system voltage planning brian moss pd / transmission planning transmission planning overview october...
TRANSCRIPT
System Voltage Planning
Brian MossPD / Transmission Planning
Transmission Planning OverviewOctober 30, 2007
October 30, 2007 System Voltage Planning 2
System Voltage Planning
Nuclear LOCA Voltage Studies (February) Identifies future nuclear switchyard voltage
deficiencies by performing LOCA simulation coupled with contingency analysis on system planning models
Determines minimum nuclear switchyard voltage limits, used to create generator voltage schedules and the TCC’s SCADA/RTCA alarm setpoints for the current year
Annual System Voltage Screening (Spring) Identifies future voltage deficiencies by performing
contingency analysis on system planning models
Annual System Voltage Analysis (Fall) Identifies existing voltage deficiencies by reviewing
the past year’s system voltage performance using PI data
October 30, 2007 System Voltage Planning 3
System Voltage Planning
Annual Transmission Capacitor Optimization (Fall) Identifies optimal sites for capacitor placement to
mitigate voltage deficiencies
Annual System Voltage Optimization (Fall) Identifies transmission transformer tap setting and
switched capacitor control setting adjustments to improve system voltage performance
Seasonal System Voltage Optimization Creates “Generator Voltage Schedules” to provide
efficient utilization of system generator voltage support, while maintaining transmission system voltage guidelines and minimum nuclear switchyard voltage limits
Completed and distributed at least 2 weeks prior to start of each season (Spring, Summer, Fall, Winter)
October 30, 2007 System Voltage Planning 4
Nuclear LOCA Voltage Studies
Nuclear Generation Inputs (January) Latest minimum grid voltage requirements, as well as
shutdown and LOCA auxiliary loads for each unit
Normal, Pre-LOCA Base Cases Latest summer peak and valley models
Sister Unit Off-Line, Pre-LOCA Base Cases Dispatch variations of normal, pre-LOCA base cases Outage non-LOCA unit at the nuclear station being
evaluated System redispatched to replace outaged unit and
serve its shutdown auxiliary load
October 30, 2007 System Voltage Planning 5
Nuclear LOCA Voltage Studies
Pre-LOCA Contingencies
Pre-LOCA, post-contingency scenario solved to a new steady-state with all equipment (capacitors and transformer taps) allowed to adjust per their control settings
GeneratorLargest Generating Unit on a Voltage
Level at Each Generating Station
Transmission Line44, 100, 230, and 500 kV Lines with
only the Worst-Case Line Outaged for Parallel, Double-Circuit Lines
Transformer100/44, 115/100, 161/66, 230/44,
230/100, 230/100/44, 230/161, and 500/230 kV Transformers
Shunt (Capacitors and Reactors)44, 66, 100, 161, 230, and 500 kV
Capacitors and Reactors
October 30, 2007 System Voltage Planning 6
Nuclear LOCA Voltage Studies
LOCA Event Simulate the initiation of a LOCA event on each pre-
LOCA, post-contingency scenario LOCA unit is outaged and LOCA auxiliary load is applied Energy is imported from off-system to replace outaged
unit and serve its LOCA auxiliary load In order to estimate the switchyard voltage immediately
following the LOCA event, transformer taps and capacitors are prevented from adjusting in the solution due to their long (30+ seconds) response times
Post-LOCA Voltage Evaluation Determine the “LOCA Voltage Drop” (post-LOCA minus
pre-LOCA, post-contingency nuclear switchyard voltage) Post-LOCA voltages are only supported by the pre-LOCA,
post-contingency capacitor MVAr support and the generator MVAR output of all remaining on-line units adjusting to maintain their generator voltage schedules in response to the LOCA event
October 30, 2007 System Voltage Planning 7
Nuclear LOCA Voltage Studies
Pre-Contingency Voltage Limits Equal to minimum grid voltage requirement plus the
worst-case (maximum) “LOCA Voltage Drop” Real-time nuclear switchyard voltage required to
maintain minimum grid voltage requirement in the event of the worst-case, pre-LOCA contingency followed by the initiation of a LOCA event
Generator Voltage Schedule Creation Maintains minimum nuclear switchyard voltage limits
equal to the pre-contingency voltage limits plus 2 kV Additional 2 kV provides an added margin of system
voltage support to the system above the required pre-contingency voltage limits
October 30, 2007 System Voltage Planning 8
Generator Voltage Schedules
Pre-Optimization Generator Voltage Schedule (GVS) Cases
Spring(3/21 - 6/20)
Summer(6/21 - 9/20)
Fall(9/21 - 12/20)
Winter(12/21 - 3/20)
Max Load(Mon-Fri)
-100%
Summer Peak(0730-2330)
- -
Peak(Mon-Fri)
76%Summer Peak(0530-2130)
90%Summer Peak(0730-2330)
76%Summer Peak(0530-2130)
90%Winter Peak(0530-2030)
Off-Peak(Sun-Thur)
42%Summer Peak(2130-0530)
60%Summer Peak(2330-0730)
42%Summer Peak(2130-0530)
65%Winter Peak(2030-0530)
Weekend(Fri-Sun)
42%Summer Peak(2130-2130)
68%Summer Peak(2330-2330)
42%Summer Peak(2130-2130)
60%Winter Peak(2030-2030)
October 30, 2007 System Voltage Planning 9
Generator Voltage Schedules
Pre-Optimization GVS Cases (continued) Latest summer peak, winter peak, or valley models Add transmission projects installed and in-service for
the majority of the season− Capacitors (including portables)− Transformers (including in-service system spares)− Transmission lines (including significant outages)
Generator maintenance outage schedule− Outage generators which are scheduled to be off-line for
maintenance during the majority of the season
Typical dispatch with reduced (75%) generator MVAr capability− Provides a margin of additional MVAr capability not
required to support the provided generator voltage schedules under typical conditions
− Allows generators to follow the provided generator voltage schedules under varying system conditions
Firm, planned transactions
October 30, 2007 System Voltage Planning 10
Generator Voltage Schedules
Optimal Power Flow (OPF) Solution Objectives
− Minimize active (MW) and reactive (MVAR) power losses
Constraints− Power balance equation− Transmission system voltage guidelines− Minimum nuclear switchyard voltage limits
Calculated in “Nuclear LOCA Voltage Studies”
− Nuclear generator bus voltage limits Voltages limited by nuclear station auxiliary system design
− Important 100 kV bus voltage limits Significant load service points
− Duke MVAr interface flow constraint Prevent schedules from relying on off-system MVAr import
(0 MVAr net interchange)
− Generator voltage limits− Merchant (IPP) MVAr support requirements
October 30, 2007 System Voltage Planning 11
Generator Voltage Schedules
Optimal Power Flow (OPF) Solution (continued) Transformer tap settings are fixed
− Tap settings are optimized in “Annual System Voltage Optimization” and would not be adjusted seasonally
Controls− Generator voltage schedules (MVAr output)− Capacitors (MVAr voltage support)
Generator voltage schedules, Beckerdite SVC voltage setpoint, and reactors’ status are extracted from the optimized cases and provided to the SOC, TCC, and the generation operators as a guide for maintaining optimal system performance under typical seasonal Max Load, Peak, Off-Peak, and Weekend conditions
October 30, 2007 System Voltage Planning 12