Building Surveying Case Study School Nursery Refurbishment & New Extension, Surrey Education, Sunbury, UK. Project Aims and Objectives: To refurbish the existing nursery and build a new extension, in order to provide a modern and challenging learning environment, required by the Department for Education and Skills (DfES). Project Based Building Surveying Services: 1. Pre-construction Phase Defined the Clients brief Led and managed the project team Production of architects drawing from the Construction Issue stage Planning and Building Control submissions Production of Specifications for all works Procurement of Contractors 2. Construction Phase Contract Administration Chairing Site Meetings Weekly structured site monitoring meetings Determining site instructions & variations Progress claims and financial control (Inc. variations) Snagging and granting Practical Completion 3. Post Construction Phase Settling the final financial account and ensuring the H&S File was produced. Establishing the 12 month defects liability period Accomplishments: As the works were undertaken during term time, I put controls in place which included banning noisy work during teaching time, deliveries were out of hours, site boundary being regularly checked and closed off, etc. Nursery – Pre Construction Phase Toilet & Shower Refurbishment New Ambulant Disabled WC Structurally Altered Refurbished Teaching Room New Extension and New Disabled Access

Upload: grahamelanders

Post on 06-Aug-2015

42 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Surrey education

Building Surveying Case Study

School Nursery Refurbishment & New Extension,

Surrey Education,

Sunbury, UK.

Project Aims and Objectives:

To refurbish the existing nursery and build a new extension, in order to provide a modern and challenging learning environment, required by the Department for Education and Skills (DfES).

Project Based Building Surveying Services:

1. Pre-construction Phase

• Defined the Clients brief

• Led and managed the project team

• Production of architects drawing from the Construction Issue stage

• Planning and Building Control submissions

• Production of Specifications for all works

• Procurement of Contractors

2. Construction Phase

• Contract Administration

• Chairing Site Meetings

• Weekly structured site monitoring meetings

• Determining site instructions & variations

• Progress claims and financial control (Inc. variations)

• Snagging and granting Practical Completion

3. Post Construction Phase

• Settling the final financial account and ensuring the H&S File was produced.

• Establishing the 12 month defects liability period

Accomplishments:

As the works were undertaken during term time, I put controls in place which included banning noisy work during teaching time, deliveries were out of hours, site boundary being regularly checked and closed off, etc.

Nursery – Pre Construction Phase

Toilet & Shower

Refurbishment

New Ambulant

Disabled WC

Structurally Altered

Refurbished Teaching Room

New Extension and New

Disabled Access

Page 2: Surrey education

Building Surveying Case StudyInfant School Refurbishment & New Extension,

Surrey Education,

Leigh, Mole Valley, UK.

Project Aims and Objectives:

To refurbish the existing and build a new extension, in order to provide a modern and challenging learning environment, required by the Department for Education and Skills (DfES).

Project Based Building Surveying Services:

1. Pre-construction Phase

• Defined the Clients brief

• Led and managed the project team

• Production of architects drawing from the Construction Issue stage

• Planning and Building Control submissions

• Production of Specifications for all works

• Procurement of Contractors

2. Construction Phase

• Contract Administration

• Chairing Site Meetings

• Weekly structured site monitoring meetings

• Determining site instructions & variations

• Progress claims and financial control (Inc. variations)

• Snagging and granting Practical Completion

3. Post Construction Phase

• Settling the final financial account and ensuring the H&S File was produced.

• Establishing the 12 month defects liability period

Accomplishments:

As the works were undertaken during term time, I put controls in place which included banning noisy work during teaching time, deliveries were out of hours, site boundary being regularly checked and closed off, etc.

Infant School - Front Elevation

Proposed Plan Showing Work Zones

Work Zone 1: New Build Office, Staff Room & Disabled WCWork Zone 2: Refurbished Toilet and LibraryWork Zone 3: New CloakroomsWork Zone 4: Refurbished Reception and Disabled Ramp AccessWork Zone 5: New Cupboards and Sink