suggestion schemes (contd…) prepared by: bhakti joshi date: february 21, 2013
TRANSCRIPT
Suggestion Schemes (contd…)
Prepared by: Bhakti JoshiDate: February 21, 2013
Total Productivity Maintenance: Brief Case Study
Hindalco manufactures aluminium products in its Renukoot plant in Uttar Pradesh. The plant has significant downtime. A team of workers identified three main reasons for equipment downtime.-Excessive time required for replacement of gaskets in an equipment-Failure of valve resulting in 12 oil-seal replacements in a year-Inappropriate insulationThe team realised the problems and eliminated them thus leading to the following:1.After eliminating the need for replacing 1,152 gaskets, 3,744 hours of productive machine time was reclaimed2.Eliminating oil-seal replacements led to reclaiming 1,536 hours3.Developing better insulation at a cost Rs. 1,780 per year, fuel savings worth Rs 4,150 were made and painting cost worth Rs 1,500 per equipment was also avoidedOverall, equipment downtime was cut by 87.16% and an annual savings of Rs. 123,000 was also achieved. The entire process was done by an empowered work force, which also perceived job enrichment
TPM stands for…
• Maintenance and production individuals working together (Total)
• Production of goods/services that meet or exceed customers’ expectations (Productive)
• Keeping equipment and plant in good or better condition than original condition at all time (Maintenance)
Goals of TPM
• Equipment capacities maintained and improved always
• Aiming towards maintaining equipment for life
• Using support from all areas of operation• Encouraging input from all employees• Using teams for continuous improvement
TPM concept: Overall Equipment Effectiveness (OEE)
OEE = Availability (A) X Performance (E) X Quality (R)
A = (T/P) x 100
A= AvailabilityT = Operating time (P-D)P = Planned operating timeD = Downtime
E = C x N x 100
E= PerformanceC = Theoretical cycle timeN = Processed amount (quantity)
T( ) R = N - Q x 100
R= Rate of QualityQ = Non-conformitiesN = Processed amount (quantity)
N( )
Example 1Week 1’s production numbers on machining center JL58 were as follows:•Scheduled operation = 10 hours/day; 5 days/week•Manufacturing downtime due to meetings, material outages, training, breaks and so forth = 410 minutes/week•Manufacturing downtime scheduled and equipment breakdown = 227 minutes/week•Theoretical (standard) cycle time = 0.5 minutes/unit•Production for the week = 4450 units•Defective parts made = 15 units
Example 1 (contd…)P = 10 hours/day X 5 days/week X 60 minutes / hour = D = 410 minutes/week + 227 minutes/week = T = (P-D) = C = N = Q = Availability = Performance = Quality = Therefore OEE =
3000 minutes / week 637 minutes /
week2363 minutes / week
0.5 minutes / unit4450 units15 units
78.8%94.2%99.7%
0.740 or 74%
Example 1 (contd…)Week 2’s production numbers on machining center JL58 were as follows:•Scheduled operation = 8 hours/day; 5 days/week•Manufacturing downtime due to meetings, material outages, training, breaks and so forth = 309 minutes/week•Manufacturing downtime scheduled and equipment breakdown = 200 minutes/week•Theoretical (standard) cycle time = 0.5 minutes/unit•Production for the week = 4550 units•Defective parts made = 10 units
Example 1 (contd…)P = 8 hours/day X 5 days/week X 60 minutes / hour = D = 309 minutes/week + 200 minutes/week = T = (P-D) = C = N = Q = Availability = Performance = Quality = Therefore OEE =
2400 minutes / week 509 minutes /
week1891 minutes / week
0.5 minutes / unit4550 units10 units
0.7879 or 78.79%1.203 or 120.3%
0.9978 or 99.78%0.787 * 1.203* 0.997=0.945 or 94.5%
Email: [email protected]: www.headscratchingnotes.net