study on private-initiative infrastructure · pdf filefinal report march 201 1 ... ha home...
TRANSCRIPT
STUDY ON PRIVATE-INITIATIVE INFRASTRUCTURE PROJECTS
IN DEVELOPING COUNTRIES IN FY2010
STUDY ON THE SMART GRID PROJECT
IN HO CHI MINH CITY
THE SOCIALIST REPUBLIC OF VIETNAM
FINAL REPORT
March 2011
Prepared for:
The Ministry of Economy, Trade and Industry
Prepared by:
Ernst & Young ShinNihon LLC
Japan External Trade Organization (JETRO)
Tokyo Electric Power Services CO., LTD (TEPSCO)
OPMAC Corporation
Preface
This report summarizes the results of the "Study on the Smart Grid Project in Ho Chi Minh City The
Socialist Republic of Vietnam" carried out as a fiscal year 2010 project by Tokyo Electric Power Services
Co., Ltd. and OPMAC Corporation under commission from Ernst & Young ShinNihon LLC.
This study, “Study on the Smart Grid Project in Ho Chi Minh City the Socialist Republic of Vietnam”, is
to investigate the feasibility of the model Project with investment of about 42 million US$ for Smart Grid
which consists of Distribution Automation System (DAS) / Automated Meter Reading system (AMR) /
Demand Response (DR) / Solar Power in order to solve the shortage of power supply and improve the
reliability of power distribution network in EVN HCMC.
It is our hope that this report is helpful in the realization of the project described above and is also of use
to interested parties in Japan.
March 2011
Tokyo Electric Power Services Co., Ltd.
OPMAC Corporation
Project area: Phu Tho Power Company (District10 and 11) of HCMC PC
Scale: 1:42,000
Dist10 and11,Project area in HCM city
i
Abbreviation and Acronyms
Organization
ASEAN Association of Southeast Asian Nations
CRIEPI Central Research Institute of Electric Power Industry
EVN Vietnam Electricity
EVN HCMC Ho Chi Minh City Power Corporation
GOJ Government of Japan
GOV Government of Vietnam
HCMC Ho Chi Minh City
IE Institute of Energy
IPP Independent Power Producer
IUCN International Union for Conservation of Nature and Natural Resources
JBIC Japan Bank for International Cooperation
JEPIC Japan Electric Power Information Center Inc.
JICA Japan International Cooperation Agency
MOIT Ministry of Industry and Trade
Moody’s Moody's Investors Service Inc.
MPI Ministry of Planning and Investment
NEDO New Energy and Industrial Technology Development Organization
NEXI Nippon Export and Investment Insurance
NLDC National Load Dispatching Center
OECD Organization for Economic Co-operation and Development
S&P Standard & Poor's
SRLDC Southern Region Load Dispatching Center
WTO World Trade Organization
Others
A/C Air Conditioner
ALBS Automatic Load Break Switch
AMI Advanced Metering Infrastructure
AMR Automated Meter Reading
Ba3 Rating Symbols(Moody’s)
BB Rating Symbols(S&P)
BOT Build, Operate and Transfer
B-PLC Broadband Power Line Carrier
BT Battery
CB Circuit Breaker
CDM Clean Development Mechanism
CPU Central Processing Unit
CT Current Transformer
DAS Distribution Automation System
ii
DB Database
DGR Directional Ground Relay
DMS Distribution Management System
DR Demand Response
DS Disconnecting Switch
DT Distribution Transformer
EIA Environmental Impact Assessment
EIRR Economic Internal Rate of Return
EMS Energy Management System
E/N Exchange of Notes
EPC Environmental Protection Commitment
EV Electrical Vehicle
FCB Feeder Circuit Breaker
FEP Front End Processor
FIRR Financial Internal Rate of Return
F/S Feasibility Study
GDP Gross Domestic Product
GIS Gas Insulated Switchgear
GW Giga Watt
GWh Giga Watt Hour
ha Hectare
HA Home Automation
HEMS Home Energy Management System
HIV/AIDS Human Immunodeficiency Virus / Acquired Immunodeficiency Syndrome
HV High Voltage
ICT Information Communication Technology
IEC International Electro-technical Commission
IRR Internal Rate of Return
JPY Japanese Yen
kV kilo Volt
kVA kilo Volt Ampere
kW kilo Watt
kWh kilo Watt Hour
L/A Loan Agreement
LAN Local Area Network
LBS Load Break Switch
LNG Liquefied Natural Gas
L-PLC Low Speed Power Line Carrier
LV Low Voltage
MRI Magnetic Resonance Imaging System
M-RTU Master Remote Terminal Unit
MUS$ Million United States Dollar
MV Medium Voltage
MVA Mega Volt Ampere
MW Mega Watt
MWh Mega Watt Hour
NPV Net Present Value
iii
OCB Oil Circuit Breaker
OCR Over Current Relay
ODA Official Development Assistance
OH Over Head
O&M Operation & Maintenance
PCB Polychlorinated Biphenyl
PCS Power Conditioning Subsystem
PDP Power Development Plan
PLC Power Line Carrier
PPF Private Public Fund
PPP Public-Private Partnership
PQ Pre Qualification
PRN Printer
PV Photovoltaic
R Resistance
REC Recloser
RMU Ring Main Unit
RTU Remote Terminal Unit
SCADA Supervisory Control and Data Acquisition
SEA Strategic Environmental Assessment
SPM Suspended Particulate Matter
TM Telemeter
TOU Time of Use
TR Transformer
TRD Transducer
TWh Tera Watt Hour
UG Under Ground
UHF Ultra High Frequency
US$ United States Dollar
VAT Value Added Tax
VCB Vacuum Circuit Breaker
VES Vietnam Environmental Standard
VHF Very High Frequency
VT Voltage Transformer
WASA Wide-Area Situational Awareness
WHM Watt Hour Meter
XLPE Cross Linked polyethylene
ZCT Zero Phase Current Transformer
ZPD Zero Phase Detection
i
Study on Private-Initiative Infrastructure Projects in Developing Countries in FY2010
Study on The Smart Grid Project in Ho Chi Minh City The Socialist Republic of Vietnam
TABLE OF CONTENTS
Executive Summary
1 Background of Project and Necessity ························································································ 1
2 Fundamental policy of this project ···························································································· 2
2.1 Fundamental policy··········································································································· 2
2.2 Problems and the solution ······························································································· 3
2.3 Advantages ····················································································································· 5
3 Overview of this project ··········································································································· 5
3.1 Fundamental idea of Project ······························································································ 5
3.2 Configuration of Project ···································································································· 7
3.3 Project cost ······················································································································· 8
3.4 Overview of preliminary economic analysis ······································································ 9
3.4.1 Financial Analysis ································································································· 9
3.4.2 Economic Analysis ································································································ 9
3.5 Environmental and social analysis ····················································································· 10
3.5.1 Project impact on environmental and social aspects ················································ 10
3.5.2 Environmental Legal Framework and Application to the project ····························· 10
4 Implementing schedule ············································································································· 11
5 Feasibility study ······················································································································· 12
5.1 Review on Availability of Finance ····················································································· 12
5.2 Feasibility for implementing project ·················································································· 12
5.3 Necessary activities··········································································································· 12
6 Competitive ability of Japanese Company················································································· 12
6.1 DAS ································································································································· 12
6.2 AMR System ···················································································································· 13
6.3 EMS ································································································································· 13
6.4 Solar Power ······················································································································ 14
6.5 Integrated System ············································································································· 14
7 Schedule to realize this project and the objection ······································································ 15
7.1 Detail schedule to realize the project ················································································· 15
7.2 Objection and the solution ································································································· 15
8 Map of project area in survey country ······················································································· 17
Chapter 1 Outline of the Country and Sector
1.1 Economy and Financial Situation of the Country ······························································· 1-1
ii
1.2 Outline of the Project Sector ······························································································ 1-2
1.2.1 EVN Organization ································································································· 1-2
1.2.2 Power Demand and Supply ···················································································· 1-4
1.2.3 Power Generation Facility ······················································································ 1-9
1.2.4 Transmission and Distribution Facility Outline ······················································· 1-10
1.2.5 Electrification Ratio ······························································································· 1-12
1.2.6 EVN Operational Target························································································· 1-12
1.2.7 Electricity Tariff ···································································································· 1-13
1.3 Situation of Project Area ···································································································· 1-15
1.3.1 Situation of EVN HCMC ······················································································· 1-15
1.3.2 Situation of Phu Tho Power Company ···································································· 1-19
1.3.3 Existing Facilities and System of EVN HCMC······················································· 1-20
1.3.4 Existing Facilities and System of Phu Tho Power Company ··································· 1-36
1.3.5 Situation of Outage and Distribution Loss ······························································ 1-49
Chapter 2 Study Methodology
2.1 Overview of Study ············································································································· 2-1
2.2 Study Methodology and Team Organization ······································································· 2-1
2.2.1 Study Methodology ······························································································· 2-1
2.2.2 Team Organization ································································································· 2-2
2.2.3 Counterpart ············································································································ 2-2
2.3 Survey Schedule ················································································································ 2-2
Chapter 3 Justification, Objectives and Technical Feasibility of the Project
3.1 Background of Project and Necessity ················································································· 3-1
3.1.1 Scope of Project ····································································································· 3-1
3.1.2 Current Analysis and Future Prospect ····································································· 3-1
3.1.3 Advantage by Project ····························································································· 3-2
3.1.4 Comparison between the Proposed Project and Other Method ································ 3-11
3.2 Analysis Needed for Decision of Project Contents ····························································· 3-14
3.2.1 Demand Forecast ··································································································· 3-14
3.2.2 Issue and Analysis of Project ·················································································· 3-16
3.2.3 Technical Analysis ································································································· 3-17
3.3 Overview of Project Plan ··································································································· 3-35
iii
3.3.1 Fundamental Policy of This Project ········································································ 3-35
3.3.2 Overview of Design and Specification ··································································· 3-36
3.3.3 Contents of Project ································································································ 3-53
3.3.4 Problems of Proposed System and Solution ···························································· 3-55
Chapter 4 Evaluation of Environmental and Social Impacts
4.1 Environmental and Social Condition of Target Area ··························································· 4-1
4.1.1 Situation Analysis ·································································································· 4-1
4.1.2 Future Projection(“without” the Project) ································································ 4-1
4.2 Project Effectiveness in Environmental Improvement ························································ 4-2
4.2.1 Social Positive Impact on Customers by DAS ························································ 4-2
4.2.2 Peak Shift and Energy Saving by AMR ·································································· 4-2
4.2.3 Distributed Power Generation Facilities (Solar Power) ··········································· 4-3
4.3 Project Impact on Environmental and Social Aspects ························································· 4-3
4.3.1 Screening based on JICA guideline ········································································ 4-3
4.3.2 Comparison with Alternatives ················································································ 4-9
4.3.3 Results of Local Consultations for Information Collection ······································ 4-13
4.4 Summary of the Law to be related to considered Environmental Social Impacts in Vietnam 4-19
4.4.1 Summary of the Law to be related to considered Environmental Social Impacts ····· 4-19
4.4.2 Summary such as the EIA in Vietnam ····································································· 4-22
4.5 Necessary Actions Taken by the Project Proponent ···························································· 4-24
Chapter 5 Financial and Economic Evaluation
5.1 Estimation of Project Cost ································································································· 5-1
5.1.1 Scope ···················································································································· 5-1
5.1.2 Project Cost ········································································································· 5-2
5.2 Preliminary Economic and Financial Analysis ··································································· 5-4
5.2.1 Expected Effect of the Project ················································································ 5-4
5.2.2 Financial Analysis and Economic Analysis ····························································· 5-10
Chapter 6 Planned Project Schedule ·························································································· 6-1
Chapter 7 Implementing Organization
7.1 Implementing Organization ······························································································· 7-1
iv
7.2 Competence of the Organization ························································································ 7-2
7.2.1 MPI ······················································································································· 7-2
7.2.2 MOIT ···················································································································· 7-2
7.2.3 EVN head office ···································································································· 7-2
7.2.4 IE ·························································································································· 7-2
7.2.5 EVN HCMC head office ························································································ 7-2
7.2.6 Phu Tho Power Company ······················································································ 7-3
Chapter 8 Technical Advantages of Japanese Company
8.1 Entry Method and Form of Japanese Company ·································································· 8-1
8.2 International Competitive Ability of Japanese Company ···················································· 8-1
8.2.1 DAS ······················································································································ 8-1
8.2.2 AMR System ······································································································· 8-2
8.2.3 EMS ······················································································································ 8-2
8.2.4 Solar Power ··········································································································· 8-2
8.2.5 Integrated System ·································································································· 8-3
8.3 Necessary Countermeasure to Obtain the Contract by Japanese Company ·························· 8-4
Chapter 9 Financial Outlook
9.1 Fund Source and Funding Plan ·························································································· 9-1
9.1.1 Fund Source ·········································································································· 9-1
9.2 Review on Availability ······································································································ 9-3
9.3 Cash Flow Analysis ··········································································································· 9-11
9.3.1 Preconditions ········································································································· 9-11
9.3.2 Conclusion ············································································································ 9-12
Chapter 10 Action Plan and Issues
10.1 Action Plan for Advancing This Project ············································································· 10-1
10.2 Activity of Related Organization in Vietnam Government ················································ 10-2
10.2.1 Activity of MPI ····································································································· 10-2
10.2.2 Activity of MOIT and EVN ··················································································· 10-3
10.3 Legal and Financial Constraints, etc. of Partner Country··················································· 10-3
v
10.3.1 Legal Restriction ··································································································· 10-3
10.3.2 Financial Restraint ································································································· 10-4
10.4 Necessity of Additional Detail Analysis ············································································ 10-4
1
Executive Summary
1 Background of Project and Necessity
GDP in Vietnam is anticipated that the growth rate from 7% to 8% will continue up to 2020 and the growth
of consumption is around 8 to 15%. According to Institute of Energy (IE) report based on the GDP, the
growth rate of power consumption is anticipated to continue the growth rate of 12.7% for every year up to
2030.
Besides, the power generator had been constructed with growth rate of 13.7% for every year up to 2009.
The power in Vietnam has been lacked under the maintenance and trouble even though the generators have
been constructed. Therefore, Vietnam will promote plans to increase the power from 20 GW in 2010 to 52
GW in 2020.
As for solution for the shortage of power, the constructions of power generators will be planned but there
are the following problems.
1) The construction plans of hydraulic power generators which have 35% in existing supply capacity, have
not been advanced smoothly due to problems such as habitant movement etc, so that the hydraulic
generator can not be expected to cover the future consumption with high growth.
2) Peak consumption in 2020 will be increased and be reached to around 52 GW, so that new power plants
of 35 GW are needed up to 2020.
As for Coal fired thermal power plants, the development with 35,000 MW needs to provide 100 million
tons per year while the output of maximum coal mining reached about 70 million tons per year.
3) As for gas and oil fired thermal power plants, the construction is normally slow and the energy source in
thermal power projects causes green house gas problem.
4) As for nuclear power plant, the signing for the construction had been implemented by Russia and Japan.
If nuclear power plant meets the schedule of the 6th Power Development Plan (PDP), the first plant will
be commissioned after 2020.
As mentioned above, the shortage of power in Vietnam is serious up to 2020 especially and the
constructions of current and fossil power plants can not be expected to solve the problems. Therefore, it is
necessary to accelerate the installation of renewable energy and connection to distribution network and
advance the energy efficiency in parallel.
2
Government of Vietnam (GOV) has also promoted the energy efficiency in parallel and the new energy
efficiency law including acceleration of the energy efficiency and support for the development of
renewable energy will be established on 1st of January in 2011.
Regarding renewable energy, wind power / biomass / geothermal / small hydropower / Solar are considered
as the renewable energy in Vietnam and the potential reported by IE is as follows.
Wind Power: 1,800 MW
Biomass energy: more than 150 MW
Geothermal energy: 340 MW
Small hydropower: 4,000 MW
Solar energy: 4~5 KWh/m2
Small hydropower has occurred damages by flood during typhoon etc, so that the additional construction
will be difficult by objections of inhabitants. The capacity of Biomass and Geo thermal energy is not so
large. Therefore, Wind and Solar power will be expected to cover the increasing consumption in Vietnam.
Especially in case of Solar energy, the generation capacity is around 3,300GW under assumption of
utilizing 1/10 land in Vietnam.
However, the Wind and Solar power are unstable due to the influence of weather condition, so that the
rising of end voltage and the fluctuation of frequency are occurred. This smart grid project with Energy
Management System (EMS) can solve the problems.
In addition, the energy efficiency such as peak-cut and reduction of distribution loss can also contribute to
solve the shortage of power. So, it is necessary to advance the peak-cut and the reduction of distribution
loss by this smart grid project with Demand Response (DR) / Automated Meter Reading (AMR) and
Advanced Distribution Automation System (DAS).
It is important to improve the reliability of distribution network as policy of power sector. This smart grid
project using Advanced DAS can also improve the reliability of distribution network due to reduction of
outage duration.
2 Fundamental policy of this project
2.1 Fundamental policy
This project will be recommended to implement based on the following fundamental policy.
3
Application of renewable energy such as Solar Power → Solution for shortage of power
Application of EMS to control switch of Solar power and Battery → Solution for connecting to
distribution network
Peak-cut by DR → Energy saving and efficiency
Reduction of distribution loss by DAS and AMR → Energy saving and efficiency
Improvement of reliability (reduction of outage duration) by DAS → High reliability for power
supply
2.2 Problems and the solution
As for promoting this project, the problems on Peak-cut by DR and Cost of solar power will be considered
and the following solutions will be proposed.
1) Peak-cut by DR
Peak-cut by DR are proposed as follows.
Large customer: Unimportant loads such as Air Conditioner (A/C) are switched off by DR.
Normal customer: All of loads are switched off by DR.
Based upon customer survey, large customers may well accept the outage of unimportant load for short
duration (example: 30 minutes) due to no outage of important load.
Normal (Small) customers are under outage for short duration, so that the dissatisfactions in the
customers are concerned in spite of short outage. As for the solution, the customers can switch on by
manual operation while the outage by DR happens. However, if most of customers will switch on, the
effect of peak-cut decrease, so that incentive is needed to advance the effect. The following incentives
are considered as ideas.
If manual operation will be implemented in the state of peak-cut, the tariff becomes much higher.
The cooperated customers can receive the privilege such as preferential tax or tariff.
The cooperated customers can receive the citation as the cooperation.
There are the following benefits as customers of Peak-cut by DR.
Residential customer under the planned outage for Peak-cut can not recover the outage so far but
this proposed system can recover the power by the manual operation on condition that the customer
pays higher tariff.
Large customer stopped all of power under the planned outage so far but the outage by this
proposed system can be limited to unnecessary load such as A/C etc. Therefore, the important load
such as product facilities can keep the power even though the planned outage for Peak-cut will be
4
implemented.
Regarding the peak-cut by DR, it is necessary to consider whether there are some problems for law in
Vietnam or not. According to Ministry of Industry and Trade (MOIT), there are no problems on law
for the peak-cut but take care to cut off frequently because the National Diet will be possible to discuss
due to a lot of complaints of customers. Vietnam Electricity (EVN) has already cut off the customers on
each substation, so that we think this better outage procedure for each customer will be acceptable.
Regarding the peak-cut by DR, there are no problems on law in Vietnam but the incentive shall be
considered in order to accelerate the energy efficiency.
2) Renewable energy such as Solar Cell
According to the International Forum on Wind Energy Development of Vietnam on 5/11/2009, Solar
Energy in Vietnam is 4~5 kWh / m2 , so that the conversion to kW is around 0.1 kW / m
2 . The area of
Vietnam land is around 330,363 k m2 and the capability of power can be calculated as follows.
Assumption: 1/10 in land is available for installation of Solar Power.
kW x 330,000 x 106 x 1/10 = 3,300 GW
The capability of solar power is huge and the solar is effective for solution on increasing peak load.
However, batteries shall be equipped in order to solve unstable generation problems influenced by
weather condition etc, so that the cost becomes more expensive.
In case of Japan, the following support system on law has been carried out, so that the Solar Power
could be expanded up to 1.4GW in 2005 and will be anticipated to reach to 14~28 GW in 2020.
Government support a part of the installation cost.
Power companies have purchased with higher tariff (48 yen /kWh) for the Solar Power since
November in 2009. However, the increased expenses on power companies can add to the normal
tariff as green cost.
In case of Vietnam, the supporting money for renewable energy will be considered on new law of
energy efficiency which will be set up on 1st of January in 2011. However, the supporting money is
small and is limited, so that the solar power will not expand widely. In order to accelerate the
installation of solar power, not only is the cost decreased, but also the additional supporting money or
other regulation is needed.
When a lot of renewable plants will be connected to the distribution network in EVN, problems such as
voltage-drop / safety etc occur. The following solutions against the problems will be considered in this
5
project and will be confirmed.
Solar cell with battery will be installed to 2 locations.
The reversed power and battery are monitored and controlled by EMS.
EMS also monitors and controls the switch for the solar.
2.3 Advantages
There are mainly five economical benefits as follows.
A) Reduction of outage duration by DAS
B) Effective construction of Substations by DAS
C) Reduction for technical loss of MV line with improvement of load unbalance by DAS
Non-technical loss reduction by AMR including smart meter
D) Solution of power shortage by Solar power
E) Effective construction of Power Generators by DR
before the project
(a)
after the project
(b)
(a)-(b)
A) Decrease of Power Failure 373 min. 77 min.
-296min.
( 4.93 h)
B) Improve of maximum
average capacity rate of the
substation
75% 83% +8%
C) Decrease of loss
(technical loss of MV line)
(non-technical loss)
(1.72%)
(2.43%)
(1.16%)
( 1.3%)
( -0.56%)
( -1.13%)
D) Solar Power Generation - 57,200 kWh/y +57,200 kWh/y
E) Demand Control by cutting
demand caused by air-
conditioners
- 255MW*2 h
*40 days/y
255MW*2 h
*40 days/y
3 Overview of this project
3.1 Fundamental idea of Project
The details of this project based on the fundamental policy are as follows.
1) Smart meter will be installed to all of customers in Phu Tho Power Company, so that AMR and DR can
be implemented.
6
2) DR can control the following load.
Residential customer: All of loads are switched off during short duration (ex: 30 minutes).
Large customer: Unnecessary load except product line etc can be switched off.
3) Solar power system with battery as asset of EVN will be installed to 2 areas as pilot project and be
connected to MV distribution feeder directly. EMS in control center can monitor and control the reverse
current and the battery.
4) Servers and operator consoles for Advanced DAS with EMS are installed in Dispatch Center for existing
Supervisory Control and Data Acquisition (SCADA) and monitor / control 110kV primary substations
and distribution network in Phu Tho Power Company. Other servers for AMR, DR and EMS etc are
installed in Control Center of Phu Tho Power Company and are connected to the advanced DAS
through LAN and Fiber Optic communication network.
5) Automatic Load Break Switch (ALBS) for Over Head (OH) will be applied as new equipment.
Automatic Ring Main Unit (RMU) for Under Ground (UG) will be also installed as new facilities in
existing room. The existing RMU of manual type will be removed to other suitable feeder as manual
type.
6) Fiber Optic will be applied as backbone network of communication and ZigBee will be applied for last
one mile communication between Remote Terminal Unit (RTU) and customers for at least 10 years.
7
3.2 Configuration of Project
The basic system configuration including all of projects is shown in the following figure.
Control Center
110kV/15kV
Substation
Distributiion feeder
(Overhead)
Distributiion feeder
(Underground)
FCB
LBS
TRD
VS
VCB Road
Solar Power
RTU
Advanced DAS Server
Smart Meter
Switch
WHM
Comunication
AMR Server
Console
FCB
VSRMU
Battery
PCSPCS
RTU
Concentrator
Concentrator
M-RTU
FEP
Optical fiber
Network
8
3.3 Project cost
The total amount of the project is around 42 MUS$ and the detail is explained as follows.
Scope Quantity
Cost
Remarks Foreign
MUS$
Local
MUS$
1. Advanced DAS / SCADA with EMS EVN HCMC Control Center
1 system
6.5
0.7
1. Advanced DAS with SCADA is installed in existing SCADA center and can implement energy management of distribution feeder.(Solar Power)
2. AMR/DR is installed in Pho Tho Power
Company and is connected to Advanced DAS by data link of Fiber Optic
2. AMR / DR Phu Tho Power Company
1 system
3. Substation facilities 4 SS 1.2 0.2 0.3 MUS$ x 4 = 1.2 MUS$ 1
st stage: 4 substations (110kV)
2nd
stage: expand to 34 substations
4. New RMU 25 units 1.2 0.1 45 kUS$ x 25 = 1,125 kUS$ → 1.2 MUS$
5.New OH DAS equipment
86 units 1.3 0.1 15 kUS$ x 86 = 1,290 kUS$ → 1.3 MUS$
6. Smart Meter, Single-phase,
Three phase Concentrator
90,000 units 8,000 units
196 units
17.0 1.0 120US$ x 90,000 = 10.8 MUS$ 700US$ x 8,000 = 5.6MUS$ 3,000US$×196=0.6MUS$
7. Solar Power 2 units 0.3 0.1 20kW: 0.15 MUS$ 0.15 x 2 = 0.3 MUS$
8. Fiber Optic 0 0 0 Use existing Fiber Optic
9.Engineering Service 1 2.5 0.7 Including Training in Japan
Sub Total - (30.0) (2.9)
10.TAX 1 6.6
0.3
Sub Total x 20% x 10%
11.Physical Contingency
1 1.5 0.1 5% x Sub Total
12.Price escalation 1 0.9 0.3 2.4% for Foreign 8.4% for Local
Total 39.0 3.6
Exchange rate: $1 = 19,491VND = 80.89 yen (by Tokyo Mitsubishi UFJ bank 10/29 2010)
9
3.4 Overview of preliminary economic analysis
The economical benefits of the project are summarized as follows.
Economic benefit Financial benefit
1.Decrease of Power Failure 53,512 US$/y 19,563 US$/y
2.Improve of maximum average capacity
rate in the substation
0.939mil.US$/y
( Total 18.78 MUS$:
20 years)
0.939mil.US$/y
( Total 18.78 MUS $:
20 years)
3.Decrease of loss
(technical loss)
(non-technical loss)
532,476 US$/y
1,074,431 US$/y
532,476 US$/y
1,074,431 US$/y
4.Solar Power Generation 5,458 US$/y 5,458 US$/y
5.Peak Demand Control by cutting
demand caused by air-conditioners
-711,713 US$/y
6.885 MUS$/y
-711,713 US$/y
2.470 MUS$/y
3.4.1 Financial Analysis
The Financial Internal Rate of Return (FIRR) of the project is of 6.90%.
FIRR Net Present Value (NPV)
( Discount rate=6.95%)
Base case 6.90% -0.13 MUS$
Initial investment increases by 10% 6.53% -1.28 MUS$
Operation & Maintenance(O&M) cost increases by
10%
6.78% -0.51 MUS$
Unit price of power purchase decreases by 10% 6.51% -1.28 MUS$
3.4.2 Economic Analysis
The Economic Internal Rate of Return (EIRR) of the project is of 22.79%.
EIRR NPV
(Discount rate=10.0%)
base case 22.79 % +30.35 MUS$
Initial investment increases by 10% 20.69% +27.43 MUS$
O&M cost increases by 10% 22.69% +30.09 MUS$
Construction cost of a new gas turbine power plant
decreases by 10%
20.90% +25.49 MUS$
10
3.5 Environmental and social analysis
3.5.1 Project impact on environmental and social aspects
Based on the JETRO Guidelines for Environmental and Social Consideration as of July 2009,
environmental and social assessment items have been examined in this study for the future scoping
conducted in feasibility studies and Environmental Impact Assessment (EIA) conducted at the stage of
project implementation. When examining project impact on environmental and social aspects, check
items in the Screening Format and the Environmental Checklist (6. Power Transmission and
Distribution Lines) of “JICA Guidelines for Environmental and Social Consideration” (April 2010) have
been referred.
The summarized results are as follows.
1) Sensitive Areas
None of the sensitive areas in the following table are found.
2) Sensitive Characteristics
The sensitive characteristics are not applied to the project.
3) Impacts on Environment
Impacts on environment caused by the project implementation have been analyzed, so that there are
slight affections but no problems due to the easy countermeasures.
3.5.2 Environmental Legal Framework and Application to the project
The Law on Environmental Protection (No.5212005/OH11) replaced the former law stipulated in 1993
and has been implemented since 2006. This law is the basis of EIA and of environmental protection in
Vietnam.
Based on the law, this project is estimated as follows.
1) Strategic Environmental Assessment (SEA )
SEA is not applicable to the Project.
2) EIA
11
EIA will not be applicable to the Project.
3) Environmental Protection Commitment (EPC)
The Project Owners are required to elaborate the EPC when EIA is not required. They are allowed to
start their production and business activities after registering the EPC.
4 Implementing schedule
The tentative implementing schedules are estimated as shown in the following figure as Japanese ODA
loan based on experiences.
Implementing Schedule on Japanese ODA loan
Item 2011 2012 2013 2014 2015
Preparation
Basic design and EVN HCMC / JICA appraisal
Approval by GOJ / GOV
E/N, L/A
Selection of consultant
Engineering Service
Detailed Design
Tendering Stage
Selection of Contractor
Construction
Design
Manufacturing
Installation and test
Commencement
12
5 Feasibility study
5.1 Review on Availability of Finance
Export credit is considered as one of the finance method but Japanese ODA (Yen loan) is the best solution
in the analyzed finance method.
5.2 Feasibility for implementing project
The implementation of this project is feasible as follows.
This project corresponds to Vietnam policy to solve the shortage of power and the low reliability.
This project also corresponds to the needs of EVN HCMC as implementing organization.
According to economical analysis, FIRR is of 6.90% and EIRR is of 22.79%.
(In case of Japanese ODA loan, there is grace period of 10 years and the interest rate is low such as
1.2%.)
5.3 Necessary activities
It is necessary to carry out the following activities in Vietnam side in order to advance this project.
Support of Vietnam government to accelerate the application of renewable energy
Incentive for customers to allow the outage for peak-cut
Request of Japanese government support for technology and finance from Vietnam government
6 Competitive ability of Japanese Company
6.1 DAS
Concerning reliability of power supply, higher technology has been already existed in Japan.
There is strong position compare with other countries.
Distribution network technology in Japan has progressed to solve a lot of subjects since 1960.
DAS was also same, it was kept progressing for improvement of supply reliability and efficiently operation
of equipment.
This DAS is applied voltage type. There is a few countries to apply this type, but this voltage type of DAS
should be definitely better technology than the others. The advantages are;
Judge and split for failure section can be applied without Central Processing Unit (CPU) and
13
communication lines
System upgrade can be applied step by step, if necessary.
Initial cost should be lower than current type which is introduced in Europe.
As of now, it is still continuing to progress for technical innovation by DAS business in Japan.
Combine advanced DAS core technology of Japan and inexpensive distribution network equipment which
made in China can create advantage of DAS.
6.2 AMR System
It is proud for higher reliability of power distribution monitoring technology which was grown in Japan.
Advanced AMR system has been already developed by Japanese companies based on existing higher
technology.
This advanced AMR system can realize two way communications with customers such as demand response
and control internal switch in smart meter as well as measure power consumption at the place from far
away.
Having proof experiment, corporate with NEDO and the state government of New Mexico, proof
experiment has already started that how much effect and influence will be occurred by realize real time
pricing and DR which are told difficult in Japan to test.
This core technology can be applied in this project as well, so that Japanese company can stand strong
position and develop lower cost compare with the other country.
6.3 EMS
It is proud for higher reliability of power distribution monitoring technology which was grown in Japan.
Advanced EMS has been already developed by Japanese companies based on existing higher technology.
This advanced EMS can corporate efficiently between many kind of power supply such as solar power and
wind power within smart grid and storage battery. And it is possible to be realized higher supply reliability
and distribution network operation.
Moreover, Curb on fluctuations equipment with storage battery which is used for to prevent influence from
sudden out put fluctuation of Photovoltaic (PV) system, has already developed by Japanese companies.
Relating this technology, proof experiment which will be understood effect and influence on distribution
network in Miyakojima island by install PV system, has already started by independent type of distribution
14
network in Miyakojima of The Okinawa Electric Power Company, Inc.
This technology can be applied in this project as well, so that Japanese company can stand strong position
and develop lower cost compare with the other country.
6.4 Solar Power
Temperature of HCMC is very hot, so that the panel of crystal silicon type with high efficiency can not be
applied to HCMC even though Japanese company has excellent competence. The panel of silicon
amorphous type is proposed in this report due to high temperature characteristics and low cost but other
foreign manufactures can make easily. In order to get higher power in the same space, hybrid type of
crystal silicon and silicon amorphous will be recommendable in detail design. In this case, Japanese
company can be applied with high competence.
As for battery, Lithium Ion battery is recommended in this report and the development has been carried out
in many countries. Japan also has developed as Japanese government projects, so that the high capacity
type for storage of power will be able to get high competence.
Furthermore, Japanese company has high competence for the inverter for solar and battery due to high
efficiency, high characteristics and familiarity to DAS.
6.5 Integrated System
Under becoming aggressively for activity on smart grid, government of every country and every standard
party also aggressively involve to advance standardization of equipments.
In Japan, ministry of economy, trade & industry put target to standardize in international and selected “7
Project and 26 items” as important items to keep strong position of Japanese companies.
They proposed to IEC etc. and put target to be established within three years.
There are 7projects as shown below.
1) Wide-Area Situational Awareness (WASA)
2) Storage battery for distribution network
3) Control of distribution network
4) DR
5) Storage battery for consumer side
6) Electric Vehicle (EV)
7) Advanced Metering Infrastructure (AMI)
15
There is all necessity technology in these projects as below.
1) DAS
2) DR network
3) Wide access communication for meters
4) Short distance communication for meters
5) Optimized management for storage battery for distribution
After fix international standard, Japanese companies can be stronger position for cost competitiveness.
In case that this proposed smart grid will be applied to Vietnam, the system and communication network
can be applied to future technology such as Home Automation (HA), battery by EV etc, so that Japanese
company can keep the high competence as the supplier of the system and communication network.
7 Schedule to realize this project and the objection
7.1 Detail schedule to realize the project
It is necessary to implement the following activities up to starting this project by Japanese ODA loan.
Request of this project (from Vietnam to Japanese Government): the first half in 2011
Implementation of Special Assistance for Project Formation (SAPROF) by JICA Grant: in 2011
E/N, L/A between Vietnam and Japanese government: the first half in 2012
After L/A, the project such as selection of consultant etc will be implemented.
7.2 Objection and the solution
The priority of Vietnam for the smart grid project is lower than the current investment such as power
generation, construction of transmission line / substation and construction of distribution feeder, so that the
investment will be limited.
In case of EVN HCMC, the income is around 800 MUS$ in 2009. The investment of this project is around
40 MUS$ which is not so large as Japan but the project cost means around 5% of the income as EVN
HCMC, so that long term to realize this project will be needed due to other high priority projects. This is
normal case for new project because client does not feel the convenience and necessity due to no
experience.
In order to overcome this blockade, the support of Japanese government such as Demonstration test project
16
supported by NEDO is needed to apply for the model area as pilot project.
After the pilot project, EVN can understand the necessity and feel the benefits, so that the system using
Japanese excellent technology can be expanded to other areas of EVN HCMC and other cities. Moreover,
this system will be expected to expand to other Asian countries and become de-facto standard.
Korea has already applied DAS project in Hai Phong as Grant and AMR project in Hanoi as also Grant. As
for Solar system, Energy Assistance France and Schneider have applied the Build, Operate and Transfer
(BOT) pilot project to Quang Binh province in central Vietnam. Competition between foreign countries and
Japan are very hard but these competitive countries proposed single function as one of smart grid system.
Japan can propose all of functions in smart grid project based on a lot of experience and excellent
technology, so that the effect for energy efficiency in Vietnam becomes much better.
In order to keep the highest position in smart grid system, it is important to obtain the initiative with high
speed. Therefore, Japanese support (ex: Demonstration test project supported by NEDO) shall be quickly
applied for Vietnam as pilot project.
17
8 Map of project area in survey country
Project area: Phu Tho Power Company (District10 and 11) of EVN HCMC
Scale: 1:42,000
Dist10 and11,Project area in HCM city
1-1
Chapter 1 Outline of the Country and Sector
1.1 Economy and Financial Situation of the Country
(This sub-clause is omitted as per contractual condition.)
1-2
1.2 Outline of the Project Sector
The sector of this project is an electric power sector. EVN which is a national organization is governing the
electric power sector of Vietnam under the supervision and management of MOIT.
1.2.1 EVN Organization
EVN is performing directly and indirectly most of the power generation, transmission and distribution both
in wholesale and retail supply of electric power. Moreover, EVN holds, as a holding company, some
subsidiaries, and those subsidiaries are classified into the direct control companies and joint venture
companies.
The organizational chart of EVN is shown in Fig. 1-2-1.
1-3
Fig
. 1-2
-1 E
VN
Org
aniz
atio
nal
Char
t
Sourc
e:
pre
par
ed b
ased
on i
nfo
rmat
ion f
rom
EV
N
1-4
The electric power sector structure by electric power flow is shown in Fig. 1-2-2.
Fig. 1-2-2 Electric Power Flow of Vietnam
[Generation] EVN direct control company EVN group company IPP entrepreneur
[HV Transmission]
[MV Distribution] EVN self-support accounting company: Five Power Companies
[LV Distribution]
Commune
Consumer
Source: Result of field survey with EVN
1.2.2 Power Demand and Supply
1) Maximum power demand
The maximum power demand of Vietnam is 13,867 MW in 2009, and has been increasing with average
annual growth rate of 11.9% during 2001 to 2009.
2) Sales energy
The sales energy of EVN is 76,046GWh in 2009, and has been increasing with average annual growth
rate of 13.7% during 2001 to 2009.
3) Electric power generation
Electric power generation is 87,109GWh in 2009, and is increasing with average annual growth rate of
14.3% during 2001 to 2009, which is shown in Table 1-2-1 below.
EVN direct control company: NLDC Transmission companies
1-5
Table 1-2-1 Power Demand by Area (2001 to 2009)
Area Item 2009 Growth rate
2001 to 2009
Growth rate
2006 to 2009
Growth rate
2008 to 2009
Whole
Country
Demand
(GWh)
Power
generation
(GWh)
Peak (MW)
76,046
87,109
13,867
14.3%
13.7%
11.9%
13.6%
12.9%
10.6%
12.8%
14.7%
9.7%
Northern
Area
Demand
(GWh)
Peak (MW)
29,445
6,207
13.8%
12.3%
13.4%
12.4%
14.5%
22.5%
Central Area Demand
(GWh)
Peak (MW)
7,426
1,482
14.1%
11.7%
12.4%
10.9%
13.7%
17.7%
Southern
Area
Demand
(GWh)
Peak (MW)
39,175
7,001
14.7%
12.9%
13.8%
11.4%
11.6%
11.9%
Source: IE
4) Power Demand Forecast
The demand forecast is made by the 6th PDP which was announced in July 2007, and at present the 7th
Power Master Plan is being drawn up after the subsequent world economy depression etc. Therefore, the
demand forecast made in the draft 7th PDP which the IE and the JICA TA team announced in a
stakeholders meeting in August 2010 is taken into consideration in this study. According to it, the
demand forecast till the year 2030 is made as shown in Table 1-2-2.
Table 1-2-2 Demand Forecast
Item
Forecasted by 2010 2015 2020 2025 2030
Peak (GW) IE 16 31 52 77 110
JICA 18 29 47 71 104
Demand
(GWh)
IE 87,665 169,821 289,882 430,867 615,205
JICA 88,017 156,341 262,545 394,678 580,795
PDP VII 87,700 164,900 257,200 381,100
Demand
growth rate
(%)
IE 14.4 14.1 11.3 8.2 7.4
JICA 14.4 12.2 10.9 8.5 8.0
Source: IE
According to the IE proposal, it is expected that electric power demand would grow with 12.7% per
annum in average (11.5% per annum by JICA TA team proposal) until the year 2030, and therefore
electric power development has become a pressing need.
1-6
The energy demand (GWh) of Table 1-2-2 is shown in Fig. 1-2-3 in a graph. Assumption of IE has
exceeded assumption of the JICA TA team a little. Anyhow, energy demand (GWh) is assumed to
increase by about 3 times in 2020 and by about 6 times in 2030 compared with the energy demand in
2010.
Fig. 1-2-3 Demand Forecast
Demand Forecast
0
100,000
200,000
300,000
400,000
500,000
600,000
700,000
2010 2015 2020 2025 2030
Year
GW
h IE
JICA
Source: IE
5) PDP
According to the 7th draft PDP which IE and JICA TA team announced in stakeholder‟s meeting in
August, 2010, electric power development by 2020 are planned as shown in Table 1-2-3.
Table 1-2-3 PDP
Power generation 2010 2015 2020
Electric power production (TWh) 100.9 194.3 329.4
Maximum demand (MW) 16,048 30,803 52,040
Total Installed capacity (MW) 19,937 43,050 69,433
1) Hydraulic power and pumped
storage (MW)
7,726(38.8%) 14,351(33.3%) 17,455(25.1%)
2) Oil & gas fire (MW) 7,703(38.6%) 10,582(24.6%) 13,625(19.6%)
3) Coal fire (MW) 3,231(16.2%) 15,365(35.7%) 32,385(46.6%)
4) Import (MW) 750(3.8%) 1,073(2.5%) 1,839(2.6%)
5) Renewable energy (MW) 527(2.6%) 1,679(3.9%) 3,129(4.5%)
6) Nuclear power (MW) 0 0 1,000(1.4%)
Reserve (MW) 3,889 12,247 17,393
Source: IE
This plan shows that the power generation facility for the year 2015 is planned to be reinforced to 2.2
times of that of the year 2010, and the power generation equipment for the year 2020 as 3.5 times of the
1-7
same, and therefore the implementation of the plan is urgent need. Moreover, in view of the kind of
power generation it is indicated that the power generation ratios by means of hydraulic power and oil
gas tend to fall from now on and the ratio of coal fire generation is going to increase. Furthermore,
renewable energy is also planned to increase to about 6 times in 2020 compared with 2010 and nuclear
power generation (1,000 MW) is expected to introduced in 2020.
Fig. 1-2-4 shows the power generation facility capacity based on the above-mentioned Electric Power
Development Plan as well as actual record.
Fig. 1-2-4 Actual and planned capacity of power generation facility
Source: Created based on IE and EVN data
6) Daily Load Curve
The daily load curve (November 12, 2009) which recorded the maximum demand of the Vietnam power
systems in 2009 is shown in Fig. 1-2-5.
0
10000
20000
30000
40000
50000
60000
70000
80000
2002 2003 2004 2005 2006 2007 2008 2010 2015 2020
Year
Inst
alle
d C
apac
ity
(MW
)
1-8
Fig. 1-2-5 Maximum Daily Load Curve of Vietnam Power System (2009)
EVN Max. Daily Load Curve in 2009
0
2000
4000
6000
8000
10000
12000
14000
16000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time
MW
Source: Created based on EVN data.
This daily load curve is calculated by the electric energy for every hour, and therefore the short-time
peak value is not reflected. The curve indicates that‟s the maximum peak demand occurs due to a
lighting load in the evening, but it turns out that the demand of daytime is also large. Moreover, the
annual load factor in 2009 is 63% from the Table 1-1 data, which is almost comparable to that of
Japanese electric power companies. EVN estimated a ratio of A/C load (W) against peak load (W) in
summer time to be approximately 40%.
In addition the monthly average daily load curve of “the whole country” and “the southern region” for
the year 2009 are shown in Fig.1-2-6 and Fig. 1-2-7 respectively.
Fig. 1-2-6 Monthly Average Daily Load Curve of Vietnam Whole Country (2009)
Monthly Average Daily Load Curve (Whole Country)
0
2000
4000
6000
8000
10000
12000
14000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time
MW
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Source: Created based on EVN data.
1-9
Fig. 1-2-7 Monthly Average Daily Load Curve of Southern Region (2009)
Monthly Average Daily Load Curve (Southen Region)
0
1000
2000
3000
4000
5000
6000
7000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time
MW
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Source: Created based on EVN data.
1.2.3 Power Generation Facility
The power generation capacity of Vietnam is 15,678 MW as of the end of 2008, EVN holds about 68% of
them, and IPP is about 32%. The structure of the generation facility is shown below.
Table 1-2-4 Power Generation Facility of Vietnam
Power Generation Facility Installed capacity (MW)
EVN power generation facility total 10,634
Hydropower generation (5,499)
Coal fire power (1,545)
Oil fire power (198)
Gas turbine (3,107)
Diesel (285)
IPP, BOT 5,044
Grand Total 15,678
Source: EVN Company profile 2008 to 2009
The power generation structure for the year 2008 is shown in Fig. 1-2-8.
1-10
Fig. 1-2-8 Power Generation Structure 2008
Source: EVN Company Profile 2008-2009
1.2.4 Transmission and Distribution Facility Outline
The outline of the transmission and distribution facility of EVN is as shown in Table 1-2-5.
Table 1-2-5 Transmission and Distribution Facility in 2007 and 2008
Electric-power-distribution equipment 2007 2008
500kV Transmission line length (km) 3,278 3,455
220kV Transmission line length (km) 7,141 7,988
110kV Transmission line length (km) 11,079 11,786
500 kV Transformer number 15 15
500kV Transformer total capacity
(MVA)
7,050 7,050
220kV Transformer number 88 92
220kV Transformer total capacity
(MVA)
14,727 16,102
110kV Transformer number 583 617
110kV Transformer total capacity
(MVA)
20,828 22,058
MV Distribution line length (km) 121,011 124,910
LV Distribution line length (km) 126,261 142,652
MV Transformer number 944 923
MV Transformer total capacity (MVA) 2,851 2,829
Distribution transformer number 194,607 210,888
Dist. transformer total capacity (MVA) 29,757 33,552
Source: EVN Company Profile 2008 to 2009
Hydropower 35%
Coal fire 10%
Oil fire 1%
Gas turbine 20%
Diesel 2%
IPP, BOT 32%
1-11
The 500kV power system and major power plants are shown in Fig. 1-2-9.
Fig. 1-2-9 500kV System and Major Power Development point by 2020
Source: “Electric Power Industry of Foreign Countries 2008", JEPIC( Japan Electric
Power Information Center Inc.)
1-12
1.2.5 Electrification Ratio
A national household electrification rate is 94.5% as of 2008.
1.2.6 EVN Operational Target
In consideration of the above mentioned power system situation, EVN has held up the operating target as
follows:
1) Ensuring the energy security for national development,
2) Implementing the roadmap for market driven tariff under the Government directions,
3) Gradual setting up the electric power market,
4) Carrying out the comprehensive program for investment, rehabilitation and upgrading of the rural and
mountainous power grids to reach the target that by 2020 most of the rural households will be accessible
to electricity as stipulated in the Decision 1855/QD-TTg (dated 27 December 2007) issued by the Prime
Minister.
According to the above-mentioned prime minister decision, the policies of the national energy development
strategy are:
1) To prioritize the implementation of the policy in assurance of nation energy security towards
synchronous development of various energy sources; to exploit and use domestic energy sources in an
economical manner; to reduce dependence on imported petroleum products; to export a rational quantity
of coal (in the immediate future, to reduce annual coal export); to connect regional energy system; to
expand petrol and oil reserve; and to combine energy security with assurance of defense and national
security,
2) To introduce the market mechanism of energy price,
3) To prioritize the development of new and renewable energy, bio-energy, and nuclear energy, to
encourage foreign investment,
4) Policy on encouraging the economical and efficient use of the energy must indentify specific
conservation requirements on sectors which consume a large volume of energy; to encourage the
application of energy-saving equipment and technologies,
5) Policy on environmental protection aims to ensure the harmony between energy exploitation and use
1-13
with environmental management.
1.2.7 Electricity Tariff
The electricity tariff, which is universal for the whole country, is shown in the category-wise in Table 1-2-6.
Table 1-2-6 EVN Electricity Tariff (effect from March 1, 2010)
No. Demand Classification Time Zone
Normal hour
Mon.-Sat. :
4:00 to 9:30
11:30 to 17:00
20:00 to 22:00
Sun :
4:00 to 22:00
Off-peak hour
22:00 to 4:00
Peak hour
Mon.-Sat. :
9:30 to 11:30
17:00 to 20:00
1 The retail price for manufacturing
unit VND VND VND
1.1 110 kV and more 898 496 1,758
1.2 From 22kV to less than 110 kV 935 518 1,825
1.3 From 6kV to less than 22 kV 986 556 1,885
1.4 Fess than 22 kV 1,023 589 1,938
2 The retail price for irrigation and a
drain pump
2.1 More than 6 kV 690 281 1,269
2.2 Less than 6 kV 717 292 1,331
3 Administration, non-business.
3.1 Hospital, school, nursery
more than 6 kV 1,009
less than 6 kV 1,063
3.2 Public lighting
more than 6 kV 1,124
less than 6 kV 1,177
3.3 Administration, non-business.
more than 6 kV 1,159
less than 6 kV 1,207
4 Enterprise unit
4.1 More than 22 kV 1,684 902 2,943
4.2 From 6kV to less than 22 kV 1,766 1,073 3,028
4.3 Less than 6 kV 1,846 1,065 3,193
5 Stepping retail price for residence
for the first 50 kWh 600
for 51-100 kWh/month 1,004
for 101-150 kWh/month 1,214
for 151-200 kWh/month 1,594
for 201-300 kWh/month 1,722
for 301-400 kWh/month 1,844
for more than 401 kWh/month 1,890
6 Wholesale price for rural area
1-14
6.1 Wholesale price for rural residence
for the first 50 kWh 432
for 51-100 kWh/month 753
for 101-150 kWh/month 886
for 151-200 kWh/month 1,227
for 201-300 kWh/month 1,326
for 301-400 kWh/month 1,420
for more than 401 kWh/month 1,455
6.2
Wholesale price for water pump for
irrigation and drainage at the total
meter
703
6.3 Wholesale price for other purposes at
the total meter 1,010
7 For collective zone and community
7.1 For collective zone and community
For city, country town :
a) The substation invested by the Buyer
for the first 50 kWh 522
for 51-100 kWh/month 889
for 101-150 kWh/month 1,062
for 151-200 kWh/month 1,419
for 201-300 kWh/month 1,533
for 301-400 kWh/month 1,641
for more than 401 kWh/month 1,682
b) The substation invested by the Seller
for the first 50 kWh 540
for 51-100 kWh/month 914
for 101-150 kWh/month 1,099
for 151-200 kWh/month 1,466
for 201-300 kWh/month 1,584
for 301-400 kWh/month 1,696
for more than 401 kWh/month 1,739
For town, suburban district :
a) The substation invested by the Buyer
for the first 50 kWh 489
for 51-100 kWh/month 843
for 101-150 kWh/month 1,008
for 151-200 kWh/month 1,331
for 201-300 kWh/month 1,438
for 301-400 kWh/month 1,540
for more than 401 kWh/month 1,578
b) The substation invested by the Seller
for the first 50 kWh 507
for 51-100 kWh/month 863
for 101-150 kWh/month 1,032
for 151-200 kWh/month 1,379
for 201-300 kWh/month 1,490
for 301-400 kWh/month 1,595
for more than 401 kWh/month 1,635
7.2 The wholesale price for other
purposes
1-15
7.2.1
City (except for apartment building,
new town, suburban town and town
(all voltage))
1,020
7.2.2 Apartment building and new town
more than 22 kV 1,574
from 6kV to 22 kV 1,687
less than 6 kV 1,763
8 The wholesale price for industrial
zone in 110-kV busbar
8.1 Transformer capacity 100MVA and
more 875 483 1,714
8.2 Transformer capacity 50MVA to less
than 100MVA 871 479 1,706
8.3 Transformer capacity less than 50MVA 859 473 1,686
Source: Received from EVN HCMC.
1.3 Situation of Project Area
The project area for this study is Phu Tho area of HCMC where 8.3% of Vietnamese population lives. Phu
Tho is located in the central part of the city and EVN proposed the area at the time of the first field survey.
The power company that supplies electric power to this area is EVN HCMC.
1.3.1 Situation of EVN HCMC
Many domestic and foreign companies is engaged in business in HCMC as a center of the Vietnam
economy, and it‟s electric power demand is large. The amount of electricity consumption in EVN HCMC
area occupies 18% of a national consumption in 2009. According to Vietnam household living standard
research results in 2008, the household electrification rate is 99.9% for the year 2008 since it is a big urban
area.
EVN HCMC is one of the five electric power distribution companies of the whole country which shares
from a 110-kV system to distribution voltage. It was established in 1976 and electric power is supplied to
24 districts of HCMC from 15 power distribution offices at the moment. Moreover, the major business is
supply and distribution of electricity up to 110 kV, electric power engineering (investigation, design, testing,
repair, manufacturing), and supply & transportation of electric item, consulting, electric power civil works,
information service, etc.
1-16
The outline of EVN HCMC is shown below. :
The number of employees (2009) 7,383 persons
The number of consumers, energy sales, the maximum demand, energy loss are as shown in Table
1-3-1.
Table 1-3-1 Outline of EVN HCMC
Year 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009
The number
of consumers
(in 1000)
860 955 1,063 1,153 1,228 1,325 1,412 1,508 1,601 1,676
Energy Sales
(GWh)
5,621 6,480 7,498 8,362 9,166 9,850 10,727 11,560 12,365 13,262
Maximum
Demand
(MW)
1,051 1,254 1,374 1,506 1,676 1,692 1,889 2,047 2,178 2,245
Sales
(in million
VND)
4,553 5,313 6,378 7,889 8,721 9,388 10,300 12,347 13,436 15,821
Energy loss
(%)
11.16 10.44 10.10 8.51 8.29 7.28 7.21 7.07 6.18 6.03
Source: EVN HCMC Company Profile 2010
The organizational chart of EVN HCMC is shown in Fig. 1-3-1.
Although "Power Companies" (subsidiary) is described in the organizational chart, it was confirmed during
the site survey that each distribution office is still the same organization as EVN HCMC. Five to six of
these 15 offices will be scheduled to shift to the power distribution subsidiaries of self-support accounting
in 2011, and all the offices are scheduled to shift by 2015 through the enforcement period for two years
according to EVN HCMC.
1-18
The financial situation of EVN HCMC is shown below.
Table 1-3-2 Financial situation of EVN HCMC (2008, 2009)
I. ASSET & CAPITAL 2008
in million
VND
2009
in Million
VND
1. Fixed Assets by end-of-year 6,410,626 7, 119,272
2. Capital for Business Activities
by end-of-year
2,034,178 1,987,985
3. Capital for basic construction investment
by end-of-year
57,033 57,033
II. EVN DEBT
1. Total debt 12,757,578 15,085,038
2. Paid total 12,688,626 14,925,690
III. RELATION WITH THE STATE BUDGET
Paid Total 186,750 229,783
1. VAT 187,510 180,127
2. Corporation income tax 41,917 31,956
3. Tax on capital 28,462 3,929
4. Import and Export Tax 5,417 3,294
5. House and Land Tax 10,876 9,895
6. Others 12,569 583
IV. BUSINESS RESULT
1. Gross turnover 13,828,693 16,324,711
2. Gross expenses 13,733,583 16,226,777
3. Profit before tax 95,109 97,935
V. PROFIT ALLOCATION
1. Gross profit 95,109 97,935
2. Corporate income tax 39,661 31,956
3. Profit after-tax 55,448 65,979
4. Receivables using paid capital 13,020 22,779
5. Retained profit 42,428 43,199
6. Established funds from retained profit 6,410,626 7,119,272
Source: EVN HCMC Company Profile 2010
The daily load curve of the weekday in October, 2010 of EVN HCMC is shown in Fig. 1-3-2. As shown in
the load curve of HCMC, the demand is increasing even the morning hours just like afternoon‟s peak hours,
and totally forms daytime peak type load characteristics. Moreover, the daily load factor serves a high
number of about 80%.
1-19
Fig. 1-3-2 HCMC daily load curve (October 2010)
0.0
500.0
1,000.0
1,500.0
2,000.0
2,500.0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Hour
Pow
er D
eman
d (M
W)
Source: SRLDC
1.3.2 Situation of Phu Tho Power Company
The outline of the Phu Tho Power Company selected as the project area is described below.
Electric power is supplied to 100,925 numbers of consumers at the Phu Tho Power Company as of the end
of August, 2010. The contract category-wise customers are as follows. :
Retail - Irrigation and drain pump: 1 house
Retail - Manufacturing industry: 4,474 houses
Company/enterprise: 8,109 houses
Retail - Residential: 87,255 houses
Others (except the above): 1,086 houses
Sum total: 100,925 houses
1-20
Further, energy sales (MWh) and sales income (million VND) are shown in Table 1-3-3.
Table 1-3-3 Energy Sales and Seles Income of Phu Tho Power Company
Energy Sales by Tariff Category
(MWh)
2007 2008 2009
Retail - Irrigation and a drain
pump
6 14 325
Retail - Manufacturing industry 147,393 138,368 130,203
Company/Enterprise 109,432 124,980 137,903
Retail – Residential 362,443 378,447 411,803
Others (except the above) 58,586 64,212 63,284
Total Energy Sales (MWh) 677,861 706,021 743,519
Sales income excluding VAT
(million VND)
798,541 853,104 981,223
Source: EVN HCMC data
According to the Phu Tho Power Company, the recovery rate of an electricity bill is about 90%.In a Phu
Tho Power Company, some digital meters have already been adopted as a watt hour meter, and the tariff
according to time zone is applied for them. This digital watt hour meter was introduced for the first time as
a pilot in 2003, and was introduced formally in 2005 thereafter. Further from now onward it is scheduled to
increase the digital type energy meters.
1.3.3 Existing Facilities and System of EVN HCMC
1) Power distribution system and facilities
The power distribution system of EVN HCMC uses the direct grounding method and its voltage levels
are 15kV and 22kV. The voltage level for all power distribution is planned to be increased to 22kV in
future. However, since HCMC has large scale distribution network,, it is assumed that complete
transition requires 10 years or more.
There are 3 types of transformers: indoor type, outdoor type, and kiosk type.
The heart of city and the suburbs use different types of overhead electric lines; i.e., 24kV XLPE made of
aluminum alloy for the heart of the city; and 3kV XLPE made of aluminum reinforced by steel for the
suburbs. Underground electric lines use 3-core XLPE.
The average line length of power distribution lines is about 5km per line and power distribution lines
are installed radially and have connected points.
Power distribution system and facilities include 630A and 800A Circuit Breaker (CB), Recloser (REC),
Disconnecting Switch (DS), Load Break Switch (LBS), and 100A and 200A fuse cutouts.
1-21
The models of typical overhead electric line and underground electric line are shown below:
Fig. 1-3-3 Model of typical overhead electric line
Source: Made by Study Team
Fig. 1-3-4 Model of typical underground electric line
Source: Made by Study Team
FCB
110kV/15kV
transformer substation
Feeder
LBS
DS DS
Recloser DS DS DS
LBS
DS
DS DS
DT DT DT Always open Always open
Always open
Always open
FCB
110kV/15kV
transformer substation
Feeder
FCB
110kV/15kV
transformer substation
Feeder
To overhead line
LBS-OFF
DT
DT
DT
DT
DT
DT
DT
RMU
RMU
RMU
RMU
RMU
RMU
RMU
LBS-ON
LBS-ON
LBS-ON
LBS-ON
LBS-ON
LBS-ON
LBS-OFF
LBS-OFF
LBS-ON
LBS-ON
LBS-ON
LBS-ON
LBS-ON
Always open
Always open
Always open
FCB:Feeder Circuit Breaker
DS:Disconnecting Switch
LBS:Load Break Switch
DT:Distribution Transformer
1-22
Actual Operation Level of 15kV Feeder is shown in Table 1-3-4.
Number of 60% to 80% of rated load current occupies 50% and Number of 40% to 60% of rated load
current occupies 30%, so number of 40% to 80% of rated load current occupies 80% in all faults.
Table 1-3-4 Actual Operation Level of 15kV Feeder
% of rated load current Percentage(%)
More than 100% 0%
80% to 100% 5%
60% to 80% 50%
40% to 60% 30%
20% to 40% 10%
Less than 20% 5%
Source: Answer from EVN HCMC
2) Substation
Boundary between transmission and distribution company is 110kV in Vietnamese electric power
facilities. Then EVN HCMC as a distribution company owned 34 distribution substations of voltage
hierarchy 110kV/15kV. Typical single line diagram of distribution substation is shown Fig.1-3-5.
Typical distribution substation has a single bus-bar and 2 transformers. Characteristics of the circuit are
below.
(1) Distribution substation has 2 banks of main transformers. Typical capacity of main transformer is
63MVA. Connection of transformer is YYd connection.- it has a internal tertiary winding. Load
ratio tap-changer is installed in primary winding and it control secondary voltage automatically.
(2) Ground fault current of distribution line is so huge because 15kV winding is grounding directly to
the earth.
(3) Secondary winding is double face tap as 15kV and 22kV. Secondary voltage shall upgrade to 22kV
by future plan.
(4) Some substation has parallel capacitor banks. Those are directly connected to 15kV switch-gear
feeders.
1-23
Fig.1-3-5 single line diagram of typical distribution substation
Source: Made by Study Team
3) SCADA
EVN HCMC uses SCADA by ABB company, which is installed in the load dispatch and communication
center. It remotely monitors 25 110kV/15kV transformer substations out of 37 transformer substations
in the district of EVN HCMC through optical communication network TM measurement and breaker
states). The SCADA remotely controls the 15kV power distribution line breaker for two 110kV/15kV
transformer substations (of the above-mentioned 25 substations).
Note that there are four 110kV/15kV transformer substations in the district controlled by Phu Tho Power
Company. They remote-monitor the open/close states of 15kV power distribution line breakers but no
remote control is provided.
110/15kV (22kV)
63MVA Tr.
110kV Bus
15kV Bus
Capacitor
1-24
Fig. 1-3-6 Conceptual diagram of SCADA operating in EVN HCMC
Source: Made by Study Team
SCADA
110kV/15kV transformer substation
110kV/15kV transformer substation
110kV/15kV transformer substation
110kV/15kV transformer substation
110kV/15kV transformer substation
‥
‥
Transformer substation
Optical communication
network
No. 1
No. 2
No. 3
No. 4
No. 25
No. 37
In Phu Tho district
In EVN HCMC district
1-25
Photo 1-1 Load Dispatch and Communication Center
Source: Taken by Study Team
The photo on the upper left shows the load dispatch and communication center, the upper right shows
the monitoring/control room of SCADA in the 110kV/15kV transformer substation, the lower left shows
SCADA maintenance terminal and the optical transmission equipment maintenance terminal, and the
lower right shows SCADA monitoring/control terminal.
Since the SCADA allows the state of the entire power system to be checked easily and rapidly, a large-
scale power failure is restored rapidly by instruction (by phone) to maintenance staffs in the transformer
substation responsible for monitoring and control. In addition, new installation or addition in a
transformer substation requires data maintenance which is done once or more a month. Data
maintenance is mainly conducted for the RTU which is used by SCADA to communicate with each
transformer substation; i.e., in many cases, the maintenance is carried out to change the definition of
communication facility configuration such as transformer substation name, position of information of
feeder circuit breaker, and used line.
1-26
The photo on the left shows SCADA system configuration.
It consists of three engineering workstation servers and
operation terminal (two for monitoring and control; one for
maintenance). To improve the reliability of the engineering
workstation server for monitoring and control and LAN,
they adopt redundant configuration using hot standby. The
SCADA also includes the display panel, system timer, and
printer. Dedicated lines (one for normal use and one for
backup) for 155Mbps optical communication network
(Synchronous Digital Hierarchy) are used between the
SCADA and the 110kV/15kV transformer substation where
about 1,200bps is used by switching six channels.
In addition, each transformer substation has RTUs (RTU210/RTU/211 by ABB and their network
protocol is RP570/RP571) and transducer board by CEWE INSTRUMENT AB.
Fig. 1-3-7 Communication by SCADA
Source: Made by Study Team
SCADA
Front end computer
110kV/15kV transformer substation
RTU/transducer board
110kV/15kV transformer substation
RTU/transducer board
110kV/15kV transformer substation
RTU/transducer board
110kV/15kV transformer substation
RTU/transducer board
Photo 1-2 SCADA System Configuration
Source: Taken by Study Team
1-27
The photo on the left shows RTU and the transducer
installed in Hoa Hung transformer substation in the
district of Phu Tho Power Company, which are used
to send the information on the open/close state
(upward) of the feeder circuit breakers on five
circuits in the district of Phu Tho Power Company
and on seven circuits in other districts to SCADA.
Note that since ten years have elapsed after delivery
of the SCADA, it will be replaced in the next year
and at that timing, moved from the load dispatch and
communication center to a new building of EVN
HCMC "Green building".
Source: Taken by Study Team
Fig. 1-3-11 Configuration of optical communication network
Source: Made by Study Team
Optical transmission equipment
(Load dispatch and communication center)
Optical communication network
Synchronous Digital Hierarchy
155Mbps
Optical transmission equipment
(110kV/15kV substation)
Optical transmission equipment
(110kV/15kV substation)
Optical transmission equipment
(110kV/15kV substation)
Optical transmission equipment
(110kV/15kV substation)
Optical transmission equipment
(110kV/15kV substation) Optical transmission equipment
(110kV/15kV substation)
Photo 1-3 RTU and the transducer
1-28
The load dispatch and communication center and 25
110kV/15kV transformer substations have the optical
transmission equipment (photo on the left), which
provides an environment for 155Mbps large-volume
high-speed optical communication network. Utilizing
this optical communication infrastructure, an optical
communication network environment between Phu Tho
Power Company and 110kV/15kV transformer
substation will be established.
Photo 1-4 Optical Transmission Equipment
Source: Taken by Study Team
4) Communication
EVN HCMC has its own optical fiber cable network connecting the head office, branch offices,
transformer substations, and related companies.
Photo 1-5 State of Communication Server Room in each office
Source: Taken by Study Team
Facility at Telecommunication & IT company Facility at EVN HCMC head office
1-29
Fig. 1-3-9 shows the conceptual diagram of the optical fiber cable network owned by EVN HCMC.
Fig. 1-3-9 Conceptual diagram of optical fiber cable network
Source: Made by Study Team
The orange line indicates the optical fiber network. They connect EVN HCMC offices, substations, and
other major areas. The black line indicates the network that is utilized by SCADA for controlling and
monitoring. Such an optical fiber network is believed to have been established in the whole HCMC.
5) Solar Power Generation
Existing situations of solar power generation in EVN HCMC area are below.
-Case1-
For power supply at rural area without commercial power supply
(1) Report of site investigation
Place: Thieng Lieng island in Duen Hai Power Company area of EVN HCMC
(2) Object of installation
1-30
There is no power supply line from electric company in the island. Each house has photovoltaic cells
and lead batteries. And supply for part of the load of his house.
(3) Situation of installation
They bought and installed PV cells their own selves. They didn‟t take any support from government.
Capacity of PV cells are around 70-80W. Small capacity solar panels are installed independently.
Lead batteries are charged directly from PV cell. The installation places are roof top or on the
pole.(Photo 1-6,7) Storage energy is supply to part of the loads through simple inverter. Major loads
of each house are fluorescent light, television, radio, video recorder and fan(Photo 1-8). These loads
are connected to the batteries for unit of only lights or television. Time for using seems to be limited.
On the other hand they own engine generator in their community. It supplies electric power in night
time to every houses through the self owned distribution line. One village man who is electrical
engineer installed PV cells and connected cables(Photo 1-12). He also operates and maintains engine
generators.
An inhabitance said that these solar power systems have had no trouble during 15 years from
installed.
Although the team tried to confirm situation of the other islands, electric power company has no
information. It seemed to be situation of power supply might be almost same.
(4) Others
Solar power project provided by French government had been existed before. Its specification seems
to be almost same as the existing solar system installed by habitant. But now they are not on the
operation. And the team has not confirmed system.
EVN HCMC wasn‟t concerned with this project, so they don‟t know the actual situation of the
project. The project was provided to habitants directly by French government.
In addition to this, they have new project, 300W PV cells are provided to 210 houses of electricity
non-supply area in islands by government of HCMC will start in next month. Whole budget is
around 1MUS$.
1-31
Source: Taken by Study Team
Photo1-9 Circuit for Lighting by PV
Photo1-6 PV Panel on the roof
Photo1-10 Circuit for TV by PV
Switching by Dispatch Panel
Photo1-11 Lead Battery
Photo1-7 PV Panel on the pole
Photo1-8 Inside Situation of the Residence
Photo1-12 Private LV Feeder in the
Island
1-32
-Case2-
Solar power system connected to the grid in city
(1) Place
Tuan An Energy Joint – stock company.
The company products electric power material such as insulator, LBS or Disconnecting switch, and
renewable energy power such as solar or wind turbine etc.
Address: 71 Ten Lua Street Binh Tan district HCMC.
WEB site www.tunan.com
Counterpart: Deputy Director Mr.Chau , Vice Director Business Mr. Tuan
Source: Taken by Study Team
(2) Situation of installation of solar power panels.
Solar power panels have been installed on the roof of their headquarter building. (Photo 1-15)
Outline of facilities are below.
a. Total output is 8.4kW. This system is largest capacity in south region of Vietnam. The system
have been Installed in 2009. They have a extension plan to 12.6kW.
b. The manufacturer of solar panel is „Solar World‟ in USA.
c. System configuration is usually connected to the grid. And also battery can be charged by both
solar panel and commercial line. When commercial line is interrupted, the circuit is switched to
battery side, and operated independently. It is not sure that the system can apply reverse power
Photo 1-13 View of Headquarter office
of Tuan An Energy Joint
(PV panel on the roof-top)
Photo1-14 Major manufacture of Tuan
AN -except for PV
1-33
flow or not. But it seems to be might possible to reverse power flow. The system diagram is
shown in Fig1-3-24. Different point of Japanese similar products is battery can be charged from
commercial line. The main purpose of this system is countermeasure for outage.
d. Lead battery is contained in the system (48V-1600Ah). Battery system is charged by solar power.
If it could not get solar radiation, charged by commercial line.
e. The controller for solar panels and battery charging is developed by cooperation with Vietnamese
Academy of science and technology and Solar lab – Institute of physics. (Photo1-18)
f. Solar panels were installed with 11.5 degree's slope. It is same as latitude of HCMC and frame is
constructed with simple structure by steel.
g. Major loads supplied by solar energy are computers in office.
(3) Solar power products.
The company develops and sells small scale solar power products. But they don‟t product of solar
power panels. They use solar power panels from USA, Germany, and China. They developed
controller of solar power and battery by themselves.
At first, this system was developed with technology of SMI in USA.
Outline of major product as follows.
a. Solar power with battery system(Photo 1-19)
This system is major products of their company of solar power for domestic market. System
configuration is similar to installed system on their company.
Output power is 2kW-3kW. 300sets of this system were sold in HCMC. And 100-150sets were
sold in the other region of Vietnam.
b. Grid connection type solar power system(Photo 1-20)
This system is for connected to grid without batteries. It is possible to allow reverse power flow.
They don't have sales experience of this system in Vietnam. But it already exported 300sets
system to Germany. Sales record performance is good, because of its reasonable price.
c. Others
Products of this company can connect to small wind or small hydro. (Each of those is connected
by direct current.) They exhibited a small wind turbine in their show room. Small wind is
1-34
manufactured by Sygnus Company in Singapore (Photo 1-21). And the other company‟s products
are introduced in their brochures. But in their opinion, small wind is not adequate to Vietnamese
wind condition.
(4) Present situation of grid connection type solar power
The major need of solar power in Vietnam is countermeasure for outage. Grid connection type solar
power without batteries is not adapted to their domestic market, because it doesn‟t use in the case of
outage.
In the EVN HCMC‟s opinion, grid connection type solar power is not installed in urban area. But
probably a lot of solar powers have already connected to the grid. Power Company may be difficult
to catch the present situation.
Even in the case of battery hybrid type, Vietnamese solar power system is directly connected to the
grid. When battery capacity is full and load is few, surplus electricity will flow to the line.
In this reason, in future amount of solar power will increase, it might be cause of voltage fluctuation.
Fig.1-3-10 Diagram of PV system installed at Tuan An
Source: Made by Study Team
Commercial line
INV-CONV
Controller
Battery INV
DDCONV
PV panel
1-35
Source: Taken by Study Team
Photo1-15 PV panels Phot1-16 frame of panels
Photo1-17 Lead batteries Photo1-18 Controller for PV system
Photo1-19 Controller for hybrid
solar and battery
Photo1-20 Controller for grid
connection type PV
Photo1-21 Small wind
1-36
(Reference) Inspection of the construction fair in Vietnam
The team inspected the construction fair opened in Phu Tho Power Company area.
Relevant with renewable energy, solar power generation was not exhibited. Only solar thermal was
exhibited(Photo 1-22). Solar power generation is not general, but solar thermal is familiar in
Vietnam.
Source: Taken by Study Team
1.3.4 Existing Facilities and System of Phu Tho Power Company
1) Power distribution system and facilities
There are 19 circuits of 15kV power distribution line in the district of Phu Tho Power Company (12
overhead circuits, five underground circuits, and two overhead/underground circuits).
Photo1-22 Solar thermal panel
1-37
Table 1-3-5 15kV Power distribution line facilities in Phu Tho Power Company
Note: Connection point: Normally-open point in LBS and RMU
Source: Made by Study Team
Photo 1-23 15kV node station
Source: Made by Study Team
FEEDER DS LBS REC RMU TR Connection
point
(1) BINH THOI OH 4 3 1 40 1
(2) QUOC TOAN OH/UG 6 3 1 2 59 3
(3) PHU THO HOA OH 3 1 1 72
(4) MINH PHONG OH/UG 5 6 1 1 48
(5) VHOA LU UG 7 16
(6) QUAN Y OH 18 4 2 80 2
(7) BAC HAI OH 10 2 1 39 3
(8) SU VAN HANH OH 9 11 2 60
(9) VSI QUAN UG 7
(10) TRI PHUONG OH 18 3 1 58 1
(11) HUNG VOONG OH 18 4 1 86
(12) AN QUANG UG 6 20 1
(13) BA THANG HAI OH 19 6 2 65 3
(14) LU GIA OH 11 4 1 75 2
(15) HONG THAI OH 13 3 65 1
(16) HIEN THANH OH 13 3 1 80 2
(17) BACH KHOA UG 13
(18) PHU BINH OH 17 4 3 2 68
(19) LY VAN UG 12
TOTAL 164 57 18 18 963
1-38
The photo above shows the so-called 15kV node station which is the only facility in the district of Phu Tho
Power Company. It is installed about 3km away from 110kV/15kV Hoa Hung transformer substation and
about 1km away from Truong Dua transformer substation. Both transformer substations send power to
this 15kV node station through non-load underground lines and then, the power is distributed from here
through three underground circuits and one overhead circuit.
The photo on the left shows the recloser implemented
on 15kV overhead line and the district of Phu Tho
Power Company has 18 reclosers. If averaged, one
recloser is implemented per circuit and it is mounted
on the branch line and the basic line so that it is
suitable for urgent go-round tasks. The recloser is
shut down on detecting failure.
Photo 1-24 Recloser
Source: Taken by Study Team
Fig. 1-3-11 HIEN THANH overhead power line diagram
Source: Made by Study Team
Recloser
110kV/15kV substation
DS
LBS
DS
DS DS
DS
DS DS
R
DS: Disconnecting switch
LBS: Load break switch
1-39
Photo1-25 Load Break Switch and Disconnecting Switch
Source: Taken by Study Team
The photo on the upper left shows a load break switch and SF6 gas is adopted as insulation. There are 57
load break switches on the basic line and branch lines and 18 load break switches on connection points,
which means about 5 load break switches are implemented per overhead circuit in the Phu Tho Power
Company area. The photo on the lower right shows the disconnecting switch. The Phu Tho Power
Company area has 164 disconnecting switches on the basic line, which means about 15 disconnecting
switches are implemented per overhead circuit. At the present, 15kV devices are implemented on the lines
in the Phu Tho Power Company area. However, since lines have been designed to boost to 22kV, the
devices are ready to be replaced with that of 22kV.
Photo1-26 RMU
Source: Taken by Study Team
1-40
The photo above shows the ring main unit by SIEMENS which supports up to 24kV and adopts SF6 gas as
insulation. Modifying the ring main units for a remote control environment would take a large cost.
Therefore, I believe the best way is to replace the device with remote-controllable automation device step
by step, taking their service life into consideration. The size of the kiosk door is about 2.5m × 2m, which is
large enough for the distribution device to go through. There are 18 ring main units in the Phu Tho Power
Company area.
The photo below shows the transformer and there are various types of it; e.g., installation-on-pole type,
floor setting type. Phu Tho Power Company area has about 963 transformers. They are insulated by oil
and no SF6 gas is used.
Photo1-27 Transformer room
Source: Taken by Study Team
2) Substation
There are 4 distribution substations of supplying to Phu Tho Power Company as a model project area.
The team surveyed typical 2 types of substation. One has outdoor type switchgear – Turong Dua
substation, and another has indoor Gas Insulated Switchgear (GIS) – Hoa Uvng substation.
Outline of each substation is below.
(1) Turong Dua distribution substation
It is a semi-outdoor type substation. Extra high voltage switchgears and main transformers were
installed outdoor, and MV switchgears were installed indoor.
Communication tower was situated in the yard. It is not sure that detail of the communication
system. (Antennas, looks like for mobile phone were installed.)(Photo1-30)
There was a transducer panel setting in the room, but not connected. All facilities in the substation
1-41
might be operated directly(Photo1-31).
Digital multi-relay systems have installed on the 15kV switchgears. Then it will be easy to get the
operational signal for CB, measuring data and some kind of status. These products are made by
ABB(Photo1-32).
Source: Taken by Study Team
Photo1-32 Communication Tower
Photo1-31 Transducer Photo1-32 Multi Relay
Photo1-28 View of Substation Photo1-29 Single line diagram of Substation
1-42
(2) Hoa Uvng distribution substation
It is also semi-outdoor type substation. Main transformers were installed outdoor. Extra high voltage
switchgears installed indoor are GIS and manufactured by Japanese manufacturer (TMT&D)
(Photo1-34). 15kV switchgears are installed indoor.
Digital multi-relay systems were also installed on the 15kV switchgear. These products were
manufactured by Alstom. It might be easy to get the various data from multi-relay to SCADA
(Photo1-35).
In the transformer substation, a capacitor is installed in the 15kV side bus. As for the protector of the
capacitor, it is thought that the incorporation to SCADA is possible relatively easily for the multi-
relay that is similar to the above(Photo1-36).
Source: Taken by Study Team
Photo1-33 View of
substation
Photo1-34 110kV GIS
Photo1-35 Multi Relay Photo1-36 Capacitor
1-43
3) Control center
Photo1-37 Annex of Phu Tho Power Company
Source: Taken by Study Team
The photo on the upper left shows the annex of Phu Tho Power Company where maintenance staffs for
power distribution lines wait on a 24-hour basis (15 staffs, 3 shifts).
The photo on the upper right shows the 3rd floor of the annex which is used as the space for staff to change
clothes, takes a rest or nap.
The photo on the middle right shows the 2nd floor of the annex, where the administrator of maintenance
department works.
The photo on the lower right shows the 1st floor of the annex which is used as the maintenance control
room. On the wall we see the underground electric line diagram and the overhead electric line diagram in
the district of Phu Tho Power Company and keys of the kiosk.
Since each floor has the size of only about 4m × 5m, it is difficult to install a set of the computer system for
DAS.
However, since the maintenance staffs for power distribution lines wait on a 24-hour basis in the annex and
for the sake of conducting the operation smoothly, the monitoring/control console for DAS should be
installed in the annex of Phu Tho Power Company.
1-44
Fig. 1-3-12 shows the current operation of 15kV power distribution line facilities and Fig.1-3-13 shows the
restoration procedure in case of an failure in a power distribution line.
Fig. 1-3-12 Operation tasks for 15kV power line facility
Fig. 1-3-13 Restoration procedure for 15kV power line failure
Source: Made by Study Team
■ Staffs
About 10 persons (3 shifts)
■ Job
Visual monitoring of voltage/current on power line
Visual monitoring of feeder circuit breakers
Control of feeder circuit breakers
Management of voltage on power line
■ Staffs
About 15 persons (3 shifts)
■ Job
Open/close operation of switch by on-site worker
110/15kV substation
Phu Tho Power Company
Load dispatch and communication
center
■ Staffs
Operation: 2 persons, maintenance: 1 person
■ Job
Monitoring of feeder circuit breakers by SCADA
Telephone
Telephone
Line failure location
Telephone
■ Collection of information on feeder circuit breakers
and relay and communication
■ Notification of power failure
■ Instruction of switch operation
110/15kV substation
Phu Tho Power Company
■ Notification of power failure
■ Manual open/close operation of switch
■ Line failure restoration
Wireless
1-45
Photo1-38 Main building of Phu Tho Power Company
Source: Taken by Study Team
The photo on the left is the main building of Phu Tho Power Company. Reading the meters is conducted
mainly by the client liaison on the 1st floor. But there is not enough space to install a set of the remote
meter reading system. However, the remote meter reading system should be installed on the 1st floor of the
main building of the Phu Tho Power Company for the sake of operation efficiency. The flow of meter
reading operation is shown in Fig. 1-3-14.
The meter is read with the staff from Phu Tho Power Company visiting a facility to read the meter visually
and input the value in a handy terminal. The data is transferred to and controlled centrally by the
Telecommunication & IT Company server. The meter is read basically once a month. The
Telecommunication & IT Company system is capable of making 100,000 bills a day.
1-46
Fig. 1-3-14 Flow of meter-reading operation
Source: Made by Study Team
Office/office of
meter reader
Customer
Home
Telecommunication & IT Company
(Charge calculation, print bills)
ATM
Bank
ATM
ATM
ATM
Handy
terminal
Input device
Charge notification
1. Staff reads meter.
2. Staff reads power meter visually, enters the
amount of power in a terminal and prints charge
notification
3. Charge notification is
given to customer
4. Staff returns to office
to transfer data from
terminal to input device
8. Bill is given to customer
Bill
Payment
by ATM is
possible
5. Power usage data is
transferred
6. Receive power usage
data, charge calculation
and output bills
Bill
7. Bill is sent
to offices.
10. Payment-done
information
Charge
11. Payment-done
information is
recorded
Optical fiber
Back bone network 10Gbps
Branch circuit 10Gbps
Branch circuit network 10Gbps
Branch circuit
10Gbps
Optical fiber
9. Deposit if paid on receiving the bill
Optical fiber
Bank
1-47
4) Communication
The optical fiber network facility is installed on the 1st floor of Phu Tho Power Company. An
environment that enables communication with substations and other EVN HCMC offices is provided
from this facility.
Photo1-39 Optical Fiber Network Facility
Source: Taken by Study Team
1-48
5) Existing watt-hour meters and status of installation
The watt-hour meters used in the Phu Tho Power Company district comply with the international
standard and no special specification is adopted. The watt-hour meter is available in two types –
mechanical and electronic. The mechanical type is produced in Viet Nam and the electronic type meters
are imported. A new watt-hour meter will be available in Viet Nam after the 6-month inspection for
model approval by the government body.
The total number of watt-hour meters in the Phu Tho Power Company area and is shown in Table 1-3-6
and the price is shown in Table 1-3-7.
Table 1-3-6 Total number of watt-hour meters
Single-phase 3-phase
Mechanical Electronic Mechanical Electronic
Phu Tho Power Company
area 89,471 1,804 6,138 3,317
Whole EVN HCMC 1,568,217 45,132 69,344 37,919
Source: EVN HCMC‟s data
Table1-3-7 Price of watt-hour meters
Source: EVN HCMC‟s data
Photo1-40 Watt-hour meter
Source: Taken by Study Team
Single-phase 3-phase
Mechanical Electronic Mechanical Electronic
Price 10 US$ 19.8 US$ 30 US$ 105.85 US$
Single phase watt-hour meter
Three phase watt-hour meter
1-49
Watt-hour meters in the Phu Tho Power Company area are classified in three types as shown in Table 1-
3-8 (1) A meter without Current Transformer (CT) and Voltage Transformer (VT), (2) A meter with CT
and without VT, (3) A meter with CT and VT
Table 1-3-8 Details of watt-hour meters installed in the Phu Tho Power Company area
Source: Phu Tho Power Company‟s data
Watt-hour meters are installed indoors in most houses. But more meters have been installed outside
(outer wall or eaves) over the last few years. In either case, the meters are stored in the meter box.
1.3.5 Situation of Outage and Distribution Loss
1) Situation of EVN HCMC
Annual Outage Duration per Customer separating Distribution Company‟s Facilities and Outside Factor
by is shown in Fig. 1-3-14.
Distribution Company‟s Facilities and Outside Factors have comparable outage duration.
Fig.1-3-14 Annual Outage Duration per Customer (hours)
Source: EVN HCMC‟s data
Causes of power outage in 15kV Feeder is shown in Fig. 1-3-15.
The outage is occurred by a variety of causes, such as switching equipment, animal and lightning surge.
Direct connection (no CT) With CT and without VT With CT and VT
Rated voltage Quantity Rated voltage Quantity Rated voltage Quantity
Single 2-wire 220V 91,688 - 0 - 0
3-phase 4-wire 220V 8,786
0.5kV 18
15kV 57 0.6kV 109
15kV 3
22kV 69
Total 100,474 199 57
Outside Factors 6.23
Distribution Company's Facilities
6.21
1-50
Fig.1-3-15 Causes of power outage in 15kV Feeder
Source: EVN HCMC‟s data
Annual trend of distribution loss in the last five years is shown in Table 1-3-9.
Since 2005, the loss has been decreased annually, so in 2009 is about 6%.
Table 1-3-9 Annual trend of distribution loss
Distribution Loss Unit 2005 2006 2007 2008 2009
Total % 7.28 7.21 7.07 6.18 6.03
Source: EVN HCMC‟s data
Others 34.1%
Lightning Surge 13.1% LBS/DS/FCO/LBFCO
32.7%
Animal 15.7%
Insulation 1.2%
Over load 0.0%
Tree 3.2%
2-1
Chapter 2 Study Methodology
2.1 Overview of Study
The following survey has been implemented in order to realize the smart grid project in Vietnam.
Survey for power supply in EVN, especially for distribution
Survey for EVN HCMC as implementing organization and for Phu Tho Power Company as model
area
Survey for the distribution network, existing facilities and systems
Survey for problems to realize the smart grid project
Survey for the proposed system configuration, the scope, the necessary investment and the schedule
etc
Economical evaluation including FIRR and EIRR
Survey for social and environmental condition
Survey for preparation of fund such as Bank loan and ODA loan etc
2.2 Study Methodology and Team Organization
2.2.1 Study Methodology
1) Survey of related documents in advance
2) Preparation of Questionnaire and site survey based on the questionnaire
3) Analysis of documents received in site
4) Hearing and meeting for related organization in Vietnam
5) Hold the workshop
Implementation of presentation in 1st survey in order to explain the survey purpose and contents
Explanation of survey results in 3rd survey in order to advance the smart grid project
6) Preparation of report for related organization
2-2
2.2.2 Team Organization
The survey team is organized as follows.
2.2.3 Counterpart
Counterpart of this survey is as follows.
EVN HCMC International Cooperation Department
Title: Director
2.3 Survey schedule
The overview of survey schedule is described in the following table.
Table 2-3-1 Survey schedule
2010
Jul
2010
Aug
2010
Sep
2010
Oct
2010
Nov
2010
Dec
2011
Jan
2011
Feb
Site Survey
Works in Japan
Project manager
TEPSCO / FUJISAWA
Economic Expert
TEPSCO / SADO
Local in Vietnam
COCOMO / HIEU
Distribution Expert
TEPSCO / HAYASHI
Environment & Social Expert
OPMAC / Fujiwara
Local in Vietnam
COCOMO / HAI
Solar Power Expert
TEPSCO / TSUJITA
DAS/AMR Expert
TEPSCO / TADA
2-3
The site survey was implemented as follows.
1) 1st site survey: from August 29 to September 22 in 2010
2010/8/30: Meeting with EVN
(Mr. Dang Hoang An Vice president)
2010//8/30: Meeting with MPI
(Mr. Ho Quang Minh Director General / Foreign Economic relations Department,
Mr. Luong Van Ket Deputy Director / Department of Industrial Economy)
2010/9/7: Meeting with EVN HCMC
(Mr. Tang Nai Tong Deputy General Director of Telecommunication and Information
Technology)
2010/9/7: Presentation in EVN HCMC (Attendant: 34 persons)
2010/9/7: Meeting with EVN HCMC and Phu Tho Power Company
to 9/22 (Mr. Nguyen Ngoc Tuyen Director / International Relation Department etc)
2) 2nd site survey: from November 16 to December 3 in 2010
2010/11/19: Meeting with MOIT
(Mr. Le Tuan Phong, Vice Director / Energy Department,
Mr. Nuyen The Vinh / Expert of Energy Department)
2010/11/23: Meeting with VEA
(Mr. Mai Thanh Dung Director / Department of Environmental Appraisal and Impact
Assessment,
Mr. Nguyen Anh Dung Official / International Cooperation & Science Technology,
Ms. Pham Thanh Tu Official / International Cooperation & Science Technology,
Mr. Ngo Hong Phuong Official / Department of Environmental Appraisal and Impact
Assessment)
2010/11/23: Meeting with EVN
(Mr. Tran Viet Anh Ph.D Deputy Director / International relation Dept etc)
2010/11/24: Meeting with EVN HCMC and Phu Tho Power Company
to 12/2 (Mr. Nguyen Ngoc Tuyen Director / International Relation Department,
Mr. Vu The Cuong Director / Engineering Department,
Mr. Nguyen Dang Viet Cuong Deputy Director / Materials & Import-Export
Department etc)
2-4
3) 3rd site survey: from January 16 to 25 in 2011
2011/1/19: Workshop in EVN
(MOIT Mr. Son Director, Mr. Ha Deputy Director
MPI Mr. Ket Deputy Director Other attendants: 38 persons)
2011/1/21: Workshop in EVN HCMC
(EVN HCMC Mr. Bao Deputy General Director Other attendants: 42 persons)
3-1
Chapter 3 Justification, Objectives and Technical
Feasibility of the Project
3.1 Background of Project and Necessity
According to MPI, the important policy for power sector in Vietnam is to solve the lacked power, to
improve the reliability and to accelerate the energy efficiency.
This project is suitable for the policy as follows.
1) Peak-cut by DR and application of renewable energy contribute to solve the lacked power.
2) DAS can reduce the outage duration when faults happen, so that the reliability of power supply is
improved.
3) Reduction of technical loss by DAS and non-technical loss by AMR, and Energy management by EMS
can accelerate the energy efficiency.
3.1.1 Scope of Project
Scope of project is as follows.
Pho Tho Power Company (District 10 and District 11)
All of customers such as shop, factory, hospital, residential customer etc
Project consists of DAS, AMR, DR and Solar power as model.
3.1.2 Current Analysis and Future Prospect
GDP in Vietnam is anticipated that the growth rate from 7% to 8% will continue up to 2020. According to
IE report based on the GDP, the growth rate of power consumption is anticipated to continue the growth
rate of 12.7% for every year up to 2030.
Besides, the power generator had been constructed with growth rate of 13.7% for every year up to 2009.
The power in Vietnam has been lacked under the maintenance and trouble even though the generators have
been constructed. Therefore, Vietnam will promote plans to increase the power from 160 GW in 2009 to
3-2
430 GW in 2015. In addition, the tariff will be increase in order to bring the foreign investment to IPP in
Vietnam which consists of approximately 30% in power generators. Nuclear power decided to be adopted
but the operation will be implemented from 2020 or over, so that the lack of power up to 2020 should be
strongly considered.
The Government of Vietnam is also promoting power consumption control at the peak hours by energy
efficiency in parallel. "Law No.50/2010/GH12 on economical and efficient use of energy" (Energy
efficiency law) passed through the National Assembly on June 17, 2010, and was enforced on January 1,
2011. This energy efficiency law consists of all the 12 chapters and 48 articles. The scope has specified
policies, measures and right, duty, and responsibility of organization, household, and individual which
promote economical and efficient use of energy. In this law, appointment of important entrepreneur with
large energy consumption, obligation of posting an energy manager to an important entrepreneur, an energy
labeling system, incentives, etc. are specified. Moreover, for renewable energy, it is pointed that suitable
renewal energy available in Vietnam is developed. Moreover, priority is given to rational development of
clean energy technology, and it is also setting to raise use rates of renewal energy to one of the energy
strategies. The above mentioned incentive covers financial support for the project which promotes
economical and efficient use of energy, incentive to companies and individuals who produce energy-
efficient products, and incentives to import duty in the case of importing energy-efficient products which
are not available domestically, etc.
If this project will not be implemented, a lot of outage by the lack of power and by faults will occur. So, the
economical growth of Vietnam and the business of Japanese company will become worse year by year.
3.1.3 Advantage by Project
The implementation of this project can solve the shortage of power and improve the reliability of power
supply, so that this project will contribute to develop Vietnam society with drawing foreign enterprise and
capital. Furthermore, this project will contribute to improve the global warming due to effects of energy
efficiency. This project also apply for Information Communication Technology (ICT), so that the skill of
Vietnam engineer will be advanced through the implementation of this project.
There are mainly five economical benefits as follows.
Technical loss reduction with improvement of load unbalance by DAS
Non-technical loss reduction by AMR including smart meter
Reduction of outage duration by DAS
Effective construction of Substations by DAS
Effective construction of Power Generators by DR
1) Technical loss reduction with improvement of load unbalance by DAS
3-3
DAS can improve the load balance of feeder by moving overload section to light load feeder.
The loss of MV feeder can be reduced around 32% based on the following example calculation.
<Example Calculation<
The effect of DAS on loss reduction could be substantial .Its value depends on the value and distribution of
loads, network parameters and network configuration before applying DAS. An example based on some
assumptions is given in order to describe the effect of DAS.
Assumptions:
(1) Rated current of each feeder =I
(2) Value of load at each node=0.1I
(3) Resistance between sections is equal having value equals R
Fig 3-1-1 Improvement of Load unbalance by DAS
<Before application of DAS>
Total losses = (0.4I)2 .R+(0.3I)
2.R+(0.2I)
2.R+(0.1I)
2.R+
(1.0I)2.R+(0.9I)
2.R+(0.8 I)
2.R+……+(0.1I)
2.R
= 4.15 I2.R
3-4
<After installation of DAS>
Source: Made by Study Team
Total losses = 2((0.7I)2 .R+(0.6I)
2.R +……+(0.1I)2.R)
= 2.80 I2.R
Effect of DAS = (4.15-2.80) *(100)/(4.15 )
= 32.5%
The technical loss of EVN HCMC is around 6.03% and the MV technical loss is around 1.72%, so that the
following technical loss (0.56%) can be reduced by DAS.
1.72% x 0.325 = 0.56%
2) Non-technical loss reduction by AMR including smart meter
Non technical losses can be improved by AMR because Smart meter in AMR can monitor theft
action/operation. In case that these projects can cover whole area in model zone, the non technical loss
by Meter problem and theft can be reduced as shown in the following Tables.
< In case of theft problem >
Smart Meter can detect the open of the cover for theft or manipulation and instantaneously drop the supply
voltage by remote control, so that non-technical loss can be reduced.
< In case of Meter problem >
Performance of electrical type for Smart Meter is much better compared with existing mechanical type. In
addition, AMR system can detect the non performance meters when they don’t reply response, so that the
3-5
loss by non performing meter can be reduced.
Mistake of the meter reader can be improved by auto meter reading using computer and electrical devices
in Smart meter.
Table 3-1-1 Effect for reduction of non-technical loss
Non-technical losses
(a)Current loss in
model divisions
(by Indian case)
(b) Phu Tho
Power
Company
(a) x 2.43/9.0
(b)Reduction
by AMR
Target in model
divisions
Meter
Non performing meter 0.47 0.13 0.13
(100%) *1
0
Under performing meter
0.28 0.08 0.00
(0%) *2
0.08
Defects of circuitry in CT/PT
1.33 0.36 0.00
(0%) *3
0.36
Mistake of meter reader
2.37 0.64 0.64
(100%) *4
0
Theft
Pilferage by manipulation of meters
0.47 0.13 0.13
(100%) *5
0
Energy theft by direct tapping
2.37 0.64 0.00
(0%) *6
0.64
Direct connection without meters
1.7 0.46 0.23
(50%) *7
0.23
Total Non-technical losses 9 % 2.43% 1.13 %
(46%)
1.31%
*1: Non performing meter can be detected when Smart Meter dose not respond.
*2: Additional solution is required for this kind of loss reduction.
*3: Additional solution is required for this kind of loss reduction.
*4: Meter is correctly read by system without human errors.
*5: Manipulation of meter can be detected by the opening/closing sensor of meter cover.
*6: Additional solution is required for this kind of loss reduction.
*7: This type of theft can possibly be detected by comparing electricity amount data between the meter in
RTU of DAS and Smart meters. However the accuracy of this theft detection would be as low as 50%.
Source: Made by Study Team
The current non-technical loss in Phu Tho Power Company area is 2.43% and can be expected to improve
up to 1.13% by promoting this project.
3) Reduction of outage duration by DAS
<Modeling of Reduction of Outage Duration>
Generally, outage duration has various reasons and various restoration time each and all. To simplify the
outage duration mechanism, all MV feeder fault including Distribution Transformer (DT) fault is
represented by the following models (before and after model) as shown in Fig. 3-1-2.
3-6
(1)Restoration Model of 15 kV OH Line before DAS
The following model shows the standard configuration of MV OH line before DAS. In case that a
fault happens at the third section in feeder, procedure of outage restoration and duration of outage in
each section can be graphically indicated as follows. Total duration for complete restoration is
estimated at 170 minutes in all sections.
Fig. 3-1-2 Restoration Model of 15KV OH Line before DAS
CB
2 nd Sec.
3 rd Sec.
4
th
Sec.
No. 1
No. 2
No. 3
No. 4
No. 5
No. 6
No. 7
No. 8
No. 9
No. 10
60
120
180
0 [Min.]
1
st
Sec.
1
st
Section
2
nd
Section
3
rd
Section
4
th Section
NO
3-7
No Affairs Elapsed Time (Minutes)
1 Circuit Breaker at 110kV/15kV s/s trip 0 -
2 Notice from Substation to Phu To Office by phone 5 (+5)
3 Staffs at “Unit” are organized and go to the site 25 (+20)
4 Finding the faulty section to isolate 55 (+30)
5 Isolate the faulty section to restore 60 (+5)
6 Finding the faulty point to restore 75 (+15)
7 Repairing the faulty point 135 (+60)
8 Inspect the repairing work 145 (+10)
9 Trial charge to check the condition of faulty point 150 (+5)
10 Commercial charge 170 (+20)
Source: Made by Study Team
(2) Restoration Model of MV OH Line after DAS
The following model in Fig. 3-1-3 shows the standard configuration of MV OH line after DAS
introduction. In case that a fault happens at the third section in the Distribution Line, procedure of
outage restoration and duration of outage in each section can be indicated graphically as follows. Total
duration by complete restoration is estimated at 125 minutes in the fault section. The remaining
healthy sections can be restored within 5 minutes.
As for underground network, the system configuration using OH LBS for DAS is similar as OH
network, so the effects by DAS is assumed to be equal to the OH restoration procedure.
3-8
Fig. 3-1-3 Restoration Model of 15 kV OH Line after DAS
Affairs Elapsed Time (Minutes)
1 Circuit Breaker at 110kV/15kV s/s trip 0 -
2 DAS detects the fault, isolates the faulty section and makes changeover procedure
5 (+5)
3 Staffs at “Unit” are organized and go to the site 15 (+10)
4 Finding the faulty point to restore 30 (+15)
5 Repairing the faulty point 90 (+60)
6 Inspect the repairing work 100 (+10)
7 Trial charge to check the condition of faulty point 105 (+5)
8 Commercial charge 125 (+20)
Source: Made by Study Team
(3) Restoration Model of MV UG Line after DAS
As for MV UG line, the network topology is similar as OH network as shown in Fig 3-1-4, so that the
reduction of outage duration is assumed the same as the effect of OH network.
CB
1st
Section
2nd
Section
3rd
Section
4th
Section
60 120 180 [Min.]
2nd
Sec.
3rd
4th Sec.
No. 1
No. 2
No. 3
No. 5
No. 6
No. 7
No. 8
0
No. 4
1st Sec.
Sec.
3-9
Interrupted Customers Hours
= (Average Outage Duration of Each Customer) x (Total No. of Customers)
= (Average Outage Duration of One Feeder) x (No. of Feeders) x (Average Customers of One Feeder)
Total No. of Customers = No. of Feeders x Average Customers of One Feeder
∴ Average Outage Duration of Each Customer = Average Outage Duration of One Feeder
<Reduction of Outage Duration in MV Feeder and DT>
Based on the reduction model of MV feeder fault including DT fault, Average Outage Duration of
One Feeder can be decreased to 20.6% from original outage duration as calculated below.
Here, reduction of Average Outage Duration of One Feeder is converted to reduction of Average
Outage Duration of Each Customer at the equal value as explained below.
This means that Average Outage Duration of Each Customer caused by also decreases to 20.6% from
the original outage duration by introduction of DAS.
In other words, Average Outage Duration of Each Customer after installation of DAS will be reduced
with 296 minutes out of original outage duration [=373 minutes x( (100%-20.6%)/100)] in EVN
HCMC.
Fig. 3-1-4 15kV Underground network applied DAS
Source: Made by Study Team
RMU (Kiosk)
Automatic LBS (Closed state)
Automatic LBS (Open state)
In case of OH/UG fault, Average Outage Duration of One Feeder (OH/UG) is,
170 minutes → 35.0 minutes (= (125+5+5+5)/4)
Weighted Average Outage Duration of One Feeder (mixed) is,
(35.0/170)x100% = 20.6%
3-10
4) Effective construction of Substations by DAS
DAS can quickly switch a lot of loads of distribution feeder when bank fault in substation happens.
Currently, EVN HCMC adopts maximum 75% operation of rated capacity, allowing 130% (2H) of rated
capacity in emergency.
DAS allows to raise the maximum operation level by quickly switching the loads of the fault bank.
Overload allowance is not considered in the raised maximum operation level because it normally takes
less than few hours for repairing the bank accident.
By raising maximum operation level of bank of substation, average operation level can also be raised.
As a result, new construction of substation can be saved by rising average operation level. After
installation of DAS, maximum 83% of rated capacity can be allowed as explained in Fig 3-1-5.
Fig. 3-1-5 Explanation of raising operation level of substation
While all banks operate at P% to rated capacity, a bank fault occurs at 4B.
Load of 4B can switch to other 5 banks by means of automatic load
switching of DAS in distribution feeder side.
Total (500% - 5P%) can be switched (P ≦ 500 – 5P)
Maximum operation level can raise to 83% (P=500/6).
5) Effective construction of Power Generators by DR
The peak-cut in peak load is effective to solve the lacked power and save the investment instead of the
construction of Power generations.
The controlled customer load shall be considered to be cut off without inconvenience and is proposed as
follows.
Unnecessary load like A/C is cut off in large customer such as hospital / shop / factory etc.
All of power is cut off in residential customer.
When DAS with EMS connected to SCADA forecast that the consumption surpasses the generator
capacity, DR can switch off the controllable load during 0.5 hour through smart meter. In case that the
4B
C Substation B Substation
3B
A Substation
2B 1B 5B 6B
100-P 200-2P 300-3P 100-P 200-2P
3-11
peak load of more than the generator capacity is anticipated to continue after the control of 0.5 hour, DR
also switches off the other controllable load in turn. However, if the customers want to recover the
power, the customers can get the power by manual operation of smart meter.
Peak-cut by DR becomes more effective because the manual operation decreases due to expensive cost,
if the tariff on peak load will be set up higher. In case of Vietnam, a part of customer’s units such as
enterprise already have adopted the difference tariff between peak and off-peak load but residential
customers keep the same tariff regardless of peak load. In case of enterprise unit (6 to 22kV customers),
the tariff on peak load is of 3,028 VND/kWh and the tariff on off-peak load is of 1,073 VND/kWh, so
that the difference between peak and off-peak tariff is around 3 times. In order to facilitate the effect of
DR, it is expected that the adopted difference will be expanded more and the difference tariff on the
residential customer will be applied.
In case the DR is applied for Phu Tho Power Company, the cost benefits will be calculated based on the
following conditions.
The consumption of A/C load is normally from 0.5 kW to 2 kW, so the average is around 1 kW. The
customer consumption in peak load is around 3 kW as assumption based on A/C load.
The consumption of large customer is around 30 kW as assumption.
The number of customer in Phu Tho area is approximately 100,000. → Normal customer: 90,000
Large customer: 8,000
(3kW x 90,000 + 30kW x 8,000) x 1/2 = 255MW
Construction of power generator of 255MW can be reduced by DR. Gas turbine generator is normally
used for the peak load, so that the effect of DR on 255MW is calculated as follows.
Construction cost: 380 US$/kW (Construction cost of Gas Turbine) x 255 MW = 97 MUS$
Fuel cost: 255MW x 2H x 40 day x 20 years x 0.15US$/kWh = 61 MUS$
(Present fuel cost is around 0.07 US$/kWh. → 0.15 US$/kWh: Average for 20 years)
Cost of Smart Meter is around 20 MUS$.
The cost of 138MUS$ (= 97 + 61 - 20) as EVN can be saved by DR in Phu Tho Power Company.
3.1.4 Comparison between the Proposed Project and Other Method
As for solution of the lacked power, there are the constructions of power generators instead of this proposed
project.
3-12
Existing plan for construction of hydraulic power generator are as follows.
Existing hydraulic power generator is occupied with 35% of generator capacity in Vietnam.
Northern area has been constructed with Lai Chau, Ban Chat and Huei Quang after Son La project.
Central area has been completed with Sesan and Srepok river projects.
Southern are has been planning with Dong Nai river project.
However, the construction plans of hydraulic power generators have not been advanced smoothly due to
problems such as habitant movement etc, so that the hydraulic generator can not be expected to cover the
future consumption with high growth.
Peak consumption in 2020 will be increased and be reached to around 52 GW, so that new power plants of
35 GW are needed up to 2020.
As for Coal fired thermal power plants, the development with 35,000 MW needs to provide 100 million
tons of coal per year while the output of maximum coal mining reached about 70 million tons per year.
As for gas and oil fired thermal power plants, the construction is normally slow and the energy source in
thermal power projects causes green house gas problem.
If nuclear power plant meets the schedule of the Master Plan VI, the first plant will be commissioned in
2020.
As mentioned above, the shortage of power in Vietnam is serious up to 2020 especially and the
constructions of current and fossil power plants can not be expected to solve the problems. Therefore, it is
necessary to accelerate the application of renewable energy and advance the energy efficiency in parallel.
Regarding renewable energy, wind power / biomass / geothermal / small hydropower / Solar are considered
as the renewable energy in Vietnam and the potential reported by IE is as follows.
Wind Power: 1,800 MW
Biomass energy: 150 MW
Geothermal energy: 340 MW
Small hydropower: 4,000 MW
Solar energy: 4-5 kWh/m2
Small hydropower has occurred damages by flood during typhoon etc, so that the additional construction
will be difficult by objections of inhabitants. The capacity of Biomass and Geo thermal energy is not so
large. Therefore, Wind power and Solar energy will be expected to cover the increasing consumption in
Vietnam.
Regarding countermeasure of the peak load, it is necessary to reduce the peak load as energy efficiency in
3-13
parallel of power plant construction. There are Peak-cut and Peak-shift as the method of peak reduction.
Peak-shift means to restrain the consumption of large customers by asking the saving and to shift the load
by changing the working time / day. Moreover, normal customers will save the consumption for peak time
by themselves due to the display on smart meter. This method is effective in developed countries because
the outage for the shortage of power is not allowed but the method is not effective in developing countries
such as Vietnam for at least 10 years. The reasons are as follows.
Cost-up of smart meter with display → Huge investment
It can not be expected to switch off by the customer’s own judge.
The developing countries can easily implement the outage for peak load.
Peak-cut means to control the customer load such as A/C etc remotely, so that the peak load can be saved.
The investment is much smaller than the construction of power generation. Furthermore, as the peak-cut
can save the construction of power generations, the emission of greenhouse gas by the power generations
can be saved. In order to realize the peak-cut, the smart meter has to be installed to all of customers and the
investment is large. However, the smart meter can be applied for AMR, so that the effectiveness of the
investment becomes more reasonable.
3-14
3.2 Analysis Needed for Decision of Project Contents
3.2.1 Demand Forecast
Although electricity demand forecast of whole Vietnam is described in Chapter 1, power demand forecast
of HCMC where the Project region is included and its preconditions and method are described herein.
According to EVN, the electricity demand track record in 2000 to 2009 of HCMC which can be set is as
follows.
Table 3-2-1 Demand track record of EVN HCMC
Year 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009
Electric
energy sales
(GWh)
5,621 6,480 7,498 8,362 9,166 9,850 10,727 11,560 12,365 13,262
Increase rate
(%/year)
- 15.3 15.7 11.5 9.6 7.5 8.9 7.8 7.0 7.3
Maximum
Power
(MW)
1,051 1,254 1,374 1,506 1,676 1,692 1,889 2,047 2,178 2,245
Increase rate
(%/ year)
- 19.3 9.6 9.6 11.3 1.0 11.6 8.4 6.4 3.1
Source: EVN HCMC Company Profile 2010
According to IE, the power demand forecast by 2020 of HCMC is as follows.
Table 3-2-2 Demand Forecast of EVN HCMC
Year 2010 2015 2020
Electric energy Sales (GWh) 15,409 26,755 42,931
Increase rate (%/ year) - 11.7 9.9
Maximum Power (MW) 2,600 4,535 7,269
Increase rate (%/year) - 11.8 9.9
Source: IE
The track record (2000-2009) of the maximum power demand of the above-mentioned HCMC and forecast
(2010-2020) are shown in Fig. 3-2-1.
3-15
Fig.3-2-1 Max Power Demand Forecast of HCMC (2000 – 2020)
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
Year
Max
Dem
and
(MW
)
Source: Created based on IE and EVN data.
According to the power demand forecast, it is assumed that the maximum power demand (MW) will
increase to about twice in 2015 and 3.2 times in 2020 compared with that of 2009.
According to the IE, the demand forecast of Vietnam is prepared considering GDP growth, population
increase, energy saving, a crewed oil price, and an electricity bill, etc. by multi-regression.
For example, the GDP growth rates are assumed as shown in Table 3-2-3.
Table 3-2-3 Assumed value of GDP growth rate (2011- 2030)
Year 2011-2015 2016-2020 2021-2030
GDP growth rate (%) 7.5 8.0 7.83
Source: IE
Moreover, the population increase is assumed as shown in Table 3-2-4.
Table 3-2-4 Assumed value of Population Increase (2009- 2030)
Year 2009 2010 2015 2020 2030
Population (1,000 people) 87,093 88,038 92,499 97,187 102,421
Source: IE
Furthermore, the power-saving effect by the spread of energy conservation is assumed, for every field and
period respectively, as an average of 1-3 %.
3-16
3.2.2 Issue and Analysis of Project
Issue and analysis of project are as follows.
1) Peak-cut by DR
EVN has already implemented the outage for peak load, so that the peak-cut will not occur problems of
customers. However, customer‟s dissatisfactions should be considered. Furthermore, it is necessary to
issue the restriction of low and the incentive for acceleration.
2) Solar Power
Cost of solar power is expensive and the purchase tariff of EVN is inexpensive, so that the solar power
is not almost used in city areas except island etc. In order to accelerate, the support of government in
Vietnam is needed.
3) Shortage of power
When the peak load is anticipated to exceed the power supply, the planned outage will be occurred by
EVN. In case of EVN HCMC, the planned outage is around 6 hours per year. The shortage of power is
serious, so the countermeasure is highly required.
4) MV of distribution feeder
EVN has a policy of MV which will change from 10 / 12.7 / 15 kV to 22kV. However, the investment
for the exchange is huge, so that the 22 kV MV feeder is limited for small area. In case of Phu Tho
Power Company, there are no 22 kV feeders. In this condition, the equipment for MV feeder shall be
issued which voltage this project will apply.
5) Communication method
Communication method is important for investment and technical solution. EVN HCMC has already
installed Fiber Optic in city area and there is EVN Telecom as subsidiary company of EVN. Therefore, the
Fiber Optic can be utilized as backbone network of this project. As for last one mile communication for all
of customers, the installation of Fiber optic is limited, so that the communication method for last one mile
shall be issued.
3-17
3.2.3 Technical Analysis
1) Analysis of communication method
The communication network of this smart grid consists of two networks – back-bone network and last
one mile network.
The analysis of the communication method adopted in the two networks is as follows:
(1) Back-bone network
The data between the control center and Master Remote Terminal Unit (M-RTU) of a substation,
and between the M-RTU and feeder (MV) RTU are sent and received through the back-bone
network.
The back-bone network must enable high speed, large capacity transmission.
There are several options for the back-bone network, which are compared in Table 3-2-5.
Table 3-2-5 Comparison of Back-bone Communication (X < △ < ○ < ◎ Good)
L-PLC (B-PLC)* UHF / VHF GPRS (GSM) Fiber Optics
Reliability △ (X) △ ○ ◎ Speed X (○) △ ○ ◎
Security ○ (○) ○ △ ◎ System Expansion X (○) △ X ◎ New Business X (○) X X ◎ Initial Cost ○ (○) ○ ◎ ○ Connection Cost (Maintenance) ◎ (◎) ◎ X ◎
*L-PLC: Low speed PLC, B-PLC: Broad band PLC
Source: Made by Study Team
Power Line Carrier (PLC) and UHF/VHF are not suitable for the back-bone network for their low
reliability and speed.
GPRS is not suitable because of its security problem in the public network. The cost could be high
to extend the DAS system and connect the network to a new system Home Energy Management
System (HEMS). In addition, it is difficult for GPRS to upgrade the lines to handle the increased
volume of DAS and HEMS network data.
This means to ask cell-phone companies, which control the GPRS, to bear the financial burden
(facility investment).
3-18
The fiber optics communication is the most suitable of the four options but the initial installation
cost is high.
However, since EVN HCMC has already established a fiber optics network in HCMC, the initial
cost could be kept low.
Therefore, the fiber optics communication, which allows high speed and large capacity transmission
as well as stable communication, is the best for the back-bone network.
(2) Last one mile network
The data between the smart meter and RTU or Concentrator are sent and received through the last
one mile communication network.
The last one mile communication network requires transmission reliability and must be built at low
cost.
It is important that the cost for smart meters must be low because they are installed in a large
number for customers.
There are several options for the last one mile communication network, which are compared in
Table 3-2-6.
Table 3-2-6 Comparison of Last One Mile Communication
PLC* UHF / VHF GPRS (GSM) ZigBee etc. Fiber Optics
Reliability △ (X) △ ○ ○ ◎ Speed X (○) △ ○ ○ ◎ Security ○ (○) ○ △ ○ ◎ System Expansion X (○) △ △ ○ ◎ New Business X (○) X X △ ◎ Initial Cost ○ (○) ○ ◎ ◎ △ Connection Cost
(Maintenance) ◎ (◎) ◎ X ◎ ◎
* Characteristics of Broad band PLC is described in ( ).
Source: Made by Study Team
The low speed PLC is low in transmission reliability because it often generates transmission error.
The method is also not suitable since the overhead caused by the retry process to recover from the
transmission error state results in loss of transmission time.
The high speed PLC, as with low speed PLC, is not suitable in terms of transmission reliability.
3-19
On the other hand, UHF/VHF is not reliable enough. The radio signal reception could be poor under
the influence of weather and new buildings. Moreover, the transmission speed is low and cannot be
extended easily to introduce the new system.
Therefore, UHF/VHF is not suitable.
It is easy for GPRS to expand into the last one mile communication because it utilizes the public
phone network.
However, there are three issues for GPRS to overcome.
a. It is public network and security must be ensured.
b. Telephone companies manage the network and we need to consult with them expand the network
into new business.
c. The maintenance cost for the entire GPRS connection would be tremendous as shown below:
<Calculation of GPRS connection cost>
1) Necessary data
(1) AMR
● Downstream data: 50 byte ● Upstream data: 100 byte
(50 + 100) byte x 24H x 2 times x 31days = 223.2 kbyte / month
(2) DR
● Downstream data: 50 byte ● Upstream data: 50 byte
● Control by every 30 minute ● Controlled day: 100 days / year
● Peak load for DR continue for 120 minutes as assumption
(50 + 50) byte x (120 / 30 minutes) x 100 day / 12 month = 3.3 kbyte / month
(3) Total: 223.2 + 3.3 = 226.5 → 227 kbyte / month
2) GPRS cost in 2010
45.5 VND / 10 kbyte in 2010
3-20
3) Cost for connection
In case of Phu Tho Power Company:
(227 / 10) kbyte x 45.5 VND x 100,000 customers x 12 month= 1,239,600,000 VND / year
In case of EVN HCMC:
1,239,600,000 VND x (1,700,000 / 100,000 customers) = 21,073,200,000 VND / year
Fiber optics is the best in terms of performance but the problem is that it takes a large cost for
installation.
Use of fiber optics is recommended since large capacity data transmission is required in the future for
customers to provide new functions and services such as remote access, remote medical diagnosis, and
HEMS.
ZigBee etc. is suitable for handling the information transmission volume of the current smart grid.
However, it is difficult for Wireless to expand into new businesses where large capacity of data is
required.
New businesses are under development and it is important that the current system be operated at
moderate cost.
Therefore, ZigBee etc. should be applied for the last one mile communication for the next several years
and it is desirable to replace it with fiber optic communication in the future.
The fiber optic network may not be built for the entire HCMC. In such case, additional network needs to
be established.
3-21
Fig. 3-2-2 Network Infrastructure of EVN HCMC
Source: Made by Study Team
Additional fiber optics
3-22
2) Deliberation of control center
Fig. 3-2-3 Office floor plan in Phu Tho Power Company
Source: Made by Study Team
With enough space on the 4th
floor of office main building, establish sever room would be proposed.
After air conditioning, power, security and other facilities shall be installed in the server room, install
AMR server, Front End Processor1 (FEP) and other devices without advanced DAS server would be
applied.
Advanced DAS server and FEP2 including monitoring and control device would be installed in Load &
Dispatch Communication Center of EVN HCMC.
A LAN network will be established in the office. The advanced DAS monitor and control operation
terminal shall be installed on the 1st floor of office annex building, and the AMR operation terminal is
installed on the 1st floor of office main building.
Office annex
3rd floor
Change room for
maintenance worker
2nd floor
Office of supervisory
personnel
1st floor
Control center
Office main building EVN Telecom
4th
floor
2nd floor
Office for customer information management
1st floor
Electric bill payment counter
3rd
floor
Parking area
Phu Tho office 4th
floor
3-23
The purpose of minimize of construction cost for control center to improve job efficiency based web
system configuration would be recommended because the system can be decentralized.
Fig 3-2-4 Image of control center system configuration
Source: Made by Study Team
The advanced DAS is responsible for monitoring the distribution system, controlling the switch, and
demand monitoring. It also performs energy management by monitoring the interconnected-solar power
and controlling the interconnected-battery.
The AMR is responsible for remote automatic meter reading and ON/OFF control of the smart meter
through the DR.
FEP exchanges data with the advanced DAS server if the data is upward/downward information of the
switch mobile unit, upward information from the interconnected-solar Power Conditioning Subsystem
(PCS) or downward information to the interconnected-battery PCS. The data is exchanged with the
AMR server if it is upward/downward information of the smart meter.
The volume of information is expected to increase in the future. Therefore, the advanced DAS server
DB
AMR Server
DB
Advanced DAS Server FEP1
OfficeLAN
Phu Tho Power Company‟s office
Load & Dispatch Communication Center
Advanced DAS
Console
Optical Communication Server
FEP2
AMR Console
Optical Communication Server
Advanced DAS monitor
MOMONConsole
OfficeLAN
Control center
3-24
may have to be dispersed into the DAS server, DR server, and EMS server.
3) Analysis of smart meter installation
(1) Structure for installing smart meters
A smart meter shall be replaced with a currently-installed watt-hour meter to facilitate installation.
Watt-hour meters are installed indoors and outdoors with the meter box.
Therefore, a smart meter having the same shape and connection method as with the current watt-
hour meter makes replacement easy.
However, the shape may be slightly different depending on the components attached to a smart
meter, but it shall have the size to fit into the meter box.
(2) Time to install smart meters
It is desirable to replace the watt-hour meter with a smart meter at the validity period of the
verification stipulated by the current law concerning watt-hour meters.
The replacement cost can be reduced by replacing the watt-hour meters at this timing.
The validity period of the verification according to the watt-hour meter type is as follows:
Single-phase watt-hour meter: 5 years
3-phase watt hour meter: 2 years
Providing smart meters for the entire Phu Tho Power Company area would require about five years.
4) Analysis of distribution devices
There are two types of method of DAS, voltage system and current one. It is different by method of
detection of fault location between voltage system and current. The difference is only this point between
them.
Voltage system is adopted mainly in Japan. Voltage system can detect fault location by activating
distribution line switch automatically at interval to recharge of fault location.
3-25
The basic summary of the system is as follows:
Fig 3-2-5 Method of detection of fault location: Voltage system
Source: Made by Study Team
On the other hand, current system is mainly adopted in Europe, e.g. urban areas in UK and France. The
system can detect fault location by detecting fault current, data transmission through communication line,
and fault section determination by CPU.
FCB SW1 SW2 SW4 SW3
FCB
110kV/15kV
Substation
SW1
Loop point
M-RTU Communication line
CPU Control Center
FDR/RTU
FEP
SW2 SW3 SW4
FDR/RTU
FDR/RTU
FDR/RTU
lock lock
Normal
Fault
FCB trip
FCB
reclose
FCB trip
FCB
Re-reclose
Load side transfer
(For fault processing or at normally open point FDR)
SW1
Time-adjusted
transmission
SW2
Time-adjusted
transmission
SW1
Time-adjusted
transmission
Achievable
by CPU
Achievable
only by
Automation
device
3-26
The summary of current systems is as follows:
Fig 3-2-6 Method of detection of fault location: Current system
Source: Made by Study Team
FCB
110kV/15kV
Substation
SW1
Loop Point
M-RTU Communication line
CPU Control Center
RTU/Battery
FEP
SW2 SW3 SW4
RTU/Battery
RTU/Battery RTU/Battery
FCB SW1 SW2 SW4 SW3
lock lock
Normal
Fault
FCB trip
Demand
SW2/SW3 to lock
Load side transfer
(for fault processing)
Activate FCB
Judge fault section by SW relay information
Achievable
by CPU
3-27
Both systems have same basic DAS functions but there are the following advantages and disadvantages.
Table 3-2-7 Comparison of voltage and current systems
Source: Made by Study Team
Current system Voltage system
Feeder Circuit
Breaker (FCB)
operation
○ 1 time △
2 times
・Fault may be expanded due to
fault current that flows twice.
・Damage in Oil Circuit
Breaker (OCB)
Fault detection
△
Unreliable
・Fault detection unreliable
under the influence of fault
location resistance. Must
cooperate with substations for
protection.
◎ Reliable
Redundancy ×
Low
・Fault section cannot be judged
or separated in case of failure
in CPU or communication
infrastructure.
◎
High
Fault detection and load side
transfer conducted by local
device alone and CPU and
communication infrastructure
remain unaffected.
Recovery time
◎ Fast ○
Relatively slow ( reclose 2
times)
Maintenance
△
・Batteries replaced every 3 to 5
years.
→Installed in many areas in a
large number (burdensome)
◎ Maintenance free
(no batteries required)
Co
st
System ×
・Local device alone cannot
detect fault. Initial cost for
distribution automation system
is high because it includes
CPU and communication
infrastructure.
◎
・Failure is detected by local
device alone and smallest scale
of distribution automation
system is introduced at low
cost.
Local device △
For every switch,
・Ground fault detection
(ZCT,ZPD,DGR)
・Short circuit detection
(CT,OCR)
・More batteries and chargers
required than voltage system.
○
3-28
Advantage of Voltage system:
Failure-resistant, capable of determining and separating fault section without CPU and
communication line.
Initial introduction cost is lower than current system.
Advantage of Current system:
No recharge is required for fault location to determine fault section.
Fault section is determined and separated faster than voltage system.
Disadvantage of Voltage system:
Fault location must be recharged to determine the fault section.
Disadvantage of Current system:
CPU and communication line required to introduce the system, initial introduction cost is high, low in
failure resistance.
This project will consider the adoption of the Current system and Voltage system.
Overhead: Voltage system
Underground: Current system
There are 2 MV distribution networks which consist of 15kV and 22kV. The distance for the branch office
in EVN HCMC and UG/OH is introduced in Table 3-2-8.
MV line for 22kV is less than 1 % and there is no 22kV feeder in model area (Phu Tho Power Company).
3-29
Table 3-2-8 Distribution networks in maintenance area of EVN HCMC
Branch
office
22 kV (km) 15 kV (km)
OH UG OH UG
Sai Gon 64.186 243.041
Phu Tho 62.433 75.098
Cho Lon 106.204 106.625
Gia Dinh 115.685 95.265
Go Vap 104.058 40.775
Tan Thuan 161.531 82.200
Binh Phu 222.412 53.127
Tan Phu 157.202 28.307
Tan Binh 111.600 69.099
Total of Urban
Area 1.105.311 79.537
Hoc Mon 292.330 39.852
Cu Chi 24.246 2.626 681.287 8.589
Thu Duc 203.483 57.181
Binh Chanh 456.400 44.310
Thu Thiem 271.966 80.322
Can Gio 152.666 3.847
Total of Rural Area 2.058.132 234.101
Total 24.246
(0.58%)
2.626
(0.06%)
3.163.443
(75.1%)
1,023,791
(24.3%)
Source: EVN HCMC Corporate pamphlet 2010
In case of 22kV, LBS is expensive in comparison with 15kV LBS. Therefore, we recommend to apply
15kV LBS for Phu Tho Power Company as 1st stage. If 22kV LBS will be needed more than 10 years later,
the existing LBS can be easily moved to other 15kV areas. As for other equipment such as RTU /
Concentrator / smart meter etc, they can be used to both voltages.
RMU for DAS on UG feeder is required to change from manual to automatic operation. The manual
mechanism in existing RMU can be modified to automatic operation type on principal due to additional
mechanism but the reliability is not so good and the operation speed is slow due to the motor operation.
Therefore, we propose that the existing manual type will be moved to the location for manual operation on
new UG feeder and the automatic new RMU will be installed in the existing room removed the manual
RMU.
5) Solar Power
Major purpose of solar power system in this project is to contribute to reliability of power supply. And
candidate place shall be required with adequate public space and large space for installation of solar
power –more than 10kW.
And it shall be substituted for emergency power as additional effect by batteries with solar power.
3-30
The hospital and school with the public place which have a large site on the map are suitable for the
candidate site.
There are 2 universities (institute of technology and institute of economy) and 3 hospitals in Phu Tho
area and they are located in district10.
It is expected by effect of installation of the hybrid system shall be maximized by installed to the same
feeder or the supply from the same substation. Furthermore it requires adequate space for installation
large scale solar power generation.
(1) Select the candidate place
The team considers about above requirement, select 2 candidate places. These places are also
recommended by Phu Tho Power Company.
a. Ho Chi Minh City University of Technology
Address: 268 Ly Thuong Kiet District10, HCMC
b. Trung Vuong Emergency Hospital
Address: 266 Ly Thuong Kiet, Phuong14 District10, HCMC
These 2 candidate places are connected to the same distribution line, and it shall be adapted to
operate hybrid system of solar energy and battery effectively.
University of technology has electric and electronics course, it also might be available for study
and development.
The hospital is stronghold for emergency and disasters, hybrid system of solar power and battery
shall be available for backup supply when outage.
Both of them have large space for install large scale solar power.
Hearing for manager of administration in the hospital, they have a good image for installing solar
power.
3-31
Fig. 3-2-7 Candidate place for PV installation
Source: Made by Study Team
(2) Outline of candidate place
a. Ho Chi Minh City University of Technology
There are 2 campuses in HCMC, candidate place is a main campus. It has 14.5ha site, and enough
space or rooftop of building for installation solar power system.
Source: Taken by Study Team
Phu Tho Power
Company
Trung Vuong
Emergency Hospital
Ho Chi Minh City
University of Technology Phu Tho area
Photo3-1 Ho Chi Minh City University
of Technology
Photo3-2 situation of the campus
3-32
b. Trung Vuong Emergency Hospital
They have a plan for rebuilding next year. (Photo 3-5) There will be enough space for
installation solar power in for example upside of parking lot by drawing of construction plan.
They have 550kVA emergency engine generator for outage now, and will have 750kVA engine
generator in their plan after rebuilding.
In the case of disaster or emergency situation, if it could difficult to get fuel, power supply shall
supply.
Source: Taken by Study Team
(3) Study of solar power
The major reason of solar power in Vietnam is countermeasure for outage power supply.
Against a lot of outage troubles are happened frequently cause of lack of power supply and fault of
distribution line, people who have solar power prepare batteries, and use them for emergency power
supply. Then solar power systems in Vietnam are not grid connection type. All of them are hybrid
with battery.
Furthermore in this project solar power and battery systems shall be connected to the grid and
controlled by DAS with energy management system for optimize of energy supply and shaving load
Photo3-3 Trung Vuong Emergency Hospital Photo3-4 Situation of the Hospital
Photo3-5 Rebuild plan of the Hospital
3-33
peak. It might be a first experience of grid connection type large scale solar battery in Vietnam.
Southern region of Vietnam has better conditions of solar radiation. Both solar radiation and during
time of sunshine are excellently stable in HCMC. This area is appropriate for solar power.
Fig. 3-2-8 Solar radiation by month of capital city of Vietnam
Source: Quote from NEDO report march/2005 „Survey for present and future plan for usage
and relevant policies of renewable energy at „Thailand, Indonesia, Malaysia, Philippine,
and Vietnam‟
Fig. 3-2-9 Duration time of sunshine by month of capital city of Vietnam
Source: Quote from NEDO report march/2005 „Survey for present and future plan for usage
and relevant policies of renewable energy at „Thailand, Indonesia, Malaysia, Philippine,
and Vietnam‟
-Outline of the scope site-
The solar power systems installed to Ho Chi Minh City University of Technology and Tung Vuoung
emergency hospital will be first trial as large scale grid connection type solar power system. These
systems are controlled power aggressively by energy center using smart grid. These systems shall
0
1
2
3
4
5
6
7
jan feb mar apr may jun jul aug sep oct nov dec
Rad
iation k
Wh/m
2/da
y
Ha NoiDa NangNha TrangTP Ho Chi Minh
0
50
100
150
200
250
300
jan feb mar apr may jun jul aug sep oct nov dec
hours
Ha NoiDa NangNha TrangTP Ho Chi Minh
3-34
have batteries and they shall stabilize grid condition and adjust output and demand regionally. And
batteries can also use for emergency power supply.
But in this project it is difficult to adjust whole area‟s output and demand. Solar power system will
adjust output and partial load, and stabilize network, as a pilot plant. In future, it will adjust energy
balance whole of the local network with DR.
Outline of energy receiving facilities of candidate site as follows
Table 3-2-9 Energy receiving facilities of candidate site
Nos. of incoming
circuits
Receiving
voltage
Transformer
capacity
Emergency
engine
generator
Monthly electricity
consumption
Trung Vuong
Emergency
Hospital
2 circuits and
preliminary
1 circuit
15kV 1,000kVA
+ 250kVA 550kW
110MWh by 2 contract
=220MWh
Ho Chi Minh
University of
Technology
14 circuits 380/220V - NA 5MWh to 80MWh each
Total 350MWh
Source: Made by Study Team
a. Ho Chi Minh University of Technology
Incoming lines are divided for each building. There are14 electricity contracts in the university.
Monthly consumption for each contracts are from 5,000kWh to 80,000kWh, and total monthly
consumption is approximately 350MWh.
Solar power and battery hybrid system shall be able to adjust power supply and demand for one
to some feeders. (Power supply estimation of solar power system is shown in Chapter3.3.)
b. Trung Vuong Emergency Hospital
Major loads of electricity are A/C, room lights, and medical equipments. There are medical
equipments which require a lot of electricity capacity such as MRI or CT scan.
Incoming lines are divided for each building. There are two electricity contracts in the hospital,
and amount of monthly consumptions are almost same.
Solar power and battery hybrid system shall not only useful for restrain of fluctuation of solar
power but also restrain of fluctuation by starting-up and shutting-down of medical equipment,
and useful for improvement of power factor. It has highly effect to stabilize network.
3-35
3.3 Overview of Project Plan
3.3.1 Fundamental Policy of This Project
This project will be recommended to implement based on the following fundamental policy.
Application of renewable energy such as Solar Power → Solution for shortage of power
Application of EMS to control switch of Solar power and Battery → Solution for connecting to
distribution network
Peak-cut by DR → Energy saving and efficiency
Reduction of distribution loss by DAS and AMR → Energy saving and efficiency
Improvement of reliability (reduction of outage duration) by DAS → High reliability for power
supply
The details of this project based on the fundamental policy are as follows.
1) Smart meter will be installed to all of customers in Phu Tho Power Company, so that AMR and DR can
be implemented.
2) DR can control the following load.
Normal customer: All of loads are switched off during short duration (ex: 30 minutes).
Large customer: Unnecessary load except product line etc can be switched off.
3) Solar power system with battery as asset of EVN will be installed to 2 areas as pilot project and be
connected to MV distribution feeder directly. EMS in control center can monitor and control the reverse
current and the battery.
4) Servers and operator consoles for Advanced DAS with EMS are installed in Dispatch Center for existing
SCADA and monitor / control 110kV primary substations and distribution network in Phu Tho Power
Company. Other servers for AMR, DR and EMS etc are installed in Control Center of Phu Tho Power
Company and are connected to the advanced DAS through LAN and Fiber Optic communication
network.
5) ALBS for OH will be applied as new equipment. Automatic RMU for UG will be also installed as new
facilities in existing room. The existing RMU of manual type will be removed to other suitable feeder as
manual type.
6) Fiber Optic will be applied as backbone network of communication and ZigBee will be applied for last
3-36
one mile communication between RTU and customers for at least 10 years.
3.3.2 Overview of Design and Specification
1) Control center
(1) Advanced DAS server
DAS function is to implement detecting distribution failure section, separating from failure section
and control remote monitor for LBS and RMU.
Connect LBS or LMU, communication network and RTU to distribution line, and install M-RTU on
substation of 110kV/15kV and install FEP, CPU and Console which displays Skelton in control
center.
Judgment of distribution failure section will be made by CPU, based on data from RTU though
communication line, and recovery operation of supply without failure section will be carried out by
remote control of automatic switch.
It is possible to apply higher level of automatic operation by CPU such like display of distribution
network map, if upgrade will be necessary.
Fig.3-3-1 Upgrade of system
Default
Substation
SW
SW
RTU
RTU
BT
BT
FCB
FEP
CPU
PRN
Communication line M-RTU
CPU
Upgrade
G-CRT
Console
CRT
Console
3-37
[Note]
FCB: Feeder Circuit Breaker, SW: Automatic Switch (LBS or LMU), BT: Battery
CRT: Display Monitor, G-CRT: Graphic Monitor), PRN: Printer
Source: made by Study Team
DR function is that providing command to AMR server to smart meters which are located beyond
load condition, if load control is necessary based on result of monitoring.
Operation of embedded switch “off” as DR will be carried out by AMR server.
As well, operation of embedded switch “on” will be carried out by it, when load control can be
released.
DR is different between house such as residential customers and factory as large customers.
a. House
When load control is carried out, in case of house as residential customer, it will be outage.
However, when push recovery switch which is applied in smart meter, power supply will be
recovered.
b. Factory (Large customers)
To consider troublesome that outage is happened for all electricity in factory, apply a part of
smart meters in factory will be outage to configure such as A/C. Same as house, when push
recovery switch on smart meter, power supply will be recovered.
Concerning starting timing of the DR, it is considered as follows.
In the beginning of this project, the DR should be started that in case of power consumption value
beyond specific time and power which are set for initial condition, though carry out load
monitoring in distribution network area.
In future, the DR will upgrade that it will be started after two way communication with customers
when power supply will be expected to beyond plan through always expectation.
The function of fluctuations of the PV system output power is to implement that repeat control of
rapid charging and discharging for storage battery though monitoring power output condition
from PV system to connect distribution network by advanced DAS server monitoring.
3-38
And this monitor and control is carried out through power conditioner.
When failure will be happened in distribution network, disconnect them and design will be
carried out that it can be back up power supply for owner of land to be rent.
Fig 3-3-2 Concept of function of fluctuations of the PV system output power
Source: Made by Study Team
We consider that in future, by charging up stationary battery between night and morning and discharging
them during day time, we can propose new charge-discharge control in order to realize load-shedding or
peak-cut.
送電Power transmission
電力系統Electric power system
発電Power generation
変電設備
Electrical energy transformation equipment
放電Discharge
充電Charging
パワーコンディショナーPower conditioner
電力供給Power supply
太陽電池Solar cells
蓄電池Storage batteries お客さま
Customer
Advanced DAS Server
監視制御monitor and control
PV出力 5分,20分平均化 5分,20分LPF (08/09/27)
0
500
1000
1500
2000
2500
3000
1
61
121
181
241
301
361
421
481
541
601
661
721
時間
電力
[W
]
PV出力 5分,20分平均化 5分,20分LPF (08/09/27)
0
500
1000
1500
2000
2500
3000
3500
4000
11:0
0:0
0
11:0
5:0
0
11:1
0:0
0
11:1
5:0
0
11:2
0:0
0
11:2
5:0
0
11:3
0:0
0
11:3
5:0
0
11:4
0:0
0
11:4
5:0
0
11:5
0:0
0
11:5
5:0
0
12:0
0:0
0
時間
電力
[W
]
太陽光発電の出力波形Output waveform of photovoltaics
変動抑制後の波形Waveform after curbing fluctuation
3-39
Fig 3-3-3. Concept of leveling of incoming electric power
Source: Made by Study Team
(2) AMR server
Remote automatic meter reading function is that meter reading work is carried out from far place to
measure power consumption value of house or factory such as large customer by watt-meter
function of smart meter.
Measured power consumption value is storage in smart meter internally and AMR server will
retrieve them periodically.
Furthermore, AMR server implements to calculate difference between power consumption in
previous month and the measured data, so that the data in present month will be finalized and be
sent to billing system. The reading work is completed after this procedure
At this time, data treatment will be same level of handy terminal. Automatic data connection to
billing system will be introduced in future.
Fig 3-3-4 Concept of AMR
Source: Made by Study Team
Transmission lines
(Optical fiber cable)
Wireless
Smart Meter
Meter Data Management System
(MDMS)House
Concentrator
House
Smart Meter
Optic Fiber Cable
ZigBee etc.
AMR Server and Console
Concentrator
Power consumptionCharging
DischargePeak
cut
3-40
(3) FEP
FEP is equipment to be interfacing advanced DAS server and AMR server.
Data communication between load switch and equipment in substation is carried out through M-
RTU in substation.
On the other hand, data communication between concentrator which communicate with smart meter
and PCS which communicated with solar panel and battery is carried out directory, not through
M-RTU in substation.
2) Communication
Applying optic fiber network which is hold by EVN HCMC for Advanced DAS and AMR is the best
solution as back bone network. However, there is possibility not to fully cover in the area.
The area of distribution network and periodical read of watt-hour meter is approx. 25km2 . And approx.
86sets of RTU for Advanced DAS and approx. 196sets of Concentrator need to be installed. Backbone
network needs to be covered throughout all the corner of the area of EVN HCMC, because 1set of RTU
in 0.3km2 and 1set of Concentrator in 0.1km
2 have to be installed.
According to the above reason, applying optic fiber cable network which is hold by EVN Telecom
(100% subsidiary company of EVN) and it should be throughout.
EVN Telecom is handling internet provider business and cellular phone provider as well. So they must
have base station and converter in the area. As shown in Fig 3-3-5, base station and converter connect
by optic fiber cable, so that the network of EVN Telecom is expected to be more suitable than current
fiber cable network.
3-41
Fig3-3-5 Optic Fiber Network of EVN Telecom
Source: Made by Study Team
3) Smart Meter
Smart meter consists of communication terminal, watt-hour meter and internal switch for shedding the
load.
Single phase 2-wire type and 3-phase 4-wire type of smart meter should be considered for smart grid.
Smart meter should be based on specification of currently-used watt-hour meter. The summary of
specification is shown in Table 3-3-1.
Optic Fiber Cellular Phone
Pole
Converter
Base Station
Cellular Phone
Base Station
Base Station
Base Station
Base Station
Optic Fiber
Optic Fiber
Optic Fiber
Optic Fiber
Converter
Pole
Pole
Pole
3-42
Table 3-3-1 Basic Specification of Smart Meter
1Phase-2Wire 3Phase-4Wire
Connection Direct Direct Indirect
Rate
Voltage
220-240V 3*220/380-
3*240/415V
3*220/380-
3*240/415V
or
3*57.8/100-
3*69.3/120V
Maximum
current 100A 100A 10A
Frequency 50/60Hz
Switch Assembled none
Accuracy Active
energy Class 1 or 2 Class 0.5 or 1
Measurement Item Active energy (Import, Export)
Monitoring Item Voltage (V), Current (A)
TOU Item Active energy (Import)
Tiers Max. 8
Freeze
Means Schedule, remote command, switch
Record
capacity
2 times
Record value Measurement Items, TOU items
Load Profile Capacity 30days
Interval 15, 30, 60min
Log
Recording
Capacity 300 events
Record event
Supply failure
Reset
Irregular
Disconnect operation
Freezing
Source: Made by Study Team
(1) Switch
Switch is assembled in a smart meter.
It allows remote switching and supply of power is started/stopped (e.g. due to moving) due to
moving without employee visit a customer.
It is possible to open the incorporated switch for the purpose of controlling the power consumption
in regional energy management.
(2) Measurement and monitoring
The current watt-hour meter only enables to measure power consumption of active energy, but smart
meter enable to measure voltage and current, as well as power consumption of active energy.
3-43
Measuring voltage can be confirmed that supply voltage to house or factory within specified range ,
so that it is used for optimum voltage supply operation.
On the other hand, measuring current can be realized current value which is consumed by house or
factory, and it is contributed to minimize power consumption by visible encourages.
Of course, it is possible to encourage consumers to save energy by making the active energy seeable.
(3) TOU
Used when the time of day tariff system is established.
(4) Freeze
Indicates the billing reset date.
(5) Load Profile
Indicates the demand measurement.
(6) Log Recording
Indicates the function to record and save events concerning the smart meter.
Concentrator which is communicated with smart meter, is capable of connection 500 sets of smart
meters per one concentrator. However, it is possibility not to perform enough by worse
communication condition.
In this case, the number of sets of concentrator needs to be increased and reduced the number of
smart meters per one concentrator or add out door repeater to improve communication sensitivity.
But in this case, it is concerned that the number of concentrator will become much larger than the
number of RTUs in distribution network. Therefore, RTU can‟t coalesce with concentrator .
4) Distribution equipment
It is shown that automatic distribution equipments are installed at 110kV/15kVsubstation in Table 3-3-2.
3-44
Table 3-3-2 Component of Substation Equipment for DAS
Component Explanation
M-RTU
M-RTU is installed in each substation to control all RTUs linking to the feeders of the substation and monitor the substation devices. (Sample)
Automatic Reclosing
Relay for FCB of OH
Lines
Automatic Reclosing Relay is installed in existing FCB board at substations. (Sample)
TRD Board
TRD board is installed in each substation to measure the voltage and current for the banks and feeders.
Source: Made by Study Team
3-45
It is shown that automatic distribution equipments are installed at OH distribution line in Table 3-3-3
Table 3-3-3 Component of Upgrading DAS Field Equipment for OH Lines
Component Explanation
LBS
LBS is automatically switching equipment of OH line controlled through RTU. (Sample)
Switch Power Supply
(SPS)
SPS is to supply the power and detect the voltage.
RTU
RTU is to control LBS by receiving command from Control Center through M-RTU and sending status data to Control Center.
Arrester
(for protection against
lightning surge)
As the field equipment for OH is installed in outside, the protection equipment against lightning is necessary. Therefore, Arrester should be installed near DAS field equipment. (Sample)
Source: Made by Study Team
LBS
RTU
SPS
3-46
It is shown that automatic distribution equipments are installed at UG 15kV distribution line in Table 3-
3-4.
Table 3-3-4 Component of Upgrading DAS Field Equipment for UG Lines
Component Explanation
RMU
(in Kiosk)
RMU is normally installed in Kiosk and the major functions are to switch the load current for distribution feeder and to break fault current for branch circuits. In the Project, new RMU are installed when the existing RMU are too old to operate. RMU for DMS (DAS) normally consists of two main circuits for automatic LBSs, two CB, RTU and Battery etc. (Sample) Main functions are as follows. - Detection of fault current - Adjusting unbalanced load for each phase - Communication and switching under no-voltage - Automatic switching with high speed of less than 1 second - High reliability against water, salt, dust and so on
RTU
RTU is a control system for RMU by receiving command from DAS through M-RTU and sending status data to Control Center. RTU has a fault detecting function as well.
Battery
Current sensing system requires battery for switching of RMU without the distribution line voltage. Battery has to be changed every 2-3 years. Battery charger is also necessary.
Source: Made by Study Team
3-47
Based on three sectionalized and three connected feeder method, 15kV distribution lines will be sectioned
by LBS. It is configured that one distribution lines is split up into three sections and every distribution lines
connects the other one.
15kV UG distribution lines also will be replaced to RMU same method.
Fig.3-3-6 Three sectionalized and three connected feeder method for OH distribution lines
Source: Made by Study Team
5) Solar Power
(1) Scale of Solar power plant
Capacity of solar power system is required huge amount of scale for adjust power supply and whole
of energy consumption of each candidate place. But in this project solar power system is positioned
as pilot plant, then its scale shall be not surplus scale of site area and cost.
20kW of solar power system requires approximately 300 square meters. This capacity‟s solar power
system shall adequate to install the panels on the roof top or above car parking space in the
candidate sites.
Plan for panel layout is shown on Fig. 3-3-7. This plan indicates using amorphous silicon type panel
and 20 degrees of panels slope angle.
Tie switch
Sectin switch
3-48
Fig 3-3-7 Layout plan for 20kW of solar power panel
Source: Made by Study Team
(2) Outline of solar power plant
Types of solar power panels are shown Fig. 3-3-7 Crystallize silicon semi-conductor type solar
panel is the most utilize at present. Although crystallize silicon semi-conductor type solar panel has
efficient of conversion, characteristic of temperature is not good and decrease output under high
temperature.
In recent years lots of amorphous silicon type solar panels are shipped as a new type of products.
Their efficient of conversion is not good and requires much space. But characteristic of temperature
excels and decrease of power output is small under high temperature. Then more energy shall
generate under atmosphere of HCMC. In this reason this study adopt amorphous silicon semi-
conductor type solar-power panel.
Fig3-3-8 Variety of Photovoltaic cell
Source: Made by Study Team
28m
10m
Photovoltaic cell Silicon
Semi-conductor
Crystallize
type Mono-crystallize
Multi-crystallize
Infinitesimal crystallize
thin film type
Amorphous thin film type
Compound
semi-conductor
Crystallize
type Mono-crystallize
Multi-crystallize
3-49
(3) Energy generation by solar power plant
Approximately energy generation by solar power plant is assumed by monthly solar radiation data.
Adequate slope angle of panel is assumed around 20 degree. This means much solar radiation can
gains in winter time in HCMC. Annual energy generation by 20kW solar power is estimated as
Table 3-3-5.
This is around 10% of consumption of candidate place, and it is enough energy generation as pilot
plant.
Table3-3-5 Annual energy generation by 20kW solar power plant
Slope angle Estimation of annual
energy generation
20degree 28.6MWh
0degree 26.3MWh
Source: Made by Study Team
(4) Outline of energy storage battery
Energy storage battery for energy storage is shown in Table 3-3-6.
3-50
Table 3-3-6 Comparison of energy storage battery
Sodium-sulfur battery Lead battery Nickel hydrogen
battery
Lithium ion battery
Characteristic
・Large capacity
・Very high density of
energy
・No memory effect
・long life of cycle
time,
・reasonable cost
・Small capacity
・generality of
maintenance
technique
・short life of cycle
time,
・reasonable cost
・Small to medium
capacity
・High efficiency of
charge and discharge
relatively
・Small to medium
capacity
・High efficiency of
charge and discharge
relatively
・no memory effect
・very high efficiency of
charge and discharge
・long life of cycle time
・reasonable cost
Present
condition
・Monopolize for large
scale energy storage
・Generally used for
UPS system
・requires huge area for using energy storage
・A lot of used for electric
car
・Development as
medium or small
capacity energy storage
system
・direct connect at direct
current circuit with
solar power and good
compatibility with solar
power
・Now on make progress
for electric car, and
willing to decrease cost,
Consideration
for use
・Operate under high
temperature, and if
not use every day,
loss turns up
・possible that
regulation of
treatment of
dangerous object
・Life time turns
down extremely,
when not attention
with depth of
discharge
・Costly when install
large scale
・Costly when install
large scale
Comment
・A lot of record as
energy storage
・large capacity
・Compact
・long life of cycle
time
・Reasonable price
・a lot of record as a
industrial use
・ease of acquisition
・Adequate for medium
scale solar hybrid
system
・Most compact as use
feasibly room
temperature
・High energy efficient of
change and discharge
・long life of cycle time
Source: Made by Study Team
In this project solar power plant capacity is 20kW. Consideration of present development situation
of energy storage battery and characteristic of battery, most adequate battery is Lithium ion battery
or nickel hydrogen battery. In this case, recommended battery is lithium ion battery considering with
possibility.
Major purpose of battery system is absorption of fluctuation of solar power plant and load.
Report from NEDO “Technical development of smoothly grid connection of energy storage system”,
required specification of energy storage battery was shown. Required spec of energy storage system
for 20kW solar power is estimated as Table3-3-7 by this study.
3-51
Table3-3-7 Capacity of battery system for absorption of fluctuation of solar power
Object Result of study
by NEDO This project
PV output 100kW 20kW
Average time 5min 5min
Maximum output
alternation 75kW/s 15kW/s
Maximum capacity of
battery 4.1kWh 1kWh
Source: Made by Study Team
Battery system repeat charge and discharge cycle accompany follow fluctuation by solar power, it is
needed to operate of depth of discharge by consideration of life time as around 20 years. Capacity of
battery is chosen consideration with this. As the result, the specification of battery system is chosen
as follow.
Table 3-3-8 Specification of energy storage battery
Item Specification
Capacity of battery 4.2kWh
Specification of
inverter system
15kW
Source: Made by Study Team
3-52
Component of solar power and battery hybrid system is shown Fig. 3-3-9.
Fig. 3-3-9 Component of solar power and battery hybrid system
Source: Made by Study Team
20kW PV Panels
20kW PV Inverter 15kW Battery
Inverter
4.2kWh Li-ion
Battery
Controller
Connect to
Emergency Circuit
For customer
Connect to grid Controlled by DAS
LV switch board
incl. SM
3-53
3.3.3 Contents of Project
1) System configuration
The basic system configuration including all of projects is shown in Fig. 3-3-10.
Fig. 3-3-10 System configuration of Project
Source: Made by Study Team
Control Center
110kV/15kV
Substation
Distributiion feeder
(Overhead)
Distributiion feeder
(Underground)
FCB
LBS
TRD
VS
VCB Road
Solar Power
RTU
Advanced DAS Server
Smart Meter
Switch
WHM
Comunication
AMR Server
Console
FCB
VSRMU
Battery
PCSPCS
RTU
Concentrator
Concentrator
M-RTU
FEP
Optical fiber
Network
3-54
2) Component in the project
A lot of Smart Meter data are transmitted to RTU through communication of last one mile (ZigBee).
The gathered data including LBS/RMU/Solar Power are transmitted to the control center through
backbone network and M-RTU in substation.
Smart Meter consists of communication device, Watt Hour Meter (WHM) and SW for future peak-cut.
In case of applying AMR, the most suitable communication network as recommendation will consists of
Fiber optic for DAS and ZigBee as the last one mile communication between RTU and Smart Meter.
This communication network will be useful for future projects such as peak-cut by DR.
Table 3-3-9 Explanation of equipment in project
Equipment Explanation
FCB FCB is a circuit breaker to switch the fault current.
FEP FEP is a data processing system to transfer data and command between the computer and communication system.
LBS (for OH) LBS is a switch of section of feeder installed in OH line.
RMU (for UG) RMU is to switch the section of feeder installed in Kiosk in UG network. The existing switch in RMU will be modified to automatic mechanism if possible. The new RMU is also equipped with automatic switches.
M-RTU M-RTU is installed in substation and the function is to control all of Remote Terminal Units under the substation.
RTU,PCS RTU and PCS is a control unit for LBS, RMU, Solar Power in the field.
Smart Meter Smart Meter is to implement AMR function and DR in future with interactive communication.
AMR AMR is to measure the power consumption and send the data to the billing system.
DR DR is to cut or shift the peak load by control of load such as A/C (Air Conditioner).
SW SW in Smart Meter is to control the customer load (ex A/C load) in future.
DMS DMS is to improve the reliability of distribution network and to reduce the distribution loss.
Advanced DAS Advanced DAS performs energy management of distribution feeder (Solar Power) and SCADA function for 110kV primary substation.
Source: Made by Study Team
3-55
3.3.4 Problems of Proposed System and Solution
1) Peak-cut by DR
Peak-cut by DR are proposed as follows.
Large customer: Unimportant loads such as A/C are switched off by DR.
Normal customer: All of loads are switched off by DR.
Based upon customer survey, large customers may well accept the outage of unimportant load for short
duration (example: 30 minutes) due to no outage of important load.
Normal (Small) customers are under outage for short duration, so that the dissatisfactions in the
customers are concerned in spite of short outage. As for the solution, the customers can switch on by
manual operation while the outage by DR happens. However, if most of customers will switch on, the
effect of peak-cut decrease, so that incentive is needed to advance the effect. The following incentives
are considered as ideas.
If manual operation will be implemented in the state of peak-cut, the tariff becomes much higher.
The cooperated customers can receive the privilege such as preferential tax or tariff.
The cooperated customers can receive the citation as the cooperation.
Regarding the peak-cut by DR, it is necessary to consider whether there are some problems for law in
Vietnam or not. According to MOIT, there are no problems on law for the peak-cut but take care to cut
off frequently because the National Diet will be possible to discuss due to a lot of complaints of
customers. EVN has already cut off the customers on each substation, so that we think this better outage
procedure for each customer will be acceptable.
Regarding the peak-cut by DR, there are no problems on law in Vietnam but the incentive shall be
considered in order to accelerate the energy efficiency.
2) Renewable energy such as Solar Cell
According to the International Forum on Wind Energy Development of Vietnam on 5/11/2009,
Solar Energy in Vietnam is 4-5 kWh / m2, so that the conversion to kW is around 0.1 kW / m
2 .
The area of Vietnam land is around 330,363 km2 and the capability of power can be calculated as
follows.
Assumption: 1/10 in land is available for installation of Solar Power.
0.1 kW x 330,000 x 106 x 1/10 = 3,300 GW
3-56
The capability of solar power is huge and the solar is effective for solution on increasing peak load.
However, batteries shall be equipped in order to solve unstable generation problems influenced by
weather condition etc, so that the cost becomes more expensive.
In case of Japan, the following support system on law has been carried out, so that the Solar Power
could be expanded up to 1.4GW in 2005 and will be anticipated to reach to 14-28 GW in 2020.
Government support a part of the installation cost.
Power companies have purchased with higher tariff (48 yen /kWh) for the Solar Power since
November in 2009.
However, the increased expenses on power companies can add to the normal tariff as green cost.
In case of Vietnam, the supporting money for renewable energy will be considered on new law of
energy efficiency which was set up on 1st of January in 2011. However, the supporting money is small
and is limited, so that the solar power will not expand widely. In order to accelerate the installation of
solar power, not only is the cost decreased, but also the additional supporting money or other regulation
is needed.
When a lot of renewable plants will be connected to the distribution network in EVN, problems such as
voltage-drop / safety etc occur. The following solutions against the problems will be considered in this
project and will be confirmed.
Solar cell with battery will be installed to 2 locations.
The reversed power and battery are monitored and controlled by EMS.
EMS also monitors and controls the switch for the solar.
4-1
Chapter 4 Evaluation of Environmental and Social
Impacts
4.1 Environmental and Social Condition of Target Area
4.1.1 Situation Analysis
Vietnam has been faced with severe power shortage mainly due to the delay of the development of
generation facilities in the country1. The reliability of distribution system stays low as the power loss rate in
2008 shows as high as 9.21%2 even though it saw a decline from previous years. The household
electrification rates and electricity consumption growth rate on the other hand reached 95.5% and 12.8%
respectively in 2008, and the number of customers and their power demand are expected to keep expanding.
Electricity customers in HCMC have been suffering from load shedding once or twice a week during the
dry season, which lasts all day long from morning until evening. Social adverse impacts caused by the
power cut have been seen as immense economic losses in major industries, and households‟ daily activities.
Over 55% of the electricity sales of the District 10 and District 11 of HCMC, to which Phu Tho Power
Company has extended its service, have been given to residential units (See the Chapter 1). Unlike
manufacturing unit and enterprise unit, stepping prices are applied to ordinary households as well as
small-scale retailers and offices running their business on the ground floor of ordinary housing complexes
in residential areas. Customers of residential units know that their electricity rates are gradually raised as
they consume, but are not fully aware around what time the power demand is high (peak hours), not high
(off-peak hours) and moderate (normal hours) because their electricity rates do not depend on when they
consume. Their consumption without an idea of shifting their demands for the benefit of a whole
community therefore has given an immense impact to the peak demand.
4.1.2 Future Projection (“without” the Project)
According to the draft paper of the Seventh PDP, the demand growth rates will reach 12 to 14% by 2015,
and 10 to 11% by 2020. The development of generation facilities (such as construction of gas turbine
thermal power plants) is an immediate need for meeting the growing electricity demand in case the Project
is not implemented.
The thermal power plants, in general, have direct and indirect environmental impacts such as CO2 emission
1 The installed capacity as of December 2008 is 15,678 MW, and power generation (output) is 74,224 million kWh. 2 EVN Corporate Profile 2008-2009.
4-2
and flue gas. Land acquisition and involuntary resettlement are also critical social issues to tackle. The
recent commitment to the development of nuclear power generation facilities in Ninh Thuan Province
shown by the Government of Vietnam is a positive sign in terms of generation capacity increase. However,
such nuclear power needs a long-term period of construction, during which social and economic losses
keep growing, and environmental and social impacts will be directly and indirectly immense which requires
considerable mitigation measures. The residents of HCMC, moreover, will not be affected by such
generation facilities as the facilities will be developed not in HCMC but in the suburban provinces near
HCMC, which may provoke the affected local residents to feel unfair.
4.2 Project Effectiveness in Environmental Improvement
4.2.1 Social Positive Impact on Customers by DAS
The DAS which enables remote operations of ALBS from the Power Company Office, will improve power
supply reliability of the current distribution system in the target areas. The number of customers and the
length of power outage caused by accidents will be mitigated3 which will reduce disturbance in their daily
activities and lives. Improvements in socio-economic aspects, in particular, will thus be expected such as
growth of local economy in employment and livelihood, betterment of existing social infrastructure and
social services, and equal distribution of benefits and losses.
4.2.2 Peak Shift and Energy Saving by AMR
The AMR introduced in the Project will require installment of smart meters, communication network, and
sales department system. The AMR can identify all customers‟ power usage patterns, and stop power
supply to them by automatically turning on and off the switch inside of the smart meter to reduce the peak
demand. It will help control power demand and shift the peak in easier and more effective way. The
necessity of constructing new generation facilities to meet the peak demand will thus be mitigated and
energy saving will be promoted.
By making the own power usage pattern visible for residential customers including retailers, they will
change their mindsets and learn to save their money through reducing their energy consumption around
peak hours and use while off-peak hours. In a long run, it will help the customers acquire a habit of saving
energy.
3 2.5 times more number of customers will recover their power distribution within a shorter period, and it will take one tenth
of time (TEPCO).
4-3
Photo 4-1 Residential cum Retailing Customers in HCMC
Source: Taken by Study Team
4.2.3 Distributed Power Generation Facilities (Solar Power)
As an alternative of gas turbine thermal power plant construction to meet the peak demand, a distributed
power generation model, i.e., solar power generation facilities, is proposed in this Project. The solar power
will not require fuel and thus not emit CO2 or flue gas by combustion of fuel. Installing solar power
facilities in a dense city like HCMC has environmental and social advantages. PV panels can be installed at
the roofs of buildings and sunshades of parking lots, for instance, which require no new land acquisition.
4.3 Project Impact on Environmental and Social Aspects
4.3.1 Screening based on JICA guideline
1) Issues to be raised for project implementation
Based on the JETRO Guidelines for Environmental and Social Consideration as of July 2009,
environmental and social assessment items have been examined in this study for the future scoping
conducted in feasibility studies and environmental impact assessments conducted at the stage of project
implementation. When examining project impact on environmental and social aspects, check items in the
Screening Format and the Environmental Checklist (6. Power Transmission and Distribution Lines) of
“Japan International Cooperation Agency Guidelines for Environmental and Social Consideration” (April
2010) have been referred4.
4 As the result of the merger of four policy-based financing institutions, overseas economic cooperation department of the
former Japan Bank for International Cooperation was separated and merged into Japan International Cooperation Agency as
of 1st October 2008. The rest of the former JBIC is now with the Japan Finance Corporation as its international wing. The
JBIC Guidelines for Environmental and Social Consideration (April 2002) and JICA Guidelines for Environmental and
Social Guidelines (April 2004) were integrated and revised as of April 2010.
4-4
2) Sensitive Areas
The Project will be conducted for the benefit of all customers of the District 10 and District 11 which
are under service of Phu Tho Power Company. These two districts are well developed urban and inland
area and located in the center of HCMC where population as many as 7,165,398 (estimated in 2009)5
lives. There are 54 ethnic groups including the majority Kinh in Vietnam, and HCMC holds many
numbers of Khmer, Hoa and Cham ethnics. These ethnic minorities join formal education in Vietnamese
language and they enjoy modern way of living as the Kinh people do in these urban centers. And none
of the sensitive areas in the following Table 4-3-1 are therefore found there.
Table 4-3-1 Application of sensitive areas to the project
Sensitive areas Application to the
project
1 National parks, nationally-designated protected areas Not Applicable
2 Primary forests or natural forests in tropical areas Not Applicable
3 Habitats with important ecological value Not Applicable
4 Habitats of rare species that require protection under domestic legislation,
international treaties, etc. Not Applicable
5 Areas in danger of large-scale salt accumulation or soil erosion Not Applicable
6 Areas with a remarkable tendency towards desertification Not Applicable
7 Areas with unique archeological, historical, or cultural value Not Applicable
8 Areas inhabited by ethnic minorities, indigenous peoples, or nomadic peoples with
traditional ways of life, and other areas with special social value Not Applicable
Source: Developed by Study Team
Photo 4-2 Typical Scenes of the District 10 and District 11 of HCMC City
Source: Taken by Study Team
5 The estimated population density of the District 10 is estimated 40,277 person per m2 in 2009 (area: 5.72 m2, population:
230,286), and that of the District 11 is estimated 44,931 (area: 5.14 m2, population: 230,946). They are the third and the
fourth biggest to the District 4 (46,542 person per m2) and the District 5 (45,260 person per m2). The estimated average
population density of urban HCMC is 11,911 person per m2 in 2009 (HCMC Statistical Office, HCMC Statistical Yearbook
2009, Statistical Publishing House, 2009).
4-5
3) Sensitive Characteristics
The Project will include replacement and disposal of existing customer meters, installment of smart
meters, replacement and reuse of switch gears, installment of other facilities and equipment,
establishment of the communication system, establishment of the solar power and battery system,
installment of transformers and set up of a distribution control center.
The control center will be established within the existing complex of Phu Tho Power Company, which
requires no new land acquisition in HCMC. The sensitive characteristics quoted in the following Table
4-3-2 therefore are not applied to the Project.
Table 4-3-2 Application of sensitive characteristics to the project
Sensitive characteristics Application to the project
1 Large-scale involuntary resettlement No temporary and permanent resettlement is anticipated.
2 Large-scale groundwater pumping It is not applicable to the Project.
3 Large-scale land reclamation, land
development, and land clearing The Project will not include such works.
4 Large-scale logging The Project site is located in the heart of developed area of
HCMC, and there are no forests existing there.
Source: Developed by Study Team
4) Impacts on Environment
Impacts on environment caused by the project implementation have been analyzed as shown in the
following Table 4-3-3 and Table 4-3-4. Impacts during construction stage and that of operation stage
have been separately examined. It is anticipated that the environmental load caused by the Project will
stay subtle, whereas it will bring positive impact to the environment. The “(+)” in the tables shows
positive impact, “(-)” shows negative, no mark means no (or almost no) impact, and “-” shows it cannot
be anticipated at the moment. The tables describe anticipated impacts and countermeasures.
Table 4-3-3 Anticipated impact on environment (construction stage)
Item Impact Construction stage Measures
1 Air pollution (-)
Transportation vehicles may
cause exhaust gas and dust while
carrying facilities and equipment
into the project site.
・ Periodic inspection and
maintenance work should be
properly conducted.
・ Efficient schedule management
of the whole construction
works, and proper time
management of the use of
equipment should be secured.
・ Watering on the streets should
be periodically done.
2 Water pollution (-)
Ground water can be
contaminated when optical fibers
are installed.
To treat by sedimentation and
carrying contaminated water to
water treatment plant by sealed
tank.
4-6
3 Soil pollution Not particularly anticipated. -
4 Waste (-)
The existing transformer may
contain PCB, and proper
treatment should be done when
being replaced.
Industrial waste disposal
contractor should be selected for
proper waste treatment.
5 Noise and vibration (-)
Transportation vehicles may
cause noise and vibration while
carrying equipment to the site.
・ Periodic inspection and
maintenance of transportation
vehicles should be properly
conducted.
・ Efficient schedule management
of the whole construction
works, and proper time
management of the use of
equipment should be secured.
6 Ground subsidence
Activities such as the intake of
groundwater are not planned in
the Project, and there is no ground
subsidence therefore anticipated.
-
7 Offensive odors Not particularly anticipated. -
8 Geographical features Not particularly anticipated. -
9 Bottom sediment Not particularly anticipated. -
10 Biota and ecosystems Not particularly anticipated. -
11 Water usage Not particularly anticipated. -
12 Accidents (-) Inappropriate safety management
can lead to accidents at any time.
Safety manual should be
developed and applied.
13 Global warming Not Applicable -
14 Involuntary resettlement Not Applicable -
15 Local economies, such as
employment, livelihood etc (+)
Employment opportunities for
laborers may benefit local
community and lead to
improvement of local livelihoods.
Labor Law should be strictly
followed and payment should be
properly done to the laborers.
16 Land use and utilization of local
resources Not Applicable -
17
Social institutions such as social
infrastructure and local
decision-making institutions
Not Applicable -
18 Existing social infrastructure and
services Not Applicable -
19 Poor, indigenous, or ethnic people -
There are ethnic minorities such
as Khmer, Hoa and Cham living
in HCMC6. The disparity between
the rich and the poor in HCMC is
7 times.
Priorities or affirmative actions
can be given to them when
necessary.
20 Misdistribution of benefits and
damages Not Applicable -
21 Local conflicts of interests Not Applicable -
22 Gender Not Applicable -
23 Children‟s rights Not Applicable -
24 Cultural heritage Not Applicable -
6 24,268 Khmer, 414,045 Hoa and 7,819 Cham ethnics were reported in HCMC when the census was conducted in 2009.
Majority of them lived in urban areas of the city.
4-7
25 Infectious diseases such as
HIV/AIDS (-)
There may be a risk of infection
when collecting laborers from /
out of the local community.
Contraceptive devices can be
distributed for immediate
solution, and awareness raising
program should be organized for
long-term impact.
26 Others Not Applicable -
Source: developed by Study Team
Table 4-3-4 Anticipated impact on environment (operation stage)
Item Impact Operation stage Measures
1 Air pollution (+)
SOx, NOx, CO, O3, soot, dust,
SPM will not be discharged by
the operation.
The project will help reduce
number of hours of load shedding,
which will mitigate air pollution
caused by burning fuels for the
operation of generators as
customers will not have to use
generators often.
-
2 Water pollution Not Applicable -
3 Soil Pollution Not Applicable -
4 Waste -
PV panel can last for 20 years,
and its battery 5 to 7 years.
Periodic replacement of panel and
batteries will be necessary and
proper treatment or recycle (or
reuse) should be done.
Industrial waste disposal
contractor should be selected for
proper waste treatment.
5 Noise and vibration (+)
The project will help reduce
number of hours of load shedding,
which will mitigate noise and
vibration caused by the operation
of generators to certain extent as
customers will not have to use
generators often.
-
6 Ground subsidence Not Applicable -
7 Offensive odors (+)
The project will help reduce
number of hours of load shedding,
which will mitigate offensive
odors caused by burning fuels for
the operation of generators to
certain extent as customers will
not have to use generators often.
-
8 Geographical features Not Applicable -
9 Bottom sediment Not Applicable -
10 Biota and ecosystems Not Applicable -
11 Water usage Not Applicable -
12 Accidents (+)
Accidents will be appropriately
and immediately treated by DAS,
which will help reduce number of
workers who suffer to get an
electric shock during their works.
-
13 Global warming (+)
The Project will help contribute to
the mitigation of global warming
by DR and application of solar
-
4-8
power and other renewable
energy sources.
14 Involuntary resettlement Not Applicable -
15 Local economies, such as
employment, livelihood etc (+)
The Project will improve the
reliability of power supply, which
will help reduce the number of
defective products caused by the
power outage and/or low voltage.
It also will help increase local
employment opportunities and
improve local livelihoods.
・ Observation by meter reader
and bill collector can be
conducted. Periodic interview
with customers can also be
conducted.
・ Transition of electricity
consumption over years can be
observed.
・ Transition of the number of
defective products over years
can be observed
・ The degree of local industry
promotion can be observed over
years.
16 Land use and utilization of local
resources Not Applicable -
17
Social institutions such as social
infrastructure and local
decision-making institutions
Not Applicable -
18 Existing social infrastructure and
services (+)
The Project will improve the
reliability of power supply, which
will help reduce the number of
defective products caused by the
power outage and/or low voltage.
It also will help increase local
employment opportunities and
improve local livelihoods.
・ Observation by meter reader
and bill collector can be
conducted. Periodic interview
with customers can also be
conducted.
・ Transition of electricity
consumption over years can be
observed.
・ Transition of the number of
defective products over years
can be observed
・ The degree of local industry
promotion can be observed over
years.
19 Poor, indigenous, or ethnic people -
There are ethnic minorities such
as Khmer, Hoa and Cham living
in HCMC. The disparity between
the rich and the poor in HCMC is
7 times.
Priorities or affirmative actions
can be given to them when
necessary.
20 Misdistribution of benefits and
damages Not Applicable -
21 Local conflicts of interests Not Applicable -
22 Gender Not Applicable -
23 Children‟s rights Not Applicable -
24 Cultural heritage Not Applicable -
25 Infectious diseases such as
HIV/AIDS Not Applicable -
26 Others (-)
Adverse impact on the elderly
people (such as heat stroke) may
be caused by the smart grid load
shedding.
・ Observation by meter reader
and bill collector can be
conducted. Periodic interview
with customers can also be
conducted.
・ Weather forecast should be paid
attention to and customers
should be well informed of the
possibility of high temperature.
・ Advises can be given to
4-9
customers for better insulation
and ventilation in their living
environment.
Source: Developed by Study Team
4.3.2 Comparison with Alternatives
It is pointed out that power generation capacity should be strengthened by installing generation facilities
such as gas turbine thermal power plants to meet the peak demand in order to solve the severe power
shortage. As an alternative to the further development of large-scale power generation facilities, this Project
proposes to install PV panels as a model of solar power generation to secure distributed generation
facilities.
Like other renewable energy sources, solar power generation will not produce CO2 or exhaust gas in its
operation as it will not use any fuel for power generation. However certain amount of CO2 will be created
indirectly in the process of panel production and their installation. A report published by the CRIEPI7, the
amount of CO2 produced by solar power generation is 0.038kg- CO2/kWh in its life cycle of 30 years. This
amount is far much less than those of coal, and the CO2 emission will be considerably mitigated compared
with oil and LNG thermal power generation (0.599~0.943kg- CO2/kWh) (Fig.4-3-1).
There will be no new land acquisition required for solar power generation as the panels can be installed on
the roofs of buildings and the sunshades of parking lots, which is one of the advantages of distributed
power generation facilities in a city like HCMC where people are dense.
Fig. 4-3-1 Life Cycle CO2 Emissions by Generation Source
0.079 0.043 0.123 0.098 0.0110.0130.0200.0380.025
0.864
0.695
0.476
0.376
0.000
0.200
0.400
0.600
0.800
1.000
Coa
lOil
LNG
(con
vent
iona
l)
LNG
(com
bine
d cy
cle) PV
Win
d
nuclea
r
geot
herm
al
hydr
o
kg-CO2/kWh (LHV)
Direct (Fuel for generation)
Indirect
7 Life cycle CO2 emissions per kWh by standard generation technologies were estimated with updated CO2 intensity of raw
materials taken into account in Japan.
4-10
Source: “Evaluation of Life Cycle CO2 Emissions of Power Generation Technologies –
Update for State-of-the-art Plants – (Rep.No.Y09027)”. July 2010. Central Research
Institute of Electric Power Industry
Anticipated environmental and social impacts brought by coal-fired thermal power generation as an
alternative to this Project are shown in the Table 4-3-58. Although the development of large-scale power
generation facilities will be taken place out of HCMC, which will not bring direct adverse impacts to the
immediate beneficiaries of the Project, they will be suffered from the power shortage in their daily lives and
have to wait for a long time until the generation facilities are completed.
Table 4-3-5 Possible environmental and social impact by coal-fired power plant construction
No Item Impact During construction stage During operation stage
1 Air Pollution (-)
Air pollution can be caused by exhausted
gas from transportation vehicles and
construction machinery. And dust
particles may be scattered near the
construction site and construction vehicle
road.
NOX, SOX and soot will be generated due
to the combustion of fuels. And coal
transportation may generate coal dust.
2 Water Contamination (-)
Drainage caused by rainfall, equipment
washing drainage, and sewage will be
generated during the work. And if waste
management isn‟t appropriately
conducted, effluents from waste may be
generated.
Thermal discharge will be produced
when using river water as cooling water.
Plant effluent and domestic waste water
will be generated through plant
operation. In case waste management
methods aren‟t appropriately conducted,
effluents from waste may be generated.
3 Soil Pollution (-)
Soil pollution can occur due to
lubrication oil or fuel oil spillage from
transportation vehicles and construction
machinery.
Soil pollution can occur due to
lubrication oil or fuel oil spillage for unit
operations. When an ash pond is used, it
is necessary to pay attention to the
contaminations from the pond.
4 Waste (-)
Construction work will generate metal
chips, waste plastic, wood shavings,
waste glass and waste oil. Domestic
wastes such as cans, bottles and food
residue will be generated by construction
workers at their work stations.
By-products generated through the
operation of coal-fired power plant are
coal ash, gypsum, sludge from waste
water treatment facility, and cooling
water canal fouling.
These by-products will be wasted if they
are discarded without recycling.
Maintenance work will generate metal
chips, waste plastic, wood shavings,
waste glass and waste oil. And domestic
waste such as cans, bottles, and food
residue will be generated at the workers‟
stations.
5 Noise and Vibration (-)
Noise and vibration arise due to
vibrations from transportation vehicles
and construction machinery.
Steam blowing during commissioning
will also generate significant noise.
Noise and vibration will be generated
through the operation of power facilities.
If a cooling tower is used, there is
significant noise and vibration from the
cooling fan of the tower.
For periodic inspections, noise and
vibration may arise due to vibration from
transportation vehicles and construction
machinery. When using vehicles for coal
transportation, noise and vibration may
occur.
8 The degree of impact depends in terms of geographical features, bottom sediment, biota and ecosystem, involuntary
resettlement, the poor, indigenous and ethnic people, local conflict of interest, and cultural heritage. The impacts described in
the table are therefore based on general assumption.
4-11
6 Ground Subsidence (-)
If the underground water level decreases
due to water being used for construction
work, there is a possibility of ground
subsidence occurring. However, water
usage during construction work stays
minimum, and such possibility is small.
There is a large possibility of ground
subsidence occurring if ground water is
used as cooling water.
7 Offensive Odor (-)
If the domestic waste management isn‟t
applicable at worker stations, offensive
odor may be generated due to waste
decomposition.
If ammonia used at SCR leaks, it may
become a source of offensive odor. If the
domestic waste management isn‟t
applicable at worker stations for
maintenance work etc, offensive odor
may be generated due to waste
decomposition.
8 Geographical Feature -
There is little impact if the proposed site
is plain. Examination will be necessary if
the site has any outstanding geographical
features.
-
9 Bottom Sediment -
If the proposed site is located inland,
there is no possibility of bottom
sediment. It is necessary to examine
when selecting the site.
-
10 Biota and Ecosystem -
Examination will be required if there
exists animals in the site that area
categorized in the IUCN Red list. Site
location and transmission line route
should be carefully examined in order to
avoid lands with environmental value.
-
11 Water Usage (-)
If the underground water level decreases
due to water used during construction
work, there is a possibility of adverse
impact to life water usage. Since water
usage for construction work is not
expected so large, the impact of
underground water level reduction on
water usage will be small.
If underground water is used for cooling
water, it will have a large impact on
water usage by decreasing underground
water level.
12 Accident (-)
Construction accidents may be caused
due to the defects of health and safety
management of construction work. It is
necessary to pay attention especially to
high altitude areas where accidents from
falling may occur as well as construction
vehicle road accidents and electricity
accident.
There is possibility of accidents
occurring such as fires due to oil spillage
or instantaneous combustion of coal,
accidents due to leakage or spillage of
chemicals like caustic soda and sulfuric
acid, accidents or incidents involving
maintenance work.
13 Global Warming (-) Transportation vehicles and construction
machinery will emit CO2.
CO2 will be emitted through operation of
coal-fired power plant.
14 Involuntary
Resettlement -
Land acquisition and involuntary
resettlement can be required.
Damage to houses and health hazards can
be caused by smoke extraction, noise
pollution, water pollution and ground
subsidence when the resettlement action
plan is not appropriately planned and
implemented.
Political intervention and/or local
movement against the operation of the
power station can occur when adverse
impacts on local residents‟ lives and
livelihoods are severe.
15
Local Economy such
as Employment and
Livelihood etc
(-)
Loss of employment and livelihoods can
be caused by temporary loss of
agricultural lands during the construction
period.
Permanent loss of employment and
livelihoods can be caused by land
acquisition due to power station
construction and surrounding areas]
16
Land Use and
Utilization of Local
Resources
(-)
Current land use and utilization of local
resources may be affected by the selected
location and transmission line route.
Temporary loss of present land use
Current land use and utilization of local
resources however may be affected by
the selected location and transmission
line route.
4-12
pattern and/or economic infrastructure
may occur
Permanent loss of present land use
pattern and/or economic infrastructure
may occur.
17
Social Institutions
such as Social
Infrastructure and
Local Decision
Making Institutions
(-)
Disruption of local community can be
caused via a conflict of interests among
politicians, government offices, and
residents. It might cause a delay in
procedures of land acquisition and
resettlement.
-
18 Existing Social
Infrastructure (-)
Temporary loss of existing social
infrastructure can occur due to the
construction works.
Traffic to/from power station may
become heavier. Social services may
become insufficient.
19 The Poor, Indigenous
and Ethnic People -
There are considerable ethnic minorities
such as Khmer, Hoa and Cham living in
Southern part of Vietnam including
HCMC. The disparity between the rich
and the poor in HCMC is 7 times.
Priorities or affirmative actions can be
given to them when necessary.
There are considerable ethnic minorities
such as Khmer, Hoa and Cham living in
Southern part of Vietnam including
HCMC. The disparity between the rich
and the poor in HCMC is 7 times.
Priorities or affirmative actions can be
given to them when necessary.
20 Misdistribution of
Benefits and Losses (-)
Disparity between the land owners and
the rest (landless farmers, wage laborers
etc) can be widened.
Local livelihoods can be affected and
health hazards can be caused in case the
environmental management plan is not
appropriately planned and implemented.
21 Local Conflict of
Interest -
Local conflict can occur between the
relocated people and the host community.
Local conflict can become constant
between the relocated people and the host
community.
22 Gender - -
23 Children‟s Rights (-)
Child labor may occur due to their
parents‟ loss of job. Children may catch
infectious diseases triggered by outsiders‟
entry into the community.
Child labor may occur due to their
parents‟ loss of job. Children may catch
infectious diseases triggered by outsiders‟
entry into the community.
24 Cultural Heritage -
There is no UNESCO World Heritage
existing in the Sourthern part of Vietnam
(as of December 2010). Careful
consideration however should be given to
pagodas and other historical buildings
near the site.
-
25 Infectious Diseases
such as HIV/AIDS (-)
Infectious diseases may spread via the
construction workers into the community.
Infectious diseases may spread via the
construction workers into the community.
Source: Developed by Study Team
The amount of CO2 emission by solar power generation facilities is on the other hand more than that of
nuclear power generation facilities (0.020kg/kWh), hydropower (0.011kg-Cos/kWh), geothermal, wind
power and other renewable energy sources (see the above Fig.4-2-1). Other environmental and social
impact borne by nuclear, hydropower and geothermal will however be bigger in terms of the scale of
investment, affects on natural environment, land acquisition and involuntary resettlement. Mitigation
measures will be required against the environmental and social impact on the affected people living near
the site in the construction period and operation period. It is anticipated to take longer time to construct
nuclear power generation facilities than others. Wind power facilities will also require land acquisition and
mitigation measures should be examined in advance.
4-13
4.3.3 Results of Local Consultations for Information Collection
32 customers were interviewed in the District 10 and District 11 where Phu Tho Power Company extends
its power distribution service, in order to see the condition of their electricity consumption and their views
on smart grid. Interviewed customers are comprised of 15 residential and 17 large customers.
1) Target of Interview Survey
The interview survey was designed not to subject to the scientific analysis since its objective was to
grab the qualitative features and information of customers in the target area, not the quantitative.
One of the pre-requisites of selecting residential customers was whether they had A/C, since the impact
brought by the smart grid is comparatively more on them than on those without A/C. Out of 15
customers, four had retail shops or office on the ground floor, and one had their rooms rented by
outsiders.
16 large customers were selected among Phu Tho Power Company‟s list of 30 major customers:
amusement park, garment industry, beer factory, plastic manufacturer, communication industry, medical
institutions, service industry, banking industry, retailers (supermarket), and people‟s committee. The
other one is a travel agency which rents the ground floor space of a residential house.
2) Method of Interview Survey
The Study Team first conducted face-to-face interviews and fulfilled the questionnaire sheets in order to
make sure that customers provided answers in proper way. However, the Study Team found it difficult
to conduct interviews without being accompanied by Phu Tho Power Company‟s staff, and had to limit
the survey implementation within working hours from Monday to Friday, while household
representatives were often out during day time. Phu Tho Power Company therefore sent the
questionnaire by post to most of the large customers and a few residential customers. They sent back the
questionnaire with their answers, which were followed up by the Study Team by contacting them again
to confirm the contents of their answers.
3) Contents of Interview Survey
The Study Team interviewed with the residential customers by asking their institutional (or personal)
identities, condition of electricity consumption and cost (out of major household expenditures), opinions
and ideas on current power supply and current electricity tariff, and smart grid.
Among all expenditures, the Study Team asked the customers to show invoices or receipts of their
4-14
electricity bill in order to figure out the exact amount of payment. The rest expenditures were answered
without such evidences. The questionnaire and summary of their answers are as in the Annex.
4) Results and Consideration of Interview Survey
(Residential Customer)
(1) Electricity Consumption and Cost
According to the statistics, expenditure on housing, electricity and water reached only 107,850
VND, which is equivalent to 6.2% of total household expenditure of urban population of HCMC as
of 20089.
Payment for electricity use among the interviewed customers however is outstanding and one of the
major expenditures among all, and some interviewed customers pay for electricity as much as for
food, education and medicine. It is assumed that the gap between the statistical figure and the
interview outcome comes from the fact that the interview targeted households with A/C who
comprise only 23.26% of the urban population of HCMC.
According to the interviewees, the amount of electricity consumption as of the interview time,
September 2010, was lower than that of dry season10
because the amount of rainfall in September
reached the highest, while average temperature and hours of sunshine were moderate11
.
(2) Frequency of Electricity Use
Among interviewees, there are those who limited their A/C use between 2 and 4 hours. Some rarely
use A/C. There however found some others who use A/C for 8 to 10 hours.
Residential customers often use A/C during night time. This comes from habits of people in
Vietnam who do not often install A/C on the ground floor where they have kitchen and dining
rooms. They instead install and use A/C in their bed rooms upstairs, so that the frequency of using
A/C during daytime is limited except dry season. They often have bad living condition (poor
ventilation, rooms without windows, etc). They use lights early evening as their rooms are dark.
They keep using A/C throughout their sleeping time. Such bad living condition and development of
privacy in urban areas bottomed up and promote using lights and A/C.
9 HCMC Statistical Office, Ho Chi Minh City Statistical Yearbook 2009, Statistical Publishing House, 2009 10 Some interviewees said that their electricity consumption in dry season often reached twice as much as that of rainy
season. 11 According to the HCMC Statistical Year Book 2009, the average temperature of September 2009 was 27.6 Celsius degrees
and the length of sunshine was 116.9 hours.
4-15
Among those who own their houses facing (or relatively close to) the alleys or the big streets,
grocery shops or sales shops do not install A/C as they have their own customers keep coming so
that they keep the doors always open. The other customers using the ground floor as offices on the
other hand keep using A/C all day long because they had to shut windows against the noise caused
by vehicles and motorbikes passing by. Those with A/C use of a few hours tried to save money by
using fans at home due to the electricity bill accounted for much in their expenditures.
Photo 4-3 Houses in narrow alleys
Source: Taken by Study Team
(3) Reflections on Current Rates of Electricity Consumption
Interviewees were satisfied with the Phu Tho Power Company‟s present electricity supply.
Although they often experience day-long load shedding and sudden power outage particularly in dry
season, no load shedding was reported during the survey period (September 2010: rainy season), no
damage to electric appliance was reported due to power outage, and they were happy about the
quick response offered by Phu Tho Power Company‟s staff as part of their customer relations.
As per electricity bill, they are not strongly willing to pay more than they currently do, but they said
they would do so if the government decides to increase the tariff and applies it to all customers
equally.
(4) Reflections on Smart Grid Introduction
It was prominent that the interviewees chose power outage, instead of choosing to pay additional
4-16
money for keep using the electricity. They fully understand the residential unit retail price gradually
increase as they use electricity more. It seems that they think they can save money by not using
electricity.
On the other hand, many of them said they would like to keep using electricity only if the additional
payment stayed within 5% to 10%, or amount neighbors accept. Some households try to use fans
during day time and A/C during night time. They therefore wished to keep using either of them, or
at least one electric appliance. Some said they were already used to having power cut one or twice a
week for a whole day.
When asked power shortage only on A/C, they answered „we can manage load shedding for 30
minutes to 1 hour,‟ „we will understand if other customers are also in the same situation,‟ „we will
be okay if certain compensation is given.‟ Others strongly demanded „we want to have high quality
of service without power outage,‟ and they requested to have 24 hours of stable power supply
instead of any compensation given to them.
Photo 4-4 Notice of Power Cut Source: Taken by Study
Team
4-17
(Large Customer)
(1) Frequency of Electricity Use and A/C Use
The results of interview saw an apparent difference by industry and by sector. Garment industry use
electricity for the sewing equipment, medical institution use for medical equipment, and
supermarkets use for frozen cases. They keep running their facilities, equipment and machines of
their own, which had kept their electricity consumption high throughout a year.
Those customers who often have their clients, and who run offices where their staffs stay all day
long are found to keep using A/C throughout the working hour in order to secure comfortable
working condition for their staff. Most of customers own generators for back-up.
(2) Reflections on Current Rates
They were satisfied with the current power distribution by Phu Tho Power Company. Reasons
raised by them were „they can use electricity for 24 hours a day,‟ „Phu Tho Power Company
provides good services.‟ As per electricity bill, they are not strongly willing to pay more than they
currently do, but they said they would do so if the government decides to increase the tariff and
applies it to all customers equally. Medical institutions have a flat rate applied nationwide so that
they feel they are privileged and well satisfied. The others feel the tariff is too expensive, but some
explained „I take it for granted to pay the bill as it is equally applied to everybody,‟ and „I am not
unsatisfied, but I am willing to pay additionally if Phu Tho Power Company improves the quality of
service.‟
(3) Reflections on Smart Grid Introduction
They did not accept any situation without A/C in order to secure comfortable and noise-free
working environment, and to keep their facilities running in the controlled room temperature. They
said they would run their generators in case A/C was stopped.
Those who accept to have A/C off said they were okay to have 30 minutes off, and 10% discount in
return.
5) Task Analysis in the Enforcement of the Differentiation Outage
(1) Promotion of customers‟ awareness raising
4-18
Source: Taken by Study Team
Photo 4-5 Phu Tho PC staff gives invoices and
collects money
EVN HCMC, on behalf of all power companies including Phu Tho Power Company, shares
information through advertisement on
newspaper, TV commercial films, and
internet when they anticipate shortages
of electricity supply, or power outage
due to the repair and maintenance
works. However, there found some
customers who did not obtain such
information because they were not
exposed to such media.
They did not know, if they did not
receive prior notices, how long the
power outage would last because they were not sure if the power outage was caused by accidental
power outage due to thunders and breakdown of facilities etc.12
, load shedding, or sudden power
outage due to the power shortage. Moreover, customers do not always remember what actually
happened.
Phu Tho Power Company‟s further efforts to keep in direct touch with customers are recommended
as possible measures to promote their understandings on smart grid. Phu Tho Power Company sends
their staff to each customer for monthly meter reading and invoice distribution. They collect money
at customers‟ addresses or at Phu Tho Power Company‟s customer center. Phu Tho Power
Company may be able to collect customers‟ view, and to explain to them about the background,
significance of smart grid load shedding and benefit given to customers. Marketing should be
strategically promoted, and allocation of communication officers will also be good to deal with
customers in order to collect further understandings of customers, and improve their awareness
toward the importance of energy saving.
They may feel unfair, at the beginning of project implementation, when their households get power
cut. Phu Tho Power Company can further promote advocacy activities in which customers‟
understandings and cooperation toward smart grid. Phu Tho Power Company also can work on PR
to make their customers more aware of prior notice on power cut, which will help increase their
understandings that the power cut is fairly implemented.
It depends on residential customers to choose whether they cooperate with Phu Tho Power
Company‟s efforts for smart grid promotion. Phu Tho Power Company is encouraged to keep
12 Load shedding in dry season lasted all day long from 7 in the morning to 6 in the evening due to the power shortage.
Sudden power outages on the other hand happened and lasted for 30 minutes to 2 hours at longest.
4-19
sending their message that energy consumption cost can be saved by cooperating with Phu Tho
Power Company and effective energy use can be promoted.
For large customers, the loads which do not affect their activities will be cut off.
(2) Improvement of Customers‟ Buildings and Houses
Houses and buildings constructed in Vietnam have poor noise protection or insulation function.
Outside noises are often heard in the houses and buildings. Ventilation is not always secured in their
houses and buildings. Living environment is often in bad condition due to the poor housing
condition, not whether they have A/C or not. The improvement of living environment in the District
10 and District 11 can be promoted in collaboration with the People‟s Committee and other
governmental organizations.
4.4 Summary of the Law to be related to considered Environmental
Social Impacts in Vietnam
4.4.1 Summary of the Law to be related to considered Environmental Social Impacts
1) EIA
The following Table 4-4-1 introduces major laws, decrees, decisions, and circulars on environment and
environmental impact assessment up to date in Vietnam.
Table 4-4-1 Legislative documents on EIA
Date No Name
Environment
2005/12/12 Order No.
29/2005/L-CTN Law on Environmental Protection (No. 5212005/QH11)
2006/08/09 Decree No.
80/2006/ND-CP
Detailing and Guiding the Implementation of a Number of Articles of
the Law on Environmental Protection
2008/02/28 Decree No.
21/2008/ND-CP
Amending and Supplementing a Number of Articles of the
Government‟s Decree No.80/2006/ND-CP of August 9, 2006
EIA
2006/11/22 Decree No:
140/2006/ND-CP
Providing for the environmental protection at stages of elaboration,
evaluation, approval and implementation of development strategies,
planning, plans, programs and projects
2007/11/26 MONRE Decision No.
19/2007/QD-BTNMT
Promulgating the Regulation on the conditions for and
provision of the service of appraising environmental
impact assessment reports
4-20
2008/12/08 MONRE Circular No.
05/2008/TT-BTNMT Guiding SEA, EIA and EPC
Source: Incorporated by Study Team
The Law on Environmental Protection (No.5212005/OH11) replaced the former law stipulated in 1993.
This law is the basis of environmental impact assessment and environmental protection in Vietnam. The
Decree No.140/2006/ND-CP was issued along with the new law in 2006.
2) Environmental Standard
The VES shows the environmental standard and industrial emission standard in Vietnam. The Law on
Standards and Technical Regulations was promulgated in 2006, followed by revisions of environmental
standard (see Table 4-4-2).
Table 4-4-2 Legislative documents on environmental standard
Date No Name
Environmental Standard
2006/6/29 Law No.68/2006/QH11 Law on Standards and Technical Regulations
2006/9/26 MONRE Decision
No.23/2006/QD-BTNMT On the issuing of the list of hazardous waste
2007/8/1 Decree No.127/2007/ND-CP Detailing the implementation of a number of articles of the Law on Standards
and Technical Regulations
2008/7/18 MONRE Decision No.
04/2008/QD-BTNMT Promulgating National Technical Regulation on Environment
2009/10/7 MONRE Circular
16/2009/TT-BTNMT Regulating National Technical Regulation on Environment
2009/11/16 MONRE Circular
25/2009/TT-BTNMT
Regulating National Technical Regulation on Environment (QCVN 07, 16,
17, 18, 19, 20, 21, 22)
Source: Incorporated by Study Team
Decrees and circulars following the Law provide details of environmental standards such as water quality,
air quality, and waste.
Among them, the MONRE Decision No. 23/2006/QD-BTNMT stipulates specific industry equipment
which creates hazardous wastes, and kinds of hazardous waste. The Project will include disposal of
distribution equipment and batteries, which is not relevant to the requirement of disposing equipment
containing hazardous wastes stipulated in the same Decision as listed in the Table 4-4-3. It is however
recommended to reconfirm its irrelevance when the Project is implemented and described in EPC.
Others are not applicable to the Project.
4-21
Table 4-4-3 Hazardous Waste List in power sector equipment
Code Waste stream EC code
A/B code
Basel
convention
Y code
Basel
convention
Hazardous
properties
State
(solid /
liquid /
sludge)
Remark
19 02 01 Transformers and capacitors
containing PCBs
16 02 09 A3180
B1110
Y10 TO, ET Solid *
19 02 02 Discarded equipment
containing or contaminated
by PCBs
16 02 10 A3180 Y10 TO, ET Solid *
19 02 03 Discarded equipment
containing
chlorofluorocarbons, HCFC,
and HFC
16 02 11 Y45 TO, ET Solid *
19 02 04 Discarded equipment
containing free asbestos
16 02 12 A2050 Y36 TO, ET Solid *
19 02 05 Discarded equipment
containing hazardous
components
16 02 13 A1030
A2010
A3180
Y10
Y29
Y31
TO, ET Solid *
19 02 06 Hazardous components
removed from discarded
equipment
16 02 15 A1030
A2010
A3180
Y10
Y29
Y31
TO, ET Solid **
TO: Toxic, ET: Ecotoxic,
*: Mirror Entries – hazardous waste only if dangerous substances are present above threshold
concentrations. ** Absolute Entries – Hazardous waste regardless of any threshold concentrations.
Source: Extracted from Attachment of MONRE Decision No.23/2006/QD-BTNMT dated 26
September 2006.
3) Social Environment
Legislative documents on land use, compensation and resettlement are found in the following table. There
will be no land acquisition or involuntary resettlement caused by the Project since the Project will not
create new buildings outside of their existing complex.
Table 4-4-4 Legislative Documents on Land Use, Compensation and Resettlement
Date No Name
Land Use, Compensation and Resettlement
2003/12/10 Order
No.23/2003/L-CTN Land Law (No. 13/2003/QHll)
2004/10/29 Decree No.
181/2004/ND-CP On the Implementation of the Land Law
2004/12/03 Decree
No.197/2004/ND-CP
Compensation, Support and Resettlement When Land is Recovered by the
State
2006/01/27 Decree
No.17/2006/ND-CP
Amending and Supplementing a Number of Articles of the Decrees
Guiding the Implementation of the Land Law and Decree
No.181/2004/ND-CP on Transformation of State Companies into
Joint-Stock Companies
Source: Incorporated by Study Team
4.4.2 Summary such as the EIA in Vietnam
4-22
1) SEA
The new Law on Environmental Protection stipulates that the objects subject to the elaboration of the
SEA 13
as show in the following table. SEA is not applicable to the Project.
Table 4-4-5 Objects subject to elaboration of SEA and application to the project
No Objects subject to elaboration of strategic environmental assessment Application to
the project
1 National socio-economic development strategies, planning and plans Not Applicable
2 Strategies, planning and plans for development of branches or domains on a
national scale Not Applicable
3 Socio-economic development strategies, planning and plans of provinces, centrally
run cities or regions Not Applicable
4 Planning for land use, forest protection and development; exploitation and
utilization of other natural resources in inter-provincial or inter-regional areas Not Applicable
5 Planning for development of key economic regions Not Applicable
6 General planning of inter-provincial river watersheds Not Applicable
Source: Article 14, Law of Environmental Protection (No.52/2005/QH11)
2) EIA
The Appendix of the Decree No. 21/2008/ND-CP shows in detail14
the objects subject to the
elaboration of the EIA15
as in the following table. EIA will not be applicable to the Project.
Table 4-4-6 Objects subject to elaboration of EIA and application to the project
No Projects Scale Application to the
project
Group of energy and radiation projects
38 Projects to build nuclear reactors All Not Applicable
39
Projects to build production, business and service
establishments using radioactive substances or
discharging radioactive wastes
All Not Applicable
40 Atomic power or thermal nuclear projects All Not Applicable
41 Thermo power projects ≥ 30 MW Not Applicable
42 Wind power projects ≥ 100 ha Not Applicable
43 Solar power projects ≥ 100 ha
The Project will
install solar pond
and batteries,
which scale will
13 Strategic Environmental Assessment refers a system of incorporating environmental considerations into policies, plans and
programs at the (strategic) stage of policy making. It is conducted prior to the environmental impact assessment at the stage
of project planning. 14 Part of the Annex of the Decree No. 80/2006/ND-CP has been revised. 15 EIA refers a prior assessment of the possible positive or negative impact that a proposed project may have on the
environment, together consisting of the natural, social and economic aspects. The assessment results will be disclosed and
share with local community for reflecting their ideas into the project.
4-23
not reach 100 ha.
Therefore it is not
applicable.
44 Hydropower projects ≥ 300,000m3 of reservoir Not Applicable
45 Projects to build height-voltage power lines ≥ 100 km in length
The Project will
not apply for
high-voltage power
line. Therefore it is
not applicable.
46 Projects to manufacture electric wires and cables ≥ 2,000 tons of aluminum
per year Not Applicable
Group of electronic and telecommunication projects
47 Projects to build radio transmission and radio
transmission-receipt stations ≥ 2 kW
Not Applicable in
power capacity
48 Projects to manufacture electric and electronic
appliances
≥ 10,000 of appliance per
year Not Applicable
49 Projects of manufacture electric and electronic
components ≥ 100 tons of products
Not Applicable as
manufacture will
not taken place, but
purchase will be
done in the Project.
50 Projects to build telecommunications lines ≥ 100 km in length Not Applicable in
size
52 Projects to manufacture telecommunications cables All Not Applicable
Source: Appendix, Decree No. 21/2008/ND-CP
3) EPC
The Project Owners are required to elaborate the EPC when EIA is not required. They are allowed to start
their production and business activities after registering the EPC. The Project Owners are to mention the
following issues in the EPC, and the District People‟s Committee will issue a certificate16
. The Project will
be conducted by Phu Tho Power Company in their service areas, and no new registration will likely be
required.
Location of execution
Type and scale of production, business or service and materials and fuel used
Kinds of wastes generated
Commitments to apply measures to minimize and treat wastes and strictly comply with the
provisions of law on environmental protection
The Project will improve facilities and install equipment in the areas where Phu Tho Power Company has
been already providing their services. SEA and EIA will therefore not be applied, while the EPC is required
for submission. When applying the EPC, the Project Owner is responsible to submit the application to
either of the District 10 or the District 11 for registration. Two districts will share information mutually for
comments. The issuance of the certificate will be taken place at shortest within five days17
.
16 Article 25, Law of Environmental Protection. 17 The Study Team interviewed with Mr. Mai Thanh Dung (Director, Department of Environmental Appraisal and Impact
4-24
4.5 Necessary Actions Taken by the Project Proponent
Upon implementation of the Project, Phu Tho Power Company will be required to develop the EPC and
submit to either of the District 10 or the District 11 for registration. The rest district will be informed by the
other for comments. Completion of registration will enable them to start the activities under the Project.
Phu Tho Power Company has to mention the following issues in the EPC.
Location of execution
Type and scale of production, business or service and materials and fuel used
Kinds of wastes generated
Commitments to apply measures to minimize and treat wastes and strictly comply with the
provisions of law on environmental protection
Assessment, Vietnam Environment Administration, VEA on 23 November 2010 in Hanoi.
5-1
Chapter 5 Financial and Economic Evaluation
5.1 Estimation of Project Cost
5.1.1 Scope
Regarding the project, system / equipment and the quantity are introduced in Table 5-1-1.
Table 5-1-1 Project scope
System / Facilities Quantity Explanation
1.Advanced DAS
and AMR
1 system
-Advanced DAS with EMS has function of SCADA for 110kV substation and will be installed in SCADA center. -AMR and DR will be installed in Phu Tho Power Company area. -Distribution feeder monitoring and remote controlling such as automatic LBS etc. -Output fluctuation control of renewable energy to connect distribution feeder.( Charge and discharge of rechargeable battery) -Consider energy management in future. -Remote meter reading by communicate with smart meter. -DR for support prevention over supply and overload. -Apply structure of thin client system and dual type of server.
2.Substation facilities
4 SS
-M-RTU, Fiber Optic device, Interface and adaptation work between M-RTU and existing Substation device, etc. -34 Primary substations in EVN HCMC can be monitored and controlled as SCADA function. At first, 4 substations in Phu Tho Power Company area can be implemented as 1
st
stage. 3.New RMU
25 units
-UG feeder : 7 feeder → 10 feeder (2014) -Needed RMU: 10 feeder×2.5 = 25 -New RMU will be installed in Existing room. -The existing RMU of manual type will be moved to other suitable site.
4.New OH DAS
equipment
86 units
-OH feeder: 12 feeder → 19 feeder (2014) -Needed OH DAS: 19×4.5 = 86 -15kV ALBS,RTU including Fiber Optic device, Switch Power Supply,, Arrester, etc.
5.Smart Meter
and Concentrator
90,000 units 8,000 units
196 units
-There are 90,000 residential customers and 8,000 large customers in Phu Tho Power Company area around 25km
2.
-Apply 500 smart meters by 1 concentrator. -In case of worse communication, communication support by repeater on out door etc. will be required.(Option)
6.Solar Power
2 sets
-20kW/customer, Solar panel, Battery, Power Conditioner, etc.
7.Fiber Optic
0 km
-Fiber Optic has already been installed in EVN HCMC including EVN Telecommunication company.
5-2
8.Engineering Service
1
-Including Training in Japan(3 managers / 7 engineers)
Source: Made by Study Team
5.1.2 Project Cost
Project cost with foreign and local money is calculated based on the scope as shown in Table 5-1-2. The
foreign cost is around 30 MUS$ and the total foreign cost including tax etc is around 39 MUS$.
Table 5-1-2 Project Cost
Scope Quantity
Cost
Remarks Foreign 10
8yen
(MUS$)
Local MVND (MUS$)
1. Advanced
DAS / SCADA
with EMS
EVN HCMC
Control Center
1 system
5.3
(6.5)
13,644
(0.7)
1. Advanced DAS with SCADA is installed in existing SCADA center and can implement energy management of distribution feeder.(Solar Power) 2. AMR/DR is installed in Phu Tho Power Company area and is connected to Advanced DAS by data link of Fiber Optic
2. AMR / DR
Phu Tho Power Company
1 system
3. Substation
facilities
4 SS 1.0
(1.2)
3,898
(0.2)
0.3 MUS$ x 4 = 1.2 MUS$ 1
st stage: 4 substations (110kV)
2nd
stage: expand to 34 substations
4. New RMU 25 units 1.0
(1.2)
1,949
(0.1)
45 kUS$ x 25 = 1,125 kUS$ →1.2 MUS$
5. New OH DAS
equipment
86 units 1.1
(1.3)
1,949
(0.1)
15 kUS$ x 86 = 1,290 kUS$ →1.3 MUS$
6. Smart Meter,
Single-phase,
Three phase
Concentrator
90,000 units
8,000 units
196 units
13.8
(17.0)
19,491
(1.0)
120US$ x 90,000 = 10.8 MUS$ 700US$ x 8,000 = 5.6MUS$ 3,000US$ x 196=0.6MUS$
7. Solar Power 2 sets 0.2
(0.3)
1,949
(0.1)
20kW: 0.15 MUS$ 0.15 x 2 = 0.3 MUS$
8. Fiber Optic 0 0 0 Use existing Fiber Optic
9. Engineering Service
1 2.0
(2.5)
13,644
(0.7)
Including Training in Japan
Sub Total - 24.3
(30.0)
56,524
(2.9)
10. TAX 1 5.3
(6.6)
5,847
(0.3)
Foreign: Sub Total x 20% x 10% Local: Sub Total x 10%
5-3
11. Physical Contingency
1 1.2
(1.5)
1,949
(0.1)
5% x Sub Total
12. Price
escalation
1 0.7
(0.9)
5,847
(0.3)
2.4% for Foreign 8.4% for Local
Total 31.5
(39.0)
70,168
(3.6)
70,168 (3.6)
Exchange rate: $1 = 19,491VND = 80.89 yen (by Tokyo Mitsubishi UFJ bank 10/29 in 2010)
Source: Made by Study Team
5-4
5.2 Preliminary Economic and Financial Analysis
5.2.1 Expected Effect of the Project
1) Expected Effect
Following 5 effects are expected after implementation of the project.
decrease of outage duration
improve of maximum average capacity rate of the substation
decrease of loss (technical loss of MV line and non-technical loss)
solar power generation
peak cut by DR
The relationship between the effects and the system / facilities in this project is described as Fig 5-2-1.
Fig 5-2-1 relationship between Effect and System / Facilities in Project
Source: Made by Study Team
Decrease of outage duration
Improve of maximum average
capacity rate of substation
Decrease of loss
Solar Power Generation
Peak-cut by DR
DAS
AMR
Facilities of Solar Power
DR
<Effect> <System / Facilities in Project>
5-5
30 MUS$ of foreign project cost calculated in Table 5-1-2 are roughly decomposed to each system as
shown in Table 5-2-1.
Table 5-2-1 Rough Decomposition of Project cost (Foreign portion)
Scope DAS AMR Solar Power DR
Advanced DAS/AMR/DR 3.5 1.0 1.0 1.0
Substation facilities 1.2
New RMU 1.2
New OH DAS equipment 1.3
Smart Meter 8.5 8.5
Solar Power 0.3
Engineering service 1.0 0.5 0.5 0.5
Total (MUS$) 8.2 10.0 1.8 10.0
Source: Made by Study Team
The components of this project can be allocated to the effects based on the utilization rate as shown in
Table 5-2-2. Therefore, the cost for each effect can be roughly calculated by multiplying the cost of Table
5-2-1 to the rate of Table 5-2-2. The rough cost is described in Table 5-2-2.
Table 5-2-2 Rough Project rate and cost for the effect
Effect DAS AMR Solar Power DR Total
(MUS$)
Decrease of outage duration 50% 4.1
Improve of maximum average
capacity rate of substation
20% 1.7
Decrease of technical loss 20% 1.6
Decrease of non-technical loss 100% 10.0
Solar Power Generation 1% 100% 1% 1.9
Peak-cut by DR 9% 99% 10.7
Source: Made by Study Team
Table 5-2-3 Expected Effects of the Project
Before the project (a)
After the project
(b) Effects (a)-(b)
1. Decrease of Outage duration
373 min.
77 min.
-296min.
(4.93 hr)
2. Improve of maximum
average capacity rate of the
substation
75%
83%
+8%
3. Decrease of loss
(technical loss of MV line)
(non-technical loss)
(1.72%)
(2.43%)
(1.16%)
(1.3%)
(-0.56%)
(-1.13%)
4. Solar Power Generation
-
+57,200kWh/year
(28,600kWh*2)
+57,200kWh/year
(28,600kWh*2)
5-6
5. Peak cut by DR
-
255MW*2 hrs
*40 days/year
255MW*2 hrs
*40 days/year
Source: Made by Study Team
2) Preconditions
Preconditions are as follows.
Construction period: 2013- 2014, commissioning: 2015
Project period: 20 years (2015-2034)
Sales (kWh) is estimated based on the actual data of 2009 and is extended with an average growth
rate of 5%.
Sales unit price per kWh in 2010 is estimated as 1,193 VND/ kWh, based on the actual data in
2009. With regard to a tariff, the Nikkei reported as of November 25 that the Government of
Vietnam plans to raise a tariff by 30% in 2011. Followed by this news, it presumes that two price
hikes will be done in 2011(+30%) and in 2015(+20%). Then sales unit price per kWh in 2015 is
estimated as 1,860 VND/ kWh.
Unit price of power purchase: 5.5c/ kWh (oral information). Price of power purchase in 2009 is
estimated as 990 VND/ kWh and price of power purchase in 2015 is estimated as 1,180 VND/
kWh by adding 200 VND.
Foreign Exchange Rate: $1=19,491 VND, $1=80.89 Yen (Tokyo-Mitsubishi UFJ Bank as of
29 October, 2010)
3) Estimate of Benefits
(1) Decrease of outage duration
Basic idea: Power failure will be decreased by 296 minutes (=4.93 hours) after the project. It will
contribute to sustain economic activities across the country. Therefore an increase of
sales will be a economic benefit. As a financial benefit, power company increases a
profit.
Estimate condition: It is estimated that sales (kWh) in 2015 is 996.4 kWh. And power failure will
decrease 296 minutes (=4.93 hours) after the project.
Economic benefit will be estimated as:
Sales (kWh)*improved power failure (hours)/8,760 hours*1,860 VND/kWh
=996.4kWh*(4.93hours/8,760hours)*1,860 VND/kWh=1,043.01 million VND=53,512 US$
5-7
Financial benefit will be estimated as:
sales (kWh)*improved power failure (hours)/8,760 hours*(1,860 VND/kWh-1,180 VND/kWh)
=996.4 kWh*(4.93hours/8,760hours)*(1,860 VND/kWh-1,180VND/kWh)
=381.31 million VND=19,563 US$
(2) Improve of maximum average capacity rate in the substation
Basic idea: Power company generally has to construct a new substation when a maximum average
capacity rate of a substation exceeds 75%. However it can postpone a construction of a
new substation until a maximum average capacity rate reaches 83%.
With regard to a economic benefit and a financial benefit, construction cost of a new substation (63
kVA*2 banks) costs 15 million US$. 2,411 million kWh of expected sales in 2034 needs 275.23
MW capacity in 2034. Meanwhile annual average capacity usage ratio in a substation is estimated as
0.224 in 2015, based on 743.519 million kWh of sales and 84.8MW.
Required units of substations in 2034 under the existing maximum average capacity rate (75%) will
be
0.224*(63 MVA*2 banks)*A*0.75=275.23MW
∴A=13.00 units are required in 2034.
Required units of substations in 2034 under the improved maximum average capacity rate (83%)
will be
0.224*(63 MVA*2 banks)*B*0.83=275.23MW
∴B=11.748 units are required in 2034.
Difference between (A) and (B) will be a number of deferred substations by improving a maximum
average capacity rate.
Construction cost to be deferred until 2034 will be
1.252 units *15 M US$=18.78 MUS$
(3) Decrease of loss (technical loss and non-technical loss)
Basic idea: Losses consist of a technical loss and a non-technical loss. Technical loss is defined to be
one caused mainly from technical and physical reasons when power is transmitted
5-8
through distribution facility. Meanwhile non-technical loss is defined to be one caused
from such human reasons as theft or non collection of electricity bills. As an economic
benefit, sales will increase in proportion with an improved loss rate. Meanwhile a profit
will also increase as a financial benefit.
Estimate condition: technical loss
sales (kWh)*(improved technical loss rate (%))
=996.4 million kWh*0.56%=5,57984 million kWh
Sales will increase:
5.57984 million kWh*1,860VND/kWh=10,378 million VND=532,476 MUS$
A financial benefit will be an increase of profit.
5.57984 million kWh *1,860VND/kWh=10,378 million VND=532,476 MUS$
non - technical loss
996.4 million kWh*(improved non-technical loss rate (%))
=996.4 million kWh*1.13%=11.259 million kWh
Economic benefit will be an increase of sales:
11.259 million kWh*1,860VND/kWh=20,941 million VND=1.074 MUS$
Financial benefit will be an increase of profit.
11.259 million kWh*1,860VND/kWh=20,941 million VND=1.074 MUS$
(4) Solar power generation
Basic idea: Power company sells power generated by two newly-installed solar power generators
(20kW*2 units). Thus Power company earns sales by selling power and does not need
to buy power from a transmission company.
As one solar power generators will generate 28,600 kWh per year, a total of 57,200 kWh is
generated with two generators.
As an economic benefit, the following sales will be expected:
57,200 kWh*1,860 VND/kWh=106,3492,000 VND=5,458 US$
Likewise, a financial benefit will be
57,200 kWh*1,860 VND/kWh=106,3492,000 VND=5,458 US$
5-9
(5) Peak cut by DR
Basic idea: The project aims to control a demand in peak time by cutting A/C and unnecessary
load for large customer. During the peak time, AMR activates to stop supplying power to
A/C and unnecessary demand so that a peaky demand will be cut off automatically.
As a result, construction of a new gas turbine power plant will be deferred from a viewpoint of an
overall national economy. Meanwhile a financial benefit consists of two factors: the first one is a
decrease of sales caused by a temporarily cut-off and the second one is a decrease of power purchase
power company has to purchase from the transmission company during the peak time.
Estimate condition: Economic benefit
Demand in peak time will be 510 MW, which consists of usage of residential customers and
unnecessary demand of large customers.
3 kW *90,000 residents + 30kW*8,000 industrial users= 510,000kW. Moreover 380 US$/kW is a
unit price to construct a new gas turbine plant.
Then a total construction cost of a new gas turbine plant is estimated as:
380 US$/kW*255,000 kW=96.9 MUS$ (i)
operating cost of a power plant mainly consists of fuel cost. 0.1 US$/kW is a unit price to generate
1kW.
An operating cost during the peak time will be
255 MW*2 hours*40days *20 years *0.1$/kW=40.8 M $ (ii)
(i)+(ii)=137.7MUS$ i.e. 6.885 MUS$/year for the 20 years
Financial benefit:
Financial benefit consists of two factors: the first one is a decrease of sales caused by a temporarily
forced power failure and the second one is an amount of power purchase a power company does not
need to purchase from the transmission company during the peak time.
In this study, the unit price of power purchase is 5.5c/kWh. With regard to a current tariff for an
industrial user, a price in peak time is two times as high as that in normal time, and a price in off-
peak time is 50% of that in normal time. When a power tariff for sales and power purchase is well
priced and is designed to reflect a fluctuating demand among in peak time, in normal time and in
5-10
off-peak time, the financial benefit may also reflect a fluctuating demand properly. In this study
therefore the unit price for power purchase in peak time presumes to be two times as high as that in
normal time, based on a belief that both a unit cost of sales and a unit cost of power purchase
proportionally change.
Annual decrease of sales caused by a temporarily power cut will be
255MW*2 hours *40 days *(1,860 VND/kWh-1,180 VND/kWh)
=13,872 million VND= 711,713 US$ /year
Annual power purchase Power Company has to purchase from the transmission company during the
peak time will be
255MW*2 hours *40 days *(1,180 VND/kWh* 2)
=48,144,000 million VND= 2.470 million US$ /year
Finally the Table below shows the summary.
Table 5-2-4 Results
Economic benefit Financial benefit
1. Decrease of outage duration 53,512 US$/y 19,563 US$/y
2. Improve of maximum average capacity
rate in the substation
0.939mil.US$/y
(Total 18.78MUS$:
20 years)
0.939mil.US$/y
(Total 18.78MUS$:
20 years)
3. Decrease of loss
(technical loss)
(non-technical loss)
532,476 US$/y
1,074,431 US$/y
532,476 US$/y
1,074,431 US$/y
4. Solar Power Generation 5,458 US$/y 5,458 US$/y
5. Peak cut by DR
(Decrease of sales caused by peak-cut)
(Power purchase at the peak time)
-711,713 US$/y
6.885 MUS$/y
-711,713 US$/y
2.470 MUS$/y
Source: Made by Study Team
5-11
5.2.2 Financial Analysis and Economic Analysis
1) Financial Analysis
FIRR is an indicator that shows if the project is feasible mainly from an implementation agency’s
viewpoint.
(1) Financial benefits and costs
Financial benefits and costs are as follows:
(Costs)
Total cost: 40.98 MUS$ (= total cost - contingency)
Construction period: 2 years( 2013-2014)
Project period: 20 years( 2015-2034)
As O&M cost, a 1% of the total cost will be spent every year.
(Benefits)
Decrease of power failure: 19,563 US$/ y
Improve of maximum average capacity rate of the substation : 0.939 MUS$/y
Decrease of loss
technical loss : 532,476 US$/y
non-technical loss : 1,074,431 US$/y
Solar power generation : 5,458 US$/y
Peak demand Control by cutting demand
decrease of sales : -711,713 US$/y
power purchase : 2.470 MUS$/y
5-12
(2) FIRR
Fig. 5-2-2
FIRR
Source: Made by Study Team
unit: million US$
Year Activities Construction O&M Reduction of
Outage Duration
Saving of Banks
Reduction of Tech Loss
Reduction of non-tech
Loss Solar Power Peak Cut
decreae sales caused by Peakcut
2010 2011 2012 2013 construction 12.294 12.294 0.000 -12.294 2014 construction 28.686 28.686 0.000 -28.686 2015 commissioning 0.41 0.41 0.0195 0.939 0.194 0.392 0.00273 2.47 -0.71100 3.306 2.896 2016 0.41 0.41 0.0195 0.939 0.194 0.392 0.00273 2.47 -0.71100 3.306 2.896 2017 0.41 0.41 0.0195 0.939 0.194 0.392 0.00273 2.47 -0.71100 3.306 2.896 2018 0.41 0.41 0.0195 0.939 0.194 0.392 0.00273 2.47 -0.71100 3.306 2.896 2019 0.41 0.41 0.0195 0.939 0.194 0.392 0.00273 2.47 -0.71100 3.306 2.896 2020 0.41 0.41 0.0195 0.939 0.194 0.392 0.00273 2.47 -0.71100 3.306 2.896 2021 0.41 0.41 0.0195 0.939 0.194 0.392 0.00273 2.47 -0.71100 3.306 2.896 2022 0.41 0.41 0.0195 0.939 0.194 0.392 0.00273 2.47 -0.71100 3.306 2.896 2023 0.41 0.41 0.0195 0.939 0.194 0.392 0.00273 2.47 -0.71100 3.306 2.896 2024 0.41 0.41 0.0195 0.939 0.194 0.392 0.00273 2.47 -0.71100 3.306 2.896 2025 0.41 0.41 0.0195 0.939 0.194 0.392 0.00273 2.47 -0.71100 3.306 2.896 2026 0.41 0.41 0.0195 0.939 0.194 0.392 0.00273 2.47 -0.71100 3.306 2.896 2027 0.41 0.41 0.0195 0.939 0.194 0.392 0.00273 2.47 -0.71100 3.306 2.896 2028 0.41 0.41 0.0195 0.939 0.194 0.392 0.00273 2.47 -0.71100 3.306 2.896 2029 0.41 0.41 0.0195 0.939 0.194 0.392 0.00273 2.47 -0.71100 3.306 2.896 2030 0.41 0.41 0.0195 0.939 0.194 0.392 0.00273 2.47 -0.71100 3.306 2.896 2031 0.41 0.41 0.0195 0.939 0.194 0.392 0.00273 2.47 -0.71100 3.306 2.896 2032 0.41 0.41 0.0195 0.939 0.194 0.392 0.00273 2.47 -0.71100 3.306 2.896 2033 0.41 0.41 0.0195 0.939 0.194 0.392 0.00273 2.47 -0.71100 3.306 2.896 2034 0.41 0.41 0.0195 0.939 0.194 0.392 0.00273 2.47 -0.71100 3.306 2.896
40.98 8.20 49.176 0.39 18.78 3.88 7.84 0.0546 49.4 -14.220 66.125 16.949
IRR= 3.44%
(b)-(a) Cost Total cost
(a)
Benefit Total benefit
(b)
5-13
FIRR is 6.90%.
Viability of the project is reviewed with a newly launched long term bond. On January 2010, the
Government of Vietnam successfully issued a 1,000 MUS$ bond with a 6.95% interest rate, a 10
year duration period. When the Study Team estimates NPV (Net Present Value) with a rate of 6.95%,
it is estimated -0.134 MUS$. As FIRR is lower than 6.95% and NPV is a negative, viability of the
project is not secured.
(3) Sensitivity analysis
Viability will change with the following conditions.
Increase of investment : Initial investment increases by 10%.
Increase of cost: O&M and cost increases by 10%.
Increase of benefit: An unit price of power purchase decreases by 10%.
Table 5-2-5 Sensitivity Analysis
IRR NPV
(discount rate=6.95%)
Base case 6.90% -0.13 MUS$
Initial investment increases by 10% 6.53% -1.28 MUS$
O&M cost increases by 10% 6.78% -0.51 MUS$
Unit price of power purchase
decreases by 10%
6.51% -1.28 MUS$
Source: Made by Study Team
5-14
2) Economic Analysis
EIRR is an indicator that shows if the project is feasible not only from an implementation agency’s
viewpoint but also from a national economy’s viewpoint.
(1) Economic benefits and costs
Economic benefits and costs are as follows:
(Costs)
Total cost: 34.09 MUS$ (= total cost - contingency - taxes)
Construction period: 2 years( 2013-2014)
Project period: 20 years( 2015-2034)
As O&M cost, a 1% of the total cost will be spent every year.
(Benefits)
Decrease of power failure: 53,512 US$/ y
Improve of maximum average capacity rate of the substation : 0.939 MUS$/y
Decrease of loss :
technical loss : 532,476 US$/y
non-technical loss : 1,074,431 US$/y
Solar power generation : 5,458 US$/y
Peak demand control by cutting demand :
decrease of sales : -711,713 US$/y
power purchase : 6.885 MUS$/y
5-15
(2) EIRR
Fig. 5-2-3 EIRR
Source: Made by Study Team
unit: MUS$
Year Activities Construction O&M Reduction of
Outage Duration Saving of
Banks Reduction of
Tech Loss Reduction of
non-tech Loss
Solar Power Peak Cut decreae sales
caused by Peakcut
2010 2011 2012 2013 construction 10.227 10.227 0.000 -10.227 2014 construction 23.863 23.863 0.000 -23.863 2015 commissioning 0.34 0.34 0.05351 0.939 0.532 1.075 0.00273 6.885 -0.71100 8.776 8.435 2016 0.34 0.34 0.05351 0.939 0.532 1.075 0.00273 6.885 -0.71100 8.776 8.435 2017 0.34 0.34 0.05351 0.939 0.532 1.075 0.00273 6.885 -0.71100 8.776 8.435 2018 0.34 0.34 0.05351 0.939 0.532 1.075 0.00273 6.885 -0.71100 8.776 8.435 2019 0.34 0.34 0.05351 0.939 0.532 1.075 0.00273 6.885 -0.71100 8.776 8.435 2020 0.34 0.34 0.05351 0.939 0.532 1.075 0.00273 6.885 -0.71100 8.776 8.435 2021 0.34 0.34 0.05351 0.939 0.532 1.075 0.00273 6.885 -0.71100 8.776 8.435 2022 0.34 0.34 0.05351 0.939 0.532 1.075 0.00273 6.885 -0.71100 8.776 8.435 2023 0.34 0.34 0.05351 0.939 0.532 1.075 0.00273 6.885 -0.71100 8.776 8.435 2024 0.34 0.34 0.05351 0.939 0.532 1.075 0.00273 6.885 -0.71100 8.776 8.435 2025 0.34 0.34 0.05351 0.939 0.532 1.075 0.00273 6.885 -0.71100 8.776 8.435 2026 0.34 0.34 0.05351 0.939 0.532 1.075 0.00273 6.885 -0.71100 8.776 8.435 2027 0.34 0.34 0.05351 0.939 0.532 1.075 0.00273 6.885 -0.71100 8.776 8.435 2028 0.34 0.34 0.05351 0.939 0.532 1.075 0.00273 6.885 -0.71100 8.776 8.435 2029 0.34 0.34 0.05351 0.939 0.532 1.075 0.00273 6.885 -0.71100 8.776 8.435 2030 0.34 0.34 0.05351 0.939 0.532 1.075 0.00273 6.885 -0.71100 8.776 8.435 2031 0.34 0.34 0.05351 0.939 0.532 1.075 0.00273 6.885 -0.71100 8.776 8.435 2032 0.34 0.34 0.05351 0.939 0.532 1.075 0.00273 6.885 -0.71100 8.776 8.435 2033 0.34 0.34 0.05351 0.939 0.532 1.075 0.00273 6.885 -0.71100 8.776 8.435 2034 0.34 0.34 0.05351 0.939 0.532 1.075 0.00273 6.885 -0.71100 8.776 8.435
34.09 6.82 40.908 1.0702 18.78 10.64 21.5 0.0546 137.7 -14.22 175.525 134.617
IRR= 22.78%
(b)-(a) Cost Total cost
(a)
Benefit total benefit
(b)
5-16
EIRR is 22.78%.
Viability of the project is reviewed with a 10.0 % of opportunity cost. This 10.0 % is a popular
discount rate World Bank or other International Organization often apply in evaluating a feasibility
of a project from a overall economic viewpoint. When the Study Team estimates NPV with a rate of
10.0 %, it is estimated +30.35 MUS$. As EIRR is higher than 10.0% and NPV is a positive,
viability of the project is confirmed.
(3) Sensitivity analysis
Viability will change with the following conditions.
Increase of investment: Initial investment increases by 10%.
Increase of cost: O&M cost increases by 10%.
Increase of benefit: Construction cost of a new gas turbine power plant decreases by 10%.
Table 5-2-6 Sensitivity Analysis
EIRR NPV
(discount rate=10.0%)
Base case 22.79 % +30.35 MUS$
Initial investment increases by 10% 20.69% +27.43 MUS$
O&M cost increases by 10% 22.69% +30.09 MUS$
Construction cost of a new gas turbine
power plant decreases by 10% 20.90% +25.49 MUS$
Source: Made by Study Team
3) Conclusion
At present nationals in Vietnam are suffering inconveniences caused by power shortage. With regard to
FIRR, it does not exceed the hurdle rate of 6.95% but EIRR is bigger than a hurdle rate of 10%.
It seems at a first glance that a project viability of a project does not lie in this project. However it is
necessary to recall that originally the project does not aim to construct a new distribution line but aim to
improve a loss of power failure etc in the existing distribution lines. In other words, the project will help
to improve a quality of power rather than increase power supply. Therefore, profitability of the project is
not so big.
Moreover the project will be expected to contribute a lot to a national economy because people in the
country can go on economic activities without worrying about power failure. Especially demand control
5-17
through AMR in peak time will help to save a huge amount of construction of a new power plant.
Thus the project will not be evaluated only by FIRR but also by its impact on national economy.
6-1
Chapter 6 Planned Project Schedule
Regarding fund source such as bank loan etc, the comparison was analyzed in Chapter 9, so that
Japanese ODA loan is suitable for this project.
The tentative implementation schedules for Japanese ODA loan are estimated as shown in Fig 6-1 and
Table 6.1 based on experiences. In case of bank loan or Grant, the schedule can be more shortened due to
shortening preparation and engineering service period.
Fig. 6-1 Implementation Schedule on Japanese ODA loan
Item 2011 2012 2013 2014 2015
Preparation
Basic design and HCMC PC/ JICA appraisal
Approval by GOJ / GOV
E/N, L/A
Selection of consultant
Engineering Service
Detailed Design
*Tendering Stage
Selection of Contractor
** Construction
Design
Manufacturing
Installation and test
Commencement
Source: Made by Study Team
6-2
Table 6-1 Explanation of Implementation Items
Stage Item Scope
Tendering Stage
Preparation Work (1) Preparation of implementation schedule (2) Preparation of scope of work (3) Coordination for bidding mode and currency
Preparation of Bidding Document
(1) Instruction to bidder (2) General condition (3) Special condition (4) Technical specification (5) Pricing schedule (6) Technical schedule (7) Bidding drawing
Promoting PQ (1) Making PQ documents such as experience, personnel
expertise, production capacity and financial capability (2) PQ evaluation
Bid Evaluation (1) Technical evaluation (2) Commercial evaluation (3) Contract negotiation
Construction Stage
Preparation of Power Interruption Plan
(1) Scheduling construction and coordination with customers
Project Management
(1) Periodical meeting and report (Monthly report for Power Utility)
(2) Management of progress and payment (3) Checking and approval for drawings and documents (4) Review and approval of the programs for manufacture
and delivery (5) Performance for factory tests and pre-shipment
inspections
Construction Supervision
(1) Construction supervision and safety management (2) Witness acceptance test and report to Power Utility (3) Check the commissioning test procedures and witness it
with Power Utility
Others
(1) Assistance of Training for O&M (in Japan and in Vietnam)
(2) Preparation for the List of Defects (3) Completion Report with As-built Drawings and O&M
Manuals
Source: Made by Study Team
7-1
Chapter 7 Implementing Organization
7.1 Implementing Organization
The implementing organization is introduced as shown in Fig 7-1.
Fig 7-1 Implementation organization
MPI MOIT
EVN IE
EVN HCMC
International
Relation Dept,
Material &
Import-Export
Dept,
Planning
Dept,
Engineering
Dept,
Investment
management
Dept,
Phu Tho Power
Company
Implementing company
Counterpart
O&M
7-2
7.2 Competence of the Organization
The sector of this project is an electric power sector and the related organization is introduced as
follows.
7.2.1 MPI
MPI is mainly to make the National Plan in Vietnam and to promote ODA loan as counterpart for
oversea countries. MPI also make the priority in a lot of candidates for ODA.
7.2.2 MOIT
The major role of MOIT is to make and establish the policy of all kind of Industries including
Power sector. Regarding smart grid, MOIT is in charge of planning the new law and policy for
renewable energy.
7.2.3 EVN head office
EVN which is a national organization is governing the electric power sector of Vietnam under the
supervisor and management of MOIT.
EVN is performing directly and indirectly most of the power generation, transmission and
distribution both in wholesale and retail supply of electric power. Moreover, EVN holds, as a holding
company, some subsidiaries, and those subsidiaries are classified into the direct control companies
and joint venture companies.
7.2.4 IE
The role of IE is mainly to implement the forecast of power supply etc and to develop new
technology for power sector including renewable energy.
7.2.5 EVN HCMC head office
EVN HCMC is an independent accounting enterprise, belonging to EVN and performing the
electricity supply over HCMC area of 15 Power Companies. EVN HCMC is main duties are sales
of power, distribution of power network system up to 110kV, performance of such power
7-3
engineering services as survey, design, testing, repairs, manufacturing, supply civil works,
performance of information services and some other tasks assigned by EVN.
7.2.6 Phu Tho Power Company
There are 15 Power Companies under EVN HCMC. One of them is Phu Tho Power Company. The
roles of Phu Tho Power Company are to manage power supply of the District 10 and District 11 and
to collect the tariff. In addition, Phu Tho Power Company implements the operation and
maintenance after the construction of projects.
8-1
Chapter 8 Technical Advantages of Japanese
Company
8.1 Entry Method and Form of Japanese Company
The following method and form are considered as the entry of Japanese company.
To receive the order after tendering and supply the equipment after contract
To invest to operation and maintenance company after commencement of this project
To invest local manufacturer in order to overcome high competition
8.2 International Competitive Ability of Japanese Company
8.2.1 DAS
Concerning reliability of power supply, higher technology has been already existed in Japan.
There is strong position compare with other countries.
Distribution network technology in Japan has progressed to solve a lot of subjects since 1960.
DAS was also same, it was kept progressing for improvement of supply reliability and efficiently operation
of equipment.
This DAS applied voltage type. There is a few countries to apply this type, but this voltage type of
distribution automation should be definitely better technology than the others. The advantages are;
Judge and split for failure section can be applied without CPU and distribution lines.
System upgrade can be applied step by step, if necessary.
Initial cost should be lower than current type which is introduced in Europe.
As of now, it is still continuing to progress for technical innovation by DAS business in Japan.
Combine advanced DAS core technology of Japan and inexpensive distribution network equipment which
made in China can create advantage of DAS.
8-2
8.2.2 AMR System
It is proud for higher reliability of power distribution monitoring technology which was grown in Japan.
Advanced AMR system has been already developed by Japanese companies based on existing higher
technology.
This advanced AMR system can realize two way communications with customers such as DR and control
internal switch in smart meter as well as measure power consumption at the place from far away.
Having proof experiment, corporate with NEDO and the state government of New Mexico, proof
experiment has already started that how much effect and influence will be occurred by realizing DR which
is difficult to test in Japan.
This core technology can be applied in this project as well, so that Japanese company can stand strong
position and develop lower cost compare with the other country.
8.2.3 EMS
It is proud for higher reliability of power distribution monitoring technology which was grown in Japan.
Advanced EMS has been already developed by Japanese companies based on existing higher technology.
This Advanced EMS can corporate efficiently between many kind of power supply such as solar power and
wind power within smart grid and storage battery. And it is possible to be realized higher supply reliability
and distribution network operation.
Moreover, Curb on fluctuations equipment with storage battery which is used for to prevent influence from
sudden out put fluctuation of PV system, has already developed by Japanese companies.
Relating this technology, proof experiment which will be understood effect and influence on distribution
network in Miyakojima Island by install PV system, has already started by independent type of distribution
network in Miyakojima Island of The Okinawa Electric Power Company, Inc.
This technology can be applied in this project as well, so that Japanese company can stand strong position
and develop lower cost compare with the other country.
8.2.4 Solar Power
Temperature of HCMC is very hot, so that the panel of crystal silicon type with high efficiency can not be
applied to HCMC even though Japanese company has excellent competence. The panel of silicon
amorphous type is proposed in this report due to high temperature characteristics and low cost but other
8-3
foreign manufactures can make easily. In order to get higher power in the same space, hybrid type of
crystal silicon and silicon amorphous will be recommendable in detail design. In this case, Japanese
company can be applied with high competence.
As for battery, Lithium Ion battery is recommended in this report and the development has been carried out
in many countries. Japan also has developed as Japanese government projects, so that the high capacity
type for storage of power will be able to get high competence.
Furthermore, Japanese company has high competence for the inverter for solar and battery due to high
efficiency, high characteristics and familiarity to DAS.
8.2.5 Integrated System
Under becoming aggressively for activity on smart grid, government of every country and every standard
parties also aggressively involve to proceed standardization of equipments.
In Japan, ministry of economy, trade & industry put target to standardize in international and selected “7
Project and 26 items” as important items to keep strong position of Japanese companies.
They put target to be established within three years.
There are 7projects as shown below.
1) WASA
2) Storage battery for distribution network
3) Control of distribution network
4) DR
5) Storage battery for consumer side
6) EV
7) AMI
There are all of necessary technologies in these projects as below.
1) DAS
2) DR network
3) Wide access communication for meters
4) Short distance communication for meters
5) Optimized management for storage battery for distribution
8-4
After fix international standard, Japanese companies can be stronger position for cost competitiveness.
In case that this proposed smart grid will be applied to Vietnam, the system and communication network
can be applied to future technology such as HA, battery by EV etc, so that Japanese company can keep the
high competence as the supplier of the system and communication network.
8.3 Necessary Countermeasure to Obtain the Contract by Japanese
Company
The priority of Vietnam for the smart grid project is lower than the current investment such as power
generation, construction of transmission line / substation and construction of distribution feeder, so that the
investment will be limited.
In case of EVN HCMC, the income is around 800 MUS$ in 2009. The investment of this project is around
40 MUS$ which is not so large as Japan but the project cost means around 5% of the income as EVN
HCMC, so that long term to realize this project will be needed due to other high priority projects. This is
normal case for new project because client does not feel the convenience and necessity due to no
experience.
In order to overcome this blockade, the support of Japanese government such as Demonstration test project
supported by NEDO is needed to apply for the model area as pilot project.
After the pilot project, EVN can understand the necessity and feel the benefits, so that the system using
Japanese excellent technology can be expanded to other areas of EVN HCMC and other cities. Moreover,
this system will be expected to expand to other Asian countries and become de-facto standard.
Korea has already applied DAS project in Hai Phong as Grant and AMR project in Hanoi as also Grant. As
for Solar system, Energy Assistance France and Schneider have applied the BOT pilot project to Quang
Binh province in central Vietnam. Competition between foreign countries and Japan are very hard but these
competitive countries proposed single function as one of smart grid system. Japan can propose all of
functions in smart grid project based on a lot of experience and technology, so that the effect for energy
efficiency in Vietnam becomes much better.
In order to keep the highest position in smart grid system, it is important to obtain the initiative with high
speed. Therefore, Japanese support (ex: Demonstration test project supported by NEDO) shall be quickly
applied for Vietnam as pilot project.
9-1
Chapter 9 Financial Outlook
9.1 Fund Source and Funding Plan
In this chapter, a candidate fund source, type of fund, its availability and feasibility will be reviewed. And it
presumes that an implementation agency is responsible to raise funds and invest the project.
9.1.1 Fund Source
1) General outline
Generally there are two types of funds when an implementation agency raises a fund outside the
company: i.e. borrowing from commercial banks or issue a bond at the monetary market of Vietnam.
On November 2010, a Base Interest Rate (VND) of the State Bank of Vietnam is 9%. Followed by this, a
corporate lending rate is 17-18% (VND), its repayment year is 1-3 years.
Sovereign bond is a typical indicator that shows a country-risk of the country concerned. On December
2010, Moody’s downgraded the rating of a Vietnamese long term Sovereign bond (foreign currency) for
fear of its vulnerable banking system in future, as B1, down from Ba3. For the same reason , in the same
month, S&P also downgraded Vietnam as BB-, down from BB. When a private company in Vietnam
wants to issue a corporate bond, its interest rate will be higher than that of a state bond because
credibility of a corporate company will be less than that of the state. After a risk premium is charged on a
corporate bond, its terms of conditions will be the same of that of borrowing.
Note: With regard to rating, Moody’s grades 9 ratings (Aaa to C). Ba3 is the fourth from the best (Aaa)
and its current prospect is as ‘negative’. S&P grades 8 ratings (AAA to CC). BB is the fifth from
the best (AAA) and its current prospect was ‘negative’.
In contrast, ODA loan tends to have a longer repayment period and a lower interest rate. It means that an
annual financial burden of ODA loan is not so big as that of borrowing and a bond. Moreover in case of
Grant Aid, an implementation agency does not have any financial obligations.
2) Necessity of Financial Guarantee
The study team interviewed a few Japanese and European banks who have a branch in Vietnam and
asked what kind of loan condition will be provided to the project while explaining the project. Then the
study team had the following comments:
9-2
(A) Stands for comment from Japanese banks (B) Stands for comment from European banks
Regarding a loan condition, an interest rate will be determined based on a country risk, a financial
condition of an implementation agency, feasibility of a project and so on. (A), (B)
From a view of risk management, it is hard to extend a credit to a company in Vietnam
unconditionally. Guarantee is a must condition. (A), (B)
When a financial intermediary extends a loan to a project, it expects that a scale of a project is
bigger than more than a few million US$ (ex. 300-500 million US$.) When a project is less than
100 million US$, a financial intermediary is reluctant to provide a loan because its scale is too
small. (B)
A long term credit may be not available in Vietnam. (A)
Almost all financial intermediaries answered that they needed guarantees in extending a credit to a
private company in Vietnam. In this project, a guarantor may be either EVN as a parent company or the
Government. With regard to a guarantee of the Government, Law on Public Debt Management
(No.29/2009/QH12)was enacted in 2009. In this Law, Article 34 defines a conditions of a
government guarantee, stating that a foreign loan under a loan agreement is valued at US$ 50 million
equivalent or higher, the value of issued international bonds is US$ 100 million equivalent or higher and
within the Government’s annual commercial loan limits and foreign borrowing guarantee, except loans
specified in Clause 4. Article 33 of this Law; the debt payment period is at least 10 years and borrowing
or issuance conditions conform with market conditions and international practice. Meanwhile it is not
clear whether EVN recently approved a guarantee for any projects or subsidiaries.
In case of ODA scheme, it also needs a guarantee from the Government. ODA scheme, when confirmed
that an implementation agency obtains a guarantee from the Government, will provide a fund.
3) Conditions of export credit
When it applies an Export Credit, it needs to pay a risk premium as well as an interest. Moreover banks
who co-finance with JBIC hedge risks by buying insurance from such insurance organizations as NEXI.
4) Other Conditions
Aside from borrowings, bonds and ODA, fund is considered to be other scheme. Moreover PPP is one
option however an implementation agency for the project was not so familiar with this scheme that it has
not reviewed it.
9-3
9.2 Review on Availability
Review on candidate fund schemes and their availability is as follows.
(1) Borrowing from banks
(2) Export credit (buyers’ credit)
(3) Issue a bond
(4) ODA Loan (Grant Aide)
(5) ODA Loan (Yen Loan)
9-4
1) Borrowing from banks
Implementation agency requests a borrowing from commercial banks. Loan in terms of VND, US$ are
popular now.
Source: Made by Study Team
Lender of a loan: Lender is a commercial bank.
Major condition: As of November 2010, a deposit rate (VND) is more than 12% and a corporate lending
rate (VND) is 17-8%, its repayment period will be less than around 3 years. Likewise
VND, a deposit rate in terms US$ is 4.5% and it is not officially announced but a
corporate lending rate (US$) will be estimated more than 10%. Its repayment period is
also estimated 1-3 years.
Other conditions: almost all banks request a guarantee of the Government to an implementation agency
for borrowing.
Availability / Feasibility: borrowing may be available provided that an implementation agency obtains a
guarantee. However an annual financial burden will be so heavy that the project
will not be feasible.
Fig. 9-2-1 Borrowing
(implementation agency)
Vietnam
JICA/JBIC
Japan
Commercial Bank
Commercial bank
Commercial Bank in Vietnam Provides a loan to PC
Power Company
9-5
2) Export Credit (Buyers’ Credit)
Export credit is a direct loan provided to a foreign importer for financing the import of Japanese
manufacturers and makers. In case that an importer wants to buy goods or technical services from Japan,
JBIC is responsible to provide such an export loan.
Fig. 9-2-2 Export Credit
Source: Made by Study Team
Lender of a loan: JBIC and commercial banks provide a loan for export portion. Both JBIC and
commercial banks co-finance to an implementation agency.
Major condition: interest rate and its repayment period will be determined in accordance with OECD
Arrangement on Guidelines for Officially Support Export Credit. According to JBIC
Official website, a standard loan condition of export credit as of November 2010 will
be that a composite interest rate between JBIC and co-financed banks: 1.43% (JPY),
repayment period: more than 8.5 years. Moreover a risk premium rate will also be
determined based on the OECD Arrangement.
It is noted that an export credit does not provide 100% to the project but has its ceilings.
For remaining portion that is not covered by an export credit, an implementation
agency is responsible to raise funds by itself.
Other conditions: almost all banks request a guarantee of the Government to an implementation agency
for borrowing.
Availability / Feasibility: Export credit will be available as the project has to import goods and facilities
such as RMU and AMR from foreign countries. When it obtains a guarantee
from the Government, an implementation agency has to follow Law on Public
Debt Management and meet certain requirements stated in the Law.
(implementation agency)
Vietnam
JBIC
JBIC extends a loan to HCMC PC with Commercial banks
Commercial Bank
Commercial bank extends a loan to HCMC PC in collaboration with JBIC
Bank
Japan
Power Company
9-6
a standard repayment period of export credit is less than 10 years. Then an
annual financial burden during the period of repayment will become quite heavy.
For cash flow, please refer to the section. 9.2.
3) Bond
An implementation agency issues a bond.
Fig. 9-2-3 Bond
Source: Made by Study Team
Lender of a loan: Lender is an investor who buys a bond at the market.
Major condition: a risk premium will be placed on the interest rate, reflecting credibility of an
implementation agency. Recent example in Vietnam shows that an interest rate: 14-
15% (VND), repayment period: 5-10 years.
Other conditions: a guarantee is required.
Availability / Feasibility: it is possible to issue a bond after an implementation agency obtains a
guarantee. However an annual financial burden will be so heavy that the
project will not be feasible. For reference it is reported that the Government
of Vietnam approved for EVN to issue an overseas bond of 1,000 MUS$ on
July 2010. However EVN is said to give up issuing an overseas bond for the
time being due to a recent unfavorable bond market condition.
(implementation agency)
Vietnam
JICA/JBIC
Japan
HCMC PC Issues a bond or a stock at the market
Commercial Bank
HCMC PC uses its retained earnings for the project
Monetary market
Power Company
9-7
4) ODA Loan (Grant Aide)
ODA is broadly divided into a bilateral aid and a multilateral aid. Following two ODA schemes belong
to the bilateral aid. Grant Aide provides a fund to the Government without the obligation of repayment
and an implementation agency receives a grant from the Government.
Fig. 9-2-4 ODA Loan (Grant Aide)
Source: Made by Study Team
Provider of a loan: JICA provides a grant.
Major condition: It does not need any financial obligation to an implementation agency. However it is
noted the amount to be provided is limited to around 3 MUS$.
Other conditions: Procedure of ODA regulates that the Government officially requests ODA to the
Government of Japan to appraise the project. Therefore an implementation agency
needs to obtain an approval from the Government and the Government requests the
Government to Japan to appraise the project.
Availability / Feasibility: Grant will be applicable when the Government of Vietnam officially requests
the Government of Japan to appraise the project. However a scale of a project is
limited because only 3 MUS$ is available in this scheme.
(implementation agency)
Vietnam Government of Vietnam
JICA
Japan Government of Japan
JICA concludes G/A and grants to HCMC PC
Gov. of Vietnam requests a grant to Gov. of Japan Both governments conclude Exchange Notes (E/N)
prior to Grant Agreement (G/A).
Power company
9-8
5) ODA Loan (Yen Loan)
Yen Loan is a bilateral loan but unlike grant aide, it requests an implementation agency to repay a loan
later.
Fig. 9-2-5 ODA Loan (Yen Loan)
Source: Made by Study Team
Provider of a loan: JICA provides a loan.
Major condition: Yen Loan is extended to an implementation agency. According to JICA Official website,
Loan Condition of Yen Loan as of November 2010 is as follows.
Interest rate 1.2% (Yen), repayment period: 30year, grant period: 10 year
As ODA Loan is defined to cover up to 85% of the total project cost, remaining portion
will be covered by an implementation agency.
Other conditions: Procedure of ODA regulates that the Government officially requests ODA to the
Government of Japan to appraise the project. Therefore an implementation agency
needs to obtain an approval from the Government and the Government requests the
Government to Japan to appraise the project.
Availability / Feasibility: When a project is approved by the Government as a ODA project, this scheme
will be applicable. Moreover a loan condition is not so heavy as that of other
funding schemes, it is most feasible.
(implementation agency)
Vietnam Government of Vietnam
JICA
Japan Government of Japan
JICA concludes L/A and extends a ODA Loan to HCMC PC
Gov. of Vietnam requests a Loan to Gov. of Japan. Both Governments conclude Exchange Notes (E/N)
prior to Loan Agreement (L/A).
Bank
Power company
9-9
6) Conclusion
The study team explained these fund schemes to EVN and PC Company. However they do not say
clearly which fund scheme will be preferable or not. As for EVN and PC company, they have a will to
implement the project. However they do not to want to worsen their financial conditions by applying a
new project since EVN is said to be suffering an accumulating financial loss. Moreover they are not
familiar with such schemes as PPP so that they do not review it.
The Study Team explained the five fund schemes. Summary is shown in the Table 9-1. As for an
implementation agency, it first considers if a loan condition such as interest and repayment period is
preferable or not. Next, it considers such qualitative factors as necessity of guarantee. Borrowing from
banks and issue of bond will lead to a big annual financial burden to an implementation agency. Then an
implementation agency may not choose such fund schemes. As a result, either Export Credit or ODA
Loan (Yen Loan) will be applicable to the project. With regard to a grant, ODA (Grant Aide) is also
applicable. Cash flow on export credit and cash flow on ODA Loan (Yen Loan) will be reviewed in the
next section.
9-10
Table 9-2-1 Fund Source and Availability
Borrowings
Export Credit
(Buyer’s Credit) Bond
O D A
(Grant Aide)
O D A
(Yen Loan)
Scheme Banks provide a loan
Provide a loan to an
importer who imports from
Japanese manufacturers
and makers.
Issue a bond at the
monetary market of
Vietnam
The Gov. of Vietnam
requests a ODA for the
project and JICA appraises
a project
The Gov. of Vietnam
requests a ODA for the
project and JICA appraises
a project
Lender Banks Co-finance by JBIC and
banks Investors JICA JICA
Terms of conditions
-Interest
-Repayment period
-Others
-17-18%(VND)
-1-3 years (approx.)
-
-1.43% (JPY)
-10 years at the maximum
(18 years (at the
maximum) for renewable
energy and water supply
project)
-pay a risk premium
-14-15% (VND)
-5-10years (approx.)
-
No financial obligation
- Amount is 3 million USD
-1.2% (JPY)
-Repayment 30 years,
grant10 years
-85% of the total cost
Other conditions
Guarantee by the
Government is
required
Guarantee by the
Government is required
Guarantee by the
Government is required
Guarantee by the
Government is required
Guarantee by the
Government is required
Annual financial
burden
Financial burden is
the biggest
Financial burden is not so
heavy as borrowings
The same as that of
borrowing -
Financial burden is the
least
Evaluation
×
△
×
△
○
(Note) ×: Bad, △: Available but still not good, ○: Good
Source: Made by Study Team
9-11
9.3 Cash Flow Analysis
In this section, cash flow is estimated based on benefits and costs shown in Chapter 5 and interest and
principal and so on. As it is obvious that borrowing from banks, bond are not feasible from a financial
viewpoint, the following two types of cash flow are estimated; namely cash flow on export credit and cash
flow on ODA Loan (Yen Loan).
Cash flow in this study is defined as follow:
Annual cash flow
= (benefits – costs)- (interest) - (principle) + (depreciation)
9.3.1 Preconditions
Major preconditions are as follows.
1) Project period: 20 years
Total construction cost: 42.63 MUS$ (including taxes, contingency and price escalation)
2) Total asset: 37.2 MUS$ = 42.63 MUS$ - 5.5 MUS$ (such non-assessable expenses as engineering
service + personnel expenses). Depreciation will start in 2015 for the next 25years.
3) Foreign Exchange Rate: $1=19,491VND, $1=80.89Yen (Tokyo Mitsubishi UFJ bank as of 29 October,
2010)
4) Borrowings are in terms of Yen.
5) Condition of Buyer’s credit is based on an indication of European bank as of December, 2010.
6) Among total 42.6 MUS$, 31.45 MUS$ (excluding 15% of the total foreign portion) is co-financed by
JBIC and a commercial bank (60% by JBIC and 40% by a commercial bank). It presumes that an
implementation agency secures a remaining amount by itself without asking a borrowing.
7) Repayment period: 12 years
8) Interest rate is determined based on the OECD Guideline. Currently a 1.43% of interest rate (over 8.5
years) is announced as a Standard Loan Condition as of November 2010 in JBIC’s Official Website,
3.28% is determined by adding risk premium.
9-12
9) Moreover an implementation agency is required to pay 1.422 MUS$ as a fee, a commission and an
insurance for a commercial banks paying to NEXI.
10) Condition of ODA Loan: 1.2 % of interest rate, 10 year of concession period and 30 years of repayment
period.
11) Among total 42.6 MUS$, 36.21 MUS$ (85% of 42.6 MUS$) is extended by JICA. It presumes that an
implementation agency secures a remaining amount by itself without asking a borrowing.
Summary is as follows.
Table 9-3-1 Cash Flow
Result Reference
Export Credit
(Buyers’ Credit)
IRR=4.49%
NPV=-7.6 MUS$
(discount rate: 6.95%)
IRR is positive but NPV is negative.
ODA Loan (Yen Loan)
IRR=9.30%
NPV=+6.0 MUS$
(discount rate: 6.95%)
Both IRR and NPV are positive.
Source: Made by Study Team
9.3.2 Conclusion
Regarding Export Credit, IRR is positive but NPV is negative. As a repayment year is a 12 year, it leads to
a big annual financial burden. Meanwhile ODA Loan, both IRR and NPV are positive. In case of ODA loan,
an implementation agency only pays an interest for the first 10 years. Actual repayment of capital will start
after the eleventh year.
It is noted that it is important to make the best use of depreciation from a view of cash flow management.
An implementation agency has to complete a construction on schedule if it plans to control a cash flow
effectively. An implementation agency is able to minimize annual cash outflow by adding a annual
depreciation to an annual profit of the project and annual repayment scheme.
9-13
Table 9-3-2 Cash Flow (Yen Loan)
Source: Made by Study Team
単位: 百万$
year 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 小計(2010-19)
利益(FIRR) - - - -12.3 -28.7 3.9 3.9 3.9 3.9 3.9 -21.4
利払・元本償還 - - - 0.0 0.0 -0.1 -0.4 -0.4 -0.4 -0.4 -1.9
減価償却費 - - - 1.7 1.7 1.7 1.7 1.7 8.5CF - - - -12.3 -28.7 5.5 5.2 5.2 5.2 5.2 -14.7
単位: 百万$
year 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 小計(2020-29)
利益(FIRR) 3.9 3.9 3.9 3.9 3.9 3.9 3.9 3.9 3.9 3.9 39.2
利払・元本償還 -0.4 -0.4 -0.4 -0.4 -0.4 -0.8 -1.7 -1.6 -1.6 -1.6 -9.5
減価償却費 1.7 1.7 1.7 1.7 1.7 1.7 1.7 1.7 1.7 1.7 17.0CF 5.2 5.2 5.2 5.2 5.2 4.8 4.0 4.0 4.0 4.0 46.7
単位: 百万$
year 2030 2031 2032 2033 2034 小計(2030-34) 総合計
利益(FIRR) 3.9 3.9 3.9 3.9 3.9 19.6 37.4
利払・元本償還 -1.6 -1.6 -1.5 -1.5 -1.5 -7.7 -19.1
減価償却費 1.7 1.7 1.7 1.7 1.7 8.5 34.1CF 4.1 4.1 4.1 4.1 4.1 20.4 52.4
Profit(FIRR)
Interest/princpal
Depreciation
Profit(FIRR)
Interest/princpal
Depreciation
Profit(FIRR)
Interest/princpal
Depreciation
9-14
Table 9-3-3 Cash Flow (Export Credit)
Source: Made by Study Team
million $
year 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 (2010-19)
Profit(FIRR) - - - -12.3 -28.7 3.9 3.9 3.9 3.9 3.9 -21.4
Interest/Princpal/Insurance etc. - - -1.4 -0.2 -0.7 -4.1 -4.0 -3.9 -3.8 -3.7 -20.4
Depreciation - - - - - 1.7 1.7 1.7 1.7 1.7 8.5CF - - -1.4 -12.4 -29.4 1.5 1.6 1.7 1.8 1.9 -33.3
million $
year 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 (2020-29)
Profit(FIRR) 3.9 3.9 3.9 3.9 3.9 3.9 3.9 3.9 3.9 3.9 39.2
Interest/Princpal/Insurance etc. -3.6 -3.5 -3.4 -3.3 -3.2 0.0 0.0 0.0 0.0 0.0 -17.0
Depreciation 1.7 1.7 1.7 1.7 1.7 1.7 1.7 1.7 1.7 1.7 17.0CF 2.0 2.1 2.2 2.3 2.4 5.6 5.6 5.6 5.6 5.6 39.2
million $
year 2030 2031 2032 2033 2034 (2030-34) total
Profit(FIRR) 3.9 3.9 3.9 3.9 3.9 19.6 37.4
Interest/Princpal/Insurance etc. 0.0 0.0 0.0 0.0 0.0 0.0 -37.4
Depreciation 1.7 1.7 1.7 1.7 1.7 8.5 34.1CF 5.6 5.6 5.6 5.6 5.6 28.1 34.0
10-1
Chapter 10 Action Plan and Issues
10.1 Action Plan for Advancing This Project
The following action will be implemented in order to realize this project.
The proposed project will be explained to a lot of related persons in Vietnam through the
workshop in order to know the advantages better.
This model project will be proposed to the demonstration test project supported by NEDO.
After the model project, the system will be expected to expand to other areas by Japanese finance
and technical support. Therefore, the action toward Japanese financing project will be
implemented in parallel.
The problems for advancing this project are as follows.
1) Advanced DAS /AMR
It is told that EVN will aggressively invest for increment of current capacity and automation. And they
may plan to increase price of electricity gradually. So they need to solve chronic and lack of electricity
supply, and it can be expected to install infrastructure that can be realized suitable power supply.
EVN HCMC still dispatches their employee at substation and it is hardly to apply remote control from
SCADA.
The activity to distribution network also same as the above, their employee is dispatch and handling
maintenance job for distribution network and reading electricity usage value by watt-hour meter. In
addition, the outage duration under maintenance and fault is long. It is easy to expect that EVN has to
spend huge number of employee for the maintenance and improve the reliability.
It is very efficient system because Advanced DAS and AMR can reduce their labor and improve the
reliability, and this system can be fit their needs.
However, automation system needs to be applied from upper layer of transmission / distribution network,
so automation for distribution network should put lower priority and late time to apply automation.
Under this consideration, the Advanced DAS will be equipped with SCADA function which can
monitor and control for 110kV primary substations. The Advanced DAS will also be installed in existing
SCADA center and be connected to Phu Tho Power Company with AMR / DR system through Fiber
Optic communication network.
10-2
The Advanced DAS is recommended to be gradually expanded to other power companies and 110kV
primary substations.
2) Solar Power
Selling tariff of renewable energy include solar power sets extremely cheap at present. And assistant for
installation is also poor.
Major renewable energy in Vietnam has been small hydro power until now. But a lot of issues are
occurred by unplanned hydro power development such as cause of flood. It is difficult to advance of
more development. Solar power plant shall have potential substitute of this issues.
Especially southern region include HCMC has good condition of solar radiation all around year, then
adequate for solar power generation. Solar power generation is less impact of environmental than wind
turbine and bio-mass generation. Those do not only install gather panels, but also install decentralize in
urban area. And these panels shall be controlled by smart grid, it shall adequate for coming Vietnamese
renewable energy.
But solar power system is more expensive installation cost than the other renewable energy. It shall need
assistant for installation or contrive of selling tariff. Special low for assistant by government shall need.
10.2 Activity of Related Organization in Vietnam Government
The activities for MPI and MOIT as related organization in Vietnam government are as follows.
10.2.1 Activity of MPI
MPI usually make the government plan for energy policy.
According to the decision of the prime minister “1855/QD-TTg dated on 2007/12/27”, the development
strategy and policy for national energy are as follows.
1) Preparation of energy priority in order to guarantee national energy, Utilization of Vietnam energy
resources, reduction of imported petroleum products, reduction of the export of coal in medium-term,
Increment of petroleum storage.
2) Introduction of market principle in energy price.
10-3
3) High priority development and Acceleration of foreign investment for new renewable energy, Biomass
energy and Nuclear energy
4) Clearness of energy efficiency require and recommendation of energy efficiency equipment and
technology in order to utilize economical and effective energy
5) Energy development and balance of utilization based on Environmental management
10.2.2 Activity of MOIT and EVN
MOIT is advancing to revise the law of energy efficiency which will enforce on 1st January 2011. The
acceleration regulation for renewable energy will be included in the new energy efficiency law. The content
is to subsidize to a part of cost for installation of renewable energy.
EVN as implementation organization has implemented to solve the shortage of power and improve the
reliability as the most important problems. Namely, the construction of power generation and application of
renewable energy has been advanced as the solution of shortage problems for power generation. In addition,
EVN has carried out the reduction of transmission and distribution loss and the development of renewable
energy.
As for improvement of the reliability, the transmission and distribution lines have been constructed so far.
Regarding smart grid, EVN started the pilot projects as single system such as Solar, AMR etc. EVN has
understanding which the power from renewable customers shall be purchased with reasonable tariff and the
tariff will be realized under Vietnam government support. Therefore, the smart grid project shall be
involved with MOIT in order to modify the tariff system and the law.
10.3 Legal and Financial Constraints, etc. of Partner Country
10.3.1 Legal Restriction
1) According to MOIT, there is no legal restriction about the peak cut by the DR.
2) According to EVN, there is no system inter-connection of solar power generation system at the moment.
The solar power generation equipment to be installed under this project will supply electric power to the
transmission and distribution network since the system inter-connection will be made. Technical
requirement for system inter-connection of the renewable energy including solar power is specified in
MOIT Circular No.32/2010-/TT-BCT named "Regulation of Power Distribution System”.
10-4
Moreover, in case that a solar power generator, in the future, sell electricity to a power utility, the unit
prices of such electricity sale to be applied are described in Decision No.73/QD-DTDL of December 30,
2009 promulgated by Electricity Regulatory Authority of MOIT. This regulation is applied when the
small-scale power generation which used renewable energy has system inter-connection. According to
EVN, the unit price for this year is decided in view of small hydropower generation which generation
unit price is cheap, and the unit price is reviewed every year. The unit price is expected to be raised in
about 12 cent/kWh from now on.
10.3.2 Financial Restraint
1) When an implementation agency raises fund for the project, it is requested to obtain a guarantee under
whatever financial scheme it may be. In case that an implementation agency requests the Government
for a guarantee, it has to follow Law on Public Debt Management (No.29 / 2009 / QH12) in which a
foreign loan has to meet a certain requirement defined in this Law.
2) As a newspaper reported that the Government plans to raise a power tariff by 30% in 2011, it is
necessary to raise a tariff towards an appropriate price level. Price hike mentioned above aims to raise a
whole sale tariff as a result it aims to invite more foreign investors to invest power development
programs in Vietnam.
As for a distribution company, a price hike brings good benefits too; first, a distribution company earns
more profit so that it can maintain good financial conditions. Second, it can improve its financial
credibility therefore it can raise fund with a lower interest rate in future.
10.4 Necessity of Additional Detail Analysis
The overview of fundamental policy and activities can be grasped in the survey but it is necessary to carry
out the detail survey and the analysis as follows.
Detail survey for Grant project
Detail survey for Japanese financing project (JICA ODA loan etc) in parallel
Survey for CDM between Vietnam and Japan etc
Annex related to Chapter4
COMPANY QUESTIONNAIRE
HOUSEHOLD QUESTIONNAIRE
Interview with Manufacturing and Enterprise Customers 1~17
Interview with Residential Customers 1~15
COMPANY QUESTIONNAIRE
Interview starting time (AM / PM)
Date (DD/MM/YY)
COMPANY’S NAME:
Address
Phuong (ward) Quan (district)
01 Respondent’s Name
02 Respondent’s Sex Male/Female 03 Respondent’s Position
A. COMPANY PROFILE
11 Which year was your company founded? (Establishment Year)
12 What kind of business
is your company
involved?
(Which industry and what kind of production they make. Please see the reference on the back)
i) Industry (secondary sector)
(Specify) e.g. textile, furniture, food products
ii) Services (tertiary sector)
(Specify) e.g. travel agency, food beverage service, hotel industry
iii) Others (Specify)
13
How many stories
does your company
occupy?
i) One story ii) Two stories iii) Three stories
iv) Four stories v) Five or more (specify)
14 How big is your
company?
i) 0-50m2 ii) 50-100m2 iii) 100-150m2
iv) 150-200m2 v) 200m2 or over (specify)
15
How long is your
company located at
the present address
i) 0-10 years ii) 10-20 years iii) 20-30 years
iv) 30-40 years v) 40-50 years vi) Over 50 years
16 Staff number
i) 1 – 5 staff ii) 6-20 staff iii) 21-50 staff
iv) 51-100 staff v) 101 -300 vi) 301 or more
If there is annual reports, brochure and financial statements (balance sheet, income statement, and cash flow statement). that introduce company profile, above questions can be omitted.
B. FACTS ABOUT ELECTRICITY CONTRACT AND MODE OF PAYMENT
21 How big is the contracted capacity? ampere
22 How does EVN-HCMPC
measure the electricity
usage for the company
i) They come every month to read the meter, and they come back a few days later with a notice for payment.
ii) Others (specify)
23 How does the company pay
for the electricity bill? i) Pay directly to the EVN staff.
ii) Pay through banks’ ATM or Post Office by (cash /
check / credit card).
iii) Pay monthly at EVN Office.
iv) Other (specify)
C. ELECTRICITY USAGE
31 How many times per day do you have power cut?
i) One time ii) Two times
iii) Three times iv) Others (specify)
32 How many hours per day do you have power cut?
i) 0-2 hours in total ii) 2-4 hours in total
iii) 4-6 hours in total iv) 6-8 hours in total
v) Over 8 hours in total
33 When in a day does EVN –HCMPC conduct power cut (or load shedding)?
i) Morning time (dawn to 11 AM)
ii) During noon (11 AM to 1 PM)
iii) Early afternoon (1 to 5 PM)
iv) Evening time (5 to 9 PM)
v) Night time (10PM to dawn)
34 Please describe average electricity consumption per month
kWh
35 Please describe how much your company pays per month for electricity bill (in average)? VND
36 Does your company have a generator to supplement the electricity supply from EVN (or HCMPC)?
i) Yes
kVA ii) No
37 For what does your
company use electricity
most?
i) Air conditioner hrs/day
ii) Room light hrs/day
iii) TV hrs/day
iv) Others (specify)
hrs/day
v) Others (specify)
hrs/day
38 Do you think the current electricity capacity at your company is
enough? i) Yes ii) No
39 Do you think the electricity bill for which your company currently
pays is too expensive? i) Yes ii) No
40 Why do you think so? For those who answer ‘Yes’
i) Because our company actually use the electricity a lot.
ii) Because the electricity bill is unusually higher than for
other expenses.
ii) Because we have to pay the electricity bill anyway even
though there are power cuts or load shedding.
iv) Others (specify)
For those who answer ‘No’
v) Because our company actually do not use electricity much.
vi) Because the electricity bill is lower than for other expenses.
vii) Others (specify)
41 Is your company satisfied with the EVN’s current service? i) Yes ii) No
42 Why do you think so? For those who answer ‘Yes’
i) Because the quality of service is good.
ii) Because they supply electricity for 24 hours.
iii) Because the electricity bill costs reasonable (OK).
iv) Others (specify)
For those who answer ‘No’
v) Because the quality of service is not good
vi) Because they often cut electricity supply.
vii) Because the electricity bill costs too much.
viii) Others (specify)
43 Will your company pay more if EVN improves their service? i) Yes ii) No
44 How much can your company afford to pay for the
electricity monthly if EVN improves their service? VND/month
D. SMART GRID
51 Are you OK if EVN must stop air conditioner?
(The other electricity appliances keep running with
stable electricity supply.)
i) 30 min ii) 1 hr iii) No
52 What do you want if EVN must
stop air conditioner?
i) It is OK if EVN gives discount by 10%
ii) Others (specify)
E. OTHERS
61 Any other information from the respondent (or staff members)
62 Recorder’s findings and comments
Interview ending time (AM / PM)
Record taken by:(name)
HOUSEHOLD QUESTIONNAIRE
Interview starting time (AM / PM)
Date (DD/MM/YY)
A. BASIC IDENTIFICATION OF RESPONDENT AND HIS/HER FAMILY
01 Respondent’s Name
02 Respondent’s Sex Male/Female 03 Respondent’s Age
04 Respondent’s Occupation
i) Employee ii) Employer iii) Housework iv) Shop owner
v) Trader vi) Worker(laborer) vii) Government staff
viii) Student ix) Unemployed x) Others (specify)
05 How many people live in your house? Adult M F
Child M F
Total M F
06 Address
07 How long have you lived in your present house?
i) 0-10 years ii) 10-20 years iii) 20-30 years
iv) 30-40 years v) 40-50 years vi) > 50 years
08 How many stories does your house have?
i) One story ii) Two stories iii) Three stories
iv) Four stories v) ≥ Five
09 How big is your house?
i) 0-50m2 ii) 50-100m2 iii) 100-150m2
iv) 150-200m2 v) > 200m2
B. HOUSEHOLD EXPENDITURE
11 How many people have jobs among all people living in your house?
i) 0 person ii) 1 persons iii) 2 persons
iv) 3 persons v) 4 persons v) ≥ 5 persons
12 What are your household’s main sources of income?
13
HOUSEHOLD MONTHLY EXPENDITURE (roughly): What do you spend monthly?
i) Food VND
ii) Health VND
iii) Education VND
iv) Water VND
v) Electricity VND
vi) Gas VND
vii) House appliances VND
viii) Land telephone VND
ix) Mobile phone(s) VND
x) Others (specify)
VND
C. FACTS ABOUT ELECTRICITY CONTRACT AND MODE OF PAYMENT
21 How big is the contracted capacity for your house? ampere
22 How does EVN-HCMPC measure the electricity usage at your house?
i) They come every month to read the meter, and they come back a few days later with a notice for payment.
ii) Others (specify)
23 How do you pay for the electricity bill?
i) Pay directly to the EVN staff.
ii) Pay through banks’ ATM or Post Office by (cash / check / credit card).
iii) Pay monthly at EVN Office.
iv) Other (specify)
D. ELECTRICITY USAGE
31 For how long do you use electricity in your house?
i) 0-10 years ii) 10-20 years iii) 20-30 years
iv) 30-40 years v) 40-50 years vi) > 50 years
32 How many times per day do you have power cut?
i) None ii) One time iii) Two times
iii) Three times iv) Others (specify)
33 How many hours per day do you have power cut?
i) 0-2 hours in total ii) 2-4 hours in total
iii) 4-6 hours in total iv) 6-8 hours in total
v) > 8 hours in total
34 When in a day do you often have power cut (or load shedding)?
i) Morning time (dawn to 11 AM)
ii) During noon (11 AM to 1 PM)
iii) Early afternoon (1 to 5 PM)
iv) Evening time (5 to 9 PM)
vi) Night time (10PM to dawn)
35 Please describe average electricity consumption per month kWh
36 Do you have a generator to supplement the electricity supply from EVN (or HCMPC)?
i) Yes
kVA ii) No
37
What kind of electrical appliance do you have? (Please identify how many of them they have. Sample: mobile phone*4)
i) Room light ii) Rice cooker
iii) Refrigerator
iv) Microwave / Toaster
v) Table fan
vi) Ceiling fan
vii) Air conditioner viii) VCR/DVD player
ix) TV x) Radio
xi) Iron xii) Hair dryer
xiii) Sewing machine
xiv) Mobile phone
xv) Dehumidifier
xvi) Personal Computer / Family Computer
xvii) Others (specify):
38 How many hours per day do you currently use the electrical appliances?
i) Air conditioner hrs/day
ii) Refrigerator hrs/day
iii) Room light hrs/day
iv) TV (including VCD / DVD watching through TV)
hrs/day
v) Table fan hrs/day
vi) Ceiling fan hrs/day
vii) Others (specify)
hrs/day
39 Do you think the current electricity capacity at your house is enough?
i) Yes ii) No
40 Do you think the electricity bill for which you currently pay is too expensive?
i) Yes ii) No
41 Why do you think so?
For those who answer ‘Yes’
i) Because we actually use the electricity a lot.
ii) Because the electricity bill is unusually higher than other expenditures such as water bill and gas.
iii) Because we have to pay the electricity bill anyway even though there are power cuts or load shedding.
iv) Others (specify)
For those who answer ‘No’
v) Because we actually do not use electricity much.
vi) Because the electricity bill is lower than other expenditures such as water bill and gas.
vii) Others (specify)
42 Are you satisfied with the current electricity supply? (quality, quantity, hours etc)
i) Yes ii) No
43 Why do you think so?
For those who answer ‘Yes’
i) Because the quality of service is good.
ii) Because they supply electricity for 24 hours.
iii) Because the electricity bill costs reasonable (OK).
iv) Others (specify)
For those who answer ‘No’
v) Because the quality of service is not good
vi) Because they often cut electricity supply.
vii) Because the electricity bill costs too much.
viii) Others (specify)
44 Are you willing to pay more if EVN improves their service in electricity supply?
i) Yes ii) No
45 How much do you like to pay for the electricity monthly, if EVN improves their service in electricity supply?
VND/month
E. SMART GRID
51
Are you OK if EVN must stop air conditioner? (but the other electricity appliances keep running with stable electricity supply.)
i) 30 min ii) 1 hr iii) No
52 What do you want if EVN must stop air conditioner?
i) It is OK if EVN gives discount by 10%
ii) Others (specify)
F. OTHERS
61 Any other information from the respondent (or family members)
62 Recorder’s findings and comments
Interview ending time (AM / PM)
Record taken by:(name)
Interview with Manufacturing and Enterprise Customers 1
Company Profile
Industry Amusement park Address Hoa Binh Street, Ward 3, District 11
Interviewee Male Position Vice Director
Establishment 1976 Total area 42 ha No of staff 600
Remarks Opens 7AM to 9PM every day. Entrance fee costs $2, with additional payment for each
attraction. 150,000 people during weekends and holidays, and 3 to 50,000 people during
week days come to the park from HCMC as well as neighboring provinces.
Condition of Electricity Use
Capacity 15kV line comes from EVN to the park. There are 50 units of 50A. 7 transformers with 7
meters.
Electricity consumption 4,000,000 kWh per year Monthly electricity bill
80,000,000,000 VND per
year
Generator There are 7 generators with capacity of 1,000 kVA.
Main use
Electricity is mainly spent for ice making at the ice staking rink, amusement attractions and
other equipment. A/C is used only for offices and restaurants. Lights are turned on during
working hour.
*Restaurants are often used for wedding parties, birthday parties and other events.
Mode of Billing EVN reads the meter and send the invoice
Mode of Payment Bank transfer
Power Outage
It sometimes occurs during morning time for 2 to 4 hours. Power outage does occur very
occasionally. All 7 meters never fall down all at once. There is no power outage in 2010.
Opinions on Current Power Supply and Electricity Cost
Current power supply Sufficient
Current electricity cost
Not expensive
(reason) It needs electricity to provide good quality of service to the
customers. We understand it is our obligation to pay electricity bill, and it
does not matter as we have sufficient revenue.
Current provided service Satisfied (reason) N/A
Willingness to pay more if the quality of EVN’s service becomes improved. Acceptable
Amount of willingness to pay if the quality of EVN’s service becomes improved.
Additional 10%
Ideas on Smart Grid
Disconnecting only A/C Not acceptable
Incentives for disconnecting A/C 10% discount
Opinion We cannot disconnect A/C in the middle of providing service to the customers. We cannot
imagine doing so, and we cannot do so. We will continue using A/C by activating generators.
Interview with Manufacturing and Enterprise Customers 2
Company Profile
Industry Apparel (Garment export / domestic wholesale) Address 3 Thang 2, District 10
Interviewee Male Position Company Owner
Establishment 1996 Total area Total 1,200m2 No of staff Total 200
Remarks Moved to the current place in 2003. There are two complexes: (i) management office cum
working station, and (ii) factory.
Condition of Electricity Use
Capacity Two phases (40A) for office and three phases (100A) for manufacturing.
Electricity
consumption
Factory: 16,637 kWh (invoiced Jun
2010. Office: 2,638 kWh (do)
Monthly
electricity bill
Factory: 22,711,698 VND.
Office: 5,498,434 VND
Generator One generator of 220 kVA
Main use
Electricity is mainly spent for large scale sewing machine (4 sets) and press iron (2 sets). To
control room temperature, A/C (6 sets) are used for 10 hrs a day (24 hrs at the busy season),
and room lights for 16 hrs from 7:30AM to 11PM. Often use TV, computers and fans too.
Mode of Billing EVN reads the meter and send the invoice
Mode of Payment Pay directly with EVN staff when they visit by cash
Power
Outage
There are power outages all of a sudden, which leads to total black out in this area. Such
outages lasted 1 to 1+1/2 hrs, which is less than that of 2009 (2 to 4 hrs) and it became rare.
Power outage often occurs during morning time and midnight.
Opinions on Current Power Supply and Electricity Cost
Current power supply Sufficient
Current electricity cost Expensive (reason) Feel it is too expensive, but EVN cuts off the power
supply if we do not pay. There is no other choice.
Current provided service Satisfied (reason) It would be good if EVN improves their response to
our telephone calls.
Willingness to pay more if the quality of EVN’s service becomes improved. Acceptable
Amount of willingness to pay if the quality of EVN’s service becomes improved.
Will pay as required
Ideas on Smart Grid
Disconnecting only A/C Not acceptable
Incentives for disconnecting A/C ―
Opinion Cannot stop A/C for the equipment to keep running. Like to use generator to keep using A/C.
Interview with Manufacturing and Enterprise Customers 3
Company Profile
Industry Beer manufacturing Address Nguyen Chi Thanh, District 10
Interviewee Male Position Mechanical Manager
Establishment Over 50 years ago Total area Over 200m2 No of staff 100 to 300
Remarks Building is 4 stories or over.
Condition of Electricity Use
Capacity Single phase (220V) and three phases (380V) (two lines).
Electricity consumption 165,076 kWh per month Monthly electricity bill 304,730,000 VND
Generator One generator
Main use Beer tanks (24 hrs), room lights (24 hrs), A/C (8 hrs)
Mode of Billing EVN reads the meter and send the invoice
Mode of Payment Money transfer
Power Outage Power outage occasionally occurs around noon for 2 to 4 hours.
Opinions on Current Power Supply and Electricity Cost
Current power supply Sufficient
Current electricity cost Expensive (reason) Because we use a lot.
Current provided service Satisfied (reason) Because it is available for 24 hrs.
Willingness to pay more if the quality of EVN’s service becomes improved. Acceptable
Amount of willingness to pay if the quality of EVN’s service becomes improved.
Like to pay more, but hope to be around 270,000,000
VND (10% off).
Ideas on Smart Grid
Disconnecting only A/C Acceptable if it is 30 minutes.
Incentives for disconnecting A/C 10% discount
Opinion ―
Interview with Manufacturing and Enterprise Customers 4
Company Profile
Industry Plastic manufacturing Address Lac Long Quan, District 10
Interviewee Male Position General Director’s Assistant
Establishment 1975 Total area 150 to 200m2 No of staff Over 300
Remarks Building is 4 stories or over
Condition of Electricity Use
Capacity Single phase (220V) and three phases (380V) (two lines)
Electricity consumption 1,398,856 kWh Monthly electricity bill 1,648,922,838 VND
Generator One generator
Main use Electricity is spent for plastic manufacturing (24 hrs), room lights (12 hrs), A/C (8 hrs)
Mode of Billing EVN reads the meter and send the invoice
Mode of Payment Pay at EVN Office.
Power Outage It occurs midnight up to 2 hours.
Opinions on Current Power Supply and Electricity Cost
Current power supply Sufficient
Current electricity cost
Expensive (reason) Because we have to pay the electricity bill anyway even
though there are power cuts or load shedding.
Current provided service Satisfied (reason) Because they supply electricity for 24 hours.
Willingness to pay more if the quality of EVN’s service becomes improved. Acceptable
Amount of willingness to pay if the quality of EVN’s service becomes improved.
―
Ideas on Smart Grid
Disconnecting only A/C Acceptable if it is 1 hour.
Incentives for disconnecting A/C 10% discount
Opinion ―
Interview with Manufacturing and Enterprise Customers 5
Company Profile
Industry Telecommunication Address Truong Son, Ward 15, District 10
Interviewee Male Position Administrative Manager
Establishment 2005 Total area 100 to 150m2 No of staff 6 to 20
Remarks Building has 2 stories.
Condition of Electricity Use
Capacity Single phase (220V, 10-100A)
Electricity consumption 1,460 kWh Monthly electricity bill 2,696,000 VND
Generator None
Main use Room lights (6 hrs), A/C (6 hrs), TV (4 hrs)
Mode of Billing EVN reads the meter and send the invoice
Mode of Payment Pay directly with EVN staff when they visit by cash
Power Outage It occurs once a day for 4 to 6 hours. Often in the morning time.
Opinions on Current Power Supply and Electricity Cost
Current power supply Sufficient
Current electricity cost Expensive (reason) Because we have to pay the electricity bill anyway
even though there are power cuts or load shedding.
Current provided service Satisfied (reason) Because the quality of service is good.
Willingness to pay more if the quality of EVN’s service becomes improved. Not acceptable
Amount of willingness to pay if the quality of EVN’s service becomes improved.
Does not want to pay more than we currently do.
Ideas on Smart Grid
Disconnecting only A/C Not acceptable
Incentives for disconnecting A/C ―
Opinion
We are concerned about the affects to the telecommunication equipment and facilities if
power outage repeatedly occurs. They might get broken easily.
Interview with Manufacturing and Enterprise Customers 6
Company Profile
Industry Manufacturing Address To Hien Thanh, District 10
Interviewee Male Position Manager of Mechanical Department
Establishment 2002 Total area 50 to 100m2 No of staff 20 to 50
Remarks Building has 2 stories.
Condition of Electricity Use
Capacity Single phase (220V, 10-100A) and three phase (380V) (two lines).
Electricity consumption 738,177 kWh Monthly electricity bill 1,656,757,894 VND
Generator One generator
Main use Electricity is mainly spent for equipment and frozen warehouse for 24 hrs. Also used for
room lights (12 hrs), A/C (8 hrs) and TV (8 hrs).
Mode of Billing EVN reads the meter and send the invoice
Mode of Payment Pay at EVN Office
Power Outage Power outage occurs for 4 to 6 hours, around noon.
Opinions on Current Power Supply and Electricity Cost
Current power supply Sufficient
Current electricity cost Expensive (reason) Because we have to pay the electricity bill anyway
even though there are power cuts or load shedding.
Current provided service Satisfied (reason) Because electricity is supplied for 24 hours.
Willingness to pay more if the quality of EVN’s service becomes improved. Acceptable
Amount of willingness to pay if the quality of EVN’s service becomes improved.
Like to pay more, but hope to keep within
1,500,000,000 VND.
Ideas on Smart Grid
Disconnecting only A/C Acceptable if it is 30 minutes
Incentives for disconnecting A/C 10% discount
Opinion ―
Interview with Manufacturing and Enterprise Customers 7
Company Profile
Industry Medical institution Address Nguyen Chi Thanh, District 10
Interviewee Male Position Personal Manager
Establishment Over 50 years ago Total area Over 200m2 No of staff Over 300
Remarks 4 to 5 storied or over.
Condition of Electricity Use
Capacity Single phase (220V, 10-100A) and three phases (380V) (two lines)
Electricity consumption 19,363 kWh Monthly electricity bill 22,641,156 VND
Generator One generator
Main use Electricity is mainly spent for A/C and medical equipment (24 hrs). Also used for room
lights (12 hrs) and TV (8 hrs).
Mode of Billing EVN reads the meter and send the invoice
Mode of Payment Pay at EVN Office.
Power Outage Power outage occurs around noon up to 2 hours.
Opinions on Current Power Supply and Electricity Cost
Current power supply Sufficient
Current electricity cost Expensive (reason) Because we actually use the electricity a lot.
Current provided service Satisfied (reason) Because electricity is supplied for 24 hrs.
Willingness to pay more if the quality of EVN’s service becomes improved. Acceptable
Amount of willingness to pay if the quality of EVN’s service becomes improved.
Does not matter how much. Will pay as it requires.
Ideas on Smart Grid
Disconnecting only A/C Acceptable if it is within 30 minutes
Incentives for disconnecting A/C 10% discount
Opinion ―
Interview with Manufacturing and Enterprise Customers 8
Company Profile
Industry Service Address Lu Gia, Ward 15, District 10
Interviewee Male Position Organization Manager
Establishment 20 to 30 years ago Total area 50 to 100m2 No of staff Over 300
Remarks 3 storied.
Condition of Electricity Use
Capacity Single phase (220V, 10-100A)
Electricity consumption 13,972 kWh Monthly electricity bill 32,212,624 VND
Generator One generator
Main use Electricity is spent for A/C (8 hrs), room lights (12 hrs), and TV (8 hrs).
Mode of Billing EVN reads the meter and send the invoice
Mode of Payment Pay at EVN
Power Outage Power outage occurs during morning time up to 2 hours.
Opinions on Current Power Supply and Electricity Cost
Current power supply Sufficient
Current electricity cost Expensive (reason) Because we actually use the electricity a lot.
Current provided service Satisfied (reason) Because it is supplied for 24 hours.
Willingness to pay more if the quality of EVN’s service becomes improved. Acceptable
Amount of willingness to pay if the quality of EVN’s service becomes improved.
Like to pay more, but hope to pay 10% less.
Ideas on Smart Grid
Disconnecting only A/C Acceptable if it is 30 minutes
Incentives for disconnecting A/C 10% discount
Opinion ―
Interview with Manufacturing and Enterprise Customers 9
Company Profile
Industry Banking Address Ly Thuong Kiet, District 11
Interviewee Male Position Sales Manager
Establishment 2000 Total area 150 to 200m2 No of staff 50 to 100
Remarks Building has 4 or 5 stories, or even more.
Condition of Electricity Use
Capacity Single phase (220V, 10-100A)
Electricity consumption 218,691 kWh Monthly electricity bill 492,542,159VND
Generator One generator
Main use Electricity is mainly spent for A/C (12 hrs), room lights (16 hrs), TV (16 hrs), computer (24
hrs).
Mode of Billing EVN reads the meter and send the invoice
Mode of Payment Pay at EVN Office
Power Outage Power outage occurs during night time up to 2 hours.
Opinions on Current Power Supply and Electricity Cost
Current power supply Sufficient
Current electricity cost Expensive (reason) Because we actually use the electricity a lot.
Current provided service Satisfied (reason) Reasonable price
Willingness to pay more if the quality of EVN’s service becomes improved. Acceptable
Amount of willingness to pay if the quality of EVN’s service becomes improved.
―
Ideas on Smart Grid
Disconnecting only A/C Acceptable if it is 30 minutes.
Incentives for disconnecting A/C 10% discount
Opinion ―
Interview with Manufacturing and Enterprise Customers 10
Company Profile
Industry Retailer (supermarket) Address Dinh Nghe, District 11
Interviewee Male Position Receptionist
Establishment 2000 Total area Over 200m2 No of staff 100 to 300
Remarks Building has 3 stories
Condition of Electricity Use
Capacity Single phase (220V, 10-100A) and three phases (380V)
Electricity consumption 89,991 kWh Monthly electricity bill 166,123,386 VND
Generator One generator
Main use Spent for A/C (12 hrs), room lights (24 hrs), TV (6 hrs), and frozen case (24 hrs)
Mode of Billing EVN reads the meter and send the invoice
Mode of Payment Money transfer
Power Outage Power outage occurs around noon up to 2 hours.
Opinions on Current Power Supply and Electricity Cost
Current power supply Sufficient
Current electricity cost Expensive (reason) Because we have to pay the electricity bill anyway
even though there are power cuts or load shedding.
Current provided service Satisfied (reason) Because electricity is supplied for 24 hours.
Willingness to pay more if the quality of EVN’s service becomes improved. Acceptable
Amount of willingness to pay if the quality of EVN’s service becomes improved.
Like to pay more, but hope the price keeps current
amount.
Ideas on Smart Grid
Disconnecting only A/C Acceptable if it is 30 minutes
Incentives for disconnecting A/C 10% discount
Opinion ―
Interview with Manufacturing and Enterprise Customers 11
Company Profile
Industry Medical institution Address Su Van Hanh, District 10
Interviewee Male Position Organization Officer
Establishment Over 50 years ago Total area Over 200m2 No of staff 100 to 300
Remarks Building has 4 or 5 stories, or even more.
Condition of Electricity Use
Capacity Single phase (220V, 10-100A) and three phases (380V) (two lines)
Electricity consumption 275,520 kWh Monthly electricity bill 305,799,648 VND
Generator One generator
Main use Electricity is spent for A/C (12 hrs), room lights (18 hrs), and medical equipment (12hrs).
Mode of Billing EVN reads the meter and send the invoice
Mode of Payment Pay at EVN
Power Outage Power outage occurs around noon up to 2 hours.
Opinions on Current Power Supply and Electricity Cost
Current power supply Sufficient
Current electricity cost Expensive (reason) Because we have to pay the electricity bill anyway
even though there are power cuts or load shedding.
Current provided service Satisfied (reason) Because electricity is supplied for 24 hrs.
Willingness to pay more if the quality of EVN’s service becomes improved. Acceptable
Amount of willingness to pay if the quality of EVN’s service becomes improved. ―
Ideas on Smart Grid
Disconnecting only A/C Acceptable if it is around 30 minutes
Incentives for disconnecting A/C 10% discount
Opinion ―
Interview with Manufacturing and Enterprise Customers 12
Company Profile
Industry Telecommunication Address Thanh Thai, District 11
Interviewee Male Position Manager
Establishment 2000 Total area 150 to 200m2 No of staff 100 to 300
Remarks Building has 4 to 5 stories or even more.
Condition of Electricity Use
Capacity Single phase (220V, 10-100A) and three phases (380V) (two lines)
Electricity consumption 946,669 kWh Monthly electricity bill 1,915,449,349 VND
Generator One generator
Main use Electricity is spent for A/C (10 hrs) and room lights (24 hrs)
Mode of Billing EVN reads the meter and send the invoice
Mode of Payment Money transfer
Power Outage It occurs mostly in the afternoon up to 2 hours.
Opinions on Current Power Supply and Electricity Cost
Current power supply Sufficient
Current electricity cost Expensive (reason) Because we have to pay the electricity bill anyway even
though there are power cuts or load shedding.
Current provided service Satisfied (reason) Because electricity is supplied for 24 hours.
Willingness to pay more if the quality of EVN’s service becomes improved. Acceptable
Amount of willingness to pay if the quality of EVN’s service becomes improved. ―
Ideas on Smart Grid
Disconnecting only A/C Acceptable if it is 30 minutes
Incentives for disconnecting A/C 10% discount
Opinion ―
Interview with Manufacturing and Enterprise Customers 13
Company Profile
Industry Apparel (Garment export) Address Truong Son, Ward 15, District 10
Interviewee Male Position Administrative Manager
Establishment Over 30 to 40 years Total area Over 200m2 No of staff Over 300
Remarks Building has 3 stories.
Condition of Electricity Use
Capacity Single phase (220V, 10-100A and three phase (380V) (two lines)
Electricity consumption 284,846 kWh Monthly electricity bill 399,123,723 VND
Generator One generator
Main use Electricity is spent for A/C (6 hrs), room lights (16 hrs), and sewing machines (700 sets) for
16 hrs.
Mode of Billing EVN reads the meter and send the invoice
Mode of Payment Money transfer
Power Outage It occurs 6 to 8 hours.
Opinions on Current Power Supply and Electricity Cost
Current power supply Sufficient
Current electricity cost Expensive (reason) Because we have to pay the electricity bill anyway
even though there are power cuts or load shedding.
Current provided service Satisfied (reason) Because the quality of service is good.
Willingness to pay more if the quality of EVN’s service becomes improved. Acceptable
Amount of willingness to pay if the quality of EVN’s service becomes improved. ―
Ideas on Smart Grid
Disconnecting only A/C Acceptable
Incentives for disconnecting A/C ―
Opinion ―
Interview with Manufacturing and Enterprise Customers 14
Company Profile
Industry Retailer (supermarket) Address 3 Thang 2, District 10
Interviewee Male Position Administrative Officer
Establishment 1997 Total area Over 200m2 No of staff 100 to 300
Remarks Building has 3 stories
Condition of Electricity Use
Capacity Single phase (220V, 10-100A) and three phases (380V) (two lines)
Electricity consumption 537,273 kWh Monthly electricity bill 1,237,341,806 VND
Generator One generator (10,000 kVA)
Main use Electricity is spent for A/C and room lights
Mode of Billing EVN reads the meter and send the invoice
Mode of Payment Money transfer
Power Outage It occurs around noon.
Opinions on Current Power Supply and Electricity Cost
Current power supply Sufficient
Current electricity cost Expensive (reason) Because we actually use the electricity a lot.
Current provided service Satisfied (reason) Because the quality of service is good.
Willingness to pay more if the quality of EVN’s service becomes improved. Acceptable
Amount of willingness to pay if the quality of EVN’s service becomes improved. ―
Ideas on Smart Grid
Disconnecting only A/C Acceptable if it is 30 minutes
Incentives for disconnecting A/C 10% discount
Opinion ―
Interview with Manufacturing and Enterprise Customers 15
Company Profile
Industry Local government institution Address Binh Quoi, District 11
Interviewee Male Position Administrative Officer
Establishment 1975 Total area Over 200m2 No of staff 50 to 100
Remarks Building has 3 stories.
Condition of Electricity Use
Capacity Single phase (220V, 10-40A)
Electricity consumption 68,248 kWh Monthly electricity bill 90,612,870 VND
Generator None
Main use A/C (12 hrs) and room lights (24 hrs)
Mode of Billing EVN reads the meter and send the invoice
Mode of Payment Money transfer
Power Outage There is no power outage except repair works.
Opinions on Current Power Supply and Electricity Cost
Current power supply Sufficient
Current electricity cost Not expensive (reason) We pay as we use.
Current provided service Satisfied (reason) Because the quality of service is good.
Willingness to pay more if the quality of EVN’s service becomes improved. Acceptable
Amount of willingness to pay if the quality of EVN’s service becomes improved.
Does not matter how much. We will pay as required.
Ideas on Smart Grid
Disconnecting only A/C Acceptable if it is 30 minutes
Incentives for disconnecting A/C 10% discount
Opinion ―
Interview with Manufacturing and Enterprise Customers 16
Company Profile
Industry Medical institutions Address Ly Thuong Kiet, District 10 Establishment 1970
Interviewee Male Position Administrative Manager Total area 32,000m2
No of staff Over 1,000
Remarks 27 Depts such as internal, surgery, ophthalmology, obstetrical and gynecology. 700 beds and
1,500 out-patients per day. Staff work on 3 shifts for 8 hours. Day-time shift begins at 7AM
up to 4:30PM. Building has 5 stories.
Condition of Electricity Use
Capacity 15 kV line (3) and three phases transformer (2) (250kVA and 1,000kVA). Each building has
two meters.
Electricity consumption 200,000 kWh (invoiced Nov
2010) Monthly electricity bill
240,000,000 VND
Generator One generator with 550kVA capacity for emergency unit
Main use
A/C (Management dept 100 sets, emergency unit 200 sets, in-patient dept 150 sets, total 450
sets), room lights and equipment. There are 200 sets of TV mainly in the in-patient dept.
Management dept uses A/C 8 hrs a day, in-patient dept 8 to 12 hrs per day. They change air
from 5AM to 9AM by opening windows (during it A/C is off). Emergency unit use A/C for
24 hours.
Mode of Billing EVN reads the meter and
send the invoice Mode of Payment
Bank transfer (pay twice
monthly)
Power Outage Power distribution never stops as we have both ordinary line and back-up line except
repair works. Repair works are taken place during midnight.
Remarks The electricity cost is invoiced highest in June. It was 265,000,000 VND using 243,000 kWh
invoiced in June 2010 mainly due to the A/C use. The amount of electricity consumption keeps
increasing as we purchase new equipment every year.
Opinions on Current Power Supply and Electricity Cost
Current power supply Sufficient
Current electricity cost Not expensive (reason) Because we apply flat rate (1,009 VND per kWh).
Current provided service Satisfied (reason) Because the quality of service is good, 24 hours supply,
and we apply flat rate which is cheaper.
Willingness to pay more if the quality of EVN’s service becomes improved. Acceptable
Amount of willingness to pay if the quality of EVN’s service becomes improved. 20% increase
Ideas on Smart Grid
Disconnecting only A/C
Can do so at management dept. We however cannot accept it at out-patient dept and
emergency unit as patients pay the cost for our service.
Opinion One a week is okay. Prior notice as least one day advance is preferred.
Interview with Manufacturing and Enterprise Customers 17
Company Profile
Industry Travel agency Address Thanh Thai, Ward 14, District 10
Interviewee Male Position Manager
Establishment 2005 Total area 60m2 No of staff 5
Remarks Run the office on the ground floor of 4-storied residential building.
Condition of Electricity Use
Capacity Single phase (220V, 10-40A)
Electricity consumption 638 kWh (invoiced Oct
2010) Monthly electricity bill
941,239 VND (same
period)
Generator None
Main use A/C (10 hrs), room lights (8 hrs), PC (6 sets) (8 hrs), refrigerator (24 hrs). Also use fan
when necessary.
Mode of Billing EVN reads the meter and send the invoice
Mode of Payment Pay directly with EVN staff when they visit
Power
Outage
There is no scheduled power outage occurred except repair works because we live close to
the Ward 14 People’s Committee.
Opinions on Current Power Supply and Electricity Cost
Current power supply Sufficient
Current electricity cost Not expensive (reason) Because it is applied to everybody.
Current provided service Satisfied (reason) Because the quality of service is good.
Willingness to pay more if the quality of EVN’s service becomes improved. Acceptable
Amount of willingness to pay if the quality of EVN’s service becomes improved.
Like to pay more, but hope to keep the current
amount.
Ideas on Smart Grid
Disconnecting only A/C Acceptable if it is 1 hour
Incentives for disconnecting A/C 5% discount
Disconnecting all electricity supply Acceptable if it is 2 hours
Willing to stay disconnected or pay additionally to
recover the electricity immediately.
Choose to pay additionally if it is within
10% increase.
Opinion ―
Interview with Residential Customers 1
Identity of interviewee and living environment
Interviewee Male Address Ly Thuong Kiet, District 11
Age Born in 1931 Occupation Retired
No of person living Adult 11 (M 5, F 6) Child 7 (M 2, F 5) Total 18 (M 7, F 11)
Living period Over 50 No of story One story Total area 150 to 200 m2
No of those with jobs 6 Their occupations Salary taker, business
Condition of Electricity Use and Household Expenditures
Capacity 220V, 20A Mode of billing EVN reads the meter and send the invoice
Generator None Mode of payment Pay at EVN Office
Electricity consumption 2,500 kWh Monthly electricity bill 4,500,000 VND
Power outage Seldom to have Power outages. Within 2 hours if there is any.
Percentage of electricity cost among major household expenditures Approximately 25%
Owned electric appliances and length of use per day
A/C 3 pcs (2 to 3 hrs), room lights (3 hrs), refrigerator 2 pcs (24 hrs), TV 5
sets (1 to 2 hrs), table fan / ceiling fan 10 pcs (5 hrs). Also owns rice cooker,
mobile phone 12 sets and PC.
Other major household expenditures
Food (4.5 mil VND), health (3 mil VND), education (3 mil VND), water (0.12 mil
VND), gas (0.3 mil VND), home appliance (1.5 mil VND), land phone (0.6 mil VND),
and mobile phone (1.5 mil VND)
Opinions on Current Power Supply and Electricity Cost
Current power supply sufficient
Current electricity cost expensive (reason) Because we actually use the electricity a lot.
Current provided service satisfactory (reason) Because the quality of service is good.
Willingness to pay more if the quality of EVN’s service becomes improved. Acceptable
Amount of willingness to pay if the quality of EVN’s service becomes improved.
Within 4,500,000 VND. Hope the quality becomes
further improved, but do not like to pay more.
Ideas on Smart Grid
Disconnect only A/C Does not matter for 30 minutes or 1 hour.
Incentives for turning off A/C 10% discount from the current cost
Disconnect all electric appliances. Okay to do so for 1 to 2 hours.
Willing to stay disconnected or pay additionally to recover the electricity immediately.
Choose to stay connected. Cannot afford to
pay additionally.
Opinion
Cannot get disconnected as we need A/C during night time, and room lights and equipment
running during daytime. It is not convenient to get disconnected all electric appliances at
once. We may be able to choose to disconnect A/C only in order to use fan instead. We prefer
to have the Power outage from 2 to 4 in the morning.
Interview with Residential Customers 2
Identity of interviewee and living environment
Interviewee Male Address 3 Thang 2, Ward 15, District 11
Age Born in 1970 Occupation Retailer of medical equipment
No of person living Adult 10 (M 5, F 5) Child 3 (M 0, F 3) Total 13 (M 5, F 8)
Living period 40 to 50 years No of story 1 Total area 100 to 150 m2
No of those with jobs 6 Their occupations Salary takers, business
Condition of Electricity Use and Household Expenditures
Capacity 220V, 10-40A Mode of billing EVN reads the meter and send the invoice
Generator None Mode of payment Pay directly with EVN staff when they visit
Electricity consumption 1,500 kWh Monthly electricity bill 3,000,000 VND
Power outage Seldom to have Power outage
Percentage of electricity cost among major household expenditures Approximately 20%
Owned electric appliances and length of use per day
A/C 4 pcs (5 hrs), room light (4 hrs), refrigerator 2 pcs (24 hrs), TV 5 sets (3
hrs), and fan (2 to 4 hrs). Also owns rice cooker, DVD player, iron, mobile
phone 12 sets, and PC.
Other major household expenditures
Food (4.5 mil VND), education (6 mil VND), water (0.2 mil VND), gas (0.5 mil
VND), home appliance (0.3 mil VND), land phone (0.3 mil VND), and mobile
phone (1.2 mil VND)
Opinions on Current Power Supply and Electricity Cost
Current power supply sufficient
Current electricity cost Not expensive (reason) Because we pay as the Government decides.
Current provided service satisfied (reason) Because the quality of service is good, and they supply
electricity for 24 hours.
Willingness to pay more if the quality of EVN’s service becomes improved. Acceptable
Amount of willingness to pay if the quality of EVN’s service becomes improved.
Does not matter to pay as the Government requires us to
pay.
Ideas on Smart Grid
Disconnect only A/C Does not matter for 30 minutes to 1 hour.
Incentives for turning off A/C 10% discount
Disconnect all electric appliances. Total disconnection is not acceptable, but 30 minutes may be
okay. We will follow if EVN decides so.
Willing to stay disconnected or pay
additionally to recover the electricity
immediately.
Choose to pay additionally (up to 10%) rather
than staying disconnected.
Opinion Cannot afford to pay additionally over 10%.
Interview with Residential Customers 3
Identity of interviewee and living environment
Interviewee Male Address Ly Thuong Kiet, District 10
Age Born in 1963 Occupation CEO
No of person living Adult 6 (M 4, F 2) Child 1 (M 1, F 0) Total 7 (M 5, F 2)
Living period 65 years since his parents moved
to the current place No of story 1 Total area 42 m2
No of those with jobs 6 Their occupations Salary taker, small-scale business
Condition of Electricity Use and Household Expenditures
Capacity 220V, 10-40A Mode of billing EVN reads the meter and send the invoice
Generator Yes (2 horse
power) Mode of payment
Pay directly with EVN staff when they visit or pay
at EVN office.
Electricity consumption
463 kWh (invoiced for Sep 2010) Monthly electricity bill
766,000 VND (invoiced for Sep
2010)
Power outage Scheduled power cut lasted from 7 AM to 6 PM twice a week during dry season (prior
notice was sent). Otherwise all-of-a-sudden power outage lasts within two hours.
Percentage of electricity cost among major household expenditures Approximately 7%
Owned electric appliances and length of use per day
A/C (3 to 4 hrs), room lights (night time), refrigerator (24 hrs), TV 2 sets (3 to 4
hrs), fan (12 hrs). Also own rice cooker, DVD player, radio, iron, mobile phone
(5 sets) and PC (1).
Other major household expenditures
Food (3 mil VND), health (3 mil VND), education (2.5 mil VND), water (0.2
mil VND), gas (0.27 VND), land phone (0.7 to 0.8 mil VND), mobile phone (0.7
to 0.8 mil VND)
Opinions on Current Power Supply and Electricity Cost
Current power supply Sufficient
Current electricity cost Not expensive (reason) Because we actually do not use electricity much.
Current provided service
Both satisfied and not
satisfied
(reason) Because there are many Power outages during
dry season. Otherwise satisfied.
Willingness to pay more if the quality of EVN’s service becomes improved. Acceptable
Amount of willingness to pay if the quality of EVN’s service becomes improved.
Around 1 mil VND
Ideas on Smart Grid
Disconnect only A/C Does not matter if it is around 1 hour.
Incentives for turning off A/C Not necessary
Opinion Do not want A/C disconnected if possible.
Interview with Residential Customers 4
Identity of interviewee and living environment
Interviewee Female Address Ly Thuong Kiet, Ward 14, District 10
Age Born in 1953 Occupation House work
No of person living Adult 5 (M 2, F 3) Child 0 (M 0, F 0) Total 5 (M 2, F 3)
Living period 35 years No of story 4 Total area 330 m2
No of those with jobs 4 Their occupations Salary taker, business
Condition of Electricity Use and Household Expenditures
Capacity 220V, 10-40A Mode of billing EVN reads the meter and send the invoice
Generator None Mode of payment Pay directly with EVN staff when they visit
Electricity consumption
800kWh (invoiced in Sep
2010)
Monthly electricity bill
1,500,000 VND (invoiced in Sep
2010)
Power outage All-of-a-sudden power outage does not happen often. It is within 2 hours during night
time (11 PM to 12 AM) if any.
Percentage of electricity cost among major household expenditures
Less than 20% (approximately)
Owned electric appliances and length of use per day
A/C 3 pcs (10 hrs from 8PM to 6AM), room lights (5 hrs from 6PM to 11
PM), refrigerator 3 pcs (24 hrs), TV 3 sets (4 hrs), fan 3 pcs (all day long).
Also own rice cooker, DVD player, iron, dryer, mobile phone 5 sets, and PC
1 set.
Other major household expenditures
Food (3 to 4 mil VND), health (2 mil VND), water (0.3 VND), gas (0.29
VND), land phone (50,000 VND), and mobile phone (0.5 VND)
Opinions on Current Power Supply and Electricity Cost
Current power supply Sufficient
Current electricity cost Expensive (reason) Because it becomes more expensive as we use
electricity.
Current provided service Satisfied (reason) Satisfied as long as there is no power outage.
Willingness to pay more if the quality of EVN’s service becomes improved. Not acceptable
Amount of willingness to pay if the quality of EVN’s service becomes improved.
Around 1mil VND
Ideas on Smart Grid
Disconnect only A/C Does not matter for 30 minutes.
Incentives for turning off A/C 10% discount. Maximum 1 mil VND
Disconnect all electric appliances. Can accept if it is around 30 minutes.
Willing to stay disconnected or pay additionally to recover the electricity immediately.
Does not like to pay additionally. Would choose
to have all electricity disconnected.
Opinion Does not want to have power cut every day. Can accept if it is once a week or month. Would
like to receive prior notice one week advance. May consider if the amount of additional
payment is feasible but would like to keep it as the current amount.
Interview with Residential Customers 5
Identity of interviewee and living environment
Interviewee Female Address 3 Thang 2, Ward 14, District 10
Age Born in 1936 Occupation Retired
No of person living Adult 4 (M 2, F 2) Child 2 (M 1, F 1) Total 6 (M 3, F 3)
Living period 34 years No of story 2 Total area 150~200 m2
No of those with jobs 2 Their occupations Teacher, engineer
Condition of Electricity Use and Household Expenditures
Capacity 220V, 10-40A Mode of billing EVN reads the meter and send the invoice
Generator None Mode of payment Pay directly with EVN staff when they visit
Electricity consumption
374 kWh (invoiced Sep 2010) Monthly electricity bill
440,000 VND (invoiced Sep 2010)
Power outage It lasted 8AM to 5PM once a week during dry season. It does not happen during rainy
season.
Percentage of electricity cost among major household expenditures -
Owned electric appliances and length of use per day
A/C 1 pc (seldom use), room lights (5 hrs from 6 PM to 11 PM), refrigerator 1
pc (24 hrs), TV (10 hrs), fan (all day long). Also own rice cooker, microwave,
ceiling fan, DVD player, radio, iron, dryer, sewing machine, mobile phones (4
sets), PC (1 set) and electric cooker.
Other major household expenditures
Water (0.2 mil VND), gas (0.15 mil VND), land phone and internet (0.3
mil VND), and mobile phone (0.4 mil VND)
Opinions on Current Power Supply and Electricity Cost
Current power supply Sufficient
Current electricity cost Not expensive (reason) as it was decided by the Government.
Current provided service Satisfied (reason) Power outage seldom happens. EVN staff come
immediately once we call them.
Willingness to pay more if the quality of EVN’s service becomes improved. Depends
Amount of willingness to pay if the quality of EVN’s service becomes improved.
No idea. Cheaper is better.
Ideas on Smart Grid
Disconnect only A/C Not acceptable
Incentives for turning off A/C -
Opinion Would like to enjoy high living standard without any power outage.
Disconnect all electric appliances.
It is not acceptable, but it does not matter as the house has a good ventilation
system.
Willing to stay disconnected or pay additionally to recover the electricity immediately.
Choose to have all disconnected instead of
paying additionally.
Opinion Although there are prior notices on newspapers at least 2 days in advance when EVN
conducts power cut (load shedding, repair works), it does not happen as it says. Do not like
to have any power cut.
Interview with Residential Customers 6
Identity of interviewee and living environment
Interviewee Male Address 3 Thang 2, Ward 14, District 10
Age Born in 1968 Occupation Self employed
No of person living Adult 7(M 4, F 3) Child 3 (M 1, F 2) Total 10 (M 5, F 5)
Living period 12 years No of story 5 Total area 184 m2
No of those with jobs 7 Their occupations Teacher, banker, tailor
Condition of Electricity Use and Household Expenditures
Capacity 220V, 10-40A Mode of billing EVN reads the meter and send the invoice
Generator None Mode of payment Pay directly with EVN staff when they visit, or pay at
EVN Office.
Electricity consumption 300 kWh Monthly electricity bill 250,000~300,000 VND
Power outage
It accidentally occurs occasionally, which lasts only 10 to 30 minutes. There is no regular
time
Percentage of electricity cost among major household expenditures Approximately 2%
Owned electric appliances and length of use per day
Room lights (5 hrs), refrigerator (24 hrs), TV (12 hrs), fan (12 hrs). Also own
rice cooker, ceiling fan, DVD player, iron sewing machine, mobile phone (10
sets), computer, and electric cooker
Other major household expenditures
Food (9 mil VND), education (5 mil VND), water (0.45 VND), gas
(268,000 VND) and mobile phone (2 mil VND)
Reason not to have A/C
Would like to purchase one, but we cannot afford to buy one as it costs 5 mil
VND or over.
Opinions on Current Power Supply and Electricity Cost
Current power supply Sufficient
Current electricity cost Expensive (reason) Would like to make it for free.
Current provided service Fair (reason) Not good, not bad
Willingness to pay more if the quality of EVN’s service becomes improved Acceptable
Amount of willingness to pay if the quality of EVN’s service
becomes improved. As the quality improves.
Ideas on Smart Grid
Disconnect only A/C Acceptable for 30 minutes or 1 hour.
Incentives for turning off A/C Cannot think of.
Disconnect all electric appliances. Depends on EVN. Will accept if neighbors do the same.
Willing to stay disconnected or pay additionally to recover the
electricity immediately. Cannot choose one.
Opinion Cannot resist if the Government decides. Will accept to pay additionally if neighbors do the
same. Have no idea about the frequency of the disconnection.
Interview with Residential Customers 7
Identity of interviewee and living environment
Interviewee Female Address 3 Thang 2, Ward 14, District 10
Age Born in 1971 Occupation Merchant
No of person living Adult 7(M 4, F 3) Child 3 (M 1, F 2) Total 10 (M 5, F 5)
Living period 17 to 18 years No of story 4 Total area Over 200 m2
No of those with jobs 6 Their occupations Driver, university student
Condition of Electricity Use and Household Expenditures
Capacity 220V, 10-40A Mode of billing EVN reads the meter and send the invoice
Generator None Mode of payment Pay directly with EVN staff when they visit
Electricity consumption 660 kWh Monthly electricity bill 1,200,000 VND
Power outage
Scheduled power outage lasts from 9AM to 4PM once a week with prior notice.
Unscheduled one happens occasionally lasting within 2 hours.
Percentage of electricity cost among major household expenditures ―
Owned electric appliances and length of use per day
A/C (3 hrs), room lights (5 hrs, from 6PM to 11PM), refrigerator 1 pc (24 hrs),
TV 2 sets (5 to 6 hrs), fan (5 to 6 hrs). Also own rice cooker, toaster, DVD
player, iron and mobile phones (4 sets)
Other major household expenditures
Land phones (100,000 VND), mobile phones (300,000 VND)
(No information on other expenditures)
Opinions on Current Power Supply and Electricity Cost
Current power supply Sufficient
Current electricity cost Expensive (reason) would like to keep within current cost.
Current provided service Satisfied (reason) Because the quality of service is good. It can be
further improved.
Willingness to pay more if the quality of EVN’s service becomes improved. Not acceptable
Amount of willingness to pay if the quality of EVN’s service becomes improved.
Would like to keep the current
cost.
Ideas on Smart Grid
Disconnect only A/C Acceptable for 30 minutes or 1 hour.
Incentives for turning off A/C Will follow as neighbors do.
Disconnect all electric appliances. Acceptable if it occurs occasionally about 30 minutes
Willing to stay disconnected or pay additionally to recover the electricity immediately.
Will follow if neighbors pay additionally, but it is not so
acceptable. Choose to have disconnection
Opinion Prefer to have power outage during night time. Hope it will not occur quite often.
Interview with Residential Customers 8
Identity of interviewee and living environment
Interviewee Female Address 3 Thang 2, Ward 14, District 10
Age Born in 1965 Occupation Stock dealer
No of person living Adult 18 (M 9, F 9) Child 0 (M 0, F 0) Child 18 (M 9, F 9)
Living period 10 years No of story 5 Total area 500 m2
No of those with jobs 18 Their occupations Laborer, company employee
(remarks) Apart from 6 family members, 12 people rent rooms in the house. It cost 3.5 mil VND with water, gas and
electricity cost inclusive, or 2 mil VND without.
Condition of Electricity Use and Household Expenditures
Capacity 220V, 20-80A
380V, 10-40V Mode of billing EVN reads the meter and send the invoice
Generator None Mode of payment Pay at EVN Office.
Electricity consumption
3,237 kWh (1,067 + 2,170)
invoiced Sep 2010.
Monthly electricity bill
5,100,000 VND (1.8 mil + 3.3 mil)
invoiced Sep 2010.
Power outage
It occurs twice a week during dry season. Unscheduled power outage does not occur.
There has been no power outage in September.
Percentage of electricity cost among major household expenditures -
Owned electric appliances and length of use per day
A/C 18 pcs (10 hrs), room lights (24 hrs), refrigerator 4 pcs (24 hrs), TV 18 sets (5
hrs), fan (24 hrs). Also own rice cooker, microwave, ceiling fan, DVD player, iron
(5 to 6 sets), mobile phones (18 sets), and computer (18 sets).
Other major household expenditures
Water (0.7 VND), gas (0.3 VND), home appliance (0.5 VND), land phone (35,000
VND), mobile phone (1 mil VND). No information on other expenditures.
Opinions on Current Power Supply and Electricity Cost
Current power supply Sufficient Because one phase and three phase are both installed.
Current electricity cost Expensive
(reason) It cost around 5.5 mil VND in rainy season, whereas it
costs 10 mil VND in dry season. I think it would cost less if we
try to save energy.
Current provided service Satisfied (reason) because there is no breakdown of electric appliance.
Willingness to pay more if the quality of EVN’s service becomes improved Acceptable
Amount of willingness to pay if the quality of EVN’s service becomes improved.
Will follow the amount neighbors agree.
Would like to prioritize safety.
Ideas on Smart Grid
Disconnect only A/C Not acceptable
Incentives for turning off A/C N/A
Disconnect all electric appliances. Not acceptable
Willing to stay disconnected or pay additionally to recover the electricity immediately.
Will choose to pay additionally (up to 10%).
Interview with Residential Customers 9
Identity of interviewee and living environment
Interviewee Male Address 3 Thang 2, Ward 14, District 10
Age Born in 1980 Occupation Own a company (CEO of construction and architecture
company)
No of person living Adult 2 (M 1, F 1) Child 1 (M 1, F 0) Total 3 (M 2, F 1)
Living period 1 No of story 4 Total area 350 m2
No of those with jobs 1 Their occupations Own a company
Condition of Electricity Use and Household Expenditures
Capacity 220V, 10-40A Mode of billing EVN reads the meter and send the invoice
Generator None Mode of payment Pay directly with EVN staff when they visit
Electricity consumption 400 kWh Monthly electricity bill 700,000 VND
Power outage
Scheduled power outages occur twice a week during dry season. Unscheduled outage
occurs lasting within 2 hours. We obtain prior notice through TV and internet.
Percentage of electricity cost among major household expenditures ―
Owned electric appliances and length of use per day
A/C 2 pcs (8 hrs), room light (15 hrs), refrigerator (24 hrs), TV (4 hrs), fan
(4 hrs). Also own rice cooker, microwave, DVD player, iron, mobile phone
(2 sets) and computer (4 sets).
Other major household expenditures
Water (0.2 million VND), land phone (0.1 mil VND), mobile phone (1. 4mil
VND). No information on other expenditures.
Opinions on Current Power Supply and Electricity Cost
Current power supply Sufficient
Current electricity cost Not expensive (reason) Does not matter as the tariff is applied equally to
others.
Current provided service Satisfied (reason) because there is no specific problems.
Willingness to pay more if the quality of EVN’s service becomes improved. Not acceptable
Amount of willingness to pay if the quality of EVN’s service becomes improved.
It is better to enjoy the improved service, but we are not
willing to pay more.
Ideas on Smart Grid
Disconnect only A/C Not acceptable
Incentives for turning off A/C N/A
Opinion Very annoyed by noise and dust when keeping open the door and windows. It is not
comfortable and it becomes hot without A/C
Disconnect all electric appliances. Not acceptable
Willing to stay disconnected or pay additionally to recover the electricity immediately.
Choose to pay additionally if the new price is generally
acceptable. As we run a company here, we would like to use
electricity during working hour.
Interview with Residential Customers 10
Identity of interviewee and living environment
Interviewee Male Address 3 Thang 2, Ward 14, District 10
Age Born in 1963 Occupation Business
No of person living Adult 2 (M 1, F 1) Child 2 (M 1, F 1) Total 4 (M 2, F 2)
Living period 30 to 40 years No of story 2 Total area 100~150 m2
No of those with jobs 1 Their occupations business
Condition of Electricity Use and Household Expenditures
Capacity 220V, 10-40A Mode of billing EVN reads the meter and send the invoice
Generator None Mode of payment Pay directly with EVN staff when they visit or transfer
money.
Electricity consumption 500~600 kWh Monthly electricity bill 1,000,000 VND
Power outage Scheduled power outage occurs twice a week during dry season. Unscheduled power
outages during rainy season last about 2 hours (irregular occurrence)
Percentage of electricity cost among major household expenditures Approximately 6%
Owned electric appliances and length of use per day
A/C 3 pcs (9 hrs from 9 PM to 6 AM), room lights (4 hrs from 6PM to 10PM),
refrigerator 1 pc (24 hrs), TV 2 sets (3 hrs from 7PM to 10PM), fan (1 to 2 hrs),
ceiling fan (10 hrs). Also own rice cooker, microwave, DVD player, iron, dryer,
sewing machine, mobile phones (4 sets), and electric water heater.
Other major household expenditures
Food (0.6 mil VND), education (0.8 mil VND), water (0.1 mil VND), gas (0.1 mil
VND), land phone (0.1 to 0.15 mil VND), mobile phone (0.5 mil VND)
Opinions on Current Power Supply and Electricity Cost
Current power supply Sufficient
Current electricity cost Expensive (reason) Electricity bill costs high compared with the income
level.
Current provided service Satisfied (reason) EVN tries to keep improving service.
Willingness to pay more if the quality of EVN’s service becomes improved. Not acceptable
Amount of willingness to pay if the quality of EVN’s service becomes improved.
Would like to keep the
current cost.
Ideas on Smart Grid
Disconnect only A/C Acceptable if it is 30 minutes.
Incentives for turning off A/C ―
Opinion We cannot sleep if A/C stops during night time. Hope the power outage does not happen
every day.
Disconnect all electric appliances. Would like to use at least one of electric appliances.
Willing to stay disconnected or pay additionally to recover the electricity immediately.
Choose to pay additionally if it is up to
10%.
Opinion We are used to have power outage once a week because it actually occurred during dry
season. Would like to have less if possible. 4 hours power cut is acceptable if it is during day
time.
Interview with Residential Customers 11
Identity of interviewee and living environment
Interviewee Female Address Ba Vi, Bac Hai Building, Ward 15, District 10
Age Born in 1978 Occupation Company employee
No of person living Adult 6 (M 3, F 3) Child 3 (M 2, F 1) Total 9 (M 5, F 4)
Living period 4 No of story 2 Total area 50~100 m2
No of those with jobs 4 Their occupations Salary taker
Condition of Electricity Use and Household Expenditures
Capacity 220V, 10-20A Mode of billing EVN reads the meter and send the invoice
Generator None Mode of payment Pay directly with EVN staff when they visit
Electricity consumption 800 kWh Monthly electricity bill 1,200,000 VND
Power outage Occasionally occurs and lasts within 2 hours. In the morning time.
Percentage of electricity cost among major household expenditures Less than 10%
Owned electric appliances and length of use per day
A/C 2 sets (4 hrs from 1AM to 4PM), room lights (6 hrs), refrigerator 1 pc (24
hrs), TV (3 hrs), fan (4 hrs). Also own rice cooker, microwave, DVD player,
iron, mobile phone and PC.
Other major household expenditures
Food (3 mil VND), health (2 mil VND), education (3 mil VND), water (0.4 mil
VND), gas (0.5 mil VND), home appliance (0.6 mil VND), land phone (1 mil
VND), mobile phone (1 mil VND)
Opinions on Current Power Supply and Electricity Cost
Current power supply Sufficient
Current electricity cost Expensive (reason) electricity costs more than other facilities (gas and
water).
Current provided service Satisfied (reason) Because the quality of service is high, and electricity is
supplied 24 hours a day.
Willingness to pay more if the quality of EVN’s service becomes improved. Acceptable
Amount of willingness to pay if the quality of EVN’s service becomes improved.
―
Ideas on Smart Grid
Disconnect only A/C Not acceptable
Incentives for turning off A/C 10% discount
Interview with Residential Customers 12
Identity of interviewee and living environment
Interviewee Female Address Thanh Thai, Ward 14, District 10
Age Born in 1970 Occupation Company employee
No of person living Adult 5 (M 2, F 3) Child 1 (M 0, F 1) Total 6 (M 2, F 4)
Living period 20 to 30 years No of story 3 Total area 50~100 m2
No of those with jobs 3 Their occupations Salary taker
Condition of Electricity Use and Household Expenditures
Capacity 220V, 10-20A Mode of billing EVN reads the meter and send the invoice
Generator None Mode of payment Pay directly with EVN staff when they visit
Electricity consumption 300 kWh Monthly electricity bill 500,000 VND
Power outage Occasionally occurs.
Percentage of electricity cost among major household expenditures Approximately 8%
Owned electric appliances and length of use per day
A/C 2 sets (4 hrs), room lights (4 hrs), refrigerator 2 pcs (24 hrs), TV (4 hrs), fan
(5 hrs). Also owns rice cooker, microwave, DVD player, radio, iron, mobile
phone (4 sets), PC, electric water heater and blender.
Other major household expenditures
Food (3 mil VND), education (1.5 mil VND), gas (0.5 mil VND), land phone
(0.1 mil VND), mobile phone (0.6 mil VND)
Opinions on Current Power Supply and Electricity Cost
Current power supply Sufficient
Current electricity cost Expensive (reason) tariff is too high.
Current provided service Not satisfied (reason) tariff is too high.
Willingness to pay more if the quality of EVN’s service becomes improved. Acceptable
Amount of willingness to pay if the quality of EVN’s service becomes improved.
Around 500,000 VND (current
level)
Ideas on Smart Grid
Disconnect only A/C Acceptable
Incentives for turning off A/C ―
Opinion Does not want to stop A/C as we often use it.
Interview with Residential Customers 13
Identity of interviewee and living environment
Interviewee Female Address 9 Thang 2, Ward 8, District 11
Age Born in 1943 Occupation Retired / housework
No of person living Adult 4 (M 2, F 2) Child 2 (M 2, F 0) Total 6 (M 4, F 2)
Living period 20 years No of story 3 Total area 180 m2
No of those with jobs 2 Their occupations Foreign company employee
Condition of Electricity Use and Household Expenditures
Capacity 220V, 10-40A Mode of billing EVN reads the meter and send the invoice
Generator None Mode of payment Pay directly with EVN staff when they visit
Electricity consumption 460 kWh Monthly electricity bill 750,000 VND
Power outage
Scheduled power outage occurs once a week for a whole day during dry season. It
occasionally and irregularly occurs during rainy season for two hours.
Percentage of electricity cost among major household expenditures Approximately 6%
Owned electric appliances and length of use per day
A/C 2 pcs (7 hrs from 10PM to 5AM), room lights (4 hrs from 6PM to 10 PM),
refrigerator 1 set (24 hrs), TV 3 sets (4 hrs), fan (7 to 8 hrs). Also own rice
cooker, ceiling fan, DVD player, iron, mobile phone (2 sets) and PC.
Other major household expenditures
Food (8 mil VND), health (1 mil VND), education (1 mil VND), water (0.2 mil
VND), gas (0.3 mil VND), home appliance (0.2 mil VND). Land phone
(100,000 VND), fuel (600,000 VND)
Opinions on Current Power Supply and Electricity Cost
Current power supply Sufficient
Current electricity cost Expensive
(reason) We have to pay any way like neighbors do, although
there is power outage, and it becomes more expensive as we
consume.
Current provided service ― (reason) no special idea. Follow as neighbors do.
Willingness to pay more if the quality of EVN’s service becomes improved. As neighbors do.
Amount of willingness to pay if the quality of EVN’s service becomes improved.
Better to pay less.
Ideas on Smart Grid
Disconnect only A/C Acceptable if it is 30 minutes.
Incentives for turning off A/C N/A
Opinion There is no big deal as we use A/C only during night time. We do not think the
Government discounts the electricity tariff.
Disconnect all electric appliances. Acceptable if it is 1 to 2 hrs.
Willing to stay disconnected or pay additionally to recover the electricity immediately.
Choose to pay additionally 5% if neighbors also do.
Interview with Residential Customers 14
Identity of interviewee and living environment
Interviewee Male Address Thanh Thai, Ward 14, District 10
Age Born in 1936 Occupation Grocery shop owner
No of person living Adult 6 (M 3, F 3) Child 0 (M 0, F 0) Total 6 (M 3, F 3)
Living period 40 years No of story 1 Total area 120 m2
No of those with jobs 3 Their occupations Teacher, grocery shop owner (2)
Condition of Electricity Use and Household Expenditures
Capacity 220V, 10-40A Mode of billing EVN reads the meter and send the invoice
Generator None Mode of payment Pay directly with EVN staff when they visit
Electricity consumption 892 kWh (invoiced Nov
2010)
Monthly electricity bill
1,500,000 VND (invoiced Nov
2010)
Power outage
There are scheduled shortages once a week from 7AM to 5PM during dry season.
Percentage of electricity cost among major household expenditures Approximately 14%
Owned electric appliances and length of use per day
A/C 1 pc (11 hrs from 5PM to 4AM), room lights (4 hrs from 6PM to 10PM),
refrigerator 2 pcs (24 hrs), TV 5 sets (out of which 2 sets for a whole day), fan 5 pcs
(8 hrs). Also own rice cooker, DVD player, radio (3 sets), iron (2 sets), dryer (2 pcs),
mobile phone (3 sets), electric water heater.
Other major household expenditures
Food (4.5 mil VND), gas (0.1 mil VND), home appliance (0.2 mil VND), land
phone(30,000~40,000 VND), mobile phone (0.3 mil VND), fuel (0.3 mil VND).
Water is free as well water is used.
Opinions on Current Power Supply and Electricity Cost
Current power supply Sufficient
Current electricity cost Not expensive (reason) no problem as we are rich.
Current provided service
Satisfied / not
satisfied
(reason) Satisfied, but we would like to enjoy stable power
supply without any power shortage or power outage.
Willingness to pay more if the quality of EVN’s service becomes improved. Acceptable
Amount of willingness to pay if the quality of EVN’s service becomes improved.
Up to 3,000,000 VND
Ideas on Smart Grid
Disconnect only A/C Not acceptable
Incentives for turning off A/C ―
Opinion Not good for health. Will purchase a generator if they disconnect A/C.
Disconnect all electric appliances. Not acceptable
Willing to stay disconnected or pay additionally to
recover the electricity immediately. Choose to pay additionally up to 20%.
Opinion Not good for health. Will purchase a generator if they disconnect A/C.
Interview with Residential Customers 15
Identity of interviewee and living environment
Interviewee Female Address Ly Thai To, District 10
Age Born in 1963 Occupation House work
No of person living Adult 3 (M 1, F 2) Child 0 (M 0, F 0) Total 3 (M 1, F 2)
Living period 56 years since parents
moved. No of story 3 and roof top Total area 300 m2
No of those with jobs 1 Their occupations driver
Condition of Electricity Use and Household Expenditures
Capacity 220V, 10-40A Mode of billing EVN reads the meter and send the invoice
Generator None Mode of payment Transfer money through post office.
Electricity consumption
933 kWh (invoiced Oct 2010)
464 kWh (invoiced Nov 2010) Monthly electricity bill
1,743,027 VND (invoiced Oct 2010)
767,976 VND (invoiced Nov 2010)
Power outage
Scheduled power outage occurs once a week during dry season. Repair works and all of a sudden
power outage occurs irregularly during rainy season lasting within 2 hrs.
Percentage of electricity cost among major household expenditures Approximately 6%
Owned electric appliances and length of use per day
A/C 3 pcs (11 hrs from 8PM to 7AM), room lights (6 hrs from 6PM to 12AM),
refrigerator (24 hrs), TV 3 sets (a few hours), fan 2 pcs (all day long). Also
owns rice cooker, microwave, DVD player (2 sets), radio (2 sets), iron (2 pc),
dryer (2 pcs), mobile phone (3 sets) and PC.
Other major household expenditures
Food (4 mil VND), education (3 to 4 mil VND), water (0.3 mil VND), gas (0.1
mil VND), home appliance (0.6 mil VND), land phone (384,689 VND), mobile
phone (1 mil VND), fuel (0.6 mil VND)
Opinions on Current Power Supply and Electricity Cost
Current power supply Sufficient
Current electricity cost Expensive (reason) Because we use a lot of electricity.
Current provided service Satisfied (reason) Convenient. No trouble.
Willingness to pay more if the quality of EVN’s service becomes improved. ―
Amount of willingness to pay if the quality of EVN’s service becomes improved.
Follow as neighbors do.
Ideas on Smart Grid
Disconnect only A/C Acceptable if it is 30 minutes.
Incentives for turning off A/C 10% discount
Disconnect all electric appliances. Not acceptable
Willing to stay disconnected or pay additionally to recover the electricity immediately.
Choose to pay additionally if it is within an
increase of 100,000~200,000 VND.
Opinion Do not want to have power outage during evening time as preparation for dinner requires
electricity. Additional payment should be as low as possible.