strategic open pit mine planning course.pdf
TRANSCRIPT
LQ
S L
ati
n A
meric
a A
venid
a L
uis
Th
ayer
Oje
da
013
0 O
fi. 30
4, P
rovid
encia
. S
anti
ago
, C
hil
e T
el:
562
-65
738
98
Fax:
56
2-6
5738
97
Toda la información contenida en este manual es de propiedad del Señor Kadri Dagdelen y cualquier reproducción parcial o total de la misma será sancionada legalmente.
Introduction to Mining Practices- Case Studies Open Pit Mining Terminology Pit Geometry and Slope Angles Open Pit Mine Planning Concepts - Circular Analysis Geologic Block Modeling Techniques Assay and Composite Sections and Block Modeling
Geostatistical Resource Estimation Techniques
Economic Definition of Ore Break-even Cutoff Grades and Stripping Ratio Analysis Economic Block Modeling, Cone and L&G Mining Analysis Final Pit Limits, Nested Pits and Mining Sequence Determination Cutoff Grade Policy, Scheduling and Stockpile Management
Mine Sequence, Cutoff Grade, Process Flow Determination
UNIT OPERATIONS AND EQUIPMENT SELECTION Drilling Fundamentals and Drill Selection Blasting Fundamentals Front End Loaders; Hydraulic Shovels and Cable Shovels Excavator Selection Considerations Equipment Cost Calculations Cat Handbook Truck Haulage and Cycle Times
Fleet Size Determination
Dispatch Systems In Pit Crushing and conveying systems
Mineral Processing
Mining Project Cash Flow Analysis Net Present Value Calculations
Mine Sequence, Cutoff grade and Process Flow NPV optimization
Papers by Kadri Dagdelen.
Bingham Canyon MinePorphyry Copper
Case Study
Sur
face
Min
e D
esig
n
2
Sur
face
Min
e D
esig
n
General Information
3
Sur
face
Min
e D
esig
n
General Information
•World’s first low grade copper mine.
•5 billion tons of material and 13 million tons of copper produced since 1906.
•Overall stripping ratio is 0.4:1.
•Mine daily production is 111 Kton of ore and 99.2 Kton of waste. (40 and 36 Mton/year respectively).
•Reserves are at 1.0 Btons @ 0.5% Cu per ton which results in 25 years mine life.
4
Sur
face
Min
e D
esig
n
General Information
•210 Kton of copper; 350 oz of gold; 2.5 MM oz of silverand 6350 ton of moly per year.
•2.5 miles long; 0.5 miles deep.
•Truck haulage – haul road 150 ft wide; also 3 tunnels for ore and waste haulage.
•Mine operates three 8-hour shifts per day, 365 days per year.
5
Sur
face
Min
e D
esig
n
General Information
Layout
6
Sur
face
Min
e D
esig
n
General Information
Geology
7
Sur
face
Min
e D
esig
n
General Information
•Block model dimensions 100 x 100 x 50 ft. Each block is assigned a value of Cu, Au, Ag, and Mo using a geostatistical technique known as kriging.
•Development drilling on 400 by 600 ft centers.
•Density 2.58 t/m3 or equivalent tonnage factor of 12.38 ft3/ton.
8
Sur
face
Min
e D
esig
n
Mine Plan
•Pushbacks range from 100 ft to 200 ft in width and 50 ft in height.
•Five ore shovel production faces to meet average grade and metallurgical blending requirements.
•Five waste shovel production faces to meet long range stripping requirements.
•Operating interramp pit slope, including bench face angles and catch benches, is 34o; catch benches are 50 ft wide.
9
Sur
face
Min
e D
esig
nMine Plan
Typical Mining Sequence
10
Sur
face
Min
e D
esig
n
Mine Plan
•Ore is being mined in lower 900 ft of the pit and highest active waste stripping occurs 2000 ft higher elevation.
•In extreme cases, mining room must be brought down nearly 40 benches before new ore is exposed; this process can take as long as seven years.
•Slope angles for the ultimate pit limits are defined by subdividing the pit surface in 26 sectors.
11
Sur
face
Min
e D
esig
n
Mine Plan
•Slope angles for each of these sectors range from 29 to 50 degrees.
•Slope angles will be achieved by double benching or single benching and control blasting – “digging to hard”.
•Slope dewatering using near horizontal drains improves slope angles by 3 to 5 degrees in the ultimate slope.
•Mining plans are developed by defining the volume of ore and waste between series of pushbacks.
12
Sur
face
Min
e D
esig
n
Mine Plan
•The material in pushbacks sequentially mined by a computerized mining simulator algorithm. Highest relative profit margin ore is mined first.
•Haulage roads are added to the incremental pits.
•Mine plan is a series of annual plans for five-year followed by five year plans to the end of mine life.
13
Sur
face
Min
e D
esig
n
Drilling
•Drills operate 5 days per week and two 8-hour shifts per day.
•8 Bucyrus-Erie 60R track-mounted electric drills.
•They can drill 57 to 65 ft in a single pass by exerting 120 Klb thrust.
•Rotary tricone bits with carbide inserts are used to drill 12.25 in diameter holes.
•One drill can drill 12 holes per 8-hour shift.
•Two drilltech D75K track-mounted units; carbide insert bits 9.875 in diameter – 4 35-ft drill rods.
14
Sur
face
Min
e D
esig
n
Drilling
•D75K drills are used in resilient (hard) formations where closer patterns are necessary for proper fragmentation.
•One secondary drill uses 2.5-in and 12-ft drill rods to drill boulders. Also mine has rubber-tired rock breaker.
•Drill patterns vary with the rock types but range from 30 x 30 ft to 36 x 36 ft for 12.25-in holes. 25 x 25 ft to 30 x 30 ft for 9.875-in holes.
15
Sur
face
Min
e D
esig
n
Blasting
•Two ANFO trucks – blending of ammonium nitrate prills and fuel oil occurs when bulk delivery trucks deliver these material to the mine-site storage tanks.
•Commercial bulk emulsion-blend explosives are used in wet holes.
•Holes are primed with two 0.75-lb boosters placed near the bottom of the explosive column.
•A 200-ms delay is inserted into each booster and connected to individual 7.5-grain primaline down-lines.
16
Sur
face
Min
e D
esig
n
Blasting
•25 grain detonating cord is used for trunk lines and cross ties.
•Surface delays of 17 ms are used between holes and 100 ms between rows.
•A single strand of detonating cord extended from the pattern and initiated by a non-electric cap taped to the cord.
•Drill cuttings are used for stemming. Each hole produces 2.4 to 3.7 tons of cuttings. These cuttings are forced into loaded holes.
17
Sur
face
Min
e D
esig
n
Blasting
•Powder factor varies between 0.13 to 0.25 lbs of explosive per ton depending on rock type; average 0.16 lb per ton.
•Ground motion due to blasting is limited to 25 in/sec at the planned final pit slopes.
18
Sur
face
Min
e D
esig
n
Loading
•2 15-yd3 P&H2100; availability averages 78%; 10 Ktons per shovel shift.
•4 27-yd3 P&H2800 Mark II; availability averages 80%; 15 Ktons per shovel shift.
•3 30-yd3 P&H 2800 XP; availability averages 80%; 15 Ktons per shovel shift.
• 2 34-yd3 P&H 2800 XPA; availability averages 80%; 20 Ktons per shovel shift.
•2 8-yd3 International; 1 12-yd3 Clark; 2 12-yd3
Caterpillar rubber tired FEL’s.
19
Sur
face
Min
e D
esig
n
Loading
•Power is provided by 44-kva substations; radial lines are then fed to smaller substations with voltage reduced to 5500 V ac.
•Electric connections between the switch houses and shovels are made through trailing cables up 2000 ft for shovels and 3000 ft for the drills.
20
Sur
face
Min
e D
esig
n
Haulage
•Mainly trucks and some rail.
•Truck haulage utilizes a fleet of 44 trucks composed of 28 190-ton CAT-785 mechanical drive; 8 170-ton Unit Rig diesel electric; 8 170-ton Wabco diesel electric trucks.
•In 1990 34 truck-shifts/shift are scheduled with average availability of 94% for the new, larger trucks; 84% for the smaller, older trucks.
•All trucks are equipped with two-way radios to assist appropriate dispatching.
21
Sur
face
Min
e D
esig
n
In-Pit Crusher
•Movable, 60- by 109-in, 1000-hp Allis Chalmers gyratory crusher that has a capacity of 120,000 tons per day on continuous basis.
•Two trucks at a time at a dumping rate of one truck per minute.
•3 to 4 weeks are required to move the crusher.
•-10 in crushed rock is fed directly to a 72-in conveyor.
•The belt is 5 mile ling to Copperton concentrator and capable of carrying 10,000 tph at 900 ft/min speed.
22
Sur
face
Min
e D
esig
n
Road Maintenance
•28 miles of haulage roads and 40 miles of service roads.
•20 dozers (CAT D9H, D9L, D10L).
•11 graders (CAT 16G).
•2 scrappers (CAT 631).
•4 salt trucks (5.4 or 6 ton capacity).
•6 water trucks (converted 65-ton or 59-ton haulage trucks; 10,000 to 30,000 gallons capacity).
Sur
face
Min
e D
esig
n
Open Pit Mining Fundamentals
Dr. Kadri Dagdelen
Colorado School of Mines
2
Sur
face
Min
e D
esig
n
Terminology
• BENCH: Ledge that forms a single level of operation above which mineral or waste materials are mined from the bench face.
3
Sur
face
Min
e D
esig
n
Terminology (Cont.)
• BENCH HEIGHT: Vertical distance between the highest point on the bench (crest) and the lowest point or the bench (toe). It is influenced by size of the equipment, mining selectivity, government regulations and safety.
4
Sur
face
Min
e D
esig
n
Terminology (Cont.)
• BENCH SLOPE OR BANK ANGLE : Horizontal angle of the line connecting bench toe to the bench crest.
5
Sur
face
Min
e D
esig
n
Terminology (Cont.)
• BERM: Horizontal shelf or ledge within the ultimate pit wall slope left to enhance the stability of the a slope within the pit and improve the safety.Berm interval, berm width and berm slope angle are determined by the geotechnical investigation.
6
Sur
face
Min
e D
esig
n
Terminology (Cont.)
• OVERALL PIT SLOPE ANGLE: The angle measured from the bottom bench toe to the top bench crest. It is the angle at which the wall of an open pit stands and it is determined by: rock strength, geologic structures and water conditions.
7
Sur
face
Min
e D
esig
n
Terminology (Cont.)
• The overall pit slope angle is affected by the width and grade of the haul road.
8
Sur
face
Min
e D
esig
n
Terminology (Cont.)
• HAUL ROADS: During the life of the pit a haul road must be maintained for access.
• HAUL ROAD - SPIRAL SYSTEM: Haul road is arranged spirally along the perimeter walls of the pit.
9
Sur
face
Min
e D
esig
n
Terminology (Cont.)
• HAUL ROAD – SWITCH BACK SYSTEM: Zigzag pattern on one side of the pit.
• HAUL ROAD WIDTH: Function of capacity of the road and the size of the equipment. Haul road width must be considered in the overall pit design.
10
Sur
face
Min
e D
esig
n
Haul Road Effect on Pit Limits
11
Sur
face
Min
e D
esig
n
Terminology (Cont.)
• ANGLE OF REPOSE: Maximum slope of the broken material.
• SUBCROP OR ORE DEPTH: Depth of waste removed to reach initial ore.
• PRE-PRODUCTION STRIPPING: Stripping done to reach initial ore.
12
Sur
face
Min
e D
esig
n
Terminology (Cont.)
• ULTIMATE PIT LIMITS: Vertical and lateral extend of the economically mineable pit boundary. Determined on the basis of cost of removing overburden or waste material vs. the mineable value of the ore.
• PIT SCHEDULING: Material may be mined from the pit either in 1) sequential pushbacks 2) conventional pushbacks.
13
Sur
face
Min
e D
esig
n
Terminology (Cont.)
• STRIPPING RATIO: Expressed in tons of waste to tons of ore in hard rock open pit operations. Critical and important parameter in pit design and scheduling
• AVERAGE STRIP RATIO: Total waste divided by total ore within the ultimate pit.
• CUTOFF STRIPPING RATIO: Costs of mining a ton of ore and associated waste equals to net revenue from the ton of ore.
14
Sur
face
Min
e D
esig
n
Single Working Bench
15
Sur
face
Min
e D
esig
n
Shovel in Working Bench
16
Sur
face
Min
e D
esig
n
Two Working Benches
17
Sur
face
Min
e D
esig
n
Final Pit Limit
18
Sur
face
Min
e D
esig
n
Cresson Mine – Year 2001
19
Sur
face
Min
e D
esig
n
Cresson Mine – Year 2007
20
Sur
face
Min
e D
esig
n
Cresson Mine – Year 2011
21
Sur
face
Min
e D
esig
n
Pit Sequence (1)
22
Sur
face
Min
e D
esig
n
Pit Sequence (2)
23
Sur
face
Min
e D
esig
n
Pit Sequence (3)
24
Sur
face
Min
e D
esig
n
Pit Sequence (4)
25
Sur
face
Min
e D
esig
n
Section of Pit Sequence
Dr. Kadri Dagdelen
Colorado School of Mines
Source: Hustrulid and KuchtaOpen Pit Mine Planning and Design
Open Pit Mine Planning and Design: Fundamentals
Sur
face
Min
e D
esig
n
2
Geometrical Considerations
Parts of a bench
Cumulative frequencydistribution of measured
bench face angles (Call, 1986).
Sur
face
Min
e D
esig
n
3
Geometrical Considerations
Section through a working bench.Functioning of catch benches.
Sur
face
Min
e D
esig
n
4
Geometrical Considerations
Double benches at final pit limits. Catch bench geometry (Call, 1986).
Typical catch bench design dimensions (Call, 1986).Bench height Impact zone Berm height Berm width Minimum bench width
(m) (m) (m) (m) (m)15 3.5 1.5 4 7.530 4.5 2 5.5 1045 5 3 8 13S
urfa
ce M
ine
Des
ign
5
Geometrical Considerations
Safety berms at bench edge
Sur
face
Min
e D
esig
n
6
Geometrical Considerations
Height of reach as a function of bucket size.Sur
face
Min
e D
esig
n
7
Geometrical Considerations
Example orebody geometry.Ramp access for the example orebody.
Blast design for the ramp excavation.Sur
face
Min
e D
esig
n
8
Shovel Working Range
Sur
face
Min
e D
esig
n
9
Geometrical Considerations
Minimum width drop cutgeometry with shovelalternating from side to side.
Sur
face
Min
e D
esig
n
10
Geometrical Considerations
Minimum width drop cutgeometry with shovelalternating from side to side.
Sur
face
Min
e D
esig
n
11
Geometrical Considerations
Isometric view of the ramp in waste approaching the orebody.
Diagrammatic representation of the expanding mining front.
Sur
face
Min
e D
esig
n
12
Geometrical Considerations
Dropcut / ramp placement in ore. Expansion of the mining front.
Sur
face
Min
e D
esig
n
13
Geometrical Considerations
Plan view of an actual pit bottomShowing drop cut and miningExpansion (McWilliams, 1959).
Sur
face
Min
e D
esig
n
14
Geometrical Considerations
Extension of the currentRamp close to the pit wall(McWilliams, 1959).
Sur
face
Min
e D
esig
n
15
Geometrical Considerations
Creating initial access / benches.
Shovel cut sequence when initiatingbenching in a hilly terrain (Nichols, 1956).
Sidehill cut with a shovel.
Sur
face
Min
e D
esig
n
16
Geometrical Considerations
Detailed steps in the development of a new production level.Sur
face
Min
e D
esig
n
17
Geometrical Considerations
Parallel cut with drive by.Sur
face
Min
e D
esig
n
18
Geometrical Considerations
Parallel cut with the double spotting of trucks.Sur
face
Min
e D
esig
n
19
Geometrical Considerations
Parallel cut with the single spotting of trucks.Sur
face
Min
e D
esig
n
20
Geometrical Considerations
Time sequence showing shovelloading with single spotting.
Sur
face
Min
e D
esig
n
21
Geometrical Considerations
(Continued).Sur
face
Min
e D
esig
n
22
Geometrical Considerations
Time sequence showing shovelloading with double spotting.
Sur
face
Min
e D
esig
n
23
Geometrical Considerations
(Continued).
Sur
face
Min
e D
esig
n
24
Geometrical Considerations
(Continued).Sur
face
Min
e D
esig
n
25
Geometrical Considerations
Section and plan views through a working bench.
Simplified presentation of a safety berm.
Sur
face
Min
e D
esig
n
26
Geometrical Considerations
Initial geometry for the push back example.
Cut mining from bench 1.
Cut mining from bench 2.
Sur
face
Min
e D
esig
n
27
Geometrical Considerations
Overall slope angle.
Safety bench geometryshowing bench face angle.
Sur
face
Min
e D
esig
n
28
Geometrical Considerations
Overall slope angle with ramp included.
Interramp slope angles.
Sur
face
Min
e D
esig
n
29
Geometrical Considerations
Overall slope angle withWorking bench included.
Interramp angles associated withthe working bench.
Sur
face
Min
e D
esig
n
30
Geometrical Considerations
Overall slope angle withone working bench an a ramp section.
Interramp slope angles for a slope containinga working bench and a ramp.
Sur
face
Min
e D
esig
n
31
Geometrical Considerations
Overall slope angle for a slope containing two working benches.Sur
face
Min
e D
esig
n
32
Geometrical Considerations
Slopes for each working group.
Sur
face
Min
e D
esig
n
33
Geometrical Considerations
Final overall pit slope.Sur
face
Min
e D
esig
n
Advances in Pit Slope Management SystemsAdvances in Pit Slope Management Systems
Dr. Kadri DagdelenProfessor
Mining Engineering DepartmentColorado School of MinesGolden, Colorado 80401
Pit Slope Failure ProblemsPit Slope Failure Problems
l Continue to be the source of human and financial losses
l Recent examples from Wyoming coal mines and Grasberg pit in Indonesia point to additional research needs to be done in the area of pit slope management
l Pit slope monitoring research is undertaken at the Colorado School of Mines using Lidar Scanners with funding from Kennocott Energy and 3-DP
Plane FailurePlane Failure
l Failure plane must daylight in the slope face; i.e. its dip must be smaller than slope (S>P)
l Plane must strike parallel or nearly parallel (within 20o) to the slope face.
l Less common than other failure modes
Plane Failure in a Limestone Plane Failure in a Limestone QuarryQuarry
Wedge FailureWedge Failure
DAYLIGHTING WEDGE
NON-DAYLIGHTING WEDGE
• Most common mode of failure for rock slopes
• Line of intersection must daylight into slope face
• Often, failure is sudden
Circular FailureCircular Failure
l Soilsl Stock pilesl Reclamation pilesl Waste dumpsl Highly weathered overburden rocks
Toppling and StepToppling and Step--Path Path ModesModes
Toppling Mixed modes(e.g. Toppling & Step-Path)
Overall Slope DesignOverall Slope Design
l Identify geological sectors; their strength characteristics and possible mode of failures
l Determine maximum height and angle for inter-ramp design
l Determine bench geometryl Incorporate bench geometry into Inter-ramp
designl Overall slope design
Failure Modes in Different Failure Modes in Different Sectors Sectors
Pit Slope Monitoring Pit Slope Monitoring -- What to look for What to look for
l Overhang rockl New geological structuresl Swell and/or increased rock fall activity on highwalll Heavy precipitationl Signs of stressl Tension cracksl Movement (acceleration)l Increased water levels
Tension Crack Measurements Tension Crack Measurements l The formation of cracks behind slope is a sign of instability
(Safety Factor ˜ 1)l Monitoring changes in crack width and direction can provide
information on extent of unstable area
InclinometersInclinometers
l Inclinometers measure horizontal deflections of a borehole
l They can- Locate failure surface - Determine nature of failure surface
(rotational or planar)- Measure movement along failure
surface and determine if movement is accelerating
Borehole extensometerBorehole extensometer
l Consists of tensioned rods anchored at different points in a borehole.
l Measures changes in distance between anchors, as well as collar
l Provides displacement information across discontinuities.
New and Emerging TechnologiesNew and Emerging Technologiesl Automated Total Station Network (robots)
l Non-reflective Laser scanners (Lidar systems: Cyra, Riegl, I-Site)
l Radar Technologies
l GPS (Local sensors with multiple antenna)
l TDR (Time Domain Reflectometry)
l Digital photogrammetry
l Arial photography (Kodak)
Automated Total Station Network in Automated Total Station Network in Chuquicamata Mine, ChileChuquicamata Mine, Chile
• A network of automated total stations for geotechnical monitoring of pit slopes that operate continuously 24 hours a day, 7 days a week and during the 365 days a year.
• Provide a reliable and quantitative information in real time thatallows to establish with anticipation the behavior of the rock massand geologic structures on the pit slopes.
Completely Automated Electronic Completely Automated Electronic Station Network using Station Network using LeicaLeica TCA2003TCA2003
Motorized Station, Leica TCA2003
Characteristics• Reach with 1/3 prisms in average
atmospheric conditions : 2500/3500 mts.• Precision in distance : 1mm + 1 ppm• Angular precision : 0.3” (0.1 mgon)• Increase of lens : 30 x• Compartment for the insertedable
memory card PCMCIA.• Integrated application programs :
Reframing, orientation of horizontal circleand drag of levels, reseccion anddistance of connection between twopoints.
• Capture of information in modality ATR and DIST.
WirelessWireless CommunicationCommunication NetworkNetworkBridge
Bluebox
Switch
Energy
SHELTER 1
SHELTER 2
SHELTER 6
SHELTER 5
ARTURO OESTE
SHELTER 3
SHELTER 4
ARTURO ESTE
CONTROL ROOM ETHERNET NETWORK
SHELTER 1
SHELTER 2
SHELTER 6
SHELTER 5
ARTURO OESTE
SHELTER 3
SHELTER 4
ARTURO ESTE
CONTROL ROOMCONTROL ROOM
LocationLocation of Stations of Stations andand IntegrationIntegration of of InformationInformation
Software of Information Integration
• Have a Computational Software that allows to totally integrate and administer the acquisition of geotechnical data, procesingand analisis of the information in real time originating from therobotic system (TCA) intalled in each of the monitoring stations.
Total Station and Prism Locations in Total Station and Prism Locations in Chuquicamata Mine, ChileChuquicamata Mine, Chile
CasetaEste
CasetaOeste
GPS Surveyed Control Stations in GPS Surveyed Control Stations in Chuquicamata Mine, ChileChuquicamata Mine, Chile
Coordenadas de laEstación de MonitoreoAPS(N;E;Z)
ZONA-5 ZONA-6 ZONA-7
D1 D2 D3D4
“D” (PR-1)
“E1” (PR-2) Matus (PR-3)
GT-1 PR-4
Morgan (PR-5)
S4
S3
S5
S2
S1
D5
.
PILAR GT-1
APS-WEST. Norte : 2085.491Este : 3870.863Elev
Cota : 2846.745
Slope Stability Radar Technology Slope Stability Radar Technology from from GroundProbeGroundProbe of Australiaof Australia
Complete Pit Wall Coverage from Complete Pit Wall Coverage from Remote LocationsRemote Locations
Radar Scan Lines
Location and Time of Wall Location and Time of Wall MovementsMovements
18:13 8th October 2003
20:47 8th October 2003
23:22 8th October 2003
02:04 9th October 2003
Dis
plac
emen
t (m
m)
Incr
easin
g dis
place
men
t with
time
Slip Area
Slope Stability Radar FeaturesSlope Stability Radar Features• High deformation precision (± 0.2 mm std. dev.)
• Broad area coverage (~1000’s pixels/scan)
• Continuous operation (~ 1’s min/scan, 24 hrs/day)
• 30-850m range
• All weather operation (incl. dust, fog)
• Rapid Deployment
• Remote Operation via radio link and internet
• High resolution CCD Camera
• Custom software with alarm settings
SSRViewerSSRViewer Images ScreenImages Screen
SSRViewerSSRViewer Figures ScreenFigures Screen
10mm movement over 45 hours in Region 1
0.0mm movement over 45 hours in Region 2
15mm movement over 45 hours in Region 3
Laser Scanning TechnologiesLaser Scanning TechnologiesThere are Many 3D Laser Scanners There are Many 3D Laser Scanners
Major Companies with Products are:Major Companies with Products are:
ll CyraxCyrax ((LeicaLeica) ) www.cyra.comwww.cyra.com (USA)(USA)ll OptechOptech ILRIS (Canada)ILRIS (Canada)ll II--site (site (MaptekMaptek) ) www.isite3d.comwww.isite3d.com (Australia)(Australia)ll LMS 3D Scanning systems (Riegl) LMS 3D Scanning systems (Riegl) www.riegl.co.at www.riegl.co.at
(Austria)(Austria)ll Z+F Laser Measuring Systems (Z+F Laser Measuring Systems (ZollerZoller+ + FröhlichFröhlich) )
www.zofre.dewww.zofre.de (Germany)(Germany)
CyraxCyrax 24002400
Other Application in Laser Technologies Other Application in Laser Technologies Riegl Z 210i Lidar Laser ScannerRiegl Z 210i Lidar Laser Scanner
•1200+ ft scan range•2.5cm accuracy @ 900 ft•5 cm accuracy > 900 ft•361 degrees x 80 degree scan•9000 Hz
SpecificationsSpecifications
Riegl LPM 800 HARiegl LPM 800 HA
•3000 ft scan range1cm accuracy @ 1250 ft2 cm accuracy > 1250 ft
•0.018 degrees step size•360 degrees of horizontal rotation•180 degrees of vertical rotation •1000 Hz
SpecificationsSpecifications
Riegl Z 420 Lidar Laser ScannerRiegl Z 420 Lidar Laser Scanner
•2400+ ft scan range•1cm accuracy in topo mode•6 mm accuracy in detail mode•0.01 degree step size•361 degrees x 90 degree scan window•8000 - 12000 Hz
SpecificationsSpecifications
High Wall Scan (Pre Blasting)High Wall Scan (Pre Blasting)
PostPost--Blast ScanBlast Scan
Pre Blast TrianglesPre Blast Triangles
Post Blast TrianglesPost Blast Triangles
Combined Combined –– Pre / PostPre / Post
Dynamic Cross SectionDynamic Cross Section
Complete Pit Scan using Complete Pit Scan using RieglRiegl
Pit Wall Scan Using Pit Wall Scan Using RieglRiegl
Pit Wall Failure Scan Pit Wall Failure Scan -- RiegleRiegle
NoModerate< 150 m~ hoursBroad Area
~ 1’s cmPhotogram-metry
YesDifficultn/a~ secsDiscrete Points
~ 1’s cmGPS
Extenso-meters
LIDAR SCANNER
Laser (Prisms)
SSR –GROUND PROBE
Technology
YesEasy850 m(1.4km)
~ minsBroad Area
± 0.2 mm
NoDifficult2 kmTwice Daily
Discrete Points
~ 1’s cm
NoEasy900 m~ secsBroad Area
~ 1’s cm
Difficult
Deployment
Yesn/a~ secsDiscrete Points
~ 1’s mm
All weather
RangeUpdate Rate
Wall Coverage
Precision
Slope Monitoring Systems
Slide Management OptionsSlide Management Optionsl Reduce slope anglel Dewater unstable areal Leave unstable areasl Continue miningl Unload slidel Partial clean upl Step-out
l Reduce slope height by segmenting the slope
l Support unstable groundl Contingency Planningl Blastingl Erosion control measures
(reclamation)- Geotextiles against erosion
and raveling- Vegetating and planting
Instability can be left alone if it is in
– an abandoned area,
– an inactive area,
– an area that can be avoided
Leave Unstable Areas untouchedLeave Unstable Areas untouched
Continue miningContinue miningIf the displacement rate is low and predictable, living with the displacement while continuing to mine may be the best action.
Dis
plac
emen
t (cm
)
Time
1/4/02 5/4/02 11/4/02 16/4/02
50
100
150 May continue mining (displacement rate is constant)
Basic Principles of DrainageBasic Principles of Drainagel Prevent surface water from entering to the slope through
open tension cracks and fissuresl Reduce water pressure in the vicinity of the potential
failure surface l Providing for gravity flow of water is the most common
methodl Pumping is used on a temporary basis depending on the
urgency of the problem
Bench section view
Inclined bench for gravity flow
Slope crest
Bench face view
Benches sloped toward toe
Method of Slope DrainageMethod of Slope Drainage
POST
FLOWER PATCH
EXPL
ODI
NG
BLIND RODEO CREEK 1RODEO CREEK
GRAND JE
AN
AM
AN
DA
ANTI
POST
CH
RIS
TYS
DORM
ANT
JB
AN
FO
PA
TS
MIDNIGHT
60
60
60
50
85
80
60
55
50
25
60
60
75
N-00-B
EM
ILYS
LAST LAUGH78
RODEO CREEK
BLIND RODEO CREEK 1P
OW
ER
FUL
Horizontal Drain NetworkHorizontal Drain Network(303 drains/34 miles since 1999)(303 drains/34 miles since 1999)
Unload SideUnload Side
l Even though unloading has been a common response, in general it has been unsuccessful.
l In fact, there are situations involving high water pressure where unloading actually decreases stability.
Partial cleanPartial clean--upup
• Partial cleanup may be the best choice where a slide blocks a haul road or fails onto a working area
• Only that material necessary to get back into operation need be cleaned up
New (Flatter) Overall Slope Angle
Old Overall Slope Angle
Originally Planned Slope DesignNew Slope Design
Failure SurfaceStep out
StepStep--outoutl Increased highwall stability due
to shallower slope angle It locks up reserves
lAdvantages of leaving step out should be weighed against cleaning by considering ore lock up and having safer overall slope
Reduce slope height by Reduce slope height by segmenting slopesegmenting slope
Support unstable groundSupport unstable ground
Buttress
Rock Bolts
Anchors, Tiebacks, and Anchors, Tiebacks, and ShotcreteShotcrete
1. Reinforced concrete dowel to prevent loosening of slab at crest
2. Tensioned rock anchors to secure sliding failure along crest
3. Tieback wall to prevent sliding failure on fault zone
4. Shotcrete to prevent raveling of zone of fractured rock
5. Drain hole to reduce water pressure within slope
6. Concrete buttress to support rock above cavity
Mesh & BoltsMesh & Bolts
ButtressingButtressing
ButtressingButtressing
NE Wall Sept 2002NE Wall Sept 2002
2% ramp & buttress
mudslide
4880 buttress
unwting cut
N-00-B
4640
4280
NE Wall UnNE Wall Un--weighting Cutweighting Cut
Prism Data Feb 2002 to Feb 2003Prism Data Feb 2002 to Feb 2003PRISM DATA - All In Movement Area
-2.00
-1.80
-1.60
-1.40
-1.20
-1.00
-0.80
-0.60
-0.40
-0.20
0.00
0.20
2/1/02
2/15/0
23/1
/02
3/15/0
23/2
9/024/1
2/024/2
6/02
5/10/0
25/2
4/02
6/7/02
6/21/0
27/5
/02
7/19/0
28/2
/02
8/16/0
28/3
0/029/1
3/029/2
7/02
10/11
/02
10/25
/0211
/8/02
11/22
/0212/
6/02
12/20
/021/3
/03
1/17/0
31/3
1/032/1
4/032/2
8/03
DATE
MO
VE
ME
NT
IN (
INC
HE
S/D
AY
)
TN000084
TN000089
TN010095
TN010119
TN 80
TN 72
TN 97
TN 98
TN 101
TN 114
TN 115
TN 127
TN 144
TN 149
#3
#4
BlastingBlasting
Use of less charges next to toe
Linedrillholes
Productionholes Face
Pre-splitting Line drilling
SAFETY BERMCatch
Berm, ± 40 m. H13
BENCH
D5 BENCH
PUSHBACK
> 10 cm/dayStop push-back development
5 a 10 cm/dayOnly ore production stripping
2 a 5 cm/dayNormal
Displacement ratePUSHBACK DEVELOPMENT
Slide Management ExampleSlide Management Example
y = 63.213x - 2E+06
y = 16.016x - 597363
y = 8.7432x - 326060
y = 5.6082x - 209126
0
50
100
150
200
250
300
1/2/02 6/2/02 11/2/02 16/2/02 21/2/02
TIEMPO
DES
PLA
ZAM
IEN
TO (c
m)
Took outshovel
Access D5& H13 closed
Failure
Contingency PlanningContingency Planning
l Provide multiple access to production facesl Maintain double access to working benches,
whenever possiblel Stockpile ore/rockl Design to prevent noses in the plan geometryl Provide for failure costs in scheduling and budgetingl Add lag times in production schedulingl Plan step-outs
ConclusionsConclusions
l New Radar and Lidar based technologies applied to pit slope monitoring appears to be very promising in providing cost effective and accurate real time data .
l Accurate and reliable slope displacement information coupled with proper pit slope management practices has a potential to prevent unexpected catastrophic pit slope failures.
Haul Road Design
Dr. Kadri Dagdelen
Colorado School of Mines
Sur
face
Min
e D
esig
n
2
Sur
face
Min
e D
esig
n
Haul Road Design
• HAUL ROADS: During the life of the pit a haul road must be maintained for access.
• HAUL ROAD - SPIRAL SYSTEM: Haul road is arranged spirally along the perimeter walls of the pit.
3
Sur
face
Min
e D
esig
n
Haul Road Design
• HAUL ROAD – SWITCH BACK SYSTEM: Zigzag pattern on one side of the pit.
• HAUL ROAD WIDTH: Function of capacity of the road and the size of the equipment. Haul road width must be considered in the overall pit design.
4
Sur
face
Min
e D
esig
n
Haul Road Effect on Pit Limits
5
Considerations for Haul Road Design
Sur
face
Min
e D
esig
n
• Visibility• Stopping distances• Vertical alignment• Horizontal alignment• Cross section• Runaway-vehicle safety
provisions
6
Sight Distances and Stopping Distances
Sur
face
Min
e D
esig
n
• Vertical and horizontal curves designed considering sight distance and stopping distance
• Sight distance is the extent of peripheral area visible to the vehicle operator
• Sight distance must be sufficient to enable vehicle traveling at a given speed to stop before reaching a hazard
7
Sight Distances and Stopping Distances
Sur
face
Min
e D
esig
n
• On vertical curves, road surface limits sight distance
• Unsafe conditions remedied by lengthening curve• On horizontal curves, sight distance limited by
adjacent berm dike, rock cuts, trees, etc; • Unsafe conditions remedied by laying back bank or
removing obstacles
8
Sight Distance Diagrams
Sur
face
Min
e D
esig
n
⇒
Sight distance diagrams for horizontal and vertical curves(Kaufman and Ault)
9
Stopping Distances
Sur
face
Min
e D
esig
n
• Stopping distances depend on truck breaking capabilities, road slope and vehicle velocity
• Stopping distance curves can be derived based on SAE service break maximum stopping distances
10
Stopping Distance Characteristics
Sur
face
Min
e D
esig
n
For example, stopping distance characteristics of vehicles of 200,000 to 400,000 pounds GVW
(Kaufman and Ault)
11
Stopping Distances
Sur
face
Min
e D
esig
n
• Prior to final road layout, manufacturers of vehicles that will use the road should be contacted to verify the service brake performance capabilities
12
Vertical Alignment
Sur
face
Min
e D
esig
n
• Establishment of grades and vertical curves that allow adequate stopping distances on all segments of the haul road• Maximum sustained grades
• Reduction in grade significantly increases vehicle uphill speed• Reduction in grade decreases cycle time, fuel consumption, stress
on mechanical components and operating costs• Reduction in grade increases safe descent speeds, increasing
cycle time• The benefits of low grades offset by construction costs associated
with low grades
13
Vehicle Performance Chart
Sur
face
Min
e D
esig
n
14
Vehicle Retarder Chart
Sur
face
Min
e D
esig
n
15
Vertical Alignment
Sur
face
Min
e D
esig
n
• Maximum sustained grades• Some states limit maximum grades to 15 to 20% and
sustained grades of 10%• Most authorities suggest 10% as the maximum safe
sustained grade limitation• Manufacturer studies show 8% grades result in the
lowest cycle time exclusive of construction consideration
16
Vertical Alignment
Sur
face
Min
e D
esig
n
• Maximum sustained grades• Property boundaries, geology, topography, climate
must be considered on a case by case basis. • Lower operating costs must be balanced against higher
capital costs of low grades.• Truck simulators and mine planning studies over the
life of mine should be used to make the determination of the appropriate grades
17
Vertical Curves
Sur
face
Min
e D
esig
n
• Vertical curves smooth transitions from one grade to another
• Minimum vertical curve lengths are based on eye height, object height, and algebraic difference in grade
18
Stopping Distance vs. Vertical Curve
Sur
face
Min
e D
esig
n
For example, vertical curve controls 9 ft eye height (usually minimum height for articulated haulage trucks of 200,000 to 400,000 pound of GVW)
19
Horizontal Alignment
Sur
face
Min
e D
esig
n
• Deals primarily with design of curves and considers previously discussed radius, width, and sight distance in addition tosuperelevation
• Cross slopes also should be considered in the design
20
Curves, Superelevation, and Speed Limits
Sur
face
Min
e D
esig
n
• Superelevation grade recommendations vary but should be limited to 10% or less because of traction limitations
• Depending on magnitude of the side friction forces at low speed, different values are suggested for small radius curves
• Kaufman and Ault suggest .04-.06 fpf(basically the normal cross slope)
21
Curves, Superelevation, and Speed Limits
Sur
face
Min
e D
esig
n
• CAT suggests higher slopes with traction cautions and 10% maximum caution
• Again, where ice, snow, and mud are a problem, there is a practical limit on the degree of superelevation
22
Curve Superelevation
Sur
face
Min
e D
esig
n
(CAT)
23
Recommended SuperelevationRates
Sur
face
Min
e D
esig
n
(Kaufman and Ault)
If superelevation is not used, speed limits should be set on curves.
24
Curves, Superelevation, and Speed Limits
Sur
face
Min
e D
esig
n
• Centrifugal forces of vehicles on curves are counteracted by friction between tire an road and vehicle weight as a result of superelevation
• Theoretically, with superelevation, side friction factors would be zero and centrifugal force is balanced by the vehicle weight component
• To reduce tire wear, superelevation or speed limits on curves are required
25
Combinations of Alignments
Sur
face
Min
e D
esig
n
• Avoid sharp horizontal curvature at or near the crest of a hill
• Avoid sharp horizontal curves near the bottom of sustained downgrades
• Avoid intersections near crest verticals and sharp horizontal curvatures
• Intersections should be made flat as possible• If passing allowed, grades should be constant and
long enough
26
Cross Section
Sur
face
Min
e D
esig
n
• A stable road base is very important• Sufficiently rigid bearing material should be
used beneath the surface• Define the bearing capacity of the material
using the California Bearing Ratio (CBR)
27
California Bearing Ratio
Sur
face
Min
e D
esig
n
28
Subbase Construction
Sur
face
Min
e D
esig
n
29
Sur
face
Min
e D
esig
n
Cross Slopes
• Cross slopes provide adequate drainage and range from ¼ to ½ inch drop per foot of width (approximately .02 to .04 foot per foot)
• Lower cross slopes used on smooth surfaces that dissipate water quickly and when ice or mud is a constant problem
30
Sur
face
Min
e D
esig
n
Cross Slopes
• Higher cross slopes permit rapid drainage, reduce puddles and saturated sub-base, and are used on rough surfaces (gravel and crushed rock) or where mud and snow are not a problem
• High cross slopes can be particularly problematic with ice or snow on high grades (+5%)
31
Sur
face
Min
e D
esig
n
Recommended Rate of Cross-Slope Change
(Kaufman and Ault)
Slope change should be gradual.
32
Sur
face
Min
e D
esig
n
Width
• On straight or tangent segments, width depends on• Vehicle width• Number of lanes• Recommended vehicle clearance, which ranges
from 44 to 50% of vehicle width
33
Sur
face
Min
e D
esig
n
Minimum Road Design Widths for Various Size Dump Trucks
(Couzens, SME Open Pit Planning and Design)
34
Sur
face
Min
e D
esig
n
Typical Design Haul Road Width
(Couzens, SME Open Pit Planning and Design)
Typical design haul-road width for two-way traffic using 77.11-t (85-st) trucks
35
Sur
face
Min
e D
esig
n
(Kaufman and Ault)
Typical Haulageway Sections
36
Sur
face
Min
e D
esig
n
Width
• Berm height and width as a function of vehicle size and material type
• Ditch(es) added to basic recommendations• Runaway provisions may also add to width• Road wider on curves because of overhang• Minimum turning radius considered on
curves (should be exceeded)
37
Sur
face
Min
e D
esig
n
⇒
Haulageway Widths on Curves
38
Sur
face
Min
e D
esig
n
Safety Provisions - Berms
• Triangular or trapezoidal made by using local material• Stands at natural angle of repose of construction
material• Redirects vehicle onto roadway• Minimum height at rolling radius of tire
39
Sur
face
Min
e D
esig
n
Berms
• Larger boulders backed with earthen material• Near vertical face deflects vehicle for slight
angles of incidence• Problems with damage and injury and
availability of boulders• Minimum height of boulder at height of tire
allowing chassis impact
40
Sur
face
Min
e D
esig
n
Runaway Provisions
• With adverse grades some safety provision should be integrated to prevent runaway vehicles
• Primary design consideration is required spacing between protective provisions
• Driver must reach a safety provision before truck traveling too fast to maneuver
• Maximum permissible speed depends on truck design conditions and operator
41
Sur
face
Min
e D
esig
n
Runaway Provisions
• Maximum permissible speed, equivalent downgrade, and speed at break failure determine distance between runaway truck safety provisions
• For example, at an equivalent downgrade of 5% and a maximum speed of 40 mph,
Speed at Failure 10 mph 20 mphProvision Spacing 1,000 ft 800 ft
(Kaufman and Ault)
42
Sur
face
Min
e D
esig
n
Runaway Precautions
(Atkinson SME Handbook)
43
Sur
face
Min
e D
esig
n
Median Runaway-Vehicle Provision Berms
• Vehicle straddles collision berm and rides vehicle to stop
• Made of unconsolidated-screened fines• Critical design aspects spacing between
berms and height of berm• Height governed by height of undercarriage
and wheel track governed by largest vehicle
44
Sur
face
Min
e D
esig
n
Median Runaway-Vehicle Provision Berms
• Requires maintenance in freezing conditions • Agitation to prevent damage to vehicle• May cover berm in high rainfall areas
45
Sur
face
Min
e D
esig
n
Escape Lanes
• Good tool for stopping runaway but expensive to construct
• Entrance from road is important; spacing, horizontal, vertical curve and superelevationare all considered in design
• Deceleration mainly by adverse grade and high rolling resistance material
46
Sur
face
Min
e D
esig
n
Escape Lanes
• Length a function of grade and speed at entrance and rolling resistance
• Stopping by level section median berm, sand or gravel or mud pits, road bumps or manual steering
47
Sur
face
Min
e D
esig
n
Escape Lanes
48
Sur
face
Min
e D
esig
n
Maintenance
• The road surface is deformed by the constant pounding of haulage vehicles.
• A good road maintenance program is necessary for safety and economics.
49
Sur
face
Min
e D
esig
n
Safety Considerations
• Dust, potholes, ruts, depressions, bumps, and other conditions can impede vehicular control.
50
Sur
face
Min
e D
esig
n
Economic Considerations
• The wear on every component is increased when a vehicle travels over a rough surface.
• If the vehicle brakes constantly, unnecessary lining wear occurs as well.
51
Sur
face
Min
e D
esig
n
Dust Control
• Dust may infiltrate brakes, air filters, hydraulic lifts, and other components of machinery.
• The abrasive effect of dust will result in costly cleaning or replacement of these items.
52
Sur
face
Min
e D
esig
n
Deterioration Factors
• Weather• Vehicles follow a
similar path• Spillage
53
Sur
face
Min
e D
esig
n
Motor Graders
• A motor grader should be used to maintain cross slopes, remove spills, and to fill and smooth surface depressions as they occur.
54
Sur
face
Min
e D
esig
n
Road Drainage
• To avoid overflow, roadside ditches and culverts should be periodically cleaned.
• Avoid erosion or saturation of subbase materials.
Haul Road Design
Open Pit Contour Maps
Dr. Kadri Dagdelen
Source: Hustrulid and Kuchta
Sur
face
Min
e D
esig
n
2
Sur
face
Min
e D
esig
n
Example of Mapping Procedure
3
Sur
face
Min
e D
esig
n
Plan View of a Portion of the Open Pit
Crests denoted by dashed lines and toes by solid lines.
4
Sur
face
Min
e D
esig
n
Example of Mapping Procedure
5
Sur
face
Min
e D
esig
n
Midbench Elevation
6
Sur
face
Min
e D
esig
n
Plan View of Midbench Elevation
7
Sur
face
Min
e D
esig
n
Map Based on Midbench Contours
8
Sur
face
Min
e D
esig
n
Procedure to Convert Midbench to Toe and Crest Contours
9
Sur
face
Min
e D
esig
n
Representation of Crests and Toes
10
Sur
face
Min
e D
esig
n
Designing a Spiral Ramp Inside the Wall
11
Sur
face
Min
e D
esig
n
Completing the new crest lines
12
Sur
face
Min
e D
esig
n
Pit Layout Including Ramp
13
Sur
face
Min
e D
esig
n
Design of a Spiral Ramp Outside the Wall
14
Sur
face
Min
e D
esig
n
Pit Layout Including Ramp
15
Sur
face
Min
e D
esig
n
Design of a Switchback
16
Sur
face
Min
e D
esig
n
Design of a Switchback
17
Sur
face
Min
e D
esig
n
Design of a Switchback
18
Sur
face
Min
e D
esig
n
Pit Layout Including Ramp
19
Sur
face
Min
e D
esig
n
Example of Two Switchbacks
20
Sur
face
Min
e D
esig
n
Plan and Section Views of Pit Without Ramp
21
Sur
face
Min
e D
esig
n
Plan and Section Views of Pit With Ramp
22
Sur
face
Min
e D
esig
n
Road Volume in the Ramp
1
Block Modeling and Ore Reserves Estimation
Dr. Kadri Dagdelen
Sur
face
Min
e D
esig
n
2
Basic Block Model Information
• Topography Data • Drill Data• Sampling• Assays
Sur
face
Min
e D
esig
n
3
Topography Data
3D Display (Color Coded Elevations)
Sur
face
Min
e D
esig
n
4
Drill Data
Drill Hole Data Sources
•Collar Coordinates•Geologic Logs•Down Hole Surveys•Lab Tests
Sur
face
Min
e D
esig
n
5
Samplings
Sampling Data
•Rock Types•Alteration Types•Metal Grades•Attributes
Sur
face
Min
e D
esig
n
6
Samplings (Cont.)
Data Collections
Sur
face
Min
e D
esig
n
7
Assays
Assay Data for Cu and Mo
Multiple Cutoffs
Rock Types
AlterationsSur
face
Min
e D
esig
n
8
Geological Interpretation
Section View Showing Topography and Alteration Types
Sur
face
Min
e D
esig
n
9
Geological Interpretation
Boundaries for rock types
Sur
face
Min
e D
esig
n
10
Geological Interpretation
Color Filled Display for Alteration Types
Sur
face
Min
e D
esig
n
11
3D Geological View
3D Display of Alteration Type Solids
(With Drill Hole Piercing Points)
Sur
face
Min
e D
esig
n
12
Composites
Composited Grade Data with Corresponding Assay Interval Data
Sur
face
Min
e D
esig
n
13
3D Block Models
3D View of the Block Models
Sur
face
Min
e D
esig
n
14
Block Estimation
Kriging - Geological Interpolation Technique for Ore Reserve Estimation
Sur
face
Min
e D
esig
n
15
Block Values
Block by Block Profit Values in Association with Block Grade Data and Alteration Type Boundaries
Sur
face
Min
e D
esig
n
16
Block Models
Interpolated Grades from Drill Hole Data
Sur
face
Min
e D
esig
n
17
Ore Reserve Estimation
Interpolated Grades from Drill Hole Data
Sur
face
Min
e D
esig
n
18
Economic Pit Limits
Economic Pit Limits for Different Economic Scenarios
Sur
face
Min
e D
esig
n
19
3D View of Economic Pit Limits
3D View of Economic Pit Limits for Different Economic Scenarios
Sur
face
Min
e D
esig
n
20
Mine Planning Application(Open Pit Mine)
Yearly Maps for the Open Pit Mine Scheduling
Sur
face
Min
e D
esig
n
21
Geologic Resource Modeling Techniques
• Exploratory Data Analysis• Variogram Analysis• Search Strategies• Simple Kriging, Ordinary Kriging, Indicator
Kriging, Co-Kriging• Cross Validation• Uncertainty and Risk Evaluation
Sur
face
Min
e D
esig
n
22
Frequency and Cumulative Frequency Plots
•Classical Statistics•Data Posting and Display•Histograms •Cumulative Histograms•Probability Plots
Sur
face
Min
e D
esig
n
23
Inverse Distance Technique
• In general, ∑∑=
=
=n
iin
ip
i
pi v
d
dv
1
1
1
1
ˆ
• Inverse distance technique is the simplest interpolation method.
• Give more weight to the closest samples, and less to those that are farthest away.
∑=
= n
ipi
pi
i
d
dw
1
1
1
∑=
=n
iiivwv
1
ˆ 11
=∑=
n
iiwS
urfa
ce M
ine
Des
ign
24
Inverse Distance Technique (pg257)
v1
v2
d1
d244
1
1
1
34
1
1
1
24
1
1
1
14
1
1
1
2
24
2
23
2
22
2
21ˆ vvvvv
id
d
id
d
id
d
id
d
iiii∑∑∑∑
====
+++=
v̂ Inverse Distance Square
• We can make the weights inversely proportional to any power of the distance.
• If p=2, it is called Inverse Distance Square.
d3
d4
v3
v4
Sur
face
Min
e D
esig
n
25
Inverse Distance Square Example
V1=0.2
V2=0.3
d1=1d2=2
v̂
• Estimate the unknown point by using the Inverse Distance Square technique
d3=4
V3=0.5
v̂
v1= 0.2 d1 =1
v2= 0.3 d2 =2
v3= 0.5 d3 =4
?ˆ =v
Sur
face
Min
e D
esig
n
26
Inverse Distance Square Example
• First of all, calculate the weights w1, w2, w3
21161
1621
241
221
211
211
1 ==++
=w
214
162141
241
221
211
221
2 ==++
=w
211
1621161
241
221
211
241
3 ==++
=w Note:1321 =++ www
Sur
face
Min
e D
esig
n
27
Inverse Distance Square Example
• Then, calculate
233.05.0211
3.0214
2.02116ˆ =×+×+×=v
v̂
Sur
face
Min
e D
esig
n
28
Estimation Error
• Error estimation between estimation (Exploration data) and true value (Blasthole data).
Error = Estimated Grade – True Grade
e.g., Estimation Error for Block 1 = 0.463 – 0.433 = 0.031
Sur
face
Min
e D
esig
n
29
Histogram of Errors
Sur
face
Min
e D
esig
n
30
Scatter Graph
True grades agai n s t E s t i mated grades
0.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
0.80
0.90
0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80 0.90True (%)
Est
imat
ed (
%)
Sur
face
Min
e D
esig
n
Surface Mine DesignMNGN312 - MNGN512
Sur
face
Min
e D
esig
n
Lecture 5September 14, 2004
InstructorDr. Kadri Dagdelen
2
Geologic Block Modeling
• Assume that a geologic model to be created by using 75ft by 75ft blocks from the exploration data set. Estimate the grade of these blocks using the inverse distance square (IDS) technique.
• Use rectangular search neighborhood of 37.5ft x 37.5ft.
• Assume that the center of the block represents the block grade.
Sur
face
Min
e D
esig
n
3
Geologic Block Modeling
• Estimate the grade of the block (block size 75ft x 75ft) for exploration data set.
75ft
75ft
1̂v2v̂
Estimate the center point
Sur
face
Min
e D
esig
n
4
Geologic Block Modeling
• Rectangular search neighborhood of 37.5ft x 37.5ft.75
ft 37.5ft
37.5ft 37.5ft
37.5ft
Use all the exploration holes within a given block (For this block, use 3 exploration samples)
75ft
Sur
face
Min
e D
esig
n
5
Inverse Distance Technique
• In general,
∑∑=
=
=n
iin
ip
i
pi v
d
dv
1
1
1
1
ˆ
• Inverse distance technique is the simplest interpolation method.
• Give more weight to the closest samples, and less to those that are farthest away.
∑=
= n
ipi
pi
i
d
dw
1
1
1
∑=
=n
iiivwv
1
ˆ 11
=∑=
n
iiw
Unknown pointSampling points
Weights
Sur
face
Min
e D
esig
n
6
Inverse Distance Technique
v1
v2
d1
d244
1
1
1
34
1
1
1
24
1
1
1
14
1
1
1
2
24
2
23
2
22
2
21ˆ vvvvv
id
d
id
d
id
d
id
d
iiii∑∑∑∑
====
+++=
v̂ Inverse Distance Square
• We can make the weights inversely proportional to any power of the distance.
• If p=2, it is called Inverse Distance Square (IDS).
d3
d4
v3
v4
Sur
face
Min
e D
esig
n
7
Inverse Distance Square Example
V1=0.2
V2=0.3
d1=1d2=2
v̂
• Estimate the unknown point by using the Inverse Distance Square technique
d3=4
V3=0.5
v̂
v1= 0.2 d1 =1
v2= 0.3 d2 =2
v3= 0.5 d3 =4
?ˆ =v
Sur
face
Min
e D
esig
n
8
Inverse Distance Square Example
• First of all, calculate the weights w1, w2, w3
21161
1621
241
221
211
211
1 ==++
=w
214
162141
241
221
211
221
2 ==++
=w
211
1621161
241
221
211
241
3 ==++
=w
Note:
121
1416321 =
++=++ www
• Then, calculate
233.05.0211
3.0214
2.02116ˆ =×+×+×=v
v̂
Sur
face
Min
e D
esig
n
9
Geologic Block Modeling
25
25
g1
d1
36.352525 221 =+=d
Sur
face
Min
e D
esig
n
10
Geologic Block Modeling
0032.00008.0
∑=
n
i id12
1
Block1 X Y vi x dist y dist di 1/di2 wi wi*viCentered on 12.5 12.5 0.42 25 25 35.35534 0.0008 0.25 0.105
(X=37.5, Y=37.5) 62.5 12.5 0.24 -25 25 35.35534 0.0008 0.25 0.0637.5 62.5 0.41 0 -25 25 0.0016 0.5 0.205
0.0032 1 0.37(Estimated Grade)
Sur
face
Min
e D
esig
n
11
Geologic Block Modeling
• Using the estimated block values, one normally determines the overall estimated bench average grade of the copper ore at some cutoff, i.e, 0.7%Cu.
Sur
face
Min
e D
esig
n
12
Geologic Block ModelReconciliation
• Determine the average grade of 75ft by 75ft grid blocks for the blasthole data set (blasthole2004.txt) by averaging the grades of 9 blast holes that fall within each block.
Block 1 Grade
= (0.42+0.35+0.24+0.33+ … + 0.46) / 9
=0.35
Sur
face
Min
e D
esig
n
13
Geologic Block ModelReconciliation
• Error estimation between estimation (Exploration data) and true value (Blasthole data).
Error = Estimated Grade – True Grade
e.g., Estimation Error for Block 1
= 0.37 – 0.35 = 0.02
Sur
face
Min
e D
esig
n
14
Geologic Block ModelReconciliation
• Histogram of Error (Example of 100ft x 100ft estimation)
Histogram of Estimation Errors (Estimation - True)
0
0.5
1
1.5
2
2.5
3
3.5
-0.2 -0.15 -0.1 -0.05 0 0.05 0.1 0.15 0.2 0.25 More
Bin
Fre
quen
cy
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%
Frequency
Cumulative %
Bin FrequencyCumulative %-0.2 0 0.00%
-0.15 0 0.00%-0.1 1 11.11%
-0.05 1 22.22%0 3 55.56%
0.05 3 88.89%0.1 0 88.89%
0.15 0 88.89%0.2 1 100.00%
0.25 0 100.00%More 0 100.00%
Sur
face
Min
e D
esig
n
15
Geologic Block ModelReconciliation
• Scatter Graph (Example of 100ft x 100ft estimation)
True grades agai n s t E s t i mated grades
0.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
0.80
0.90
0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80 0.90True (%)
Est
imat
ed (
%)
Draw a diagonal line (y=x) to show perfect estimation line.
Sur
face
Min
e D
esig
n
16
Univariate Distribution of Errors
• Error = Estimated Value - True Value• We also refer to these error as residuals.• If error is positive, then we have overestimated the true;
if error is negative, then we have underestimated the true.
If m=0, then Unbiased Estimates
Overestimates and underestimates are balanced.
We typically prefer to have a symmetric distribution.
Sur
face
Min
e D
esig
n
17
Univariate Distribution of Errors
• We would like to see the error distribution has small spread.
• Both distributions are centered on 0 and are symmetric.• The distribution shown in a), however, has error that span
a greater range.• Therefore, b) is better estimation than a).
a) b)
Sur
face
Min
e D
esig
n
18
Over and Under Estimation
• a) Negative mean: A general tendency towards the underestimation.
• b) Positive mean: A general tendency towards the overestimation.
a) b)
Sur
face
Min
e D
esig
n
19
Scatter Diagrams in EstimationE
stim
atio
n
True
Good Estimation
Est
imat
ion
True
Over Estimation at High Grade
Est
imat
ion
True
Under Estimation at Low Grade
Good Estimation: Falling closer to diagonal on which perfect estimates would plot.S
urfa
ce M
ine
Des
ign
20
Scatter Diagrams in EstimationE
stim
atio
n
True
Over Estimation at Low Grade
Est
imat
ion
True
Under Estimation at Low Grade
Sur
face
Min
e D
esig
n
1
Floating Cone Algorithm
Dr. Kadri Dagdelen
Sur
face
Min
e D
esig
n
2
Basic Procedure
Sur
face
Min
e D
esig
n
Top
-1 +1 -1 -1 -1
-1 -1 +3 -1 -1
BottomLeft Right
-1 -1
-1 -1 -1 -1
Heuristic procedure
3
Floating Cone Steps
Sur
face
Min
e D
esig
n
• The cone is floated from left to right along the top row of blocks in the section. If there is a positive block it is removed.
• Move to the second row. Start from the left and search for the first positive block. If the sum of all blocks falling within the cone is positive, the blocks are removed (mined).
• Follow the floating cone process moving from left to right and top to bottom of the section until no more blocks can be removed. Then go back to the top again and repeat the process for a second iteration. If during a given iteration no positive blocks can be mined, stop.
• The profitability of the mined area can be found by adding the values of the blocks that are to be removed.
• Overall stripping ration can be determined by dividing the number of positive blocks by the total number of negative blocks.
4
Example
Sur
face
Min
e D
esig
n
-1 -1 -1 -1 -1 +1 -1 Ore
-2 -2 +4 -2 -2
+7 +1 -3 Waste
Initial Block Model
5
Example
Sur
face
Min
e D
esig
n
-1 -1 -1 -1 -1 +1 -1 Ore
-2 -2 +4 -2 -2 Waste
+7 +1 -3 Mined
Step 1
6
Example
Sur
face
Min
e D
esig
n
-1 -1 -1 -1 -1 +1 -1 Ore
-2 -2 +4 -2 -2 Waste
+7 +1 -3 Mined
Step 2
7
Example
Sur
face
Min
e D
esig
n
-1 -1 -1 -1 -1 +1 -1 Ore
-2 -2 +4 -2 -2 Waste
+7 +1 -3 Mined
Step 3
8
Example
Sur
face
Min
e D
esig
n
-1
-2 -2
+1 -3
Final Pit
9
ShortcomingsMissing Combinations of Profitable Blocks
Sur
face
Min
e D
esig
n
-1 -1 -1 -1 -1 -1 -1 Ore
-2 -2 -2 -2 -2
+10 -3 +10 Waste
Initial Block Model
10
Sur
face
Min
e D
esig
n
Step 1
-1 -1 -1 -1 -1 -1 -1 Ore
-2 -2 -2 -2 -2 Waste
+10 -3 +10 Considered but rejected
ShortcomingsMissing Combinations of Profitable Blocks
11
Sur
face
Min
e D
esig
n
Step 2
-1 -1 -1 -1 -1 -1 -1 Ore
-2 -2 -2 -2 -2 Waste
+10 -3 +10 Considered but rejected
There are no blocks to be mined – wrong solution
ShortcomingsMissing Combinations of Profitable Blocks
12
Sur
face
Min
e D
esig
n
Correct solution
-1 -1 -1 -1 -1 -1 -1 Ore
-2 -2 -2 -2 -2 Waste
+10 -3 +10 Mined (Correct solution)
-3
Final Pit
ShortcomingsMissing Combinations of Profitable Blocks
13
ShortcomingsOver-mining
Sur
face
Min
e D
esig
n
-1 -1 -1 -1 -1 Ore
+5 -2 -2
+5 Waste
Initial Block Model
14
ShortcomingsOver-mining
Sur
face
Min
e D
esig
n
First block analyzed
-1 -1 -1 -1 -1 Ore
+5 -2 -2 Waste
+5 Mined
The search process was started from bottom to top.
Everything is mined out.
15
ShortcomingsOver-mining
Sur
face
Min
e D
esig
n
Correct solution
-1 -1 -1 -1 -1 Ore
+5 -2 -2 Waste
+5 Mined
-1 -1
-2 -2
+5
Final Pit
16
ShortcomingsCombination of problems
Sur
face
Min
e D
esig
n
-1 -1 -4 -1 -1 Ore
+5 -4 +5
+3 Waste
Initial Block Model
17
ShortcomingsCombination of problems
Sur
face
Min
e D
esig
n
First Step
-1 -1 -4 -1 -1 Ore
+5 -4 +5 Waste
+3 Considered but rejected
18
ShortcomingsCombination of problems
Sur
face
Min
e D
esig
n
Second Step
-1 -1 -4 -1 -1 Ore
+5 -4 +5 Waste
+3 Considered but rejected
19
ShortcomingsCombination of problems
Sur
face
Min
e D
esig
n
Wrong Solution
-1 -1 -4 -1 -1 Ore
+5 -4 +5 Waste
+3 Mined
Everything is mined out.
20
ShortcomingsCombination of problems
Sur
face
Min
e D
esig
n
Correct Solution
-1 -1 -4 -1 -1 Ore
+5 -4 +5 Waste
+3 Mined
-4
+3
Final Pit
21
ExampleInitial Data
Sur
face
Min
e D
esig
n
% recovery through mill and smelter 90.00%Value of recovered copper $1.00 per lbStripping and haulage to dump (level 1) $0.50 per tonMining and transportation to plant level $0.80 per tonHaulage cost increase per ton per bench $0.10 per ton/benchProcessing, smelting and refining $1.20 per tonGeneral overhead, administration, etc. $1.20 per tonUltimate Pit Slope 1:1
22
ExampleGeologic Model
Sur
face
Min
e D
esig
n
0.00 1.15 0.08 0.05 0.00 0.00 0.05
0.00 1.25 1.15 1.13 0.00
1.13 1.15 0.50
Copper Grades (%)
23
ExampleBlock Values
Sur
face
Min
e D
esig
n
P = Price
s = Sales Cost
c = Processing Cost
y = Recovery
m = Mining Cost
gB = Block Grade
BV = Block Value
mcygsPBV B −−−= **)(Ore Block:
Waste Block:
mBV −=
24
ExampleEconomic Model
Sur
face
Min
e D
esig
n
-0.50 17.50 -0.50 -0.50 -0.50 -0.50 -0.50
-0.60 19.20 17.40 17.04 -0.60
16.94 17.30 -0.70
Value per block ($/ton)
25
ExampleEconomic Model
Sur
face
Min
e D
esig
n
-0.50 17.50 -0.50 -0.50 -0.50 -0.50 -0.50
-0.60 19.20 17.40 17.04 -0.60
16.94 17.30 -0.70
Value per block ($/ton)
5.178.04.29.0*2000*100/15.1*)01( =−−−=BV
26
ExampleEconomic Model
Sur
face
Min
e D
esig
n
-0.50 17.50 -0.50 -0.50 -0.50 -0.50 -0.50
-0.60 19.20 17.40 17.04 -0.60
16.94 17.30 -0.70
Value per block ($/ton)
2.38.04.29.0*2000*100/0.0*)01()/($ −=−−−=tonBV If mined as ore
6.0)/($ −=tonBV If mined as waste
27
ExampleEconomic Model
Sur
face
Min
e D
esig
n
Value per block ($/ton)Values rounded to the nearest $
-1 18 -1 -1 -1 -1 -1
-1 19 17 17 -1
17 17 -1
28
ExampleFloating Cone Algorithm
Sur
face
Min
e D
esig
n
1st Increment
-1 18 -1 -1 -1 -1 -1
-1 19 17 17 -1
17 17 -1
1
29
ExampleFloating Cone Algorithm
Sur
face
Min
e D
esig
n
2nd Increment
-1 18 -1 -1 -1 -1 -1
-1 19 17 17 -1
17 17 -1
1 22
2
30
ExampleFloating Cone Algorithm
Sur
face
Min
e D
esig
n
3rd Increment
-1 18 -1 -1 -1 -1 -1
-1 19 17 17 -1
17 17 -1
2 2
2
1 3
3
31
ExampleFloating Cone Algorithm
Sur
face
Min
e D
esig
n
4th Increment
-1 18 -1 -1 -1 -1 -1
-1 19 17 17 -1
17 17 -1
3
3
1 2 2
2
4
4
32
ExampleFloating Cone Algorithm
Sur
face
Min
e D
esig
n
5th Increment
-1 18 -1 -1 -1 -1 -1
-1 19 17 17 -1
17 17 -1
3
3
1 2 2
2
4
4
5
5
5
33
ExampleFloating Cone Algorithm
Sur
face
Min
e D
esig
n
6th Increment
-1 18 -1 -1 -1 -1 -1
-1 19 17 17 -1
17 17 -1
3
3
1 2 2
2
4
4
5
5
5 6
34
ExampleFloating Cone Algorithm
Sur
face
Min
e D
esig
n
Ultimate Pit Limit
-1
-1
-1
35
ExampleTotal Economic Value
Sur
face
Min
e D
esig
n
Value Per block considering:
Tonnage/block = 10,000 tons
-5,000 175,000 -5,000 -5,000 -5,000 -5,000
-6,000 192,000 174,000 170,400
169,400 173,000
36
ExamplePit Reserves
Sur
face
Min
e D
esig
n
Bench Ore tons Waste tons S.R. $
1 10,000 50,000 5.00 150,0002 30,000 10,000 0.33 530,4003 20,000 0 0.00 342,400
Total 60,000 60,000 1.00 1,022,800
1
Manual Pit Design
Dr. Kadri Dagdelen
Sur
face
Min
e D
esig
n
2
Manual Pit DesignStripping Ratio
Sur
face
Min
e D
esig
n
)/($)/($Pr)/($covRe).(.
tonCostStrippingtonCostoductionTotaltonValueeredBreakevenRS −=
)/($)/($)/($
tonCostStrippingtonCostMiningSurfacetonCostMiningUG
BreakevendUndergrounorSurface−
=
1:58.6)/66.0$
/70.0$/04.5$ =−=tonwaste
tonoretonoreBreakevendUndergrounorSurface
3
Manual Pit DesignExample
Sur
face
Min
e D
esig
n
Ore Grade (%Cu) 0.90 0.85 0.75 0.70 0.65 0.50 0.40
Conc. Recovery (%) 0.900 0.900 0.900 0.900 0.900 0.900 0.900Smelt. Recovery (%) 0.980 0.980 0.980 0.980 0.980 0.980 0.980Ref. Recovery (%) 0.990 0.990 0.990 0.990 0.990 0.990 0.990
Total Recovery (%) 0.873 0.873 0.873 0.873 0.873 0.873 0.873
Recovered Quantity (lb/ton) 15.7 14.8 13.1 12.2 11.3 8.7 7.0
Costs per ton
Finance 0.62 0.62 0.62 0.62 0.62 0.62 0.62Mining 0.70 0.70 0.70 0.70 0.70 0.70 0.70Concentration 2.68 2.68 2.68 2.68 2.68 2.68 2.68Smelter 1.70 1.48 1.38 1.29 1.21 1.19 1.18Refining 1.80 1.57 1.36 1.27 1.20 1.16 1.12
Total cost ($/ton) 7.50 7.05 6.74 6.56 6.41 6.35 6.30
Stripping cost ($/ton) 0.66 0.66 0.66 0.66 0.66 0.66 0.66
Breakeven stripping ratio
Copper Price ($/lb)0.90 10.07 9.56 7.65 6.73 5.70 2.29 -0.020.75 6.50 6.19 4.67 3.95 3.13 0.30 -1.610.70 5.31 5.06 3.68 3.03 2.27 -0.36 -2.140.65 4.12 3.94 2.69 2.10 1.42 -1.02 -2.67
07.10/66.0$
/5.7$/90.0$7.15=
−∗=
wasteoftonoreoftonlblbs
BESR
4
Manual Pit DesignStripping Ratio – Grade - Price
Sur
face
Min
e D
esig
n
S.R. - Ore Grades - Cu Prices
-4.00
-2.00
0.00
2.00
4.00
6.00
8.00
10.00
12.00
0.40 0.50 0.60 0.70 0.80 0.90
% Cu
Str
ipp
ing
Rat
io
0.90 $/lb0.75 $/lb0.70 $/lb0.65 $/lb
5
X'
SR =
A B
Y'Y
Topo
Orebody
X'Y'
SR = YX
X
Manual Pit DesignHypothetical Cross Section
Sur
face
Min
e D
esig
n
6
Manual Pit DesignS.R. in Section
Sur
face
Min
e D
esig
n
First
X’ = 30
Y’ = 5
S.R. = 6
G = 0.67%
Second
X’ = 39.6
Y’ = 6
S.R. = 6.6 (Breakeven)
G = 0.70%
First
X = 10
Y = 5
S.R. = 2
G = 0.48%
Second
X = 15
Y = 3
S.R. = 5
G = 0.70%
5 : 1 < 6.6 : 1 OK
Current Price = 0.90 $/lb
7
Manual Pit DesignRepeat for All Sections
Sur
face
Min
e D
esig
n Pit contouror Final pit
1
Cutoff Grade Optimization
Dr. Kadri Dagdelen
Sur
face
Min
e D
esig
n
2
Factors Influencing The Cutoff Grades
Sur
face
Min
e D
esig
n
• As the Cutoff Grade increases in a given operation cash flow also increases
• The ultimate adjustment of the dial is influenced by the available capacities in the mining system
• The Cutoff Grade is not only function of economic parameters but also capacities of the mining system with respect to mining,milling and the market (refining)
3
What Is Cutoff Grade
Sur
face
Min
e D
esig
n
1. Cutoff Grade is defined as the grade that is normally used to discriminate between ore and waste within a given deposit
2. Cutoff Grade is the dial that is used to adjust the cash flow coming from the mining operations in a given year
3. The Cutoff Grade policy allows a mining company to fine tune their operation with respect to a given financial objective
4. The Cutoff Grade dial also controls how much ore is available to the mill from a given bench and how much of final product to be produced in a given period
5. The overall influence of Cutoff Grade policy on the economics of an operation is profound
4
Economic Objectives And The Cutoff Grade
Sur
face
Min
e D
esig
n
• The cash costs related to mining, milling and refining along with the commodity price determines the lower limit to cutoff in a given period.
• If the financial objective of the company is to maximize undiscounted profits, the cutoff grade should be lowered all theway down to process breakeven cutoff grade.
• Processing every ton of ore that pays for itself will maximize the undiscounted profits for the operation.
5
Economic Objectives And The Cutoff Grade (Cont.)
Sur
face
Min
e D
esig
n
• If the financial objective of the company is to maximize the discounted profits that is Net Present Value (NPV), the Cutoff Grade in a given period has to be adjusted upwards to pay for the opportunity cost of mining low grade ore now while the higher grades are still available.
• The mining rate, milling rate, the ultimate rate of production for the commodity being sold, and the production costs determine how far the cutoff grade has to be adjusted upwards to maximize the NPV.
6
Ultimate Pit Cutoff
Sur
face
Min
e D
esig
n
• Defined as the breakeven grade that equates cost of mining, milling and refining to the value of the block in terms of recovered metal and the selling price.
• Any administrative overhead expense which would stop if mining were stopped must be included in the cost calculations.
• Overhead costs should be divided between mining and processing.
7
Ultimate Pit Cutoff
Sur
face
Min
e D
esig
n
• Price (P) $400/oz• Sales Cost (s) $5 /oz• Processing Cost (c) $ 10/ ton ore• Recovery (y) 90 %• Mining Cost (m) $ 1.20/ ton• Overhead
(Included in c and m )
8
Ultimate Pit Cutoff
Sur
face
Min
e D
esig
n eryCostSalesiceCostMiningCostMilling
gm covRe*)(Pr −+
=
tonozgm /0315.09.0*)5$400($
2.1$10$=
−+
=
9
Milling Cutoff
Sur
face
Min
e D
esig
n
• Defined as the breakeven grade that equates cost of milling and refining to the value of the block in terms of recovered metal and the selling price.
• Any administrative overhead expense which would stop if mining were stopped must be included in the cost calculations.
10
Milling Cutoff
Sur
face
Min
e D
esig
n eryCostSalesiceCostMilling
gc covRe*)(Pr −=
tonozgc /0281.09.0*)5$400($
10$=
−=
11
Block Value
Sur
face
Min
e D
esig
n
Block Grade = gB
if ggcc < < ggm <m < ggBB thenBlock Value = (P(P--S)* gS)* gBB * y * y –– c c –– mm
Else if ggBB < < ggm <m < ggcc thenBlock Value = Block Value = --mm
12
Block Value
Sur
face
Min
e D
esig
n
Block Grade = gB
if ggcc < < ggB B << ggmm thenBlock contains marginal ore.
• Marginal ore pays for processing cost but not for mining cost.
13
Block Value Calculation Example
Sur
face
Min
e D
esig
n
a) Ore BlockBlock grade = gB = 0.11 oz/tonggc c < < ggm < m < ggBB
0.0281 < 0.0315 < 0.11Block Value = (P(P--S)*S)* ggBB * y * y –– c c –– mm
Block Value = (400 - 5)*0.11*0.9 - 10 - 1.20= $27.9/ton of block
14
Block Value Calculation Example
Sur
face
Min
e D
esig
n
b) Waste BlockBlock Grade = gB = 0.01 oz/tonggB B < < ggc c << ggmm
0.01 < 0.0281 < 0.0315
therefore
Block Value = -- $1.20/ton$1.20/ton= Mining Cost
15
Mine Design Parameters For The Case Study
Sur
face
Min
e D
esig
n
• Price (P) $600/oz• Sales Cost (s) $5 /oz• Processing Cost (c) $ 19/ ton ore• Recovery (y) 90 %• Mining Cost (m) $ 1.20/ ton• Fixed Costs (fa) 8.35 M/year• Mining Capacity (M) Unlimited• Milling Capacity (C) 1.05 M• Capital Costs (CC) 105 M• Discount Rate (d) 15%
16
Calculation of Ultimate Pit Cutoff Grade
Sur
face
Min
e D
esig
n eryCostSalesiceCostMiningCostMilling
gm covRe*)(Pr −+
=
tonozgm /038.09.0*)5$600($
2.1$19$=
−+
=
17
Calculation of Milling Cutoff Grade
Sur
face
Min
e D
esig
n eryCostSalesiceCostMilling
gc covRe*)(Pr −=
tonozgc /035.09.0*)5$600($
19$=
−=
18
Grade Tonnage Distribution
Sur
face
Min
e D
esig
n
Avg. IntervalGrade
0.000 - 0.020 70,000 0.01000.020 - 0.025 7,257 0.02250.025 - 0.030 6,319 0.02750.030 - 0.035 5,591 0.03250.035 - 0.040 4,598 0.03750.040 - 0.045 4,277 0.04250.045 - 0.050 3,465 0.04750.050 - 0.055 2,428 0.05250.055 - 0.060 2,307 0.05750.060 - 0.065 1,747 0.06250.065 - 0.070 1,640 0.06750.070 - 0.075 1,485 0.07250.075 - 0.080 1,227 0.07750.080 - 0.100 3,598 0.09000.100 - 0.358 9,576 0.2290
Cutoff Grade 0.035
KTonsGrade Interval KTons Grade
89,167
36,348
Waste
0.1023
Ore
Oz/ton
19
Constant Cutoff Grades.Yearly Tons and Grade Schedules.
Table 3
Sur
face
Min
e D
esig
n
Year Cutoff Avg QM Qc Qr Profits Grade Grade $M/year
1 0.035 0.102 3.6 1.05 96.3 33.02 0.035 0.102 3.6 1.05 96.3 33.03 0.035 0.102 3.6 1.05 96.3 33.04 0.035 0.102 3.6 1.05 96.3 33.05 0.035 0.102 3.6 1.05 96.3 33.06 0.035 0.102 3.6 1.05 96.3 33.07 0.035 0.102 3.6 1.05 96.3 33.08 0.035 0.102 3.6 1.05 96.3 33.09 0.035 0.102 3.6 1.05 96.3 33.0
10 0.035 0.102 3.6 1.05 96.3 33.0For 11 to 34 0.035 0.102 3.6 1.05 96.3 33.0
35 0.035 0.102 3.4 1.00 91.7 31.4TOTAL 0.035 0.102 125.8 36.70 3365.9 1154.2
NPV $M 218.5
20
Profit
Sur
face
Min
e D
esig
n
Profits ($M) = (P Profits ($M) = (P –– s ) x s ) x QQrr –– QQcc x c x c –– QQmm x mx m
P – Price S – Sales CostQm – Total Material MinedQc – Ore Tonnage Processed By The MillQr – Recovered Ouncesc – Milling Costs ($/ton)m – Mining Costs ($/ton)
21
Shortcomings of the traditional cutoff grades
Sur
face
Min
e D
esig
n
• They are established to satisfy the objective of maximizing the undiscounted profits from a given mining operation.
• They are constant unless the commodity price and the costs change during the life of mine AND
• They do not consider grade distribution of the deposit.
22
Traditional
Sur
face
Min
e D
esig
n
eryCostSalesiceofitMinimumonDepreciatiCostMilling
gc covRe*)(PrPr
−++
=
tonozgc /060.09.0*)5$600($
3$10$19$=
−++
=
23
Nontraditional ????????
Sur
face
Min
e D
esig
n eryCostSalesiceonDepreciatiCostMilling
gc covRe*)(Pr −+
=
tonozgc /054.09.0*)5$600($
10$19$=
−+
=
24
Constant Cutoff GradesYearly Tons and Grade Schedules
Table 4
Sur
face
Min
e D
esig
n
Year Cutoff Avg Qm Qc Qr Profits Grade Grade $M/year
1 0.060 0.153 6.90 1.05 144.60 57.82 0.060 0.153 6.90 1.05 144.60 57.83 0.060 0.153 6.90 1.05 144.60 57.84 0.060 0.153 6.90 1.05 144.60 57.85 0.060 0.153 6.90 1.05 144.60 57.86 0.054 0.141 6.00 1.05 132.80 51.97 0.054 0.141 6.00 1.05 132.80 51.98 0.054 0.141 6.00 1.05 132.80 51.99 0.054 0.141 6.00 1.05 132.80 51.9
10 0.054 0.141 6.00 1.05 132.80 51.9For 11 to 27 0.035 0.102 3.60 1.05 96.30 33.0
28 0.035 0.102 0.30 0.09 8.10 2.8TOTAL 0.035 0.102 125.80 28.44 3032.10 1112.7
NPV $M 355.7
25
Declining Cutoff Grades
Sur
face
Min
e D
esig
n
eryCostSalesiceCostFixedonDepreciatiCostMilling
gc covRe*)(Pr −++
=
tonozgc /069.09.0*)5$600($95.7$10$19$
=−
++=
26
Declining Cutoff Grades
Sur
face
Min
e D
esig
n eryCostSalesiceCostFixedCostMilling
gc covRe*)(Pr −+
=
tonozgc /050.09.0*)5$600($
95.7$19$=
−+
=
27
Declining Cutoff Grades
Sur
face
Min
e D
esig
n
eryCostSalesiceCostFixedofMinimumonDepreciatiCostMilling
gc covRe*)(Pr.Pr
−+++
=
tonozgc /075.09.0*)5$600($
95.7$3$10$19$=
−+++
=
28
Declining Cutoff Grades
Sur
face
Min
e D
esig
n
eryCostSalesiceCostMilling
gc covRe*)(Pr −=
tonozgc /035.09.0*)5$600($
19$=
−=
29
Declining Cutoff GradesYearly Tons and Grade Schedules.
Table 5
Sur
face
Min
e D
esig
n
Year Cutoff Avg QM Qc Qr **Profits Grade Grade $M/year
1 0.075 0.182 9.2 1.05 171.6 62.82 0.075 0.182 9.2 1.05 171.6 62.83 0.075 0.182 9.2 1.05 171.6 62.84 0.075 0.182 9.2 1.05 171.6 62.85 0.075 0.182 9.2 1.05 171.6 62.86 0.069 0.169 8.2 1.05 160.0 57.17 0.069 0.169 8.2 1.05 160.0 57.18 0.069 0.169 8.2 1.05 160.0 57.19 0.069 0.169 8.2 1.05 160.0 57.1
10 0.069 0.169 8.2 1.05 160.0 57.1For 11 to 17 0.050 0.132 5.4 1.05 124.8 39.5
18 0.050 0.132 1.3 0.26 30.5 9.6
TOTAL 125.8 18.11 2562.5 885.6NPV $M 357.7
**Profits ($M)= (PProfits ($M)= (P--s) xs) x QrQr –– Qc x c Qc x c –– QmQm x m x m –– f af a
30
Cutoff Grade Optimization
Determination Of Optimum Cutoff Grades
When The MillIs Bottleneck
Sur
face
Min
e D
esig
n
31
Formula for Optimum Cutoff Grade
Sur
face
Min
e D
esig
n ySPFfc
ig ic *)(
)(−
++=
• Where FFii = d x NPV= d x NPVii /C/Cf = f = ffaa/C /C
and fa is annual fixed costs
32
Optimum Cutoff GradesYearly Tons and Grade Schedules
Table 6
Sur
face
Min
e D
esig
n
Year Cutoff Avg QM Qc Qr **Profits NPV Grade Grade $M $M
1 0.161 0.259 18.0 1.05 245.2 95.9 413.82 0.152 0.255 17.2 1.05 241.0 94.4 380.03 0.142 0.250 16.5 1.05 236.4 92.6 342.64 0.131 0.245 15.7 1.05 231.3 90.5 301.45 0.120 0.239 14.9 1.05 225.7 88.1 256.16 0.107 0.232 14.1 1.05 219.6 85.4 206.47 0.092 0.213 12.1 1.05 200.9 76.7 152.08 0.079 0.188 9.8 1.05 177.9 65.9 98.19 0.065 0.163 7.6 1.05 153.6 53.9 46.9
TOTAL 125.8 9.45 1931.4 743.4NPV $M 413.8
**Profits ($M)= (PProfits ($M)= (P--s) x s) x Qr Qr –– Qc x c Qc x c –– Qm Qm x m x m –– f af a
33
Summary
Sur
face
Min
e D
esig
n
Avg Total Total Strip Profits NPV Life Undiscounted NPV Grade Amount Amount Ratio % Reduction % Increase
mined processed INC CUM INC CUMQm Qr $M $M yrs
Traditional 0.102 125.8 36.70 2.43 4453.4 218.5 35 n/a n/a n/a n/a
Heuristic 0.125 125.8 28.44 3.42 1127.4 355.7 28 3.6 3.6 63.0 63.0(Depr)
Heuristic 0.164 125.8 18.11 5.95 885.6 357.1 18 20.4 23.3 0.3 63.4(Depr and
Fixed Costs)
Lanes's 0.235 125.8 9.45 12.31 743.4 413.8 9 16.0 35.6 15.9 89.0Approach
34
Cutoff Grade Optimization
One Constraint Cutoff Grade
Optimization Algorithm
Sur
face
Min
e D
esig
n
35
Steps Of The Algorithm
Sur
face
Min
e D
esig
n
1. Start with Grade-Tonnage Curve.
2. Define: P - PriceC - Milling Capacity s - Marketing Costsm - Mining Costsc - Milling Costsfa - Fixed Costsd - Discount Rate
36
Steps Of The Algorithm (Cont.)
Sur
face
Min
e D
esig
n
3. Determine the cutoff grade gc for year (i).
ySPFfc
ig ic *)(
)(−
++=
• Where FFii = d x NPV= d x NPVii /C/Cf = f = ffaa/C /C
and fa is annual fixed costs
37
Steps Of The Algorithm (Cont.)
Sur
face
Min
e D
esig
n
4. For Cutoff Grade gmilling (i):
• Determine Ore Tonnage Tc and Grade gc
• Determine the Waste Tonnage Tw
• Stripping Ratio ((srsr) = ) = TTww//TTcc
38
Steps Of The Algorithm (Cont.)
Sur
face
Min
e D
esig
n
5. Set
QQcc = C = C if if TTcc > C> CQQcc = = TTcc if if TTcc < C< C
And
QQmm = Q= Qcc(1+(1+srsr))
39
Steps Of The Algorithm (Cont.)
Sur
face
Min
e D
esig
n
6. Determine the annual profit (Pi) by using the following equationPi =(PPi =(P--s) x Qc x s) x Qc x ggcc x y x y –– Qc x (c + f) Qc x (c + f) –– Qm Qm x mx m
P - Prices - Marketing Costs Qm - Total material minedQc - Ore tonnage processed by the millc - Milling Costs ($/ton)m - Mining Costs ($/ton)gc - Average Grade (Opt)y - Recoveryf - Fixed Cost ($/ton)
40
Steps Of The Algorithm (Cont.)
Sur
face
Min
e D
esig
n
7. Adjust the Grade-Tonnage Curve of the deposit for Qc and QQww = = Qm Qm –– QcQc .
8. If Qc < CQc < C in year (i) go to step 9 otherwise
Set i = i+1i = i+1 and go to Step 3.
41
Steps Of The Algorithm (Cont.)
Sur
face
Min
e D
esig
n
9. Calculate incremental NPV for each year (i)
∑=
+−+=
N
ijij
ji d
PNPV 1)1(
42
Steps Of The Algorithm (Cont.)
Sur
face
Min
e D
esig
n
10. If NPV1 for this iteration is not within some tolerance (say plusplus--minus $500K minus $500K ) on the NPV1 of the previous iteration go to Step 1otherwiseotherwiseStop the cutoff grade gc (i) for years i = 1i = 1, NN is Optimum Policy.
Open Pit Sequencing and Production Scheduling
Dr. Kadri Dagdelen
Sur
face
Min
e D
esig
n
2
Sur
face
Min
e D
esig
n
Open pit production scheduling
• It is a timed sequence of extraction of the ore and waste within the ultimate pit limits from the initial condition of the deposit up to a predetermined stage that mat be referred to as an intermediate of final pit limit.
• It sets the relationship between quantity and quality of the material to be mined, time, geometry of the orebody, and the available resources.
3
Sur
face
Min
e D
esig
n
Time
Stri
ppin
gV
olum
e
Declining Stripping Ratio Method
1
2
3
4
5
67
1
2
76
5
4
3
1
2
3
4
5
67
Orebody
Waste
4
Sur
face
Min
e D
esig
n
Increasing Stripping Ratio Method
Orebody
Waste
5
Sur
face
Min
e D
esig
n
Constant Stripping Ratio Method
Orebody
Waste
6
Sur
face
Min
e D
esig
n
Long Term Production Scheduling
•Long term production scheduling is usually carried out from the initial condition of the deposit (i.e. initial topography) to the ultimate pit limit, in periods of at least one year.
•Its purpose is to determine ore reserves, stripping ratios, future investments, and to conserve and develop owned resources.
•Long term production scheduling takes into account capital availability, geometry and grade distribution of the orebody, metallurgical and physical properties of the material, as well as environmental and legal constraints.
7
Sur
face
Min
e D
esig
n
Short Term Production Scheduling
•Short term production scheduling is concerned with schedules on a daily, weekly or monthly basis.
•Its main objective is to furnish the requirements of the processing plant with ore of uniform quality to ensure operating efficiency.
•To accomplish this objective, short term production scheduling has to comply with restrictions imposed by the long term plan, equipment availability, blending of different materials from different sites within the mine, and the availability of exposed ore.
8
Sur
face
Min
e D
esig
n
Objectives in Open Pit Mine Planning
• To ensure the tonnage required by the processing plant in order to operate efficiently and to produce the expected amount of concentrate per mining period.
• To meet the grade specifications at the processing plant within a given range for each ore parameter that has an effect on the operating costs or the quality of the final product.
9
Sur
face
Min
e D
esig
n
Objectives in Open Pit Mine Planning (cont.)
• To minimize the pre-production stripping volume required to expose enough ore at the beginning of the mine life in order to ensure a continuous operation.
• To defer waste stripping as long as possible to maximize cash flow in the early years of the operation.
10
Sur
face
Min
e D
esig
n
Objectives in Open Pit Mine Planning (cont.)
• To ensure a feasible schedule in terms of mining practice. This implies mining exposed material sequentially, keeping appropriate mining widths, maintaining access to the mining areas, and maintaining stable pit walls.
• To ensure the schedule is compatible with the remaining periods. In other words, the present schedule must ensure the feasibility of the future extraction.
11
Sur
face
Min
e D
esig
n
Objectives in Open Pit Mine Planning (cont.)
• To mine the orebody in such a way that for each year the cost to produce a given kilogram of metal is at minimum.
• To develop an achievable start-up schedule with respect to manpower training, equipment deployment, infrastructure and logistical support in order to ensure positive cash flow as planned.
• To have enough exposed ore at the beginning of each scheduling period to offset any problem that could arise in the case of underestimation of ore tonnages and grades in the reserves model.
12
Sur
face
Min
e D
esig
n
Objectives in Open Pit Mine Planning (Cont.)
• To maximize design pit slope angles in response to adequate geotechnical investigations, and yet through careful planning minimize the adverse impacts of any slope instability, should itoccur.
• To properly examine the economic merits of alternative ore production rate and cutoff grade scenarios.
• To thoroughly subject the proposed mining strategy, equipment selection, and mine development plan to “what if” contingency planning, before a commitment to proceed is made.
13
Sur
face
Min
e D
esig
n
Pit Sequence Planning
• Orebodies are normally mined in stages, so as to defer waste stripping and maximize the net present value of the surface mining venture.
• These stages are commonly called sequences, expansions, phases, working pits, slices, or pushbacks.
• They are the basic building block on which more detailed time period planning is subsequently made.
• Phase planning should commence with mining that portion of the orebody which will yield the maximum cash flow and then proceed to mine other stages of lessening cash flow.
14
Sur
face
Min
e D
esig
n
Procedure to obtain the pushbacks
• Generate nested pits by increasing and/or decreasing the product price.
• According to the size of the deposit, pick a number of phases that allow enough operating room for the equipment.
15
Sur
face
Min
e D
esig
n
Example of how to obtain the pushbacks
•% Recovery through mill and smelter 90%
•Value of recovered copper $1.10/lb
•Stripping and haulage to dump (level 1) $0.50/ton
•Mining and transportation to plant level $0.80/ton
•Haulage costs increase per bench $0.10/ton
•Processing, smelting and refining $1.20/ton
•General overhead, administration, etc. (ore blocks only) $1.20/ton
•Ultimate pit slope 1 : 1
16
Sur
face
Min
e D
esig
n
Example of how to obtain the pushbacks (Cont.)
Block Model showing copper grades in %
Level1 0.00 0.10 0.15 0.08 0.05 0.00 0.00 0.05 0.03 0.00 0.05 0.05 0.05 0.05 0.05 0.052 0.00 0.22 0.08 0.25 0.15 0.13 0.10 0.13 0.45 0.20 0.20 0.32 0.10 0.15 0.24 0.213 0.05 0.05 0.12 0.13 0.02 0.14 0.11 0.08 0.22 0.09 0.08 0.15 0.22 0.20 0.14 0.054 0.04 0.15 0.12 0.45 0.08 0.09 0.25 0.20 0.29 0.14 0.15 0.04 0.24 0.05 0.02 0.045 0.05 0.08 0.15 0.12 0.30 0.21 0.09 0.79 0.10 0.45 0.32 0.23 0.01 0.01 0.01 0.016 0.08 0.10 0.08 0.01 0.05 0.34 0.45 0.02 0.01 0.04 0.38 0.00 0.00 0.00 0.01 0.15
17
Sur
face
Min
e D
esig
n
Example of how to obtain the pushbacks (Cont.)
Economic Model showing block values in $/ton
Original copper price of $1.10/lb1 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.502 -0.60 1.06 -0.60 1.65 -0.60 -0.60 -0.60 -0.60 5.61 0.66 0.66 3.04 -0.60 -0.60 1.45 0.863 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 0.96 -0.70 -0.70 -0.70 0.96 0.56 -0.70 -0.704 -0.80 -0.80 -0.80 5.41 -0.80 -0.80 1.45 0.46 2.24 -0.80 -0.80 -0.80 1.25 -0.80 -0.80 -0.805 -0.90 -0.90 -0.90 -0.90 2.34 0.56 -0.90 12.04 -0.90 5.31 2.74 0.95 -0.90 -0.90 -0.90 -0.906 -1.00 -1.00 -1.00 -1.00 -1.00 3.03 5.21 -1.00 -1.00 -1.00 3.82 -1.00 -1.00 -1.00 -1.00 -1.00
mcygsPBV B −−−= **)(
mBV −=
For ore blocks:
For waste blocks:
18
Sur
face
Min
e D
esig
n
Example of how to obtain the pushbacks (Cont.)
The floating cone algorithm was used to find the ultimate pit limit
Pit1 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 12 -0.60 1.06 -0.60 1.65 -0.60 -0.60 -0.60 -0.60 5.61 0.66 0.66 3.04 -0.60 -0.60 1.45 0.86 23 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 0.96 -0.70 -0.70 -0.70 0.96 0.56 -0.70 -0.70 34 -0.80 -0.80 -0.80 5.41 -0.80 -0.80 1.45 0.46 2.24 -0.80 -0.80 -0.80 1.25 -0.80 -0.80 -0.80 45 -0.90 -0.90 -0.90 -0.90 2.34 0.56 -0.90 12.04 -0.90 5.31 2.74 0.95 -0.90 -0.90 -0.90 -0.90 56 -1.00 -1.00 -1.00 -1.00 -1.00 3.03 5.21 -1.00 -1.00 -1.00 3.82 -1.00 -1.00 -1.00 -1.00 -1.00 6
7The ore block left at the right cannot be mined due to slope constraints. All ore blocks are mined in the first iteration. 8
91 102 113 124 135 146 15
19
Sur
face
Min
e D
esig
n
Example of how to obtain the pushbacks (Cont.)
To find a smaller pit reduce the copper price to 0.60/lb Economic block model
1 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.502 -0.60 -0.60 -0.60 -0.60 -0.60 -0.60 -0.60 -0.60 1.56 -0.60 -0.60 0.16 -0.60 -0.60 -0.60 -0.603 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.704 -0.80 -0.80 -0.80 1.36 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80 -0.805 -0.90 -0.90 -0.90 -0.90 -0.90 -0.90 -0.90 4.93 -0.90 1.26 -0.90 -0.90 -0.90 -0.90 -0.90 -0.906 -1.00 -1.00 -1.00 -1.00 -1.00 -1.00 1.16 -1.00 -1.00 -1.00 0.40 -1.00 -1.00 -1.00 -1.00 -1.00
mcygsPBV B −−−= **)(
mBV −=
For ore blocks:
For waste blocks:
20
Sur
face
Min
e D
esig
n
Example of how to obtain the pushbacks (Cont.)
The floating cone algorithm was used to find the limit of the pit at $0.60/lb
1 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.502 -0.60 -0.60 -0.60 -0.60 -0.60 -0.60 -0.60 -0.60 1.56 -0.60 -0.60 0.16 -0.60 -0.60 -0.60 -0.603 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.704 -0.80 -0.80 -0.80 1.36 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80 -0.805 -0.90 -0.90 -0.90 -0.90 -0.90 -0.90 -0.90 4.93 -0.90 1.26 -0.90 -0.90 -0.90 -0.90 -0.90 -0.906 -1.00 -1.00 -1.00 -1.00 -1.00 -1.00 1.16 -1.00 -1.00 -1.00 0.40 -1.00 -1.00 -1.00 -1.00 -1.00
123456
21
Sur
face
Min
e D
esig
n
Example of how to obtain the pushbacks (Cont.)
To find an intermediate pit reduce the copper price to $0.86/lb Economic Block Model
1 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.502 -0.60 0.11 -0.60 0.57 -0.60 -0.60 -0.60 -0.60 3.67 -0.60 -0.60 1.65 -0.60 -0.60 0.42 -0.603 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.704 -0.80 -0.80 -0.80 3.47 -0.80 -0.80 0.37 -0.80 0.99 -0.80 -0.80 -0.80 0.22 -0.80 -0.80 -0.805 -0.90 -0.90 -0.90 -0.90 1.04 -0.90 -0.90 8.63 -0.90 3.37 1.35 -0.90 -0.90 -0.90 -0.90 -0.906 -1.00 -1.00 -1.00 -1.00 -1.00 1.56 3.27 -1.00 -1.00 -1.00 2.18 -1.00 -1.00 -1.00 -1.00 -1.00
22
Sur
face
Min
e D
esig
n
Example of how to obtain the pushbacks (Cont.)
To find an intermediate pit reduce the copper price to $0.86/lb Economic Block Model
1 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 Pit2 -0.60 0.11 -0.60 0.57 -0.60 -0.60 -0.60 -0.60 3.67 -0.60 -0.60 1.65 -0.60 -0.60 0.42 -0.60 13 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 24 -0.80 -0.80 -0.80 3.47 -0.80 -0.80 0.37 -0.80 0.99 -0.80 -0.80 -0.80 0.22 -0.80 -0.80 -0.80 35 -0.90 -0.90 -0.90 -0.90 1.04 -0.90 -0.90 8.63 -0.90 3.37 1.35 -0.90 -0.90 -0.90 -0.90 -0.906 -1.00 -1.00 -1.00 -1.00 -1.00 1.56 3.27 -1.00 -1.00 -1.00 2.18 -1.00 -1.00 -1.00 -1.00 -1.00
The ore block left at the right cannot be mined due to slope constraints. All ore blocks are mined in the first iteration.
123456
23
Sur
face
Min
e D
esig
n
Example of how to obtain the pushbacks (Cont.)
The three pits shown in together
1 $0.60/lb23456
$1.10/lb$0.86/lb
24
ABCD
EF
Design Phase Limits Ultimate Pit
Ore
Rock Type I
Rock Type II
Sur
face
Min
e D
esig
n
Hypothetical Deposit and Pit Development Sequence
25
Sur
face
Min
e D
esig
n
Tonnage Inventory by Phase
Waste Ore Waste Ore Waste Ore5100 15,0005050 32,0005000 50,000 2,000 4,0004950 38,000 18,000 15,0004900 15,000 20,000 18,0004850 4,000 10,000 15,000 22,0004800 3,000 9,000 4,000 9,000 16,0004750 2,000 8,000 3,000 9,000 3,000 10,0004700 2,000 7,000 5,000 20,0004650 1,000 6,000 8,000 22,0004600 3,000 17,0004550 1,000 7,000
Total 159,000 27,000 65,000 31,000 95,000 76,000
Thousands of tonnes
Phase "A" Phase "B" Phase "C"Bench
26
Sur
face
Min
e D
esig
n
Summary by Phase
Waste above Waste on Ore Cumulativefirst ore ore Ore Life* ore lifebench benches (years) (years)
A 150,000 9,000 27,000 1.08 1.08B 55,000 10,000 31,000 1.24 2.32C 75,000 20,000 76,000 3.04 5.36D 128,000 38,000 125,000 5.00 10.36E 182,000 49,000 151,000 6.04 16.40F 220,000 45,000 130,000 5.20 21.60Total 810,000 171,000 540,000 21.60
*Assuming an annual milling rate 0f 25,000 tonnes
Phase
Thousands of tonnes
27
Sur
face
Min
e D
esig
n
Hypothetical Deposit and Pit Development Sequence
Time (Years)
10
ore deliveriesrequired to sustainMinimum waste stripping
Time (Years)Pre-production
(Mill
ions
of t
onne
s)C
umul
ativ
e St
ripp
ing
250
0
500
750
A
B
C
D
(Mill
ions
of t
onne
s)D
evel
oped
Ore
50
0
1000
100
150
BA
C
D
It requires 128 M tonnes strippingPhase "D" life = 5 yearsPhase "D" ore = 125 M tonnes
-10 -5
200
25050
F
200 M
25 M
75 M50 M
- Pre-production period
A proposed stripping
- Production period50 M tonnes / year
4 yrs. Yr 1
scheduleE
42-3
E
F
2015
stripping scheduledue to the proposedEarlier ore development
25
Period
-10 -5 0 5 10 15 20 25
schedule
4 yrs. Yr 1- Pre-production period
A proposed stripping50 M tonnes / year
- Production period
B
A
C
D
25 M50 M
200 M75 M4
2-3
0
500
250
-10 -5 0 51 2 3 42550
50
75
150
Pre-productionPeriod
200
BA
C
D
0
50
100
-10 -5 0 5
1.08
1.24
3.04
27 31
76
28
Sur
face
Min
e D
esig
nTime (Years)
10
ore deliveriesrequired to sustainMinimum waste stripping
Time (Years)
Pre-production
(Mill
ions
of
tonn
es)
Cum
ulat
ive
Stri
ppin
g
250
0
500
750
A
B
C
D
(Mill
ions
of t
onne
s)D
evel
oped
Ore
50
0
100
150
BA
C
D
It requires 128 M tonnes strippingPhase "D" life = 5 yearsPhase "D" ore = 125 M tonnes
-10 -5 50
200 M
25 M
75 M50 M
- Pre-production period
- Production period50 M tonnes / year
4 yrs. Yr 1
E
42-3
Estripping scheduledue to the proposedEarlier ore development
Period
-10 -5 0 5 101 2 3 4
75
505025
Cushion = 0.66 years
Cushion = 0.80 years
Cushion = 0.34 years
5.003.04
1.241.08
27 31
76
125
($374M)
Period 1$46M
Period 2$42M
Period 3$63M
Period 5$51M
Period 4$65M
Period 6$48M
Period 7 $43MPeriod 8 $16M
Period 1$81M
Period 2$72M
Period 3$63M
Period 5$37M
Period 6$32MPeriod 7
$43M
Period 8$9M
($398M)
Period 4$61M
Period 1$50M
Period 2$37M
Period 3 $60M
Period 4$50M
Period 5 $49M Period 6$50M
($366M)
Period 7 $52M
Period 8 $19M
($372M)
Period 1 $42MPeriod 7 $57MPeriod 8 $11M
Period 2$32M
Period 3$71M
Period 4 $51M
Period 5 $57MPeriod 6 $52M
Long Term Planning and Sequencing
Dr. Kadri Dagdelen
Colorado School of Mines
Sur
face
Min
e D
esig
n
2
Sur
face
Min
e D
esig
n
Long Term Planning and Sequencing
• Objective is to determine the suitability of the limestone resource for the subsequent processing by the cement plant
• Life of mining and reclamation plans• Equipment Selection• Facility layout and Permitting
3
Sur
face
Min
e D
esig
n
Long Term Planning and Sequencing
• Create a geologic model• Define structural domains and stratigraphy• Chemistry• Long and short term variability
• Long term reserves and average chemistry• Estimate the block chemical values• Estimate possible raw mix requirements
• Quarry layout and operational plan yearly mine plans
4
Sur
face
Min
e D
esig
n
Long Term Planning and Sequencing
• Determine mineable resource boundaries• Haul road layout • Define long term reclamation needs
5
Sur
face
Min
e D
esig
n
Midlothian Cement Quarry:Case Study
• Current production 1.8 million tons of limestone• One 50ft to 60ft bench operation • In pit crushing - 1000 ton/per hour capacity• Expand the capacity to 3.6 million tons by bringing
the second bench into production• 50 percent of the production from first 50ft bench
and another 50 percent from the second bench.• %SO3 is not very good for the limestone coming
from the second bench. Blending of these two benches are necessary.
6
Sur
face
Min
e D
esig
n
Midlothian Cement Quarry:Case Study
• Quarry currently operates 10 hours per shift, 5 days per week
• 1000 ton per hour Krubb In Pit Crusher• 2000 ft long main movable belt conveyor
with 500 ft long extension belt• Komatsu 14 and 10 cubic yard loaders
7
Sur
face
Min
e D
esig
n
Midlothian Cement Quarry:Case Study
• Determine next 50 years life of mine plans • Sequencing plan to come up with the right
blend limestone that meets the minimum of %1.3 SO3 requirements
• Determine equipment and capital investment needs for the next 10 years
8
Sur
face
Min
e D
esig
n
Quarry Development and Sequencing
9
Sur
face
Min
e D
esig
n
Holnam Quarry Mining Sequence: First Bench Development
10
Sur
face
Min
e D
esig
nHolnam Quarry Mining Sequence:
Second Bench Development During the First Three Years
11
Sur
face
Min
e D
esig
n
Holnam Quarry Mining Sequence: First and Second Bench Development
12
Sur
face
Min
e D
esig
n
Holnam Quarry Mining Sequence: First and Second Bench Development
13
Sur
face
Min
e D
esig
n
Holnam Quarry Mining Sequence: First and Second Bench Development
14
Sur
face
Min
e D
esig
n
Midlothian North Area Quarry Progress Contours Year1
15
Sur
face
Min
e D
esig
n
Midlothian North Area Quarry Progress Contours Year 2
16
Sur
face
Min
e D
esig
n
Midlothian North Area Quarry Progress Contours Year 3
17
Sur
face
Min
e D
esig
n
Midlothian North Area Quarry Progress Contours Year 4
18
Sur
face
Min
e D
esig
n
Midlothian Quarry Block Model Definition
19
Sur
face
Min
e D
esig
n
Midlothian Quarry Block Model Definition
20
Sur
face
Min
e D
esig
n
Midlothian Quarry Sequence: One Year Increments on Elevation 790
21
Sur
face
Min
e D
esig
n
Midlothian Quarry Sequence: One Year Increments on Elevation 780
22
Sur
face
Min
e D
esig
n
Midlothian Quarry Sequence: One Year Increments on Elevation 770
23
Sur
face
Min
e D
esig
n
Midlothian Quarry Sequence: One Year Increments on Elevation 760
24
Sur
face
Min
e D
esig
n
Midlothian Quarry Sequence: One Year Increments on Elevation 750
25
Sur
face
Min
e D
esig
n
Midlothian Quarry Sequence: One Year Increments on Elevation 750
26
Sur
face
Min
e D
esig
n
Midlothian Quarry Sequence: One Year Increments on Elevation 730
27
Sur
face
Min
e D
esig
n
Midlothian Quarry Sequence: One Year Increments on Elevation 720
28
Sur
face
Min
e D
esig
n
Midlothian Quarry Sequence: One Year Increments on Elevation 700
29
Sur
face
Min
e D
esig
n
Midlothian Quarry Sequence: One Year Increments on Elevation 690
30
Sur
face
Min
e D
esig
n
Equipment Selection
Three Different Options were Evaluated:• One 15 yd3 Caterpillar 992G model loader working
with a 70 ton CAT 775D truck fleet.• One 15 yd3 Caterpillar 992G model loader working
with a 98 ton CAT 777D truck fleet.• One 11 yd3 Caterpillar 990series II model loader
working with a 70 ton CAT 775D truck fleet
31
Sur
face
Min
e D
esig
n
Loader - Truck Fleet Evaluation and Cost Analysis Year 1
32
Sur
face
Min
e D
esig
n
Loader - Truck Fleet Evaluation and Cost Analysis Year 2
33
Sur
face
Min
e D
esig
n
Loader - Truck Fleet Evaluation and Cost Analysis Year 3
34
Sur
face
Min
e D
esig
n
Loader - Truck Fleet Evaluation & Cost Analysis Haul Road Profile
35
Sur
face
Min
e D
esig
n
Loader - Truck Productivity Calculations
Assumptions• 90 % Loader and truck availability resulting
in 81 % fleet availability• 92 % Operator efficiency• 75 % bucket fill factor• 2400 scheduled hrs• 0.55 min. loader cycle time
36
Sur
face
Min
e D
esig
n
Loader - Truck Productivity Calculations
Assumptions (Cont.)• 0.1 min. first bucket dump time• 0.7 min. hauler exchange time• 2492 lbs/yd3 density• 14 ton/pass; 5 passes per truck• 2400 hours per year
37
Sur
face
Min
e D
esig
n
Equipment Productivity & Cost Estimation
• For CAT 992G Loader - 775D Trucks
38
Sur
face
Min
e D
esig
n
Option 1: Cat 992G Loader -775D Trucks
The truck cycle time for four different conditions:
• Year 1: 9.67 minutes• Year 2: 11.05 minutes• Year 3: 10.86 minutes• Year 7: 11.04 minutes
39
Sur
face
Min
e D
esig
n
Option 1: Cat 992G Loader - 775D Trucks Fleet Productivity in Tons
# of 775D's Year 1 Year 2 Year 3 Year 7 1 825,332 808,107 801,532 808,669 2 1,540,565 1,524,899 1,504,316 1,525,959 3 2,111,530 2,108,190 2,070,839 2,109,657 4 2,586,695 2,644,575 2,580,165 2,644,575
40
Sur
face
Min
e D
esig
n
Option 2: Cat 992G Loader -777D Trucks
The truck cycle time for four different conditions
• Year 1: 12.16 minutes• Year 2: 12.63 minutes• Year 3: 12.42 minutes• Year 7: 12.27 minutes
41
Sur
face
Min
e D
esig
n
Option 2: Cat 992G Loader -777D Trucks
# of 777's Year 1 Year 2 Year 3 Year 7 1 945,127 903,286 920,644 934,223 2 1,731,661 1,667,466 1,695,274 1,715,981 3 2,285,652 2,234,289 2,254,834 2,275,379 4 2,737,983 2,714,476 2,724,550 2,731,266
42
Sur
face
Min
e D
esig
n
Operating Cost for the Loader and Trucks
Model Operating CostCAT 992G $125/hrCAT 775 D $63/hrCAT 777 $82/hr
43
Sur
face
Min
e D
esig
n
Operating Cost for the Loader and Trucks
Model Operating CostCAT 992G $125/hrCAT 775 D $63/hrCAT 777 $82/hr
44
Sur
face
Min
e D
esig
n
Loader - Truck Capital Requirements
Model Purchase PriceCAT 992G $1,270,000CAT 775 D $740,000CAT 777 $1,060,000
45
Sur
face
Min
e D
esig
n
Loader - Truck Capital Requirements
• At the start of the production from bench two, $2.1 M is needed to purchase 1 Cat 992G Loader and 775D truck.
• In year 2, additional $1.5M is needed to purchase 2 more Cat 775D trucks.
• For the Cat 992G loader, Cat 777D truck combination, $2.35M and $2.12M would be needed at the start and beginning of year 2.
Sur
face
Min
e D
esig
n
Loaders and Shovels
Comparative Analysis
Dr. Kadri DagdelenColorado School of Mines
Source: J. Wiebmer, Caterpillar Incorporated
2
Sur
face
Min
e D
esig
n
Hydraulic Shovel Applications
• Hard Digging• Poorly shoot material• Selective loading• Wet, jagged floor• Pitching floor• Single face operation
3
Sur
face
Min
e D
esig
n
Hydraulic Shovel Selection Considerations
• Multiple loading fronts• Fast cycle time (25 to 30
seconds)• Low capital costs• Moderate mobility• Highly productive
4
Sur
face
Min
e D
esig
n
Hydraulic ShovelFavorable Site Conditions
• Single loading face• Tight digging materials• Face height equals to stick
length• Some will dig below and
above• Soft floors
5
Sur
face
Min
e D
esig
n
Hydraulic ShovelUnfavorable Site Conditions
• Requires clean-up support• Excessive tramming• High benches
6
Sur
face
Min
e D
esig
n
Wheel Loader Applications
• Mobility and versatility• Well blasted material• Low pile profile• Smooth, level floor• No clean-up support equipment• Short mine life
7
Sur
face
Min
e D
esig
n
Wheel LoaderSelection Considerations
• Highly mobile/versatile• High bucket fill factors• Low capital costs• No clean-up support
8
Sur
face
Min
e D
esig
n
Wheel LoaderFavorable Site Conditions
• Good loading materials• Lower face profile• Multi-face loading
9
Sur
face
Min
e D
esig
n
Wheel LoaderUnfavorable Site Conditions
• Poor underfooting (tire cost)• Soft floor• Tight load area
10
Sur
face
Min
e D
esig
n
Comparison Shovels vs. Loaders
Hydraulic Shovel Wheel Loader
% Operating Weight as bucket payload
8-11% 18-21%
Cost/CY of capacity ($1000)
100-120 60-80
Economic life (1000 hours)
30-60 30-60
Operating Cost/ton 0.07 - 0.12 0.07 - 0.12
Market Share (1980) 15% 85%
Market Share (1990) 30% 70%
11
Sur
face
Min
e D
esig
n
Mobility
0 200 400 600 800 1000 1200 1400
HydraulicShovel
Wheel Loader
Feet Traveled in One Minute
12
Sur
face
Min
e D
esig
n
Breakout Force
• For similar bucket capacities, a hydraulic shovel and a wheel loader will show approximately the same breakout force.
• However, because the difference in bucket shapes, the shovel can apply twice as much force.
• The shovel can apply the force over its reach of the face.
13
Sur
face
Min
e D
esig
n
Bucket Fill Factors
Hydraulic Front Shovels 80-85%
Hydraulic backhoes 100%
Caterpillar wheel loaders 100-115%
Other wheel loaders 85-95%
14
Sur
face
Min
e D
esig
n
Power and Fuel
• Hydraulic shovels burn less fuel per hour than wheel loaders.
• But considering tons moved per gallon burned, wheel loaders and hydraulic shovel compare very favorable to each other.
15
Sur
face
Min
e D
esig
n
Two-to-Three Minute Rule
• A truck does not make money when its tires are not running.
• Truck load times should be in the two to three minute range.
• Loading times are reduced by the use of the right loading tool, better rock fragmentation, operator training, and face supervision.
16
Sur
face
Min
e D
esig
n
Loading Tool Preferences
85% 15%
60% 40%
50% 50%
Region
North & South America
Europe, Africa, Middle East
Australia, Far East
17
Sur
face
Min
e D
esig
n
Hydraulic Shovel Production Range
Operating Weight (Tons)
Production Range (tons/hour)
140 800 - 1,100
230 1,100 - 1,800
340 1,600 - 2,400
620 3,000 - 4,000
18
Sur
face
Min
e D
esig
n
Wheel Loader Production Range
ModelProduction Range
(tons/hour)
Cat 994 2,700 - 3,100
Cat 992D 1,300 - 1,700
Cat 988B 700 - 900
Cat 980F 500 - 700
Cat 966F 300 - 500
19
Sur
face
Min
e D
esig
n
Conclusions
• No two pits are the same.
• There is a wide array of loading tools to meet operational needs.
• Analysis, not luck, will yield the winner for your operation
Types of Mobile Surface Mining Equipment
•Dozers
•Scrapers
•Trucks
•Front-end Loaders
•Hydraulic Excavators
•Electric Shovels
•Draglines
•Bucket Wheel Excavators
•Blast Hole Drills
Other Bulk Material Handling Systems
Surface and Underground Mining
•Belt Conveyors•Rail Haulage
Types of Underground Mining Equipment
•Blast Hole Drills•Roofbolters•Slushers•Overshot Loaders•Load-Haul-Dump Units (LHDs)•Trucks•Belt Conveyors•Rail Transportation•Hoisting Systems
Loading & Hauling EquipmentLoading Hauling Combination Loading Hauling Combination
Rubber WheelFront End
LoaderTrucks
Loader Scrapers
Front End Loader
TrucksLoad Haul
Dump Bulldozers
Back Hoe GradersOver Shot Loaders
CrawlerTrack
LoaderBulldozers
Track Loaders
Hydraulic Shovel
Bucket Wheel Excavator
Hydraulic Shovel s
Cable Shovel
Over Shot Loaders
Drag Line
Back Hoe
RailConventional
Rail Cars Over Shot Loaders
Mine Cars/ Locomotives
OtherWalking
Drag LinePneumatic/ Hydraulic
Pneumatic/ Hydraulic
Slusher
Dredge Conveyer Conveyers
Skips
SURFACE UNDERGROUND
Comparative Equipment Size
Transport Distances
(Source: Surface Mining Equipment, Martin, et. al., 1982)
Dozers
The dozer, or bulldozer is a crawler or wheel driven tractor with a
front mounted blade for digging and pushing material.
It is used to both excavate and transport material over short
distances.
(Source: Surface Mining Equipment, Martin, et. al., 1982)
Dozer Powered Functions
(Source: Surface Mining Equipment, Martin, et. al., 1982)
Typical Dozer Production Cycle
(Source: Surface Mining Equipment, Martin, et. al., 1982)
Applications
(Source: Surface Mining Equipment, Martin, et. al., 1982)
Land clearance: The dozer can be sized to provide sufficient power, and with proper operating techniques can move most obstacles in its path, including boulders, trees, etc. This makes it the primary tool in clearing land prior to mining. Special blades are available for this application.
Stripping overburden: Some mine plans utilize scrapers and dozers for overburden removal. The dozer, in these operations,moves a portion of the overburden by pushing it over the highwall.
Grading and leveling mining benches: Draglines, electric shovels and wheel excavators require a flat work surface free of boulders; dozers are commonly used in this clean-up operation.
Applications
(Source: Surface Mining Equipment, Martin, et. al., 1982)
Feeding a belt conveyor: The dozer can be effectively employed to push material into a "belt loader" which in turn feeds a belt conveyor.
Trapping for loaders: The efficiency of small to medium sized loading equipment can be improved by using a dozer to rip and position material to be loaded.
Reclamation: Dozers are a basic tool for leveling and recontouringmined out land. Special blades and special wheel models are available for this type of work.
Fait-Allis 41B with single shank ripper leveling dragline spoil piles.
(Source: Surface Mining Equipment, Martin, et. al., 1982)
CAT D11, Black Thunder Mine, Wyoming, Spring 2002
CAT D11, Black Thunder Mine, Wyoming, Spring 2002
CAT D11, Black Thunder Mine, Wyoming, Spring 2002
Scrapers
The scraper is a rather unique machine because of its ability to
excavate material in thin horizontal layers, transport the material a
considerable distance, and then discharge it in a spreading action.
(Source: Surface Mining Equipment, Martin, et. al., 1982)
Scrapers
(Source: Surface Mining Equipment, Martin, et. al., 1982)
Scraper Powered Functions
(Source: Surface Mining Equipment, Martin, et. al., 1982)
Scrapers
(Source: Surface Mining Equipment, Martin, et. al., 1982)
Applications
(Source: Surface Mining Equipment, Martin, et. al., 1982)
Topsoil removal: The scraper is broadly used in those activities which involve selective removal of horizontal horizons and transport to storage.
General reclamation: The scraper is applied in the rough leveling and contouring phase and for replacement of the upper horizons prior to revegetation.
Ore/Coal removal (with or without ripping): Scrapers are employed in cases where the seams are thin and other types of excavating equipment are inefficient.
Applications
(Source: Surface Mining Equipment, Martin, et. al., 1982)
Overburden removal (with or without prior ripping): These can be either initial cuts or prebenching operations for other excavating equipment, or complete overburden removal.
The latter case requires a well planned circular operational layout to minimize travel distances and utilize downgrade loading and dumping.
Typically, operations of this type use dozers for preshaping, supplementary material transport and push-pull scraperloading techniques.
x
Terex S-24B tandem scraper self loading overburden.(Source: Surface Mining Equipment, Martin, et. al., 1982)
Trucks
A truck is simply a mobile piece of equipment for hauling material.
It is often an integral part of the material handeling activities in the
mine for either transport of ore from the face to processing or
stockpile, or for transport of overburden to spoil.
Trucks
(Source: Surface Mining Equipment, Martin, et. al., 1982)
Truck Powered Functions
(Source: Surface Mining Equipment, Martin, et. al., 1982)
(Source: Surface Mining Equipment, Martin, et. al., 1982)
Applications
(Source: Surface Mining Equipment, Martin, et. al., 1982)
These trucks are used exclusively for material transport. The material can be just about anything but, in mining, the broad classifications are:
•Overburden•Ore/Coal
When trucks are used to haul overburden, the mine normally has an open pit or area mine plan with dumping off of spoil benches.
Trucks can be used to haul ore/coal to a hopper or stockpile, invirtually any surface mine plan.
Dumping to stockpile is generally done in shallow lifts.
Applications
(Source: Surface Mining Equipment, Martin, et. al., 1982)
Bottom dump units, driving over a grizzly, are used to feed a hopper.
A back-in hopper station is utilized with rear dumps.
In some cases the trucks carrying coal directly to a nearby power plant will on the return trip transport ash back into the pit for burial.
Large Haul Trucks, Cripple Creek –Victor, Colorado, Fall 2002
Large Haul Truck, Cripple Creek –Victor, Colorado, Fall 2002
Wabco 3200B, 250 ton, three axel rear dump.
(Source: Surface Mining Equipment, Martin, et. al., 1982)
Rimpull three axel bottom dump coal hauler.
(Source: Surface Mining Equipment, Martin, et. al., 1982)
(World Mining Equipment, September 2002)
(World Mining Equipment, March 2003)
Front-End Loaders (FEL)The front-end loader is a wheel or crawler mounted tractor with a
front mounted bucket and is utilized in excavating, loading, and
transporting material.
Because of its versatility, the front end loader is found in a wide
variety of mining applications.
FEL Powered Functions
(Source: Surface Mining Equipment, Martin, et. al., 1982)
(Source: Surface Mining Equipment, Martin, et. al., 1982)
Applications
(Source: Surface Mining Equipment, Martin, et. al., 1982)
The wheel loader is a competitive excavator, loader and transporter.
It competes with shovels, dozers and, over short transport distances, with scrapers and trucks.
Being quite fast, mobile, and versatile, it can be used in a number of mine applications.
Because the FEL has generally not been considered to have the digging ability of a shovel in consolidated digging faces, it finds many of its applications in softer formations, coal/ore andstockpile work.
The larger sizes are more rugged and powerful, and are proving themselves in difficult digging.
Applications
(Source: Surface Mining Equipment, Martin, et. al., 1982)
The primary mine applications are the following:
•Loading and/ or transporting topsoil
•Loading and/ or transporting coal/ ore from the digging face
•Loading and/or transporting coal/ore from stockpile
•Loading and/or transporting overburden and waste
In all of the above loading can be into trucks, hoppers, railroad cars, or belt loaders.
Transport can be for distances up to 1000 feet on the level or grades up to 12%.
CAT 994D loading a haul truck
Heavy Equipment, John Tipler, 2000
Hydraulic Excavators
Hydraulic shovels, primarily a European development, have
proven themselves on construction projects.
The have now reached a level of reliability and have increased in size to the point where units are common in surface mining applications.
Digging Profile
(Source: Surface Mining Equipment, Martin, et. al., 1982)
Hydraulic Excavator Powered Functions
(Source: Surface Mining Equipment, Martin, et. al., 1982)
ApplicationsHydraulic machines are employed in overburden removal, coal/ore loading or, in the smaller sizes, for utility work generally related to mine drainage systems.
The hydraulic shovel is primarily an excavating and loading device. While it can swing and/or propel to transport material short distances, it is used almost exclusively to load trucks or, in some cases, hoppers/crushers.
Hoes have similar uses to shovels. However, their below grade digging capability makes them particularly suited to tasks such as trenching or excavating under water.
Hoes are utilized in mining when floor conditions warrant keeping machines off the bottom of the pit.
(Source: Surface Mining Equipment, Martin, et. al., 1982)
Typical Hydraulic Shovel Production Cycle
(Source: Surface Mining Equipment, Martin, et. al., 1982)
Typical Hydraulic Hoe Production Cycle
(Source: Surface Mining Equipment, Martin, et. al., 1982)
Heavy Equipment, John Tipler, 2000
CAT 5230 hydraulic excavator loading a haul truck
Electric ShovelsThe shovel is one of the oldest types of excavating equipment.
With time, the machines grew in capacity , steam power was replaced by gas, then diesel fuel and finally, in the larger units used in mining today, by electricity.
In recent years, smaller shovels below 5 cubic yards in capacity are being replaced by front-end loaders and hydraulic machines.
(Source: Surface Mining Equipment, Martin, et. al., 1982)
Steam Shovel Mining Virginia Minnesota, circa 1910
Electric Shovels
(Source: Surface Mining Equipment, Martin, et. al., 1982)
Electric Shovel Powered Functions
(Source: Surface Mining Equipment, Martin, et. al., 1982)
Applications
(Source: Surface Mining Equipment, Martin, et. al., 1982)
Electric shovels generally have the same applications as hydraulic shovels although the electric units are considered to be particularly suited to more severe digging conditions.
They are available in larger sizes and have a proven service record in multi-shift mining operations. Electric shovels also tend to have longer range capabilities.
These shovels are applied in benching operations in either overburden or coal/ore.
Discharge is commonly into trucks but can also be into mobilehoppers.
The larger models and/or those equipped with long range front ends may be applied in direct spoiling overburden removal operations.
Loading Plans
(Source: Surface Mining Equipment, Martin, et. al., 1982)
The Bucyrus-Erie 1850-B Brutus with 90-yard dipper at Pittsburg and Midway Coal Mining Company in 1961.
This shovel is currently maintained by a preservation group.
Extreme Mining Machines, Keith Haddock, 2001
The last stripping shovel produced was this 105-yard Marion 5900, sold in 1971 to Amax Coal Company’s Leahy Mine in Illinois.
Extreme Mining Machines, Keith Haddock, 2001
Draglines
(Source: Surface Mining Equipment, Martin, et. al., 1982)
Draglines
Through the years, the dragline has remained a unique excavating tool and has experienced a dramatic growth in maximum size.
With its long reach and ability to dig to substantial depths below itself, it has had broad applications on many irrigationprojects and, in more recent years, in surface mining.
The hydraulic hoe has, to some extent, replaced the smaller sized diesel draglines but the larger diesel and/ or electric machinesretain their popularity.
Draglines, along with the bucket wheel excavators, are the largest pieces of mobile equipment currently manufactured.
Draglines
(Source: Surface Mining Equipment, Martin, et. al., 1982)
Dragline Powered Functions
(Source: Surface Mining Equipment, Martin, et. al., 1982)
The world’s largest operating dragline (one of two), the Bucyrus2570-WS with 160 yard bucket at the Black Thunder Mine, WY.
Extreme Mining Machines, Keith Haddock, 2001
The 100 yard Marion 8800 loading in Kentucky
Extreme Mining Machines, Keith Haddock, 2001
Bucyrus International’s Big Muskie’s 220-yard bucket easily accommodates a high school band. Photo taken in 1969.
Extreme Mining Machines, Keith Haddock, 2001
Bucket Wheel ExcavatorsWheel excavators dig with a rotating bucket wheel that discharges the material onto a belt conveyor.
The material is transported on this conveyor or a series of beltconveyors until it is discharged from the machine.
(Source: Surface Mining Equipment, Martin, et. al., 1982)
Bucket Wheel Excavators
Wheel excavators have been used, in limited numbers, for continuous excavation of unconsolidated materials starting back in the mid 1920's.
Interest in the machines has been much greater overseas with theGermans, in particular, performing extensive application studies and machine development.
Overall use within the United States has been very limited.
(Source: Surface Mining Equipment, Martin, et. al., 1982)
Bucket Wheel Excavator Powered Functions
(Source: Surface Mining Equipment, Martin, et. al., 1982)
Applications
(Source: Surface Mining Equipment, Martin, et. al., 1982)
There are currently very few bucket wheel excavators in service in the US. They have been used for:
•Overburden excavation with direct spoiling
•Overburden excavation with conveyor or truck loading, prestripping for a large dragline or stripping shovel
•Large earthmoving projects (medium size or small fixed wheels)
•Coal excavation with conveyor or truck loading(medium size or small fixed wheels)
•Topsoil removal and Reclamation leveling (small fixed wheels)
Rhineland Lignite Mine, Germanywww.mining- technology.com
World Mining Equipment, September 2002
Förderanlagen Magdenburg (FAM) bucket wheel excavator.
Sur
face
Min
e D
esig
n
Loading Equipment
Dr. Kadri Dagdelen
Colorado School of Mines
2
Sur
face
Min
e D
esig
n
Excavators
3
Sur
face
Min
e D
esig
n
Hydraulic Shovels Specifications
4
Sur
face
Min
e D
esig
n
Excavator Specifications
5
Sur
face
Min
e D
esig
n
Digging EnvelopesFront Shovels
6
Sur
face
Min
e D
esig
n
Curl and Crowd ForcesFront Shovels
7
Sur
face
Min
e D
esig
n
Digging EnvelopesExcavators
8
Sur
face
Min
e D
esig
n
Excavators Bucket
9
Sur
face
Min
e D
esig
n
Loaders
10
Sur
face
Min
e D
esig
n
Breakout ForceLoaders
11
Sur
face
Min
e D
esig
n
Breakout Force from RackbackLoaders
12
Sur
face
Min
e D
esig
n
Carry PositionLoaders
13
Sur
face
Min
e D
esig
n
900 Series II – Dimensions Loaders
14
Sur
face
Min
e D
esig
n
900 Series II – Dimensions Loaders
15
Sur
face
Min
e D
esig
n
SpecificationsLoaders
16
Sur
face
Min
e D
esig
n
SpecificationsLoaders
17
Sur
face
Min
e D
esig
n
Travel Time – LoadedLoaders
18
Sur
face
Min
e D
esig
n
Travel Time – EmptyLoaders
19
Sur
face
Min
e D
esig
n
Excavator Production Calculations
A standard formula for cyclic excavators can be employed:
O = B x BF x D x HS x J x A x 3,600 seconds(1+S) C hour
Bucket Load Buckets/Period
20
Sur
face
Min
e D
esig
n
Bucket Load
B x BF x D/(1 + S) < Recommended Operating Capacity
• With wheel loaders:50% of full turn static tipping load fora specific bucket type
• With front shovels:Maximum load
21
Sur
face
Min
e D
esig
n
Bucket Load
• Bucket weight depends on size, duty and ground engaging tools
• Bucket size depends on reach• Bucket size (B) based on 2:1 heap• Bucket fill (BF) decreases with increasing
material consolidation
22
Sur
face
Min
e D
esig
n
(CAT)
Wheel Loader Bucket Fill Factors
23
Sur
face
Min
e D
esig
n
Weight of Materials
(CAT)
24
Sur
face
Min
e D
esig
n
Bucket Load
• % Swell increases and load factor decreases with degree of consolidation
• In place density (D) important and should be a measured number
• Loose density (D/(1 + S)) important and should be a measures number
25
Sur
face
Min
e D
esig
n
Buckets/Period
• Average cycle time (C) based on standard cycle time adjusted for:• Material• Material fragmentation• Material size distribution• Pile configuration
26
Sur
face
Min
e D
esig
n
Buckets/Period
• Average cycle time (C) based on standard cycle time adjusted for:• Consistency of operation• Swing angle (Shovels)• Travel distance (Loaders)• Operator ability
27
Sur
face
Min
e D
esig
n
Wheel Loader Cycle Time
Average cycle time for truck loading increases with machine size
.60-.7015-21
.55-.607.5-11
.50-.555.0-7.5
.45-.501.7-4.5Cycle time (min)Loader Size (cy)
28
Sur
face
Min
e D
esig
n
Cycle Time
• Hours scheduled (HS) usually a given, based on management preferences and required output
• Longer shifts appear to be trend to minimize start-up, shut-down impact
29
Sur
face
Min
e D
esig
n
Cycle Time
• Job factor (J) depends on: • Truck assignment• Management issues• Job layout (Blending, etc.)
30
Sur
face
Min
e D
esig
n
Cycle Time
• Mechanical availability (A) depends on:• Material• Management/suppliers• Age of machine• Schedule
31
Sur
face
Min
e D
esig
n
Loading Methods
• Loading method impacts cycle time and job factor• Wheel loaders
• Y pattern used with machine digging point left to right• Truck spotting location important• With a limited truck fleet and excess loader capacity,
staggered and chain loading can be utilized
32
Sur
face
Min
e D
esig
n
Loading Methods
33
Sur
face
Min
e D
esig
n
Loading Methods
(Mining Magazine)
34
Sur
face
Min
e D
esig
n
Shovels:Double Back-Up
Options include • Double back-up• Single back-up• Drive-by• Modified drive-by
35
Sur
face
Min
e D
esig
n
Shovels:Double Back-Up
• Trucks loaded on both sides• Average swing angle reduces• Clean-up allowed on one side while loading
continues• Moves required as shovel penetrates bank
36
Sur
face
Min
e D
esig
n
Shovels:Double Back-Up
37
Sur
face
Min
e D
esig
n
Shovels:Double Back-Up
Requires balance of move time versus cycle time
(Oslund and Russell)
38
Sur
face
Min
e D
esig
n
Shovels:Single Back-Up
• Truck loaded on one side• Larger swing angle• Potential clean-up delays• Potential spotting delays depending on
excavator first cycle
39
Sur
face
Min
e D
esig
n
Shovels:Single Back-Up
40
Sur
face
Min
e D
esig
n
Shovels:Drive-By
• Used with tractor trailers• Large swing angles• Potential clean-up delays• Minimal amount of shovel moves• Blending problems
41
Sur
face
Min
e D
esig
n
Shovels:Drive-By
42
Sur
face
Min
e D
esig
n
Shovels:Modified Drive-By
• Truck backs in to reduce swing angle• Potential clean-up delays• Minimal amount of shovel moves• Blending problems• Depth of cut effects cycle time and move
time
43
Sur
face
Min
e D
esig
n
Shovels:Modified Drive-By
44
Sur
face
Min
e D
esig
n
Modified Drive-By:Optimum Width
Production Estimating of Material Movement With Earth Moving Equipment
There are five factors which need to be considered in preparing aproduction estimate of earthmoving equipment for any particular job.
These factors include:1. Earthmoving Cycle Components2. Job Efficiency Factors3. Material Weights & Swell Factors4. Vehicle Payloads5. Selection of Equipment
1. Earthmoving Cycle Components
The productivity cycle of any earthmoving job may be separatedinto six components:
1. load, 2. haul or push, 3. dump, 4. return, 5. spot,6. and delay.
Each of these components is responsible for a certain percentage of thetotal cycle time.
The factors affecting these components will determine the time eachcomponent will require.
Load Factors
• Performance ability of unit• Hauling distance• Haul road condition• Grades• Miscellaneous factors affecting haul speed
Haul/Push Factors
• Size and type of loading machine • Type & condition of material to be loaded• Capacity of unit • Skill of the loading operator
Dump Factors
• Performance ability of unit• Return distance• Haul road condition• Grades• Miscellaneous factors affecting return speed
Return Factors
• Destination of material -Hopper, Over Bank, Fill, Stockpile, etc.• Condition of dump area• Type & maneuverability of hauling unit• Type & condition of material
Spot Factors
• Time spent waiting on loading unit or pusher• Time spent waiting to dump –at crusher
Delay Factors
• Maneuverability of unit• Maneuver area available• Type of loading machine• Location of loading equipment
2. Job Efficiency FactorsAn estimate must indicate sustained, or average earthmoving production over a long period of time.
Overly optimistic hourly production estimates will result in failure to maintain forecasted production, and an insufficient number of unitsassigned to the job.
It is necessary to allow for the unavoidable delays encountered on all operations such as night operating, shovel moving, blasting, weather, traffic, shutdowns, or for factors such as management and supervisionefficiency, operator experience, proper balance of auxiliary equipment such as tamping roller, pusher or spreader bulldozers, proper crusher capacity, etc.
2. Job Efficiency FactorsThe maximum productivity of an earthmover should be derated to meet actual conditions. Typical deration factors are found in the following table:
3. Material Weights & Swell FactorsThe weight of material is most often expressed in pounds per cubic yard.
Undisturbed or “in place” material is called a bank cubic yard (BCY).
Material in a loose, broken, or blasted state is called a loose cubic yard (LCY).
3. Material Weights & Swell FactorsThe relationship between bank and loose cubic yards is established by the swell factor or percent swell.
For example, the percent swell of shale is 33% indicating that one bank cubic yard of shale will swell to 1.33 cubic yards in the loosestate.
Shale weighs 2800 pounds per bank cubic yard. At a swell factor of 0.75 (inverse of 1.33) the weight of one loose cubic yard of shale is 2100 pounds (2800 pounds * 0.75).
Note: Earthfill projects employ mechanical means such as rolling, tamping and adding water to compress the deposited loose cubic yard back to the state it was in the bank. This compaction may reduce the volume of the bank cubic yard by as much as 15%.
4. Vehicle PayloadsThe rated payload of hauling units is given on the specification sheets in pounds, struck (water level) capacities and SAE capacities.
For haulers the SAE heaped capacity is for a load at a 2: 1 slope. For scrapers the SAE heaped capacity is for a load at a 1: 1 slope.
For estimating purposes, the payload in pounds should not be exceeded.
Vehicle Payloads Should Not Be Exceeded
4. Vehicle PayloadsLoaders, scrapers and haulers all carry material in the loose condition.
To assure adequate volumetric capacity, the pounds payload should be divided by the weight per loose cubic yard and compared to the heaped capacity as shown below:
5. Selection of Equipment
After the estimator has examined the job requirements and operating conditions and decided to investigate earthmoving equipment, a tentative equipment selection will be made.
The final decision will, of course, depend on which method offers the lowest cost per yard or ton.
In some cases, methods such as draglines, belt conveyors, etc. will also be considered.
Example
Rock density: 11 cubic feet per short tonSwell factor: 1.6
ShovelBucket capacity: 18.8 cubic yardsDigging cycle time: 30 seconds per passBucket fill factor: 0.92
TruckLoad capacity: 62 cubic yards struck
88 cubic yards at 2:1 SAE140 tons payload capacity
a) Calculate the number of passes to load the truck.b) Calculate the total time required to load a truck.
Loading and HaulingFleet Productivity
Dr. Kadri Dagdelen
Source : Hrebar – Lafarge 2000 Presentation
Sur
face
Min
e D
esig
n
2
Truck Selection
• Number and type of trucks selected should be based on overall system economics
• Lowest cost fleet selected considering operating and capital coats
Sur
face
Min
e D
esig
n
3
Truck Selection
• Production requirement and operating schedule
• Material characteristics• Density in place and loose, swell• General size distribution, particularly maximum
and minimum sizes and percentage of total• Hardness and texture• Ease of handling
Sur
face
Min
e D
esig
n
4
Truck Selection
• Physical and climatic conditions• Effect of altitude on engine efficiency• Effect of ambient temperature on engine cooling, tire
performance, and use of lubricants• Effect of rainfall, frost, snow, fog, etc. on road conditions
and travel
• Haul road characteristics• Length, grade, and surface condition of
segment
Sur
face
Min
e D
esig
n
5
Truck Selection
• Loading• Space and ground conditions at loading point• Type and size of loading equipment• Total availability of loading equipment
• Dumping• Dumping arrangements: rear dump into hopper, drive
over hopper, edge of spoil, windrow, etc.• Space and ground condition at dump point• Total availability of down stream equipment
Sur
face
Min
e D
esig
n
6
Truck Selection:Rear Dump
• High horsepower to weight ratio• Deep pits, high grades, maneuverability required
high impact and rough in pit conditions. • Can be used with any type of material ( e.g.,
blocky, free flowing, etc. )• Used for dumping into hoppers or over bank or fill• Economic distance limited
Sur
face
Min
e D
esig
n
7
Truck Selection:Bottom Dump
• Low HP/weight ratio• Free flowing material• Dumping over hopper or in windrow• Operational advantages: Dump on the move,
More favorable tire and axle loading, high speed hauling on level hauls
• Moderate grade and long distance hauls
Sur
face
Min
e D
esig
n
8
Production Calculations
• The prime mover delivers a force that propels the haulage vehicle plus the load
• The force the drive wheels deliver to the ground is referred to as rimpull
• This force is a function of: the torque developed by the engine, the ratio of the gears, and the size of the wheels
Sur
face
Min
e D
esig
n
9
Production Calculations
• Maximum velocity is reached when rimpullis equal to resisting forces of gravity, rolling resistance. etc.
Horsepower x 375 x EfficiencyAvailable Rimpull =
Speed in MPH
Sur
face
Min
e D
esig
n
10
Rimpull vs. Velocity
Sur
face
Min
e D
esig
n
11
Rolling Resistance
• Measure of the force required to overcome internal bearing friction and the retarding effect between the tires and the ground (i.e., tire penetration and tire flexing).
• Expressed in terms of lb/ton vehicle weight or % vehicle weight
• Haul Road Resistance can be estimated by:RR = 2%+1.5% per inch of tire penetration
Sur
face
Min
e D
esig
n
12
Rolling Resistance FactorsTYPICAL ROLLING RESISTANCE FACTORS
Various tire sizes and inflation pressures will greatly reduce or increase the rolling resistance. The values in this table are approximate, particularly for the track and track+ tire machines. These values can be used for estimating purposes when specific performance information on particular equipment and given soil conditions is not available See Mining and Earthmoving Section for more detail:
ROLLING RESISTANCE, PERCENT ̀ Tires Track Track
UNDERFOOTING Bias Radial ** +Tires A very hard, smooth roadway, concrete, cold asphalt or dirt surface, no penetration or flexing 1.5%* 1.2% 0% 1.0% A hard; smooth, stabilized surfaced roadway without penetration under load; watered; maintained 2.0% 1.7% 0% 1.2% A firm, smooth, rolling roadway with dirt or light surfacing, flexing slightly under load or undulating, maintained fairly regularly, watered 3.0% 2.5% 0% 1.8% A dirt roadway, rutted or flexing under load; little maintenance, no water, 25 mm (1”) tire penetration or flexing 4.0% 4.0% 0% 2.4% A dirt roadway; rutted or flexing under load; little maintenance, no water, 50 mm (2”) tire penetration or flexing 5.0% 5.0% 0% 3.0% Rutted dirt roadway, soft under travel, no maintenance, no stabilization 100 mm (4”) tire penetration or flexing 8.0% 8.0% 0% 4.8% Loose sand or gravel 10.0% 10:0% 2% 7.0% Rutted dirt roadway, soft under travel, no maintenance, no stabilization, 200 mm (8”) tire penetration and flexing 14.0% 14.0% 5% 10:0% Very soft, muddy, rutted roadway, 300 mm (12”) tire penetration, no flexing 20.0% 20.0% 8% 15% *Percent of combined machine weight. **Assumes drag load has been subtracted. to give Drawbar Pull for good to moderate conditions. Some resistance added for soft conditions. (CAT)
Sur
face
Min
e D
esig
n
13
Grade Resistance
• Force required to overcome gravity when moving vehicle uphill. Expressed in % vehicle weight (adds power to vehicle downhill).
• Percent Grade = Vertical rise or drop (ft) x 100Horizontal Distance (ft)
e.g., 60 ft rise in 1,000 ft, Grade = 60/ 1,000 x 100 = 6%Horizontal Distance =
(Horizontal distance2 + vertical distance2)1/2
e.g., (1,0002 +602)1/2 = 1,001.8 ft
Sur
face
Min
e D
esig
n
14
Weights and Traction
• Weights: determines the force required to propel vehicle.• Function of vehicle weight, rated capacity (CY), and
density of material hauled, number of passes of excavator
• Traction: force deliverable can be limited by traction conditions• Usable rimpull is a function of road surface and weight
on the drive wheelsUsable Rimpull =
Coefficient of Traction x Weight on Drive Wheels
Sur
face
Min
e D
esig
n
15
Coefficient of Traction Factors
(CAT)
Sur
face
Min
e D
esig
n
16
(CAT)
Altitude Deration
Sur
face
Min
e D
esig
n
17
Speed Limits
• Speed Limits: limits on curves, in pit, and on main haul roads• Curves based on radius and super elevation• In pit, ramp, and main haul roads, the speed limit
depends on haul road width and conditions
Sur
face
Min
e D
esig
n
18
Acceleration, Deceleration, Operator
• Speeds obtained from performance curves indicate maximum velocity under optimum conditions on a given profile.
• These speeds must be corrected for acceleration, deceleration, and operator performance to yield reasonable haul and return times.• F=Ma Simulation utilized to account for acceleration and
deceleration • Time studies indicate that simulated haul times are less
than actual haul times
Sur
face
Min
e D
esig
n
19
Tires
• Limit capability of machine to perform by limiting load and speed
• Ton-mile-per-hour ratings should not be exceeded and depend on:• Weight (Flex/revolution)• Speed (Flexes/period)• Ambient Temperature• Road Surface Temperature
Sur
face
Min
e D
esig
n
20
Tires
TMPH = Average Tire Load x Average Speed for Shift
Average Tire Load = Empty Tire Load + Loaded Tire Load (tons)2
Average Speed = Round Trip (mi) x Trips/ShiftTotal Hours (hr)
Limits by tire type and limits may also include maximumspeed
Sur
face
Min
e D
esig
n
21
Ton-MPH Data
(CAT)
Sur
face
Min
e D
esig
n
22
Estimating Cycle Time
• Limiting factors are considered in developing an estimate of the cycle time. The cycle time consists of variable or travel time (haul and return time) plus the fixed time (load, dump, and spot times).
• Travel time (haul and return times) is a function of payload, vehicle weight, HP/weight ratio, haul road segment lengths, rolling and grade resistance, speed limits, etc.
Sur
face
Min
e D
esig
n
23
Estimating Cycle Time
• Loading time is a function bucket size, fill factor, excavator cycle time, loose material density, and truck capacity
• Other fixed times depend on loading method and dump configuration• Spot and maneuver in loading area (typically .6-.8 min)• Dumping (typically 1-1.2 min)
• Unit production calculated considering truck payload, truck cycle time, hours per shift, and operating efficiencyS
urfa
ce M
ine
Des
ign
24
Unit Production
• Unit Production (Tons/shift)• Truck payload / Truck cycle time x Operating
efficiency x Hours/shift• Units required are a function of total shift tonnage
requirements and unit production and mechanical availability
• Units Required Operating• Tons required/shift / Unit truck production/shift
(Usually rounded up)
Sur
face
Min
e D
esig
n
25
Unit Production
• Units Required Purchased• Units Required Operating (Not rounded) /
Mechanical availability
Sur
face
Min
e D
esig
n
26
Match Factor and System
• Production of the excavator truck system dependent on the number of trucks assigned to the excavator
Sur
face
Min
e D
esig
n
27
Allocations based on at least two approaches:• Number of trucks = Truck cycle time / Load time
(excluding first pass)This calculation approach reduces excavator delays
• Number of trucks = Truck cycle time
Load time (excluding first pass) + Truck exchange time
Match Factor and System
Sur
face
Min
e D
esig
n
28
Match Factor Approach
• Match factor approach reduces truck delays compared to first method. For example:L o a d e r c y c l e t i m e . 5 m i nN o . o f p a s s e s 7E f f e c t i v e l o a d i n g t i m e ( 7 - 1 ) x . 5 3 . 0 0 m i nT r u c k s p o t t i m e ( e x c h a n g e t i m e ) 1 . 3 0 m i nH a u l , d u m p a n d r e t u r n 1 2 . 7 1 m i nT r u c k c y c l e t i m e 1 7 . 0 1 m i n
N o . T r u c k s ( 1 7 . 0 1 / 3 . 0 0 ) 5 . 6 7N o . T r u c k s ( 1 7 . 0 1 / ( 3 . 0 0 + 1 . 3 0 ) ) 3 . 9 6
Sur
face
Min
e D
esig
n
29
System Production
• System production must consider number of trucks, unit production and excavator availability.
• System production• Number of truck/shift x Unit production (Tons/shift)
x Excavator availability
• Complexity of calculations and variability of times leads to use of fleet production simulators such as FPC and TALPAC
Sur
face
Min
e D
esig
n
30
The End
Sur
face
Min
e D
esig
n
TRUCK SELECTION AND PRODUCTION CALCULATIONS
Dr. Kadri Dagdelen
Sur
face
Min
e D
esig
n
2
Wheel Loader Production Calculations
• Example:Calculate the output in tons/hr of a 990 Wheel Loader with a 11cy bucket with .55 min. cycle time and 95% bucket fill factor loading material with 3100 lbs. per LCY. Assume 85% mechanical availability and 83.3% job factor.
Sur
face
Min
e D
esig
n
3
Wheel Loader Production Calculations (Cont.)
• Equation to estimate the production per hour:
O = BC*BF*D*MA*JF*3,600sec(1+SF)*CT hour
Where,O =Production, tons/hrBC =Bucket Size, CY (Usually heaped at 2:1)BF =Bucket Fill Factor, %D =In Place Density, tons/CYMA=Mechanical Availability, %JF =Job Factor, %SF =Material Swell, %100CT =Average cycle time, seconds
Sur
face
Min
e D
esig
n
4
Wheel Loader Production Calculations (Cont.)
• Solution:
O = 11*0.95*1.55*0.85*0.833*3,600sec33sec
= 1252 tons/hr
Sur
face
Min
e D
esig
n
5
Loader-Truck Production Calculations
• Example:CAT775 truck (65ton) is loaded with a 11.0CY 990 loader with 0.55min cycle time with 95% fill factor.For truck cycle time, use the following table. Determine the number of trucks needed for the loader and the total production per hour.
0.6minSpot
1.8minReturn
1.0minDump
3.8minHaul
Truck cycle time
Sur
face
Min
e D
esig
n
6
Loader-Truck Production Calculations (Cont.)
Tons / cycle = 11CY/cycle * 0.95*3100lb/cy / 2000lb= 16.2T/cycle
# of cycles/truck = 65T / truck / 1 cycle/16.2T= 4 cycles
Loading time = (4-1) cycles * 0.55min / cycle = 1.65 min
Sur
face
Min
e D
esig
n
7
Loader-Truck Production Calculations (Cont.)
Cycle time
1.7minLoad
0.6minSpot
1.8minReturn
1.0minDump
3.8minHaul
Total Cycle time 8.9min
Sur
face
Min
e D
esig
n
8
Loader-Truck Production Calculations (Cont.)
• Number of Trucks/ Loader
No. of Trucks = Truck cycle time / Load time= 8.9 min / 1.65 min= 5.4 trucks(Assume 6 trucks)
Sur
face
Min
e D
esig
n
9
Loader-Truck Production Calculations (Cont.)
• Total ProductionAssume – 50 min / hour, and 85% availability
65T/cycle*1cycle/8.9min*50min/hr*0.85/unit = 312T/hr
Total Production = No. of trucks * tons/hr – unit= 5.4 trucks * 312T/hr per truck= 1685 tons/ hr
Sur
face
Min
e D
esig
n
10
Loader-Truck Production Calculations
• Example:
A quarry works with CAT769D flat floor trucks (Max payload 41T, Engine+-450hp) that is loaded by 8cy loader.
The material density is 2800lb/LCY and the quarry is located at the sea level, sending material at 260tons/ hour to the crusher.Calculate truck loading time, productivity, and number or trucks required.
Sur
face
Min
e D
esig
n
11
Loader-Truck Production Calculations (Cont.)
• Example (Cont.):Loader data:
Capacity: 8cyFill factor: 80%Cycle time: 0.5 min/passMechanical availability: 88%
Sur
face
Min
e D
esig
n
12
Loader-Truck Production Calculations (Cont.)
• Example (Cont.):Truck cycle time data:
Spot time: 0.8 minDump time:1.5min
Truck mechanical availability: 85%
Sur
face
Min
e D
esig
n
13
Loader-Truck Production Calculations (Cont.)
• Example (Cont.):Road profile:
4
2
4
Rolling resistance (%)
0
8
0
Grade (%)
45
20
45
Speed limit (km/hr)
1523
7622
1221
Length (m)Segment
Road condition: Firm
Sur
face
Min
e D
esig
n
14
Loader-Truck Production Calculations (Cont.)
Tons / cycle = 8CY/cycle * 0.8*2800lb/cy / 2000lb= 9T/cycle
# of cycles/truck = 41T / truck / 1 cycle / 9T= 4.6 cycles (5 cycles)
Loading time = (5-1) cycles * 0.5min / cycle = 2.0 min
Sur
face
Min
e D
esig
n
15
Loader-Truck Production Calculations (Cont.)
Haul Speed:Segment1
Total Resistance = 4%Max speed = 42km/h
< Speed limit (45km/hr)
42
Sur
face
Min
e D
esig
n
16
Loader-Truck Production Calculations (Cont.)
Conversion of Max Speed to Average Speed
Weights to HP ratio: 75050kg = 165456lb165456lb / 450hp = 368lb/hp
Haul load length: 122m = 401ft
Conversion factor = 0.51
Avg speed = 42km/hr*0.51=21.4km/hr Sur
face
Min
e D
esig
n
17
Loader-Truck Production Calculations (Cont.)
Haul Speed :Segment2
Total Resistance = 10%Max speed = 16km/h
< Speed limit (20km/hr)
Conversion factor = 1Avg speed = 16km/hr
16
Sur
face
Min
e D
esig
n
18
Loader-Truck Production Calculations (Cont.)
Haul Speed :Segment3
Total Resistance = 4%Max speed = 42km/h
< Speed limit (45km/hr)
Conversion factor = 0.68Avg speed
= 42km/hr*0.68=28.6km/hr
42
Sur
face
Min
e D
esig
n
19
Loader-Truck Production Calculations (Cont.)
Haul Time:Segment1:
0.122km / 21.4km/hr * 60min = 0.34 min
Segment2: 0.762km / 16km/hr * 60min = 2.86 min
Segment3: 0.152km / 28.6km/hr * 60min = 0.32 min
Total Haul Time:0.34+2.86+0.32 = 3.52 min
Sur
face
Min
e D
esig
n
20
Loader-Truck Production Calculations (Cont.)
Return Speed:Segment1
Total Resistance = 4%Max speed = 73km/h
> Speed limit (45km/hr)So, choose 45km/hr
Avg speed = 45km/hr*0.68=30.6km/hr
73
Sur
face
Min
e D
esig
n
21
Loader-Truck Production Calculations (Cont.)
Return Speed :Segment2
Total Resistance = -8%+2% = -6%Max speed = 69km/h> Speed limit (20km/h)
Choose 20km/hr
Avg speed = 20*0.95= 19km/h
69
6%
Sur
face
Min
e D
esig
n
22
Loader-Truck Production Calculations (Cont.)
Return Speed :Segment3
Total Resistance = 4%Max speed = 73km/h
> Speed limit (45km/hr)So, choose 45km/hr
Avg speed = 45km/hr*0.54=24.3km/hr
73
Sur
face
Min
e D
esig
n
23
Loader-Truck Production Calculations (Cont.)
Return Time:Segment1:
0.122km / 30.6km/hr * 60min = 0.24 min
Segment2: 0.762km / 19km/hr * 60min = 2.41 min
Segment3: 0.152km / 24.3km/hr * 60min = 0.38 min
Total Return Time:0.24+2.41+0.38 = 3.02 min
Sur
face
Min
e D
esig
n
24
Loader-Truck Production Calculations (Cont.)
Haul and Return Time Summary:
0.3824.30.5445734401523
2.41190.952069-62-87622
0.2430.60.6845734401221
time (min)Avg. Speed
(km/hr)ConversionLimit
(km/hr)Speed (km/hr)
Total Resistance (%)RR (%)Grade(%)
Length(m)Segment
Return
0.3228.560.6845424401523
2.86161201610287622
0.3421.420.5145424401221
time (min)Avg. Speed
(km/hr)ConversionLimit
(km/hr)Speed (km/hr)
Total Resistance (%)RR (%)Grade(%)
Length(m)Segment
Haul
Total time = 3.52min(haul)+3.02(return)=6.54 min
Sur
face
Min
e D
esig
n
25
Loader-Truck Production Calculations (Cont.)
Truck cycle time (min)
0.8minSpot
3.0minReturn
1.5minDump
3.5minHaul
2.0 minLoad
Total 10.8min
Sur
face
Min
e D
esig
n
26
Loader-Truck Production Calculations (Cont.)
• Slip condition check (Segment2):
Available Rimpull=(Grade resistance + Rolling resistance)
* Gross Vehicle Weight = (8% + 2%) * (34050kg + 41000kg)= 10%*75050kg= 7505kg
Sur
face
Min
e D
esig
n
27
Loader-Truck Production Calculations (Cont.)
Usable Rimpull: Function of road surface and weight on the drive wheels
Usable Rimpull = Coefficient of Traction * Weight on Wheel
Sur
face
Min
e D
esig
n
28
Loader-Truck Production Calculations (Cont.)
Typical Coefficient of Traction
Sur
face
Min
e D
esig
n
29
Loader-Truck Production Calculations (Cont.)
Weight of Wheel:
769D: Rear 66.7%, Front 33.3% Distribution (by CAT Performance Book)
Weight on Rear Tire is 75050kg * 0.667 = 50058kg
Then, Usable Rimpull is 0.6*50058kg*Cos(8%) = 29939kg
Sur
face
Min
e D
esig
n
30
Loader-Truck Production Calculations (Cont.)
• CONDITION CHECK
Usable Rimpull > Available Rimpull
There is no slip condition.
Sur
face
Min
e D
esig
n
31
Loader-Truck Production Calculations (Cont.)
• Unit Production
Assuming 50min / hour
Productivity:41T/cycle*1cycle/10.8min*50min/hr*0.85 = 161T/hr
Sur
face
Min
e D
esig
n
32
Loader-Truck Production Calculations (Cont.)
• Number of Trucks/ Loader
For maximum productivity: 10.8min / 2.0min = 5.4 (6trucks)
To achieve 260T/hr: 260 / 161 = 1.61 (2 trucks)
Sur
face
Min
e D
esig
n
Fleet Size Determination Using Binomial Distribution
by
Dr. Kadri Dagdelen
Sur
face
Min
e D
esig
n
2
Sur
face
Min
e D
esig
n
Example
Consider the following fleet:
One loader, 80% mechanical availability and an estimated productivity of 9,000 tons per operating shift.
Three haul trucks, 70 percent mechanical availability and an estimated productivity 0f 4,000 tons per operating shift.
3
Sur
face
Min
e D
esig
n
Example
Assume that the fleet is scheduled 100% of the time and will only be inoperative if either the loader or all the trucks are down for repairs.
4
Sur
face
Min
e D
esig
n
Wrong Assumption
One could incorrectly assume that the average loader production would be 80% of 9,000 tons per shift, or 7,200 tons per shift.
However, since the loader production is dependent on available haul trucks, the truck downtime distribution must be considered.
5
Sur
face
Min
e D
esig
n
Binomial Distribution
xnx ppxnx
n −−⋅−
)1()!(!
!
This formula gives the fraction of time x units are available out of a fleet of n units with a given availability of p.
6
Sur
face
Min
e D
esig
n
Binomial Distribution for Trucks
42.0)7.01(7.0)!12(!1
!2 121 =−⋅−
−
Availability = 70%
0 1 2 3 4 5 6
1 0.30 0.70
2 0.09 0.42 0.49
3 0.03 0.19 0.44 0.34
4 0.01 0.08 0.26 0.41 0.24
5 0.00 0.03 0.13 0.31 0.36 0.17
6 0.00 0.01 0.06 0.19 0.32 0.30 0.12
Fleet Size (n)
Number of Units Available (x)
Fraction of the time that 1 truck out of a fleet of 2 will be operating
7
Sur
face
Min
e D
esig
n
Fleet Capacity
The fleet capacity can be stated as follows:
The loader operates 80% of the time and during this time, 34% will be at 9,000 tons per shift, 44% will be at 8,000 tons per shift, and 19% will be at only 4,000 tons per shift.
0.80 x 0.34 x 9,000 = 2,448 tons
0.80 x 0.44 x 8,000 = 2,816 tons
0.80 x 0.19 x 4,000 = 608 tons
TOTAL = 5,872 tons
8
Sur
face
Min
e D
esig
n
Fleet Capacity
From this example, it can be seen that production from the loader would be 18% short of the initial estimate of 7,200 tons per shift that was determined without consideration of the haul fleet.
9
Sur
face
Min
e D
esig
n
Haul Truck Requirement Determination
Annual target objective 1,800,000 tons
Shifts scheduled 250 shifts
Tonnage requirements per shift 7,200 tons
Average truck productivity 4,000 tons per shift
Need 1.80 operating trucks per shift
3 trucks at 70% availability will average 2.1 shifts
10
Sur
face
Min
e D
esig
n
Haul Truck Requirement Determination
It could be incorrectly assumed that 3 trucks would be sufficient.
However, if the loading fleet contains only 1 loader , then 20% of the time the haul fleet would be idle waiting for the loader to be repaired.
It is also known that the loader could not keep up with three trucks and production would be limited to 9,000 tons per shift, not the 12,000 tons indicated by the haulage capacity.
11
Sur
face
Min
e D
esig
n
Haul Truck Requirement Determination
250 shifts x 0.80 x 0.34 x 9,000 tons = 612,000 tons
250 shifts x 0.80 x 0.44 x 8,000 tons = 704,000 tons
250 shifts x 0.80 x 0.19 x 4,000 tons = 152,000 tons
TOTAL = 1,468,000 tons per year
The solution in this case would be to purchase another loader or work more shifts.
Estimating Owning and Operating Costs
by
Dr. Kadri Dagdelen
Sur
face
Min
e D
esig
n
2
Sur
face
Min
e D
esig
n
Hourly owning and operating cost estimate
AnalystDate
1 2Machine Designation Track-type Tractor Wheel LoaderEstimated Ownership Period (Years) 7 5Estimated Usage (Hours/Year) 1200 1500Ownership Usage (Total Hours) 8400 7500
1. a. Delivered Price (including attachments) 135,000 1,200,000 b. Less Tire Replacement Cost if Desired 4,000 c. Delivered Price Less Tires 135,000 1,196,000
2. a. Residual Value - % of original deliverd price 35% 48%b. Less Residual Value at replacement 47,250 574,080
3. a. Value to be recovered through work 87,750 621,920 b. Cost per hour 10.45 82.92
4. a. Interest rate 16% 16%b. Interest costs 10.29 76.54
5. a. Insurance rate 1% 1%b. Insurance Costs 0.64 4.78
6. a. Tax rate 1% 1%b. Property tax 0.64 4.78
7. Total hourly owning cost 22.02 169.03
Antonio Peralta11/7/2005
Owning Costs
3
Sur
face
Min
e D
esig
n
Hourly owning and operating cost estimate
8. a. Fuel unit price 2.20 2.20 b. Fuel consumption 5 4 c. Fuel cost 11.00 8.80
9. Lube oils, filters, grease 0.46 0.43 10. a. Life of tires (Hours) 3,500
b. Tires replacement cost 1.14 c. Impact factor 0.20 d. Abrasiveness factor 0.20 e. Z factor 0.30 f. Basic factor 6.20 g. Under carriage 4.34
11. a. Extended use multiplier for repair reserve 1.00 1.00 b. Basic repair factor for repair service 4.50 4.00 c. Repair reserve 4.50 4.00
12. a. Special wear items 1.32 0.60
13. Total hourly operating cost 21.62 14.97
14. Maching Owning plus operating 43.64 184.01
15. Operator's hourly wage (include fringes) 30.00 30.00
16. TOTAL OWNING AND OPERATING COST 73.64 214.01
Operating Costs
4
Sur
face
Min
e D
esig
n
9A. Lube Oils, Filters, Grease
Unit Price Consumption Cost/Hour Unit Price Consumption Cost/HourEngineTransmissionFinal DrivesHydraulicsGreaseFilters
Total 0 Total 0
Track-type tractor Wheel Loader
5
Sur
face
Min
e D
esig
n
12A. Special Wear Items
# Cost Life $/Hour Cost Life $/Hour1 105 150 0.70 50 165 0.302 165 450 0.37 80 450 0.183 125 500 0.25 70 600 0.12456
Total 1.32 Total 0.60
Track-type tractor Wheel Loader
Drilling
Dr. Kadri Dagdelen
Sur
face
Min
e D
esig
n
2
Sur
face
Min
e D
esig
n
Drilling Methods
• Top hammer drilling
Hydraulic self-contained drills
Pneumatic drills with portable air compressors
• Down-the-hole (DTH) drilling
Pneumatically operated carriers with portable air compressors
Hydraulically operated self-contained carriers
• Rotary drilling
Drills for rotary crushing
Drills for rotary cutting
3
Sur
face
Min
e D
esig
n
Surface Drilling Methods and Applications
4
Sur
face
Min
e D
esig
n
Components of Surface Drilling Methods
5
Sur
face
Min
e D
esig
n
Top Hammer Drilling
• Soft to hard rock
• Diameter from 7/8” to 10”
• Top hammer drills can be classified according to their size and principle of operation:
Hydraulic or pneumatic handheld drills
Light hydraulic drills mounted on feeds for mechanized drilling in different types of boom applications
Pneumatic crawler drills operated by a separate portable air compressor
Hydraulic crawler or wheel-based drills operated by a powerpack onboard
6
Sur
face
Min
e D
esig
n
Principle of Top Hammer Drilling
• It can be hydraulic or pneumatic
• It combines four functions
Percussion
Feed
Rotation
Flushing
• Parameters that affect the penetration rate:
Impact energy, impact frequency, rotation speed, feed force, andflushing of the hole
7
Sur
face
Min
e D
esig
n
Relative Penetration Rate as a Function of Percussion Pressure
8
Sur
face
Min
e D
esig
n
The Optimal Adjustment of Drilling Parameters Means Maximum Penetration
9
Sur
face
Min
e D
esig
n
Flushing
10
Sur
face
Min
e D
esig
n
Flushing
11
Sur
face
Min
e D
esig
n
Penetration Rates Between Pneumatic and Hydraulic Top Hammer Drilling
12
Sur
face
Min
e D
esig
n
Bench Drilling Rig
13
Sur
face
Min
e D
esig
n
Bench Drilling Rig
A modern surface crawler drill should fulfill the following requirements, to make the operation economical:
• High penetration rate
• Short cycle times
• High quality holes
• High availability
• Low operating cost
14
Sur
face
Min
e D
esig
n
Choice of Bit Type
15
Sur
face
Min
e D
esig
n
Application Range of Tube Drill Steels
16
Sur
face
Min
e D
esig
n
DTH Drilling
• It is more efficient than top hammer drilling
• A DTH hammer follows immediately behind the bit
• Good drilling accuracy
• DTH drills are used in bench drilling of 3½” to 6½” holes on benches up to 150 feet
• DTH hammer life is dependent on:
Hammer size, operating pressure, rock abrasiveness, and rock drillability
17
Sur
face
Min
e D
esig
n
Principle of DTH Drilling
18
Sur
face
Min
e D
esig
n
A Typical DTH Hammer
19
Sur
face
Min
e D
esig
n
Features of DTH Hammer
20
Sur
face
Min
e D
esig
n
Truck Mounted DTH Drill
21
Sur
face
Min
e D
esig
n
DTH Bit Designs
22
Sur
face
Min
e D
esig
n
Rotary Drilling
• It is used in most major open pit mining operations
• Diameter from 4” to 17½”, depth up to 150 feet
• The key elements in rotary drilling are:
Sufficient torque to turn the bit in any strata encountered
Sufficiently high bit loading capability (pulldown force) for optimum penetration
Sufficient flushing air volume to remove the cuttings during penetration, as well as to provide cool air to the drill bit bearings
Selection of the proper type of bit for the material being drilled
23
Sur
face
Min
e D
esig
n
Principle Rotary Drilling
24
Sur
face
Min
e D
esig
n
Rotary Drills
25
Sur
face
Min
e D
esig
n
Rotary Drills
26
Sur
face
Min
e D
esig
n
Principles of Rotation
27
Sur
face
Min
e D
esig
n
Rotary Power versus Hole Diameter
28
Sur
face
Min
e D
esig
n
Pull Down versus Hole Diameter
29
Sur
face
Min
e D
esig
n
Principles of Feed Systems
30
Sur
face
Min
e D
esig
n
Thrust and Pulldown Force
31
Sur
face
Min
e D
esig
n
Flushing Air Compressor Size
32
Sur
face
Min
e D
esig
n
Carrousel Type Pipe Changer
33
Sur
face
Min
e D
esig
n
Rotary Drilling Accessories
• Drill bits
• Drill pipes
• Shock subs
• Stabilizers
• Saver subs
• Bit subs
34
Sur
face
Min
e D
esig
n
Rotary Drill Bit Components
35
Sur
face
Min
e D
esig
n
Rotary Bit Selection Parameters
Type of ground Tooth or insert spacing Tooth depth Cutting actionSoft formations with low compressive strengths and high drillability: shales, unconsolitaded sands, calcites
HighLarge: Inserts extended chisel shaped
Mostly gouging and scraping by skew cone action, with little chipping and crushing
Medium Formations: harder shales, limestone, sandstones, dolomites
Medium, closeMedium: Inserts short or blunt chisel shaped
Partly by gouging and scraping but with significant chipping and crushing action especially at harder end of type
Hard formations: siliceous limestones, hard sandstones, porphyry copper ores
Close with low intermeshLow: Inserts spherical or conical
Mostly by chipping and crushing by cutter rolling action
Very hard formations: taconites, quartzites
Very close with low intermesh
Very low: Insert hemispherical conical or ovoid
Nearly all excavation by true rolling action of cutters
36
Sur
face
Min
e D
esig
n
Bit Selection for Rotary Drilling
37
Sur
face
Min
e D
esig
n
Insert Shapes for Tricone Bits
38
Sur
face
Min
e D
esig
n
Penetration Rate versus Bit Load
39
Sur
face
Min
e D
esig
n
Principles of Rotary Cutting
Drilling
Dr. Kadri Dagdelen
Sur
face
Min
e D
esig
n
2
Sur
face
Min
e D
esig
n
Penetration Rate
300)log2861( 10
rpmWScP ⋅⋅−=
φ
Where:
P = penetration rate (ft/hr)
Sc = uniaxial compressive strength, in thousands of psi
W/F = Weight per inch of bit diameter, in thousands of pounds
rpm = revolutions of drill pipe per minute
Bauer and Calder, 1967 (Surface Mining Handbook)
3
Sur
face
Min
e D
esig
n
Horse Power
5.15.2 WDrpmKhp ⋅⋅⋅=Where:
D = bit diameter (in.)
W = weight on the bit in thousands of pounds
K = constant that varies with rock type.
As material strength decreases, the value of K increases. This caters for the greater teeth penetration experienced in soft rocks. Values vary from 14 x 10-5 for soft rocks down to 4 x 10-5 for high-strength materials.
Surface Mining Handbook
4
Sur
face
Min
e D
esig
n
Balancing Air Velocity
2/12/1264 dpUm ⋅=Where:
Um =
2420 fpm for 13 mm (1/2 in.) diameter platelets with a density of 2.7 g/cc
d = diameter of the chip in inches
p = density of the chip in lb/ft3
Surface Mining Handbook
5
Sur
face
Min
e D
esig
n
Bailing Velocities
6
Sur
face
Min
e D
esig
n
Bailing Velocities
7
Sur
face
Min
e D
esig
n
Air Requirements Chart
8
Sur
face
Min
e D
esig
n
Optimal Bit Load
5DC
LoadOptimumBit×
=
Where:
C = Rock compressive strength
D = bit diameter in inches
Source: R. Baker, Tamrock
9
Sur
face
Min
e D
esig
n
Total Work
TNRWWTWorkTotal ××××= π2)(
Where:
W = bit load (lbs)
R = penetration rate (feet/min)
N = bit rotation speed
T = torque (foot lbs)
Source: R. Baker, Tamrock
10
Sur
face
Min
e D
esig
n
Rotary Horsepower
CWRD
hpPowerHorse6.1)1000/(95.4
)(×××=
Where:
hp = rotary horsepower
R = bit rotational speed
D = bit diameter (inches)
W = optimum bit load (lbs)
C = rock compressive strength
Source: R. Baker, Tamrock
11
Sur
face
Min
e D
esig
n
Maximum Bit RPM
6.1)1000/(95.4)(
WDChp
RRPMBitMaximum××
×=
Where:
hp = rotary horsepower
R = bit rotational speed
D = bit diameter (inches)
W = optimum bit load (lbs)
C = rock compressive strength
Source: R. Baker, Tamrock
12
Sur
face
Min
e D
esig
n
Volume CFM
×+×
×=
14425.0
14425.0 22 D
PSFD
PCFMVolumeππ
Where:
P = penetration rate
D = bit diameter (inches)
SF = swell factor (0.6 sedimentary or 0.4 Igneous/metamorphic)
Source: R. Baker, Tamrock
13
Sur
face
Min
e D
esig
n
Air Velocity
22
183dD
CFMVelocityAir
−×
=
Where:
d = pipe diameter (inches)
D = bit diameter (inches)
CFM = effective compressor volume (CFM)
Source: R. Baker, Tamrock
14
Sur
face
Min
e D
esig
n
Compressive Strength
9.0)10000/1(2.018.2
)(DP
RWCStrengtheCompressiv
×××××
=
Where:
P = average pure penetration rate (feet/hour)
W = average bit load (lbs)
R = average bit rotation
D = bit diameter (inches)
Source: R. Baker, Tamrock
15
Sur
face
Min
e D
esig
n
Pure Penetration
)10000/(2.018.2
)(9.0 CDC
RWPnPenetratioPure
×××××
=
Where:
P = average pure penetration rate (feet/hour)
W = optimum bit load (lbs)
R = optimum bit rotation speed
D = bit diameter (inches)
C = average compressive strength
Source: R. Baker, Tamrock
Explosives
Definitions
Explosive -A chemical mixture that releases gasses and heat at high velocity, causing very high pressures.
Explosion –Thermochemical process in which mixtures of gasses, solids, or liquids react with almost instantaneous formation of gaseous pressures and heat release.
Detonation – Supersonic explosive reaction which creates a high pressure shock wave, heat, and gasses.
Theory of Blasting
The rock is affected by a detonating explosive in three principal stages.
In the first stage, starting from the initiation point, the blastholeexpands by crushing the blasthole walls. This is due to the high pressure upon detonation.
In the second stage, compressive stress waves emanate in all directions from the blasthole with a velocity equal to the sonic wave velocity in the rock. When these compressive stress waves reflect against a free rock face, they cause tensile stresses in the rock mass between the blasthole and the free face. If the tensile strength of the rock is exceeded, the rock breaks in the burden area, which is the case in a correctly designed blast.
Mechanics of Detonation
Compressive Shock Waves
Tensile Shock Waves
Mechanics of Detonation
In the third stage, the released gas volume "enters" the crackformation under high pressure, expanding the cracks.
If the distance between theblasthole and the free face iscorrectly calculated, the rockmass between the blastholeand the free face will yield andbe thrown forward.
Bench Blast
(Atlas Copco)
History of Explosives Development
1000 -Black Powder•Discovered in China around 1000 A.D.
•Mixture of potassium nitrate (saltpeter), sulfur and charcoal.
•The combustion of charcoal (C) and sulfur (S) is the fuel, and oxygen is contained within the nitrate ion (NO3).
•Marco Polo brought it to Europe where it was originally used for military purposes.
•The first blasting application was in Hungary in 1627 and by the end of the 17th century most of the European miners used black powder to loosen rock.
•The first black powder mills were established in America around the year 1775.
History of Explosives Development
1831-Safety Fuse•William Bickford, an Englishman, patented the “Miners Safety Fuse”, in 1831.
•Safety fuse gave blasters a safe and reliable means of initiating black powder.
1846 -Nitroglycerin•In 1846, Ascanio Sobrero, an Italian, discovered nitroglycerin (C3H5N3O9), but he considered it too unpredictable and hazardous for anyone to use.
History of Explosives Development
1867 -Blasting Caps
•The main problem with nitroglycerin was to get it to shoot consistently.
•Alfred Nobel, a Swede, solved this problem with the invention of the fulminate of mercury blasting cap in 1867.
•Use together with safety fuse, the blasting cap provided an excellent initiating system for nitroglycerin.
History of Explosives Development
1866 –Dynamite
•In his efforts to make nitroglycerin safer to handle, Alfred Nobel in 1866 discovered that Kieselguhr (a diatomaceous earth) not only absorbed three times its own weight of nitroglycerin, but also rendered it less sensitive to shock.
•After kneading and shaping it into a cartridge, it was wrapped in paper and the Dynamite was invented.
History of Explosives Development
1894-PETN•The explosive PETN (C5H8N4O12) was discovered in 1894.
•It was not widely used until the 1940’s and today it is the primary explosive compound in modern initiators and boosters.
1922-Electric Blasting Caps•In the beginning of the 20th century the electric initiation wasintroduced, and by 1922 the first electric delay detonator (with1 sec. delay) came into practical use.
•The introduction of the short delay detonator 10-100 milliseconds) in the late 1940's has had the greatest importancein the development of modern blasting techniques.
History of Explosives Development
1956 –ANFO
•In 1956, ANFO (Ammonium Nitrate and Fuel Oil) was introduced to the U.S. market.
•The success of the ANFO in U.S.A. is indisputable, from a consumption rate of almost nil in 1956, the consumption had increased to over 1,000,000 tons by 1975, the consumption of dynamites has, during the same time, declined from 340,000 tons to 135,000 tons.
History of Explosives Development1960’s -Water gels and slurries
•In the 1960's, we have seen the development of water gels, also called slurries.
•A slurry explosive is a high density aqueous explosive containing ammonium nitrate which is an oxidizer.
•Water gels contain 10 to 30 percent water and are sensitized by carbonaceous fuels, TNT, aluminum, or certain organiccompounds like methylamin nitrate.
•Both cap sensitive and non-cap sensitive water gel explosives are available
History of Explosives Development
1970’s-Nonel•In the late 1970's we saw new non-electrical initiating systems like Nonel being developed.
1970’s -Emulsions•1970's the development of emulsion explosives.
•Emulsion explosives are composed of separate, very small drops of ammonium nitrate solution and other oxidizers, densely dispersed in a continuous phase, which is composed of oil and wax.
•The oil/wax mixture, which is the fuel, is in this way given a very large contact surface to the oxidizer, the ammonium nitratesolution .
Properties of Explosives
In the ideal conditions of dry blastholes a simple explosive can be used, while under wet conditions, more sophisticated products are called for .
The most important characteristics of an explosive are:•velocity of detonation (VOD)•strength•detonation stability•sensitiveness (propagation ability)•density•water resistance•sensitivity•safety in handling•resistance to freezing•oxygen balance•shelf life
Classification of Explosives
The explosives used in civil engineering and mining can nowadaysbe classified as:
•High explosives•Blasting agents
High explosives are characterized by high velocity of detonation (VOD), high pressure shock wave, high density and by being cap sensitive.
Blasting agents are mixtures consisting of a fuel and oxidizer system, where none of the ingredients are classified as an explosive and when unconfined cannot be detonated by means of a #8 test blasting cap (1.0 grams of high explosives). Blasting agents have to be initiated by a primer. ANFO is a typical blasting agent.
Firing Devices
Firing methods can be divided into two main groups:
Non-electric•Safety Fuse and Blasting Cap•Detonating Cord•Nonel system
Electric•Electronic Blasting Caps
Safety Fuse and Blasting Cap
The safety fuse consists of a black powder core that is tightly wrapped with coverings of textile and waterproofing materials.
Safety fuse has a steady well controlled burning speed, usually around 40 seconds per foot.
Safety Fuse and Blasting Cap
To initiate the explosive, a plain detonator has to be attached to the safety fuse.
Detonators of different strengths expressed as a number are available, currently #6 or #8 caps.
The #8 detonator contains approximately 1.0 grams of high explosives, and the #6 about 0.8 grams.
Detonating Cord
Detonating cord consists of a PETN core which is wrapped in coverings of textiles and waterproofing materials.
Detonating cord may be initiated with a #6 detonator and detonates along its entire length at about 7000 meters/second.
It initiates most explosives.
Does not work well with ANFO in small to medium sized blastholes, (incomplete detonation).
Firing pattern for detonating cord blast.
Electric Blasting Caps
Electric detonators can be divided into three different classes according to their timing properties:
•instantaneous•millisecond delays•half second delays
The millisecond delay detonator has a built-in millisecond delay element. Delays are usually available in 25 ms delay intervals.
Electric Blasting Caps
Electric detonators may be connected in series or parallel depending on the number of detonators in the round, and the current available in the blasting machine.
Parallel series circuit.
Electric Blasting Caps
The testing instruments for blasting circuits have to be specially designed for their purpose and be approved by the authorities concerned.
An Ohm-meter is used to control the resistance of single electric detonators, detonators in series and in parallel-series and for the final check before firing.
Electric Blasting CapsThe series are connected in parallel and subsequently measured.
The resistance of the parallel connection is in accordance with Kirckhoffs law:
As the difference in resistance between the series must not exceed ± 5 percent, the resistance of the parallel connection will be:
series ofNumber /seriesResistance
R =
Rn1
...R1
R1
R1
21
+++=
ExampleAssume a blast of 250 V A-detonators with a resistance of 3.6 Ohms each. (The resistance is always 3.6 Ohms independent of legwire length.) The firing cable has a resistance of 5 Ohms and a CID 330 V A blasting machine is used.
In accordance with the instructions on the blasting machine, the round may be connected in 5 parallel series.
Number of detonators in each series: 50.
Resistance per series: 50x3.6=180 Ohms.
Resistance after parallel connection :
Resistance at the firing point is the resistance of the parallel-series connection plus the resistance of the firing cable.36 + 5 = 41 Ohms.
Ohms 365
180series ofNumber
/seriesResistanceR ===
Possible errors during measuring:Resistance too high:
* Larger number of detonators than calculated.* Sub-division into series wrongly carried out.* Poor contact ill some connection or detonator .
Resistance too low:* All detonators are not connected into the circuit.* Sub-division into series wrongly carried out.* Some part of the round not connected into the circuit.
Infinite resistance:* Interruption in series through incomplete connection.* Faulty detonator (usually torn off legwire).
Electric Blasting Caps
Blasting machines of various types are used to fire the rounds.
Shown is the model CI 50 which is designed for firing a maximum of 50 conventional detonators.
Nonel systemThe NONEL detonator functions as an electric delay detonator, but the legwires and the fuse head have been replaced by a plastic tube through which a shock wave is transmitted.
The endsplit of of the shockwave from the plastic tube initiates the delay element in the detonator.
The 3mm diameter plastic tube is coated on the inside with a thin layer of reactive material which transmits the shockwave with a velocity of about 2000 meters per second.
Non-Electric vs. Electric
Tubing Air Space
Shell
Non Electric Cap
Electric Cap
CrimpsPlug
IgnitionCharge Fuse
Powder
FuseElement
PrimingCharge
BaseCharge
ClosureBridgeWire
Nonel systemA connector with a strength of 1/3 a #8 cap is used to connect and initiate the detonators.
Nonel system
NONEL connected for bench blasting.
Nonel system
NONEL detonators may also be connected to a detonating cord using a specially designed clip if noise is not a problem.
Nonel system
A NONEL round may be fired using a plain detonator and safety fuse, or by using a specially designed NONEL system blasting machine.
Bench BlastingBench blasting is the most common kind of blasting work.
It can be defined as blasting of vertical or nearly vertical blastholes in one or more rows towards a free surface.
The blastholes can have free breakage of fixed bottom.
Free breakageFixed bottom
Bench Blasting
The tensile, compressive and shearing strengths of a rock mass vary with different kinds of rock and may vary within the same blast.
As the rock's tensile strength has to be exceeded in order to break therock, its geological properties will affect its blastability.
Faults and dirt-seams may change the effect of the explosive in the blast.
Faulty rock containing voids, where the gases penetrate without giving full effect, may be difficult to blast even though the rock may have a relatively low tensile strength.
Bench BlastingThe requisite specific charge, (kg/m3 ) provides a first-rate measure of the blastability of the rock.
By using the specific charge as a basis for the calculation, it is possible to calculate the charge which is suitable for the rock concerned.
The distribution of the explosives in the rock is of the utmost importance. A closely spaced round with small diameter blastholes gives much better fragmentation of the rock than a round of widely spaced large diameter blastholes, provided that the same specific charge is used.
Burden -the distance between the drill hole and the nearest parallel free face.
Spacing - the distance between holes along rows that are parallel to the face.
Stemming -non-explosive material that is placed in the bore hole to confine the explosives (usually placed near the collar of the hole).
Sub-drilling is the amount of hole that is drilled below the intended new bench level.
Basic Definitions
Blasting Theory
When hole depth equals the bench height masses of rock are oftenleft at the toe of the bench because of lack of reflected tension energy from the free face. The solution for this is either sub-drilling or inclined holes.
Partial Reflected
WaveUn-reflectedCompression
Wave
Leaves Un-fractured Toe
Bef
ore
Bla
stin
g
Aft
er B
last
ing
Blasting Theory
Inclined holes cause total reflective tensile waves at the toe of the bench. This causes a flat lower bench and is a more efficient use of explosives.
Total ReflectedTensile Waves
Vertical Holes vs. Inclined Holes
Vertical Holes• Easier to drill• Avoids difficulties in
fractured rock
Inclined Holes• Commonly drilled between 10 &
15 degrees• Causes more productive
reflected shock wave in toe of bench
Bench Height Factors
Research indicates that bore hole length should
be approximately 3 times the burden
distance.-Ash & Smith, Society of
Explosives Engineers, 1976
Bench Height is a function of both hole diameter and burden distance.
Zone of optimal fragmentation
Burden Spacing Equations
Burden Spacing EquationsAndersonB = K(d*L)**2
Pearse B = K*d*(P/T)**2
AshB = K*d/12
Fraenkel (meters & mm)((R*L)**0.3)*(l**0.3)*(d**0.8)
B =50 B burden distance (inches)
d hole diameter (inches)L hole length (feet)T ultimate tensile strength of rock (pounds per square inch)P stability pressure of explosive (pounds per square inch)K constants (empirically determined)
Rock characteristics are difficulty to mathematically model since rock is never really homogeneous.
Burden Spacing Equations
S/B*f*cs*p
33d
Bmax =
Langefors/Kihlström
Bmax = maximum burden (m)d = diameter in the bottom of the blasthole (mm)p = packing degree (loading density) (kg/liter or g/c3 )s = weight strength of the explosive (ANFO = 1)c = rock constant, 0.3 to 0.5c = c + 0.05 for Bmax between 1.4 and 15.0 metersf = degree of fixation, 1.0 for vertical holes
and 0:95 for holes with inclination 3:1S/B = ratio of spacing to burden
Terminology
Charge Calculations
The maximum burden in the bottom of the blasthole depends on:
•weight strength of the actual explosive (s)•charge concentration (lb)•rock constant (c)•constriction of the blasthole (R1)
Table 1a.
Kadri DagdelenFuat Bilgin
Mining Engineering DepartmentColorado Shool of MInes
RECENT DEVELOPMENTS IN VEHICLE PROXIMITY WARNING AND COLLISION AVOIDANCE SYSTEMS
USING GPS AND WIRELESS NETWORKS
10/29/2006
COLORADO SCHOOL OF MINES
2
OUTLINE
INTRODUCTION
PREVIOS WORK
CURRENT WORK
FUTURE WORK
CONCLUSIONS
MAIN
10/29/2006
COLORADO SCHOOL OF MINES
3
INTRODUCTION Surface Mining Safety Research Program
• Safety Issues• Truck Proximity Warning• Collision Avoidance
• Global Positioning System (GPS)• Wireless Network Technology
10/29/2006
COLORADO SCHOOL OF MINES
4
EE--Mail Requesting Help Mail Requesting Help
Jim:Jim:
You may or may not be aware that at couple of You may or may not be aware that at couple of weeks ago El Abra suffered a fatal accident weeks ago El Abra suffered a fatal accident when a truck driver backed through the berm. when a truck driver backed through the berm. Shortly after that happened, I was asked by Shortly after that happened, I was asked by Dennis Barlett and Hunter White to lead a team Dennis Barlett and Hunter White to lead a team of representatives from North American of representatives from North American operations to make sure that this was the last operations to make sure that this was the last accident of this type that we had to suffer. ….accident of this type that we had to suffer. ….
…………..…………..
Thanks,Thanks,
FerolFerol
The Problem We Face
10/29/2006
COLORADO SCHOOL OF MINES
5
CONCEPTUALIZED SYSTEM
• Software for dump edge recognition
• Trimble GPS
• Trimble 900 MHz radios
• Introduction to 802.11b
10/29/2006
COLORADO SCHOOL OF MINES
6
Field Tests at the Morenci Field Tests at the Morenci Copper Mine Copper Mine -- ArizonaArizona
MORENCI TEST PREVIOUS WORK
10/29/2006
COLORADO SCHOOL OF MINES
7
CURRENT WORK
• LAFARGE QUARRY IMPLEMENTATIONOptiTrack
• Real Time
• Design of the System
• Hardware Development
• Software Development
• Robustness of the System
10/29/2006
COLORADO SCHOOL OF MINES
8
OptiTrack SYSTEM CURRENT WORK
10/29/2006
COLORADO SCHOOL OF MINES
9
Description of the System (Infrastructure)
GPS Differential Correction Service
Data, DTM
GPS data
GPS Differential
GPS
Control Base
OptiTrack Network at Lafarge Quarry
Wireless CommunicationTransmitting Truck Position
Wireless Communication Between Lafarge Quarry and CSM
DTM
10/29/2006
COLORADO SCHOOL OF MINES
10
OptiTrack (Lafarge) CURRENT WORK
• Mobile Clients• Haul Trucks• Manager Trucks• PDAs
• Central Points• Repeaters• Trailer
10/29/2006
COLORADO SCHOOL OF MINES
11
OptiTrack Mobile Clients CURRENT WORK
10/29/2006
COLORADO SCHOOL OF MINES
12
OptiTrack Haul Trucks CURRENT WORK
DC Injector N-Female N-Female
Amplifier 1wt WAF2400-1000
N-Female N -Female
Barrel Adapter N-Male N -Male
Lighting Arrestor WRLA-1.2/1.8 N-Female N -Female
Jumper Cable
N-Male RPTNC-Female
LMR600
N-Male N-Male
Omni Antenna
RS 232
GPS SatellitesGPS Device & Antenna
Wireless PCMCI Card Cisco LMC 352
10/29/2006
COLORADO SCHOOL OF MINES
13
OptiTrack Central Points CURRENT WORK
• Repeater at Mechanic House
• Repeater on the Trailer
10/29/2006
COLORADO SCHOOL OF MINES
14
OptiTrack Repeater CURRENT WORK
10/29/2006
COLORADO SCHOOL OF MINES
15
OptiTrack Trailer CURRENT WORK
10/29/2006
COLORADO SCHOOL OF MINES
16
OptiTrack Trailer CURRENT WORK
10/29/2006
COLORADO SCHOOL OF MINES
17
Schematic Representation of OptiTrack TrailerCURRENT WORK
Power Supplies Solar Panels
Cisco AP 350
DC Injector N-Female N-Female
Amplifier 1wt WAF2400-1000
N-Female N-Female
Barrel Adapter N-Male N-Male
Lighting Arrestor WRLA-1.2/1.8 N-Female N-Female
Jumper Cable
N-Male RPTNC-Female
LMR600
N-Male N-Male
Coax Cable
LMR600 N-Male N-Male
Coax Cable
LMR600 N-Male N-Male
Coax Cable LMR600
N-Male N-Male
Directional Antennas WRPA2400 11-AM
V Pol N-Male
Point to Point Antenna WR2400-24M H Pol
N-Female
RPTNC-male
10/29/2006
COLORADO SCHOOL OF MINES
18
OptiTrack (CSM) CURRENT WORK
OptiTrack at CSM GPS Laboratory
Server
10/29/2006
COLORADO SCHOOL OF MINES
19
OptiTrack Antenna CURRENT WORK
Point to Point Antenna (Brown Building)
10/29/2006
COLORADO SCHOOL OF MINES
20
Schematic Representation of OptiTrack (CSM)CURRENT WORK
Cisco AP 350
RPTNC-male
Jumper Cable N-Male RPTNC-Female
DC Injector N-Female N-Female
LMR600 N-Male N-Male
Amplifier 1wt WAF2400-1000 N-Female N-Female
Barrel Adapter N-Male N-Male
Lighting Arrestor WRLA-1.2/1.8 N-Female N-Female
RF Coax Cable N-Male N-Male
Antenna on the roof of Brown Building
10/29/2006
COLORADO SCHOOL OF MINES
21
OptiTrack Software CURRENT WORK
10/29/2006
COLORADO SCHOOL OF MINES
22
Future Work
• New Mobile Clients• PDAs• Sensors
• Radar Implementation
• Mobile Adhoc Network(MANET)
10/29/2006
COLORADO SCHOOL OF MINES
23
Description of the System (Ad Hoc)
GPS Differential Correction Service
Data, DTM
GPS data
GPS Differential
GPS
Control Base
OptiTrack Network at Lafarge Quarry
Wireless CommunicationTransmitting Truck Position
Wireless Communication Between Lafarge Quarry and CSM
DTM
10/29/2006
COLORADO SCHOOL OF MINES
24
Broadcast Protocols Future Work
Existing Protocols• Flooding• Adaptive-SBA• AHBP-EX
OptiTrack Protocols• Naive Bayes• Adaptive Boosting (AdaBoost)
10/29/2006
COLORADO SCHOOL OF MINES
25
Existing Protocols Future Work
10/29/2006
COLORADO SCHOOL OF MINES
26
Machine Learning Approach Future Work
Classification
Rebroadcast
Discard
Incoming Packet
10/29/2006
COLORADO SCHOOL OF MINES
27
OptiTrack Protocols Future Work
10/29/2006
COLORADO SCHOOL OF MINES
28
Simulation Comparison Future Work
95 %Confidence Interval
10Number of Trials
100 secondsSimulation Time
50Node Max. IFQ Length
64 bytes payloadData Packet Size
100 meterNode Tx Distance
350 x 350 meterNetwork Area
NS-2 (1b7a)Simulator
ValueSimulation Parameter
8060402010Pkt. Src. Rate (pkts/sec)
20151051Average Speed (m/sec)
9070605040Number of Nodes
54321Trial
10/29/2006
COLORADO SCHOOL OF MINES
29
Delivery Ratio of the Protocols
Delivery Ratio
60
65
70
75
80
85
90
95
100
1 2 3 4 5
Trial
Deliver
y R
atio
Adaptive SBA
AHBP-EX
Flooding
AdaBoost
Naive Bayes
Future Work
10/29/2006
COLORADO SCHOOL OF MINES
30
Number of Retransmitting Nodes
Number of Retransmitting Nodes
0
10
20
30
40
50
60
1 2 3 4 5
Trial
Num
ber
of R
etra
nsm
ittin
g N
odes
Adaptive SBA
AHBP-EX
Flooding
AdaBoost
Naive Bayes
Future Work
10/29/2006
COLORADO SCHOOL OF MINES
31
End-to-End Delay Future Work
End-to-End Delay
0
0,5
1
1,5
2
2,5
3
1 2 3 4 5
Trial
End-to
-End D
elay Adaptive SBA
AHBP-EX
Flooding
AdaBoost
Naive Bayes
10/29/2006
COLORADO SCHOOL OF MINES
32
ADHOC & INFRASTRUCTURE Future Work
ADHOC
Infrastructure
10/29/2006
COLORADO SCHOOL OF MINES
33
1.1. The tests that are being carried out at CSM as well The tests that are being carried out at CSM as well as in Lafarge Quarry indicate that as in Lafarge Quarry indicate that ““OptiTrackOptiTrack”” softsoftware system can be used as a proximity warning dware system can be used as a proximity warning device to avoid collisions between off highway truckevice to avoid collisions between off highway trucks and the other vehicles as well as to monitor truck s and the other vehicles as well as to monitor truck positions with respect to dump edge on a 3positions with respect to dump edge on a 3--D topoD topography map.graphy map.
2.2. Integration of the developed GPS based system witIntegration of the developed GPS based system with other systems based on concepts such as RFID, rh other systems based on concepts such as RFID, radar, and video cameras need to be pursued to havadar, and video cameras need to be pursued to have a complete and reliable collision avoidance systee a complete and reliable collision avoidance system.m.
Conclusions
Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512
Sustainability Issues in Mining
Antonio Peralta
by
Source: Rozgonyi and Ramirez, January 2003
Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512
What is Sustainable Development?Sustainable development is:
• A concept of needs;
• Idea of limitations;
• Future oriented paradigm, and;
• A process of change.
This concept reflects a compromise between the world’s tripartite aspirations:
• ECONOMICAL: Promoting economic betterment but preserving of options for future generations.
• ECOLOGICAL: Protecting, maintaining and restoring of environmental quality.
• SOCIAL: Promoting and improving social and community stability and values.
SUSTAINABLEDEVELOPMENT
ECONOMICAL
ECOLOGICALSOCIAL
SUSTAINABLEDEVELOPMENT
ECONOMICAL
ECOLOGICALSOCIAL
Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512
Sustainable Development in Mining
§ Applying the concepts of sustainable development and sustainable natural resource management to energy and mineral resources is not an oxymoron.
§ Energy and mineral resources are mostly not renewable; sustaining any given deposit or mine is not possible. However, SD involves designing, developing and managing resources in a way that is conducive to long-term wealth creation. Minerals are a form of natural capital and thus of endowed wealth.
§ Therefore, mining projects can serve sustainability objectives if they are designed and implemented in ways that build viable long-term capacities, strengthen communities and rehabilitate damaged ecosystems.
Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512
Global Mining and Mineral Industry Trends
• International mergers, and globalization,
• Shifts in supply availability and recycling,
• Consumer demand (responsibility for the whole life cycle of the minerals, metals),
• Political restructuring,
• Economic transformations,
• Social and cultural developments,
• Public attitudes about mining and minerals,
• The new paradigm of “sustainable development”,
• An era of increasing regulations affecting all phases of activity from exploration and extraction to processing and products.
Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512
Principal Mining and Environmental Actions During Each Phase of Mine Development
Environmental assessment
Rehabilitation planExploration permit application
Exploration road construction
Rock core drillingGeochemical analysisGeostatistical analysisOrebody evaluation
Exploration
Comprehensive EIA and reviewMitigation planningReclamation and closure planningConceptual design for closureReclamation and closure costing
Closure fund design
Plan of operationsTechnology selection
Conceptual to final designsCosting and cost benefit analysisInvestment brokerage
Feasibility study
Environmental baseline studyEnvironmental assessment“Fatal Flaw” analysis
Initiation of permitting process
Initial mine and minerals process planningFacilities sitingSchedulingEconometric analysisInitial technology selection
Pre-feasibility study
PRINCIPAL ENVIRONMENTAL MANAGEMENT ACTION
PRINCIPAL MINE PLANNING ACTIONPHASE IN MINE PROJECT DEVELOPMENT
Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512
Principal Mining and Environmental Actions During Each Phase of Mine Development (cont.)
Implementation of closure planSite cleanupFinal reclamationFinal impact assessmentPost closure planning
Facilities decommissioningDismantlingDecontaminationBurialRemovalAsset recoveryRecycling
Closure
Installation of pollution control facilitiesGeneral environmental management (air,
water, land)Construction phase reclamation and
closure
Access and haul road developmentSite clearing and grubbingEarth moving and surface water managementMine dewateringUtilities installationBuilding and infrastructure construction
Construction
TreatmentMaintenanceMonitoringFinal bond release
Post closure
General environmental managementPerformance assessment/auditMonitoringConcurrent reclamationFinal closure designPartial closurePartial bond release
Ore extractionSize reductionMinerals processingSmelting and refiningMaintenance and upgrade
Production
PRINCIPAL ENVIRONMENTAL MANAGEMENT ACTION
PRINCIPAL MINE PLANNING ACTIONPHASE IN MINE PROJECT DEVELOPMENT
Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512
Elements of Environmental Planning
A). INITIAL PROJECT EVALUATION
B). THE STRATEGIC PLAN
C). THE ENVIRONMENTAL PLANNING TEAM
Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512
Environmental Planning Procedures (EPP)A). INITIAL PROJECT EVALUATION:
1. Prepare a detailed outline of the proposed action.
2. Identify permit requirements.
3. Identify major environmental concerns.
4. Evaluate the opportunity for and likelihood of public participation in the decision making process.
5. Consider the amount and effect of delay possibly resulting from public participation during each stage of the project.
6. Evaluate the organization and effectiveness of local citizens groups.
7. Determine the attitudes and experiences of governmental agencies.
8. Consider previous industry experience in the area.
9. Consider recent experience of other companies.
10. Identify possible local consultants and evaluate their ability and experience.
11. Consider having a local consultant check the conclusions of the initial evaluation.
Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512
Environmental Planning Procedures (EPP) (cont.)
B). THE STRATEGIC PLAN:
1. Outline of technical information needed to obtain permits and to address legitimate environmental, land use and socio-economic concerns. Permitting process is quite long and complex.
2. Categorically assign responsibilities for the acquisition of the technical information and hire necessary consultants.
3. Prepare a schedule for obtaining information and data and for submitting permit applications to the appropriate agencies.
4. Select local legal, technical and public relations consultants.
5. Avoid hostile confrontations with environmental groups.
6. Develop a consistent program for the generation of credible factual information.
7. Perform risk assessment.
8. Perform cost analysis.
9. Prepare mine reclamation plan.
Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512
Environmental Planning Procedures (EPP) (cont.)
C). THE ENVIRONMENTAL PLANNING TEAM
The team shall be multidisciplinary:
Ø Mining engineers
Ø Metallurgical engineers
Ø Biologists
Ø Environmentalists
Ø Toxicologists
Ø etc.
Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512
Risk Assessment
1. Data collection and hazard evaluation.
2. Toxicity assessment.
3. Exposure assessment.
4. Risk characterization.
a). Non carcinogenic risks.
b). Carcinogenic risks.
5. Risk assessment / management by considering:
a). What types of problems or failures could occur, and what is the probability that each one will occur?
b). What types of environmental impacts could result?
c). What types of compliance-related retrofits or remediation methods could be required?
d). What are the possible fines or remediation costs?
Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512
Cost Analysis
By considering:
Ø Capital costs
Ø Operating costs
Ø Closure costs
Ø Potential costs for retrofits associated with regulatory compliance
Ø Potential cost for remediation
Ø Life-cycle environmental costs
Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512
Mine Reclamation
i. Surface and groundwater management
ii. Mine waste management
iii. Tailings management
iv. Cyanide heap and vat leach systems
v. Acid Mine Drainage Control
vi. Landform reclamation
vii. Revegetation
viii. Site stability
ix. Subsurface stabilization
x. Erosion prevention
Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512
Mine Reclamation
i. Surface and groundwater management
ii. Mine waste management
iii. Tailings management
iv. Cyanide heap and vat leach systems
v. Acid Mine Drainage Control
vi. Landform reclamation
vii. Revegetation
viii. Site stability
ix. Subsurface stabilization
x. Erosion prevention
Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512
Location of the McLaughlin Mine in California
Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512
Facilities map of the McLaughlin Mine
Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512
Mine waste management
1) 2)
3) 4)
M
c
L
a
u
g
h
l
i
n
Early stage for waste disposal & AMD control facilities Advance of the waste disposal works
Final limit of the waste dump Erosion control by revegetating is started
Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512
5) 6)
7) 8)
Mine waste management (cont.)
M
c
L
a
u
g
h
l
i
n
Advance on the erosion control & and pit backfilling
South pit is backfilled & west dump is almost covered
East waste dump is completely covered
Waste dumps encapsulation is finished
06/14/ 98
05/04/ 92 05/04/ 93
05/10/ 93
Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512
Acid Mine Drainage Control
AMD control facilities at the west waste dump
Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512
Revegetation
Supervising the revegetation works on the west waste dump
(notice the AMD control facilities on the right side)
Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512
Minimizing AMD in open pit mining through mine planning
Antonio Peralta
by
Acid Mine Drainage (AMD)Acid Mine Drainage (AMD)
q It encompasses all issues associated with the environmental effects of sulphide oxidation resulting from mining activities.
q Its significant potential for long-term environmental degradation makes it one of the biggest environmental issues facing the mining industry.
Acid Mine Drainage ExamplesAcid Mine Drainage Examples
Contributing FactorsContributing Factors
q Primary factors are directly involved in the generation of sulphide oxidation products.
q Secondary factors consume or alter those products.
q Tertiary factors are the physical conditions that influence the process.
Problems for Mine OperatorsProblems for Mine Operators
q Impact on mine water quality.
q Impact on aquatic ecosystems.
q Impact on riparian communities.
q Impact on groundwater quality.
q Impairment of the use of waterways.
q Revegetating and stabilizing mine wastes.
q Long term liability.
Acid Mine Drainage ControlAcid Mine Drainage Control
q There is a number of well established principles for minimizing AMD.
q Mine planning to minimize AMD is the most cost effective and desirable solution to the problem.
q Treatment is less desirable due to the long term nature of AMD and associated high treatment costs.
Principles to Prevent Acid Mine DrainagePrinciples to Prevent Acid Mine Drainage
q Exclusion of oxygen from wastes.
q Control of water flux within wastes.
q Minimize transport of oxidation products.
q Neutralization of AMD with alkaline materials.
q Monitoring to determine the effectiveness of remediation measures.
11stst Step Step –– Characterization of Rock TypesCharacterization of Rock Types
q Geological assessment.
q Geochemical tests, classified as static and kinetic tests.
q Static testing evaluates the acid generating and acid neutralizing processes.
q Kinetic testing evaluates the rate of sulphide oxidation, AMD characteristics, and assess potential management techniques.
Geological Assessment Geological Assessment –– Information SourcesInformation Sources
q Acid generation characteristics of similar ore bodies and host rocks.
q Relevant information should be logged and recorded from drill core during the exploration stage.
q Core samples must be retained for further testing.
Geological Assessment Geological Assessment –– SamplingSampling
q Sampling should be representative, based on accepted statistical procedures.
q Representative profiles of all geological units should be sampled.
q The number of samples will depend on geological variability, complexity of rock types, and level of confidence required.
Geological Assessment Geological Assessment –– Handling of SamplesHandling of Samples
q Samples should be stored in a cool, dry environment to minimize sulphide oxidation prior to testing.
q Static tests may require as little as 2 grams of sample.
q Kinetic tests require a minimum of 500 grams of sample.
Geological Assessment Geological Assessment –– InterpretationInterpretation
q Topography and drillholes
Geological Assessment Geological Assessment –– InterpretationInterpretation
q Cross section of the drillholes
Geological Assessment Geological Assessment –– InterpretationInterpretation
q Interpretation of rock types
Geological Assessment Geological Assessment –– InterpretationInterpretation
q 3D view of two interpreted sections
Geological Assessment Geological Assessment –– InterpretationInterpretation
q 3D view of two interpreted sections
Geochemical Tests Geochemical Tests –– Static TestsStatic Tests
q Acid base accounting or net acid producing potential (NAPP) test.
q Net acid generation (NAG) test.
q Saturated paste pH and conductivity (EC).
q Total and soluble metal analysis
Net Acid Producing PotentialNet Acid Producing Potential
q NAPP is determined by subtracting the estimated acid neutralizing capacity of a sample from the estimated potential acidity of the sample.
q It has three components:Maximum potential acidity (MPA)Acid neutralizing capacity (ANC)Sample classification.
Net Acid Generation TestNet Acid Generation Test
q NAG comprises the addition of a strong oxidizing agent such hydrogen peroxide to a prepared sample and the measurement of the solution pH and acidity after the oxidation reaction is complete.
q This test can provide and indication of sulphide reactivity and available neutralizing potential within 24 hours.
Saturated paste pH and conductivitySaturated paste pH and conductivity
q The test gives a preliminary indication of the in situpH and the reactivity of the materials present in the sample.
q A crushed sample (<1 mm) is saturated to create a paste and the pH and EC is determined after a period of equilibration.
Total and soluble metal analysisTotal and soluble metal analysis
q Initial screening should compare metal concentration in the solids with that of the background soils and country rocks in the area.
q Statistical methods are available to determine whether any enrichment is significant.
Geochemical Tests Geochemical Tests –– Kinetic TestsKinetic Tests
q They simulate weathering and oxidation of rock over time under exposure to moisture and air.
q They provide an indication of the oxidation rate and time periods for onset of acid generation (lag time).
q Columns and humidity cells are the most used kinetic test techniques.
Rock ClassificationRock Classification
q Acid Generating (AG)
q Potentially acid generating (PAG)
q Potentially acid consuming (PAC)
q Potentially neutral (PN)
Classification for regulatory and permitting purposes.
22ndnd Step Step –– Quantifying the Materials to be disposedQuantifying the Materials to be disposed
q AMD waste materials includes overburden, waste rock, pit walls, pit floor and tailings.
q A database of the AMD parameters determined in the tests is required.
q A predictive AMD block model should be created using the information available in the database.
Block Modeling Block Modeling
q A block model is a three-dimensional spatial representation of an ore body.
q It is used to quantify the geology an economics of the deposit.
q It is developed by dividing the ore body and the host rock into regularly shaped blocks representing the smallest mineable unit.
Information in the Block Model Information in the Block Model
q Ore grades.
q Contaminants.
q Metallurgical recoveries.
q Physical parameters of the ore.
q Economic parameters.
q Environmental parameters.
Steps to create a block modelSteps to create a block model
q Produce a detailed geologic interpretation.
q Create drill hole composites per material type.
q Perform statistical analysis.
q Perform spatial analysis if sufficient data exist.
q Interpolate a value into each block, for each of the required variables.
Complete Block ModelComplete Block Model
q Block model includes waste and ore blocks.
Constrained Block ModelConstrained Block Model
q Block model includes only ore blocks.
Block Model and Mine DesignBlock Model and Mine Design
q Blocks inside and outside the final pit limit.
33rdrd Step Step -- Mining DevelopmentMining Development
q Site potential and reserves
éExpected pit development
q Development phasing
éPeriod of development
éAreas of extractionby phase
2005
2035
2020
2050
Maps for different time periodsMaps for different time periods
Coordination with ReclamationCoordination with Reclamation
q Clearing / Vegetation removal
q Topsoil management
q Overburden / Waste rockmanagement
q Grading principles
q Erosion control
q Revegetation
Isolation Strategy Isolation Strategy
q The objective is to isolate reactive wastes for selective disposal either separately or within non-reactive materials.
q In some cases, it may be preferable to segregate highly reactive wastes within a separate facility to permit intensive treatment and control strategies.
Waste EncapsulationWaste Encapsulation
q AMD waste is selectively handled and surrounded with non-acid producing materials to limit flow of air and water into waste and AMD flow out.
q A cell structure is formed. The surface is covered with compacted benign material, usually clay.
InIn--Pit DisposalPit Disposal
q Similar in concept to encapsulation. Method is useful where a mined out pit of sufficient size is available.
q With effective mine planning an early closure of one of a series of mined pits allows for in-pit disposal of AMD wastes.
CoCo--disposal and Blending of Wastedisposal and Blending of Waste
q Involves the blending/mixing and co-disposal of AMD wastes with benign non-acid producing materials or even acid neutralizing materials.
q Small cells within a waste dump are rapidly filled and covered to reduce AMD generation and water ingress.
CoversCovers
q A low permeability cover is constructed over an existing waste dump, mainly using locally available borrow or benign waste, to reduce the infiltration of surface water and infusion of air into the dump.
Recovery and TreatmentRecovery and Treatment
q Option for marginal acid producing wastes where subsequent acid drainage is recovered and treated downstream.
q Collection/recovery systems can include catchment ponds, drains, trenches and groundwater bores.
ConclusionsConclusions
qMine planning can be a cost effective method to control AMD in open pit mines.
q There are three basic steps to achieve AMD control: characterize the rock types, quantify the amount and content of the rocks, and develop a mine plan according to the previous steps.
q The mine plan should include waste management strategies to minimize AMD: isolation, encapsulation, in-pit disposal, co-disposal, blending, covers, and treatment.
q A combination of these strategies could be highly effective to control AMD.
Questions and comments???????Questions and comments???????
Summitville, ColoradoSummitville, Colorado
Summitville, ColoradoSummitville, Colorado
According to the United States Environmental Protection Agency (US EPA), mining generates twice as much waste as all other American industries put together.
So-called "hard rock" mining wastes are acidic and contaminated with toxic heavy metals which have poisoned more than 12,000 miles of streams and rivers and 180,000 acres of lakes.
EPA estimates the public cost to clean up the more than 550,000 abandoned mines in America at between $32-72 billion.
The very scale of today's massive open-pit mining operations means that sometimes cleanup costs will outstrip the value of the metals pulled out of the ground, as happened with the $232 million cleanup of the Summitville mine in southern Colorado.
Examples, ColoradoExamples, Colorado
At Eagle mine, a zinc, copper and silver operation, ten million tons of mine waste and mine tailings were left along the banks of theEagle River in Gilman Colorado.
Cleanup costs exceeded $55 million which totaled more than $5.50per ton of mine waste.
A zinc, lead and silver mine at Smuggler Mountain in PitkinColorado. The estimated cost for environmental recovery is $7.2 million. This equals $2.40 per ton of waste.
Feasibility StudiesThe formal feasibility study includes an economic analysis of the rate of return that can be expected from the mine at a certain rate of production.
Some of the factors considered during such an economic analysis are:
Tons in the depositGrade of the mine productMill recoverySale price of the metal or mineralCost of mining per tonCost of milling per tonRoyaltiesCapital cost of the mine
Capital Cost of the millExploration and development costMining rate, tons per dayDepreciation method usedDepletion allowanceWorking capital necessaryMiscellaneous costs of operationTax rate
Risk
Mining is a very risky business.
The most serious risks in any mining project are those associated with:
•Geology: the actual size and grade of the minable portion of the deposit,
•metallurgical factors: how much of the orebody can be recovered, and
•Economics: metal markets, interest rates, mining, processing,ect.
Return on Investment
In order to compensate for risk, a mining organization will require a minimum acceptable rate of return on investment.
The cost of borrowing capital for the mine or of generating the needed capital internally within the company must be considered.
If a company has a number of attractive investment opportunities, the rate of return from the proposed mine venture may be compared with the rate expected on a different mining venture elsewhere, or with some other business opportunity unrelated to mining.
Management has an obligation to its stockholders or investors toselect projects with the best rate of return.
As a general rule of thumb, a project must have better than a 15-percent rate of return to be considered by a major company.
An individual commonly expects a 30- to 50 percent rate of return to consider investing in a mining venture.
Among other uses of the cash flow generated by the mine, these funds must finance:
•continuing exploration elsewhere, •pay for past failures, and •contribute to the mine's portion of main office and general overhead.
Time Value of MoneyMoney has a time value. The future value of an investment can be calculated by:
where:P = Present value of investmentF = Future value of investmenti = interest rateN = number of years
For example $100 invested at 10% interest for 1, 2, and 3 years would yield:
F = 100(1 + .10)1 = $110.00F = 100(1 + .10)2 = $121.00F = 100(1 + .10)3 = $133.10
Ni)P(1F +=
Time Value of MoneyConversely money received in the future is not as valuable as money received today. If money is received in the future:
Using the same example:
P = 110.00/(1 + .10)1 = $100.00P = 121.00/(1 + .10)2 = $100.00P = 133.10/(1 + .10)3 = $100.00
Ni)(1/FP +=
DCF-ROR
The criterion most commonly employed in the minerals industry when evaluating the rate of return on an investment proposal is called the discounted cash flow rate of return (DCF-ROR).
The term is a special version of the more generic term, internal rate of return (IRR).
The internal rate of return is defined a that interest rate which equates the sum of the present value in cash inflows with the sum of the present value of cash outflows for a project:
ΣPV cash inflows = ΣPV cash outflows (3)
DCF-RORThe DCF-ROR can be calculated by:
(4)
where:CFn = Amount of cash in or out in a given yearn = YearN = Project lifei = DCF-ROR
Once the cash flows for a project have been determined, the interest rate i can be solved for using an iterative process, i.e. guess at an initial value for i and then solve Equation 4 until a result of 0 is obtained.
0i)(1
CFN
0nn
n =+∑
=
Steps Involved in Cash Flow Analysis
The evaluation of a mining project is usually an iterative process using the following steps:
1. Select a mining method2. Select a production rate3. Calculate Capital and Operating Costs4. Select cutoff grade and tonnage5. Calculate cash flow and return
Change steps 4, 2, and 1 and select the alternative that gives thehighest return.
Steps Involved in Cash Flow AnalysisIn a feasibility study, attempt to quantify all geologic, technical,marketing, environmental, political, etc. factors. Many of thesevariables are dependent on each other. A feasibility study are usually divided into the pre-production, production, and post-production phases:
1. Preproduction PeriodExploration
Water and land acquisitionMine and mill capital
Working capital, etc2. Production Period
Revenue less costsCalculation Of Annual Cash Flow
3. Postproduction PeriodEquipment salvage
Working capital liquidation
Steps Involved in Cash Flow Analysis
DepletionOne of the features that distinguish a mining enterprise from many other businesses is that during production, the company’s assets, i.e. the ore, is consumed.
The percentage depletion allowance is based on the idea that as minerals are extracted, the mine is worth less.
The percentage depletion allowance permits mining companies to deduct a certain percentage from their gross income to reflect the mine's reduced value over time.
DepreciationDepreciation is an allowable deduction when computing taxable income that represents the exhaustion, wear, and tear of property used in a trade or business, or of property held for the production of income.
The purpose of the depreciation deduction is to provide a means by which a business or trade can recapture the capital needed to keep itself in business.
Therefore depreciation allowances for capital assets are deducted from taxable income in an orderly manner such that the property owner has deducted the initial investment in the asset by the time it wears out or becomes exhausted.
Having recaptured the initial asset cost from the annual tax deductions, the owner can, in theory, replace the worn-out piece of equipment with a new one and keep himself in business.
Case StudyThe calculation of the cash flow and DCF-ROR is illustrated using a bedded zinc deposit, producing 6000 tons per day, with total reserves of 22.5 MM Tons @ 14% zinc.
Simplifying and other assumptions:1. No royalty2. No investment tax credits3. Straight line depreciation and depreciation life equal to life of property4. Federal, state, and local taxes equal to 40% net after depletion5. No replacement or additional equipment requirements 6. No start-up costs or learning curve 7. Uniform grade mined over mine life 8. Uniform production rate over mine life 9. Operating costs constant over mine life 10. Mine would be division of large profitable corporation with 100% of exploration
and development expensed11. No consideration of cost depletion12. Price/cost differential constant over life of mine with no consideration of escalation
and inflation
Cash Flow Calculations
Pre-Production PeriodYear 1 2 3 4 5 6 7 TotalExploration *1 2,000 4000 4000 0 0 0 0 10,000Development *2 0 0 0 4000 8000 8000 0 20,000Mine/Mill 0 0 0 15000 36000 36000 0 87,000Working Capital 0 0 0 0 0 2600 9,300 11,900Total Investment (2,000) (4,000) (4,000) (19,000) (44,000) (46,600) (9,300) (128,900)Tax Savings *3 800 1600 1600 1600 3200 3200 0 12,000Net Cash Flow (1,200) (2,400) (2,400) (17,400) (40,800) (43,400) (9,300) (116,900)
*1 Expensed under Section 617 of IRS Code*2 Expensed*3 Assume federal, state, and local tax rate = 40% of net after depletion
Cash Flow Calculations ($1,000)
Zinc Smelter Schedule
PaymentsSilver: Deduct 2 Troy oz., pay for 80% of remainder at
Handy & Harman quotation for refined silver inMetals Week, averaged for the calendar monthfollowing delivery, less $.055 per oz.
Lead: No payment.
zinc: Pay for 85% of zinc content at delivery price for prime western zinc published in Metals Week, averaged for the calendar month following delivery,less $.015 per pound.
Zinc Smelter Schedule
DeductionsSmelter Charge:
$170/dry ton
Price Adjustment: Increase by $3.00 per ton for each $.01 that the zincquotation exceeds $.40 per pound. Fractions in proportion.
Decrease by $2.00 per ton for each $.01 that the zinc quotation decreases below $.40 per pound. Fractions in proportion.
Smelter Schedule CalculationsConcentrate Grade = 55%zinc Price = $0.47/lb
Payments:2,000 lb/ton * 0.55 * 0.85 * $(0.47- 0.015)/lb = $425.43/ton
Deductions:Base Charge 170.00Price Adjustment(47- 40)c * $3.00/c = 21.00Total Deductions: (191.00)
Freight:Truck 5.00Rail 15.00Total Freight: (20.00)
Net Smelter Return/Ton Concentrate (NSR/T) $214.43/ton
Revenue and Operating CalculationsRevenue/year = Tons/year Concentrate * NSR/ton
Tons/year Concentrate = (Tons/year Ore * Grade * Mill Recovery)/(Conc. Grade)Mine Schedule = 250 Days/yearMill Recovery = 90%
Tons/year Concentrate = 6,000 T/D * 250 D/Y * 0.14 * 0.9/0.55 = 343,636 Tons/year Concentrate .
Revenue/year ($1,000) = 343,636 T/Y * $214.43/1,000 = $73,684/Year
Direct Operating cost/Year = Tons/year Ore * Operating Costs/Ton OreDirect Operating Costs
Mining $15.00 /Ton OreMilling 5.00Overhead 3.00
Total 23.00 /Ton Ore
Operating Cost/Year ($1,000) = 6,000 T/D * 250 D/Y * $23.00/T/1,000 = $34,500/Year
Production PeriodYear 7 8 9 10 11 12-21Revenues 73,684 73,684 73,684 73,684 73,684 73,684Operating Costs (34,500) (34,500) (34,500) (34,500) (34,500) (34,500)Net Before D & D 39,184 39,184 39,184 39,184 39,184 39,184Depreciation (5,800) (5,800) (5,800) (5,800) (5,800) (5,800)Net After Depr. 33,384 33,384 33,384 33,384 33,384 33,384Depletion (6,211) (16,211) (16,211) (16,211) (16,211) (16,211)Taxable Income 27,173 17,173 17,173 17,173 17,173 17,173Tax @ 40% (10,869) (6,869) (6,869) (6,869) (6,869) (6,869)Net After Tax 16,304 10,304 10,304 10,304 10,304 10,304Depreciation 5,800 5,800 5,800 5,800 5,800 5,800Depletion 6,211 16,211 16,211 16,211 16,211 16,211Cash Flow 28,315 32,315 32,315 32,315 32,315 32,315Working Capital (9,300) 0 0 0 0 0Net Cash Flow 19,015 32,315 32,315 32,315 32,315 32,315
Depletion Calculation: 7 8 9 10 11 12-21Initial Recapture 10,00022% Revenue 16,211 16,211 16,211 16,211 16,211 16,21150% Net After Depr. 16,692 16,692 16,692 16,692 16,692 16,692Depletion Earned 16,211 16,211 16,211 16,211 16,211 16,211Depletion Recaptured 10,000 0 0 0 0 0Recapture Balance 0 0 0 0 0 0Depletion Claimed 6,211 16,211 16,211 16,211 16,211 16,211
Depreciation and Depletion
Depreciation/Year = (Mine & Mill capital)/Mine Life
Mine Life = Reserves/Annual Production= 22,500,000 Tons/(6,000 T/D * 250 D/Y) = 15 years
Depreciation/Year ($1,000) = $87,000,000/15 Yr/1,000 = $5,800/Year
Depletion ($1,000):
Statutory % * Revenue or 50% Net after Depreciation, Select Smaller
zinc Depletion Rate = 22%
22% * $73,684 = $16,211 <=== Select SmallerOR
50% * $33,384 = $16,692
Production PeriodYear 7 8 9 10 11 12-21Revenues 73,684 73,684 73,684 73,684 73,684 73,684Operating Costs (34,500) (34,500) (34,500) (34,500) (34,500) (34,500)Net Before D & D 39,184 39,184 39,184 39,184 39,184 39,184Depreciation (5,800) (5,800) (5,800) (5,800) (5,800) (5,800)Net After Depr. 33,384 33,384 33,384 33,384 33,384 33,384Depletion (6,211) (16,211) (16,211) (16,211) (16,211) (16,211)Taxable Income 27,173 17,173 17,173 17,173 17,173 17,173Tax @ 40% (10,869) (6,869) (6,869) (6,869) (6,869) (6,869)Net After Tax 16,304 10,304 10,304 10,304 10,304 10,304Depreciation 5,800 5,800 5,800 5,800 5,800 5,800Depletion 6,211 16,211 16,211 16,211 16,211 16,211Cash Flow 28,315 32,315 32,315 32,315 32,315 32,315Working Capital (9,300) 0 0 0 0 0Net Cash Flow 19,015 32,315 32,315 32,315 32,315 32,315
Depletion Calculation: 7 8 9 10 11 12-21Initial Recapture 10,00022% Revenue 16,211 16,211 16,211 16,211 16,211 16,21150% Net After Depr. 16,692 16,692 16,692 16,692 16,692 16,692Depletion Earned 16,211 16,211 16,211 16,211 16,211 16,211Depletion Recaptured 10,000 0 0 0 0 0Recapture Balance 0 0 0 0 0 0Depletion Claimed 6,211 16,211 16,211 16,211 16,211 16,211
Post-Production PeriodYear 22Working Capital 11,900After-Tax Reclam. -8,000Net Cash Flow 3,900
DCF-ROR or Internal Rate of ReturnPresent Value Present Value Present Value
Year (j) Net CF 1/(1+.20)^j CF @ 20% 1/(1+.25)^j CF @ 25% 0.21509 CF @ 21.509%1 (1,200) 0.833 (1,000) 0.800 (960) 0.823 (988)2 (2,400) 0.694 (1,667) 0.640 (1,536) 0.677 (1,626)3 (2,400) 0.579 (1,389) 0.512 (1,229) 0.557 (1,338)4 (17,400) 0.482 (8,391) 0.410 (7,127) 0.459 (7,982)5 (40,800) 0.402 (16,397) 0.328 (13,369) 0.378 (15,403)6 (43,400) 0.335 (14,535) 0.262 (11,377) 0.311 (13,485)7 19,015 0.279 5,307 0.210 3,988 0.256 4,8628 32,315 0.233 7,515 0.168 5,422 0.210 6,8009 32,315 0.194 6,263 0.134 4,337 0.173 5,597
10 32,315 0.162 5,219 0.107 3,470 0.143 4,60611 32,315 0.135 4,349 0.086 2,776 0.117 3,79112 32,315 0.112 3,624 0.069 2,221 0.097 3,12013 32,315 0.093 3,020 0.055 1,777 0.079 2,56714 32,315 0.078 2,517 0.044 1,421 0.065 2,11315 32,315 0.065 2,097 0.035 1,137 0.054 1,73916 32,315 0.054 1,748 0.028 910 0.044 1,43117 32,315 0.045 1,457 0.023 728 0.036 1,17818 32,315 0.038 1,214 0.018 582 0.030 96919 32,315 0.031 1,011 0.014 466 0.025 79820 32,315 0.026 843 0.012 373 0.020 65721 32,315 0.022 702 0.009 298 0.017 54022 3,900 0.018 71 0.007 29 0.014 54
367,726 3,580 (5,666) 0
By Linear Interpolation
DCF-ROR = 20% + 3580/(3580+5666)*(25-20)% = 21.9%
Exact Solution 21.5090%
Present Value of Cash Flows at 21.5% Discount Rate
(20,000)
(15,000)
(10,000)
(5,000)
0
5,000
10,000
1 3 5 7 9 11 13 15 17 19 21
Year
$ *1
000
Projected Cash Flows For Bedded Zinc Deposit
-50000-40000-30000-20000-10000
010000200003000040000
1 3 5 7 9 11 13 15 17 19 21
Year
$ *1
000
Definitions of troy ounce on the Web:
ounce: a unit of apothecary weight equal to 480 grains or one twelfth of a pound
he traditional unit of weight for gold is the troy ounce, named, it is thought, after a weight used at the annual fair at Troyes in France in the Middle Ages.
Although the metric system is used increasingly in mining and the gold business, the troy ounce remains the basic unit in which the price of 995 gold is quoted.
One troy ounce = 31.1034807 grams, 32.15 troy ounces = 1 kilogram, 1 troy ounce = 480 grains,
Mine Production Scheduling Mine Production Scheduling OptimizationOptimization
-- The State of Art The State of Art --
K. Dagdelen
ProfessorMining Engineering Department
Colorado School of MinesGolden, Colorado 80401
AP
CO
M 2
005
OPEN PIT OPTIMIZATIONOPEN PIT OPTIMIZATION
For Each Block in The For Each Block in The ModelModel
ll If a given block of If a given block of material should be material should be mined?mined?
ll When it Should be When it Should be mined?mined?
ll Once it is mined what to Once it is mined what to do with the block of do with the block of MaterialMaterial
AP
CO
M 2
005
OPEN PIT OPTIMIZATIONOPEN PIT OPTIMIZATIONStart
Physical Capacities
Ultimate pit
Design Of Cuts
Cutoff Grade
Steps of Traditional Planning by Circular Analysis
ExtractionScheduling
ProductionCosts
AP
CO
M 2
005
OPEN PIT OPTIMIZATIONOPEN PIT OPTIMIZATIONULTIMATE PIT LIMITS
AP
CO
M 2
005
OPEN PIT OPTIMIZATIONOPEN PIT OPTIMIZATIONULTIMATE PIT LIMITS
l Identifies What blocks should be mined and which ones should be left in the ground.
l Defines the lateral and vertical extent to which a given deposit can economically be mined to
l 3-D Breakeven Analysis l Moving Cone algorithm gives sub-optimum resultsl Lerchs and Grossmann algorithm gives true
breakeven pit that maximizes the undiscounted profits
AP
CO
M 2
005
OPEN PIT OPTIMIZATIONOPEN PIT OPTIMIZATIONULTIMATE PIT LIMITS
The Lerchs and Grossmann Algorithml Only finds the maximum profit pit boundary l No time value of money is consideredl The pit that maximizes discounted profits (NPV) by
taking into account time value of money is much smaller than the ultimate pit found by this technique
AP
CO
M 2
005
OPEN PIT OPTIMIZATIONOPEN PIT OPTIMIZATIONULTIMATE PIT LIMITS
l Common practice is to apply Lerchs and Grossmann’s algorithm to the economic block model that is generated to discounted block values
l Economic block model is generated by discounting block values based on a rough initial production schedule
AP
CO
M 2
005
OPEN PIT OPTIMIZATIONOPEN PIT OPTIMIZATIONULTIMATE PIT LIMITS
l If the schedule is not defined by identifying effect of waste stripping on the overall cash flows then the ultimate pit limit may not be correct
l NPV analysis on the last incremental pushbacksalways results in elimination of non-contributing incremental pits
AP
CO
M 2
005
OPEN PIT OPTIMIZATIONOPEN PIT OPTIMIZATIONStart
Physical Capacities
Ultimate pit
Design Of Cuts
Cutoff Grade
Steps of Traditional Planning by Circular Analysis
ExtractionScheduling
ProductionCosts
AP
CO
M 2
005
OPEN PIT OPTIMIZATIONOPEN PIT OPTIMIZATIONDESIGN OF PUSHBACKS
Economic block models are developed by varying eitherl Metal Price l Cutoff Grade l Minimum profits required per ton of orel Some ratio in block evaluation equationl As these variables change the pit outline also changesl Each outline is then used as pushbacks
AP
CO
M 2
005
OPEN PIT OPTIMIZATIONOPEN PIT OPTIMIZATIONDESIGN OF PUSHBACKS
PHASE 2
PHASE 1
PHASE 3
AP
CO
M 2
005
OPEN PIT OPTIMIZATIONOPEN PIT OPTIMIZATIONDESIGN OF PUSHBACKS
l The concept is based on mining “next best ore” without considering impact of stripping to be done ahead of time
l First incremental pit contains the ore that has the highest average overall value per ton. The subsequent pits have lower and lower average value per ton of ore
l The push back designs do not take into account effect of timing of waste stripping on the NPV
l Blending requirements can not be taken into account
AP
CO
M 2
005
OPEN PIT OPTIMIZATIONOPEN PIT OPTIMIZATIONDESIGN OF PUSHBACKS
AP
CO
M 2
005
OPEN PIT OPTIMIZATIONOPEN PIT OPTIMIZATIONStart
Physical Capacities
Ultimate pit
Design Of Cuts
Cutoff Grade
Steps of Traditional Planning by Circular Analysis
ExtractionScheduling
ProductionCosts
AP
CO
M 2
005
OPEN PIT OPTIMIZATIONOPEN PIT OPTIMIZATIONCUTOFF GRADES
2005
SM
E A
nnua
l Mee
ting
Cutoff GradesCutoff Gradesl A cutoff grade is the grade that is used to
differentiate between ore and waste in a given mining environment. Although the definition of cutoff grade is straight forward, the determination of it is not.
l To determine if a block of material should be milled or taken to the waste dump, breakeven mill cutoff may be used.
Milling cutoff grade
2005
SM
E A
nnua
l Mee
ting
McLaughlin Gold MineMcLaughlin Gold MineCalifornia, USACalifornia, USA
Waste dumps
Autoclave Mill
Pit
Waste Ore and waste discrimination
Cutoff grade
Stockpiles
Ore
2005
SM
E A
nnua
l Mee
ting
Round Mountain Gold MineRound Mountain Gold Mine
Waste dumps
Leach Pads
Stockpiles
Low grade stockpiles
Crusher
WasteOxide
Sulfide
CIP Mill
Ore
Breakeven Mill Cutoff GradeBreakeven Mill Cutoff Grade
l The lowest economic grade where mining, milling, and administration cost are equal to revenues obtained from the metal produced.
Breakeven cutoff grade = Milling Cost
(Price – Refining Cost - Sales Cost) * Recovery
l Traditionally, this breakeven cutoff grade has been widely used in a production scheduling.
2005
SM
E A
nnua
l Mee
ting
McLaughlin Mine Case StudyMcLaughlin Mine Case Study20
05 S
ME
Ann
ual M
eetin
g
l The economic and operational parameters:
Price (P) 600 $/oz
Sales Cost (s) 5 $/oz
Processing Cost (c) 19 $/ton ore
Recovery (y) 0.9
Mining Cost (m) 1.2 $/ton
Fixed Cost (fa) 8.35M $/year
Mining Capacity (M) Unlimited
Processing Capacity (C) 1.05M tons
Discount Rate (d) 15 %
Production Scheduling By Production Scheduling By Breakeven Cutoff Grade (Case1)Breakeven Cutoff Grade (Case1)
2005
SM
E A
nnua
l Mee
ting
l If one uses breakeven cutoff grade for a production scheduling:
$19/ton
($600/oz - $5.0/oz) * 0.90Breakeven cutoff grade =
= 0.035 oz/ton
l All the materials above 0.035oz/ton goes to process, and below goes to waste dump.
McLaughlin Case StudyMcLaughlin Case Study20
05 S
ME
Ann
ual M
eetin
g
l Consider a case study from McLaughlin Mine in California where an epithermal gold deposit was mined by an open pit.
l The grade distribution within the ultimate pit limit is:
Grade CategoryFrom To midpoint Ktons
0 0.02 0.0100 70,0000.02 0.025 0.0225 7,257
0.025 0.03 0.0275 6,3190.03 0.035 0.0325 5,591
0.035 0.04 0.0375 4,5980.04 0.045 0.0425 4,277
0.045 0.05 0.0475 3,4650.05 0.055 0.0525 2,428
0.055 0.06 0.0575 2,3070.06 0.065 0.0625 1,747
0.065 0.07 0.0675 1,6400.07 0.075 0.0725 1,485
0.075 0.08 0.0775 1,2270.08 0.1 0.0900 3,5980.1 0.358 0.2290 9,576
125,515
Ton
s
Grade intervals36,346 [email protected]/ton
89,167 tons
SR=2.45
COG
Yearly Mining and Milling RatesYearly Mining and Milling Rates20
05 S
ME
Ann
ual M
eetin
g
l Assuming the deposit is homogeneously distributed, yearly mining rate is given as follows:
l Yearly ore tons: 1.05Mtons (Limited by process capacity)l Yearly ounces recovered: 1.05Mtons x 0.102 oz/ton x 0.9
= 96.3kozl Yearly waste tons: 1.05Mtons x 2.45 (SR) = 2.58Mtonsl Yearly mining rates: 1.05M + 2.58M = 3.62Mtons
Yearly Schedules by Breakeven Yearly Schedules by Breakeven Cutoff Grade (Cont.)Cutoff Grade (Cont.)
2005
SM
E A
nnua
l Mee
ting
l Mining the deposit with breakeven cutoff grade of 0.035oz/ton at 1.05M tons process capacity:
Avg Qm Qc Qr Profits
Year (i) COG Ore Grade (Mtons) (Mtons) (ktons) ($M)
1 0.035 0.102 3.6 1.05 96.3 33.0
2 0.035 0.102 3.6 1.05 96.3 33.0
3 0.035 0.102 3.6 1.05 96.3 33.0
4 0.035 0.102 3.6 1.05 96.3 33.0
5 0.035 0.102 3.6 1.05 96.3 33.0
6 0.035 0.102 3.6 1.05 96.3 33.0
7 0.035 0.102 3.6 1.05 96.3 33.0
8 0.035 0.102 3.6 1.05 96.3 33.0
9 0.035 0.102 3.6 1.05 96.3 33.0
10 0.035 0.102 3.6 1.05 96.3 33.0
11 to 34 0.035 0.102 3.6 1.05 96.3 33.0
35 0.035 0.102 3.4 1.00 91.7 31.4
Total 125.8 36.7 3,365.9 1,154.2
(NPV@15%)
$218.5
Shortcomings of the Traditional Shortcomings of the Traditional Cutoff GradesCutoff Grades
l They are established to maximizing the undiscounted profits from a given mining operation.
l They are constant unless the commodity price and the costs change during the life of the mine.
l They do not consider grade distribution of the deposit.
2005
SM
E A
nnua
l Mee
ting
AP
CO
M 2
005
OPEN PIT OPTIMIZATIONOPEN PIT OPTIMIZATIONCUTOFF GRADES
l Many open pit mines are still designed and operated using cutoff grades based on breakeven economic analysis which maximizes undiscounted profits
l The cutoff grades should be set to much higher levels than the breakeven cutoff during the initial years of the operation
AP
CO
M 2
005
OPEN PIT OPTIMIZATIONOPEN PIT OPTIMIZATIONCUTOFF GRADES
l The heuristic algorithm to define optimum declining cutoff grades that maximize the NPV of a given project was developed by Kenneth Lane in 1965
l Applying this method to a given project results in higher NPV for a project specially if capacities are not in harmony with the grade distribution of the deposit
Declining Cutoff GradeDeclining Cutoff Grade20
05 S
ME
Ann
ual M
eetin
g
l Traditional cutoff grade (constant cutoff grade) does not maximize the NPV.
l Many approaches have been suggested to improve NPV of the project.
l K. F Lane in 1964 suggested an heuristic algorithm to obtain cutoff grades higher than breakeven grades during the early years that maximize the Net Present Value (NPV) of a project
Optimum Cutoff Grades by Lane’s Optimum Cutoff Grades by Lane’s Algorithm Algorithm
2005
SM
E A
nnua
l Mee
ting
l Lane’s approach considers the mining operation to be constrained by the capacities of mine, mill, and refinery.
l The cutoff grades are optimized by considering the grade distribution of the deposit in providing highest quality of ore to the mill subject to three capacity constraints.
l This approach has been successfully used in the mining industry for many years.
Optimum Cutoff Grades by OptiPit Optimum Cutoff Grades by OptiPit ®®20
05 S
ME
Ann
ual M
eetin
g
l Linear Programming (LP) based algorithm and software is being developed to optimize cutoff grades under complex mining and process constraints.
l Mathematical programming approach is very powerful and provides complete flexibility in modeling complex operating environments.
l This approach will be described and demonstrated using four case studies coming from gold mines in Western United States.
Round Mountain Gold MineRound Mountain Gold Mine
Waste dumps
Leach Pads
Stockpiles
Low grade stockpiles
Crusher
WasteOxide
Sulfide
CIP Mill
Ore
AP
CO
M 2
005
COMPLICATED PROCESSES AND COMPLICATED PROCESSES AND CAPACITIESCAPACITIES
Dump
ROM Leach
Cr Leach
Cr
Flot.
10M tons/yr
limited by crusher
5M tons/yr
1.05M tons/yr
2M tons/yr
Proc 1
Proc 2
Proc 3
Proc 4
Tailings
80%
20%
Autoclave
Mine
Phase1
Phase2
Mining Capacity: 12M tons/yr
Refining Capacity: 350 koz/yr
Stockpile available
AP
CO
M 2
005
AP
CO
M 2
005
OPEN PIT OPTIMIZATIONOPEN PIT OPTIMIZATIONCUTOFF GRADES
l Linear Programming (LP) based algorithm and software is being developed to optimize cutoff grades under complex mining and process constraints.
l Mathematical programming approach is very powerful and provides complete flexibility in modeling complex operating environments.
CUTOFF GRADE FORMULATION CUTOFF GRADE FORMULATION
McLaughlin mine
Mine
Dump MillCutoff Grade
Index i
Index g
Index d
Index t: YearsT
ons
Grade intervals
igdtX
l Decision variables:
AP
CO
M 2
005
AP
CO
M 2
005
OPEN PIT OPTIMIZATIONOPEN PIT OPTIMIZATIONFUTURE
l NO scheduler in the market that incorporates shortcomings discussed
l There are efforts to develop methods that will overcome these shortcomings
l The advancements in hardware and software technology in recent years is providing an unique opportunity to solve this problem by way of “Linear –Integer Programming” techniques
l In the mean time, the use of computer programs that optimizes sub-problems will give you higher NPV for a given project if not the optimum.
1
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Push Backs or Phases
• Defines how the pit will evolve with time.
• Defines ore tons and its quality for different time periods.
• Defines waste tons for removal schedules.
• Defines the cash flows and overall project economics.
2
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Push Backs or Phases Example
Phase 1 Phase 2
3
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Push Backs or Phases Example (Cont.)
Phase 3 Phase 4
4
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Push Backs or Phases Example (Cont.)
Cross Section
5
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Cutoff Grade
• Minimum grade of the material for processing.
• Normally used to discriminate between ore and waste within a given orebody.
• Cutoff grade is Dynamic.
Read “Cutoff Grade Optimization” by Dr. Dagdelen
6
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Breakeven Cutoff Grade
• The lowest economic grade where mining, milling, and administration cost are equal to revenues obtained from the metal produced.
• Cutoff grades in the pit are normally much higher than the breakeven cutoff grade.
• Cutoff grades decline as the mine matures, and approaches the breakeven cutoff.
7
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Hypothetical Case Study
• Consider a hypothetical case study where an epithermal gold deposit will be mined by an open pit.
• The grade distribution within the ultimate pit limit is:Grade Category
From To midpoint Ktons0 0.02 0.0100 70,000
0.02 0.025 0.0225 7,2570.025 0.03 0.0275 6,3190.03 0.035 0.0325 5,591
0.035 0.04 0.0375 4,5980.04 0.045 0.0425 4,277
0.045 0.05 0.0475 3,4650.05 0.055 0.0525 2,428
0.055 0.06 0.0575 2,3070.06 0.065 0.0625 1,747
0.065 0.07 0.0675 1,6400.07 0.075 0.0725 1,485
0.075 0.08 0.0775 1,2270.08 0.1 0.0900 3,5980.1 0.358 0.2290 9,576
125,515
8
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Mine Design Parameters
• Capacities and Costs are:
Price (P) 600 $/oz
Sales Cost (s) 5.00 $/oz
Processing Cost (c) 19.0 $/ton ore
Recovery (y) 90 %
Mining Cost (m) 1.2 $/ton
Fixed Costs (fa) 8.35 $M/yr
Mining Capacity (M) Unlimited
Milling Capacity (C) 1.05 M
Capital Costs (CC) 105 $M
Discount Rate (d) 15 %
9
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Traditional Cutoff Grades
• Traditionally, a cutoff grade is used to determine if a block of material should be mined or not.
• And, another cutoff is used to determine whether or not it should be milled or taken to the waste dump.
Ultimate pit cutoff grade
Milling cutoff grade
10
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Ultimate Pit Cutoff Grade
• Ultimate pit cutoff grade is defined as the breakeven grade that equates cost of mining, milling, refining and marketingto the value of the block in terms of recovering metal and the selling price.
Ultimate pit cutoff grade = Milling Cost + Mining Cost
(Price – Refining Cost - Sales Cost) * Recovery
$19/ton + $1.2/ton
($600/oz - $5.0/oz) * 0.90Ultimate pit cutoff grade =
= 0.038 oz/ton
11
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Milling Cutoff Grade
• Milling cutoff grade is defined as the breakeven grade that equates cost of milling, refining and marketing to the value of the block in terms of recovering metal and the selling price.
Milling cutoff grade = Milling Cost
(Price – Refining Cost - Sales Cost) * Recovery
$19/ton
($600/oz - $5.0/oz) * 0.90Milling cutoff grade =
= 0.035 oz/ton
12
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Milling Cutoff Grade (Cont.)
• In the milling cutoff grade, no mining cost is included since this cutoff is basically applied to those blocks that are already selected for mining.
• The depreciation costs, general and administrative costs (G & A) and the opportunity costs are not included in the cutoff grade.
• The basic assumption is that all of these costs including fixed costs defined as G & A will be paid by the material whose grade is much higher than the established cutoff grades.
13
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Summary of the Traditional Cutoff Grades
• The ultimate pit limit cutoff is used to ensure that no material (unless they are in the way of other high grade blocks) is taken out of the ground unless all of the direct costs associated with gaining the metal can be recovered. (This assurance is automatically built into the ultimate pit limit determination algorithms like Learchs – Grossmann and Moving Cone)
• The milling cutoff is used to ensure that any material that provides positive contribution beyond the direct milling, refining and marketing costs will be milled.
14
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Shortcomings of the Traditional Cutoff Grades
• They are established to satisfy the objective of maximizing the undiscounted profits from given mining operation.
• They are constant unless the commodity price and the costs change during the life of the mine.
• They do not consider grade distribution of the deposit.
15
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Yearly Tons and Grades Schedules by Constant Cutoff Grades
• Define:Qm: Amount of total material mined in a given year (Mtons)
Qc: The ore tonnage processed by the mill (Mtons)
Qr: The recovered gold (koz)
• The annual cash flows:
Profits ($M) = (P - s) * Qr – Qc * c – Qm * m
16
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Yearly Tons and Grade Schedules by Constant Cutoff Grades
• Mining the deposit with traditional milling cutoff grade of 0.035oz/ton at 1.05M tons milling capacity (Table3):
Avg Qm Qc Qr Profits
Year (i) COG Ore Grade (Mtons) (Mtons) (ktons) ($M)
1 0.035 0.102 3.6 1.05 96.3 33.0
2 0.035 0.102 3.6 1.05 96.3 33.0
3 0.035 0.102 3.6 1.05 96.3 33.0
4 0.035 0.102 3.6 1.05 96.3 33.0
5 0.035 0.102 3.6 1.05 96.3 33.0
6 0.035 0.102 3.6 1.05 96.3 33.0
7 0.035 0.102 3.6 1.05 96.3 33.0
8 0.035 0.102 3.6 1.05 96.3 33.0
9 0.035 0.102 3.6 1.05 96.3 33.0
10 0.035 0.102 3.6 1.05 96.3 33.0
11 to 34 0.035 0.102 3.6 1.05 96.3 33.0
35 0.035 0.102 3.4 1.00 91.7 31.4
Total 125.8 36.7 3,365.9 1,154.2
(NPV@15%)
$218.5
17
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Yearly Tons and Grades Schedules by Constant Cutoff Grades (NPV Calculation)
• NPV of the project:
NPV = 33.0(1 + 0.15)1
33.0(1 + 0.15)2
+ 33.0(1 + 0.15)3
+
33.0(1 + 0.15)4
+ 33.0(1 + 0.15)5
+ …
33.0(1 + 0.15)34
+
= $218.5M
31.4(1 + 0.15)35
+
18
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Summary of Constant Cutoff Grade
• Total 28.44M tons is mined (Avg. grade 0.102 oz/ton)
• Overall stripping ratio: 1: 2.42
• Mine life: 35 years
• Undiscounted profits: $1154.2M
• NPV: $218.5M
19
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Declining Cutoff Grade
• Traditional cutoff grade (constant cutoff grade) does not maximize the NPV.
• Many approaches have been suggested such that NPV is improved.
• Using cutoff grade higher than breakeven grades during the early years for a faster recovery of capital investments and using breakeven grades during the later stages has been practiced in the industry.
20
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Heuristic Cutoff Grade
• The traditional cutoff grade is modified so that they include depreciation, fixed costs and minimum profit per ton required for a period of time to obtain a much higher cutoff grade during the early years.
• After the end of the initial period, minimum profit requirement is removed from the equation to lower the cutoff grades further until the plant is paid off.
• At that point, the depreciation charges are also removed.
21
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Concept of Heuristic Cutoff Grade
• The concept is demonstrated pictorially as follows:
Idealized cross section of a series of pits for various cutoff grades
22
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Capital Cost
• Assume:
Capital Cost: $105M (Depreciated during the first 10 years)
• Depreciation cost per year
$105M / 10 yrs = $10.5M / yr
• Depreciation cost per ton
$10.5M / 1.05M tons = $10 / ton of ore
23
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Minimum Profit
• Assume:
Minimum profit of $3.0 per ton will be imposed to increase the cash flows further during the first five years
24
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Heuristic Cutoff Grade Calculation
• The milling cutoff grades will be:
g milling = Milling Cost + Depreciation + Minimum Prof.
(Price – Refining Cost - Sales Cost) * Recovery
$19/ton + $10/ton + $3/ton
($600/oz - $5.0/oz) * 0.90Ultimate pit cutoff grade =
= 0.060 oz/ton
Yr 1 to 5
25
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Heuristic Cutoff Grade Calculation (Cont.)
g milling = Milling Cost + Depreciation
(Price – Refining Cost - Sales Cost) * Recovery
$19/ton + $10/ton
($600/oz - $5.0/oz) * 0.90Ultimate pit cutoff grade =
= 0.054 oz/ton
Yr 6 to 10
26
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Heuristic Cutoff Grade Calculation (Cont.)
g milling = Milling Cost
(Price – Refining Cost - Sales Cost) * Recovery
$19/ton
($600/oz - $5.0/oz) * 0.90Ultimate pit cutoff grade =
= 0.035 oz/ton
Yr 11 to Depletion
27
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Yearly Tons and Grade Schedules
• The year by year tons and grade schedule obtained modified cutoff grade policy (Table4):
Avg Qm Qc Qr Profits
Year (i) COG Ore Grade (Mtons) (Mtons) (ktons) ($M)
1 0.060 0.153 6.9 1.05 144.6 57.8
2 0.060 0.153 6.9 1.05 144.6 57.8
3 0.060 0.153 6.9 1.05 144.6 57.8
4 0.060 0.153 6.9 1.05 144.6 57.8
5 0.060 0.153 6.9 1.05 144.6 57.8
6 0.054 0.141 6.0 1.05 132.8 51.9
7 0.054 0.141 6.0 1.05 132.8 51.9
8 0.054 0.141 6.0 1.05 132.8 51.9
9 0.054 0.141 6.0 1.05 132.8 51.9
10 0.054 0.141 6.0 1.05 132.8 51.9
11 to 27 0.035 0.102 3.6 1.05 96.3 33.0
28 0.035 0.102 0.3 0.09 8.1 2.8
Total 125.8 28.44 3,032.1 1,112.7
(NPV@15%)
$355.7
28
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Summary of Modified Cutoff Grade
• Again, a total 28.44M tons is mined (Avg. grade 0.106 oz/ton)
• Overall stripping ratio: 1: 3.88
• Mine life: 25 years
• Undiscounted profits: $1112.7M (3.6% reduction from Table3)
• NPV: $355.7M (63% increase from Table3)
29
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Heuristic Cutoff Grade (Including G & A)
• Assume:
Fixed Costs per year: $8.35M / year
Fixed Costs per ton: ($8.35M/year) / (1.05Mtons/year)
= $7.95 / ton
• In the previous calculations, the G & A costs were not included in the cutoff grade and profit calculations.
30
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Heuristic Cutoff Grade Calculation (With G & A)
• The milling cutoff grades will be:
g milling = Milling Cost + Depreciation + Minimum Prof. + Fixed cost
(Price – Refining Cost - Sales Cost) * Recovery
$19/ton + $10/ton + $3/ton + $7.95/ton
($600/oz - $5.0/oz) * 0.90Ultimate pit cutoff grade =
= 0.075 oz/ton
Yr 1 to 5
31
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Heuristic Cutoff Grade Calculation (With G & A) (Cont.)
g milling = Milling Cost + Depreciation + Fixed cost
(Price – Refining Cost - Sales Cost) * Recovery
$19/ton + $10/ton + $7.95/ton
($600/oz - $5.0/oz) * 0.90Ultimate pit cutoff grade =
= 0.069 oz/ton
Yr 6 to 10
32
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Heuristic Cutoff Grade Calculation (With G & A) (Cont.)
g milling = Milling Cost + Fixed cost
(Price – Refining Cost - Sales Cost) * Recovery
$19/ton + $7.95/ton
($600/oz - $5.0/oz) * 0.90Ultimate pit cutoff grade =
= 0.050 oz/ton
Yr 11 to Depletion
33
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Yearly Tons and Grades Schedules
• The year by year tons and grade schedule obtained modified cutoff grade policy that includes fixed costs (Table5):
Avg Qm Qc Qr Profits
Year (i) COG Ore Grade (Mtons) (Mtons) (ktons) ($M)
1 0.075 0.182 9.2 1.05 171.6 62.8
2 0.075 0.182 9.2 1.05 171.6 62.8
3 0.075 0.182 9.2 1.05 171.6 62.8
4 0.075 0.182 9.2 1.05 171.6 62.8
5 0.075 0.182 9.2 1.05 171.6 62.8
6 0.069 0.169 8.2 1.05 160.0 57.1
7 0.069 0.169 8.2 1.05 160.0 57.1
8 0.069 0.169 8.2 1.05 160.0 57.1
9 0.069 0.169 8.2 1.05 160.0 57.1
10 0.069 0.169 8.2 1.05 160.0 57.1
11 to 17 0.050 0.132 5.4 1.05 124.8 39.5
18 0.050 0.132 1.3 0.26 30.5 9.6
Total 125.8 18.11 2,562.5 885.6
(NPV@15%)
$357.1
34
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Summary of Modified Cutoff Grade with Fixed Cost Included
• The policy of declining cutoff grades calculated with depreciation, minimum profit, and the G & A cost further improved the NPV of the deposit by 1% ($355.7M vs. $357.5M)
• Overall undiscounted profits were adversely reduced by 20% ($1112.7M vs. $885.6M)
35
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Lane’s Approach
• Declining cutoff grades throughout the mine life gives higher NPV.
• The question is, “How should the cutoff grades be determined to obtain the highest NPV?”
• K. F. Lane discussed the theoretical background, a general formulation, and a solution algorithm.
Read “Choosing the Optimum Cutoff Grade” by K.F. Lane
36
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Lane’s Approach (Cont.)
• Lane showed that cutoff grade calculations that maximize NPV have to include the fixed costs associated with not receiving the future cash flow quicker due to the cutoff grade decision taken now.
• Underlying philosophy in inclusion of the opportunity cost is that every deposit has a given NPV associated with it at a given point in time and that every ton of material processed by the mill during a given year should pay for the cost of not receiving the future cash flows by one year sooner.
37
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Cutoff Grade Equation for Lane’s Approach
• The cutoff grade equation that maximizes the NPV of the deposit constrained by the mill capacity is:
g milling (i) = c + f + Fi
(P - s) * y
Where i = 1, …, N (mine life), gmilling(i) is the cutoff grade to be used in Year i.
38
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Cutoff Grade Equation for Lane’s Approach (Cont.)
• Fi is the opportunity cost per ton of ore in Year i and it is defined as:
Fi = d * NPVi / C
• f is defined as:f = fa / C
Where d is the discount rate; NPVi is the NPV of the future cash flows of the years (i) to the endof mine life;fa is the annual fixed costs
39
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Yearly Tons and Grades Schedules
• The year by year tons and grade schedule resulted from Lane’s approach (Table6):
Avg Qm Qc Qr Profits NPV
Year (i) COG Ore Grade (Mtons) (Mtons) (ktons) ($M) ($M)
1 0.161 0.259 18.0 1.05 245.2 95.9 413.8
2 0.152 0.255 17.2 1.05 241.0 94.4 380.0
3 0.142 0.25 16.5 1.05 236.4 92.6 342.6
4 0.131 0.245 15.7 1.05 231.3 90.5 301.4
5 0.120 0.239 14.9 1.05 225.7 88.1 256.1
6 0.107 0.232 14.1 1.05 219.6 85.4 206.4
7 0.092 0.213 12.1 1.05 200.9 76.7 152.0
8 0.079 0.188 9.8 1.05 177.9 65.9 98.1
9 0.065 0.163 7.6 1.05 153.6 53.9 46.9
Total 125.8 9.45 1,931.4 743.4
(NPV@15%)
$413.8
40
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Steps to Obtain Table 6 (1st Iteration)
Avg Waste Ore SR Qm Qc Qr Profits NPV Year (i) NPVi Cog Ore Grade (Mtons) (Mtons) (Mtons) (Mtons) (ktons) ($M) ($M)
1 0 0.050 0.133 101.5 24.0 4.2 5.5 1.05 125.7 39.9 $255.02 0 0.050 0.133 97.1 23.0 4.2 5.5 1.05 125.7 39.9 $253.43 0 0.050 0.133 92.6 21.9 4.2 5.5 1.05 125.7 39.9 $251.54 0 0.050 0.133 88.2 20.9 4.2 5.5 1.05 125.7 39.9 $249.35 0 0.050 0.133 83.7 19.8 4.2 5.5 1.05 125.7 39.9 $246.86 0 0.050 0.133 79.3 18.8 4.2 5.5 1.05 125.7 39.9 $243.97 0 0.050 0.133 74.9 17.7 4.2 5.5 1.05 125.7 39.9 $240.6…21 0 0.050 0.133 12.7 3.0 4.2 5.5 1.05 125.7 39.9 $86.622 0 0.050 0.133 8.3 2.0 4.2 5.5 1.05 125.7 39.9 $59.723 0 0.050 0.133 3.8 0.9 4.2 5.1 0.91 108.9 33.1 $28.7
Total 125.8 24.0 2,874.0 910.8 (NPV@15%)
$255.0
Year 1: Cog= 19+8.35/1.05+(0*0.15)/1.05 = 0.050(600-5)*0.9
Year 2: Cog= 19+8.35/1.05+(0*0.15)/1.05 = 0.050(600-5)*0.9
41
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Steps to Obtain Table 6 (2nd Iteration)
2nd iterationAvg Waste Ore SR Qm Qc Qr Profits NPV
Year (i) NPVi Cog Ore Grade (Mtons) (Mtons) (Mtons) (Mtons) (ktons) ($M) ($M)1 $255.0 0.118 0.238 116.6 8.9 13.1 14.8 1.05 224.9 87.8 $399.52 $253.4 0.118 0.238 102.9 7.9 13.1 14.8 1.05 224.9 87.8 $371.73 $251.5 0.117 0.236 89.1 6.8 13.1 14.8 1.05 223.0 86.6 $339.74 $249.3 0.117 0.236 74.5 5.7 13.1 14.8 1.05 223.0 86.7 $304.05 $246.8 0.116 0.236 61.6 4.8 12.9 14.6 1.05 223.0 86.8 $262.96 $243.9 0.115 0.236 48.2 3.8 12.9 14.5 1.05 223.0 86.9 $215.57 $240.6 0.115 0.236 34.8 2.7 12.9 14.6 1.05 223.0 86.9 $160.98 $236.8 0.114 0.235 20.0 1.6 12.9 14.6 1.05 222.1 86.3 $98.29 $232.4 0.112 0.234 7.0 0.5 15.6 7.5 0.45 94.8 30.5 $26.6
Total 125.0 8.9 1,881.8 726.4 (NPV@15%)
$399.5
Year 1: Cog= 19+8.35/1.05+(255*0.15)/1.05 = 0.118(600-5)*0.9
Year 2: Cog= 19+8.35/1.05+(253.4*0.15)/1.05 = 0.118(600-5)*0.9
42
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Steps to Obtain Table 6 (3rd Iteration)
3rd iterationAvg Waste Ore SR Qm Qc Qr Profits NPV
Year (i) NPVi Cog Ore Grade (Mtons) (Mtons) (Mtons) (Mtons) (ktons) ($M) ($M)1 $399.5 0.157 0.257 118.1 7.4 15.9 17.7 1.05 242.9 94.9 $411.82 $371.7 0.149 0.253 101.2 6.6 15.4 17.3 1.05 239.1 93.2 $378.73 $339.7 0.141 0.250 84.8 5.9 14.4 16.2 1.05 236.3 92.8 $342.24 $304.0 0.131 0.245 69.0 4.9 14.1 15.8 1.05 231.5 90.5 $300.75 $262.9 0.120 0.238 54.7 4.2 13.2 14.9 1.05 224.9 87.7 $255.46 $215.5 0.108 0.232 40.7 3.3 12.3 14.0 1.05 219.2 85.3 $206.07 $160.9 0.093 0.215 27.5 2.5 11.1 11.7 1.05 203.2 78.6 $151.68 $98.2 0.077 0.189 15.3 1.7 9.0 9.5 1.05 178.6 66.6 $95.79 $26.6 0.057 0.158 7.1 0.9 8.4 8.8 1.05 149.3 50.0 $43.5
Total 125.8 9.5 1,925.0 739.7 (NPV@15%)
$411.81
Year 1: Cog= 19+8.35/1.05+(399.5*0.15)/1.05 = 0.157(600-5)*0.9
Year 2: Cog= 19+8.35/1.05+(371.7*0.15)/1.05 = 0.149(600-5)*0.9
43
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Steps to Obtain Table 6 (4th Iteration)
4th iterationAvg Waste Ore SR Qm Qc Qr Profits NPV
Year (i) NPVi Cog Ore Grade (Mtons) (Mtons) (Mtons) (Mtons) (ktons) ($M) ($M)1 $411.8 0.160 0.259 117.0 7.8 15.0 17.8 1.05 244.8 96.0 $412.32 $378.7 0.151 0.255 101.4 6.7 15.1 17.0 1.05 241.0 94.7 $378.23 $342.2 0.142 0.250 85.2 5.9 14.4 16.2 1.05 236.3 92.8 $340.24 $300.7 0.131 0.245 70.0 5.1 13.7 15.6 1.05 231.5 90.7 $298.45 $255.4 0.118 0.238 55.9 4.2 13.3 14.6 1.05 224.9 88.0 $252.46 $206.0 0.105 0.230 41.8 3.3 12.7 13.9 1.05 217.4 84.3 $202.37 $151.6 0.091 0.213 28.0 2.7 10.4 12.0 1.05 201.3 77.1 $148.38 $95.7 0.076 0.182 16.5 2.0 8.3 10.2 1.05 172.0 61.8 $93.59 $43.5 0.062 0.162 8.0 1.2 6.7 8.5 1.05 153.1 52.6 $45.7
Total 125.8 9.5 1,922.1 738.0 (NPV@15%)
$412.30
Year 1: Cog= 19+8.35/1.05+(411.8*0.15)/1.05 = 0.160(600-5)*0.9
Year 2: Cog= 19+8.35/1.05+(378.7*0.15)/1.05 = 0.151(600-5)*0.9
44
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Table 6
Table 6Avg Waste Ore SR Qm Qc Qr Profits NPV
Year (i) NPVi Cog Ore Grade (Mtons) (Mtons) (Mtons) (Mtons) (ktons) ($M) ($M)1 $413.8 0.161 0.259 18.0 1.05 244.8 95.7 $413.82 $380.0 0.152 0.255 17.2 1.05 241.0 94.4 $380.23 $342.6 0.142 0.250 16.5 1.05 236.3 92.5 $342.84 $301.4 0.131 0.245 15.7 1.05 231.5 90.6 $301.75 $256.1 0.119 0.239 14.9 1.05 225.9 88.2 $256.36 $206.4 0.105 0.232 14.1 1.05 219.2 85.2 $206.67 $152.0 0.091 0.2131 12.1 1.05 201.4 77.0 $152.38 $98.1 0.077 0.188 9.8 1.05 177.7 65.7 $98.29 $46.9 0.063 0.163 7.6 1.05 154.0 54.3 $47.2
Total 125.8 9.5 1,931.7 743.7 (NPV@15%)
$413.82
Year 1: Cog= 19+8.35/1.05+(413.8*0.15)/1.05 = 0.161(600-5)*0.9
Year 2: Cog= 19+8.35/1.05+(380.0*0.15)/1.05 = 0.152(600-5)*0.9
45
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Summary of Lane’s Approach
• Lane’s approach gives 90% higher NPV and 35% lower undiscounted profits than constant cutoff grade (Table3).
• Total tons mined are the same.
• Tons milled is lower (36.7Mtons vs. 9.45Mtons)
• Ounces of gold recovered is lower (3.37Moz vs. 1.93Moz)
• Mine life is significantly shorter (36yrs vs. 10yrs)
1
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Cutoff Grade Optimization 2
• How to determine a cutoff grade policy where
Mining capacity, milling capacity, and refining capacity may be limited,AndMaximizing NPV of the projects
Read “An NPV Maximization Algorithm For Open PitMine Design” by Dr. Dagdelen
2
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Definition of the Problem
• The problem is to maximize the NPV subject to production constraints:Maximize ∑
=+
=N
id iiprofitNPV
1)1(
1*)(
Subject to MiQm ≤)( for i = 1,…N
CiQc ≤)( for i = 1,…N
RiQr ≤)( for i = 1,…N Where
i: Year indicator
N: Mine life in yearsQm: Amount of total metal mined in a given year (Ore + Waste)
Qc: Ore tonnage processed in a given year
Qr: Recovered metal (in tons) in a given year
M: Annual mining capacity in tonsC: Annual milling capacity in tonsR: Annual refinery capacity in tons
3
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Derivation of Opportunity Costs of Mining Low Grades
• Define:
V: Maximum possible present value of future profits (cash flows) from the operation (NPV of total operation)
Profits ($M): Profits (Cash flow) from mining Qm amount of material
Vq: Maximum possible present value of future profits (cash flows) after the next Qm amount of material has been mined
v=V-Vq: Marginal increase in present value to be achieved by mining next Qm of material
4
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Derivation of Opportunity Costs of Mining Low Grades (Cont.)
TdVqMprofits
V)1(
))($(+
+=
))($()1(* VqMprofitsdV T +=+
If i is relatively small, then )*1()1( Tdd i +=+
VqMprofitsTdV +=+ )($)*1(*
VqMprofitsTdVV +=+ )($**
TdVMprofitsVqV **)($ −=−
5
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Derivation of Opportunity Costs of Mining Low Grades (Cont.)
Let v=V-Vq then
TVdMprofitsv **)($ −=
The opportunity cost of taking low grades now when higher grades are still available
We need to set cutoff grade so that we do not delay high grade
6
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Basic Present Value Expression
• Annual profits can be calculated as follows:
TVdTfQmQcQsrPv mcr ******)( −−−−−−=
WhereP: Metal price per ton of productr: Marketing cost per ton of product
c: Processing cost per ton of orem: Mining cost per ton of ore
f: Annual fixed administrative costs
s: Sales cost per ton of product
T: Number of time periods that will take to mine, concentrate and refine Qm amount of material from the pit (i.e. years)
7
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Mine Limiting Case
• When the mining capacity is the bottleneck in the system:
MQ
T m=
mcrm QM
VdfmQcQsrPv *
)*(**)(
+
+−−−−=
COG
vm
vm is a function of cutoff grades
8
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
COG of Mine Limiting Case
• Cutoff grade of mine limiting case is:
ysrPc
gm *)( −−=
where
y: Metallurgical recovery
9
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Concentrator Limiting Case
• When the concentrator capacity is the bottleneck in the system:
CQ
T c=
mcrc QmQC
VdfcQsrPv **
)*(*)( −
+
+−−−=
• Cutoff grade of concentrator limiting case is:
ysrPC
Vdfc
gc *)(
)*(
−−
++
=
10
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Refinery Limiting Case
• When the refinery capacity is the bottleneck in the system:
RQ
T r=
mcrr QmQcQR
VdfsrPv ***)
)*(( −−
+−−−=
• Cutoff grade of refinery limiting case is:
yR
VdfsrP
cg r
*)*(
+−−−
=
11
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Balancing Cutoff Grade (Cont.) Mine - Mill
C/M
g mc
12
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Balancing Cutoff Grade (Cont.)Mine - Refinery
R/M
g mr
13
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Balancing Cutoff Grade (Cont.)Mill - Refinery
R/C
g rc
14
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Open Pit Copper Case StudyDeposit Reserves
(Mtons)(%Cu)
15
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
First Year Production Reserves
(Mtons)(%Cu)
16
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Open Pit Copper Case Study Unit of mining: ton
Price (P): $25/ 1%Cu of one unit of mining
(=$25/1%Cu*1ton = $25/0.01tonCu = $25/20lbsCu
= $1.25/lbCu)
Mining Cost (m): $1/ one unit of mining = $1/ton
Concentrator Cost (c): $2/ one unit of mining = $2/ton
Refinery Cost (s): $5/ 1%Cu of one unit of mining
Fixed Cost (f): $300M /yr
Mine capacity (M): 100M one unit of mining /yr = 100Mtons/yr
Concentrator capacity (C): 50M one unit of mining /yr = 50Mtons/yr
Refinery capacity (R): 40M of 1%Cu of one unit of mining /yr
(=40M*0.01tonCu /yr = 400k tons Cu /yr)
Recovery (y): 100%
Discount rate (d): 15%
17
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Mine Limited Case
(V=0) (V=1174)
18
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Concentrator Limited Case
(V=0) (V=1174)
19
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Refinery Limited Case
(V=0) (V=1174)
20
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Balancing Cutoff Grade
Balancing Cutoff Grades (V=0)
-300
-200
-100
0
100
200
300
400
500
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9
COG
Pro
fit vm
vc
vr
gm gr
gc
Gopt
Feasible Region
21
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Balancing Cutoff Grade
Balancing Cutoff Grades (V=1174)
-250
-200
-150
-100
-50
0
50
100
150
200
250
300
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9
COG
Pro
fit vm
vc
vr
Gopt
22
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Limiting Economic Cutoff Grades
CuCutonCu
tonysP
cg m %10.0%
1*)525(2
1*)1*%1/)($525()/($2
*)(=
−=
−=
−=
• Cutoff grade of mine limiting case is (V=0):
• Cutoff grade of concentrator limiting case is (V=0):
CuCutonCu
yrtonMyrM
ton
ysPC
Vdfc
g c %40.0%1*)525(
50300
2
1*)1*%1/)($525()/(50)/($300
)/($2
*)(
)*(
=−
+=
−
+=
−
++
=
23
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Limiting Economic Cutoff Grades (Cont.)
• Cutoff grade of refinery limiting case is (V=0):
( ) 1*))/1*%1(40
)/($300)1*%1/($525
)/($2
*)*(
−−
=
+
−−=
yrtonCuMyrM
tonCu
ton
yR
VdfsP
cg r
CuCu %16.0%1*
40300
525
2=
−−
=
24
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Grade – Tonnage Curve
25
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Average Grade Above Cutoff
26
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Ore : Material Ratio
27
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Product : Material Ratio
28
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Product : Ore Ratio
29
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Grade – Tonnage Relationship
Cutoff Quantity Tons Below Tons Above Avg Grade Cu Produced Ore to Product to Product to Ore to(%Cu) (Mtons) Cutoff Cutoff Above Cutoff (%Cu of Material Material Ore Waste
(Mtons) (Mtons) (%Cu) 1ton of Material) Ratio Ratio Ratio Ratio(C ) ( R) (C/M) (R/M) (R/C)
0.00 100 0 1000 0.500 500 1.0 0.500 0.500 0.00
0.10 100 100 900 0.550 495 0.9 0.495 0.550 0.11
0.20 100 200 800 0.600 480 0.8 0.480 0.600 0.25
0.30 100 300 700 0.650 455 0.7 0.455 0.650 0.43
0.40 100 400 600 0.700 420 0.6 0.420 0.700 0.67
0.50 100 500 500 0.750 375 0.5 0.375 0.750 1.00
0.60 100 600 400 0.800 320 0.4 0.320 0.800 1.50
0.70 100 700 300 0.850 255 0.3 0.255 0.850 2.33
0.80 100 800 200 0.900 180 0.2 0.180 0.900 4.00
0.90 100 900 100 0.950 95 0.1 0.095 0.950 9.00
30
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Balancing Economic Cutoffs
gmc: Ore : Material = C:M = 50M/100M =0.5
Then, from the table above gmc= 0.50 %Cu
gmr: Product : Material = R:M = 40M/100M =0.4
Then, from the table above gmr= 0.45 %Cu
grc: Product : Ore = R:C = 40M/50M =0.8
Then, from the table above grc= 0.60 %Cu
31
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Choosing Optimum Cutoff Grade
32
MN
GN
433
Min
e S
yste
ms
Ana
lysi
s
Choosing Optimum Cutoff Grade
Gmc = 0.40%Cu Grc = 0.40%Cu Gmr = 0.16%Cu Then, Gopt = 0.40%Cu