strategies for a meaningful design review - bcxa · 2016-09-28 · at the end of this session,...
TRANSCRIPT
Thomas Anderson, CCP
STRATEGIES FOR A MEANINGFUL DESIGN
REVIEW
21st National Conference on Building Commissioning
AIA Quality Assurance
The Building Commissioning Association is a Registered Provider with The American Institute of Architects Continuing Education Systems (AIA/CES). Credit(s) earned on completion of this program will be reported to AIA/CES for AIA members. Certificates of Completion for both AIA members and non-AIA members are available upon request.
This program is registered with AIA/CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product.
Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation.
21st NCBC Conference 2
Design Review Presentation Overview
I. Learning ObjectivesII. BenefitsIII.ProcessIV.Presentation StrategiesV.Conclusion
21st NCBC Conference 3
At the end of this session, participants will be able to:
1. Understand the methodology and process of meaningful design reviews
2. Learn presentation strategies to enable the designer and owner to seriously consider suggestions
3. Know how to support optimized system performance through design review
I. Learning Objectives
21st NCBC Conference 4
DR: Design ReviewCx: CommissioningCxA: Commissioning AuthorityOPR: Owners Project RequirementsBoD: Basis of Design
21st NCBC Conference
Presentation Acronyms
5
Owner asks:“Why Design Review?”
“I hire the best architects & engineers.”
21st NCBC Conference
II. Design Review Benefits
6
CxA Provider Offers:• Independent set of eyes• Perspective from installations and
operations• Known areas of concern
We all have individual, unique blind spots
21st NCBC Conference
Design Review Benefits
7
CxA Provider Offers:Can reduce construction costs Examples:
• Avoidance of system oversizing• Chilled Water Design Delta T:
o Initial 10° F Delta To DR: Use 15° F Delta T or greatero Reduced initial costo Permanent reduced operating cost
21st NCBC Conference
Financial Benefits of Design Review
8
Real world example:Burlington International Airport (BTV)
Central Cooling Plant (240 ton)An Energy Efficiency Upgrade Project
DR alone increased savings by:• 150 MWh/yr 75 kW Peak ($7,500./yr)• DR Cost: $8,000.
21st NCBC Conference
Financial Benefits
9
When should DR occur?IDEALLY:
Schematic DesignDesign Development95% CD (With controls 100% complete)
21st NCBC Conference
III. Design Review Process
10
DR Verifies Compliance with:
Owners Project Requirements (OPR)
Basis of Design (BoD)
21st NCBC Conference
Design Review Process
11
DR must be in Cx scope Required for LEED Enhanced Cx
Will not accept project without DR (Our company policy)
21st NCBC Conference
DR Process
12
CxA DR: 2 weeksDesigner Response: 1 weekCxA reviews response & closes items
with no further action requiredDR Meeting: ASAPCxA Updates: 2 days
21st NCBC Conference
DR Process Schedule
13
Face to Face meeting best
Owner presence is critical
Discuss solutions and next steps
21st NCBC Conference
DR Meeting
14
21st NCBC Conference
Sample DR Table
15
Have items been implemented?
Check at each new DR phase
Designer follow-through is a frequent problem
21st NCBC Conference
Back-check
16
Required for LEED Enhanced Cx
Document Back-check Results
Back-check: include in CxA fee
21st NCBC Conference
Back-check
17
DR Comment Fundamentals: Maintain a respectful/positive tone Avoid authoritarian tone Never ever make Designer look bad
State the Issue
State the Solution/Opportunity
21st NCBC Conference
IV. Presentation Strategies
18
CxA experience is viable basis
Relate Cx problems from other projects
CxA experience will be accepted most designers have minimal startup experience
“Experience” is objective
21st NCBC Conference
“In Our Experience”
19
CxA opinion not a viable basis
CxA “Opinion” is subjective
Everybody has one
21st NCBC Conference
“In Our Opinion”
20
Highly Effective Non Threatening
“Paddle type piping flow switches always pose a startup problem in our experience because they require field trimming based on specific flow.”
“Previous project experience has shown DP type flow switches are far less problematic. Could DP switches be specified?”
21st NCBC Conference
“In Our Experience” ExampleA Question Format is:
21
“The control spec calls for mercury type piping thermometers. Recent State of Vermont legislation prohibits mercury.”
“Can alcohol type thermometers be used?”
Designer will appreciate being informed
21st NCBC Conference
Reference Local Codes
Example
22
“Reheat coil detail conflicts with the control schematic diagram.”
“…reconcile conflicts during final checking.”“… as the design progresses.”“… as the design is finalized.”
Non-threateningNo one expects error free progress design
21st NCBC Conference
Design ConflictsExample
23
Identify Opportunity Clearly
Estimate Annual Savings
Estimate cost impacts
Include spreadsheet (.pdf)
21st NCBC Conference
Energy Cost Opportunities
24
“Applying a VFD to the constant speed 10 HP HW pump will save 31,000 kWh and 4.5 kW and save $3,800./ Yr.”
“Installation cost about $1,300.”
21st NCBC Conference
Energy Cost Reduction
Example:
25
CxAs Need To:
Have a clear understanding of efficiency opportunities
Develop tools to quickly analyze opportunities
21st NCBC Conference
Energy Cost Reduction
26
Be careful using “Good Practice” in comment:
Can appear subjective
Reference “newly available information”
New approaches have been proven effective
21st NCBC Conference
“Evolving Practice”
27
“VAV main supply duct calls for extractors and splitters. The recently published “Advanced VAV System Design Guide, California Energy Commission” suggests avoiding these.
21st NCBC Conference
Evolving Practice Example
Reference: Advanced VAV System Design Guide, California Energy Commission
28
Reference a Code or Standard:
A powerful method
HVAC: ASHRAE, SMACNA, etc.
Plumbing: ASPE, etc.
Lighting: IESNA
21st NCBC Conference
Code/Standard Compliance
29
• “Heating HW Control Diagram: VFD pump DP sensor shown very close to pump sets.”
• “ASHRAE Standard 90.1 – 2007, 6.5.4.1 states, ‘Differential pressure shall be measured at or near the most remote heat exchanger or the heat exchanger requiring the greatest differential pressure.’”
21st NCBC Conference
Code/Standard Compliance
Example:
30
A Frustratingly Poor Design
Avoid commenting when frustrated
Imagine designer is close friend
Be tactful while working towards Owner’s best interests
21st NCBC Conference
Design Review Mindset
31
Recognize:
Team working to meet Owners‘ interests
Designers face time & financial pressures
Share knowledge & experience while being respectful
(They have knowledge too!)
21st NCBC Conference
Design Review Mindset
32
Always listen to Designer Response
Always Possible You Could be Wrong
Every New Project:
• We Always Learn New Things
21st NCBC Conference
Could I Be Wrong?
33
California Commissioning Collaborative
Cx Assistant™
cacx.org
21st NCBC Conference
Technical Resources
34
California Commissioning Collaborative:
Design Review Tool ModuleMaster Reference Guide
http://resources.cacx.org/library/holdings/DesignReview Tool Master Reference Document.pdf
21st NCBC Conference
Technical Resources
35
DR is Most Valuable part of Cx Process
It’s Really HOW You Say It
Never Ever Make the Designer Look Bad, but:
Be Diligent Looking Out for Owners Interests
21st NCBC Conference
DR Conclusion
36