synchronize bts master_slave
TRANSCRIPT
Alcatel BSS
Synchronize BTS Master /
Slave Site
BTS Document
Reconfiguration Method
Release B9
3BK 17422 1071 RJZZA Ed.04
Status RELEASED
Short title MPI107 / MDR1
All rights reserved. Passing on and copying of this document, useand communication of its contents not permitted without writtenauthorization from Alcatel.
BLANK PAGE BREAK
2 / 32 3BK 17422 1071 RJZZA Ed.04
Contents
Contents
Preface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
1 Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 71.1 Presentation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
1.1.1 Cases . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81.1.2 Options . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81.1.3 Restrictions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 91.1.4 Grouped Task Sequence . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
1.2 Preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 91.2.1 Prerequisites . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 91.2.2 Site Specific Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 101.2.3 External Tasks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
1.3 Scheduling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 101.4 Telecom/Supervision Outage and Operating Impact . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111.5 Resources . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
1.5.1 Tools . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 121.5.2 Supplies . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 121.5.3 Applicable Documents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
2 Scenario . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
2.1 Before Going On-Site . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 162.2 Before You Start . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
2.2.1 Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 162.2.2 Required Knowledge . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
2.3 Scenario Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 172.3.1 Initial Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 172.3.2 Check Hardware Technical Status and Perform Retrofit Action on Master G2 BTS
(C1, C2) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 172.3.3 Install Synchronization Cables and Remove XGND . . . . . . . . . . . . . . . . . . . . . . . . 192.3.4 Configure Master G2 BTS (C3) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 192.3.5 Configure Slave BTSs (C5, C6) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 202.3.6 Final Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
2.4 Reverse Procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 232.4.1 Lock Impacted Cells and RA for G2 BTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 232.4.2 Disconnect Synchronization Cables and Replace Board(s) . . . . . . . . . . . . . . . . . 232.4.3 Modify BTS Characteristics . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 242.4.4 Unlock Impacted Cells and RA for G2 BTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 252.4.5 Final Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
2.5 Specific Tasks For The Scenario . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 252.5.1 Master / Slave Configurations for BTS Sites . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 252.5.2 Install Synchronization Cables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 272.5.3 Configure G2 BTS Master/ Slave STSE / STSP and STSR Boards . . . . . . . . . . 31
3BK 17422 1071 RJZZA Ed.04 3 / 32
Figures
FiguresFigure 1: BTS Site Master / Slave Synchronization . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
Figure 2: Cabling A9100 BTS Indoor / A9100 BTS Indoor (Chain and Star Configuration) . . . . . . . . . . . . . . 26
Figure 3: Cabling G2 BTS Indoor Std / A9100 + G2 BTS Indoor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
Figure 4: A9100 Indoor BTS XCLK ports . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
Figure 5: G2 Standard Indoor BTS XCLK OUT Port Location on the Back Panel . . . . . . . . . . . . . . . . . . . . . . . 28
Figure 6: G2 Standard Indoor BTS Cabling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
Figure 7: G2 Mini Indoor BTS XCLK Port Locations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30
4 / 32 3BK 17422 1071 RJZZA Ed.04
Preface
Preface
Purpose This scenario defines how to synchronize a BTS site equipped with G2 orA9100 BTS or both.
Applicable to BSS at technical release B9.
What’s New In Edition 04Overall document quality was improved following an editorial review.
In Edition 03Editorial improvements due to replacement of “INSPAW” with “Customerdocumentation CD” in Software Tools (Section 1.5.1.2)
In Edition 02Editorial update in Modify BTS Characteristics (Section 2.3.5.4).
In Edition 01Creation of B9 document.
Update Install Synchronization Cables forA9100 BTS (Section 2.5.2.1) withfigures and explanations.
Audience This document is intended for:
Field service technicians
Specialists
Project managers
Foremen.
Assumed Knowledge You must have a basic understanding of the following:
For planning purposes:
Network architecture and reshuffling principles
Scheduling.
3BK 17422 1071 RJZZA Ed.04 5 / 32
Preface
For realization purposes:
Alcatel operations and maintenance concepts for BSS
Alcatel 1353-RA OMC-R operation
Equipment (BSC, BTS, MFS) hardware configurations
Windows environment.
6 / 32 3BK 17422 1071 RJZZA Ed.04
1 Overview
1 Overview
This Overview gives information needed by project managers and foremen, forpresentation to the customer and for site planning.
3BK 17422 1071 RJZZA Ed.04 7 / 32
1 Overview
1.1 PresentationClock synchronization between different BTSs is required for typicalapplications, such as:
Synchronous handover
Cell shared by two BTSs.
MASTER SLAVE HW+SW limitation
G2 Standard G2/A9100 3
G2 Mini G2/A9100 2
A9100 Medi / Mini G2 1
A9100 Medi / Mini A9100 3 BTSs in chain
2 BTSs in star
Table 1: Possible BTS Synchronization
This method covers retrofit actions for the boards of G2 BTSs, changing thesynchronization mode from "free running" to "PCM" for the master G2 BTSs,and synchronizing one or several slave BTSs to a master BTS.
G2 Slave BTSs are always in star connection.
G2 BTS equipped with STSE, STSP boards can be master or slave.
G2 BTS equipped with STSR boards can only be slave.
1.1.1 Cases
The following cases apply for the new synchronized BTSs:
Retrofit Action - Preparing the master G2 BTS:
C1: G2 BTS with redundant configuration (2 STSx boards)
C2: G2 BTS non-redundant configuration (1 STSx board).
Master Configuration:
C3: Change of master G2 BTS synchronization mode from "free running"
to "PCM synchronization"
C4: Master A9100 BTS.
Slave Configuration:
C5: Slave G2 BTS(s)
C6: Slave A9100 BTS(s).
1.1.2 Options
None.
8 / 32 3BK 17422 1071 RJZZA Ed.04
1 Overview
1.1.3 Restrictions
Synchronization with G1 Mark II BTS is not covered.
1.1.4 Grouped Task Sequence
The following figure shows the grouped task sequence for this scenario. Clickon a box in the figure below to go to the corresponding grouped task.
OMC−R BTS
C2
C3
C5 C6
Final Checks
Initial Checks
InstallSynchronization Cables
Configure Slave BTSs
Configure Master G2 BTS
Check HTS and Perform Retrofit Action on Master G2 BTS
Figure 1: BTS Site Master / Slave Synchronization
1.2 Preparation
1.2.1 Prerequisites
The following prerequisites apply:
All the BTSs on the non-synchronized site are configured as master
All the BTSs on the site, including the new integrated BTSs, are consideredinstalled, commissioned and connected to the BSC
3BK 17422 1071 RJZZA Ed.04 9 / 32
1 Overview
G2 Mini-BTS Indoor and Outdoor and G2 BTS Standard Outdoor must bepre-cabled. This means cabling between the connection box and the
subrack is present (old versions of G2 BTS could be without pre-cabling)
Maximum number of BTSs on site is four
Distance between BTSs (according to the cable length) is maximum 10
meters.
To provide a higher quality of synchronized handover, it is preferableto replace the STSE AAxx or STSE ABxx boards of the Master BTSwith STSE ACxx10 or STSP performing a "Retrofit Action" (see CheckHardware Technical Status and Perform Retrofit Action on Master G2 BTS(C1, C2) (Section 2.3.2)). Make sure that the Hardware Technical Statusof the boards is the same, in accordance with Set STSE / STSP, STSRBoard Switches (Section 2.5.3.1)
1.2.2 Site Specific Information
The following site-specific information is needed:
Master BTS identification and type
Slave BTS(s) identification and type.
1.2.3 External Tasks
None.
1.3 SchedulingThe following table describes the sites, personnel, and duration of eachgrouped task and the total time to perform the scenario.
Note: Time based on technical constraints
In the following table, the number of resources shown does not take intoaccount individual customer or safety requirements.
Grouped Task BSC BTS Site OMC-R Time /Task
Initial Checks - 1 Com 1 ope. C1, C2: around 15 min.
Check HTS andPerform Retrofit
- 1 Com 1 ope. C1: around 30 min.
C2: around 25 min.
InstallSynchronizationCables
- 1 Com - max 1h (depending on the fieldconfiguration)
Configure MasterBTS
- 1 Com 1 ope. C3: 30 min. + 10 min./ board+2min./ cell
10 / 32 3BK 17422 1071 RJZZA Ed.04
1 Overview
Grouped Task BSC BTS Site OMC-R Time /Task
Configure SlaveBTS
- 1 Com 1 ope. C5: 1h + 10 min./ board
C6: around 25 min.
Final Checks - 1 Com 1 ope. 20 min.
TOTAL TIME C1, C2: max 30 min.
C3: max 55 min.
C5: max 1h15 min.
C6: max 25 min.
ope. : OMC-R operator
Com : Commissioning Team
1.4 Telecom/Supervision Outage and Operating ImpactThe table below describes the traffic outage and loss of supervision causedby the concerned grouped tasks.
Out.Ref. Grouped Task
Tel. /GPRSOut Tel. Red Sup.Out
Oper.Impact Impacts...
- Initial Checks - - - - -
1 Check HTS andPerform Retrofit
C2: 15 min. +2 min./ cell
- - - CS and GPRSTraffic OUTAGE1only in C2
- InstallSynchronizationCables
- - - - None
2 Configure MasterBTS
C3: 28 min. +2 min./ cell
- - - CS and GPRSTraffic OUTAGE2only in C3
3 Configure MasterBTS
C5: 33 min. +10 min. /board+ 2 min./ BTS+ 2 min./ cell
- - - CS and GPRSTraffic OUTAGE3only in C5
- Final Checks - - - - None
TOTAL TIME C1: None C2:15 min. + 2min./ cell C3:28 min. + 2min./ cell C5:33 min. + 10min./ board +2 min./ BTS +2 min./ cell.
3BK 17422 1071 RJZZA Ed.04 11 / 32
1 Overview
1.5 Resources
1.5.1 Tools
The following tables describe the necessary hardware tools, software tools,and forms.
1.5.1.1 Hardware Tools
Item Part Number Use at ...
Installation tools. - BTS
Laptop PC with CD-ROM reader for reading on-linedocumentation and for the BTS Terminal. Connection cable.
- BTS
Trace mobiles equipped with SIM cards. - BTS
1.5.1.2 Software Tools
Item Part Number Use at ...
BTS Terminal in release B9. - BTS
Customer documentation CD with the version associatedto the current document edition. Remember that thedocument you are reading cannot be used with a paperversion. It is an on-line document using hypertext linkstowards the applicable documents (all these are supportedon the same CD-ROM). All words in "italic" are hypertextlinks.
- BTS
1.5.1.3 FormsNone.
1.5.2 Supplies
The following table describes the necessary supplies.
Item Part Number Contents Use at ...
Site Documentation. - - BTS, OMC-R
Synchronization cables. See Master / Slave Configurations forBTS Sites (Section 2.5.1).
- BTS site
Heat-shrinkable sleeving. - - BTS site - onlyfor OutdoorBTSs.
12 / 32 3BK 17422 1071 RJZZA Ed.04
1 Overview
1.5.3 Applicable Documents
The following documents are needed to complete this scenario:
B9 BSS Methods Handbook
BSS Configuration Handbook
BSS Surveillance Handbook
Network Reconfiguration Recommendations
The specific documents applicable to this scenario are:
BTS Terminal User Guide
G2 BTS Hardware Description
Evolium BTS A9100 Hardware Description.
3BK 17422 1071 RJZZA Ed.04 13 / 32
1 Overview
14 / 32 3BK 17422 1071 RJZZA Ed.04
2 Scenario
2 Scenario
This Scenario presents all checks needed before beginning the scenario, andall detailed tasks to be performed on each site.
3BK 17422 1071 RJZZA Ed.04 15 / 32
2 Scenario
2.1 Before Going On-SiteBefore going on-site, you must check that the following information andsupplies are available.
All Prerequisites (Section 1.2.1) are fulfilled
The customer has been informed of the
Date
Time
Site name
Site address
Purpose of operation.
Personnel are available and ready for operation (Refer to Scheduling(Section 1.3))
Site Specific Information (Section 1.2.2) is available and ready for operation
Tools (Section 1.5.1) are available and ready for operation
Supplies (Section 1.5.2) are available and ready for operation
Documentation is available and ready for operation.
Ensure that the technical release level of the delivered board is in accordancewith the BSS hardware technical release document.
Ensure that the method used at the BSS site is at the same level as at theOMC-R.
2.2 Before You Start
2.2.1 Checks
Perform the following operations:
Check that all Prerequisites (Section 1.2.1) are fulfilled
Check the availability of all necessary tools and materials
Inform the operator.
Among the cases described in Cases (Section 1.1.1) and the options describedin Options (Section 1.1.2), identify which cases and options apply to you.
2.2.2 Required Knowledge
You must be familiar with the following:
Safety Rules and Precautions
Telecom/Supervision Outage and Operating Impact (Section 1.4)
Reverse Procedure
16 / 32 3BK 17422 1071 RJZZA Ed.04
2 Scenario
Grouped Task Sequence (Section 1.1.4)
Operating Hints
How to document Faults and Anomalies.
2.3 Scenario DescriptionThe detailed tasks for synchronizing a BTSs site are described below.
2.3.1 Initial Checks
Note Task Description Site To do Outage
- Perform an Audit Alarm State of the BSS. OMC-R 10 min. None.
- View Status of Managed Objects andAlarms for all impacted BTSs. Print outthe results.
OMC-R 5 min. None.
- For each concerned cell of the site,Set Cell Telecom Parameters (HOparameters/General HO control), checkand/or set the following parameter to therequired value :
SYNCHRONIZED HO = enabled.
OMC-R 1 min./ cell None.
2.3.2 Check Hardware Technical Status and Perform Retrofit Action onMaster G2 BTS (C1, C2)
2.3.2.1 Check Hardware Technical Status of STSx Board(s)
Note Task Description Site To do Outage
- Check the hardware technical status ofthe STSx boards as shown in HardwareTechnical Status for STSE, STSP, STSR(Section 2.5.3.2) and perform the retrofitaction, if is necessary.
BTS 5 min. None.
2.3.2.2 Shut Down Impacted Cells and RA for Master G2 BTS to Retrofit
Note Task Description Site To do Outage
C2 Shut Down Cell (WTC = 3 min.) foreach cell on Master BTS.
OMC-R 4 min. START1
3BK 17422 1071 RJZZA Ed.04 17 / 32
2 Scenario
Note Task Description Site To do Outage
OMC-R 1 min. OUTAGE1C2
EXCH
Lock Function (RA) for Master BTS.
Note: Perform all the lock actions in sequence,without loosing time and inform the BTS site whendone.
2.3.2.3 Perform Retrofit Action on Master G2 BTS
Note Task Description Site To do Outage
C1 With the BTS terminal, disableCLLK2 and FHU2.
BTS 1 min. None.
BTS 10 min. OUTAGE1 for C2.
None for C1.
C1
C2
Replace the STSx board with theSTSE ACxx10 board, with switchesin position as shown in Set STSE/ STSP, STSR Board Switches(Section 2.5.3.1).
In C2: Inform OMC-R when ready.
BTS 1 min. None.C1 With BTS terminal, perform initFHU2 and CLLK2
Note: A FIT alarm on CLLK SBL is normal (15 min.).
C1 With BTS terminal, disable CLLK1and FHU1.
BTS 1 min. None.
C1 Replace the STSx board with anSTSE ACxx10 board, with switchesin position as shown in Set STSE/ STSP, STSR Board Switches(Section 2.5.3.1).
BTS 10 min. None.
BTS 1 min. None.C1
EXCH
With BTS terminal, perform initCLLK1 and FHU1.
Note: FIT alarm on CLLK SBL is normal (15 min.).
2.3.2.4 Unlock Impacted Cells and RA for Retrofited Master G2 BTS
Note Task Description Site To do Outage
C2 Unlock Function (RA). OMC-R 3 min. OUTAGE1
C2 Unlock Cell for each cell on BTS. OMC-R 2 min./cell END1
18 / 32 3BK 17422 1071 RJZZA Ed.04
2 Scenario
2.3.3 Install Synchronization Cables and Remove XGND
Remember that internal pre-cabling for the G2 BTS Mini Indoor/Outdoor andG2 BTS Standard Outdoor is a prerequisite (either for master or for slave).
2.3.3.1 Install Synchronization Cables
Note Task Description Site To do Outage
- Depending on the final configuration, installsynchronization cables between the BTSs, ifthey are not already installed (refer to InstallSynchronization Cables (Section 2.5.2)) andconnect them only at Master side. Be sure tolabel each cable.
BTS 1h max,dependingon the fieldconfiguration.
None.
2.3.3.2 Remove the XGND Strap on Master
Note Task Description Site To do Outage
C4 Remove the XGND strap on
Master A9100 BTS top rack (see figure in A9100BTS (Section 2.5.2.1)).
BTS 1 min. None.
2.3.4 Configure Master G2 BTS (C3)
2.3.4.1 Shut Down Impacted Cells and RA for Master G2 BTS
Note Task Description Site To do Outage
C3 Shut Down Cell (WTC = 3 min.), cell(s) onMaster BTS.
OMC-R 4 min.START2
OMC-R 1 min. OUTAGE2C3 Lock Function (RA) for Master BTS.
Note: Perform all the lock actions insequence, without loosing time.
2.3.4.2 Prepare Master G2 BTS HW Configuration
Note Task Description Site To do Outage
C3 At the BTS terminal, open a ModifyHW Configuration session.
BTS 1 min. OUTAGE2
3BK 17422 1071 RJZZA Ed.04 19 / 32
2 Scenario
Note Task Description Site To do Outage
BTS 10 min./ board OUTAGE2C3 Replace the STSE board(s) with STSPboard(s) or change switch positions,as shown in Set STSE / STSP, STSRBoard Switches (Section 2.5.3.1).
Note: Check HTS of STSx boards, referring toHardware Technical Status for STSE, STSP,STSR (Section 2.5.3.2).
BTS 1 min. OUTAGE2C3 At the BTS terminal, perform ModifyHW Configuration "End Modification ofHW Configuration". Note: A hardware audit starts after this action.
Do not modify BTS characteristics until thisaction ends.
EXCH Inform the OMC-R team that the BTSis reconfigured.
BTS / OMC-R 1 min. OUTAGE2
2.3.4.3 Unlock Impacted Cells and RA for Master G2 BTS
Note Task Description Site To do Outage
C3 Unlock Function (RA) for each cell onMaster BTS.
OMC-R 3 min. OUTAGE2
C3 Unlock Cell for each cell on MasterBTS.
OMC-R 2 min./ cell END2
C3 View Status of Managed Objectsand Alarms for impacted BTS. Then,compare with initial status and alarms.Mainly check that there are no clockalarms.
OMC-R 5 min. None.
OMC-R 15 min. None.CHECK Perfom some call tests and DisplayUSD Detailed Cell Information.
Note: If call tests are unsuccessful, are applythe Reverse Procedure.
2.3.5 Configure Slave BTSs (C5, C6)
2.3.5.1 Shut Down Impacted Cells and RA for Slave G2 BTS
Note Task Description Site To do Outage
C5 Shut Down Cell ( WTC = 3 min.), for eachcell on Slave BTS. OMC-R 4 min. START3
OMC-R 1 min. OUTAGE3C5 Lock Function (RA) for each Slave BTS.
Note: Perform all the lock actions in sequence,without loosing time.
20 / 32 3BK 17422 1071 RJZZA Ed.04
2 Scenario
2.3.5.2 Remove the XGND Strap on Slave
Note Task Description Site To do Outage
C6 Remove the XGND strap on Slave A9100 BTS(s) toprack (see the figure in A9100 BTS (Section 2.5.2.1)).
BTS 1 min. None.
2.3.5.3 Prepare Slave BTS(s) HW Configuration
Note Task Description Site To do Outage
C5 At the BTS terminal, open a Modify HW Configurationsession.
BTS 1 min. OUTAGE3
BTS 10min./board
OUTAGE3C5 Replace the STSE board(s) with STSP or withSTSR and/or change switch positions, as shown inSet STSE / STSP, STSR Board Switches (Section2.5.3.1).
Note: Check HTS of STSx boards,referring toHardware Technical Status forSTSE, STSP, STSR (Section 2.5.3.2).
BTS 1 min. OUTAGE3C5 At the BTS terminal, perform Modify HW Configuration"End Modification of HW Configuration".
Note: A hardware audit starts after thisaction. Do not modify BTS characteristicsuntil this action ends.
C5
C6
Connect synchronization cables at Slave side (referto Install Synchronization Cables (Section 2.5.2)).
BTS 5 min. OUTAGE3 for C5
None for C6.
EXCH Inform the OMC-R team that the BTS is ready for thelogical configuration.
BTS/OMC_R
1 min. OUTAGE3 for C5
None for C6.
2.3.5.4 Modify BTS Characteristics
For each Slave BTS, perform a BTS power off/on after the slave is declaredin the OMC-R.
Note Task Description Site To do Outage
C5
C6
For each Slave BTS, Modify BTSCharacteristics by declaring the BTSas slave and by selecting the name ofthe concerned Master BTS.
OMC-R 2 min./ BTS OUTAGE3 forC5
None for C6.
C5
C6
Perform a BTS power off/on and waituntil the SBL BTS OMU is IT.
BTS 15 min. OUTAGE3.
3BK 17422 1071 RJZZA Ed.04 21 / 32
2 Scenario
2.3.5.5 Unlock Impacted Cells and RA for Slave G2 BTS
Note Task Description Site To do Outage
C5 Unlock Function (RA) for each cell onSlave BTS.
OMC-R 3 min. OUTAGE3
C5 Unlock Cell for each cell on Slave BTS. OMC-R 2 min./ cell END3
BTS
OMC-R
15 min. None.CHECK Perform some call tests and handoverfrom Master cell(s) to Slave cell(s) andvice versa. Display USD Detailed CellInformation. Note: If call tests are unsuccessfull, apply the
Reverse Procedure (Section 2.4).
2.3.6 Final Checks
Note Task Description Site To do Outage
- Perform an Audit Alarm State for theBSS.
OMC-R 10 min. None.
- View Status of Managed Objects andAlarms for all impacted BTSs. Thencompare with initial status and alarms.Mainly check that there are no clockalarms.
OMC-R 5 min. None.
BTS/OMC-R 5 min. None.- Disconnect Clock cable at Slave BTSside. View Status of Managed Objectsand Alarms for the concerned BTS. Youmust have a Clock alarm, RA alarm andan alarm on the associated TREs dueto the switchover on the internal clock.Reconnect the Clock cable.
Note: Perform this test in association with theBTS site for the cable connection and cabledisconnection. If unsuccessful, apply theReverse Procedure (Section 2.4).
22 / 32 3BK 17422 1071 RJZZA Ed.04
2 Scenario
2.4 Reverse Procedure
2.4.1 Lock Impacted Cells and RA for G2 BTS
Note Task Description Site To do Outage
C2
C3
C5
Lock Cell for all cells on impacted BTS. OMC-R 1 min. -
C2
C3
C5
Lock Function (RA) for impacted BTS. BTS 2 min. -
2.4.2 Disconnect Synchronization Cables and Replace Board(s)
2.4.2.1 Put the XGND Strap Back
Note Task Description Site To do Outage
C4
C6
Put the XGND strap back in place onthe Master / Slave A9100 BTS (seefigure in A9100 BTS (Section 2.5.2.1)).
BTS 1 min. -
2.4.2.2 Disconnect Synchronization Cables
Note Task Description Site To do Outage
BTS 5 min. -C3
C5
Disconnect the synchronization cableson the Master and Slave G2 BTSs.
Note: Disconnect the synchronization cable forthe A9100 BTS just after the declaration of theSlave BTSs as Master!
2.4.2.3 Replace Board(s)
Note Task Description Site To do Outage
C3
C5
At the BTS terminal, open a Modify HWConfiguration session.
BTS 1 min. -
C1 At the BTS terminal, disable CLLK2and FHU2.
BTS 1 min. -
3BK 17422 1071 RJZZA Ed.04 23 / 32
2 Scenario
Note Task Description Site To do Outage
C1
C2
C3
C5
Replace the STSx board(s) with theinitial board(s) and/or modify switchpositions as shown in Set STSE /STSP, STSR Board Switches (Section2.5.3.1).
BTS 10 min./ board -
BTS 1 min. -C3
C5
At the BTS terminal, perform Modify HWConfiguration "End of HW ModificationConfiguration". Note: A hardware audit starts after this action.
Do not modify BTS characteristics until thisaction ends.
BTS 1 min. -C1 At the BTS terminal perform, an initFHU2 and CLLK2.
Note: A FIT alarm on the CLLK SBL is normal(15 min.).
C1 At the BTS terminal, disable CLLK1and FHU1.
BTS 1 min. -
C1 Replace the STSx board with STSEACxx10 board, with switches in positionas shown in Set STSE / STSP, STSRBoard Switches (Section 2.5.3.1).
BTS 10 min. -
BTS 1 min. -C1 At the BTS terminal, an init CLLK1 andFHU1
Note: A FIT alarm on the CLLK SBL is normal(15 min.).
EXCH Inform OMC-R that the BTS hardwareinstallation is done.
BTS / OMC-R 1 min. -
2.4.3 Modify BTS Characteristics
Note Task Description Site To do Outage
C5
C6
For each previous Slave BTS, ModifyBTS Characteristics by declaring it asMaster.
OMC-R 5 min. -
C4
C6
Disconnect the synchronization cableson the A9100 BTSs.
BTS 5 min. -
C5 Perform a BTS power off/ on. BTS 15 min. -
24 / 32 3BK 17422 1071 RJZZA Ed.04
2 Scenario
2.4.4 Unlock Impacted Cells and RA for G2 BTS
Note Task Description Site To do Outage
C2
C3
C5
Unlock Function (RA) for each impactedBTS.
OMC-R 3 min. -
C2
C3
C5
Unlock Cell for each cell on impactedBTSs.
OMC-R 2 min./ cell. -
CHECK Perform some call tests on eachconcerned BTS. Display USD DetailedCell Information.
BTS
OMC-R
10 min. -
2.4.5 Final Checks
Note Task Description Site To do Outage
- Perform an Audit Alarm State for theBSS.
OMC-R 10 min. -
- View Status of Managed Objects andAlarms for all impacted BTSs. Thencompare with initial status and alarms.
OMC-R 5 min. -
2.5 Specific Tasks For The Scenario
2.5.1 Master / Slave Configurations for BTS Sites
The following table shows the cable types used for the different BTS Master /Slave configurations.
Master/ SlaveG2 MiniInd
G2 MiniOut G2 St Ind G2 St Out
A9100 IndMini/Medi
A9100 OutMini/ Medi
G2 Mini Ind 2x EMCC - 2x EMCC - 2xSC23 -
G2 Mini Out - - - - - 2x OCC23
G2 St Ind 2x SSRC - 2x SSRC - 2x SC23 -
G2 St Out - - - 2x EOCC - 2x OCC23
3BK 17422 1071 RJZZA Ed.04 25 / 32
2 Scenario
Master/ SlaveG2 MiniInd
G2 MiniOut G2 St Ind G2 St Out
A9100 IndMini/Medi
A9100 OutMini/ Medi
A9100 Ind Mini/Medi - - 2xSCG23 - 1xSCG3 -
A9100 Out Mini/Medi - 2x OCC23 - 2xOCC23
- 1x OCC33
Table 2: Cable Types for Different Configurations
2.5.1.1 Example 1: Master A9100 BTS Indoor, Slaves A9100 BTS Indoor in Chain andStar Configurations
A9100 BTS A9100 BTS A9100 BTS
A9100 BTS
A9100 BTS
A9100 BTS
IN 1 −− OUT 1IN 1 −− OUT 2
IN 1 −− OUT 1IN 1 −− OUT 2
IN 1 −− OUT 1IN 1 −− OUT 2
IN 1 −− OUT 1IN 1 −− OUT 2
IN 1
IN 1
Figure 2: Cabling A9100 BTS Indoor / A9100 BTS Indoor (Chain and StarConfiguration)
26 / 32 3BK 17422 1071 RJZZA Ed.04
2 Scenario
2.5.1.2 Example 2: Master G2 BTS Indoor Std, Slaves A9100 BTS and G2 BTSs Indoor
G2 BTS G2 BTS
G2 BTS
A9100 BTS
Master Slave 1
Slave 2
Slave 3
IN
IN
IN 1IN 2
OUT2 x SSRC
2 x SSRC
2 x SC23
Figure 3: Cabling G2 BTS Indoor Std / A9100 + G2 BTS Indoor
2.5.2 Install Synchronization Cables
2.5.2.1 A9100 BTSBetween A9100 BTSs, one cable has to be installed between the XCLK OUTport on the Master BTS and the XCLK IN port on the Slave BTS.
A9100 Indoor BTS
The XCLK ports and XGND strap are on the top panel.
Abis Interface Group
External Input/Output Interface Group
External Clock Interface Group
Abis 4 Abis 3 Abis 2 Abis 1
Abis Relays
XB
CB
XG
PS
XC
LK1
In
XC
LK2
In/O
ut
XC
LK1
Out
XIO Interface Connectors
Krone Strip
Equipment Labels
XR
T
XGND GND
Power Supply and Circuit Breaker Area(DCBREAK)
Interconnection Area (BTSCA)
Circuit Breakers
Abis 4 I Abis 3 I Abis 2 I Abis1
0V−48V
BTSINT
0 0
I
0
I
SR5
SR4
SR3
0
I
SR2
I
0
I
0
I
SR1
Figure 4: A9100 Indoor BTS XCLK ports
A9100 Outdoor BTS
3BK 17422 1071 RJZZA Ed.04 27 / 32
2 Scenario
The XCLK ports and XGND strap are located on the energy bay, near theAbis connections.
1. Run and secure the cables in the cable tray between the racks.
2. Introduce the synchronization cable in the BTS compartment through thecable entry tube. Use a heat-shrinkable sleeve to isolate.
3. Secure the cable inside the plinth.
4. Connect a 9-way SubD connector to the synchronization cable.
5. Label the cables.
6. Connect the synchronization cables to the relevant XCLK port.
2.5.2.2 G2 BTSG2 BTS Standard Indoor (1.25m or 2m)
Two cables have to be installed between the back panel X600 ports on theMaster BTS and the front panel CLK IN ports of the STSx boards on theSlave BTS.
1
2
3
4
5
6
7
8
to Slave1
to Slave2
to Slave3
to Slave4
to Slave5
X108
X204
X503 X502
X301
X600
X501
SMBI
SMBI
MBSR Subrack
SCFE
X600
Figure 5: G2 Standard Indoor BTS XCLK OUT Port Location on the Back Panel
28 / 32 3BK 17422 1071 RJZZA Ed.04
2 Scenario
X600MBSR2
X600MBSR1
X600
STSE
MBSR2
STSE
CLK IN
MBSR1
CLK IN
X600
STSE
MBSR2
STSE
CLK IN
MBSR1
CLK IN
Slave BTS 1
Slave BTS 2
SSRC
SSRC
SSRC SSRC
Figure 6: G2 Standard Indoor BTS Cabling
Master BTS cabling:
1. Unscrew the waveguide gasket. Unscrew the rack top front plate.
2. Run the cable through the waveguide gasket, then behind the rack topfront plate.
3. Connect the ground on the MBSR back side, using the material and screwsfurnished with the cable.
4. Run the cables on the left side of the frame.
5. At the top of the rack, unscrew the two captives screws (flat bladescrewdriver needed). At the bottom of the rack, undo the two latchbolts-socket cap screws ( 8mm Allen key needed).
6. Pull the frame on the rails out from the outer cladding as far as it will go toretain the maximum of spare cable length.
7. Connect the cables to the X600 connector at the back side (see Figure 5).
8. Check that shielding is in contact with the waveguide gasket and re-secure it.
9. Insert the frame back in the rack doing the reverse operations for steps 6,5, and 1.
Slave BTS cabling:
1. Unscrew the waveguide gasket. Unscrew the rack top front plate.
2. Run the cable through the waveguide gasket, then behind the rack topfront plate.
3. Connect the ground on the MBSR back side, using the material and screwsfurnished with the cable.
3BK 17422 1071 RJZZA Ed.04 29 / 32
2 Scenario
4. Run the cables on the left side of the frame.
5. Connect the cables to the CLK IN connector on the front side of the STSxboards see Figure G2 Standard Indoor BTS Cabling (6).
6. Check that shielding is in contact with the waveguide gasket and re-secure it.
G2 BTS Mini IndoorEquipment Labels
Clock Synchr
Power Supply Cover Plate
Clock N Clock R Clock N Clock R
Ext Alarm
NOMINAL INPUT
Current: xxxVoltage: xxx
0 V xx/xxV
M/S1 M/S1 S2 S2
AbisLinkA AbisLInkB Q1−Test
Figure 7: G2 Mini Indoor BTS XCLK Port Locations
Two cables have to be installed between the right connection ports of the BTSs:
On the Slave BTSs: synchronization cables coming from the Master BTS
have to be connected to the M/N&R ports
On the Master BTS: synchronization cables going to the Slave BTSs have to
be connected to the S1/N&R (for Slave 1) and S2/N&R (for Slave 2) ports
Port N (normal) is connected to port N (normal) of the second BTS
Port R (redundant) is connected to port R (redundant) of the second BTS.
For Slave BTSs, check that the internal cables are connected between theinside ports of the connection box and CLK IN ports of the STSx boards.
Note: For the Master configuration, the cables exist but they are not connected.
In the specific case of non-redundant G2 BTS, only one synchronization cablebetween Master and Slave is necessary.
G2 BTS Mini and Standard Outdoor
Two cables have to be installed between the connection boxes of the BTSs:
On the Slave BTSs: synchronization cables coming from the Master BTShave to be connected to the CLK N&R ports
On the Master BTS: synchronization cables going to the Slave BTSs have to
be connected to the CLK N&R ports
30 / 32 3BK 17422 1071 RJZZA Ed.04
2 Scenario
Port N of the Master BTS is connected to port N of the Slave BTS
Port R of the Master is connected to port R of the Slave BTS.
To install the synchronization cables:
1. Run and secure the cables in the cable tray between the racks.
2. Introduce the synchronization cable in the BTS compartment through thecable entry tube. Use a heat-shrinkable sleeve to isolate.
3. Secure the cable inside the plinth.
4. Connect a 9-way SubD connector to the synchronization cable.
5. Secure the cables at the top of the connection box.
6. Label the cables.
7. Connect synchronization cables to the CLK ports of the connection box.
8. For the Slave BTS, check that the internal cables are connected between theconnection box and the CLK IN ports of the STSx.
2.5.3 Configure G2 BTS Master/ Slave STSE / STSP and STSR Boards
2.5.3.1 Set STSE / STSP, STSR Board Switches1. Remove the board from the BTS.
2. Set SWITCH 2 (Master or Slave) to:
OFF for a Master BTS (default value for STSE / STSP)
ON for a Slave BTS (default value for STSR).
Note: The position of Switch 2 can be checked at the BTS terminal by followingthe menu path:
Show > HW Configuration > SBL and select CLLK from the list.
3. Set SWITCH 3 (Clock synchronization frequency, used when the BTS isSlave) to:
OFF if Master BTS is a G2
ON in all other cases.
4. Set SWITCH 4 (to change from "PCM synchronization" to "free running",used for a G2 Master BTS equipped with an STSP board) to:
ON if PCM Synchronization
OFF if free running.
Note: The position of Switch 4 can be checked with the BTS terminal by followingthe menu path
Show > HW Configuration > SBL and selecting CLLK from the list.
5. When all switches are correctly set, re-insert the board in the BTS.
2.5.3.2 Hardware Technical Status for STSE, STSP, STSRWithin a BTS, the hardware technical status must be the same for both STSE(or STSP, STSR) boards.
If two BTS are synchronized, the hardware technical status must be compatible:
3BK 17422 1071 RJZZA Ed.04 31 / 32
2 Scenario
STSE AAxx11/STSE ABxx11 can only be linked to:STSE AAxx11/STSE ABxx11 or STSP 12 or STSR 18
STSE ACxx10 can only be linked to:STSE ACxx10 or STSP 11 or STSP 12 or STSR 17.
32 / 32 3BK 17422 1071 RJZZA Ed.04