Coal Connectivity Projects : Perspective & Issues SUDHENDU J. SINHA DIRECTOR PLANNING, RAILWAY BOARD Date :21.11.2013

Upload: shavonne-shaw

Post on 17-Dec-2015

226 views

Category:

Documents


6 download

TRANSCRIPT

Page 1: SUDHENDU J. SINHA DIRECTOR PLANNING, RAILWAY BOARD Date :21.11.2013

Coal Connectivity Projects : Perspective & Issues

SUDHENDU J. SINHADIRECTOR PLANNING,RAILWAY BOARD Date :21.11.2013

Page 2: SUDHENDU J. SINHA DIRECTOR PLANNING, RAILWAY BOARD Date :21.11.2013

Importance

Critical for evacuation & transportation of 615 MT of Coal production target by 2016-17.

MCL - incremental production significant for AP, TN and Karnataka.

Ch projects important for Rajasthan, Maharashtra and Gujarat.

Page 3: SUDHENDU J. SINHA DIRECTOR PLANNING, RAILWAY BOARD Date :21.11.2013

Imp …

• Substantially increase coal availability.• Improve Power Scenario.• Enhance Freight Rev. of Rlys. • Enhance incremental rev. of

Jharkhand.

Page 4: SUDHENDU J. SINHA DIRECTOR PLANNING, RAILWAY BOARD Date :21.11.2013

COAL CONNECTS

No. Of Project : 31 [Jointly identified by Min. of Rly., Power & Coal] CRITICAL : 5

MAJOR : 9

MINOR : 17

Page 5: SUDHENDU J. SINHA DIRECTOR PLANNING, RAILWAY BOARD Date :21.11.2013

SWEEPRAILWAY WISE: SUBSIDIARY WISE:ECR- 18 CCL- 12 SECR- 06 NCL- 07ECOR- 03 SECL- 05ER- 01 MCL- 05SER- 01 BCCL- 01SER+ ECR- 01 SCCL - 01SCR- 01

Page 6: SUDHENDU J. SINHA DIRECTOR PLANNING, RAILWAY BOARD Date :21.11.2013

SN

Name of Project Coal Field Coal Subsi. Co.

State

1 Tori-Shivpur -Kathautia

North Karanpura

CCL JH.

2 Shivpur -Kathautia North Karanpura

CCL JH.

3 Jharsuguda-Sardega IB Valley MCL Odisha

4 Bhupdeopur-Korichappar-Baroud

Mand-Raigarh

SECL CH.

5. Diversion of fire affected area.

JHARIA BCCL Jh . WB

CRITICAL COAL CONNECTS

Page 7: SUDHENDU J. SINHA DIRECTOR PLANNING, RAILWAY BOARD Date :21.11.2013

TORI- SHIVPUR- KATHAUTIA

Page 8: SUDHENDU J. SINHA DIRECTOR PLANNING, RAILWAY BOARD Date :21.11.2013
Page 9: SUDHENDU J. SINHA DIRECTOR PLANNING, RAILWAY BOARD Date :21.11.2013

1. Tori-Shivpur New Line (CCL)

Milestone :•Stage I - Conditional clearance. [29.4.11/ 1.8.12]•Stage II - Clearance on 19.6.13.•Work from Tori end.•TDC: June 2016. [ CCI Target for Mar /2015]

• 43 Km. 1094 Cr. 60MT out of total 140 MT.

• Deposit work of CCL CAO/CON/ECR

Page 10: SUDHENDU J. SINHA DIRECTOR PLANNING, RAILWAY BOARD Date :21.11.2013

Assistance Required

• Complete possession of required 375 ha of land is made available by Jh by 30.10.13. At present, 99 ha of Govt. and Raiyati (Pvt.) land are not available at 131 locations/stretches in the entire span of 44 km.

• Tree Felling and Clearance by 30.10.13.• Adequate security for men and machines deployed. • Deputation of LA & Forest officials to resolve issues.• Beef up Security at vulnerable loctions. • Ensuring inter-district coord. (Chatra, Latehar,

Hazaribagh)

Page 11: SUDHENDU J. SINHA DIRECTOR PLANNING, RAILWAY BOARD Date :21.11.2013

2 Shivpur-Kathautia (Part of Tori-Kathautia Revised Alignment)

Milestone :

• Early identification of forest : to enable Rlys to file Stage-I.

• Land Acquisition.• Handing Over Possession.• Final Forestry Clearance.

• Shivpur-Hazaribag was not agreed by MoEF hence changed to Shivpur-Kathautia

•47.70 Km 1250 Cr. CCL CAO/CON/ECR.

Page 12: SUDHENDU J. SINHA DIRECTOR PLANNING, RAILWAY BOARD Date :21.11.2013

3. Jharsuguda-Barpalli-Sardega

• 52.41 Km. IB Valley Odisha 555 Cr. MCL CAO/CON/SER .

• Takes off from Jharsuguda-FCI-Shunting neck & terminates at buffer end at Sardega. Includes Dhutra connection.

•Passes through Jharsuguda & Sundergarh districts, 24 vill., 2 Tehsils- Jharsuguda & Hemgir & 2 Forest Div. -Sambalpur & Sundergarh.

•To evacuate and transport 60 MT of coal from Gopalpur-Manoharpur Blocks in IB valley of MCL.

Page 13: SUDHENDU J. SINHA DIRECTOR PLANNING, RAILWAY BOARD Date :21.11.2013

•Jharsuguda-Barpalli-Sardega …•Includes : Con. of Main Sdg. b/n FCI Shtg. Neck &

Sardega. : Loading Bulb at Barpali. : Rail Flyover at Jharsuguda.

•Target : Dec.’14.

• 29.8.2013 : After hectic persuasion by the Railways, Stage- I forest clearance has been forwarded by the State Govt. to MoEF and the clearance is likely to be obtained shortly.

Page 14: SUDHENDU J. SINHA DIRECTOR PLANNING, RAILWAY BOARD Date :21.11.2013

• 27.2.2012 : MOU with CH.• 3 corridors : East. North. East-West Corridor. • Bhupdeopur- Korichhapar/Baroud [Mand- Raigarh]- Part

East Corridor.• Execution : SPV route with CH. CIL. IRCON. Bhupdeopur-

korichappar-Korba & Gevra road –Pendra road projects  .

• NL b/n Bhupdeopur-Korichapar will be extended to Korba via Dharmjaigarh - 63 km project costing 344 Cr. • Gevra Road to Pendra Road (East-West Corridor), 122 km .“In

Principle” approval from Plg Comm. • March 13: 2 JVs formed. Land acquisiton is in process. • TDC : 2yrs for Ph I & 3 Yrs. For complete.

4. Bhupdeopur-Korichappar-Baroud

Page 15: SUDHENDU J. SINHA DIRECTOR PLANNING, RAILWAY BOARD Date :21.11.2013

1. PROPOSED RAIL CORRIDORS IN NORTHERN REGION OF CHHATTISGARH

2. SURVEYS IN PROGRESS

Page 16: SUDHENDU J. SINHA DIRECTOR PLANNING, RAILWAY BOARD Date :21.11.2013

1. PROPOSED RAIL CORRIDORS IN NORTHERN REGION OF CHHATTISGARH

2. SURVEYS IN PROGRESS

Page 17: SUDHENDU J. SINHA DIRECTOR PLANNING, RAILWAY BOARD Date :21.11.2013

1. PROPOSED RAIL CORRIDORS IN NORTHERN REGION OF CHHATTISGARH

2. SURVEYS IN PROGRESS

East

Page 18: SUDHENDU J. SINHA DIRECTOR PLANNING, RAILWAY BOARD Date :21.11.2013

Diversion of Fire Affected Railway Lines in Jharia area of BCCL

133 Track km. 172 trains I/C 46 Pass. DHN & ADRA

Page 19: SUDHENDU J. SINHA DIRECTOR PLANNING, RAILWAY BOARD Date :21.11.2013
Page 20: SUDHENDU J. SINHA DIRECTOR PLANNING, RAILWAY BOARD Date :21.11.2013

MAJOR COAL CONNECTIVITY PROJECTS

Page 21: SUDHENDU J. SINHA DIRECTOR PLANNING, RAILWAY BOARD Date :21.11.2013

1. Piparwar Railway Siding [CCL]

• 30 Km. 90.60 Cr. CCL RITES 25 MT

Roadblocks :Severe Law & Order problem

TDC- Dec.’13 for Ph I & Jun’14 for Ph II

Page 22: SUDHENDU J. SINHA DIRECTOR PLANNING, RAILWAY BOARD Date :21.11.2013

Facts : • 12.5 Km 129Cr CCL 12-15 MT CAO/C/ECR.

• take off from 11th km of Piparwar.

Milestone :• Transferred to RVNL.

. Target : June 2015

2. Ashoka Siding Project [CCL]

Page 23: SUDHENDU J. SINHA DIRECTOR PLANNING, RAILWAY BOARD Date :21.11.2013

3. Shivpur-Chatti Bariatu & Hazaribagh-Banadag Sdgs.

Facts : • Shivpur-Chatti Bariatu (14 km) & Hazaribagh-

Banadag (9 km)• ECR. NTPC CAO/CON/ECR• Survey by RITES

Milestone :Shivpur-Chatti-Bariatu : DPR submitted to

NTPC.

Banadag project : Likely to be opened for Goods Traffic.

Page 24: SUDHENDU J. SINHA DIRECTOR PLANNING, RAILWAY BOARD Date :21.11.2013

4. Koderma-Hazaribagh-Barkakhana-Ranchi -NL

Milestone :• TDC for Koderma-Hazaribagh : Oct.’13

Hazaribagh-Barkakhana (57 km) : Sept.’14 Barkakhana-Ranchi (65 km): Dec.’15

Facts : • 189 km. 2957.21 Cr. JH share - 66% CAO/CON/ECR. • Important for evacuation of coal from Hazaribagh-Banadag siding.

Page 25: SUDHENDU J. SINHA DIRECTOR PLANNING, RAILWAY BOARD Date :21.11.2013

5. Koderma – Tilaiya New Line

Milestone :• Stage-II forest clearance from BH –Pending. • fly over at Manpur - To avoiding reversal. NTPC to give consent.• Land acquisition Issues. 70% civil work in non forest area is complete.

• TDC : 2014-15 – Stage-I -non forest land (40km) : 2018-19 – Stage-II in forest land (25km)

Fact : • 64 Km. Line [34 km under forest area of Bh & Jh] 418 Cr.

CAO/CON/ECR• Critical for : BARH Thermal Power Plant of NTPC [Operational -Feb’ 14].

• Involves construction of 5 long tunnels 6 via ducts bridges.

Page 26: SUDHENDU J. SINHA DIRECTOR PLANNING, RAILWAY BOARD Date :21.11.2013

6. Angul- Talcher Bulb Line

• Doubling of feeder lines• Auto signalling

Page 27: SUDHENDU J. SINHA DIRECTOR PLANNING, RAILWAY BOARD Date :21.11.2013

Rail Corridor connecting Angul-Talcher Line

7.

Facts : • 85 Km. 5200 Cr RITES Odisha (IDCO). • Corridor involves laying of Railway lines & roads.

Milestone :• Feasibility report submitted. State Govt. has requested to implement

through PPP route.

•CMPDIL has suggested change in alignment that needs to be firmed up.

• PPP Policy in place.10/12/12.•5 Models: Non Govt Pvt. Line JV BOT Cap Augmentation : Fundng by customers : Annuity Alternative: Feeder route Doubling and auto Signalling.

Page 28: SUDHENDU J. SINHA DIRECTOR PLANNING, RAILWAY BOARD Date :21.11.2013

8. Bhadrachalam-Sattupalli NL

Milestone :

• Rs.6 cr. provided by SCCL to SCR for conducting FLS etc. by SCCL.• Sept. 2013- Working Plan of Construction to be

submitted.• Nov 13. – Terminal Arrangement for Sattupalli to be

finalised by SCCL.

Facts : • 56.25 Km 337.50 Cr SCCL CAO/CON/SCR.

Page 29: SUDHENDU J. SINHA DIRECTOR PLANNING, RAILWAY BOARD Date :21.11.2013

9. Vasundhara : Addl. Link

Odisha Govt.+ MCL+ SECR+ Rampia Co. ‘Common Corridor Concept’

Page 30: SUDHENDU J. SINHA DIRECTOR PLANNING, RAILWAY BOARD Date :21.11.2013

Balance Coal Connectivity ProjectsS.No. Name of Project

Executing Agency

Coal SubsiProjects

Status

1.Renovation of Chainpur-Sarubera DHN CCL TDC Sept. 2013.

2Completion of balance work of Dhori siding of CCL.

ECR CCL Work completed

3 Improvement of Dudhi Chua siding. DHN NCL TDC July 2013Raising of speed from SKTN to DCH

4 Modification of Dudhi Chua Yard for 2nd Silo

DHN NCL TDC Sept.2013. 10 addl. rakes

5 New Railway Siding for Block B project

RITES NCL Feasibility report submitted by RITES to NCL.

6 Complete track renewal at Shaktinagar to Jayant Silo of NCL including improvement to Jayant and Spur siding

RITES NCL Estimate submitted by RITES.

7 Balance work of KBJ railway line between Krishnashila and Shaktinagar Railway station

RITES NCL NCL to submit full estimate value.

8 PRL system Amlohri and Nigahi RITES NCL DPR is under process by RITES

Page 31: SUDHENDU J. SINHA DIRECTOR PLANNING, RAILWAY BOARD Date :21.11.2013

S.No. Name of Project Executing Agency Coal SubsiProjects Status

9 Krishanshila Railway siding RITES NCL DPR is under process by RITES

10 Railway Sdg at Lakhanpur Coalfields of Bishrampur Area

RITES have done initial survey and feasibility study

SECL SECL has to give the DPR for taking the

project further

11 New Rly Siding at Kusmunda area SECR SECL Nov’ 13 TDC DPR

12 Construction of New sdg. parallel to old sdg. at Bhatgaon area

SECR SECL DPR under approval

13 Magadh and Amarpalli Rly. Siding CCL March 2013 - Feasibility report of Amarpalli submittedApril 2013 – Feasibility report of Magadh submitted.

14 Renovation of CP siding of Giridih of MNK area

ASN CCL TDC Dec 2013.

15 Renovation of Swang & Jarandih siding

DHN CCL Estimate under preparation.

16 Temporary connect of Lingraj siding with Talcher main line.

RITES MCL DPR under preparation. Feasibility report in advanced stage.

17 2nd siding at Himgir station, Kanika RITES MCL DPR approved by SECR. Land issue to be sorted by MCL.

Balance Coal Connectivity Projects

Page 32: SUDHENDU J. SINHA DIRECTOR PLANNING, RAILWAY BOARD Date :21.11.2013

ISSUES:AREAS OF CONCERN

• Environmental clearances.

• Land acquisition and possession.

• Law & order.

Page 33: SUDHENDU J. SINHA DIRECTOR PLANNING, RAILWAY BOARD Date :21.11.2013