support material the ndp operations guide is a tool to assist municipalities to comply with ndpg...
TRANSCRIPT
SUPPORT MATERIALThe NDP Operations Guide is a tool to assist Municipalities to comply with NDPG operational procedures. The Guide provides quick guidance on NDPG processes, outputs required and tools to assist in developing the outputs. The Operations Guide does not replace the NDP Toolkit, but introduces additional support for operational management. The NDP Toolkit should be used together with the Operations Guide. This Roadmap serves as a guide on how to use the Operations Guide:
STAGE 1
REGISTRATION
NDP OPERATIONS GUIDE ROADMAP
DESCRIPTIONThis is the first step in the process for a municipality to
register their township for NDPG funding. The standard Registration form will guide the
municipality through a series of evaluation questions and require information about location, intent, focus
and management. Should this stage of the process prove successful, the next step in
the strategic partnership will be initiated to sign the Funding Agreement. Registration takes place only in set periods determined by the NDP.
Orientation Pack
STAGE 2
PREPARATION
STAGE 4
EXIT AND REVIEW
STAGE 3
IMPLEMENTATION
Project Preparation
Township Regeneration Strategy
Business and Project Plans
Economic Area Analysis
Exit and Review Documents
Exit and Review Documents
Prepare & Submit Application
Complete and Submit Funding Agreement
DESCRIPTIONThis stage will start with a process of engagement and
discussion to scope, programme and prioritise a collection of projects in order to clarify concepts.
This will be the first step in building the Business Case which includes providing detailed information on
the programme and assessing its feasibility. Then to prepare a plan for implementation (Business Plan) that will be approved by the NDP to authorise release
of CG. Aligned with this process to compile a Township Regeneration Strategy that will mainstream sustainable
township development over the long term.
DESCRIPTIONThis stage will involve the implementation
of the approved programme by using Capital Grant Funds. Funding and investment
partners will be brought on-board. Funding may also be available for any necessary project
management, capacity building and detailed planning to ensure the success of the project. Payment requests will be made according to
milestones identified and agreed.
DESCRIPTIONThe purpose of this stage is to effect handover and closure, including the establishment of all
management systems and the building of capacity if not already available. During this
stage the key success factors of the programme as identified within the Business Plan are also
reviewed. Audits or assessments may be undertaken with or without the support of
municipalities.
Currently ClosedNDPG Toolkit
NDPG Language: Clarification of Key Terms
Minimum Filing Requirements
Funding Agreement & Schedules
NDPG Glossary of Terms
Financial Policies and Procedures
Budgeting Process Practice Note
Benchmark Costing Report
Web Training Manual
Web Progress Report Template
Schedule 3A MPS: Current Year
Schedule 3B MTEF: 3 Year Forecast
VAT Guidance Note
CG Payment Claim Process
TA Payment Claim Process
Credit Order Instruction
Capital Draw Down Letter Template
Technical Assistance Payment Request Template
Shortlisting and Verification
Approval
Registration Checkpoint: Signed Funding Agreement
Status Quo Assessment
Detailed Investigations
Prepare & Submit Business Plan/s and Project Plan/s
Prepare Township Regeneration Strategy
Preparation Checkpoint: Approved Business Plan/s
Scope Process
Finalise Design Work
Appoint Implementer/Contractor
Contract Management
Handover and Final Completion
Prepare Close-out Report/s
Implementation Checkpoint: Close-out Report/s
Start Operations
Prepare Exit Strategy/s
Conclude Award Closure
Exit and Review Checkpoint: Exit Strategy and Signed Award Closure Template
Tech
nic
al A
ssis
tan
ce G
ran
t
Cap
ital G
ran
t
Sample Audits
by NDP
Grant Administration
Finance and Budget
Approval
Required
STAGE 1: REGISTRATION
Prepare & Submit Application to NDP
Prepare for and Attend Verification Site Visit
Receive Letter of Approval
Attend Induction Workshop
Complete and Submit Funding Agreement
Registration Checkpoint: Signed Funding Agreement
MUNICIPAL PROCESS NDP ROLE SUPPORT MATERIAL
Complete the Registration Form and include information on:
•Municipal and Township Information•Programme and Project Details•Investment Leverage Potential•Planning Costs and TA Requirements•Capital Costs and CG Requirements•Budget and Milestones•Supporting Documentation eg. Maps and diagrams•Municipal Declaration/s
Prepare and Provide Additional Information
Aknowledge Shortlisting
Adjustments and Additional Information to FA
Final Signed Funding Agreement from NDP
This stage is currently
closed. No new applications are considered.
Funding Agreement Schedules include:•General Project Description•Overall Project Costs•Milestone Payment Schedule•Authorisation by the Municipality•Council Resolution•Special Conditions•NDPG Award Letter•Delegations
GUIDE:Support in preparing and reviewing
Submission. (may include combined Municipal workshops)
Grant Administration
Induction
•Orientation Pack
•NDPG Toolkit•Funding Agreement and Schedules•NDPG Language: Clarification of Key Terms•Minimum Filing Requirements•Glossary of Terms
Finance and Budget
•Financial Policies and Procedures•Budgeting Process Practice Note•Benchmark Costing Report•Web Training Manual•Web Progress Report Template•Benchmark Costing Report•Schedule 3A MPS: Current Year•Schedule 3B MTEF: 3 Year Forecast•VAT Guidance Note•CG Payment Claim Process•TA Payment Claim Process•Credit Order Instruction•Capital Draw Down Letter Template•Technical Assistance Payment Request Template
GUIDE:Guidance on adjustment/improvement of
Submissions.
CONTRACTUAL:Approval of Funding Agreement between Municipality and National Treasury
GUIDE:Guidance on way forward in respect of
processes and procedures to be followed.
APPROVE:Approval of Initial Award.
STAGE 2: PREPARATION (BUILDING THE BUSINESS CASE)
NDP ROLE SUPPORT MATERIAL
GUIDE:Provide programme management guidance in respect of scope, time and costs for appointing service
providers.
Township Regeneration Strategy
Economic Area Analysis
Business and Project Plans
Project Preparation
Grant Administration
Finance and Budget
•NDPG Toolkit•Funding Agreement and Schedules•NDPG Language: Clarification of Terms•Minimum Filing Requirements•NDPG Glossary of Terms
•Economic Area Analysis, Interpretation and Recommendations
•NDPG Business Plan Template•NDPG Project Plan Template•NDPG Project Plan Worksheet
•Guidance Note: TRS
GUIDE:Guide preparation of:
TRS, Status Quo, Detailed Investigations Business/Project
Plan/s.
CONTRACTUAL: Confirmation of Approved
Capital Programme
APPROVE:TA Payments.
Business and Project Plans
•Financial Policies and Procedures•Budgeting Process Practice Note•Benchmark Costing Report•Web Training Manual•Web Progress Report Template•Benchmark Costing Report•Schedule 3A MPS: Current Year•Schedule 3B MTEF: 3 Year Forecast•VAT Guidance Note•CG Payment Claim Process•TA Payment Claim Process•Credit Order Instruction•Capital Draw Down Letter Template•Technical Assistance Payment Request Template
MUNICIPAL PROCESS
Set Up Technical Oversight Management Structures
Scope the work required:•Long-range planning in place?•Level of planning readiness?
Decide who will do the work:•In-house.•Service Provider: Components of work•Service Provider: Manage entire process
Scope Planning and Preparation
Status Quo Assessment
Detailed Investigations (detailed feasibilities)
Business Plan/ Project Plan
TRS(Township Regeneration
Strategy)
Preparation Checkpoint: Business Plan
THIS STEP INVOLVES:Desk top assessment and engagement with Municipality and Stakeholders to determine:•Planning work.•Institutional arrangements.•Critical components of intervention.
TYPICAL OUTPUTS:*Status Quo Review Report.*Scoping of Detailed Investigations.*Scoping of TRS.*Recommendations to strengthen management of award.
TYPICAL OUTPUTS:* Strategic planning document to guide development of townships over long term.* Alignment to other strategic planning documents and processes eg. IDP, Budget.
TYPICAL OUTPUTS:* Technical: (EIA, Traffic Survey, Rezoning etc)* Economic and Social: (Safety Strategy, Socio-economic Survey, Economic Assessment etc)
CHARACTERISTICS* Long Term* Township Focused* Multi-Sectoral* Strategic* Coherent
TRS could be an existing document or part of
set of documents
TYPICAL BP/PP OUTPUTS:* Implementation Plan* Financial Plan* Leverage Plan* Risk Management Plan* Exit Strategy
THIS STEP INVOLVES:Use of technical studies and detailedinvestigations to generate overall plan for programme to draw on NDPG to catalyse its implementation.
THIS STEP INVOLVES:Investigation to describe,in detail, the challengesand constraints of theintervention.
BP = Measurable at township levelPP = Nodal/Linkage/General Improvement/Other Discrete Projects
THIS STEP INVOLVES:Review of existing/new information and engagementwith stakeholders to develop a long term plan for township Development.
•Guidance Note on Project Preparation
STAGE 3: IMPLEMENTATION
Procurement of Contractors
Implementation Checkpoint: Close-Out Report
MUNICIPAL PROCESS
Manage Construction and Hand-Over
Prepare Draft Close-Out Report per Project:
SUPPORT MATERIALNDP ROLE
•Ensure that completion was achieved within budget and timeframe.•Confirm whether objectives where achieved.•Outline any events of significance, unresolved disputes, suggested improvements.•Confirm that the quality of work is acceptable, history is available, handover complete.
APPROVE:TA/ and CG Payments.
Resolve Procurement of Resources for Implementation of Business Plan
Mobilise Professional Team (new/existing) for Implementation
Implementation Team Commissions Detailed Design
Final Design for Implementation
GUIDE:•Guidance on preparation of Close-Out documentation.
Grant Administration
•NDPG Toolkit•Funding Agreement and Schedules•NDPG Language: Clarification of Terms•Minimum Filing Requirements•NDPG Glossary of Terms
Finance and Budget
Exit and Review Documents
•Exit and Review Guidance Note•Close-Out Report Template•Award Closure Sheet
Adjust and Submit Final Close-Out Report/s per Project
Cap
ital G
ran
t Q
uart
erl
y D
raw
Dow
ns
•Financial Policies and Procedures•Budgeting Process Practice Note•Benchmark Costing Report•Web Training Manual•Web Progress Report Template•Benchmark Costing Report•Schedule 3A MPS: Current Year•Schedule 3B MTEF: 3 Year Forecast•VAT Guidance Note•CG Payment Claim Process•TA Payment Claim Process•Credit Order Instruction•Capital Draw Down Letter Template•Technical Assistance Payment Request Template
GUIDE:•Guidance in respect of cost, scope and time management of professional team.
GUIDE:•Programme management guidance in respect of implementation progress.
Option: Appoint Service Provider (new/existing)
for Exit and Review
STAGE 4: EXIT AND REVIEW
Start Operations
Exit Stage Gate: Award Closure Sheet
MUNICIPAL PROCESS
Prepare and Submit Draft Exit Strategy/s for Programme/s
Sign and Submit Closure Sheet per Award
Sample Audits on Awards/Programmes/
Projects
NDP ROLE SUPPORT MATERIAL
•Confirm Programme Completion.•Evaluate Programme Achievements.•Operations Plan – Confirm Sustainability.•Overall Assessment and Recommendations•Compliance Requirements
Grant Administration
•NDPG Toolkit•Funding Agreement and Schedules•NDPG Language: Clarification of Terms•Minimum Filing Requirements•NDPG Glossary of Terms
Finance and Budget
Exit and Review Documents
•Exit and Review Guidance Note•Close-Out Report Template•Award Closure Sheet
GUIDE:Provide programme management guidance in respect of scope, time
and costs.
APPROVE:TA Payments.
CONTRACTUAL:Agreement on Closure of the Award.
Adjust and Submit Final Exit Strategy/s per Programme
•Financial Policies and Procedures•Budgeting Process Practice Note•Benchmark Costing Report•Web Training Manual•Web Progress Report Template•Benchmark Costing Report•Schedule 3A MPS: Current Year•Schedule 3B MTEF: 3 Year Forecast•VAT Guidance Note•CG Payment Claim Process•TA Payment Claim Process•Credit Order Instruction•Capital Draw Down Letter Template•Technical Assistance Payment Request Template
Adjust and Submit Final Close-Out Report/s per Project (STAGE 3)
GUIDE:Guidance on preparation of
Exit and Review Documentation
GUIDE:Sample audits on Awards/
Programmes/Projects
Use Close-Out Report/s as inputs
TYPICAL MUNICIPAL PROGRAMME MANAGEMENT FUNCTIONS FOR NDPG
Township Regeneration Strategy
Economic Area Analysis
Business and Project Plans
Project Preparation
Grant Administration
Finance Budget
•NDPG Toolkit•Funding Agreement and Schedules•NDPG Language: Clarification of Terms•Minimum Filing Requirements•NDPG Glossary of Terms
•Economic Area Analysis, Interpretation and Recommendations•Examples
•NDPG Business Plan Template•NDPG Project Plan Template•NDPG Project Plan Worksheet
•Guidance Note on Project Preparation
•Guidance Note: TRSINITIAL PLANNING
ADMINISTRATION
FINANCIAL MANAGEMENT
REVIEW AND TECHNICAL OVERSIGHT
PROGRAMME/ PROJECT MANAGEMENT
COMMUNICATION
INVESTMENT AND PARTNERSHIPS
•Develop a preliminary work plan.•Control changes to the initial work plan to reflect the actual status.
MUNICIPAL DUTIES OUTPUTS
•Establish communication structure and responsibilities for the award.•Facilitate and convene meetings where applicable.•Manage reporting to Public, Council and NDP Unit. •Draft and keep relevant documentation of meetings. Eg. Minutes
•Complete and submit monthly web reports.•Keep and file all relevant documentation and monitor information distribution•Ensure quality management in the provision of professional services, construction and internal.
•Complete and send payment requests (TA and CG) to NDP.•Authorize and refer invoices to NDP for payment.•Review and submit revised Schedule 3A MPS twice a year.•Review and submit revised Schedule 3B MPS twice a year.•Manage and control the cost budget.
• WORK PLAN
•Comment on draft technical outputs and refer to NDP for comment.•Approve technical outputs and provide copies of outputs to NDP.•Send technical outputs to NDP for approval.•Manage the execution of the work in accordance with the approved technical documents.
•Facilitate adjustments and technical sign off of milestones as required.•Submit updated programme information to NDP.•Draft progress reports.
•Secure agreements with government partners at Local, Provincial and National levels.•Structure and drive the public-private partnerships (stakeholder and investor negotiations).
•CONTRACTUAL DOCUMENTATION•GIS DATA
•SCHEDULE 3A MPS•SCHEDULE 3B MPS•UPDATED FINANCIAL RECORDS•TA/CG PAYMENT REQUESTS
• STATUS QUO REPORT•TOWNSHIP REGENERATION STRATEGY•BUSINESS AND PROJECT PLAN•FEASIBILITY STUDIES•EXIT DOCUMENTATION
•WORK PLAN•NDPG WEB REPORT•PROGRESS REPORTS •PROJECT PLAN•BUSINESS PLAN
•MINUTES OF MEETINGS
•AGREEMENTS
SUPPORT MATERIAL
•Draft relevant tender documentation.•Send tender documentation to NDP for comment.•Manage the evaluation of proposals and tenders and facilitate awards.•Appoint consultants and contractors and manage their budgets
PROCUREMENT
• TENDER DOCUMENTATION•CONSTRUCTION CONTRACTS•LETTERS OF APPOINTMENT•SERVICE LEVEL AGREEMENTS
The NDPG requires Municipalities to have capacity in place to provide efficient programme management. Typical Municipal programme management functions include:
•Financial Policies and Procedures•Budgeting Process Practice Note•Benchmark Costing Report•Web Training Manual•Web Progress Report Template•Benchmark Costing Report•Schedule 3A MPS: Current Year•Schedule 3B MTEF: 3 Year Forecast•VAT Guidance Note•CG Payment Claim Process•TA Payment Claim Process•Credit Order Instruction•Capital Draw Down Letter Template•Technical Assistance Payment Request Template