suspended footbridge final design report tucuecito,...

29
Suspended Footbridge Final Design Report Tucuecito, Panama 2015 Penn State Student Chapter of Bridges to Prosperity 113 Hammond Building University Park, PA 16802 [email protected] Website: http://asce.pennstatebridgestoprosperity.org Primary Design Contact: [email protected]

Upload: hoangbao

Post on 04-Jun-2018

216 views

Category:

Documents


1 download

TRANSCRIPT

Suspended Footbridge Final Design Report

Tucuecito, Panama 2015

Penn State Student Chapter of Bridges to Prosperity

113 Hammond Building

University Park, PA 16802

[email protected]

Website: http://asce.pennstatebridgestoprosperity.org

Primary Design Contact: [email protected]

2

Table of Contents

1.0 INTRODUCTION................................................................................................................... 3

2.0 DESIGN OBJECTIVE ........................................................................................................... 3

3.0 SITE VISIT.............................................................................................................................. 4

3.1 Topographical Survey .......................................................................................................... 4

3.2 Potential Suppliers ................................................................................................................ 4

3.3 Community Interviews.......................................................................................................... 4

4.0 DESIGN CONSTRAINTS ..................................................................................................... 5

5.0 DESIGN PROCESS ................................................................................................................ 5

5.1 Loads ..................................................................................................................................... 6

5.2 Cable Selection and clamps .................................................................................................. 6

5.3 Anchor and Tower Selection ................................................................................................ 7

5.4 Additional Checks ................................................................................................................. 7

5.5 Suspender Design.................................................................................................................. 7

5.6 Wood Crossbeam and Decking Design ................................................................................ 7

Appendix A: Survey and Site Data ................................................................................................ 9

Appendix B: Calculations ............................................................................................................ 17

Appendix C: Design Calculation Tables ..................................................................................... 19

Appendix D: Site Specific Bridge Drawings ............................................................................... 23

3

1.0 INTRODUCTION

This report details the design rationale for the suspended footbridge to be constructed by Penn

State Bridges to Prosperity in the community of Tucuecito, Panama from May 13, 2015 to June

13, 2015. Site layout was approved for Tucuecito in December 2014. Four students traveled to

Tucuecito in June 2014 to interview community members on the need for a bridge and to gather

site data used to create the design of the suspended footbridge.

The community of Tucuecito is located over an hour drive north of Penonome – refer to App A,

Fig 1 and 2 for map of area. The Rio Tucue, located at the edge of Tucuecito, floods frequently

and isolates the community from healthcare, education and markets. The Rio Tucue is shown in

App A, Fig 3 as it runs by Tucuecito. The existing crossing point for the Rio Tucue is the road

leading from Tucuecito to Penonome that crosses the river on a concrete slab sitting on the river

bed. This crossing is the only entrance to the community and is shown in App A, Fig 4. During

normal river flow community members must walk through the water flowing over the concrete

slab, however the rainy season lasts from June to November when heavy rainfall increases the

depth and velocity of the water flow. The crossing point of the river usually takes two to three

hours maximum to flood but twice it has flooded in less than an hour. Flooding makes crossing,

particularly for children, dangerous, if not impossible.

The proposed footbridge will eliminate this problem, providing safe travel to healthcare,

education and food. The closest clinic to Tucuecito, the Centro de Salud de Tuabre, is a 2.5 hour

walk from the community. Several children from the community attend high school in Penonome

along with two students who attend college also in Penonome. The Tucuecito community has

three small stores but they only carry dry food. To get other types of food residents are required

to travel to Penonome over the river. The proposed bridge, designed by Penn State Bridges to

Prosperity, is in partnership with the non-profit organization Bridges to Prosperity (B2P). This

report details the bridge design process, as well as a structural design.

2.0 DESIGN OBJECTIVE

The objective is to design a constructible, durable, and safe pedestrian bridge to cross the Rio

Tucue in Tucuecito, Panama in accordance with the Bridges to Prosperity Suspended Bridge

Manual, 4th edition. The bridge will see pedestrian, animal and bicycle traffic. The Penn State

B2P Chapter proposes our design of a cable-supported, pedestrian bridge for Tucuecito to

eliminate the risks associated with flooding that prevent travel to school, health facilities, and

markets. The proposed bridge will be located 25 meters upstream from the existing crossing

point.

4

3.0 SITE VISIT

Penn State Bridges to Prosperity conducted a site inspection at Tucuecito in June 2014 to

accomplish several objectives:

Complete a topographical survey of the site

Coordinate and procure suppliers and materials for construction

Interview community members to determine if there is a need for a new bridge and to

discuss community participation in the construction of the proposed bridge

3.1 Topographical Survey

Penn State Bridges to Prosperity used an automatic level to survey the proposed site and create a

profile view along the center line of the bridge, shown in App A, Fig 5. The survey points from

the proposed bridge site are shown in App A, Table 1. The proposed bridge’s tower-to-tower

span is 29.9 meters. The high water level, determined by interviews with community members, is

approximately 2.9 meters below the calculated low point of the proposed bridge under full

deflection as shown in App A, Fig 6. The calculations that determined the tower-to-tower span

and freeboard can be found in Appendix B.

3.2 Potential Suppliers

As a gold level university project, Penn State Bridges to Prosperity is not responsible for

securing in-country supplies and construction materials. B2P Program Manager, Jake Moriarty,

will locate and procure all supplies and materials needed for the project. There is a road from

Penonome to Tucuecito that will allow supplies and materials to be transported to the bridge site

via vehicles.

3.3 Community Interviews

In addition to performing a topographical survey of Tucuecito, Penn State B2P members also

conducted a meeting with the community during the site trip. Members had the chance to

interview the president of the community during this meeting where she mentioned many times

that the flooding caused by the heavy rain blocked the only entrance into the community. Also,

the heavy rain can prevent community members from returning home because the flooding

blocks a section of the community. Due to these two blockages an internal and external bridge

were desired by the community. Many community members fear that one day someone will get

bitten by a poisonous snake and will not have access to proper medical care due to the

impassable river conditions. Also, previous floods have prevented food importation. During the

5

community meeting many men from the community were willing to put in the work for the

necessary external bridge.

4.0 DESIGN CONSTRAINTS

As stated in the Bridges to Prosperity design manual there are several design constraints that

require consideration during the beginning of the design process.

First, the bridge had to be designed near the existing crossing point of the river. This is to

accommodate the familiarity and function of the community with the existing crossing point. The

distance between the proposed bridge and the existing crossing point will be approximately 25

meters.

Second, the bridge had to be designed at a location where there will be sufficient freeboard but

that avoids trees and other obstacles when it comes time to start construction. The bridge has

been located to avoid as many trees and shrubs as possible in this heavily vegetated area (see

App A, Fig 7.)

Finally, the proposed bridge must be able to be constructed using predominantly local materials

and labor. Local materials are used to reduce the cost of transporting materials and allow for

easier accessibility of material. The bridge construction is designed to be built with minimal

skilled labor so we can rely on the community members to provide the majority of the labor

force. This not only helps control the cost of the bridge but also empowers the community

members, which is a goal of B2P.

5.0 DESIGN PROCESS

Throughout this report the standard B2P convention of standing downstream of the bridge and

looking upstream to determine left and right is used. This view with the proposed bridge

placement can be seen in App A, Fig 8. Using the data gathered from the survey a profile view

of the bridge was created, App A, Fig 5. The number of tiers was then calculated to achieve the

required freeboard (Appendix B.) The Cable Lookup Tool, App C, Table 1, was used to

calculate the size and number of cables required for the span. With the number of tiers

determined along with the span being set by the location of the abutments, the construction

drawings in Appendix D were chosen.

In the original survey the point marked for the left side abutment was located 2.0 meters

horizontally from the edge of the slope. The B2P manual specifies that abutments be located 3.0

meters from the edge of an exposed soil slope. For the bridge design to meet the given

6

constraints, the abutment was moved 1.0 meter farther south (away from the river bank) as

shown in App A, Fig 9. The slope between points J and K in App A, Fig 5 was calculated and

used to adjust the elevation of the new abutment point. The table of survey points, App A, Table

1, was then adjusted to show this change.

The layout of the road and approach wall also creates potential erosion issues with runoff, which.

There is a drainage ditch on the west side of the road by the left abutment, App A, Fig 10. The

ditch cuts away from the road to drain in the river at the proposed location of the approach wall.

This would cause water to flow against the stone approach wall and erode the soil under it

causing a possible collapse of the wall. Penn State Bridges to Prosperity’s solution to this is to

move the location of the drainage ditch as it cuts away from the road, as shown in App A, Fig

11. The new drainage ditch will cut away from road above the anchor to avoid the entire bridge.

The proximity of the approach wall to the road was a concern during site layout. From

discussions with the B2P in country manager it was determined not to be an issue because of the

driving style in Panama. Drivers are very careful not to damage their vehicles since they have to

pay for damages to company vehicles. Also the road does not see much traffic as it ends in

Tucuecito. The approach wall next to the road will be constructed with added width in the small

chance that a vehicle would collide with it.

The freeboard for the proposed bridge is slightly under the standard set by B2P. To increase the

freeboard the foundation of the left abutment will be raised so that 0.15 meters is exposed,

instead of leaving the top of the foundation level with the ground. This was discussed with B2P

during the first TAB call and Penn State Bridges to Prosperity was told the modification would

make the freeboard acceptable.

5.1 Loads

The Bridges to Prosperity manual requires the chapter to consider live loads, dead loads, and

wind loads acting on the bridge, App C, Table 2. The loads are taken from the B2P manual. The

dead load is 0.98 kN/m, the live load is 4.07 kN/m, and the wind load is 0.29 kN/m. The

controlling load combination is the dead load plus the live load plus the wind load, which gives a

distributed load of 5.34 kN/m.

5.2 Cable Selection and clamps

The cable that is available for this project is 1 1/8 in. diameter steel cable. The cable is repurposed

cable from shipping docks. Using the Bridges to Prosperity look-up tool, App C, Table 1, it was

determined that three walkway cables and two handrail cables are sufficient for a 29.9 meter

span. Using a breaking strength of 108,000 pounds and a factor of safety of 3, the maximum span

allowed for three walkway cables is 89 meters. Each cable will have a length of 68.6 meters. The

7

number of drop-forged clamps that will be used for each 1 1/8 inch diameter cable is 6. The

clamps should be spaced every 144 mm. The torque required to tighten these clamps is 225 foot

– lbs. Therefore, a total of 60 drop-forged clamps are needed for this project. All of this can be

seen in App C, Table 3.

5.3 Anchor and Tower Selection

The proposed anchors are located in soil, App A, Fig 12, therefore a gravity anchor is most

appropriate. The B2P manual is used to determine the appropriate anchor type. The span of the

proposed bridge is 29.9 meters. The left abutment was calculated to require three tiers so the left

anchor type will be a 3G60. The right abutment was calculated to require two tiers so the right

anchor type will be a 2G60. The number of tiers cannot be reduced based on the site layout. The

left side of the river is heavily wooded and moving the abutment farther from the bank to

increase the height, would require the removal of many trees. Survey data, App A, Table 1, was

also not recorded farther than the original anchor location, so moving the abutment back would

require an additional survey.

5.4 Additional Checks

The final difference in elevation between the two abutments is 0.36 meters, which is less than the

maximum height difference allowed by Bridges to Prosperity. The maximum height difference

allowed is 4% of the span length, which is 1.20 meters for a span of 29.9 meters. The design sag

was calculated to be 1.46 meters and the hoisting sag was 1.34 meters, shown in App C, Table

4. The proposed bridge is over a gorge, which requires a freeboard of 3.0 meters by Bridges to

Prosperity. The proposed design has a freeboard of 2.9 meters. It does not meet the requirements

in the B2P manual but was approved during TAB call #1.

5.5 Suspender Design

The suspenders were designed with a factor of safety of 5 to account for the multiple times the

rebar was likely to be bent. The suspenders are going to be attached to the crossbeams at an

interval of 1 meter, and #3 deformed bars will be used.

5.6 Wood Crossbeam and Decking Design

A width of 1.0 m was selected for the footbridge from the Bridges to Prosperity Design Manual.

The type of wood Penn State Bridges to Prosperity will have in Panama is currently unknown.

The length of the crossbeams will be 1.36 meters, and the decking boards will be 2 meters

staggered at 2 meters. In addition, a nailer with cross section dimensions of 4 cm by 18 cm will

8

be used.

A representation of all critical dimensions is provided in App C, Table 5.

9

Appendix A: Survey and Site Data

Table 1: Survey points from proposed bridge site in Tucuecito, Panama

Station Backsight Height of

Instrument Forsight

Elevation

(m)

Horizontal

Distance

(m)

Notes

A 1.09 101.09 100.00 0.0 Right Anchor

B 1.42 99.67 10.0 Front of Right Abutment

C 1.77 99.32 13.2

HWL 3.57 97.52 16.2 High Water Level

D 3.68 97.41 16.4

E 5.38 95.71 18.9

F 7.01 94.08 21.9 Existing Water Level

G 7.01 94.08 29.1 Existing Water Level

H 6.48 94.61 30.8

HWL 3.57 97.52 32.5 High Water Level

I 2.97 98.12 32.9 Edge of Cliff

J 2.93 98.16 35.9 Front of Left Abutment

K 2.67 98.42 42.9

L 1.70 99.39 45.9 Left Anchor

Date: June 15, 2014

Location: Tucuecito (Cocle, Panama)

Surveyors: Jen Kearney, Eric McCall, Steven Mezzacappa, Yulissa Guerrero

Contact: Jake Moriaty

Local government official: Julio, [email protected]

10

Figure 1: Map of Coclé, Panama showing location of Tucuecito and elevations.

Figure 2: Map showing distances between Tucuecito, Caimital, and Penonome.

11

Figure 3: Map of Proposed Bridge Location

Figure 4: View of existing crossing point from right side of river. Downstream of proposed

bridge.

12

Figure 5: Cross Section A-A of Proposed Pedestrian Bridge Location

Figure 6: Section A-A Elevation with design dimensions

Figure 7: View from Right Abutment location looking at Left Abutment location

13

Figure 8: View of existing ravine with proposed bridge placement. Picture is taken downstream

looking upstream.

Figure 9: View from Left Abutment location. Orange stakes are along centerline of proposed

bridge.

14

Figure 10: View of road leading out of Tucuecito. Location of Left Abutment and Anchor.

15

Figure 11: Site Map of Tucuecito, Panama, info collected on June 15, 2014.

16

Figure 12: View of Right Anchor location at orange stake. Taken at Right Abutment.

17

Appendix B: Calculations

Span = distance between cable resting points

= 25.9m + 4m

= 29.9m

Maximum height difference (ΔHmax) = Span/25

= 29.9m / 25

= 1.20m

Elevation between right abutment location and left abutment location (right anchor location

assumed to be 100m). Left foundation will be raised .15 meters above ground level to increase

freeboard.

Left abutment elevation = 98.16m + 0.15m = 98.31m

Right abutment elevation = 99.67m

Height difference (ΔH) = Right abutment elevation - left abutment elevation

= 99.67m - 98.31m

= 1.36m > ΔHmax

Left abutment requires one more tier than right abutment for height difference to be under

maximum allowable. Each tier is one meter in height.

Assume two tiers on right side and three on left side to achieve maximum freeboard.

Elevation of left tower walkway cable = elevation of foundation + height of tiers + height of

tower

= 98.31m + 3m + 0.4m

= 101.71m

Elevation of right tower walkway cable = elevation of foundation + height of tiers + height of

tower

= 99.67m + 2m + 0.4m

=102.07m

Height difference (ΔH) = 102.07m - 101.71m

= 0.36m < ΔHmax

Design Sag (hsag) = span×5%

= 29.9m×5%

= 1.5m

Low point (f) = (4×hsag - ΔH)2 / (16×hsag)

= (4×1.5m - 0.36m)2 / (16×1.5m)

= 1.33m (measured from low side)

18

High Water Level (HWL) = 97.52 m (from survey data)

Freeboard (Fb) = Low side elevation - f - HWL

= 101.71m - 1.33m - 97.52m

= 2.86m

Minimum Freeboard for gorges = 3m

Hoisting Sag = Span×4.6%

= 29.9×4.6%

= 1.38

Appendix C: Design Calculation Tables

Table 1: Cable Look-up Tool (Reference provided by Bridges to Properity)

DECK CABLES:

3 @ 108,000 pounds

HAND CABLES:

2 @ 108,000 pounds

TOTAL BREAKING FORCE = 540,000 pounds

MAXIMUM SPAN LENGTH FOR 540000 lb. CABLE CAPACITY (FS=3)

Deck Width: 100cm

Max Span: 89m

Sag (m): 4.45

Table 2: Design Loading

Assumed Material Unit Weights

Reference: Suspended Bridge Manual, 4th edition,

Volume 3 part 1.1

Steel 7850 kg/m3 = 76.9 kN/m3

Concrete 2400 kg/m3 = 23.5 kN/m3

Gabions 1900 kg/m3 = 18.6 kN/m3

Timber 900 kg/m3 = 8.8 kN/m3

General Soil 1800 kg/m3 = 17.6 kN/m3

Loads

DL 100 kg/m = 0.98 kN/m

LL 415 kg/m = 4.07 kN/m

WL 30 kg/m = 0.29 kN/m

Load Combinations

Application

DL+LL 515 kg/m = 5.05 kN/m Most components

DL+LL+WL 545 kg/m = 5.34 kN/m Loaded windguy design

DL+WL 130 kg/m = 1.27 kN/m Unloaded windguy design

Material Properties

Material

Strength

(MPa)

Strength

(ksi)

Concrete 10.3 1.5 Note: Strength if mixed by hand

Steel Pipe 240 35

Steel

Reinforcing 275 40

Timber 3.96 0.575

Soil 1.44 0.21

Table 3: Cable Quantities

Cable Quantities Cable Diameter 1 1/8"

Number of cables 5 dleft 10.6 m

dright 11.5 m

Length/Cable 68.6 m

Total Length 343 m

Clamps Spacing 144 mm

#/Cable 6 Total Number 60 Torque 225 foot*lbs.

Table 4: Additional checks for bridge clearance verification.

Site Input

Design Notes:

Horizontal Distance from Right Anchor

Front of Foundation on Left

Side 35.9 m

Design Manual: 4rd Edition of Suspended Bridge Manual

Front of Foundation on

Right Side 10 m

Horizontal Distance is assumed to be zero at right anchor

Vertical Elevations

Front of Foundation on Left

Side 98.16 m

Elevation assumed to be 100 m at the anchor location for the

left side Front of

Foundation on Right Side

99.67 m

High Water Level 97.52 m

Material Dimensions

Reference: Tower Height 1.4 m

Suspended Bridge Manual, 4th edition

Saddle Height 0.4 m

Volume 3.2

Tier Height 1 m

Foundation Height 1 m

Site Dimensions

Site Condition Gorge

Soil Conditions Soil

Span Length 29.90 m

OK *Note: Walkway saddle to walkway saddle span Initial Δh 1.51 m

Check for Δh < L/25 1.20 m

NG Part 1: 2.4 Number of Tiers on Left

Side 3

*Note: If NG, add tiers on either side to meet requirements

Number of Tiers on Right Side 2

Height of Left Abutment 5.4 m *Includes height of tower, tiers and foundation

Height of Right Abutment 4.4 m Elevation of Left Tower 102.71 m *0.15 meter of foundation exposed

Elevation of Right Tower 103.07 m Elevation of Left Walkway

Cable 101.71 m *0.15 meter of foundation exposed Elevation of Right Walkway

Cable 102.07 m Final Δh 0.36 m

OK Anchor Type Gravity

Bridge Clearance Verification

Low Elevation 101.71 m

Suspended Bridge Manual, 4th edition

High Water Level 97.52 m

Volume 3

Design Sag (Bd) 5

% of Span

Part 1: 2.4

Design Sag (hsag) 1.50 m

Hoisting Sag (Bh) 4.60

% of Span

Part 1: 2.4

Hoisting Sag (hsag) 1.38 m Design Sag Low Point (f) 1.32 m

Part 1: 2.4 Freeboard (fb) 2.9 m

Part 1: 2.4

Freeboard Limit 3 m

Part 1: 1.1 Freeboard Check 2.87 > 3 NG

Foundation Position Limits Minimum Distance from edge 3 m

OR Max degree slope 35 degrees

Table 5: Summary Table

Critical Dimensions

Span 29.9 m Deck Width 1.0 m Freeboard (fb) 2.9 m Design Sag (hsag) 1.50 m Hoisting Sag (hsag) 1.38 m Final Δh 0.36 m Depth to Anchor 0.7 m * Reference 2G60 drawing

Distance to back of left anchor 10.6 m

Distance to back of right anchor 11.5 m

Construction Drawings Reference: Suspended Bridge Manual, 4th edition, Volume 3 section 2.8

Right Side Anchor 2G60

Left Side Anchor 3G60 Tower T1 and TQ Decking Plan W31 Decking Section W32 Decking Detail W33

Appendix D: Site Specific Bridge Drawings

11

50

cm

10

60

cm