International Journal of Mechanical Engineering and Technology (IJMET), ISSN 0976 – 6340(Print), ISSN 0976 – 6359(Online) Volume 4, Issue 1, January - February (2013) © IAEME 30 SUCCESS FACTORS ENHANCING BUSINESS PERFORMANCE OF ENGINEERING PROCUREMENT CONSTRUCTION (EPC) INDUSTRIES M.D.Nadar 1 , Dr. D.N.Raut 2 , Dr. B.E.Narkhede 3 and Dr.S.K.Mahajan 4 1 Research scholar- Production Engineering 2 Dean Administration-VJTI, Mumbai 3 HOD- Production Engineering Department, VJTI, Mumbai 4 Director- DTE, Government of Maharastra, Mumbai Email: [email protected] 1 , [email protected] 2 , [email protected] 3 ABSTRACT Engineering procurement construction projects play an important role in national economic development. India, which contributed approximately 8.5% to the total of India’s GDP. Project schedule slips, budget overruns, compromised quality, resulting claims and counter-claims problems have plagued the industry. The reasons for poor project performances abound. Previous researches have dealt much with the problems of project risk and uncertainty, variations in project outcomes, work fragmentation, complex relationships among stakeholders and activities, and excessive phase overlaps in general. In this paper dealt with EPC industries project success factors Construction projects are implementing different phases., viz., conception phase, definition phase, planning phase, scheduling phase, controlling phase and termination phase Various factors affect construction projects performance and success of projects i.e., completion periods of projects , project budget and better service to owner’s of project. The objective of this paper studying success factors variables, project functions, project activities, of project team members, project team members skills, attitude, experience, project tools, methods of project implementation enhancing the business performance of engineering procurement construction industries. Construction projects completion times are in line with owner’s requirements, and identifying gap reduction factors between project budget and project cost and improving business performance enhancing factors for construction project industries. To collect data, to record the collected data in tabular format, to analyze the recorded data by using statistical procedure and interpret ate success factors plays role in the EPC industry business operations. INTERNATIONAL JOURNAL OF MECHANICAL ENGINEERING AND TECHNOLOGY (IJMET) ISSN 0976 – 6340 (Print) ISSN 0976 – 6359 (Online) Volume 4 Issue 1 January- February (2013), pp. 30-43 © IAEME: www.iaeme.com/ijmet.asp Journal Impact Factor (2012): 3.8071 (Calculated by GISI) www.jifactor.com IJMET © I A E M E

Upload: iaeme

Post on 01-Nov-2014

711 views

Category:

Documents


3 download

DESCRIPTION

 

TRANSCRIPT

Page 1: Success factors enhancing business performance of  engineering procurement  construction 2

International Journal of Mechanical Engineering and Technology (IJMET), ISSN 0976 –

6340(Print), ISSN 0976 – 6359(Online) Volume 4, Issue 1, January - February (2013) © IAEME

30

SUCCESS FACTORS ENHANCING BUSINESS PERFORMANCE OF

ENGINEERING PROCUREMENT CONSTRUCTION (EPC)

INDUSTRIES

M.D.Nadar1,

Dr. D.N.Raut2,

Dr. B.E.Narkhede3

and Dr.S.K.Mahajan4

1Research scholar- Production Engineering

2Dean Administration-VJTI, Mumbai

3HOD- Production Engineering Department, VJTI, Mumbai

4Director- DTE, Government of Maharastra, Mumbai

Email: [email protected], [email protected]

2, [email protected]

3

ABSTRACT

Engineering procurement construction projects play an important role in national

economic development. India, which contributed approximately 8.5% to the total of India’s

GDP. Project schedule slips, budget overruns, compromised quality, resulting claims and

counter-claims problems have plagued the industry. The reasons for poor project

performances abound. Previous researches have dealt much with the problems of project risk

and uncertainty, variations in project outcomes, work fragmentation, complex relationships

among stakeholders and activities, and excessive phase overlaps in general. In this paper

dealt with EPC industries project success factors

Construction projects are implementing different phases., viz., conception phase,

definition phase, planning phase, scheduling phase, controlling phase and termination phase

Various factors affect construction projects performance and success of projects i.e.,

completion periods of projects , project budget and better service to owner’s of project. The

objective of this paper studying success factors variables, project functions, project activities,

of project team members, project team members skills, attitude, experience, project tools,

methods of project implementation enhancing the business performance of engineering

procurement construction industries. Construction projects completion times are in line with

owner’s requirements, and identifying gap reduction factors between project budget and

project cost and improving business performance enhancing factors for construction project

industries. To collect data, to record the collected data in tabular format, to analyze the

recorded data by using statistical procedure and interpret ate success factors plays role in the

EPC industry business operations.

INTERNATIONAL JOURNAL OF MECHANICAL ENGINEERING

AND TECHNOLOGY (IJMET)

ISSN 0976 – 6340 (Print) ISSN 0976 – 6359 (Online) Volume 4 Issue 1 January- February (2013), pp. 30-43 © IAEME: www.iaeme.com/ijmet.asp Journal Impact Factor (2012): 3.8071 (Calculated by GISI) www.jifactor.com

IJMET

© I A E M E

Page 2: Success factors enhancing business performance of  engineering procurement  construction 2

International Journal of Mechanical Engineering and Technology (IJMET), ISSN 0976 –

6340(Print), ISSN 0976 – 6359(Online) Volume 4, Issue 1, January - February (2013) © IAEME

31

Keywords: project team, project planning, project manager, project packages, project

activities, project schedule slips, project budget overrun, project cost

1. INTRODUCTION

The purpose of this paper is studying to overcome construction projects complexities

problems through successful factors of projects functions from conception phase to

termination phase [1] (functions starts from conception phase, definition phase, planning

phase, scheduling phase, implementation phase, monitoring and controlling phase and

termination phases). Identifying complex functions with various variables to enhance

complex function performance in construction projects operations [7]. Success factors to

optimize the complexities of construction projects. Exhausted literature survey and EPC

industry site visits are used to design and to develop the questionnaire. The questionnaire

circulates amongst engineering procurement construction industries, Consultant, owners,

Construction management CEO, programme managers, project managers around 500

numbers questionnaires are mailed, personally submitted with request, and received

43numbers. Questionnaires The questionnaire contents five parts viz., part-A(Company

information), part-B(Measuring project success), part-C(Factors affecting project success),

part-D(Use of computer packages for project management) and part-E(Project delay).

Questionnaires analysis gives various functions complexities in execution of construction

projects and corresponding variables (task, resources, time, and precedence) favors for

success of functions and affecting success of construction projects execution.

2. RESEARCH METHODOLOGY

• To interview senior management of contractor, Construction management, consultant

and owner of the project, EPC industry project head and visit to meet construction

project site head interact and to collect the research related data and information • To collect research related data and information of EPC industry through literature

survey of referred research problems related national and international journals

• To design and to develop questionnaire with five parts of questionnaire part-

A(Company information), part-B(Measuring project success), part-C(Factors

affecting project success), part-D(Use of computer packages for project management)

and part-E(Project delay).

• Data and information of EPC industries related business operations problems

collected through questionnaires.

• To record data and information from the collected questionnaires in the excel sheet

and in the tabular format. Statistical tools are using to analyze the data and

information.

• To observe and compare the business operations of EPC industries research related

different problems and various characteristics of business operational activities,

various operational factors to enhance the business performance activities and

characteristics of operational variables [7]. To conclude the variables and factors are

involves in success of EPC industries business operations.

Page 3: Success factors enhancing business performance of  engineering procurement  construction 2

International Journal of Mechanical Engineering and Technology (IJMET), ISSN 0976 –

6340(Print), ISSN 0976 – 6359(Online) Volume 4, Issue 1, January - February (2013) © IAEME

32

3. QUESTIONNAIRE DESIGN

This paper addresses studying and identifying the factors to stream line the input

variables (resources, planning, scheduling) and driving factors to controlling (monitoring,

updating) business operations of EPC industries. The questionnaire design and framework

based on rigorous survey of EPC industry business operations related research journals of

national, international literatures. And continuously visiting the site of EPC industry

project execution and contact project site head for collect data and information related

research variables and factors. The questionnaire consists of the following data and

information collecting tools (questions). The questions divided in to five parts. part-

A(Company information), part-B(Measuring project success), part-C(Factors affecting

project success), part-D(Use of computer packages for project management) and part-

E(Project delay).

3.1 Questionnaire – Company information

Questionnaire contents company’s information are company’s name, location of business

operation, capacity of business operation in terms of manpower, turnover yearly, project

size in terms of project cost, project duration and manpower involves in the executed

project.

3.2. Questionnaire – Measuring project success factors The executed project details includes project site, project details like type of the project i.e.,

mechanical, electrical, plumbing, HVAC, civil etc., technical capacity, type of the operational

functions i.e., design, supply, installation, testing and commissioning, and project cost,

projected executed time duration planned and actual, project success factors activities in

tactical management planning like design planning, project site execution planning,

manpower planning and material, machines and equipments [13] delivery planning to site

daily, weekly and monthly, safety, security and housekeeping planning, project selection,

material handling planning, risk mitigation etc., what are methods are using to drive the

success factors.

3.3. Success factors importance in project execution Various factors are measuring relatively in the project execution monitoring phase, well

defined tasks, responsibilities, reporting hierarchy organizations, project frequent feedback,

well defined control procedures, use of management tools like PERT/CPM, use contingency

plans, absence of lengthy procedures and absence of legal hurdles. The scales are defined

relatively in between (1-7) 7 is most important and 1 is least important. Construction project

success are defined different ways in questionnaire like project completion with in planned

schedule, planned budget and minor delay[17], minor escalated budget, delivered

construction project meets client’s quality, technical specification, functional envisaged by

the client, project benefits meets client’s satisfaction, commercially profitable to client, meets

client’s objective of their business. The scales are defined relatively in between (1-5) 1 is

most important and 5 is least important. Precautionary measures to optimize the success

factors are defining the following questions and scales are defined relatively in between (1-5)

1 is most important and 5 is least important. The questions are error free estimation of

project completion time and project cost, composition of project team, choice of project

leader, adequate of project funding, minimal start up difficulties, public support, project

Page 4: Success factors enhancing business performance of  engineering procurement  construction 2

International Journal of Mechanical Engineering and Technology (IJMET), ISSN 0976 –

6340(Print), ISSN 0976 – 6359(Online) Volume 4, Issue 1, January - February (2013) © IAEME

33

progress monitoring and control techniques. Attributes of project organizations are plays

roles in construction project success. The questions are defines the follows co-ordination

among the major functions, informal structure, funding support and resources allocation,

stability of policies and well defined reporting hierarchy and scales are defined relatively in

between (1-5) 1 is most important and 5 is least important. Construction project success is

defined in the questions of qualities of project team and project manager size of the team,

team spirit, job knowledge, willingness to learn, cost conscious, commitment to other projects

and commitment to project dead line and administrative authority, technical competence,

leadership style, timely decision making skills, communication skills, attitude and

commitment , clarity of purpose, unbiased, involvement in details and scales are defined

relatively in between (1-5) 1 is most important and 5 is least important. Construction projects

success further consider the client attributes and projects characteristics. The following

factors are given below in the questionnaire frequent interaction with project team, fast

response to project team queries, prompt payment of bills, co-ordination with project

team[11], commitment with project team [3,4,5,11,12], incentives for successful completion,

good rapport with organization etc., and size of the project, manpower requirement, technical

complexities of project, technical skills requirements, Stringent quality / tolerance

specifications, frequent changes to design requirements and special requirements of materials

and equipments and scales are defined relatively in between (1-5) 1 is most important and 5 is

least important. External factors are deviating the construction project success state and

these factors are presented in the questionnaire non –availability of materials in time, non-

availability of technical personnel, co-ordination with multiple agencies [14, 15], unexpected

ground conditions, price escalations, changes government policies, legal disputes,

discrepancies in contract documents, bad weather and mistakes and repetitions of activities

and scales are defined relatively in between (1-5) 1 is most important and 5 is least important.

3.4. Computer packages tool role in construction project success Construction Project Company uses computer packages factors (computer hardware,

software, internet facility, E-mail facility, fund transfer, telephone facility etc.,) involves in

successful project execution process. How far computer packages tool contribution to

construction project success defined the questions and scales are defined relatively in

between (1-5) 1 is most important and 5 is least important. Planning, scheduling, resource

allocations, resource histograms, budgeting, cash flow, crashing, report generation, project

budgeting, project updating, project change management, on-line project status, planning for

remaining work, earned value analysis, multi-project planning, multi-project resource

sharing, contractors monitoring, bill of materials, materials tracking and management,

transportation and distribution, risk mitigation, supply chain management, warehouse and

stores management functions, accounting, bill payment, bill collection, shift-wise planning,

integrated equipment maintenance, integrated shop floor planning, integrated quality

planning and control, information communication / transfer [2,12] and Email / EDI support

3.5. Project Delay factors: Construction project delay [17] causes are based on managerial degree of decision maker

favors to owners, quality of owner’s project manager, expected profit rate, market

standardization degree, strategic orientation, ability solve the design problems, risk control

capability, resource utilization degree, the number of follow-up of projects, the proportion of

educational and experience literacy of project team members.

Page 5: Success factors enhancing business performance of  engineering procurement  construction 2

International Journal of Mechanical Engineering and Technology (IJMET), ISSN 0976 –

6340(Print), ISSN 0976 – 6359(Online) Volume 4, Issue 1, January - February (2013) © IAEME

34

4. QUESTIONNAIRE RESPONDENTS

The questionnaire respondents are executives, contract management, consultant,

architect, owners and contractor’s Project manager, program manager, Procurement manager,

executives, projects of civil, HVAC, MEP etc.,

Table 1

Type of Industry Region Type

Mumbai –and Around

the Mumbai

Govt. Public Sector /

Private/Partnership or

Propietorship

Typical duration of

Projects in last FY

Less than 6 months 7

6-24 months 14

24-36 months 24

More than 36 months 7

Total questionnaires are received from respondents are 52 Programme mangers and Project

managers of contractors and construction management are 14 and 20 respectively out of 52

respondents, Project managers of consultancy 10 out of 52 respondents, Contractor Chief

Executing officer 4 out of 52 respondents and project owner of 4 out of 52 respondents. The

respondents industries based on ownerships are Government, propertiership, public sector

and private partnership.

5. SURVEY RESEARCH FINDINGS

Research finds variables for success of EPC industry operations are project success

factors for Environments of monitoring of progress of project implementation, project

success declaring environments, project enhancing factors, project implementing contractors,

construction management and consultancy attributes, executing project managers qualities,

project implementing team members qualities, attributes of qualities, complexities of

projects, attributes of project owners and attributes of external factors.

5.1. Research analysis of monitoring of project process methods Project progress implementation Monitoring climate involvement in project success is given

below.

Table 2

Code Factors Success factors %

C11 Well defined tasks and responsibilities 10.98%

CI2 Well defined reporting hierarchy 11.98%

C13 Well defined control procedures 13.48%

C14 Frequent feedback 12.31%

C15 PERT / CPM Techniques 11.15%

C16 Computer based Techniques 10.98%

C17 Use of contingency plans 10.98%

CI8 Absence of lengthy procedure 9.32%

C19 Absence of legal Hurdles 8.82%

Page 6: Success factors enhancing business performance of  engineering procurement  construction 2

International Journal of Mechanical Engineering and Technology (IJMET), ISSN 0976 –

6340(Print), ISSN 0976 – 6359(Online) Volume 4, Issue 1, January - February (2013) © IAEME

35

Figure 1

5.2. Research analysis of Environment of project success: Project success environment

declaring factors are given below.

Table 3

Code Factors Success factors %

C21 Project completed within planned due date

or minor delay

13.5%

C22 Project completed within planned budget or

minor escalation

11.39%

C23 Project meets technical /quality

specification of the client

6.33%

C24 Project provides satisfactory benefit to the

client (C24)

18.74%

C25 Project delivers the functionality envisaged

by the client (C25)

16.46%

C26 Project achieves stated business objectives

of the client (C26)

16.46%

C27 Project is commercially profitable for the

client

17.72%

Figure 2

Page 7: Success factors enhancing business performance of  engineering procurement  construction 2

International Journal of Mechanical Engineering and Technology (IJMET), ISSN 0976 –

6340(Print), ISSN 0976 – 6359(Online) Volume 4, Issue 1, January - February (2013) © IAEME

36

Project success environments are declared the factors from more important to least

important are projects provide satisfactory benefits to clients to project meets technical /

quality specification of the client

5.3. Research analysis of Enhancing factors for project success in EPC industry Enhancing project success environment through the following factors are given below.

Table 4

Code Factors Success factors

%

C31 Accurate initial estimates (Cost and time). 14.2%

C32 Composition of project team. 18.0%

C33 Choice of project leader. 12.1%

C34 Adequate funding to completion. 18.4%

C35 Progress monitoring and control techniques. 16.7%

C36 Minimal start-up difficulties 13.0%

C37 Public support for the project 7.5%

Project enhancing factors are ensuring the success of project implementation viz., adequate

funding for completion, composition of project team and project monitoring and control

techniques.

Figure 3

5.4. Research analysis of project implementing operational factors of contractors,

construction management organizations and consultancy organizations characteristics

influencing the project success. The following factors are influencing the success of the

project implementation in EPC industries.

Table 5

Code Factors Success factors %

C41 Informal structure. 12.3%

C42 Funding support. 18.2%

C43 Allocation of resources. 14.5%

C44 Stability of policies. 19.5%

C45 Co-ordination among major functions. 16.4%

C46 Well defined reporting hierarchy. 19.1%

Policy remains same for all project owners encourages the success of project implementation

like the quoting project price, method of project operational policies, project team

Page 8: Success factors enhancing business performance of  engineering procurement  construction 2

International Journal of Mechanical Engineering and Technology (IJMET), ISSN 0976 –

6340(Print), ISSN 0976 – 6359(Online) Volume 4, Issue 1, January - February (2013) © IAEME

37

motivational scheme, well defined organization hierarchy etc., funding support of stake

holders, contractors and vendors allocation of resources are make success of project

implementation, co-ordination amongst project implementation team in multi major functions

like HVAC, Civil, plumbing, Electrical, Building Management Systems (BMS)etc.,

Figure 4

project implementation viz., stability of organizational polices, well defined reporting

hierarchy, adequate funding for completion of project, co-ordination amongst contractor,

construction management and consultancy operational functions of project implementation,

allocation and available of resources on time of activities execution and project execution to

take place as team and follows as informal structure in the project implementation.

5.5. Research analysis of qualities of project manager characteristics is influencing the

project success. The project manager characteristics are influencing the project success in the

project execution are listed in the following success factors table.

Table 6

Code Factors Success factors %

C51 Technical competence. 20.00%

C52 Administrative authority. 6.27%

C53 Leadership style. 9.02%

C54 Clarity of purpose. 11.37%

C55 Timely decision making. 15.69%

C56 Communication skills. 16.08%

C57 Attitude and commitment. 11.76%

C58 Involvement in details 9.80%

Project manager plays crucial role in the success of project implementation of construction

industries operations. Technical competence characteristics of project manager are given the

below. Technical qualification, technical skills and technical experience are contributing in

the success of project implementation. Project manager communication characteristic reduces

the hierarchical communicational gaps own organizations, communication process in the

construction execution are existing amongst construction management, project owner and

consultancy. Project manager plays role as information receiver and distributor. Project

manager timely decision making characteristic, attitude and commitment, clarity of purpose

factors are important in the project implementation success.

Page 9: Success factors enhancing business performance of  engineering procurement  construction 2

International Journal of Mechanical Engineering and Technology (IJMET), ISSN 0976 –

6340(Print), ISSN 0976 – 6359(Online) Volume 4, Issue 1, January - February (2013) © IAEME

38

Figure 5

5.6. Research analysis of qualities of project team characteristics is influencing the project

success. The project team characteristics are influencing the project success in the project

execution are listed in the following success factors table.

Table 7

Code Factors Success factors %

C61 Small size of the team. 6.56%

C62 Job Knowledge. 16.39%

C63 Team Spirit. 14.34%

C64 Willingness to learn 19.26%

C65 Cost Consciousness 15.57%

C66 Commitment deadlines 19.26%

C67 Absence of commitments to other projects. 8.61%

Figure 6

Project team efforts are required to develop willingness to learn, commitment to deadline.

These efforts are lead to major project success contribution. Job knowledge, cost

consciousness and team work factors plays in the project success.

Page 10: Success factors enhancing business performance of  engineering procurement  construction 2

International Journal of Mechanical Engineering and Technology (IJMET), ISSN 0976 –

6340(Print), ISSN 0976 – 6359(Online) Volume 4, Issue 1, January - February (2013) © IAEME

39

5.7. Research analysis of qualities of project owner characteristics is influencing the project

success. The project owner plays major role in the success of the project implementation. The

project owner characteristics are listed in the following success factors table.

Table 8

Code Factors Success factors %

C71 Frequent interaction with project team. 13.21%

C72 Fast response to queries 15.47%

C73 Clarity of purpose 15.09%

C74 Good rapport with project organization. 10.57%

C75 Commitment to the project. 13.58%

C76 Prompt payment of bills. 13.21%

C77 Incentives for successful project completion 7.92%

C78 Co-ordination with project Team 10.94%

Project owner roles are important in the project execution success fast response to queries of

consultant, contractors, construction management reduce the delay of project activities, the

project product purpose clarity are required to be known by the client, frequent interaction

with project team, commitment to the project and prompt payment of bills enhance the

project success.

Figure 7

5.8. Research analysis of project complexities is resisting the project success. The project

complexities plays major role in the success of the project implementation. The project

complexities characteristics are listed in the following success factors table.

Table 9

Code Factors Success factors %

C81 Large size of the project. 5.33%

C82 Large manpower requirement. 10.66%

C83 Non-similarity to previous projects 14.34%

C84 Technical complexity of the project. 15.98%

C85 Stringent quality / tolerance specifications 17.62%

C86 Special technical skill requirements. 11.89%

C87 Frequent changes to original design specifications. 11.48%

C88 Special material / equipment requirements. 12.70%

Page 11: Success factors enhancing business performance of  engineering procurement  construction 2

International Journal of Mechanical Engineering and Technology (IJMET), ISSN 0976 –

6340(Print), ISSN 0976 – 6359(Online) Volume 4, Issue 1, January - February (2013) © IAEME

40

Project complexities are resisting the project execution success are ranking in the table-9.

Large size of the project increase the complexity of project characteristic resisting the success

of the project execution, consequently large manpower requirements increase the difficulties

and complexity of managing project execution it may lead to affect project success in

construction industry. Similarly the ranking of project success resisting factors are technical

skills requirements, frequent changes of original design specifications, special materials and

equipments requirements, non-similarities of previous projects, technical complexity of

projects and Stringent quality / tolerances specifications resisting the project

Figure 8

5.9. Research analysis of project External factors resisting the project success. External

factors plays major role in the success of the project implementation. External factors

characteristics are listed in the following success factors table.

Table 10

Code Factors Success factors %

C91 Non availability of materials in time 12.64%

C92 Non-availability of technical personnel 13.75%

C93 Coordination with multiple agencies 13.01%

C94 Unexpected “ground” conditions 10.08%

C95 Price escalations. 9.67%

C96 Changes in Government policies. 8.18%

C97 Legal disputes 9.67%

C98 Discrepancies in contract documents. 5.95%

C99 Mistakes and repetitions of activities. 9.67%

C910 Bad weather. 6.69%

External factors ranking are described the descending order in the success point of view.

Discrepancies in contract documents resisting the project progress and lead to delay in the

project completion, Bad weather, changes in government polices, price escalations, legal

disputes, mistakes and repetitions of activities are lead significantly to hurdle the project

progress, unexpected ground conditions may lead to disturb the project considerable

progress. Finally the following factors non availability of materials in time, co ordination of

multiple agencies and non availability of technical personnel.

Page 12: Success factors enhancing business performance of  engineering procurement  construction 2

International Journal of Mechanical Engineering and Technology (IJMET), ISSN 0976 –

6340(Print), ISSN 0976 – 6359(Online) Volume 4, Issue 1, January - February (2013) © IAEME

41

Figure 9

6. SUMMARY OF RESEARCH ANALYSIS AND PROJECT SUCCESS IN EPC

INDUSTRY

Projects are successfully implemented when controlling the following factors are

operational systems of contractors, consultants and construction management most important

to enhance the EPC industry business success External factors resisting the project success.

External factors plays major role in the success of the project implementation. External

factors characteristics are listed in the following success factors table.

Table 11

Code Factors Success factors %

C1 Project monitoring methods 11.4%

C2 Project success environment 11.4%

C3 Project success enhancing factors 11.4%

C4 Operational systems of contractor,

consultant and construction management

12.5%

C5 Qualities project manager 10.8%

C6 Qualities project team 11.8%

C7 Client characteristics 11.1%

C8 Project complexities 10.4%

C9 External factors 9.1%

Figure-10

Page 13: Success factors enhancing business performance of  engineering procurement  construction 2

International Journal of Mechanical Engineering and Technology (IJMET), ISSN 0976 –

6340(Print), ISSN 0976 – 6359(Online) Volume 4, Issue 1, January - February (2013) © IAEME

42

7. CONCLUSION

This paper reports the findings of an Action Research based investigation, which was

concerned with determining whether best practice used in other EPC industries to facilitate

the success of construction business process. The ranking of success factors gives ideas to

implement the EPC industries project follows the guide lines to success of the project in the

form of cost, time and quality development. The results of this research suggest that: The

operational methods of contractor, consultant and Construction management is to be

improved. Theses all success factor related to quality of project operational systems.

Contractor, subcontractors, construction management and consultant the quality success

factors are considered the following sequences. The qualities of project team, project

monitoring methods, project success environment, project success enhancing factors, client

characteristics, project manager attributes. Project complexities and external factors are to

limit the success of project implementation.

EPC industry success factors are implementing methodology to be developed is scope of this

paper. Like subcontractor rating, vendor selection, supplier certification, project team

training, project manager qualities training program, Design and development of

constructional process operational systems in construction activities

8.ACKNOWLEDGMENT

We express our sincere thanks to our institute management of VJTI for allowing us

work on construction management, we extend our sincere thanks to Dr.L.Ganapathy

(Professor in NITIE-Mumbai) give us proper guidance to search the construction industry

problems, our thanks to Shri. Dharmaraj, Adhithya Erode. who give us vision, mission and

financial support for this research work and also make me to develop this paper we extend

our sincere thanks to Dr. K.M.Vasudevan pillai and Dr.R.I.K.Moorthy, CEO and Principal

Pillai Institute of Information Technology New Panvel , for giving us continuous motivation

and time to complete this research work paper publication and last but not least our thanks

to our family members for giving us patience to complete the paper publication.

9.REFERENCES

[1] Evbuomwan NFO, Anumba CJ. An integrated framework for concurrent life-cycle design

and construction. Adv. Eng. Software 1998;29(7–9):587–97.

[2] Latham M. Constructing the team: joint review of procurement and contractual

arrangements in the United Kingdom construction industry: final report. London: Department

of the Environment; 1994.

[3] Payne J, Thomas K, Perkins M, Parker R, Small J. Working in an integrated team,

E3112. London: Construction Productivity Network; 2003.

[4].Alshawi M, Faraj I. Integrated construction environments. Construction Innovation

2002:233–51.

[5] Loo R. Assessing ‘‘team climate’’ in project teams. Int J Project Manage 2003;21(7):

511-7.

[6] CII, Procurement and materials management: a guide to effective project execution,

Construction Industry Institute, Implementation Resource 7-3, 1999.

[7]Y.Y. Su, L.Y. Liu, Real-time tracking and analysis of construction operations, Proc.,

Construction Research Congress, ASCE, Grand Bahama Island, Bahamas, 2007.

Page 14: Success factors enhancing business performance of  engineering procurement  construction 2

International Journal of Mechanical Engineering and Technology (IJMET), ISSN 0976 –

6340(Print), ISSN 0976 – 6359(Online) Volume 4, Issue 1, January - February (2013) © IAEME

43

[8] Matthews, J., Rowlinson, S., 1999. Partnering: incorporating safety management.

Engineering, Construction and Architectural Management 6 (4), 347–357

[9] Benjamin, R., Levinson, E., 1993. A framework for managing IT enabled change. Sloan

Management Review 34 (4), 23}33.

[10] Soderberg, J., 1996. How can IT a!ect the construction process. In: Langford, D.A.,

Retik, A. (Eds.), The Organisation and Management of Construction: Shaping Theory and

Practice, Vol. 3. Spon, London, pp. 217}225

[11] S.G. Yeomans, N.M. Bouchlaghem, A. El-Hamalawi, An evaluation of current

collaborative prototyping practices within the AEC industry, Automation in Construction 15

(2006) 139 – 149

[12] Sir M. Latham, Constructing the Team, Final Report of the Government — Industry

Review of Procurement and Contractual Arrangements in the UK Construction Industry,

HMSO, London UK, 1994.

[13] Joachim Vedder, Eilı´s Carey, A multi-level systems approach for the development of

tools, equipment and work processes for the construction industry, Applied Ergonomics 36

(2005) 471–480

[14] Ander Errasti, Roger Beach, Aitor Oyarbide, Javier Santos, A process for developing

partnerships with subcontractors in the construction industry: An empirical study,

International Journal of Project Management 25 (2007) 250–256

[15] L. Alberto Franco, Mike Cushman, Jonathan Rosenhea, Project review and learning in

the construction industry: Embedding a problem structuring method within a partnership

context, European Journal of Operational Research 152 (2004) 586–601

[16] R. Navon Research in automated measurement of project performance indicators,

Automation in Construction 16 (2007) 176–188

[17] Daniel.W.M, Chan, Mohan. M. Kumaraswamy, Compressing construction durations:

lessons learned from Hong knog building projects, International journal of project

management 20(2002), 23-35

[18] Urjit R. Patel, Saugata Bhattacharya Infrastructure in India: The economics of transition

from public to private provision Journal of Comparative Economics 38 (2010) 52–70

[19] T.Baladhandayutham and Dr. Shanthi Venkatesh, “e-Procurement - An Empirical Study

on Construction Projects Supply Chain Kuwait”, International Journal of Management (IJM),

Volume 3, Issue 1, 2012, pp. 82 - 100, Published by IAEME

[20] Lakshmi Vishnu Murthy Tunuguntla and Dr. Mu.Subrahmanian, “Building An

Integrated Framework For It Governance Factors And Business-It Alignment”, International

Journal of Management (IJM), Volume 3, Issue 1, 2012, pp. 19 - 28, Published by IAEME

[21] Tanmaya Kumar Das, Dillip Kumar Mahapatra and Gopakrishna Pradhan, “An

Integrated Framework For Interoperable And Service Oriented Management Of Large Scale

Software”, International journal of Computer Engineering & Technology (IJCET), Volume 3,

Issue 3, 2012, pp. 459 - 483, Published by IAEME

[22] T.Baladhandayutham and Dr. Shanthi Venkatesh, “Construction Industry In Kuwait –

An Analysis On E-Procurement Adoption With Respect To Supplier’s Perspective”,

International Journal of Management Research and Development (IJMRD), Volume 2,

Number 1, 2012, pp. 1 - 17, Published by IAEME