t-flex workshop roger snoble, l.a. metro chief executive officer october 29, 2007 los angeles county...

11
T-FLEX Workshop Roger Snoble, L.A. Metro Chief Executive Officer October 29, 2007 Los Angeles County Metropolitan Transportation Auth

Post on 20-Dec-2015

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: T-FLEX Workshop Roger Snoble, L.A. Metro Chief Executive Officer October 29, 2007 Los Angeles County Metropolitan Transportation Authority

T-FLEX Workshop

Roger Snoble, L.A. Metro Chief Executive Officer October 29, 2007

Los Angeles County Metropolitan Transportation Authority

Page 2: T-FLEX Workshop Roger Snoble, L.A. Metro Chief Executive Officer October 29, 2007 Los Angeles County Metropolitan Transportation Authority

2

Metro Orange Line – October 28, 2005

Page 3: T-FLEX Workshop Roger Snoble, L.A. Metro Chief Executive Officer October 29, 2007 Los Angeles County Metropolitan Transportation Authority

3

Orange Line Route Map

3,825 Parking Spaces

New Canoga Station and Parking (Dec. 2006)

Page 4: T-FLEX Workshop Roger Snoble, L.A. Metro Chief Executive Officer October 29, 2007 Los Angeles County Metropolitan Transportation Authority

4

Metro Orange Line

• A 14.5 mile dedicated bus way running east and west across the San Fernando Valley –14 Stations–7 Park-n-ride parking lots –3,825 parking spaces–Parallel Bike path–Off Board fare collection–All high capacity buses–And More!

Page 5: T-FLEX Workshop Roger Snoble, L.A. Metro Chief Executive Officer October 29, 2007 Los Angeles County Metropolitan Transportation Authority

5

Metro Orange Line

STATION STOPS – rail-like station shelters including amenities such as seating, art work, lighting, security CCTV cameras, ticket vending machines, bike lockers etc.

Page 6: T-FLEX Workshop Roger Snoble, L.A. Metro Chief Executive Officer October 29, 2007 Los Angeles County Metropolitan Transportation Authority

6

Orange Line Ridership

21,00520,217 20,659

19,004 19,048

21,428

23,24323,814 23,826

25,47524,804

23,814

25,618

-

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

18,000

20,000

22,000

24,000

26,000

28,000

Sep-06 Oct-06 Nov-06 Dec-06 J an-07 Feb-07 Mar-07 Apr-07 May-07 J un-07 J ul-07 Aug-07 Sep-07

Page 7: T-FLEX Workshop Roger Snoble, L.A. Metro Chief Executive Officer October 29, 2007 Los Angeles County Metropolitan Transportation Authority

7

North Hollywood Lowe Enterprises – Perspective

Orange Line Station

Red Line Station

Page 8: T-FLEX Workshop Roger Snoble, L.A. Metro Chief Executive Officer October 29, 2007 Los Angeles County Metropolitan Transportation Authority

8

Metro Gold Line Eastside Extension

Page 9: T-FLEX Workshop Roger Snoble, L.A. Metro Chief Executive Officer October 29, 2007 Los Angeles County Metropolitan Transportation Authority

9

6 Mile Alignment

1.7 Miles of Tunnel

8 Stations (6 At-grade

& 2 Underground)

Park & Ride Facility

Direct Connection to the Pasadena Metro Gold Line

$898.8 million

Opens in 2009

Gold

Line

Gold

Line

Metro Gold Line Eastside ExtensionProject Overview

Page 10: T-FLEX Workshop Roger Snoble, L.A. Metro Chief Executive Officer October 29, 2007 Los Angeles County Metropolitan Transportation Authority

10

• Excavation of both tunnels was completed in December 2006 with no measurable surface settlement.

• Construction of the two underground stations is underway.

Metro Gold Line Eastside Extension Under Construction

Page 11: T-FLEX Workshop Roger Snoble, L.A. Metro Chief Executive Officer October 29, 2007 Los Angeles County Metropolitan Transportation Authority

11

1st & Boyle