500.00 Rp37,500.00 -

Tenaga Kerja :Pekerja Oh 0.15 Rp30,000.00 - Rp4,500.00

Tukang Kayu Oh 0.075 Rp42,500.00 - Rp3,187.50

Kepala Tukang Kayu Oh 0.008 Rp45,000.00 - Rp360.00

Mandor Oh 0.008 Rp45,000.00 - Rp360.00

Jumlah Rp37,500.00 Rp8,407.50 Rp45,907.50

Keuntungan maksimal 10% Rp4,590.75

Jumlah harga Rp50,498.25

Dibulatkan Rp50,498.00

` Uraian Jenis pekerjaan Sat. Koeff.Harga Sat. Jumlah Harga Jumlah Harga Bahan / Upah Bahan Upah Bahan + UpahRp. Rp. Rp. Rp.

1 2 3 4 5 6 7 8

7.2 PEKERJAAN PLAFOND

1 1 M2 LANGIT - LANGIT GYPSUM (SNI. Edisi Rev. 2002)

Bahan :Gypsum M3 0.375 Rp63,600.00 Rp23,850.00

Paku 1/2" . 1" Kg 0.03 Rp16,500.00 Rp495.00

Tenaga kerja :Pekerja Oh 0.07 Rp30,000.00 Rp2,100.00

Tukang Kayu Oh 0.1 Rp40,000.00 Rp4,000.00

Kepala Tukang Kayu Oh 0.01 Rp42,500.00 Rp425.00

Mandor Oh 0.0035 Rp90,000.00 Rp315.00

Jumlah Rp24,345.00 Rp6,840.00 Rp31,185.00

Dibulatkan Rp31,180.00

No. Uraian Jenis pekerjaan Sat. Koeff.Harga Sat. Jumlah Harga Jumlah Harga Bahan / Upah Bahan Upah Bahan + UpahRp. Rp. Rp. Rp.

1 2 3 4 5 6 7 8

Page 59: TABEL  RAB john AHS 2012

2 1 M2 Pas. Flapond & Rangka Flapond (Borneo Super)

Bahan :Kaso 5/7 Kayu Borneo m3 0.014 Rp3,232,300.00 Rp45,252.20

Reng 3/4 Kayu Borneo m3 0.004 Rp1,900.00 Rp7.60

Paku Kg 0.22 Rp12,900.00 Rp2,838.00

Tenaga KerjaPekerja Org 0.188 Rp30,000.00 Rp5,640.00

Tukang Kayu Org 0.1 Rp42,500.00 Rp4,250.00

Kep. Tk. Kayu Org 0.038 Rp45,000.00 Rp1,710.00

Mandor Org 0.011 Rp90,000.00 Rp990.00

Jumlah Rp48,097.80 Rp12,590.00 Rp60,687.80

Dibulatkan Rp60,680.00

No. Uraian Jenis pekerjaan Sat. Koeff.Harga Sat. Jumlah Harga Jumlah Harga Bahan / Upah Bahan Upah Bahan + UpahRp. Rp. Rp. Rp.

1 2 3 4 5 6 7 8

11 PEKERJAAN PENGECETAN

1 M2 PENGECATAN BIDANG TEMBOK BARU DENGAN SANLEX, 2 X LAPIS CAT PENUTUP (SNI. Edisi Rev. 2002)

Bahan :Plamir kg 0.1 Rp11,700.00 Rp1,170.00 -

Ampelas lbr 0.15 Rp4,000.00 Rp600.00 -

Cat Dasar kg 0.1 Rp17,500.00 Rp1,750.00 -

Cat Penutup 2 x kg 0.26 Rp13,500.00 Rp3,510.00 -

Rol Cat bh 0.01 Rp32,000.00 Rp320.00 -

Tenaga Kerja :Pekerja oh 0.028 Rp30,000.00 - Rp840.00

Tukang Cat oh 0.063 Rp40,000.00 - Rp2,520.00

Kepala tukang Cat oh 0.0063 Rp42,500.00 - Rp267.75

Mandor oh 0.0025 Rp90,000.00 - Rp225.00

Jumlah Rp7,350.00 Rp3,852.75 Rp11,202.75

Dibulatkan Rp11,200.00

1 M2 PENGECATAN PLAFOND BARU DENGAN SANLEX, 2X LAPIS CAT PENUTUP (SNI Edisi Rev. 2002)

Bahan :Plamir Kg 0.1 Rp11,700.00 Rp1,170.00 -

Ampelas Lbr 0.15 Rp4,000.00 Rp600.00 -

Cat Dasar Kg 0.1 Rp17,500.00 Rp1,750.00 -

Cat Penutup, 2x Kg 0.28 Rp13,500.00 Rp3,780.00 -

Rol Cat Bh 0.01 Rp32,000.00 Rp320.00 -

Tenaga Kerja :Pekerja Oh 0.03 Rp30,000.00 - Rp900.00

Tukang Cat Oh 0.075 Rp40,000.00 - Rp3,000.00

Kepala Tukang Cat Oh 0.008 Rp42,500.00 - Rp318.75

Mandor Oh 0.003 Rp90,000.00 - Rp270.00

Jumlah Rp7,620.00 Rp4,488.75 Rp12,108.75

dibulatkan Rp12,100.00

1 M2 PENGECATAN BIDANG KAYU BARU, 3X LAPIS PENUTUP (SNI. Edisi Rev. 2002)

Bahan :

Cat Meni Kg 0.2000 Rp 19,200.00 Rp 3,840.00 -

Plamir Kg 0.1500 Rp 17,000.00 Rp 2,550.00 -

Ampelas Lbr 0.1500 Rp 4,000.00 Rp 600.00 -

Cat Dasar Kg 0.1700 Rp 12,500.00 Rp 2,125.00 -

Cat Penutup, 3x Kg 0.3500 Rp 51,900.00 Rp 18,165.00 -

Kuas bh 0.1000 Rp 12,500.00 Rp 1,250.00

Tenaga Kerja :

Pekerja Oh 0.0700 Rp 30,000.00 - Rp 2,100.00

Tukang Cat Oh 0.1050 Rp 40,000.00 - Rp 4,200.00

Kepala Tukang Cat Oh 0.0040 Rp 42,500.00 - Rp 170.00

Mandor Oh 0.0025 Rp 45,000.00 - Rp 112.50

Jumlah Rp 28,530.00 Rp 6,582.50 Rp 35,112.50

12. PEKERJAAN LAIN - LAIN

12.1 Pegangan Tangga

No Jenis Bahan Bangunan sat harga satuan (Rp)

1 Pegangan tangga ( balustrade ) profil jati m' Rp 107,300.00

Page 60: TABEL  RAB john AHS 2012

850.00 #REF!

138,500.00 #REF!

153,500.00 #REF!

30,000.00 -40,000.00 -42,500.00 -90,000.00 -

#REF!Harga Sat. Jumlah Harga

Bahan / Upah Bahan

Rp. Rp.

5 6

9,300.00 #REF!17,700.00 #REF!

Page 61: TABEL  RAB john AHS 2012

30,000.00 -40,000.00 -42,500.00 -90,000.00 -

#REF!

### #REF! 12,900.00 #REF! 15,000.00 #REF!

30,000.00

42,500.00

45,000.00 90,000.00

#REF!

Page 62: TABEL  RAB john AHS 2012

---

#REF!#REF!#REF!#REF!#REF! #REF!

Jumlah Harga Upah Bahan + UpahRp. Rp.7 8

#REF!

--

#REF!#REF!#REF!#REF!#REF! #REF!

#REF!

#REF!

#REF!

#REF!

#REF!#REF! #REF!

#REF!

I1

Page 63: TABEL  RAB john AHS 2012

No.

1

2

3

Page 64: TABEL  RAB john AHS 2012

`

Page 65: TABEL  RAB john AHS 2012

TABEL 6

DAFTAR VOLUME PEMBANGUNAN RUMAH 2 LANTAI

No. URAIAN PEKERJAAN VOLUME SAT

(a) (b) ( c) (d)

1 PEKERJAAN PERSIAPAN

1.1 Pembersihan dan Pengukuran lapangan 198.000 m21.2 Pemasangan Bouwplank 58.000 m'1.3 Direksi keet 4.000 m21.4 Los Kerja 10.000 m2

1.5 Papan proyek 0.320 m2

1.6 Pagar Proyek 116.000 m'

2 PEKERJAAN TANAH

2.1 Galian Tanah 125.281 m32.2 Urugan Pasir Dibawah 4.314 m3

2.3 Urugan Tanah Kembali 41.760 m3

3 PEKERJAAN PONDASI

3.1 Pas. Aanstamping Batu Belah 14.396 m3Pas. Pondasi Batu Kali 44.663 m3

3.2 Pas. Pondasi Telapak Tipe 1 #NAME? bh

Pas. Pondasi Telapak Tipe 2' #NAME? bh

4 PEKERJAAN BETON

4.1 Sloof Beton Bertulang Type 15/30 6.570 m34.2 Kolom praktis Beton Bertulang 15/15 7.776 m3

Kolom Struktur Beton Bertulang 15/30 7.776 m34.3 Ring Balk Beton Bertulang Type 15/20 0.450 m34.4 Balok Bertulang Type 15/25 0.413 m3

Balok Bertulang Type 15/30 3.150 m3Balok Bertulang Type 15/35 1.995 m3

4.5 Plat Lantai Type 17.100 m3

4.6 Tangga 0.486 m3

5 PEKERJAAN DINDING

5.1 Pasangan Bata Merah 1 : 3 104.54 m25.2 Pasangan Bata Merah 1 :5 742.97 m25.4 Pekerjaan Plesteran 12.71 m2

5.5 Pekerjaan Acian 0.06 m2

6 PEKERJAAN PINTU DAN JENDELA

Pek. Kusen Pintu & Jendela 1.49 m3Pek. Pintu 35.09 m2Pek. Daun Jendela 11.27 m2Pas. Kaca 5 mm polos 12.55 m2Pas. Engsel Pintu 40.00 bhPas. Engsel Jendela Kupu-Kupu 24.00 bhPas. Kunci Tanam Pintu Biasa 28.00 bhPas. Kunci Tanam Km/Wc 2.00 bh

Pas. Kunci Selot 30.00 bh

7 PEKERJAAN ATAP

Page 66: TABEL  RAB john AHS 2012

7.1 Pemasangan Kuda - Kuda 19.129 m3Pemasangan Gording 6/12 0.223 m3Pemasangan Rangka Atap (kaso & reng) 0.665 m3Pemasangan List Plank 2 x ( 2x 20 cm) 0.228 m3Pemasangan Papan Ruiter dan balok Bubungan 0.174 m3

Pemasangan Atap Genteng Kodok / Glazuur 86.300 m3

7.2 Pekerjaan Plafond GypsumPekerjaan Langit -langit Gypsum 297.0000 m3

Pekerjaan Pas Palafond & Rangka Plafond 148.500 m3

8 PEKERJAAN LANTAI

8.1 Pekerjaan Urugan Tanah Dibawah Lantai 44.250 m3

8.2 Pekerjaan pasir urug lantai 29.500 m3

8.3 Pasangan Keramik 20 x 20 5.561 m3

8.4 Pasangan Keramik 30 x 30 289.437 m3

9 PEKERJAAN INSTALASI LISTRIK

Pasangan Lampu TL 26.000 bhPasangan Lampu Taman 6.000 bhPasangan Lampu Gantung 2.000 bhPasangan Saklar Tunggal 15.000 bhPasangan Saklar Ganda 5.000 bhPasangan Stop Kontak 16.000 bhlampu downlight 5.000 bh

Pasangan meteran listrik 1.000 bh

10 PEKERJAAN SANITASI

Pemasangan Mesin Pompa Air 1.000 bhPemasangan Pipa Air Bersih Dia 3/4" 19.680 mPemasangan Kloset Jongkok Porselen 1.000 bhPemasangan Pipa Air Kotor Dia 4" 53.120 mPemasangan Kloset Duduk / MonoBlock 1.000 bhPemasangan Wastafel 1.000 bhPemasangan Bak Mandi Fiberglass , Kap 0,30 m3 3.000 bhPemasangan Bath Tube 1.000 bhPemasangan Bak Cuci Piring 2.000 bhPemasangan Bak Kontrol 1.000 bhPemasangan Kran Air 6.000 bhPemasangan Septictank dan Rembesan 1.000 unit

Pemasangan floor Drain 3.000 unit

11 PEKERJAAN PENGECATAN

11.1 Pekerjaan Pengecatan Dinding 1527.15 m211.2 Pekerjaan Pengecatan Kusen 46.36 m2

11.3 Pekerjaan Pengecatan Plafond 270.68 m2

12 PEKERJAAN LAIN-LAIN

12.1 Pekerjaan Pegangan Tangga 30.030 m

Page 67: TABEL  RAB john AHS 2012

TABEL 7RENCANA ANGGARAN BIAYA

NO URUTAN PEKERJAAN SAT VOLHARGA SATUAN JUMLAH HARGA

JUMLAHHARGA UPAH HARGA BAHAN HARGA UPAH HARGA BAHAN

1 PEKERJAAN PERSIAPAN1.1 Pembersihan Lapangan m2 240.00 Rp 7,180.00 Rp 1,723,200.00 Rp 1,723,200.00 1.2 Pekerjaan Pasangan Bouwplank m1 68.00 Rp 9,826.00 Rp 28,900.00 Rp 668,168.00 Rp 1,965,200.00 Rp 2,633,368.00 1.3 Pembuatan Direksikeet m2 12.00 Rp 204,740.00 Rp 673,648.00 Rp 2,456,880.00 Rp 8,083,776.00 Rp 10,540,656.00 1.4 Pekerjaan Los Kerja m2 12.00 Rp 122,790.00 Rp 822,305.46 Rp 1,473,480.00 Rp 9,867,665.52 Rp 11,341,145.52 1.5 Pekerjaan Papan Nama Proyek m1 0.32 Rp 3,000.00 Rp 458,781.00 Rp 960.00 Rp 146,809.92 Rp 147,769.92 1.6 Pekerjaan Pagar Proyek m1 14.00 Rp 31,756.00 Rp 342,743.55 Rp 444,584.00 Rp 4,798,409.70 Rp 5,242,993.70

sub total Rp 6,767,272.00 Rp 24,861,861.14 Rp 31,629,133.14 PERSENTASI % 21% 79%

NO URUTAN PEKERJAAN SAT VOLHARGA SATUAN JUMLAH HARGA

JUMLAHHARGA UPAH HARGA BAHAN HARGA UPAH HARGA BAHAN

2 PEKERJAAN TANAH 2.1 Galian Tanah Pondasi m3 204.300 Rp 18,416.00 Rp 3,762,388.80 Rp 3,762,388.80 2.2 Urugan Pasir Dibawah Pondasi m3 68.100 Rp 8,827.00 Rp 601,118.70 Rp 601,118.70

sub total Rp 4,363,507.50 Rp -00 Rp 4,363,507.50 PERSENTASE % 100% 0%

NO URUTAN PEKERJAAN SAT VOLHARGA SATUAN JUMLAH HARGA

JUMLAHHARGA UPAH HARGA BAHAN HARGA UPAH HARGA BAHAN

3 PEKERJAAN PONDASI 3.1 Pekerjaan Pondasi Batu Kali

Pasangan Aanstamping m3 25.24 Rp 55,021.00 Rp 267,000.00 Rp 1,388,730.04 Rp 6,739,080.00 Rp 8,127,810.04 Pasangan Pondasi Batu Kali m3 91.94 Rp 97,494.00 Rp 467,520.00 Rp 8,963,110.89 Rp 42,981,451.20 Rp 51,944,562.09 Urugan Pasir m3 8.51 Rp 12,524.00 Rp 108,000.00 Rp 106,610.55 Rp 919,350.00 Rp 1,025,960.55

sub total Rp 10,458,451.48 Rp 50,639,881.20 Rp 61,098,332.68 PERSENTASI % 17% 83%

NO URUTAN PEKERJAAN SAT VOLHARGA SATUAN JUMLAH HARGA

JUMLAHHARGA UPAH HARGA BAHAN HARGA UPAH HARGA BAHAN

4 PEKERJAAN BETON4.1 Sloof

1 M3 Sloof Beton Bertulang K-225 15/30 m3 5.44 Rp407,922.10 Rp2,015,061.30 Rp2,221,135.83 Rp10,972,008.78 Rp13,193,144.61 1 M3 Sloof Gantung Beton Bertulang K-225 15/3 m3 1.13 Rp407,922.10 Rp2,015,061.30 Rp460,951.97 Rp2,277,019.27 Rp2,737,971.24

4.2 Kolom1 M3 Kolom Beton Bertulang K-225 15/15 m3 7.78 Rp 1,290,098.41 Rp 6,326,356.41 Rp 10,031,805.24 Rp 49,193,747.47 Rp 59,225,552.70 1 M3 Kolom Beton Bertulang K-225 15/30 m3 7.78 Rp 964,824.40 Rp 4,884,798.44 Rp 7,502,474.53 Rp 37,984,192.67 Rp 45,486,667.20

4.3 RingBalk

Page 68: TABEL  RAB john AHS 2012

1 M3 Ring Balk Beton Bertulang K-225 15/20 m3 0.45 Rp 653,389.40 Rp 3,212,708.55 Rp 294,025.23 Rp 1,445,718.85 Rp 1,739,744.08 4.4 Balok

1 M3 Balok Beton Bertulang K-225 15/25 m3 0.41 Rp 559,938.99 Rp2,771,726.26 Rp 230,974.83 Rp 1,143,337.08 Rp 1,374,311.92 1 M3 Balok Beton Bertulang K-225 15/30 m3 3.15 Rp 543,181.15 Rp 2,688,596.93 Rp 1,711,020.61 Rp 8,469,080.34 Rp 10,180,100.95 1 M3 Balok Beton Bertulang K-225 15/35 m3 1.99 Rp 525,036.40 Rp 2,598,545.89 Rp 1,047,447.62 Rp 5,184,099.06 Rp 6,231,546.68

4.5 Plat Lantai1 M3 Plat Lantai Beton Bertulang K-225 m3 17.10 Rp 580,549.80 Rp 2,906,561.32 Rp 9,927,401.64 Rp 49,702,198.63 Rp 59,629,600.27

4.6 Tangga1 M3 Tangga Beton K225 m3 0.49 Rp 728,874.97 Rp 3,715,507.49 Rp 354,233.24 Rp 1,805,736.64 Rp 2,159,969.88

sub total Rp 33,781,470.75 Rp 168,177,138.78 Rp 201,958,609.53 PERSENTASI % 17% 83%

NO URUTAN PEKERJAAN SAT VOLHARGA SATUAN JUMLAH HARGA

JUMLAHHARGA UPAH HARGA BAHAN HARGA UPAH HARGA BAHAN

5 PEKERJAAN DINDING DAN PLESTERAN5.1 Pasangan Bata Merah 1 : 3 m2 741.47 Rp 15,375.00 Rp 46,284.50 Rp 11,400,132.00 Rp 34,318,660.78 Rp 45,718,792.78 5.2 plesteran Dinding m2 1573.51 Rp 15,375.00 Rp 42,838.00 Rp 24,192,716.25 Rp 67,406,021.38 Rp 91,598,737.63 5.3 Acian m2 1573.51 Rp 20,530.00 Rp 6,452.00 Rp 32,304,160.30 Rp 10,152,286.52 Rp 42,456,446.82

Rp 67,897,008.55 Rp 111,876,968.68 Rp 179,773,977.23 PERSENTASI % 38% 62%

NO URUTAN PEKERJAAN SAT VOLHARGA SATUAN JUMLAH HARGA

JUMLAHHARGA UPAH HARGA BAHAN HARGA UPAH HARGA BAHAN

6 PEKERJAAN KUSEN PINTU DAN JENDELAPek. Kusen Pintu & Jendela m3 1.49 Rp 1,266,720.00 Rp 4,500,000.00 Rp 1,887,463.47 Rp 6,705,180.00 Rp 8,592,643.47 Pek. Pintu m2 35.09 Rp 181,420.00 Rp 140,000.00 Rp 6,365,882.66 Rp 4,912,488.00 Rp 11,278,370.66 Pek. Daun Jendela m2 11.27 Rp 145,136.00 Rp 122,500.00 Rp 1,635,218.28 Rp 1,380,183.00 Rp 3,015,401.28 Pas. Kaca 5 mm polos m2 12.55 Rp 8,958.00 Rp 82,500.00 Rp 112,465.90 Rp 1,035,771.00 Rp 1,148,236.90 Pas. Engsel Pintu bh 40 Rp 8,958.00 Rp 20,000.00 Rp 358,320.00 Rp 800,000.00 Rp 1,158,320.00 Pas. Engsel Jendela Kupu-Kupu bh 24 Rp 5,972.00 Rp 7,500.00 Rp 143,328.00 Rp 180,000.00 Rp 323,328.00 Pas. Kunci Tanam Pintu Biasa bh 28 Rp 26,062.00 Rp 125,000.00 Rp 729,736.00 Rp 3,500,000.00 Rp 4,229,736.00 Pas. Kunci Tanam Km/Wc bh 2 Rp 25,406.00 Rp 35,000.00 Rp 50,812.00 Rp 70,000.00 Rp 120,812.00 Pas. Kunci Selot bh 30 Rp 8,958.00 Rp 8,050.00 Rp 268,740.00 Rp 241,500.00 Rp 510,240.00

sub total Rp 11,551,966.32 Rp 18,825,122.00 Rp 30,377,088.32 PERSENTASI % 19% 62%

NO URUTAN PEKERJAAN SAT VOLHARGA SATUAN JUMLAH HARGA

JUMLAHHARGA UPAH HARGA BAHAN HARGA UPAH HARGA BAHAN

7 PEKERJAAN ATAP7.1 Pemasangan Kuda - Kuda m3 19.12908 Rp 702,000.00 Rp 3,656,600.00 Rp 13,428,614.16 Rp 69,947,393.93 Rp 83,376,008.09

Pemasangan Gording 6/12 m3 0.2232 Rp 13,112.50 Rp 5,391,651.20 Rp 2,926.71 Rp 1,203,416.55 Rp 1,206,343.26 Pemasangan Rangka Atap (kaso & reng) m2 0.6648 Rp 8,150.00 Rp 70,535.00 Rp 5,418.12 Rp 46,891.67 Rp 52,309.79 Pemasangan List Plank 2 x ( 2x 20 cm) m2 0.228 Rp 9,950.00 Rp 43,344.00 Rp 2,268.60 Rp 9,882.43 Rp 12,151.03

Page 69: TABEL  RAB john AHS 2012

Pemasangan Papan Ruiter dan balok Bubungan m 0.1736 Rp 20,223.00 Rp 45,174.33 Rp 3,510.71 Rp 7,842.26 Rp 11,352.98 Pemasangan Atap Genteng Kodok / Glazuur m2 86.3 Rp 8,407.50 Rp 37,500.00 Rp 725,567.25 Rp 3,236,250.00 Rp 3,961,817.25

sub total Rp 14,168,305.55 Rp 74,451,676.84 Rp 88,619,982.39

PERSENTASI % 16% 84%

NO URUTAN PEKERJAAN SAT VOLHARGA SATUAN JUMLAH HARGA

JUMLAHHARGA UPAH HARGA BAHAN HARGA UPAH HARGA BAHAN

7.2 PEKERJAAN PLAFONDPekerjaan Langit -langit Gypsum m2 297.00 Rp 6,840.00 Rp 24,345.00 Rp 2,031,480.00 Rp 7,230,465.00 Rp 9,261,945.00 Pekerjaan Pas Palafond & Rangka Plafond m2 148.50 Rp 12,590.00 Rp 48,097.80 Rp 48,097.80 Rp 7,142,523.30 Rp 7,190,621.10

sub total Rp 2,079,577.80 Rp 14,372,988.30 Rp 16,452,566.10 PERSENTASI % 13% 87%

NO URUTAN PEKERJAAN SAT VOLHARGA SATUAN JUMLAH HARGA

JUMLAHHARGA UPAH HARGA BAHAN HARGA UPAH HARGA BAHAN

8 PEKERJAAN LANTAI8.1 Pekerjaan Urugan Tanah Dibawah Lantai m3 44.25 Rp 46,000.00 Rp 2,035,482.31 Rp 2,035,482.31 8.2 Pekerjaan pasir urug lantai m3 29.50 Rp 8,250.00 Rp 108,000.00 Rp 243,372.88 Rp 3,185,972.31 Rp 3,429,345.19 8.3 Pasangan Keramik 20 x 20 m2 5.56 Rp 40,612.50 Rp 72,749.00 Rp 225,843.50 Rp 404,552.51 Rp 630,396.01 8.4 Pasangan Keramik 30 x 30 m2 289.44 Rp 36,787.50 Rp 70,508.98 Rp 10,647,645.24 Rp 20,407,872.30 Rp 31,055,517.55

sub total Rp 13,152,343.94 Rp 23,998,397.12 Rp 37,150,741.06

PERSENTASI % 35% 65%

NO URUTAN PEKERJAAN SAT VOLHARGA SATUAN JUMLAH HARGA

JUMLAHHARGA UPAH HARGA BAHAN HARGA UPAH HARGA BAHAN

9 PEKERJAAN INSTALASI LISTRIKPasangan Lampu TL bh 26 Rp 35,000.00 Rp 296,570.00 Rp 910,000.00 Rp 7,710,820.00 Rp 8,620,820.00 Pasangan Lampu Taman bh 6 Rp 35,000.00 Rp 226,950.00 Rp 210,000.00 Rp 1,361,700.00 Rp 1,571,700.00 Pasangan Lampu Gantung bh 2 Rp 45,000.00 Rp 175,660.00 Rp 90,000.00 Rp 351,320.00 Rp 441,320.00 Pasangan Saklar Tunggal bh 15 Rp 25,000.00 Rp 96,000.00 Rp 375,000.00 Rp 1,440,000.00 Rp 1,815,000.00 Pasangan Saklar Ganda bh 5 Rp 25,000.00 Rp 118,250.00 Rp 125,000.00 Rp 591,250.00 Rp 716,250.00 Pasangan Stop Kontak bh 16 Rp 25,000.00 Rp 108,420.00 Rp 400,000.00 Rp 1,734,720.00 Rp 2,134,720.00 lampu downlight bh 5 Rp 15,000.00 Rp 318,420.00 Rp 75,000.00 Rp 1,592,100.00 Rp 1,667,100.00 Pasangan meteran listrik bh 1 Rp 30,000.00 Rp 321,610.00 Rp 30,000.00 Rp 321,610.00 Rp 351,610.00

sub total Rp 2,215,000.00 Rp 15,103,520.00 Rp 17,318,520.00

PERSENTASI % 13% 87%

NO URUTAN PEKERJAAN SAT VOLHARGA SATUAN JUMLAH HARGA

JUMLAHHARGA UPAH HARGA BAHAN HARGA UPAH HARGA BAHAN

10 PEKERJAAN SANITASIPemasangan Mesin Pompa Air bh 1 Rp 75,000.00 Rp 1,200,000.00 Rp 75,000.00 Rp 1,200,000.00 Rp 1,275,000.00 Pemasangan Pipa Air Bersih Dia 3/4" m 19.68 Rp 3,816.00 18,600 Rp 75,098.88 Rp 366,048.00 Rp 441,146.88 Pemasangan Kloset Jongkok Porselen bh 1 Rp 168,150.00 Rp 341,580.00 Rp 168,150.00 Rp 341,580.00 Rp 509,730.00

Page 70: TABEL  RAB john AHS 2012

Pemasangan Pipa Air Kotor Dia 4" m 53.12 Rp 8,588.25 Rp 48,437.50 Rp 456,207.84 Rp 2,573,000.00 Rp 3,029,207.84 Pemasangan Kloset Duduk / MonoBlock bh 1 Rp 143,762.50 Rp 1,025,126.00 Rp 143,762.50 Rp 1,025,126.00 Rp 1,168,888.50 Pemasangan Wastafel bh 1 Rp 109,375.00 Rp 292,830.00 Rp 109,375.00 Rp 292,830.00 Rp 402,205.00 Pemasangan Bak Mandi Fiberglass , Kap 0,30 m3 bh 3 Rp 348,750.00 Rp 168,000.00 Rp 1,046,250.00 Rp 504,000.00 Rp 1,550,250.00 Pemasangan Bath Tube bh 1 Rp 44,437.50 Rp 1,800,000.00 Rp 44,437.50 Rp 1,800,000.00 Rp 1,844,437.50 Pemasangan Bak Cuci Piring bh 2 Rp 14,850.00 Rp 236,880.00 Rp 29,700.00 Rp 473,760.00 Rp 503,460.00 Pemasangan Bak Kontrol bh 1 Rp 104,770.00 Rp 326,362.50 Rp 104,770.00 Rp 326,362.50 Rp 431,132.50 Pemasangan Kran Air bh 6 Rp 4,950.00 Rp 25,031.25 Rp 29,700.00 Rp 150,187.50 Rp 179,887.50 Pemasangan Septictank dan Rembesan unit 1 Rp 15,000.00 Rp 3,926,308.82 Rp 15,000.00 Rp 3,926,308.82 Rp 3,941,308.82 Pemasangan floor Drain unit 3 Rp 5,175.00 Rp 25,000.00 Rp 15,525.00 Rp 75,000.00 Rp 90,525.00

sub total Rp 2,312,976.72 Rp 13,054,202.82 Rp 15,367,179.54 PERSENTASI % 15% 85%

NO URUTAN PEKERJAAN SAT VOLHARGA SATUAN JUMLAH HARGA

JUMLAHHARGA UPAH HARGA BAHAN HARGA UPAH HARGA BAHAN

11 PEKERJAAN PENGECATAN11.1 Pekerjaan Pengecatan Dinding m2 1527.154 Rp 5,035.00 Rp 11,750.00 Rp 7,689,220.39 Rp 17,944,059.50 Rp 25,633,279.89 11.2 Pekerjaan Pengecatan Kusen m2 46.356 Rp 3,735.00 Rp 20,387.00 Rp 173,139.66 Rp 945,059.77 Rp 1,118,199.43 11.3 Pekerjaan Pengecatan Plafond m2 270.682 Rp 4,353.75 Rp 7,620.00 Rp 1,178,481.76 Rp 2,062,596.84 Rp 3,241,078.60

sub total Rp 9,040,841.81 Rp 20,951,716.11 Rp 29,992,557.92 PERSENTASI % 30% 70%

NO URUTAN PEKERJAAN SAT VOLHARGA SATUAN JUMLAH HARGA

JUMLAHHARGA UPAH HARGA BAHAN HARGA UPAH HARGA BAHAN

12 PEKERJAAN LAIN - LAIN12.1 Pekerjaan Pegangan Tangga m 30.03 Rp 107,300.00 Rp 3,222,219.00 Rp 3,222,219.00

sub total Rp 3,222,219.00 Rp 3,222,219.00

PERSENTASI % 0% 100%

Page 71: TABEL  RAB john AHS 2012

TABEL 8REKAPITULASI RENCANA ANGGARAN BIAYA

NO JENIS PEKERJAAN HARGA PEKERJAAN

1 PEKERJAAN PERSIAPAN Rp31,629,133.14

2 PEKERJAAN TANAH Rp4,363,507.50

3 PEKERJAAN PONDASI Rp61,098,332.68

4 PEKERJAAN BETON Rp201,958,609.53

5 PEKERJAAN DINDING Rp179,773,977.23

6 PEKERJAAN KUSEN PINTU DAN JENDELA Rp30,377,088.32

7 PEKERJAAN ATAP & PLAFOND Rp105,072,548.49

8 PEKERJAAN LANTAI Rp37,150,741.06

9 PEKERJAAN INSTALASI LISTRIK Rp17,318,520.00

10 PEKERJAAN PENGECATAN Rp29,992,557.92

11 PEKERJAAN SANITASI Rp15,367,179.54

12 PEKERJAAN LAIN - LAIN Rp3,222,219.00

JUMLAH Rp717,324,414.40

BIAYA TAK TERDUGA 5 % Rp35,866,220.72

SUB TOTAL Rp753,190,635.12

JASA KONTRAKTOR 10 % Rp75,319,063.51

SUB TOTAL Rp828,509,698.64

PPN 10 % Rp82,850,969.86

TOTAL Rp911,360,668.50

DI BULATKAN Rp712,226,600.00

TERBILANG : Tujuh Ratus Dua Belas Juta Dua Ratus Dua Puluh Enam Ribu Enam Ratus Rupiah

Page 72: TABEL  RAB john AHS 2012

TABEL 9

DAFTAR KEBUTUHAN BAHAN

NO PEKERJA DAN BAHAN VOL SAT KOEFKEBUTUHAN

HARGA SATUAN JUMLAH HARGA

BAHAN BAHAN BAHAN

1. PEKERJAAN PERSIAPAN

1.1 1M2 PEK. PEMBERSIHAN DAN PENGUKURAN KEMBALI (SITE)

1.2 1M' PEK. PASANGAN BOUWPLANK 68.00 m'

kayu kaso ,albasia 0.012 0.816 Rp 1,500,000.00 Rp 1,224,000.00

Kayu Papan 3/20 0.007 0.476 Rp 1,500,000.00 Rp 714,000.00 Paku 5-12 kg 0.020 1.360 Rp 20,000.00 Rp 27,200.00 Jumlah Rp 1,965,200.00 Rp 1,965,200.00

1.3 1M2 LOS KERJA /GUDANG 12 m2

Kayu Borneo Super 0.100 1.200 Rp 1,500,000.00 Rp 1,800,000.00 Paku kg 0.250 3.000 Rp 20,000.00 Rp 60,000.00 Seng Glb BJLS 25 lbr 1.100 13.200 Rp 35,750.00 Rp 471,900.00 Triplex 3mm lbr 0.500 6.000 Rp 62,100.00 Rp 372,600.00 Jumlah Rp 2,704,500.00 Rp 2,704,500.00

1.4 1M2 PEK. DIREKSI KEET 12.00

Kayu Borneo Super 0.100 1.200 Rp 1,500,000.00 Rp 1,800,000.00 Paku kg 0.250 3.000 Rp 13,000.00 Rp 39,000.00 Seng Glb BJLS 25 (80X180)cm lbr 1.100 13.200 Rp 35,750.00 Rp 471,900.00 Tripleks 3mm lbr 0.500 6.000 Rp 62,100.00 Rp 372,600.00 Semen PC Zak 0.100 1.200 Rp 1,120.00 Rp 1,344.00 Pasir Pasang org 0.250 3.000 Rp 175,000.00 Rp 525,000.00 Bata Merah bh 70.000 840.000 Rp 750.00 Rp 630,000.00 Jumlah Rp 3,839,844.00 Rp 3,839,844.00

1.5 1M2 Papan Nama Proyek 0.32

papan albasia 3/30 0.180 0.058 Rp 1,500,000.00 Rp 86,400.00 kayu 5/7 kg 0.060 0.019 Rp 1,500,000.00 Rp 28,800.00 Paku lbr 0.250 0.080 Rp 13,000.00 Rp 1,040.00 Cat,warna standar lbr 0.100 0.032 Rp 50,000.00 Rp 1,600.00 Jumlah Rp 117,840.00 Rp 117,840.00

m3

m3

m3

m2

m3

m2

m3

Page 73: TABEL  RAB john AHS 2012

1.6 1M' PAGAR PENGAMANAN PROYEK 10.00 m'

Kayu Borneo Super 0.036 0.360 Rp 1,500,000.00 Rp 540,000.00 Paku kg 0.020 0.200 Rp 13,000.00 Rp 2,600.00 Seng Gelombang BJLS 25 lbr 1.430 14.300 Rp 35,750.00 Rp 511,225.00 Pengecatan dg Cat Minyak 2x ltr 1.800 18.000 Rp 25,350.00 Rp 456,300.00 Jumlah Rp 1,510,125.00 Rp 1,510,125.00

Rp 10,137,509.00

NO PEKERJA DAN BAHAN VOL SAT KOEFKEBUTUHAN

HARGA SATUAN JUMLAH HARGA

BAHAN BAHAN BAHAN

2. PEKERJAAN TANAH

2.1 1 M3 PEK.GALIAN TANAH PONDASI 204.30 m3

2.2 1M3 URUGAN PASIR BAWAH PONDASI 68.100 m3

Pasir Urug 1.20 81.720 Rp 90,000.00 Rp 7,354,800.00

Jumlah Rp 7,354,800.00 Rp 7,354,800.00

NO PEKERJA DAN BAHAN VOL SAT KOEFKEBUTUHAN

HARGA SATUAN JUMLAH HARGA

BAHAN BAHAN BAHAN3. PEKERJAAN PONDASI

3.1 1M3 PASANGAN ANSTAMPING BATU BELAH 25.24 m3

Batu Kali 1.20 30.288 Rp 200,000.00 Rp 6,057,600.00

Pasir Urug 0.30 7.572 Rp 90,000.00 Rp 681,480.00 Jumlah Rp 6,739,080.00 Rp 6,739,080.00

3.1.1 1 M3 PONDASI BATU KALI 1 : 5 91.94 m3

Batu Kali 1.10 101.134 Rp 200,000.00 Rp 20,226,800.00 PC (50kg) zak 136.00 12503.840 Rp 1,120.00 Rp 14,004,300.80

Pasir Pasang 0.54 50.015 Rp 175,000.00 Rp 8,752,688.00 Jumlah Rp 42,981,451.20 Rp 42,981,451.20

3.1.2 1M3 URUGAN PASIR BAWAH PONDASI 8.510 m3

Pasir Urug 1.20 10.212 Rp 90,000.00 Rp 919,080.00 Jumlah Rp 919,350.00 Rp 919,350.00

Rp 50,639,881.20

3.2.1 1 BUAH PONDASI TELAPAK SETEMPAT TIPE P1 12.00 Bh

m3

m3

m3

m3

m3

m3

m3

Page 74: TABEL  RAB john AHS 2012

Cor Beton 0.26 3.147 Rp 587,000.00 Rp 1,847,289.00 Bekisting m2 0.95 11.340 Rp 65,034.55 Rp 737,491.80 Besi Tulangan Kg 44.68 536.184 Rp 10,167.00 Rp 5,451,382.73

Rp 8,036,163.53 Rp 8,036,163.53

3.2.2 PONDASI TELAPAK SETEMPAT TIPE P2 8.00 Bh

Cor Beton 0.12 0.938 Rp 587,000.00 Rp 550,606.00 Bekisting m2 0.95 7.560 Rp 65,034.55 Rp 491,661.20 Besi Tulangan Kg 31.11 248.876 Rp 10,167.00 Rp 2,530,322.29

Rp 3,572,589.49 Rp 3,572,589.49

NO PEKERJA DAN BAHAN VOL SAT KOEFKEBUTUHAN

HARGA SATUAN JUMLAH HARGA

BAHAN BAHAN BAHAN

4. PEKERJAAN BETON

1 M3 SLOOF BETON BERTULANG K-225 15/30 5.44 m3

COOR BETON K-225 1.00 5.445 Rp 529,665.00 Rp 2,884,025.93

BEKISTING DENGAN PAPAN 10.57 57.577 Rp 103,309.10 Rp 5,948,234.61 BESI TERPASANG U-24 kg 38.65 210.460 Rp 10,167.00 Rp 2,139,748.24 JUMLAH Rp 10,972,008.78 Rp 10,972,008.78

1 M3 SLOOF GANTUNG K-225 15/30 1.13 m3

COOR BETON K-225 1.00 1.130 Rp 529,665.00 Rp 598,521.45

BEKISTING DENGAN PAPAN 10.57 11.949 Rp 103,309.10 Rp 1,234,436.20 BESI TERPASANG U-24 kg 38.65 43.677 Rp 10,167.00 Rp 444,061.62 JUMLAH Rp 2,277,019.27 Rp 2,277,019.27

PEKERJAAN KOLOM1 M3 KOLOM BETON BERTULANG K-225 15/15 7.78 m3

COOR BETON K-225 1.00 7.776 Rp 529,665.00 Rp 4,118,675.04

BEKISTING DENGAN PAPAN 26.67 207.386 Rp 103,309.10 Rp 21,424,852.75 BESI TERPASANG U24 kg 299.15 2326.175 Rp 10,167.00 Rp 23,650,219.68 JUMLAH Rp 49,193,747.47 Rp 49,193,747.47

1 M3 KOLOM BETON BERTULANG K-225 15/30 7.78 m3

COOR BETON K-225 1.00 7.776 Rp 529,665.00 Rp 4,118,675.04

BEKISTING DENGAN PAPAN 20.00 155.520 Rp 110,840.50 Rp 17,237,914.56 BESI TERPASANG U24 kg 210.32 1635.448 Rp 10,167.00 Rp 16,627,603.07 JUMLAH Rp 37,984,192.67 Rp 37,984,192.67

m3

m3

m3

m2

m3

m2

m3

m2

m3

m2

Page 75: TABEL  RAB john AHS 2012

1 M3 RING BALK BETON BERTULANG K-225 15/20 0.45 m3

COOR BETON K-225 1.00 0.450 Rp 529,665.00 Rp 238,349.25

BEKISTING DENGAN PAPAN 14.48 6.516 Rp 103,309.10 Rp 673,115.61 BESI TERPASANG U24 kg 116.77 52.548 Rp 10,167.00 Rp 534,253.99 JUMLAH Rp 1,445,718.85 Rp 1,445,718.85

1 M3 BALOK BETON BERTULANG K-225 15/25 0.41 m3COOR BETON K-225 m3 1.00 0.413 Rp 529,665.00 Rp 218,486.81 BEKISTING DENGAN PAPAN m2 17.33 7.150 Rp 103,309.10 Rp 738,645.86 BESI TERPASANG U24 kg 44.40 18.315 Rp 10,167.00 Rp 186,204.41 JUMLAH Rp 1,143,337.08 Rp 1,143,337.08

1 M3 BALOK BETON BERTULANG K-225 15/35 1.99 m3

COOR BETON K-225 1.00 1.99 Rp 529,665.00 Rp 1,056,681.68

BEKISTING DENGAN PAPAN 15.94 31.80 Rp 103,309.10 Rp 3,285,260.37 BESI TERPASANG U24 kg 41.52 82.83 Rp 10,167.00 Rp 842,157.01 JUMLAH Rp 5,184,099.06 Rp 5,184,099.06

1 M3 BALOK BETON BERTULANG K-225 15/30 3.15 m3COOR BETON K-225 m3 1.00 3.150 Rp 529,665.00 Rp 1,668,444.75 BEKISTING DENGAN PAPAN m2 16.67 52.511 Rp 103,309.10 Rp 5,424,812.50 BESI TERPASANG U24 kg 42.96 135.322 Rp 10,167.00 Rp 1,375,823.09 JUMLAH Rp 8,469,080.34 Rp 8,469,080.34

1 M3 PLAT LANTAI BETON BERTULANG K-225 17.10 m3

COOR BETON K-225 1.00 17.100 Rp 529,665.00 Rp 9,057,271.50

BEKISTING DENGAN PAPAN 8.67 148.224 Rp 110,840.50 Rp 16,429,202.99 BESI TERPASANG U24 kg 139.29 2381.796 Rp 10,167.00 Rp 24,215,724.14 JUMLAH Rp 49,702,198.63 Rp 49,702,198.63

1 M3 TANGGA BETON K225 0.49 m3

COOR BETON K-225 1.00 0.486 Rp 529,665.00 Rp 257,417.19

BEKISTING DENGAN PAPAN 17.17 8.347 Rp 110,840.50 Rp 925,158.87

m3

m2

m3

m2

m3

m2

m3

m2

Page 76: TABEL  RAB john AHS 2012

BESI TERPASANG U24 kg 126.12 61.292 Rp 10,167.00 Rp 623,160.58 JUMLAH Rp 1,805,736.64 Rp 1,805,736.64

NO PEKERJA DAN BAHAN VOL SAT KOEFKEBUTUHAN

HARGA SATUAN JUMLAH HARGA

BAHAN BAHAN BAHAN

5. PEKERJAAN DINDING

1 M2 PASANGAN BATA MERAH ad 1 : 3 741.47 m2Bata Merah bh 70.000 51902.900 Rp750.00 Rp 38,927,175.00 PC semen zak 14.37 10654.924 Rp1,120.00 Rp 11,933,514.77 Pasir Pasang m3 0.04 29.659 Rp175,000.00 Rp 5,190,290.00 Jumlah Rp 56,050,979.77 Rp 56,050,979.77

1 M2 PLESTERAN DINDING + ACIAN 1573.51 m2PC semen zak 6.480 10196.345 Rp 1,120.00 Rp 11,419,906.18 Pasir Pasang m3 0.019 29.897 Rp 175,000.00 Rp 5,231,920.75 Jumlah Rp 16,651,826.93 Rp 16,651,826.93

Rp 72,702,806.69

NO PEKERJA DAN BAHAN VOL SAT KOEFKEBUTUHAN

HARGA SATUAN JUMLAH HARGA

PRINT

BAHAN BAHAN BAHAN

6. PEKERJAAN KUSEN PINTU PINTU DAN JENDELA

1 m3 PASANG KUSEN K. Borneo 1.49 m3Kayu borneo ,balok m3 1.200 1.79 Rp 3,750,000.00 Rp 6,705,180.00 Jumlah Rp 6,705,180.00 Rp 6,705,180.00

1 m3 Pintu panel kayu borneo 35.09 m2Kayu borneo papan M3 0.035 1.228122 Rp 3,500,000.00 Rp 4,298,427.00 Jumlah Rp 4,298,427.00 Rp 4,298,427.00

Pek. Daun Jendela 11.3 m2

kayu borneo , papan 0.035 0.394 Rp3,500,000.00 Rp 1,380,183.00 Jumlah Rp 1,380,183.00 Rp 1,380,183.00

Pas. Kaca 5 mm polos 12.6 m2

Kaca 1.100 13.810 Rp75,000.00 Rp 941,610.00 Jumlah Rp 941,610.00 Rp 941,610.00

PASANG ALAT-ALAT AKSESORIS

A 1 buah engsel pintu 40 BhEngsel pintu buah 1 40 Rp 20,000.00 Rp 800,000.00 Jumlah Rp 800,000.00 Rp 800,000.00

m2

m2

Page 77: TABEL  RAB john AHS 2012

PRINT

B 1 buah engsel jendela 24 BhEngsel jendela buah 1 24 Rp 7,500.00 Rp 180,000.00 Jumlah Rp 180,000.00 Rp 180,000.00

C 1 Buah pasang kunci tanam biasa 28 Bhkunci tanam buah 1 28 Rp 125,000.00 Rp 3,500,000.00 Jumlah Rp 3,500,000.00 Rp 3,500,000.00

D 1 buah kunci tanam kamar mandi 2 BhSlot buah 1 2 Rp 35,000.00 Rp 70,000.00 Jumlah Rp 70,000.00 Rp 70,000.00

E 1 BUAH PASANG KUNCI SELOT (SNI. Edisi Rev. 2002) 30 BhKunci selot buah 1 30 Rp 8,050.00 Rp 241,500.00 Jumlah Rp 241,500.00 Rp 241,500.00

18,730,961.00

NO PEKERJA DAN BAHAN VOL SAT KOEFKEBUTUHAN

HARGA SATUAN JUMLAH HARGA

BAHAN BAHAN BAHAN

7. PEKERJAAN ATAP

1 M3 PASANG KUDA-KUDA 19.13 m3Balok kayu borneo super M3 1.100 21.042 Rp 3,232,300.00 Rp 68,014,017.81 Besi strip Kg 15.000 286.936 Rp 6,050.00 Rp 1,735,964.01 Paku biasa 2" . 5" Kg 0.800 15.303 Rp 12,900.00 Rp 197,412.11 Jumlah Rp 69,947,393.93 Rp 69,947,393.93

Pek. Pas. Gording 6/12 0.22 m2kayu kamper banjar m3 1.100 0.246 Rp 4,900,000.00 Rp 1,203,048.00 Paku kg 0.128 0.029 Rp 12,900.00 Rp 368.55 Jumlah Rp 1,203,416.55 Rp 1,203,416.55

Pek. 1 m2 Pas. Rangka Atap (kaso&Reng) 0.66 m'

kayu kamper banjar 0.014 0.009 Rp 4,900,000.00 Rp 45,605.28 Paku biasa 2" . 5" kg 0.150 0.100 Rp 12,900.00 Rp 1,286.39 Jumlah Rp 46,891.67 Rp 46,891.67

1 M2 PASANG LISPLANK 2 x ( 2 x 20 cm ) , KAYU KAMPER ( SNI.Edisi Rev.2002 ) 0.23 m'

Kayu Kamper, Papan 0.0086 0.002 Rp4,900,000.00 Rp 9,607.92

m3

m3

Page 78: TABEL  RAB john AHS 2012

Paku biasa 2" - 5" kg 0.06 0.014 Rp12,900.00 Rp 176.47 Jumlah Rp 9,882.43 Rp 9,882.43

Pek. 1 m" Pas. Papan Ruiter dan Balok Bubungan 0.17 m'Balok 8/12 Borneo Super m3 0.010 0.002 Rp3,232,300.00 Rp 5,386.82 Papan 2/20 Borneo Super m3 0.004 0.001 Rp3,232,300.00 Rp 2,244.51 Paku Kg 0.128 0.022 Rp9,500.00 Rp 210.93 Jumlah Rp 7,842.26 Rp 7,842.26

1 M2 PASANG ATAP GENTENG KODOK / GLAZUUR ( SNI. Edisi Rev. 2002) 86.3 m'genteng kodok bh 25.000 2157.500 Rp 1,500.00 Rp 3,236,250.00 Jumlah Rp 3,236,250.00 Rp 3,236,250.00

1 M2 LANGIT - LANGIT GYPSUM (SNI. Edisi Rev. 2002) 270.68 m3Gypsum M3 0.375 101.506 Rp63,600.00 Rp 6,455,765.70 paku 1 - 3 cm Kg 0.03 8.120 Rp20,000.00 Rp 162,409.20 Jumlah Rp 6,618,174.90 Rp 6,618,174.90

1 M2 Pas. Flapond & Rangka Flapond (Borneo Super) 270.68 m2kayu borneo balok m3 0.012 3.248 4,250,000.00 Rp 13,804,782.00 Paku Kg 0.100 27.068 13,000.00 Rp 351,886.60 Jumlah Rp 14,156,668.60 Rp 14,156,668.60

Rp 20,774,843.50

NO PEKERJA DAN BAHAN VOL SAT KOEFKEBUTUHAN

HARGA SATUAN JUMLAH HARGA

BAHAN BAHAN BAHAN

8. PEKERJAAN LANTAI1 M3 URUGAN TANAH DIBAWAH LANTAI

1 M3 PASIR URUG LANTAI 310.62 m3

Pasir Urug 1.200 372.743 Rp 90,000.00 Rp 33,546,906.00 Jumlah Rp 33,546,906.00 Rp 33,546,906.00

1 M2 PAS.LANTAI KERAMIK 30x30 287.00 m2Ubin Keramik, uk. 30x30 cm Bh 11.110 3188.514 Rp 2,545.00 Rp 8,114,769.28 Semen Portland Kg 11.380 3266.003 Rp 1,120.00 Rp 3,657,923.47 Pasir Pasang M3 0.042 12.054 Rp 175,000.00 Rp 2,109,413.25 Semen Warna Kg 1.500 430.493 Rp 5,000.00 Rp 2,152,462.50

m3

Page 79: TABEL  RAB john AHS 2012

Jumlah Rp 16,034,568.50 Rp 16,034,568.50

1 M2 PAS.LANTAI KERAMIK 20x20 17.88 m2Ubin Keramik, uk. 20x20 cm Bh 25.000 446.875 Rp 1,600.00 Rp 715,000.00 Semen Portland Kg 11.380 203.418 Rp 1,120.00 Rp 227,827.60 Pasir Pasang M3 0.042 0.751 Rp 175,000.00 Rp 131,381.25 Semen Warna Kg 1.500 26.813 Rp 5,000.00 Rp 134,062.50 Jumlah Rp 1,208,271.35 Rp 1,208,271.35

50,789,745.85

PRINT

NO PEKERJA DAN BAHAN VOL SAT KOEFKEBUTUHAN

HARGA SATUAN JUMLAH HARGA

BAHAN BAHAN BAHAN9 PEKERJAAN ELEKTRIKAL

Lampu TL 26 bhLampu TL Bh 1 26.000 Rp6,000.00 Rp 156,000.00 Kabel m' 5 130.000 Rp58,114.00 Rp 7,554,820.00 Jumlah Rp 7,710,820.00 Rp 7,710,820.00

Lampu Taman 6 bhLampu Taman Bh 1 6.000 Rp165,000.00 Rp 990,000.00 Kabel m' 5 30.000 Rp12,390.00 Rp 371,700.00 Jumlah Rp 1,361,700.00 Rp 1,361,700.00

Lampu Gantung 2 bhLampu Gantung Bh 1 2.000 Rp145,000.00 Rp 290,000.00 Kabel m' 5 10.000 Rp6,132.00 Rp 61,320.00 Jumlah Rp 351,320.00 Rp 351,320.00

Sakelar Ganda 5 bhSakelar Ganda Bh 1 5.000 Rp18,500.00 Rp 92,500.00 Kabel m' 5 25.000 Rp19,950.00 Rp 498,750.00 Jumlah Rp 591,250.00 Rp 591,250.00

Sakelar Tunggal 15 bhSakelar Ganda Bh 1 15.000 Rp12,000.00 Rp 180,000.00 Kabel m' 5 75.000 Rp16,800.00 Rp 1,260,000.00 Jumlah Rp 1,440,000.00 Rp 1,440,000.00

Stop Kontak 16 Bh 1 16.000 Rp13,500.00 Rp 216,000.00

Page 80: TABEL  RAB john AHS 2012

Kabel m' 5 80.000 Rp18,984.00 Rp 1,518,720.00

PRINT

Jumlah Rp 1,734,720.00 Rp 1,734,720.00

lampu downlight 5 bhSekring Bh 1.000 5.000 105000 Rp 1,592,100.00 Jumlah Rp 1,592,100.00 Rp 1,592,100.00

KWH 1 bhKWH Bh 1 1.000 Rp285,000.00 Rp 285,000.00 Kabel m' 5 5.000 Rp7,322.00 Rp 36,610.00 Jumlah Rp 321,610.00 Rp 321,610.00

Rp 15,103,520.00

NO PEKERJA DAN BAHAN VOL SAT KOEFKEBUTUHAN

HARGA SATUAN JUMLAH HARGA

PRINT

BAHAN BAHAN BAHAN

10 PEKERJAAN PENGECATAN

1 M2 PENGECATAN DINDING 1527.15 m2Ampelas lbr 0.1 152.715 Rp2,650.00 Rp 404,695.81 Cat Dasar kg 0.1 152.715 Rp50,000.00 Rp 7,635,770.00 Cat Penutup 2 x kg 0.26 397.060 Rp23,500.00 Rp 9,330,910.94 Rol Cat bh 0.025 38.179 Rp15,000.00 Rp 572,682.75 Jumlah Rp 17,944,059.50 Rp 17,944,059.50

1 M2 PENGECATAN KUSEN 46.36 m2Cat Meni Kg 0.200 9.271 Rp 17,250.00 Rp 159,928.20 Plamir Kg 0.150 6.953 Rp 17,000.00 Rp 118,207.80 Ampelas Lbr 0.010 0.464 Rp 2,650.00 Rp 1,228.43 Cat Dasar Kg 0.170 7.881 Rp 32,000.00 Rp 252,176.64 Cat Penutup, 2x Kg 0.260 12.053 Rp 32,000.00 Rp 385,681.92 Kuas bh 0.050 2.318 Rp 12,000.00 Rp 27,813.60 Jumlah Rp 945,036.59 Rp 945,036.59

1 M2 PENGECATAN PLAFOND 270.68 m2Plamir Kg 0.100 27.068 Rp 11,700.00 Rp 316,697.94 Ampelas Lbr 0.150 40.602 Rp 4,000.00 Rp 162,409.20 Cat Dasar Kg 0.100 27.068 Rp 17,500.00 Rp 473,693.50 Cat Penutup, 2x Kg 0.280 75.791 Rp 13,500.00 Rp 1,023,177.96 Rol Cat Bh 0.010 2.707 Rp 32,000.00 Rp 86,618.24 Jumlah Rp 2,062,596.84 Rp 2,062,596.84

Rp 20,951,692.93

Page 81: TABEL  RAB john AHS 2012

NO PEKERJA DAN BAHAN VOL SAT KOEFKEBUTUHAN

HARGA SATUAN JUMLAH HARGA

BAHAN BAHAN BAHAN

11 PEKERJAAN SANITASI

1 UNIT PAS MESIN POMPA AIR 1 bhPompa Air Merek Sanyo Bh 1.000 1.000 Rp 1,200,000.00 Rp 1,200,000.00 Jumlah Rp 1,200,000.00 Rp 1,200,000.00

MEMASANG 1M' PIPA PVC SAL.AIR BERSIH TYPE AW,DIA 3/4" 19.68 m'Pipa PVC m' 1.200 23.616 Rp 3,500.00 Rp 82,656.00 Perlengkapan (35% x Harga Pipa ) Ls 1.000 19.680 Rp 1,225.00 Rp 24,108.00 Jumlah Rp 106,764.00 Rp 106,764.00

MEMASANG 1M' PIPA PVC SAL AIR KOTOR TYPE AW,DIA 4" 53.12 m'Pipa PVC m' 1.200 63.744 Rp 31,250.00 Rp 1,992,000.00 Perlengkapan (35% x Harga Pipa ) Ls 1.000 53.120 Rp 10,937.50 Rp 581,000.00 Jumlah Rp 2,573,000.00 Rp 2,573,000.00 MEMASANG 1 BUAH KLOSET DUDUK / MONOBLOCK 1.00 bhKloset Duduk / Monoblock Bh 1.000 1.000 Rp 967,100.00 Rp 967,100.00 Perlengkapan (6% x Harga Kloset) Ls 1.000 1.000 Rp 58,026.00 Rp 58,026.00 Jumlah Rp 1,025,126.00 Rp 1,025,126.00

MEMASANG 1 BUAH KLOSET JONGKOK PORSELEN 1.00 m'Kloset Jongkok Porselen bh 1 1 Rp335,400.00 Rp 335,400.00 Semen Portland Kg 6 6 Rp850.00 Rp 5,100.00 Pasir Pasang Ls 0.01 0.01 Rp108,000.00 Rp 1,080.00 jumlah Rp 341,580.00 Rp 341,580.00

MEMASANG 1 BUAH WASTAFEL 1 bhWastafel Bh 1.000 1.000 Rp 256,800.00 Rp 256,800.00 Perlengkapan ( 12% x Harga Wsatafel ) Ls 1.000 1.000 Rp 30,816.00 Rp 30,816.00 Semen Portland Kg 6.000 6.000 Rp 850.00 Rp 5,100.00 Pasir Pasang m3 0.010 0.010 Rp 10,800.00 Rp 108.00 Jumlah Rp 292,824.00 Rp 292,824.00

MEMASANG 1 BUAH BAK MANDI FIBREGLASS, KAP. 1,00 M3 3 bhBak Fibreglass Bh 1.000 3.000 Rp 150,000.00 Rp 450,000.00 Pelengkapan ( 12% x Harga Bak ) Ls 1.000 3.000 Rp 18,000.00 Rp 54,000.00 Jumlah Rp 504,000.00 Rp 504,000.00

MEMASANG 1 BUAH BATH TUBE 1 bhBarh Tube Bh 1.000 1.000 Rp 1,500,000.00 Rp 1,500,000.00 Perlengkapan ( 20 % x Harga Bath Tube ) Ls 1.000 1.000 Rp 300,000.00 Rp 300,000.00

Page 82: TABEL  RAB john AHS 2012

Rp 1,800,000.00 Rp 1,800,000.00

MEMASANG 1 BH FLOOR DRAIN 3Floor Drain bh 1.000 3.000 Rp 25,000.00 Rp 75,000.00

Rp 75,000.00 Rp 75,000.00

MEMASANG 1BH.BAK CUCI PIRING STAINLESS STEEL 2 bhBak cucui Stainless Steel m' 1.000 2.000 Rp 211,500.00 Rp 423,000.00 Water Drain + Asesoris Set 1.000 2.000 Rp 25,380.00 Rp 50,760.00 Jumlah Rp 473,760.00 Rp 473,760.00

MEMASANG 1 BAK KONTROL DARI PAS, BATA,UK. 60 x 60 x 65 CM 1 bhBatu Bata Bh 336.000 336.000 Rp 425.00 Rp 142,800.00 Semen Portland Kg 114.000 114.000 Rp 850.00 Rp 96,900.00 Pasir Pasang m3 0.184 0.184 Rp 108,000.00 Rp 19,872.00 Batu Kerikil M3 0.033 0.033 Rp 153,500.00 Rp 5,065.50 Besi Beton Kg 4.850 4.850 Rp 9,300.00 Rp 45,105.00 Pasir Beton m3 0.120 0.120 Rp 138,500.00 Rp 16,620.00 Jumlah Rp 326,362.50 Rp 326,362.50

MEMASANG 1 BH KRAN AIR DIA 1/2" ATAU 3/4" 6 bhKran Air Bh 1.000 6.000 Rp 25,000.00 Rp 150,000.00 Seal Tape Bh 0.025 0.150 Rp 1,250.00 Rp 187.50 Jumlah Rp 150,187.50 Rp 150,187.50

1 UNIT SEPTITANK 2,00 x 1,50 x 1,50 M + REMBESAN 1 bhGalian Tanah m3 4.500 4.500 Rp 27,868.00 Rp 125,406.00 Pasir Urug m3 0.214 0.214 Rp 129,195.00 Rp 27,673.57 Lantai Kerja m2 2.250 2.250 Rp 50,053.00 Rp 112,619.25 Pas. Bata 1Pc : 2Psr + Plesteran m2 15.000 15.000 Rp 91,464.00 Rp 1,371,960.00 Plat Beton Penutup m3 0.300 0.300 Rp 1,889,700.00 Rp 566,910.00 Pipa PVC 4"jenis AW + sambungan m' 5.400 5.400 Rp 39,062.50 Rp 210,937.50 Pipa GIP 1,5" m' 1.200 1.200 Rp 38,333.33 Rp 46,000.00 Galian Tanah untuk rembesan m3 3.375 3.375 Rp 27,868.00 Rp 94,054.50 Pas. Injuk m2 5.400 5.400 Rp 160,000.00 Rp 864,000.00 Pasangan Kerikil 3,5 Cm m2 1.050 1.050 Rp 140,000.00 Rp 147,000.00 Pipa PVC 4"berlubang jenis AW m' 9.000 9.000 Rp 39,062.50 Rp 351,562.50 Urugan Kembali/perataan tanah m3 1.125 1.125 Rp 7,276.00 Rp 8,185.50 Jumlah Rp 3,926,308.82 Rp 3,926,308.82

Page 83: TABEL  RAB john AHS 2012

NO PEKERJA DAN BAHAN VOL SAT KOEFKEBUTUHAN

HARGA SATUAN JUMLAH HARGA

BAHAN BAHAN BAHANPEKERJAAN LAIN LAIN

PEGANGAN TANGGA 30.03 bhPegangan tangga ( balustrade ) profil jati Bh 1.000 30.030 Rp 107,300.00 Rp 3,222,219.00 Jumlah Rp 3,222,219.00 Rp 3,222,219.00

T O T A L H A R G A B A H A N Rp 796,657,359.802

Page 84: TABEL  RAB john AHS 2012

TABEL 10DAFTAR KEBUTUHAN MATERIAL

NO Jenis Material Volume Sat KoefKebutuhan Total

Bahan Kebutuhan

1 Ampelas 1527.154 lbr 0.150 229.073Ampelas 46.356 Lbr 0.150 6.953Ampelas 270.682 Lbr 0.150 40.602

jumlah 276.6292 Bathtube 1.000 Bh 1.000 1.000

jumlah 1.0003 Bak cuci Stainless Steel 2.000 m' 1.000 2.000

jumlah 2.0004 Bak Fibreglass 3.000 Bh 1.000 3.000

jumlah 3.0005 Balok k.Borneo Super 19.129 m3 1.100 21.042

jumlah 21.0426 Bata Merah 4.000 bh 70.000 280.000

Bata Merah 104.544 bh 80.000 8363.520Bata Merah 742.969 bh 80.000 59437.496

jumlah 68081.0167 Batu Bata 1.000 Bh 336.000 336.000

jumlah 336.0008 Batu Kali 14.396 m3 1.200 17.275

Batu Kali 44.663 m3 1.200 53.595Batu Kerikil 1.000 M3 0.033 0.033

jumlah 70.9049 Bekisting pondasi telapak tipe 1 #NAME? m2 0.945 #NAME?

Bekisting pondasi telapak tipe 2 #NAME? m2 0.945 #NAME?jumlah #NAME?

10 BEKISTING DENGAN MULTIPLEK 7.776 m2 20.000 155.520BEKISTING DENGAN MULTIPLEK 17.100 m2 8.668 148.224BEKISTING DENGAN MULTIPLEK 0.486 m2 17.174 8.347

jumlah 312.09111 BEKISTING DENGAN PAPAN 6.570 m2 10.574 69.473

BEKISTING DENGAN PAPAN 7.776 m2 26.670 207.386BEKISTING DENGAN PAPAN 0.450 m2 14.479 6.516BEKISTING DENGAN PAPAN 0.413 m2 11.988 4.945BEKISTING DENGAN PAPAN 3.150 m2 10.284 32.395BEKISTING DENGAN PAPAN 1.995 m2 16.670 33.257BEKISTING DENGAN PAPAN 7.776 m2 17.500 136.080

jumlah 490.05112 BESI TERPASANG U24 6.570 kg 210.320 1381.802

BESI TERPASANG U24 7.776 kg 299.148 2326.175BESI TERPASANG U24 7.776 kg 116.773 908.027BESI TERPASANG U24 0.450 kg 33.029 14.863BESI TERPASANG U24 0.413 kg 48.047 19.819BESI TERPASANG U24 3.150 kg 42.960 135.322BESI TERPASANG U24 1.995 kg 46.815 93.396BESI TERPASANG U24 17.100 kg 44.399 759.223BESI TERPASANG U24 0.486 kg 47.827 23.244

jumlah 5661.87213 Besi Tulangan #NAME? Kg 44.682 #NAME?

Besi Tulangan #NAME? Kg 31.110 #NAME?jumlah #NAME?

14 Cat Dasar 1527.154 kg 0.100 152.715Cat Dasar 46.356 Kg 0.170 7.881

Page 85: TABEL  RAB john AHS 2012

Cat Dasar 270.682 Kg 0.100 27.068jumlah 187.664

15 Cat Meni 46.356 Kg 0.200 9.271jumlah 9.271

16 Cat Penutup 2 x 1527.154 kg 0.260 397.060Cat Penutup, 2x 270.682 Kg 0.280 75.791Cat Penutup, 3x 46.356 Kg 0.350 16.225

jumlah 489.07617 COOR BETON K-225 6.570 m3 1.000 6.570

COOR BETON K-225 7.776 m3 1.000 7.776COOR BETON K-225 7.776 m3 1.000 7.776COOR BETON K-225 0.450 m3 1.000 0.450COOR BETON K-225 0.413 m3 1.000 0.413COOR BETON K-225 3.150 m3 1.000 3.150COOR BETON K-225 1.995 m3 1.000 1.995COOR BETON K-225 17.100 m3 1.000 17.100COOR BETON K-225 0.486 m3 1.000 0.486

jumlah 45.71618 Cor Beton #NAME? m3 0.262 #NAME?

Cor Beton #NAME? m3 0.117 #NAME?jumlah #NAME?

19 Engsel jendela Biasa 24.000 m3 1.000 24.000Engsel Pintu Nylon 4" 40.000 m3 1.000 40.000

jumlah 64.00020 Galian Tanah 1.000 m3 4.500 4.500

Galian Tanah untuk rembesan 1.000 m3 3.375 3.375jumlah 7.875

21 Genting Beton 86.300 bh 11.000 949.300Genting Beton Bubungan 0.174 bh 4.000 0.694

jumlah 949.99422 Gording 8/12 k.kamper Banjar 0.223 m3 0.012 0.003

jumlah 0.00323 Kabel 26.000 m' 5.000 130.000

Kabel 6.000 m' 5.000 30.000Kabel 2.000 m' 5.000 10.000Kabel 15.000 m' 5.000 75.000Kabel 5.000 m' 5.000 25.000Kabel 16.000 m' 5.000 80.000

jumlah 350.00024 Kaca polos 5 mm 12.555 m2 1.000 12.555

jumlah 12.55525 Kaso-kaso 5/7 k.kamper Banjar 0.665 m3 0.006 0.004

jumlah 0.000 0.00426 Kayu 3/30 k.kamper Banjar 0.228 m3 0.004 0.001

Kayu 8/12 k.kamper Banjar 0.665 m3 0.010 0.007jumlah 0.008

27 Kayu Borneo Super 32.000 m3 0.010 0.320Kayu Borneo Super 10.000 m3 0.100 1.000Kayu Borneo Super 8.750 m3 0.100 0.875Kayu Borneo Super 15.000 m3 0.036 0.540Kayu Borneo 5/7 0.32 m3 1.430 0.46Kayu Kamper Banjar 1.490 m3 1.100 1.639Kayu Kaso 5/7 Borneo Super 148.500 m3 0.014 2.079Kayu Kaso 6/12 Borneo Super 148.500 m3 0.004 0.594Kayu Papan Albasia 3/30 0.32 m3 0.036 0.01Kayu Papan Albasia 116.000 m3 0.007 0.812

jumlah 8.32828 Keramik KW.1 DN Putih 5.561 m2 1.010 5.617

Keramik KW1 DN Warna Royal 289.437 m2 1.010 292.331

Page 86: TABEL  RAB john AHS 2012

jumlah 297.94729 Kloset Duduk / Monoblock 1.000 Bh 1.000 1.000

jumlah 1.00030 Kran Air 6.000 Bh 1.000 6.000

jumlah 6.00031 Kuas 46.356 bh 0.100 4.636

jumlah 4.63632 Kunci tanam Alpha 28.000 buah 1.000 28.000

jumlah 28.00034 Lampu Taman 6.000 Bh 1.000 6.000

Lampu TL 40 Watt 26.000 Bh 1.000 26.00035 jumlah 32.000

Lantai Kerja 1.000 m2 2.250 2.250jumlah 2.250

36 Lem Kayu 1.490 Kg 1.000 1.490Lem Kayu 35.089 kg 0.750 26.317

jumlah 27.80737 List Gypsumboard 7cm 161.270 m' 1.000 161.270

jumlah 161.27038 List Kayu 12.555 m' 4.000 50.219

List Kayu Profil K. Kamper 2 cm 35.089 m' 4.000 140.357jumlah 190.576

39 Paku 68.000 kg 0.020 1.360Paku 12.000 Kg 1.250 15.000Paku 12.000 kg 1.250 15.000Paku 0.320 kg 0.100 0.032Paku 10.000 kg 5.800 58.000Paku 1.490 kg 0.017 0.025Paku 35.089 kg 1.280 44.914Paku 11.267 kg 0.100 1.127Paku 19.129 kg 0.220 4.208Paku 0.223 kg 0.210 0.047Paku 0.665 kg 0.250 0.166Paku 0.228 kg 0.250 0.057Paku 0.174 kg 0.038 0.007

jumlah 139.94340 PakuGypsum + Paku Biasa 270.682 kg 0.220 59.550

jumlah 59.55041 Pas. Bata 1Pc : 2Psr + Plesteran 1.000 m2 15.000 15.000

jumlah 15.00042 Pas. Injuk 1.000 m2 5.400 5.400

jumlah 5.40043 Pasangan Kerikil 3,5 Cm 1.000 m2 1.050 1.050

jumlah 1.05044 Pasir Beton 1.000 m3 0.120 0.120

jumlah 0.12045 Pasir Pasang 12.000 org 0.250 3.000

Pasir Pasang 44.663 m3 0.430 19.205Pasir Pasang 104.544 m3 0.058 6.064Pasir Pasang 742.969 m3 0.058 43.092Pasir Pasang 12.776 m3 0.006 0.077Pasir Pasang 0.174 m3 0.210 0.036Pasir Pasang 5.561 m3 0.030 0.167Pasir Pasang 289.437 m3 0.030 8.683Pasir Pasang 1.000 m3 0.030 0.030Pasir Pasang 1.000 m3 0.030 0.030

jumlah 80.38446 Pasir Urug 14.396 m3 0.400 5.759

Pasir Urug 4.314 m3 1.200 5.176

Page 87: TABEL  RAB john AHS 2012

Pasir Urug 29.500 m3 1.200 35.400Pasir Urug 1.000 m3 0.214 0.214

jumlah 46.54947 PC (50 Kg) 4.000 zak 0.160 0.640

PC (50 kg) 44.663 zak 0.130 5.806PC (50 Kg) 104.544 zak 0.160 16.727PC (50 Kg) 742.969 zak 0.160 118.875PC (50 Kg) 12.776 zak 0.160 2.044PC (50 Kg) 86.300 zak 0.160 13.808PC (50kg) 5.561 zak 2.160 12.012PC (50kg) 289.437 zak 0.518 149.928

jumlah 319.84048 Pegangan tangga ( balustrade ) profil jati 30.030 Bh 1.000 30.030

jumlah 30.03049 Pengecatan dg Cat Minyak 2x 0.320 ltr 1.800 0.576

jumlah 0.57650 Pipa GIP 1,5" 1.000 m' 1.200 1.200

Pipa PVC 19.680 m' 1.200 23.616Pipa PVC 53.120 m' 1.200 63.744Pipa PVC 4"berlubang jenis AW 1.000 m' 9.000 9.000Pipa PVC 4"jenis AW + sambungan 1.000 m' 5.400 5.400

jumlah 102.96051 Plamir 1527.154 kg 0.100 152.715

Plamir 46.356 Kg 0.150 6.953Plamir 270.682 Kg 0.100 27.068

jumlah 186.73752 Plat Beton Penutup 1.000 m3 0.300 0.300

jumlah 0.30053 Pompa Air Merek Sanyo 1.000 Bh 1.000 1.000

jumlah 1.00054 Profil Gypsumboard 10 mm 297.000 m' 0.347 103.059

jumlah 103.05955 Rangka + Panil k. Kamper Banjar 35.089 m3 0.050 1.754

Reng 3/4 k.kamper Banjar 0.665 m3 0.006 0.004jumlah 1.758

56 Rol Cat 1527.154 bh 0.010 15.272Rol Cat 270.682 Bh 0.010 2.707

jumlah 17.97857 Saklar Ganda 5.000 Bh 1.000 5.000

Saklar Ganda 16.000 Bh 1.000 16.000jumlah 21.000

58 Saklar Tunggal 15.000 Bh 1.000 15.000jumlah 15.000

59 Seal Tape 6.000 Bh 0.025 0.150jumlah 0.150

60 Semen Portland 1.000 Kg 6.000 6.000Semen Portland 1.000 Kg 114.000 114.000

jumlah 120.00061 Semen Warna 50.265 kg 0.013 0.653

Semen Warna 237.220 kg 0.013 3.084Semen Warna 16.127 kg 0.013 0.210Semen Warna 17.733 kg 0.013 0.231Semen Warna 10.508 kg 0.013 0.137

jumlah 4.31462 Seng Gelombang BJLS 25 116.000 lbr 1.430 165.880

Seng Glb BJLS 25 10.000 lbr 1.100 11.000Seng Glb BJLS 25 (80X180)cm 4.000 lbr 1.100 4.400

jumlah 181.28063 Slot 30.000 buah 1.000 30.000

Page 88: TABEL  RAB john AHS 2012

jumlah 30.00064 Tripleks 3mm 10.000 lbr 0.500 5.000

Triplex 3mm 4.000 lbr 0.500 2.000jumlah 7.000

65 Urugan Kembali/perataan tanah 1.000 m3 1.125 1.125jumlah 1.125

66 Wastafel 1.000 Bh 1.000 1.000jumlah 1.000

67 Water Drain + Asesoris 2.000 Set 1.000 2.000

jumlah 2.000

Page 89: TABEL  RAB john AHS 2012

TABEL 11DAFTAR KEBUTUHAN TENAGA KERJA

NO PEKERJA DAN BAHAN VOL SAT KOEFK.TENAGA HARGA TUMLAH HARGA

KERJA SATUAN UPAH UPAH

1. PEKERJAAN PERSIAPAN

1 1M2 PEK. PEMBERSIHAN DAN PENGUKURAN KEMBALI (SITE) 240Pekerja Terampil org 0.100 24.000 Rp 39,600.00 Rp 950,400.00 mandor org 0.050 12.000 Rp 64,400.00 Rp 772,800.00 Jumlah Rp 1,723,200.00 Rp 1,723,200.00

PEK. PASANGAN BOUWPLANK 68pekerja oh 0.100 6.800 Rp 39,600.00 Rp 269,280.00 tukang kayu oh 0.100 6.800 Rp 49,500.00 Rp 336,600.00 mandor oh 0.005 0.340 Rp 64,400.00 Rp 21,896.00 kepalatukang kayu oh 0.010 0.680 Rp 59,400.00 Rp 40,392.00 Jumlah Rp 668,168.00 Rp 668,168.00

1M2 LOS KERJA /GUDANG 12Ongkos Pasang ls 1.000 12.000 Rp 39,600.00 Rp 475,200.00 Jumlah Rp 475,200.00 Rp 475,200.00

1M2 PEK. DIREKSI KEET 12Ongkos Pasang ls 1.000 12.000 Rp 39,600.00 Rp 475,200.00 Jumlah Rp 475,200.00 Rp 475,200.00

1 M2 PAPAN NAMA PROYEK 0.32 m'Ongkos Pasang ls 1.000 0.320 Rp 39,600.00 Rp 12,672.00 Jumlah Rp 12,672.00 Rp 12,672.00

1M' PAGAR PENGAMANAN PROYEK 10 m'Ongkos Pasang ls 1.000 10.000 Rp 39,600.00 Rp 396,000.00 Jumlah Rp 396,000.00 Rp 396,000.00

Rp 3,750,440.00

m2

m2

m2

m2

Page 90: TABEL  RAB john AHS 2012

NO PEKERJA DAN BAHAN VOL SAT KOEFK.TENAGA HARGA TUMLAH HARGA

KERJA SATUAN UPAH UPAH

2. PEKERJAAN TANAH

1 M3 PEK.GALIAN TANAH PONDASI 204.300 m3Pekerja org 0.400 81.720 Rp 39,600.00 Rp 3,236,112.00 Mandor org 0.040 8.172 Rp 64,400.00 Rp 526,276.80 Jumlah Rp 3,762,388.80 Rp 3,762,388.80

1M3 URUGAN PASIR DIBAWAH PONDASI 68.100 m3Pekerja org 0.30 20.430 Rp 39,600.00 Rp 809,028.00 Mandor org 0.01 0.681 Rp 64,400.00 Rp 43,856.40

Jumlah Rp 852,884.40 Rp 852,884.40

Rp 4,615,273.20

NO PEKERJA DAN BAHAN VOL SAT KOEFK.TENAGA HARGA TUMLAH HARGA

KERJA SATUAN UPAH UPAH

3 PEKERJAAN PONDASI

B3 1M3 PASANGAN ANSTAMPING BATU BELAH 25.240 m3Pekerja org 0.78 19.687 Rp 39,600.00 Rp 779,613.12 Tukang Batu 1/2 Terampil org 0.39 9.844 Rp 49,500.00 Rp 487,258.20 Kep. Tukang Batu org 0.039 0.984 Rp 59,400.00 Rp 58,470.98 Mandor org 0.039 0.984 Rp 64,400.00 Rp 63,392.78 Jumlah Rp 1,388,730.04 Rp 1,388,730.04

B4 1 M3 PONDASI BATU KALI 1 : 5 91.940 m3Pekerja org 1.50 137.910 Rp 39,600.00 Rp 5,461,236.00 Tk. Batu Terampil org 0.60 55.164 Rp 49,500.00 Rp 2,730,618.00 Kep. Tukang Batu org 0.06 5.516 Rp 59,400.00 Rp 327,674.16 Mandor org 0.075 6.895 Rp 64,400.00 Rp 444,070.20 Jumlah Rp 8,963,110.89 Rp 8,963,110.89

Page 91: TABEL  RAB john AHS 2012

1M3 URUGAN KEMBALI TANAH 8.510 m3Pekerja Terampil org 0.300 2.553 Rp 39,600.00 Rp 101,098.80 Mandor org 0.0100 0.085 Rp 64,400.00 Rp 5,480.44 Jumlah Rp 106,610.55 Rp 106,610.55

Rp 10,458,451.48 B7 PONDASI TELAPAK SETEMPAT TIPE P1 12.00 Bh

Cor Beton 0.26 3.147 Rp 107,575.00 Rp 338,538.52 Bekisting m2 0.95 11.340 Rp 20,700.00 Rp 234,738.00 Besi Tulangan Kg 44.68 536.184 Rp 2,107.50 Rp 1,130,007.78

Rp 1,703,284.31 Rp 1,703,284.31

B8 1 BUAH PONDASI TELAPAK SETEMPAT TIPE P2 8.00 Bh

Cor Beton 0.12 0.938 Rp 107,575.00 Rp 100,905.35 Bekisting m2 0.95 7.560 Rp 20,700.00 Rp 156,492.00 Besi Tulangan Kg 31.11 248.876 Rp 2,107.50 Rp 524,506.17

Rp 781,903.52 Rp 781,903.52

4. PEKERJAAN BETON STRUKTURAL

C1 1 M3 SLOOF BETON BERTULANG K-225 15/30 5.450 m3

COOR BETON K-225 1.00 5.450 Rp 107,575.00 Rp 586,283.75

BEKISTING DENGAN PAPAN 10.57 57.630 Rp 20,700.00 Rp 1,192,939.65 BESI TERPASANG U-24 kg 38.65 210.653 Rp 2,107.50 Rp 443,952.04 JUMLAH Rp 2,223,175.45 Rp 2,223,175.45

PEKERJAAN KOLOMC2 1 M3 KOLOM STRUKTUR BETON BERTULANG K-225 15/30 7.780 m3

COOR BETON K-225 1.00 7.780 Rp 107,575.00 Rp 836,933.50

BEKISTING DENGAN MULTIPLEK 20.00 155.600 Rp 20,700.00 Rp 3,220,920.00 BESI TERPASANG U24 kg 210.32 1636.290 Rp 2,107.50 Rp 3,448,480.33 JUMLAH Rp 7,506,333.83 Rp 7,506,333.83

C3 1 M3 KOLOM BETON BERTULANG K-225 15/15 7.780 m3

COOR BETON K-225 1.00 7.780 Rp 107,575.00 Rp 836,933.50

BEKISTING DENGAN PAPAN 26.67 207.493 Rp 20,700.00 Rp 4,295,096.82 BESI TERPASANG U24 kg 299.15 2327.371 Rp 2,107.50 Rp 4,904,935.31 JUMLAH Rp 10,036,965.63 Rp 10,036,965.63

m3

m3

m3

m2

m3

m2

m3

m2

Page 92: TABEL  RAB john AHS 2012

C4 1 M3 RING BALK BETON BERTULANG K-225 15/20 0.450 m3

COOR BETON K-225 1.00 0.450 Rp 107,575.00 Rp 48,408.75

BEKISTING DENGAN PAPAN 17.50 7.875 Rp 20,700.00 Rp 163,012.50 BESI TERPASANG U24 kg 46.82 21.067 Rp 2,107.50 Rp 44,398.18 JUMLAH Rp 255,819.43 Rp 255,819.43

C5 1 M3 BALOK BETON BERTULANG K-225 15/35 2.000 m3

COOR BETON K-225 1.00 2.000 Rp 107,575.00 Rp 215,150.00

BEKISTING DENGAN PAPAN 15.94 31.880 Rp 20,700.00 Rp 659,916.00 BESI TERPASANG U24 kg 41.52 83.040 Rp 2,107.50 Rp 175,006.80 JUMLAH Rp 1,050,072.80 Rp 1,050,072.80

C7 1 M3 BALOK BETON BERTULANG K-225 15/30 3.150 m3COOR BETON K-225 m3 1.00 3.150 Rp 107,575.00 Rp 338,861.25 BEKISTING DENGAN PAPAN m2 16.67 52.511 Rp 20,700.00 Rp 1,086,967.35 BESI TERPASANG U24 kg 42.96 135.322 Rp 2,107.50 Rp 285,192.01 JUMLAH Rp 1,711,020.61 Rp 1,711,020.61

C9 1 M3 BALOK BETON BERTULANG K-225 15/25 0.872 m3COOR BETON K-225 m3 1.00 0.872 Rp 107,575.00 Rp 93,791.95 BEKISTING DENGAN PAPAN m2 17.33 15.112 Rp 20,700.00 Rp 312,822.73 BESI TERPASANG U24 kg 44.40 38.710 Rp 2,107.50 Rp 81,582.12 JUMLAH Rp 488,196.81 Rp 488,196.81

C111 M3 PLAT LANTAI BETON BERTULANG K-225 17.100 m3

COOR BETON K-225 1.00 17.100 Rp 107,575.00 Rp 1,839,532.50

BEKISTING DENGAN MULTIPLEK 8.67 148.224 Rp 20,700.00 Rp 3,068,233.20 BESI TERPASANG U24 kg 139.29 2381.796 Rp 2,107.50 Rp 5,019,635.94 JUMLAH Rp 9,927,401.64 Rp 9,927,401.64

C121 M3 TANGGA BETON K225 0.490 m3

COOR BETON K-225 1.00 0.490 Rp 107,575.00 Rp 52,711.75

BEKISTING DENGAN MULTIPLEK 17.17 8.415 Rp 20,700.00 Rp 174,199.94 BESI TERPASANG U24 kg 126.12 61.797 Rp 2,107.50 Rp 130,237.05

JUMLAH Rp 357,148.74 Rp 357,148.74

m3

m2

m3

m2

m3

m2

m3

m2

Page 93: TABEL  RAB john AHS 2012

NO PEKERJA DAN BAHAN VOL SAT KOEFK.TENAGA HARGA TUMLAH HARGA

KERJA SATUAN UPAH UPAH

D. PEKERJAAN DINDING

D1 1 M2 PASANGAN BATA MERAH ad 1 : 3 741.472 m2Pekerja Terampil org 0.32 237.271 Rp 39,600.00 Rp 9,395,933.18 Tk. Batu Terampil org 0.1 74.147 Rp 49,500.00 Rp 3,670,286.40 Kep. Tukang Batu org 0.01 7.415 Rp 59,400.00 Rp 440,434.37 Mandor org 0.015 11.122 Rp 64,400.00 Rp 716,261.95 Jumlah Rp 14,222,915.90 Rp 14,222,915.90

D4 1 M2 PLESTERAN DINDING + ACIAN 1573.510 m2 D2 1 M2 PASANGAN BATA MERAHPekerja Terampil org 0.2 314.702 Rp 39,600.00 Rp 12,462,199.20 Pekerja TerampilTk. Batu Terampil org 0.15 236.027 Rp 49,500.00 Rp 11,683,311.75 Tk. Batu TerampilKep. Tukang Batu org 0.015 23.603 Rp 59,400.00 Rp 1,401,997.41 Kep. Tukang BatuMandor org 0.01 15.735 Rp 64,400.00 Rp 1,013,340.44 MandorJumlah Rp 26,560,848.80 Rp 26,560,848.80 Jumlah

Rp 40,783,764.70

NO PEKERJA DAN BAHAN VOL SAT KOEFK.TENAGA HARGA TUMLAH HARGA

KERJA SATUAN UPAH UPAH

6. PEKERJAAN KAYU

1 m3 PASANG KUSEN K. Borneo 1.49 m3Pekerja Terampil org 6 8.940 Rp 39,600.00 Rp 354,033.50 Tk. Kayu Terampil org 18 26.821 Rp 49,500.00 Rp 1,327,625.64 Kep. Tk. Kayu org 2 2.980 Rp 59,400.00 Rp 177,016.75 Mandor org 0.3 0.447 Rp 64,400.00 Rp 28,787.57 Jumlah Rp 1,887,463.47 Rp 1,887,463.47

Page 94: TABEL  RAB john AHS 2012

1 m3 Pintu panel kayu borneo 35.089 m2Pekerja Terampil org 1 35.089 Rp 39,600.00 Rp 1,389,532.32 Tk. Kayu Terampil org 2.5 87.723 Rp 49,500.00 Rp 4,342,288.50 Kep. Tk. Kayu org 0.25 8.772 Rp 59,400.00 Rp 521,074.62 Mandor org 0.05 1.754 Rp 64,400.00 Rp 112,987.22 Jumlah Rp 6,365,882.66 Rp 6,365,882.66

1 M2 DAUN JENDELA KACA (TANPA KACA ) 11.267 m2Pekerja org 0.8 9.013 Rp 39,600.00 Rp 356,932.22 Tukang Kayu org 2.0 22.534 Rp 49,500.00 Rp 1,115,413.20 Kepala Tukang Kayu org 0.20 2.253 Rp 59,400.00 Rp 133,849.58 Mandor org 0.040 0.451 Rp 64,400.00 Rp 29,023.28 Jumlah Rp 1,635,218.28 Rp 1,635,218.28

1 M2 PASANGAN KACA, T= 5 MM 12.555 m2Pekerja org 0.015 0.188 Rp 39,600.00 Rp 7,457.55 Tukang Kayu org 0.15 1.883 Rp 49,500.00 Rp 93,219.39 Kepala Tukang Kayu org 0.015 0.188 Rp 59,400.00 Rp 11,186.33 Mandor org 0.0008 0.010 Rp 64,400.00 Rp 646.82 Jumlah Rp 112,465.00 Rp 112,465.00

1 BUAH PASANG ENGSEL PINTU 40.00 bhPEKERJA oh 0.015 0.600 Rp 39,600.00 Rp 23,760.00 tkg kayu oh 0.150 6.000 Rp 49,500.00 Rp 297,000.00 kepala tkg kayu oh 0.015 0.600 Rp 59,400.00 Rp 35,640.00 mandor oh 0.0008 0.032 Rp 64,400.00 Rp 2,060.80 Jumlah Rp 358,320.00 Rp 358,320.00

1 BUAH PASANG ENGSEL JENDELA KUPU-KUPU 24 BhPEKERJA oh 0.010 0.240 Rp 39,600.00 Rp 9,504.00 tkg kayu oh 0.100 2.400 Rp 49,500.00 Rp 118,800.00 kepala tkg kayu oh 0.010 0.240 Rp 59,400.00 Rp 14,256.00 mandor oh 0.0005 0.012 Rp 64,400.00 Rp 772.80 Jumlah Rp 143,328.00 Rp 143,328.00

1 BUAH PASANG KUNCI TANAM BIASA 28 Bh

Page 95: TABEL  RAB john AHS 2012

PEKERJA oh 0.01 0.280 Rp 39,600.00 Rp 11,088.00 tkg kayu oh 0.5 14.000 Rp 49,500.00 Rp 693,000.00 kepala tkg kayu oh 0.01 0.280 Rp 59,400.00 Rp 16,632.00 mandor oh 0.005 0.140 Rp 64,400.00 Rp 9,016.00 Jumlah Rp 729,736.00 Rp 729,736.00

1 BUAH PASANG KUNCI TANAM KAMAR MANDI 2 BhPEKERJA oh 0.005 0.010 Rp 39,600.00 Rp 396.00 tkg kayu oh 0.500 1.000 Rp 49,500.00 Rp 49,500.00 kepala tkg kayu oh 0.005 0.010 Rp 59,400.00 Rp 594.00 mandor oh 0.003 0.005 Rp 64,400.00 Rp 322.00 Jumlah Rp 50,812.00 Rp 50,812.00

1 BUAH PASANG KUNCI SELOT 30 BhPEKERJA oh 0.015 0.450 Rp 39,600.00 Rp 17,820.00 tkg kayu oh 0.150 4.500 Rp 49,500.00 Rp 222,750.00 kepala tkg kayu oh 0.015 0.450 Rp 59,400.00 Rp 26,730.00 mandor oh 0.0008 0.024 Rp 64,400.00 Rp 1,545.60 Jumlah Rp 268,740.00 Rp 268,740.00

Rp 11,551,965.41

NO PEKERJA DAN BAHAN VOL SAT KOEFK.TENAGA HARGA TUMLAH HARGA

KERJA SATUAN UPAH UPAH

7. PEKERJAAN ATAP

1 M3 PASANG KUDA-KUDA 19.12908 m3Pekerja 1/2 Terampil org 4 76.516 Rp 30,000.00 Rp 2,295,489.60 Tk. Kayu Terampil org 12 229.549 Rp 42,500.00 Rp 9,755,830.80 Kep. Tk. Kayu org 1.2 22.955 Rp 45,000.00 Rp 1,032,970.32 Mandor org 0.2 3.826 Rp 90,000.00 Rp 344,323.44 Jumlah Rp 13,428,614.16 Rp 13,428,614.16

Pek. Pas. Gording 6/12 0.2232 m2Pekerja org 0.35 0.078 Rp 30,000.00 Rp 2,343.60 Tk. Kayu Terampil org 0.035 0.008 Rp 42,500.00 Rp 332.01 Kep. Tk. Kayu org 0.015 0.003 Rp 45,000.00 Rp 150.66 Mandor org 0.005 0.001 Rp 90,000.00 Rp 100.44

Page 96: TABEL  RAB john AHS 2012

Jumlah Rp 2,926.71 Rp 2,926.71

Pek. 1 m2 Pas. Rangka Atap (kaso&Reng) 0.6648 m'Pekerja org 0.1 0.066 Rp 30,000.00 Rp 1,994.40 Tk. Kayu Terampil org 0.1 0.066 Rp 42,500.00 Rp 2,825.40 Kep. Tk. Kayu org 0.01 0.007 Rp 45,000.00 Rp 299.16 Mandor org 0.005 0.003 Rp 90,000.00 Rp 299.16 Jumlah Rp 5,418.12 Rp 5,418.12

1 M2 PASANG LISPLANK 2 x ( 2 x 20 cm ) , KAYU KAMPER ( SNI.Edisi Rev.2002 ) 0.23 m'Pekerja org 0.1 0.023 Rp 30,000.00 Rp 684.00 Tk. Batu Terampil org 0.1 0.023 Rp 42,500.00 Rp 969.00 Kep. Tk. Batu org 0.01 0.002 Rp 45,000.00 Rp 102.60 Mandor org 0.05 0.011 Rp 90,000.00 Rp 1,026.00 Jumlah Rp 2,781.60 Rp 2,781.60

Pek. 1 m" Pas. Papan Ruiter dan Balok Bubungan 0.174 m'Pekerja org 0.115 0.020 Rp 30,000.00 Rp 599.96 Tk. Kayu Terampil org 0.346 0.060 Rp 42,500.00 Rp 2,549.84 Kep. Tk. Kayu org 0.035 0.006 Rp 45,000.00 Rp 270.30 Mandor org 0.006 0.001 Rp 90,000.00 Rp 90.62 Jumlah Rp 3,510.71 Rp 3,510.71

1 M2 PASANG ATAP GENTENG KODOK / GLAZUUR ( SNI. Edisi Rev. 2002) 86.3Pekerja org 0.15 12.945 Rp 30,000.00 Rp 388,350.00 Tukang Kayu org 0.075 6.472 Rp 42,500.00 Rp 275,081.25 Kepala Tukang Kayu org 0.008 0.690 Rp 45,000.00 Rp 31,068.00 Mandor org 0.008 0.690 Rp 45,000.00 Rp 31,068.00 Jumlah Rp 725,567.25 Rp 725,567.25

NO PEKERJA DAN BAHAN VOL SAT KOEFK.TENAGA HARGA TUMLAH HARGA

KERJA SATUAN UPAH UPAH

8. PEKERJAAN PLAFOND

1 M2 LANGIT - LANGIT GYPSUM 270.682 m3Pekerja org 0.07 18.948 Rp 39,600.00 Rp 750,330.50

Page 97: TABEL  RAB john AHS 2012

Tukang Kayu org 0.1 27.068 Rp 49,500.00 Rp 1,339,875.90 Kepala Tukang Kayu org 0.01 2.707 Rp 59,400.00 Rp 160,785.11 Mandor org 0.0035 0.947 Rp 64,400.00 Rp 61,011.72 Jumlah Rp 2,312,003.23 Rp 2,312,003.23

1 M2 Pas. Flapond & Rangka Flapond (Borneo Super) 270.682 m2Pekerja org 0.150 40.602 Rp 39,600.00 Rp 1,607,851.08 Tukang Kayu org 0.2500 67.671 Rp 49,500.00 Rp 3,349,689.75 Kep. Tk. Kayu org 0.025 6.767 Rp 59,400.00 Rp 401,962.77 Mandor org 0.075 20.301 Rp 64,400.00 Rp 1,307,394.06 Jumlah Rp 6,666,897.66 Rp 6,666,897.66

Rp 8,978,900.89

NO PEKERJA DAN BAHAN VOL SAT KOEFK.TENAGA HARGA TUMLAH HARGA

KERJA SATUAN UPAH UPAH

9. PEKERJAAN LANTAI

1 M3 PASIR URUG LANTAI 310.62 m3Pekerja Terampil org 0.150 46.593 Rp 39,600.00 Rp 1,845,079.83 Mandor org 0.050 15.531 Rp 64,400.00 Rp 1,000,194.79 Sewa Alat Pemadat ls 1.000 310.620 Rp 35,000.00 Rp 10,871,682.50 Jumlah Rp 13,716,957.12 Rp 13,716,957.12

1 M2 PAS.LANTAI KERAMIK 30x30 DN 287.00 m2Pekerja Terampil org 0.62 177.937 Rp 39,600.00 Rp 7,046,301.24 Tk. Batu Terampil org 0.35 100.448 Rp 49,500.00 Rp 4,972,188.38 Kep. Tk. Batu org 0.035 10.045 Rp 59,400.00 Rp 596,662.61 Mandor org 0.03 8.610 Rp 64,400.00 Rp 554,474.34 Jumlah Rp 13,169,626.56 Rp 13,169,626.56

1 M2 PAS.LANTAI KERAMIK KM/WC 20x20 DN 17.88 m2Pekerja Terampil org 0.620 11.083 Rp 39,600.00 Rp 438,867.00 Tk. Batu Terampil org 0.350 6.256 Rp 49,500.00 Rp 309,684.38 Kep. Tk. Batu org 0.035 0.626 Rp 59,400.00 Rp 37,162.13 Mandor org 0.03 0.536 Rp 64,400.00 Rp 34,534.50 Jumlah Rp 820,248.00 Rp 820,248.00

Rp 27,706,831.68

Page 98: TABEL  RAB john AHS 2012

NO PEKERJA DAN BAHAN VOL SAT KOEFK.TENAGA HARGA TUMLAH HARGA

PRINT

KERJA SATUAN UPAH UPAH

PEKERJAAN ELEKTRIKAL

Lampu TL 26 bhOngkos Pasang ls 1.000 26.000 Rp 35,000.00 Rp 910,000.00 Jumlah Rp 910,000.00 Rp 910,000.00

Lampu Taman 6 bhOngkos Pasang ls 1.000 6.000 Rp 35,000.00 Rp 210,000.00 Jumlah Rp 210,000.00 Rp 210,000.00

Lampu Gantung 2 bhOngkos Pasang ls 1.000 2.000 Rp 45,000.00 Rp 90,000.00 Jumlah Rp 90,000.00 Rp 90,000.00

Saklar Tunggal 15 bhOngkos Pasang ls 1.000 15.000 Rp 25,000.00 Rp 375,000.00 Jumlah Rp 375,000.00 Rp 375,000.00

Sakelar Ganda 5 bhOngkos Pasang ls 1.000 5.000 Rp 25,000.00 Rp 125,000.00 Jumlah Rp 125,000.00 Rp 125,000.00

Stop Kontak 16 bhOngkos Pasang ls 1.000 16.000 Rp 25,000.00 Rp 400,000.00 Jumlah Rp 400,000.00 Rp 400,000.00

lampu downight 5 bhOngkos Pasang ls 1.000 5.000 Rp 15,000.00 Rp 75,000.00 Jumlah Rp 75,000.00 Rp 75,000.00

KWH 1 bhOngkos Pasang ls 1.000 1.000 Rp 30,000.00 Rp 30,000.00 Jumlah Rp 30,000.00 Rp 30,000.00

Page 99: TABEL  RAB john AHS 2012

Rp 2,215,000.00

PRINT

NO PEKERJA DAN BAHAN VOL SAT KOEFK.TENAGA HARGA TUMLAH HARGA

PRINT

KERJA SATUAN UPAH UPAH \

PEKERJAAN PENGECATAN

1 M2 PENGECATAN DINDING 1527.15 m2Pekerja oh 0.020 30.543 Rp 39,600.00 Rp 1,209,505.97 Tukang Cat oh 0.063 96.211 Rp 59,400.00 Rp 5,714,915.70 Kepala tukang Cat oh 0.0063 9.621 Rp 54,000.00 Rp 519,537.79 Mandor oh 0.0025 3.818 Rp 64,400.00 Rp 245,871.79 Jumlah Rp 7,689,831.25 Rp 7,689,831.25

1 M2 PENGECATAN KUSEN 46.36 m2Pekerja oh 0.070 3.245 Rp 39,600.00 Rp 128,498.83 Tukang Cat oh 0.009 0.417 Rp 49,500.00 Rp 20,651.60 Kepala Tukang Cat oh 0.006 0.278 Rp 59,400.00 Rp 16,521.28 Mandor oh 0.003 0.116 Rp 64,400.00 Rp 7,463.32 Jumlah Rp 173,135.02 Rp 173,135.02

1 M2 PENGECATAN PLAFOND 270.68 m2Pekerja Oh 0.030 8.120 Rp 39,600.00 Rp 321,570.22 Tukang Cat Oh 0.075 20.301 Rp 49,500.00 Rp 1,004,906.93 Kepala tukang Cat Oh 0.008 2.030 Rp 59,400.00 Rp 120,588.83 Mandor Oh 0.003 0.812 Rp 64,400.00 Rp 52,295.76 Jumlah Rp 1,499,361.73 Rp 1,499,361.73

Rp 9,362,328.01

NO PEKERJA DAN BAHAN VOL SAT KOEFK.TENAGA HARGA TUMLAH HARGA

KERJA SATUAN UPAH UPAH

PEKERJAAN SANITASI

1 UNIT PAS MESIN POMPA AIR 1 bhOngkos Pasang Ls 1.000 1.000 Rp 75,000.00 Rp 75,000.00 Jumlah Rp 75,000.00 Rp 75,000.00

MEMASANG 1M' PIPA PVC SAL.AIR BERSIH TYPE AW,DIA 3/4" 19.68 m'Pekerja Oh 0.036 0.708 Rp 30,000.00 Rp 21,254.40

Page 100: TABEL  RAB john AHS 2012

Tukang Pipa Oh 0.060 1.181 Rp 40,000.00 Rp 47,232.00 Kepala Tukang Pipa Oh 0.006 0.118 Rp 42,500.00 Rp 5,018.40 Mandor Oh 0.002 0.035 Rp 45,000.00 Rp 1,594.08 Jumlah Rp 75,098.88 Rp 75,098.88

MEMASANG 1M' PIPA PVC SAL AIR KOTOR TYPE AW,DIA 4" 53.12 m'Pekerja Oh 0.081 4.303 Rp 30,000.00 Rp 129,081.60 Tukang Pipa Oh 0.135 7.171 Rp 40,000.00 Rp 286,848.00 Kepala Tukang Pipa Oh 0.014 0.717 Rp 42,500.00 Rp 30,477.60 Mandor Oh 0.004 0.218 Rp 45,000.00 Rp 9,800.64 Jumlah Rp 456,207.84 Rp 456,207.84

MEMASANG 1 BUAH KLOSET DUDUK / MONOBLOCK 1.00 bhPekerja Oh 3.300 3.300 Rp 30,000.00 Rp 99,000.00 Tukang Batu Oh 1.100 1.100 Rp 40,000.00 Rp 44,000.00 Kepala Tukang Batu Oh 0.001 0.001 Rp 42,500.00 Rp 42.50 Mandor Oh 0.016 0.016 Rp 45,000.00 Rp 720.00 Jumlah Rp 143,762.50 Rp 143,762.50

MEMASANG 1 BUAH WASTAFEL 1 bhPekerja Oh 1.200 1.200 Rp 30,000.00 Rp 36,000.00 Tukang Batu Oh 1.450 1.450 Rp 40,000.00 Rp 58,000.00 Kepala Tukang Batu Oh 0.150 0.150 Rp 42,500.00 Rp 6,375.00 Mandor Oh 0.100 0.100 Rp 45,000.00 Rp 4,500.00 Jumlah Rp 104,875.00 Rp 104,875.00

MEMASANG 1 BUAH BAK MANDI FIBREGLASS, KAP. 0,30M3 3 bhPekerja Oh 1.8 5.400 Rp 30,000.00 Rp 162,000.00 Tukang Batu Oh 2.7 8.100 Rp 40,000.00 Rp 324,000.00 Kepala Tukang Batu Oh 0.54 1.620 Rp 42,500.00 Rp 68,850.00 Mandor Oh 0.11 0.330 Rp 45,000.00 Rp 14,850.00 Jumlah Rp 569,700.00 Rp 569,700.00

MEMASANG 1BH.BAK CUCI PIRING STAINLESS STEEL 1 bhPekerja Oh 0.030 0.030 Rp 30,000.00 Rp 900.00 Tukan Pipa Oh 0.300 0.300 Rp 40,000.00 Rp 12,000.00

Page 101: TABEL  RAB john AHS 2012

Kepala Tukang Pipa Oh 0.030 0.030 Rp 42,500.00 Rp 1,275.00 Mandor Oh 0.015 0.015 Rp 45,000.00 Rp 675.00 Jumlah Rp 14,850.00 Rp 14,850.00

MEMASANG 1 BAK KONTROL DARI PAS, BATA,UK. 60 x 60 x 65 CM 6 bhPekerja Oh 2.160 12.960 Rp 30,000.00 Rp 388,800.00 Tikang Batu Oh 0.720 4.320 Rp 40,000.00 Rp 172,800.00 Kepala Tukang Batu Oh 0.072 0.432 Rp 42,500.00 Rp 18,360.00 Mandor Oh 0.108 0.648 Rp 45,000.00 Rp 29,160.00 Tukang Gali Oh 0.100 0.600 Rp 32,500.00 Rp 19,500.00 Jumlah Rp 628,620.00 Rp 628,620.00

MEMASANG 1 BH KRAN AIR DIA 1/2" ATAU 3/4" 6 bhPekerja Oh 0.010 0.060 Rp 30,000.00 Rp 1,800.00 Tukan Pipa Oh 0.100 0.600 Rp 40,000.00 Rp 24,000.00 Kepala Tukang Pipa Oh 0.010 0.060 Rp 42,500.00 Rp 2,550.00 Mandor Oh 0.005 0.030 Rp 45,000.00 Rp 1,350.00 Jumlah Rp 29,700.00 Rp 29,700.00

1 UNIT SEPTITANK 2,00 x 1,50 x 1,50 M + REMBESAN 1 bhTambahan Upah Ls 0.600 0.600 Rp 25,000.00 Rp 15,000.00 Jumlah Rp 15,000.00 Rp 15,000.00

T O T A L H A R G A U P A H Rp 177,788,722.41

Page 102: TABEL  RAB john AHS 2012

718.098 m2org ### ### Rp 30,000.00 Rp 6,893,736.00 org ###71.810 Rp 40,000.00 Rp 2,872,390.00 org ### 7.181 Rp 42,500.00 Rp 305,191.44 org ###10.771 Rp 90,000.00 Rp 969,431.62

Rp 11,040,749.06 ###

Page 103: TABEL  RAB john AHS 2012

TABEL 12PERSENTASE BIAYA BAHAN DAN UPAH TERHADAP SETIAP PEKERJAAN

No Uraian Jenis PekerjaanJumlah Harga Jumlah Harga Persentase Persentase

Bahan Upah Bahan + Upah Bahan Upah Jumlah Harga

Bahan + Upah1 PEKERJAAN PERSIAPAN Rp24,861,861.14 Rp6,767,272.00 Rp31,629,133.14 79% 21% 100.00%2 PEKERJAAN TANAH Rp-00 Rp4,363,507.50 Rp4,363,507.50 0% 100% 100.00%3 PEKERJAAN PONDASI Rp50,639,881.20 Rp10,458,451.48 Rp61,098,332.68 83% 17% 100.00%4 PEKERJAAN BETON Rp168,177,138.78 Rp33,781,470.75 Rp201,958,609.53 83% 17% 100.00%5 PEKERJAAN DINDING Rp111,876,968.68 Rp67,897,008.55 Rp179,773,977.23 62% 38% 100.00%6 PEKERJAAN PINTU DAN JENDELA Rp18,825,122.00 Rp11,551,966.32 Rp30,377,088.32 62% 38% 100.00%7 PEKERJAAN ATAP DAN PLAFOND Rp88,824,665.14 Rp16,247,883.35 Rp105,072,548.49 85% 15% 100.00%8 PEKERJAAN LANTAI Rp23,998,397.12 Rp13,152,343.94 Rp37,150,741.06 65% 35% 100.00%9 PEKERJAAN ELEKTRIKAL Rp15,103,520.00 Rp2,215,000.00 Rp17,318,520.00 87% 13% 100.00%

10 PEKERJAAN SANITASI Rp13,054,202.82 Rp2,312,976.72 Rp15,367,179.54 85% 15% 100.00%11 PEKERJAAN PENGECATAN Rp20,951,716.11 Rp9,040,841.81 Rp29,992,557.92 70% 30% 100.00%12 PEKERJAAN LAIN-LAIN Rp3,222,219.00 Rp-00 Rp3,222,219.00 100% 0% 100.00%

J U M L A H Rp539,535,691.99 Rp177,788,722.41 Rp717,324,414.40 75% 25% 100.00%

Page 104: TABEL  RAB john AHS 2012

TABELHARGA PER M2 BANGUNAN RUMAH 2 LANTAI

No Total Anggaran Biaya

1 Rp 712,226,600.00 282 Rp 2,525,626.24

TABEL

HARGA PER M3 BETON

No Total Biaya Pekerjaan Beton

1 Rp 201,958,609.53 45.72 Rp 4,417,292.42

Luas Bangunan m2 Harga Per m2 Bangunan

Harga per m2 bangunan rumah tinggal 2 lantai seharga Rp 2,525,626.24

Volume Total Beton (m3) Harga Per m3 Beton

Harga per m3 beton seharga Rp 4,417,292.42