sustainable roadway materials for the i-90 project 1... · sustainable roadway materials for the...
TRANSCRIPT
Jay Behnke, P.E.S.T.A.T.E. Testing L.L.C.
FHWA Tollway National Open House,August 20, 2013
Sustainable Roadway Materials for the I-90 Project
Tollway – Building GREEN Waste – reduction work zone Striving to “eliminate construction waste
that is traditionally sent to landfills for disposal”
Recycling 100% of In Place Materials “Recycled Concrete, asphalt and other
materials, including roof shingles and tires will be used as base materials, backfill and in new pavements.”
2
http://www.illinoistollway.com/construction-and-planning/environmental-initiatives/building-green-roadways
Recycling Plan in Profile
Existing Pavement
Proposed Pavement
Black Rock Concrete and for Capping Agg.
PGE or RCA in Black Rock Concrete
Subgrade Granular Embankment, SpecialLimited offsite disposalModification my be necessary
3
Part 1:
REMOVE EVERYTHING!
…..but keep it.
4
Salvaging Existing Asphalt: Milled Asphalt will be recycled into
one of the following: PGE
Mechanically blended with Crushed Concrete for use in lower lift
Capping Aggregate 3” lift over PGE
Component of WMA Fine FRAP / Coarse FRAP 3” Stabilized Sub Base Shoulders
Component of Black Rock Concrete Lower Lift of Composite PCC
5
The GOOD, the BAD and the UGLY
6
Salvaging Existing Concrete: Concrete will be recycled into Porous Granular
Embankment (PGE) in one of the following ways: Break in place (Rubblized)
Difficult to achieve target gradation Mobile crushers
Best Option Off Site crushing
7
Production of Crushed Concrete Engineer will approve removal
and stockpile method. Stockpile pads are required for
stationary crushers. Contamination from existing
base - not acceptable. May be used for subgrade
treatments. Mobile Crushers PGE Production
Stationary Crushers Composite Pavement
8
Salvaging Existing Granular Material: Remove the Granular Bank Run and move into one of
the following locations for future use: Stockpile Windrow Off Site
9
Sub Base Widening Tollway is adding a lane
and shoulder Widening needed Existing ditches are used
for widening Remove topsoil and
stockpile separate
10
Grade changes throughout the I-90 Corridor
Additional Hurdles:
11
Part 1 A:
ALL GONE!
…..let’s start new.
12
Create a Working Platform: Determine Immediate Bearing Value (IBV) of Sub Base IBV ≥ 8.0 Disc Dry
Moisture content≤120% Air dry top 8” for 3 consecutive days
Compact ≥95% relative compaction
IBV < 8.0 Need to stabilize the base
13
Disc-ing In-Place Material (IBV ≥ 8.0)
14
Subgrade Stabilization Treatments (IBV < 8.0)
Lime Stabilization Fly Ash Stabilization
Clay Soils Granular Soils
FLY ASHLIME
15
Lime or Fly Ash Modification
Contractor will elect to use either Lime or Fly Ash
Collect soil samples to be modified
Send samples to an accredited lab for a Soil Modification Mix Design
Must be approved by the Tollway
16
Fly Ash Soil Stabilization I-90 – Jane Addams Memorial Tollway is mostly Granular Soils Fly Ash Stabilization @ 8% rate Modified 12 inches
17
Lime Soil Stabilization
18
Working Platform is Complete
19
Part 2:
PUT EVERYTHINIG BACK
20
Start adding back the Recycled Materials
Granular Embankment Special
6” Lift
21
Placing PGE over the Granular Embankment Special
22
Porous Granular Embankment
PGE
6” of PGE 5” Max Size for PCC 4” Max Size for RAP
Tollway allows more RAP than IDOT (50% max RAP) Contaminated RAP – not
allowed Mechanical blending is
required if using RAP
Feed material only from approved source Unknown material needs re-
certification
23
PGE
24
Capping Aggregate
3” Lift over PGE
Materials from approved source
CA6 gradation if it’s crushed concrete
”C” Quality or better 100% passing 3” max. for
RAP (must be well graded)
25
Hwy 23 – Looking East (Capping Aggregate)
26
Ready for WMA? …not quite.
27
Stabilized Base
WARM MIX ASPHALT 3” Stabilized Base of WMA Up to 65% ABR allowed
with Category 1FRAP PG58-28
What is WMA? Chemical admixtures or
water “foam” Modify viscosity of asphalt
cement (binder) At lower production and
laydown temperatures, acts like “normal” HMA.
After slightly longer “curing”, has physical properties similar to “normal” HMA.
28
Jane Addams Tollway WMA, FRAP, RAS
29
WMA – stabilized base
30
Composite Pavement – 2 Lift Pavement
Black Rock PV Lift
Lower Lift only From 8 ¼” to 9” Includes RAP from Milling
Process Lower Quality Virgin
Aggregates
Top Lift only 3” Virgin Only
31
PCC Production Trial Batching Test Section Two Plants are required Paving Train Different between
contractors
Dowel Baskets or DBI are accepted
32
Composite Pavement
33
Black Rock Concrete
34
PCC Placement
35
PCC Placement
36
PCC Placement
37
Difficult Staging area – requires unique solution
38
Millions of $’s Saved on I-90Avg. bid price based on 2006 - 2009 Single Lift JPCP Projects Approximately 1,188,086
sq. yds. of 12” JPCP placed on I-294 and I-88
Average low bid price = $56.37 / SY
Avg. bid prices received on 6 2013 jobs for Composite JPCP > 750,000 sq. yds. to be built
on I-90 in 2013 11.25” Composite JPCP -
$40.30/SY avg. of all bids 12” Composite JPCP -
$45.92/SY avg. of all bids 13” Composite JPCP -
$49.70/SY avg. of all bids
39
THANK YOU40