structural steel fibre reinforced construction

Upload: tyukgomba

Post on 03-Jun-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/12/2019 Structural Steel Fibre Reinforced Construction

    1/2

    During the last 15 years, the structuraluse of steel fibres as the only principalreinforcing in concrete has beendeveloped and widely used.

    Such novel techniques, where steel fibres completelyreplace all traditional reinforcing bars and fabric, havebeen used repeatedly in the following applications involv-

    ing plane structural members:

    Pile-supported industrial slabs where the ground does

    not provide any bearing capacity (TAB-Structuralwith span-to-depth ratios of up to 22).

    Ground-bearing general rafts as general foundations

    under condominiums, schools, hospitals, office tow-

    ers, clad-rack warehouses, shopping malls and tanks

    (TAB-Raft).

    Cast in-situ free suspended elevated slabs in residen-

    tial and commercial applications (TAB-Slab, span-to-

    depth ratio of up to 35).

    Second phase layers on top of concrete planks and

    void formers.

    Composite floors on steel decking (TAB-deck with up

    to two hour fire rating).

    Retaining walls.

    Bridge slabs.

    The steel-fibre-only reinforced concrete in these appli-

    cations, with dosage rates of 30100kg/m3 depending on

    the application and type of fibre used, is able to resist the

    moments, negative and positive, together with the shear,

    shrinkage and punching stresses, so that all reinforcing

    steel is omitted. Continuity and starter bars are generally

    needed, as in traditional concrete.

    The site conditions require the steel-fibre-reinforced

    concrete to be fully pumpable and flowing in such a way

    that it does not require any mechanical vibration.

    Matrix saturation

    An essential feature is the need to saturate the concretematrix with steel fibres in such a way that the steel fibre

    spacing in all directions is equal to at least the maximum

    aggregate size. The fibre length should be 2.5 to 3 times the

    size of aggregate so that the fibre can overlap and bridge

    fully all large aggregate particles.

    The 3D-fibre spacing, s, is a function of the fibre diame-

    ter, d, and dosage rate, Vm , as follows:

    s = 122 d/Vm

    For example:

    50kg/m3 of TABIX+1/60, s =122 1/50 = 17.25mm100kg/m3 of TABIX1.3/50, s = 122 1.3/100 =

    15.86mm.

    The correct steel fibres for these structural uses are of

    round cross-section (BS EN 14889-1, Group I(1)), strong,

    ductile, rather stiff (ie, difficult to bend between three fin-

    gers of your hand) and should provide an anchoring shape

    so that they offer high pull-out loading. Undulated TABIX,

    HE hooked ends and Twincone (conical button ends),

    which provide total anchorage are the shapes that are most

    commonly used in our structural applications.

    Examples of pull-out loadings of individual steel fibres

    are as follows:

    1mm/60mm (L/d = 60),1500MPa,TABIX+ 800N

    1mm/50mm (L/d=50), 1500MPa, HE+ 600N

    1mm/54mm (L/d=54), 1000MPa,Twincone 700N

    1.3mm/50mm (L/d = 38),900MPa,TABIX13/50 800N

    Stiff fibres that do not bend easily also create less fric-

    tion inside the plastic concrete matrix, so that there is lessslump loss. Consequently, a stiffer fibre has less tendency

    to show at the surface of the concrete.

    To achieve the workability that is needed on the job site,

    the larger 1.3mm-diameter fibres are generally used, up to

    the very high dosage rates of 80 and 100kg/m3, while the

    1mm-diameter fibres are limited to a dosage rate of

    50kg/m3.

    Smaller-diameter fibres are not used although they sat-

    urate the concrete at lower dosage rates, as low as 25kg/m3

    for a 0.60mm diameter fibre. Their very low pull-out load

    (125N) together with a loss of workability at higher

    dosages, makes it extremely difficult to use them.

    Mix designSelecting the correct mix design is essential to ensure that

    the concrete can be satisfactorily transported, pumped

    (using a minimum 125mm-diameter line), placed and fin-

    ished. Hence the purchase order of concrete shall include

    at least the following:

    the mix design together with the aggregate grading

    the cement content and the maximum water/cement

    ratio of no more than 0.55 (preferably 0.50); a super-

    plasticiser is needed to supply a flowing concrete

    the slump prior to any addition of superplasticiser and

    the strength class.

    The aggregate grading should be continuous, with

    20mm maximum aggregate size together with an increasedcontent of 12mm maximum size to ensure that the steel

    fibres can fit between the aggregate particles. The

    gravel/sand ratio should be 0.9:1.0, with at least 475

    500kg/m3 fines smaller than 200 (including 320350kg/m3

    of cementitious material).

    CONCRETE SEPTEMBER 2007 23

    FIBRES

    Structural steel-fibre-reinforced

    concrete construction

    XAVIER DESTRE, ARCELOR MITTAL

    Figure 1 left: Installationof a TAB-Structural pile-supported ground floorslab in a Bauhaus

    warehouse in Ingelsta,Sweden. The slab is300mm-thick requiring45kg/m3 dosage rate ofTABIX+1/60 over a pilegrid of 3.5m 3.5m toallow for a uniformlydistributed load of50kN/m2. Fibre blastmachines were on-siteto introduce the steelfibres into the concrete,

    which was laid at a rateof 500m2 to 1650m2 per

    day.

    Figure 2: TAB-Raft usedas a general foundation(4000m2) slab under anoffice building inCouillet, Belgium. This

    raft is 400mm-thickrequiring 50kg/m3

    HE+1/50 fibres using aconcrete pump. Columnstarter bars were tiedonto steel fabric.

    (Photos:ArcelorMittal.)

  • 8/12/2019 Structural Steel Fibre Reinforced Construction

    2/2

    Steel fibre mixingUsing the above-listed fibres, various methods are possi-

    ble. In the UK, very few concrete plants can mix the fibres

    into the central mixer. Most often the fibres are therefore

    introduced at a rate of 1 minute per cubic metre into the

    ready-mixed concrete truck revolving at maximum speed

    by using blast machines or being loaded onto mobile con-

    veyor belts or the aggregate belts used to load the ready-

    mixed trucks. TABIX+1/60 and Twincone are blown into the ready-

    mixed truck using proprietary blast machines pro-

    vided by Arcelor Mittal UK and other services

    companies.

    HE+1/50 and TABIX1.3/50 steel fibres can be intro-

    duced using a conveyor belt.

    TABIX1.3/50 can also be loaded in the truck mixer

    prior to dumping any of the constituent materials into

    it.

    Design criterionBasically, there is almost always a steel-fibre-only rein-

    forced concrete solution for plane elements when,working

    under unfactored-service loadings together with their ownweight, the concrete stresses in flexure and shear are less

    than 5N/mm2 and 1.5N/mm2 respectively, the latter calcu-

    lated at mid-depth with a 45 angle of distribution of

    stresses. Currently, steel fibres do not replace the principal

    reinforcing bars in beams and columns.

    For suspended slabs and rafts, the above design rules

    are derived from no less than five full-scale tests (including

    several fire tests) conducted using the TAB-Deck system

    (steel fibres used in composite metal deck construction)

    together with 15 years experience in numerous countries in

    Europe and the Americas involving several million cubic

    metres of concrete. As outlined in Concrete Society

    Technical Report 63, Guidance for the design of steel-

    fibre-reinforced concrete(2), Arcelor Mittals methods arepart of the design assisted by testing route.

    AdvantagesThere are numerous advantages resulting from the use of a

    pre-reinforced concrete that is readily and easily placed or

    pumped into the forms:

    higher-quality concrete elements as there are no more

    mistakes related to the installation of steel and no

    unexpected variations in the effective depth

    design and technical assistance by Arcelor Mittal

    appointed structural engineers

    reduced and controlled concrete shrinkage

    slabs and rafts with flat soffits,without drop panels

    anti-progressive-collapse reinforcement as in NorthAmerican Standards is included in all TAB-Slabs,

    ensuring that no catastrophic collapse occurs if a col-

    umn fails

    TAB-Slabs are flat slabs and do not need any beams

    or pedestals and so are quite easy to cast on-site when

    non-rectangular floors are required, resulting in

    greater design freedom

    material savings due to a reduction in thickness in

    most cases is feasible

    material savings due to the replacement of two layers

    of reinforcement and stirrups as they are completely

    omitted

    labour savings as cutting, bending and placing of steel

    are no longer needed labour savings during installation as the concrete is

    self-levelling and does not need poker vibration; it is

    easily consolidated in the formwork

    the concrete has a more professional appearance as it

    is completely smooth against smooth formwork

    project schedules benefit as the critical path task of

    installing and tying traditional reinforcement is omit-

    ted; it is commonplace to see several weeks saved on

    large projects

    crane savings as there is no handling of steel

    better job site management as there is no need to store

    and handle cut and bent steel reinforcement

    better personnel safety; none of the risks attributable

    to traditional steel a better environment with less crane noise, cutting

    and bending of steel and no noise from concrete

    vibrators

    the concrete is easily pumped.

    SEPTEMBER 2007 CONCRETE

    FIBRES

    24

    References:

    1. BRITISH STANDARDS INSTITUTION. BS EN 14889-1:

    Fibres for concrete. Steel fibres. Definitions,

    specifications and conformity. BSI, 2006.2. CONCRETE SOCIETY. Guidance for the design of steel-

    fibre-reinforced concrete, Technical Report 63. TheConcrete Society, Camberley, 2007.

    Figure 7: A 150mm-thick TAB-Deck composite floor onsteel decking with 30kg/m3 HE1/50 steel fibres at abuilding site in Thanet, UK.

    Figure 6: A completed building in Talinn, Estonia, whichhad five 230mm-thick TAB-Slab floors with a 7.5m spanand the raft foundation, all with a fibre dosage of80kg/m3.

    Figure 3 and 4: TAB-Raft was used for the

    350mm-thick, 2000m2ground slab underneath

    a condominiumbuilding. Figure 3

    shows the installationof 80kg/m3

    TABIX1.3/50 includingthe column footing

    thickening. The raftsurface is mirror

    finished, as shown inFigure 4, in order to

    comply with therequirements for a

    parking garage.

    Figure 5: A typicalinstallation of a TAB-Slab steel-fibre-only

    free suspendedelevated slab 180mm-thick, using 100kg/m3

    TABIX1.3/50. Anti-progressive-collapse

    reinforcement isprovided from column

    to column.