Purpose Statement
To review our Quality Management System (QMS), Environmental Management System (EMS), and
Occupational Health & Safety Management System (OHSAS) to ensure suitability, adequacy, and
effectiveness. In doing so, we are able to determine opportunities for improvement and performance,
while assessing the need for changes to the QMS, EMS and OHSAS systems.
April 2015 3
Executive Summary ISO-9001 QMS
5 Action Items open since the last Management Review
ISO-14001 EMS 3 Action Items open since the last
Management Review 1 Action Items closed since the last
Management Review
BS-18001 OHSAS 3 Action Items open since the last
Management Review
Service Maintenance Areas Exceeded the monthly goal set for meeting the
SLA Exceeded the monthly goals set for internal
inspections
Business Administration Exceeded the monthly goal set for processing
vendor payments within 16 days
Street Repair Division Asphalt and Concrete are below the monthly
goals set for meeting the SLA Slightly behind the monthly goal set for
performing STS Work Planned Projects Asphalt and Concrete exceeded the monthly
goals set for internal inspections
Fleet Acquisition & Replacement Fleet Acquisition exceeded the monthly goals
set for the monthly PM
Transportation Division Exceeded the monthly goals set for meeting
the SLA Exceeded the monthly goals set for internal
inspections
April 2015 4
Action Items
Please refer to the Action Item List
STS-FRM-003, rev. 1, 12/7/07April 2015 5
Environmental Spills
April 2015 6
Objective: Decrease the number of reportable petroleum-based spills over 1 gallon.
April FY 14/15
STS-FRM-003, rev. 1, 12/7/07April 2015 7
Safety Compliance
April 2015 8
Objective: Reduce the number of collisions within the department by 10%
Number of non-preventable and preventable collisions
April 2015 9
Preventable and non-preventable collisions
Street Services April 2015 Issued Ytd.
District / Divisions Preventable Non-preventable Preventable Non-preventable
SMA 1 0 0 0 1
SMA 2 0 1 0 2
SMA 3 0 0 1 2
SMA 4 0 0 0 0
Nights 0 0 0 2
SRD 0 2 3 9
CFI 0 0 0 0
TRN 1 0 1 3
Department Totals 1 3 5 19
STS-FRM-003, rev. 1, 12/7/07April 2015 10
Service Maintenance Areas
April 2015 11
Objective: Respond to service requests in accordance with the SLA.
FY 14-15 Percentage of Closed SRs Meeting the SLA - Goal 99%
97%
98%
99%
100%
Monthly % 100% 100% 99.9% 100% 99% 100.0% 99.9%
Goal 99% 99% 99% 99% 99% 99% 99% 99% 99% 99% 99% 99%
YTD Avg 100% 100% 99.9% 100% 99% 100.0% 99.9%
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
* YTD APR-2015- Number of SR closed (1855) & Number of SR closed on time (1849)
SMA Monthly %
SMA – 1 100%
SMA – 2 100%
SMA – 3 100%
SMA – 4 99.9%
April 2015 12
Objective: Respond to 3-1-1 service requests in accordance with the SLA.
FY 14-15 Percentage of Closed SRs Meeting the SLA - Goal 99% (SMA-1)
94%
96%
98%
100%
Monthly % 100% 100% 100% 100% 100% 100% 100%
Goal 99% 99% 99% 99% 99% 99% 99% 99% 99% 99% 99% 99%
YTD Avg 100% 100% 100% 100% 100% 100% 100%
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
504 / 504 236/236263 / 263
365/364334/331 656/656 602/602
April 2015 13
Objective: Respond to 3-1-1 service requests in accordance with the SLA.
FY 14-15 Percentage of Closed SRs Meeting the SLA - Goal 99% (SMA-2)
94%
96%
98%
100%
Monthly % 100% 100% 100% 100% 100% 100% 100%
Goal 99% 99% 99% 99% 99% 99% 99% 99% 99% 99% 99% 99%
YTD Avg 100% 100% 100% 100% 100% 100% 100%
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
522 / 522 277 / 277 280 / 280 363/363 437/436 866/866 630/630
April 2015 14
Objective: Respond to 3-1-1 service requests in accordance with the SLA.
FY 14-15 Percentage of Closed SRs Meeting the SLA - Goal 99% (SMA-3)
94%
96%
98%
100%
Monthly % 100% 100% 100% 99% 100% 99.9% 99.5%
Goal 99% 99% 99% 99% 99% 99% 99% 99% 99% 99% 99% 99%
YTD Avg 100% 100% 100% 99% 100% 99.9% 99.5%
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
612 / 612374 / 374
405 / 405
623/618
661/6591203/1202
812/808
April 2015 15
Objective: Respond to 3-1-1 service requests in accordance with the SLA.
FY 14-15 Percentage of Closed SRs Meeting the SLA - Goal 99% (SMA-4)
94%
96%
98%
100%
Monthly % 100% 100% 99.7% 100% 100% 100% 100%
Goal 99% 99% 99% 99% 99% 99% 99% 99% 99% 99% 99% 99%
YTD Avg 100% 100% 99.9% 100% 100% 100% 100%
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
691/ 691 357/ 357287/ 288
504/504 668/6671019/1019 894/894
April 2015 16
Objective: Achieve a 97% Safety pass rate for SMA inspections.
FY 14-15 Inspection Pass Rate
85%
90%
95%
100%
Monthly % 100% 100% 100% 100.0% 100.0% 100% 100%
Goal 97% 97% 97% 97% 97% 97% 97% 97% 97% 97% 97% 97%
YTD % 100% 100% 100% 100.0% 100.0% 99.6% 100.0%
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
129/129 212/212 98/98 86/86 293/293160/160 253/254
April 2015 17
Objective: Achieve a 97% Environmental pass rate for SMA inspections.
FY 14-15 Inspection Pass Rate
85%
90%
95%
100%
Monthly % 100% 100% 100% 100.0% 100.0% 100% 100%
Goal 97% 97% 97% 97% 97% 97% 97% 97% 97% 97% 97% 97%
YTD % 100% 100% 100% 100.0% 100.0% 100.0% 100.0%
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
129 / 129 212 / 212 98 / 98 86/86 254/254 160/160 293/293
April 2015 18
Objective: Achieve a 97% Quality pass rate for SMA inspections.
FY 14-15 Monthly SMA Inspection Pass Rate (all SMA's)
80%
85%
90%
95%
100%
Monthly % 96.9% 98.1% 99.0% 100.0% 93.8% 100.0% 100%
Goal 97% 97% 97% 97% 97% 97% 97% 97% 97% 97% 97% 97%
YTD Avg 96.9% 97.7% 97.9% 100.0% 93.8% 100.0% 100.0%
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
125/ 129208/ 212
97/ 9886/86 254/254
150/160
293/293
April 2015 19
Objective: Track the number of inlets cleaned.
0
250
500
750
1,000
1,250
1,500
Cleaned 1,028 782 872 587 411 446 581
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
746.50 cy
*Cubic yards of debris removed
609 cy
716 cy
587cy
411cy
446.33cy
581cy
STS-FRM-003, rev. 1, 12/7/07April 2015 20
Business Administration
April 2015 21
Objective: Process 85% of payments for goods and services within 16 days.
70%
75%
80%
85%
90%
95%
100%
Monthly % 99.3% 98.8% 98.2% 98.8% 98.9% 99.0% 98.8%
Goal 85% 85% 85% 85% 85% 85% 85% 85% 85% 85% 85% 85%
YTD Average 99.3% 99.0% 98.8% 98.8% 98.9% 99.0% 98.8%
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
406/409 401/406 390/397 264/261 414/411 391/388 519/507
STS-FRM-003, rev. 1, 12/7/07April 2015 22
Vendor Performance
April 2015 23
Objective: Ensure key vendors perform according to specifications.Vendor Type Customer
ServiceDelivery Quality Envir. Perf. Comments
Apac Asphalt No comments
Hertz Equipment Rental
No comments
TXI Asphalt Base
No comments
Southern Star Concrete Delivery
No comments
NPL Concrete Street Repair
No comments
Kirby Smith Equipment Rental
No comments
Holcim Bulk Cement Del.
No comments
G & K Uniform Rental
No comments
Flagship Sweeping X
Sweeper needs to sweep against the curb line.
Striping Technology Pavement Markings
No comments
Good Earth R-O-W Mowing
No comments
April 2015 24
Objective: Ensure key vendors perform according to specifications.Vendor Type Customer
ServiceDelivery Quality Envir. Perf. Comments
Custom Concrete Concrete Delivery
No comments
Heart Land Emulsion No comments
Northwest Propane Propane No comments
.
STS-FRM-003, rev. 1, 12/7/07April 2015 25
Street Repair Division
April 2015 26
Objective: Perform service requests for major asphalt street repairs in accordance with the SLA.
FY 14-15 Percentage of Closed SRs meeting SLA - Goal 92%
0%
20%
40%
60%
80%
100%
Monthly % 68.7% 92% 63.0% 29% 51.0% 53.0% 87%
Goal 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92%
YTD Avg. 68.7% 91.7% 63.0% 29.0% 51.0% 53.0% 87.0%
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
46 / 67
12 / 12
7/11
10/34
28/54 17/32
47/54
Asphalt activity declined from Nov 14 – Jan 15 due to extreme cold temps, weather, precipitation and a record winter with regards to ice and snow falls. 90 to 45 day deadline reduction also took crews away from our planned work to get the MCC work completed.
From Feb through April, 15, the upward trend indicates our goal should be resumed weather permitting. Although not shown in this slide at this time, we do not expect this upward trend to continue in May. Regretfully in May 2015 a record for having had the wettest May ever was set. Inevitably, asphalt cannot be applied. Throughout June, however, our crews resumed work aggressively to make up for lost time, and expect to resume the upward trend.
April 2015 27
Objective: Perform service requests for major concrete street repairs in accordance with the SLA.
FY 14-15 Percentage of Closed SRs meeting SLA - Goal 92%
20%
40%
60%
80%
100%
Monthly % 80.5% 80.0% 80.0% 70.0% 76.0% 72% 75%
Goal 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92%
YTD Avg. 80.5% 80.0% 80.0% 70.0% 76.0% 76.0% 76.3%
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
62/77 46/60 40/50 44/62 38/50 38/53 59/79
FY 13-14 showed 387 SRs from Oct – Apr and our 92% goal was exceeded as 94.32%. Comparably, FY 14–15, from Oct 14 – April 15 SRs have reached 431, or 44 projects more. This increase coupled with the record inclement weather patterns experienced, thus far, have caused this decline in completion of SRs and not meeting our 92% goal. 90 to 45 day deadline reduction also took crews away from our planned work to get the MCC work completed. As dryer/better weather has not set in, in June, crews will resume normal workloads and begin to trend upwardly to reach our goal. The restoration of a 90-day completion timeframe for MCCs will also help us get back to goal.
April 2015 28
Objective: Perform Street Maintenance Work Plan projects in accordance with FY 14-15 program goals.
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
150
160
170
180
190
200
210
220
YTD Goal YTD Actual
YTD Goal 14 26 36 47 57 77 100 125 149 170 193 217
YTD Actual 5 11 18 26 33 43 62
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Program Goals
Rehabilitation - 30
Restoration – 12
Partial Reconstruction - 115
Full Depth Asphalt– 60
Increased SR workload, record inclement hot/cold weather impacted our in house planned work as noted in prior slides. Better weather will allow us to get caught up by year’s end and reach our total Lane Mile goal.
April 2015 29
Objective: Perform Street Maintenance Work Plan projects in accordance with FY 14-15 program goals.
Program status - 77%
Refer to slide 28’s comments
Objective: Perform Street Maintenance Work Plan projects in accordance with FY 14-15 program goals.
April 2015 30Program status – 72%
04/2015 31
Objective: Perform Street Maintenance Work Plan projects in accordance with FY 14-15 program goals.
Program status -58%
April 2015 32
Objective: Perform Street Maintenance Work Plan projects in accordance with FY 14-15 program goals.
Program status - 60%
April 2015 33
Objective: Achieve a 97% Safety pass rate for SRD Asphalt inspections.
FY 14-15 Inspection Pass Rate
85%
90%
95%
100%
Monthly % 98.5% 99.0% 97.1% 95.5% 96% 98.5% 100.0%
Goal 97% 97% 97% 97% 97% 97% 97% 97% 97% 97% 97% 97%
YTD % 99.1% 98.7% 98.3% 95.5% 95.6% 98.5% 100.0%
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
195/198 101/102
99/102
130/132158/160
131/132 253/253
April 2015 34
Objective: Achieve a 97% Safety pass rate for SRD Concrete inspections.
FY 14-15 Inspection Pass Rate
85%
90%
95%
100%
Monthly % 99.4% 100% 99.4% 99.5% 100.0% 100.0% 100.0%
Goal 97% 97% 97% 97% 97% 97% 97% 97% 97% 97% 97% 97%
YTD % 99.3% 99.6% 99.5% 99.5% 100.0% 100.0% 100.0%
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
153/154 115/115
160/161187/187 128/128
149/149198/198
April 2015 35
Objective: Achieve a 97% Environmental pass rate for SRD Asphalt inspections.
FY 14-15 Inspection Pass Rate
85%
90%
95%
100%
Monthly % 100% 100% 100% 100.0% 100.0% 100% 100%
Goal 97% 97% 97% 97% 97% 97% 97% 97% 97% 97% 97% 97%
YTD % 100% 100% 100% 100.0% 100.0% 100.0% 100.0%
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
198 / 198 102/102
102 / 102132/132
160/160132/132
253/253
April 2015 36
Objective: Achieve a 97% Environmental pass rate for SRD Concrete inspections.
FY 14-15 Inspection Pass Rate
85%
90%
95%
100%
Monthly % 100% 100% 100% 100% 100% 100% 100.0%
Goal 97% 97% 97% 97% 97% 97% 97% 97% 97% 97% 97% 97%
YTD % 100% 100% 100% 100% 100% 100% 100.0%
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
154 / 154 115 / 115161 / 161
187/187128/128
149/149198/198
April 2015 37
Objective: Achieve a 97% Quality pass rate for SRD Asphalt inspections.
FY 14-15 Monthly Inspection Pass Rate
80%
85%
90%
95%
100%
Monthly % 99.0% 99.0% 99.0% 95.5% 95.6% 98.5% 100%
Goal 97% 97% 97% 97% 97% 97% 97% 97% 97% 97% 97% 97%
YTD Avg 99.0% 99.0% 99.0% 95.5% 95.6% 98.5% 99.6%
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
196/198 101/102
101/102
126/132 155/160
131/132252/253
April 2015 38
Objective: Achieve a 97% Quality pass rate for SRD Concrete inspections.
FY 14-15 Monthly Inspection Pass Rate
80%
85%
90%
95%
100%
Monthly % 100% 100% 99.4% 100% 99.2% 100.0 100%
Goal 97% 97% 97% 97% 97% 97% 97% 97% 97% 97% 97% 97%
YTD Avg 100% 100% 99.8% 99.5% 99.2% 100.0 99.5%
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
154/154 115/115
160/161 186/187127/128 149/149 197/198
April 2015 39
Objective: Track the amount of construction materials recycled from major street construction repairs.
0
2,000
4,000
6,000
8,000
FY 14-15 SRD Street Construction Material Spoils
(cubic yards)
Asphalt 1,164 4,180 2,785 3,956 3,312 3,079 2,358
Concrete 2,978 1,907 2,326 2,032 2,203 2,136 3,195
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
STS-FRM-003, rev. 1, 12/7/07April 2015 40
Fleet Acquisition & Replacement
April 2015 41
Objective: Ensure 95% of Fleet PM’s are turned-in on time.
FY 14-15 M-5 Report (Ytd.)
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
PM's 54% 82% 96% 96% 100% 100% 100%
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
April 2015 42
Objective: Ensure 95% of Fleet PM’s are turned-in on-time (April 2015).
PM'S TURNED IN ON TIME
Division PM'S DueTurned -in on time/ (M-5) Late
Adjusted late/ #Comments % of Fleet turned in on time
Admin 0 0 0 N/A 0%
SMA -1 4 0 4 0/4 100%
SMA -2 4 3 1 0/1 100%
SMA -3 4 3 1 0/1 100%
SMA -4 7 3 4 0/4 100%
EMS 2 0 2 0/2 100%
QAI 3 2 1 0/1 100%
Nights 4 4 0 0/0 100%
SRD-A 15 8 7 0/7 100%
SRD-C 10 4 6 0/6 100%
TRN 5 3 2 0/2 100%
TxDOT 0 0 0 N/A 100%
Total 59 29 28 0/28 100%
STS-FRM-003, rev. 1, 12/7/07April 2015 43
Transportation
April 2015 44
Objective: Respond to Signal Maintenance Operations /Emergency Calls in accordance with the SLA.
FY 14-15 Percentage of Closed SRs meeting SLA
80%
85%
90%
95%
100%
Monthly % 97.8% 99.0% 98.1% 100% 100% 100% 100%
Goal 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95%
YTD 97.8% 98.4% 98.3% 99% 99% 99% 99%
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
469 / 491
132 / 133124 / 129
137/137 145/146 123/123 157/157
April 2015 45
Objective: Respond to Traffic Sign Maintenance - Emergency Calls in accordance with the SLA.
FY 14-15 Percentage of Closed SRs meeting SLA
80%
85%
90%
95%
100%
Monthly % 100% 99.0% 98.6% 100.0 100.0 100% 100%
Goal 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95%
YTD 100% 99.5% 99.2% 99.4% 99.5% 99.6% 99.6%
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
205/205 113/114 141/143
137/137126/126
150/150184/185
April 2015 46
Objective: Respond to Engineering Request / Emergency Response in accordance with the SLA.
FY 14-15 Percentage of Engineering Request Completed within the SLA
70%
80%
90%
100%
Monthly % 98.4% 94.6% 98.2% 100% 93.6% 100.0 97.4%
Goal 90% 90% 90% 90% 90% 90% 90% 90% 90% 90% 90% 90%
YTD 98.4% 96.5% 97.1% 97.8% 97.0% 97.5% 97.5%
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
443/450
258 / 273
319 / 325 358/362
126/126
445/445
445/457
April 2015 47
Objective: Perform Signal Construction Traffic Hardware Repair / Emergency Response in accordance with the SLA.
FY 14-15 Percentage of Closed SR's meeting the SLA
60%
80%
100%
Monthly % 100% 100% 100% 100% 100% 100% 100%
Goal 99% 99% 99% 99% 99% 99% 99% 99% 99% 99% 99% 99%
YTD 100% 100% 100% 100% 100% 100% 100%
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
44 / 44 26 / 26 34 / 34 26/26 24/24 29/29 29/29
April 2015 48
• Objective: Perform Lane Line Striping in accordance with program goals.
Long line striping is below target due to weather delays – we will still
meet goal by September.
0
125
250
375
500
Goal YTD
Goal 15 45 75 105 135 165 215 265 315 365 419 419
YTD 33 52.4 60.5 60.5 72.8 72.8 118.6
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Fy 14-15 Total Lane Lines Striped Goal = 419 linear miles
April 2015 49
Objective: Perform Crosswalk Striping in accordance with program goals.
0
100
200
300
400
500
600
700
Goal YTD
Goal 20 50 80 120 150 180 210 240 270 320 370 370
YTD 65 138 178 201 269 283 334
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Fy 14-15 Crosswalk Striping Goal = 370 Crosswalks
April 2015 50
Objective: Achieve a 97% Safety pass rate for TRN inspections.
FY 14-15 Inspection Pass Rate
85%
90%
95%
100%
Monthly % 100% 100% 100% 100% 100% 100% 100%
Goal 97% 97% 97% 97% 97% 97% 97% 97% 97% 97% 97% 97%
YTD % 100% 100% 100% 100% 100% 100% 100%
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
197/197 122/122 255/255
234/234139/139
240/240181/181
April 2015 51
Objective: Achieve a 97% Environmental pass rate for TRN inspections.
FY 14-15 Inspection Pass Rate
85%
90%
95%
100%
Monthly % 100% 100% 100% 100% 100% 100% 100%
Goal 97% 97% 97% 97% 97% 97% 97% 97% 97% 97% 97% 97%
YTD % 100% 100% 100% 100% 100% 100% 100%
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
197/197 122/122 255/255234/234
139/139240/240 181/181
April 2015 52
Objective: Achieve a 97% Quality pass rate for TRN inspections.
FY 14-15 Monthly Inspection Pass Rate
80%
85%
90%
95%
100%
Monthly % 100% 100% 99.6% 100% 100% 100.0 100%
Goal 97% 97% 97% 97% 97% 97% 97% 97% 97% 97% 97% 97%
YTD Avg 100% 100% 99.8% 100.0 100.0 100.0 100.0
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
197/197 122/122 254/254 234/234 139/139 240/240 181/181
STS-FRM-003, rev. 1, 12/7/07April 2015 53
Customer Feedback
March 2015 54
Crew & Quality Complaints/Compliments27 Crew Complaints & Compliments
8 were referred to other departments 16 Handled Internally
Crew Complaints SRD-C (SR# 15-00167022) SRD-A (SR# 15-00155235) SRD-C (SR# 15-00161617) SRD-A (SR# 15-00161942) SRD-A (SR# 15-001149958) SRD-C (SR# 15-00118833) SMA-1 (SR# 15-00106447) SMA-3 (SR# 15-00146910) SMA-3 (SR# 15-00148691) SMA-3 (SR# 15-00149248) SMA-3 (SR# 15-00145855) SMA-4 (SR# 15-00169127) SMA-4 (SR# 15-00158960)
55
Crew & Quality Complaints/Compliments (continued)
Crew Complaints
CFI ( INSPECTION) ( SR# 15-00159002) TRN( CONTRACTOR) ( SR# 15-00117346) TRN ( SR# 15-00152161)
3 Compliments
SMA-3 ( SR# 15-00145939) SMA-4 ( SR# 15-00147299)SMA-4 ( SR# 15-00129896)
0 Quality Complaints
0 Accidents
April 2015
April 2015 56
Employee RecognitionStreet Services April 2015 Issued Ytd.
District / Divisions W.O.W. CardEmployee Recognition W.O.W. Card
Employee Recognition
SMA 1 0 1 1 2
SMA 2 0 0 0 2
SMA 3 0 0 1 0
SMA 4 0 1 0 6
Nights 0 0 0 0
SRD 0 0 0 1
TRN - Operations 0 1 0 5
TRN - Shop 0 0 1 0
Admin 0 0 23 0
Department Totals 0 3 26 16
STS-FRM-003, rev. 1, 12/7/07April 2015 57
Audits Findings and Recommendations
April 2015 58
Audit Findings, and Recommendations (cont.) EMS / QMS / OHSAS External Audits
March 16 – 19, 2015