Sustainable Design of the
Integrated Pipeline Project
From Definition to Implementation
March 2, 2017Rachel A. Ickert, P.E. and Russell L. Gibson, P.E.
Stewardship of resources
Reliability
Level of Service
Lifecycle cost
Design life
Why Sustainability?
Integrated Pipeline
Key Sustainable Features that Differentiate IPL
• Research for Pipeline Design and Construction• Re-used pipeline excavation for reservoir embankment
• Plan for long term operations and maintenance
• Improved local skills and capabilities• Regional partnership/effective leadership and commitment
Line J – Pipeline Research
•Tests IPL design criteria, specifications, details
•Test pipe suppliers•Ability to meet standards
•UTA’s CLSM research
•Real-Time GIS As-Built process
Served as a prototype for the IPL project and allowed lessons learned to be leveraged by testing and refining:
Line J - Innovative Procurement
• Construction Manager at Risk (CMAR)• Competitive Sealed Proposals• Quality\experience\other criteria for selection• Allows owner\CMAR to jointly select subs\vendors• Raises the bar on the whole industry• Allowed for municipalities\water districts\river authorities in Texas
Line J – Installation and CLSM
• Factory Inspection of Lining and Coating• Lining thickness, coating holidays, steel cleanliness, steel thickness, welding parameters
Line J – Best Practices in QA/QC
Re-used Pipeline Excavation for
Reservoir Embankment
• Identified material suitable-for-beneficial-reuse from:• pipeline ROW• reservoirs
•Structured construction contracts to:• benefit from suitable on-site-materials• PL12 + PL13 + MBR
Plan for Long Term O&M•Development of O&M manuals•Accessibility:
• Pipeline designed to provide adequate access for CA and O&M•Monitoring:
• Pressure/surge• Pump efficiency• Pump/motor condition
•Sonic leak detection
Plan for Long Term O&MEnergy Management
LeadershipRisk ManagementStrategic Planning
Improved Local Skills and Capabilities
• Fair Opportunity Purchasing and Contracting Policy• Local & National Engineers • Estimated $100 Million per Year in Construction Jobs• Academia• Value Engineering
Regional Partnership / Effective Leadership and Commitment
• Estimated $500 million capital savings• Supply reliability• Sharing of assets
Conclusion