SunGuide SM Software Development Project Release 3.0 Kick-off Meeting April 5, 2007. Agenda. Introductions. Agenda. Meeting Objectives. Provide overview of: Development Team Software Architecture Components being implemented Budget Schedule Not an objective: - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

SunGuideSunGuideSMSM Software Development Project Software Development Project

Release 3.0 Kick-off MeetingRelease 3.0 Kick-off MeetingApril 5, 2007April 5, 2007

Page 2: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 2

AgendaAgenda

Time Item Lead

1:00 – 1:10 Introductions and Opening Remarks Tillander

1:10 – 1:20 High Level Overview – meeting objectives Dellenback

1:20 – 1:30 Project Team Dellenback

1:30 – 2:45

High level discussion of work items:AVLEvent ManagementReporting SubsystemRoad RangerIncident DetectionEvent ViewerConfiguration EditorOperational InterfaceAmerican Dynamics CCTV DriverMessage Arbitration System modificationsEH / SL EnhancementsVariable Speed Limit Signs511Web ServerOperational Data Store Build

Heller

2:45 – 3:00 Overlap of Reporting Subsystem and Operational Data Store Heller

3:00 – 3:15 Break

3:15 – 3:30General activities:DocumentationFAT Deployments

Dellenback

3:30 – 3:45 Budget Dellenback

3:45 – 4:15 Schedule Dellenback

4:15 – 4:45 Open Discussion / Action Item Summary All

Page 3: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 3

Introductions

Page 4: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 4

AgendaAgenda

Time Item Lead

1:00 – 1:10 Introductions and Opening Remarks Tillander

1:10 – 1:20 High Level Overview – meeting objectives Dellenback

1:20 – 1:30 Project Team Dellenback

1:30 – 2:45

High level discussion of work items:AVLEvent ManagementReporting SubsystemRoad RangerIncident DetectionEvent ViewerConfiguration EditorOperational InterfaceAmerican Dynamics CCTV DriverMessage Arbitration System modificationsEH / SL EnhancementsVariable Speed Limit Signs511Web ServerOperational Data Store Build

Heller

2:45 – 3:00 Overlap of Reporting Subsystem and Operational Data Store Heller

3:00 – 3:15 Break

3:15 – 3:30General activities:DocumentationFAT Deployments

Dellenback

3:30 – 3:45 Budget Dellenback

3:45 – 4:15 Schedule Dellenback

4:15 – 4:45 Open Discussion / Action Item Summary All

Page 5: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 5

Meeting ObjectivesMeeting Objectives

Provide overview of:

– Development Team

– Software Architecture

– Components being implemented

– Budget

– Schedule

Not an objective:

– Discuss specific design details

Page 6: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 6

Release 3.0 Development Release 3.0 Development ActivitiesActivities

Page 7: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 7

Software OwnershipSoftware Ownership

Page 8: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 8

AgendaAgenda

Time Item Lead

1:00 – 1:10 Introductions and Opening Remarks Tillander

1:10 – 1:20 High Level Overview – meeting objectives Dellenback

1:20 – 1:30 Project Team Dellenback

1:30 – 2:45

High level discussion of work items:AVLEvent ManagementReporting SubsystemRoad RangerIncident DetectionEvent ViewerConfiguration EditorOperational InterfaceAmerican Dynamics CCTV DriverMessage Arbitration System modificationsEH / SL EnhancementsVariable Speed Limit Signs511Web ServerOperational Data Store Build

Heller

2:45 – 3:00

General activities:DocumentationFAT Deployments

Dellenback

3:00 – 3:15 Break

3:15 – 3:30 Budget / Schedule Dellenback

3:30 – 4:00 Open Discussion / Action Item Summary All

Page 9: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 9

Project TeamProject Team

Page 10: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 10

AgendaAgenda

Time Item Lead

1:00 – 1:10 Introductions and Opening Remarks Tillander

1:10 – 1:20 High Level Overview – meeting objectives Dellenback

1:20 – 1:30 Project Team Dellenback

1:30 – 2:45

High level discussion of work items:AVLEvent ManagementReporting SubsystemRoad RangerIncident DetectionEvent ViewerConfiguration EditorOperational InterfaceAmerican Dynamics CCTV DriverMessage Arbitration System modificationsEH / SL EnhancementsVariable Speed Limit Signs511Web ServerOperational Data Store Build

Heller

2:45 – 3:00 Overlap of Reporting Subsystem and Operational Data Store Heller

3:00 – 3:15 Break

3:15 – 3:30General activities:DocumentationFAT Deployments

Dellenback

3:30 – 3:45 Budget Dellenback

3:45 – 4:15 Schedule Dellenback

4:15 – 4:45 Open Discussion / Action Item Summary All

Page 11: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 11

Release 3.0 Development Release 3.0 Development ActivitiesActivities

Page 12: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 12

AVLAVL

Data Driver Development; note that this provides “generic” support for any class of vehicle that has “AVL capability” that can be reported (e.g. Road Ranger, Maintenance Vehicle, etc.):

– D4 Tablet

– XML Interface (based on D7’s efforts)

Subsystem Development

– Design new database tables

– Subscribe for RR location data from RR subsystem

– Subscribe for AVL location data from External Data driver

– Publish location update data to subscribers

– Store location update data to database

– Develop queries for retrieving vehicle track records

– Develop geo-location queries for geo-fence violations

Page 13: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 13

AVL: continuedAVL: continued

GUI Development– Develop vehicle icon selector– Develop geo-fence creation and editing functionality– Develop vehicle status and position updates for display– Develop vehicle list, summary, and detail dialogs– Develop “Find Vehicle on Map” functionality– Develop “breadcrumb track” data retrieval and display– Develop Admin Editor screen for add and deleting

tracked vehicles– Develop Admin Editor screen for maintaining AVL data

source locations

Page 14: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 14

Event ManagementEvent Management

Migrating Release 2.2.0 to “SunGuideSM Compliant”; implies building an “EM Subsystem” that is compliant to the SunGuideSM Architecture Guidelines

EM will be based on the requirements used to build Release 2.2.0

Release 2.2.0 had two methods of “event management”:– HTML GUI that supports single incident management– Tabular GUI that supports multiple “events”

Features will be combined into a SINGLE GUI and termed “event management”

Page 15: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 15

Event Management: continuedEvent Management: continued

Manage events and EM user permissions– Users may add, modify, delete events– Users may associate related events, contacts

Activate and deactivate response plans– Send DMS, HAR, remote messages to MAS as

recommended– Send recommended email messages

Process event data subscriptions

GUI enables input for Road Ranger performed activities

Page 16: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 16

Event Management:Event Management:Response Plan GenerationResponse Plan Generation

“Old” Incident Management subsystem is migrating to a “Response Plan Generator” (i.e. all incident/event management will be combined in the EM subsystem)

Generate response plans– Messages generated as specified by:

• Message templates• Abbreviations• Device linking information• Event parameters (location, severity, etc.)

Suggest applicable email alert messages when generating a response plan

Recommend predefined response plans as appropriate Manage message and device templates

– Add, modify, and delete message templates Manage device templates Manage predefined plans

– Add, modify, and delete predefined plans

Page 17: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 17

Road RangerRoad Ranger

The RR subsystem will be used to manage, dispatch, collect data and coordinates of RR Service Patrols.

Collect and provide vehicle status information– Vehicle and beat identification– Status (e.g. patrolling assist-motorist, etc)

Collect and provide shift information– Shift start and end times.– Vehicle mileage.– Driver, vehicle, radio, and route identification

Page 18: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 18

Road Ranger: continuedRoad Ranger: continued

Collect and provide service call information– Dispatch, arrival, and departure times– Location– Reason for stop– Services rendered– Lane blockages

Drivers:– District 4 Tablet PC– XML based interface

Page 19: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 19

Incident DetectionIncident Detection

Subsystem Development– Design new database tables– Subscribe for TSS alarms from TSS– Subscribe for VisioPaD alarms from driver– Publish combined alarms to subscribers– Log alarms to database

VisioPaD Driver Development– Accept incident data from CitiLog TCP Server– Publish incident alarms to ID subsystem

GUI Development– Adapt current TSS Alarm handling to include VisioPaD

alarms– Send Alarm Dismissed or Accepted message to IDS– Create and send new Event message to EM

Page 20: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 20

Event Viewer (EV)Event Viewer (EV)

The EV will be a read only web site that displays the following: – Active events with a lane blockage– Active events without a lane blockage– Recently inactive events

The site will provide an "Event Details" page that will display details about a specific event record

The EV web site runs on a Windows IIS server

The EV web site will prompt for a username and password

An administrative application will also be provided to set up accounts for the web site

Page 21: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 21

Configuration EditorConfiguration Editor

‘config.xml’ file is the master configuration file for all SunGuideSM processes

If an error is made in editing the XML file it can cause serious side effects

Windows based editor will be developed that simplifies the editing process (and make it less error prone)

Will be rarely used

Page 22: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 22

Operational Interface (GUI Mods)Operational Interface (GUI Mods)

Modify functionality to support District 5 requirements:– Record and Preview .wav files (used in conjunction with

511)– Generate alerts when incidents are “over” – Modify the display of TSS data– Provide additional capability to alter the color coding

scheme used by an operator

Page 23: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 23

American Dynamics CCTV DriverAmerican Dynamics CCTV Driver

District 5 requirement

Develop a CCTV Driver:– For a American Dynamics SpeedDome camera: RAS917-

OPC Speed Dome ultra 7 version 11) – The driver will implement the communications protocol

defined by American Dynamics for that camera

The driver will allow for configuration via XML file of the standard CCTV subsystem camera commands (pan, tilt, zoom, focus iris) to allow for adding other camera types via configuration file RATHER than developing custom drivers (does not work for NTCIP devices)

Page 24: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 24

Message Arbitration System ModsMessage Arbitration System Mods

Optionally combine messages in a queue (specifically Travel Time with another message)

Page 25: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 25

EH / SL EnhancementsEH / SL Enhancements

Status Logger (performance enhancement)– Develop C# client library– Develop Java client library

Executive Handler– Convert binary EH data types to XML format– Add EH process list editing to SunGuideSM installer

Page 26: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 26

Variable Speed Limit Signs (VSLs)Variable Speed Limit Signs (VSLs)

Using TSS data as a basis, recommendations for new speed limits will be “displayed” (prompted) to the user

“Thresholds” will be configurable by the system administrator

Will require user interaction to be displayed

Messages will go through MAS to VSL devices

VSLs will be displayed on the map

Any changes will be logged

Page 27: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 27

511511

511 Messages (simple view):– Floodgate– Link Condition– Travel Times

Will gather travel time information (sensor independent) from the Travel Time subsystem via the data bus

Messages will be created based on the Travel Time data

WAV files will be create in accordance with D5 “rules” (established as part of the iFlorida project)

Interface to Logictree will be developed to place WAV files on the “live” 511 telephonic system

Message library management tools will be developed

Page 28: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 28

Web ServerWeb Server

“Clickable” regions will be configurable by the administrator

Many configurable parameters

Map features will include:– Traffic information– Cameras– DMSs– Abnormal road conditions– Alerts– Event Icons– All monitored facilities (roadways, ramps, etc)– Statewide traffic monitoring sites (as icons)– Color-coded roadways– Road segments with no data available (if no data is available

for that segment)– Legend for all colors and icons

Page 29: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 29

Web Server: continuedWeb Server: continued

Popups– Roadway link travel conditions– Current event report (from event icon)

Links to Other Web Sites (all configurable)– All metro, regional web sites– 511– Help page– Email to webmaster/customer support

Miscellaneous Information– Emergency information banner for large/serious conditions– Weather information– Road closures– Major events– Construction– 511 Logo/Banner/Promotional text

Page 30: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 30

Reporting SubsystemReporting Subsystem

Migrating Release 2.2.0 to “SunGuideSM Compliant” based on the requirements provided (i.e. same functionality)

Generate reports for the following:– Performance measures– Road Ranger activities and status– SunGuideSM software availability:

• Central computer system• Information portal• Video Wall

– Device availability– Camera usage– Incident management monthly report– Traveler information monthly report– Traffic flow monthly report– Vehicle and position report

Page 31: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 31

Operational Data StoreOperational Data Store

ODS:

– A database repository for generating reports contained in the iFlorida CFDW SDD (needed by the iFlorida FOT)

– The repository maintains three years of data– Different than the SunGuideSM “Data Archive” (flat file based)

ReportsTraffic Detector Data Tables Traffic Speed Graphs by Segment

Toll Tag Reader Data Tables Daily Summary of Suspect Data

Travel Time Data Tables Typical Volumes by Detector

Summary Count Tabulations by Detector Summary Report Tabulations by RWIS

Traffic Volume Graphs by Detector Road Weather Graphical Data Reports

Summary Count Tabulations by Segment 511 Messages and Traffic Conditions

Traffic Volume Graphs by Segment Post-Incident Analysis

Spot Speed Tabulations by Detector Daily Incident Report

Traffic Speed Graphs by Detector Traveler Information Web Site Usage

Average Speed Tabulation by Segment DMS / VSL Usage

Page 32: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 32

Combined Reporting ConceptCombined Reporting Concept

Motivation– Requirements review identified 7 common reports– Common interface

Common GUI – User presented with report selection– Report parameter input

Reporting subsystem– Crystal Report Template– Retrieves data

• SunGuideSM Database• ODS

– Formats report

Data archive writes– ODS tables– CSV archive file

Reporting / ODS GUI

Data Bus

Reporting Subsystem

Data Archive

CSV Data Archive Flat

FileSunGuide Database

Operational Data Store

Page 33: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 33

AgendaAgenda

Time Item Lead

1:00 – 1:10 Introductions and Opening Remarks Tillander

1:10 – 1:20 High Level Overview – meeting objectives Dellenback

1:20 – 1:30 Project Team Dellenback

1:30 – 2:45

High level discussion of work items:AVLEvent ManagementReporting SubsystemRoad RangerIncident DetectionEvent ViewerConfiguration EditorOperational InterfaceAmerican Dynamics CCTV DriverMessage Arbitration System modificationsEH / SL EnhancementsVariable Speed Limit Signs511Web ServerOperational Data Store Build

Heller

2:45 – 3:00 Overlap of Reporting Subsystem and Operational Data Store Heller

3:00 – 3:15 Break

3:15 – 3:30General activities:DocumentationFAT Deployments

Dellenback

3:30 – 3:45 Budget Dellenback

3:45 – 4:15 Schedule Dellenback

4:15 – 4:45 Open Discussion / Action Item Summary All

Page 34: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 34

AgendaAgenda

Time Item Lead

1:00 – 1:10 Introductions and Opening Remarks Tillander

1:10 – 1:20 High Level Overview – meeting objectives Dellenback

1:20 – 1:30 Project Team Dellenback

1:30 – 2:45

High level discussion of work items:AVLEvent ManagementReporting SubsystemRoad RangerIncident DetectionEvent ViewerConfiguration EditorOperational InterfaceAmerican Dynamics CCTV DriverMessage Arbitration System modificationsEH / SL EnhancementsVariable Speed Limit Signs511Web ServerOperational Data Store Build

Heller

2:45 – 3:00 Overlap of Reporting Subsystem and Operational Data Store Heller

3:00 – 3:15 Break

3:15 – 3:30General activities:DocumentationFAT Deployments

Dellenback

3:30 – 3:45 Budget Dellenback

3:45 – 4:15 Schedule Dellenback

4:15 – 4:45 Open Discussion / Action Item Summary All

Page 35: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 35

AgendaAgenda

Time Item Lead

1:00 – 1:10 Introductions and Opening Remarks Tillander

1:10 – 1:20 High Level Overview – meeting objectives Dellenback

1:20 – 1:30 Project Team Dellenback

1:30 – 2:45

High level discussion of work items:AVLEvent ManagementReporting SubsystemRoad RangerIncident DetectionEvent ViewerConfiguration EditorOperational InterfaceAmerican Dynamics CCTV DriverMessage Arbitration System modificationsEH / SL EnhancementsVariable Speed Limit Signs511Web ServerOperational Data Store Build

Heller

2:45 – 3:00 Overlap of Reporting Subsystem and Operational Data Store Heller

3:00 – 3:15 Break

3:15 – 3:30General activities:DocumentationFAT Deployments

Dellenback

3:30 – 3:45 Budget Dellenback

3:45 – 4:15 Schedule Dellenback

4:15 – 4:45 Open Discussion / Action Item Summary All

Page 36: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 36

Factory Acceptance Testing (FAT)Factory Acceptance Testing (FAT)

Steps:

– Functional Configuration Audit (FCA)

– Test Readiness Review (TRR)

– FAT Execution:

• Planned for Aug 6-10, 2007

Software will be installed at TERL for IV&V and deployed to existing RTMCs after the IV&V

Page 37: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 37

Deployments Planned Deployments Planned

Deployment to existing installations:– D2– D4– D5– D6– D7– TERL

New Deployments– Palm Beach– Ft. Myers– One site TBD

Staff: combination of SwRI (TERL and SA) and IBI staff

Page 38: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 38

DocumentationDocumentation

Documents to be updated:– Software Requirements Specification (SRS)– Software Design Document (SDD)– Interface Control Documents (ICDs)– Version Description Document (VDD)– Software User’s Manual (SUM)– Database Design Document (DBDD)– Software Integration Plan (SIP)– Software Integration Case Procedures (SICP)– Administrator training material

Other:– Rational RequisitePro (requirements) Database

Page 39: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 39

SunGuideSunGuideSMSM Upgrades Upgrades

Upgrade:– “Turning on” a new subsystem: run the installer and

install just the new subsystem– Major releases can potentially require significant

upgrades to many components

Installer:– No confidence in running installer in “repair mode”

(little success in getting it to work in a complex environment such as SunGuideSM)

– For release 3.0: SwRI will develop script to copy critical files and restore after “upgrade”

Page 40: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 40

AgendaAgenda

Time Item Lead

1:00 – 1:10 Introductions and Opening Remarks Tillander

1:10 – 1:20 High Level Overview – meeting objectives Dellenback

1:20 – 1:30 Project Team Dellenback

1:30 – 2:45

High level discussion of work items:AVLEvent ManagementReporting SubsystemRoad RangerIncident DetectionEvent ViewerConfiguration EditorOperational InterfaceAmerican Dynamics CCTV DriverMessage Arbitration System modificationsEH / SL EnhancementsVariable Speed Limit Signs511Web ServerOperational Data Store Build

Heller

2:45 – 3:00 Overlap of Reporting Subsystem and Operational Data Store Heller

3:00 – 3:15 Break

3:15 – 3:30General activities:DocumentationFAT Deployments

Dellenback

3:30 – 3:45 Budget Dellenback

3:45 – 4:15 Schedule Dellenback

4:15 – 4:45 Open Discussion / Action Item Summary All

Page 41: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 41

BudgetBudget

AVL $234,792.00

Event Management $263,512.00

Reporting Subsystem $157,181.00

Road Ranger $131,023.00

Incident Detection $66,483.00

Event Viewer $49,951.00

Configuration Editor $25,005.00

Operational Interface $34,548.00

American Dynamics CCTV Driver $37,900.00

Message Arbitration System Modifications $17,444.00

EH / SL Enhancements $32,383.00

Variable Speed Limit Signs $24,574.00

511 $193,960.00

Web Server $93,111.00

Operational Data Store Build $216,587.00

FAT $55,085.00

Documentation $34,402.00

D5 Testing / Documentation / Deployment $51,133.00

Deployments $164,563.00

Page 42: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 42

AgendaAgenda

Time Item Lead

1:00 – 1:10 Introductions and Opening Remarks Tillander

1:10 – 1:20 High Level Overview – meeting objectives Dellenback

1:20 – 1:30 Project Team Dellenback

1:30 – 2:45

High level discussion of work items:AVLEvent ManagementReporting SubsystemRoad RangerIncident DetectionEvent ViewerConfiguration EditorOperational InterfaceAmerican Dynamics CCTV DriverMessage Arbitration System modificationsEH / SL EnhancementsVariable Speed Limit Signs511Web ServerOperational Data Store Build

Heller

2:45 – 3:00 Overlap of Reporting Subsystem and Operational Data Store Heller

3:00 – 3:15 Break

3:15 – 3:30General activities:DocumentationFAT Deployments

Dellenback

3:30 – 3:45 Budget Dellenback

3:45 – 4:15 Schedule Dellenback

4:15 – 4:45 Open Discussion / Action Item Summary All

Page 43: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 43

ScheduleSchedule

Important dates:– Design Reviews:

• “iFlorida” related activities: May 2-3, 2007, D5 Headquarters, Deland

• EM / PM / RR / AVL: May 8-9, 2007 – D6 RTMC, Miami– FAT: Aug 6-10, 2007 – SwRI, San Antonio– IV&V: Aug 29-30, 2007 – TERL, Tallahassee

Post-development dates:– Source code, installers, documentation to FDOT by

September 3, 2007– Deployment:

• Districts (order TBD): early October (note: this date could be accelerated based on the “speed” of IV&V)

Page 44: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 44

Detailed Schedule ReviewDetailed Schedule Review

Page 45: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 45

AgendaAgenda

Time Item Lead

1:00 – 1:10 Introductions and Opening Remarks Tillander

1:10 – 1:20 High Level Overview – meeting objectives Dellenback

1:20 – 1:30 Project Team Dellenback

1:30 – 2:45

High level discussion of work items:AVLEvent ManagementReporting SubsystemRoad RangerIncident DetectionEvent ViewerConfiguration EditorOperational InterfaceAmerican Dynamics CCTV DriverMessage Arbitration System modificationsEH / SL EnhancementsVariable Speed Limit Signs511Web ServerOperational Data Store Build

Heller

2:45 – 3:00 Overlap of Reporting Subsystem and Operational Data Store Heller

3:00 – 3:15 Break

3:15 – 3:30General activities:DocumentationFAT Deployments

Dellenback

3:30 – 3:45 Budget Dellenback

3:45 – 4:15 Schedule Dellenback

4:15 – 4:45 Open Discussion / Action Item Summary All

Page 46: SunGuide SM  Software Development Project Release 3.0 Kick-off Meeting April 5, 2007

April 5, 2007Release 3.0 Kickoff Meeting 46

Discussion ?