sustainable design for appledore island

Upload: val-katz

Post on 16-Feb-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/23/2019 Sustainable Design for Appledore Island

    1/35

    Sustainable Design

    for Appledore IslandFinal Alpha Team Project

    Cyara New

    Reid BalkindAbhi GuptaValerie Katz

    Yungton Yang

  • 7/23/2019 Sustainable Design for Appledore Island

    2/35

    2

    Introduction

    Appledore Island is located about six miles off the coast of Maine and New

    Hampshire; the island is completely self-sufficient and is home to the Shoals Marine

    Laboratory. Being self-sufficient, it produces its own power and freshwater and it

    manages all of its wastewater.

    To generate power, Shoals Marine Laboratory uses one of its three diesel

    generators, arrays of solar panels, and a 7.5 kW Bergey Wind Turbine to provide

    power in winter months when wind is more prevalent and the sun less intense. In

    an effort to make the island more sustainable, the Alpha Team aims to move

    Appledore Island away from diesel generators and towards cleaner sources of

    energy.

    Freshwater supply comes from a well that is twenty feet deep with a six-foot

    diameter. The water from this well is treated by filtration and chlorination. If the

    water level in this well gets too low, however, there will be mixing between this

    fresh well and a saltwater watershed, making it unsuitable for consumption. To

    prevent this during dry summers when the well is insufficient and cannot meet the

    freshwater demand, a reverse osmosis unit desalinates salt water, a process that is

    energy intensive. The Alpha Team aims to facilitate this process by producing the

    requisite additional energy in a sustainable way, or determine a new process to

    implement altogether.

    Finally, the island treats wastewater through four septic systems, three leach

    fields, four composting toilets, and a FRICKle filter that treats gray water. The

    FRICKle filter contains foam media on which bacteria grow. These bacteria respire

  • 7/23/2019 Sustainable Design for Appledore Island

    3/35

    3

    anaerobically and purify the water. All systems are therefore quite sustainable, but

    there is room for additional considerations as there are still inefficiencies with the

    FRICKle Filter.

    The mission of Shoals Laboratory is toprovide education and research

    programs that advance the 1) understanding of marine and coastal ecosystems and

    2) development of sustainable solutions to environmental challenges (The Mission

    of the Shoals Marine Laboratory). The Alpha Teams goal is to facilitate Shoals

    Laboratorys second goal and help tocontinue the islands efforts of becoming

    increasingly sustainable. This will be accomplished through the implementation of

    sustainable designs to improve the islands energy systems by shifting away from

    diesel, a freshwater supply independent of the existing well, and a better

    wastewater treatment system.

    Energy

    While Appledore Island has made strides in its energy production via the

    implementation of solar panel and a wind turbine, it still uses some diesel for fuel.

    Several solar arrays are in place on top of dorms two and three, and a 7.5 kW wind

    turbine was brought onto the island in 2007. Diesel fuel is still being used however

    to supplement the energy provide via these sustainable methods. Based on the

    average generator capacity utilization graph (Appendix A) it was determined that

    the island uses diesel generators to obtain 652.5 kWh/day. At this rate the

    Appledores greenhouse gas footprint is 163 kg CO2/ day. (Appendix A)

  • 7/23/2019 Sustainable Design for Appledore Island

    4/35

    4

    Technologies Considered

    To provide the island with more sustainable sources of energy to meet the

    demand of 652.5 kWh/day currently being met by diesel fuel engines, several

    green energy systems were considered. Solar panels with storage were considered

    to harness solar energy, a wind turbine with hydrogen storage, fuel cells, and

    batteries were considered to harness wind energy. Hydroelectric, geothermal, and

    biomass systems were also considered.

    Figure 1. Comparing Energy Type to Annualized Costs

    In comparing the several energy systems available, the three cheapest

    options were hydropower, solar with storage, and biomass. A detailed calculation of

    the annualized costs can be found in Appendix B.

    Wind power was also ruled out because the island has a wind turbine, and it

    is primarily used in the winter, when the wind is the strongest. As the Alpha Team

    seeks to replace diesel generator usage, most of which is during the summer on

    $0.00

    $2,000.00

    $4,000.00

    $6,000.00

    $8,000.00

    $10,000.00

    $12,000.00

    $14,000.00

    Solar withStorage

    Wind withStorage

    Geothermal Hydropower Biomass (BFB)

    Energy Source vs Annualized Cost

  • 7/23/2019 Sustainable Design for Appledore Island

    5/35

    5

    Appledore, it is not reasonable to install another wind turbine. The annualized cost

    of wind power was determined to be $13,030.17.

    For a geothermal power plant, the Alpha Team recommends a flash steam

    power plant because at 235C (Lecture Slides 2-25 Slide 5), the pressure of the

    steam would be 100000 kPA (Appendix B Geothermal), and at this pressure steam

    becomes a liquid. Flash steam must be 175-235 degrees, so the well needed to

    extract this high temperature superheated liquid would be 2.5-3.5 km deep, making

    geothermal an impractical endeavor. The cost of geothermal power was determined

    to be $13,138.14 per year.

    Hydroelectric Energy

    Hydroelectric was another option explored, with an abundance of water

    surrounding the island providing the requisite environment for this system.. All

    calculations are available in Appendix B Hydroelectric. With the significantly low

    annualized cost of $4,756.58 per year, hydroelectric was a very affordable choice for

    Appledore. After calculation, however, is that it requires a massive area of 2,250,000

    m2, or 617 acres. Considering the island spans only 95 acres, the proposal for such a

    large basin is unreasonable. It would impede the marine activities that take place

    around the island and seriously hinder research conducted by Shoals Laboratory.

    Furthermore, the system would need to be located far enough from the island and

    large enough (about 0.86 square miles) that it would not be worthwhile. The basin

    would need to be 6 meters deep with a channel that is 30 m x 5 m, and would need

    50 turbines each with a 0.108 m radius.

  • 7/23/2019 Sustainable Design for Appledore Island

    6/35

    6

    Solar Energy

    The Alpha Team recommends solar energy with storage to as a possibility to

    eliminate diesel use because solar power is already used on the island and

    extending this infrastructure is very viable and simple. All calculations are available

    in more detail in Appendix B - Solar. Also it is cost effective at$9,880.07 per year.

    We recommend BP 3160 solar panels whose max power output is 160 W per panel,

    this equates to 836.8 Wh produced per panel per day. Because Appledore only

    averages 5.23 peak sun hours per day, additional energy must be stored (Lecture

    Slides 2-9 Slide 19). Accounting for inefficiencies with the inverter and battery, solar

    panels must collect 1028.26 kWh/day. This equates to 1229 panels that would cover

    approximately 16668 ft2.

    Because solar panels are most efficient when they are perpendicular to the

    suns rays these panels should be placed at an angle. However, during the summer

    months, the sun is higher in the sky, and thus the panels should have a tilt less than

    45 degrees. It is recommended to place solar panels at the locations latitudinal

    angle, + 15 degrees, and so for a summer bias we subtract 15 degrees and

    recommend that these panels be placed at about a 28 degree angle (Lecture Slides

    2-9 Slide 17). At this angle the panels would cover 14,722 square feet. The

    advantages of solar energy remain the time of maximum energy usage; the summer

    provides the maximum output. The other advantage remains that the infrastructure

    already exists. The problem, however, is the large amount of space needed to

    accommodate the panels. However, in comparison to other sources, area usage is

    low, and cost is not severely high. Our recommendation is that these panels be

  • 7/23/2019 Sustainable Design for Appledore Island

    7/35

    7

    placed on top of buildings with appropriately slanted roofs before resorting to open

    space on the north side of the island.

    Biomass Energy

    Biomass energy was the final option considered. Biomass energy very simply

    utilizes different waste material for energy generation, with an efficiency of 90%

    (What to Expect from Biomass Boiler Systems). There are many sources of fuel for

    biomass systems, inclusive of wood pellets, wood chips, human and animal waste,

    crop residue, and municipal solid waste (Types of Biomass Fuels). Furthermore,

    there are two main types of biomass systems that the Alpha Team considered: the

    combined cycle and the bubbling fluidized bed. In the first system, waste is burned

    and the heat generated is used to boil water, which then turns into steam and turns

    a turbine to produce electricity. The main fuel used is carbon based options, which

    usually consists heavily of wood related waste and pellets. In the second system,

    solid particles levitate above liquid moving at a low velocity, causing the particles to

    act as a fluid. The bubble and fluid movement causes interactions with high heat

    transfer, allowing for water to be boiled, which turns into steam and turns a turbine.

    The main fuel used in this system is wood, plant remains, and solid waste. The Alpha

    team recommends the utilization of the second system, simply because of the higher

    number of feedstock options, and because the capital cost of a BFB is half as much as

    a CC system ($4,114 vs $8,180) (Capital Cost for Electricity Plants). All calculations

    are outlined in Appendix B Biomass. Because Biomass systems are generally used

    for large scale energy production, it seems unfeasible for Appledore Island to

    implement this system. If there was a larger energy need, biomass would be a viable

  • 7/23/2019 Sustainable Design for Appledore Island

    8/35

    8

    option. Furthermore, biomass systems require a large amount of space for the

    boilers and fuel storage (Advantages and Disadvantages of Biomass). Currently,

    biomass energy would have an annualized cost of $11,846.90, but this is not

    considering the cost of resources. Biomass fuel is very expensive, and even with the

    use of waste from the island, fuel would need to be imported.

    Energy Conclusion

    With the technologies looked into: solar power, hydropower, and biomass

    considered, solar was determined to be the best solution. Hydropower is the

    cheapest option, but it is very space intensive. Biomass is economically viable for

    large energy production needs, but for the small scale of Appledore is not feasible as

    biomass may need to be imported. Solar power was determined to be the best

    option. It is relatively cheap, and reliable as sun input is reliable in summer months.

    Additionally solar arrays are already in place in Appledore, so extending this

    existing system makes most sense.

  • 7/23/2019 Sustainable Design for Appledore Island

    9/35

    9

    Drinking Water Treatment

    Celia Thaxter Island Garden

    Each season Shoals Laboratory uses about 157,029 gallons of water sourced

    from both a well on the northern region of the island, as well as a reverse osmosis

    unit (2014 Sustainable Energy Report 46-47). In the summer of 2014 the size of the

    watershed was estimated to be 53,840 ft^2, but this well must be supplanted by a

    reverse osmosis unit because if the water in the well runs too low, the risk is run of

    contamination with saltwater.

    Water conservation efforts on the island are evident as residents are

    restricted to only two navy style showers a week in which water only runs during

    rising. These efforts however can be improved with the Celia Thaxter Island Garden.

    This garden was first cultivated in the late 1800s when by Celia Thaxter whose

    father established a hotel on the island. She had a love for gardening and art, and her

    prose and poetry received considerable fame. The garden drew in many artists and

    writers and for this reason holds great historical value and is worthy of being

    preserved (About Celia Thaxter's Island Garden). The flowers in the garden need

    freshwater, however when water is limited it is difficult to justify using fresh well

    water to cultivate the blooms when it is needed elsewhere. Our proposal is a rain

    water collection system estimated roughly to cost around $4,000. The island

    conducts tours of the garden seven times a summer, each tour with 24 people, and

    each person is charged 100, this brings in a total $16,800, and it is reasonable to

    have some of this revenue directed towards a system to make the garden more

    sustainable.

  • 7/23/2019 Sustainable Design for Appledore Island

    10/35

    10

    Technologies Considered

    Because the well currently on the island is insufficient in dry years, other

    freshwater sources are necessary. To meet the additional freshwater need options

    considered included: digging another well, slow sand filter, rapid sand filter, and

    solar distillation. Reverse Osmosis is currently in use on Appledore but uses a high

    level of energy, making it necessary to consider other options. Solar distillation was

    possibly the most environmentally friendly option as once it was built it would only

    require upkeep to run and no further inputs. Comparatively, while the two types of

    filtration would require upkeep and inputs to keep it running, they would still be

    relatively minor complications for an operation this small. These two methods

    would also take up very little space on the island and dont depend on

    uncontrollable variables such as the sun.

    Figure 2. Filtration System vs Annualized Cost

    The rapid sand filter cost includes the cost of system installation, sand,

    backwashing, chlorine, and the contact tank. The slow sand filter cost includes the

    $0.00

    $400.00

    $800.00

    $1,200.00

    $1,600.00

    $2,000.00

    Slow Sand Filtration Rapid Sand Filtration Solar Distil lation

    Filtration System vs Annualized Cost

  • 7/23/2019 Sustainable Design for Appledore Island

    11/35

    11

    cost of the system installation, sand, chlorine, and contact tank. The solar distillation

    cost only includes the cost of system install, per nature of the technology. All

    calculations are outlined in Appendix C.

    With slow sand and rapid sand filtration systems already partially or

    completely in place on Appledore, the Alpha Team believes it is in the best interest

    of the island to continue working with sand filters. However, because solar

    distillation is so cheap, the Alpha team performed an analysis on all 3 systems.

    Solar Distillation

    Solar distillation utilizes solar energy in order to evaporate and purify salt

    water. Because this process utilizes salt water versus fresh water which the other

    two require it would put much less of a strain on the island. The fresh water source

    has steadily grown smaller which poses a potential problem. This method uses solar

    heat to evaporate salt water. A black heat-absorbent surface is placed at the bottom

    of the container to help capture heat inside the container more quickly. The

    evaporated water then condenses on the cool plastic of the top part of the container.

    During the condensation part of the process much of the heat energy is reabsorbed.

    This evaporated water is now pure of salt and bacteria and will drip down the side

    to a collection basin where it can now be used to drink safely. This process isnt very

    time efficient and does require a comparatively large area to hold all of the housings.

    The upside to this process though is that it doesnt require any further treatment to

    the water and the solar distillation housings only require the water to work. It is

    also environmentally friendly in this regard. The annualized cost of the system is

  • 7/23/2019 Sustainable Design for Appledore Island

    12/35

    12

    $617.51, which is outlined in Appendix C Solar Distillation. However, the size

    required is 2592.5 m2, a very large section of space.

    Rapid Sand Filtration

    Rapid sand filtration utilizes porous media filtration in order to clean the

    water of colloidal and suspended solid. It requires fresh water to run as it wont

    clean the salt out of sea water. The water is run through a tank containing sand and

    uses gravity to pull it through. The sand will remove any suspended solids in the

    water. As the sand gets more clogged up the water will experience head loss or a

    loss of pressure. In order to clean the sand it must be backwashed. Backwashing is

    when water is forced the opposite way through the filter. The water will cause the

    sand to expand and release all of the collected waste from the water. This process

    does require energy to run. After the water is filtered through the sand it still may

    have bacteria present, such as cryptosporidium or giardia lambia. Thus, it requires

    disinfection which is accomplished with the use of chlorination. The water is sent to

    a contact tank where it is exposed to chlorine that should kill varying levels of

    bacteria depending on the amount of time spent in there. After leaving the contact

    tank the water will be safe enough to drink. This process is very time efficient but

    does have its fair share of downsides. First of all, it requires fresh water to run.

    Second of all, it requires energy and chlorine to run which contribute to annual

    costs. Another problem is that it does require the use of chemicals to clean the water

    which is an area of concern for many people. The Alpha Team calculates a rapid

    sand filter would need to be 0.043 m2. It would also require 78.792 kg of sand

    initially and then 3.747 kg of chlorine per year with a contact tank with an area of at

  • 7/23/2019 Sustainable Design for Appledore Island

    13/35

    13

    least 275 gal, and 3.5 kw/day to backwash. With these factors in mind the

    annualized cost of a rapid sand filter would come out to $1,730.99. All calculations

    are outlined in Appendix C Rapid Sand Filtration.

    Slow Sand Filtration

    Slow sand filtration is a process very similar to rapid sand filtration. Rather

    than utilizing backwashing the sand, though, the top layer of sand must be replaced

    every few months. This process has all the same pros and cons of rapid sand

    filtration except for discrepancies in the price to run it and the fact that slow sand

    filtration does require its consumers to be careful of water usage, as it does take

    time for water to cleanse under this system. The slow sand filter would need to be

    2.17 m2and would require 7000 kg of sand with the top 2 inches of it being replaced

    yearly. It would also require the same amount of chlorine and a contact tank as the

    rapid sand filter. This means that the slow sand filter comes out to be $859.26

    annually. All calculations are outlined in Appendix C Slow Sand Filtration.

    Drinking Water Conclusion

    In conclusion, the Alpha Team recommends the use of a slow sand filter. It is

    a cheap option for water purification and requires little space to operate. Although

    the use of chlorine is a downfall of this process, the benefits are greater than the

    losses, and ultimately beats out the other technologies. Rapid Sand filtration is very

    expensive in regards to the other choices, while solar distillation is cheap and does

    not use chlorination, but requires a large amount of space that would be difficult to

    find on Appledore.

  • 7/23/2019 Sustainable Design for Appledore Island

    14/35

    14

    Wastewater Treatment

    Technologies Considered

    The islands wastewater systems at the time being are relatively sustainable,

    however the FRICKle filter has been having issues due to its design, so the Alpha

    Team proposes wastewater treatment options for effluent from primary settling.

    Two general methods were considered: combined blackwater and greywater

    treatment and separate blackwater and greywater treatment. In combined

    treatment systems, septic tanks are proposed for primary treatment, where solids in

    the wastewater will settle and be anaerobically digested, with remaining liquid

    waste being passed to a secondary treatment system. These secondary treatment

    systems include constructed wetlands, leach fields, rotating biological filters, and

    trickle filters. This provides 4 options in combined treatment, with the septic tank

    paired with each secondary option. For separated systems, a composting toilet

    would be used to separate and collect blackwater, with the remaining greywater

    being treated in a secondary system, either constructed wetlands or leach fields.

    This provides 2 separated treatment options, with the composting toilets paired

    with the two secondary options. The Alpha Team compared the annualized costs of

    the 6 options presented, and proceeded to conduct a more thorough review of the

    top 2 options. All calculations are outlined in Appendix D.

  • 7/23/2019 Sustainable Design for Appledore Island

    15/35

    15

    Figure 3. Wastewater Treatment Options vs Annualized Costs

    The Alpha Team decided to consider two technologies for a combined system. We

    would use either a septic tank with a constructed wetlands or a septic tank with a

    leach field as they were by far the cheapest options.

    Septic Tank

    Septic Tanks are necessary for primary treatment of wastewater. In the

    septic tank, solids settle and are anaerobically digested. The purpose of the septic

    tank is to collect the solids and remove large pieces of material such that the

    secondary treatment option can consume the remaining waste and cleanse it such

    that consumption or environmental discharge is acceptable. The Alpha team

    calculates that the annualized cost of this system is $1,193.30, compared to the

    other primary treatment option of composting toilets which cost $6,708.59, nearly 3

    times as much as septic tanks. Comparing size, the septic tank was 2400 gal, while

    22 composting toilets would be needed, or about 2200 liters (581 gal). All

    0.00

    2000.00

    4000.00

    6000.00

    8000.00

    Septic + CW Septic +Leach

    Septic +RBC

    Septic +Trickling

    Compost +CW

    Compost +Leach

    GW and Combined Systems Annualized Costs

  • 7/23/2019 Sustainable Design for Appledore Island

    16/35

    16

    calculations are outlined in Appendix D, under the septic tank and composting toilet

    sections.

    Constructed Wetlands

    The constructed wetlands receive wastewater from a pipe connected to the

    septic tank. Wastewater can either flow above the existing soil, or it can flow

    through the soil, such as gravel, clay, or sand. The flow of the wastewater is

    relatively even, flowing across the width of the wetland. The Constructed Wetland

    contains microorganisms known as periphyton that break down the pollutant in

    wastewater, and much of the waste and excess concentration of nutrients are

    consumed by the many plants that exist in the wetland. The purpose of the

    constructed wetland is to mimic natural wetlands, and thus it is necessary to place

    plants into the system. As saltwater is used from the ocean, it is necessary to use

    saltwater plants such as saltmeadow hay, salt grass, sea lavender, and salt marsh

    aster. The cost of just the wetlands is $435.36, while the cost of the combined septic

    tank and constructed wetlands system is $1628.66. The size of the wetland is

    3208.33 ft3. All calculations are listed under Appendix D Combined System

    Constructed Wetland.

    Leach Field

    Leach fields are a secondary treatment option for wastewater, cleaning the

    water after it has gone through a primary treatment option. The system generally

    contains a large number of perforated pipes that leach wastewater from them into

    the soil such that the microorganisms can cleanse it, but animals in the ecosystem

    wont be able to reach it. The leach fields contain bacteria in the soil that remove

  • 7/23/2019 Sustainable Design for Appledore Island

    17/35

    17

    dissolved organic material in the effluent. The annualized cost of the system is

    $623.71, with a size of 4800 ft2. All calculations are listed under Appendix D

    Combined System Leach Field.

    Conclusion

    After comparison of the constructed wetlands and leach field, the Alpha team

    chose the constructed wetlands as the secondary treatment option for wastewater,

    allowing for the entire system to be composed of a septic tank and a constructed

    wetland. There were many considerations that led to this decision. As the

    calculations show, the constructed wetlands is cheaper than the leach field by a cost

    of $1628.66 to $1817.01, which is another good reason to use the constructed

    wetlands over the leach field. The constructed wetlands also provides Appledores

    inhabitants with an aesthetically pleasing piece of land and wildlife a habitat to live

    in. Taking all of these considerations into account, it is clear why the septic tank and

    constructed wetlands combination is better than the septic tank and leach field

    system.

  • 7/23/2019 Sustainable Design for Appledore Island

    18/35

    18

    System Placement

    The placement of systems is dependent on existing infrastructure and the

    natural characteristics of the island. The Alpha team recommends placing a Solar

    Panel Field in an area that is large and open, such as the north side of Appledore

    Island. These could hypothetically go anywhere there is room and direct sunlight.

    Ideally, the Slow Sand Filtration would be placed in an area where the soil is mostly

    sand as it requires a lot of sand to function. Further, close placement to housing and

    Constructed

    Wetlands

    Solar Panel Field

    Slow SandFiltration

  • 7/23/2019 Sustainable Design for Appledore Island

    19/35

    19

    dormitories will provide fast access to drinking water for the population on the

    island. Constructed Wetlands were placed very close to water in a marshy area,

    necessary for water flow into the system. Placement also considered the location of

    the restrooms, as it is necessary to treat the water in a timely manner without

    allowing the harsh smell of the wastewater to reach the people of Appledore.

    Conclusion

    The most sustainable design for Appledore Island includes Solar Power for

    Energy, Slow Sand Filter with Chlorination for Drinking Water, and Constructed

    Wetlands with a Septic Tank for Wastewater. The Alpha Team finds solar power the

    best option for energy because of its inexpensiveness and space efficiency.

    Appledore currently uses solar power, making it viable to extend the infrastructure

    onto more buildings or further onto the island. The next step is to increase the

    production and application of the solar energy so Appledore no longer needs to use

    Diesel Fuels. The Slow Sand Filter was chosen because it was the less expensive

    compared to rapid sand. However, it does require a high usage of sand but it does

    not backwash the water, which is important as energy demand does not increase.

    Appledore must watch its water consumption as the slow sand filter cleans slowly,

    and there will be less water available in comparison to other systems. As for

    wastewater, Constructed Wetlands are the lease least expensive overall and

    extendable. Because of their characteristics, it will provide a good habitat for

    wildlife and blend in with the environment. The Constructed Wetlands are also

    much smaller than the Leach fields, making it the best option for wastewater. The

  • 7/23/2019 Sustainable Design for Appledore Island

    20/35

    20

    Alpha Team finds these to be the most sustainable options for Appledore moving

    forward.

    WORKS CITED

    About Celia Thaxter's Island Garden.. (n.d). Retrieved May 5, 2015, from

    http://www.sml.cornell.edu/sml_publiced_aboutthegarden.html

    Advantages and Disadvantages of Biomass. Eco Home Essentials, 2015. Web. 11

    May 2015.

    Bach, Alan, Michelle Bowen, Paroma Chakravarty, and Sean Snow.2014 Sustainable

    Engineering Report. Shoals Marine Laboratory, 2015.

    Capital Cost for Electricity Plants. U.S. Energy Information Administration, April 12,

    2013. Web. 11 May 2015.

    Jones, Ben. What to Expect from Biomass Boiler Systems. The Green Home:

    Construction and Lifestyle. Web. 11 May 2015.

    The Mission of the Shoals Marine Laboratory. (n.d). Retrieved May 5, 2015, from

    http://www.sml.cornell.edu/sml_welcome_mission.html

    Types of Biomass Fuels. Types of Biomass Fuels. Hurst Boiler and Welding

    Company, Inc., 2015. Web. 11 May 2015.

  • 7/23/2019 Sustainable Design for Appledore Island

    21/35

    21

    Appendix A

    Appledore Island information

    The above graph (Lecture Notes 1-30 Slide 20) outlines the average generator

    capacity utilization on Appledore over the course of 1 day. For a baseline, it is

    assumed that the power used is 30 kW, and therefore the overall energy used per

    day is 720 kWh. However, the Alpha Team aims to attain a more accurate measure

    of energy used. Therefore, the graph was broken as follows:

    30 kW * 12 hr + 26.25 kW * 3 hr + 21.25 kW * 6 hr = 652.5 kWh/day

    Knowing the energy used per day, the amount of CO2 produced can be calculated.

    . *

    .

    9. = 163 kg CO2/day

    The rate at which energy is used can also be determined.

    verage Generator Capa city Utilization over a Da y

    0

    10

    20

    30

    40

    50

    60

    10:15 AM 4:15 PM 10:15 PM 4:15 AM 10:15 AM

    0%

    15%

    29%

    44%

    59%

    74%

    88%

  • 7/23/2019 Sustainable Design for Appledore Island

    22/35

    22

    . = 27.1875 kW

    Because Appledore only functions for 3 months of the year, costs, energy usage, and

    other factors relying on time must keep this in consideration.

    = 91.25 days 91 days

    Appendix B

    Energy Systems

    Solar Energy

    The annualized costs were calculated as follows. First, the uniformed costs:

    Capital Cost = $4183/kW, Discount Rate = 0.05, Lifetime = 20 years

    ($4183*27.1875 kW)[ .(+.)]= $9125.61

    Then the annualized costs were calculated by adding uniform and O&M Costs:

    $9125.61 + ($27.75/kW/yr * 27.1875 kW) = $9,880.07

    It is assumed that BP 3160 Solar Panels are used, which have a max power output of

    160W, voltage of 35V, current of 4.5 amps, and a size of 31 x 63.(Lecture Slides 2-

    9 Slide 22). Appledore has 5.23 Peak Sun Hours (Lecture Slides 2-9 Slide 23), or the

    effective sunlight received per day. Therefore, the energy per panel per day is:

    160 W * 5.23 PSH = 836.8 Wh /day / panel

    Assuming the efficiency of the inverter is 0.75, and the efficiency of the battery is

    0.8, the amount of energy needed to be stored is:

    EPSH+ Enight =

    . .

    . +(. )

    . .. = 1028.26 kWh

    The number of panels needed are:

  • 7/23/2019 Sustainable Design for Appledore Island

    23/35

    23

    *

    . = 1229 panels

    The area needed is:

    (31 in * 63 in)*(1229 panels) = 2,399,836.5 in2= 16,665.53 ft2

    The preferred angle for the panels is:

    42.96 - 15 = 27.96 28

    Shifting the area used by the panels to:

    63 *cos(27.96) = 55.65 = Adjusted Side Length

    31 * 55.65 = 1725 in2= Adjusted Area per panel

    1725 in2 * 1229 panels *( )2= 14,722.4 ft2

    Hydroelectric Energy

    The annualized costs were calculated as follows. First, the uniformed costs:

    Capital Cost = $2936/kW, Discount Rate = 0.05, Lifetime = 50 years

    ($2936*27.1875 kW)[ .(+.)]= $4372.42

    Then the annualized costs were calculated by adding uniform and O&M Costs:

    $4372.42 + ($14.13/kW/yr * 27.1875 kW) = $4,756.58

    Size of the basin was assumed to be 1500m x 1500m x 6m.

    V = 13,500,000 m3

    A = 2,250,000 m2

    The channel has a length of 30m and width of 5m, having an area of 150 m2

    . This

    makes the velocity of fluid:

    vfluid ==

    *

    = 4.167 m/s

    Assuming the Alpha Team uses 50 turbines, each turbine will have a radius of :

  • 7/23/2019 Sustainable Design for Appledore Island

    24/35

    24

    Etotal= Ptotal*

    *

    652500 Wh = Ptotal*

    *

    Ptotal= 27,187.5 W

    Ptotal= nturbines* pturbines

    27,187.5 W = 50 turbine * pturbines

    pturbines = 543.75 W

    pturbines=* Atpv

    3 *efficiency

    543.75 W =

    r

    2

    (1027

    )(4.167)

    3

    (0.4)

    r = 0.108 m

    Biomass Energy

    The annualized costs were calculated as follows. First, the uniformed costs:

    Capital Cost = $4114/kW, Discount Rate = 0.05, Lifetime = 20 years

    ($4114*27.1875 kW)

    [

    .

    (+.)]= $8975.08

    Then the annualized costs were calculated by adding uniform and O&M Costs:

    $8975.08 + ($105.63/kW/yr * 27.1875 kW) = $11,846.90

    Wind Energy

    The annualized costs were calculated as follows. First, the uniformed costs:

    Capital Cost = $6230/kW, Discount Rate = 0.05, Lifetime = 30 years

    ($6230*27.1875 kW)[ .(+.)]= $11,018.29

    Then the annualized costs were calculated by adding uniform and O&M Costs:

    $11,018.29 + ($74.00/kW/yr * 27.1875 kW) = $13,030.17

  • 7/23/2019 Sustainable Design for Appledore Island

    25/35

    25

    Geothermal Energy

    The annualized costs were calculated as follows. First, the uniformed costs:

    Capital Cost = $6243/kW, Discount Rate = 0.05, Lifetime = 45 years

    ($6243*27.1875 kW)[ .(+.)]= $9549.39

    Then the annualized costs were calculated by adding uniform and O&M Costs:

    $9549.39 + ($132/kW/yr * 27.1875 kW) = $13,138.14

    Pressure of steam is calculated as stated:

    1 Kb *

    *

    = 100,000 kPa

    Appendix C

    Drinking Water Treatment Systems

    Chlorination

    The annualized cost for chlorine were calculated.

    Present cost * Chlorine (kg) = Annualized Cost

    $10/kg * 3.747 kg = $37.47

    Sizing for the contact tank was completed as follows:

    Residual Chlorine = 1.2 mg/L

    Concentration of E.Coli = 0.034 0.05 mg min/L

    Concentration of Girardia = 47 150 mg min/L

    Concentration = 150 mg/L = ConcC2 * time = ConcC2 * V/Q

    150 = 1.2 *

    .

    V = 275 gal or 1041 L

  • 7/23/2019 Sustainable Design for Appledore Island

    26/35

    26

    Slow Sand Filtration

    The annualized costs were calculated. First, the annualized costs for the system:

    Capital Cost = $100/m2, Discount Rate = 0.05, Lifetime = 15 years

    ($100*2.17 kW)[ .(+.)]= $20.91

    Uniformized Cost + O&M Cost = Annualized Cost

    $20.91 + $100.00 = $120.91

    Then the annualized cost for the sand:

    Capital Cost = $1/kg, Discount Rate = 0.05, Lifetime = 15 years

    ($1*7000 kg)[ .(+.)]= $674.40

    Uniformized Cost + O&M Cost = Annualized Cost

    $674.40 + $0.00 = $674.40

    Then the annualized cost for the contact tank:

    Capital Cost = $1/gal, Discount Rate = 0.05, Lifetime = 15 years

    ($1*275 gal)[ .(+.)]= $26.49

    Uniformized Cost + O&M Cost = Annualized Cost

    $26.49 + $0.00 = $26.49

    The annualized costs were calculated by adding chlorine, system, contact tank, and

    sand:

    $37.47 + $120.91 + $674.40 + $26.49 = $859.26

    The slow sand filter was sized as follows:

    Assuming flow rate (Q) = 1.168 gal/min because demand = needed flow rate

  • 7/23/2019 Sustainable Design for Appledore Island

    27/35

    27

    Assuming V = 0.05 gpm/ft2as average loading rate such peak loading rate does not

    exceed 0.1 gpm/ft2

    A =

    =

    .

    . = 23.36 ft2= 2.17 m2

    Amount of sand used:

    Assuming depth of sand is 4 feet:

    (23.36 ft2) * (4 ft) = 93.44 ft3

    93.44 ft3 *,.

    = 2.65 * 106cm3

    Density of Sand = 2.65 g/cm3

    Mass of Sand = 7000 kg

    Rapid Sand Filtration

    The annualized costs were calculated. First, the annualized costs for the system:

    Capital Cost = $100/m2, Discount Rate = 0.05, Lifetime = 20 years

    ($100*0.043 m2)

    [

    .

    (+.)]= $0.35

    Uniformized Cost + O&M Cost = Annualized Cost

    $0.35 + $500.00 = $500.35

    Then the annualized cost for the sand:

    Capital Cost = $1/kg, Discount Rate = 0.05, Lifetime = 20 years

    ($1*78.792 kg)[ .(+.)

    ]= $6.32

    Uniformized Cost + O&M Cost = Annualized Cost

    $6.32 + $0.00 = $6.32

    Then the annualized cost for backwashing:

  • 7/23/2019 Sustainable Design for Appledore Island

    28/35

    28

    Capital Cost = $4183/kW*70 GPD*0.05 kW/GPD = $14,640.5

    Discount Rate = 0.05, Lifetime = 20 years

    ($14640.5)[ .

    (+.)]= $1174.79

    Uniformized Cost + O&M Cost = Annualized Cost

    $1174.79 + $0.00 = $1174.79

    Then the annualized cost for the contact tank:

    Capital Cost = $1/gal, Discount Rate = 0.05, Lifetime = 20 years

    ($1*275 gal)[ .(+.)]= $22.07

    Uniformized Cost + O&M Cost = Annualized Cost

    $22.07 + $0.00 = $22.07

    The annualized costs were calculated by adding chlorine, system, contact tank, and

    sand:

    $37.47 + $500.35 + $6.32 + $1174.79 + $22.07= $1,740.99

    The rapid sand filter was sized as follows:

    A ==

    . .

    = 23.36 ft2= 2.17 m2

    Amount of sand used:

    Assuming depth of sand is 27, or 2.25 feet:

    Vsand= 1.05 ft3= 29,733 cm3

    Density of Sand = 2.65 g/cm3

    Mass of Sand = 78,792 g = 78.792 kg

    Solar Distillation

  • 7/23/2019 Sustainable Design for Appledore Island

    29/35

    29

    The annualized costs were calculated. First, the annualized costs for the system:

    Capital Cost = $0.35/m2, Discount Rate = 0.05, Lifetime = 10 years

    ($0.35*2592.5 m2)[ .

    (+.)]= $117.51

    Uniformized Cost + O&M Cost = Annualized Cost

    $117.51 + $500.00 = $617.51

    The size of the Solar Distillation system was determined as follows:

    A =.

    Q =.

    .

    = 6366.74 L/day

    E = 0.3

    G =.

    =

    A =. .

    ../

    = 2592.5 m2

    Appendix D

    Wastewater Treatment Systems

    Septic Tank

    The annualized cost of the septic tank was determined as follows:

    Capital Cost = $3.60/gal, Discount Rate = 0.05, Lifetime = 20 years

    ($3.60*2400 gal)[ .(+.)]= $693.30

    Uniformized Cost + O&M Cost = Annualized Cost

    $693.30 + $500 = $1193.30

    The size of the septic tank was determined as follows:

  • 7/23/2019 Sustainable Design for Appledore Island

    30/35

    30

    V =

    *

    =

    = 2400 gallons

    Composting Toilet

    The annualized cost of the composting toilet was determined as follows:

    Capital Cost = $3000/unit, Discount Rate = 0.05, Lifetime = 15 years

    ($3000*22 units)[ .(+.)]= $6358.59

    Uniformized Cost + O&M Cost = Annualized Cost

    $6358.59 + $350 = $6708.59

    The sizing of the toilets was completed as follows:

    500 L/year urine * 0.25 years = 125 L/summer urine / person

    50 L/year feces * 0.25 years = 12.5 L/ summer feces/person

    160 people live on island at peak time

    125 * 160 persons = 20,000 L urine

    12.5

    * 160 persons = 2,000 L feces

    Each toilet holds 1,100 L of waste, with 22,000 L of waste

    Thus number of toilets =,

    /= 22 toilets

    Combined System Constructed Wetland

    The annualized cost of the combined constructed wetland was determined as

    follows:

    Capital Cost = $0.72/ft3, Discount Rate = 0.05, Lifetime = 20 years

    ($0.72*3208.33 ft3)[ .(+.)]= $185.36

    Uniformized Cost + O&M Cost = Annualized Cost

  • 7/23/2019 Sustainable Design for Appledore Island

    31/35

    31

    $185.36 + $250 = $435.36

    The cost of the entire system is:

    $435.36 + $1193.30 = $1628.66

    Sizing for the wetlands were as follows:

    Hydraulic Retention Time = 10 days

    Flow rate from septic tank is 2400 gal

    HRT == 10 days =

    /

    V = 24,000 gal *.

    = 3208.33

    Separated System Constructed Wetland

    The annualized cost of the separate constructed wetland was determined as follows:

    Capital Cost = $0.72/ft3, Discount Rate = 0.05, Lifetime = 20 years

    ($0.72*2180 ft3)[ .(+.)]= $125.95

    Uniformized Cost + O&M Cost = Annualized Cost

    $125.95 + $250 = $375.95

    The cost of the entire system is:

    $375.95 + $6708.59 = $7084.54

    The sizing of the constructed wetland was completed as follows:

    Assuming flow rate (Q) = 1677 gallons/day

    Assuming Hydraulic Retention Time = 10 days

    HRT == 10 days =

    /

    V = 16770 gal *.

    = 2180

  • 7/23/2019 Sustainable Design for Appledore Island

    32/35

    32

    Combined System Leach Field

    The annualized cost of the combined leach field was determined as follows:

    Capital Cost = $0.70/ft2, Discount Rate = 0.05, Lifetime = 15 years

    ($0.70*4800 ft2)[ .(+.)]= $323.71

    Uniformized Cost + O&M Cost = Annualized Cost

    $323.71 + $300 = $623.71

    The cost of the entire system is:

    $623.71 + $1193.30 = $1817.01

    The sizing of the leach field was completed as follows:

    Appledore Percolation rate = 36.3 min/in

    Treatment Area = 2.00 ft2/gal/day

    .

    *

    = 4800

    Separate System Leach Field

    The annualized cost of the separate leach field was determined as follows:

    Capital Cost = $0.70/ft2, Discount Rate = 0.05, Lifetime = 15 years

    ($0.70*3554 ft2)[ .(+.)]= $239.68

    Uniformized Cost + O&M Cost = Annualized Cost

    $239.68 + $300 = $539.68

    The cost of the entire system is:

    $539.68 + $6708.59 = $7248.27

    Sizing of the leach field was completed as follows:

    Appledore Percolation rate = 36.3 min/in

  • 7/23/2019 Sustainable Design for Appledore Island

    33/35

    33

    Treatment Area = 2.00 ft2/gal/day

    Using Greywater Flow Rate of 1677 gal/day

    .

    *

    = 3554

    Rotating Biological Filter

    The annualized cost of the RBC media was determined as follows:

    Capital Cost = $2.85/ft2, Discount Rate = 0.05, Lifetime = 20 years

    ($2.85*7360 ft2)[ .(+.)]= $1683.17

    Uniformized Cost + O&M Cost = Annualized Cost

    $1683.17+ $1500 = $3183.17

    The annualized cost of the RBC tank was determined as follows:

    Capital Cost = $3.00/ft3, Discount Rate = 0.05, Lifetime = 20 years

    ($3.00*101.91 ft3)[ .(+.)]= $24.53

    Uniformized Cost + O&M Cost = Annualized Cost

    $24.53+ $1500 = $1524.53

    The cost of the entire system is the media, tank, and septic tank:

    $3183.17 + $1524.53 + $1193.30 = $5901.00

    Sizing of the media is as follows:

    BOD Removed = BOD5 * 0.5

    441 * 0.5 = 220.5

    220.5

    30

    = 190.5

    190.5

    *2400*3.785

    * 2.2046* 10

    -6

    = 3.8

  • 7/23/2019 Sustainable Design for Appledore Island

    34/35

    34

    3.8

    *

    .

    = 7360media

    Size of Tank was calculated as follows:

    Assuming media of 3ft radius disk, area = 28.27 ft2

    Area of a 12 ft radius disk = 113.097 ft2

    . .9= 0.25 ratio

    Therefore, to proportionally determine the surface area:

    104,000 ft2* 0.25 = 25,996.09 ft2

    Proportion of total SA to media area:

    ,99.9 = 3.532

    Shaft length can then be determined as :

    .= 7.078 ft

    Volume then is determined as:

    7.078 ft * 6 ft wide * 2.4 ft deep = 101.92 ft3

    Trickling Filter

    The annualized cost of the combined leach field was determined as follows:

    Capital Cost = $6500/m3, Discount Rate = 0.05, Lifetime = 20 years

    ($6500*1.817 m3)[ .(+.)]= $947.71

    Uniformized Cost + O&M Cost = Annualized Cost

    $947.71+ $1500 = $2447.71

    The cost of the entire system is:

    $2447.71+ $1193.30 = $3641.00

  • 7/23/2019 Sustainable Design for Appledore Island

    35/35

    35

    The sizing for the trickling filter is as follows:

    2400 gal/day = 9.085 m3/day

    Hydraulic Loading Rate =

    = 10

    =

    9.

    A = 0.9085 m2

    V = 0.9085 m2* 2m = 1.817 m3