Tom Anderson's presentation at the ASHRAE Winter 2012 Conference in Chicago, IL. Discover how the Design Review (DR) process can provide the building owner with significant value. Done well, a commissioning DR can help the team control construction costs while ensuring that building systems and equipment are optimized to meet the owner's needs. This presentation teaches viewers how to conduct meaningful design reviews to help the design team meet the Owner's Project Requirements. The presentation also addresses the financial benefits of DR, scheduling design review for maximum benefit, the mechanisms of the DR process, and presentation and communication strategies that enable the design team and owner to fully consider alternative approaches proposed in the DR process. This presentation was given by Tom Anderson, CCP, Principal of Cx Associates, LLC, on January 23, 2012 at the ASHRAE Winter 2012 Conference.

TRANSCRIPT

Page 1: Strategies For A Meaningful Design Review by Tom Anderson

STRATEGIES FOR A MEANINGFUL DESIGN REVIEW

THOMAS ANDERSON, CCP

Burlington, Vermont cx-associates.com

[email protected]

Page 2: Strategies For A Meaningful Design Review by Tom Anderson

I. Learning Objectives for this Session

• Understand the methodology and process of meaningful design reviews

• Learn presentation strategies to enable the designer and owner to seriously consider suggestions

• Know how to support optimized system performance through design review

ASHRAE is a Registered Provider with The American Institute of Architects Continuing Education Systems. Credit earned on completion of this program will be reported to ASHRAE Records for AIA members. Certificates of Completion for non-AIA members are available on request. This program is registered with the AIA/ASHRAE for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product. Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation.

2

Page 3: Strategies For A Meaningful Design Review by Tom Anderson

Design Review Presentation Overview

I. Learning Objectives II. Benefits III. Process IV. Presentation Strategies V. Conclusion

3

Page 4: Strategies For A Meaningful Design Review by Tom Anderson

Presentation Acronyms

• DR: Design Review • Cx: Commissioning • CxA: Commissioning Authority • OPR: Owners Project Requirements • BoD: Basis of Design

4

Page 5: Strategies For A Meaningful Design Review by Tom Anderson

II. Design Review Benefits

Owner asks:

• “Why Design Review?”

• “I hire the best architects & engineers.”

5

Page 6: Strategies For A Meaningful Design Review by Tom Anderson

Design Review Benefits

• CxA Provider Offers: – Independent set of eyes – Perspective from installations and

operations – Known areas of concern

• We all have individual, unique blind spots 6

Page 7: Strategies For A Meaningful Design Review by Tom Anderson

Financial Benefits of Design Review

• Can reduce construction costs – Examples:

• Avoidance of system oversizing • Chilled Water Design Delta T:

• Initial 10°F Delta T • DR: Use 15°F Delta T or greater • Reduced initial cost • Permanent reduced operating cost

7

Page 8: Strategies For A Meaningful Design Review by Tom Anderson

Financial Benefits • Real world example:

Burlington International Airport (BTV) Central Cooling Plant (240 ton)

An Energy Efficiency Upgrade Project

• DR alone increased savings by: • 150 MWh/yr 75 kW Peak ($7,500./yr) • DR Cost: $8,000.

8

Page 9: Strategies For A Meaningful Design Review by Tom Anderson

III. Design Review Process

When should DR occur?

IDEALLY: Schematic Design Design Development 95% CD (With controls 100% complete)

9

Page 10: Strategies For A Meaningful Design Review by Tom Anderson

III. Design Review Process

DR Verifies Compliance with

• Owners Project Requirements (OPR)

• Basis of Design (BoD)

10

Page 11: Strategies For A Meaningful Design Review by Tom Anderson

DR Process

• DR must be in Cx scope – Required for LEED Enhanced Cx

• Will not accept project without DR

– (Our company policy)

11

Page 12: Strategies For A Meaningful Design Review by Tom Anderson

DR Process Schedule

• CxA DR: 2 weeks • Designer Response: 1 week • CxA reviews response & closes items

with no further action required • DR Meeting: ASAP • CxA Updates: 2 days

12

Page 13: Strategies For A Meaningful Design Review by Tom Anderson

DR Meeting

• Face to Face meeting best • Owner presence is critical • Discuss solutions and next steps

13

Page 14: Strategies For A Meaningful Design Review by Tom Anderson

Sample DR Table

14

Page 15: Strategies For A Meaningful Design Review by Tom Anderson

Back-check

• Have items been implemented? • Check at each new DR phase • Designer follow-through is a frequent

problem

15

Page 16: Strategies For A Meaningful Design Review by Tom Anderson

Back-check

• Required for LEED Enhanced Cx • Document Back-check Results • Back-check: include in CxA fee

16

Page 17: Strategies For A Meaningful Design Review by Tom Anderson

IV. Presentation Strategies

• DR Comment Fundamentals: – Maintain a respectful/positive tone – Avoid authoritarian tone – Never ever make Designer look bad

• State the Issue

• State the Solution/Opportunity

17

Page 18: Strategies For A Meaningful Design Review by Tom Anderson

“In Our Experience”

• CxA experience is viable basis • Relate Cx problems from other projects

• CxA experience will be accepted

– most designers have minimal startup experience

• “Experience” is objective

18

Page 19: Strategies For A Meaningful Design Review by Tom Anderson

“In Our Experience Example” A Question Format is

• Highly Effective • Non Threatening

“Paddle type piping flow switches always pose a startup problem in our experience because they require field trimming based on specific flow.”

“Previous project experience has shown DP

type flow switches are far less problematic. Could DP switches be specified?”

19

Page 20: Strategies For A Meaningful Design Review by Tom Anderson

Reference Local Codes

Example:

“The control spec calls for mercury type piping thermometers. Recent State of Vermont legislation prohibits mercury.”

“Can alcohol type thermometers be used?”

Designer will appreciate being informed

20

Page 21: Strategies For A Meaningful Design Review by Tom Anderson

Design Conflicts Example:

“Reheat coil detail conflicts with the control schematic diagram.”

“…reconcile conflicts during final checking.” “… as the design progresses.” “… as the design is finalized.”

• Non-threatening • No one expects error free progress design

21

Page 22: Strategies For A Meaningful Design Review by Tom Anderson

Energy Cost Opportunities

• Identify Opportunity Clearly • Estimate Annual Savings

• Estimate cost impacts • Include spreadsheet (.pdf)

22

Page 23: Strategies For A Meaningful Design Review by Tom Anderson

Energy Cost Reduction Example:

• “Applying a VFD to the constant speed 10 HP HW pump will save 31,000 kWh and 4.5 kW and save $3,800./ Yr.”

• “Installation cost about $1,300.”

23

Page 24: Strategies For A Meaningful Design Review by Tom Anderson

Energy Cost Reduction CxA’s Need To:

• Have a clear understanding of efficiency opportunities

• Develop tools to quickly analyze

opportunities

24

Page 25: Strategies For A Meaningful Design Review by Tom Anderson

“Evolving Practice”

Be careful using “Good Practice” in comment: • Can appear subjective • Reference “newly available information”

• New approaches have been proven effective

25

Page 26: Strategies For A Meaningful Design Review by Tom Anderson

Evolving Practice Example • “VAV main supply duct calls for extractors and

splitters. The recently published “Advanced VAV System Design Guide, California Energy Commission” suggests avoiding these.

Reference: Advanced VAV System Design Guide, California Energy Commission

26

Page 27: Strategies For A Meaningful Design Review by Tom Anderson

Code/Standard Compliance

Reference a Code or Standard:

• A powerful method

HVAC: ASHRAE, SMACNA, etc. Plumbing: ASPE, etc.

Lighting: IESNA

27

Page 28: Strategies For A Meaningful Design Review by Tom Anderson

Code/Standard Compliance Example: • “Heating HW Control Diagram: VFD pump

DP sensor shown very close to pump sets.” • “ASHRAE Standard 90.1 – 2007, 6.5.4.1

states, ‘Differential pressure shall be measured at or near the most remote heat exchanger or the heat exchanger requiring the greatest differential pressure.’”

28

Page 29: Strategies For A Meaningful Design Review by Tom Anderson

Design Review Mindset

A Frustratingly Poor Design

• Avoid commenting when frustrated

• Imagine designer is close friend • Be tactful while working towards Owner’s

best interests

29

Page 30: Strategies For A Meaningful Design Review by Tom Anderson

Design Review Mindset Recognize:

• Team working to meet Owners‘ interests • Designers face time & financial pressures • Share knowledge & experience while being

respectful (They have knowledge too!)

30

Page 31: Strategies For A Meaningful Design Review by Tom Anderson

• Always listen to Designer Response

• Always Possible You Could be Wrong

• Every New Project:

– We Always Learn New Things

Could I Be Wrong?

31

Page 32: Strategies For A Meaningful Design Review by Tom Anderson

Technical Resources

• California Commissioning Collaborative

• Cx Assistant™

• cacx.org

32

Page 33: Strategies For A Meaningful Design Review by Tom Anderson

California Commissioning Collaborative:

Design Review Tool Module Master Reference Guide

http://resources.cacx.org/library/holdings/DesignReview Tool Master Reference Document.pdf

Technical Resources

33

Page 34: Strategies For A Meaningful Design Review by Tom Anderson

• DR is Most Valuable part of Cx Process

• It’s Really HOW You Say It

• Never Ever Make the Designer Look Bad,

but:

• Be Diligent Looking Out for Owners Interests