s&w credit crunch

Upload: alanstark

Post on 07-Apr-2018

227 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 S&W Credit Crunch

    1/46

    Shepherd and Wedderburn LLP

    Contracting in the Credit Crunch

    Seminar by Shepherd and Wedderburn

  • 8/3/2019 S&W Credit Crunch

    2/46

    Shepherd and Wedderburn LLP

    Overview of current market-place

    Presentation by Kevin Taylor

  • 8/3/2019 S&W Credit Crunch

    3/46

  • 8/3/2019 S&W Credit Crunch

    4/46

    47 October 2008Contracting in the Credit Crunch

    Consequences

    Financial grease not available

    If finance available more expensive Refocus on risk

    The real economy jobs and spending

    Insolvency predictions

    unwise to bet on imminent recovery John Authers

  • 8/3/2019 S&W Credit Crunch

    5/46

    57 October 2008Contracting in the Credit Crunch

    Know your

    Clients

    Lenders Procedures e.g. contracts, debt recovery

    Insolvency regimes

    Rights contract reviews

    Tools litigation as a weapon

    Options

  • 8/3/2019 S&W Credit Crunch

    6/46

    67 October 2008Contracting in the Credit Crunch

    Silver Linings

    SG health spending

    Transport projects Olympics and Commonwealth Games

    Social housing new and maintenance

    FE Sector e.g. Glasgow Colleges 300M

    Energy sector O & G, renewables/wind

    Demand for housing not gone

    Civil engineering only marginal contraction

    Sting in the tail lead times

    Need to be prepared

  • 8/3/2019 S&W Credit Crunch

    7/46

    Shepherd and Wedderburn LLP

    Client Issues and Funder Requirements

    Presentation by Euan McLeod

  • 8/3/2019 S&W Credit Crunch

    8/46

    87 October 2008Contracting in the Credit Crunch

    Introduction

    Not all bad news

    Market changed for good?

    Funders belt, braces and a little bit more

    Tension between funder and contractor/consultant

    requirements

  • 8/3/2019 S&W Credit Crunch

    9/46

    97 October 2008Contracting in the Credit Crunch

    Client Issues

    Deal structure

    Value engineering

    Mothballing projects

    Payment guarantees

    Meeting the Banks requirements

  • 8/3/2019 S&W Credit Crunch

    10/46

    107 October 2008Contracting in the Credit Crunch

    Structure

    Who is the client?

    SPV structure?

    Is the employer the same as the proprietor?

    Offshore companies?

    Procurement routes?

    Direct contracting

  • 8/3/2019 S&W Credit Crunch

    11/46

    117 October 2008Contracting in the Credit Crunch

    Legal Value Engineering

    No retention

    Advance payments

    More frequent payments

    Payment for offsite materials

  • 8/3/2019 S&W Credit Crunch

    12/46

    127 October 2008Contracting in the Credit Crunch

    Mothballing Projects

    Right to terminate Can you terminate? Consequences of termination?

    Liabilities Retention Defects

    Resurrecting the project

    Banks consent

    Ongoing obligations security and insurance

    Future liability for the works

  • 8/3/2019 S&W Credit Crunch

    13/46

    137 October 2008Contracting in the Credit Crunch

    Payment Guarantees

    Who grants it?

    Extent of liability capped?

    Period of liability?

  • 8/3/2019 S&W Credit Crunch

    14/46

    147 October 2008Contracting in the Credit Crunch

    Issues Arising out of Funding

    Review the Facility Letter

    Conditions Precedent action list

    Typical requirements Approval of construction team Competence Constitution Financial strength

    Approval of procurement route Insurance

  • 8/3/2019 S&W Credit Crunch

    15/46

    157 October 2008Contracting in the Credit Crunch

    Typical Deliverables to the Fund

    Site investigation & environmental certified copy reports reliance letters

    Collateral Warranties (incorporating step-in rights) main contractor warranty main consultants collateral warranties other consultants?

    sub-contractors?

    Certified true copy building contract & appointments

    Certified true copy sub-contracts

  • 8/3/2019 S&W Credit Crunch

    16/46

    167 October 2008Contracting in the Credit Crunch

    Typical Deliverables to the Fund

    Report on procurement documentation

    Performance Bond/Parent Company Guarantee assignationin security?

    Brokers letters for professional indemnity insurance

    Assignation in Security of building contract & appointments

  • 8/3/2019 S&W Credit Crunch

    17/46

    Shepherd and Wedderburn LLP

    Standard Protections Contractors andConsultants

    Presentation by Juliet Haldane

  • 8/3/2019 S&W Credit Crunch

    18/46

    187 October 2008Contracting in the Credit Crunch

    Agenda

    What protections do standard T&Cs already provide to

    Contractors and Consultants? Payment

    Suspension

    Termination

    How can these existing protections be further strengthened?

  • 8/3/2019 S&W Credit Crunch

    19/46

    197 October 2008Contracting in the Credit Crunch

    Payment

    Housing Grants, Construction and Regeneration Act 1996

    Instalments

    Due Date

    Final Date

    Withholding notices

  • 8/3/2019 S&W Credit Crunch

    20/46

    207 October 2008Contracting in the Credit Crunch

    Payment

    1 day beforeFinal Datefor Payment

    28 Daysafter deliveryof Statement

    Oncertificationof thestatement

    Agreedstage orperiodic

    ICE

    28 days afterreceivingStatement

    56 days afterStatement or42 days afterFinal

    Statement

    Receipt ofStatement

    Schedule ofPayments orquarterly

    FIDIC

    7 daysbefore Final

    Date

    14 days afterdue date or

    period inContractData

    7 days afterassessment

    date

    Agreedassessment

    intervals

    NEC

    5 daysbefore FinalDate

    14 days fromdue date

    Receipt ofApplication

    Agreedstage orperiodic

    SBCC/JCT

    WithholdingFinal DateDue DateInstalments

  • 8/3/2019 S&W Credit Crunch

    21/46

    217 October 2008Contracting in the Credit Crunch

    Suspension

    Where a sum due under a construction contract is not paid infull by the final date for payment and no effective notice to withhold

    payment has been given, the person to whom the sum is due has theright..to suspend performance of his obligations under the contract tothe party by whom payment ought to have been made

    Housing Grants, Construction and Regeneration Act 1996

  • 8/3/2019 S&W Credit Crunch

    22/46

    227 October 2008Contracting in the Credit Crunch

    Suspension

    Expiry of 21 days from Final DatePLUS 7 days notice of intention tosuspend

    ICE

    Expiry of 21 days from notice ofintention to suspend

    Note also right to suspend for failure

    to submit financial arrangements

    FIDIC

    N/ANEC

    Failure to pay continues for 7 daysafter a notice of intention to suspend(with grounds)

    SBCC/JCT

    Conditions additional to failure topay by Final Date

  • 8/3/2019 S&W Credit Crunch

    23/46

    237 October 2008Contracting in the Credit Crunch

    Termination

    Non-payment

    Insolvency

    Breach of assignation provisions

    Common Law material breach

  • 8/3/2019 S&W Credit Crunch

    24/46

    247 October 2008Contracting in the Credit Crunch

    Adjudication

    Housing Grants, Construction and Regeneration Act 1996

    Right to refer dispute to adjudication

    Timetable for securing appointment of adjudicator and referral ofdispute

    Decision within 28 days (or 42 by agreement)

    Impartial decision which is binding until final determination by courts,arbiter or agreement

    Scheme for Construction Contracts

  • 8/3/2019 S&W Credit Crunch

    25/46

    257 October 2008Contracting in the Credit Crunch

    Construction Contracts Bill

    Due to be enacted Autumn 2009.

    Applicable only to construction contracts entered into after Bill in force

    Principle Changes Payment Notices Act avoidance provisions

  • 8/3/2019 S&W Credit Crunch

    26/46

    267 October 2008Contracting in the Credit Crunch

    In Conclusion

    Check the conditions under which you are being asked to work

    At tender stage, raise any amendments to standard T&Cs

    Think cash flow equally applicable in boom times

  • 8/3/2019 S&W Credit Crunch

    27/46

    Shepherd and Wedderburn LLP

    Contractor/Consultant Payment Protections

    Presentation by Ian Hughes

  • 8/3/2019 S&W Credit Crunch

    28/46

    287 October 2008Contracting in the Credit Crunch

    Introduction to the Practical Issues

    What is the contract?

    Who is my employer going to be?

    Is the employer credit worthy? How do I get paid?

    Payment Protections available to me?

    Downward Payment Protections

    Insurance?

  • 8/3/2019 S&W Credit Crunch

    29/46

    297 October 2008Contracting in the Credit Crunch

    1

    st

    Stage Tender Enquiry

    Advertised or issued direct to contractors/consultants

    Ascertain identity of proposed employer

    new or existing?

    company number is key not name

    partnership (LLP or other?)

    offshore entity

    Ascertain estimated contract value and cashflow

    proposed contract period

    maximum exposure two/three/four months

    Any initial works/services?

  • 8/3/2019 S&W Credit Crunch

    30/46

    307 October 2008Contracting in the Credit Crunch

    Initial Pre-Construction Services/Works

    Initial design phase appointment

    Pre-Construction Services Agreement

    Carrying out initial designs Planning Building Warrant Stage E?

    Carrying out detailed pricing and design reviews

    Producing sub-contractor tender documents

    Progressing the detailed design

    At risk? or Under contract?

    Agree initial fee

    Agree scope of works/services

    Negotiate and agree legals before you start

  • 8/3/2019 S&W Credit Crunch

    31/46

    317 October 2008Contracting in the Credit Crunch

    Credit Check Process

    Liaise with Finance Director/Manager

    Provide the financial information

    FD to carry out credit check

    FD liaise with legal director/advisors to agree risk profile

    FD instructs as to payment protection measures required

  • 8/3/2019 S&W Credit Crunch

    32/46

    327 October 2008Contracting in the Credit Crunch

    Security Options Available

    Payment Guarantee

    types available? unlimited guarantee of all sums

    capped - at level of maximum exposure?

    termination funds

    expiry payment of final account stepped at PC

    who from ultimate parent company, shareholder?

    Third Party Payment Bond

    similar to a Performance/Guarantee Bond

    types available? 10% only?

    expiry not PC! who from UK Bank/Surety, Foreign Surety?

  • 8/3/2019 S&W Credit Crunch

    33/46

    337 October 2008Contracting in the Credit Crunch

    Security Options Available

    Advance Payments

    specific element

    front-end loaded cashflow bond back?

    Escrow/Trust Accounts/Agreements

    ring fenced funds

    full amount for drawdown

    rolling fund

    termination fund

    need to be strictly worded to avoid liquidators hands

  • 8/3/2019 S&W Credit Crunch

    34/46

    347 October 2008Contracting in the Credit Crunch

    Security Options Available

    Standard Security over the site

    Unlikely to be worthwhile due to funders security

    Ranking

    Step-in Rights in Collateral Warranties

    obligatory or discretionary?

    step-in period

    payment of outstanding and future sums capped?

    beware who you grant step-in rights to!

    100 company loss of guarantee/bond

  • 8/3/2019 S&W Credit Crunch

    35/46

    357 October 2008Contracting in the Credit Crunch

    Timing of Security Placement

    As soon as possible

    Prior to or at contract Letter of Intent or Pre-Construction Services Agreement

    Formal Appointment/Building Contract

    Include in contract a right to suspend if not delivered

    Dont delay late delivery or late payment

    Insolvency horse might have bolted!

  • 8/3/2019 S&W Credit Crunch

    36/46

    367 October 2008Contracting in the Credit Crunch

    Protections Down the Chain

    Extended payment terms

    Include Construction Act compliant pay when paid clause Section 113 HGCRA 1996

    Applicable only where third party insolvency arises

    Beware Retention Bonds or Retention Free offers

    cashflow mismatch

    lack of fund for defects

    Carry out similar credit check process, as for an employer

  • 8/3/2019 S&W Credit Crunch

    37/46

    377 October 2008Contracting in the Credit Crunch

    Insurance against Insolvency?

    very little or nothing available in current market

    new Zurich product being introduced into the UK US product which covers sub-contractor default

    Third Parties (Rights Against Insurers) Act 1930

    Not one for recovering payment of sums due but

    may provide protection where a sub-contractor or sub-consultant has become insolvent

    Provides a means of access to a defendants insurance

    On insolvency insured rights can transfer to claimant

    Liquidator etc obliged to provide details of insurances

    Most commonly applies re All Risks, PII and PLI policies Policies likely to be on a claimed made basis so act quick.

    Insurance?

  • 8/3/2019 S&W Credit Crunch

    38/46

    387 October 2008Contracting in the Credit Crunch

    In Conclusion..

    Get the initial facts and details correct

    Do the credit checks

    Choose your preferred security option

    Get your security in place before you start

    Insurance unlikely to be the panacea

    This is best practice for life not just the Credit Crunch!

  • 8/3/2019 S&W Credit Crunch

    39/46

    Shepherd and Wedderburn LLP

    Credit Control and Debt RecoveryEnforcement of Bonds/Payment Guarantees

    Presentation by Douglas Stewart

  • 8/3/2019 S&W Credit Crunch

    40/46

    407 October 2008Contracting in the Credit Crunch

    Overview

    Credit Control and Debt Recovery

    Reducing exposure to bad debt

    Managing and recovering late payments

    Enforcement of Bonds/Payment Guarantees

    Procedures Pitfalls

  • 8/3/2019 S&W Credit Crunch

    41/46

    417 October 2008Contracting in the Credit Crunch

    Credit Control and Debt Recovery

    Ensuring that late payments do not become bad debts

    Effective systems to manage credit issues

  • 8/3/2019 S&W Credit Crunch

    42/46

    427 October 2008Contracting in the Credit Crunch

    Credit Control and Debt Recovery

    Reducing exposure to bad debt

    Credit checks

    Payment terms and invoicing procedures

    Managing credit levels

    Advance payments

  • 8/3/2019 S&W Credit Crunch

    43/46

    437 October 2008Contracting in the Credit Crunch

    Credit Control and Debt Recovery

    Managing and recovering late payments

    Up front meetings with clients

    Credit limits

    Separate credit control functions

    Demand letters and further procedure

    Interest on late payments

  • 8/3/2019 S&W Credit Crunch

    44/46

    447 October 2008Contracting in the Credit Crunch

    Enforcement of Bonds / Payment of Guarantees

    Procedures

    Insolvency

    Establishment of debt due

    Equivalent defence

  • 8/3/2019 S&W Credit Crunch

    45/46

    457 October 2008Contracting in the Credit Crunch

    Enforcement of Bonds / Payment of Guarantees

    Pitfalls

    Review of the terms of the bond or guarantee

    Credit checks on bondsman or guarantor

    Ensure means of recourse against bondsman or guarantor

  • 8/3/2019 S&W Credit Crunch

    46/46

    467 October 2008Contracting in the Credit Crunch

    Questions?