supreme court of new south wales common law div …

74
1 SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV PROCEEDING MOORE v SCENIC TOURS PTY LTD (‘SCENIC’) PLAINTIFF’S FINAL SUBMISSIONS INDEX 1. OVERVIEW 3 2. LIABILITY ISSUES ASSOCIATED WITH CONSUMER GUARANTEES 4 2.1. Application of consumer guarantees 4 2.1.1. ‘Consumers’ 2.1.2. ‘Services’ 2.1.3. Reliance upon Scenic 2.1.4. Making known the desired purpose or result 2.1.5. Extra-territoriality 2.2. The experience on the cruises 9 2.2.1. What happened on each cruise? 2.2.2. What did Scenic know before embarkation? 2.2.3. How did Scenic respond? 2.2.4. How should Scenic have responded? 2.3. Non-compliance with consumer guarantee 41 2.3.1. The principles of the purpose guarantee 2.3.2. The principles of the result guarantee 2.3.3. The exceptions in s 61(3) of the ACL do not apply 2.3.4. Non-compliance with the purpose and result guarantee 2.3.5. The care and skill guarantee 2.3.6. Non-compliance with the care and skill guarantee 2.4. Exclusions and limitations on liability do not apply 47 2.4.1. The proper construction of the clauses 2.4.2. Section 64 of the ACL 2.4.3. Unconscionable conduct 2.4.4. Unjust terms 2.4.5. Unfair terms 2.4.6. Remedies for unconscionable conduct and unfair terms

Upload: others

Post on 02-Oct-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

1

SUPREME COURT OF NEW SOUTH WALES

COMMON LAW DIV PROCEEDING

MOORE v SCENIC TOURS PTY LTD (‘SCENIC’)

PLAINTIFF’S FINAL SUBMISSIONS

INDEX

1. OVERVIEW 3

2. LIABILITY ISSUES ASSOCIATED WITH CONSUMER GUARANTEES 4

2.1. Application of consumer guarantees 4

2.1.1. ‘Consumers’

2.1.2. ‘Services’

2.1.3. Reliance upon Scenic

2.1.4. Making known the desired purpose or result

2.1.5. Extra-territoriality

2.2. The experience on the cruises 9

2.2.1. What happened on each cruise?

2.2.2. What did Scenic know before embarkation?

2.2.3. How did Scenic respond?

2.2.4. How should Scenic have responded?

2.3. Non-compliance with consumer guarantee 41

2.3.1. The principles of the purpose guarantee

2.3.2. The principles of the result guarantee

2.3.3. The exceptions in s 61(3) of the ACL do not apply

2.3.4. Non-compliance with the purpose and result guarantee

2.3.5. The care and skill guarantee

2.3.6. Non-compliance with the care and skill guarantee

2.4. Exclusions and limitations on liability do not apply 47

2.4.1. The proper construction of the clauses

2.4.2. Section 64 of the ACL

2.4.3. Unconscionable conduct

2.4.4. Unjust terms

2.4.5. Unfair terms

2.4.6. Remedies for unconscionable conduct and unfair terms

Page 2: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

2

2.5. Responsibility for loss 58

2.5.1. Scenic’s service providers

2.5.2. The exceptions in s 267(1)(c) of the ACL do not apply

2.6. Loss arising from non-compliance with consumer guarantees 62

2.6.1. Causation

2.6.2. Non-compliance could not be remedied

2.6.3. ‘Major’ failure to comply

3. QUANTUM OF DAMAGES 67

3.1. Heads of damages 67

3.1.1. Meaning of ‘foreseeable loss

3.1.2. Availability of damages for disappointment and distress

3.2. Methodology of loss of value 69

3.2.1. Background to admissions

3.2.2. Admissions as to how defendant calculated loss of value

3.3. Amount 72

3.3.1. Section 267(3)

3.3.2. Section 267(4)

4. RESTITUTIONARY ACTION FOR MONEY HAD & RECEIVED 73

4.1. Basis for recovery 73

Page 3: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

3

1. OVERVIEW

1. In its short opening written submissions dated 20 April 2016, the plaintiff set out its

position in respect to each of the identified common issues. Without repeating that

statement, those answers are also adopted in this document.

2. For the reasons that follow, the pivotal findings on liability that should be made are as

follows.

3. First, the plaintiff and group members made known to the defendant that the

recreational experience that they sought was a tour, by cruise, along European waters.

This experience included, along the way, the enjoyment of certain landmarks as well as

luxurious dining and accommodation centred on the cruise ship.

4. Secondly, albeit in varying degrees, the plaintiff and group members experienced

significant or substantial disruption to their tour by cruise.

5. Thirdly, in respect to all subject cruises, the defendant knew, or ought to have known,

that there was a significant risk of substantial disruption to the cruising component of

the tour.

6. Fourthly, properly construed, Scenic’s terms and conditions did not entitle Scenic to

unilaterally (and without any liability) substitute a different touring experience where

that would substantially diminish or negate the purpose or result which the plaintiff and

group members sought when acquiring Scenic’s services.

7. Fifthly, and alternatively to the last proposition, if Scenic’s terms and conditions did

have that effect, and the terms were not otherwise avoided by s 64 of the Australian

Consumer Law, then such terms would be unjust and/or unfair.

8. Sixthly, the consumer guarantees in ss 60 and/or 61(1) and (2) of the Australian

Consumer Law were not complied with by Scenic.

9. Seventhly, Scenic’s retention of the full purchase price paid for by passengers who

received a substantially downgraded or diminished touring experience constitutes

unconscionable conduct in circumstances where: (a) Scenic knew that its passengers

wished to enjoy a luxurious cruise experience; (b) Scenic knew, or ought to have

known, that there was a significant risk of substantial disruption to the cruising

component of the tour; and (b) passengers had no understanding (and Scenic took no

steps to see that they understood) that the application of Scenic’s terms and conditions

would permit such retention even in the face of that knowledge.

Page 4: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

4

2. LIABILITY ISSUES ASSOCIATED WITH CONSUMER GUARANTEES

2.1. Application of consumer guarantees

10. The consumer guarantees under the Schedule 2 of the Competition and Consumer Act 2010

(Cth) (the ‘ACL’) are not contractual obligations, but obligations imposed by statute,

concerning which s 267 provides a statutory remedy2.

2.1.1 ‘Consumers’

11. This is relevantly defined in s 3(3) of ACL, where:

a. The amount paid for the services does not exceed $40,000; or

b. The services were of a kind ordinarily acquired for personal, domestic, or

household use or consumption

12. By s 3(10), a rebuttable presumption applies that a person who acquires services alleges

that he or she is a consumer.

13. Although the matter was left in issue in the Defence, there is no serious suggestion that

Mr Moore is anything other than a ‘consumer’ for the purposes of the ACL.

2.1.2 ‘Services’

14. The word ‘Services’ is defined in the ACL in s 2 to include:

(a) any rights, benefits, privileges …. to be provided, granted or conferred in trade or

commerce;

(b) (without limiting (a)), the rights, benefits, privileges that are, or are to be

provided, granted or conferred under:

….

(ii) a contract for or in relation to the provision of, or the use or enjoyment

of … recreation..

It is noted that by this definition, ‘services’ need not be actually supplied pursuant to a contract.

This takes on some significance when considering the defendant’s argument concerning s 275 of

the Australian Consumer Law (see section 3.1.2 of these submissions below).

15. Scenic broadly functioned as a tour operator. It agreed to provide recreational services

to the plaintiff and group members by dint of a tour, by cruise (and associated luxurious

accommodation and dining), along European rivers, stopping at certain destinations.

The character of the services supplied is disputed, not the least in the sense of

identifying when the services ceased to be supplied.

2 Alameddine v Glenworth Valley Horse Riding Pty Ltd [2015] NSWCA 219 at [77]

Page 5: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

5

16. Scenic initially appeared to contend (pars 4(b) & (d) of the Defence) that the services

ceased after the bookings were made by the passengers; that its role was simply to

“arrange” the tour. Such contention would be wrong, in that Scenic’s functions

included, but was not limited to, helping to arrange the tour bookings. Scenic’s initial

contention is contrary to the content of the powers that were exercisable by Scenic in

accordance with the Terms and Conditions3. Clauses 2.9 and 2.10 deal (respectively)

with the circumstances in which the tours could be cancelled or delayed after bookings

had been received, but prior to the embarkation of cruises. Moreover, to adopt the

extremely narrow construction that Scenic’s services ceased after the passengers had

made their bookings would relegate Scenic to a position that it was no different in

substance to the other intermediaries (eg travel agents, like Harvey Bay Travel) who

assisted passengers to book and pay for the tours

17. The defendant’s short outline of submissions revealed some shift: Scenic’s position was

now that the only services that it was required to perform were during the tour. In this,

Scenic relies upon Clause 2.7 of the terms and condition, which plainly indicates, by its

terms, that Scenic’s obligations extend beyond the point when the tour was booked.

But this position is also an incomplete expression of Scenic’s obligations. Clause 2.7 is

titled what are Scenic’s “Tour” obligations. It is not a statement that expressly or

impliedly limits the services that Scenic was required to perform before the tour

commenced. As has been noted, cll 2.9 and 2.10 are indicative of obligations to

perform prior to the embarkation of a cruise.

18. The contractual provisions setting out Scenic’s powers under the terms and conditions

evince a monitoring role for Scenic; of determining, for example, whether or not a

cruise could proceed at all (cll 2.9-2.10). It also had a role in managing passengers: for

example, explaining why there needed to be variations, or, indeed, why there needed to

be cancellations or delay of cruises, and generally adjusting passengers’ expectations.

Thus, Scenic had staff who, the night before an embarkation, gathered a group together

to explain changes to itineraries4. In several instances, Scenic sent out letters to

passengers on the eve of a scheduled departure, notifying them of changes of itinerary

and, even, changes of the booked ship. Given the nature of the particular recreational

experience: cruising along European waters, it is natural that the tour operator’s services

extend to dealing with the exigencies of cruise travel.

19. Scenic contends that clause 2.7 has the effect that Scenic was entitled to merely supply

the cruise where it could, if river conditions allowed it, but if that did not occur, its

obligation was merely to provide the best alternative tour to provide as many of the

tourist attractions in the itinerary as possible. This is a flawed conception of Scenic’s

obligations and the services it was required to provide. Firstly, the ‘terms and

conditions’ are not to be viewed in a vacuum, but in a context (known to passenger and

tour operator alike) which included both: (a) the representations made by Scenic as to

benefits (luxurious and relaxing cruise travel, ‘five star’ accommodation and dining)

3 These appear at Ex P8 (CB 4/1235) for Scenic Tours and P9 (Ex CB4/1343) for Evergreen Tours. Although there are some differences, these are insubstantial in the context of the issues in this proceeding. Henceforth reference will be made to the Scenic terms and conditions. 4 For example, see Moore, par 23 (CB 3/550)

Page 6: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

6

promoted in the travel brochure (in which the terms and conditions appear) as well as

(b) the backdrop of consumer guarantees applicable to the services5. At the time these

services were performed, Scenic’s obligations under the contract were affected by

statute6, even if the statutory obligations were not part of the contract. These consumer

guarantees cannot be effectively ousted by the contractual terms (s 64 of the ACL). Put

another way, one would not construe cl 2.7 in a way that its application would be

avoided by the statute.

20. Further, the scope of the obligations does not depend entirely upon Scenic’s subjective

perception as to how it should respond. Clause 2.7 speaks ultimately of “appropriate”

alternatives. What is ‘appropriate’ in this context includes consideration of whether the

alternative/s being considered by Scenic are reasonably fit for the purpose for which

they are conferred: or put another way, whether they would amount to compliance with

Scenic’s statutory obligations in ss 61(1) and (2) of the ACL. It is not simply a case of

what Scenic subjectively regards as ‘appropriate’. Thus to take the example of one of

the hypotheticals put to Mr Cairncross7, it may well have been appropriate for Scenic to

decide that, in the event that one of its cruises had enjoyed smooth sailing for a period

of a few days, until it suddenly came up against an unexpected lock closure, to utilise (if

it could), disembarkation to a nearby port, use of a bus to transport passengers to

another ship on the other side of the river; with the obstacle overcome in a matter of

hours. It is another thing, however, when the tour operator has notice of multiple

closures along a river, or rivers, along a cruise path and the obstacles presented to its

ships that had previously embarked, to take the unilateral decision to regularly bus

passengers to landmark excursions ashore over a substantial number of days in the

belief that it was doing its best to adhere to a passenger’s itinerary.

21. The unreasonable, if not absurd, result of Scenic’s interpretation of its obligations was

brought into sharp focus when its Senior Counsel, in response to a question from the

Court, argued that the terms and conditions were such that, if faced with the

hypothetical situation that no part of the tour could be conducted by cruise (because of

river conditions), Scenic could substitute coach travel in its entirety8. This, of course,

would be a complete negation of the purpose and result guarantees and the benefits

held out in the tour brochure. So, a litmus test for compliance with cl 2.7 should be that

a discretion upon Scenic is not properly exercised to such extent that the proposed

‘alternative’ to be taken would have the effect of substantially diminishing the result or

purpose of the services to be provided.

22. Scenic also contended that it had no obligation to cancel (or delay) a tour after

embarkation. Whilst it is true that there is no express provision to that effect, the more

relevant point is that there is no express provision which would fetter Scenic’s ability to

cancel a cruise after embarkation. In this, apparently, Scenic reads down cl 2.7, due to

5 The existence of the consumer guarantees is implicitly acknowledged in cl 2.15 of Scenic’s terms and conditions (CB 4/1235) 6 For a recent illustration of contracts being construed against a backdrop of statutory provisions, see Victoria v Tatts Group Ltd (2016) 90 ALJR 392; [2016] HCA 5 7 T 117 8 T 37.42

Page 7: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

7

circumstances outside of its control, which substitutes a promise to exercise reasonable

endeavours to “provide or arrange appropriate alternatives” where Scenic was unable to

provide the tour in accordance with a passenger’s itinerary. But neither the text, nor

context, indicates that the expression ‘appropriate alternatives’ is to be narrowly

construed. Where it became apparent that a cruise which had already embarked was, or

would continue to be substantially disrupted, cl 2.7 was broad enough to indicate that

Scenic had it within its power to cancel the tour and offer refunds9, or future credits to

further cruises at a later point in time. At any rate, cl 2.7 cannot overcome the content

of the statutory guarantees in s 61 and allow a tour operator to effect whatever

alternative it subjectively deems to be appropriate if that alternative does not comply

with the requirements of the statute.

23. In summary, Scenic agreed to supply services in the provision of recreation, by river

cruise along European rivers. This required it to assist with arrangements for the

bookings and, up to and beyond the point of embarkation, to continue to monitor

whether passengers were likely to experience, were experiencing, and were likely to

continue to experience, a relaxing recreational experience by cruise. Where it became

apparent that this was not likely to occur, or was not occurring, it was required to

properly manage the situation for its passengers, such as by putting in place alternative

arrangements, even if that meant that the recreational experience was to be deferred

until a later point than that which had been originally scheduled; or, at least, ensure

passengers’ would receive the money’s worth for what they had lost.

24. These services were provided in trade and commerce: they were integral to Scenic’s

commercial operations.

2.1.3 Reliance upon Scenic

25. Section 61(3) of the ACL effectively creates a (rebuttable) presumption that the

purpose and result guarantees apply unless a consumer did not rely upon the supplier’s

skill or judgment or it was unreasonable for the consumer to so rely upon the supplier’s

skill or judgment11.

26. Following the defendant’s late amendments to its Defence12, which puts reliance in

issue, the Court is no longer in a position to decide whether the presumption is

rebutted in the case of each and every group member; although it can decide whether it

was rebutted in the instance of the plaintiff and in the circumstances of the group

members called to give evidence.

27. It was not put to the plaintiff, or any of the other group members (nor, of course, Mr

Childs) who gave evidence, that they did not rely upon Scenic’s exercise of judgment. It

follows that the presumption of reliance was not rebutted in any of their cases.

9 Ex P24 (CB 5/1776, 1777); Ex P38 (CB 6/1958) 11 This exception does not apply to the care and skill guarantee in s 60 of the ACL. The current position reflects what occurred under the former Trade Practices Act 1974 (Cth) where the implied warranties concerning purpose and result in s 74(2) were subject to the exception but the implied warranty in s 74(1) was not. 12 Pars 13(c) & 14(c)

Page 8: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

8

28. As an objective matter and, in view of the circumstance that the passengers only had

contractual arrangements with the defendant, and that those arrangements envisaged

the monitoring and management functions referred to above (including by the cruise

director on the ship – an employee of the defendant), it is difficult to conceive that the

passengers would not rely upon Scenic to make decisions, in particular, as to whether

cruises should proceed at all, or if disrupted, what should thereafter occur.

29. Noting the specific denial of actual reliance in Scenic’s Defence (as amended), there is

no suggestion in the pleading that it was unreasonable for the plaintiff or other group

members to rely upon the defendant’s skill and judgment if, in fact, he or they did so

rely.

2.1.4 Making known the desired purpose or result

30. Mr Moore (and each other group member) impliedly made known that the particular

purpose and/or result they hoped to achieve in acquiring Scenic’s services was a

relaxing experience, derived from a tour by cruise (with associated luxurious dining and

accommodation facilities) to certain identified European destinations (identified with

reference to certain landmarks). The implication arises from the fact of acquisition, as

well as the defendant’s own description of what is acquired13. In this context, the

brochures that passengers relied upon in deciding to make the tours depicted a relaxing

holiday by cruise and other services on board (viz accommodation and dining).

Passengers did not pay for a tour to the European destinations by other means (train or

coach)14.

31. Scenic Tours (Evergreen) admit that they knew of the wish of the plaintiff and group

members to experience travel and accommodation by cruise15. It could hardly contend

otherwise, given its promotional brochure which extolled tour with these benefits.

2.1.5 Extra-territoriality

32. By s 32(1) of the Fair Trading Act 1987 (NSW), the ACL applies to persons16 carrying

on business within NSW, or bodies corporate incorporated or registered under NSW

law.

33. The facts that Scenic carried on business within NSW and was incorporated or

registered under NSW law are deemed to have been admitted as a result of Scenic’s

failure to dispute the facts asserted in the plaintiff’s notice to admit17.

13 Dillon v Baltic Shipping Co (1989) 21 NSWLR 614 at 642A; see also Taperell, Vermeesch & Harland, Trade Practices and Consumer Protection (3rd ed, 1983) [1732], p 829, with reference to the old s 71(2) of the Trade Practices Act 1974 (Cth) 14 Ex P8-9 15 Defence filed 16 December 2015, par 7(b), 8(a) 16 Which also means corporations: Interpretation Act 1987, ss 8(d), (e) 17 CB 1/114-115

Page 9: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

9

34. At any rate, the ACL extends to conduct (and other things) occurring or existing

outside or partly outside NSW: Fair Trading Act 1987 (NSW), s 32(2) & s 5A. In this

case, certain services were to be performed outside of New South Wales.

2.2 The experience on the cruises

2.2.1 What happened on each cruise?

35. The evidence relied upon by the plaintiff is generally an amalgam of two things: first,

indications (based upon the defendant’s internal email correspondence and the cruise

directors’ tour notes) as to what was lost, primarily, in sailing days on the subject

cruises. There is a caveat to the reliance that the Court should place on the tour notes.

They were plainly inserted by the cruise directors, however it is not always (or even

often) apparent what the source of the information was. Without it, the chronicle is

limited in terms of its reliability as a statement of fact. Sometimes what is expressed

amounts to bare opinion, such the opinion that an event is ‘unexpected’ or had

occurred ‘suddenly’. This type of evidence is inherently self-serving – cruise directors

have a natural sympathy towards their employer - and should be accorded no weight

unless the basis for the opinion is identified: there is no indication anywhere in the tour

notes of the qualifications or level of experience of the cruise director to make such

opinion. Further, at least one instance, there was an occasion where lines of

communication were blurred: where there was an inconsistency between what a cruise

director had said and what Lucas Sandmeier had reported18.

36. Scenic could have called the real decision-makers – Messrs Brown and/or Moroney – if

it wanted to put some explanation for the decisions that were taken; in preference to

hiding behind the unsourced opinions of its cruise directors. For its own unexplained

reasons it did not do so. The real probative value of the tour notes from the cruise

directors is where they contain admissions.

37. Secondly, there is testimonial evidence of group members on some of the cruises which

delineates the natural consequences, or ramifications of the lost cruising days. This

essentially consists of bus coaches to land excursions and the use of hotel

accommodation on-shore. The Court is invited to infer that the experience of these

sample group members (which is broadly similar) would have also broadly been the

experience of group members on other cruises, to the extent that those cruises also had

a diminished number of sailing days.

The days for which there were ‘alterations’ or ‘variations’

38. The defendant’s documents indicate its own internal assessment of the ‘days lost’ due

to the river levels and conditions. The references in the table below are (generally) tour

itinerary variations prepared by the defendant.

18 Ex P25 (CB 5/1794)

Page 10: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

10

Cruise Ship scheduled to embark

Ship which actually embarked

Days lost

Reference

FRCR190513.1 Scenic Emerald Scenic Emerald 10 Ex P RB-119

STC200513.2 Scenic Jewel Scenic Ruby 6 Ex P27

EGFC250513.1 Amadeus Silver Amadeus Silver 9 Ex P5320

STC270513.1 Scenic Ruby Scenic Jewel 11 CB 2/415-41621 & Ex P5922

STC270513.2 Scenic Sapphire Scenic Sapphire 9 Ex P5523

STC290513.1 Scenic Pearl Scenic Pearl 11 Ex P5524

STC290513.2 Scenic Diamond Scenic Diamond 8 Ex P5725

STC030613.1 Scenic Jewel Scenic Ruby 10 Ex P5526 Ex P DM-127

EGFC080613.1 Amadeus Silver Amadeus Brilliant 8 Ex P6028

STC100613.1 Scenic Sapphire Scenic Diamond 1 Ex D7129

STC100613.2 Scenic Ruby Scenic Sapphire 6 CB 3/531-54130

STC120613.1 Scenic Pearl Scenic Ruby 1 Ex D5431

STC120613.2 Scenic Diamond Scenic Pearl 2 Ex P4332

39. The table also reveals that a measure of the defendant’s internal dislocation arising from

the conditions was that for most of these cruises, the defendant substituted a different

vessel, the so-called ‘ship swap’. Whatever the merits of this option for some

passengers, for those who had certain physical incapacities, and valued a cruise tour

partly for the benefit of leaving luggage in one place for an extended period, this was

not especially appealing, even if they put up with it.

40. More detailed descriptions of the disruption to cruise scheduling, both documentary

and testimonial, in respect to specific cruises, follows.

FRCR190513.1

41. On 20 May 2013, Ms Yyvonne de Sera, the tour director, recorded informing

passengers about the water situation and reported being informed by the ship’s captain

19 CB 2/499-501 20 Ex P53 (CB 6/2127-2128) 21 Part of Annex B to Holgye, 11/5/15 22 Ex P59 (CB 6/2255-2256) 23 Ex 955 (CB 6/2157-2158) 24 Ex P55 (CB 6/2149-2151) 25 Ex P57 (CB 6/2182-2183) 26 Ex P55 (CB 6/2152-2153) 27 CB 3/813-814 28 Ex P60 (CB 7/2853-2855) 29 Ex D71 30 This is Annex K to Peattie, 15/5/15 31 Ex D54 (CB 6/2093-2098) 32 Ex P43 (CB 6/1989A)

Page 11: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

11

that due to high water levels, the dock in Tournus was under water and, accordingly,

the ship would sail directly to Macon33. This occurred before the embarkation of the

cruise. It was noted that embarkation occurred whilst the ship was docked in an ugly

industrial harbour 34.

42. The First Captain of the Emerald reported that from 22 to 30 May 2013, the ship was

forced to stay in the Saone area during this period due to high water35.

43. A document discovered by Scenic indicated that there was an estimated increase of bus

travel of nearly 11 hours for this cruise beyond what was scheduled36.

44. Mr Britten gave evidence of his experience on the tour that commenced on 19 May

2013, featuring a cruise along the ‘South of France’ route. By the schedule the cruise

was scheduled to embark at Chalon-sur-Saone and disembarked at Tarascon/Avignon.

45. On the night of 19 May 2013, Mr Britten recalls that Scenic’s cruise director, Yvonne,

spoke of Scenic having experienced difficulties due to the weather.

46. On 20 May 2013, Mr Britten and his wife travelled to Paris in heavy rains, when they

boarded a train for a day journey to Dijon. After lunch, they took a coach from Dijon

to Chalon-sur-Saone, to take them to the dock for boarding.

47. On 21 May 2013 some land excursions were enjoyed, but the cruise did not proceed, as

was scheduled, to Tournus37.

48. Some land excursions (by bus) were experienced on 22 May 2013, before the ship

travelled to Macon.

49. On 23 May 2013, the ship was scheduled proceed to cruise down the Rhone River near

Macon39. No sailing occurred on 23 May 201340.

50. Between 24 and 26 May 2013, Mr Britten experienced further land excursions which

involved significant time on coaches41.

51. Later on 26 May 2013, Mr Britten recalled being informed by the cruise director that

passengers would need to pack their bags to leave the Emerald and travel to another

vessel moored down the river42.

33 Ex P13 (CB 5/1601) 34 Ibid 35 Ex P17 (CB 5/1739) 36 Ex P35 (CB 6/1935) 37 Britten, pars 24-26; (CB 2/424) 39 Britten, pars 33-34; (CB 2/424) 40 Britten, par 34 41 Britten, pars 37-58; (CB2/425-427) 42 Britten, pars 59-60; (CB 2/427-428)

Page 12: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

12

52. On 27 May 2013, Mr Britten recalled trips to Valance and Arch by coach travel. He

estimated that 10 hours were spent by coach travel43.

53. There were further land excursions between 28 and 30 May 201344, which again

featured extensive coach travel, until the ship commenced cruising in the evening. This

was the second day of cruising over the previous 10 days45.

54. The next day Mr Britten and his wife were looking forward to the scheduled trip to the

La Camargue National Park however, once informed of the extent of the bus travel to

and from that destination, and having regard to the extent of coach travel already

endured, they declined to go46.

55. Soon after his return home, Mr Britten prepared a detailed factual summary of his

experience47. The document chronicled his experience of extensive and uncomfortable

bus travel and perception of sub-standard hotel accommodation. Eventually, Mr Britten

listed his complaints in correspondence with Scenic on 24 July 201348.

56. Scenic identified variations to all but 3 of the scheduled 14 days49. Those variations

repeatedly listed coach excursions and accommodation in hotels.

57. It was put to Mr Britten, somewhat vaguely, that Scenic representatives had explained

to passengers that the cruise was being disrupted because of “sudden” and

“unexpected” events along the river system50. No evidence was adduced by Scenic to

provide any basis for the proposition that the events were sudden or unexpected.

STC2001513.2

58. This is the first of the 12 Jewel of Europe cruises, along the Budapest to Amsterdam

cruise path.

59. The plaintiff accepts that notes prepared by the cruise directors on the Scenic and

Evergreen cruises embarking on 11 May 2013 (from Budapest), on 13 May 2013(in

both directions) and 15 May 2013 (in both directions) indicated that those cruises had

proceeded without alternation.

60. On 26 May 2013, Patrick Doyle, the cruise director, recorded that River Main was

closed, with high water threatening the program. Already a tour was cut short because

43 Britten, pars 62-71; (CB 2/428-429) 44 Britten, pars 72-94; (CB 2/429-431) 45 Britten, par 95 46 Britten, pars 97-100 47 Britten, pars 104-105; (CB 2/485-488) 48 Ex P RB1 (CB 2/502-504) 49 Ex P RB1 (CB 2/500-501) 50 T 151.31

Page 13: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

13

of a “high water issue”51. The cruise director notified Lucas Sandmeier that according to

the ship’s captain there was no chance for the ship to move with water level rising52.

61. The next day, Doyle also noted that the cruise was being weather affected.53 Although

cruising from the opposite direction (from Amsterdam), it is pertinent to note that on

27 May 2013, Marin Dimow recorded a variation for that cruise, as a result of rising

river levels on the Danube54.

62. Between 28 and 31 May 2013, there were partial, if not complete closures on the Main

River, at Steinbach, Wurzburg and Schweinfurt55. The ship was still stuck in Bamberg.

EGFC250513.1

63. This ship, the MS Amadeus Silver, embarked (from Amsterdam) on 25 May 2013.

64. By 28 May 2013, tour notes for the cruise indicated that due to high water at a bridge

after Frankfurt, the ship was about to stop sailing58.

65. On 29 May 2013, by 8pm, Wurzburg was closed due to high water and the Captain of

the ship decided to dock the ship at Neustadt60.

66. On 30 May 2013, Alexandra Graeff reported that the water level on the Main had

increased again since yesterday. The ship was on its way to Wurzburg, but it was not

clear if it could be reached. On a worst case scenario (advised to it by Luftner), the ship

could be stuck in Wurzburg until Tuesday, 4 June 2013, as it would not be able to pass

the bridges.

67. By 31 May 2013, the ship was stuck just before Wurzburg – it could not pass the last

bridge63.

68. On 1 June 2013, a 2 hour drive to ‘Nurnberg’ was offered to passengers. It was raining

all the time64.

69. On 2 June 2013, a bus trip was provided to Salzburg. The longest route had to be taken

for one of the buses because it was the only one not under water65. The cruise director

recorded seeing flooded fields, forests in a pool and houses in the middle of lakes66.

51 Ex P27 (CB 5/1816) 52 Ex D16 (CB 5/1632) 53 Ex P27 (CB 5/1816) 54 Ex D29 (CB 5/1809) 55 Ex P52 (CB 6/ 2109) 58 Ex D66 60 Ex D66 63 Ex D66 64 Ex D66 65 Ibid. 66 Ibid.

Page 14: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

14

70. On 4 June 2013, the cruise director arranged a land based excursion to the abbey at

Melk, however observed that a lot of guests should not be on a bus tour and some

should not be on walking tours67. By the next day, 5 June 2013, many guests on this

cruise were reported as getting really sick68.

71. As at 6 June 2013, the high water levels on the river Main and localised flooding had

made navigation impossible for the ship69.

STC270513.1

72. Mr Holgye and Mr Cairncross gave evidence in respect to this cruise, scheduled to

embark on Scenic Ruby on 27 May 2013 at Amsterdam. This cruise proceeded without

disruption until 30 May 2013.

73. Mr Holgye recalled70 that on 28 May 2013, as the ship was sailing from Amsterdam to

Dusseldorf, he observed large, mature trees growing out of the water: a tell-tale sign of

rising river levels. On the same day, he recalled a conversation with the ship’s cruise

director, Kurt, in which he wanted to take up the offer to sit in the wheel house with

the captain. He was told by Kurt that this was not possible because the ship’s captain

was dealing with very strong currents and the rising water levels. Kurt later referred to

rising river levels in the presence of the ship’s company later that evening. In answer to

this indication, one passenger sought assurance that the rising river levels would not

mean a “glorified bus tour” with the cruise director saying “definitely not. We just need

to make some adjustments”71. Mr Holgye was not challenged on the content of this

conversation; though it was suggested it occurred a few days later72. Mr Holgye’s

estimate of timing of the conversation should be accepted: it is supported by what is

contained in a letter of complaint he sent to Scenic on 23 July 201373. No one was

called by Scenic to contradict the timing of this conversation.

74. The ship made its way from Dusseldorf to Cologne on 29 May 2013. Mr Cairncross

recalled that this was the first tour he experienced. He and his wife got off the boat and

it was very wet and cold to proceed with an outdoor excursion in the circumstances74.

75. On 30 May 2013, however, the ship was unable to cruise to Rudesheim, but needed to

dock in Mainz75. That day, passengers were required to undergo a ship swap to the

Scenic Jewel, at that point in Bamberg,76 to continue to cruise up the rivers.

67 Ibid 68 Ibid 69 Ex P36 (CB 6/1950) 70 Holgye, pars 23-24, CB2/ 400 71 Holgye, pars 26-28 72 T 135 73 Holgye, CB 2/410 74 T 128-129 75 Holgye, pars 32-33 76 Holgye, par 34

Page 15: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

15

76. Mr Holgye, and other passengers, arrived at Bamberg at 6pm to board the Scenic Jewel.

After lengthy bus tours, this was very debilitating to Mr Holgye, who suffered from the

disability of polio77.

77. The defendant suggested that on 31 May 2013, a cruise director had told passengers on

this cruise that it was because of unexpectedly high river levels that the cruise could not

cruise to Mittenburg78. The defendant did not, however, adduce evidence to support the

proposition that the high river levels were, in fact, ‘unexpected’.

78. On 31 May 2013, Scenic organised a 4 hour bus trip to Bamberg where it was expected

that passengers would embark upon the Scenic Jewel79. Mr Cairncross was told that the

conditions were such that there was no way that the ship could cruise80.

79. Mr Cairncross’ handwritten notes referred to “pissing” rain on 1 Jun 2013 and noted

that the region was flooded81. The next day, Mr Cairncross’ notes recorded that

passengers were ‘stranded’82. From 1 June to 3 June 2013, Mr Holgye recalled that there

was no cruising and passengers remained stuck in Bamberg. During this period, Mr

Holgye’s wife was ill and opportunities to visit sites in Nuremburg were missed.

80. On 3 June 2013, passengers were put on coaches for scheduled land-based excursions

to Nuremberg. However, that experience was interrupted83. On the evening of 3 June

2013, the cruise director, Kurt described the rivers were the “worst for 500 years” and

he could not confirm whether or not the ship could do any cruising84.

81. On or about 4 June 2013, passengers were bussed to Krems, and were required to

embark on Scenic Sapphire. Mr Holgye described the location as an abandoned

industrial area85. There passengers remained in Krems for at least the next 4 days. Mr

Holgye records extensive bus travel and walking during this period.

82. Mr Cairncross and his wife decided to leave the cruise on 5 June 2013, incurring

substantial expenses in accommodation and travel86.

83. From 5 – 9 June 2013, Mr and Mrs Cairncross made their own way independently,

before re-joining the cruise at Budapest on 10 June 2013, so they could get on with the

final limb of their holiday87.

77 Holgye, pars 38-41 (CB 2/402-403 78 T 125.50 79 T 126.7; see also Holgye, par 42 (CB 2/403) 80 T 126.21 81 Cairncross, Annexure ‘G’, CB 2/376 82 Ibid, CB 2/377 83 Cairncross, pars 39-40; CB 2/357 84 Cairncross, par 41 85 Holgye, par 65, CB 406 86 Cairncross, par 56, also CB 2/385 87 Cairncross, pars 58-60; also CB 2/386

Page 16: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

16

84. On 6 June 2013, Mr Cairncross complained to his travel agent about his experience88.

85. As at 7 June 2013, Scenic records indicated that this ship had not been able to sail for

10 days89.

86. On 9 June 2013, Mr Holgye and passengers had to endure a 3 hour coach trip from

Krems to Budapest, where he and his wife finished the trip90.

87. A variation schedule annexed to Mr Holgye’s affidavit indicates the extent to which

cruising was disrupted, and was substituted with successive coach excursions and

relocations, according to Scenic’s own records91. Letters of complaint were sent to

Scenic92.

STC270513.2

88. This ship was scheduled to embark at Budapest on 27 May 2013. On 29 May 2013, the

ship cruised to Vienna99.

89. By 31 May 2013, the cruise director noted that the Melk lock was closed (just as the

ship had arrived in Melk) and it was questionable when the ship would sail again. The

cruise director noted that the ship could not sail onwards: there was high water on the

Danube and the lock of Melk had closed100.

90. As at 2 June 2013, the ship could not sail due to high waters101.

91. As at 3 June 2013, this ship was recorded as being stuck in Krems102. On 3 June 2013,

passengers were informed that they would be disembarking the ship and moving to the

Scenic Jewel in Bamberg103.

92. As at 7 June 2013, this ship had been unable to sail for 6 days104. By 10 June 2013, there

had been 8 ‘unplanned stationery days’105.

93. By 8 June 2013, the passengers were cruising through the Rhine Gorge106. On 9 June

2013 the cruise proceeded to Amsterdam.

88 Cairncross, Annex Q (CB 2/391-392) 89 Ex P45 (CB 6/1999-2000) 90 Holgye, pars 86-94, CB 407-408 91 Holgye, Annex ‘B’ (CB 2/415-416) 92 Holgye, Annex A (CB 2/410-411), Annex C (CB 417-419) 99 Ex D67 100 Ibid 101 Ibid 102 Ex P26 (CB 5/1802) 103 Ibid 104 Ex P45 (CB 6/1999-2000) 105 Ex P46 (CB 6/2002) 106 Ex D67

Page 17: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

17

STC290513.1

94. This ship was scheduled to embark at Amsterdam on 29 May 2013.

95. As at 1 June 2013, the ship’s cruise director had recorded that the River Main was

closed due to high water107.

96. As at 7 June 2013, it was recorded that this ship had not been able to sail for 10 days108.

STC290513.2

97. This ship was scheduled to embark at Budapest on 29 May 2013.

98. As at 2 June 2013, the ship’s cruise director had noted that it was not possible to go to

Durnstein110.

99. On 6 June 2013, a coach left from Vienna but between Passau and Deggendorf, the

Regensburg Motorway was closed111.

100. As at 7 June 2013, this ship had not been able to sail for 8 days112. By the next day, the

cruise director had observed that passengers were tired of bus-rides113.

STC030613.1

101. The plaintiff, Mr Moore, and another passenger who is not a group member (Mr

Childs) gave evidence of their experience on the cruise STC030613.1 from Amsterdam

to Budapest. This was the ship earmarked to be undertaken by Scenic Jewel but which

eventually was undertaken by Scenic Ruby.

102. In his affidavit, Mr Moore provided very detailed recollections of his experience. His

account was not seriously challenged in cross-examination. Indeed the thrust of much

of the cross-examination was that he enjoyed the part of the tour which did not involve

any disruption to the cruise component. This was a proposition that had never been

disputed. He was a good witness. He wrote a contemporaneous letter of complaint114.

Mr Childs also sent a letter of roughly contemporaneous complaint on 1 July 2013115.

The Court should have no reservation in accepting his evidence. Mr Childs is not a

group member in these proceedings and his evidence was unchallenged by the

defendant.

107 Ex D68 108 Ex P45 (CB 6/1999-2000) 110 Ex D69 111 Ibid 112 Ex P45 (CB 6/1999-2000) 113 Ibid 114 Ex P DM-1 (CB 3/799-802) 115 Ex P HC-1 (CB 2/337-339)

Page 18: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

18

103. Both Mr Moore and Mr Childs, and other passengers on this cruise, were sent a letter

of 1 June 2013. Scenic referred to high water levels being experienced on the river

Main, preventing navigation, noted that the ship that was due to embark (Scenic Jewel)

was not able to be in Amsterdam for the embarkation and foreshadowed a ship swap 116

.

104. Mr Childs recalls being told by the cruise director as early as the point of embarkation

on 3 June 2013, that Scenic was having problems with rising river levels, and that there

would be a ship swap after a few days117. Mr Moore recalls being told by the cruise

director that the Scenic Jewel had been stuck in Bamberg for 8 days due to the river

levels118.

105. The tour proceeded, as scheduled, from 3 – 5 June 2013. As at 3 June 2013, the Main

and Danube rivers were closed altogether with major flooding happening119.

106. On 5 June 2013, it was clear to Mr Moore that when the ship arrived in Cologne, the

river level was too high. On 6 June 2013, the ship only got as far as Marksberg when it

had to go back120.

107. The defendant’s records indicate that, between 5 and 8 June 2013, there were full

closures along the Main River, Danube (German border), Danube (Vienna) and

Danube (Budapest)121.

108. The next morning, on 6 June 2013, Mr Moore noted that the cruise commenced for

only a very short period of time towards the Marksburg Castle. The cruise was unable

to proceed up the Rhine Gorge but, instead, proceeded back to Koblenz. There the

ship became moored between four other boats; 2 on either side (obscuring the balcony

view that Mr Moore and his partner had paid for).

109. After several long and uncomfortable bus excursions for Mr Moore, on the afternoon

of 8 June 2013, passengers were taken to the Scenic Jewel, which had been moored in

Bamberg, an abandoned industrial area, where they remained until 12 June 2013.

Plainly, it was not just the periodical rainy weather which would have given rise to

disappointment122. A further factor was that road excursions were limited (not all could

be attended because of the road conditions) and uncomfortable in view of the weather,

which was both wet and cold.

110. By 7 June 2013, the ship’s cruise director had commented that, so far, more travelling

time had been spent on a bus than on the ship and “these guests hate travelling on a

bus”123.

116 Ex P HC-1 (CB 2/316) 117 Childs, par 22 (CB 2/294) 118 Moore, par 23 (CB 3/550) 119 Ex D27 (CB 5/1796) 120 T 64-65 121 Ex P52 (CB 6/2109-2114) 122 T 70.35 123 Ex D53 (CB 6/2084)

Page 19: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

19

111. On 12 June 2013, the ship cruised from Bamberg to Berching, which cruise was

affected by several delays through the locks and bridges. Several planned excursions,

including one to Salzburg (which had particular value to Mr Moore’s partner) were

missed.

112. On 13 June 2013, plans were afoot to undertake a further ship swap in Vienna (on the

Scenic Pearl). Mr Moore did not think his back could withstand an 8 hour bus trip and

it was suggested he take a train to Vienna. This Mr Moore and his partner accepted and

they arrived in Vienna (in Mr Moore’s case) with significant back pain.

113. On 15 June 2013, Mr Moore experienced what he perceived as a rushed trip to

Bratislava, missing museums and shops. The scheduled departure to Vienna was

delayed, which meant that he and his partner spent only one of the two nights there.

114. Mr Childs annexed several photos depicting the high river levels and effects of

flooding: of the Rhine River near Marksburg castle125 (on 6 June 2013), Wurzburg126 (8

June 2013), the Danube River near Bamberg127 (9 June 2013), Regensburg128 (11 June

2013), the Danube River near Passau and river between Passau and Linz129 (14 June

2013), the Danube River near Vienna130 (15 June 2013), and Budapest131 (16 June 2013).

115. Mr Childs was not required to attend for cross-examination. His evidence should be

accepted in its entirety.

116. The defendant’s records corroborate the ship being stuck in Bamberg as at 10 June

2013132 .

EGFC80613.1

117. The cruise director, Herbert Heutter noted that most guests were unhappy and upset

when they arrived at the Novotel hotel conference, prior to embarkation. They were

upset about not having the choice to fly home or continuing to go on the tour,

especially when APT was doing so134.

118. Mr Willems gave evidence of his trip scheduled to embark on 8 June 2013, from

Budapest to Amsterdam. The intention was to embark on Amadeus Silver, but in the

event, the ship Amadeus Brilliant was used from Vienna.

125 Ex P HC-1 (CB 2/317-320) 126 CB 2/322 127 CB 2/323-325 128 CB 2/327-328 129 CB 2/329-330 130 CB 2/331 131 CB 2/333-334 132 Ex P46 (CB 6/2002) 134 Ex D70

Page 20: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

20

119. Mr Willems recalled that on the evening of 8 June 2013, after being shown his and his

partner’s room, the cruise director indicated that the ship would be stuck in Budapest

for the first 2 nights. There, for the next few days, the bus tours, including a bus tour

that took passengers to where Amadeus Brilliant was located (moored alongside other

Evergreen ships in an industrial area near Vienna). The flooding around Budapest on 9

June 2013 was significant135.

120. On 12 June 2013, after a bus tour from Vienna to Salzburg, the cruise director had

indicated to Mr Willems that the Amadeus Silver, located in Nuremburg, would sail that

night. It had been a 14 hour bus trip from Vienna to Nuremburg.

121. Despite the promise, on 13 June 2013, planned trips to Durnstein in the Wachau wine

region136, to Linz and the town of Passau and the Cesty Krumlov, did not eventuate.

The ship was docked about 40 kilometres away from the city of Nuremburg.

122. It was put to Mr Willems that on 13 June 2013, the cruise director, Herbert explained

that the closure of the locks, preventing cruising to Regensburg were “unexpected” or

“sudden”137. Whether or not this is what Herbert actually said, it was clearly a case of

the cruise director conveying Evergreen’s view. That did not make the view accurate, or

even reasonable, in the absence of any evidence by Evergreen to explain the basis for

the view. The Court could not determine that the closure was unexpected or sudden.

The better view is that it simply was a foreseeable result of the river conditions. Having

taken the decision to continue with the scheduled cruise (unlike its competitors at the

time), in the context of severe flooding, a closure of the lock should not be regarded as

unexpected or sudden.

123. On 14 June 2013, a walking tour of Regensburg was scheduled as was the sailing along

the Rhine-Main-Danube canal to Nuremburg. Due to the flooding this did not occur.

The defendant’s records confirm that, as at 14 June 2013, the ship could not sail to

Regensburg138.

124. On 15 June 2013, Mr Willems boarded a bus tour into Nuremburg. It was not until

7pm that day that Mr Willems and his partner were able to cruise.

125. The next day, after a walking tour of Bamberg, the ship cruised towards Wurzburg. The

cruise proceeded as scheduled until 22 June 2013.

126. The Court may more comfortably accept the accuracy of all of these accounts in view

of the defendant’s decision not to call evidence.

135 CB 2/265-266 136 Ex P MW1 (See the photo of Melk, as part of this region, at CB 2/269) 137 T 107-108 138 Ex P59 (CB 6/2255-2256)

Page 21: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

21

STC100613.1

127. Before the scheduled date of embarkation (at Amsterdam) for this cruise, on 7 June

2013, Scenic notified travel agents for passengers that the Scenic ‘Space-Ship’ would not

be able to sail into Budapest due to high water levels. Clients would be put up in a hotel

for a night and join the ship in Vienna140.

128. Between 9 & 14 June 2013, there were full closures along the Danube German Border,

Danube (Vienna) and Danube (Budapest)141.

129. By 10 June 2013, the Faulbach (along the Main River) was closed. Bamberg to lock

Hausen (along the Main-Danube canal) was closed. Mr Sandmeier recorded that the

Hungarian Government had declared a state of emergency for 3 counties.

130. On 19 June 2013, the water police restrained the cruise at the Jochenstein lock142. The

same day, preparations were made for a ship swap with Scenic Pearl.

STC100613.2

131. Mr Peattie gave evidence of his experience on the Scenic ship due to embark Budapest

on 10 June 2013. It was intended to be on Scenic Sapphire but in the result turned out

to be the Scenic Diamond.

132. On 7 June 2013, passengers on this ship received a letter from Scenic (Kim Scoular)

indicating that passengers would be re-directed from Budapest to Vienna143.

133. Mr Peattie and his wife endured a long bus trip to Vienna. Mr Peattie took the

opportunity to video record this bus trip. The experience featured him feeling thrown

around and luggage also falling from the overhead storage144.

134. Contrary to what was represented, however, Mr Peattie recalled that the bus arrived in

the industrial town of Krems145. There they remained for 4 days, with Mr Peattie and

his wife being privy to a view of a concrete wharf 146.

135. On the evening of 14 June 2013, Mr Peattie received his first indication that there

would be sailing. This was subject to a ship swap to another Scenic ship 300 km away.

He recalled the cruise director explaining that because of a damaged lock, it was

necessary to escort the passengers by bus to go around it.147 It was put to Mr Peattie

that the cruise director had indicated that on the preceding two days, a lock had

140 Ex D44 (CB 6/1973-1974) 141 Ex P52 (CB 6/2109-2114) 142 Ex D71 143 CB 2/520 144 Peattie, pars 35-36; Ex P3; CB 2/510 145 Peattie, pars 40-44; CB 2/510-11 146 CB 2/528 147 Peattie, par 61; CB 2/513

Page 22: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

22

suddenly and unexpectedly been discovered to be damaged. Mr Peattie denied this: they

were informed that the military had been working on it for some time148.

136. The next day, the ship sailed a short distance to Melk. Mr Peattie was disappointed that

this port was not near any town or village149.

137. On 14 or 15 June 2013, Mr Peattie and fellow passengers endured a 13 hour bus trip,

taking them away from the Scenic Sapphire and arriving on the Scenic Jewel150. By the

time he arrived on the Scenic Jewel, Mr Peattie was physically and mentally tired from

the coach trips and needed medication. He had endured 6 days of views of concrete

walls or dust bowls and had missed out on visiting Linz and Passau151.

138. Mr Peattie’s complaint to Donna Willis on 26 August 2013 described his experience152,

including the extended stay in Krems and the lack of sailing time.

2.2.2 What did Scenic know (or should have known) before embarkation of the cruises?

139. This question is germane to the case of non-compliance with the care and skill

guarantee. The plaintiff contends that the question (and the associated questions of

how Scenic actually responded to the knowledge and how it should have responded) is

not determinative of the claim for damages based on non-compliance with the purpose

and result guarantees.

140. The defendant admits (as it must) that there were high water levels in Europe from

about May 2013 along the paths of the cruises provided by it153. As at 30 May 2013,

Lucas Sandmeier knew enough to apologise to guests about adverse weather conditions

over the past few months causing various levels of disruption to all forms of navigation

on many major European waterways154.

141. The following survey highlights matters that would indicate that Scenic either knew, or

should have known, of the real and substantial prospect that certain cruises that were

about to embark were likely to face substantial disruption, in respect to the cruising

period.

142. It is important to note that save for the single South of France cruise in May 2013, all of

the following cruises concerned the same cruise-path; albeit that the path was

approached from differing directions (Amsterdam to Budapest; Budapest to

Amsterdam). It is also important to keep in mind the temporal proximity of these

cruises. Twelve of the thirteen subject cruises (not including the French cruise)

occurred in the period from 20 May to 12 June 2013. The store of knowledge acquired

(or which was ascertainable) developed over the subject period. That is, absent any

148 T 171.40 149 Peattie, par 62; and see the photos at CB 2/527 150 Peattie, pars 67-68 151 Peattie, pars 71-76, CB 2/ 514 152 CB 2/535-541 153 Par 10 of the Defence (CB 1/50-51) 154 Ex P16 (CB 5/1717A)

Page 23: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

23

intervening event, it would naturally be inferred that what was known (or ascertainable)

about river levels along the Jewels of Europe cruise-path in the lead up to a cruise on

20 May 2013 was also likely to be relevant to the cruises on 12 June 2013. Such

inference is strengthened in circumstances where the defendant has not called any

witness to give evidence to the contrary.

FRCR190513.1

143. The high water levels along this cruise-path did not suddenly materialize. River levels

had risen across the cruise-path in early May 2013: between 1 and 4 May 2013, Scenic’s

vessels could not sail between Tarascon and Avignon156. On 6 May 2013, another tour

operator, Avalon, attributed the high water levels along the Rhone River due to a

sudden rise in temperature, which had caused snows of the past European winter to

rapidly melt158.

144. By 15 May 2013, Avalon had reported that water levels on the Seine were rising again,

so arrangements were made whereby the Avalon Scenery would leave for Paris earlier in

order not to get stuck in the bridges of Paris159.

145. By 16 May 2013, Scenic was advising its guests that the high water levels on the Rhone

and Saone had resulted in a revised itinerary160.

146. As at 18 May 2013 the ship of a different company, the ‘Avalon Scenery’ was stuck at

Viviers161.

147. On 23 May 2013, Avalon had reported that two of its ships, the ‘Avalon Affinity’ and

‘Avalon Luminary’ were supposed to enter the Moselle River, but the river was reported

as carrying high water162.

148. In the afternoon of 24 May 2013, Lucas Sandmeier’s email message to Justin Brown

indicated that the critical water level for safe passage at the Pont la Feuillee, at the entry

of the river Saone to Lyon was currently 50cm over the point where it needed to be163.

149. A communication from Lucas Sandmeier to Scenic personnel on 29 May 2013 indicated

that in the 24 hours from 8:00am on 28 May 2013, water levels at Pont de Feuillee in

Lyon exceeded the safe passage level164.

150. The experience endured by passengers like Mr Britten on board Scenic Emerald was

entirely foreseeable, if not the predictable outcome, resulting from the rising river levels

156 Ex P13 (CB 5/1585-1589) 158 Ex P10 (CB 5/1555) 159 Ex D14 (CB5/1578) 160 Ex P11 (CB 5/1579) 161 Ex P12 (CB 5/1580) 162 Ibid 163 Ex D15 (CB 5/1606) 164 Ex D22 (CB 5/1681)

Page 24: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

24

that had occurred earlier in the month.

STC270513.1

151. On 26 May 2013, Patrick Doyle, the cruise director, recorded that River Main was

closed, with high water threatening the program. The cruise director notified Lucas

Sandmeier that according to the ship’s captain there was no chance for the ship to

move with water level rising165.

152. The next day, Doyle also noted that the cruise was being weather affected.166 It is

pertinent to note that on 27 May 2013, Marin Dimow recorded a variation for cruise

STC200513.1 (travelling in the same direction), as a result of rising river levels on the

Danube167.

153. Scenic’s tour director for the cruise STC030613.1 told David Moore on 3 June 2013

that the Scenic Jewel had been stuck in Bamberg for 8 days, at that point168. This was

about 25 May 2013.

STC270513.2

154. The day before this ship was set to embark, on 26 May 2013, Scenic was aware that the

River Main was closed and that high water was threatening the program of cruise

STC200513.2.

STC290513.1 & STC290513.2

155. The day before these ships were set to embark records show that Scenic knew or had

the means of knowing of the partial or complete closures along parts of the Main River,

at Steinbach, Wurzburg, Schweinfurt and Trunstadt.

156. On the day of the scheduled embarkation, the defendant knew or had the means of

knowing that:

a. the Scenic Jewel was stuck in Bamberg due to high water levels;

b. there was a concern that parts or all of the Amadeus Silver would have to be run as

a ‘land tour’

STC030613.1

165 Ex D16 (CB 5/1632) 166 Ex P 27 (CB 5/1816) 167 Ex D29 (CB 5/1809) 168 Moore, par 23; CB 3/550

Page 25: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

25

157. Following the departure of the cruises on 29 May 2013, but before the scheduled

embarkation of the cruise on 3 June 2013 (from Amsterdam), Scenic knew, or it was

ascertainable that:

a. Scenic Jewel remained stuck in Bamberg and could not make it to Amsterdam in

time for disembarkation;

b. The Amadeus Silver could be stuck in Wurzburg for a further 4 days;

c. Lucas Sandmeier reported (on 1 June) that navigations may be impacted in certain

areas along the Rhine River, navigation on the Main River had stopped, a lock was

closed in Melk and the canals between the Danube and Main Rivers may be

closed170;

d. The Scenic Sapphire was stuck in Melk171;

e. The Avalon ships ‘Luminary’ and ‘Vista’ were stuck in Frankfurt172 and Avalon

ship ‘Visionary’ was stuck in Vienna173, and ‘Tranquility’ was stuck in Lindau174;

f. Other tour operators, Avalon and Viking, had started to cancel cruises, and noted

that, for 3 June 2013, the Main and Danube were closed, altogether, with the Rhine

probably closed from that date175;

g. (as at 2 June) Coblence (Germany) was forecasted to be closed for navigation on

the Monday (3 June)176;

h. There were likely to be interruptions of the Rhine, with water flowing from

Amsterdam177;

158. From 31 May to 2 June 2013, Lucas Sandmeier reported to Justin Brown that there was

a substantial rise in the water level at Basel179.

159. Lucas Sandmeier expressed his opinion to Justin Brown on Sunday, 2 June 2013, that

ships would certainly not move on 2 June, and likely not for a few more days180.

160. On 2 June 2013, it appeared that Justin Brown was resigned to the prospect of

substantial disruption affecting cruises that had embarked, as well as cruises about to

170 Ex P18 (CB 5/1744) 171 Ex P21 (CB 5/1762) 172 Ex P19 (CB 5/1750-1751); & Ex P23 (CB 5/1773) 173 Ex P19 (CB 5/1752) 174 Ex P22 (CB 5/1768) 175 Ex D27 (CB 5/1796) 176 Ex P20 (CB 5/1756 - 1757) 177 Ibid 179 Ex D26 (CB 5/1785) 180 Ex P24 (CB 5/1778)

Page 26: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

26

embark: he raised the possibility with Glen Moroney that passengers might just need to

be kept on board, to try to get ships to their disembarkation and embarkation points as

best as they could and make a refund181.

EGFC080613.1

161. From the embarkation of cruises on 3 June 2013 until the embarkation of the Amadeus

Silver from Budapest on 8 June 2013, the defendant knew, or had the means of

knowing:

a. 4 of its ships (all embarking on either 27 or 29 May 2013, from opposite directions)

were stuck182;

b. The Czech Government had declared a state of emergency in response to

widespread flooding in most regions of Bohemia;

c. There were full closures along the Main River, Danube (German border), Danube

(Vienna) and Danube (Budapest) from 5 to 8 June 2013.

d. APT had cancelled 4 of its cruises scheduled for 6, 7 & 8 June 2013 (with two of

the 4 cruises embarking from the same point)183;

e. Uniworld had cancelled its cruises (Prague to Belgrade and Prague to Vienna)

scheduled for 7 June 2013184;

f. Viking had cancelled its cruises scheduled for 8, 9 & 12 June 2013 on the basis

that the Danube would be closed from Nuremburg to Budapest til 16 June

2013185;

g. Lucas Sandmeier’s opinion that the re-opening for navigation of various rivers

was very uncertain and his information that Passau (along the Upper Danube)

had experienced its highest water level in 600 years;

h. As at 6 June 2013, even coach travel between Passau and Regensburg was

affected by a closing of the motorway186;

162. On 3 June 2013, Evergreen published on facebook an entry, ostensibly to inform

people about the experience of those passengers on cruise number 3. The entry noted

the high river levels in northern Europe, the circumstance that high water levels were

affecting navigation on some rivers187.

181 Ex P24 (CB 5/1775) 182 Ex P26 (CB 5/1802) 183 Ex P30 (CB 5/1836); Ex P33 (CB 6/1870) 184 Ex P37 (CB 6/1954) 185 Ex P34 (CB 6/1921-1922) 186 Ex P46 (CB 6/2001) 187 Ex P MW-1 (CB 2/259)

Page 27: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

27

163. On 6 June 2013, Evergreen sent a letter to passengers on its earlier cruise (number 3),

noting continued high water levels on the river Main and the ship’s inability to navigate

those areas of the river188.

164. On 7 June 2013, the day prior to embarkation, Angus Crichton predicted to Lucas

Sandmeier and others that the Amadeus Silver may only get 6 -7 days of cruising

(almost 50%)189.

165. On the same day, Kim Scoular sent a message to a range of people foreshadowing that

peak water levels were expected in Budapest on 9 & 10 June 2013190.

166. Later that evening (7 June 2013), Lucas Sandmeier reported that although certain parts

of the Rhine and Main Rivers were open (with limitations), the entirety of the Danube

River was closed. Passau had indicated that no ship could dock in Passau or Lindau

through to 16 June 2013191.

167. On 8 June 2013, the date of embarkation, Lucas Sandmeier reported that only daylight

cruising was allowed along the Main River. The lock Hausen (between Bamberg and

Nuremberg, along the Main-Danube canal) was closed during the work and various

parts of the Danube (Passau-Krems, Krems –Bratislava, Bratislava – Budapest) were

closed. Lock Hausen (between Bamberg and Nuremberg) was closed during work and

was expected to re-open mid-week. This meant that ships could not sail between

Nuremberg and Bamberg192.

STC100613.1 & STC100613.2

168. The defendant knew that from 9 – 14 June 2013, there were full closures along the

Danube (German border), Danube (Vienna) and Danube (Budapest).

169. On 9 June 2013, the day that these cruises embarked, Lucas Sandmeier reported that

Faulbach (along the Main River) was closed; Bamberg to lock Hausen (along Main-

Danube-canal) was closed; that the re-opening of rivers between Vienna and Budapest

was expected to occur no earlier than Wednesday (12 June 2013) and the re-opening of

the rivers between Budapest and Hungary would occur no earlier than Saturday (15

June 2013)193. Separately, Sandmeier reported that new arrangements would have to be

made for the disembarkation of cruise number 4 and embarkation of cruise number 13

because ships could not approach Budapest194.

170. By the date of the embarkation of these ships, on 10 June 2013, Scenic was aware that

cruises that had proceeded along the same river paths on 27 and 29 May 2013 had lost a

188 Ex P36 (CB 5/1950) 189 Ex P40 (CB 6/1969) 190 Ex D41 (CB 6/1960) 191 Ex D45 (CB 6/1976-1977) 192 Ex P42 (CB 6/1985-1986) 193 Ex D46 (CB 6/1987-1988) 194 Ex P43 (CB 6/1989A)

Page 28: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

28

substantial number of sailing days195.

STC120613.1 & STC120613.2

171. On 11 June 2013, the day before the Scenic Pearl was scheduled to embark at

Amsterdam, and the Scenic Diamond was scheduled to embark at Budapest, Scenic was

aware that the Main-Danube Canal (Bamberg to lock Hausen) remained closed (with

an opening not before 12 June 2013); that the water authorities had extended the

navigation ban on the upper Danube, various locks on the Danube remained closed,

and flooding was scheduled to peak between Hungary and Budapest (whose cruise path

was expected to be closed until Saturday, 15 June 2013)196.

172. Another update on the same day (whose time was not apparent) indicated that the

Wurzburg bridge along the Main River could not be passed by passenger ships; the

Main Danube Canal (Bamberg to lock Hausen) remained closed (and would not re-

open before 12 June), that the Danube River was closed (between Straubing and

Ottensheim; and between Ennshafen and Novi Sad)197.

173. What was apparently the last update prior to the embarkation of cruises on this date

indicated that the stretch between Faulbach to Marktbreit along the Main River was

closed; the stretch between Straubing to the German/Austrian border along the

Danube was closed, that the stretch between Budapest and Mohacs was to be re-

opened for navigation no earlier than 15 June 2013198.

174. Records of Scenic and other tour operators the day after the embarkation of these ships

(13 June 2013) indicate that:

a. The lock in Altenworth (between Melk and Vienna) remained closed through to

18 or 19 June 2013 due to the off-shore terminal being washed out, as a result

of the floods199;

b. The ban on navigation between Vienna and Budapest would not be lifted until

midday on 14 June 2013200;

c. Shipping was closed from Vienna all the way to Belgrade201;

d. Part of the Danube (Kelheim to Regensburg and Regensburg to Vilshofen) was

closed202.

195 Ex P44 (CB 6/1995) 196 Ex P47-49 (CB 6/2012-13; 6/2015, 2018) 197 Ex D48 (CB 6/2021) 198 Ex D50 (CB 6/2024) 199 Ex P50 (CB 6/2050) 200 Ibid 201 Ex P51 (CB 6/2067) 202 Ibid

Page 29: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

29

2.2.3 How did Scenic respond?

Proposals for providing refunds

175. Earlier in May 2013, in connection with the cruises along the South of France cruise-

path, Justin Brown was informed by Lucas Sandmeier that British guests, upon hearing

news about the weather and alarmed by the ramifications for their cruise, chose not to

fly to France but cancelled their trips. Sandmeier asked Brown what Scenic’s position

was as to reimbursing the unused portion of the cruise. Brown’s response was that

Scenic could not offer refunds but, rather obliquely, left it to Chris (Townson) to offer

‘action’ to the UK guests203.

176. On 29 May 2013, Justin Brown received a report from Melanie Koch about two guests

on the cruise FRCR190513.1 wanting to leave the cruise and pressing for

compensation. Brown stated the general position (consistent with Scenic’s position in

this proceeding) was, in Scenic’s belief, there were alterations (caused by events beyond

its control), Scenic would not offer refunds or compensation “should the guests choose

to leave the tour”. If guests wanted to leave the cruise, they would be encouraged to

stay, but if they did decide to leave, that request would be facilitated, but the guests

would have to bear the expense204.

177. Later that day, and in response to an indication that certain UK guests were wanting to

leave FRCR190513.1, Justin Brown sought advice from Emma Lindsay (Scenic’s UK

Operations Manager) as to whether Scenic’s terms and conditions would be effective to

oust UK laws in a way as to prevent compensation being delivered. Lindsay opined that

the UK laws ousted the terms and conditions, confirming Justin Brown’s beliefs.

Lindsay quipped that it was a shame that UK guests weren’t as “easy as the Aussie

guests”205.

178. What is notable about these two sets of communications, for present purposes, was a

consciousness within the defendant as to passengers’ wishing to leave their cruises and

seeking to recover refunds; as well as a clear statement that Scenic could facilitate

passengers’ voluntary cancellation if passengers took the positive step of requesting

same.

179. On or about 2 June 2013, Justin Brown had communications with Lucas Sandmeier

which suggested that he had in mind, as an option, cancellation of cruises that had

embarked, with refunds for the unused portion of the cruise206.

180. By 4 June 2013, Brown’s thinking had altered: those passengers who had embarked, and

who wanted to leave, would have their exit ‘facilitated’, but Scenic would not cancel

unless it was unable to offer reasonable services and there was a risk to the planned

disembarkation place and time207.

203 Ex P10 (CB 5/1556-1562) 204 Ex P15 (CB 5/1662) 205 Ex P14 (CB 5/1652-1653) 206 Ex P24 (CB 5/1775, 1777) 207 Ex P29 ( CB 5/1823-1825)

Page 30: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

30

181. On 7 June 2013, Brown again indicated the prospect that in circumstances where the

defendant cancelled cruises, an ‘equitable’ refund could be given to passengers208.

182. As for those who were due to embark on Scenic cruises on 10 and 12 June 2013, (and

the Evergreen cruise on 8 June 2013), Scenic’s position was reactive: those not wanting

to embark could choose to cancel and obtain a refund, however Scenic would not

advertise this option. Scenic’s preference was to re-schedule the cruise tour for later in

the year.210

183. But even this reactive approach did not appear to be implemented. Mr Willems gave

evidence of the Evergreen tour director, Herbert Heutter telling passengers about to

embark on the Amadeus Silver on 8 June 2013 that if passengers wanted to go home,

they would receive no refunds, but very shortly thereafter, held out the prospect that

there might be some refund at the end of the cruise211. This appeared to be inconsistent

with what Mr Heutter was informed by Mr Crichton, who said Evergreen could

support passengers with transfers to airports, but not providing refunds212.

184. On 10 June 2013, Justin Brown proposed to Glen Moroney that for the Jewel of

Europe cruises (both directions) on 27 and 29 May 2013, Scenic should consider a

refund of $150 per person per lost day due to the significant loss of sailing days.

Moroney rejected that proposal213.

185. Separately, on the same day, Brown suggested to Moroney refunds for the disrupted

parts of tours to compensate for the “unplanned stationery days” tallied for cruises on

27 and 29 May and 3 June 2013. Brown thought passengers on these cruises would

expect a 50% minimum refund. He was plainly motivated by what he perceived that

Scenic’s competitors were offering214.

186. On 11 June 2013, Kim Scoular was telling call centre staff in response to inquiries to

inform passengers whose cruises were scheduled for late in June (ie beyond the period

in issue in this proceeding), that their cruises could be re-scheduled to later in 2013 or

2014215. It is not clear why this option was not presented to cruises in the subject

period.

187. These communications reveal at least two things: first, the fluidity in the decision-

making process of Justin Brown; and, secondly, it appeared that the ultimate say in

things rested with Scenic’s owner, Mr Moroney. Curiously, however, it appeared that

Scenic was informing local travel agents, who in at least one instance complained to

208 Ex P38 (CB 6/1958) 210 Ex P31 (CB 6/1841-1842) Ex P32 (CB 6/1851-1852) 211 Willems, par 58, CB 2/225 212 Ex P39 (CB 6/1964) 213 Ex P44 (CB 6/1995) 214 Ex P46 (CB 6/2002) 215 Ex P49 (CB 6/2019)

Page 31: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

31

Scenic that passengers were expecting a full refund, that the decision not to provide

refunds rested with Scenic’s General Manager, Mr Brown216.

188. The issue as to precisely which person was responsible for the decision not to offer

refunds was left uncertain as a result of Scenic’s decision not to call either Messrs

Brown or Moroney, for fear of what might be exposed in cross-examination.

189. In the events that occurred, there was:

a. no cancellation by the defendant of any of the cruises; nor any re-scheduling of

the cruises to later in the year;

b. no policy of providing refunds for passengers for the unused portion of their

cruises in which no sailing occurred.

c. no options were provided to passengers, either before or after embarkation, that

the tours may be wholly or partly cancelled, delayed or re-scheduled for later in

the year.

190. A consequence of the defendant’s failure to cancel cruises before embarkation was to

negate the capacity of some passengers to claim upon any travel insurance that they had

arranged.

Scenic’s awareness of limits of Covermore insurance coverage

191. In its terms and conditions, Scenic recommended that passengers take out travel

insurance217. More than that, Scenic provided Covermore Travel Insurance218. As will be

later indicated (section 3.2.2), it appeared that Scenic intervened with Covermore, at the

behest of Mr Moore, after his claim for travel insurance had been initially rejected.

192. Scenic was therefore on notice of the basic terms and conditions of at least Covermore

insurance. As at July 2012, passengers who took out such insurance had the option of

seeking coverage for the costs of cancelling their tours (or ‘Journeys’) due to

circumstances outside the passenger’s control. However, there was an exclusion to this

coverage where the ‘transport provider’ caused the cancellation219. There was also a

general exclusion for claims for consequential loss, including loss of enjoyment220.

Arguably, these provisions in the policy would have entitled Covermore to decline

indemnity for the costs incurred through the cancellation of a cruise where the cruise

had embarked. In that situation, if passengers had embarked and Scenic took the

position not to provide refunds for the unused portion of the tour, passengers would

suffer a loss without any recompense. This is, of course, what occurred.

216 Ex P41 (CB 6/1978) 217 Clause 2.16 in Ex P8 (CB 4/1235) 218 Ex P5 219 Ex P7 (p 23 of the product disclosure statement) 220 Ex P7 (p 31 of the product disclosure statement)

Page 32: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

32

193. Mr Britten gave evidence that the verbal explanation he received from Zurich as to why

his insurance claim was rejected was because he had received a ‘partial’ tour221. There is

no specific evidence that Scenic was aware of this, albeit that it would be surprising if it

was not also aware of Zurich’s terms.

194. The subject of Scenic’s awareness of the terms of insurance policies could not be

pursued without witnesses being called. However, it is likely that Scenic was at least

aware that a decision to engage upon a ‘partial’ tour might jeopardise the prospects of

passengers recovering from insurers. This, in turn, should have been a relevant

consideration as to what options should be presented to passengers.

Management of passengers

195. These omissions by the defendant necessitated careful management of passengers,

particularly those who had already embarked upon cruises.

196. On 6 June 2013, Mr Willems’ partner, Judy Buchanan, expressed her view on Facebook

that passengers scheduled to proceed (on the Amadeus Silver, for cruise number 9)

should have had the option to cancel if the tour could not be conducted in its original

form. What was Evergreen’s public response? It was not some statement of general

position capable of being read by Facebook users as a statement of general application,

but a request for Ms Buchanan to discuss her issues privately223.

197. Scenic was criticised for the adequacy of its communications with passengers scheduled

to embark on its cruises, insofar as travel updates were concerned. On 7 June 2013, a

passenger unfavourably compared Scenic to its competitors. Glen Moroney accepted

the criticism and Justin Brown promised that updates would be placed on its website224.

This exchange of messages occurred over half way through the subject period of

cruises.

198. In his email of 7 June 2013225, Angus Crichton predicted to Lucas Sandmeier and others

that, as a worse case, passengers on the Amadeus Silver (due to embark the next day)

would get almost 50% of sailing days. Probably anticipating that this prediction, if it

came to pass, would not reasonably achieve the purpose or result that passengers who

paid for a tour by cruise desired, Crichton suggested that:

“We need to work on their Europe dreams and make sure they get to experience

as much as possible but just on a different form of transport. I’m sure there can

be some very ‘quirky and unique’ experiences that they might be able to do and

happy to ‘value add’ where we can”.

199. This thinking evinces an approach by which the defendant was happy to retain the

monies it received from passengers for a full cruise tour that its marketing had

221 T 152.42 223 Ex P MW-1 (CB 2/264) 224 Ex P28 (CB 5/1819) 225 Ex P40 (CB 6/1969)

Page 33: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

33

promoted if it could re-align passengers’ expectations so that they were content with

the result of experiencing a bus tour around European land destinations. The plaintiff

says that this is unconscionable conduct (see section 2.4.3 below).

200. That inference is supported by an email sent by Kim Scoular to Justin Brown on 5 June

2013226. With reference to the Scenic cruises of 27 May, 29 May and 3 June 2013, Ms

Scoular was emphasising the importance of ensuring that passengers could get as much

of their touring itineraries achieved as possible: Scenic would only look at compensation

(ie a whole or partial refund) if there was a discrepancy with what Scenic was finally able

to deliver. There is no reference, here, to the failure to deliver the cruise component of

the experience.

201. Crichton’s internal communications concerned cruise number 9. Crichton’s

expectations as to the extent of disruption (on 7 June 2013) appeared to be inconsistent

with what the Amadeus Silver cruise director was telling Mr Willems and his partner

(Judy Buchanan) on the same date. Both passengers informed the cruise director that

they did not want to spend the whole tour on busses. In response to Ms Buchanan’s

indication that she did not want to spend a week on a bus, the cruise director said she

was “98% sure that (you) will be on the ship in the next 2 days”227.

2.2.4 How should Scenic have responded?

202. This question is relevant to the issue of compliance with the care and skill guarantee,

which requires proof of fault.

FRCR190513.1

203. In circumstances where it knew that its vessels had been stuck along the cruise-path

(such as at Avignon) and other restrictions upon movement earlier in the month of May

2013 and through its own acknowledgment on 16 May 2013 of high water levels

existing along the Rhone and Saone Rivers, there was at least a real and foreseeable risk

of substantial disruption to the cruising of this vessel, due to embark on 19 May 2013.

Even if (which it should have) Scenic did not take the decision to unilaterally cancel (or

delay the cruise itself) passengers should have been informed of the risk, informed of

the alternative to cancel and re-schedule the tour at a later point within the next year.

204. The defendant’s failure to provide an explanation, subject to scrutiny, as to why it

embarked and proceed with the cruise, should fortify the Court in reaching this

conclusion.

STC200513.2

205. The plaintiff does not contend that it was unreasonable for the defendant to decide that

this cruise could proceed without some disclosure. However, the option that was

226 Ex D36 (CB 6/1898) 227 Willems, par 53; CB 2/224

Page 34: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

34

actually considered for certain cruises that had already embarked but which ran into

(unexpected) disruption, was to cancel the remainder of the trip and offer an (equitable)

refund. This is what should have occurred in respect to this cruise.

EGFC250513.1, STC270513.1 & STC270513.2

206. It appears that by 25 May 2013, Scenic was aware that the Scenic Jewel (STC2001513.2)

was stuck in Bamberg due to high water levels.

207. By 26 May 2013, Scenic was aware from the report of one of its cruise directors that the

River Main had closed, with high water threatening the program of the cruise

STC200513.2. On the day of the scheduled embarkation of these cruises, the defendant

had also received a report of a variation for one of its other cruises (STC200513.1) as a

result of rising river levels along the Danube.

208. There was, accordingly, a real and foreseeable risk of substantial disruption to the

cruising of each of these vessels known by the defendant prior to or at embarkation.

Even if Scenic did not take the decision to unilaterally cancel (or delay the cruise itself)

passengers should have been informed of the risk, informed of the option to cancel and

re-schedule the tour at a later point within the next year.

209. Once embarked on these cruises, passengers should have had the option to cancel the

tour and be supplied with a refund for the unused part of their cruises.

210. On 3 June 2013, it appears that Evergreen prepared a letter228 for its guests on

EGFC250513.1, although Scenic had not proven whether or how it was disseminated

to its guests. Assuming in its favour that it was brought to its passengers’ notice, all that

the letter did, in substance, was to explain why it was necessary to accommodate

passengers in Salzburg for 2 nights.

211. On 4 June 2013, Scenic internal communications229 indicated an intention to send a

message to passengers on cruises STC270513.1 & STC270513.2, purporting to explain a

ship swap, whilst indicating that water levels over the next 72 hours were a ‘variable’

factor i.e. uncertain. However Scenic did not adduce any evidence to show that the

proposed message, or something like it, was actually sent to passengers on those

particular cruises. At any rate, in an earlier point in the letter, reference was made to the

river situation ‘improving’ and a prediction of improved weather. Further, no

alternative option was provided as to what passengers might do.

STC290513.1 & STC290513.2

212. By reason of the matters known or ascertainable prior to and up to the point of

embarkation of these cruises on 29 May 2013, including the closures of the Main River

and alterations being made to STC200513.2 (and EGFC250513.1), there was a real and

foreseeable risk of substantial disruption to the cruising of these vessels.

228 Ex D28 (CB 5/1804) 229 Ex D31 (CB 5/1834)

Page 35: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

35

213. Prima facie, and in the absence of substantial evidence to the contrary, these cruises

should have been cancelled. If not, passengers should have been informed of the risk,

informed of the alternative to re-schedule the tour at a later point within the next year.

214. Once embarked on these cruises, passengers should have had the option to cancel the

tour and be supplied with a refund for the unused part of their cruises.

STC030613.1

215. Since the embarkation of the previous cruise tours on 29 May 2013, the Main River

continued to be at least partially closed (and completely closed from 1 June 2013) and

the Rhine, Upper Main was completely closed from 1 June 2013. The Scenic Jewel

remained stuck in Bamberg and the Scenic Sapphire was stuck in Melk. Other operators

(Avalon and Viking) had started to cancel its cruises, including a cruise for 2 June

2013230, for the stipulated reason of “unprecedented high water levels”. By 2 June 2013,

Justin Brown was already contemplating the possibility of providing partial refunds.

216. Prima facie, and in the absence of substantial evidence to the contrary, these cruises

should have been cancelled. If not, passengers should have been informed of the risk,

informed of the option to cancel and re-schedule the tour at a later point within the

next year.

217. On or about 1 June 2013, it appears that Scenic drafted a letter to guests indicating a

change of ship (from the Scenic Jewel to the Scenic Ruby) and attributed this to high

water levels on the Main River231. The letter only refers to the alteration in the form of a

ship swap, and to the extent it assigns a cause (the high river levels), that cause only

explains the circumstances of a ship swap; not the impact of those conditions upon the

cruise. The letter does not say anything about the risks of disruption to the cruise once

embarked: to the contrary, in the penultimate paragraph, the letter speaks in positive

terms about Scenic making the “cruise experience onboard .. truly memorable”.

218. Once embarked on these cruises, passengers should have had the option to cancel the

tour and be supplied with a refund for the unused part of their cruises.

EGRC080613.1

219. From 3 June 2013, the date when Scenic’s last cruise embarked (from Amsterdam), up

to 8 June 2013 parts of the Main River, the Main Danube Canal the Danube Kelhaim

German Border, the Danube German Border (Vienna) and Danube Budapest were

completely closed. Angus Crichton estimated that this cruise could only be expected to

get about 50% of is sailing days.

230 Ex P24 (CB 5/1775) 231 Ex D25 (CB5/1717))

Page 36: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

36

220. APT had cancelled 4 of its cruises for 6, 7 & 8 June 2013232. Uniworld had cancelled its

cruises scheduled for 7 & 9 June 2013233.

221. As at 4 June 2013, Kim Scoular anticipated that passengers on this cruise would need to

be accommodated in a hotel. She recommended that for those guests anxious about

departure, they should be offered the alternative of sailing later in the year, with

refunds. On the same day, Justin Brown also indicated that passengers scheduled for

this cruise should be given the option of cancellation.

222. On 4 June 2013, Kim Scoular sent an email to Justin Brown and Andrew Kelleher

giving her opinion as to the responses that call centre employees of the defendant

should provide to anxious passengers inquiring about the status of the cruises

EGRC080613.1, STC100613.1, STC100613.2, STC120613.1 and STC120613.2234.

Scenic did not establish whether or how, this opinion was actually translated into

communications with passengers on those scheduled cruises, and/or whether what

responses were received by passengers.

223. The content of the document is, however, consistent with Scoular’s view that

passengers should be offered the opportunity to re-schedule their cruises for later in the

year, if not 2014; and if not, a refund. The message also demonstrates Scenic’s reactive

approach: the option to re-schedule was only to be provided begrudgingly: the “first

and foremost” message that the call centres employees was to provide to passengers

was upbeat – that Scenic was operating its cruise itineraries with best possible outcomes

for guests given current circumstances.

224. On 5 June 2013, Kim Scoular apparently was preparing a letter to be provided for

passengers on this cruise235. It is unclear, however, that a letter in those terms was

received by Evergreen’s passengers. It may have been received by passengers if they

made inquiry through their local travel agent236. However, the letter, or eblast was not

included, for example, in the exhibit to Mr Willems’ affidavit. He only referred to

Facebook entries as the means of communications he and his partner received. The

Facebook entry that Mr Willems and his partner saw late in the evening of 6 June

2013237 reported that Evergreen had not cancelled any departures and indicated

Evergreen’s expectation that it would continue to operate this cruise. Assuming, in

Evergreen’s favour, that most, if not all other passengers on this cruise saw the letter,

there is no reference in it to indicate any options that passengers may have. There was

certainly no disclosure of the option to cancel and re-schedule the cruise for later in the

year.

225. On 7 June 2013, the day before this cruise embarked, Scenic apparently drew comfort,

or perhaps hope, from the circumstance that river levels were dropping in the Main

232 Ex P33 (CB 6/1870) 233 Ex P37 (CB 6/1954) 234 Ex D34 (Ex CB 6/1843-1844) 235 Ex D37 (CB 6/1899) 236 Ex D38 (CB 6/1907) 237 Ex P MW-1 (CB 2/264)

Page 37: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

37

River. It remained the case, however, that parts of that particular river were not

navigable238. It gambled that this situation would change. Even then, on the same date,

Angus Crichton predicted that passengers on this cruise would only experience almost

50% of the cruising experience.

226. Scenic/Evergreen should have implemented Kim Scoular’s and Justin Brown’s

recommendations to provide a cancellation option for passengers for cruises scheduled

to embark on 8, 10 & 12 June 2013 respectively, albeit that it should have done so pro-

actively; rather than in response to the initiative of passengers. It has not put anyone

forward to explain in this proceeding why it did not.

STC100613.1 & STC100613.2

227. As at 4 June, Justin Brown indicated that if guests requested cancellation of cruises

scheduled to embark on this date (and the cruises on 12 June 2013), Scenic would agree

to that.

228. Curiously, however, on the same day, Mr Brown sent to Donna Willis and Kim Scoular

a prepared ‘forward-looking statement’ in an email, intended to be directed to

passengers on these cruises239. Scenic has not proven that the content of this statement

was brought to the attention of passengers on these cruises. Assuming in its favour,

however, that it did, the statement did not contain the option of passenger cancellation

that Mr Brown had been contemplating that very day. At any rate, read as a whole, the

message speaks of the disruption as being a past event and speaks in confident tones of

these cruises being scheduled to operate “without impact”.

229. On 7 June 2013, Ana Wolfsteiner sent an email proposing some amendments to

proposed communications to passengers240. There is no evidence to indicate that the

message was converted into an actual communication to passengers. The only actual

interruption the email envisaged was simply to the embarkation process at Budapest,

although it did note that the flooding may not allow for uninterrupted cruising on 10 &

12 June 2013.

230. On the same day, the tour guide for the cruise scheduled to embark from Budapest on

10 June 2013 told the group that the “river had flooded and there (is) damage to the

locks. Other cruise operators have cancelled their cruises but Scenic are still sailing”241.

231. Leading up to and including 10 June 2013, at least part of the Danube River was

completely closed and Scenic vessels were stuck in various places along the cruise-path.

232. On 7 June 2013, Scenic sent a letter to passengers scheduled to embark upon

STC100613.2242. The letter warned that peak river levels were expected to reach

238 Ex D41 (CB 6/1960) 239 Ex D33 (CB6/1840)) 240 Ex D 40 (CB 6/1955) 241 Peattie, par 24 (CB 2/509). Mr Peattie’s evidence in this respect was unchallenged. 242 Ex D44 (CB 6/1973). The letter also appears as Annex “B” to Mr Peattie’s affidavit (CB 2/520)

Page 38: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

38

Budapest that weekend. The main purpose of the letter, however, was to explain the

alteration: ie why instead of embarking at Budapest, passengers would be taken by

coach to Vienna to board the Scenic Sapphire. No options were presented to

passengers about cancelling the tours and re-scheduling them for later in the year.

233. Plainly, there was a real and substantial risk that these cruises would be substantially

disrupted, in respect to cruising time. The cruises should have unilaterally been

cancelled by the defendant. At least passengers should have been provided with the

option of re-scheduling their cruises at some later point in the year.

STC120613.1 & STC120613.2

234. On 4 June 2013, Justin Brown advised Glen Moroney that guests on these cruises who

voluntarily wanted to cancel could do so without penalty. This option was not,

however, to be advertised243.

235. By 11 June 2013, the Main-Danube canal remained closed, there was a navigation ban

on the upper Danube and flooding was expected to peak between Hungary and

Budapest. A state of emergency was declared, affecting Budapest. STC030613 remained

stuck in Bamberg, and the navigation route between Budapest and Mohacs (in

Hungary) was scheduled to re-open no sooner than 15 June 2013.

236. On 11 June 2013, Kim Scoular suggested that passengers anxious about tours scheduled

for late June could be assisted by re-scheduling their tours for later in the 2013/14

year244.

237. On 11 June 2013, Donna Willis foreshadowed that an eblast would be sent to the

Australian and New Zealand agents of passengers scheduled to embark the following

day at Budapest on STC120613.2245. There is no evidence as to whether or when such

message was ever conveyed to agents, let alone passengers for this cruise. Be that as it

may, and assuming in Scenic’s favour that the message was transmitted to the

passengers on this cruise, the message anticipated that water levels may disrupt the

cruise; and that there may be certain closed sections of the river. The only solution

offered to passengers was ship swaps. No offer or alternative was provided to

passengers on this cruise to cancel and re-schedule the tour for later in the year or

2013-2014.

238. Again, there was a real and substantial risk that these cruises would be substantially

disrupted, in respect to cruising time. Passengers should have been provided with the

option of re-scheduling their cruises at some later point in the year.

243 Ex P32 (CB 6/1851-1852) 244 EX P49 (CB 6/2018-2019) 245 Ex D47 (CB 6/2017)

Page 39: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

39

Content of explanation of options

239. If, as is submitted, an option should have been presented to passengers to cancel

(where it was unnecessary for the defendant to unilaterally cancel) and to re-schedule

their cruises in advance of the embarkation of the cruises, an issue arises as to how that

option should be explained. Plainly, the option should be provided with some

explanation, or disclosure. The precise content of the explanation varied in accordance

with the specific circumstances affecting each individual cruise. However, the common

thread should have been to the following effect:

‘There has, for the past few months, been a very high (possibly unprecedented)

level of flooding along the cruise route for your tour, which has affected river

levels such that there is a real and substantial prospect that your scheduled tour

will be significantly disrupted, to the extent that the tour involves cruising along

the rivers. As to how much disruption there might be, we cannot say. However

where cruising cannot occur, this will mean much more transportation by bus

(where that is possible) and accommodation and dining on-shore in order to get

you to the places you want to go to on land. We propose to do what we can to

reduce interruption, but we cannot guarantee that you won’t experience

significant disruption to cruising time: it could be 2 days, it could be 5 or 6,

maybe more. We can, if you wish, cancel the tour now and look into providing

refunds. Alternatively, we can also offer to delay your cruise to some future point

within the next 12 months. Please let us know what you would like to do’.

240. As indicated there may be slight variations according to the particular cruise. Where the

cruises have occurred in close temporal proximity to other cruises affected by river

levels, it would also be reasonably expected that some reference might be made to that

circumstance as well. Thus, it might be expected that for cruises scheduled to occur on

3, 8, 10 and/or 12 June 2013, reference might be made to the fact that ships that had

embarked on 25 and 27 May 2013 had suffered a major loss of sailing days. For the

Evergreen cruise due to depart on 8 June 2013, it might have been expected that the

prediction of Angus Crichton – that the cruise was only likely to enjoy 50% of

scheduled sailing time – might be imparted.

241. Scenic disputes the above contentions. Its proposition is, apparently, that any

hypothetical warning, or disclosure, to passengers would have had to include a

prediction quantifying the extent of the likely disruption. That is not so. The plaintiff

accepts that any prediction by Scenic as to the extent or nature of disruption would be

imprecise. A predication is just that. It is not a promise. But when Scenic knew, for

example, that a major part of the cruise-path had been closed, that circumstance itself

says something as to existence and magnitude of a risk that that the cruise that had

embarked, and/or a cruise shortly to embark, was likely to be disrupted. Indeed, it is the

imprecision and uncertainty as to how long a cruise was likely to be disrupted which

generated the need for disclosure and the presentation of alternative options.

Page 40: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

40

When to present the explanation

242. As has been noted, for certain cruises scheduled to embark in June 2013, Scenic’s

personnel had considered the option of cancellation several days in advance of the date

of embarkation. Further, there were instances where passengers were presented with

letters from Scenic prior to embarkation, indicating a ship swap or change in itinerary.

243. The testimonial evidence of the plaintiff’s witnesses indicates that there was staff,

particularly cruise directors (Scenic employees) who convened the passengers on the

night before or date of embarkation before the point of actual embarkation onto the

various ships. There does not appear to be (and the defendant has not taken any steps

to establish) any impediment preventing the defendant, through its cruise directors, to

provide the explanation and present the option to passengers just prior to embarkation,

if not a day or days before.

244. As indicated in the Opening address, for those instances (i.e. all cruises save for cruises

2 – 3) where the option of cancellation should have been provided to passengers before

they embarked, the option should have been provided as follows:

No. Cruise code Date by which option should have been provided (European time zone)

1 FRCR190513.1 18 May

2 STC200513.2 Not Applicable

3 EGFC250513.1 Not Applicable

4 STC270513.1 25 May

5 STC270513.2 26 May

6 STC290513.1 28 May

7 STC290513.2 28 May

8 STC030613.1 2 June

9 EGFC080613.1 6 June

10 STC100613.1 8 June

11 STC100613.2 8 June

12 STC120613.1 11 June

13 STC120613.2 11 June

245. For cruises 2-5 (incl), where it might be said that the risk of substantial disruption to the

cruising experience emerged after the date when the cruises embarked, the option of

cancellation and the provision of ‘equitable’ refunds should have been provided, as

follows:

No. Cruise code Date by which option should have been provided

2 STC200513.2 27 May

3 EGFC250513.1 30 May

4 STC270513.1 30 May

5 STC270513.2 3 June

Page 41: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

41

2.3 Non-Compliance with Consumer Guarantees

246. This is not a case where the outcome of the question whether the guarantee of care and

skill has been complied with mandates the outcome of whether the purpose or result

guarantees were complied with.

2.3.1 Principles concerning the purpose guarantee

247. Where a supplier in trade or commerce supplies services to a consumer and the

consumer, expressly or by implication, makes known to the supplier any particular

purpose for which the services are acquired, there is a guarantee that the services (and

any product resulting from the services) will be reasonably fit for that purpose (ACL, s

61(1)).

248. Where the consumer makes known the result s/he wishes to achieve, s/he is at the

same time specifying the ‘particular’ purpose of achieving that result246.

249. Section 61(1) of the ACL closely resembles the former implied warranty in s 74(2) of

the Trade Practices Act. Authorities that had considered that earlier provision indicated

that:

a. It is a question of fact whether the services, or the finished product from the

services, were reasonably fit for the purpose247;

b. A breach of the warranty could occur without any negligence by the defendant.

In this sense, liability is strict248.

250. This guarantee is ‘more strict’ than the result guarantee249, since a result is less subjective

than a purpose250.

2.3.2 Principles concerning the result guarantee

251. Where a supplier in trade or commerce supplies services to a consumer and the

consumer, expressly or by implication, makes known to the supplier the result that the

consumer wishes the services to achieve, there is a guarantee that the services (and any

246 Taperell, Vermeesch & Harland, Trade Practices and Consumer Protection (3rd ed, 1978) [1741], p 837 247 Hardwick Game Farm v Suffolk Agricultural Poultry Producers Association [1969] 2 AC 31 at 115, cited in Heydon, Trade Practices Law [16.760] 248 Gharibian v Propix Pty Ltd, t/as Jamberoo Recreational Park (2007) ATPR 42-171; [2007] NSWCA 151 at [62]; followed in Fugro Spatial Solutions Pty Ltd v Cifuentes [2011] WASCA 102 at [144]; Schepis & Ors v Elders IXL Ltd (1987) 40-759 at 48,219; Corones, The Australian Consumer Law (2nd ed, Thomson Reuters) [9.390] 249 Taperell, [1741], p 837 250 Explanatory Memorandum to the Trade Practices Amendment (Australian Consumer Law) Bill (No.2) 2010

Page 42: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

42

product251 resulting from the services) will be of such a nature and quality that they

might reasonably be expected to achieve that result (ACL, s 61(2)).

252. Under the former s 74(2) of the Trade Practices Act, breach of the warranty could occur

without any negligence by the defendant.252 This reflected the position at common law,

where a supplier contracting to produce a specified result may be liable if the result is

not realized253. It has observed that it is expected achievement that is important in this

context254. Liability is strict255.

253. Whether the services might reasonably be expected to achieve the result is a question of

fact256.

2.3.3 The exceptions in s 61(3) of the ACL do not apply

254. The premise underling the exception, or presumption, is that the consumer usually

acquires the services of the particular supplier because its skills or knowledge are

beyond those of the consumer.

255. There is no suggestion that Mr Moore, or any of the other group members who gave

evidence, ignored the supplier’s advice, or perhaps stipulated that the supplier exercise

their skill or judgment in a certain way. The presumption of actual reliance is not

rebutted in the instances of Mr Moore or the other group members who gave evidence.

256. The defendant pleaded a lack of actual reliance. It did not plead an absence of

reasonable reliance (if there was actual reliance). It would, at any rate, be difficult to

conceive that it was unreasonable for the plaintiff to rely upon the defendant in

circumstances where the defendant did not clearly disclaim responsibility for Mr Moore

and others relying upon it’s skill or judgment, say, in determining whether a cruise tour

should proceed (prior to embarkation) or continue (once embarked).

257. A recurring feature, however, of the cross-examination of the plaintiff’s witnesses was

that they were aware of the risk that cruises may be disrupted because of river levels

before they set out. Conceptually, it does not matter for this purpose whether such

awareness sprang from awareness of the content of Scenic’s terms and conditions. It is

not part of the case for the plaintiff or group members that they were ignorant of such

risk. Their contention is that they did not bargain for a situation where the purpose or

result that they had made known to Scenic would be substantially diminished

(“compromised”). Awareness of a risk did not negate the existence of the consumer

guarantees in s 61(1) or (2).

251 An ordinary meaning of ‘product’ in this context may include the result from the services. 252 Corones, [9.390] 253 Young & Marten Ltd v McManus Childs Ltd [1969] 1 AC 454 per Lord Upjohn at 474; cited in Taperell et al [1741], pp 837-838 254 Crawford v Mayne Nickless ( 1992) 59 SASR 490 at 502.5 255 Taperell, [1741], pp 837-838 256 Warnock v ANZ Banking Group Ltd (1989) ATPR 40-928

Page 43: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

43

2.3.4 The purpose and result guarantees were not complied with

258. The ACL imposed upon Scenic the obligation that the purpose or result of the services

it performed (including, relevantly, decisions whether or not to cancel or delay tours)

would be reasonably fit for the purpose or result desired by the passengers. They were

not. For all of the subject cruises, the result or outcome, albeit in differing degrees,

followed a pattern: a distressing and disappointing experience marked by discomfort

and upheaval arising from the substantial substitution of coach travel and on-shore

accommodation, for travel by cruise, generally over many days (see the table located at

paragraph 36, above).

259. It is true that some cruises were disrupted more than others: the cruises that embarked

on 12 June 2013 (and one of them on 10 June 2013), in the result, suffered a day or two

in terms of disruption of cruising time. Even in that case, however, this was still not an

insubstantial disruption affecting the result or purpose that group members bargained

for. In terms of whether the result or outcome was reasonably fit for purpose, group

members may have tolerated disruption measured in minutes, perhaps even some

hours, but not a day or days, and to the extent that even a day or two was lost, that

would still represent a diminution in value set against what was paid for in the tour

component of the booking price.

260. To reiterate, it is unnecessary, in respect to these consumer guarantees, to establish fault

on the part of the defendant. It is unnecessary, therefore, to establish whether the

defendant knew, or should have known (through the means available to it) that the

cruising component of the tour was likely to be disrupted before that occurred. To the

extent that the defendant relies upon forces at play that hindered achievement of the

purpose or result guarantees, this is considered in the section below concerning s 267 of

the ACL.

261. The defendant contends that a failure to cancel a cruise could not amount to non-

compliance with these guarantees, but, to the contrary, a decision to cancel (before or

after embarkation) would be antithetical to the purpose and result guarantees, because

cancellation would mean that the object of the service – the supply of a relaxing,

recreational experience – would not be achieved. Moreover, the defendant says, there

would have been incidental inconvenience and expense to the passenger if such

decision to cancel had been made.

262. However, if, as the plaintiff contends, the service to be supplied required monitoring

and management before or after a cruise had embarked, a decision to cancel, or a

decision to offer the opportunity for passengers to cancel, where those decisions were

justified, would be seen as a service that was reasonably provided, and therefore would

not amount to non-compliance with the obligation. Moreover, it would not just be a

decision to cancel. The decision to cancel (or option to cancel) would (or should) be

accompanied by the option of a re-schedule at a later date. If that option was exercised

by a passenger, the purpose or result desired by passengers (and implicitly made known

to the defendant) would be deferred; not defeated. If, alternatively, the option of a

refund was provided, and exercised, then although the original purpose and result

sought to be achieved may not have been exercised, for the purposes of s 267,

Page 44: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

44

passengers would have no real grievance (other than fleeting disappointment) – they

would have received their money back. In short, the exercise of the options that should

have been provided would have meant that no loss would have been sustained.

263. In this case, it was the decision to embark, if not, the decision to continue proceeding

with the cruises, in the face of expected or actual disruption, that produced the

outcome or result which was the antithesis of the purpose or desired result: what

defeated the purpose or result sought to be achieved by the passengers was the

disappointment and distress they experienced and the grievance that they did not

substantially receive the value for what they had bargained for when each of them paid

their tour price.

2.3.5 Principles relating to the care and skill guarantee

264. Where a person (in trade or commerce) supplies services to a consumer, there is a

guarantee that services will be rendered with due care and skill (ACL, s 60)

265. The legislative intent is that this guarantee would apply in a similar way to the implied

warranty in the repealed s 74(1) of the Trade Practices Act. This provision was interpreted

so as to require the service to be of a quality that could reasonably be expected from a

competent person in the particular trade. The supplier would be liable in respect of the

services if s/he has, through a want of skill, fallen below that standard257, or put another

way, the warranty was breached if the service was performed in a careless or unskilful

way258.

266. Parliament chose the expression ‘due’ care in preference for ‘reasonable’ care. It has

been suggested that ‘due’ care is a higher standard than ‘reasonable’ care259. What is

‘reasonable’ is to be assessed objectively. That may be affected where the service

provider professes to have special skill260.

2.3.6 The care and skill guarantee was not complied with

267. For the reasons set out in section 2.2.4 above, save for the cruises 2 & 3, the defendant

was, or should have been, aware of facts that indicated that there was a real and

substantial risk or prospect that the cruising component of these tours would be

disrupted before each cruise embarked. The option of unilateral cancellation was

plainly considered by the defendant without reference to the wishes of the passengers,

especially for the cruises in early June 2013. The option of providing refunds and re-

scheduling tours was also considered.

268. For cruises 1 and 8-11, these should have been unilaterally cancelled before the cruises

had embarked. For cruises 6 & 7, these cruises probably should also have been

unilaterally cancelled, albeit that the case for unilateral cancellation in those cases is of

257 Taperell, Vermeesch & Harland, Trade Practices and Consumer Protection (3rd ed, 1978) [1740], p 836 258 Corones, The Australian Consumer Law (2nd ed), [9.355] 259 Corones, [9.430] 260 As occurs in the law of negligence: Rogers v Whitaker (1992) 175 CLR 479 at 483

Page 45: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

45

lesser force.

269. In all cases other than cruises 2-3, the option of voluntary cancellation should have

been canvassed before embarkation. For cruises 2-5, the option of cancellation and

partial refunds (or re-scheduling) should have been provided.

270. To the extent that these alternative options were canvassed internally, the defendant’s

personnel were (at best) positively discouraged from promoting them. Indeed, the

defendant’s attitude was to manage or re-align its passengers’ expectations, so as to off-

set the loss of cruising time, in order to have passengers put up with much more coach

travel and accommodation on-shore. In other words, they could endure a holiday

experience with less benefits and to a lesser standard than what they paid for. The

defendant’s position was, apparently, that just because passengers were not cruising did

not mean that they were not enjoying the holiday experience. That is to miss,

altogether, the essence of the experience that Scenic’s promotional material emphasised.

271. In this, what is plain is that the defendant did not, in effect, take its passengers into its

consideration. Conceivably, some passengers might have been willing to negotiate to

receive an inferior ‘product’ than what they had bargained for: at the risk of

generalization, perhaps younger, fitter and healthier persons may have been prepared to

suffer the substantial loss of cruising experience in order to enjoy land destinations,

even if that involved more extensive coach travel and walking then which had been

scheduled. But because Scenic did not inquire, or offer alternatives, it was never in a

position to know. Scenic, instead, gambled that it could proceed to the point of

disembarkation, providing incidental or associated services whilst being indifferent to

whether, in doing so, its services were, or were likely, to substantially satisfy the desired

purpose or result made known to it by the passengers.

272. This should not have been Scenic’s decision to unilaterally make. Even by the terms and

conditions upon which it places so much store, where circumstances occurred that were

beyond the defendant’s control such that it was unable to provide the tour in

accordance with the itinerary, the defendant promised to use “reasonable endeavours to

provide or arrange appropriate alternatives” (cl 2.7) (emphasis supplied) . As explained

above, in Section 2.1.2 of these submissions, it is hard to see how the exercise of the

evaluative judgment that cl 2.7 required could be undertaken without reference to

consideration of what alternatives may have been suitable for the purposes of the

defendant’s passengers.

273. Scenic points to the absence of expert opinion evidence from the plaintiff as to what

reasonable tour operators would do. But this omission is hardly momentous in

circumstances where the reasonable practices of tour operators was demonstrated, in

part, by the conduct of Scenic’s competitors who did unilaterally cancel cruises in the

first ten days of June 2013. Scenic seeks to explain away its competitors’ conduct by

suggesting that the reason for the decision of other operators to cancel was simply a

lack of ships.

Page 46: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

46

274. That is not, however, how the competitors explained the problem. In an undated

letter261 from Viking cruises, but apparently referable to a cruise that occurred on 2 June

along the Danube (‘Romantic Danube’), unlike Scenic, Viking was prepared to provide

a partial refund as well as credits to another cruise to those passengers who had had

their cruise disrupted. Viking made a point of contrasting the reasons why it allowed

one of its ships to cruise, but not another. The cruise which was cancelled before the

embarkation date on 2 June 2013 was cancelled because it had become stuck in

Frankfurt, along the Main River, from late May and could not reach Nuremberg in time

for the next cruise.

275. Another partial explanation for the refund and credit to another cruise was that Viking

did what Scenic/Evergreen did: as part of a contingency plan, it provided extra bus

rides and hotel stays in an attempt to get passengers to tourist destinations: a plan

which Viking conceded was “unsuccessful” in providing an “enjoyable experience”.

This is what led to Viking’s apology262.

276. APT’s announcement of cancellations for scheduled cruises on 4 June 2013, for

example, was founded upon its “indepth assessment of current and forecast water levels

for the coming days”263. APT had a capacity for ship swaps as well264. On the same day,

when explaining why he decided to cancel the 4 cruises scheduled for 6, 7 & 8 June,

Chris Hall, CEO of APT Tours265, referred to “safety concerns due to the high flood

waters.”266

277. On 4 June 2013 (a Tuesday), internal Avalon communications indicated that Avalon did

not expect any movement of ships before the end of the week267.

278. On 6 June 2013, Viking Cruises indicated that its decision to cancel cruises scheduled

for 8 & 9 June 2013 was explicable by the fact that the Danube River would continue to

be closed from Nuremburg til Budapest until 16 June 2013268.

279. On 6 June 2013, Uniworld explained that its decision to cancel cruises from Prague to

Belgrade and Prague to Vienna, scheduled for 7 June 2013, was explicable to ‘record

high water levels’269.

280. At a broader level, however, Scenic’s point about the omission of expert evidence is a

smokescreen for its own failure in this proceeding to explain why it did not proceed in

accordance with Justin Brown’s convictions and its unexplained failure to explain why it

conducted itself the way that it did.

261 Ex D61 (CB 7/2508) 262 Ibid 263 Ex P33 (CB 6/1870) 264 Ibid 265 Ex P33 (CB 6/1870) 266 Ex P30 (CB 5/1836) 267 Ex D30 (CB 5/1826) 268 Ex P34 (CB 6/1921) 269 Ex P37 (CB 6/1954)

Page 47: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

47

281. In the event, and for reasons which Scenic has not been willing to divulge to the Court

under scrutiny, the options favoured by Justin Brown in respect to some of the cruises

were not pursued. The Court should infer such explanations as Scenic had do not assist

Scenic’s position.

282. Scenic also posits that any decision to cancel before or after embarkation, or any offer

of alternatives to its passengers, may have meant that the aspirations of those

passengers who were more willing to take risks (by commencing or continuing a cruise)

would be disregarded; that other passengers might be ‘abandoned’. It says that,

depending upon how many passengers may have wished to continue to travel, there

may have been commercial impediments to proceeding. This supposition, or

explanation for why Scenic conducted itself as it did, is not established in evidence.

283. Moreover, just as with the position before a cruise has embarked, whereby Scenic may

cancel a cruise if there are insufficient bookings (which would disappoint those

passengers who had booked a tour, expecting it to proceed), so too a decision to cancel

because of actual or anticipated river levels (either unilaterally, of because after an

option to cancel had been exercised there were insufficient passengers willing to

proceed) would also likely displease some passengers. Those ‘disappointed’ in that sense

would not have suffered a compensable loss. To the contrary, those passengers would

either receive an equitable refund or the opportunity to re-schedule a tour at a later

point in time. Conceivably, some might also have looked to travel insurance

arrangements in the event that they could not recover from Scenic. Faced, then, with a

potential choice between inconveniencing some who might be temporarily put out if a

cruise did not commence or proceed, because of a cancellation decision, for which

Scenic could not reasonably be criticised, and inevitably disappointing others for whom

there was a real and substantial risk that the purpose and result that they had hoped for

(the luxurious holiday cruise of a lifetime) would not be achieved, Scenic preferred the

latter course.

2.4 Exclusions and limitations on liability do not apply

2.4.1 The proper construction of the clauses

284. By its Defence, the defendant rely upon clauses in cll 2.10(h), 2.12(b), 2.13 and 2.14(b)

of its Terms and Conditions, to either exclude altogether or limit its liability.

285. Upon its proper construction, cl 2.12(b) does not apply in this proceeding. The

plaintiff (and group members) do not claim loss arising from conduct of the service

provider. In this proceeding, the loss that was suffered arose from the defendant’s

conduct. The point is considered further in Section 2.5, below.

2.4.2 Section 64 of the ACL

286. Section 64 of the ACL avoids contractual provisions to the extent that it (or they)

purport to exclude, restrict or modify, or has the effect of excluding, restricting or

modifying certain types of clauses. If an exclusion clause is void under s 64, it has no

force or effect.

Page 48: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

48

287. An obvious example is a clause which purports to exclude, altogether, the existence of

the guarantees, however, a clause only purporting to restrict the application of the

guarantee is no more effective. Similarly, a clause purporting to limit the monetary

liability of the supplier for consequential losses is also ineffective270.

288. All of the exclusion clauses relied upon by the defendant infringe s 64 of the ACL.

They all effectively exclude (or limit) liability for what, in the circumstances, was non-

compliance with the consumer guarantees.

289. Against the possibility that s 64 of the ACL does not apply, the exclusion and limitation

clauses would not be effective because it is unconscionable in the circumstances for

Scenic to rely upon them. Further, or alternatively, the provisions are unjust or unfair.

2.4.3 Unconscionable conduct

290. Section 21(1) of the ACL prohibits persons, in trade or commerce and in connection

with the supply of services to a person, from engaging in conduct that is, in all of the

circumstances, unconscionable.

Considerations of whether conduct is unconscionable

291. Section 21(1) is not confined by the notion of unconscionable under unwritten law (s

21(4(a))).

292. In considering whether conduct, to which a contract relates, is unconscionable, the

Court’s consideration of the contract may include consideration of its terms and the

manner and the extent to which the contract is carried out (ie it is not limited to

circumstances relating to the formation of the contract): s 21(4)(c). The provision is not

limited, in its scope, to ‘consumers’.

293. The concept of ‘unconscionable’ is not defined. Ordinarily, the conduct must be doing

what would not be done in good conscience, or is irreconcilable with what is right or

reasonable: ASIC v National Exchange Pty Ltd (2005) 148 FCR at 140. It is a value-laden

term and indicates a degree of moral tainting. It may include undue pressure and unfair

tactics, taking advantage of vulnerability or a lack of understanding: Tonto Home Loans

Australia Pty Ltd v Tavares [2011] NSWCA 389 at [291]; ACCC v Lux Distributors Pty Ltd

[2013] FCAFC 90 at [41]; Paciocco v ANZ (2015) 321 ALR 584; [2015] FCAFC 50 at

[296] – [306].

294. A non-exhaustive list of discretionary considerations that a court may have regard to in

determining whether a supplier has contravened s 21 include:

a. Relative bargaining power of the supplier and customer (s 22(1)(a))

270 Eg Dillon v Baltic Shipping Co (1989) 21 NSWLR 614 at 642B-C

Page 49: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

49

b. Whether as a result of the supplier’s conduct, the customer was required to

comply with conditions that were not reasonably necessary for the protection of

the supplier’s legitimate interests (s 22(1)(b));

c. Whether any undue influence or pressure was exerted on, or any unfair tactics

were used against the customer by the supplier (or a person on the supplier’s

behalf) (s 22(1)(d)

d. The extent to which the supplier was willing to negotiate the terms and

conditions of the contract, the terms and conditions of the contract, the conduct

of the supplier and customer in complying with the terms and conditions, any

conduct that the supplier or customer engaged in, in connection with their

commercial relationship, after they entered into the contract (s 22(1)(j)

Analysis

295. The action for unconscionable conduct is set out in paragraphs 17E to 17I of the

pleading. It embraces procedural and substantive ‘unconscionability’.

296. As to its procedural aspects, it is the circumstances that the defendant made no effort

to ensure that the terms and conditions (including relevant exclusions) were brought to

the attention of passengers until after tour bookings had been made and paid for.

Passengers became bound once they had paid their non-refundable tour deposit. (per cl

1.2 of the terms and conditions). In answer to this, the defendant initially accepted this

position271. However, it subsequently changed its position to contend272 that a new, or

substituted contract came into existence even after the deposit had been paid when

passengers actually signed the terms and conditions. Such proposition should be

rejected: any document containing the terms and conditions signed by the passengers

itself indicated that the passenger would have been bound by the time they had paid

their deposit. A new contract would only be substituted if it contained materially

different terms. In the circumstances, the group members were bound when they paid

their deposit; not when some of them signed terms and conditions.

297. It was a matter of chance whether, at the time they paid their deposits, passengers were

even aware of the existence of the terms and conditions; let alone their content. Mr

Willems and Mr Peattie admitted that each was aware of the existence of the terms and

conditions before booking. Mr Cairncross read the terms and conditions, but it was not

entirely clear whether that was at the time he made his booking or paid the balance of

his tour price273. Others (Messrs Moore274, Holgye275, Britten276) had not read the terms

and conditions prior to their bookings. Another passenger on cruise STC120613.1

complained that the terms and conditions were not sent to him before he paid his tour

price277.

271 T 38.40 272 T 44.2 273 T 113.21-.34 274 T 54 275 T 133.7 276 T 145-146; Britten, pars 8-13 (CB 2/422). 277 Ex D54 (CB 6/2093)

Page 50: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

50

298. In each case, however, the cross-examination of the plaintiff’s witnesses stopped short

of attempting to elicit admissions that these passengers understood and accepted

Scenic’s view that, pursuant to the terms and conditions, Scenic was entitled to convert

a cruise experience into an extended bus tour for a substantial period.

299. For those passengers who were even aware of the existence of the terms and

conditions, none of these passengers could reasonably have been expected to be

particularly assiduous in studying them. It was more likely that passengers may have had

regard to them when they received a special booklet, after paying the balance of the

tour price, where that booklet contained the itinerary and map. It was only at this point

that Scenic took a positive step to bring the terms and conditions to the (booked)

passenger’s attention.

300. That Mr Moore was ignorant of the terms and conditions by the time he had paid his

non-refundable deposit279 is not to the point. Scenic’s terms and conditions stipulated

he was bound by that point and Scenic had no basis for assuming that an excited

passenger in the position of Mr Moore, who would likely be focussing on the benefits

of the experience Scenic promoted, had understood the fine print. The point, here, is

that the terms and conditions, written in (barely legible) small font, were tucked away

towards the back of a voluminous document280 and it was only once a passenger had

booked and paid up his or her money, that they were more prominently brought to a

passenger’s attention. This occurred by means of the provision of a booklet that

contained a passenger’s itinerary, a map of the cruise and the terms and conditions.

301. In these circumstances, it could hardly be said that there was any, or any reasonable,

bargaining as to the content of the terms and conditions. In a real sense, Scenic was

relying upon the inertia (or lack of inquisitiveness) of the run of the mill passenger who

would, at the time of booking and paying a deposit, naturally be focussing and excited

about the prospect of a luxurious holiday experience; rather than being concerned

about the fine print.

302. Thus, the circumstance that a passenger like Mr Moore became bound to the contract

at the time he paid his non-refundable deposit means that it is irrelevant that Mr (and

Mrs) Moore may have later signed the terms and conditions at or about the time he

paid the balance of his tour price281. Depending upon when that booklet was received,

in terms of the proximity to the departure date, if passengers, once apprised of the

terms and conditions, were so dissatisfied with them as to want to cancel the tour, the

passengers might then be liable to a cancellation fee282.

303. The defendant apparently assumed, and still relies upon the proposition, that either

passengers were either previously aware, or would, or should become aware (by reading

and understanding) of the terms and conditions themselves, or have them explained to

279 T 54 - 56 280 Ex P DM1 (CB3/773-774. The brochure begins at CB 3/562) 281 T 79-82 282 This is the effect of cl 2.6(d) of the terms and conditions (Ex P8, CB 4/1235)

Page 51: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

51

them by local travel agents, whom the passengers approached to make the bookings,

prior to, or at the point of the bookings being made.

304. The assumption that the local travel agents would answer any queries in relation to

terms and conditions, or even knew of them, was misconceived. Further, there is no

evidence of the defendant’s practices (or arrangements with retail travel agents) to

support the assumption in any event.

305. Moreover, it is incorrect to impute to the passengers any knowledge held by the local

travel agents in any event. Any knowledge of the terms and conditions by travel agents

for the customers would not be necessarily imputed to the customers themselves. In

this context, a travel agent is essentially a broker, selling travel products, and acting a

‘middleman’ between potential traveller and the supplier and it is unclear whether the

agent is acting for one, the other, both, or merely for itself283. In this context, where the

supplier (the defendant), as tour operator, is relying upon brokers to dispense or

disseminate information such as the content of terms and conditions, such disclosure

should be taken to be on behalf of and for the benefit of the supplier. To that extent,

the agent would be the agent of the supplier in that respect.

306. Thus, at the procedural level, plainly, the terms and conditions (all, of which were

standard terms of a consumer contract), as a whole, were not the subject of any real, or

reasonable negotiation, prior to the plaintiff (and other group members) being bound

by them. They were not the subject of any explanation to passengers, in terms of their

legal or practical effect. Clauses 2.10, 2.12 – 2.14 all were exclusionary clauses. It was

important that these passengers be made aware of them and it was not until the tour

bookings were made that the defendant took any positive step to make the passengers

aware of them.

307. At a substantive level, the defendant was very conscious about the existence of the

exclusionary clauses. In late May 2013, once the difficulties of the South of France

cruise became apparent, Justin Brown inquired of one Scenic’s UK Operations

Manager (Emma Lindsay) whether Scenic’s terms and conditions284 could effectively

“eliminate” compensation that might arise to passengers under UK law. This was in a

context where it had been reported that British guests departed the cruise in question

and a query had been raised as to whether they might be entitled to refunds285.

308. Scenic’s whole approach during the pendency of the cruise period (and continuing

throughout this proceeding) has been that where variations had to be made because of

rising river levels, it was simply a misfortune for passengers for which it bore no

responsibility. This was irrespective of whether the purpose or result for which the

passengers paid their money and booked their tickets was reasonably accomplished.

283 Cameron v Qantas Airways Ltd (1995) ATPR 41-417 at 40,436. 284 Presumably the terms and conditions applicable to British guests were the same as, if not at least substantially similar to, those applicable to Australian passengers. 285 Ex P14 (CB 5/1652-1653)

Page 52: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

52

309. But where circumstances arose, as the plaintiff says they arose in this proceeding, where

consumer guarantees were not complied with, and where that occurred because the

defendant was aware of the real and substantial risk that passengers would have their

cruising experience disrupted (because of river levels) before they embarked, and/or

refused to provide options to cancel cruises to passengers after the cruises had

embarked (when the risks had materialized) it is unconscionable for the defendant to

continue to retain the monies paid to it by the passengers and to rely upon the

exclusion clauses as justification for refusing to pay refunds.

310. It is unconscionable to retain monies paid by passengers on a particular (promoted)

basis (a luxurious, relaxing cruise) when the defendant knew, or should have known

(before embarkation), and/or became aware (after embarkation) that there was a not

insignificant risk that a substantially different experience would occur. That is

particularly so where the basis for retention of the monies is the content of terms and

conditions of a contract which became binding upon passengers as early as when they

had paid their deposits and Scenic took no steps to ascertain that passengers

understood that Scenic could continue to retain the whole of the tour price if, in fact,

the purpose or result of the tour experience was substantially diminished.

2.4.4 Unjust terms

311. Upon finding a provision to be unjust (in the circumstances relating to the contract at

the time it was made), the Court may:

a. decide to refuse to enforce any or all provisions;

b. declare the contract wholly or partly void (Contracts Review Act 1980 (NSW), s 7)

Considerations as to whether provisions are unjust

312. In determining whether a provision in a contract is unjust in the circumstances relating

to the contract at the time it was made), the Court shall have regard to the public

interest and to all of the circumstances of the case, including the consequences or

results as those arising in the event of compliance with any or all provisions, or non-

compliance with, or contravention of, any or all of the provisions (Contracts Review Act, s

9(1)).

313. Mandatory considerations that the Court shall have regard to (to the extent that they are

relevant to the circumstances) in determining whether provisions are unjust include:

a. Whether or not there was any material inequality in bargaining power between

the parties to the contract;

b. Whether or not prior to or at the time the contract was made, its provisions were

the subject of negotiation;

c. Whether or not it was reasonably practicable for the party seeking relief to

negotiate for the alteration of or to reject any of the provisions;

Page 53: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

53

d. Whether or not any provisions impose conditions that are unreasonably difficult

to comply with or not reasonably necessary for the protection of the legitimate

interests of any party to the contract,

e. Whether any undue influence, unfair pressure or tactics were exerted on or used

against a party seeking relief under the Act by any other party (or any person

acting or appearing or purporting to act for or on behalf of the party);

f. The commercial or other setting, purpose and effect of the contract (Contracts

Review Act, s 9).

314. The concept of ‘unjust’ is defined (s 4) to include the notions of something that is

“unconscionable, harsh or oppressive”, however it is by no means limited to those

concepts: West v AGC (Advances) Ltd (1986) 5 NSWLR 610 at at 620. Contracts, or

contractual provisions may be unjust because its terms, consequences or effects are

unjust (substantive injustice) or because of the unfairness of the methods used to make

it (procedural injustice). Most unjust contracts will be the product of both procedural

and substantive injustice: West at 620. At the heart of the evaluative exercise that courts

use to determine whether a contract is unjust is recognition of the inadequacy of one

party to protect his or her interests in the circumstances: Provident Capital Ltd v Papa

(2013) 84 NSWLR 231at [7].

Application

315. The plaintiff relies upon the same circumstances applicable to his action for

unconscionable conduct to contend that the exclusionary clauses were unjust terms. In

particular, there was no serious efforts made to draw the content of the terms and

conditions to the attention of passengers, at least until they were bound by them and

the effect of the application of the terms, should Scenic’s construction of the terms be

accepted, would be to allow it to continue to retain the monies paid to it in the

knowledge that the purpose, result and indeed bargain that passengers paid their monies

for would be substantially diminished.

2.4.5 Unfair terms

Relevant provisions

316. A term of a ‘consumer contract’ is void if the term is unfair and the contract is a

‘standard form contract’ (ACL, s 23(1)).

317. A ‘consumer contract’ is (relevantly) a contract for the supply of services to an

individual whose acquisition of the services is wholly or predominantly for personal,

domestic or household use or consumption (s 23(3)). There is a rebuttable presumption

that a contract is a standard form contract where that is alleged (s 27(1)). There is also a

list of mandatory matters that a court will take into account in determining whether a

contract is a standard form contract (s 27(2)).

318. A term in a consumer contract is unfair if:

Page 54: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

54

It would cause a significant imbalance in the parties’ rights or obligations arising

under the contract (s 24(1)(a)); and

It is not reasonably necessary in order to protect the legitimate interests of the

party who would be advantaged by the term (s 24(1)(b)); and

It would cause detriment (financial or otherwise) to a party if it was to be

applied or relied on (s 24(1)(c)).

319. The consumer carries the onus on the matters in s 24(1)(a) and (c); the supplier carries

the onus re s 24(1)(b): ACCC v Chrisco Hampers Australia Ltd [2015] FCA 1204 at [43].

320. ‘Significant imbalance’ is a factor regarded as established if a term is so weighted in

favour of the supplier as to tilt the parties’ rights and obligations significantly in its

favour. This may be by granting to the supplier a beneficial option, discretion or power,

or by imposing on the consumer a disadvantageous burden, or risk or duty: Director

General of Fair Trading v First National Bank Plc, per Lord Bingham at [17]; followed in

ACCC v Chrisco Hampers Australia Ltd [2015] FCA 1204 at [47]-[49] and in ACCC v

ACN 117372915 Pty Ltd (formerly known as Australian Medical Institute Pty Ltd) [2015] FCA

368 at [950].

321. It has been suggested that the question whether an imbalance should be regarded as

‘significant’ is resolved by answering whether the imbalance is ‘large, weighty,

considerable, solid or big’286.

322. By s 24(4), there is a rebuttable presumption that a term will not be reasonably

necessary in order to protect the legitimate interests of the party who would be

advantaged by the term.

323. Relevant matters that a court must take into account in determining whether a term is

‘unfair’ include:

a. The extent to which the term is transparent; and

b. The contract as a whole (s 24(2)).

324. A term is ‘transparent’ if it is:

a. Expressed in reasonably plain language; and

b. Legible; and

c. Presented clearly; and

d. Readily available to any party affected by the term (s 24(3))

(see Director General of Fair Trading v First National Bank plc [2002] 1 AC 481, per Lord

Bingham)

286 Miller’s Australian Competition and Consumer Law Annotated (38th ed, 2016) [1.S2.24.15], p 1660

Page 55: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

55

325. Section 24(2)(a) only requires the Court to consider transparency in relation to the

particular term that is said to be unfair and only in relation to the matters concerning

that term in s 24(1)(a) – (c).

326. Examples of unfair terms are:

terms that permit, or have the effect of permitting, one party (but not another)

to avoid, or limit performance of the contract (s 25(1)(a));

terms that permit, or have the effect of permitting, one party unilaterally to vary

the characteristics of the services to be supplied (s 25(1)(g).

327. The examples, or categories, of unfair terms (in s 25) are not exhaustive: Chrisco Hampers

at [96].

Analysis of cl 2.6(d)

328. The defendant admits that the subject contracts were consumer contracts and standard

form contracts287.

329. Clause 2.6(d) provides that any cancellation of the tour by the passenger prior to the

departure would result in cancellation fees being incurred at various staggered levels.

Where cancellations were notified 61 days or less before the departure date, this would

be at the level of 100% of the tour price.

330. Clause 2.10 generally provided the grounds upon which the defendant was entitled to

vary the passenger’s itinerary, in the event of certain circumstances. In this proceeding,

the defendant relies upon the grounds in sub-paragraphs (e)(1) and (f). The variation

comprises the substitution of another vessel or motorcoach for all or part of the

itinerary and also to provide alternative accommodation. By cl 2.10(h), the defendant

purported to disclaim liability for such variations.

331. Clause 2.6(d) caused a significant imbalance in the parties’ rights and obligations. This is

so because if, as the plaintiff contends, the proper performance of the defendant’s

consumer guarantees required it to provide an option to passengers to cancel the

cruises (as distinct from unilaterally cancelling the cruise itself) prior to the relevant

departure date, and if such option was exercised, the passenger would be liable to

essentially forfeiting its tour price, without having the tour re-scheduled. The

passengers should, in this case, be relieved against this form of forfeiture.

332. It would also cause detriment if relied upon by the defendant. Here, the clause would

have been relied upon: the defendant’s denial that the plaintiff and group members

suffered any loss flowing from non-compliance with the guarantees is centred upon the

proposition that the plaintiff and group members would have suffered loss anyway288.

That is because if, as its obligation to provide a service with due care required Scenic to

287 par 17D of the Defence, as amended. 288 Par 24(b) of the Defence

Page 56: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

56

present an option to passengers to cancel before they embarked on a cruise, they would

have been liable to pay the entirety of the tour price to Scenic as a ‘cancellation’ fee.

333. As a matter of substance, therefore, cl 2.6 is unfair. Relevant also to that determination

is the circumstance that the clause was neither presented clearly or readily available and

hence, was not ‘transparent’. The term appeared amid a series of other terms which

themselves were obscurely tucked in towards the back-end of the travel brochure.

334. The defendant has not adduced evidence on whether the provision was reasonably

necessary in order to protect the defendant’s legitimate interests. Accordingly, it has not

rebutted the presumption (s 24(4)) that the term was not reasonably necessary. It

should therefore be found that cl 2.6(d) is an unfair term.

Analysis of cl 2.10

335. The substantive effect of this provision (with its various sub-paragraphs) is to confer a

power upon the defendant to unilaterally alter the nature and extent of the touring

experience enjoyed by passengers, even if that was to thwart the purpose or result for

which they bargained for. The evidence shows the internal convictions of the

defendant’s personnel, at certain times, were that certain tours should be cancelled (with

passengers encouraged to re-schedule a new tour) and that refunds may be given in

certain circumstances. But where, as here, those convictions were not acted upon, by its

terms, cl 2.10 entitles the defendant to do what it liked, even to substitute a bus tour for

a cruising tour, without reference to the passengers, and if any passenger complained,

the passenger would be shown cl 2.10.

336. This is a paradigm example of an unfair term: s 25(1)(a) of the ACL.

337. The provision would cause detriment if relied upon. In this proceeding, the detriment is

very real: the defendant’s essential Defence is that it could properly substitute a vastly

different (and inferior) touring experience to that which it promoted, because of

circumstances beyond its control and not be liable for it.

338. Again, in the absence of any evidence establishing the provision was reasonably

necessary to protect its interest, the defendant has not rebutted the presumption that it

is not. It should therefore be found that cl 2.10 is an unfair term.

Defence

339. Neither cl 2.6(d) nor cl 2.10 of the terms and conditions could properly be

characterised as “defining” the subject matter of the contract, such as to fall within the

exception in s 26(1)(a) of the ACL.

340. The former provision dealt with a liability to bear a cancellation fee in the event of a

contingency.

Page 57: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

57

341. The latter provision concerned changes to tour price and variations to a tour itinerary

(as well as purporting to exclude liability for variations). The circumstance that parties

foreshadow circumstances in which their rights or obligations may change (and purport

to regulate what might occur if those circumstances come to pass) does not “define”

the subject matter of the service that is provided. In its interpretation of corresponding

legislation in Britain, the English Court of Appeal characterised a legislative provision

like s 26(1)(a) of the ACL as a provision that goes to the “core” of a contractual

arrangement. The English Court of Appeal determined that contractual provisions that

were contingent upon the occurrence of a particular event could not be the subject of

bargaining between supplier (in that case, a Bank) and the customer such as to amount

to core terms289. Another way of putting the point is that a term ‘defines’ the subject

matter of the contract where the consumer has a choice whether to acquire the service

having regard to the term290. That reasoning would not apply to an alteration of rights

or obligations arising from a contingent (and necessarily hypothetical) event.

2.4.6 Remedies for unconscionable conduct and unfair terms

342. These provisions appear in Chapter 2 of the ACL.

343. By s 237, a person (‘injured person’) who has suffered, or is likely to suffer, loss or

damage because of conduct by another person engaged in in contravention of (these

provisions), or is appearing, or purporting to rely upon a term that has been declared

(under s 250 of the ACL) to be an ‘unfair term’, to make such order/s as the Court

thinks fit.

344. Such order must be an order that the court thinks will compensate the injured person

(wholly or partly) for the loss or damage, or will prevent or reduce the loss or damage

that has been suffered, or will be suffered, by the injured person.

345. Without limiting s 237, the orders that a court may make under that provision against a

respondent includes:

An order declaring the whole or part of the contract void (s 243(a));

An order varying the contract (s 243(b));

An order refusing to enforce any or all of the provisions (s 243(c))

346. An order may be made under s 243 whether or not the Court makes an order under s

237 (s 244).

347. The Court may declare that a term is ‘unfair’ pursuant to s 250 of the ACL, or its

inherent jurisdiction.

289 OFT v Abbey National plc [2009] WLR (D) 69, cited in Corones, The Australian Consumer Law [6.70] 290 Explanatory Memorandum to Trade Practices (Australian Consumer Law) Bill 2010, [5.60]-[5.61]

Page 58: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

58

348. An injunction also lies to prevent the attempt to enforce an unfair term: s 232(3) of the

ACL.

Unfair terms

349. A declaration and order avoiding cll 2.6 and 2.10 should be made, at least in the suit of

Mr Moore. Alternatively, an injunction should be made so as to prevent the

defendant’s reliance upon those terms.

2.5 Responsibility for loss

2.5.1 Scenic’s service providers

350. When it came to performing the critical function of monitoring and managing the

cruise experience of passengers, either before or after embarkation of the scheduled

cruises, Scenic did not delegate those functions to its ‘service providers’: Scenic Europe

or Luftner. If it had, there would have been no reason for Justin Brown, Kim Scoular,

Angus Crichton and others to have engaged in the communications that they did with

Lucas Sandmeier and others who were closer to the events along the European rivers.

351. Moreover, delegation of such functions would not have reflected the arrangements

Scenic had with its passengers. Clause 2.7 (to reiterate) indicated that when

circumstances (including river levels or weather conditions) arose which were outside

“Our” control, and “We” were unable to provide the tour in accordance with the

itinerary, “We” would use reasonable endeavours to provide or arrange appropriate

alternatives. The personal pronoun is for Scenic, used in a context where cruise ships

have embarked.

2.5.2 The exceptions in s 267(1)(c) of the ACL do not apply for non-compliance with

the purpose or result guarantees

352. Section 267(1)(c) of the ACL provides an exception to a consumer’s right to take action

against a supplier for non-compliance with the purpose and result guarantees291. To

paraphrase, the exception arises where the failure to comply with (either) guarantee did

not occur only because of:

(i) conduct (including a representation) by some person other than the supplier

(or an employee or agent of a supplier); or

(ii) a cause independent of human control that occurred after the services were

supplied (emphasis supplied)

353. As a whole, the exception in s 267(1) generally deals with what, in general law, would be

regarded as true intervening causes – the ‘novus actus interveniens’ doctrine. The result

or purpose could not be achieved only because of (i) the conduct by third persons or (ii)

291 The exception does not apply where the non-compliance is with the due care guarantee in s 60 of the ACL.

Page 59: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

59

circumstances which, effectively, severed the causal link between the failure to achieve

the result or purpose and the non-compliance with the guarantee(s).

Scenic Europe personnel were not acting as independent contractors

354. The persons referred to in s 267(1)(c)(i) might include sub-contractors, although the

categories are not limited to that292. In relation to sub-contractors, or independent

contractors, suppliers will not be liable for the conduct of sub-contractors.

355. It is anticipated that the defendant will cite cl 16.1 of the services agreement between

Scenic Australia and Scenic Europe293 in support of its contention that personnel from

the latter were not agents, but independent contractors. Certainly, a statement by which

the parties identify what they understand to be their legal relationship is entitled to

weight. However, the Court looks to the substance, not the form of arrangements and

may characterise, for itself the arrangement294. In this case, there were other provisions

in the arrangements indicating that Scenic Europe personnel acted on behalf of, and as

agents, for the defendant:

a. Clause 4.1, which provides that STE is to deliver services “promptly in response

to … and to the satisfaction of STA”

b. Clause 12.2, which provides that in performing services, STE is to “make all

reasonable enquiries of STA to ascertain requirements and comply with all

reasonable directives and instructions provided by STA from time to time”

356. There are a range of indications in the defendant’s correspondence pointing to the

reality not only of a close collaborative relationship between STA and STE but that, on

occasions, STE acted in accordance with STA’s instructions and direction:

a. On 16 May 2013, in a different letter to guests, Kim Scoular referred to “our”

helpful cruise director (the concept of “cruise director” was itself defined in

Scenic’s terms and conditions as “Our guide on Your cruise who is Our

employee”);

b. On 29 May 2013, Lucas Sandmeier sought opinions from Scenic personnel in

response to options he presented to them295;

c. On 30 May 2013, Lucas Sandmeier expressed an apology to guests “on behalf of

Scenic Tours”296;

292 Another example may be a terrorist hijacking a cruise, preventing the cruise from proceeding. 293 The agreement begins at Ex D2 (CB 5/1356) 294 South Sydney District Rugby League Football Club v News Ltd (2000) 177 ALR 611; Dal Pont, Law of Agency (3rd ed, 2014) [1.6], p 8 295 Ex D22 (CB 5/1682) 296 Ex P16 (CB 5/1717A)

Page 60: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

60

d. On 2 June 2013, when commenting to his colleagues (Kim Scoular and Aleisha

Fittler) on water levels, Justin Brown foreshadowed that he would be talking with

Lucas Sandmeier about “our options”297;

e. Later on the same day, Brown set out what those options for current cruises

(including partial refunds and a return home) for Sandmeier298.

f. On 14 June 2013, Mr Kozma, of Scenic Tours Europe299, admitted to Mr

Willems that the European service provider was “just following directions from

Scenic in Australia who said they wanted to proceed with a bus tour”300.

357. It is not disputed that ‘nautical partners’, such as KD Cruise Services Ltd, who were

contracted to Scenic’s European ‘agents’, were themselves, independent contractors.

The plaintiff sought particulars of the advices that KD Cruise provided to its service

providers, but received an essentially non-responsive reply301. It is not apparent,

however, that the defendant itself relied upon the advice of such nautical partners and

the defendant has not adduced evidence as to the nature of and the extent to which

advice provided by those nautical partners was relied upon by Scenic Europe (or

Luftner Cruises) in respect to the subject cruises in this proceeding.

358. At any rate, whether decisions were taken by the defendant based upon information

and advice received from its European service providers, and/or, more indirectly, from

nautical partners who provided information or advice to the service providers, for this

exception to be properly invoked, the defendant still needs to establish that the relevant

decisions affecting what happened on the cruises were those (entirely) of other people.

Here, the responsibility for making decisions did not lie only with its agents, or sub-

contractors, or those informing (or advising) them. The evidence indicates that critical

decisions affecting the management of the cruises were with Scenic, and Justin Brown

in particular. Doubtless, in performing its functions as a service provider to its

passengers, the defendant relied upon information supplied to it by its European

affiliates who, in turn, relied upon local or regulatory authorities. But ultimately, the

arrangements between the defendant and Scenic Europe were such that the defendant

had the power to make, and made, the critical decisions on whether a cruise could

proceed at all (or be delayed) or, once commenced, whether the cruise might continue

(and, if not, what consequence would follow). Thus, on 29 May 2013, Justin Brown

referred to “the circumstances where we continue the cruise or tour and alterations are

made due to circumstances out of our control, we do not offer refunds or compensation

…In this cruise, we have continued to offer the cruise and associated attractions as best

we can”302 (emphasis supplied).

297 Ex P24 (CB 5/1776) 298 Ex P24 (CB 5/1777) 299 Ex P MW1 (CB 2/275) 300 Willems, par 107, (CB 3/232) 301 CB 1/111 (the request) and CB 1/116 (the response) 302 Ex P15 (CB 5/1662)

Page 61: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

61

359. It is not clear at all, even at a conceptual level, how any unspecified conduct of nautical

partners caused loss in this situation. It might have been one thing if these nautical

partners had informed Scenic’s European agents that its cruises could not proceed

because of certain one-off, or unexpected incidents, for such directive to be conveyed

to the defendant and for the defendant then to heed the directive. In such a case, the

defendant might fairly argue that any loss or damage was caused by the directive of the

nautical partners. In such a case, the defendant might say that it did what it could in

presenting a cruise, but was prevented from doing so because of the decisions and

information of local officials.

360. These were not, however, the circumstances in any of the subject cruises. In the case of

every cruise, the defendant allowed the cruise to proceed, independent of any advice

supplied by ‘nautical partners’ and, once embarked, allowed each cruise to continue to

proceed. It apparently did so, motivated by a desire to ensure that as much as the land-

based itineraries were adhered to and to that end, it did not matter that the cruising

component would be substantially impaired. The loss in value (and disappointment)

was suffered by passengers because of the defendant’s conduct in not cancelling tours,

or providing alternative arrangements to passengers, once it became known to the

defendant (irrespective of the source of that knowledge) that there would be substantial

disruption; and not because of any temporary obstacle that needed to be overcome.

361. Even if the conduct of some other person or entity frustrated Scenic in delivering a

cruising experience, this did not prevent Scenic from providing services that would

satisfy the consumer guarantees. Thus, a decision by some other person to close a lock

or part of a river along a cruise-path was not, or could not, generate a loss to the

passengers if the defendant was reasonably adaptable in providing an alternative, such

as cancelling a cruise (coupled, perhaps with the offer of a re-scheduled tour), offering a

refund

The harmful result did not occur only because of circumstances beyond Scenic’s control

after Scenic had provided services

362. By its terms, the causes beyond the suppliers’ control, for the purposes of s 267(c)(ii) of

the ACL, must have occurred after the services were provided. But where the supplier

has the capacity, in its provision of services, to respond (in terms of affecting the result

or purpose desired by the consumer) to circumstances not of its making, in a way that

might affect the outcome or result sought to be achieved by the consumer, the

exception would not apply.

363. In this case, even with the difficulties faced by the river levels, Justin Brown was

internally weighing, and canvassing with other Scenic personnel, the prospect of

cancelling cruises, offering partial refunds or credits for future cruises. These

deliberations, and communications, occurred after cruises had embarked. For the

purposes of the exception, however, these deliberations would not have occurred if, on

a proper characterization, Scenic’s services had already ceased to be provided and

Scenic was doing no more than acting as a conduit for other persons.

Page 62: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

62

364. The tour operator may not have been able to control the weather, or river levels. It was,

however, in a position (in the performance of services) to offer alternative

arrangements to passengers in the event of conditions occurring that were beyond its

control, both before and after cruises had embarked: cancellation and the offer of an

alternative tour or cruise. This explains why, as part of his management of the problem,

at different times, Justin Brown proposed303 providing ‘equitable’ refunds to affected

passengers to those who had embarked.

365. It follows that even if it be found that river levels rose unexpectedly (or to a degree

greater than that which was anticipated) or other conditions impeded the result or

purpose made known by the passengers, such circumstances do not avail Scenic in the

sense of acting as an intervening cause.

366. Accordingly in the circumstances of this case, s 267(1)(c) of the ACL does not bar a

claim arising from non-compliance with the purpose or result guarantees.

2.6 Loss arising from non-compliance with consumer guarantees

2.6.1 Causation

367. Section 267(3) of the ACL confers a right upon a consumer, who satisfies the pre-

requisites in s 267(1) and where the failure to comply with a guarantee cannot be

remedied, to recover compensation against a supplier for a loss of value.

368. Since liability under ss 61(1) and (2) of the ACL is strict, it is unnecessary for the Court,

in determining contravention of each of those provisions, to consider counter-factuals

as to what would have happened if Scenic, acting reasonably (and in compliance with its

guarantee in s 60 of the ACL), provided explanations or options to the passengers; and,

specifically, how passengers would have responded. In this regard, in an action under s

267(3) for non-compliance with the purpose and result guarantees, loss (of value) or

damage is sustained, for the purposes of s 267, simply because the purpose or result has

not (reasonably) been achieved.

369. Where the action under s 267 arises from non-compliance with s 60 of the ACL, the

requirement of causation may be different. As indicated, for some of the cruises

(particularly those of early June 2013), compliance with the care and skill guarantee

required unilateral cancellation and re-scheduling by the defendant (as was undertaken

by other tour operators, such as APT and Viking). For other cruises (in late May 2013),

compliance with the care and skill guarantee required the presentation of a choice.

Different requirements of causation apply in those situations.

370. Where the exercise of proper care and skill required (for example) unilateral conduct by

the supplier, it is irrelevant to consider the potential response of passengers. This is

because, ex hypothesi, there was no need to present passengers with an option. Thus for

group members (and the plaintiff) on the cruises 1 and 8-11(incl) and (probably) cruises

303 Ex P38 (CB 6/1958); Ex P44 (CB 6/1995-1996)

Page 63: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

63

6-7, where the cruises should have been unilaterally cancelled, evidence as to what

passengers would have done is unnecessary.

371. If it was to be found, however, that proper care and skill merely required the

presentation of an option to passengers, then the response of passengers as to what they

would have done in a hypothetical situation is relevant. In this context, the option

would need to be presented and explained in similar terms to what is set out in

paragraph 237 above.

Evidence of what passengers would have done

372. Much of the cross-examination of the plaintiff and the sample of group members

proceeded upon the limited nature of explanations actually provided by

Scenic/Evergreen or limited hypotheticals. No one was asked what they would have

done in circumstances where Scenic:

a. explained that there was a real risk of substantial disruption (measured in days) to

the cruising component of the tour; and

b. explained that a likely consequence of such disruption was (aside from the loss of

cruising time), substantially increased coach travel time, and dining and

accommodation on-shore; and

c. explained that so long as passengers could reach certain landmark events on the

itineraries, by whatever means, including the extended use of coach travel (and

dining and accommodation facilities on-shore), Scenic/Evergreen would

interpret that as compliance with its obligations to provide services to its

passengers; and

d. (accordingly) would not in lieu of cancelling tours itself, offered or presented

passengers the opportunity to cancel the tours, before or after they had

embarked, and re-schedule tours to occur in 2013/14.

373. It was put to Mr Moore (cruise 8) that if, upon arrival at Amsterdam, before he had

embarked, he had been informed that the river situation was uncertain, that there was a

prospect of sailing for a few days but Scenic did not know what was going to happen

after that, he would have wanted to proceed with the cruise. Mr Moore denied this and,

reasonably enough, said he would have asked lots of questions304: one of which was why

didn’t Scenic cancel the cruise305; another might have been what were his alternatives

and another one, yet, was the likelihood of whether he would stay on the ship or get on

a bus306. It was not a question that delay of a cruise would have suited his position: he

had a timeframe to get back to the college.

374. Mr Childs was on the same cruise as Mr Moore. His letter of complaint to Mr Moroney

of Scenic Tours of 1 July 2013 clearly indicated his position: Scenic should have

unilaterally cancelled the tour so as to enable him to claim on travel insurance and re-

schedule the cruise at a later date307. Mr Childs was not cross-examined.

304 T 73 305 T 74.41 306 T 75 307 Ex P HC1 (CB 2/337)

Page 64: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

64

375. Certain hypothetical scenarios were put to Mr Cairncross (cruise 4), but they were very

limited; and did not particularly concern the question of how he would have responded

in the hypothetical events postulated. It concerned what he would do if, after travelling

smoothly for four or five days, the ship had unexpectedly had its progress halted

because of closure of a lock. The question was whether he would be prepared to take a

bus to another ship on the other side of the lock. Mr Cairncross assented to that

position308. There was subsequently argument with the defendant’s counsel as to

whether or not Scenic was negligent at the point of which Mr Cairncross proffered his

opinion that Scenic should have advised passengers that his cruise may be severely

compromised309. Mr Cairncross was not asked what he would have done if, having

received advice, he would have exercised any option made available to him.

376. A further hypothetical was put to Mr Cairncross as to whether he thought Scenic

should cancel the cruise if, as at 27 May, the entire river system was free or open. Mr

Cairncross accepted that, in those specified circumstances, it would be reasonable to

proceed310. No questions were raised as to what he would have done if he had received

a warning after the cruise had embarked.

377. Mr Holgye was on the same cruise (cruise 4). When it was put to him that had he been

informed that he might have to spend only one or two days on buses, he would have

continued to proceed with the cruise, Mr Holgye disputed the proposition311. His

evidence that he would have attempted to cancel had he known that there was likely to

be significant bus time was unchallenged312.

378. In the case of Mr Willems (cruise 9), it was suggested that by reason of a Facebook

entry posted on 6 June 2013, which referred to the challenging conditions, he and his

wife were prepared to accept a ‘compromised’ experience. However, there was no

evidence from Evergreen to indicate what options it presented to passengers on this

cruise to avert such compromise. To the contrary, on 6 June 2013, an Evergreen

representative indicated that Mr Willems could not cancel his cruise313. Besides which,

if, by that time, Mr Willems had cancelled the trip, he “would have lost everything”

because of his travel insurance arrangements314.

379. Plainly, after the Facebook entry was posted by Evergreen (apparently on 6 June 2013),

Mr Willems’ partner, Ms Buchanan unambiguously indicated that she expected an

option to cancel to be presented: she only wanted a cruising delay to be for a short

time315 and did not want to spend 2 weeks on a coach316. The next day, Mr Willems

308 T 117-118 309 T 121-122 310 T 124 311 T 138 312 T 138.19 313 Willems, par 46 (CB 2/222) 314 T 100, 102.44 315 Britten, par 53 (CB 2/224) 316 Ex P MW1; (CB 2/264); also Ex D74

Page 65: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

65

recalled an Evergreen representative predicting that s/he was “98% sure that you will

be on the ship in the next two days.”317

380. In the case of Mr Peattie (cruise 11), he received the opinion from his travel agent on 4

June 2013 (before his scheduled embarkation on 10 June 2013) that based on a Scenic

update, everything looked as though it would operate as normal318. Whilst the Scenic

update, upon which that opinion was based, indicated that high water levels had

dramatically impacted cruising on the Rhine, Main and Danube rivers (between

Amsterdam and Budapest) in the previous week, it emphasised that Scenic was (at that

point) currently scheduled to operate the June 10 (and 12) cruises “without impact” to

embarkation or ship availability319. Mr Peattie interpreted the opinion and update as

suggesting that there may be some disruption, but it was not going to be significant;

particularly because of the use of the words “without impact”320. That interpretation

was reasonable. On 7 June 2013, passengers were told that because Budapest was under

water, passengers would be moved to Vienna by coach. When it was put to him that he

was content to proceed, without embarking at Budapest (ie that he was content with the

variation), Mr Peattie explained that he had no choice: the tour director said that if they

did not proceed, they would not receive a refund321. Contrary to what they had been led

to believe, however, passengers embarked at Krems. Mr Peattie was not asked what he

would have done if Scenic had presented to him the option of cancelling the tour and

re-scheduling it for later in the year.

381. Mr Britten (cruise 1) was cross-examined on the basis that the disruption that affected

his cruise was declared to be sudden or unexpected322. It was not put to him what he

would have done if options had hypothetically been presented to him, either before or

after he embarked.

382. To reiterate, for certain cruises in particular (cruises 2-5), the causation inquiry will be

affected by timing. Thus, for Messrs Holgye and Cairncross, who embarked on cruise 4

(STC270513.1) the relevant question is not what they would have done in a

hypothetical situation before the cruise embarked on 27 May, but what they would have

done when the exercise or proper care and skill would have made it reasonably

apparent that the cruise they had embarked upon was being, or was likely to be,

substantially disrupted. In their case, the cruise proceeded without disruption for 4 days,

but there was little if any cruising thereafter. The causation question (as to what they

would have done when presented with an option at the appropriate date) really applied

as at 30 or 31 May 2013323.

383. That most of the witnesses accepted that they were aware of a risk that their tours may

be disrupted due to river levels (whether they had read the terms and conditions or not)

does not advance the defendant’s position, in circumstances where (a) it is a statement

317 Willems, par 54 (CB 2/224) 318 Peattie, Annex ‘A’ (CB 2/518) 319 Ibid (CB 2/519) 320 T 166.22 321 T 169.11 322 T 151 323 As indicated in the Opening, at T 32.22

Page 66: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

66

of the obvious and (b) the plaintiff and witnesses have not asserted that passengers

believed that their tours would be completely free from disruption. It would have been

one thing if one of the subject cruises embarked from Amsterdam in, say, March 2013

(ie where there could be no suggestion of any recent flooding or rising river levels) until

a ‘sudden’ or ‘unexpected’ closure of a lock, caused a ship to be stuck for 2 hours, until

the ship could be safely moored and a bus could take passengers to a nearby adjacent

port where the cruise would continue. In such case, it is very likely that the

inconvenience, temporary and perhaps fleeting, would have willingly been endured.

384. The case for the plaintiff, and the circumstances of the witnesses called is that (a) the

defendant was aware before embarkation that there was a risk of substantial disruption;

and/or (b) the defendant became aware of a risk of substantial disruption after

embarkation. ‘Substantial’, in this context, means real or substantial; not temporary,

fleeting or ephemeral. In neither category of case did the defendant take the steps that

proper care and skill required of it. To the extent that the exercise of proper care and

skill required the provision of an option to a passenger, that option should have been

provided with an explanation (and prediction) that the cruising component of the tour

was likely to be substantially disrupted, which would necessitate alternative

arrangements that might substantially diminish the purpose or result that passengers

wished to achieve from their tour experience. None of the plaintiff’s witnesses were

asked what they would have done had an explanation by Scenic of this kind been

supplied to them.

2.6.2 Non-compliance could not be remedied

385. There is no indication in the ACL as to how a supplier may be expected to ‘remedy’ a

failure to comply with a consumer guarantee in relation to services. Here a harmful

result – a ruined holiday – has occurred. The defendant has not offered the passengers

another cruise.

386. Since the non-compliance with the consumer guarantees cannot be remedied, the

plaintiff has a right to compensation under s 267(3)(b) of the ACL, and it is

unnecessary to consider whether there was a ‘major’ failure to comply.

2.6.3 ‘Major’ failure to comply

387. In any event, there was a ‘major’ failure to comply. A failure to comply is a ‘major

failure in a range of circumstances, such as where:

The services would not have been acquired by a reasonable consumer fully

acquainted with the nature and extent of the failure (ACL, s 268(a);

The services are substantially unfit for a purpose for which the services of the

same kind are commonly supplied and cannot, easily and within a reasonable

time, be remedied to make them fit for such a purpose (ACL, s 268(b));

The services were unfit for the particular purpose for which they were acquired

or were not of such nature as might reasonably be expected to achieve the result

the consumer desired (made known to the supplier) and the services cannot

Page 67: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

67

easily, and within a reasonable time, be remedied to make them fit for such

purpose or to achieve such result (ACL, ss 268(c)-(d)).

388. The considerations relevant to ss 268(b)-(d) have effectively been addressed above. As

to s 268(a), the question is an objective one: how would the reasonable consumer have

reacted. That hypothetical reasonable consumer would need to be acquainted with the

circumstances that:

Scenic had actual or constructive awareness of the likely substantial disruption of

the cruising component of the tours;

Notwithstanding such awareness, Scenic had not:

o exercised its power to cancel the tours; or

o offer to its passengers the opportunity to cancel (either before or after

embarking), with refunds and/or the opportunity to re-schedule for

another tour;

Even in the absence of any prior knowledge of the risk or prospect of

substantial disruption, once the cruises had embarked Scenic had not cancelled

tours, or offered passengers the opportunity to leave.

3. QUANTUM OF DAMAGES

3.1 Heads of damages

389. There are two kinds of loss under s 267 of the ACL. First, there is the head

representing the reduction in the value of the services below the price paid (s 267(3)(b)).

390. Secondly, the consumer may also recover damages for any loss or damage suffered

because of the failure to comply with the guarantee if it was reasonably foreseeable that

the consumer would suffer such loss or damage as a result of the failure (ACL, s

267(4)). Legislative emphasis has been given to the separate and independent nature of

these heads of damage (s 267(5)).

391. The methodology for calculating reduction in value is considered below in section 3.2.

3.1.1 Meaning of ‘foreseeable’ loss

392. The remedy in s 267(4) is discretionary. The expression ‘reasonably foreseeable’ has

been equated to ‘probable consequence of’324

393. Professor Carter325 makes the following points about s 267(4):

rules on contract damages would not be applicable save by analogy;

the concept of ‘reasonably foreseeable’ would displace general contract damages

rules (Hadley v Baxendale);

324 Explanatory Memorandum, Trade Practices Amendment (Australian Consumer Law) Bill (No.2) 2010, [7.114] 325 J W Carter, Contract Law and the Australian Consumer Law, [2-23]

Page 68: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

68

Whether loss or damage is ‘reasonably foreseeable’ is probably determined at

the time that the consumer guarantee is not complied with;

The impact of the provision is to enable recovery not only of out of pocket

expenses, but other consequential loss.

3.1.2 Availability of damages for disappointment and distress

394. Under general law, compensation is available for disappointment and distress as a

reasonably foreseeable head of damage. This head of damage is apposite in this context:

Baltic Shipping Co v Dillon (1993) 176 CLR 344 at 364.2; 22 NSWLR 1; Jarvis v Swan Tours

Ltd [1973] QB 233). This head of damages has been recognised under the

corresponding legislative provision providing compensation for foreseeable loss for

contravention of a consumer guarantee in New Zealand326, whose legislative framework

was a model for the consumer guarantees in the ACL.

395. In response, the defendant relies upon s 275 of the ACL, and it asserts that the

provision picks up and applies provisions of Part 2 of the Civil Liability Act (NSW)

limiting damages for non-economic loss, of which, the defendant asserts a claim for

disappointment and distress is a species.

396. Firstly, s 275 of the ACL does not pick up the provisions of Part 2 of the Civil Liability

Act. By its terms, s 275 applies to a state law limiting liability for a breach of contract for

the supply of services327. The intent of s 275 of the ACL, similar to the former s 74(2A)

of the former Trade Practices Act, is to ensure that in actions for damages for breaches of

contract for breach of implied warranties, state laws quantifying or regulating damages

for breach of contract are not evaded. More specifically, the intent is to prevent a

constitutional inconsistency between a federal provision imposing a warranty in a

contract and whose contravention would otherwise have provided ‘full contractual

liability’ (like the old s 74(2) of the Trade Practices Act) and a state law regulating or

modifying damages recoverable in contract328.

397. Here, however, the plaintiff and group members do not sue in contract or seek

recovery for damages for breach of a term of the contract. They (relevantly) sue under s

267(4) of the ACL329, that is, a statutory claim for damages for ‘foreseeable loss’ (a

notably tortious measure) because of non-compliance with a statutory obligation.

Section 60 and 61 of the ACL (unlike the former Sections 74(1)-(2) of the Trade Practices

Act) are not terms that are implied, by statute, into a contract. The provisions are

independent statutory obligations applicable to the supply of services to a consumer330.

326 Malbon & Nottage (ed), Consumer Law and Policy in Australia and New Zealand (2013), p 124, citing Hosking v The Warehouse Ltd (District Court of NZ, 5/10/98) 327 Alameddine v Glenworth Valley Horse Riding Pty Ltd [2015] NSWCA 219 at [63]. In this case, the claimant sued in tort and under the ACL, but not in contract. 328 Perisher Blue Pty Ltd v Nair-Smith [2015] NSWCA 90 at [185]-[187] 329 It is not suggested that the caps under the Civil Liability Act (NSW) apply to the compensation recoverable under s 267(3) of the ACL. 330 Alameddine v Glenworth Valley Horse Riding Pty Ltd [2015] NSWCA 219 at [77]

Page 69: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

69

398. Secondly, even if the provisions of Part 2 of the Civil Liability Act were picked up and

applied by s 275 of the ACL, the provisions were not engaged. The provisions should

be construed as being subject to a geographic limitation that the relevant injury be

suffered in New South Wales. The central focus of Part 2 is reducing liability for

personal injury damages, which makes it appropriate to fix the geographic limitation to

the place where the personal injury was suffered. This would be consistent with the

High Court’s reasoning in Insight Vacations Pty Ltd v Young (2011) 243 CLR 149 where,

as in this case, although the relevant contract may have been governed by NSW law, the

injury, and the performance of the services, occurred outside of New South Wales. In

this case, the personal injury – the ‘suffering’ or ‘loss of amenity’ constituted by

disappointment and distress – was also suffered outside of New South Wales.

3.2 Methodology of loss of value

399. The defendant’s opposition to the claim extended even to resisting the proposition that

Mr Moore suffered any loss, or disappointment at all. His cross-examination suggested

that he enjoyed the early part of the tour and was exaggerating the difficulties associated

with extended bus – travel331. This was probably the least attractive aspect of the cross-

examination: to suggest that Mr Moore enjoyed the early part of his tour, and therefore

that it wasn’t all a bad experience: the insinuation is that Mr Moore should have been

grateful for the benefits that he received. Moreover, it does not reckon with the facts,

not seriously contradicted by the defendant, that there was a reduction in the cruise

time promoted by Scenic332. Mr Moore was not challenged on that.

400. A statement of loss of value, in this respect, is very much an objective matter. It is a

matter that the defendant is peculiarly positioned to know. Put another way, it is a

matter in which there are real practical limitations upon proof that a plaintiff can

supply. The difficulties in assessing loss of value in a case of this kind were observed by

Devlin J in Biggin v Permanite [1951] 1 KB 422. In that case, the plaintiff was entitled to

damages against a seller for delivery of defective goods, with the damages referable to a

diminution in the market value of goods333. But the law does not permit difficulties in

estimating loss to defeat an award of damages by way of compensation for loss actually

suffered334. In cases of this kind, it is recognised that there may be an element of

guesswork in the damages calculation335.

331 T84.39 332 Ex P DM1 (CB 3/813-814) 333 Cited in McGregor on Damages (18th ed) [8-008] 334 Sellars v Adelaide Petroleum NL (1994) 179 CLR 332 at 349; Gray v Richards (2014) 88 ALJR 968; [2014] HCA 40 at [55] 335 Fink v Fink (1946) 74 CLR 127; applied in Placer (Granny Smith) v Thiess Contractors (2003) 77 ALJR 768; 196 ALR 257 at [38]

Page 70: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

70

3.2.1 Background to admissions

401. This principle does not however find complete expression in this context because at

least some evidence has been adduced, centred around admissions made on the

defendant’s behalf, and other documents tendered by the plaintiff.

402. On 23 August 2013, Covermore indicated to Mr Moore that it would pay out his claim

for insurance for the sum of $1293 per passenger. The letter expressly indicated that

this sum was calculated by reference to information provided by Scenic in a letter336.

Covermore’s letter also identified that the sum of $1293 was attributable to the

‘difference between cruise and bus tour’.

403. That description can only have come from Scenic. It is to be recalled that only one

week before, Covermore informed Mr Moore that his claim was unsuccessful337. Why

the change of position? A clue lies in Justin Brown’s letter to Mr Moore back on 6

August 2013, in which he expressed “disappointment” with Covermore’s position and

which he also indicated that he had “advised Covermore that their reply to you was not

aligned with the way in which they had advised us they would review such claims’338. It

should be inferred that the reference to ‘their reply’ was probably some verbal

indication, if not some prior notification made by Covermore prior to its letter of 16

August.

404. The point, however, is that Scenic was providing information to Covermore and it was

probably the case that this information included the bit about the $1293 being

attributable to the difference between a cruise and a bus tour. The information would

not have come from Mr Moore.

405. This collaboration between Scenic and Covermore, trying to work in the interests of its

disgruntled former passengers, and providing information to enable the insurer to

assess the loss of value, also appears to have occurred with other travel insurers,

including Zurich339.

406. As part of its preparation for trial, the plaintiff sought to elicit information from the

defendant as to the loss of value arising from the reduction in cruising days: in effect, to

tease out how, in the case of Mr Moore, Scenic had calculated the difference between a

bus and a cruise tour. It issued a notice to produce340 directed to that purpose. That

notice was the subject of objection by Scenic (notwithstanding that no application was

formally brought to set aside the notice. The notice simply was not complied with).

Commercial confidentiality was cited as a concern.

336 The letter being Ex 4 (formerly MFI 3) 337 CB 3/819 338 CB 3/816 339 T 139.15 340 CB 1/66-67 (especially, par 2-3). Paragraph 3 of the notice referred to the figure of $732.66 identified in CB2/824

Page 71: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

71

3.2.2 Admissions as to how the defendant calculated loss of value

407. In order to avoid debate about whether to produce documents that might reveal

Scenic’s calculation of loss of value, the defendant’s counsel342 indicated the way in

which Scenic itself had calculated the loss in value:

i. identify the number of days allocated to a cruise (A);

ii. divide the total price of the cruise (B) tour by the days allocated to a cruise (B

divided by A);

iii. multiply the figure in (ii) by the number of days lost.

408. Counsel for Scenic did not qualify his statement as to how Scenic calculated the loss of

value to the Court by stating that this was purely a mathematical calculation. It can only

be inferred that the statement by counsel reflected a considered position in itself

reflecting his client’s instructions343.

409. Scenic argues that even on some of the ‘lost’ cruising days, benefits were provided

(accommodation and dining). There are two answers to that. First, the loss of value

centres upon the lost cruising experience. If the relevant promise by Scenic was to

provide benefits A + B + C344, but all that was provided was B + C, the loss is the lost

benefits A.

410. Secondly, Scenic did not otherwise adduce evidence that would dis-entangle the

provision of some benefits from other benefits that were not provided. The plaintiff

tendered various ‘variation schedules’, prepared by Scenic, which were indicative of the

loss suffered through impacts on the passenger’s sailing schedule. Those variation

schedules were enclosed with ‘itinerary variations’, which, on their face, appear to

reflect Scenic’s assistance to passengers to make travel insurance claims345. It is notable

that in arriving at a figure for ‘daily cost’, Scenic did not separately try to break down or

apportion the benefits attributable to accommodation and dining from the cruising

component of the tour.

411. In summary, through the issue of its notice to produce and the tender of the variation

schedules and itinerary variations, the plaintiff did all that it practicably could to identify

the loss of value arising from the lost, or reduced, cruising component of the tours. In

contrast, the defendant had ample opportunity to put on evidence to indicate its view

of the proper methodology of loss. It did not do so. It was confronted with coercive

court process issued by the plaintiff to flush out that position. It initially resisted that

process before its counsel made admissions in Court. It was notified that the plaintiff

would rely upon Scenic’s documents, which did not apportion the ‘daily cost’ in

accordance with individual benefits. The principle of Armory v Delamirie (1722) 93 ER

342 CB 1/205 - 208 343 That the defendant’s counsel sought instructions is apparent at T35.29 (CB 1/207) 344 Where A represents the cruise component; B represents accommodation and C represents food and beverages. 345 Ex P54 & 55 (CB 6/2146-2165)

Page 72: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

72

664346 indicates that in the absence of any competing methodology proposed by the

defendant, the methodology proposed by the plaintiff should be accepted. Further, and

more generally, in support of its position, the plaintiff invokes Lord Mansfield’s dictum

in Blatch v Archer347 that all evidence is to be weighed according to the proof which it

was within the power of one side to produce and in the power of the other to have

contradicted348.

3.3 Amount

3.3.1 Section 267(3)

412. The standard cost for Mr Moore’s cruise was $7,195, per person349. Mr Moore

purchased an upgrade from the Moselle deck standards stateroom to the category PP

Balcony suite, at a costs of $2,455350.

413. The total cost incurred (and paid for) by Mr Moore was $10,990. This comprised the

costs of the standard room, plus the upgrade, together with port costs and taxes351.

414. Based on the above expenditure, the cost per day to Mr Moore was $732.66.

415. Mr Moore’s cruise was disrupted for 10 of the 15 days352.

416. Applying the loss methodology referred to above, Mr Moore should receive $7,362.60.

That sum is the result of multiplying 10 days at the rate of $732.66.

417. To this sum should be added an interest component, which is calculated at $1,350 up to

to the date of these submissions.

418. The plaintiff does not propose to make submissions on the loss of value of other

passengers, even including group members, on the basis that calculations of individual

group members’ claims for damages is not a common issue for determination.

3.3.2 Section 267(4)

419. It was put to Mr Moore, and some of the other witnesses for the plaintiff, that they

enjoyed parts of the tour prior to the disruption. It was not, however, put to Mr Moore

that he enjoyed the compromised part of the experience: the extended coach travel, the

inconvenience of participating in a ship swap; and the accommodation and dining

onshore that was of an inferior quality to that which Scenic had promoted as being

available on the ship.

346 applied in Tobin v Ezekiel (2012) 83 NSWLR 757 at [100]-[101] 347 (1774) 98 ER 969 at 970 348 The dictum was referred to by the High Court in ASIC v Hellicar (2012) 247 CLR 345 at [166]-[168], [250]-[269]. 349 Ex P8 (CB 4/1058) 350 Ex P DM1 (CB 3/783) 351 Ibid (CB3/813) 352 Ex P DM1 (CB3/813-814)

Page 73: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …

73

420. According to the defendant’s documents, Mr Moore did not receive approximately 2/3

of the cruising experience he bargained for. An award of damages under this head is

very much based on impression. Relevant in this regard was the genuineness of the

complaints made to Scenic after his experience353. Relevant also was the circumstances

in which Mr Moore had used long-acquired savings (and long service leave) to pay for

this particular tour experience, which was partly designed to alleviate his grief (and that

of his partner) from recent family deaths354. It is submitted that an appropriate

allowance for this head of damages is $2,000.

4 RESTITUTIONARY ACTION FOR MONEY HAD & RECEIVED

4.1 Basis for recovery

421. This action (in common law) is relied upon as an alternative: ie, if the action for

damages (for contravention of the statutory guarantees) fails.

422. The action is for money had and received. A category of that action355 is where there is

a failure of consideration (Moses v Macferlan) which arises where payments are made for a

purpose that fails, such as where the contemplated state of affairs disappears.

423. Where the consideration is partly severable (such that the purchase price may be

apportioned), and where a claimant has no remedy in damages, there should no longer

be any requirement that the failure of consideration be “total”. This is a proposition

accepted, separately, by Gummow J in Roxborough356. That view was approved by

Callinan J in his concurrence in Roxborough357. It was also approved by Heydon J in

Equuscorp358, It was also the view of a majority of the High Court in David Securities Pty

Ltd v CBA that the concept, when applied to circumstances where consideration could

be apportioned or “broken up”, was misleading and inapt359.

424. It is also a proposition shared by Basten JA and Young AJA recently in the New South

Wales Court of Appeal361 and previously by McColl JA (with whose reasons Basten JA

and Campbell JA agreed) in the Court of Appeal362.

353 Ex P DM1 (CB 3/799-802, 805-806, 809-812) 354 Moore, 2/6/15, par 6 (CB 3/548) 355 Recovery for money had and received “depends on the existence of a qualifying or vitiating factor”: Farah Constructions v Say Dee Pty Ltd (2007) 230 CLR 89 at [150]; David Securities Pty Ltd v CBA (1992) 175 CLR 353 at 379 356 Roxborough v Rothmans (2001) 208 CLR 516 at [105]-[107] 357 (2001) 208 CLR 516 at [198] 358 Equuscorp Pty Ltd v Haxton (2012) 246 CLR 498 at [136]-[137]. The plurality alluded to, but did not decide the issue: at [33] 359 (1992) 175 CLR at 382-383 361 Nu Line Construction Group v Fowler [2014] NSWCA 51 at [11], [192] 362 Juul v Northey [2010] NSWCA 211 at [217]

Page 74: SUPREME COURT OF NEW SOUTH WALES COMMON LAW DIV …