submitted to the department of civil engineering

104
ROAD MAINTENANCE PRACTICES IN BANGLADESH 625.76 1991 ABD A THESIS ON SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING, BANGLADESH UNIVERSITY OF ENGINEERING AND TECHNOLOGY, DHAKA IN PARTIAL FULFILMENT OF THE REQUIREMENTS FOR THE DEGREE OF POST GRADUATE DIPLOMA IN GEOTECHNICAL AND TRANSPORTATION ENGINEERING UNDER AIT - BUET JOINT PROGRAMME BY I'1D _ ABDUS SABUR FEBRUARY, 1991 1111111111111111111111111111111111 #80266# ,

Upload: others

Post on 16-May-2022

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

ROAD MAINTENANCE PRACTICESIN BANGLADESH

625.761991ABD A THESIS ON

SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING,BANGLADESH UNIVERSITY OF ENGINEERING AND TECHNOLOGY, DHAKAIN PARTIAL FULFILMENT OF THE REQUIREMENTS

FOR THE DEGREE OF

POST GRADUATE DIPLOMA IN GEOTECHNICAL ANDTRANSPORTATION ENGINEERING

UNDER

AIT - BUET JOINT PROGRAMME

BY

I'1D_ ABDUS SABUR

FEBRUARY, 1991

1111111111111111111111111111111111#80266#

,

Page 2: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

ROAD MAINTENANCE PRACTICESTN BANGJ~AJ~ESJcI

A THESIS

BYMD. ADJ~US SABUR.

APPllOV61lAS TO STYLE ANIl CONTENT IIY

----~~~~---MIl.SYEIlNOOIl-UD-IlEEN AHMEDAssociate ProfessorDepartment of Civil EngineeringIIUET., Ilhaka.

1M_. ~_~_~_Ilil.Mil. MAZHAllllL HOQUEAssociate ProfessorDepartment of Civil EngineeringIIllET,Ilhaka.

Dil. MllHAMMAIl ZAKARIAAssociate ProfessorIlepartment of Civil EngineeringIIllET,Dhaka

Chairman(Supervisor)

Hember

~Iember

Page 3: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

INDEX

Synopsis

Acknowledgment

List of Tables

List of Figures

Appendix

CHAPTER - 1 INTRODUCTION

1.1 General Introduction

1.2 Importance and Significance of Road Maintenance

1.3 Objectives of the Project Study

1.4 Quantity and Characteristics of Roads andHighways in Bangladesh

1.5 Definition, Implications of Road Maintenance

1.6 Classification of Road Maintenance

CHAPTER - 2 REVIEW OF LITERATURE

2.1 Introduction

2.2 Pavement Evaluation

I

II

IV

V

1-15

1

1

6

6

16-30

16

16

2.2.1

2.2.2

Deduct Value or Deduct Point Method

Present Serviceability Index (PSI) Method

16

18

,2.3 Roughness Measurements

2.3.1 Method for Measurement of Roughness

2.4 Method for Measuring Deflection Value

19

19

21

2.4.1 Analysis of Deflection Data 24

2.5 Maintenance Activities 26

2.5.1

2.5.2

Routine Maintenance

Special Maintenance

26

27

Page 4: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

2.5.3

2.5.4

2.5.5

Betterments

Rehabilitative Maintenance

Emergency Works

27

28

29

EVALUATION TECHNIQUE FOR MAINTENANCE

Evaluation of Road Maintenance Needs

Evaluation Techniques

CHAtTER - 3

3.1

3.2

3.2.1

3.2.2Maintenance of Paved Roads

Maintenance of unpaved Roads

31-39

31

32

32

38

Thickness of Overlay

DisintegrationSkid hazard

Maintenance Operations

SYMPTOMS, CAUSES AND TREATMENT OF ROAD FAILURESCracking

Distortion

40-55

40

41

42

43

46

46

50

52

53

Maintenance of Roadway Surfaces

Maintenance of Shoulders

Maintenance of Drainage Structures

4.5.1

4.5.2

4.5.3

4.6

CHAPTER - 4

4.1

4.2

4.3

4.4

4.5

CHAPITR - 5

5.1

5.2

5.3

5.4

5.5

CHAPITR - 6

6.1

ROAD MAINTENANCE MANAGEMENT

Introduction

Maintenance Manpower

Maintenance Manpower in Bangladesh

Mechanization and Equipment Planning

Management of Funds

ROAD MAINTENANCE PRACTICES IN BANGLADESHIntroduction.

56-63

56

56

56

58

61

64-83

64

Page 5: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

6.2 Road Construction and Maintenance Organisations 646.3 Problems of Road Maitenance in Bangladesh 68

6.3.1 Problems for Arrangement of Traffic 686.3.1.1 Works on Edges and Shoulders 736.3.1.2 Restricting the Traffic to One Lane 74•6.3.1.3 Working in the Centre of 75the Carriageway6.3.1.4 Diversions 76

6.3.2 Financial Capacity 786.3.3 Institutional Capacity 78

6.4 Existing Road Maintenance Technique 796.5 Financial Pattern for Maintenance (Upazila road) 82

CHAPTER - 7 RESEARCH FINDINGS AND RECOMMENDATIONS 84-867.1 Findings 847.2 Recommendations 86

REFERENCES 94

Page 6: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

I

Evaluation techniques for sUccessful maintenance works. are

SYNOPSIS

In recent times rand networks in Bangladesh are expanding much faster than

corresponding increases in maintenance budgets and insti tutional

capnci ties. In this research various aspect of road maintenance works are

reviewed. To this end, road kilometrege for various categories of roads arestudied.

re"iewed. Symptoms, causes and treatments for road failures are highlighted

for routine as well as for periodic maintenance. This study showed that

fund spent fOl' maintenance is not quite adequate. Appropriate or scientif ic

methods for maintenance are not yet devised and documented in the countr~'.

Standard maintenance procedures and materials to be used in .maintenance are

disclJssed. Manpower and equipments required for maintenance are alsoincluded in this study.

Page 7: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

ACKNOWLEDGMENT

The author expresses his heartiest gratitude and profound indebtness to

Mr. Syed Noor-Ud-Deen Ahmed, Associate Professor, Department of Civil

Engineering for his affectionate guidance, help, encouragement and active

co-operation in making this report possible. His keen interest on the

topic and valuable advise throughout the study were of great help. and

acted as a prime mover is materializing the project report.

The author expresses his gratitude to Dr. Alamgir Mujibul Hoque, Professor

and Head, Department of Civil Engineering, for sincere co-operation and

encouragement.

The aqthor expresses gratitude to all the senior executives involved in

construction and maintenance related activities for contributing their

valuable opinion.

The support, co-operation and encouragelDent of colleagues are also

acknowledged with thanks.

II

Page 8: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

LIST OF TABLES

TABLE-I. 1 Road Network Under RHD in Selected YearsTABLE-I. 2 Road Network Under RHD in Mid 1988~TABLE-I. 3 Road Kilometrege in different OrganisationsTABLE-I. 4 Total Paved Road under RHD according to WidthTABLE-2.1 Deduct Values for Flexible PavementTABLE-2.2 Asphalt Pavement Rating Form

TABLE-4.1 Recommendations for Patching Material

TABLE-5.1 Road Maintenance Staff for a Typical Road Division

TABLE-5.2 The Machineries, Equipments for Maintenanceowned by the Roads and Highways Department

TABLE-5.3 Equipment owned by Typical Road Division

TABLE-5.4 The Average Annual Expenditure for Maintenanceby Roads and Highways Department

TABLE-5.5 The Average Annual Expenditure forMaintenance by Road Type

TABLE-5.6 Annual Maintenance Expenditure of differentRoad Circles in Bangladesh

TABLE-6.1 Types of Maintenance Works done by Roads andHighways Department

III

7

11

12

12

1730

50

5759.

60

61

62

62

83

Page 9: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

FIGURE-lo1

F1GURE-2.1

FIGURE-2.2

FIGt'RE-2.3

FIGliRE-2.4

FIGURE-2.5

FIGURE-2.6

FI Gt'RE-4. 1

FIGERE-4.2

FIGERE-4.3

FIGURE-4.4

FIGERE-4.5

FIGURE-4.6

FI Gt'RE-6. 1

FIGtllE-6.2

FI GtllE-6. 3

FI GlJllE-6. 4

FI Gt'RE-6. 5

LIST OF FIGUR.ES

Road map of Bangladesh

Diagramatic Arrangement of Bump-Integrator

Benkelman Beam

Diagramatic Arrangement of Deflection Beam

The Thickness of Bituminous Premix Overlay Required

Asphalt Concrete Overlay ThicknessCondition Rating

Photograph Showing Potholes

Photograph Showing Water Stagnant

Photograph Showing Alligator Cracking or Map Cracking

Photograph Showing Shallow Depression

Steps for Repairing Potholes

Photograph Showing of Repairing Potholes

Standard Traffic Signals

Sign Layout for Edge Working

Sign Layout for Lane Closure

Sign Layout for Centre Line Working

Sign Layout for Diversion

IV

13

20

22

23

25

25

30

4444

4545

48

49

71

73

7576

77

Page 10: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

A.

APPENDIX

Particle Size Distribution for Gravel Surfacing. 88-93B. Grading for Cracked Rock Patching Material.C. . Requirements for Premixed Macadam used for Patching MaterialD. Recommended Chipping Size.

E. Spraying Temperatures.

F. Road Condition Survey Form.

G. Road Classifiction and Geometric Standards.

v

Page 11: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

CHAPTER - 1INTRODUCTION

1.1 GENERAL INTRODUCTION

It is an established fact that development and improvement of

transportation systems and services are essential to the healthy

socio-economic growth of a nation. This is true for developing

countries particularly the least developed countries like Bangladesh

where transportation systems and services have not yet achieved a

level of acceptance in relation to quality, quantity, efficienq',

convenience and safety.

Bangladesh is a populous country with a geographical area of only

1,43,410 Sq. Km. and confronted with the problem of accommodating an

ever-growing huge population on a very limited land area and even more

limited natural resources. This dichotomous situation puts Bangladesh

in a condition in which every attention need to be given in the

investment of its very limited financial and natural resources in the

spheres of feeding, housing, educating and providing related services

and facilities for the attainment of an improved quality of meaningful

life.

1.2 IMPORTANCE AND SIGNIFICANCE OF ROAD MAINTENANCEOf manifold services and facilities needed for improved human .life

transportation is one of the most important. In fact, transportation

is a kind of service which is owned and utilized by the entire

population. Basic quality of transportation and transportation

related services are as such major determinants of so called

1

Page 12: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

developments, progress and prosperity which are so often acclaimed as

being achieved.

It is said that the level of discipline achieved by any nation is

reflected on traffic scenes and behaviors. A cursory look at these

parameters on roads and rails in Bangladesh represents melancholy

pictures. The common experience on roads and highways is one of

indiscipline and chaos in which multimodal vehicles are competing to

utilize very limited road spaces without paying any heed to general

courtesy and general sense of discipline. Precarious road conditions

arising out of poor or no road maintenance makes the situation worse

and more vulnerable. It appears that very little attention is paid

and very little amount of money is spent on road maintenance which is

so very important for the upkeep of the huge investment made on roads

and highways out of very limited national funds. It must be

emphasized that keeping roads and highways in serviceable and well-

maintained condition is a very important responsibility of all

concerned organisations. Stated differently, it is the right and

privilege of the citizens of Bangladesh to get the quality of roads

and highways services which are afforded by well maintained roads and

other transport facilities. Any departure or negligence from these

responsibilities on any ground whatsoever reflect and represent a

credibili ty gap between the road builders- maintainers and the road

users.

The importance of road maintenance lies mainly in the need to protect

the substantial investment that has been made on highways.

Furthermore, the significance of the maintenance function is seen in

2

Page 13: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

the vital need to continue the economic and social benefits that are

derived from the public road system. The travelling public is

actually aware of the condition of public streets and highways. The

need for road maintenance may be clear to most engineers but is not soclear to the layman.

The three main reasons for maintaining a road are:

i. To prolong the life of the road.

ii. To reduce vehicle operating costs.

iii. To keep the road serviceable.

i. To Prolong the Life of the Road

Roads deteriorate due to the damaging actions of traffic and

climate. Heavy trucks and buses cause most damage to roads. The

damage caused by a loaded vehicle follows a power law so that if

the axle load is increased by a factor of two the damage is

increased by a factor of approximately twenty. Thus a small

number of overloaded lorries can cause a disproportionate amountof damage.

Water in all forms causes a road to deteriorate. If the road is

subject to flooding, the road may break up in a very short period

of time. Rainfall, if allowed to collect on the road surface or

shoulders, eventually finds its way into the road structure with

consequential rapid damage. Planned maintenance should be such

that the road is at all times capable of carrying the applied

traffic loads and the drainage system must be maintained so that

water does not enter the road pavement.

3

Page 14: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

The quality of the original construction must be of adequate

standard to prevent rapid deterioration of the road. However,

construction cost must always be balanced against the available

funds. 1t is economically sound to build a road to a certain

standard and then provide additional strengthening overlays as a

part of a planned maintenance system.

Failing to maintain a road is virtually the same as failing to

put oil in a car, a little negligence can have expensive

consequences.

ii. To Reduce Vehicle Operating Costs

The largest single import into Bangladesh is petroleum oil. A

large proportion of this is used in motor fuels (gasoline or

diesel). Traffic is presently growing at a rate of between 7 and

10% per annum and most of this growth is accounted for by

commercial vehicles. The cost of vehicular travel is reflected

in almost all walks of life, high transport costs mean less

competitive exports and reduced economic activity. Valuable

foreign exchange must always be earned to finance oil imports.

If a road is badly maintained with a rough or potholed riding

surface, the costs to vehicles travelling on the roads are

increased due to:

a. Using more fuel

b. Transporting less goods in a given time

c. Increased repair and maintenance costs

d. Increased tyre wear

e. Shorter vehicle life.

4

Page 15: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

Extensive economic studies have shown that vehicle operating

costs are closely related to road roughness. The smoother the

road the lower the vehicle operating costs. In national terms a

better maintained road network means a lower oil import burdenand more competitive exports. It has been shown that if even a

•small decrease in roughness of the road network could be

achieved, the savings in vehicle operating costs would far

outweigh the additional maintenance costs (Reference No.12).

iii. To Keep the Road Serviceable

If the roads are closed due to flooding, landslips, cuIvert or

bridge failure etc., communications are disrupted with serious

social and economic consequences. Strenuous, and generally

expensive, efforts are always made to restore communications inthe minimum time.

It is a fact that the many such emergencies could be prevented

if attention is given to the standards of construction andregular inspection and maintenance actions.

It is commonly found that maintenance is not properly carried outbecause:

1. People often do not fully realize the importance of roadmaintenance.

ii. Maintenance presents muchthan new construction. greater problems of management

iii. New road construction is more popular with some people thanroad maintenance works.

iv. Insufficient funds are allocated for maintenance.

v. Maintenance is more difficult to plan and supervise than newconstruction because roads are spread throughout thecountry, not concentrated in one particular place.

5

Page 16: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

economic advantage to both owner and taxpayer.

and owners of roadway pavements. For users, both automobiles and

Maintenance can provide major economic advantages to both users

"

In addition, roads

undertaken with the~

more miles of modern roads can be provided.

The project study on road maintenance wasobjectives of studying:

shorter time for less cost than new roads can be built, providing

maintenance when operated on safe, smooth pavements. For owners,commercial vehicles become more fuel efficient and require less

can remain in use while being modernized with asphalt, and old

roads frequently can be improved and put back into service in a

1.3 OBJECTIVES OF THE PROJECT STUDY:

1. The existing road maintenance practices followed by differentorganisations in Bangladesh.

ii. Evaluation technique to be followed for maintenance purpose.

iii. Suggestion for improved maintenance practices in Bangladesh.

1.4 QUANTITY AND CHARACTERISTICS OF ROADS AND HIGHWAYS IN BANGLADESH:

In Bangladesh roads and highways facilities are very limited compared

to even moderately developed countries. According to statistics from

Roads and Highways Department Bangladesh had only 600 Kms. of 'high

type' roads at the time of partition of India. After the independence

oC Bangladesh there was a total of 4025 Kms. of roads of which 3460

KIIs.where 'high type', that is mostly bituminous pavements and the

remainder was brick-soled or stablized earth roads. According to the

same source about 9000 Kms. of roads have been built on the post

independence period of which 4557 Kms. nearly belong to the high typeroad category.

6

Page 17: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

ROAD NETWORK UNDER ROADS AND HIGHWAYS DEPARTMENT(RHD) IN SELECTED YEARS

historical development or road network, under Roads and Highways

TABLE - 1.1

on

(In Kilometre)

High type Low type Totalroads(a)* roads(b)**

600 6002500 225 27253160 242 34023460 565 40254285 1407 56924775 2600 73756218 4695 109137218 5103 12321

following table present .information in selected yearsThe

1982

1971

1965

1960

1947

Department since 1947.

1980

Year

1985

1988

Source: Roads and Highways Department, Dhaka.

* 'High type' roads refer to paved roads having asphalt and cementconcrete surface.

** 'Low type' roads refer to infrastructure comprising brick paved,partly paved, stone/gravel and earthen roads.

According to another statistical information from the Roads and

Highways Department the total quantum of 'high type' roads built upto

June 30, 1988 amounts to 7156 Kms. A breakdown of these high type

road kilometrege in relation to width of road pavement is summarizedbelow

7

Page 18: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

------------------------------------------------------------------------------------------------------------------------------------------Source: Roads and Highways Department as on 30.06.1988.

244.58379.1218.04550.6824.701. 61

349.93327.3579.12

1281.41590.4585.31

2713.57

Road length 1Kml

Road length 1Kml

Below 3.663.66

3.96 to 5.185.496.71

Over 6.71

Below 3.663.66

3.96 to 5.185.496.71

Over 6.71

NATIONAL HIGHWYS (paved)

Pavement width 1M}

Total:

REGIONAL HIGHWAYS (paved)

Pavement width 1M}

----------------------------------------------------------------------Total: 1218.73----------------------------------------------------------------------Source: Roads and Highways Department as on 30.06.1988.FEEDER ROADS (Paved)

Pavement width 1M} Road length 1KmlBelow 3.66 232.753.66 1003.403.96 to 5.18 66.425.49 253.966.71 54.91Over 6.71 7.78---------------------------------------------------------------------Total: 1619.23---------------------------------------------------------------------

Source: Roads and Highways Department as on 30.06.1988.

8

Page 19: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

UPAZILA CONNECTING ROADS (Paved)

Pavement width iMlBelow 3.66

3.663.96 to 5.18

5.496.71

Over 6.71

Road length lKml793.46710.8133.8855.566.813.22---------------------------------------------------------------------Total: 1603.74---------------------------------------------------------------------

Source: Roads and Highways Department as on 30.06.1988.

TOTAL PAVED ROAD UNDER ROADS AND HIGHWAYS DEPARTMENTCategory of Road

National HighwaysRegional HighwaysFeeder RoadsUpazila Connecting Roads

Road length lKml2713.571218.731619.231603.74

Percentage

38172322---------------------------------------------------------------------

Total: 7155.27 100---------------------------------------------------------------------Besides the •high type' roads stated above the Roads and Highways

Department also have some roads which are either partly paved or aregravel or earthen roads.

summarized below:Total roads other than •high type' are

----------------------------------------------------------------------Category of Roads Present Condition

-----------------------------------HBB orPartlypaved

Gravelroad

Earthenroad

----------------------------------------------------------------------1. National Highways 63.06 25.55

+32.422. Regional Highways 129.32 21.713. Feeder Roads 512.81 106.89 722.14+42.254. Upazila Connecting Roads 1358.50 20.00 1876.29+198.05----------------------------------------------------------------------

2063.69 126.89 2645.69+272.72----------------------------------------------------------------------

+ In the form of tracks as on 30.06.1988.Source: Roads and Highways Department as on 30.06.1988.

9

Page 20: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

KUTCHA ROAD :(in Kms)---------------------------------------------------------------------------

Authority 1984-85 1985-86 1986-87 1987-88 1988-89---------------------------------------------------------------------------l. Zila Parishad

2. Pourashava/Poura Corporation

3. Upazi1a Parishad

4. Union Parishad

16936

3299

22581

101774

16452

3339

23065

102016

16049

3403

23306

102420

15936 15759

3468 3742

24516 27420

104196 107259---------------------------------------------------------------------------144590 144872 145178 148114 154180---------------------------------------------------------------------------

Source: Local Govern.ent Engineering Bureau (LGEB).

Roads under Pourashava/Poura Corporations are maintained by their ownstaff. Pourashavas cannot afford to spend amount liberally on road

maintenance and development, because their own source of income from

taxes is very limited. They have to provide a number of services and

utilities such as water supply, sanitation, electricity etc. in

addition to road construction and maintenance.

Besides Roads and Highways Department, a major part of the remaining

roads are constructed and maintained by the local bodies in

conjunction with the engineer of L.G.R.D. Ministry. Their maintenancework is very slow and rare. Their maintenance work is not quiteregular. Maintenance is usually undertaken on emergent basis when the

road condition is deplorable. The total road kilometrege under localbodies is given below:

10

Page 21: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

ROAD KILOMETREGE UNDER LOCAL BODIES

PUCCA ROAD (Paved)(in kms)---------------------------------------------------------------------------

Authority 1984-85 1985-86 1986-87 1987-88 1988-89---------------------------------------------------------------------------1. Zila Parishad 4210 4516 4759 5000 52422. Pourashava/

Poura Corporation 4241 4379 4336 4690 50003. Upazila Parishad 444 455 468 484 5004. Union Parishad---------------------------------------------------------------------------

8895 9350 9563 10174 10742---------------------------------------------------------------------------Source: Local Govern.ent Engineering Bureau (LGEB)

TABLE - 1.2

ROAD NETWORK UNDER RHO IN MID 1988

---------------------------------------------------------------------------Length in km----------------------------------------

Category ofroads

Pavedroad

Partlypaved orbrick pavedroad

Earthenroad

Total

---------------------------------------------------------------------------1. National Highways 2714 63 58 28352. Regional Highways 1219 129 22 13703. Feeder roads 1619 513 764 2896---------------------------------------------------------------------------

4.

Sub-Total:Percentage:

Upazila connectingroads

555278.12

1604

7059.90

1359

84411. 88

2075

7101100.00

5038---------------------------------------------------------------------------

Total:Percentage:

715658.97

206417.01

291424.02

12134100.00---------------------------------------------------------------------------

11

Page 22: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

177056100.00

15709488.74

20641.16

1789810.10

Total:Percentage:

TABLE-1.3

ROAD KILOMETREGE IN DIFFERENT ORGANISATIONS(Upto Mid 1988)

below:Total road kilometrege according to types of road is given in the table

---------------------------------------------------------------------------Authority Paved Partly Paved Earthen/ Total Percentage ofroad or brick Kutcha paved road/paved road road earthen road----------------------------------------------------------------------------1. Roads and Highways 7156 2064 2914 12134 40/2Department

2. Zila Parishad 5242 15759 21001 29/103. Pourashava/ 5000 3742 8742 28/2.3Poura Corporation4. Upazila Parishad 500 27420 27920 3/17.45. Union Parishad 107259 107259 -/68.3---------------------------------------------------------------------------

---------------------------------------------------------------------------

TABLE-1.4

TOTAL PAVED ROAD UNDER RHD ACCORDING TO WIDTH

---------------------------------------------------------------------------Double Lane(5.49-7.32m)

Total Percentage---------------------------------------------------------------------------1. National Highways 1958 2714 722. Regional Highways 578 1219 483. Feeder Roads 317 1619 20

41604

7156

66

2919

Upazila Connecting RoadsTotal :---------------------------------------------------------------------------

4.

---------------------------------------------------------------------------

12

Page 23: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

A map illustrating the ro"d network of Bano;ladesh is shown in Fig.I.!

u

H 0

Fig.!.l

ROAD MAP OF

BANGLADESH

,".',i ,",4'p '''.u••••• 14 •••• _

Road ~ap of Bangladesh.

A

•N

,I

(Source Roads and Highways Department, Dhaka)

13

Page 24: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

1.5 DlFINITION, IMPLICATIONS OF ROAD MAINTENANCE:'Maintenance' is defined as the preserving and keeping of each type of

~way, structure and facility as nearly as possible in its original

aondition as constructed or as subsequently improved and the operation

of highway facilities and services to provide satisfactory and safetransportation. Maintenance is no improvement works to upgrade the~d for traffic growth or the replacement of the capital elements of

the road such as the pavement, bridges etc. Maintenance includes both

physical maintenance activities and traffic service activities.

The maintenance needs of a road network can be predicted fairly

accurately from a set of structural characteristics, such as age,

climate, traffic, design standards, construction quality. The safety

and convenience of traffic using the road are governed to a large

extent by the quality of maintenance. The operation-economics of road

transport is influenced by the degree of maintenance imparted to the

read. The life of an asset can be preserved and prolonged if adequate

maintenance measures are undertaken in proper time. The propermaintenance of roads, therefore, assumes greater significance in suchsituations.

1.6 CLASSIFICATION OF ROAD MAINTENANCE:

Maintenance cooperations can be classified as follows:

i. Routine Maintenance, embracing work items such as filling of

potholes and repairing of cracks which are required to be carried

out by the maintenance staff almost round the year;

14

Page 25: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

ii. Periodic Maintenance, covering more extensive maintenance

operations such as applying a seal or renewal coat which are

required to be done periodically every few years;

iii. Rehabilitative Maintenance, operations required to bring a

deteriorated road back upto the original standard;

iY. Improvements, minor improvements, widening etc. which are too

small to involve a construction unit;

v. Emergency Repairs, repairs required immediately to restore

communications.

ID a perfectly maintained road system there should not be any

rehabilitative maintenance. A planned programme of routine and

periodic maintenance should prevent deterioration to a state where

rehabilitation is required. Rehabilitative maintenance is always more

expensive than regular routine and periodic maintenance.

Mayso called emergency repairs should never OCcur. A high proportion

of emergencies could be prevented by proper construction standards andregular maintenance.

15

Page 26: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

2.1 INTRODUCTION

comfort and an increased level of safety is vehicular movement.

CHAPTER-2

REVIEW OF LITERATURE

springs, shock absorber etc., increased ridingsuspension system,

The major hindrance to smooth vehicular movements on a road surface

aay be caused by a number of factors such as poor surface texture,

faulty finishing, potholes, cracks, corrugations, rutting and pavement

deformations. These factors inhibit the need for pavement evaluation.

One of the most desirable characteristics of good road pavement is a

reasonably smooth riding surface. A smooth pavement surface brings a

number of .advantages some of which include higher vehicle operating

speed, less fuel consumption and eventual fuel economy, less wear and

tear of vehicle tyres, less changes in vehicle spare parts such as

2.2 PAVEMENT EVALUATION

Pavement evaluation is a technique of assessing the condition of a

pavement, both structurally and from the point of view of surfacecharacteristics. It is also known as pavement condition survey andrating of pavement. Evaluation of pavements can be done by a number

of methods some of which are briefly discussed below.

2.2.1 Deduct Value or Deduct Point Method

A simple but quite widespread method was developed initially at the

Texas A & M University and is known as Deduct Value or Deduct Point

Method. In this method, Certain deduct points are associated withspecific values of various distress factors.

16

The deduct points

Page 27: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

TABLE-2.1

5

(3 )

10

15

10

15

20

10

15

2

7

8

(2 )

8

12

12

18

12

o5

5

5

(1)

10

10

15

10

Degrees of Extent or Amount of DistressDistress -- _

Slight

Moderate

Severe

Slight

Moderate

Severe

Slight

Moderate

Deduct values for flexible pavementTypes of Distress---------------------------------------------------------------------

---------------------------------------------------------------------Ilutting

---------------------------------------------------------------------Ravelling

---------------------------------------------------------------------Flushing

points are then subtracted from an established "Perfect" score

indicate the relative importance of the distress type. These deduct

(Reference No.5).Table 2.1, gives the deduct points for various levels of distress

(usually 100) to arrive at the overall rating score of the pavement.

17

5

20

101520

1520

25

10

20

40

2

7

18

81218

10

15

20

15

30

5

o5

7

15

51015

10

15

20

Severe

SlightModerateSevere

Slight

Moderate

Severe

Good

Fair

Poor

---------------------------------------------------------------------Corrugations

---------------------------------------------------------------------Alligatorcracking

---------------------------------------------------------------------Patching

Failures------------------------------------------------------------------------------------------------------------------------------------------

--------------

Page 28: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

Deduct Points for CrackingLongitudinal Cracking

Sealed Partially Sealed Not Sealed(1) (2) (3) (1) (2) (3) (1) (2) (3)Slight 2 5 8 3 7 12 5 10 15Moderate 5 8 10 7 12 15 10 15 20Severe 8 10 15 12 15 20 15 20 25Transverse CrackingSlight 2 5 8 3 7 10 3 7 12Moderate 5 8 10 7 10 15 7 12 15Severe 8 10 15 10 15 20 12 15 20

Source Principles and practices of Highway Engineering by L.R.Kadiyali, 1984.

2.2.2 Present Serviceability Index (PSI) Method

One of the major contributions of AASHO Road Test was the develpment

of a rating system involving the measurement of pavement deformation,

riding quality and the extent of cracking and patching. The rating

is known by the term present serviceability Index (PSI) and is

probably the most widely used pavement rating measure is existence

today. The following equations give the value of PSI for flexible andrigid pavements:Flexible Pavements

PSI = 5.03 - 1.91 log(1 + SV) - 1.38(RD)' - 0.01 {C + P

Rigid Pavements :

PSI = 5.41 - 1.78 log(l + SV) - 0.09 {C + PIn the above equations:

PSI = Present Serviceability Index

18

Page 29: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

~ = Slove variance over a 22.5 cm length, giving an index of thelongitudinal profile

RD = Rut depth under a 1.2 m straight edge

C = Percent of total area showing distress in terms of crackedarea

P = Percent of total area showing distress in terms of patchedarea.

In the AASHO Test, the longitudinal profile was monitored by theCROLE profilometer.

2.3 RlJUGHNESS MEASUREMENTS:

The riding quality of a pavement is determined to a large extent by

its structural adequacy , the traffic load repetitions it has been

subjected to, the specifications adopted for the surfacing initiallyand the maintenance inputs. Hence a measure 0 f the pavemen tPerformance can be obtained by monitoring its roughness.

2.3.1 Method for Measurement of Roughness:

The equipment called bump-integrator for measuring the roughness ofthe pavement is shown in Figure 2.1. It consists essentially of asingle - wheeled trailor, comprising rectangular chassis within which

a pneumatic - tyred wheel is mounted, the load and tyre size being ofa standard type. The wheel, enclosed by a mudguard, support thechassis through two single-leaf springs, one on each side of the

.heel. The springs are anchored to the front end and shackled to the

rear end of the chassis through ball - bearing fixtures.

19

Page 30: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

The process involved is as follows:

I. At first, the distance the bump-integrator has travelled iscalculated. This is achieved by multiplying the number in the

wheel revolutions column by the known distance the wheel travelsin one revolution.

2. Now, having worked out the distance travelled and knowing the

time taken, the speed of the integrator is calculated.

Speed =Distance

Time

Figure-2.1 : Diagraaaatic Arrange.ent of Apparatus

Source : Bump Integrator Measure.ents in Routine Assess.ent ofHighway .aintenance needs by W.G. Keir.

20

Page 31: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

3. The irregularity index is calculated as follows:

Integrator counter value x number ofwheel revolutions in one mile-------------------------------------

Recorded number of wheel revolutions

4. There is a correction made on the basis that recorded values

decrease by 2 percent for each mile per hour above 20 mph

(32 km/hr) and increase similarly below 20 mph (32 km/hr).

Normally, three runs are averaged to produce an overall 'r'

irregularity index value which is rounded up and down and quotedas a whole number.

2.4 METHOD FOR MEASURING DEFLECTION VALUE

The Benkelman Deflection Beam is shown in Figure 2.2 is used formeasuring deflection value.

deflection is as follows:The procedure of measuring the rebound

1. Ten points are selected along the outer wheel path for each lane.

2. The rear dual wheel assembly of the truck is brought near the

marked point and the Probe of the beam is inserted between the

dual wheels so that the top rests on the road where the

deflection is to be measured. The dual wheels are centred over

the marked point. A dual - type truck axle with a standard load(18 KIP) is used for the test.

21

Page 32: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

,r

SEE VIEW-.- BATTER'" ."

"'OJUSTASLfII("'R LEG

F:lONl' lfGS

''''1.1. aeARING 'IVOT

Figure-2.2 : Benkelaan Beaa

Source : Asphalt overlays for Highway and street Rehabilitation, theAsphalt Institute, Manual Series No.17 (MS-17) June 1983Edition)

22

Page 33: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

o 2-44mfa.':Jb l'22m(4ft}c O,30m(1tt)

d 0:91';'(J't)e.. ~:..~~lm ,2fO

effective." ..lenoth" t;74m(2lt;

-', ~.;..~

I a h~,bd =i---c-, . --"-.e -'----I: + .: + . : I. I In-, Erev~t;an\ f\ I --'1'1 .' I r-'------,--,

Shoe \ . I ./ / " . ./ ..L I .1 .l Dimensions~~~ -7"m~'7,;; \<' . 7'\rnZialpos.ltion Initiol ~slUon ~ Twl,n RecOrding . I

8 r wtree15NT • Pi t dIal' Base Sing e~he~~~i" . .ec\m ~nQmiC: test" : ~ • \>'0 '7t gaUr 'reme 'oot,::"'~&~~~[~~7~W U- \ LI . ~I. Ettectlve lenoth of beam I

Figure-2.3 Diagraaaatic Representation of the Deflection Bea.(Benke IIIan Bel1lllType)

Source TRRL Laboratory Report 935-1980.

23

Page 34: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

3. The dial gauge reading noted initially in the position describedin step 2 above.

4. The truck is driven forward at a slow speed and dial gauge

readings are taken when the truck stops at 2.7 m and 9m form themeasuring point.

5. Pavement temperature is recorded.

6. The final and the intermediate dial readings are subtract fromthe initial reading.

2.4.1 Analysis of Deflection Data

The first step in analysing deflection survey data, after corrections

for temperature etc. is to make a simple check on the variability ofmeasurements. The recommended procedure as follows:

1. The mean of ten consecutive values (1.a km of road if 100 mspacing is adopted) are calculated.

2. The mean value plus and minus one third of the mean provide therange within which the ten readings should lie;

3. Deflections which differ more than one third from the mean areconsidered as out of the range.

Deflections are divided into homogeneous groups fixing most

appropriate chainage limits and based on data in each section, "mean

plus standard deviation value" is computed and used for the

computation of the overlay thickness. Through these procedure

sections requiring deferent overlay thicknesses are separated fromsections where reconstruction is needed.

24

Page 35: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

I '

70

II

-I

,I

i'';

II

60'-50 mm

I-J'0'75 t!"m (30)( 10 in l

1.2:i

.' ..

40 ~OMeasUred' C:eflectlon

;t_ .... _

iII .

0.7.5

The Thickness of Bituminous Premix Overlay Required toReduce the Deflection of a Payment to Three DesignatedValues.

0.000 '0.0:1:0 0.040 0.060 0.080 0.100 0,120 C,UO 0.160 0.180AnD,INCHES

TRRL Laboratory Report 935-1980.

" RRD. MM0.50 "1.00 1,50 '00 . 2.50 _~.99'" " I I

'" EAL,'SO " 10,000,000• '""~ :llxj" 12

$,000,000~~~~mO~"" 10i~. '"",0 '" • 2.000,000.u ~~!:;"'200 • U

1;000.000~< ~u% '":Ee;'" ., 500,000~<

>~ 12S200,000~o

" 100 100,000~>

" 50,000020,000" 10.000

" s.ooo

Asphalt overlays for Highway and Street Rehabilitation. TheAsphalt institute Manual Series No.17 (MS-17) June, 1983.

25

20

a00

00

Figure-2.4

..--.

Source

Figure-2.5: Asphalt Concrete over lay thickness required to reducepayment deflections from a measured to a designdeflection value (rebound test).

1(Xl,

i

--'/:i ;,

Source

2

4

6

a

' .•'"o"C•>ox

'E•"Co•gE

""0'

Page 36: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

2.5 MAINTENANCE ACTIVITIES :

2.5.1 Routine Maintenance - Normal repair and maintenance of highway

facility as near to the originally constructed condition but not

inducing better improvement work. Routine maintenance comprisesi. Surface maintenance:

Heavy grading

Light grading

Soil aggregate surface patching

Skin patching of paved road

Minor repair of asphalt pavement

Concrete joint sealing

Road - way cleaning etc.

ii. Shoulders, side road, approaches and median strips maintenance:Shoulder grass cutting

Shoulder patching

Shoulder light grading etc.

Repairs to median, approaches etc.

iii. Drainage system maintenance:

Drainage cleaning

Culvert cleaning and repairing

iv. Road side maintenance:

Side slope repairing

Road side grass cutting

Maintenance to road side development etc.

26

Page 37: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

v. Traffic service operation maintenance:

Traffic marking maintenance

Maintenance of road sign, guide posts, guide rails, guardrails, right of.way posts and km posts.

Maintenance of traffic signals and road lighting.

vi. Maintenance and repair of structures:

Bridge maintenance

Box and pipe culvert maintenance

Miscellaneous structures (retaining wall, tunnels etc.)

2.5.2 Special Maintenance

Special maintenance of the highway facilities as near as possible to

the originally constructed condition usually the same as routine work

but involved more work at greater cost.

Asphalt seal - coating (more than 600 m2/km)

Asphalt surface levelling or redressing

Surface regravelling (more than 400 m2/km)

Major repair of shoulders, side road approaches and median stripsMajor side slope repairing

Dust palliatives

2.5.3 Betterments:

Though it does not fall under maintenance, it is sometimes done fromthe maintenance funds. It includes improvement and repair works to

highway facilities to a condition better than originally constructede.g.

Improvement of geometry

Pavement and shoulder widening and improvement

27

Page 38: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

Base stabilization

Improvement of surface

Replacement and extension of minor structures

Construction of minor retaining walls

Erosion protection and paving of ditches

Provision of rest areas, bus stops, and shelters

Installation of traffic signal, road lighting, road signs, guideposts, right of way posts and km posts

Planning and landscaping.

2.5.4 Rehabilitative Maintenance:

The condition of some roads will be such that simple resealing or

overlaying will only be temporary expedients to hold the roadtogether for a short time. In these cases where roads havedeteriorated so badly that complete failure is in evidence, the only

solution is to completely rehabilitate the road pavement. This is an

expensive operation and it is always preferable to carry out regular

preventative periodic maintenance than to let a road deteriorateuntil it needs rehabilitation.

At the present time in Bangladesh a high percentage of the major road

network needs rehabilitation before a proper preventative maintenance,system can be implemented. This will require a large injection offunds over a limited period of time to bring the roads back upto an

acceptable standard. Rehabilitative maintenance work should becarried out in strict priority order.

28

Page 39: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

When carrying out rehabilitation work maximum use should be made of

the materials from the old road pavement. Rehabilitation work isnormally be done by contract.

Areas of road requiring rehabilitative maintenance will normally be

clearly shown from the road condition survey forms, and approximate

quantities and costings may be obtained. For detailed estimating and

design of the rehabilitative maintenance works some additional

testing (e.g. subgrade CBR) may be required.

2.5.5 E.ergency Works:

Some emergency work wi11 always occur but all too often so called

eaergency works may be traced to faulty construction or lack of

preventative maintenance. As emergency work may fluctuate widely from

year to year depending on the weather conditions it is necessary to

allow emergency funds to be carried over from one financial year to

the next so that only the average emergency budget over a period ofyears is considered.

There are no means of assessing true emergency works from the roadcondition survey forms. Historical data will show that some roadsare more prone to emergency works than other roads. However, ifareas marked critical on the road condition survey forms are

neglected they will soon become so called emergency repair. Table-2.2

below shows Asphalt Pavement Rating Form.

29

Page 40: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

TABLE-2.2

ASPHALT PAVEMENT RATING FORM

STREET OR ROUTE

LENGTH OF PROJECT

PAVEMENT TYPE

CITY OR COUNTRY

WIDTH

DATE

.(Note : A rating of 'a' indicates defect does not occur)Defects RatingTransverse Cracks .Longitudinal Cracks ...........•................Alligator Cracks ..•....•.......................Shrinkage Cracks ..•.....•......................Rutting .............•..........•..•............Corrugations .Raveling ...............••...............•.•.•..Shoving or Pushing ..............•.........•....Pot Holes .............•.........•...........••.Excess Asphal t .......................•.......•.Polished Aggregate ......•............•.......••Deficient Drainage •................•........•••Overall Riding Quality (0 is excellent;10 is very poor) .........................•....•

0-50-50-10

. 0-50-100-50-50-100-100-100-50-10

0-10

Sum of DefectsCondition Rating = 100 Sum of Defects= 100 - -------

Condition Rating =

-Asphalt pavement rating form.

RECONSTRUCTION OVERLAY ROUTINEMAINTENANCE

20o... .1///////////////////////

40 60 80 100Figure-2.6: Condition Rating as a general indicator of type

maintenance.

Source : Asphalt overlays for Highway and Street Rehabilitation. TheAsphalt Institute, Manual Series No. 17 (MS-17) June, 1983, Edition).

30

Page 41: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

CHAPTER - 3EVALUATION TECHNIQUE FOR MAINTENANCE

3.1 EVALUATION OF ROAD MAINTENANCE NEEDS

The first step in the planning of maintenance of roads, streets and

llghways is the evaluation of existing pavements in terms of physical

condi tion, structural capaci ty, roughness etc. For this purpose,

condition surveys may be undertaken for the visual assessment of the

pavement. Such surveys would cover not only the type but also the

aagnitude of the distress and its location.

Apart from visual surveys, pavement surface evaluation based on

riding quality (i.e. road roughness) and skid resistance should also

from the basis for taking maintenance decisions.

Necessary information about routine maintenance needs will be readily

available as the maintenance staff are expected to be continuously

in touch with the physical condition of the road. However, for

periodic renewal requi rements and a long-term maintenance strategy,

condi tion surveys carried out at a fixed frequency are a must. At

least two condition surveys are conducted on each stretch of road

eyery year, one before and other after the monsoon.,

Based on the condition evaluation, the causes for the various defects

observed should be examined and a decision taken whether to initiate

a particular maintenance activity.

Where distress on the pavement has reached a stage where pot-holes

exist and deter the smooth operation of vehicles, the situation

should be rectified immediately. For other defects like cracking,

31

Page 42: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

ravelling etc. the optional strategy should be determined having

regard to the various factors involved including the availability of

financial resources, and a decision taken whether to go in fortemporary measures like seal/renewal coat or tostrengthen/reconstruct the pavement.

3.2 EVALUATION TECHNIQUES

For maintenance purposes, roads are generally classifiedtypes:

1. Paved road.

2. Unpaved road.

into two

3.2.1 Maintenance of Paved Roads:

'Before going for actual maintenance activities, the factor involved

in maintenance requirements and guides for the maintenance activitiesmust be assessed.

Inadequacies in roads in general are related to a number of factors

which include increase in traffic volume, inadequate initial design

in relation to traffic volume, use of substandard or inferior quality

materials. Poor construction quality control and poor quality of

routine and special maintenance operations due especially to budgetconstraints.

For assessment of road maintenance works should be the factors asoutlined below to be investigated:

1. Road Inventory: It includes evaluation of pavement conditions,

shoulders, major and minor structures, drainage, stability ofslopes, ridii adequacy, gradients etc.

32

Page 43: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

Z. Pavement Inventory : It consists of identifying and evaluating

any kind of "Pavement distress manifestation" (cracking,

deformations, defects, joint deficiencies) for flexible and riidpavements.

3. Traffic study, projections, potential development schemes in

agriculture, mining, forestry, industry fishing etc.

•. Present serviceability Index (PSI) concept.

1. lIoadInventory :

The design of many old roads are based on anticipated traffic volumes

which are less than actual traffic volumes. If a geometric

eyaluation indicates narrowness of pavements to accommodate actual

traffic, if the curves are too sharp, if available sight distance is

too short, or if the pavements surface is distorted, these

deficiencies should be rectified immediately. In such cases,

bricksoled asphalt pavement can be used to widen pavement, to improve

road alignment, to re-establish cross-section and improve shouldersfor any type of existing pavement structure.

I.provements to the cross-section of existing pavement sho~ld conform

to standards for median widths, safety features, cross slopes,

shoulder slopes, and ditches or other drainage features.

2. Pavement Inventory:

Pavement inventories for the purpose of maintenance include measures

of skid resistance, riding quality, structural capacity and surfacedistress. "Surface distress" includes ravelling, cracking and

channeling (rutting) or other forms of asphalt pavement distortions;

in portland cement concrete pavements it includes cracking and

33

Page 44: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

spalling, pumping and faulting at joints. Evaluating pavement

condition involves assessing the current state of these distresses

and an estimation of the time when the distresses might reach a

critical or terminal level of serviceability - a level in which

maintenance is urgently needed.

Evaluation techniques for asphalt pavements fall into two general

categories. The first, the deflection procedure in which pavement

deflection are measured and analyzed in relation to traffic. Thisprocedure has the advantage of directly measuring the responses ofthe in-place pavement structure to traffic loading. The secondcalled the effective thickness procedure, uses relationships between

subgrade strength, pavement structure and traffic loading. Convenient

means of classifying the surface condition at a deflection test point

are detailed below:

Classification of Road Surface Condition-----------------------------------------------------------------Deformation under a 2-meterlong straight - edge

Degree of cracking (visiblecracks)

-----------------------------------------------------------------Classification:Index :

Deformation : Classification : Crack length/: Index : unit area

-----------------------------------------------------------------01 Less than 10 mm C1 NilO2 10 mm to 14 mm C2 Not greater than 1 m/m203 15 mm to 19 mm C3 Greater than 1 m/m2

not greater , , 2 m/m204 20 mm to 25 mm C4 Greater than 2 m/m2

not , , , , 5 m/m205 Greater than 25 mm C5 Greater than 5 m/m2

(revelling & pothol-ing imminent, immed-iate maintenancerequired)-----------------------------------------------------------------

Source: TRRL Laboratory Report 935 - 1980.

34

Page 45: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

Deflection values are most useful when they are accompanied by other

indicators of pavement performance. Measurement of rut depths,

cracking in the wheelpaths and crack depths are simple measures of

pavement condition that can easily be made at the same time when

deflection surveys are being carried out. Deformation or rut depth in

the wheelpaths can be measured by placing a two-meter straightedge

transversely to the road over the deflection test point, any

deformation below the straightedge being measured with a calibratededge.

An assessment of the amount of cracking at a deflection test point

can be made by measuring the linear cracking within a one-meter

square frame. It is done by placing the frame over the deflection

test point with one side parallel to the edge of the road such that

it encloses the maximum length of cracking. The cracks can be

'Chalked in' and measured with a flexible tape.

The measurement of pavement surface deflection under a standard

wheel load is a common practice in many countries. In this regard,

the best known instrument for deflection measurement is the Benkelman

Beam which measures the deflection, at creep speed, between the tyres

of a dual-type truck axle with a standard load (18 KIP). About 250

tests/day over a distance of 5 km can be taken and tolerable criteria

.ay be developed for various pavement types in different regions.

Attempts to automate the Benkelman Beam have been made successfully

in the French "Deflectograph". In this case, a short beam is

.echanically moved as the carrying truck moves forward. Both wheel

paths are tested every 4 m at 2 km/hr with an output of 16 lane

35

Page 46: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

km/day. Some degree of sensitivity is sacrificed as against a faster

output.

There are also other instrument like 'Curviameter', 'Dynafleet',

'Pavement Profiter' or 'Road-Rater' for deflection tests.

Surface deflection measurements do not provide any measure of

absolute properties of pavement, but can be related to the

composition and quality of pavement layers, subgrade properties and

axle load repetitions.

3. Traffic Study:'

Traffic analysis are made based on existing and anticipated future

development of an area. While considering the design and

construction of a new road or upgrading an existing one, it is a

commonpractice to undertake traffic volume count and classification

surveys at suitable times and intervals in order to assess as

accurately as possible the Average Annual Daily Traffic (AADT). In

such a survey, the class of vehicle is also identified and records

are tabulated in standard forms. Projections of future traffic

growth are made, based on past records when available, and assessment

are made of generated and developmental traffic. These values are

used in commondesign procedures. But once the road is constructed

and opened to traffic, the monitoring of traffic usage is often a

bapazard undertaking and sometimes neglected altogether despite the

fact that the traffic density is a fundamental factor in proper

assessment of pavement performances and the timing of maintenances.

Along with traffic usage, the vehicles mix and axle-loadings should

also be monitored as overloading of vehicles is a serious problem in

36

Page 47: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

a developing country like ours. Implementation of a procedure to

statistically monitor the loadings of heavy good vehicles would

provide a useful, if not essential, input in a totally integrated

highway maintenance programme.

4. Present Serviceability Index (PSI) Canadian Good Road Association(CGRA)Concept :

The present serviceability concept describes present serviceability

as the ability of a specific section of pavement to provide a smooth

and comfortable ride at that particular time of rating. The ability

can be quantified by a value called Present Serviceability Index

(PSI) .

Generally, pavements do not become totally impossible but they

frequently show distress either functionally, where patching and/or

resurfacing can overcome the discomfort of the road user, or

structural failure where the pavement is -no longer capable of

sustaining traffic loads and remedial measures require overlaying or

reconstruction. The causes of distress or failure of the pavement

may be induced by traffic - high gross loads (General over

stressing), high tyre loads (local over stressing), high repeated

loading (fatique effects) and may also be due to poor design or

construction or maintenance.

The PSI of a section of pavement on a road is defined as the mean

opinion of members of a rating panel on the present ability of that

pavement in its present condition, and without regard to the

geometries of the road section, to serve safely, comfortably and

conveniently, high-speed, high volume mixed automobile and truck

37

Page 48: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

traffic. The panel is composed of a small number (generally five) of

persons. The opinion of the panel members is recorded on a linear

scale wi th a range of 0.0 to 10.0 representing extremely poor to

extremely good pavement surfaces respectively.

lhe PSI generally indicates how well the section of pavement is

serving the traffic using it at the time of rating.

riding quality as measured by PSI, is as follows:

PSI Riding quality

0-2 Very poor2-4 Poor4-6 Fair6-8 Good8-10 Very good

The relative

It has been shown that new pavement surfaces have PSI values of

between 8.0 and 9.5. Experience has also indicated that pavements

are on the average, resurfaced or reconstructed at a PSI value of

4.5. Thus, the terminal PSI value of 4.5 can be used to define the

life of a pavement.

3.2.2 Maintenance of Unpaved Roads

Normally there are two types of unpaved roads, viz:

a. Earthen Roads which are constructed using natural soil found on

the route.

b. Gravel Roads which are surfaced with a layer of improved material

stronger than natural soil.

With proper maintenance an unpaved road can provide a good level of

service for traff ic volumes upto several hundred vehicles per day.

38

Page 49: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

The purpose of maintenance is to provide a smooth passage for

vehicles by repairing damages caused by a combination of the weatherand the traffic.

The first objective of maintenance is to keep the road in such acondition that it sheds water quickly.

,If the road does not shed

water, the surface will become soft and ruts and pot holes will

quickly appear and make earthen roads impossible.

Maintenance is needed to restore a good camber on the road to enablewater to drain off quickly. This is best achieved by regular

grading. On gravel roads, grading is needed to restore gravel from

the shoulders which has been lost from the road surface and to remove

the deep pot holes and corrugations.

In dry seasons, dragging the road surface may be effective in

providing smooth passage for vehicles and in stopping the formation

of corrugations. This may be carried out with a motor grader or with

a drag towed by a tractor or other vehicle. The object is to remove

loose material from the road surface.

Soft spots on the road may need to be patched. Patching can also be

used for general repairs to the road surface when equipment is notavailable.

As the surface of gravel road wears away, new gravel must be added

before rapid deterioration of the surface starts. Regravelling mayalso be used to correct other defects when these become severe and

may also be used to improve an engineered earth road to gravel road.

39

Page 50: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

I CHAPrER-4

SYMPrOMS, CAUSES AND TREATMENT OF ROAD FAILURES

The types of defects in bituminous surfacing are grouped under four

categories as follows:

4.1 CRACK!NG

Cracking takes many forms. Simple crack filling may be the right

treatment in some cases. In others, complete removal of the affected

area and the installation of drainage may be necessary before

effective repairs can be carried out. Types of distresses in

asphaltic road pavements due to cracking, their symptoms, probable

causes and possible remedial treatment are summarized below

Types ofdistress

1. Hair -linecrack

2. Alli-gatorcracks

3. Reflec-tioncracks

4. Edgecracks

Symptoms

Short and finecracks at closeintervals onthe surface.

Interconnectedcracks forminga series ofsmall blocks.

Cracks inasphalt over-lays whichreflect thecrack patternin the pavementstructureunderneath.Crack near andparallel topavement edge.

40

Probable causes

Insufficient bitu-men excessivefilter or impropercompaction.

Excessi ve deflec-tion of surfaceover unstablesubgrade.

Due to joints andcracks in thepavement layerunderneath.

Lack of lateral(shoulders)supportand settlement ofunderlyingmaterials.

Possible typeof treatment

The treatment willdepend on whetherpavement is struc-turally sound, orunsound. Where thepavement is struc-turally sound,thecracks should befilled with a lowviscosity binder ora slurry seal orfog seal dependingon the width ofcracks Unsoundcracked pavementswill need strength-ening or rehabilit-ation treatment.

Page 51: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

5. Shrin-kagecracks

4.2 DISTORTION

Interconnectedcracks forminga series oflarge blocks,with sharpcorners andangles.

Volume'change inthe asphalt mixor in the baseor subgrade.

Pavement distortion is any change of the pavement surface from its

original shape. It usually is caused by such things as too little

co.paction of the pavement courses, too many fines in surface

mixtures, too much asphalt, swelling of underlying courses, or

settlements.

Types of distresses in asphaltic road pavements due to distortion,

their symptoms, probable causes and possible remedial treatment are

suamarized below:

Types ofdistress

Symptoms Causes Possible typesof treatment

1. Rutting Longitudinaldepressionwhich developsin the wheeltracks.

Consolidation orlateral movementof underlyingcourses or dis-placement in as-phalt surfacedue to traffic.

Removal of thesurface lalyer inthe affected areaand replacementwith freshmaterial.

2. Corrug-ations

3. Shallowdepres-sion

Formation ofregular un-dulations.

Localizedshallowdepressions.

41

Lack of stabilityof the asphaltmix.

Presence of in-adequatelycompactedpockets.

Scarification andrelaying of surf-acing,or cuttingof high spots andfilling of lowspots.

Filling with premixmaterials.

Page 52: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

4. Settle- Upward dis- Expansion of ice Deep patching shouldment placement due in the lower be done for perma-and to Sub-grade courses of the nent repair.upheaval swelling. pavement or the

subgrade.

5. Utility Due to cut Lac of adequatedepres- for utility compaction ofsians. installation backfil material.

or repair.

4.3 DISINTEGRATIONDisintegration is the breaking up of a pavement into small, loosefragments. This includes the dislodging of aggregate particles. If

not stopped in its early stages, it can progress until the pavementrequires complete rebuilding. Types of distresses, symptoms,

probable causes and possible types of treatment for disintegrationare summarized below:

Types ofdistress

Symptoms I Probable Causes Possible type oftreatment

Lack of compactionduring construct-tion, too littleasphalt, disinte-grating aggregate

1. Potholes

2. Ravelling

3. Edge,breaking

Bowl-shapedholes fromlocali zed pave-ment disintegra-tion.

Progressive se-paration ofaggregate part-cles in a pave-ment, from sur-face downward orfrom the edgesinward.Irregular break-age of pavementedges.

42

Limited quantityof asphalt or ex-cessively thinsurface or toomany or too fewfines or poordrainage.

Water infiltrat-tion,poor lateralsupport fromshoulders, in-adequate strengthof pavement edgesetc.

Filling potholes withpremix material, orpanetration patching.

Application of cut-back covered withcoarses and orsllurry seal orpremix renewal coat.

Cutting the affectedarea to regular sec-tions and rebuildingwith simultaneousattention paid to theproper constructionof shoulders.

Page 53: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

4.4 SKID HAZARD

Few dry pavements are slippery. But there are a number of things

than can make a pavement slippery when wet. The smooth pavement

condition usually is the result of a film of asphalt on the surface,

a polished aggregate in the surface course. The object of a skid

hazard improvement is to restore the pavement surface to a condition

where water can flow around most of the surface aggregate particles,

leaving contact between tire and aggregate. Types of distresses,

sFlptoms, causes and remedial treatment for skid hazard discussed

below:

Types of Symptoms Probable CausesI

Possible types ofdistress treatment

1. Bleeding Upward movement Excess of asphalt Sand blinding, openor of asphalt in in one or more graded premix liquidflushing an asphalt pavement layers. seal coat,burning ofasphalt excess binder,

removal of affectedarea.

2. Polished Aggregate not Characteristics Application of liqu-aggregate covered by of some rocks id seal, fog seal or

asphalt. (Limestone) slurry seal depend-ing on the extent ofdamage.

43

Page 54: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

PHOTOGRAPH SHOWING SOME CASE STUDIES

,

Figure-4.1 Pot holes on road at Raapura Road, Dhaka

figure-4.2 Water Stagnant on roads near Mohakhali, Dhaka

44

Page 55: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

Figure-4.3 Alligator Cracking or Map Cracking onroads at Tejgaon Industrial Area, Dhaka.

, Figure-4.4 Shallow Depression on Road side near New Market, Dhaka

45

Page 56: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

4.5 MAINTENANCE OPERATIONSIn Chapter-3 , a discussion has been made about types of failures,

evaluation for maintenance etc. It is convenient to categorize the

practices in terms of the following types of classes of highwaymaintenance, the maintenance of :

1. Road way surfaces;

2. Shoulders and approaches;

3. Road sides;

4. Drainage structures.

4.5.1 Maintenance of Road Way Surfaces

Patching:

When road failure is due to a poor mixture or gradation of materials

it is usually necessary to remove the unsuitable material and

replace it with suitable materials of the proper gradation.

Patching may consist simply of an application of a thin coat of

bituminous material to an area where cracking or ravelling appears

and spreading a coarse mineral aggregate over the affected area.

Care must be exercised in the application of the proper amount of

bituminous material in order to prevent bleeding, with the resultingslipperiness of the repaired surface.

For permanent repair of a deep patch the procedure is as describedbelow :

a. Remove the surface and base as deep as necessary to reach firm

support, extending at least a foot into good pavement outside the

cracked area. Some of the subgrade will also have to be removed.

46

Page 57: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

Make the cut square or rectangular with faces straight andvertical.

b. If water is a cause of the failure, install drainage.

c. Apply a tack coat to the vertical faces.

d. Backfill the hole with a graded hot asphalt plant mix. If the

asphalt mixture is not available, make backfill with a goodgranular base material.

e. Compact in layers if the hole is more than 6 inch deep by usinghand rammers or a small vibrating hammer.

f. Full depth asphalt mix placed directly, needs no prime.

g. If granular base is used it should be primed.

h. Use a straightedge or a straight line to check the quality. andthe alignment of the patch.

47

Page 58: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

Materials :

The materials used for patching will depend on those present in the

existing road. Recommended materials are given in the Table-4.1.

In Figure-4.5 steps for repairing a Pothole is given.

(1) Untreated Pot hole

~~. "o .•.q:.o',4:D.;4,: .••.. 9. , .. ;'O',o".-d .•••• P. <t:J:~ .• a:: ..Q .•4.:•....•• ;o::~ ..r7:...••'..•: ~ '0' .,:".

(2) Surface and base removedto firm support

(31 Tack coat applied • (4) Full depth asphalt mixtureplaced and being compacted

. ",'

(5) Finished patch compacted to levelof surrounding pavement

Figure-4.5 : Steps for repairing a Pothole.Source: Road Maintenance Handbook Volume-I, United Nations

Economic Commission for Africa

48

Page 59: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

REPAIRING OF POTHOLES

Figure-4.6 Repairing of Pothole by Dhaka Municipal Corporationon New Airport Road, Dhaka.

49

Page 60: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

TABLE-4.1

RECOMMENDATIONS FOR PATCHING MATERIAL

Layer

Base

Existing Material

GravelRepair Material

Gravel of at least as goodquality as the original.

plusor

Cement stabilised,bitumenstabilised,crushed rock orbitumen macadam.

Gradedfines,premix

crushed rocksoil cementmacadam.

Surface Surface dressing( New, thin )

Surface dressings whichhave built up to severalcentimeters thickness andpremix surfaces.

Binder andchippings

Premix macadam plus sealof binder and chippings.

Source: Overseas Role Note 2, TRRL 1981.

Specifications for suitable gravels, which may be used for patchinghave been given in the Appendix. These are suitable forstabilisation with 5-10 percent of cement. If crushed rock is used

for the patching material, gradings are shown in Appendix.

4.5.2 Maintenance of Shoulders:

The importance of properly maintaining the shoulders or berms is

realized when their intended functions are understood. The mosti.portant functions of shoulders are to provide space for vehicles

leaving the travelled surface of the roadway, to facilitate running

off of surface water from the pavement to the nearby drainage ditches

and to support the edge of pavement or road surface. Shouldersshould be kept stable, smooth, and with proper elevation and cross

slope. The most common defect is depressions in the shoulders along

the edge of the pavement which defeat the important functions of the

50

Page 61: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

shoulders. It creates a traffic hazard, collects and holds dirty

water which may be splashed upon pedestrians. Most shoulders on

existing highways in Bangladesh are of natural or untreated soil and

the maintenance organization must make it mandatory to properly

maintain the shoulder in its natural condition or to improve it as

the volume of traffic increases or when the funds permit.

A well-graded gravel shoulder will provide a satisfactory all-weather

shoulder for light traffic; the maintenance of shoulders of this type

will follow a pattern similar to that of soil aggregate surfaces.

This will include the dragging and blading of the shoulder surface

for the proper slope and the filling of any ruts. It may be

necessary to replace worn out and lost materials at periodic

intervals. This work can be done with a light motor grader.

The condition of the shoulder for all paved roads should also be

examined and rated along with the pavement condition. The shoulder

may be of bituminous concrete, bituminous seal, gravel turfed.

51

Page 62: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

Rating for shoulder may be done as per proforma given below:

Rating Bituminousconcrete

Bituminousseal

Gravel Grass

Very Smooth; Smooth; Well trimmed Full coverGood 1 No patches No patches and compact mowed to pave-

ment level.

Good 2 Smooth; Minor Minor rutting 25-50 mm buildFew patches patching confined to up above pave-

outside ment level.shoulder.

Fair 3 Some potholes Some pot holes Minor cross Bare gap at(Less than minor edge rutting by edge of10% by area) rutting erosion. Loose bitumen.

stone averagedia 14 mm.

Poor 4 Pot holed Pot holed over Longitudinal Unmowed buildover 30% by 30% by area rutting by up over 30 mmarea. Iunrepaired) erosion at edge of solid so as(unrepaired) of bitumen to pond water

(depth of rut adjacent to14 mm). edge of

bitumen.

4.5.3 Maintenance of Drainage Structures:

Proper drainage maintenance requires that all structures and

appurtenances pertaining to removal of water from the highway have to

be kept in good working condition so as to provide free and

unobstructed flow. Generally, maintenance operation consist of

those relating to:

i. surface drainage;

i1. ditches and

iii.subsurface drainage, storm sewers, culverts etc.

Water have a harmful effect on shoulders, slopes, ditches and other

features. High water velocities can cause erosion which, when

52

Page 63: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

\

severe, can lead to the road being cut. Alternatively; low

velocities in drainage facilities can lead to silt being deposited

which, in turn, can lead to a blockage, blockage often result in

further erosion.

Good surface drainage is maintained by having the pavement surface as

water-proof as possible and by having such crown and surface

smoothness that the water will flow freely to the road edge and on to

the shoulder.

Similarly, shoulders are maintained flush with the pavement and

smooth enough to provide for free flow of water away from the edge of

the road and across the shoulder to the side ditch in out sections or

down slope of fill sections.

However, proper highway design can contribute

maintenance difficulties due to inadequate drainage.

to eliminate

For example, if

pavement and bases or sub-bases have to be constructed in a trench, a

proper subgrade drainage either by constructing shoulders of porous

materials or by placing pipe drains through the shoulders can

contribute to ease of maintenance.

4.6 THICKNESS OF OVERLAYOverlay thickness for flexible highway pavements are determined by

means of deflection measurements. Measurements are generally made

using the Benkelman Beam although large scale measurements can be

made using a device such as

53

Page 64: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

i. California continuous deflectometer or

ii. Dynaflect.

Using the Benkelman Beam shown in Figure 9 pavement deflections are

obtained for the project under study by testing the outer wheel-path

at a minimum of ten locations selected within each section of equal,

or nearly equal. The random sampling technique is used to select the

test locations. A Representative Rebound Deflection (RRD) value is

the mean of measured rebound deflections, which have been adjusted

for temperature and most critical period of the year, plus two

standard deviations. This value encompasses approximately 97 percent

of all deflections measured.

OVERLAYSThere is an important distinction between 'maintenance' and other

pavement rehabilitation techniques, including 'overlays'.

less than 25 mm (1 in) thick, for example, are

Overlays,

considered

maintenance, and overlays of greater thickness are considered capital

improvements. The purpose of overlay design is to determine the

appropriate thickness of either an asphalt or granular layer which,

when placed on an existing pavement, will overcome the strength

deficiencies of the pavement and retain its own structural integrity

throughout the design period.

BASIC PRINCIPLESThe pavement deflection caused by a standard axle load is an

indication of the rate at which permanent pavement deformation will

occur under traffic. As the functional adequacy of the pavement is

54

Page 65: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

dependent, in part, on this permanent deformation, a relationship

between the cumulative number of standard axle loads and measured

surface deflection can be developed. Using this relationship a

design deflection can be determined for any particular trafficloading.

The Representative Rebound Deflection equals ( x + 2s)

fc where x = the arithmetic mean of the individual values that

have been adjusted for temperature.

s = standard deviation.

f = temperature adjustment factor.

c = critical period adjustment factor.

Standard deviation, s = .f ------n - 1

If all deflection measurements are made at the same temperature then

the adjustment can be applied to the mean deflection value.

55

Page 66: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

CHAPTER-5ROAD MAINTENANCE MANAGEMENT

5.1 INTRODUCTION

The key to good management is careful planning and programming of

the work to e done. The main objectives of maintenance management

are the allocation of available maintenance resources according to

actual needs and priorities, increasing the productivity, the

development of uniform ways for doing the work, and the monitoringand evaluation of the outputs for the continuous improvement of thesystem.

5.2 MAINTENANCE MANPOWERMaintenance of road in developing countries like Bangladesh is labour

intensive and therefore, the output depends upon "labour

productivity". The operations require use of skilled and unskilled

workers. Right type of persons should be employed for every type of

work. While female labour can be good transporters for small loads,

only skilled male laboures should be employed for work like

bituminous construction. Regular training regarding works to be

carried out, use of tools, plant and materials, etc. should bei.ported to those workers.

5.3 MAINTENANCE MANPOWER IN BANGLADESHIn Bangladesh Roads and Highways Department maintains the large

portion of the roads and highways. Roads and Highways Department has

divided Bangladesh into ten road circles, consisting of two or more

56

Page 67: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

road divisions. Each Road Division has a maintenance gangconsisting of work assistants and coolies. On roads where pothole

repair is needed they take the necessary repairing materials on truck

and repair the potholes. They cannot use roller everywhere because

use of roller is not economic for small repairs and at far distances.

Road maintenance staff for a typical road division under Roads andHighways Department is given in the Table 5.1.

TABLE-5.1

ROAD MAINTENANCE STAFF FOR A TYPICAL ROAD DIVISIONUNDER ROADS AND HIGHWAYS DEPARTMENT

Sl. Name of the Post No. of Post TotalNo. holder1. Professional:

i. Executive Engineer 1i i. Sub-Divisional Engineer 3

iii. Assistant Engineer 1 52. Technical Staff :

i. Sectional Officer 11 113. Skilled Technicians

i. "ark Assistant 69

ii. Jeep driver 4

iii. Truck driver 5iv. Roller driver 7

v. Mechanic 8

vi. Assistant Mechanic 11vii. Mason 8

vii i.Carpenter 3 115

57

Page 68: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

51.No.

Name of the Post No. of Postholder

Total

4- Non-Skilled Labourers

i. Cooly

ii. Peon

iii. Chowkidar

iv. Road guard

v. Helper

vi. Boatman

189

9

13

27

16

3 257Source : Roads and Highways Department, Dhaka.

The maintenance activities can be conveniently done by maintenance

gangs (size of each gang varying from 3 to 7 persons depending on

workload) with the supporting hand tools (shovel, hoe, hammer,

masons, tools, basket, iron and wooden rammers etc.) and equipments

like small roller (for compaction), tar boilers and mini truck (3tonner) for movement of equipments and labourers.

5.4 MECHANISATION AND EQUIPMENT PLANNING

The spectrum of technologies available for maintenance of roads

ranges from labour based to equipment based, although the relativeproportions can differ substantially. The socia-economicrequirements in Bangladesh is basically for labour based maintenance

to provide employment to a large number of people but it may be

necessary to use special equipment to achieve a specified quality in

the end product of certain activities, such as the use of (a) roller

for compaction on (b) grit spreader and bitumen distributor for good

surface dressing. Even the labour based methods use equipment in the

58

Page 69: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

form of hand tools and equipment based approaches use labour in the

form of operator. The machineries, equipment owned by the Roads and

Highway Department is given in the Table 5.2

TABLE-5.2

The Machineries, Equipments for Maintenance owned by Roads andHighways Department (June, 1990)

51.No. Name of Equipment

1. 3 - Wheeled Static Road Roller

2. 2 - Wheeled Static Road Roller

3. Pneumatic Tyre Roller

4. Soil Compactor 12/18 Ton

5. Bull Dozer Crawler

6. Bull Dozer ,Tyre

7. Scraper

8. Motor grader

9. End loader tyre

10. End loader crawler

11. Water Tanker

12. Dump Truck

13. Tractor Trailor

14. Flat bed truck

15. Mobile crane

16. Mobile servicing unit

17. Mobile bitumen mixer

59

No. ofEquipment

412

37

74

54

36

6

11

60

36

5

40

36

10

297

1

21

21

Page 70: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

81.No. Name of Equipment

18. Mobile Generator

19. Forklift Truck

20. Road marking machine

Source: Roads and Highways Departaent, Dhaka.

No. ofEquipment

30

5

2

The equipment owned by a typical Road Division of Roads and Highways

Department is given in the Table-5.3

TABLE-5.3Equipment Owned by two Typical Road Division of Roads and HighwaysDepartment

81. No. Name of Equipment No.of Equipment(Division - 1)

No.of Equipment(Division - 2)

1.

2.

3.

4.

5.

6.7.

Source

Water Tanker 3 2

Flat bed Truck 6 6

Mobile bitumen mixer 2 1

Mobile servicing unit 1 1

Roller(a) 3 - Wheeled Static Roller 8 4

(b) 2 - Wheeled Static Roller 1 2

Concrete mixer 1 4

Bitumen boiler 3 2

Roads and Highways Department, Dhaka.

60

Page 71: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

5.5 MANAGEMENT OF FUNDS

Maintenance funds are allocated from the revenue budget, so that it

is very scarce in a developing country like Bangladesh. Financial-allocation for routine maintenance are therefore allocated of a fixed

sum per mile plus a variable sum for pavement repairs. The amounts

allocated may also vary with the type of road and/or traffic volume.

The fixed sum per mile is generally determined from previous

~xperience and the cost of pavement repairs may be deduced from the

road condition.

The average annual road maintenance expenditure of Roads and HighwaysDepartment is given in Table-5.4.

TABLE-5.4

THE AVERAGE ANNUAL EXPENDITURE FOR MAINTENANCE OFROADS AND HIGHWAYS DEPARTMENT

(Taka in lakhlYear A11oc- Pay Material Equipment/ Misce- Special Ferry

ation Transpor- 11aneous repairtat ion

1985-86 4100.00 515.26 751.54 180.92 296.74 1952.68 1065.011986-87 4900.00 608.49 620.47 333.82 284.95 1933.82 1342.631987-88 6150.00 696.16 767.12 346.20 279.25 2870.83 1571. 901988-89 7500.00 775.13 816.28 411. 61 621.54 3117.96 2055.761989-90 8000.00 829.31 901.32 499.10 720.21 3423.32 2721. 32

Source: Roads and Highways Departaent, Dhaka.

61

Page 72: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

The average annual expenditure for maintenance by road type is given

in the Table-5.5

TABLE-5.5

AVERAGE ANNUAL EXPENDITURE FOR MAINTENANCE BY ROADTYPE

Type of the Total Length Average width of Average annualRoads (in km) pavement expenditure per km

(in m) (Taka in lac)

National 2834.60 6.71 0.91Highway

Regional 1369.76 5.49 0.79Highway

Other Roads 8059.90 3.66 0.16Source : Roads and Highways Department, Dhaka.

The annual road maintenance expenditure of different road circles ofRoads and Highways Department is given in the Table-5.6

TABLE-5.6

ANNUAL ROAD MAINTENANCE EXPENDITURE OF DIFFERENTROAD CIRCLES IN BANGLADESH (1989-90)

(ROADS AND HIGHWAYS DEPARTMENT)

(Taka in Lakh)51- Name of RHD Total Departmen- Special Ferry TotalNo. Circle Length tal Expen Repair Mainten-

(in km) -diture ance

1- Dhaka road 980.46 365.60 1205.48 747.25 2318.33circle

2. Mymensingh 1382.37 188.27 350.46 86.00 624.73road circle

3. Chittagong 1232.03 262.73 297.88 560.61road circle

62

Page 73: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

(Taka in Lakh)5l. Name of RHD Total Departmen- Special Ferry TotalNo. Circle Length tal Expen Repair Mainten-

• (in km) -diture ance

4. Sylhet road 1960.90 404.67 452.27 165.93 1022.87circle

5. CHT road 428.96 30.65 80.06 110.71circle

6. Khagrachari 192.75 4.76 24.64 29.40road circle

7. Rajshahi road 1275.83 240.54 282.82 24.59 547.95circle

8. Jessore road 1530.32 358.42 437.00 186.79 982.21circle

9. Rangpur road 1741.21 162.16 556.52 718.68circle

10. Barisal road 1475.43 159.42 260.10 229.44 648.96circle

12180.26 2177.22 3947.23 1440.00 7564.45

Source: Roads and Highways Department, Dhaka.

~'(j<;jJ

63

Page 74: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

CHAPTER-6

ROAD MAINTENANCE PRACTICES IN BANGLADESH

6.1 INTRODUCTION

Road transport plays a significant role in the economic development

of Bangladesh. For this reason a significant part of the national

budget is spent in road building and maintenance. Even if the design

and construction of the road conform to requirements and standards,

maintenance is still needed. A poorly maintained road is not only

inconvenient to the users and detrimental to the road itself but it

is highly uneconomic. So road maintenance is quite important. Due

to lack of maintenance, roads deteriorate quickly. On the other

hand, proper maintenance prolongs the life and improves the quality

of service of roads and highways.

6.2 ROAD CONSTRUCTION AND MAINTENANCE ORGANISATIONS

Before going into the details of road maintenance procedure as

followed in Bangladesh a brief discussion on various organisations

entrusted with the construction and maintenance of roads streets and

highways in Bangladesh seems to be in order. In Bangladesh a major

portion of roads and highways are constructed and maintained by the

Roads and Highways Department (RHD). Local bodies like Zila

Parishads, Pourashavas/Poura Corporations, Upazila Parishads, Union

Parishads etc. also build substantial amounts of roads of different

fuoctional classifications within their jurisdictions.

The Roads

constructingand Highways Department is mainly responsible

and maintaining inter-district and inter-city roads

64

forin

Page 75: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

Bangladesh. The total road kilometrege within the jurisdiction of

the Roads and Highways Department is shown in Table-1.2.

The Roads and Highways Department maintains ten road circles each

having two or more road divisions. Each road division is entrusted

with the task of constructing and maintaining the roads within its

jurisdiction. Construction of roads in Bangladesh is financed mainly

from development budget, while road maintenance is financed mainlyfrom revenue budget.

Besides, these normal road jurisdictions there are many large and

special road projects which are constructed, rehabilitated and

maintained by the Roads and Highways Department. Due to scarcity of

local resources these types of projects are financed by different

international organisations such as the Asian Development Bank (ADB),

the World Bank etc. These kinds of roads are sometimes undertaken•

during emergent situations such as floods etc. A brief description

of such' projects under the Roads and Highways Department is givenbelow :

Project Title

1. Feeder Roads'Improvement Project

2. Road ImprovementProject

65

Location and Jurisdiction

*To improve 300 kms of roads in thedistricts of Mymensingh, Tangail,Jamalpur, Sherpur, Netrokona andKishorganj.

*To improve 330 kms of selectedportion of national roads (Daudkandito Feni, Dohazari to Cox's Bazar,Daulatdia to Faridpur, Faridpur toJhenidah and Jhenidah to Kushtia.)

Page 76: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

3.

Project Title

Road Rehabilitation andMaintenance Project.

Location and Jurisdiction

*Repair and Resealing of about 100 kmsof selected portions of national roads(Dhaka to Daudkandi, Feni toChittagong, Chittagong to Dohazari).

*Rehabilitation of 132 kms of roads(Dasuria-Natore-Rajshahi).

*Maintenance programme of 2000 kmof priority road in North-west andSouth-west.

Besides Roads and Highways Department, a significant part of the

road system is constructed and maintained by local bodies. At

present, such local bodies in Bangladesh possess the following roadkilometreges:a. lila Parishads - 21,000 kms of feeder roads having crest width

of 6m to 7.3m connecting UpazilaQuarters and other Growth Centres withnearly arterial road system.

Headthe

b.

c.

Pourashavas/Poura Corporations

UpazilaParishads

About 9000 kms of urban roads within theterritorial jurisdiction of the Pourashavas.

About 28000 kms of rural roads having crestwidth of 3.65m to 4.6m connecting Unions toUpazila Head Quarters and important localmarkets.

d. Union Parishads- About 1,08,000width of 2.43mand farms toQuarters.

kms ofto 3.65mlocal

roads having crestconnecting villagesmarkets/Union Head

The responsibility for the construction and maintenance of national

and regional district roads rests on the Roads and HighwaysDepartment. The Zila Parishads mainly maintains and develops feeder

roads including inter-upazila roads which connect Upazilas and other

important growth centres with the abutting arterial road system.

The Zila Parishads have substantial financial resources at their

disposal and they spent a substantial portion (approximately 70%) of

66

Page 77: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

their resources for the construction and maintenance of feeder roads.

The sources of funds are as enumerated below :

a. Normal revenUe income - Land transfer fee, income from assets,lease of ferry ghats etc.

b. Works programme grants.

c. Special foreign aided projects.

d. Divisional Development Board funds.

There are four Municipal Corporations i.e Dhaka, Chittagong, Rajshahi

and Khulna and eighty eight Pourashavas. Except Dhaka and Chittagong

Municipal Corporations, most of 'the Pourashavas are going through

considerable financial constraints. Their resource bases are narrow

and their share of Development Assistance Fund compared to upazila

parishads is too inadequate. Due to resource constraints most ofthere pourashavas are not in a position to meet theirresponsibilities of properly maintaining municipal roads. Most ofthe Pourashavas do not have adequate technical personnel andequipments.

The Upazila Parishads are adjudged as the nuclei of development.

They have their own programmes of construction and improvement ofroads. These roads mainly connect important markets and union

headquarters within the upazilas. With the exception of some brick-

surfaced roads these consists mainly of kutcha or earthen roads. The

road construction and maintenance works of upazila parishads are

mainly undertaken by resources from Development Assistance Fund andFood for Works Programme (FFWP).

67

Page 78: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

T~ Union Parishads have certain responsibilities theconstruction and maintenance of roads within their jurisdictions.

These consists mainly of small kutcha roads connecting villages and

bazars within the union parishads. Those works are undertaken with

their own resources as well as shares receiving from the DevelopmentAssistance Fund and Food For Works Programme.

6.3 PROBLEMS OF ROAD MAINTENANCE IN BANGLADESH

6.3.1 Problems for Arrangement of Traffic:

Since maintenance operations involve considerable hardship,inconvenience and hazard to traffic and also hazards to maintenance

workmen all possible precautions should be taken to make safe

arrangements for traffic. These include erection of barriers, signs,

red flags and lights. The maintenance locations are surrounded by

white and red stripped barriers, fences and directional cones to

guide the approaching vehicles onto another line. Efforts should be

made to confine work in half the pavement width at a time, leavingthe other half for use by the traffic. Where this is not possible,diversion roads may have to be constructed or the traffic diverted tosome other alternative routes.

Selecting and positioning temporary road signs, theprinciples should be applied.

following

i. Traffic control devices must always be in a good and usablecondition;

ii. Traffic control devices must always be visible;

iii. Traffic control devices must be correctly located;

iv. Traffic control devices must be properly mounted and fixed andmust possess adequate stability.

68

Page 79: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

T~ following plans show traffic control devices for maintenance

sites on paved and unpaved roads. They are proposed with the

intention of assisting those responsible for the sign posting of

maintenance sites in choosing suitable traffic control devices andtheir locations.

. _.

Men working ahead

Carrigeway narrows

Carrigeway narrowsto left

69

Keep left here

'.0..~\.I:,. .

Keep right here

Speed reduction(maximum speed BOkm/h)

Page 80: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

Carrigeway narrowsto right End of work site

Detour100m IDetour>

Detour 100 m ahead

Turn right

Detour necessary to right

;,"'--~.," ~~ "

, .~'.--

Turn left

ooo

--_._-o ;? Standared Heights and Burried~ -~._ Depth for Traffic Signs

70

oo

Page 81: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

Barrier Drum Traffic Cone(Other sizes also available)

•.Stop/Go Paddle forTraffic Controller

"; ."

Lane Closed Barrier Warning Flag

Color: White/red/whiteor All redor All orange

Figure-6.I Showing different Traffic Signals Completion and Removalof temporary signs.

Source Road Maintenance handbook, Volume-I, United Nations EconomicCommission for Africa.

71

Page 82: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

All temporary signs must be removed as soon as the work they relateto is complete. The procedure includes

Clean tools;

Load all tools, equipment and reusable materials on to truck;

Collect all traffic warning signs and cones, wipe clean and loadonto truck, stacking them carefully;

Check that nothing has been left behind and that the site isclean and neat.

Maintenance work can be divided in the following four categories fromthe point of view of safety and traffic control :

i. Repairing the edges of the carriageway, shoulders, cleaning out

drains, cutting grass etc. where carriageway is not affected;

ii. Repairing the carriageway restricting to one lane while trafficcan be allowed on the other lane;

iii. While working on the centre line such as centre line marking/

painting necessitating the traffic to use restricted width oneither side;

iv. Total closure of the road necessitating use of diversion due towidening/reconstruction of an existing road.

72

Page 83: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

6.3.1.1 WORKS ON EDGES AND SHOULDERS

The positioning of the cautionary signs for this category are

illustrated in Figure-6.2. Before starting the work, all warning

signs should be installed in the following manner. 'Men at work'

should be placed 200 M before approaching the work area and

'Restriction Ends' sign should be displayed 200 M beyond the work

.area. When the work is completed, these signs should be removed inthe reverse order.

Figure-6.2 : Sign layout for edge working.

Source Overseas road Note-2. Maintenance Technique for DistrictEngineers.

73

Page 84: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

6.3.1.2 RESTRICTING THE TRAFFIC TO ONE LANE

At times, the traffic is to be restricted to one lane only due to

repairs being carried out in the other lane such as major patch

repairs, etc. The position of various cautionary and warning signs

are illustrated in Figure-6.3, which are to be installed before

start of the work the following sequence :

i. 'Men at work' sign to be put up 200M before commencement of thework;

ii. 'Narrow Road Ahead' should be at 100M ahead of work area;

iii. 'Keep left/right' sign to be placed at the commencement point

of the work and next to the barriers on the either end of thework area;

iv. 'Barriers' should be placed on both sides of the work area;

v. Drums painted white and black should be placed at 9M interval

for guiding the traffic. In the approaches tare to be kept ina tapered manner;

vi. 'Restriction Ends' sign should be installed 200M beyond thework area.

74

Page 85: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

In addition to the above. a watchman should be present at thebarrier to control the traffic at all times.

CJY4QlFigure-6.3 : Sign Layout for Lane Closure

Source Overseas Road Note-2, Maintenance Technique for DistrictEngineers.

6.3.1.3 WORKING IN THE CENTRE OF THE CARRIAGEWAY

While working in the centre of the carriageway. adequate attention

has to be paid from the safety point of view, for example.

marking/painting of centre line. The positioning of the various

cautionary and warning signs are illustrated in Figure 6.4 The

sequence of installation of these signs are the same as in the

traffic arrangement to one lane. Except in this case, the vehicles

will keep onlJ' to the left in each direction. When the work is

.completed. it should be ensured that the signs are removed in thereverse order.

75

Page 86: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

rT1/{2J.'VI .

Figure-6.4 : Sign Layout for Centre line working.

Source : Overseas Road Note-2, Maintenance Technique for DistrictEngineers.

6.3.1.4 DIVERSIONS

In the interest of safety and convenience of traffic, appropriate

.easures must be taken whenever traffic on any section of a road is

to be diverted to another route, or made to separate from its

normal path into another. Basic principles to be kept in mind are

(i) that the traffic must be guided properly where it is required

to follow an alternate facility; (ii) given a clear warning of anyhazards that may be present ahead.

After the diversion has been completed and before work starts,

warning signs, barriers and cones must be placed around the work

area. The layout shown in Figure-6.5 is recommended. Signs mustbe placed in the following order :

1. 'Men working' signs should be placed 200 meters in frontof the work area.

76

Page 87: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

2. 'Turn left/right ahead' signs should be placed 100 meters infront of the work area.

3. 'Turn left/right' arrows should be placed immediately beforethe start of the diversion.

4. Cones should be placed diagonally across the road to lead intothe diversion.

5. 'Keep left/right' arrows should be placed at the ends of thelines of cones.

6. 'Barriers' should be placed behind the line of cones.

7. 'Road clear' signs should be placed 200 meters beyond the endsof the diversion.

Signs, lights, barriers and other traffic control devices

should be kept maintained ln a satisfactory condition until

such time as the traffic is restored and allowed to follow itsnormal path.

Figure-6.5 : Sign Layout for Diversion.Source Overseas Road Note-2, Maintenance Technique for District

Engineers.

77

Page 88: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

TRAFFIC SAFETY AT NIGHT

Traffic safety substantially decreases at night time during maintenance.

Necessary lighting arrangements may be made during night with flashing

lights when required. The barricade should be protected with red warning

lamps at night which should stay lit from sunset to sunrise. In addition,

alternate black and white diagonal strips should be marked on these for

effective advance warning preferably with reflecltorised paint.

6.3.2 Financial Capacity

The capacity to pay for road maintenance from domestic sources

depends on a country resources. Gross National Product (GNP) per

capita may thus be a good index of financial capacity, but some

governments are able to capture more of it than others. And of the

fiscal intake, the allocation to highways is a political decision•

about national priorities.

6.3.3 Institutional Capacity:

The differences in Gross National Product (GNP) per capita and its

rate of change, the ratio of network length to Gross National

Product, the age distribution of roads and the volume of traffic - do

not fully account for the variation in road conditions from country

to country. Institutional capacity has several facts. One is the

size of labour forces that can be applied to the activity. Othersare the soundness of the maintenance strategy - type, level and

timing of intervention and the managerial and operation efficiency

with which the strategy is executed. This depend, in turn, on suchfactors as governmental commitment, institutional structure,managerial ability, staff quality, accountability and incentives.

78

Page 89: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

6.4 EXISTING ROAD MAINTENANCE TECHNIQUE

Techniques for the evaluation of roadway pavement conditions have

been discussed in detail in Chapter-3. Types of maintenance works

done by the Roads and Highways Department is given in Table 6.1. But

the most important and crucial consideration is the technology ofproperly and economically maintaining roads.

pursued.

In Bangladesh appropriate and scientific or engineering methods have

not yet been devised and documented. Field crews do the job in their

own way under the supervision of a Field Maintenance Engineer. Proper

evaluation and assessment as well as maintenance planning is old,

sometime methods are inadequate. Budgeting cost estimations are not

in keeping with modern techniques. Priorities are seldom determined

on the basis of factual data and national interest. In the developed

world where manpower is limited but resources are not very limited

machines and automatic or semi-automatic process are

Accordingly research documents on such methods are abundant. But in

the developing countries like Bangladesh where population pressure is

heavy, employment opportunities are limited and resource limitations

are significant, labour intensive methods are highly encouraged.

Techniques and procedures for such labour intensive methods areneither well documented nor well researched.

The methods adopted for the maintenance work for the roads within the

jurisdiction of the Roads and Highways Department are discussedbelow:

79

Page 90: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

At present roads are maintained by surfacing with pea-grave Is-bitumen

.ix. This Premix Bituminous Surface (PBS) deteriorates by cracking

and ravelling quite quickly. It lacks durability under heavy traffic

and often requires bituminous surface seal coat to provide for the

required waterproofing quality. Construction methods are labour-

oriented but often lacks quality control. In most of the cases pea-

gravels or shingles are heated in trays over an open fire and hot

bitumen mixed in with band hoes. During the mixing operation in

trays, little control over bitumen temperature and the uniformity of

.ixing is exercised. Aggregates are seldom properly graded and often

lacks mechanical bondage. Premix Bituminous Surface materials are

sometimes blended in mechanical mixer/heaters. In such cases the

quality of the mix improves considerably but handling is slower and

the temperature of the mix decreases appreciably before application

to the road. A cold mix cannot function properly as a tack coat.

Repairing of pot holes, application levelling courses etc. are done

by the grouting method which often lacks quality control. Sometimes

bitumen is heated on open trays and then applied directly on the road

on eye estimation without proper temperature control. The quantity of

the bitumen required for the purpose is not accurately estimated. If

excess bitumen is used the surface bleeds during scorching heat. In

the event the percentage of bitumen used in the mix is less than the

required amount proper binding is not ensured. Items like pot hole

repairs, levelling courses etc. are also done with premixed materials

consisting f graded aggregates and bitumen emulsions or cut-backs. In

such cases appropriate technology using labour intensive method isadopted.

80•

Page 91: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

81

above

Maintenance of feeder roads under project support is an important

issue. Normally a road generally needs a period of three to four

years for the completion of its construction. Maintenance problems

emerges after the road has been in service for a certain period of

time. These maintenance works are obviously of routine type for thefollowing categories of roads :

i. Herring-Bone-Bond (HBB) - Shoulder maintenance (Earth work) plus

the replacement of damaged bricks usually set in herring-bone-bonds.

Maintenance programmes adopted by local bodies (Upazila Parishads)are as discussed below :

ii. Water Bound Macadam (WBM) - Shoulder maintenance (Earth work)

plus the re-surfacing of macadam pavements where ruts and pot-holes are formed.

Besides maintenance of various road surfaces as stated

iii. Bituminous Shoulder maintenance (Earth work) plus the

carpeting, surface painting and seal coating and pot holesrepair.

clearance of slit and weeds in the bridge/culvert openings are also

needed now and then. Since the life expectancies of feeder roads

vary from three to seven year a gradual maintenance programme should

be prepared and followed by each upazila and be closely co-ordinated

with the District Executive Engineer who has the responsibility of

scrutinizing all maintenance proposals and arrange for allocation of

Page 92: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

rollers (5-7 tons) needed for such maintenance works should be

equipments like tar boiler, hand compactor, wheel borrows etc. should

provided by the Executive Engineer from the district pool and he

Other small

provide necessary hand tools including tar boilers (where needed) to

the upazilas to perform the maintenance works. Only the small road

funds as being practiced by the donor agencies. The project should

should co-operate in such schedules 'of operation.

be procured by the upazilas for their maintenance gangs.

6.5 FINANCIAL PATTERN FOR MAINTENANCE (UPAZILA ROADS)

During the life of the project Upazila Parishad should undertake themaintenance responsibilities as follows:

Upazila GOB Donor(own resource)

1st year maintenance 100%2nd year maintenance 15% 25% 60%3rd year maintenance 35% 25% 40%4th year maintenance 40% 25% 35%

After the project period is over, the upazila parishad should bear

the total cost of maintenance of the completed feeder roads. The

resources for such maintenance works should come from the UpazilaDevelopment Assistance (UDA) fund.

82

Page 93: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

5. Jungle cutting.

7. Earth work in road embankment and bridge approaches.

workofNameSI.No.

1. Surface maintenance including patch repair, pot holes repair,minor undulations.

TABLE-G. ITYPES OF MAINTENANCE WORKS DONE BY ROADS AND HIGHWAYS DEPARTMENT

2. Pre-mixed seal coat with tack coat surface painting.

3. Levelling, dressing of shoulder slopes and berms as required,shoulder maintenance.

4. Cutting and clearance of drains and clearance of beds of bridges,culverts etc. including training are required.

6. Maintenance of mile post, boundary pillars, lane marks, singsetc.

8. Baily bridges (wooden decks).

83

Page 94: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

CHAPTER-7

RESEARCH FINDINGS AND RECOMMENDATIONS

7.1 FINDINGS

The findings of this research are summarized as follows

1. Road network in Bangladesh is presently classified mainly into

five categories such as national highways, regional highways,

feeder roads, urban roads and rural roads. Detailed

characteristics of these roads are shown in appendix-G. Total

paved roads (7156 km) under Roads and Highways Department in the

national highway category about 72% are double-lane paved, double

lane roads in the Regional highways, feeder roads and Upazila

connecting roads under the Roads and Highways Department are 48%,

20% and 4% respectively. These data shown in Table- 1.4

2. Roads and Highways Department is the main organisation for

constructing and maintaining roads and highways in Bangladesh.

Total roads under Roads and Highways is 12134 km of which 7156

km. Paved road, 2064 km partly paved or brick paved and 2914 kmearthen road.

Of the total road kilometrege in Bangladesh as of mid-1988 only

11% of the roads are paved or partly paved and the remaining are

earthen or kutcha roads. The total amount of paved or partly

paved roads is approximately 20,000 km. These data shown in Table1.3.

84

Page 95: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

4. Annual allocation of funds for road maintenance has increased

•Corporation, Upazila Parishad, Union Council are respectively

13%, 5%, 17% and 65%. These data shown in Table 1.3.

in 1989-90

period was

the annual

from Tk.4100.00 lakh in 1985-86 to Tk. 8000.00 lakh

(Table-5.6). The average allocation during these

Tk.6,130 lakh. Average incremental growth in

where the total quantum of these roads is approximately 165,000

km only 6.5% are paved and the remaining 93.5% are earthen or

kutcha roads. The percentage distribution of the total roads

constructed and maintained by Zila Parishad, Pourashava/Poura

3. Besides roads and Highways Department local bodies like Zila

Parishad, Pourashava/Poura Corporation, Upazila Parishad, Union

Council construct and maintain a substantial amount of roads

maintenance allocation was around 18%.

5. The average annual maintenance expenditure per kilometre is Tk.62,000.00. 1t is seen that the average annual expenditure on

maintaining one kilometre of road is Tk. 91,000.00 lakh for

national highway, Tk.79,000.00 for regional highway andTk.16,OOO.00 for other categories of road.

85

through routine or periodic maintenance.

As a result, the adverse effects

From this study it is found that if timely allotment is made of

sufficient funds to the concerned organisation road maintenance

programmes must improve. If timely allotment of fund is not made

damages to roads are intensified by natural calamities, likeflood, excess rain etc.

cummulate and render most of the roads beyond economic repair

Page 96: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

6. Equipment and machineries for maintenance owned by different

organisations is generally satisfactory. But the distribution todifferent field offices is not done properly.

8. Though the organisation engaged for maintenance activities. have

adequate manpower for maintenance works but no organisation have

sufficient manpower and equipment for evaluation of existing

pavements in terms of physical condition, structural capacity,roughness etc.

our country is

adequate maintenance

of the professional,proportion

there areintensive,staffs. The

As the maintenance of roads and highways inmainly labour

engineers and

technical, skilled and non-skilled labour is 1:2:23:52. This isgiven in Table 5.1.

7.

9. Appropriate and scientific or engineering methods have not yet

been devised and documented. Field crews do the job in their own

way under the supervision of a Field Maintenance Engineer.

86

2. Fund requirement for proper and timely maintenance must be

estimated by the concerned organisations in appropriate time.Sufficient fund for maintenance to be assured.

road

forcontrol

evaluation forQuality

road maintenance work,

be done properly.maintenance materials must be assured.

RECOMMENDATIONS1. Before going for

condition should

7.2

Page 97: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

4. Departments and organisations concerned with road maintenance

works should take steps to acquire adequate number of equipments

and machineries in order to undertake maintenance works speedilyand effectively.

maintaining the roads must chalk out a. programme of road

maintenance at the end of the year. This must be placed to the

appropriate authority so that allocation of funds can give as perrequirement.

3. Department and organisations which are responsible for

5. Upazila connecting roads must be considered for maintenance andaccordingly allotment should be given.

6. Training of all personnel involved in maintenance is an integral

part of the maintenance function. Such training, as may be

required by the operating and maintenance personnel must beassured by the concerned organisations.

87

Page 98: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

APPENDIXA. PARTICLE SIZE DISTRIBUTION FOR GRAVEL SURFACING

B. GRADING FOR CRUSHED ROCK PATCHING MATERIAL

as Sieve •• Passing~

37.50 mm 10020.00 80 10010.00 55 805.00 40 602.36 30 50

600.00 II m 15 3075.00 II m 5 15

Source Overseas Road Note-2, TRRL 1981.

88

Page 99: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

C. REQUIREMENTS FOR PREMIXED MACADAM USED FOR PATCHING MATERIAL

14 mm nominal size

BS Sieve (mm) % Passing

20.00 100

14.00 90 100

10.00 55 75

6.30 25 45

3.35 15 25

75.00 Jl m 2 6

Binder Content 4 5%

Source: Overseas Road Note-2, TRRL 1981.

D. RECOMMENDED CHIPPING SIZE (mm)

Lane Traffic Category

Twe ofSurface

Approximate number of commercial vehicles currently carriedper day in the lane under consideration

(1) (2) I (3) I (4) I (5)Over-2000 1000-2000 200-1000 20-200 Less than 20

Very hard 10 mm 10 mm 6 mm 6 mm 6 mm

Hard 14 14 10 6 6

Normal 20** 14 14 10 6

Soft * 20** 14 14 10

Very Soft * * 20** 14 10

* Unsuitable for surface dressing.** 20 mm chippings may be used for remedial treatment where trafficspeeds are low. Very particular care should be taken when using20 mm chippings to ensure that no loose chippings remain on thesurface when the road is opened to unrestricted traffic as thereis a high risk of wind screen breakage.

Source : Overseas Road Note-2, TRRL 1981.

89

Page 100: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

F. ROAD CONDITION SURVEY FORM

Source: Overseas Road Note-2, TRRL 1981.

80 - 90

35 45

Temperature

55 - 65

105 - 115

125 - 135

140 - 150

150 - 160

155 - 165

165 - 175

Slot Jets'c

95 - 115

65 - 80

50 60

115 - 135

140 - 155

160 - 170

165 - 175

170 - 190

180 - 200

Atomising jets'c

Spraying

E. SPRAYING TEMPERATURES

Grade

MC - 250

MC - 70

Cutback grades

MC - 30

MC - 800

MC -3000

Penetration grades

400/500

280/320

180/200

80/100

ROAD N~~E: ROAD SECTION NO.

.SHEET START POINT:

DISTANCE FROMLAST RECORD metres

INSPECTIOR:DATE:

90

Record No.Record Type.

Locationidentifi-cation

GENERAL

Page 101: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

VerticalALIGNMENTS Horizontal

Flood Height

Cut/FillLEFT HeightSIDE SLOPE Slope

Type

LEFT SIDE WidthDRAINS Type

LEFT WidthSHOULDER Type

WidthTypeAgeLeft EdgeCamber

CARRIAGEWAY CrackingPotholesRuttingRoughnessRight Edge

RecommendedMaintenanceActions

RIGHT WidthSHOULDER Type

RIGHT SIDE WidthDRAINS Type

.Cut/FillRIGHT HeightSIDE SLOPE Slope

Type

Source The Road Maintenance Proble., Hodgkinson, W.G.

91

Page 102: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

G. ROAD CLASSIFICATION AND GEOMETRIC STANDARDS

S1. Type of Roads DefinitionNo. ( Crest width) (pavement width) (shoulder width)(in each side)

1. 2 34 5 6

A. ARTERIAL ROADS

1. National National Highways form the major arterialsystem Highways and are defined as roadsconnecting the national capital with thedivisional and district headquarters, portcities,places of economic, commercial andstrategic importance, and other importantpoints as decided from time to time on thebasis of traffic requirements.

Category-itA" 12.192 m 6.71 m 2.75 m(40'-0") (22'-0") (9'-0")Category-liB" 12.192 m 5.86 m 3.36 m(40'-0") (18'-0") (11'-0")

2. RegionalHighways Regional Highways refer to roads connecting differ

-ent regions with each other, not connected bynational highways.

Category-"Alf

Category-liB"

10.98 m(36'-0")

10.98 m(36'-0")

5.86 m(18' -0" )

3 •. 66 m(12'-0")

2.75 m(12'-0")

3.66 m(12'-0")

3. District Roads District Roads may be defined as roads connectingSub-divisional Headquarters and important commer-cial centres of the district with each other andthe road system.

9.144m(30'-0")

92

3.66 m(12'-0")

2.75 m(9'-0")

Page 103: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

B. FEEDER ROADS

4.88 m(16'-0")

Roads connecting Villages and farms to localmarkets.

1. 83 m(6'-0")

3.66 m(12'-0")

Roads connecting Upazila Headquarters and othergrowth centres with the arterial road system.

Roads connecting Union HQ's/Markets with the Upa-zila H.Q. or the road system.

7.32 m(24'-0")

RURAL ROADSUpazila Roads

Union Roads

c.

3.66 m(12' -0")

Village Roads Roads connecting mosques, weels, & different parasof the Villages.2.44 m(8'-0")

Source Roads and Highways Departaent, Dhaka.

93

Page 104: SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING

REFERENCES

1. 'ASPHALT OVERLAY FOR HIGHWAY AND STREET REHABILITATION' The AsphaltInstitute, Manual Series No.17(MS-17), June, 1983.

2. 'A DEFLECTION SURVEY TECHNIQUE FOR PAVEMENT EVALUATION IN DEVELOPINGCOUNTRIES' by H.R. Smith.

3. 'CODE OF PRACTICE FOR MAINTENANCE OF BITUMINOUS SURFACES OF HIGHWAYS'IRC : 82-1982.

4. 'POCKET BOOK FOR HIGHWAY ENGINEERS', IRC, NEW Delhi, 1983.

5. 'PRI.NCIPLES AND PRACTICE OF HIGHWAY ENGINEERING' by L.R.Kadiyali,1984.

6. 'ROAD MAINTENANCE HANDBOOK VOLUME I', United NationsCommission for Africa.

Economic

7. 'HIGHWAY ENGINEERING' Wright, P.H. & Paquette R.J., John Witey andSons.

8. 'OVERSEAS ROAD NOTE 2', Maintenance Technique for District Engineers.

9. '~~NUAL FOR MAINTENANCE OF ROADS', IRC, 1983.

10. 'JOURNAL OF THE INSTITUTION OF ENGINEERS', BANGLADESH., by Md.Majid, Md. Eunus Sikdar and Syed Noor-Ud-deen Ahmed, Vol.16,January, 1988.

AbdulNo.1,

11. '20AD CONSTRUCTION AND MAINTENANCE ACTIVITIES OF THE LOCAL BODIES' areport by LGEB.

12. 'THE ROADmaterialsDepartment,

MAINTENANCE PROBLEM' Hodgkinson, W.G. SAARC Seminar onand costs of Road construction, Roads and HighwaysDhaka, Bangladesh, 1984.

94