FCSL2000 Series - INSTALLATION INSTRUCTIONS
CAUTION: BEFORE CONNECTING THE FIXTURE TO A POWER SUPPLY, MAKE SURE THE POWER IS SWITCHED OFF.
DETAILED ILLUSTRATIONSTUD WALL INSTALLATION corporatet 800.900.1730f 630.889.8106 3609 Swenson Ave. St. Charles, IL 60174
2458893
GENERAL:1. Before starting the installation, make sure all electricity has
been turned off and electrical breaker has been locked out and tagged out.
2. To ensure the success of the installation, be sure to read these instructions and review the diagrams thoroughly before beginning.
3. All electrical connections must be in accordance with local codes, ordinances, or the National Electrical Code.
NOTE: The important safeguards and instructions appearing in this manual are not meant to cover all possible conditions and situations that may occur.
IMPORTANT: Temporarily remove Splatter Shield and contents from Back Box housing and set aside.
1. Install Drywall Mounting Brackets onto Back Box using 6-32 screws provided. Orient Back Box as shown. Fig 1
2. Adjust brackets to align front face of backbox flush to face of finished wall surface. Then fasten brackets to studs. Fig 2
3. Orient Back Box housing as shown to attach conduit. Connect conduit to backbox using 3/4” K.O.s. Fig 3
4. Optional Hanger Bar Brackets can be used to hang the Back Box between studs or braces to complete installation. Fig 4
6. Reinstall Splatter Shield and all contents using the (2) 8-32 screws provided. Fig 5
IMPORTANT: All wiring connections must be made in accordance with local electrical codes, ordinances, and the National Electric Code.
STUD
Back Box
Adjustable Back BoxPosition In / Out
DrywallMounting Brackets
Back Box
Adjustment Slots
6-32 screwsprovided
Align to face of finished wall
Fig 1
Fig 2
Back Box Conduit Entry____
Foam Block Insert toRetain Back Box Form
Splatter Shield
Wing Nuts
Threaded Rod
SL2000 SeriesUniversal Back Box
Concrete Pour Form(by others)
(4) 3/4” Knockouts - (2) on back and (1) on each side
Fig 3
Back Box Splatter Shield____
8-32 screws provided
BACKBOX
STUD
MOUNTING BRACKETS
Figure 2 (stud wall)
MOUNTING BRACKETS
BACKBOX
ADJUSTMENT SLOTS
Figure 1 (stud wall)
Figure 3 (stud wall)
SPLATTER GUARD
SL 2000 series backbox installation in hollow (stud) wall construction (2” x 4” min.): 1. Install the (2) slotted mounting brackets provided as shown in Figure 1, using the (4) 6-32 screws provided. 2. Adjust the brackets (by loosening the screws) so that the front face of the backbox will be flush or slightly in front of the finished wall surface after installation (see Figure 2). 3. Orient fixture housing electrical connections as directed on inisde label. Failure to do so will result in faceplate not installed in the correct oreintation (critical STEP for SL2003, SL2040, and SL2041 models). 4. Secure the mounting brackets to wood or metal studs (hardware by others) so that the front face of the back box will be flush or slightly in front of the finished wall surface after installation (see Figure 2). 5. Connect conduit to backbox using 3/4” NPT fittings. Pull wires into back housing for electrical connections to be made later. 6. Install splatter guard provided as shown in Figure 3, using the (2) 8-32 screws provided securely and finish wall. 7. Before continuing, remove splatter guard and debris from backbox to allow for proper fitment.
SL 2000 SERIES STUD WALL INSTALLATION
FILE NAME: SL 2000 SERIES INSTALLATION INSTRUCTIONS.SLDDRW
Foam Block Insert toRetain Back Box Form
Splatter Shield
Wing Nuts
Threaded Rod
SL2000 SeriesUniversal Back Box
Concrete Pour Form(by others)
BACKBOX
STUD
MOUNTING BRACKETS
Figure 2 (stud wall)
MOUNTING BRACKETS
BACKBOX
ADJUSTMENT SLOTS
Figure 1 (stud wall)
Figure 3 (stud wall)
SPLATTER GUARD
SL 2000 series backbox installation in hollow (stud) wall construction (2” x 4” min.): 1. Install the (2) slotted mounting brackets provided as shown in Figure 1, using the (4) 6-32 screws provided. 2. Adjust the brackets (by loosening the screws) so that the front face of the backbox will be flush or slightly in front of the finished wall surface after installation (see Figure 2). 3. Orient fixture housing electrical connections as directed on inisde label. Failure to do so will result in faceplate not installed in the correct oreintation (critical STEP for SL2003, SL2040, and SL2041 models). 4. Secure the mounting brackets to wood or metal studs (hardware by others) so that the front face of the back box will be flush or slightly in front of the finished wall surface after installation (see Figure 2). 5. Connect conduit to backbox using 3/4” NPT fittings. Pull wires into back housing for electrical connections to be made later. 6. Install splatter guard provided as shown in Figure 3, using the (2) 8-32 screws provided securely and finish wall. 7. Before continuing, remove splatter guard and debris from backbox to allow for proper fitment.
SL 2000 SERIES STUD WALL INSTALLATION
FILE NAME: SL 2000 SERIES INSTALLATION INSTRUCTIONS.SLDDRW
Fig 5
Fig 4
Optional - Hanger Bar (HB) ______
26” Max Length(14.25” Min Length)
Horizontal Adjustment
26” Max Length
Wall Stud
Wall BracingWall Stud
Hanger Bar
Hanger Bar
(14.25” Min Length)Vertical Adjustment
Drywall Mounting Brackets included w/ Back Box Kit
CONFIDENTIAL
THIS DOCUMENT IS THE PROPRIETARY PROPERTY OF FC LIGHTING, INC. ANY UNAUTHORIZED TRANSFER, USE OR REPRODUCTION IS STRICTLY PROHIBITED. © FC LIGHTING, INC.
FCSL2000 Series - INSTALLATION INSTRUCTIONS
CAUTION: BEFORE CONNECTING THE FIXTURE TO A POWER SUPPLY, MAKE SURE THE POWER IS SWITCHED OFF.
DETAILED ILLUSTRATION
corporatet 800.900.1730f 630.889.8106 3609 Swenson Ave. St. Charles, IL 60174
2458893
BRICK WALL INSTALLATION
GENERAL:1. Before starting the installation, make sure all electricity has
been turned off and electrical breaker has been locked out and tagged out.
2. To ensure the success of the installation, be sure to read these instructions and review the diagrams thoroughly before beginning.
3. All electrical connections must be in accordance with local codes, ordinances, or the National Electrical Code.
NOTE: The important safeguards and instructions appearing in this manual are not meant to cover all possible conditions and situations that may occur.
IMPORTANT: Temporarily remove Splatter Shield and contents from Back Box housing and set aside.
1. Install (2) slotted Masonry Mounting Brackets onto each side of the Back Box using (4) 6-32 adjustment screws provided. Orient Back Box as shown. Fig 1
NOTE: Ensure Back Box face is flush with Brick face. Fig 2
2. Then fasten brackets to brick using appropriate hardware (by others). Adjust Back Box vertical position for optimal spacing between upper and lower bricks. Then tighten adjustment screws.
3. Connect conduit to backbox using 3/4” K.O.s. Fig 3
4. Reinstall Splatter Shield and all contents using the (2) 8-32 screws provided. Fig 4
IMPORTANT: All wiring connections must be made in accordance with local electrical codes, ordinances, and the National Electric Code.
Back Box Conduit Entry____
Foam Block Insert toRetain Back Box Form
Splatter Shield
Wing Nuts
Threaded Rod
SL2000 SeriesUniversal Back Box
Concrete Pour Form(by others)
(4) 3/4” Knockouts - (2) on back and (1) on each side
Fig 3
Masonry Mounting Brackets Included w/ Back Box Kit
Flush Mounting to Brick FaceMOUNTING BRACKETS
BACKBOX
BRICK
Figure 4 (brick wall)
SPLATTER GUARD
Figure 6 (brick wall)
FLUSHED WITH FINISHED SURFACE
Figure 5 (brick wall) BRICK
SL 2000 SERIES BRICK WALL INSTALLATION
SL 2000 series backbox installation in brick wall construction (Utility Brick shown): 1. Install the (2) slotted mounting brackets provided as shown in Figure 4, using the (4) 6-32 screws provided. 2. Adjust the brackets vertically for optimal gap spaces between upper and lower brick surfaces and back housing 3. Orient fixture housing electrical connections as directed on inisde label. Failure to do so will result in faceplate not installed in the correct oreintation (critical STEP for SL2003, SL2040, and SL2041 models). 4. Secure the mounting brackets to the top of the brick (hardware by others) so that the front face of the back box will be flush or slightly in front of the finished wall surface after installation (see Figure 5). 5. Connect conduit to backbox using 3/4” NPT fitting with teflon tape on conduit. Pull wires into back housing for electrical connections to be made later. 6. Install Internal support block and splatter guard provided as shown in Figure 6, using the (2) 8-32 screws provided securely and finish wall. 7. Before continuing, remove splatter guard and debris from backbox to allow for proper fitment.
FILE NAME: SL 2000 SERIES INSTALLATION INSTRUCTIONS.SLDDRW
Fig 2
Orient Back Box As Shown
6-32 adjusment screws provided
MOUNTING BRACKETS
BACKBOX
BRICK
Figure 4 (brick wall)
SPLATTER GUARD
Figure 6 (brick wall)
FLUSHED WITH FINISHED SURFACE
Figure 5 (brick wall) BRICK
SL 2000 SERIES BRICK WALL INSTALLATION
SL 2000 series backbox installation in brick wall construction (Utility Brick shown): 1. Install the (2) slotted mounting brackets provided as shown in Figure 4, using the (4) 6-32 screws provided. 2. Adjust the brackets vertically for optimal gap spaces between upper and lower brick surfaces and back housing 3. Orient fixture housing electrical connections as directed on inisde label. Failure to do so will result in faceplate not installed in the correct oreintation (critical STEP for SL2003, SL2040, and SL2041 models). 4. Secure the mounting brackets to the top of the brick (hardware by others) so that the front face of the back box will be flush or slightly in front of the finished wall surface after installation (see Figure 5). 5. Connect conduit to backbox using 3/4” NPT fitting with teflon tape on conduit. Pull wires into back housing for electrical connections to be made later. 6. Install Internal support block and splatter guard provided as shown in Figure 6, using the (2) 8-32 screws provided securely and finish wall. 7. Before continuing, remove splatter guard and debris from backbox to allow for proper fitment.
FILE NAME: SL 2000 SERIES INSTALLATION INSTRUCTIONS.SLDDRW
Fig 1
Align to face of finished wall
Proper OrientationPosition
ProperOrientationPosition
Back Box Splatter Shield____
Fig 4
Back Box
8-32 screws provided
Foam Block Insert toRetain Back Box Form
Splatter Shield
Wing Nuts
Threaded Rod
SL2000 SeriesUniversal Back Box
Concrete Pour Form(by others)
BACKBOX
STUD
MOUNTING BRACKETS
Figure 2 (stud wall)
MOUNTING BRACKETS
BACKBOX
ADJUSTMENT SLOTS
Figure 1 (stud wall)
Figure 3 (stud wall)
SPLATTER GUARD
SL 2000 series backbox installation in hollow (stud) wall construction (2” x 4” min.): 1. Install the (2) slotted mounting brackets provided as shown in Figure 1, using the (4) 6-32 screws provided. 2. Adjust the brackets (by loosening the screws) so that the front face of the backbox will be flush or slightly in front of the finished wall surface after installation (see Figure 2). 3. Orient fixture housing electrical connections as directed on inisde label. Failure to do so will result in faceplate not installed in the correct oreintation (critical STEP for SL2003, SL2040, and SL2041 models). 4. Secure the mounting brackets to wood or metal studs (hardware by others) so that the front face of the back box will be flush or slightly in front of the finished wall surface after installation (see Figure 2). 5. Connect conduit to backbox using 3/4” NPT fittings. Pull wires into back housing for electrical connections to be made later. 6. Install splatter guard provided as shown in Figure 3, using the (2) 8-32 screws provided securely and finish wall. 7. Before continuing, remove splatter guard and debris from backbox to allow for proper fitment.
SL 2000 SERIES STUD WALL INSTALLATION
FILE NAME: SL 2000 SERIES INSTALLATION INSTRUCTIONS.SLDDRW
CONFIDENTIAL
THIS DOCUMENT IS THE PROPRIETARY PROPERTY OF FC LIGHTING, INC. ANY UNAUTHORIZED TRANSFER, USE OR REPRODUCTION IS STRICTLY PROHIBITED. © FC LIGHTING, INC.
FCSL2000 Series - INSTALLATION INSTRUCTIONS
CAUTION: BEFORE CONNECTING THE FIXTURE TO A POWER SUPPLY, MAKE SURE THE POWER IS SWITCHED OFF.
DETAILED ILLUSTRATION
corporatet 800.900.1730f 630.889.8106 3609 Swenson Ave. St. Charles, IL 60174
2458893
POURED CONCRETE INSTALLATION
Back Box Conduit Entry____
Foam Block Insert toRetain Back Box Form
Splatter Shield
Wing Nuts
Threaded Rod
SL2000 SeriesUniversal Back Box
Concrete Pour Form(by others)
(4) 3/4” Knockouts - (2) on back and (1) on each side
Fig 2
Back Box Splatter Shield Included w/ Back Box Kit
MOUNTING BRACKETS
BACKBOX
BRICK
Figure 4 (brick wall)
SPLATTER GUARD
Figure 6 (brick wall)
FLUSHED WITH FINISHED SURFACE
Figure 5 (brick wall) BRICK
SL 2000 SERIES BRICK WALL INSTALLATION
SL 2000 series backbox installation in brick wall construction (Utility Brick shown): 1. Install the (2) slotted mounting brackets provided as shown in Figure 4, using the (4) 6-32 screws provided. 2. Adjust the brackets vertically for optimal gap spaces between upper and lower brick surfaces and back housing 3. Orient fixture housing electrical connections as directed on inisde label. Failure to do so will result in faceplate not installed in the correct oreintation (critical STEP for SL2003, SL2040, and SL2041 models). 4. Secure the mounting brackets to the top of the brick (hardware by others) so that the front face of the back box will be flush or slightly in front of the finished wall surface after installation (see Figure 5). 5. Connect conduit to backbox using 3/4” NPT fitting with teflon tape on conduit. Pull wires into back housing for electrical connections to be made later. 6. Install Internal support block and splatter guard provided as shown in Figure 6, using the (2) 8-32 screws provided securely and finish wall. 7. Before continuing, remove splatter guard and debris from backbox to allow for proper fitment.
FILE NAME: SL 2000 SERIES INSTALLATION INSTRUCTIONS.SLDDRW
Orient Back Box As Shown
ProperOrientationPosition
Back Box Face Flush to Concrete_ Back Box Face Flush to Composite
Fig 4Fig 3
GENERAL:1. Before starting the installation, make sure all electricity has
been turned off and electrical breaker has been locked out and tagged out.
2. To ensure the success of the installation, be sure to read these instructions and review the diagrams thoroughly before beginning.
3. All electrical connections must be in accordance with local codes, ordinances, or the National Electrical Code.
NOTE: The important safeguards and instructions appearing in this manual are not meant to cover all possible conditions and situations that may occur.
IMPORTANT: Temporarily remove Splatter Shield and contents from Back Box housing and set aside.
1. Install the (2) Threaded Rods provided in through the Splatter Shield and into the Back Box as shown. Fig 1
2. Ensure that face of Back Box is flush with face of finished surface. Connect conduit to backbox using 3/4” K.O.s. Fig 2 Orient Back Box in proper position as shown.
NOTE: Ensure front of Back Box is flush with finished wall face.
2. Reinstall the Splatter Shield and contents into the Back Box and allow Threaded Rods to pass through the Pour Form. Fasten the Back Box assembly to the Pour Form using (2) Wing Nuts provided on the already installed Threaded Rods. Refer to Fig 3.
4. For additional Composite or Topcoat finish, again ensure front of Back Box is flush with finished wall face. Fig 4
IMPORTANT: All wiring connections must be made in accordance with local electrical codes, ordinances, and the National Electric Code.
Figure 7 (concrete pour)
INTERNAL SUPPORT BLOCK
SPLATTER GUARD
WING NUTS
THREADED ROD
Figure 8 (concrete pour)
POUR FORM
SL 2000 SERIES POURED CONCRETE INSTALLATION
SL 2000 series backbox installation in poured concrete construction: 1. Install the (2) threaded rod provided as shown in Figure 7, using the (2) 8-32 x 2" long rods provided. 2. Attach assembly to pour form ensuring the Orientation of the backbox housing electrical connections is followed per inside label instructions. Failure to do so will result in faceplate not installed in the correct oreintation (critical STEP for SL2003, SL2040, and SL2041 models).
FILE NAME: SL 2000 SERIES INSTALLATION INSTRUCTIONS.SLDDRW
Proper OrientationPosition
Fig 1
Figure 7 (concrete pour)
INTERNAL SUPPORT BLOCK
SPLATTER GUARD
WING NUTS
THREADED ROD
Figure 8 (concrete pour)
POUR FORM
SL 2000 SERIES POURED CONCRETE INSTALLATION
SL 2000 series backbox installation in poured concrete construction: 1. Install the (2) threaded rod provided as shown in Figure 7, using the (2) 8-32 x 2" long rods provided. 2. Attach assembly to pour form ensuring the Orientation of the backbox housing electrical connections is followed per inside label instructions. Failure to do so will result in faceplate not installed in the correct oreintation (critical STEP for SL2003, SL2040, and SL2041 models).
FILE NAME: SL 2000 SERIES INSTALLATION INSTRUCTIONS.SLDDRW
Finished WallSurface
Align housing to face of finished wall
Align housing to face of finished wall
Finished Wall Surface
Concrete, Blockor Brick Structure
Stucco or othersurface topcoat
18 AWG Anti-wicking CableWaterproof Wire Nuts (3) Included
IP68 Rated SealedOptical/Driver Unit
Hanger Bar Thru KOHorizontal & Vertical
6-32 ThreadedInserts forMounting Brackets
(4) Ø 3/4” KO(Ø 1-1/8 True Size)(2 in back & 1 @ each end)
TRSTamper ResistantScrew (Optional)
CONFIDENTIAL
THIS DOCUMENT IS THE PROPRIETARY PROPERTY OF FC LIGHTING, INC. ANY UNAUTHORIZED TRANSFER, USE OR REPRODUCTION IS STRICTLY PROHIBITED. © FC LIGHTING, INC.
FCSL2000 Series - INSTALLATION INSTRUCTIONS
CAUTION: BEFORE CONNECTING THE FIXTURE TO A POWER SUPPLY, MAKE SURE THE POWER IS SWITCHED OFF.
DETAILED ILLUSTRATION
corporatet 800.900.1730f 630.889.8106 3609 Swenson Ave. St. Charles, IL 60174
2458893
GENERAL:1. Before starting the installation, make sure all electricity has
been turned off and electrical breaker has been locked out and tagged out.
2. To ensure the success of the installation, be sure to read these instructions and review the diagrams thoroughly before beginning.
3. All electrical connections must be in accordance with local codes, ordinances, or the National Electrical Code.
NOTE: The important safeguards and instructions appearing in this manual are not meant to cover all possible conditions and situations that may occur.
1. To finish step light installation, remove the Splatter Shield and all contents from the Back Box. Complete all wiring in the Back Box, then snap the fixture assembly into the back box using the Snap-In Captures & Leads. Fig 1
2. Use Shims to compensate for misalignment of the front of the Back Box and the finished wall surface. Fig 2
3. Ensure proper orientation of Back Box as shown. Connect conduit to backbox using 3/4” K.O.s. Fig 3
4. Splatter Shield and standard mounting installation hardware are included in and ship with the Back Box assembly. (2) 8-32 screws provided to secure and remove the Splatter Shield and contents. Fig 3
7. Optional Tamper Resistant Screws (TRS) can be usd for additional security using Torx Pin screws, painted to complement the faceplate. Fig 4
3) WIRING: Make wiring connections. All wiring connections must be made in accordance with local electrical codes, ordinances, and the National Electric Code.
Fixture Snaps into Back Box
FixtureAssembly
Snap-In Capture
Right Side
Left Side Universal Back BoxTop
Fixture WiringOut
Snap-In Lead
Fig 1
Back Box Splatter Shield____
Distance recessed = X
Snap-In Lead
Snap-In Capture
Wall surface
Wall surface
Added Shims to equal “X” X
Torx screws w/ pin, finished to complement faceplate finish.
Optional - Tamper Resistant Screws (TRS)
Tamper Resistant Torx Screws(TR20 w/Pin)
Shims provided to compensate for Back Box misalignment.
Shims - (8 ea.) included w/ Fixture
Fig 2
FIXTURE & BACK BOX ASSEMBLY
Foam Block Insert toRetain Back Box Form
Splatter Shield
Wing Nuts
Threaded Rod
SL2000 SeriesUniversal Back Box
Concrete Pour Form(by others)
(4) 3/4” Knockouts
(2) on back,(1) on each side
Fig 3
BACKBOX
STUD
MOUNTING BRACKETS
Figure 2 (stud wall)
MOUNTING BRACKETS
BACKBOX
ADJUSTMENT SLOTS
Figure 1 (stud wall)
Figure 3 (stud wall)
SPLATTER GUARD
SL 2000 series backbox installation in hollow (stud) wall construction (2” x 4” min.): 1. Install the (2) slotted mounting brackets provided as shown in Figure 1, using the (4) 6-32 screws provided. 2. Adjust the brackets (by loosening the screws) so that the front face of the backbox will be flush or slightly in front of the finished wall surface after installation (see Figure 2). 3. Orient fixture housing electrical connections as directed on inisde label. Failure to do so will result in faceplate not installed in the correct oreintation (critical STEP for SL2003, SL2040, and SL2041 models). 4. Secure the mounting brackets to wood or metal studs (hardware by others) so that the front face of the back box will be flush or slightly in front of the finished wall surface after installation (see Figure 2). 5. Connect conduit to backbox using 3/4” NPT fittings. Pull wires into back housing for electrical connections to be made later. 6. Install splatter guard provided as shown in Figure 3, using the (2) 8-32 screws provided securely and finish wall. 7. Before continuing, remove splatter guard and debris from backbox to allow for proper fitment.
SL 2000 SERIES STUD WALL INSTALLATION
FILE NAME: SL 2000 SERIES INSTALLATION INSTRUCTIONS.SLDDRW
8-32 screws provided
Proper OrientationPosition
Fig 4