summary environmental effect...
TRANSCRIPT
S
um
mary
En
vir
on
men
tal
Eff
ect
Rep
ort
23
Summary Environmental Effect Report
In the Rotterdam port area space is needed
to accommodate the growth of port and industri-
al activities. With continuing economic growth, it
is expected that port and industrial activities will
also grow. Due in part to these economic deve-
lopments, the quality of the living environment
in Rijnmond has come under pressure. The cab-
inet therefore wants to decide on a package of
measures to accomplish the following:
• to reinforce the Rotterdam mainport by
solving the anticipated space shortage for
port and industrial activities;
• to improve the quality of life in Rijnmond by
utilising the opportunities afforded by
solving the space shortage problem.
Following studies and consultations in the
context of the Rotterdam Mainport
Development Project, the cabinet would like to
go ahead with three sub projects designed to
realise this double objective:
• the Existing Rotterdam Area (ERA) – a set of
projects aimed at more intensive utilisation
of space in the existing port and industrial
area and improvement of the quality of the
environment and the living environment;
• land reclamation – a new port and industrial
area of 1,000 net hectares, linked to the
existing Maasvlakte, which would be con-
structed in stages;
• a 750-hectare wildlife and recreational area
– a large-scale wildlife and recreational area
near Rotterdam, designed to improve the
quality of the living environment.
The Core Planning-plus Decision Process
(PKB+)
The decision process concerning the
Rotterdam Mainport Development Project will
take place via a Core Planning-plus Decision
Process (PKB+), with respect to the following
subjects:
• the location and scope of the land reclama-
tion;
• the area within which sand extraction may
take place;
• possible locations for compensating natural
resources lost through land reclamation;
• the location(s) and layout of a 750-hectare
wildlife and recreational area.
The PKB+ will reserve the necessary space
for the land reclamation and the 750-hectare
wildlife and recreational area sub projects and
the preconditions will be established for the
further elaboration of these two sub projects.
The preconditions, for example, concern fitting
in spatially, the environment, quality of life and
the economy. The project activities of the
‘Existing Rotterdam Area’ (ERA) sub project
concern the question of how the sub projects
contribute to the realisation of the double
objective. The PKB+ will also make this assess-
ment with respect to the other two sub proj-
ects.
Introduction
2424
25
Summary MER
S
um
mary
En
vir
on
men
tal
Eff
ect
Rep
ort
25
The Role of the Environmental Effect Report in
PKB+
For several of the activities from the PKB+
Rotterdam Mainport Development Project, an
environmental effect report (MER) procedure
must be followed. The environmental effect
report, which describes the effect of the sub
projects, was formulated in that context. The
MER provides the environmental data needed
for a proper weighing of interests in the deci-
sion process on the PMR projects.
This MER Rotterdam Mainport Development
Project provides answers to the following
questions:
• what are the positive and negative effects of
the sub projects?
• how can the negative effects be mitigated
(softened) and compensated for?
• to what extent will they contribute to the
second part of the double objective?
• what would be the most environmentally
friendly implementation of the sub projects?
Nearly all activities that take place in the
context of the Existing Rotterdam Area sub proj-
ect – as far as can be determined at present –
will not be subject to the MER. The MER report
describes these activities. They provide insight
in the contributions of the projects designed to
improve the quality of life in and around the
port.
The construction of a new strip of land at
sea would affect protected natural areas. In
these areas the ‘no, unless’ principle from
national and European nature conservation
regulations will apply. The ‘no, unless’ principle
describes the pros and cons that must be consid-
ered to ensure a carefully decision about land
reclamation. The PKB+ explains how the ‘no,
unless’ principle is applied, making use of infor-
mation from this MER. This information particu-
Figure S.1 Search areas of the Rotterdam Mainport Development Project (sub projects)
Den Haag
Goeree
Voorne
Rotterdam
search area 750 ha wildlife & recreational area
search area sanddredging
search area landreclamation
existing Rotterdam area
2626
larly refers to the effect of land reclamation on
protected natural areas, along with mitigation
and compensation of such areas.
The environmental effect report was com-
piled for part 1 of the PKB+, which contains the
policy plans formulated by the cabinet. MER
and part 1 of the PKB+ are subject to public
participation, legal advice from the Commission
for Environmental Effect Reports and adminis-
trative consultation, among others. The results
of this are described in part 2. In part 3 of the
PKB+, as a result of this information, the
cabinet formulated its definitive standpoint
about the project and submitted it for approval
to the Lower and Upper Houses. If they agree
with the cabinet’s standpoint, possibly in re-
vised form, there will be an official government
resolution and the implementation of the sub
projects can get underway.
Marker
The environmental effect report on the
Rotterdam Mainport Development Project con-
sists of three memorandums, a main report and
this summary. The summary deals with the fol-
lowing subjects:
Problem, vision and objective:
• the need to provide space in the port of
Rotterdam;
• bottlenecks in the quality of the living envi-
ronment;
• the vision relating to the development of the
Rotterdam mainport;
• the cabinet’s project objective.
Solutions:
• the possibilities for realising the project
objective;
• the choice of three sub projects;
• the existing Rotterdam area sub project;
• the land reclamation sub project;
• the 750-hectare wildlife and recreational
area sub project;
• alternatives to PMR.
Effects of the solutions:
• effects per theme;
• effects from a local perspective;
• effects on protected natural areas and the
consequences for mitigation and compensa-
tion;
• PMR’s contribution to resolving bottlenecks
in the quality of the living environment;
• PMR’s contribution to political ‘environmen-
tal’ criteria.
27
Summary MER
S
um
mary
En
vir
on
men
tal
Eff
ect
Rep
ort
Existing Maasvlakte
Skyline of Rotterdam seen from the Maasboulevard
The need to provide space for expansion in the
port of Rotterdam.
With stable and rapid economic growth, the
cabinet foresees a short-term space shortage
in the existing port and industrial area at
Rotterdam. This particularly applies to the
deep-sea container sector, related distribution
and chemical sectors. The scale of the expected
space shortage is difficult to estimate with cer-
tainty. To determine the scale of the space
shortage, the assumption was that there would
be a bandwidth of growth in world trade and its
consequences for supply, dispatch and trans-
hipment via Rotterdam port. The demand for
industrial sites by deep-sea-related companies,
which cannot be satisfied in the existing area,
could vary with rapid economic growth from
350 to 700 hectares in 2020. This estimate does
not allow for space demands related to urbani-
sation and new industrial activities.
Bottlenecks in the Quality of the Living
Environment
There is a large concentration of companies
in the Rotterdam region. Because of the con-
centration of activities in this area, virtually all
forms of environmental effect are present. In
past decades, economic development and relat-
ed urban growth have put increasingly pressure
on the remaining wildlife and recreational
areas. Production and transport activities in the
Rotterdam region, moreover, contribute to
(supra) regional environmental problems.
Figure S.2 gives a profile of the Rotterdam
region. Table S.1 summarises the major bottle-
necks for environmental quality, the country-
side, recreation and spatial quality. This table
also includes an indication of autonomous
developments – the projected situation in
Rijnmond if the cabinet’s proposals for develop-
ing the Rotterdam mainport are not imple-
mented.
Vision on the Development of Rotterdam
Mainport
Taking the strengths of the Dutch economy
as starting points, the cabinet would like to
reinforce the position of the Netherlands as an
international trading and industrial country.
Rotterdam mainport is one of these strengths.
For this reason, the cabinet is endeavouring to
create favourable conditions in the Rotterdam
region for existing and new companies. These
conditions include sufficient space, good acces-
sibility and sustainable development of goods
transport. The cabinet favours improving the
quality of life in the Rotterdam region. The
region must offer sufficient space, greenery,
recreational and leisure facilities to make the
area an attractive place to live and work.
These cabinet aspirations dovetail well with
the spatial vision of the Rotterdam region
Problem, vision and objective
2828
29
Summary MER
S
um
mary
En
vir
on
men
tal
Eff
ect
Rep
ort
29
towards developing the area. This vision as-
sumes teamwork on the part of the city, the
port and the (Rijn-Maas) delta. Besides
developing the port, the region endeavours to
see the further growth and development of the
urban economy and more, higher quality wild-
life and recreational areas in the delta.
The Cabinet’s Project Objective
Based on existing bottlenecks in the
Rotterdam region and the vision of developing
Rotterdam mainport and the surrounding area,
the cabinet has formulated the aforementioned
double objective as follows:
• reinforcing the mainport by solving the
space shortage problem;
• improving the quality of life in the
Rotterdam region by utilising the potential
afforded by resolving the space shortage.
In formulating the plans for realising this
objective, along with the Municipality province
of South Holland, Metropolitan Area and the
Municipality of Rotterdam, the national govern-
ment started the Rotterdam Mainport
Development Project.
Figure S.2 Profile of Rijnmond region
Den Haag Zoetermeer
Delft
Pijnacker
Berkel enRodenrijs
Bleiswijk
Hoek van Holland
Oostvoorne
Brielle
Maassluis
Rozenburg VlaardingenRotterdamSchiedam
Spijkenisse
HoogvlietBarendrechtVoorne-Putten
Hellevoetsluis
Rockanje
VlissingenAntwerpen
Haringvliet
Maasvlakte
SlufterEuropoort
Nieuwe MaasBotlek
Oude Maas
WaalhavenEemhaven
VierhavensMerwehaven Park bij Euromast
Kralingse bos
Nieuwe Waterweg
Hartelkanaal
Spui
De Ro
tte
Delftse Schie
Maasgeul
Bernisse
Midden Delfland
PolderSchieveen
Duinen van Voorne
Brielse meer
Voordelta
Duinen van GoereeKleinProfijt
Rhoonsegrienden Carnisse
grienden
Albrandswaard
PortlandCarnisselande
Zuiderpark
Oostvoornse meer
N57
N496
N15
Beerdam
A15
A29
A16
A20
A13
A4
N218
A20
Stenen Baakplein
DintelhavenbrugSuurhoffbrug
Hartelbrug
Calandbrug
Botlekspoortunnel
Botlektunnel
Beneluxtunnel
Beneluxplein
Ridderster
Van Brienenoordbrug
Noorderdam
5km0
3030
current bottlenecks autonomous developments
environmental
quality
wildlife
recreation
spatial
quality
• CO2 emissions are currently increasing
• NOx-, SO2-deposits are above the established
policy aims
• NO2 and fine dust have exceeded limits at
several locations
• stench and dust nuisance in residential areas
exceeds established policy aims
• traffic noise level is a bottleneck
• a small number of sweet water tidal areas
(characteristic estuary resources)
• lack of a dynamic of dune coast
• too few, large-scale (inner dike) natural areas
• natural areas are under pressure due to
increasing urbanisation and other space
utilisation
• too few interconnections between natural
areas
• lack of greenery close to the city
• accessibility of natural areas for tourists is
insufficient
• recreational facilities are lacking in quality
• no optimum use of available, scarce space
(utilisation value)
• proximity to beach, dunes and woods. The per-
ception of greenery and the village character
of the town and air quality are important (per-
ceptual values) for the residents of the
Rotterdam region
• reduction in the quality of the living environ-
ment is putting pressure on a good business
establishment climate (future value)
• without supplementary measures, the intended
reduction objectives for air quality and noise
pollution would not be met
• environmental quality could come under further
pressure due to increasing acceptance by the
surroundings of nuisance and inconvenience,
the introduction of a 24-hour economy, in-
crease in space productivity and intensification
of utilisation of the existing port and industrial
area
• the quality of the natural environment will
come under further pressure due to increased
urbanisation, e.g.
• realisation of the Provincial ecological main
structure and the Green-Blue Ribbon
• recovery of natural resources through changed
management of the Haringvliet sluices
• the quality of recreational facilities will come
under further pressure due to increased ur-
banisation and increasing demand
• recreational behaviour will be more variable
and less time will be spent on one type of
recreation
• more leisure time will be used to going out,
visiting outdoor recreation and sport
• without supplementary the Rotterdam region,
spatial quality (utilisation value, perception
value and future value) will deteriorate
Table S.1 Major bottlenecks in the quality of the living environment
31
Summary MER
S
um
mary
En
vir
on
men
tal
Eff
ect
Rep
ort
31
Possibilities of realising the Project Objective
In May 1998 the preliminary memorandum
PKB+/MER, Rotterdam Mainport Development
Project appeared. It contained the following
possible solutions, which needed to be exam-
ined to resolve the space shortage and, in this
context, to improve the quality of the living
environment:
• better utilisation of the existing port and
industrial sites in the Rotterdam area;
• better utilisation of existing and planned
port and industrial sites in Southwest
Netherlands (Moerdijk, Vlissingen and
Terneuzen);
• land reclamation for a new port and
industrial area in the form of an expansion
of the Maasvlakte.
Restricted Possibilities in the Existing Area
The study relating to better utilisation of the
existing area resulted in the conclusion that the
demand for space could not be fully satisfied
there. In particular, there will be insufficient
space for the container sector and for new
chemical companies. There were limited oppor-
tunities for expanding existing companies and
for intensifying existing sites. There were also
possibilities for improving the quality of the
living environment, such as controlling local
noise pollution or developing city greenery.
Southwest Netherlands, Insufficient Solace
The harbours of Southwest Netherlands do
not offer any solution for petrochemicals. The
space still available at Terneuzen will be used
for the autonomous growth of the companies
in the area. In Moerdijk, space could only be
found by constructing industrial sites in the so-
called Moerdijk Corner. Developing this area,
however, could endanger the quality of life in
the urban area. In addition, qua location (shal-
low water, too far from the sea, inferior hinter-
land transport), the harbours of Moerdijk and
Terneuzen are not suitable for deep-sea contain-
er transhipment. Space could be developed in
the harbour of Vlissingen for establishing deep-
sea container terminals. Shipping companies,
however, apparently do not view Vlissingen as
an alternative to Rotterdam. The harbours of
Terneuzen, Vlissingen and Moerdijk therefore
have an independent, fully-fledged position in
the network of port and industrial sites around
Rotterdam mainport, supplementary to and
working in concert with Rotterdam port.
However, the harbours in Southwest
Netherlands offer insufficient solace for the
space shortage in Rotterdam port. Since
Southwest Netherlands does not offer a solu-
tion for the space shortage, any improvement
in the quality of the living environment, for
example, by housing environmentally hazard-
ous companies from Rotterdam region, is not
longer under discussion in the project.
Solutions
32
33
Summary MER
Land Reclamation offers Sufficient Space
The timely construction of new land in the
North Sea linked to the existing Maasvlakte
could provide qualitatively good space for new
port and industrial activities. With construction
in stages, ultimately a new, 1,000 net hectares
of port and industrial area could be created.
With rapid economic growth by 2020 there
would be space demands for between 350 and
700 hectares. Such space demand from deep-
sea-related growth sectors cannot be found in
the existing port area. In addition, allowances
have been made for space demands needed for
long-term urban development. Based on this,
the cabinet would like to realise a maximum of
1,000 net hectare port and industrial area. This
would provide sufficient space to accommodate
the growth of deep-sea container sector and
related distribution activities, as well as for any
new, large-scale chemical establishments. The
cabinet would also like to make it possible for
environmentally objectionable companies, after
carefully consideration, to be removed from the
existing to the new port area. This could im-
prove the quality of the living environment.
The MER takes a net land reclamation of 1,000
hectares as its starting point.
Wildlife and Recreational Area close to the
City
If it should be decided to proceed with land
reclamation, the cabinet would also like to con-
struct a 750-hectare wildlife and recreational
area close to the city. The plan of action and the
ROM-Rijnmond Policy Covenant have deter-
mined that there is a shortage of 1,750 hectares
of wildlife and recreational areas. It was agreed
that, in combination with port expansion, 750
hectares of this would be realised, physically
linked to the reclaimed land. Later, the cabinet
decided to realise the 750 hectares in and
around the urban area, since an easily accessi-
ble and open wildlife and recreational area near
the city would provide a better contribution to
the intended quality improvement of the living
environment.
A Choice of Three Sub Projects
Based on a study of three possible solu-
tions, the cabinet reached the conclusion that
the double objective of the Rotterdam Mainport
Development Project could best be realised by
making possible the three sub projects men-
tioned (see Figure S.1):
• the Existing Rotterdam Area;
• land reclamation;
• a 750-hectare wildlife and recreational area
in the vicinity of Rotterdam.
These three sub projects are inseparably
linked with each other and should be imple-
mented in mutual connection. Any improve-
ment in the quality of the living environment
could only be brought about in combination
with resolving the space shortage, and vice
versa.
Existing Rotterdam Area Sub Project (ERA)
The ERA sub project consists of 14 projects,
which should result in improving the quality of the
living environment and in creating extra space.
Projects for intensifying and optimising space
utilisation
• Filling in the fourth Petroleum Harbour and
the Hartel Canal West, which will create
extra space.
• An efficient utilisation of tank storage capac-
ity and refinery sites.
• Stimulating higher space productivity in the
container sector.
• Tightening land-issue policy (establishment,
land price and options policies), geared
towards more efficient utilisation of space.
• Stimulating and facilitating the cleaning up
of contaminated harbour sites, including use
of the soil decontamination fund, so that
S
um
mary
En
vir
on
men
tal
Eff
ect
Rep
ort
34
sites could be reused.
• Developing the Waalhaven East Future
Vision, a study of the westerly shift of the
boundaries between the harbour and the
city.
Projects for improving the quality of the living
environment
• Setting up a sound expertise centre to devel-
op technology for reducing noise nuisance.
• locally reducing noise pollution from traffic
by building double-layer ZOAB (very open
asphalt concrete), taking measures at the
Caland Bridge and placing baffle boards.
• Industrial ecology: developing a pilot project
for joint (energy) provision for multiple
companies or a cluster of companies in the
Botlek area.
• Construction of river parks at Delfshaven,
Tarwewijk, Oud-Charlois, Wielewaal,
Heijplaat and Pernis.
• Arranging greenery on the Rozenburg
Peninsula.
• Opening of Lake Oostvoorne: research into
the possibilities and desirability of re-estab-
lishing the sea link.
• Realising ferry connections for slow traffic
between Hoek van Holland, the Rozenburg
Peninsula and the existing Maasvlakte and
between Heijplaat and the north side of the
Maasoever.
• An area-targeted approach designed to
improve the quality of the living environ-
ment throughout the area round the har-
bour sites.
The Land Reclamation Sub Project
In the PKB+ part 1, the cabinet proposes
reserving space and preconditions for the con-
struction of reclaimed land. The final design of
the reclaimed land will only come about during
the following stages of the project. This design
should fit in the space allotted and precondi-
tions, including environmental considerations.
To assess the cabinet’s proposals for spatial
reservation and environmental preconditions,
the MER describes the environmental effect of
two realistic examples of potential land recla-
mation, the so-called reference designs I and II
(see figures S.3 and S.4).
The reference designs comprise the follow-
ing components:
• a harbour entry point;
• port and industrial sites;
• infrastructure;
• sea walls and dams.
These components function as building
blocks for the design, based on various possi-
bilities of shaping and fleshing them out. Other
important ingredients of the reference designs
are the location of the search area and meas-
ures to limit the negative environmental effect
(mitigation) as much as possible.
A northerly location
Reference designs I and II are both situated
in the northern part of the search area.
Together with the existing Maasvlakte, they
form a single large port and industrial area. A
southerly
variant also exists for reference design II, to
give an impression of the effects of a southerly
location.
Harbour entrance of sea-going vessels and
inland navigation
The reference designs differ from each other
in the way in which incoming sea-going vessels
enter the reclaimed land. In reference design I,
sea-going vessels would make use of the
existing harbour entrance. They would have to
sail around via a still-to-be-realised short-cut in
the existing Maasvlakte. As with sea-going ves-
sels, inland shipping would have access to the
reclaimed land via a short-cut. In reference
35
Summary MER
S
um
mary
En
vir
on
men
tal
Eff
ect
Rep
ort
demarcatielijn
Ouddorp
E U R O G E U L
M A A S G E U LNoorderdam
MOT - terrein
Hoek van Holland
M a a s v l a k t e E u r o p o o r t
Slufter
Voorne
Oostvoorne
Hellevoetsluis
Goeree
Oostvoornse Meer
Yangtzehaven
Brielse Meer
Harin
g-
vlie
t
nieuwe Zuiderdam
POSSIBLE LAYOUTS
containers
distribution
other sectors
chemicals
soft seawall
area for active outdoor sports
viewpoint Land’s Endaccess recreational area
access harbour
parking space
MaascentreNAP -25 to -40m
NAP 0 to -1m
NAP -1 to -3m
NAP -3 to -6m
NAP -6 to -15m
NAP -15 to -25m
viewpoint
beach and bank recreation
recreational centre
small watersport
Figure S.3 Reference design I
36
design II, the current harbour entrance would
be extended and constructed further into the
sea, so that sea-going vessels would have suffi-
cient length to reduce speed and sail directly to
the reclaimed land. Inland shipping would have
access to the reclaimed land via a short-cut
through the existing Maasvlakte.
Horseshoe-shape layout of the industrial sites
In laying out the reference designs, the new
port and industrial sites form a horseshoe
shape around a central harbour canal. Figure
S.4 shows a possible surface area partition of
the industrial sectors. The final partitioning will
be determined by space demand from the mar-
ket. The designs are flexible enough to offer
space for various arrangement scenarios.
Infrastructure for all forms of transport
The port and industrial area will be opened
up to all forms of transport. The current infra-
structure bundle in the south of the Maasvlakte
would be extended directly to the reclaimed
land. Space has already been reserved for this
at the existing Maasvlakte. A second road link
along the infrastructure bundle could be re-
served as a main artery for recreational traffic
and as an emergency means of opening up the
reclaimed land.
Soft sea walls and dams
Both reference designs show the sea walls
made of sand in the west and south (‘soft’ sea
walls). Although the cost of upkeep of soft sea
walls is greater than that of hard sea walls, the
construction costs are considerably lower.
Moreover, a soft sea wall fits in better with the
natural environment. In reference design I, the
southern dam would have to be extended par-
tially. In reference design II, the dams of the
existing harbour entrance would be extended.
Measures for mitigating negative environment
effect
Because of the northerly position of the port
and industrial sites with respect to the
Haringvliet Estuary, the sea will continue to
have a major influence on the Haringvliet
Estuary and the bordering dunes. Reference
designs I and II flesh out the endeavour to con-
serve the existing natural quality of the
Haringvliet Estuary and bordering dunes. In
addition, the reference designs included some
degree of natural development through the
construction of a soft sea wall. This stimulates
sand transport in the direction of the
Haringvliet Estuary, which enables new natural
resources to develop there.
The 750-Hectare Wildlife and Recreational Area
Project
A search was carried out both to the south
and the north of Rotterdam for the possibility of
developing one or more wildlife and recreation-
al areas with a combined size of 750 hectares.
Based on a bill of specifications, the search
area was restricted to the following locations
(see Figure S.5):
Central IJsselmonde
This polder area is situated among urban
areas (Rhoon, Portland/Carnisselande and
Rotterdam), de A15 motorway and the Oude
Maas. Currently, the area is mainly intended for
agriculture with some recreational use.
The North Flank of Rotterdam
This area comprises the Schiezone sub-
sections, the so-called intermediary zone (this
refers to the area among the urban districts of
Rotterdam, Berkel and Rodenrijs in South
Polder and Schiebroeks Polder) and a section of
Eendragts Polder. These areas currently have a
mainly agricultural function, but are situated on
the periphery of the urban district. Because of
their locations, the areas are very important as
sections of recreational and interconnected eco-
37
Summary MER
S
um
mary
En
vir
on
men
tal
Eff
ect
Rep
ort
demarcatielijn
Ouddorp
E U R O G E U L
M A A S G E U L
Noorderdam
MOT - terrein
Hoek van Holland
M a a s v l a k t e E u r o p o o r t
Slufter
Voorne
Oostvoorne
Hellevoetsluis
Goeree
Oostvoornse Meer
Yangtzehaven
Brielse Meer
Harin
g-
vlie
t
verlengde Noorderdam
nieuwe Zuiderdam
NAP -25 to -40m
NAP 0 to -1m
NAP -1 to -3m
NAP -3 to -6m
NAP -6 to -15m
NAP -15 to -25m
POSSIBLE LAYOUTS
containers
distribution
other sectors
chemicals
soft seawall
area for active outdoor sports
viewpoint Land’s Endaccess recreational area
access harbour
possible bridge connection
parking space
viewpoint
beach and bank recreation
recreational centre
small watersport
Figure S.4 Reference design II
38
logical zones
Three Main Variants
Three main variants have been developed
for these two locations jointly, based on cohe-
sion with other wildlife and recreational areas,
accessibility, nature development, perceptual
value and safety. In each of these three main
variants there is room for intensive and exten-
sive recreation and nature development.
Main Variant I
Main variant I consists of a 750-hectare wild-
life and recreational area at Central IJsselmonde.
The IJsselmonde plan area as a whole is seen
as an attractive, appealing and accessible wild-
life and recreational area (see Figure S.6). There
is room for intensive and extensive recreation
in the northern section. This section would be
designed as an open park with woods and with
ample space and recreational facilities (cycle
and footpaths, lawns, picnic areas and the like).
The layout and management in the southern
section are geared strongly towards the devel-
opment of wetland natural resources, which
could easily provide for extensive co-recrea-
tional use via a system of footpaths.
Connections to the city would be enhanced in
the form of a interconnected green zone.
Main Variant II
Main variant II consists of a 600-hectare wild-
life and recreational area at Central IJsselmonde
(northern section) and, in addition, 150 hectares
in the north flank of Rotterdam. This variant
corresponds to main variant I. However, a small
section in the south of the plan area would
retain its agricultural function (see Figure S.7).
This main variant also contains two possibilities
for fleshing out the location in the north flank
of Rotterdam (see Figures S.9 and S.10). One
possibility (variant A) consists of arranging the
Figure S.5 Central IJsselmonde and the north flank of Rotterdam
Midden IJsselmonde
Eendragtspolder
Schiezone
Intermediaire zone
Den Haag Zoetermeer
Delft
Pijnacker
Berkel enRodenrijs
Bleiswijk
Hoek van Holland
Oostvoorne
Brielle
Maassluis
Rozenburg VlaardingenRotterdamSchiedam
Spijkenisse
HoogvlietBarendrechtVoorne-Putten
Hellevoetsluis
Rockanje
VlissingenAntwerpen
Haringvliet
Maasvlakte
SlufterEuropoort
Nieuwe MaasBotlek
Oude Maas
WaalhavenEemhaven
VierhavensMerwehaven Park bij Euromast
Kralingse bos
Nieuwe Waterweg
Hartelkanaal
Spui
De Ro
tte
Delftse Schie
Maasgeul
Bernisse
Midden Delfland
PolderSchieveen
Duinen van Voorne
Brielse meer
Voordelta
Duinen van Goeree
KleinProfijt
Rhoonsegrienden
Carnissegrienden
Albrandswaard
PortlandCarnisselande
Zuiderpark
Oostvoornse meer
5km0
39
Summary MER
S
um
mary
En
vir
on
men
tal
Eff
ect
Rep
ort
Schiezone and Intermediary Zone sub areas
(together 150 hectares) as an extensive recrea-
tional area to support recreational routes and
ecological interconnections . The second possi-
bility (variant B) is the arrangement of the
Eendragts Polder sub area along the Rotte (150
hectares) for extensive and route-related recre-
ational and wildlife development.
Main Variant III
Main variant III also consists of 600 hectares
of wildlife and recreational area at Central
IJsselmonde (southern section), combined with
150 hectares in the north flank of Rotterdam.
This variant is the same as variant I, except for
a small section in the northwest of the Central
IJsselmonde plan area, which will retain its
present function (see Figure S.8). The layout of
the north flank corresponds to that of main
variant II.
For all three main variants, the possibilities
of reinforcing tidal waters for the southwestern
section of the IJsselmonde plan area (bordering
the Essen Dike and piping network) were stu-
died. The layout variants for this section of the
plan area consist of wetland with pastures (wet
mosaic landscape) or tidal environment. Both
variants offer accessibility for recreation via a
network of footpaths.
Alternatives of PMR
Besides a description of the separate sub
projects, attention was given to alternatives to
the total Rotterdam Mainport Development
Project (i.e. the combination of the three sub
projects). Descriptions were included of a Zero
Alternative and the Friendliest Environmental
Alternative (MMA), along with an alternative
consisting of a package of policy decisions of
the kind included in the PKB+ part 1 (the so-cal-
led Proposed Package of Policy Decisions).
Figure S.11 shows the relationships of the sub
Figure S.6 Variant I
A 15
Koedood zone
Heinenoordtunnel
golfbaan
Klein Profijt
Rhoonse grienden
Rhoon
Rotterdam Pendrecht
Zegenpolder
Portland - Carnisselande
Molenpolder
polderhet buitenland
van Rhoon
Portlandpolder
extensive recreation
intensive recreation
wet land
covering
piping network
New to develop
main route for slow traffic
main opening up with stop
green connection
Existing situation / autonomus development
Koedood
Essendijk
OudeMaas
Essendijk
0 250 500 750 1000 m
Carnisse grienden
40
Figure S.7 Variant II
Rhoonse grienden
A 15
Rotterdam Pendrecht
Rhoon
Heinenoordtunnel
Portland - Carnisselande
Klein Profijt
golfbaan
Koedood zone
Zegenpolder Molenpolder
polderhet buitenland
van Rhoon
Portlandpolder
extensive recreation
intensive recreation
wet land
covering
piping network
New to develop
main route for slow traffic
main opening up with stop
green connection
Existing situation / autonomus development
Essendijk
OudeMaas
Koedood
Essendijk
0 250 500 750 1000 m
Carnisse grienden
Figure S.8 Variant III
polderhet buitenland
van Rhoon
A 15
Koedood zone
Heinenoordtunnel
golfbaan
Klein Profijt
Rhoonse grienden
Rhoon
Rotterdam Pendrecht
Zegenpolder
Portland - Carnisselande
Molenpolder
Portlandpolder
extensive recreation
intensive recreation
wet land
covering
piping network
New to develop
main route for slow traffic
main opening up with stop
green connection
Existing situation / autonomus development
Koedood
Essendijk
OudeMaas
Essendijk
0 250 500 750 1000 m
Carnisse grienden
41
Summary MER
S
um
mary
En
vir
on
men
tal
Eff
ect
Rep
ort
Figure S.10 Variant B for the north flank: Eendragts Polder location
Bleiswijk
Zevenhuizen
Eendragtspolder
Rottemeren
RotterdamNesselande
Hoge Bergse bos
Oosteindsche polder
Zevenhuizer plas
deRotte
layout concerning the connecting area
New to develop
0 250 500 750 1000 m
Figure S.9 Variant A for the north flank: Schiezone en Intermediary zone locations
INTERMEDIAIRE ZONE
SCHIEZONE
Airport Rotterdam
polder Schieveen
Zuidpolder
Schiebroekse polder
Rotterdam Schiebroek
Bergsche plassen
Ackerdijkse plassen
Delftsche S
chie
Oude Lee
Rotterdam Overschie
Oost-Abtspolder
Berkel en Rodenrijs
A13
layout concerning the connecting area
New to develop
0 250 500 750 1000 m
42
projects and the PMR alternatives. Zero Alternative
The Zero Alternative is the situation ex-
pected in 2020 without implementation of the
PMR projects. This is also referred to as ex-
pected autonomous developments. The Zero
Alternative assumes an unchanged policy or a
policy that has already resulted in a decision
process. The Zero Alternative serves as a frame
of reference for the effect description. The
effect of the sub projects will be determined by
comparing the situation with sub projects with
the situation without sub projects. The memo-
randum sections describe the Zero Alternative
by discussing the current situation and autono-
mous development.
The Friendliest Environmental Alternative
The Friendliest Environmental Alternative
(MMA) is the most environmentally friendly
combination of solutions. The MMA should
offer a reasonable and fully-fledged alternative
and not be regarded as impractical in advance.
According to the MER guidelines, the MMA in
Sub projectexisting
Rotterdam Area
set of project
activities
Sub projectland reclamation
referencedesigns
Sub project750 ha
wildlife and recreational area
location and
design variants
Zero Alternative
Friendliest Environmental Alternative (MMA)
Planned Package of Policy Decisions
Figure S.11 sub projects and alternatives of PMR
43
Summary MER
S
um
mary
En
vir
on
men
tal
Eff
ect
Rep
ort
PMR does not have to be developed as a new,
separate alternative, since the quality of the
living environment is used as the starting point
in formulating the sub projects. The MMA is
therefore defined as a combination of the fol-
lowing:
• the set of project activities of the existing
Rotterdam area sub project;
• the most environmentally friendly variant of
land reclamation;
• the most environmentally friendly location
and design variant for a 750-hectare wildlife
and recreational area.
For the Existing Rotterdam Area sub proj-
ect, the entire set of project activities is part
of the MMA. For the 750-hectare wildlife and
recreational area sub project, in retrospect
the friendliest variant was chosen, after the
environmental effect of the location and de-
sign variants were brought into focus. This is
variant I with sub variant ‘tides’. This variant
contributes considerably to improving the
quality and quantity of the natural environ-
ment.
The friendliest variant (MMV) in the land
reclamation sub project was developed in retro-
spect, after clarifying the environmental effect
of the reference designs. The mitigating meas-
ures applied to the reference designs are
geared towards retaining and developing some
natural resources. The MMV only assumed the
retention of natural resources. Table S.2 gives
an overview of the measures that could be
taken.
The Planned Package of Policy Decisions
Based in part on the described environmen-
tal effect of the three sub projects and the
MMA, the cabinet has included the Planned
Package of Policy Decisions in the PKB+ part 1.
The package contains the following:
• the ERA project programmes;
• the set of preconditions for realising the
land reclamation;
• the preferred variant for the 750-hectare
wildlife and recreational area.
The package of policy decisions for the
Existing Rotterdam Area project consists of the
Table S.2 Overview of measures in the most environmentally friendly variant of land reclamation
Measure restricting of:
the natural environment
most compact possible reclaimed land • effect on the marine environment area through
taking up space
located as far north as possible • effect on Voorne and Goeree dune vegetation
partial hard sea wall • effect on the morphology of the Haringvliet
Estuary and on the Voorne and Goeree dune vege-
tation
changed orientation southern coastline • effect on the morphology of the Haringvliet
Estuary and on the vegetation of the Voorne and
Goeree dune
landscape
zas northerly and as compact a location
as possible • visibility from the coats of Delfland, Voorne and
Goeree
44
entire set of projects for intensifying utilisation
of space and improving the quality of the living
environment. These projects are designed to
provide an impetus for resolving the space
shortage, for improving the quality of the natu-
ral environment, for offering quality wildlife
and recreational areas and spatial quality in the
region of Rotterdam.
For the land reclamation sub project, the
cabinet has not chosen a particular reference
design. With the PKB+, the cabinet would like
to make possible the construction of reclaimed
land and the sand extraction needed for this
purpose. In the PKB+ part 1, therefore, precon-
ditions were established in the areas of fitting
in with the environment, the environment, qual-
ity of life and the economy. The reference de-
signs and their effects have served as aids in
defining environmental preconditions. The ulti-
mate realisation must take place within these
preconditions. The package of policy decisions
included in the PKB+ part 1 for land reclama-
tion therefore concern the preconditions that
will apply to land reclamation and sand dredg-
ing when the time comes, and not to the speci-
fic location, arrangement and utilisation of the
reclaimed land.
The 750-hectare wildlife and recreational
sub project consists of a planned package of
policy decisions from a combination of variants
I and III (see Figures S.12 and S.13, respective-
ly). This involves 600 hectares at Central
IJsselmonde and two locations in the north
flank of Rotterdam – the Schiezone and the
South and Schiebroeks polders (intermediary
zone), of 150 hectares in total. The barrier
between the urban area and the 600 hectares at
Central IJsselmonde formed by the infrastruc-
ture bundle (A15 motorway and the Betuwe
Railway Line) will be removed wherever possi-
ble, by creating green interconnections for slow
and public traffic.
Figure S.13 Preferred variant, 750-hectare wildlife and recreational area (north flank)
45
Summary MER
S
um
mary
En
vir
on
men
tal
Eff
ect
Rep
ort
extensive recreationboundary concrete policy decision in PKB+ part1
0 250 500 750 1000 m
INTERMEDIAIRE ZONE
SCHIEZONE
Ackerdijkse plassenBerkel en Rodenrijs
Rotterdam Schiebroek
Bergsche plassen
Delftsche S
chie Rotterdam Overschie
Airport Rotterdam
Oost-Abtspolder
Oude Lee
polder Schieveen
Zuidpolder
Schiebroekse polder
A13
Figure S.12 Preferred variant, 750-hectare wildlife and recreational area (Central IJsselmonde)
wet nature with additional recreational usesboundary concrete policy decision in PKB+ part 1
intensive en extensive recreation
green connection
golfcourse Oude Maaswildlife and recreation are is leading, urban functions and functions related to wildlife and nature possible
piping network
Zegenpolder MolenpolderEssendijk
Portlandpolder
OudeMaas0 250 500 750 1000 m
Rotterdam Pendrecht
A 15
Koedood zone
Portland - Carnisselande
Carnisse griendenKlein Profijt
Rhoonse grienden
Essendijk
Rhoon
polderhet buitenland
van Rhoon
Koedood
The MER clarifies the environmental effect
of PMR. The effect was assessed and described
in comparison to the reference situation, or the
situation in 2020 without realisation of PMR. As
a gesture towards the various interested par-
ties, other cross-sections of the description of
the effect and assessment were given (Table
S.3).
Effect per Theme
Existing Rotterdam Area
The intensification projects in the Existing
Rotterdam Area sub project would result in bet-
ter utilisation of the scarce space in the port
(see page S.40, Table S.6). The implementation
of these projects should not cause an unaccept-
able increase of environmental effect in resi-
dential and recreational areas. The ERA sub
project therefore includes projects for im-
proving the quality of the living environment.
These projects are aimed at limiting any reduc-
tion in environmental quality in the Rotterdam
region. Over time, improvement will be feasi-
ble. The projects are especially designed to
reduce noise production and noise nuisance. In
addition, the ERA projects would contribute to
improved quality of wildlife and recreational
Effect
4646
Table S.3 Perspective of the environmental effect description
Cross-sections aim and effect per theme
aim and effect per theme • mapping out the negative and positive environmental effect
for relevant policy areas
(local effect) • offer insight in the consequences of PMR for the perception
and perspective of residents, tourists and other users of the
Rotterdam region
(effect on protected natural • provide insight as to how PMR satisfies national and European
environment) conservation areas, laws and regulations relating to nature
conservation; this deals with mitigation and compensation of
protected natural environment
(effect on quality) • indicate the contribution of PMR to the second part of the dou-
ble objective, improving the quality of the living environment,
resolving bottlenecks in the quality of life and contribute to
political environmental criteria
47
Summary MER
S
um
mary
En
vir
on
men
tal
Eff
ect
Rep
ort
47
areas in the residential surroundings and better
links between these areas..
Land Reclamation
The reference designs for land reclamation
are neutral with respect to the natural environ-
ment, recreation, traffic and transport themes
(see page 41, Table S.7). There are negative
effects for nature conservation. The negative
effects consist of a loss of protected surface
area, in particular open sea, shallow or deep
coastal zones, channels and mud flats. The
area loss would be mainly caused by the direct
space possession for reclaimed land (2,500 ha).
Land reclamation could also affect protected
species of nature such as sea strips and open,
dry dunes in the Voorne and Goeree dunes,
through a reduction in salt spray. Land recla-
mation would also result in the development of
new natural resources in the Haringvliet
Estuary (such as shallows and salt marshes).
The positive effects for nature development do
not balance the negative effects of existing
natural resources. For this reason, the nature
conservation theme was given a negative
assessment.
The reference designs differ in their effects
on the coast and sea theme. Reference design
II, with its own harbour entrance, is nautically
as safe as the current harbour entrance.
Reference design I, with access via a short-cut
in the existing Maasvlakte, could meet safety
norms with operational measures. This could
reduce the swiftness of dealing with nautical
traffic in the harbour. At present, it is being
studied as to whether acceptable nautical safe-
ty could be realised with reference design I, in
combination with an acceptable speed of
dealing with traffic. In both reference designs,
incidentally, there would be considerable in-
crease in coastal upkeep of the reclaimed land.
In addition, reference design II is expected to
require a substantial increase in maintenance
dredging work. The maintenance of dredging
work would decrease with reference design I.
Various effects among the reference designs
also occur with the landscape theme. Reference
design II, because of its own distinct harbour
entrance, creates a more appealing harbour
than does reference design I. The design is
therefore also more visible from the coast of
Delfland.
750-Hectare Wildlife and Recreational Area
The preferred variant of the 750-hectare
wildlife and recreational area sub project pro-
vides a high degree of cohesion and quality for
wildlife and recreation. Moreover, it retains the
option over time of opening the area to tidal
waters (see page 43, Table S.8). All the variants
considered scored high on the wildlife and
recreation themes. The main differences relate
to opening up or not opening up the area to
tidal waters and to the spatial distribution of
the 750 hectares. Opening up the area to tidal
waters would result in higher natural resources.
The location of the 750 hectares close to the
city, as is the case in variant I (750 hectares at
IJsselmonde) and variant II (600 hectares
situated to the north of IJsselmonde) would
result in greater cohesion and higher recrea-
tional quality.
The Friendliest Alternative (MMA)
The friendliest environmental variant for
land reclamation is geared towards conserva-
tion of existing natural resources. It could
result in limiting the degradation of natural
resources in the Voorne and Goeree dunes.
Contrarily, the opportunities afforded by the
reference designs for nature development in
the MMA would be less utilised (particularly
the development of tidal waters in the
Haringvliet Estuary).
48
The Effects from a Local Perspective
Environmental effect can also be viewed
from a local, regional or supra-regional per-
spective. The MER main report discusses three
such perspectives. This summary only presents
the most important conclusions on the effect,
as perceived by residents, tourists and others
who use the Rotterdam region.
Residents attach great importance to nearby
beaches, dunes and woods, the green quality of
the residential area and the quality of the air.
PMR would make a positive contribution to per-
ceptions of the area, especially with the imple-
mentation of the ERA projects and the con-
struction of a 750-hectare wildlife and
recreational area. Over time, the ERA projects
are intended to improve the general quality of
the living environment in the Rotterdam region.
Special attention will go to reducing noise pol-
lution. The ERA projects would not contribute
directly to any local improvement of air quality.
The ERA projects will increase the amount of
urban green and recreational areas. The 750-
hectare wildlife and recreational area sub proj-
ect will increase the number and quality of
recreational opportunities close to the urban
area. Use of reclaimed land could have a nega-
tive effect on the perception of residents be-
cause extra (rail) traffic to and from the reclaimed
land would cause extra noise nuisance.
Effects of Protected Natural Resources: mitiga-
tion and compensation
The Existing Rotterdam Area projects and
the preferred variant of the 750-hectare wildlife
and recreational area sub project would not
have any effect on protected natural resources.
The areas where these projects are planned do
not any protected status.
The reference designs of land reclamation
would affect protected natural areas, particular-
ly the North Sea, the Voordelta and the Voorne
and Goeree dunes. Together, these areas form
a major part of the so-called Ecological Main
Structure of the Netherlands. They are protect-
ed by the National Structure Scheme, Green
Areas. Parts of these areas belong to the
European Natura 2000 network. They are listed
as protected natural areas based on the interna-
tional EU Habitat Directive and to be designated
in procedure based on the international EU Bird
Directive. There are also specific
natural resources that enjoy international pro-
tection, such as the common seal, sea strips,
open, dry dunes and wet dune valleys.
Conservation of these areas and of specific
natural resources that occur means that any
‘significant’ negative effect of land reclamation
should be prevented, whever possible. If that is
not possible, then it should be limited as much
as possible (mitigated) through measures on
the reclaimed land itself. The significant effect
that remains after mitigation should be com-
pensated for. If such compensation should take
place with species of nature that would be lost,
it is assumed that there would also be compen-
sation for species of nature. The compensation
measures were only examined for any negative
effect on protected species of nature.
Land reclamation leads to the loss of an
area with five protected species of nature.
These are open sea, deep coastal zone, shallow
coastal zone (collectively called marine environ-
ment), sea strips and open, dry dunes. This
area loss would be caused particularly by the
space taken up by the reclaimed land and by
the possible effect on the Voorne and Goeree
dunes, due to a decrease in salt spray.
49
Summary MER
S
um
mary
En
vir
on
men
tal
Eff
ect
Rep
ort
Mitigation
Measures to limit the effect, mitigating
measures, are part of the reference designs for
land reclamation. The measures are especially
based on the conservation of existing natural
resources and, in addition, on enabling some
natural development in the Haringvliet Estuary.
This would involve the following mitigation
measures:
• a northerly location of the reclaimed land;
• a compact stretch of reclaimed land;
• a soft sea wall at the western and southern
side of the reclaimed land.
Compensation
The effect to be compensated for as a con-
sequence of land reclamation is approximately
the same for reference designs I and II (see
Table S.4). For mitigation and compensation
measures, therefore, no distinction is made
between the reference designs.
The MER contains a description of the na-
ture and scope of the compensatory measures
needed to meet the compensation obligation.
The package of mitigating and compensatory
measures will be established in PKB+ part 3.
There are various potential compensation
measures to meet the compensation require-
ment. The EU Habitat Directive and the EU Bird
Directive, as well as the Structure Scheme,
Green Areas, require the following, e.g.:
• compensation wherever possible for the
same natural resources (habitats and spe-
cies) that would be lost;
• compensation should take place in the vicin-
ity of the locations where the effect is
expected and/or ties in with the European
Natura 2000 network (conservation of the
integrity of the ecosystem).
If these principles were applied, then the fol-
lowing compensation measures would be the
most suitable:
• compensation of the marine environment:
creating a sea reserve for Haringvliet
Estuary;
• compensation of the dune environment:
developing a dune area at the ‘Kop van de
Brouwersdam’;
• compensation of the dune environment:
developing a dune area for the Delfland
coast.
The following are reserve options:
• reserve option, compensation of the dune
environment: developing the agricultural
area the Enden at Goeree into a dune area;
• reserve option, compensation of the dune
environment: developing a dune area at the
interior of the Delfland coast;
• reserve option, compensation of the marine
environment: opening up Lake Oostvoorne;
• reserve option, compensation of the dune
environment: a beach corner at Haringvliet
Estuary;
• reserve option, compensation of the dune
environment: Goeree East Dunes.
Tabel S.4 Effect to compensate by reference design I and II
Intervention/consequence maximum expected effect
of space in use • 2500 ha marine environment
salt spray reduction • 10 ha sea strips
• 16 ha open, dry dunes
50
Contribution of PMR to resolving bottlenecks
in the quality of the living environment in the
Rotterdam region
In the area of environmental quality (noise),
on the one hand the planned package of policy
decisions in the PKB+ would contribute via the
ERA projects. On the other hand, there would
be an increase in noise nuisance through the
growth of rail traffic (in particular) to and from
the reclaimed land. PMR would not make any
specific contribution to resolving bottlenecks in
the area of local air quality.
In the area of wildlife and recreation, the
planned package of policy decisions would
make a major contribution to the resolution of
existing bottlenecks. The planned package of
policy decisions would reduce the bottleneck of
insufficient quality and scale of wildlife areas
and interconnections among areas. This pack-
age would also make a major contribution
towards resolving the bottleneck of insufficient,
easily accessible recreational areas. Finally, the
planned package of policy decisions would
improve the local business establishment cli-
mate.
PMR contribution to political criteria
Table S.5 shows the degree to which PMR
would contribute to political consideration crite-
ria. Only those criteria were examined that
were relevant to the quality of the living envi-
ronment.
Recreation on the Maasoever
51
Summary MER
S
um
mary
En
vir
on
men
tal
Eff
ect
Rep
ort
Political criteria PMR contribution
Table S.5 PMR contribution to political criteria read further ->
criterion 2:
Improving accessibility,
measuring opportunities for a
shift in type of goods transport in
favour of pipelines, rail or inland
shipping (modal shift)
criterion 3:
Degree of intensive and
economical space utilisation
criterion 5:
Improving the total environmental
quality of the residential and
living environment, in which the
emphasis is on dust, stench,
emissions and noise nuisance
criterion 6:
Degree of innovative and
economical use of raw materials
and energy
• the effect of land reclamation on accessibility by road, rail and inland navi-
gation is limited
• attention is necessary to realise swift accessibility to reclaimed land wit-
hout its own harbour entrance for sea-going vessels (reference design I)
with an adequate level of nautical safety
• a modal shift in the direction of more road traffic would take place as a
result of the establishment of container and distribution companies on
reclaimed land
• land reclamation affords opportunities for a shift to using environmentally-
friendly transport methods (container transport)
• ERA intensification projects would contribute to a more intensive, frugal use
of space
• phased construction of reclaimed land would contribute to frugal use of
space; each phase could be the final one
• compact design of reclaimed land would contribute to frugal use of space
• land reclamation would make a ‘shift process’ possible in the long term for
new urban developments in the existing Rotterdam port area
• ERA projects aim to contribute in the longer term to improving environmen-
tal quality, particularly for noise nuisance and reduction of CO2 emissions.
Limiting other aspects such as stench and dust are not part of ERA
• land reclamation would provide a modest contribution to the total environ-
mental quality of the residential and living environment
• land reclamation would result in an increase in noise pollution, especially
as a consequence of (rail) traffic
• land reclamation would result in an increase in CO2 emissions
• by offering space to remove environmentally hazardous companies away
from the existing port area, land reclamation could contribute to an impro-
vement in the quality of the living environment
• in the longer term, the ERA project ‘Industrial Ecology’ could contribute to a
reduction in emissions and less consumption of raw materials and energy
• new industrial activities on reclaimed land would result in an increase of
total energy consumption in the region
• the arrangement of reclaimed land would afford opportunities for sustaina-
ble industrial sites in which clustering of companies could contribute to
innovative, economical use of raw materials and energy
52
criterion 7:
Developing the quality and
accessibility of regional
recreational potential
criterion 8:
Degree of damage to the natural
and landscape resources or
conservation and development of
scale and quality of the natural
environment
criterion 9:
Degree in which safety (flood
protection), water quality,
resilience and natural processes
of the water systems are affected
criterion 13:
Degree of flexibility in scale, lay-
out and use of solutions
• the ERA projects ‘realising river parks, ‘greenery arrangement on the
Rozenburg Peninsula’ ‘realising ferry connections’ are designed to increase
recreational potential in the surrounding residential area
• because of land reclamation, the current Slufters Beach would disappear,
to be replaced by a new stretch of beach further away
• the 750-hectare wildlife and recreational area would bring large-scale
recreational facilities closer to the city
• the ERA projects ‘realising river parks’ and ‘greenery arrangement of the
Rozenburg Peninsula’ would improve the quantity and quality of green
areas in the surrounding residential area
• land reclamation would have a negative effect on protected natural areas,
particularly by taking up space and reducing salt spray
• land reclamation would result in new natural resources in the Haringvliet
Estuary
• land reclamation would result in a reduction of open landscape from the coast
• the 750-hectare wildlife and recreational area would bring about a high
degree of cohesion and quality for wildlife and recreation and, moreover,
would keep open the option of introducing the effect of tidal waters in the
area in the long term
• coastal safety and sea walls would not change because of the construction
of reclaimed land and sand extraction
• with the 750-hectare wildlife and recreational area, tidal variants would
result in strengthening the natural process in the water system
• tidal variants mean that the presence of secondary dams as additional
protection would disappear; the risks of flooding would meet legally
established standards
• the ERA package represents a flexible package of specific arrangement
measures to policy intentions, which could be introduced in phases
• land reclamation could be introduced in phases and is expandable;
construction of an own harbour entrance for the reclaimed land could be
realised at various points in time
• opportunities for phasing the 750-hectare wildlife and recreational area
would depend on the instruments available
• land reclamation is extremely flexible in terms of layout and use
Political criteria PMR contribution
Table S.5 PMR contribution to political criteria (sequel)
53
Summary MER
S
um
mary
En
vir
on
men
tal
Eff
ect
Rep
ort
S
um
mary
En
vir
on
men
tal
Eff
ect
Rep
ort
55
Overview of the effect in Tables
5656
Table S.6 Overview of intended effects of the ERA projects on environmental quality (MK), wildlife and
recreation (NR) and spatial quality (RK)
ERA-projects environ. aspects intended effects
MK NR RK
intensification projects
filling the 4th Petroleum Harbour ■ sustainable use of available space
and Hartel Canal West
efficient utilisation of tank storage ■ sustainable use of available space
4th, 5th, 7th Petroleum Harbour
increased productivity ■ sustainable use of available space
container sector
accentuated land-issue policy ■ sustainable use of available space
measures for ■ sustainable use of available space through
soil decontamination accelerated availability of economic
soil decontamination locations
future vision, Waalhaven ■ ■ sustainable use and improvement of environmental
East quality in the existing residential area around
Waalhaven East
Quality of life projects
Targeted area approach ■ improving environmental quality in all districts
around the port
knowledge centre noise ■ reducing noise produced by
industry and transport
reduction of traffic noise ■ reducing local noise nuisance produced by the
Caland Railway Bridge in Rozenburg and along other
infrastructure
industrial ecology ■ reducing noise pollution, reducing emissions
of C02 and N0x, and reducing thermal
discharges
wildlife and recreation on the ■ more and better quality natural environment
Rozenburg Peninsula and recreation for residential areas, better
interconnections between natural areas
research into opening ■ improving the quality of life at West Voorne
Lake Oostvoorne with new wildlife and recreational opportunities
realisation of river parks ■ more and better quality natural environment
and recreation for residential areas; better
interconnections between natural areas
research into potential ■ improving accessibility of recreational areas and
ferry conenctions the living environment in the Hoek van Holland,
reinforcing coastal route for cyclists and hikers
S
um
mary
En
vir
on
men
tal
Eff
ect
Rep
ort
57
Summary MER
57Table S.7 Overview, Assessment of Land Reclamation Effect
Theme/aspects reference design I reference design II
-
0
0 (-)*
- - (0)*
+
-
-
0
-
0
0
+
+
-
0
0
0
0
0
0
-
0
0
0
0
0
-
+
-
0
0
+
+
+
-
0
0
0
-
-
-
0
-
0
0
+
+
-
0
0
0
0
0
0
-
0
0
0
0
0
-
+
0
++
+
+
+
+
* These scores depend on the outcome of current research into nautical safety and the swiftness of handling traffic
coast and sea
retention of coastline
coastal safety
nautical accessibility of port area and channel
nautical safety
maintenance dredging work
total
natural environment
national and international diversity of ecosystems
national and international diversity of species
Total
recreation
beach recreation
water sports
active outdoor sports
port-related recreation
accessibility
total
traffic and transport
accessibility by road
accessibility by rail
accessibility by inland navigation
modal shift
total
environmental quality
noise
air quality
stench
water quality
external safety
total
landscape
experience with openness along the coast
experience with variation in spatial dimensions
structure and cohesion
identity and image
total
spatial quality
future value
use value
total
5858
Table S.8 Summary of the assessment of the effect of 750-hectare wildlife and recreational area sub project
north situated of south situated of
IJsselmonde IJsselmonde
concentrated impetus shared impetus
theme / aspects I≈ I≠ IIa≈ IIa≠ IIb≈ IIb≠ IIIa≈ IIIa≠ IIIb≈ IIIb≠
natural enviroment
(inter)national variety of ecosystems ++ ++ ++ ++ ++ ++ ++ ++ ++ ++(inter)national diversity of species ++ ++ ++ + ++ + ++ + ++ +ecosystem, natural cohesion + + + + + + + + + +potential of the area + 0 + 0 ++ + + 0 ++ +effect on existing natural resources + + - - 0 0 - - 0 0total ++ + + 0 + + + 0 + +landscape, archaeology,
cultural history and geology
geology + 0 + 0 + - + 0 + -cultural history and archaeology - - - - - - - - - -landscape identity and image ++ 0 + 0 + 0 + 0 + 0landscape diversity 0 0 + + + + + + + +landscape cohesion / structure + + + + + + + + + +total 0 0 0 0 0 0 0 0 0 0recreation
cohesion ++ ++ ++ ++ ++ ++ + + + +recreational quality ++ ++ ++ ++ ++ ++ ++ ++ + +accessibility + + ++ ++ + + + ++ + +effect on existing facilities ++ + ++ ++ ++ ++ ++ ++ ++ ++total + + ++ ++ + + + + + +soil and water
renewable water management ++ ++ ++ ++ ++ ++ ++ ++ ++ ++soil - 0 - 0 - 0 - 0 - 0soil and surface water 0 + - 0 0 0 - 0 0 0total + + 0 + 0 + 0 + 0 +environmental quality
noise 0 0 0 0 0 0 - - - -external safety 0 0 0 0 0 0 0 0 0 0air 0 0 0 0 0 0 0 0 0 0total 0 0 0 0 0 0 - - - -coast and sea
safety from flooding - 0 - 0 - 0 - 0 - 0total - 0 - 0 - 0 - 0 - 0spatial quality
future value ++ ++ 0 + + + - 0 0 0use value - 0 - - -- - - - -- --total 0 + 0 0 - 0 - - - -trafic and transport
accessibility -- -- - - - - - - - -traffic safety - - - - - - - - - -total - - - - - - - - - -
≈ with tidal waters ≠ without tidal waters a Schiezone and Intermediary zone b Eendragtspolder
S
um
mary
En
vir
on
men
tal
Eff
ect
Rep
ort
5959
6060