Page 1: SUEZ’s Water Technologies & Solutions for the Upstream Oil

SUEZ’s Water Technologies& Solutions

for the UpstreamOil & Gas industry

Page 2: SUEZ’s Water Technologies & Solutions for the Upstream Oil

full-service provider delivering across the value chain

2 I SUEZ Water Technologies & Solutions

Specialty

chemicals

and expert

services

Engineering,

procurement,

construction

Equipment

and systems

Water

services

(BOO, O&M,

mobile water)

Lifecycle

services

Data intelligence

for asset

performance

Water quality

monitoring

technologies delivery modelssolutions & services

Page 3: SUEZ’s Water Technologies & Solutions for the Upstream Oil

10 Years of Oman Experience

Page 4: SUEZ’s Water Technologies & Solutions for the Upstream Oil

End User: PDO Musallim

Project: ILS Replacement

Delivery 2016

Plant Details:

Combination of Deoiler & Desander Hydrocyclones

Capacity: 126,000BWPD

Inlet Oil: 500ppmv

Inlet TSS: 242mg/l

Outlet Oil: 30ppmv norm / 50ppmv max

Outlet TSS: 10mg/l max

Sand Handling package included

Water Treatment

Page 5: SUEZ’s Water Technologies & Solutions for the Upstream Oil

End User: PDO Musallim

Project: Q0113-00

Delivery 2015

Plant Details:

Combination of Deoiler & Desander Hydrocyclones

Capacity: 132,000BWPD

Inlet Oil: 500ppmv

Inlet TSS: 242mg/l

Outlet Oil: 30ppmv norm / 50ppmv max

Outlet TSS: 10mg/l max

Sand Handling package included

Water Treatment

Page 6: SUEZ’s Water Technologies & Solutions for the Upstream Oil

End User: PDO Musallim

Project: Full Facilities Ph I & II

Delivery 2007 & 2008

Plant Details:

Combination of Deoiler & Desander Hydrocyclones

Capacity: 125,800 BPD

Inlet Oil: 500ppmv

Inlet TSS: 242mg/l

Outlet Oil: 30ppmv norm / 50ppmv max

Outlet TSS: 10mg/l max

Sand Handling package included

Water Treatment

Page 7: SUEZ’s Water Technologies & Solutions for the Upstream Oil

Water Treatment

End User: Occidental of Oman

Project: Mukhaizna

Delivery 2008

Project: Wadi Latham

Delivery 2006

End User: Daleel Petroleum

Project Arabian Field

Delivery 2016

Desander & Deoiler Hydrocyclone + IGF - 50,000 BWPD

Inlet Oil Content: 5,000 ppm

Inlet Solid Content: 1,000 ppm

Outlet Oil Content: < 50 ppm

2x IGF trains – each 189,000 BWPD

Inlet Oil Content: 200 ppmv

Outlet Oil Content: < 20 ppmv

2 x IGF, NSF trains – each 50,000BWPD

Outlet Oil Content: 40 ppm(v)

Outlet Solids Content: <1.6 mg/L TSS

Page 8: SUEZ’s Water Technologies & Solutions for the Upstream Oil

End User

Project Qarn Alam

Delivery 2010

Plant Details:

2 x Corrugated Plate Interceptor Tanks

4 x Induced Gas Flotation Vessels

Capacity: 480,230 BWPD

Inlet Oil Concentration: 4,000 ppm

Outlet Oil Concentration: < 20 ppm

Inlet Operating Pressure: 3 kPag

Water Treatment

Page 9: SUEZ’s Water Technologies & Solutions for the Upstream Oil

SUEZ is ready to workby your side

www.suez.com [email protected]

Page 10: SUEZ’s Water Technologies & Solutions for the Upstream Oil

CPI Performance at PDO

Page 11: SUEZ’s Water Technologies & Solutions for the Upstream Oil

Background ► Petroleum Development Oman (PDO) is the leading exploration and

production company in the Sultanate of Oman

► PDO deliver the majority of the country's crude oil production and

natural gas supply, but above all we focus on delivering excellence,

growth and sustainable value creation within and well beyond our

industry

► PDO produce 70% of the country's crude oil production and nearly all

of its natural gas supply

► Production of produced water is increasing along with oil production

• Current ratio is 9 bbl Produced Water (PW) / bbl Oil

• Oil API varies from light to heavy

► PDO has different configurations of PW treatments to meet

specifications for WI/DWD/other re-uses

► One of the PW configuration is CPI+IGF installed at QASP; where Oil

Viscosity is API 16

Qarn Alam

Page 12: SUEZ’s Water Technologies & Solutions for the Upstream Oil

PDO has considered CPIs for primary treatment at few location

(e.g. Qarn Alam, Nimr )

Key Features of CPI in QASP:

► Heavy oil removal from produced water

► Coalescing pack to enhance oil separation

► Better separation and remove oil droplets above 75 microns

► Low pressure application

► Gravity flow, thus avoid additional pumping which can cause shearing of oil droplets

► Avoid requirement for surge tank at upstream

► Low maintenance

CPI Requirement in PDO

Page 13: SUEZ’s Water Technologies & Solutions for the Upstream Oil

Design envelope of CPIs at Qarn Alam:

Parameters Design

Configuration 2 x 50% CPIs

CPI inlet 4000 ppmv

CPI outlet 200 ppmv

Total design flow rate 76,800 m3/d

(38,400 m3/d per CPI)

Design temperature 90oC

Current operation Temp. 50oC

Operating pressure 0.02 – 0.03 barg

CPI -1 / 2 IGF -1 /2 / 3 / 4

Qarn Alam

Gross

Separation

Primary Treatment Secondary Treatment

To Disposal

Injection System

CPIs supplied by SUEZ

• Flow mechanism is by gravity from

separators to IGF

• CPIs has coalescer packs to

facilitate separation

CPI is selected as primary treatment

option for QASP PW treatment

CPIIGF

CPIs at Qarn Alam

Page 14: SUEZ’s Water Technologies & Solutions for the Upstream Oil

• CPI performance is being monitored since CPI its operating

phase (year 2012)

• No performance deterioration even at OIW peaks at CPI inlet

• Superior OIW separation efficiency even at current low operating

fluid temperature

• Low inflow also a contributor for improved performance

0

1000

2000

3000

4000

5000

6000

7000

8000

OIW

(p

pm

v)

Date

Corrugated Plate Interceptors (T-2740)

CPI Inlet CPI Outlet Average CPI Inlet Average CPI Outlet

180

2516

2012 2013

Design Inlet 4000 ppmv

75

215

1034

149

1635

2014 2015

6407

208 183

Q 1 - Q2 2016

0

5,000

10,000

15,000

20,000

25,000

30,000

35,000

40,000

m3/

d

Date

Produced Water Flow Rate Per CPI

Produced Water Production Average Produced Water Production

2012 2013

20,834

24,793

Q1 - Q2 2016

23,785

2014 2015

21,47722,293

Operating flow 55% - 65% of design / CPI

PDO has seen a satisfactory performance record in meeting Oil in Water (OIW) at CPI

outlet within the design envelope

CPIs Performance at QASP

Consistently meeting design

envelope with immense

fluctuations of inlet OIW

Page 15: SUEZ’s Water Technologies & Solutions for the Upstream Oil

Thank You

15

Page 16: SUEZ’s Water Technologies & Solutions for the Upstream Oil

Meet the experts 16 I

Q A