system based audit of diakonia · 2014. 4. 8. · diakonia head office, diakonia‘s auditor,...
TRANSCRIPT
Final Report 2010-11-18
SYSTEM-BASED AUDIT
OF
DIAKONIA
Ms Cristina A. Rodriguez-Acosta
Ms Stina Waern
Ms Lina Lenefors
Mr Arne Svensson
System-based Audit of Diakonia
2
Table of Contents
1 Executive Summary ............................................................................................................. 6
1.1 Introduction .......................................................................................................................... 6
1.2 Observations and analysis .................................................................................................... 6
1.2.1 The organizational structure ................................................................................ 6
1.2.2 Management of operations ................................................................................... 2
1.2.3 Financial management and control ..................................................................... 3
1.2.4 Aid effectiveness ................................................................................................... 4
1.3 Overall conclusions .............................................................................................................. 4
1.4 Recommendations ................................................................................................................ 5
2 Introduction .......................................................................................................................... 7
2.1 Sida‘s support through the NGO-appropriation ................................................................... 7
2.2 Diakonia ............................................................................................................................... 7
2.3 The co-operation between Diakonia and Sida ...................................................................... 8
2.4 Purpose and scope of this system-based audit ...................................................................... 8
2.5 The Audit team ..................................................................................................................... 8
2.6 Methodology ........................................................................................................................ 8
2.6.1 General approach ................................................................................................. 8
2.6.2 Methodology ......................................................................................................... 9
2.6.3 Reviewed documents and persons interviewed .................................................. 11
2.7 Field visits .......................................................................................................................... 11
2.7.1 Visited regional offices and country offices ....................................................... 11
2.7.2 Visited partner organisations ............................................................................. 11
2.7.3 Core support or project support ......................................................................... 15
2.8 This report and how to read it ............................................................................................ 16
3 Organisational structure .................................................................................................... 16
3.1 Vision, mission statement, goals, policies and activity plans ............................................ 16
3.1.1 Steering documents ............................................................................................. 16
3.1.2 Observations and analysis .................................................................................. 18
3.1.3 Conclusions and recommendations .................................................................... 20
3.2 Mandate and the role of the governing board ..................................................................... 21
3.2.1 Observations and analysis .................................................................................. 21
3.2.2 Conclusions and recommendations .................................................................... 22
3.3 Organization and decision- making .................................................................................... 22
3.3.1 Observations and analysis .................................................................................. 23
3.3.2 Conclusions and recommendations .................................................................... 26
System-based Audit of Diakonia
3
4 Management of operations ................................................................................................ 26
4.1 Results Based Management ................................................................................................ 26
4.1.1 Diakonia’s tools and methods for programme cycle management (PCM) ........ 27
4.1.2 Observations and analysis .................................................................................. 29
4.1.3 Conclusions and recommendations .................................................................... 31
4.2 Criteria and procedures for selection of partners and their project/programmes ............... 32
4.2.1 Observations and analysis .................................................................................. 32
4.2.2 Conclusions and recommendations .................................................................... 38
4.3 Involvement and ownership of partners and target groups in planning, monitoring and
evaluation of projects/programmes .................................................................................... 38
4.3.1 Observations and analysis .................................................................................. 38
4.3.2 Conclusions and recommendations .................................................................... 39
4.4 Systems for risk assessment and risk management (including corruption as a risk) ......... 40
4.4.1 Observations and analysis .................................................................................. 40
4.4.2 Conclusions and recommendations .................................................................... 41
4.5 Exit strategies with regard to sustainability of partner organisations as well as to projects and
programmes ........................................................................................................................ 42
4.5.1 Observations and analysis .................................................................................. 43
4.5.2 Conclusions and recommendations .................................................................... 44
5 Financial management and control .................................................................................. 44
5.1 Financial systems ............................................................................................................... 44
5.1.1 Observations and analysis .................................................................................. 45
5.1.2 Conclusions and recommendations .................................................................... 46
5.2 Compliance with Agreements ............................................................................................ 47
5.2.1 Observations and analysis .................................................................................. 47
5.2.2 Conclusions and recommendations .................................................................... 49
5.3 Transfers of funds and bank and cash holdings ................................................................. 50
5.3.1 Observations and analysis .................................................................................. 50
5.3.2 Conclusions and recommendations .................................................................... 51
5.4 Systems, rules and routines for procurement ..................................................................... 52
5.4.1 Observations and analysis .................................................................................. 52
5.4.2 Conclusions and recommendations .................................................................... 53
5.5 Audits ................................................................................................................................. 53
5.5.1 Observations and analysis .................................................................................. 53
5.5.2 Conclusions and recommendations .................................................................... 56
6 Aid effectiveness ................................................................................................................. 57
6.1.1 Observations and analysis .................................................................................. 57
System-based Audit of Diakonia
4
6.1.2 Conclusions and recommendations .................................................................... 59
7 Sammanfattning (Executive Summary in Swedish) ........................................................ 61
7.1 Inledning ............................................................................................................................... 61
7.2 Observationer och analys ..................................................................................................... 61
7.2.1 Organisationsstruktur ............................................................................................... 61
7.2.2 Verksamhetsstyrning ................................................................................................. 62
7.2.3 Ekonomisk styrning och kontroll ............................................................................... 63
7.2.4 Biståndseffektivitet .................................................................................................... 63
7.3 Övergripande slutsatser ........................................................................................................ 64
7.4 Rekommendationer .............................................................................................................. 65
Annexes (Separate document)
Annex 1 Terms of Reference
Annex 2 Inception Report
Annex 3 Validation Matrix
Annex 4 Persons Interviewed and Consulted
Annex 5 Documentation of Materials Reviewed and Cited
Annex 6 Brief field visit reports from partner organisations
Annex 7 Notes on AWEPON
Annex 8 Notes on KEWWO
Annex 9 Diakonia‘s policy
System-based Audit of Diakonia
5
Acronyms and Abbreviations
ACT Action by Churches Together
AWEPON African Women´s Economic Policy Network
CJPC Catholic Justice and Peace Commission
CO Country office
CSO Civil Society Organisations
EFK Evangeliska Frikyrkan
EPZ Export Processing Zones
ESA Eastern and Southern Africa
HAP Humanitarian Accountability Partnership
HO Head office
KEWWO Kenya Women Workers Organization
NGO Non-Governmental Organization
OVC Orphaned and Vulnerable Children
PCM Programme cycle management
PHS Project Handling System
PME Planning, Monitoring and Evaluation
PO Partner Organisation
RBM Results based Management
RFP Request for Proposal
RO Regional office
SA Svenska Alliansmissionen
Sida Swedish International Development Cooperation Agency
ToR Terms of Reference
System-based Audit of Diakonia
6
1 Executive Summary1
1.1 Introduction
The base and board of Diakonia are presently five Swedish protestant churches: the Swedish Alliance
Mission, the Baptist Union of Sweden, Inter Act, the United Methodist Church and the Mission
Covenant Church of Sweden. Diakonia works for a fair and sustainable development characterised by
respect for all human rights, democracy, gender equality, economic and social justice, and peace and
reconciliation. Diakonia believes a strong and vigorous civil society is of fundamental importance for
any development to be sustainable. Diakonia seldom carry out development activities of its own in
the South, but supports local partner organisations. Together with members of the congregations
Diakonia works in Sweden with popular education, mobilisation, campaigning and fundraising.
1.2 Observations and analysis
The Audit Team has analyzed relevant documentation available at Diakonia and Sida. The Audit
Team has carried out field visits to the regional offices for Eastern and Southern Africa (ESA) and
Latin America and the country offices in Peru, Colombia and Kenya to study documentation and
interview key informants. To study the whole organisational chain the field visits have also included
visits to a sample of 15 Partner Organisations to review their systems and interview representatives of
the Partner Organisations. The Team has also conducted interviews with staff at Sida, staff at
Diakonia head office, Diakonia‘s auditor, Diakonia‘s Chair of the Board and a sample of four other
members of Diakonia‘s Board. In total some 135 persons have been interviewed.
In summary, the Audit Team‘s observations and analyses are the following using the structure of the
Audit questions per ToR:
1.2.1 The organizational structure
Vision, mission statement, goals, policies and activity plans:
Diakonia‘s task, overall objective and vision are shared by the Board and staff and all well rooted
throughout the organisation. Among the Partner Organisations Diakonia is appreciated not only for
the funds but also for the shared values and the added-value of the support to the capacity
development. However, the Team is of the opinion that changes in the membership structure of the
discussed magnitude may have the potential of jeopardising the business should the values, mission
& vision be significantly changed without having a consensus among the most important
stakeholders
Mandate and the role of the governing board:
The mandate and the role of the Board are clear. However, the changes in the membership structure
will influence the Board and create a significant risk for Diakonia that must be adequately addressed.
The consequences of the merge of three of the five member organisations into one and the risk that
1 En sammanfattning på svenska återfinns i kapitel 7. The Executive Summary is translated into Swedish in Chapter 7.
System-based Audit of Diakonia
2
the remaining two member organisations will withdraw their membership should be carefully
analysed.
Organization and decision- making:
Diakonia is in the process of establishing a more decentralised structure facilitating flexibility and
ability to adapt to new circumstances and development needs. So far this process has proven to be
successful. Performance contracts and annual appraisals would increase the results orientation and
secure a good working environment with clear expectations and adequate feedback where good
results are acknowledged and rewarded.
The organisation and the decision-making mandate and delegation procedures are clear. The PHS is
well suited for Sida-funded programmes and projects. However, it is not flexible enough to handle
funding from EU and UN.
1.2.2 Management of operations
Results based management (RBM):
Diakonia at all levels as well as its Partner Organisations are making significant efforts to increase
the results orientation. The PME Handbook defines minimum standards for the PCM in a
comprehensive and adequate way. The PME Handbook and the PHS are used in practice at all levels.
The Management Reports provides a key information flow from the Country Programmes to the RO
and the HO. RBM is practiced but there is room for improvements when it comes to formulating
clear objectives and measurable results indicators.
Criteria and procedures for selection of partners and their project/programmes:
The criteria for selecting countries and building programmes are adequate and used in practice in the
ongoing restructuring and decentralisation process. However, it may not always be possible to get
funding to a comprehensive Country programme of the required size. The criteria for choosing
Partner Organisations and maintaining partnership are also adequate and used in practice.
Involvement and ownership of partners and target groups in planning, monitoring and
evaluation of projects/programmes:
Diakonia has a well developed view on the involvement and ownership of partners and target groups
in planning, monitoring and evaluation of projects/programmes with clear distinction between
Diakonias responsibility for its programmes and the Partner Organisations responsibility for their
programmes and projects. These fundamental principles for Diakonia‘s cooperation are adhered to at
all levels. However, baseline information is seldom gathered in a systematic way.
Systems for risk assessment and risk management (including corruption as a risk):
The decision memorandums made up in PHS include risk analysis. Diakonia has a Zero tolerance on
corruption. The format and instructions for reporting suspicions of corruption or misuse of funding
are comprehensive. In the studied Country programmes there are few incidents on suspected
corruption or misuse of funding. These incidents, however, indicate some weaknesses in Diakonia‘s
processes and division of responsibilities in case of suspicion of corruption or misuse of funding.
Exit strategies with regard to sustainability of partner organisations as well as to projects and
programmes:
System-based Audit of Diakonia
3
Diakonia has routines for closing a programme and criteria for phasing out Partner Organisations.
However, there are no exit strategies with regard to sustainability of Partner Organisations. It seems
to be rare to phase out a partner because it is able to sustain of its own with other funding.
1.2.3 Financial management and control
Financial systems:
All financial information for Diakonia is registered in Visma (information from PHS, Hogia/Flex,
Mysoft and Local financial systems). However, the processes are inefficient due to the use of several
different systems at different levels. There are plans to further develop the financial system as well as
the PHS with the aim to design a comprehensive global system. This will have the potential to
increase the efficiency significantly as the present overlaps and duplications will be eliminated.
Compliance with Agreements:
Diakonia meets Sida‘s terms and conditions with a few exceptions as detailed in this report. The new
agreements with Partner Organizations and the close monitoring of the Partner Organisations internal
control system has the potential of securing that the Partner Organisations also comply with the
regulations. However, the monitoring of the Partner Organisations internal control system should be
done more systematically through more frequent visits to the partners. In order to avoid reporting
through several levels it might in some cases be possible to use tripartite contracts.
Transfers of funds and bank and cash holdings:
One of the tree visited Country offices requires only one signature for check payments, bank
transfers, and financial transactions. Cash payments have in a few Partner Organisations been done in
a way that opens up for misuse of funding and corruption. Diakonia has not always taken adequate
action not even in cases where this problem has been reported by the auditor in the management
letter.
Systems, rules and routines for procurement:
Diakonia has procurement guidelines in place. These should also be applied by the Partner
Organisations. However, in practice procurement is not even regulated in all contracts with Partner
Organisations. Some Partner Organisations have procurement regulations in place that are meeting
International standards. Other Partner Organisations are practicing procurement in a way that opens
up for corruption and misuse of funding.
Audits:
In member-based Partner Organisations it is stressed that the Auditor‘s report is directed to the
members. The Management letter should be available for the Board, the members and the donors
upon request. Some local auditors are reluctant to issue both specific Audit Certificates and Audit
reports arguing that their Audit opinion in the Audit report is what they are required to deliver
according to the International Accepted Standards they are using. The competence is high enough at
all levels of Diakonia to analyse audit reports and management letters. However, there is need to
improve the processes when it comes to how Diakonia act in practice on suspected irregularities.
System-based Audit of Diakonia
4
1.2.4 Aid effectiveness
Diakonia respect the Partner Organisations‘ ownership and is actively supporting the further
development of their capacity. Diakonia try to align with the Partner Organisations‘ own systems and
procedures as far as possible. Diakonia also tries to coordinate reporting and harmonise requirements
with other donors to a particular Partner organisation. Diakonia has been active in the area of aid
effectiveness especially on the global level. Diakonia has declared its awareness of the need to
continue to work pro-active in this regard.
1.3 Overall conclusions
The aim of the System-based audit is in the ToR stated as quoted in the table below. The Audit Team
has for each aim summarized the overall conclusions in the table.
Aim of the System-based audit The Audit Team’s assessment
to examine the reliability and relevance of the
systems for operational and financial control that
exist in Diakonia, and to assess to what extent that
the systems are adhered to and implemented on all
levels within the organization
1. The systems for operational and financial control
at Diakonia are relevant and reliable. However, there
is a tendency not to act systematically and fast
enough when corruption or misuse of funding can be
suspected.
2. The systems are implemented on all levels within
the organization. The internal systems used by
Partner Organisations are in most cases meeting at
least an equivalent standard. However, some Partner
Organisations have weak internal control.
to determine, on the basis of the examination,
whether the documentation and reports received
by Sida under current agreements reflect the real
situation, and can therefore be considered to
function as reliable data for Sida in the assessment
processes
The documentation that is received by Sida under
current agreements reflects the real situation, and can
therefore be considered to function as reliable data
for Sida in the assessment processes.
to assess if Diakonia meets Sida‘s terms and
conditions, as well as assess if their control system
secure that the partners also comply with these
regulations
1. Diakonia meets Sida‘s terms and conditions with
few exceptions as detailed in the report.
2. Diakonia‘s control system secures that the
partners also comply with these regulations with few
exceptions as detailed in this report.
to provide inputs to the organization‘s processes
of change and systems development.
The Audit Team has in the report provided Diakonia
with concrete recommendations on how to further
develop the management systems.
The more detailed conclusions are summarized at the end of each section.
System-based Audit of Diakonia
5
1.4 Recommendations
The recommendations are presented at the end of each section. The recommendations proposed
herein are consistent with the major findings and conclusions presented above. The Audit Team has
the following recommendations in order of priority2:
Highest priority (in the order they appear in the report):
Diakonia goes through a transparent institutional visioning process with the aim at reaching
consensus on the long-term direction and a shared vision within the framework of the new
membership architecture (section 3.1)
The impact of the changes regarding Diakonias member organisations should be carefully
analysed including a risk assessment (section 3.2)
Diakonia should introduce Performance contracts and annual appraisals (section 3.3)
PHS should be developed as intended to facilitate also the operations of projects funded by
the EU, the UN and other donors (section 3.3)
The PME Handbook should be further developed in order to increase the flexibility on RO
and CO levels especially when Programmes have support from others than Sida (section 4.1)
Objectives and results indicators for programmes and projects should be thoroughly
developed in order to provide necessary and valid information for the further development of
the programmes and projects (section 4.1).
Diakonia should assist its Partner Organisations in introducing Results Based Management
and the development of precise and measurable objectives and results indicators (section 4.1).
Diakonia should continue its efforts to implement participatory monitoring and evaluation
systematically in cooperation with its Partner Organisation (section 4.1)
Diakonia HO should give RO systematic feed-back on the reports (section 4.1)
In targeted countries where it is difficult to finance a cost-effective programme through core
funding Diakonia should consider reviewing the design of the Country programmes in order
to facilitate having a project portfolio financed by different donors in addition to the core
programme (section 4.2)
Diakonia should implement a model for risk assessments and risk management (section 4.4)
Diakonia and its Partner Organisations should carefully follow up the misuse of funding that
has been reported in the past and continue to report any suspected misuse in the future.
(section 4.4)
Diakonia should implement a common process on how to handle reported incidents and mis-
use of funding (section 4.4)
Incident reports should always be written in PHS without delay (section 4.4)
When incidents of suspected misuse of funding has been reported in a partner organisation the
Regional manager should be responsible for the investigation and the investigation should be
carried out at the regional office (section 4.4)
Diakonia should intensify its efforts to increase the compliance with the agreements with Sida
(sections 5.2)
Diakonia should monitor the Partner Organisations‘ internal controls systems in a more
systematic way (section 5.2)
2 The recommendations with highest priority are marked (h) in the relevant section.
System-based Audit of Diakonia
6
Diakonia should consider using tripartite contracts when activities are being coordinated by a
Partner Organisation but implemented by other organisations (section 5.2)
As a precaution all checks and financial transactions should be signed by two people (section
5.3)
Diakonia should require that cash payment in Partner organisations should not be allowed for
payment over for example 1 000 SEK (section 5.3)
Diakonia includes procurement regulations in all contracts with Partner Organisations (section
5.4)
Diakonia in its follow up of the Partner Organisations internal control secure compliance with
the procurement regulations (section 5.4)
Diakonia should establish routines and incentives that guarantee that audit reports, audit
certificates and management letters are submitted in time (section 5.5)
Lower priority (in the order they appear in the report):
Diakonia should develop a communication strategy for the organisation globally (section 3.1)
Diakonia should review its reporting system with the aim to avoid duplications and focus on
relevant information for different stakeholders (section 4.1)
Diakonia should in its dialog with Partner Organisations more explicit ask for risk
assessments and information on risk management (section 4.4)
Diakonia should clarify the criteria for different types of partnership with and without
financial support (section 4.5)
In the agreements with the Partner Organisations Diakonia should request them to conduct
baseline studies (section 4.5)
Diakonia continues its efforts to implement an efficient financial management system (section
5.1)
Diakonia should visit the Partner Organisations more frequently for monitoring their internal
control system (section 5.2)
Diakonia should agree on realistic deadlines particularly in the case of projects funded
through Partner Organisations head offices to lower organisational levels (section 5.2)
Diakonia should change the requirements when it comes to signing the contracts to comply
with the Partner Organisation‘s own regulations (section 5.3)
Diakonia should advice its Partner Organisations that the Management letter should be
available for the Board, the members and the donors upon request (section 5.5)
Diakonia should make efforts to have regular meetings with other organisations that support
partners in the same country (section 6)
Diakonia should always actively participate in meetings that the Partner Organisations are
organising for their funders (section 6)
Diakonia should discuss the added value of regional cooperation with regional churches and
networks (section 6)
System-based Audit of Diakonia
7
2 Introduction
2.1 Sida’s support through the NGO-appropriation
The goal with Sida‘s support to civil society in development co-operation is to promote the
development of a vibrant and democratic civil society that improves the possibilities for poor people
to improve their living conditions3. This objective also encompasses support to and through Swedish
Civil Society Organisations (CSOs) via the appropriation for non-governmental organisations (NGO-
appropriation).
Sida gives high priority to efficiency and quality assurance in its development co-operation. Within
the framework of its responsibility to exercise controls, Sida has the assignment of following up that
development co-operation funds are used efficiently for intended purposes, regardless of how the
funds are channelled. Sida‘s basic approach in respect of ownership of contributions implies that its
development co-operation partners are responsible for the implementation of contributions, and thus
that partners also have the responsibility for exercising control of its operations.
To enable Sida to follow up whether the frame organisations are able to fulfil their contractual
obligations vis-à-vis Sida, Sida has decided to make regular system-based audits of the organisations
with which Sida has framework agreements on grants from the appropriation for CSOs.
2.2 Diakonia
Diakonia is a Christian organization that together with local partners works for sustainable change for
the most vulnerable and poor people in the world. Diakonia is formed by five Swedish churches that
initiated its work in 1966. Diakonia‘s member organisations are: The Swedish Covenant Church
(Svenska Missionskyrkan), Interact (Evangeliska Frikyrkan), The Baptist Union of Sweden (Svenska
Baptistsamfundet), Swedish Alliance Mission (Svenska Alliansmissionen), and The United Methodist
Church in Sweden (Metodistkyrkan). The aim of their work is for all people to be allowed to live under
dignified circumstances in a just and sustainable world, free from poverty. Its central work areas are
democratization, human rights, economic and social justice, and peace and reconciliation. The work
is carried out in partnership with approximately 400 local organisations, associations and popular-
based movements in more than 30 countries.
Diakonia's head office is situated in Sweden. The head office has about 36 employees working with
coordination of development work, information, education, opinion building, advocacy, fundraising,
marketing and administration.
Diakonia has regional offices in Africa, Asia, the Middle East and Latin America as well as local
offices in most of the 30 programme countries. The regional offices are responsible for the overall
work and decisions about the activities in the regions. In the regional office there is a manager,
executive officers and staff responsible for defined programmes. Their task is to closely follow and
support programmes and partners and also to monitor, evaluate and report results. This work is
carried out in close cooperation with the staff at the local offices and the partner organisations.
3 Policy for Sida‘s support to civil society in development cooperation, Sida, 2007
System-based Audit of Diakonia
8
2.3 The co-operation between Diakonia and Sida
Diakonia has had a framework agreement with Sida since the early 1990‘s. Diakonia has received
330 400 000 SEK from Sida for its programme for 2008-2010. In 2010, Diakonia will submit a
funding proposal for a one-year transition period.
2.4 Purpose and scope of this system-based audit
The aim of the system-based audit is:
to examine the reliability and relevance of the systems for operational and financial control
that exist in Diakonia, and to assess to what extent that the systems are adhered to and
implemented on all levels within the organisation;
to determine, on the basis of the examination, whether the documentation and reports received
by Sida under current agreements reflect the real situation, and can therefore be considered to
function as reliable data for Sida in the assessment processes;
to assess if Diakonia meets Sida‘s terms and conditions, as well as assess if their control
system secure that the partners also comply with these regulations
to provide inputs to the organisation‘s processes of change and systems development.
2.5 The Audit team
Sida has commissioned the Swedish management consultancy company Professional Management
AB to carry out the system-based audit. The Audit Team consists of four consultants Ms. Cristina A.
Rodriguez-Acosta, Ms. Stina Waern, Ms. Lina Lenefors and Mr. Arne Svensson (team leader). Ms.
Barbro Svensson has assisted the team.
2.6 Methodology
2.6.1 General approach
Professional Management‘s audits are always conducted in accordance with internationally accepted
standards issued by INTOSAI and IFAC. These include international standards on auditing and
international standards on review engagements.
The Inception Report submitted to Sida 2010-05-26 is attached at Annex 2.
The ToR have provided a comprehensive set of areas to be studied where the Audit Team has
documented current status and identified the observations regarding validity/importance, compliance
and enforcement wherever appropriate. The Audit Team has applied a three-pronged approach in
order to collect data for meeting the objectives and ensuring that audit findings, analysis, conclusions
and recommendations are based on evidence. In order to ensure the full exploration of all the
elements underlying ToR and the Audit Questions, the Audit Team has devised a validation method
(matrix), which is attached to the report (Appendix 3). The Validation matrix details for each
assignment element the sources of information including the written documentation that is requested
System-based Audit of Diakonia
9
and the verification method that has been used. This includes the choices of data collection and
sampling techniques. The validation matrix was attached to the Inception Report.
2.6.2 Methodology
The Audit Team has elaborated on the methodology in the Inception Report (Annex 2 to the Final
Report). After Sida‘s approval of the Inception Report the Audit Team carried out the detailed
planning of the study visits, interviews and review of documentation. The Audit Team has used a
variety of data-gathering techniques:
1. Analyzed relevant documentation available at Diakonia and Sida, and partners in the field;
2. Conducted interviews with Diakonia‘s Chair of the Board and a sample of four other
members of Diakonia‘s Board;
3. Conducted interviews with the Diakonia staff and Diakonia‘s auditor;
4. Conducted interviews with relevant staff at Sida;
5. Carried out field visits to study the whole organisational chain. The field visits has included
mapping and documentation of the management and financial systems and interviews with
relevant staff and stakeholders;
6. Assessed the management systems per ToR;
7. Provided recommendations on how to improve operational management and control at
Diakonia.
Furthermore, the Team has considered the key aspects of the aid effectiveness agenda, i.e. to what
extent Diakonia‘s systems for management and control provides for harmonisation with other CSO
donors, local ownership, alignment with local systems and core funding. In addition the Audit team
has described the view of Diakonia‘s auditor on the audit of framework grants from Sida.
The documentation and verification of findings and observations is detailed for each assignment
element in the Validation Matrix. In brief the major steps in the assessment of each of the assignment
elements per ToR are the following; however, as explained by the validation matrix it varies from one
Audit element to another:
1. Check whether Diakonia has a documented system (We can take as an example the system for
M&E that might include Guidelines, Handbook and/or other documents). Check how the
system was developed, how and by whom it was approved and how it was intended/planned
to be implemented.
2. Check if relevant staff at Diakonia is familiar with system and know how it should be used.
3. Check how the system is used in practice at Diakonia. Check reports against defined quality
standards.
4. Check how the system is used in practice at Diakonia‘s regional offices and country offices.
Check if relevant staff at the regional and country offices is familiar with the system and
know how it should be used. Check reports against defined quality standards.
5. Check if each one of the Partner Organisations has a documented system. Check if the system
meets at least the Diakonia requirements. Check if staff at the Partner Organisations HQ is
familiar with the system and Diakonia‘s requirements. Check reports against defined quality
standards.
6. Check reports from the Partner Organisations local branches and programmes/projects against
defined quality standards.
System-based Audit of Diakonia
10
The final stage in the analysis of data consists in combining results from different types of sources.
As is detailed in the validation matrix the data-collecting techniques – studies of written documents,
observations, interviews etc - that are used varies from one audit element to another. Thus, the
evidence is a combination of documentary, physical, testimonial and analytical. In this way the Team
has provided reasonable assurance that audit evidence is competent (valid and reliable) and actually
represents what it purports to represent. The audit criteria representing the normative standards
against which the audit evidence is judged varies also; however, in many cases there is establish
international best practice or good practice to compare with.
The system-based audit includes the whole organisational chain within Diakonia as well as the
Partner Organisations. Thus, the relationship, communication, reporting etc has been studied at all
levels; (1) HO in relation to the regional offices, (2) the regional offices in relation to the country
offices, (3) the country offices in relation to the Partner Organisations. The Team has assessed the
role of the regional office in relation to the HO as well as its relation to the country
offices/programmes.
The selection of Partner Organisations to visit has been made in the Inception Phase. Initially we
have aimed at identifying specific risks in connection to individual Partner Organisations or groups of
Partner Organisations. In addition, in the Tender the Team proposed criteria for the selection of
Partner Organisations. Our understanding of Diakonia‘s way of working was that the following
aspects should be taken into consideration:
Diakonia supports partners that work nation wide, as well as in specific regions of the country
with a focus on marginalised areas. Diakonia also works with partner organisations on various
levels in the region. Some partners have the characteristics of grass root movements; others
are NGOs working on national and international level. A significant number of the partners
are membership organisations or networks. Thus, the sample of Partner Organisations was
made to be representative in these regards.
The partner organisations have focus on diverse issues, capturing all of Diakonia‘s thematic
areas in different combinations. Their work reaches out to marginalised and vulnerable groups
such as women, children, youth at risk and workers. Thus, the sample of partner organisations
also intended to cover all thematic areas and target groups.
Data-collection is always a compromise between the ideal and the reality. It is seldom economically
possible to interview all stakeholders and visit all locations and partners. Thus, sampling is in reality
necessary in most cases. The sample size can be determined by the application of a statistically-based
formula or through the exercise of professional judgement objectively applied to the circumstances.
As stated in the International Standards the auditor‘s judgement should be used regarding the most
efficient manner to obtain sufficient appropriate audit evidence in the particular circumstances. Thus,
the sample size is determined by the auditor and the final selection of Partner Organisations and
country offices were risk-based and based on the criteria as stated above. Even if the sample of
Partner Organisations and country offices is representative for Diakonia this is not a guarantee for
compliance at all other Partner Organisations and country offices. However, obtaining evidence from
System-based Audit of Diakonia
11
all Partner Organisations and country offices would be too expensive relative the benefits. The
sampling is done objectively by the Auditor and is not influenced by Diakonia or Sida.
Available data may be inaccurate, incomplete or conflicting. Thus, the Audit Team has not drawn any
conclusion that is not permitted by the quality of the data. Audit evidence is all the information used
by the Audit Team in arriving at the conclusions. The Team has combined physical evidence, oral
evidence, documentary evidence and analytical evidence in the evidential process. Corroboration of
evidence is the most powerful technique for increasing reliability. In order to ensure that evidence is
competent (valid and reliable) the Team has used the validation matrix (Appendix 3). However, the
sources of evidence are to large extent information generated within the auditee including its Partner
Organisations. Internal information is viewed as less reliable that sources of evidence from outside
the audited entity. However, conclusions and recommendations in this report are never based on
evidence from a single source.
2.6.3 Reviewed documents and persons interviewed
A list of persons contacted and interviewed is attached (Annex 4). The list contains approximately
135 persons. The interviews were semi-structured. Based on the verification matrix a number of pre-
defined questions for each target group were formulated. Departing from these rather broad questions
follow-up questions were formulated individually dependent on the respondents‘ answers.
It is always the responsibility of the audited organization to make sure that all important and relevant
information has been brought to the auditors‘ attention. The Audit Team has studied all relevant
documents that we have been provided with by Sida, Diakonia and the Partner Organisations studied
in the field. A list of documents reviewed is attached (Annex 5).
2.7 Field visits
2.7.1 Visited regional offices and country offices
The Audit Team has conducted the following visits to Diakonia´s regional offices and country
offices:
The regional office for Latin America and the Country Office for Colombia were visited
August 15 – 20, 2010. Peru Country office was visited August 23 – 27, 2010.
The regional office for Eastern and Southern Africa and the country office for Kenya were
visited August 15-20, 2010.
The field visits included studies of partner organisations (please refer to sub-section 2.7.2 and
Appendix 6).
2.7.2 Visited partner organisations
The Audit Team has studied 15 Partner Organisations. These are briefly described in this sub-section.
A brief summary of the main findings at each visit is attached at Appendix 6.
Colombia
The main right holders reached by the Colombia programme are victims of violence, women, afro
descendents and indigenous people. This is done mainly through partner organisations, of which
System-based Audit of Diakonia
12
some they self are main target groups. Other target groups are local and national authorities, the
international community as well as public opinion in Sweden and Europe.
The Colombia programme is composed of 19 Partner Organisations. Most of them are located in
Bogotá. Eleven of the Partner Organisations are given institutional support. The programme has a
large number of partners in Bogotá and gives additional priority to the regions of Chocó, Magdalena
Medio and Antioquia. The program is composed of seven NGO:s, three CBO:s, six networks and
three partners with special characteristics ( Dial a network of international cooperation agencies,
Peace Brigades International – PBI and the Fond for Strengthening and Protection – FFP). The
support to several networks (the Alianza, CCEEU and Plataforma Colombiana) covers a large
number of partners and stimulates political coordination and joint actions at national and local level.
Based on the analysis in the Inception Phase the following six Partner Organisations in Colombia has
been studied:
PLATAFORMA COLOMBIANA - A network with around 80 member organizations. Its
main activities are to promote and strengthen economic, social and cultural rights, focusing on
the right to land, the right to education and the right to health.
ILSA – A NGO specialized in ESC rights. One important aspect of its work is the economical
justice within Free Trade Agreements. ILSA‘s main objective is to contribute to democracy
through the redistribution of goods and extensive social services for all people, as an
important matter of justice.
FFP – A joint initiative of Diakonia and its partners aimed at strengthening the security and
protection of social leaders and sectors vulnerable to the internal armed conflict. The work is
based on human rights and International Humanitarian Law and has a strong component of
capacity-building for self-protection.
CINEP/Banco de Datos - Cinep is a Jesuit organization, one of the most recognized human
rights organizations in the country, with wide range of publications and activities on both
civil, political rights and ESC-rights. The overall objectives are to transform the society into
one with social justice and equity. Banco de Datos is part of Cinep and is one of the most
important references regarding information on political violence in Colombia.
AVRE - An NGO specialized in psycho-social work with a human rights perspective,
articulated with actions of prevention, rehabilitation and reconstruction. AVRE supports
individuals and organizations of victims of socio-political violence, with the purpose of
strengthening their capacities, through different social dynamics, psycho-social attention and
organizational processes.
APSCP-NATIONAL – A national peace network whose most important objective is to make
contributions, from a perspective of citizenship, in peace processes between the Colombian
government and illegal armed groups.
Peru
According to Diakonia Strategy Plan 2008-2010 the Peru programme ―is well suited in the regional
programme fulfilling most criteria for choice of country‖. Among the existing partners, two are
networks, 12 are NGOs and one is coordination between three organisations. Seven of the partner
organisations receive institutional support and eight partners‘ project support. The programme
composition takes into account all levels of society where many partners work at several levels at the
same time. The geographical focus is Lima with surroundings and the southern Andean region. The
System-based Audit of Diakonia
13
main thematic areas continue to be human rights, democracy and participation in turn corresponds to
the actual context and problem analysis. The main focus on rights holders is on the local and regional
level, reaching out to populations and organisations in rural and marginalised urban areas;
communities, CBOs, unions, associations, universities, opinion leaders; journalists, parliamentarians,
communicators, businessmen, judges, human rights defenders, and authorities at communal,
municipal, regional and State levels with a special emphasis on women.
Based on the analysis in the Inception Phase the following seven Partner Organisations in Peru has
been studied:
APRODEH: Association for Human Rights is a collective dedicated to the defence and
promotion of the HR. Since its foundation in 1983, it has taken on the fight against impunity
and look for truth and justice for all victims of the period of political violence between 1980
and 2000. Aprodeh also make campaigns on the violations on economic, social and cultural
rights.
FLORA TRISTAN: The Centre of Peruvian Women is a feminist organization, with the
interest to support changes in the conditions of Peruvian women and to promote actions that
strengthen their organization and presence in the society. Flora Tristan works both with
women‘s and youth organisations in urban and rural areas and with state institutions and local
and regional governments.
SER: The Association of Rural Educational Service is a development NGO. It supports
efforts accomplished by organized peasants and local promotion teams, defending their rights
and the rural development.
CEPES: Peruvian Center for Social Studies. The main aim is the work for rural development
and the organisation is one of the biggest and most important within this area in Peru. The
work includes peasant and indigenous communities, international trade, rural conditions,
territorial development and environment.
CNDDHH: National Coordinator for Human Rights. It is a network of 65 human rights
organizations all over Peru and one of the most important HR-organisation. They work with
defence, promotion and education of the HR and with the strengthening of democracy.
CNDDHH has a special consultative status at the ECOSOC as well as within OAS.
IDL: It is dedicated to the defence and promotion of HR, peace, democratic values and the
State of Law in Peru. The overall objective is to promote the democratic transition and
thereby avoid that the country lives a similar period of violence as the years 1980-2000 again.
IDL participate and promotes forums debate and coordination, among state institutions as
well as within civil society.
Also, CALANDRIA, the Peruvian Association of Social Communications was visited by the Team.
Calandria is a women‘s right based organization promoting social, economic and cultural rights of
women. Calandria was added to the sample proposed in the Inception report as it turned out that there
was room for one more organisation in the schedule and it was of interest to increase the number of
organisations with project support in the sample.
Kenya
System-based Audit of Diakonia
14
The Kenya programme consists of 12 Partner Organisations drawn mainly from National and Local
NGOs, a Women‘s network, FBOs and an economic and development policy analysis think tank. The
partners have focus on diverse issues of concern capturing all of Diakonia‘s thematic areas and an
outreach on marginalised and vulnerable groups such as women, children, youth at risk and workers
especially those in exploitative employment in the horticultural and floriculture industries and in
Export Processing Zones (EPZ). There has also been a focus on marginalised areas especially in the
North Western Kenya where the focus has been work to promote peace and development amongst the
pastoralist communities as well as supporting women‘s involvement amongst the pastoralist
communities. In addition part of the Lake Victoria Livelihoods Programme which is a regional
programme incorporating the three East Africa Countries (Kenya, Uganda and Tanzania) is partly
implemented with partners in Kenya who to an extent are seen to complement the Kenyan
programme especially in the areas of HIV and AIDS awareness, social justice concerns for people
living with or affected by HIV and AIDS and economic empowerment of fisher folks around the lake
region. A significant number of the partners are membership organisations or networks with a (Inter)
national outreach.
Diakonia partners in Kenya especially the FBOs also have a regional and international network and
linkages which they use especially for advocacy purposes. In the Strategic Plan Diakonia‘s
programme compositions has been summarised as follows:
Based on the analysis in the Inception Phase the following Partner Organisations in Kenya has been
studied:
CJPC: The Catholic Secretariat is the Administrative Centre through which the KEC
implements and co-ordinates various pastoral programs. The Secretariat is composed of 14
Commissions. One of these is the Catholic Justice and Peace Commission (CJPC). The
project contributes to results under two themes in the Diakonia Kenya programme
strategic plan: (1) Peace and conflict management and (2) Democracy.
System-based Audit of Diakonia
15
MCF: MCF offer support and rehabilitation to girls so as to enable them a dignified life. They
undertake education and vocational training for the children, promote awareness of
HIV/AIDS amongst their children and surrounding communities, offer better health care and
nutrition to their beneficiaries and offer psychosocial support.
2.7.3 Core support or project support
Needless to say, there are a few differences in the way the management systems are practised
when it comes to Partner Organisations that receives core support (budget support) compared to
those who have project support. Thus, it is important that the sample of Partner Organisations for
the field visits include both Partner Organisations with core support and Partner Organisations
with project support.
From the Strategic Plan it is not always clear if a Partner Organisation has core funding or project
funding. For the sample of Partner Organisations above we have checked this in consultation with
Diakonia. Six of the selected Partner Organisations have project support and nine have core funding.
Thus, the Team is in a position also to assess differences in the management systems related to type
of funding.
Colombia
Partner Core funding or Project funding
Plataforma Colombiana Core
ILSA Core
CINEP Core
AVRE Core
FFP Core (administrated by Justapaz)
APS-C Project (administrated by Justapaz)
Peru
Partner Core funding or Project funding
APRODEH Core
Flora Tristan Core
SER Project
CEPES Project
CNDDH Core
IDL Core
CALANDRIA Project
Kenya
Partner Core funding or Project funding
MCF Project
CJPC Project
Currently, all partner organizations in the Kenya programme receive project support. Their
agreements come to an end this year. Diakonia will get into core funding in the next phase.
System-based Audit of Diakonia
16
2.8 This report and how to read it
This Report is divided into six sections as follows:
The Executive Summary in section ONE contains the overall conclusions and the
recommendations.
Section TWO is introductory.
Section THREE focuses on the organisational structure.
Section FOUR is concerned with the management and control of activities.
Section FIVE reviews the financial management systems and internal control.
Section SIX analyses aid effectiveness.
The various sections of the report answer the audit questions pertinent to the overall purpose of the
system-based audit and the elements stipulated therein. At the end of each section the Audit Team has
summarized the conclusions. Based on the conclusions the Audit Team has finally submitted concrete
recommendations in each sub-section. The recommendations with highest priority are marked (h).
These recommendations are summarized and prioritized in the Executive Summary.
3 Organisational structure
3.1 Vision, mission statement, goals, policies and activity plans
In this section we will first identify the vision, mission, goals and policies as formulated in the
steering documents. In sub-section 3.1.2 we will then analyse to what extent these are known and
practiced within Diakonia.
3.1.1 Steering documents
The mission statement is formulated in the statutes as follows:
Diakonias’s task
Diakonias‘s task is to seek God‘s will and based on fundamental Christian values perform its mission
by4:
Working for the freedom and redemption of mankind and to ensure that just and fair
structures are created or restored.
Analysing for forces behind injustice and conflicts from both a theological and social
perspective as well as seeking alternative solutions.
Tackling distribution of wealth issues by exposing unjust structures and working for greater
fairness in the distribution of resources.
Overall Objective
4 Statutes for Diakonia, revised and adopted in June 2
nd, 2007
System-based Audit of Diakonia
17
The overall objective of Diakonia‘s work is ―to change unfair political, economical, social and cultural
structures that hinder women and men from living their lives in dignified circumstances”.
Vision
Diakonia has a vision of a world where all women and men can live their lives in dignified circumstances, in a
fair and sustainable world, free from poverty. Diakonia‘s vision is based both on a theological foundation and
on respect for the universally recognised Human Rights.
Diakonia states that to create a fair and sustainable world all people have a shared but differentiated
responsibility. Diakonia therefore works to empower the poor and to challenge the privileged. Qualitative
participation is the key through which women and men can become involved in the process of change.
Everybody must contribute their share, but the rich and powerful have a special responsibility to act. Each
individual has a personal responsibility to the larger social or societal community. A life lived in dignity
presupposes that society as a whole is functioning, that it is characterised by trust between people, by
solidarity and by the sharing of mutual responsibilities and common resources.
Steering documents
The main steering documents are the following:
The Diakonia Policy
The Strategy Plan
The Gender Policy
The HIV and Aids Policy
Position Papers (debt and PRSPs, trade…)
Handbooks
Diakonia’s Policy
The following five themes form the basis of Diakonia‘s policy:
1. Democratisation
2. Human Rights
3. Social and Economic Justice
4. Gender Equality
5. Peace and reconciliation
For a more detailed description of the Policy please refer to Appendix 9.
Diakonia Strategy Plan 2008-2010
The Strategy Plan constitutes the overall steering document for all Diakonia operations for the period
of 2008-2010.
The Strategy Plan for 2008-2010 is divided into following five general parts:
Section A: General Framework briefly explains Diakonia‘s identity, ideological fundament, view of the world,
policy, theory of change, work methods, and organization. In Section B the regional strategy plans for the
period are outlined, one region at the time, including per region one regional part and one part for each
programme. At the end of each regional chapter is the budget. Section C explains the information and
advocacy work implemented in Sweden, the European Union and internationally, including descriptions and
System-based Audit of Diakonia
18
strategies for each target group and chosen thematic agendas and positions to be promoted. The section
concludes with a budget.
Section D describes Diakonia‘s organisational development during the period. The section summarises all
internal processes, sets up results and lists main activities to be carried out during the period. Finally, Section
E summarises the budgets from sections B, C and D. In the annex preliminary lists of partners and amounts
for each programme per financing source is presented.
Other policies and strategies
Global Fundraising Policy and Guidelines provides a regulating framework for Diakonia‘s
international fundraising, including ethical, political, technical and administrative principles and
considerations, as well as to set up global fundraising objectives and strategies for how to reach them.
Environmental guidelines for Diakonia‘s head office were adopted 2008-11-13. Diakonia continues
to develop the environment policy.
Guidelines for Diakonia‘s work on HIV&Aids contains a short analysis on how HIV&Aids relate to
Diakonia‘s themes and policy, definition of mainstreaming in the Diakonia context, strategies for
how to mainstream HIV&Aids related issues into the work and a mainstreaming matrix with
instructions and suggested activities for the implementation of the guidelines and how to mainstream.
The Gender manual is a tool to monitor how a gender perspective has been incorporated into the
structures and everyday work of an organisation, looking at the institutional, project and rights
holders‘ levels.
Diakonia has no global communication strategy. However, a strategy document on how to make Diakonia
more known among the Swedish public. It closely defines target groups and how to work to reach out to
these groups. The brand strategy is to be integrated in all communication efforts to present a clear and
persistent image of Diakonia. The long-term plan to reach out to new donor groups and involve them as
Change Sponsors is closely integrated with the brand strategy. Diakonia bases external communication
work largely on stories and accounts collected at partner and project visits, and written material from
partners and staff. The graphic profile helps to maintain a joint basic graphic presentation of Diakonia all
over the world. Campaigning as a working method has shown positive results and Diakonia plans to
develop it even further.
3.1.2 Observations and analysis
The task and the vision are well rooted within Diakonia. The five member organisations are satisfied
with the policies and goals. Staff at Diakonia adheres to the policies and goals. During the field visits,
staff interviewed as well as the partner organisations state that they share the vision and goals of
Diakonia.
Diakonia emphasises that it is primarily lead by its historical identity and the set of values linked to
it. Participation by the constituencies in policy discussions, public awareness campaigns and
advocacy activities is fundamental for Diakonia‘s legitimacy and ultimately its strength in promoting
agendas in Sweden and internationally.
System-based Audit of Diakonia
19
There have been discussions on adding environmental protection and/or climate change to the five
themes that form the basis of Diakonia‘s policy5. However, key informants state that other
organisations have more knowledge and experience and are more professional in this area. This leads
them to the conclusion that Diakonia should focus on areas where it has competitive advantages.
On the other hand, Diakonia has indicated that it would phase out some aspects of their Social and Economic
Justice theme. This would negatively affect the work of some counterparts who have concentrated on
economic justice rights under the Free Trade Agreements.
Diakonia has expanded rapidly over the last few years. The size has almost doubled in 12 years6. The
principles are satisfied with the present size of the organisation and the ambition is to consolidate the
activities at this level. The goals and plans are based on that view. However, some of the informants
at the regional and country level are of the opinion that Diakonia should continue to expand as long
as there is a need for support and Diakonia has the capacity to further improve the quality of its
services.
Interviewees are satisfied with the communication strategy for the work in Sweden. However, it is
emphasised that there is a need also for a comprehensive communication strategy for the
organisation globally.
The informants supported by documentation have indicated that there are some important features
defining Diakonia as a development organization:
Diakonia is working close to the partner organisations on the policy processes as well as the
practices on grassroots level
The participatory approach has created trust among partner organisations and the general
public in the countries where Diakonia operates
Diakonia has established a proactive agenda to alter structures that generate and maintain
poverty
In Diakonia‘s long-term work for change focus is put on changing the structures that generate and
maintain poverty. The programmes are intended to not merely deliver direct benefits to poor and
discriminated women and men, but also address the root causes of the problems experienced.
However, the active work among the most vulnerable has showed that there are practical solutions to
these problems and these practices have had more impact on policies than pure advocacy work. Also,
in the advocacy work Diakonia does not merely react on others agendas and proposals, but
proactively tries to influence the agenda and propose alternative solutions based on the organisation‘s
own experience. This is believed to create more trust among policy makers.
There is an uncertainty how the ongoing discussions on major changes on the principal level and the
governance structure will affect the future direction of Diakonia. The process is described as semi-
5 See for example general Assembly 2010
6 The annual turnover was 382 MSEK in 2009 compared to 192 MSEK in 1997.
System-based Audit of Diakonia
20
transparent where stakeholders have bits and pieces but few have the full picture of what is being
discussed (please refer to section 3.2 for more details).
3.1.3 Conclusions and recommendations
Diakonia‘s mission statement is its task as formulated in the Statutes. The task, overall objective and
vision are well known within Diakonia and shared by the Board and staff. Among the Partner
Organisations Diakonia is appreciated not only for the funds but also for the shared values.
In addition to the Statues the Diakonia Policy is an important steering document. The Diakonia
Policy sets five basic themes that permeate all work for development and justice. By and large the
principles and other key informants agree on these priorities even if there from time to time have
been discussions on adding themes or focus on fewer themes.
Diakonia has a communication strategy for the work in Sweden but not a comprehensive
communication strategy for the organisation globally. Diakonia is working world wide with an
ambition to increase the support from the Swedish Embassies, the EU, the UN and other funders.
Thus, there is a need to develop such a strategy.
Most Diakonia‘s staff works in the countries where the Partner Organisations operate. Diakonia‘s
decentralised organization facilitates a partnership characterised by trust, needs-based capacity
building, activities to link the Partner Organisations, linking between the work in South and
information work in Sweden, as well as planning, monitoring and evaluation of programmes and
projects.
It may be tempting to conclude that in this highly decentralised structure it is not of significant
importance if there are some changes on the principles level. However, Diakonia has in its steering
documents emphasised that participation by the constituencies in policy discussions, public awareness
campaigns and advocacy activities is fundamental for Diakonia‘s legitimacy and ultimately its
strength in promoting agendas in Sweden and internationally. Thus, the Team is of the opinion that
changes in the membership structure of the discussed magnitude may have the potential of
jeopardising the business should the values, mission & vision be significantly changed without having
a consensus among the most important stakeholders. Thus, the risk may be overcome by a transparent
institutional visioning process with the aim at reaching consensus on the long-term direction and a
shared vision within the framework of the new membership architecture.
The Audit Team recommends that
Diakonia goes through a transparent institutional visioning process with the aim at reaching
consensus on the long-term direction and a shared vision within the framework of the new
membership architecture (h)
Diakonia should develop a communication strategy for the organisation globally (l)
System-based Audit of Diakonia
21
3.2 Mandate and the role of the governing board
3.2.1 Observations and analysis
Diakonia‘s highest decision-making level is the Council of Representatives (representantskapsmötet),
where the five communions (Diakonia‘s member organisations) are represented. Diakonia‘s member
organisations are: The Swedish Covenant Church (Svenska Missionskyrkan), Interact (Evangeliska
Frikyrkan), The Baptist Union of Sweden (Svenska Baptistsamfundet), Swedish Alliance Mission
(Svenska Alliansmissionen), and The United Methodist Church in Sweden (Metodistkyrkan).
The Board is appointed by the General Assembly and is responsible for the financial management
and makes decisions on operational and budget planning based on guidelines established by the
Council of Representatives.
According to the interviews the mandate and the role of the Board has been clear. However, ongoing
changes in the member organisation structure will have significant impact on how Diakonia will be
governed in the future.
Three of the five churches that are members of Diakonia will merge into one. These are the Swedish
Covenant Church, the Baptist Union of Sweden and the United Methodist Church in Sweden. The
preparations have been ongoing for more than a year and the new congregation will be established 1st
of January 2012.
The consequences of this merge for Diakonia has been discussed at several meetings. In addition to
the new huge member organisation there will be only two smaller congregations left among the
present members. The Board of one of these smaller congregations - Interact (Evangeliska Frikyrkan,
EFK) - has 2009 taken a preliminary decision to leave Diakonia. The final decision will be taken
within a year and be coordinated with the other changes of Diakonia due to the merge of the three
organisations. The reason for the preliminary decision to leave Diakonia is that Diakonia‘s profile
was more clearly separated from EFK‘s before. Now there is more of a competition on resources.
When EFK is leaving its membership it calls for a review of the membership also by the remaining
smaller church namely the Swedish Alliance Mission (Svenska Alliansmissionen, SA). This has been
discussed in SA´s Executive Committee (Verkställande utskott) and will be further discussed in its
Board.
There have also been discussions on how to find other member organisations willing to replace the
ones leaving. However, all like-minded organisations are already involved in international
development cooperation in other organisational structures and it is difficult to find other
organisations that share the same basic values. There have been discussions with SMR on the future
cooperation between the two frame organisations.
One idea that has been discussed is to have also the member congregations youth organisations as
member organisations of Diakonia. The Swedish Covenant Church, the Baptist Union of Sweden and the
United Methodist Church in Sweden have established Ekumenia as their joint Youth organisation.
System-based Audit of Diakonia
22
A working group has been established to review the statutes of Diakonia. The proposal will be presented
at the Council of Representatives meeting in January 2011 and the decision made at the General
Assembly in June 2011.
Diakonia is administrating the Sida-supported development cooperation of the Baptist Union of Sweden.
The other congregations manage their own international development cooperation. According to the
informants the international work of the congregations sometimes are rather close to what Diakonia is
doing but there is no formal cooperation between Diakonia and its member organisations in the field7.
Diakonia wants to have strong partner organisations with adequate capacity for development
cooperation and the Swedish congregations often support weak churches that do not have the
required capacity for development cooperation.
As indicated above the cooperation between Diakonia and its member organisations has been in
different forms and has been changing over time. A few examples:
The Methodist Church globally is active in all countries where Diakonia is supporting partner
organisations. These partners also sometimes have some kind of connection or cooperation with
the United Methodist Church in Sweden.
The Swedish Alliance Mission and Diakonia had earlier cooperation in South Africa before
Diakonia phased out.
The Swedish Covenant Church (Svenska Missionskyrkan) has discussed to hand over the Sida-
financed projects to Diakonia after the merge.
3.2.2 Conclusions and recommendations
The mandate and the role of the Board are clear.
The consequences of the merge of three of the five member organisations are, however, not clear and
has not been analysed and discussed enough in a transparent way. In addition too the consequences of
the merge itself, it is possible that the remaining two member organisations will withdraw their
membership. The reduction of the number of member organisations to maybe only one is a
significant change in the governance structure of Diakonia. It will probably have an impact on not
only the governance but also the fundraising from churches and individuals and the relationship with
other stakeholders. It may also influence how Diakonia is organised; one of the alternatives that have
been discussed is to integrate Diakonia as a department of the merged church.
The Audit Team recommends that
The impact of the changes regarding Diakonia‘s member organisations should be carefully
analysed including a risk assessment
3.3 Organization and decision- making
In this section the Audit Team will cover the following audit questions per ToR:
Decision-making mandate and delegation procedures through the whole organization chain
Authorisations
7 Diakonia shares office in Kinshasa/DRC with the Swedish Covenant Church and the Baptist Union of Sweden
System-based Audit of Diakonia
23
Promotion of good administration, transparency in the administration of funds, and
counteraction of corruption
Existence of (and adherence to) office manuals/working orders which stipulate rules for e.g.
decision mandate for travels, rules for per diems, travel reports, segregation of duties etc.
3.3.1 Observations and analysis
The organisation
On 8 March 2007, Diakonia‘s Board adopted a Decision of Intention regarding an organisational
change. According to the decision, delegation shall be transferred from the head office to the regional
offices, and onward from the regional offices to the country offices. This decentralisation involves a
change in the division of responsibilities and to some extent new roles. More decisions are delegated
to regional offices and program planning and monitoring is decentralised.
The purpose of the change is to conform to Diakonia‘s policy, strategy plans and to meet changed
terms regarding development work as effectively as possible. It is estimated that the decision will be
fully implemented by 2011.
As part of the organisational development process a new structure at the HO has been introduced
with the following departments: Financial and Administrative, International, Human Resources,
Fundraising and Communication, and Policy and Advocacy. The five heads of these departments, the
Deputy General Secretary and the General Secretary forms a Senior Management Group for
coordination of Diakonia. The Group has no decision making power.
The figure below illustrates the new Diakonia organisation:
Sri Lanka
India
Bangladesh
Burma
Thailand
Cambodia
Palestine/Israel
Egypt
Lebanon
Iraq/Kurdistan
General Secretary
Human Resources Dept
Deputy General Secretary
Financial and Administrative
Dept
International Dept
Fundraising and Communication
Dept
Policy and Advocacy Dept
Africa Latin America Asia Middle East
Guatemala
El Salvador
Honduras
Nicaragua
Colombia
Peru
Bolivia
Paraguay Somalia
Kenya
Uganda
Zambia
Zimbabwe
Moçambique
Congo-Kinshasa
Mali
Senegal
Burkina Faso
System-based Audit of Diakonia
24
There is an ongoing process at the HO on the manning of the new organisational structure. Some
changes will be made in September and later during the autumn.
During 2010 the process of integrating the regional office for West and Central Africa with the
regional office for Southern and Eastern Africa has began with the aim to create only one Africa
region with its regional office in Kenya. The regional director for West and Central Africa left office
1st of June 2010 and some staff has already been transferred to Kenya. According to the interviews at
the RO in Nairobi the decentralisation process is following the plan. The country office for Kenya
will shortly be separated from the regional office in terms of staff and office space.
South Africa has already been phased out and the CO was closed 1st of May 2010. In addition
Iraq/Kurdistan, El Salvador, Ghana, Senegal and India will be phased out during the period.
During the field visit to Latin America, the process of decentralization was perceived as mostly
successful and useful, but it is understood as an unfinished process. Some interviewees underlined the
importance for allowing for flexibility in the handling of projects and programs.
The Regional managers are meeting each other and the Senior Management Group at the HO twice a year in
Sweden. The formal vertical organisational structure is also supplemented by networks horizontally. Some of
these are clearly defined and others are more ad hoc. For example Diakonia has established three internal
networks relating to global political and economic structures, HIV and aids and Gender equality. The networks
consist of Policy Officers at the HO and appointed focal persons in each region (sometimes staff at the RO,
sometimes at CO).
Order of delegation
Diakonia‘s Order of Delegation8 is intended to clarify the responsibilities and competences for the
following:
To make decisions concerning development of activities.
To make decisions concerning finance and administration.
To make decisions concerning personnel and supervision of work.
To employ personnel.
To be Signing Officers.
To represent Diakonia with representatives, organisations, authorities, the mass media and the
general public.
To be responsible for satisfactory, safe working environment.
8 Order of Delegation dated 15-09-2005; DELEGATION OF DECISION MAKING FOR
FINANCE – PERSONNEL - AND ACTIVITIES
System-based Audit of Diakonia
25
The Order of Delegation also includes ―guidelines concerning methods of working within the
regions‖.
In addition Diakonia has decided on a new ―Diakonia Order of Delegation, In accordance with
decision of intent, 2011‖. This document contains transitional rules until 2011. In order to be able to
implement the organisational change progressively in accordance with the Decision of intent 2011,
Diakonia need to work with both the ―new‖ Order of Delegation and the ―old‖ Order of Delegation.
The transitional rules apply in agreement with each region‘s organisational development plan which
has been approved by the Head Office. If things are unclear in the Order of Delegation, the issue is
passed on to the immediate head. The interviewees state that there has been no problems working
with the ―old‖ and ―new‖ Order of Delegation simultaneously.
The Board decides on signatories for bank accounts and money transfers at the HO. The decisions
can be found in the Minutes from the Board meetings. Different types of authorisations are given for
different kinds of transactions. Most common is the right to sign jointly for two signatories (f. e.
payments). A new decision always has to be taken in case of change of staff.
The right to sign bank accounts on regional level is decided by the Regional Manager. The right to
sign bank accounts at country level is also decided by the Regional Manager. In many countries a
particular Power of Attorney from HO is needed in order to be able to sign a bank account in
accordance with local legislation.
Diakonia has established guidelines regarding how to organise and systematise the offices and
workplaces so that important information easily can be found by anyone in the organization9. The
guidelines also regulate how working material shall be treated when a project or a specific activity is
finished, and the material passes on from being active working material to stored archives, or gets
thrown away. The rules apply for all Diakonia workplaces.
The Project Handling System (PHS)
All that is done along the annual cycles of the PME Handbook is registered and – if implying
documentation of some kind – filed in Diakonia‘s computerised project handling system (PHS),
through which also payments to partners and regional and country offices are made and controlled.
Through the PHS the Project Cycle Management (PCM)10
is controlled in terms of confirming that
tasks are being done and done in the right order (e.g. that a contract is preceded by a decision
memorandum). All essential project documentation, such as partner‘s applications, contracts, reports,
etc, is also filed in the PHS. Through the PHS it can be controlled that the quality is in line with the
PME Handbook11
.
There is a manual on how to use the Project Handling System (PHS). However, documents are often
uploaded in the PHS very late12
.
9 Diakonia Archive Rules, Regional and Country Offices, Final version 2009-02-19
10 For details on PCM please refer to sub-section 4.1.1
11 For details on the Handbook please refer to sub-section 4.1.1
12 For example contract for the period starting 1 Jan 2009 uploaded in Nov 2009. For older documents sometimes several
years.
System-based Audit of Diakonia
26
Diakonia is in a process preparation for purchasing a new PHS that is better adapted to a multi donor
situation and improved grant management.
It is stated that strengthening partners‘ administrative capacity shall be considered when:
the partner organisation has a deficient financial management, administration or
administrative routines
the narrative and/or financial reporting from partner organisation is deficient
the partner organisation has deficient routines for internal control
3.3.2 Conclusions and recommendations
Diakonia is in the process of establishing a more decentralised structure facilitating flexibility and
ability to adapt to new circumstances and development needs. So far this process has proven to be
successful.
Not a few Partner organisations use Performance contracts for each staff member with annual
performance appraisals. It is well known that this kind of instruments increase the results orientation.
It is also a useful tool to secure a good working environment with clear expectations and adequate
feedback where good results are acknowledged and rewarded. Diakonia has so far not used
Performance contracts and annual performance appraisals.
The PHS is well suited for Sida-funded programmes and projects. However, it is not flexible enough
to handle funding from the EU and the UN.
The organisation and the decision-making mandate and delegation procedures are clear. However, the
Team proposes some clarifications when it comes to suspected corruption or misuse of funding. This
issue will be dealt with more in detail in sub-section 5.2.
The Audit Team recommends that
PHS should be developed as intended to facilitate also the operations of projects funded by
the EU, the UN and other donors(h)
Diakonia should introduce Performance contracts and annual appraisals (h)
4 Management of operations
4.1 Results Based Management
In this section we will answer the following audit questions per ToR:
Results based management including the use of the activity plan; and results reports as a
guiding instruments;
Formulation of goals
Systems for planning, monitoring, evaluation and measuring of results
System-based Audit of Diakonia
27
Systems for reporting progress and results, and for reporting on deviation from plans
(narrative as well as financial) in a timely manner
Budgeting processes
Firstly, the systems, methods and tools are presented briefly in sub-section 4.1.1. Secondly, the Team has
in sub-section 4.1.2 summarised its observations and analysis. The conclusions and recommendations are
to be found in sub-section 4.1.3.
4.1.1 Diakonia’s tools and methods for programme cycle management (PCM)
The Planning, Monitoring and Evaluation (PME) Handbook
The Planning, Monitoring and Evaluation (PME) Handbook defines minimum standards for the
project and programme cycle management (PCM). This includes manuals and criteria for programme
and project planning, monitoring tools and formats and guidelines for in depth evaluations.
The PME Handbook consists of the following parts:
1. Introduction: Status of the PME Handbook, mechanisms for handbook developments and
exceptions, implementation and future development of the PME Handbook.
2. Programme and Project Management: Hub of the PME Handbook. Checklists for programme
and project cycle management and links to corresponding formats. Who does what and in what order.
3. Planning Manual: Manual for the planning of a strategy plan through six phases, including
Diakonia‘s basic LFA structure and associated concepts, such as indicators, outcomes and impacts.
4. Monitoring Manual: Includes tools, formats and requirements for narrative and financial
monitoring of both programmes and individual projects.
5. Evaluation Manual: Orientation and guidelines for different kinds of evaluations, but also a
manual in terms of what is required from all programmes and projects in terms of evaluations.
6. Phasing Out: Steps to take and issues to consider before and when ending cooperation with a
partner or closing a whole programme.
7. Programme Building: Criteria for choice of country, criteria for programme building, criteria for
choice of partners, giving an added value to the programmes and Diakonia‘s different roles.
8. General Conditions for Partners: Information for potential partners regarding under what
conditions a partnership may be established, including application format to use first time support is
given. The only chapter in the PME Handbook intended for partners.
9. Toolkit: The following tools are briefly explained and accessible through links: the PHS Manual,
the Gender Manual, Guidelines for HIV&Aids Mainstreaming, Directions for SMC‘s work with
evaluations, Looking Back Moving Forward: Sida‘s evaluation manual, and the Octagon.
10. Abbreviations and list of formats: Which formats are minimum formats and which cannot be
changed?
Monitoring
Diakonia states that monitoring of projects and programs have the following purposes:
to make sure that the financial contributions to partners‘ projects or capacity building are
spent in accordance with approved work plans and budgets
to estimate the outcomes and impacts, expected or not, that the projects have lead to
to estimate partners‘ changed capacity due to the capacity building activities Diakonia
supports
System-based Audit of Diakonia
28
to estimate Diakonias added value to the programmes in terms of facilitating synergies
between partners and complementing partners‘ work with advocacy work towards Swedish
and European institutions
A central purpose for Diakonia‘s monitoring permeating all the above mentioned, is to learn from
experience in order to become an effective development organisation and a strategic partner and
donor to partner organisations. This means bringing the lessons learned from one cycle into the next
one, but it also means being sensitive to the need for adjustments during a cycle when reality so
requires.
A minimum of monitoring routines and tools have been standardised for the whole organization in
the Monitoring Manual of the PME Handbook. The system rests upon a simplified logical framework
approach (LFA). It has been pointed out that where the EU more elaborate logical framework has
been applied and this is considered a benchmarking tool which could be useful for the development
of the Sida financed developing cooperation work as well. Monitoring of partners‘ projects is
primarily done through visits at the office or at places where the project is being implemented.
Information is also gathered through email and phone conversations with staff at the partner
organisations and the beneficiaries.
Diakonia‘s observations are often documented in PHS. The RO may decide on a using a different
format as long as that format permits to capture the same information as the template in PHS. The
purposes of the log in the PHS are:
to always remember what is important
a space for making notes on advances and difficulties of the project, e.g. individual examples
of change
a space for taking note of short reflections, analysis and lessons learned
to systematise qualitative follow up of each partner
to facilitate communication within the programme team
to provide material for the annual and final reports
the idea is to have a kind of checklist, a reminder of what is important, a guide for
conversation, reflection and analysis, but also for control.
Reporting
From the PHS it is possible to print out pre-defined reports, for example:
Financial programme report with a summary of the budget per financing source, allocations
and expenditure for each programme.
Annual financial report including the budget with financing source for each programme and
the allocations for each project and expenditures.
A list with documents connected to a project for a specific cost centre.
Requisition report with information about payments, which have been done in PHS
Contact person report - a list with the partner addresses, telephone and contact person.
Stakeholders bank information with information about partners‘ bank and bank account.
System-based Audit of Diakonia
29
4.1.2 Observations and analysis
Diakonia at all levels as well as its Partner Organisations are making significant efforts to increase
the results orientation. The PME Handbook defines minimum standards for the PCM in a
comprehensive way. It provides tools, guidance and basic requirements. The Handbook also
establishes who does what and when, although the division of responsibilities is today somewhat
generally expressed as Diakonia is in the midst of a process of reorganisation. In the case of the Latin
American region, some sections of the PME have been changed to adapt to local rules and
regulations. The need for a new PME was also noted. Among others the interviewees requested more
flexibility for the ROs and COs. Some of the interviewees also stated that the Handbook was too
Sida-oriented which made it sometimes difficult to use it when the funding was from other sources
for example the EU or the UN. Interviewees also underlined the need to make the Handbook more
applicable for the Swedish programme.
Some of the Partner Organisations the Team has visited have practiced RBM for many years and are
quite advanced. These organisations are sometimes used by Diakonia as good examples that are
presented at meetings with the Diakonia network.
On the other hand, there are also Partner Organisations that need a lot of support in order to be able to
use RBM. Objectives are sometimes not measurable and results indicators are missing. Sometimes
there are results indicators in place but in the absence of base line studies it is still impossible to
establish evidence on progress. According to the interviews there is demand for assistance in
introducing and further developing RBM in practice in several countries. Based on the successful
activities in the Diakonia networks in some countries this support could be systematised.
The PME Handbook and the PHS are used in practice at all levels as described in sub-section 4.1.1.
However, some of the interviewees at the ROs and the COs stated that the PHS is too much tailor—
made for Sida-supported projects and programmes and not flexible enough to be used for EU-
funding.
In addition to these more general observations the Team has studied the following three
documents/processes more in detail:
1. The assessments of reports from partner organisations and the feed-back to them
Diakonia makes three kinds of assessments of the reporting from partners using specific assessment
forms:
For reading, assessing and approving partners‘ narrative reports a specific format is used.
There is also an assessment form for partners‘ financial reports.
Assessment form for partners‘ audit reports.
Based on the assessments of partners‘ narrative, financial and audit reports feedback is always given
to the Partner Organisations. The feedback includes both positive and negative aspects and
challenges. The feedback is often made in writing. It is also discussed at the meetings with the
Partner Organisations. Partner's audit report must be approved by Diakonia before any further
payment is done.
System-based Audit of Diakonia
30
The Partner Organisation is always contacted in the following cases:
1. The partner has not fulfilled Diakonia‘s reporting requirements regarding dates, form and content
2. The narrative report do not relate to the approved application, has low quality, is not in accordance
with the observations made during the field visits, is not in accordance with the financial report‘s
content and/or does not include explanations to budget balances higher than 10%.
3. If the grants from Diakonia are not reported or are incorrect and/or the financial report has low
quality, is based on a completely incorrect exchange rate, is overlapping between two consecutive
reports, open balance does not correspond to the previous report's closing balance, the period's
balance is over 10% of Diakonia's contribution (unless deviation is duly reported), the expense items
do not match with budget items and/or the reported expenditures do not correspond with the reported
activities in the narrative report.
4. The audit: the grants from Diakonia are not reported or appear incorrect, no original audit has been
signed, no separate specification of costs and revenues of the project is distinguishable in the audited
annual accounts, no audit certificate and/or management letter is included, financial statements
(Balance, Incomes and expenditures, etc) are not included, the auditor's opinion contains remarks, the
closing balance do not match with the closing balance in the financial report.
The assessments of reporting from the Partner Organisations have been done in accordance with the
above mentioned guidelines in the Partner Organisations studied by the Team during the field visits.
The Partner Organisations appreciate the feed-back. Approximately every second Partner
Organisation would like to have either more feed-back especially on the narrative reporting and/or
more oral feed-back in addition to the written.
2. Management Reports within Diakonia
The Management Reports are at two levels: from the CO to the RO and from the RO to the HO.
Diakonia has written instructions and formats for the Management Reports from CO to RO as well as
for from RO to HO. Responsible for the first level is the County Manager or Country Representative
and the Regional Manager at the second. The Management Report is a tool for monitoring of the
overall implementation of operations, which includes both programmatic and non programmatic
work. It provides overall and selected information and analysis to show major deviations from plans
as well as main threats and opportunities.
The process of reporting from the CO to the RO is followed in practice. Also, the process of reporting
from the RO to the HO is adhered to. It is sometimes not clear how results on country level are
aggregated on higher organisational levels. The results should also be analysed more in-depth in
relation to the objectives for Sida‘s support to civil society. Feedback on the reports and discussions
over key issues are stated as compulsory in the system. However, according to the interviews during
the field visits there is not enough feed back from HO on the reports.
3. Evaluation plans
It is stated that an evaluation plan should be elaborated and agreed upon with Partner Organisations
for each programme. The plan should include the following content:
The main reason, purpose and scope of each evaluation.
A tentative budget for each evaluation (unless the evaluation is integrated in partners‘ strategy
plan and budget).
System-based Audit of Diakonia
31
If an evaluation is part of the Partner Organisations own planning this is also included in the plan,
even though it doesn‘t require that Diakonia plays an active part in the process.
The evaluation plans should be registered and uploaded in PHS. They should be revised and updated
annually. The Team has been provided with evaluation plans for the Partner Organisations in the
sample. There are evaluation plans in place; some of which comprehensive and others more
rudimentary. The quality could in most cases be further improved and it is not clear how it is
followed up that the evaluations really are carried out in accordance with the plans.
Normally there is a small M&E component included in all agreements between Diakonia and the
Partner Organisations. Diakonia has emphasised the importance of the right holders‘ perspective in
M&E. Therefore, Diakonia has in cooperation with the Partner Organisations organised trainings in
LFA and M&E in order to move from a primarily activity-based reporting to results oriented.
Reviewing the annual reports 2008 and 2009 from Partner Organisations in Kenya it is obvious that
the trainings have had effect
4.1.3 Conclusions and recommendations
The PME Handbook defines minimum standards for the PCM in a comprehensive and adequate way.
However, there is a need to further develop the Handbook to increase the flexibility on RO and CO
levels especially when Programmes have support from others than Sida. Its usefulness for the
Swedish programme could also be increased.
The PME Handbook and the PHS are used in practice at all levels. The Management Reports
provides a key information flow from the Country Programmes to the RO and the HO.
When it comes to the three in-depth studies the Team has come to the following conclusions:
1. The assessments of reports from partner organisations and the feed-back to them is very much
appreciated and are of good quality;
2. Management Reports within Diakonia are comprehensive but the feed-back is less
comprehensive;
3. There are evaluation plans in place; however, the quality of the Evaluation plans could be
further improved as well as the follow up that the evaluations really are carried out in
accordance with the plans.
There is room for improvement when it comes to formulating clear objectives and measurable results
indicators. Without these elements it is not possible to evaluate the truthful outcome and impact of
the efforts undertaken within each project. Thus, objectives and results indicators ought to be more
precise and measurable, which will improve the possibility to evaluate results in short, medium and
long term. The demands of the EU in the form of the Logical Framework Approach for individual
projects, are well known and many organizations are already working to improve their objectives and
indicators in accordance with these. However, this approach to certain projects should be balanced
with the general approach of supporting the Partner Organisations in their own efforts to develop the
use of RBM. There seems to be an awareness that it will be necessary to go through this process.
System-based Audit of Diakonia
32
Diakonia has comprehensive plans and reports that are lengthy and sometimes contains overlapping
information. It is sometimes also difficult to know if statements in reports are referring to validated
results, work in progress or expected results.
The Audit Team recommends that
The PME Handbook should be further developed in order to increase the flexibility on RO
and CO levels especially when Programmes have support from others than Sida (h)
Objectives and results indicators for programmes and projects should be thoroughly
developed in order to provide necessary and valid information for the further development of
the programmes and projects (h)
Diakonia should assist its Partner Organisations in introducing Results Based Management
and the development of precise and measurable objectives and results indicators (h)
Diakonia should continue its efforts to implement participatory monitoring and evaluation
systematically in cooperation with its Partner Organisation (h)
Diakonia HO should give RO systematic feed-back on the reports (h)
Diakonia should review its reporting system with the aim to avoid duplications and focus on
relevant information for different stakeholders (l)
4.2 Criteria and procedures for selection of partners and their project/programmes
In this section we will answer the following audit questions per ToR:
Criteria and procedures for selection of partners and their project/programmes
Criteria for assessment and selection of member organisations and partner organisations and
their projects/programmes
4.2.1 Observations and analysis
The theoretical process includes the following steps where criteria for selection are required:
1. Choice of country or context for long-term commitment
2. Programme building
3. Choice of partner organisations
4. Maintaining or phasing out partnerships
These for steps are presented in turn in this sub-section, followed by a paragraph on the information
needed for selection of partners and the specific criteria for advocacy.
1. Criteria for choosing country or context for long-term commitment
Diakonia considers the following criteria when assessing the possibility of opening a new programme
for long-term commitment. The criteria are likewise used for considering the closure of a programme.
Criteria 1: Not in Europe
Although Diakonia collaborates with many actors and target groups in Sweden and Europe, the main
rights-holders that Diakonia exists for are found on all continents except Europe, North America and
Oceania.
System-based Audit of Diakonia
33
Criteria 2: Poor, oppressed and exposed to violence
All Diakonia‘s work aims ultimately at changing the conditions for the poor, oppressed and people
exposed to violence or affected by unfair political, social, economical or cultural structures, in order
for them to change their own reality to a life in dignity.
Criteria 3: Degree of organization
Diakonia theory of change is that civil society is a vehicle for changing the people‘s conditions for
living a life in dignity. The efficiency of Diakonia‘s support therefore depends on the degree of
organization at hand. If an organised civil society is completely or almost completely lacking, very
strong arguments in line with other criteria is needed. With the civil society at hand it must also be
possible to find partners according to the criteria for selection of partners mentioned under A.5.5.
These criteria must also be carefully weighed against the second criteria, between which a paradox
may lie.
Criteria 4: Thematic focus
For Diakonia to build a new programme it is necessary that Diakonia‘s thematic focus and policy is
considered relevant for the contextual analysis made and likewise partners can be found who share
that analysis and focus.
Criteria 5: A long term perspective
Applied reversely, all criteria obviously work also the other way around, as criteria for ending a
programme. If the criteria thus points at the conclusion that funding would be more strategic if
reallocated to another programme, Diakonia‘s history in the context in question must be taken into
due account before making such a decision. Over time Diakonia may have built important
relationships and accumulated much knowledge. This gives Diakonia a considerable credibility in its
relations with other actors, enough strategic to reconsider a continuation of the programme.
Criteria 6: The need for Diakonia
Even though all other criteria points at building a new programme an inventory and analysis of other
similar actors must be made. Diakonia‘s approach may be already well represented by other donors. If
the potential partners are already on the verge of saturation of funds, Diakonia‘s contribution is not
likely to make much difference or even have a negative effect.
Criteria 7: Diakonia’s own capacity
If Diakonia intends to open a new programme the organisations capacity in terms of human and
financial resources must obviously be sufficient in order to expand, unless it is a matter of reallocation
of resources from a programme about to close.
Criteria 8: Fundraising and information in Sweden
Some countries and regions have a stronger relation to Diakonia‘s constituencies, the public and to
back donors, all of which Diakonia depends financially. The effect a new programme will have on
Diakonia‘s profile and ability to raise funds is essential when deciding on new programmes if
Diakonia‘s operations around the world are to be financially sustainable.
Criteria 9: Regional links
Diakonia is a fairly small organization and must consider as to what extent synergies to and from a
new programme would be possible in order to stay focused and concentrate the limited resources
available enough to be able to make difference. It is generally more effective to concentrate
operations to a smaller amount of programmes than to distribute resources in a scattered way.
Criteria 10: Advocacy in Sweden, EU and on the International level
Some partners are strategic in analysing the situation of the poor and vulnerable rights-holders in
respect to the effects of larger global structures. These kinds of partners are important in order to
System-based Audit of Diakonia
34
make full use of the potential of Diakonia‘s programmes in developing countries, by facilitating
linkages to advocacy work on the Swedish, European and international level.
Diakonia states that it is important to note that the criteria are not absolute. Programmes can be
justified even though all criteria are not equally fulfilled. All are nevertheless always taken into
account. This has been the case in the three countries the Team visited. The choice of these three
countries for Country programmes are relevant and meeting the criteria.
2. Criteria for programme building
For opening a new programme a Decision memorandum has to be approved by Diakonia's Board of
Directors and uploaded in PHS. Diakonia states that an effective programme composition must be
based on understanding the context and adequate problem analyses. Diakonia makes this analysis
with active participation of local actors. Even though such analysis should be done continuously it is
mainly done in relation to the planning process following Diakonia‘s Planning manual.
Diakonia states that a programme should be designed to be as powerful and strategic as possible. The
base of a programme should be grassroots‘ organisations of different kinds. The role of NGOs should
be complementing and facilitating. The reason for this distinction is that without the support and
leadership of member based organisations civil society will pose no challenge for power holders, nor
will the agendas hold any legitimacy or sustainability if they address problems and suggest solutions
for people that never participated in their elaboration. At the same time, NGOs are often much better
equipped in terms of analysis and tools than are grassroots‘ organisations.
Related to this is the idea to construct a programme where Diakonia‘s added value is maximised. By
constituting a platform and meeting point for partner organisations the programme builder should
consider the ―supply and demand‖ of knowledge and skill within the partner group. In a well
constructed programme they are both met within the programme.
A country programme should:
Be designed in complete accordance with Diakonia‘s basic values and policy.
Be strategically elaborated and grounded in each context respectively on the basis of an
updated contextual analysis in which a variety of national actors have participated.
Be based upon an analysis of the existing civil society, its problem analysis, its chosen
priorities, and the ongoing processes in which they intervene.
Be concentrated geographically as to facilitate the possibility for partners within the
programme to meet and exchange ideas.
Be composed with the ‗supply‘ and ‗demand‘ sides in mind within the partner group. In a
well constructed programme they are both met (important for mainstreaming).
Include cross cutting issues around which partners gather, qualitative participation being the
strongest one.
Be primarily designed to strengthen grassroots‘ organisations and facilitate the achievement
of their objectives, be it via or in collaboration with NGOs.
Take into consideration all levels of society in accordance with figure 5.
System-based Audit of Diakonia
35
For cost-effective administration and follow-up as well as for maximising Diakonia‘s added
value a programme should contain 12–16 partner organisations or aim at developing the
programme until this level is reached.
Contain components of advocacy work on national level.
Have, or strive towards, a clear gender perspective and include at least one organization who
primarily works for equality between women and men.
Give an added value in relation to the priorities of other donor agencies; be complementary to
other programmes.
Should not become a burden to partners or even saturate them with extra activities. Other
donors‘ may for example already be requiring time and effort from partners.
The Team has found that the planning process has included analysis meeting the requirements as
stated in the criteria. The Planning manual has been adequately used and followed. The
documentation contains descriptions of the context and adequate problem analyses. Key informants
outside Diakonia; read Partner Organisations and the Swedish Embassy in Nairobi, are of the opinion
that the Country programmes in the visited countries are built up with relevant partners.
3. Criteria for choosing partners and for maintaining partnerships
All partner organisations in the programme are assessed regarding the criteria below. The criteria are
absolute and should be fulfilled by all partners. The partner organization should:
Share Diakonia‘s values as expressed in the policy.
Sympathise with Diakonia‘s vision, general problem analysis and overall objective to change
unjust structures.
Fit well in to how Diakonia envisions the programme in the near future.
Be clearly oriented towards reaching outcomes and impacts beyond the activities
Possess administrative skills, or willingness to possess such skills, in order to fulfil
Diakonia‘s requirements.
Be willing to participate with other partners and networks that emerge or may emerge as a
result of the partner group and Diakonia coming together.
Have or be willing to adjust to formal and actual structures in order to exercise transparency,
accountability, participation, influence, non-discrimination.
Fulfil or be willing to fulfil Diakonia‘s gender indicators during the programme period.
This regards the organization‘s internal structure and culture as well as the projects
themselves.
Where relevant - have an intercultural perspective and an inclusive view of indigenous
peoples and ethnic groups.
In HIV/AIDS affected regions, be willing to analyse the socioeconomic consequences of
HIV/AIDS for the rights holders and adjust the work accordingly.
The criteria are assessed not only when a partnership is established the first time. Also when contracts
are renewed the criteria are considered and assessed. Partner Organisations that are not longer
meeting the criteria are phased out in a dialogue with the partner. Thus, the criteria above are also
used for phasing out Partner Organisations. However, in addition Partner Organisations may be
phased out due to non-compliance with agreements. Please refer to chapter 5 for details.
System-based Audit of Diakonia
36
In the Kenya Programme two partners were phased out 2008 after an assessment based on these sets
of criteria respectively:
TWCC (Turkana Women Conference Centre) were phased out due to capacity limitations and
resistance to build up necessary organisational capacity to deliver and report on results.
The 2007 audit report from CREDO (Constitution & Reform Education Consortium) had a
qualified opinion with respect to a banking fraud. The management letter submitted did not
include management response. Seeking clarifications, Diakonia received no response and
subsequently a decision was taken not to renew the partnership with the organisation.
In Peru, Diakonia is trying to find new ways of still supporting its Partner Organisations and
maintaining partnership. It has proposed the introduction of platform models (grouping partners with
similar themes/goals/objectives) to raise funds together. Two Requests for Proposals (RFPs) to the EU
have been awarded for human rights and local economic development and democracy. A third RFP on
gender issues is hoped to be awarded. Administrative/logistical issues (narrative and financial reports)
are being discussed with the Regional Office. The platform model will be discussed more in detail in
sub-section 4.5 Exit strategies.
Required information on Partner Organisations
The Team has found that the requested information is adequate and comprehensive and, thus, is
meeting the needs for the assessment. Partner‘s proposal template includes 1) Contact information, 2)
Short summary of project/action plan, 3) Description of applying organization, 4) Problem analysis
(regarding project/action plan), 5) Goal analysis 6) Geographic area and target group, 7) Gender
analysis of project/action plan, 8) HIV and Aids analysis of project/activity plan, 9) Monitoring
system, 10) Risk analysis, 11) Analysis of social and financial sustainability; and 12) Budget and
financing.
The following documents must be attached for new partner organisations: 1) Institutional information
2) Organisational chart 3) Copy of last years audit report 4) Copy of last year‘s narrative and
financial report 5) Copy of registration document; and 6) Copy of last institutional evaluation (if
existing).
Criteria for prioritising themes/issues for advocacy To make strategic choices of themes and issues for public awareness and advocacy work in Sweden and
internationally Diakonia has elaborated a set of criteria to serve as a checklist and guidance. They serve both on a
more general level, such as for choosing between geographic areas, and on a more specific level when choosing
what to focus on within that area.
The criteria capture three aspects; (1) if the theme is well founded in Diakonia‘s policy and constituency; (2) if the
theme is in line with the work and priorities made by rights-holders and partners in the regions and (3) if it is
considered feasible to have an impact on agendas and behaviour in Sweden and internationally. The criteria are as
follows:
Criteria 1 The theme is in line with Diakonia‘s global analysis, policy and main themes.
2 Possibility to stimulate debate, commitment, mobilisation (incl. popular education) among Diakonia‘s
System-based Audit of Diakonia
37
constituency, congregations and new target groups.
3 Potential for fundraising.
4 The theme reflects the priorities of partners and civil society in relation to Diakonia‘s over all regional
analysis.
5 Existence of strategic partners in the developing countries with a profound work within the theme and
that can feed into Diakonia‘s advocacy work in Sweden, the EU and internationally through
consequence analyses and ideological discussions.
6 Possibility to network in Sweden.
7 Existence of relevant networks in Europe and internationally to connect to.
8 Accumulated competence and experience within advocacy, popular education, mobilisation
and fundraising on the theme.
9 Sweden and/or the EU plays or is considered able to play an important role on the theme.
10 Possibility to wake interest for the theme in media.
11 Possibility for Diakonia to offer something unique relative other Swedish organisations.
On the basis of these criteria the issues and areas listed below were chosen for the period 2008-2010.
Global political and economic structures
Focus on a more equal distribution of resources and more resources transferred for poverty
eradication.
Focus on increased policy space for developing countries.
Focus on democratisation of global financial institutions and organisations.
Focus on increased qualitative participation by civil society organisations in processes of
crucial importance for development
Focus on how these structures affect women and men in different ways
Focus on shared but differentiated responsibility of rich and poor.
Peace and justice
Focus on the conflict in Israel/Palestine and its driving forces (main priority).
Focus on the conflict in the Democratic Republic of Congo and its driving forces (second
priority).
Other conflict areas such as Colombia, Burma, Zimbabwe, Somalia (lesser extent)
When it comes to Global political and economic structures the interviewees state that the criteria are
used in practice. In the area of Peace and justice Colombia is the only of the mentioned countries that
the Team visited. In Colombia some of the interviewees highlighted concerns related to Diakonias
ability to achieve the goals. One of the goals of the Swedish Government for cooperation with
Colombia is to strive towards a solution to the armed internal conflict by means of negotiations.
Towards this end, Diakonia arranged a seminar that took part a few months ago, involving several
actors in Colombia. A few of the interviewees doubt that Daikonia has the experience and
professional capacity to act adequately in the conflict. However, the dialogue should continue and a
wide range of actors should be invited to workshops allowing for open and imaginative ideas for
constructive cooperation. Among the parties it should be considered to include the Swedish Foreign
Office, Sida Head Office, the Swedish Embassy in Bogotá, several among the counterparts of
Diakonia (CINEP, Justapaz,…) and other donors.
System-based Audit of Diakonia
38
4.2.2 Conclusions and recommendations
The Team‘s assessment is that the criteria for selecting countries and building programmes are
adequate and used in practice in the ongoing restructuring and decentralisation process. The present
work on scaling up in prioritised countries and phasing out in others is clearly guided by the criteria
referred to in sub-section 4.2.1.
Also, building up the programmes is clearly guided by the criteria. A programme is composed by
grassroots‘ organisations, social and popular movements, indigenous organisations, churches and
ecumenical organisations, research institutes, and networks and umbrella organisations. To be cost-
effective it is supposed to contain 12-16 partner organisations. The Country programmes in the three
visited countries include 19, 15 and 12 Partner Organisations respectively. Based on the experience
from these countries the estimated number of Partner Organisations for cost-effectiveness seems
relevant. Also the size and capacity of the organisations, the size and character of the partners‘
programmes/projects and other factors are important. One weak Partner Organisation with suspected
misuse of funding can create more work for the CO than a handful well-functioning Partner
Organisations do.
The Programmatic approach is commendable. However, it may not always be possible to get funding
to a comprehensive programme of the required size. In order to attract more funding in some of the
selected countries it may be necessary to design the programme differently for example by having a
smaller core country programme combined with individual projects financed by different donors.
The Audit Team recommends that
In targeted countries where it is difficult to finance a cost-effective programme through core
funding Diakonia should consider reviewing the design of the Country programmes in order
to facilitate having a project portfolio financed by different donors in addition to the core
programme (h)
4.3 Involvement and ownership of partners and target groups in planning, monitoring and evaluation of projects/programmes
4.3.1 Observations and analysis
Diakonia states that socially sustainable development is a bottom-up process where the activities
should be based on local initiatives. The Partner Organisations and Diakonia view the cooperation as
long term change processes where Diakonia and its partners contribute with skills and resources in
order to reach a common goal. The concept of cooperation has precedence over the concept of
assistance. However, it is also emphasised that there must be a clear division of roles and
responsibilities between Diakonia and its partners in the work to reach the shared goal. The
cooperation between Diakonia and its Partner Organisations is focused on capacity building and
organisational development. Regardless of activity, the guiding principles are to support partners‘ and
System-based Audit of Diakonia
39
the rights holders‘ needs and efforts to develop knowledge and skills in order to effectively address
their own situation.
The interviewees at the visited COs and ROs told the Team that they have a horizontal working
relationship with the Partner Organisations based on trust, cooperation and coordination. Examples of
participatory planning include the assembly of partner organisations, especially when tri-annual plans
were being developed. In addition meetings are held with the network regularly and trainings are
offered in areas where the Partner Organisations have expressed shared needs.
In for example Kenya Diakonia gathers all Partner Organisations twice a year. In February an
―annual reflection‖ is organised to review the last years work, share results, review the relationship
between Diakonia and the partners, discuss the coming year‘s priorities and identify generic capacity
building needs. In September/October a ―capacity building meeting‖ is held on the topic (-s)
identified in February.
The Partner Organisations that the Team has visited have stated that Diakonia‘s requirements are fair.
They have stressed the importance of showing members and the general public that the Partner
Organisations are reliable and accountable. Diakanonia‘s requirements have facilitated the
development of transparent procedures and increased cost-effectiveness.
The rights holders‘ qualitative participation is at the core of the organisations and projects Diakonia
supports. Partners also participate in Diakonia‘s planning and monitoring when possible; however, not
primarily for the sake of ownership but for increasing the quality of Diakonias‘s programmes. The
programmes are owned by Diakonia and the analysis and the objectives set in the strategic plan are
Diakonia‘s. However, on the one hand the dialogue with the Partner Organisations influences
Diakonia‘s priorities, but on the other hand Diakonia emphasises that it is primarily lead by its
historical identity and the set of values linked to it. Participation by the constituencies in policy
discussions, public awareness campaigns and advocacy activities is fundamental for Diakonia‘s
legitimacy and ultimately its strength in promoting agendas in Sweden and internationally. With all
partners a certain match between identities is required in the sense that values and priorities are
shared, but beyond that the relation is in reality very much characterised by giving and taking and
mutual influence and learning. It is emphasised that Diakonia‘s opinions and analyses should
contribute to partners‘ and rights holders‘ perspectives on the work, rather than jeopardising their
sense of ownership over the projects.
4.3.2 Conclusions and recommendations
Diakonia has a well developed view on the involvement and ownership of partners and target groups
in planning, monitoring and evaluation of projects/programmes with clear distinction between
Diakonias responsibility for its programmes and the Partner Organisations responsibility for their
programmes and projects. These fundamental principles for Diakonia‘s cooperation are adhered to at
all levels.
Diakonia is mainly focussing on increasing the capacity that already exists locally. The Team is of
the opinion that Diakonia has a good balance between building capacity on the systems level (the
enabling environment), the organisational level and the individual level. Diakonia also seems to have
System-based Audit of Diakonia
40
a good grasp of the linkages between the three levels; thus, facilitating the involvement of target
groups in an adequate way.
As is already discussed earlier in the report there is room for improvement of the monitoring and
evaluation practises in the entire organisational chain. The Partner Organisations‘ evaluation plans in
connection to the Diakonia funding are mainly focused on measuring the results of the interventions.
Often the need for baseline studies is neglected. Target groups are often involved in the Partner
Organisation‘s planning of programmes and projects; however, baseline information is seldom
gathered in a systematic way.
The Audit Team recommends that
In the agreements with the Partner Organisations Diakonia should request them to conduct
baseline studies (l)
4.4 Systems for risk assessment and risk management (including corruption as a risk)
4.4.1 Observations and analysis
The decision memorandum made up in PHS constitutes the formal basis for decisions. It contains all
important information on what grounds decisions are/were taken and includes risk analysis in the
form of
Explanations on how external and/or internal factors may jeopardise the fulfilment of the
project‘s objectives.
Explanations on how coping strategies deal with these external and/or internal factors.
Diakonia tries to include when relevant findings in conflict impact assessment, feasibility-, and
climate impact assessment.
Risks can be identified through many different perspectives and on a more or less detailed level
depending on the context. It is within the scope of this system-based to assess certain types of risks.
These assessments are reported in the relevant sub-sections. One such example is that Diakonia Peru
Country office requires only one signature for check payments, bank transfers, and financial
transactions. Please refer to section 5.3 for details. The Team considers this a serious risk and has in
sub-section 5.3 recommended that as a precaution all checks and financial transactions should be
signed by two people.
Regarding corruption as a risk and procedures for acting on suspicions of corruption, Diakonia has
developed practical routines for how regional managers, programme officers and head of departments
and administrators shall report when financial or administrative irregularities are discovered13
.
Diakonia has a zero-tolerance level for misuse of funds or abuse of entrusted powers. The routines
when acting on suspicions of corruption including the division of responsibilities are described in the
Diakonia PME Handbook and the PHS manual. The routines were enforced in two instances in Latin
13
There is a special format for the report available at the Intranet and in the PHS and instructions on how to fill in the
report dated 2009-06-05
System-based Audit of Diakonia
41
America (Guatemala, 2009 and Colombia, 2010). In both instances incident reports were filed and
procedures followed. Staff with long experience of the region was not able to recall any other
instances of serious deviations from the routines for the last five years.
In section 5.5 the Team has summarised the findings related to the audits of three Partner
Organisations in Kenya. Two of these are also reviewed more in detail in Appendix 7 and 8. When it
comes to one of these - KEWWO - the Country Programme Manager submitted an Incident, alert and
non conformity report on the PHS on the 5th
May 2010. The misuse of funding in the other Partner
Organisation - AWEPON - has not been reported in the PHS.
In summary the risks in these two cases have been managed as follows:
In the management letter for 2007 for the African Women´s Economic Policy Network
(AWEPON) the Auditor has noted ―irregular funds virement‖. It is stated in the management
letter that Diakonia funding of USD 37,518 was not used for the agreed Project and that the
transfer was done without the donor‘s consent. In June 2010 Diakonia requested AWEPON to
pay back USD 37,518 as refunding of mis-applied funds in order to facilitate repayment to
Sida14
. AWEPON had not replied as per the Team‘s field visit mid-August 2010. In addition
to this the Auditor also in the management letter for 2007 noted a bunch of ―irregular
procurements payments‖. This has, however, not led to any action from Diakonia. Please refer
to Appendix 7 for more details. The partnership with the organisation has not been renewed.
The review of the audit report and management letter revealed that the Kenya Women
Workers Organization (KEWWO) financial records contained significant inconsistencies that
may impact on the accountability of funds given by Diakonia in 2008. However, the extent is
unknown as KEWWO refused to cooperate for the in-depth audit in August 2009. Diakonia
wrote to KEWWO in November 2009 to restart the in-depth audit. However, the office was
closed. None of the donors have been able to contact KEWWO at any level. Diakonia has
now engaged a firm to confirm the legal status of KEWWO and conduct a due diligence test.
Please refer to Appendix 8 for more details.
The Incident Report are normally not uploaded in PHS; it is saved on the Intranet, with limited access
for a smaller number of staff at management level, due to confidentiality. The Incident reports are
discussed at the Senior Management Team meetings at the HO.
4.4.2 Conclusions and recommendations
The decision memorandums made up in PHS include risk analysis. However, Diakonia has not
decided on a specific model for risk assessments and how this model should be used. Thus, also risk
management is an area that should be further developed15
.
Diakonia has a Zero tolerance on corruption. If there are suspicions on corruption this shall be
reported to the nearest management at once. HO shall also be informed as soon as a suspected case is
14
Letter from the Regional manager to the Chairperson, 9 June 2010 15
In the comments to the draft report Diakonia asked us to clearly define the two concepts ―Risk Assessment and Risk
Management‖; what does these two concepts include. Thus, we have separated from this report submitted two examples
of models that we have developed as assignments for Sida and another Swedish agency. Hopefully, these two examples
can inspire Diakonia in its efforts to develop its own concept.
System-based Audit of Diakonia
42
discovered. The format and instructions for reporting the suspicions are comprehensive. However, the
process on how to handle the case is not clear and also the division of responsibilities for the actions
needed is unclear.
Management at CO and RO is aware that issues surrounding Diakonia‘s partnership with AWEPON
and KEWWO need to be addressed and resolved promptly. Diakonia has contacted the partner
organisations several times and directed them to facilitate completion of audit processes or refund the
funding in question according to Diakonia‘s funding guidelines. The Country Programme Manager is
still closely following up to ensure that adequate actions are taken.
These incidents, however, indicate some general problems in Diakonia‘s processes and division of
responsibilities in case of suspicion of corruption or misuse of funding. There is no evidence of any
action from the HO regarding these incidents. The division of responsibilities between HO, RO and
CO needs to be clarified as well as the process of handling the incident. A few examples of questions
that must have an answer: How long is it acceptable to wait with reporting the incident? How long is
it acceptable to wait for the partner organisation‘s action? Who should lead the investigation? What
kind of action should be taken by Diakonia? When should legal actions be considered? What kind of
legal actions should be considered?
The relationship between Diakonia and its partners is built on trust and shared values. Thus, it is
natural that programme managers at Diakonia make friends with their counterparts. Taken this into
account it doesn‘t seem right to give the programme manager the responsibility for investigating
suspected corruption and misuse of funding. In some circumstances it is also a security issue. When
an incident is reported the head of next level of the organisation should take over and lead the
process. The programme manager and the partner organisation still needs to be involved in the
process but the process leader should be for example the Regional manager.
The Audit Team recommends that
Diakonia should implement a model for risk assessments and risk management (h)
Diakonia should in its dialog with Partner Organisations more explicit ask for risk
assessments and information on risk management (l)
Diakonia and its Partner Organisations should carefully follow up the misuse of funding that
has been reported in the past and continue to report any suspected misuse in the future (h)
Diakonia should implement a common process on how to handle reported incidents and mis-
use of funding (h)
Incident reports should always be written in PHS without delay (h)
When incidents of suspected misuse of funding has been reported in a Partner Organisation
the Regional manager should be responsible for the investigation and the investigation should
be carried out at the regional office (h)
4.5 Exit strategies with regard to sustainability of partner organisations as well as to projects and programmes
System-based Audit of Diakonia
43
4.5.1 Observations and analysis
Evaluations were carried out of all country programmes 2009 as basis for decision on phasing out
activities in the following countries: North Iraqi, El Salvador, Ghana, Senegal, South Africa and
India.
If Partner Organisations cannot live up to the criteria mentioned in sub-section 4.3 they must be
phased out and leave room for others16
. The possible reasons for phasing out a Partner Organisation
are all found in the ―Assessment form of partner‖, which is to be filled out every time a contract is to
be signed. Unless the reason for no longer meeting these criteria is financial irregularities, a phase out
plan is drawn up to make it possible for partners to adapt to the situation and equip itself adequately,
including for example initiatives on Diakonia‘s part to assist in finding alternative donors (see
below). A special memo explaining the reasons for phasing out is drafted and approved.
According to the interviewees few Partner Organisations have been phased out besides where the
Programme is closed. The main reasons for phasing out have been problems with the accountability
and sometimes the performance or resistance to build necessary capacity.
The closing of a programme must be preceded by the following actions/documents17
1. A programme evaluation focusing both on results, lessons learned and analysis of the criteria
2. A time table not exceeding three years
3. Decision memorandum
4. Decision by the Board of Directors
5. Responsible finalisation of all partnerships including phase out plans
6. Closing of all projects in PHS
7. Documentation of the whole process (electronic filing under programme).
8. Closure of programme in PHS
As already been mentioned in sub-section 3.3 the CO in South Africa closed 1st of May 2010 and five
more Country programmes are to be phased out. These processes have been carried out in accordance
with the stated procedure.
In many of the countries where Diakonia is working, there have been significant reductions in the
support from Sida. Diakonia has tried to maintain its relations with the Partner Organizations in
various ways. In Peru, where the reductions are about 50 %, the concept is to group the Partner
Organizations in clusters (―platforms‖), in which the members could develop new concepts and
applications in common. However, these platforms could also be used for cost-saving and increased
cost-effectiveness by working closer together and for example share some staff resources.
There seems to have been no discussion in Peru concerning the relevance of continuing supporting all
the Partner Organizations. The relations with most of them have been very long, for some several
decades, which indicate a high degree of loyalty in Diakonia. On the other hand, it might also
indicate the most comfortable way for Diakonia, just letting the cooperation continue.
16
The PME Handbook 17
The PME Handbook
System-based Audit of Diakonia
44
A third aspect involves core funding v. project funding: Funding for projects is time-limited, for the
period the project is running, which might be two-three years. Core funding does not have the
regulating time dimension, and the possibility for this type of support to continue ―for ever‖ is
considerable. There is also a risk for the Partner Organisations to become dependent on the support.
The Partner Organizations that Diakonia works with in the studied countries differ in strength and in
degree of support from other donors. Some are very big, very well organized, like CINEP in
Colombia, certified according to ISO 9001:2008, and with a long history. Others are quite small,
newer and with Diakonia as the major, or the only, donor. For the bigger ones, the contribution from
Diakonia is about 4-5% of their total budget, compared with 70-80% for the smaller and weaker ones.
According to key informants it has been rare to phase out Partners Organisations because they are
able to sustain on their own with other funding. One would think that the very big reduction of
support from Sida would be an opportunity for Diakonia to work through the options with an open
mind. It would seem a natural step to take to cease supporting the big, well established Partner
Organisations, in favour of the weaker ones. New roles could be discussed, where the big Partner
Organisations could act as mentors or coaches for the smaller ones at workshops or seminars. This
has also been practised to some extent but not explored systematically. In this way, relations would
still be maintained with all of them, while the support is utilised as usefully as possible.
4.5.2 Conclusions and recommendations
Diakonia has routines for closing a programme and criteria for phasing out Partner Organisations.
However, there are no exit strategies with regard to sustainability of Partner Organisations. It has
been rare to phase out Partners Organisations because they are able sustain on their own with other
funding.
As mentioned earlier in the report (section 4.3) Diakonia emphasises that the concept of cooperation
has precedence over the concept of assistance. Thus, it is a little bit surprising not to find elaborated
concepts of cooperation based on other forms than funding. Phasing out a Partner Organisation seems
to be synonym with not funding the Partner Organisation any more. Thus, the Team‘s conclusion is
that Diakonia should elaborate on when and how partnerships can be maintained within the Country
programme structure also without continued funding.
The Audit Team recommends that
Diakonia should clarify the criteria for different types of partnership with and without
financial support (l)
If the Platform model is to be applied by Diakonia in the rest of Latin America or globally,
cost-saving aspects and considerations ought to be taken into account (l)
5 Financial management and control
5.1 Financial systems
In this section we will present our findings in the following areas:
System-based Audit of Diakonia
45
Financial reporting system
Project management systems and chart of accounts
5.1.1 Observations and analysis
The administrative systems in Diakonia are at present the following18
:
VISMA – Financial system (bookkeeping, accounting, payments etc) – is the core part of Diakonia‘s
administrative systems. All other administrative systems are connected to Visma and deliver financial
information. The HO updates the book-keeping to enable overall financial reports and follow-up.
Twice a month reports are automatically sent by a report generator to all ROs with an updated
financial lists. The ROs work independently with financial systems of their own. Each month the ROs
have to present a monthly accounting report to the HO. This report, after being checked, is booked in
Visma. The monthly report is presented according to a standardised format that facilitates checking
the information and also facilitates informative demands concerning the general audit of Diakonia.
PHS – Project Handling System – is a system used for handling projects worldwide. All projects
connected to Diakonia‘s programmes are registered in the PHS. PHS enables planning, monitoring
and reporting of all projects connected to Diakonia‘s programmes. All financial information about the
projects can be found in PHS. Allocations and payments are registered and payments to partners are
transferred within the system. The programmes and their budgets are also registered in PHS. This
enables HO and RO to do financial monitoring by using reports found in PHS. All payments that are
being done through PHS are transferred to Visma and all information related to a project created by
another system is imported from Visma into PHS.
HOGIA Salary system is used at HO by all staff. The system keeps track of leaves, holidays and
also produces salary slips. At the ROs only the expatriates with Swedish employment agreements use
the system for time registration. Their time reporting (vacation, over-time etc.) is done in this system,
but they do not use the system for travel reporting. Hogia also records contracts, courses and so on.
All financial information is linked to Visma. FLEX Travel expenses system is used only at the HO,
so far. All financial information is linked to Hogia. Booking information from Hogia regarding
salaries is transferred automatically to Visma.
MYSOFT fundraising system is a register program that keep track on all individuals and
churches/congregations that donates funds to Diakonia. This enables Diakonia to work professionally
with fundraising. Through the system is it possible to evaluate different campaigns and keep track on
money donated to certain projects or areas. All financial information is linked to Visma. The Mysoft
system is handled by the Department of Fundraising and Communication.
The figure below shows the administrative and financial IT systems Diakonia is using and how they
interact. The most central parts are the financial system at HO, Visma, and the PHS system. While
PHS contains information on projects and programmes, Visma contains information regarding
financial transactions made by Diakonia in all parts of the world. Visma is handled by the Financial
Department at the HO.
18
Strategy Plan 2008-2010
System-based Audit of Diakonia
46
All RO and CO have Local financial systems for accounting. For example SIIGO accounting system is used
by Colombia National Office and Latin America Regional Office, as well as some Colombian counterparts.
Every other Latin American country uses their respective national accounting system as required by national
law. Office costs are booked as well as some project related costs. The book keeping at the local offices is
audited annually by a local auditor in the country.
To get the accounting from the RO and CO booked at HO in Visma these offices prepare the monthly
reports with the compiled information from the transactions in the local book keeping system. HO
books the information manually in Visma. All information regarding costs on projects in the monthly
report is transferred automatically to PHS.
The interviewees state that the diverse systems create a lot of extra work and are highly inefficient.
They wish that in the future Visma, or another financial system, could be used through the whole
organisation. Pilot studies have been carried out on a very initial level with test on internet speed and
possibilities to register information in a Visma system at all RO.
The PHS system has been functioning well; however, it is not adjusted to a situation with several
back-donors with different reporting requirements. Thus, the system will be changed in order to have
more efficient internal control and reporting. The goal is to have a new system in place in January
2012.
Interviews supplemented by review of documentation at the ROs and COs indicate that manuals and
procedures are followed and known by administrators in charge of PHS, payments and procurement.
Petty cash, archives management, bank accounts, are being correctly handled.
5.1.2 Conclusions and recommendations
All financial information for Diakonia is registered in Visma (information from PHS, Hogia/Flex,
Mysoft and Local financial systems). However, the processes are inefficient due to the use of several
different systems at different levels. There are plans to further develop the financial system as well as
the PHS with the aim to design a comprehensive global system. This will have the potential to
increase the efficiency significantly as the present overlaps and duplications will be eliminated.
Diakonia continues the work of developing a uniform IT infrastructure for the entire organisation.
System-based Audit of Diakonia
47
The Audit Team recommends that
Diakonia continues its efforts to implement an efficient financial management system (l)
5.2 Compliance with Agreements
5.2.1 Observations and analysis
Sida‘s grants to Diakonia are regulated in agreements and the General Conditions for Sida‘s Grants to
Swedish Non-Governmental Organisations.
Diakonia‘s grants to partners are regulated in the following documents:
Co-operation agreements with partners
General conditions for Diakonia‘s co-operation with partner
The Team has examined both Diakonia‘s own compliance with the general conditions and Diakonia‘s
internal control of the compliance in the Partner Organisations.
Assessment of compliance with Sida’s General Conditions
In this sub-section the Audit Team presents the assessment of Diakonia‘s compliance with the
―General Conditions for Sida’s Grants to Swedish Non-Governmental Organisations (2003)‖.
Conditions reviewed Yes No Comments
Agreements (Section 5)
The organization enters into agreements with
organisations at the next level. x
The organization‘s agreements with next-level
organisations come into effect before funds are
disbursed.
x
The organization‘s agreements with next-level
organisations include applicable conditions
from the General Conditions, sections 6, 8, 9, 10,
and 11.
x Agreements with partner organisations do not
always include regulations regarding
procurement.
Requisition and disbursement of funds (Section 6)
Sida funds are only disbursed from the organization
to a next-level organization when the latter has
submitted the stipulated reports.
x
Administration of funds (Section 7)
The organization keeps Sida funds in a separate bank
account. x
Two persons in the organization are to sign jointly
for the separate bank account for Sida funds. x Colombia country office representative is, at the
moment, the only person with authority to sign
checks and approve bank financial transactions.
The organization ensures that next-level
organisations keep Sida funds in a bank account. x Please note the comments on the situation in
Somalia in section 5.3. Taken into account the
context in which Diakonia operates in Somalia
System-based Audit of Diakonia
48
Diakonia is acting appropriate that should be
regarded as in compliance with Sida‘s
intensions.
Repayment of funds (Section 8)
The organization repays Sida funds that have not
been used. x
Results reports and financial accounts (Section 9)
The organization applies generally accepted
accounting principles. x
Financial audit (Section 10)
The organization is audited in accordance with
Sida‘s audit instruction 1. x
A certified auditor audits the organization. x
The organization submits an audit certificate to Sida,
in accordance with audit instruction 1. x
The organization submits an audit report to Sida in
accordance with the Audit Guide. x
In agreements with next-level organisations, the
organization has included conditions related
to financial audit in accordance with the Audit
Guide.
x
The organization reviews the financial audit in
organisations at the next level, in accordance with
the Audit Guide.
x
Assessment of compliance with Diakonia’s framework agreements with Sida
In this sub-section the Audit Team presents the assessment of Diakonia‘s compliance with relevant
parts of the agreements with Sida.
Conditions reviewed Yes No Observations
4.6 Obligations of Information x
6.2.2 Budget Diakonia shall describe the calculation of own
contribution as well as their control system regarding
the origin of their own contributions.
x
8.3 Administration of funds Diakonia should keep Sida funds in a separate bank
account. This account should be signed by at least
two persons in the organization. Diakonia should
ensure that local NGOs at next level keep Sida funds
in a bank account.
x The CO in Peru does not keep a separate bank
account for Diakonia funds.
Colombia CO representative is, at the moment,
the only person with authority to sign checks
and approve bank financial transactions.
8.5 Financial audit
There should be an unbroken chain of audit
certificates / audit reports with audit memorandum /
x Several partner organisations has not submitted
audit certificates and/or management letters
System-based Audit of Diakonia
49
management letter for Sida funds down to the final
beneficiary organization.
8.5.1 Diakonia is responsible for the control of the
financial audit in organizations at all levels. x In the absence of management letters Diakonia
is not in a position to control and act on issues
identified by the auditor
8.6 Procurement regulations x Agreements with partner organisations do not
always include regulations regarding
procurement.
8.7 Misuse of funds and inappropriate behaviour x Please refer to section 4.4
9.5 Administration grant x
11 Repayment of funds x
5.2.2 Conclusions and recommendations
Diakonia meets Sida‘s terms and conditions with a few exceptions as detailed in this report. The new
agreements with Partner Organizations and the close monitoring of the Partner Organisations internal
control system has the potential of securing that the Partner Organisations also comply with the
regulations. However, the tables above show that there are still a few parts of the internal control
system that Diakonia should develop further to better meet Sida‘s regulations. The Team is also of
the opinion that the monitoring of the Partner Organisations internal control system should be done
more systematically through more frequent visits to the partners. Diakonia could for example develop
a checklist or a questionnaire for internal control and monitoring, to be used at the start of the
cooperation with a new Partner Organisation and follow-up meetings the all others.
Diakonia comply with the agreement that Sida funds are only disbursed from the organization to a
next-level organization when the latter has submitted the stipulated reports. The consequence is that
disbursement of funds are sometimes late in relation to what is agreed in the contract with the Partner
Organisation and also late in relation to Diakonia‘s own internal reporting requirements. In order to
avoid reporting through several levels it might in some cases be possible to use tripartite contracts.
This means an agreement between for example Diakonia, the coordinating Partner Organisation and
the implementing organisation. Such an agreement should be based on a ToR or a Programme/project
document that clearly outlines the division of responsibilities between the parties.
The Audit Team recommends that
Diakonia should intensify its efforts to increase the compliance with the agreements with Sida
(h)
Diakonia should monitor the Partner Organisations‘ internal controls systems in a more
systematic way (h)
Diakonia should visit the Partner Organisations more frequently for monitoring their internal
control system (l)
Diakonia should consider using tripartite contracts when activities are being coordinated by a
Partner Organisation but implemented by other organisations (h)
System-based Audit of Diakonia
50
Diakonia should agree on realistic deadlines particularly in the case of projects funded
through Partner Organisations head offices to lower organisational levels (l)
5.3 Transfers of funds and bank and cash holdings
5.3.1 Observations and analysis
At the HO the right to sign Diakonia is regulated by the Boards decision per capsulam of the 21
September 2009. Also, the rights to sign at RO and CO levels are clearly regulated.
The right to sign the Partner Organisations is decided by each Partner Organisation.
The Partner Organisations are to keep funds granted by Diakonia in a bank account whose holder
should be, if possible, the Partner Organisation itself. The information about the bank account is
included in appendix 1 to the contract, which should be signed jointly by two persons authorised by
the organisation.
The General conditions for the support to the Partner Organisations are available through the PME
handbook. It is stated that agreements take precedence over General Conditions. Diakonia states that
the contract shall be signed respectively by the authorised representative of Diakonia and a board
member and the financial manager of the partner. However, in practice the agreement must be signed
by the Partner Organisation in accordance with its own regulations. The signatory partner is solely
responsible for the implementation of the project.
In Somalia lacking a bank system the Partner Organisations have accounts with financial brokers.
The ―Amal brokerage‖ keeps accounts and issues check books and operates in the same way as
banks.
Under the contract with the Partner Organisation, Diakonia may decide to withhold the disbursement,
wholly or in part:
i) if substantial deviations from the presented Work Plan and budget occur;
ii) if reports are not delivered as agreed on;
iii) if the main programme objectives are endangered;
iv) if the programme develops unfavourably in terms of the sub-goals or in any unfavourable manner.
v) if improper implementation as described in the contract is detected or suspected
Before taking such a decision, Diakonia shall initiate discussions with the Partner Organisation.
During the period in which the contract is valid, the plan/project supported may not be transferred to
another organisation without prior agreement in writing between both parties.
Diakonia states that the payments to the Partner Organisation shall be stopped when:
the partner has not reported to Diakonia in spite of reminders
the partner organisation has not remitted the receipt of the previous payment
the partner organisation has not presented satisfactory answers to Diakonia‘s inquiries
there are substantial deviations from the partner organisation‘s Work Plan and budget
System-based Audit of Diakonia
51
the partner organisation‘s main programme objectives are endangered
the partner organisation‘s programme develops unfavourably in terms of the sub-goals or in
any unfavourable manner
the partner organisation‘s implementing and administrative capacity is too weak despite
organisational strengthening
there are is reason to believe that there has been embezzlement
One of the three visited Country offices - Diakonia Peru Country office - requires only one signature
(the CO representative) for check payments, bank transfers, and financial transactions. At the
moment no alternative plans are in place. The Team considers this a serious risk that makes the
procedures vulnerable. According to key informants this is not a unique example; this has also been
practiced in for example Mozambique.
After reviewing the audit memorandum for Latin America and ESA the Team has found no major
internal control mechanisms or financial report problems. However, some bank reconciliations in the
beginning of 2009 at the RO for ESA were done late due to the fact that posting entries in the year
2009 was done upon finalisation of the 2008 annual audit. The Auditor also noted that cash count for
US Dollars in the month of May 2009 indicated a balance of zero while the cash book reflected a
negative balance of USD 6,099.93. No reconciliation was done to explain the discrepancy.
The Team has noted cash transfers in Partner Organisations that constitutes major risks. One example
is mentioned in section 4.4 and Appendix 7. A total of six payments were made on 12 Nov 2007 in
cash to the same vendor for printing and binding reports for invoices made on 2 Nov 2007. The cash
payment amounted to more than 110.000 SEK without any purchase order, payment vouchers or
quotations from other vendors. In this case there were no reason at all for cash payments, no reason at
all for non-compliance with procurement regulations and no reasons at all for using the vendor that
were paid and no evidence that the goods were delivered. No actions have been taken by Diakonia in
regard to this obvious case of suspected misuse of funding. However, Diakonia has initiated actions
on other problems related to the same Partner Organisation as referred to in section 4.4.
5.3.2 Conclusions and recommendations
Diakonia states that the contract shall be signed by a board member and the financial manager of the
partner. However, each Partner Organisation has the responsibility for the decision on who should be
authorised to sign for the organisation.
One of the tree visited Country offices requires only one signature for check payments, bank
transfers, and financial transactions19
. The Team considers this a serious risk that makes the
procedures vulnerable.
19
In Latin America checks are signed by only one authorized person but the procedure applied in the preparation phase
requires at least one or two prepared and revised signatures. Diakonia states that it is difficult to have two signatures for
checks, as it will cause delays and stop in processes (due to small structures with few staff, travelling, etc)
System-based Audit of Diakonia
52
Cash payments have been done in away that opens up for misuse of funding and corruption. Diakonia
has not always taken adequate action not even in cases where this problem has been reported by the
auditor in the management letter.
The Audit Team recommends that
Diakonia should change the requirements when it comes to signing the contracts to comply
with the Partner Organisation‘s own regulations (l)
Diakonia should require that cash payment in Partner organisations should not be allowed for
payment over for example 1 000 SEK (h)
As a precaution all checks and financial transactions should be signed by two people (h)
5.4 Systems, rules and routines for procurement
5.4.1 Observations and analysis
In all work carried out by Diakonia transparency, good governance, anti-corruption, environmental
protection, non discrimination and respect for Human Rights are core values20
. Diakonia states that it
is important to ensure that procurements are carried out transparently, efficiently, in accordance to
general law, in a commercial way with competition and in accordance with Diakonia‘s policy and
goals in all purchases of goods or services, independently of the items value. It also involves
documenting the procedures so that controls and audits can take place.
Thus, Diakonia‘s contracts with Partner Organisations shall always have a paragraph on procurement.
However, in practice agreements with Partner Organisations do not always include regulations
regarding procurement.
Diakonia‘s Procurement guidelines are to be used by all Diakonia offices when buying goods or
services. These Guidelines also apply to Partner Organistaions when they procure with grants from
Diakonia. Partner Organisations need to apply the procurement rules set out in the contract Diakonia
has with the back-donor financing the programme in question. Partners may use their own
procurement procedures and rules if considered meeting Diakonia standards. Diakonia assists Partner
Organisations regarding procurement guidelines in case they have no rules. This has been done by
assisting the Partner Organisation to developing its own guidelines and also in helping Partner
Organisations to implement and apply Diakonia‘s. Partner Organisations must document the
procurement processes so they can be followed up in reports and audits.
Diakonia states that the procurement guidelines are tools that give guidance when buying goods or
services. When using the guidelines they also serve as a form of ―protection‖ or insurance for
avoiding unethical or corrupt actions when negotiating or buying things from different suppliers. The
rules are also to help the procuring employee in the comparison of different quotes from suppliers.
The Team has visited Partner Organisations with more rigorous regulations of procurement than
those presented in Diakonia‘s guidelines. One example is MCF in Kenya that seems handle
20
Procurement Guidelines for Diakonia, 2009-03-20
System-based Audit of Diakonia
53
procurement policies and practices in a way that could serve as a learning example for Diakonia‘s
Partner Organisations. On the other hand there are Partner Organisations that neither in theory or in
practice are even close to what Sida is requiring. One example has been mentioned in section 5.3.
5.4.2 Conclusions and recommendations
Diakonia has procurement guidelines in place. These should also be applied by the Partner
Organisations. However, in practice procurement is not even regulated in all contracts with Partner
Organisations. Some Partner Organisations have procurement regulations in place that are meeting
International standards. Other Partner Organisations are practicing procurement in a way that opens
up for corruption and misuse of funding.
The Audit Team recommends that
Diakonia includes procurement regulations in all contracts with Partner Organisations (h)
Diakonia in its follow up of the Partner Organisations internal control secure compliance with
the procurement regulations (h)
5.5 Audits
In this section we will cover the following audit questions per ToR:
Audits in all parts of the organization, quality of audit certificates including an assessment of
whether audits comply with Sida‘s audit requirements for Diakonia
Competence and routines at Diakonia for analysing and acting on audit issues and suspected
irregularities
The view of Diakonia‘s auditor on the audit of framework grants from Sida.
5.5.1 Observations and analysis
The Diakonia Audit guide is to be applied to all projects and programmes21
. It is therefore necessary
that Diakonia HO secure that all Ro and CO use and apply the updated Audit guide. The two major
changes to the earlier version of the Diakonia Audit guide are: 1) Sida is demanding that the
International Standard on Auditing (ISA) shall be used instead of General Accepted Auditing
Standards. ISA should therefore be used in all cases where it is possible. 2) Diakonia only has one
instruction for all grants instead of two as before. In the old version there was one instruction for
grants above 200 000 SEK, and one for grants below 200 000 SEK. The other adjustments which
have been made are regarding: 1) Appointment of auditor, 2) Risk of corruption, 3) Subsequent links,
4) Format for audit certificate, 5) Format for audit memorandum and 6) Comments on audit for
Humanitarian projects 2006 and 2007. The partner organisations‘ auditors seem to have been
informed on these changes by the partner organisations to a varying degree.
The Team has found the Diakonia Audit guide to be well known at the ROs and COs visited.
21
Diakonia Audit Guide 2009-11-10
System-based Audit of Diakonia
54
Diakonia has also informed the Partner Organisations on the need to adhere to the Diakonia Audit
guide. In for example Kenya the Diakonia Audit guide was presented and discussed at the Partners
forum where all Partner Organisations participated.
Local auditors are used at the COs and the Partner Organisations in all countries except in Somalia,
where auditors from Kenya are used. In some countries Diakonia has experienced difficulties with the
quality of the local auditors especially in Mozambique (ÖhrlingsPriceWaterhouseCoopers) and
Zimbabwe (BDO).
ÖhrlingsPriceWaterhouseCoopers has audited Diakonias financial reports under the agreement with
Sida in accordance with generally accepted auditing standards, based upon SNT 4400 and in
accordance with Sida‘s Audit instructions. The Team‘s opinion is that the Audit certificate from
ÖhrlingsPriceWaterhouseCoopers is of good quality22
. It notes that agreements with Partner
Organisations do not include regulations regarding procurement. It also notes that formal
Management letters in some cases have not been submitted. In addition, the Audit Memorandum23
notes some significant observations. It notes that in four out of five samples where Management letter
is missing the audit reports contain the corresponding information. During the review 2009
ÖhrlingsPriceWaterhouseCoopers noticed that unreported project costs which should have been
reported 2008 or earlier amounts to MSEK 45.7 out of which MSEK 19.7 relates to project costs for
the years 2007 and 2008, MSEK 24.4 to 2004-2006 and MSEK 1.6 to 2003.
The audit for each RO and CO depends upon the legal status, inherent risk and control risk for that
office. In most locations, local regulations require both a Management audit and an Audit of year-end
to be performed for the local reporting purposes. Regarding the Management audit it is required that
Management letters will be raised. If there is no issue to be reported this should be stated in the
report. Any comment by the auditor of internal control or any other issue should be documented in
the Management letter. Each office gets a written management response to its own Management
letter. It is recommended to include the Management response in the Management letter below each
recommendation from the auditor. The same principles apply for the Partner Organisations.
The grant Audit Certificate is sometimes a separate document and sometimes included as a separate
signed page in the Audit Financial Statement. However, it is also common to see the Audit opinion in
the Audit report as the Audit certificate. The wording of the Audit opinion is normally close to what
is required in the Audit Certificate required by Sida. At least the message is the same. However, for
some local auditors it is confusing to be required to deliver both the Audit report and an Audit
certificate. This has been communicated with Sida for some time by FAR and some of the auditors
used by the frame organisations24
. Diakonia‘s auditor share the views expressed in these Memos to
Sida. The issues under discussion and the different views on these are clearly presented in these
22
Audit Certificate for Diakonia, dated 14 May 2009 23
Audit Memorandum regarding the audit of Diakonia‘s agreement with Sida for 2008-2010, dated 14 May 2009 24
PM: Synpunkter på Sidas nya revisionsregel, 2009-04-06 (Diakonia, Plan Sverige, Rädda Barnen, Svenska Röda
Korset); Svar från Sida på detta PM, 209-06-04; PM: Synpunkter på Sidas revisionshandbok 2009-11-16 (Diakonia, Plan
Sverige, Rädda Barnen, Svenska Röda Korset och PricewaterhouseCoopers); Skrivelse från FAR till Sida: Revisors
granskning och rapportering avseende program/projekt/insatser som genomförs helt eller delvis med stöd av medel från
Sida, 25 maj 2010 med bilagan Kommenterade Sida-dokument samt Sidas svar till FAR, 2010-06-30
System-based Audit of Diakonia
55
documents. Sida has assigned Ehrenberg Konsult to together with Allegretto review and clarify Sidas
instruction25
. The Team has been told that the draft problem analysis will be available in a few weeks.
Diakonia has a special form for the assessment of the Partner Organisations‘ audit reports. Partner's
audit report must be approved by Diakonia before any further payment is permitted. Furthermore, if
the Audit report is not approved Diakonia will not renew the contract.
The Team‘s assessments of the Audit memorandums from Partner Organisations in Colombia and
Peru showed no major irregularities. However, as will be detailed below, there have been some
reported irregularities in Kenya. Most common comments in the three visited countries taken together
had to do with the need to strengthen internal administrative controls in the Partner Organisations.
The most common comment in Peru was on timing problems due to clash between Peruvian end of
the fiscal year and Diakonia‘s. This forces auditors in Peru to comment on matters which would not
appear if audits were done after the completion of the Peruvian fiscal year.
Also the Assessments carried out by Diakonia reveal some administrative problems to address in the
Partner Organisations. Frequent notes in Management letters from Auditors and Assessments from
Diakonia regarding Partner Organisations are the following:
Risk analysis are not carried out and/or documented.
Only one staff knows how the financial management system works.
The annual budget is not broken down into shorter periods (quarterly for example) where
performance is monitored against budgeted performance.
Deviations or variances from work plans and budgets are not extracted and analysed.
Action plans are not developed on how to eliminate identified problems.
Appropriate action is not taken to rectify identified issues and/or there is no follow up to
secure that planned action has taken place.
It takes long time before questions to management on reports or financial statements are
clarified.
Purchase of goods and services without quotes or a quote only from the selected provider.
Purchase orders are missing.
Payment vouchers are missing.
Surprise cash counts are not carried out.
Less frequent notes in Management letters from Auditors and Assessments from Diakonia are as
follows:
Deduction from salary is done for Pay as You Earn Systems or National Social Security
systems but payments are not made to the relevant state organs.
Large amounts of cash are withdrawn from bank for payment to vendors.
The Team has assessed the competence and routines at Diakonia for analysing and acting on audit
issues and suspected irregularities. The Team has found that the competence is good when it comes to
the analysis. However, when it comes to action it is more complicated. Then it is not only a question
of analytical skill. Programme officers who are highly competent in objective analysis may have
25
Sidas instruktion för bidragsposten Stöd genom svenska organisationer i det civila samhället, 2010-02-18.
System-based Audit of Diakonia
56
difficulties when it comes to action. The necessary actions influence the relations with the
counterparts within the Partner Organisation and, thus, the character of that relation plays a
significant role.
In most cases Diakonia has had a fruitful dialogue with the Partner Organisation on the audit reports
and management letters leading to constructive actions by the partner in order to solve the identified
problems. However, there are also examples where the Partner Organisation has not taken adequate
action and, thus, Diakonia has had to act accordingly:
The 2007 audit report from CREDO (Constitution & Reform Education Consortium) had a
qualified opinion with respect to a banking fraud. The management letter submitted did not
include management response. Seeking clarifications, Diakonia received no response and
subsequently a decision was taken not to renew the partnership with the organisation.
In the management letter for 2007 for the African Women´s Economic Policy Network
(AWEPON) the Auditor has noted ―irregular funds virement‖. This issue has not been solved
yet. Please refer to Appendix 7 for more details.
The review of the audit report and management letter revealed that the Kenya Women
Workers Organization (KEWWO) financial records contained significant inconsistencies that
may impact on the accountability of funds given by Diakonia in 2008. This issue has not been
solved yet. Please refer to Appendix 8 for more details
The Country Programme Manager submitted an Incident, alert and non conformity report on
KEWWO on the PHS on the 5th
May 2010. The misuse of funding in AWEPON has not been
reported in the PHS.
These examples indicate that there is need for changes on the system level on how to handle these
issues, not to put the individual programme officers in an impossible situation of mixed loyalties
based on invested trust.
5.5.2 Conclusions and recommendations
The audit of framework grants from Sida has been communicated with Sida for some time by
Diakonia and other frame organisations, some of their auditors and FAR. The issues under discussion
and the different views on these are clearly presented in the documents mentioned in sub-section
5.5.1.
In most Partner Organisations the Audits are of good quality even if they sometimes are not meeting
the requirements when it comes to Audit certificates. In member-based organisations it is stressed
that the Auditor‘s report is directed to the members. For the sake of transparency the Management
letter should be available for the Board, the members and the donors upon request.
Some local auditors are reluctant to issue both specific Audit Certificates and Audit reports arguing
that their Audit opinion in the Audit report is what they are required to deliver according to the
International Accepted Standards they use. The Team‘s understanding is that this issue will be
addressed by Sida. Since a comprehensive analysis will be available shortly that will give a much
System-based Audit of Diakonia
57
more substantive point of departure for recommendations than is the case in this system-based audit
of one frame organisation only the Team will not provide any recommendations in this regard.
The Team is of the opinion that the competence is high enough at all levels of Diakonia to analyse
audit reports and management letters. However, there is need to improve the processes when it comes
to how Diakonia act in practice on suspected irregularities. Please refer to the recommendations in
section 4.4.
The Audit Team recommends that
Diakonia should establish routines and incentives that guarantee that audit reports, audit
certificates and management letters are submitted in time (h)
Diakonia should advice its Partner Organisations that the Management letter should be
available for the Board, the members and the donors upon request (l)
6 Aid effectiveness 6.1.1 Observations and analysis
The Team has in section 4.3 detailed how Diakonia views ownership. It is obvious that Diakonia
respect the leadership of the Partner Organisations and help strengthen their capacity to exercise it.
Diakonia also accept the Partner Organisations systems and procedures to the maximum extent
possible given the need to comply with the regulations set by the back-donors. Where use of the
Partner Organisation‘s systems is not feasible, Diakonia tries to establish additional safeguards and
measures in ways that strengthen rather than undermine these systems and procedures. There have
been some problems related to different requirements on the Partner Organisations as detailed in
section 5.5. None of the visited Partner Organisations have been forced to establish specific structures
for the implementation of the Diakonia-financed projects and programmes in addition to the usual
day-to-day management.
Diakonia distinguishes between core funding and project support. Both can be granted. As is detailed
in sub-section 2.7.3 the Team has visited both partner organisations receiving core funding and others
with project support. Six of the selected partner organisations have project support and nine have core
funding. Thus, the Team has been in a position also to assess differences in the management systems
related to type of funding. Core funding is understood as funding directed to the organisation as a
whole, to be channelled within the organisation in the way that partners find most convenient.
Diakonia does however consider it important that the responsibility for covering the administrative
costs is shared between all back donors. Partners are therefore expected to strive for administrative
contributions in negotiations with other back donors26
.
Long term partnerships are often characterised by core funding, but not necessarily. For example
currently all partner organizations in the Kenya programme receive project support. Core funding is
not common during the pilot phase. Even though project funding limits the funds to a separate
project, the project is preferably an integral part of a larger strategy plan.
26
The PME Handbook
System-based Audit of Diakonia
58
Diakonia's current frame agreements with Sida/Seka and Sida/Rela imply a three plus one year
contract, meaning that the contract is for four years. The final report should be submitted already
after the first three years. The last year is considered a bridging year and is reported separately for
one year on the same results as the final report. The normal contract template needs editing for
periods shorter than four years.
Presently Diakonia is reviewing its instruments also detailing in the agreements the differences in
requirements between core funding and project support.
Many interviewees has pointed out that core funding facilitate aid effectiveness. Diakonia‘s Eastern
and Southern Africa region has also elaborated on this issue in a paper27
:
Ownership: Core funding is a more flexible funding where the Partner Organization is given
the freedom to allocate funds to the various budget items. The pre-requisite is that the Partner
Organization must have the needed capacity to take on this responsibility.
Harmonization: Development is a joint effort of many actors. Most Partner Organizations
have multiple donors who are interested in the same results. Core funding among the co-
funders would not only make it easier for the Partner Organizations to service them but also
catalyze the harmonization process. For example, because funding will be made into a basket,
reporting would be done generally without segregation.
Managing for results: Support to Partner Organizations is given to facilitate them in achieving
their planned results. Failing to support overhead costs means that the Partner Organizations
are expected to work for results without any consideration of the people necessary for those
results. Sustainable results require investments in staff skills, strategic work and
organizational development. Thus, the contract period normally used at present is assessed as
giving the Partner Organizations a reasonable number of years to work against their visions.
One year contracts are assessed to be too short to be efficient.
Mutual accountability: Donors and partners are accountable for development results. This
confirms healthy partnerships where both the donor and the partners have roles and
responsibilities. Core funding recognizes that there are many contributors to development
results and none can claim the full share.
When it comes to alignment on a more general level, traditionally Diakonia has not been cooperating
in the field with other international organisations, donors or the other Swedish frame organisations
with the aim at harmonising procedures. In 2009, Diakonia became a member of the Humanitarian
Accountability Partnership (HAP). HAP is an organisation that aims to raise the quality and
coordination of humanitarian action in the world. Diakonia is also member of CONCORD and take
part in its advocacy and training activities on the EC level. Diakonia has also participated in the
activities of Action by Churches Together (ACT). Diakonia is also a member of, and has been very
active both in APRODEV and in Eurodad regarding aid effectiveness on a European and global level.
Diakonia was very active in the process leading up to the Accra meeting. Diakonia took part in and
contributed towards the following workshops amongst other things:
- Northern Regional Workshop on Civil Society and Aid Effectiveness, held in Brussels on
Monday 15 October & Tuesday 16 October 2007
27
Diakonia, Eastern and Southern Africa region: Core funding, 16th December 2008
System-based Audit of Diakonia
59
- Global North / South Civil Society Dialogue meeting in Nairobi, November 15/16, 2007
- International Forum on civil society and aid effectiveness in Ottawa 3-6 February, 2008
- Actively participating, representing APRODEV, in the Open Forum for CSO Development
Effectiveness, in the Global Facilitation Group, 29 an30 June 2008; and
- The Accra meeting itself,
In 2007 Diakonia together with other Swedish NGO‘s in Kenya made a study called ―Consequences
of the Paris Agenda on Civil Society in Kenya‖. In Kenya Diakonia has also organised seminars for
the Partner Organisations in cooperation with other Swedish frame organisations as for example Save
the Children in order to establish shared views on for example anti-corruption and procurement.
Diakonia tries to participate in meetings and seminars arranged by the Partner Organisations to meet
with their other funders among others with the aim to coordinate reporting and harmonise
requirements on performance assessments so as to avoid presenting Partner Organisations with an
excessive number of potentially conflicting targets and results indicators.
Diakonia also participates in seminars and meetings arranged by the Swedish Embassies.
Interviewees at Diakonia have underlined the importance of increased coherence between Sida-
Stockholm and the Swedish Embassies. Among others coordination on the reporting requirements are
requested.
Interviewees have proposed that Diakonia on the regional level of its organisation should cooperate
with relevant regional church organisations in order to share experiences, disseminate findings from
local programmes and projects, coordinate and prioritise country programmes and projects.
6.1.2 Conclusions and recommendations
Diakonia respect the Partner Organisations‘ ownership and is actively supporting the further
development of their capacity. Diakonia try to align with the Partner Organisations‘ own systems and
procedures to the extent possible; however, the need to comply with back-donors requirements puts
some limitations to these efforts.
Long term partnerships are often characterised by core funding, but not necessarily. The normal
contract period of three plus one year is adequate in order to give the Partner Organisations enough
time to implant their strategic plans and achieve sustainable results. Core funding is not common
during the pilot phase. Diakonia considers it important that the responsibility for covering the
administrative costs is shared between all back donors. Partner organisations are therefore expected
to strive for administrative contributions in negotiations with other back donors.
At the individual Partner Organisation level Diakonia has participated in efforts to harmonise
procedures. Diakonia has also been active in the area of aid effectiveness in general especially on the
global level. Diakonia has declared its awareness of the need to continue to work pro-active in this
regard.
The Audit Team recommends that
Diakonia should make efforts to have regular meetings with other organisations that support
CSOs in the same country (l)
System-based Audit of Diakonia
60
Diakonia should always actively participate in meetings that the Partner Organisations are
organising for their funders (l)
Diakonia should discuss the added value of regional cooperation with regional churches and
networks (l)
System-based Audit of Diakonia
61
7 Sammanfattning (Executive Summary in Swedish)
7.1 Inledning
Diakonia är det gemensamma biståndsorganet för fem svenska kyrkor, nämligen Alliansmissionen,
Baptistsamfundet, Evangeliska Frikyrkan, Metodistkyrkan och Missionskyrkan. Diakonias
representantskap fattar beslut av övergripande karaktär, utser styrelseledamöter och fastställer de
ekonomiska ramarna.
Diakonias arbete sker i partnerskap med cirka 400 lokala organisationer, samfund och folkligt
förankrade rörelser i ett 30-tal länder. Genom dessa görs insatser för varaktig förändring av
situationen för de mest utsatta och fattiga. Centrala arbetsområden är demokratisering, mänskliga
rättigheter, jämställdhet, ekonomisk och social rättvisa samt fred och försoning. Diakonia anser att ett
starkt civilt samhälle är av fundamental betydelse för en hållbar utveckling. Tillsammans med
medlemskyrkorna arbetar Diakonia i Sverige med folkbildning, mobilisering, kampanjer och
insamling.
7.2 Observationer och analys
Vi har analyserat relevant dokumentation från Diakonia och Sida. Dessutom har vi genomfört
fältresor till de regionala kontoren för Afrika och Latinamerika, samt landkontoren för Kenya,
Colombia och Peru, för dokumentgranskning och intervjuer. För att studera hela organisationskedjan
har vi också besökt ett urval på 15 partnerorganisationer för att granska deras system och intervjua
representanter för dessa organisationer. Vi har också intervjuat Sidapersonal, personal vid Diakonias
huvudkontor, Diakonias revisor samt Diakonias styrelseordförande och ett urval på ytterligare fyra
styrelseledamöter. Sammanlagt har 135 personer intervjuats.
Sammanfattningsvis har vi gjort följande observationer (i den ordningsföljd som anges i
uppdragsbeskrivningen i bilaga 1):
7.2.1 Organisationsstruktur
Mission, vision, mål och policies
Diakonias uppgift, övergripande mål och vision delas av styrelse och personal och är väl förankrat i
hela organisationen. Partnerorganisationerna uppskattar Diakonia inte bara för det ekonomiska stödet
utan även för värdegemenskapen och stödet i utvecklingen av organisationernas kapacitet. Vi
bedömer dock att de pågående förändringarna av huvudmannaskapsstrukturen innebär en risk om
dessa förändringar medför att grundläggande värderingar, uppgifter och vision skulle ändras märkbart
utan att detta är förankrat hos de viktigaste intressenterna.
Styrelsens roll och mandat
Styrelsen har en tydlig roll och ett tydligt mandat. Förändringarna av huvudmannaskapsstrukturen
kommer emellertid att påverka styrelsearbetet och innebär en betydande risk som måste hanteras på
rätt sätt. Konsekvenserna av att tre medlemskyrkor slås samman och att de två återstående eventuellt
lämnar Diakonia bör analyseras mera noggrant.
System-based Audit of Diakonia
62
Organisation och beslutsprocesser
Diakonia håller på att utveckla en mer decentraliserad organisation som är mer flexibel och som är
lättare att anpassa till nya förutsättningar och utvecklingsbehov. Hittills har processen varit
framgångsrik. Införande av resultatkontrakt och årliga uppföljningar av resultat skulle öka
resultatorienteringen ytterligare och säkerställa en bra arbetsmiljö med tydligt avgränsade krav och
förväntningar och en återkoppling där goda resultat uppmärksammas och belönas.
Organisation och beslutsprocesser är tydliga. Projekthanteringssystemet är utformat för Sida-stödda
program och projekt och behöver göras mer flexibelt så att det även passar för EU- och FN-stöd.
7.2.2 Verksamhetsstyrning
Resultatstyrning
Såväl Diakonia, på alla nivåer, som partnerorganisationerna gör stora ansträngningar för att öka
resultatorienteringen. Diakonias handbok anger minimistandarden i projektcykeln på ett
ändamålsenligt sätt. Handboken och projekthanteringssystemet används i praktiken på alla nivåer.
Rapporteringssystemet ger ett bra informationsflöde från landkontoren till regionkontoren och vidare
till huvudkontoret. Diakonia använder resultatstyrning men denna kan vidareutvecklas när det gäller
att formulera tydliga mål och mätbara resultatindikatorer.
Kriterier och procedurer för val av partnerorganisationer och deras projekt eller program
Kriterierna för såväl val av länder som för programutformningen är ändamålsenliga och används i
praktiken i det pågående omstrukturerings- och decentraliseringsarbetet. Det kan emellertid i vissa
länder vara svårt att få tillräckligt med programstöd till breda landprogram. Kriterierna för val av
partnerorganisationer och att vidmakthålla partnerskap är också ändamålsenliga och används i
praktiken.
Partnerorganisationers och målgruppers delaktighet i planering, uppföljning och utvärdering
av projekt och program
Diakonia har ett väl utvecklat förhållningssätt när det gäller partnerorganisationernas och
målgruppernas delaktighet i planering, uppföljning och utvärdering av projekt och program med en
tydlig fördelning mellan Diakonias ansvar för sina program och partnerorganisationernas ansvar för
sina projekt och program. Dessa fundamentala principer efterföljs på alla nivåer. Emellertid saknas
ofta systematiskt insamlad information om läget vid projektstart.
System för riskanalys och riskhantering (inklusive korruptionsrisker)
Besluts-PM i projekthanteringssystemet inkluderar riskanalys. Diakonia har nolltolerans vad gäller
korruption. Format och instruktioner för rapporteringen om korruption och misshushållning av
resurser är innehållsdigra. I de studerade länderna finns få fall av rapporterade incidenter. Dessa
incidenter indikerar emellertid en viss svaghet i Diakonias sätt att hantera misstankarna och
ansvarsfördelningen i den fortsatta processen.
Utfasningsstrategier vad gäller partnerorganisationer, projekt och program
Diakonia har rutiner för avslutning av program och kriterier för utfasning av partnerorganisationer.
Emellertid finns det inga utfasningsstrategier avseende hållbarhet för partnerorganisationen. Det
System-based Audit of Diakonia
63
verkar vara ovanligt att fasa ut en partnerorganisation på grund av att den kan klara sig genom egen
finansiering.
7.2.3 Ekonomisk styrning och kontroll
Ekonomisystem
All finansiell information rörande Diakonia finns registrerad i Visma (information från PHS,
Hogia/Flex, Mysoft och lokala ekonomisystem). Men processerna är ineffektiva på grund av att man
använder sig av flera olika system på olika nivåer. Planer finns att vidareutveckla ekonomisystemet
och PHS med målet att skapa ett sammanhållet globalt system. Detta har potential att signifikant öka
effektiviteten genom att nuvarande överlappningar och dubbelarbete försvinner.
Avtalsefterlevnad
Diakonia svarar upp mot Sidas villkor och föreskrifter med några få undantag som finns beskrivna i
denna rapport. De nya avtalen med partnerorganisationerna och den noggranna bevakningen av
partnerorganisationernas system för internkontroll har potential att säkra att även
partnerorganisationerna efterlever villkoren. Men uppföljningen av partnerorganisationernas
internkontroll borde göras mer systematiskt genom mer frekventa besök hos partnerorganisationerna.
För att undvika att rapportera genom flera nivåer kan det eventuellt i vissa fall vara möjligt att
använda sig av trepartsavtal.
Medelsöverföring samt hantering av bankkonton och kontanter
Ett av de tre besökta landskontoren krävde endast en signatur för betalning med check,
banköverföringar och finansiella transaktioner. Kontant betalning har i ett fåtal partnerorganisationer
gjorts på ett sätt som öppnar upp för felaktig medelsanvändning och korruption. Diakonia har inte
alltid snabbt vidtagit erforderliga åtgärder - inte ens i fall där problemet har rapporterats av revisorn.
System, regler och rutiner för upphandling
Diakonia har fastställda riktlinjer för upphandlingar. Dessa bör också vara minimistandard för
partnerorganisationerna. Men i praktiken är upphandling inte ens reglerat i alla kontrakt med
partnerorganisationer. Vissa partnerorganisationer har regler för upphandling som möter
internationell standard. Andra partnerorganisationer använder sig av upphandlingar på ett sätt som
öppnar upp för korruption och felaktig medelsanvändning.
Revision
I medlemsbaserade partnerorganisationer betonas att revisionsberättelsen är riktad till medlemmarna.
Revisions-PM ska finnas tillgängligt för styrelsen, medlemmarna och givarna vid begäran. Vissa
lokala revisorer är ovilliga att utfärda både revisionsintyg och revisionsrapporter med argumentet att
deras åsikt som revisor i revisionsrapporten är vad de är skyldiga att leverera enligt internationell
standard. Kompetensen att analysera revisionsrapporter och revisions-PM är tillräckligt hög på alla
nivåer inom Diakonia. Men det finns behov att förbättra processerna kring hur Diakonia handlar
praktiskt när det kommer till misstänkta oegentligheter.
7.2.4 Biståndseffektivitet
Diakonia respekterar partnerorganisationernas ägarskap och stöttar aktivt den vidare utvecklingen av
deras kapacitet. Diakonia försöker anpassa sig till partnerorganisationernas egna system och metoder
System-based Audit of Diakonia
64
så långt det är möjligt. Diakonia försöker också koordinera rapporteringen och harmonisera kraven
med andra givare till en specifik partnerorganisation. Diakonia har varit aktiv inom området
biståndseffektivitet, speciellt på den globala nivån. Diakonia är medveten om behovet att fortsätta att
arbeta pro-aktivt inom detta område.
7.3 Övergripande slutsatser
Målen med systemrevisionen enligt uppdragsbeskrivningen finns angivna i tabellen nedan. Vi har för
varje mål sammanfattat våra övergripande slutsatser i tabellen.
Målen för systemrevisionen Vår bedömning
att granska tillförlitligheten och relevansen i
systemet för operativ och finansiell kontroll inom
Diakonia och att bedöma i vilken utsträckning
systemet tillämpas och efterföljs på alla nivåer
inom organisationen.
1. Systemen för operativ och finansiell kontroll
inom Diakonia är relevanta och tillförlitliga.
Emellertid finns en tendens att inte agera
systematiskt och snabbt nog när korruption
eller felaktig användning av finansiering
misstänks.
2. Systemen är implementerade på alla nivåer
inom organisationen. De interna system som
används av partnerorganisationerna möter i
de flesta fall åtminstone en likvärdig
standard. Emellertid har vissa
partnerorganisationer en svag internkontroll.
att avgöra, på basis av granskningen, om
dokumentationen och rapporterna till Sida enligt
nuvarande ramavtal återspeglar den verkliga
situationen och därmed kan anses fungera som
tillförlitlig information för Sida i
bedömningsprocessen
Dokumentationen till Sida enligt nuvarande avtal
återspeglar den verkliga situationen och kan därför
anses fungera som tillförlitlig information för Sida i
bedömningsprocessen.
att bedöma om Diakonia efterlever Sidas villkor
samt om Diakonias kontrollsystem säkrar att även
partnerorganisationerna efterlever dessa villkor
1. Diakonia efterlever Sidas villkor med få
undantag som finns beskrivna i denna
rapport.
2. Diakonias kontrollsystem säkrar att
partnerorganisationerna också efterlever
dessa villkor
att bidra med förslag till organisationens
förändringsprocesser och systemutveckling
The Audit Team has in the report provided Diakonia
with concrete recommendations on how to further
develop the management systems.
Vi har i rapporten bidragit med konkreta
rekommendationer om hur Diakonia kan
vidareutveckla styrsystemen.
Mer detaljerade slutsatser finns i slutet av varje avsnitt.
System-based Audit of Diakonia
65
7.4 Rekommendationer
Rekommendationerna finns presenterade i slutet av varje avsnitt. De föreslagna rekommendationerna
överensstämmer med de mest betydelsefulla iakttagelserna och slutsatserna som finns presenterade
ovan. Vi har följande rekommendationer i prioritetsordning:
Högst prioritet (i den ordning som de återfinns i rapporten):
Diakonia genomgår en öppen institutionell visionsprocess med målet att nå konsensus kring
den långsiktiga inriktningen och en gemensam vision inom ramen för den nya
sammansättningen av medlemmar (kapitel 3.1).
Förändringarna beträffande Diakonias medlemsorganisationer bör noggrant analyseras,
inkluderande en riskbedömning (kapitel 3.2).
Diakonia bör införa tydliga åtaganden och årliga uppföljningar av dessa (kapitel 3.3).
PHS bör utvecklas för att förenkla/underlätta genomförandet av projekt finansierade av EU,
FN och andra givare (kapitel 3.3).
PME-handboken bör utvecklas för att öka flexibiliteten på regionkontors- och
landkontorsnivåerna, speciellt för program som har stöd från andra än Sida (kapitel 4.1).
Mål och resultatindikatorer för program och projekt bör vidareutveckla för att ge nödvändig
och validerad information som underlag för programmens och projektens fortsatta utveckling
(kapitel 4.1).
Diakonia bör ge sina partnerorganisationer stöd i att introducera resultatstyrning och att
utveckla mätbara mål- och resultatindikatorer (kapitel 4.1).
Diakonia bör fortsätta sina ansträngningar att systematiskt implementera participatoriska
uppföljnings- och utvärderingssystem i samarbete med partnerorganisationerna (kapitel 4.1)
Diakonias huvudkontor bör ge de regionala kontoren systematisk återkoppling på rapporterna
(kapitel 4.1)
I de länder där Diakonia bestämmer sig för att bedriva verksamhet och det är svårt att få full
budgetfinansiering för ett kostnadseffektivt program bör Diakonia överväga att se över
utformningen av landsprogrammen för att möjliggöra en projektportfölj som finansieras av
olika givare som komplement till kärnprogrammet (kapitel 4.2.).
Diakonia bör införa en modell för riskbedömning och riskhantering (kapitel 4.4)
Diakonia och dess partnerorganisationer bör noggrant följa upp de exempel på felaktig
medelshantering som har rapporterats och fortsätta rapportera misstänkta oegentligheter även
i framtid (kapitel 4.4)
Diakonia bör införa en gemensam process kring hur inrapporterade incidenter och felaktig
medelsanvändning ska hanteras (kapitel 4.4)
Incidenter ska alltid omedelbart rapporteras i PHS (kapitel 4.4)
När incidenter om misstänkta oegentligheter har rapporterats om en partnerorganisation bör
regionchefen ha ansvaret för utredningen och utredningsarbetet bör bedrivas på
regionkontoret (kapitel 4.4)
Diakonia bör intensifiera sina ansträngningar att efterleva avtalen med Sida (kapitel 5.2)
Diakonia bör följa upp partnerorganisationernas internkontrollsystem mer systematiskt
(kapitel 5.2)
Diakonia bör överväga att använda trepartsavtal när aktiviteter är koordinerade av en
partnerorganisation men implementerade av andra organisationer (kapitel 5.2)
System-based Audit of Diakonia
66
I förebyggande syfte bör checker och finansiella transaktioner signeras av två personer
(kapitel 5.3)
Diakonia bör kräva att kontantbetalningar i partnerorganisationer inte tillåts för belopp
överstigande till exempel 1 000 kronor (kapitel 5.3)
Diakonia inkluderar regler för upphandling i alla kontrakt med partnerorganisationer (kapitel
5.4)
Diakonia i uppföljningen av partnerorganisationerna internkontroll säkerställer att
upphandlingsreglerna efterlevs (kapitel 5.4)
Diakonia bör införa rutiner och incentivs som garanterar att revisionsrapporter, revisionsintyg
och revisions-PM lämnas in i tid (kapitel 5.5)
Lägre prioritet (i den ordning som de återfinns i rapporten):
Diakonia bör utveckla en kommunikationsstrategi för organisationen globalt (kapitel 3.1)
Diakonia bör revidera rapporteringssystemet med syfte att undvika dubbleringar och fokusera
på vad som är relevant information för olika intressenter (kapitel 4.1)
Diakonia bör i dialogen med partnerorganisationerna mer explicit be om riskanalyser och
information om riskhantering (kapitel 4.4)
Diakonia bör klargöra vilka kriterier som gäller för olika typer av partnerskap med eller utan
finansiellt stöd (kapitel 4.5)
I avtalen med partnerorganisationerna bör Diakonia be dem genomföra baslinjestudier
(kapitel 4.5)
Diakonia fortsätter sina ansträngningar att införa ett effektivt ekonomisystem (kapitel 5.1)
Diakonia bör besöka partnerorganisationerna oftare för att följa upp deras system för
internkontroll (kapitel 5.2)
Diakonia bör överenskomma om realistiska deadlines särskilt när det gäller projektstöd som
går genom partnerorganisationers huvudkontor till lägre nivåer inom organisationen (kapitel
5.2)
Diakonia bör ändra kraven när det gäller underskrift av kontrakt så att dessa krav
överensstämmer med partnerorganisationerna egna system (kapitel 5.3)
Diakonia bör ge partnerorganisationerna rådet att revisions-PM bör vara tillgängliga för
styrelsen, medlemmarna och givare enligt önskemål (kapitel 5.5)
Diakonia bör eftersträva att regelbundet träffa andra organisationer som ger stöd till
partnerorganisationerna i samma land (kapitel 6)
Diakonia bör alltid delta aktivt i möten som partnerorganisationer anordnar för sina givare
(kapitel 6)
Diakonia bör diskutera mervärdet av regionalt samarbete med kyrkor och nätverk på regional
nivå (kapitel 6).