Page 1: T-76.115 Project Review SOLIData I2 Iteration 2005-FEB-08

T-76.115 Project Review

SOLIDataI2 Iteration

2005-FEB-08

Page 2: T-76.115 Project Review SOLIData I2 Iteration 2005-FEB-08

2

T-76.115 Project ReviewT-76.115 Project Review

Agenda

Project status (20 min) - Arttu Overview on the iteration – Arttu Goals – Arttu Realization of Tasks – Arttu Working Hours – Arttu LOCs – Janne Quality - Mikko Risks – Markus Change management – Markus Work practices – Arttu

Work results (25 min) presenting the iteration’s results

Releases DEMO

Plan for Next Iteration FD (5 min) - Arttu Questions/Discussion etc (10 min)

Page 3: T-76.115 Project Review SOLIData I2 Iteration 2005-FEB-08

3

T-76.115 Project ReviewT-76.115 Project Review

Introduction to the project

This project focuses on producing single-click Bluetooth connectivity between Symbian OS mobile device and Bluegiga server. The idea is to enable video streaming for smart phones in public places (e.g. train, bus).

Mobile

Access Point

Streaming server

Access Point

MobileMobileMobile

EasyStreaming application

BlueTooth / WLAN

LAN

Page 4: T-76.115 Project Review SOLIData I2 Iteration 2005-FEB-08

4

T-76.115 Project ReviewT-76.115 Project Review

Overview on the iteration

A successfully two mini-increment’s plan conducted in the I2 iteration (not successful in I1) Increased quality

The 1st test round revealed nasty bugs which we were not aware we had time to fix some of founded bugs of 1st testing round

Motivation The motivation was kept up because of clear mid-milestones

Early in move The mid-milestones forced continuous work

We had good start in the I2, better than in I1 Plan + requirements were all set before Christmas vacation Design + implementation was started during Christmas time Original plan was to start implementation before Christmas this was over-optimisms

We (almost everybody) had relaxing Christmas vacation – as planned

The team members have had long absences (unreachable) Arttu: 2004-DEC-15 – 2005-JAN-16 Heikki: 2005-JAN-13 – 2005-FEB-21 Pekka: 2005-FEB-01

Internal milestones were updated once during iteration We had buffer in internal plan as response to changing conditions

Testing was completed on time 1st round: 6 bugs found (2 critical, 2 major) 2nd round: 5 bugs found (0 critical, 2 major)

Two additional testing packets released The goal of the iteration is very well filled

Page 5: T-76.115 Project Review SOLIData I2 Iteration 2005-FEB-08

5

T-76.115 Project ReviewT-76.115 Project Review

Overview on the iteration – milestone update

Deliverable Deadline(changes bolded)

I2 iteration planning for customer/mentor Tue 2004-DEC-14

Requirements for I2 refined Thu 2004-DEC-16

1st testing release Mon 2005-JAN-24 – 18:00

1st testing round results Thu 2005-JAN-27

Test specification for customer review Fri 2004-JAN-28

2nd testing release Tue 2005-FEB-01 – 18:00

2nd testing round results Fri 2005-FEB-04

Delivery of increment’s deliverables for customer review Thu 2005-FEB-03

Document walkthroughs Mon 2005-FEB-07

Delivery of documents to customer/mentor Tue 2005-FEB-08

Updated

Page 6: T-76.115 Project Review SOLIData I2 Iteration 2005-FEB-08

6

T-76.115 Project ReviewT-76.115 Project Review

Status of the iteration’s goals

Goal 1: Easy delivery ”Two empty access points can be set up using memory stick. The YES mobile

application can be used from the both access points so that re-installation is not needed when changing the access point ”

Goal 2: Configurable New requirements to make the APP configurable

Goal 3: Fix bugs founded in I1 Mainly fixed (bug #5 not fixed)

Req ID Short description

FR-APP-090 The bearer handling of the YES application must not disturb or be affected by the original bearer configurations.

FR-APP-050 When starting the application it must connect to an available access point of the YES-provider configured into the YES application.The AP must configure the SIS package to include the following:

- Access point name

- Bearer name- Initial URL (start page)

FR-AP-040 The AP must be installed by sticking in a USB-stick without other user interactionIt must be possible to use a single USB stick with just one release of the software to install multiple AP’s.Prerequisite: WRAP in correct version

FR-USR-020 The system must be possible to use without manual configuration.NFR-040 The user does not need to reconnect to the system within a single

system using session.FR-APP-100 The GPL license text must be included in the app so that it can be seen

in the file-system of the phone named as ‘license.txt’.

FR-AP-060

FR-AP-050

Page 7: T-76.115 Project Review SOLIData I2 Iteration 2005-FEB-08

7

T-76.115 Project ReviewT-76.115 Project Review

Status of the iteration’s deliverables

Configurable version of the system implemented OK, selected requirements filled

some bugs still open Added 2 smaller requirements during the iteration

Project Plan Minor updates to update iteration plans, current version 1.44 OK, except detailed plans for FD iteration

Risk Management 3 closed risks

Requirements document 3 CRs (change request), current version 1.41

Technical Specification Complete, review held for version 1.1 (current 1.2)

Admin user manual Complete, review held for version 0.2 (current 0.4)

Testing overview for I2 System Test Plan and Report (includes test log)

2 plans+reports from both testing rounds Progress Report for I2 Architecture Design

No updates

Page 8: T-76.115 Project Review SOLIData I2 Iteration 2005-FEB-08

8

T-76.115 Project ReviewT-76.115 Project Review

Realization of the tasks

Planned Realized

PP I1 I2 I2 FD TotalFeasibility study 86 0 0 0 0 86

Requirements 24,1 0,5 12 8,75 4 37,35

Design 4 77,1 28 10,5 4 95,6

Implementation 0 161,65 145 198,75 60 420,4

Testing 0 23,75 40 41,6 70 135,4

Finalization & Delivery

10,25 17,5 20 8,5 19 55,25

Meetings 84,65 33,3 61 31,05 40 189

Project mgmt 59,9 15,75 28 30,45 25 131,1

Risks 0 1,25 5 0,5 2 3,75

Studying 78,75 13 10 0 0 91,75

General 13,9 17,25 34 34 19 84,15

Total 361,55 361,05 383 364,1 243 1330

Unplanned

Page 9: T-76.115 Project Review SOLIData I2 Iteration 2005-FEB-08

9

T-76.115 Project ReviewT-76.115 Project Review

Realization of the tasks

Design workshop was used Efficient

Implementation time was overrun by 37% Extremely difficult to estimate Bug fixes etc was not taken care well enough in the beginning New subtasks were added during iteration (e.g. INF:Maintenance) This includes also some ‘studying’ hours, because it's hard to separate

between studying and implementation. Learn by doing

Page 10: T-76.115 Project Review SOLIData I2 Iteration 2005-FEB-08

10

T-76.115 Project ReviewT-76.115 Project Review

Working hours by person

Janne was sick for 1 week Markus moved to new apartment

no internet connection, yet

Pekka’s hours were counted incorrectly -6 hours for the iteration (383h vs. 377h)

Realized hours in this iteration

Real Plan DiffArttu 30,3 30 0,3Heikki 28 24 4Tommy 48 49 -1Pekka 79,3 78 1,3Janne 58,3 73 -14,7Mikko 58,8 55 3,8Markus 57,8 68 -10,3Total 360,5 377 -16,5

Page 11: T-76.115 Project Review SOLIData I2 Iteration 2005-FEB-08

11

T-76.115 Project ReviewT-76.115 Project Review

Working hours by person

Overall, we followed the plan quite well!

Markus, Janne have more to do in FD iteration

more resources in peer-testing

Realized hours in this iteration Plan in the beginning of this iteration

PP I1 I2 Subtot FD TotalArttu 97 29 30 156 34 190Heikki 58 63 24 144 46 190Tommy 62 55 49 166 24 190Pekka 41 71 78 190 0 190Janne 37 47 73 157 33 190Mikko 38 45 55 138 52 190Markus 31 51 68 150 40 190Total 363 361 377 1101 229 1330

Latest plan (inc. realized hours and other updates)

PP I1 I2 Subtot

FD Total

Arttu 97 29 30 156 34 190Heikki 58 63 28 148 42 190Tommy 62 55 48 165 25 190Pekka 41 71 79 191 0 191Janne 37 47 58 142 48 190Mikko 38 45 59 142 48 190Markus 31 51 58 140 50 190Total 363 361 360 1085 247 1331

Real Plan DiffArttu 30,3 30 0,3Heikki 28 24 4Tommy 48 49 -1Pekka 79,3 78 1,3Janne 58,3 73 -14,7Mikko 58,8 55 3,8Markus 57,8 68 -10,3Total 360,5 377 -16,5

Page 12: T-76.115 Project Review SOLIData I2 Iteration 2005-FEB-08

12

T-76.115 Project ReviewT-76.115 Project Review

Software size in Lines of Code (LOC)

PP I1 I2 FD

Total (NCLOC + COM) 0 2538 1853

Comments (COM) 0 779 1013

PP I1 I2 FDCCommDbDump (implemented as separate testing software) 0 180/2 197/2

CYesAOLoader 0 0 97/29

CYesApp 0 0 15/29

CYesAppUi 0 0 69/47

CYesConfig 0 0 236/206

CYesContainer 0 963/329 697/390

CYesDocument 0 242/112 130/112

TYesIndex 0 0 34/2

CYesProfile 0 0 126/23

Total (NCLOC + COM) 0 2538 1853

Comments (COM) 0 779 1013

More detailed table

Page 13: T-76.115 Project Review SOLIData I2 Iteration 2005-FEB-08

13

T-76.115 Project ReviewT-76.115 Project Review

Software size (Continued)

The basis for the YES-App is OfficeAgent

Current implementation has reduced the dependencies for the original code

practically everything has been written again, own code this is reason for reduced number of LOCs Removed unneeded code from OfficeAgent

Page 14: T-76.115 Project Review SOLIData I2 Iteration 2005-FEB-08

14

T-76.115 Project ReviewT-76.115 Project Review

BugID

severity end of I1 (30.11.04)

test round #1(26.1.05)

test round #2(4.2.05)

4 Minor Open Open Fixed5 Major Open Open Open6 Trivial Open Fixed Fixed7 Enhancemen

tRe-evaluate Open Fixed

9 Enhancement

Re-evaluate Fixed Fixed

10 Minor -- Open Won’t fix11 Minor -- Open Not verified13 Critical -- Open Open14 Major -- Open Open15 Critical -- Open Fixed16 Enhancemen

t-- -- Open

17 Minor -- -- Open18 Major -- -- Open19 Major -- -- Open20 Enhancemen

t-- -- Open

21 Minor -- -- Open

Bug history

Page 15: T-76.115 Project Review SOLIData I2 Iteration 2005-FEB-08

15

T-76.115 Project ReviewT-76.115 Project Review

bug ID

severity description cost (h)

5 major User cannot receive the installation package if some other user is at the state where he selects if he accepts the installation package from AP.

3?

13 critical Application crashes if it tries to contact to some other BT then the AP. 10

14 major Application crashes if no appropriately named BT devices are found. 7

16 enhancement

Application crashes if prefix is too long. 5

17 minor Reading empty values from the configuration file does not work. 1

18 major Application crashes after going out of range. 17

19 major Changes in the AP's BT name may not reach the application. *

20 enhancemnt

The GPL license file could not be read with default software. *

21 minor URL longer then 50 crashes the program. 3

Open bugs and estimated cost to fix

Page 16: T-76.115 Project Review SOLIData I2 Iteration 2005-FEB-08

16

T-76.115 Project ReviewT-76.115 Project Review

Quality assessment

Legend

Coverage:

0 = nothing

1 = we looked at it

2 = we checked all functions

3 = it’s tested

Quality:

= quality is good

= not sure

= quality is bad

Functional area Coverage Quality Comments

YES Application 3 Few major bugs still exist, but these are extreme cases. Functionalities are ok.

Access point 3 Not tested with more then two phones. Deployment ok.

Streaming server 2 All ok.

We could not test with many phones (>2) because additional phones were not available early enough.

to be conducted in FD iteration

Page 17: T-76.115 Project Review SOLIData I2 Iteration 2005-FEB-08

17

T-76.115 Project ReviewT-76.115 Project Review

Quality - Description of configurable version?

YES Application UI improved – nicer graphics Improved BT connection handling, e.g. in closing the App. Tested with multiple phones, and with very ‘nasty’ settings in them Testing was performed also from security point of view more ‘interesting’

test cases

Access Point Can be released using USB stick

Does not include WRAP upgrading

Streaming Server No modifications during I2.

Page 18: T-76.115 Project Review SOLIData I2 Iteration 2005-FEB-08

18

T-76.115 Project ReviewT-76.115 Project Review

Risks

Open risks Technology – 0 risks Development environment – 2 risks Requirements – 1 risk Resources - 3 risks Implementation – 1 risk

Changes Tech_Risk_1 (”Bluetooth driver”) CLOSED Tech_Risk_2 (”Properties of devices”) CLOSED Rsc_Risk_1 (”Too many hours planned for iteration I1”) CLOSED Impl_Risk_1 (”Responsibilities unknown”), propability MEDIUM LOW

Page 19: T-76.115 Project Review SOLIData I2 Iteration 2005-FEB-08

19

T-76.115 Project ReviewT-76.115 Project Review

Change Management

Change request (CR1) opened to improve ’one-click’ requirement Opened in I1 CANCELLED CR2 has another approach for that one (configurable)

Change request (CR2) opened to improve requirements for I2 ACCEPTED Missing implementation for improved one-click configurable

Change request (CR3) opened to define BT connection requirement better, and add GPL license text into the APP

ACCEPTED

Page 20: T-76.115 Project Review SOLIData I2 Iteration 2005-FEB-08

20

T-76.115 Project ReviewT-76.115 Project Review

Requirement Management

ComponentUser reqs, USR 0 (9) 3 (9) 9 (9) 0 (9)YES Client Application, APP 0 (8) 3 (8) 8 (10) 0 (10)YES Server, STR 0 (6) 1 (6) 4 (6) 0 (6)Connectivity, CON 0 (3) 2 (3) 2 (3) 0 (3)Access Point, AP 0 (4) 1 (4) 6 (6) 0 (6)Non-Functional, NFR 0 (4) 0 (4) 2 (4) 0 (4)

PP I1 I2 FD

WLAN requirements are still in req spec Streaming server has requirement for broadcast streaming not

going to be done Non-functional requirements (NFRs) almost implemented not tested

Legend

N (M)

N = # of requirements implemented

M = total # of requirements

Page 21: T-76.115 Project Review SOLIData I2 Iteration 2005-FEB-08

21

T-76.115 Project ReviewT-76.115 Project Review

Used work practices

New practices used in I2 Started to use own task for bug fixings (mentor proposed) Improved bug analyzing price added for each bug (mentor proposed) Weekly code release for the customer Pair programming in mobile application Requirement matrix status of each requirement

Page 22: T-76.115 Project Review SOLIData I2 Iteration 2005-FEB-08

22

T-76.115 Project ReviewT-76.115 Project Review

Results of the iteration

Major deliverables of the I2 iteration Configurable version of the system

Missing implementation for improved one-click configurable Admin user manual Test plan & reports

Minor deliverables Review report Change requests (3 pcs)

Updates Project Plan Requirements Specification Architecture Design Technical Specification SEPAs

Page 23: T-76.115 Project Review SOLIData I2 Iteration 2005-FEB-08

23

T-76.115 Project ReviewT-76.115 Project Review

DEMO

Page 24: T-76.115 Project Review SOLIData I2 Iteration 2005-FEB-08

24

T-76.115 Project ReviewT-76.115 Project Review

FD iteration

10-h

elm

i

17-h

elm

i

24-h

elm

i

3-m

aalis

10-m

aalis

Iteration planning

Refining reqs/arch

Design

Implementation

Testing

Peer testing

Finalization+delivery

Review s

Iteration planning

Delivery

Delivery for reviewTesting release

Testing release

Test spec review

PP I1 I2 FD TotalFeasibility study 86 0 0 0 86

Requirements 24,1 0,5 8,75 4 37,35

Design 4 77,1 10,5 4 95,6

Implementation 0 161,65 198,75 60 420,4

Testing 0 23,75 41,6 70 135,4

Finalization & Delivery 10,25 17,5 8,5 19 55,25

Meetings 84,65 33,3 31,05 40 189

Project mgmt 59,9 15,75 30,45 25 131,1

Risks 0 1,25 0,5 2 3,75

Studying 78,75 13 0 0 91,75

General 13,9 17,25 34 19 84,15

Total 361,55 361,05 364,1 243 1330

Risks in FD iteration: Pekka in Australia (not available

anymore for the project) absence of Mikko, Markus &

Tommy at end of iteration. Especially Mikko missing at second testing phase

Janne, Heikki to cover

Page 25: T-76.115 Project Review SOLIData I2 Iteration 2005-FEB-08

25

T-76.115 Project ReviewT-76.115 Project Review

Questions/Discussion

DEMO

Requirements

Testing

Results – used effort

Implementation

FD iteration