    Summary of Subsidiary Plans

    Risk Management Plan

    The Risk Management Plan describes the methodology of the risk managementprocess that will be implemented for the duration of the project. There are tools and

    techniques stating how to properly identify risks, and to determine the probability and

    impact of incident occurrences. The risks are assessed both qualitatively and

    quantitatively. The Risk Owners consist of Dr. Lipsett, Roger Marchand, AICT and the

    University of Alberta facilities. Dr. Lipsett and Roger Marchand are responsible for risks

    generated by the project, while AICT and University of Alberta Facilities are responsible

    for risks posed by the environment wherein the project takes place. Any risk-related

    documentation additions or adjustments will be made following the specified process.

    Any changes made to the Execution Phase of the project may impose new risks, which

    will require a complete iteration of the risk assessments in the specified area. Anychanges to the Risk Management Plan must be approved by Dr. Lipsett directly.

    Risk Register

    All risks that have been currently identified within the project have been compiled into

    the Risk Register. The register specifies the types of risks, their probability of occurring

    and the impact that an incident would have on the project. Each risk has been assigned

    a Risk Owner who will be responsible for all aspects of that risk, as well as a response

    plan for all possible incidents. As new risks are identified during the life cycle of the

    project, the Risk Register is to be updated as per documentation guidelines.

    Gantt Chart

    The Laboratory Development Project was initiated on January 31st, 2011, and the

    initiation phase was completed on February 21st, 2011. The Planning Phase was

    initiated on February 22nd, 2011. A draft of the Project Planning Report was submitted

    to Dr. Lipsett for review on March 22nd

    , 2011 to acquire feedback about the contents ofthe report, and to obtain any further recommendations that were not already stated by

    the project team. The Planning Phase was closed on April 11th, 2011. The duration

    Execution Phase will be from May 1st, 2011 to May 30th, 2011. At that point, and Dr.

    Lipsett will assess the completion and determine if any further actions need to take

    place to satisfy the project requirements.

  • 8/7/2019 Summary of Subsidiary Plans

    2/2

    Layout Plan

    A proposed layout of Mec E 1-38 has been created. Laboratory dimensions, existing

    architecture, and electrical supplies have been included. Suggested locations of

    furniture and equipment have been specified. The layout plan is subject to change as

    per stakeholder requests during the Execution Phase.