strategic open pit mine planning course.pdf

1009

Click here to load reader

Upload: alissonbrasil

Post on 23-Dec-2015

322 views

Category:

Documents


83 download

TRANSCRIPT

Page 1: Strategic Open Pit Mine Planning Course.pdf

LQ

S L

ati

n A

meric

a A

venid

a L

uis

Th

ayer

Oje

da

013

0 O

fi. 30

4, P

rovid

encia

. S

anti

ago

, C

hil

e T

el:

562

-65

738

98

Fax:

56

2-6

5738

97

Toda la información contenida en este manual es de propiedad del Señor Kadri Dagdelen y cualquier reproducción parcial o total de la misma será sancionada legalmente.

Page 2: Strategic Open Pit Mine Planning Course.pdf
Page 3: Strategic Open Pit Mine Planning Course.pdf

Introduction to Mining Practices- Case Studies Open Pit Mining Terminology Pit Geometry and Slope Angles Open Pit Mine Planning Concepts - Circular Analysis Geologic Block Modeling Techniques Assay and Composite Sections and Block Modeling

Geostatistical Resource Estimation Techniques

Economic Definition of Ore Break-even Cutoff Grades and Stripping Ratio Analysis Economic Block Modeling, Cone and L&G Mining Analysis Final Pit Limits, Nested Pits and Mining Sequence Determination Cutoff Grade Policy, Scheduling and Stockpile Management

Mine Sequence, Cutoff Grade, Process Flow Determination

UNIT OPERATIONS AND EQUIPMENT SELECTION Drilling Fundamentals and Drill Selection Blasting Fundamentals Front End Loaders; Hydraulic Shovels and Cable Shovels Excavator Selection Considerations Equipment Cost Calculations Cat Handbook Truck Haulage and Cycle Times

Fleet Size Determination

Dispatch Systems In Pit Crushing and conveying systems

Mineral Processing

Mining Project Cash Flow Analysis Net Present Value Calculations

Mine Sequence, Cutoff grade and Process Flow NPV optimization

Papers by Kadri Dagdelen.

Page 4: Strategic Open Pit Mine Planning Course.pdf

Bingham Canyon MinePorphyry Copper

Case Study

Sur

face

Min

e D

esig

n

Page 5: Strategic Open Pit Mine Planning Course.pdf

2

Sur

face

Min

e D

esig

n

General Information

Page 6: Strategic Open Pit Mine Planning Course.pdf

3

Sur

face

Min

e D

esig

n

General Information

•World’s first low grade copper mine.

•5 billion tons of material and 13 million tons of copper produced since 1906.

•Overall stripping ratio is 0.4:1.

•Mine daily production is 111 Kton of ore and 99.2 Kton of waste. (40 and 36 Mton/year respectively).

•Reserves are at 1.0 Btons @ 0.5% Cu per ton which results in 25 years mine life.

Page 7: Strategic Open Pit Mine Planning Course.pdf

4

Sur

face

Min

e D

esig

n

General Information

•210 Kton of copper; 350 oz of gold; 2.5 MM oz of silverand 6350 ton of moly per year.

•2.5 miles long; 0.5 miles deep.

•Truck haulage – haul road 150 ft wide; also 3 tunnels for ore and waste haulage.

•Mine operates three 8-hour shifts per day, 365 days per year.

Page 8: Strategic Open Pit Mine Planning Course.pdf

5

Sur

face

Min

e D

esig

n

General Information

Layout

Page 9: Strategic Open Pit Mine Planning Course.pdf

6

Sur

face

Min

e D

esig

n

General Information

Geology

Page 10: Strategic Open Pit Mine Planning Course.pdf

7

Sur

face

Min

e D

esig

n

General Information

•Block model dimensions 100 x 100 x 50 ft. Each block is assigned a value of Cu, Au, Ag, and Mo using a geostatistical technique known as kriging.

•Development drilling on 400 by 600 ft centers.

•Density 2.58 t/m3 or equivalent tonnage factor of 12.38 ft3/ton.

Page 11: Strategic Open Pit Mine Planning Course.pdf

8

Sur

face

Min

e D

esig

n

Mine Plan

•Pushbacks range from 100 ft to 200 ft in width and 50 ft in height.

•Five ore shovel production faces to meet average grade and metallurgical blending requirements.

•Five waste shovel production faces to meet long range stripping requirements.

•Operating interramp pit slope, including bench face angles and catch benches, is 34o; catch benches are 50 ft wide.

Page 12: Strategic Open Pit Mine Planning Course.pdf

9

Sur

face

Min

e D

esig

nMine Plan

Typical Mining Sequence

Page 13: Strategic Open Pit Mine Planning Course.pdf

10

Sur

face

Min

e D

esig

n

Mine Plan

•Ore is being mined in lower 900 ft of the pit and highest active waste stripping occurs 2000 ft higher elevation.

•In extreme cases, mining room must be brought down nearly 40 benches before new ore is exposed; this process can take as long as seven years.

•Slope angles for the ultimate pit limits are defined by subdividing the pit surface in 26 sectors.

Page 14: Strategic Open Pit Mine Planning Course.pdf

11

Sur

face

Min

e D

esig

n

Mine Plan

•Slope angles for each of these sectors range from 29 to 50 degrees.

•Slope angles will be achieved by double benching or single benching and control blasting – “digging to hard”.

•Slope dewatering using near horizontal drains improves slope angles by 3 to 5 degrees in the ultimate slope.

•Mining plans are developed by defining the volume of ore and waste between series of pushbacks.

Page 15: Strategic Open Pit Mine Planning Course.pdf

12

Sur

face

Min

e D

esig

n

Mine Plan

•The material in pushbacks sequentially mined by a computerized mining simulator algorithm. Highest relative profit margin ore is mined first.

•Haulage roads are added to the incremental pits.

•Mine plan is a series of annual plans for five-year followed by five year plans to the end of mine life.

Page 16: Strategic Open Pit Mine Planning Course.pdf

13

Sur

face

Min

e D

esig

n

Drilling

•Drills operate 5 days per week and two 8-hour shifts per day.

•8 Bucyrus-Erie 60R track-mounted electric drills.

•They can drill 57 to 65 ft in a single pass by exerting 120 Klb thrust.

•Rotary tricone bits with carbide inserts are used to drill 12.25 in diameter holes.

•One drill can drill 12 holes per 8-hour shift.

•Two drilltech D75K track-mounted units; carbide insert bits 9.875 in diameter – 4 35-ft drill rods.

Page 17: Strategic Open Pit Mine Planning Course.pdf

14

Sur

face

Min

e D

esig

n

Drilling

•D75K drills are used in resilient (hard) formations where closer patterns are necessary for proper fragmentation.

•One secondary drill uses 2.5-in and 12-ft drill rods to drill boulders. Also mine has rubber-tired rock breaker.

•Drill patterns vary with the rock types but range from 30 x 30 ft to 36 x 36 ft for 12.25-in holes. 25 x 25 ft to 30 x 30 ft for 9.875-in holes.

Page 18: Strategic Open Pit Mine Planning Course.pdf

15

Sur

face

Min

e D

esig

n

Blasting

•Two ANFO trucks – blending of ammonium nitrate prills and fuel oil occurs when bulk delivery trucks deliver these material to the mine-site storage tanks.

•Commercial bulk emulsion-blend explosives are used in wet holes.

•Holes are primed with two 0.75-lb boosters placed near the bottom of the explosive column.

•A 200-ms delay is inserted into each booster and connected to individual 7.5-grain primaline down-lines.

Page 19: Strategic Open Pit Mine Planning Course.pdf

16

Sur

face

Min

e D

esig

n

Blasting

•25 grain detonating cord is used for trunk lines and cross ties.

•Surface delays of 17 ms are used between holes and 100 ms between rows.

•A single strand of detonating cord extended from the pattern and initiated by a non-electric cap taped to the cord.

•Drill cuttings are used for stemming. Each hole produces 2.4 to 3.7 tons of cuttings. These cuttings are forced into loaded holes.

Page 20: Strategic Open Pit Mine Planning Course.pdf

17

Sur

face

Min

e D

esig

n

Blasting

•Powder factor varies between 0.13 to 0.25 lbs of explosive per ton depending on rock type; average 0.16 lb per ton.

•Ground motion due to blasting is limited to 25 in/sec at the planned final pit slopes.

Page 21: Strategic Open Pit Mine Planning Course.pdf

18

Sur

face

Min

e D

esig

n

Loading

•2 15-yd3 P&H2100; availability averages 78%; 10 Ktons per shovel shift.

•4 27-yd3 P&H2800 Mark II; availability averages 80%; 15 Ktons per shovel shift.

•3 30-yd3 P&H 2800 XP; availability averages 80%; 15 Ktons per shovel shift.

• 2 34-yd3 P&H 2800 XPA; availability averages 80%; 20 Ktons per shovel shift.

•2 8-yd3 International; 1 12-yd3 Clark; 2 12-yd3

Caterpillar rubber tired FEL’s.

Page 22: Strategic Open Pit Mine Planning Course.pdf

19

Sur

face

Min

e D

esig

n

Loading

•Power is provided by 44-kva substations; radial lines are then fed to smaller substations with voltage reduced to 5500 V ac.

•Electric connections between the switch houses and shovels are made through trailing cables up 2000 ft for shovels and 3000 ft for the drills.

Page 23: Strategic Open Pit Mine Planning Course.pdf

20

Sur

face

Min

e D

esig

n

Haulage

•Mainly trucks and some rail.

•Truck haulage utilizes a fleet of 44 trucks composed of 28 190-ton CAT-785 mechanical drive; 8 170-ton Unit Rig diesel electric; 8 170-ton Wabco diesel electric trucks.

•In 1990 34 truck-shifts/shift are scheduled with average availability of 94% for the new, larger trucks; 84% for the smaller, older trucks.

•All trucks are equipped with two-way radios to assist appropriate dispatching.

Page 24: Strategic Open Pit Mine Planning Course.pdf

21

Sur

face

Min

e D

esig

n

In-Pit Crusher

•Movable, 60- by 109-in, 1000-hp Allis Chalmers gyratory crusher that has a capacity of 120,000 tons per day on continuous basis.

•Two trucks at a time at a dumping rate of one truck per minute.

•3 to 4 weeks are required to move the crusher.

•-10 in crushed rock is fed directly to a 72-in conveyor.

•The belt is 5 mile ling to Copperton concentrator and capable of carrying 10,000 tph at 900 ft/min speed.

Page 25: Strategic Open Pit Mine Planning Course.pdf

22

Sur

face

Min

e D

esig

n

Road Maintenance

•28 miles of haulage roads and 40 miles of service roads.

•20 dozers (CAT D9H, D9L, D10L).

•11 graders (CAT 16G).

•2 scrappers (CAT 631).

•4 salt trucks (5.4 or 6 ton capacity).

•6 water trucks (converted 65-ton or 59-ton haulage trucks; 10,000 to 30,000 gallons capacity).

Page 26: Strategic Open Pit Mine Planning Course.pdf

Sur

face

Min

e D

esig

n

Open Pit Mining Fundamentals

Dr. Kadri Dagdelen

Colorado School of Mines

Page 27: Strategic Open Pit Mine Planning Course.pdf

2

Sur

face

Min

e D

esig

n

Terminology

• BENCH: Ledge that forms a single level of operation above which mineral or waste materials are mined from the bench face.

Page 28: Strategic Open Pit Mine Planning Course.pdf

3

Sur

face

Min

e D

esig

n

Terminology (Cont.)

• BENCH HEIGHT: Vertical distance between the highest point on the bench (crest) and the lowest point or the bench (toe). It is influenced by size of the equipment, mining selectivity, government regulations and safety.

Page 29: Strategic Open Pit Mine Planning Course.pdf

4

Sur

face

Min

e D

esig

n

Terminology (Cont.)

• BENCH SLOPE OR BANK ANGLE : Horizontal angle of the line connecting bench toe to the bench crest.

Page 30: Strategic Open Pit Mine Planning Course.pdf

5

Sur

face

Min

e D

esig

n

Terminology (Cont.)

• BERM: Horizontal shelf or ledge within the ultimate pit wall slope left to enhance the stability of the a slope within the pit and improve the safety.Berm interval, berm width and berm slope angle are determined by the geotechnical investigation.

Page 31: Strategic Open Pit Mine Planning Course.pdf

6

Sur

face

Min

e D

esig

n

Terminology (Cont.)

• OVERALL PIT SLOPE ANGLE: The angle measured from the bottom bench toe to the top bench crest. It is the angle at which the wall of an open pit stands and it is determined by: rock strength, geologic structures and water conditions.

Page 32: Strategic Open Pit Mine Planning Course.pdf

7

Sur

face

Min

e D

esig

n

Terminology (Cont.)

• The overall pit slope angle is affected by the width and grade of the haul road.

Page 33: Strategic Open Pit Mine Planning Course.pdf

8

Sur

face

Min

e D

esig

n

Terminology (Cont.)

• HAUL ROADS: During the life of the pit a haul road must be maintained for access.

• HAUL ROAD - SPIRAL SYSTEM: Haul road is arranged spirally along the perimeter walls of the pit.

Page 34: Strategic Open Pit Mine Planning Course.pdf

9

Sur

face

Min

e D

esig

n

Terminology (Cont.)

• HAUL ROAD – SWITCH BACK SYSTEM: Zigzag pattern on one side of the pit.

• HAUL ROAD WIDTH: Function of capacity of the road and the size of the equipment. Haul road width must be considered in the overall pit design.

Page 35: Strategic Open Pit Mine Planning Course.pdf

10

Sur

face

Min

e D

esig

n

Haul Road Effect on Pit Limits

Page 36: Strategic Open Pit Mine Planning Course.pdf

11

Sur

face

Min

e D

esig

n

Terminology (Cont.)

• ANGLE OF REPOSE: Maximum slope of the broken material.

• SUBCROP OR ORE DEPTH: Depth of waste removed to reach initial ore.

• PRE-PRODUCTION STRIPPING: Stripping done to reach initial ore.

Page 37: Strategic Open Pit Mine Planning Course.pdf

12

Sur

face

Min

e D

esig

n

Terminology (Cont.)

• ULTIMATE PIT LIMITS: Vertical and lateral extend of the economically mineable pit boundary. Determined on the basis of cost of removing overburden or waste material vs. the mineable value of the ore.

• PIT SCHEDULING: Material may be mined from the pit either in 1) sequential pushbacks 2) conventional pushbacks.

Page 38: Strategic Open Pit Mine Planning Course.pdf

13

Sur

face

Min

e D

esig

n

Terminology (Cont.)

• STRIPPING RATIO: Expressed in tons of waste to tons of ore in hard rock open pit operations. Critical and important parameter in pit design and scheduling

• AVERAGE STRIP RATIO: Total waste divided by total ore within the ultimate pit.

• CUTOFF STRIPPING RATIO: Costs of mining a ton of ore and associated waste equals to net revenue from the ton of ore.

Page 39: Strategic Open Pit Mine Planning Course.pdf

14

Sur

face

Min

e D

esig

n

Single Working Bench

Page 40: Strategic Open Pit Mine Planning Course.pdf

15

Sur

face

Min

e D

esig

n

Shovel in Working Bench

Page 41: Strategic Open Pit Mine Planning Course.pdf

16

Sur

face

Min

e D

esig

n

Two Working Benches

Page 42: Strategic Open Pit Mine Planning Course.pdf

17

Sur

face

Min

e D

esig

n

Final Pit Limit

Page 43: Strategic Open Pit Mine Planning Course.pdf

18

Sur

face

Min

e D

esig

n

Cresson Mine – Year 2001

Page 44: Strategic Open Pit Mine Planning Course.pdf

19

Sur

face

Min

e D

esig

n

Cresson Mine – Year 2007

Page 45: Strategic Open Pit Mine Planning Course.pdf

20

Sur

face

Min

e D

esig

n

Cresson Mine – Year 2011

Page 46: Strategic Open Pit Mine Planning Course.pdf

21

Sur

face

Min

e D

esig

n

Pit Sequence (1)

Page 47: Strategic Open Pit Mine Planning Course.pdf

22

Sur

face

Min

e D

esig

n

Pit Sequence (2)

Page 48: Strategic Open Pit Mine Planning Course.pdf

23

Sur

face

Min

e D

esig

n

Pit Sequence (3)

Page 49: Strategic Open Pit Mine Planning Course.pdf

24

Sur

face

Min

e D

esig

n

Pit Sequence (4)

Page 50: Strategic Open Pit Mine Planning Course.pdf

25

Sur

face

Min

e D

esig

n

Section of Pit Sequence

Page 51: Strategic Open Pit Mine Planning Course.pdf

Dr. Kadri Dagdelen

Colorado School of Mines

Source: Hustrulid and KuchtaOpen Pit Mine Planning and Design

Open Pit Mine Planning and Design: Fundamentals

Sur

face

Min

e D

esig

n

Page 52: Strategic Open Pit Mine Planning Course.pdf

2

Geometrical Considerations

Parts of a bench

Cumulative frequencydistribution of measured

bench face angles (Call, 1986).

Sur

face

Min

e D

esig

n

Page 53: Strategic Open Pit Mine Planning Course.pdf

3

Geometrical Considerations

Section through a working bench.Functioning of catch benches.

Sur

face

Min

e D

esig

n

Page 54: Strategic Open Pit Mine Planning Course.pdf

4

Geometrical Considerations

Double benches at final pit limits. Catch bench geometry (Call, 1986).

Typical catch bench design dimensions (Call, 1986).Bench height Impact zone Berm height Berm width Minimum bench width

(m) (m) (m) (m) (m)15 3.5 1.5 4 7.530 4.5 2 5.5 1045 5 3 8 13S

urfa

ce M

ine

Des

ign

Page 55: Strategic Open Pit Mine Planning Course.pdf

5

Geometrical Considerations

Safety berms at bench edge

Sur

face

Min

e D

esig

n

Page 56: Strategic Open Pit Mine Planning Course.pdf

6

Geometrical Considerations

Height of reach as a function of bucket size.Sur

face

Min

e D

esig

n

Page 57: Strategic Open Pit Mine Planning Course.pdf

7

Geometrical Considerations

Example orebody geometry.Ramp access for the example orebody.

Blast design for the ramp excavation.Sur

face

Min

e D

esig

n

Page 58: Strategic Open Pit Mine Planning Course.pdf

8

Shovel Working Range

Sur

face

Min

e D

esig

n

Page 59: Strategic Open Pit Mine Planning Course.pdf

9

Geometrical Considerations

Minimum width drop cutgeometry with shovelalternating from side to side.

Sur

face

Min

e D

esig

n

Page 60: Strategic Open Pit Mine Planning Course.pdf

10

Geometrical Considerations

Minimum width drop cutgeometry with shovelalternating from side to side.

Sur

face

Min

e D

esig

n

Page 61: Strategic Open Pit Mine Planning Course.pdf

11

Geometrical Considerations

Isometric view of the ramp in waste approaching the orebody.

Diagrammatic representation of the expanding mining front.

Sur

face

Min

e D

esig

n

Page 62: Strategic Open Pit Mine Planning Course.pdf

12

Geometrical Considerations

Dropcut / ramp placement in ore. Expansion of the mining front.

Sur

face

Min

e D

esig

n

Page 63: Strategic Open Pit Mine Planning Course.pdf

13

Geometrical Considerations

Plan view of an actual pit bottomShowing drop cut and miningExpansion (McWilliams, 1959).

Sur

face

Min

e D

esig

n

Page 64: Strategic Open Pit Mine Planning Course.pdf

14

Geometrical Considerations

Extension of the currentRamp close to the pit wall(McWilliams, 1959).

Sur

face

Min

e D

esig

n

Page 65: Strategic Open Pit Mine Planning Course.pdf

15

Geometrical Considerations

Creating initial access / benches.

Shovel cut sequence when initiatingbenching in a hilly terrain (Nichols, 1956).

Sidehill cut with a shovel.

Sur

face

Min

e D

esig

n

Page 66: Strategic Open Pit Mine Planning Course.pdf

16

Geometrical Considerations

Detailed steps in the development of a new production level.Sur

face

Min

e D

esig

n

Page 67: Strategic Open Pit Mine Planning Course.pdf

17

Geometrical Considerations

Parallel cut with drive by.Sur

face

Min

e D

esig

n

Page 68: Strategic Open Pit Mine Planning Course.pdf

18

Geometrical Considerations

Parallel cut with the double spotting of trucks.Sur

face

Min

e D

esig

n

Page 69: Strategic Open Pit Mine Planning Course.pdf

19

Geometrical Considerations

Parallel cut with the single spotting of trucks.Sur

face

Min

e D

esig

n

Page 70: Strategic Open Pit Mine Planning Course.pdf

20

Geometrical Considerations

Time sequence showing shovelloading with single spotting.

Sur

face

Min

e D

esig

n

Page 71: Strategic Open Pit Mine Planning Course.pdf

21

Geometrical Considerations

(Continued).Sur

face

Min

e D

esig

n

Page 72: Strategic Open Pit Mine Planning Course.pdf

22

Geometrical Considerations

Time sequence showing shovelloading with double spotting.

Sur

face

Min

e D

esig

n

Page 73: Strategic Open Pit Mine Planning Course.pdf

23

Geometrical Considerations

(Continued).

Sur

face

Min

e D

esig

n

Page 74: Strategic Open Pit Mine Planning Course.pdf

24

Geometrical Considerations

(Continued).Sur

face

Min

e D

esig

n

Page 75: Strategic Open Pit Mine Planning Course.pdf

25

Geometrical Considerations

Section and plan views through a working bench.

Simplified presentation of a safety berm.

Sur

face

Min

e D

esig

n

Page 76: Strategic Open Pit Mine Planning Course.pdf

26

Geometrical Considerations

Initial geometry for the push back example.

Cut mining from bench 1.

Cut mining from bench 2.

Sur

face

Min

e D

esig

n

Page 77: Strategic Open Pit Mine Planning Course.pdf

27

Geometrical Considerations

Overall slope angle.

Safety bench geometryshowing bench face angle.

Sur

face

Min

e D

esig

n

Page 78: Strategic Open Pit Mine Planning Course.pdf

28

Geometrical Considerations

Overall slope angle with ramp included.

Interramp slope angles.

Sur

face

Min

e D

esig

n

Page 79: Strategic Open Pit Mine Planning Course.pdf

29

Geometrical Considerations

Overall slope angle withWorking bench included.

Interramp angles associated withthe working bench.

Sur

face

Min

e D

esig

n

Page 80: Strategic Open Pit Mine Planning Course.pdf

30

Geometrical Considerations

Overall slope angle withone working bench an a ramp section.

Interramp slope angles for a slope containinga working bench and a ramp.

Sur

face

Min

e D

esig

n

Page 81: Strategic Open Pit Mine Planning Course.pdf

31

Geometrical Considerations

Overall slope angle for a slope containing two working benches.Sur

face

Min

e D

esig

n

Page 82: Strategic Open Pit Mine Planning Course.pdf

32

Geometrical Considerations

Slopes for each working group.

Sur

face

Min

e D

esig

n

Page 83: Strategic Open Pit Mine Planning Course.pdf

33

Geometrical Considerations

Final overall pit slope.Sur

face

Min

e D

esig

n

Page 84: Strategic Open Pit Mine Planning Course.pdf

Advances in Pit Slope Management SystemsAdvances in Pit Slope Management Systems

Dr. Kadri DagdelenProfessor

Mining Engineering DepartmentColorado School of MinesGolden, Colorado 80401

Page 85: Strategic Open Pit Mine Planning Course.pdf

Pit Slope Failure ProblemsPit Slope Failure Problems

l Continue to be the source of human and financial losses

l Recent examples from Wyoming coal mines and Grasberg pit in Indonesia point to additional research needs to be done in the area of pit slope management

l Pit slope monitoring research is undertaken at the Colorado School of Mines using Lidar Scanners with funding from Kennocott Energy and 3-DP

Page 86: Strategic Open Pit Mine Planning Course.pdf

Plane FailurePlane Failure

l Failure plane must daylight in the slope face; i.e. its dip must be smaller than slope (S>P)

l Plane must strike parallel or nearly parallel (within 20o) to the slope face.

l Less common than other failure modes

Page 87: Strategic Open Pit Mine Planning Course.pdf

Plane Failure in a Limestone Plane Failure in a Limestone QuarryQuarry

Page 88: Strategic Open Pit Mine Planning Course.pdf

Wedge FailureWedge Failure

DAYLIGHTING WEDGE

NON-DAYLIGHTING WEDGE

• Most common mode of failure for rock slopes

• Line of intersection must daylight into slope face

• Often, failure is sudden

Page 89: Strategic Open Pit Mine Planning Course.pdf

Circular FailureCircular Failure

l Soilsl Stock pilesl Reclamation pilesl Waste dumpsl Highly weathered overburden rocks

Page 90: Strategic Open Pit Mine Planning Course.pdf

Toppling and StepToppling and Step--Path Path ModesModes

Toppling Mixed modes(e.g. Toppling & Step-Path)

Page 91: Strategic Open Pit Mine Planning Course.pdf

Overall Slope DesignOverall Slope Design

l Identify geological sectors; their strength characteristics and possible mode of failures

l Determine maximum height and angle for inter-ramp design

l Determine bench geometryl Incorporate bench geometry into Inter-ramp

designl Overall slope design

Page 92: Strategic Open Pit Mine Planning Course.pdf

Failure Modes in Different Failure Modes in Different Sectors Sectors

Page 93: Strategic Open Pit Mine Planning Course.pdf

Pit Slope Monitoring Pit Slope Monitoring -- What to look for What to look for

l Overhang rockl New geological structuresl Swell and/or increased rock fall activity on highwalll Heavy precipitationl Signs of stressl Tension cracksl Movement (acceleration)l Increased water levels

Page 94: Strategic Open Pit Mine Planning Course.pdf

Tension Crack Measurements Tension Crack Measurements l The formation of cracks behind slope is a sign of instability

(Safety Factor ˜ 1)l Monitoring changes in crack width and direction can provide

information on extent of unstable area

Page 95: Strategic Open Pit Mine Planning Course.pdf

InclinometersInclinometers

l Inclinometers measure horizontal deflections of a borehole

l They can- Locate failure surface - Determine nature of failure surface

(rotational or planar)- Measure movement along failure

surface and determine if movement is accelerating

Page 96: Strategic Open Pit Mine Planning Course.pdf

Borehole extensometerBorehole extensometer

l Consists of tensioned rods anchored at different points in a borehole.

l Measures changes in distance between anchors, as well as collar

l Provides displacement information across discontinuities.

Page 97: Strategic Open Pit Mine Planning Course.pdf

New and Emerging TechnologiesNew and Emerging Technologiesl Automated Total Station Network (robots)

l Non-reflective Laser scanners (Lidar systems: Cyra, Riegl, I-Site)

l Radar Technologies

l GPS (Local sensors with multiple antenna)

l TDR (Time Domain Reflectometry)

l Digital photogrammetry

l Arial photography (Kodak)

Page 98: Strategic Open Pit Mine Planning Course.pdf

Automated Total Station Network in Automated Total Station Network in Chuquicamata Mine, ChileChuquicamata Mine, Chile

• A network of automated total stations for geotechnical monitoring of pit slopes that operate continuously 24 hours a day, 7 days a week and during the 365 days a year.

• Provide a reliable and quantitative information in real time thatallows to establish with anticipation the behavior of the rock massand geologic structures on the pit slopes.

Page 99: Strategic Open Pit Mine Planning Course.pdf

Completely Automated Electronic Completely Automated Electronic Station Network using Station Network using LeicaLeica TCA2003TCA2003

Motorized Station, Leica TCA2003

Characteristics• Reach with 1/3 prisms in average

atmospheric conditions : 2500/3500 mts.• Precision in distance : 1mm + 1 ppm• Angular precision : 0.3” (0.1 mgon)• Increase of lens : 30 x• Compartment for the insertedable

memory card PCMCIA.• Integrated application programs :

Reframing, orientation of horizontal circleand drag of levels, reseccion anddistance of connection between twopoints.

• Capture of information in modality ATR and DIST.

Page 100: Strategic Open Pit Mine Planning Course.pdf

WirelessWireless CommunicationCommunication NetworkNetworkBridge

Bluebox

Switch

Energy

SHELTER 1

SHELTER 2

SHELTER 6

SHELTER 5

ARTURO OESTE

SHELTER 3

SHELTER 4

ARTURO ESTE

CONTROL ROOM ETHERNET NETWORK

Page 101: Strategic Open Pit Mine Planning Course.pdf

SHELTER 1

SHELTER 2

SHELTER 6

SHELTER 5

ARTURO OESTE

SHELTER 3

SHELTER 4

ARTURO ESTE

CONTROL ROOMCONTROL ROOM

LocationLocation of Stations of Stations andand IntegrationIntegration of of InformationInformation

Software of Information Integration

• Have a Computational Software that allows to totally integrate and administer the acquisition of geotechnical data, procesingand analisis of the information in real time originating from therobotic system (TCA) intalled in each of the monitoring stations.

Page 102: Strategic Open Pit Mine Planning Course.pdf

Total Station and Prism Locations in Total Station and Prism Locations in Chuquicamata Mine, ChileChuquicamata Mine, Chile

CasetaEste

CasetaOeste

Page 103: Strategic Open Pit Mine Planning Course.pdf

GPS Surveyed Control Stations in GPS Surveyed Control Stations in Chuquicamata Mine, ChileChuquicamata Mine, Chile

Coordenadas de laEstación de MonitoreoAPS(N;E;Z)

ZONA-5 ZONA-6 ZONA-7

D1 D2 D3D4

“D” (PR-1)

“E1” (PR-2) Matus (PR-3)

GT-1 PR-4

Morgan (PR-5)

S4

S3

S5

S2

S1

D5

.

PILAR GT-1

APS-WEST. Norte : 2085.491Este : 3870.863Elev

Cota : 2846.745

Page 104: Strategic Open Pit Mine Planning Course.pdf

Slope Stability Radar Technology Slope Stability Radar Technology from from GroundProbeGroundProbe of Australiaof Australia

Page 105: Strategic Open Pit Mine Planning Course.pdf

Complete Pit Wall Coverage from Complete Pit Wall Coverage from Remote LocationsRemote Locations

Radar Scan Lines

Page 106: Strategic Open Pit Mine Planning Course.pdf

Location and Time of Wall Location and Time of Wall MovementsMovements

18:13 8th October 2003

20:47 8th October 2003

23:22 8th October 2003

02:04 9th October 2003

Dis

plac

emen

t (m

m)

Incr

easin

g dis

place

men

t with

time

Slip Area

Page 107: Strategic Open Pit Mine Planning Course.pdf

Slope Stability Radar FeaturesSlope Stability Radar Features• High deformation precision (± 0.2 mm std. dev.)

• Broad area coverage (~1000’s pixels/scan)

• Continuous operation (~ 1’s min/scan, 24 hrs/day)

• 30-850m range

• All weather operation (incl. dust, fog)

• Rapid Deployment

• Remote Operation via radio link and internet

• High resolution CCD Camera

• Custom software with alarm settings

Page 108: Strategic Open Pit Mine Planning Course.pdf

SSRViewerSSRViewer Images ScreenImages Screen

Page 109: Strategic Open Pit Mine Planning Course.pdf

SSRViewerSSRViewer Figures ScreenFigures Screen

10mm movement over 45 hours in Region 1

0.0mm movement over 45 hours in Region 2

15mm movement over 45 hours in Region 3

Page 110: Strategic Open Pit Mine Planning Course.pdf

Laser Scanning TechnologiesLaser Scanning TechnologiesThere are Many 3D Laser Scanners There are Many 3D Laser Scanners

Major Companies with Products are:Major Companies with Products are:

ll CyraxCyrax ((LeicaLeica) ) www.cyra.comwww.cyra.com (USA)(USA)ll OptechOptech ILRIS (Canada)ILRIS (Canada)ll II--site (site (MaptekMaptek) ) www.isite3d.comwww.isite3d.com (Australia)(Australia)ll LMS 3D Scanning systems (Riegl) LMS 3D Scanning systems (Riegl) www.riegl.co.at www.riegl.co.at

(Austria)(Austria)ll Z+F Laser Measuring Systems (Z+F Laser Measuring Systems (ZollerZoller+ + FröhlichFröhlich) )

www.zofre.dewww.zofre.de (Germany)(Germany)

CyraxCyrax 24002400

Page 111: Strategic Open Pit Mine Planning Course.pdf

Other Application in Laser Technologies Other Application in Laser Technologies Riegl Z 210i Lidar Laser ScannerRiegl Z 210i Lidar Laser Scanner

•1200+ ft scan range•2.5cm accuracy @ 900 ft•5 cm accuracy > 900 ft•361 degrees x 80 degree scan•9000 Hz

SpecificationsSpecifications

Page 112: Strategic Open Pit Mine Planning Course.pdf

Riegl LPM 800 HARiegl LPM 800 HA

•3000 ft scan range1cm accuracy @ 1250 ft2 cm accuracy > 1250 ft

•0.018 degrees step size•360 degrees of horizontal rotation•180 degrees of vertical rotation •1000 Hz

SpecificationsSpecifications

Page 113: Strategic Open Pit Mine Planning Course.pdf

Riegl Z 420 Lidar Laser ScannerRiegl Z 420 Lidar Laser Scanner

•2400+ ft scan range•1cm accuracy in topo mode•6 mm accuracy in detail mode•0.01 degree step size•361 degrees x 90 degree scan window•8000 - 12000 Hz

SpecificationsSpecifications

Page 114: Strategic Open Pit Mine Planning Course.pdf

High Wall Scan (Pre Blasting)High Wall Scan (Pre Blasting)

Page 115: Strategic Open Pit Mine Planning Course.pdf

PostPost--Blast ScanBlast Scan

Page 116: Strategic Open Pit Mine Planning Course.pdf

Pre Blast TrianglesPre Blast Triangles

Page 117: Strategic Open Pit Mine Planning Course.pdf

Post Blast TrianglesPost Blast Triangles

Page 118: Strategic Open Pit Mine Planning Course.pdf

Combined Combined –– Pre / PostPre / Post

Page 119: Strategic Open Pit Mine Planning Course.pdf

Dynamic Cross SectionDynamic Cross Section

Page 120: Strategic Open Pit Mine Planning Course.pdf

Complete Pit Scan using Complete Pit Scan using RieglRiegl

Page 121: Strategic Open Pit Mine Planning Course.pdf

Pit Wall Scan Using Pit Wall Scan Using RieglRiegl

Page 122: Strategic Open Pit Mine Planning Course.pdf

Pit Wall Failure Scan Pit Wall Failure Scan -- RiegleRiegle

Page 123: Strategic Open Pit Mine Planning Course.pdf

NoModerate< 150 m~ hoursBroad Area

~ 1’s cmPhotogram-metry

YesDifficultn/a~ secsDiscrete Points

~ 1’s cmGPS

Extenso-meters

LIDAR SCANNER

Laser (Prisms)

SSR –GROUND PROBE

Technology

YesEasy850 m(1.4km)

~ minsBroad Area

± 0.2 mm

NoDifficult2 kmTwice Daily

Discrete Points

~ 1’s cm

NoEasy900 m~ secsBroad Area

~ 1’s cm

Difficult

Deployment

Yesn/a~ secsDiscrete Points

~ 1’s mm

All weather

RangeUpdate Rate

Wall Coverage

Precision

Slope Monitoring Systems

Page 124: Strategic Open Pit Mine Planning Course.pdf

Slide Management OptionsSlide Management Optionsl Reduce slope anglel Dewater unstable areal Leave unstable areasl Continue miningl Unload slidel Partial clean upl Step-out

l Reduce slope height by segmenting the slope

l Support unstable groundl Contingency Planningl Blastingl Erosion control measures

(reclamation)- Geotextiles against erosion

and raveling- Vegetating and planting

Page 125: Strategic Open Pit Mine Planning Course.pdf

Instability can be left alone if it is in

– an abandoned area,

– an inactive area,

– an area that can be avoided

Leave Unstable Areas untouchedLeave Unstable Areas untouched

Page 126: Strategic Open Pit Mine Planning Course.pdf

Continue miningContinue miningIf the displacement rate is low and predictable, living with the displacement while continuing to mine may be the best action.

Dis

plac

emen

t (cm

)

Time

1/4/02 5/4/02 11/4/02 16/4/02

50

100

150 May continue mining (displacement rate is constant)

Page 127: Strategic Open Pit Mine Planning Course.pdf

Basic Principles of DrainageBasic Principles of Drainagel Prevent surface water from entering to the slope through

open tension cracks and fissuresl Reduce water pressure in the vicinity of the potential

failure surface l Providing for gravity flow of water is the most common

methodl Pumping is used on a temporary basis depending on the

urgency of the problem

Page 128: Strategic Open Pit Mine Planning Course.pdf

Bench section view

Inclined bench for gravity flow

Slope crest

Bench face view

Benches sloped toward toe

Method of Slope DrainageMethod of Slope Drainage

Page 129: Strategic Open Pit Mine Planning Course.pdf

POST

FLOWER PATCH

EXPL

ODI

NG

BLIND RODEO CREEK 1RODEO CREEK

GRAND JE

AN

AM

AN

DA

ANTI

POST

CH

RIS

TYS

DORM

ANT

JB

AN

FO

PA

TS

MIDNIGHT

60

60

60

50

85

80

60

55

50

25

60

60

75

N-00-B

EM

ILYS

LAST LAUGH78

RODEO CREEK

BLIND RODEO CREEK 1P

OW

ER

FUL

Horizontal Drain NetworkHorizontal Drain Network(303 drains/34 miles since 1999)(303 drains/34 miles since 1999)

Page 130: Strategic Open Pit Mine Planning Course.pdf

Unload SideUnload Side

l Even though unloading has been a common response, in general it has been unsuccessful.

l In fact, there are situations involving high water pressure where unloading actually decreases stability.

Page 131: Strategic Open Pit Mine Planning Course.pdf

Partial cleanPartial clean--upup

• Partial cleanup may be the best choice where a slide blocks a haul road or fails onto a working area

• Only that material necessary to get back into operation need be cleaned up

Page 132: Strategic Open Pit Mine Planning Course.pdf

New (Flatter) Overall Slope Angle

Old Overall Slope Angle

Originally Planned Slope DesignNew Slope Design

Failure SurfaceStep out

StepStep--outoutl Increased highwall stability due

to shallower slope angle It locks up reserves

lAdvantages of leaving step out should be weighed against cleaning by considering ore lock up and having safer overall slope

Page 133: Strategic Open Pit Mine Planning Course.pdf

Reduce slope height by Reduce slope height by segmenting slopesegmenting slope

Page 134: Strategic Open Pit Mine Planning Course.pdf

Support unstable groundSupport unstable ground

Buttress

Rock Bolts

Page 135: Strategic Open Pit Mine Planning Course.pdf

Anchors, Tiebacks, and Anchors, Tiebacks, and ShotcreteShotcrete

1. Reinforced concrete dowel to prevent loosening of slab at crest

2. Tensioned rock anchors to secure sliding failure along crest

3. Tieback wall to prevent sliding failure on fault zone

4. Shotcrete to prevent raveling of zone of fractured rock

5. Drain hole to reduce water pressure within slope

6. Concrete buttress to support rock above cavity

Page 136: Strategic Open Pit Mine Planning Course.pdf

Mesh & BoltsMesh & Bolts

Page 137: Strategic Open Pit Mine Planning Course.pdf

ButtressingButtressing

Page 138: Strategic Open Pit Mine Planning Course.pdf

ButtressingButtressing

Page 139: Strategic Open Pit Mine Planning Course.pdf

NE Wall Sept 2002NE Wall Sept 2002

2% ramp & buttress

mudslide

4880 buttress

unwting cut

N-00-B

4640

4280

Page 140: Strategic Open Pit Mine Planning Course.pdf

NE Wall UnNE Wall Un--weighting Cutweighting Cut

Page 141: Strategic Open Pit Mine Planning Course.pdf

Prism Data Feb 2002 to Feb 2003Prism Data Feb 2002 to Feb 2003PRISM DATA - All In Movement Area

-2.00

-1.80

-1.60

-1.40

-1.20

-1.00

-0.80

-0.60

-0.40

-0.20

0.00

0.20

2/1/02

2/15/0

23/1

/02

3/15/0

23/2

9/024/1

2/024/2

6/02

5/10/0

25/2

4/02

6/7/02

6/21/0

27/5

/02

7/19/0

28/2

/02

8/16/0

28/3

0/029/1

3/029/2

7/02

10/11

/02

10/25

/0211

/8/02

11/22

/0212/

6/02

12/20

/021/3

/03

1/17/0

31/3

1/032/1

4/032/2

8/03

DATE

MO

VE

ME

NT

IN (

INC

HE

S/D

AY

)

TN000084

TN000089

TN010095

TN010119

TN 80

TN 72

TN 97

TN 98

TN 101

TN 114

TN 115

TN 127

TN 144

TN 149

#3

#4

Page 142: Strategic Open Pit Mine Planning Course.pdf

BlastingBlasting

Use of less charges next to toe

Linedrillholes

Productionholes Face

Pre-splitting Line drilling

Page 143: Strategic Open Pit Mine Planning Course.pdf

SAFETY BERMCatch

Berm, ± 40 m. H13

BENCH

D5 BENCH

PUSHBACK

> 10 cm/dayStop push-back development

5 a 10 cm/dayOnly ore production stripping

2 a 5 cm/dayNormal

Displacement ratePUSHBACK DEVELOPMENT

Slide Management ExampleSlide Management Example

y = 63.213x - 2E+06

y = 16.016x - 597363

y = 8.7432x - 326060

y = 5.6082x - 209126

0

50

100

150

200

250

300

1/2/02 6/2/02 11/2/02 16/2/02 21/2/02

TIEMPO

DES

PLA

ZAM

IEN

TO (c

m)

Took outshovel

Access D5& H13 closed

Failure

Page 144: Strategic Open Pit Mine Planning Course.pdf

Contingency PlanningContingency Planning

l Provide multiple access to production facesl Maintain double access to working benches,

whenever possiblel Stockpile ore/rockl Design to prevent noses in the plan geometryl Provide for failure costs in scheduling and budgetingl Add lag times in production schedulingl Plan step-outs

Page 145: Strategic Open Pit Mine Planning Course.pdf

ConclusionsConclusions

l New Radar and Lidar based technologies applied to pit slope monitoring appears to be very promising in providing cost effective and accurate real time data .

l Accurate and reliable slope displacement information coupled with proper pit slope management practices has a potential to prevent unexpected catastrophic pit slope failures.

Page 146: Strategic Open Pit Mine Planning Course.pdf

Haul Road Design

Dr. Kadri Dagdelen

Colorado School of Mines

Sur

face

Min

e D

esig

n

Page 147: Strategic Open Pit Mine Planning Course.pdf

2

Sur

face

Min

e D

esig

n

Haul Road Design

• HAUL ROADS: During the life of the pit a haul road must be maintained for access.

• HAUL ROAD - SPIRAL SYSTEM: Haul road is arranged spirally along the perimeter walls of the pit.

Page 148: Strategic Open Pit Mine Planning Course.pdf

3

Sur

face

Min

e D

esig

n

Haul Road Design

• HAUL ROAD – SWITCH BACK SYSTEM: Zigzag pattern on one side of the pit.

• HAUL ROAD WIDTH: Function of capacity of the road and the size of the equipment. Haul road width must be considered in the overall pit design.

Page 149: Strategic Open Pit Mine Planning Course.pdf

4

Sur

face

Min

e D

esig

n

Haul Road Effect on Pit Limits

Page 150: Strategic Open Pit Mine Planning Course.pdf

5

Considerations for Haul Road Design

Sur

face

Min

e D

esig

n

• Visibility• Stopping distances• Vertical alignment• Horizontal alignment• Cross section• Runaway-vehicle safety

provisions

Page 151: Strategic Open Pit Mine Planning Course.pdf

6

Sight Distances and Stopping Distances

Sur

face

Min

e D

esig

n

• Vertical and horizontal curves designed considering sight distance and stopping distance

• Sight distance is the extent of peripheral area visible to the vehicle operator

• Sight distance must be sufficient to enable vehicle traveling at a given speed to stop before reaching a hazard

Page 152: Strategic Open Pit Mine Planning Course.pdf

7

Sight Distances and Stopping Distances

Sur

face

Min

e D

esig

n

• On vertical curves, road surface limits sight distance

• Unsafe conditions remedied by lengthening curve• On horizontal curves, sight distance limited by

adjacent berm dike, rock cuts, trees, etc; • Unsafe conditions remedied by laying back bank or

removing obstacles

Page 153: Strategic Open Pit Mine Planning Course.pdf

8

Sight Distance Diagrams

Sur

face

Min

e D

esig

n

Sight distance diagrams for horizontal and vertical curves(Kaufman and Ault)

Page 154: Strategic Open Pit Mine Planning Course.pdf

9

Stopping Distances

Sur

face

Min

e D

esig

n

• Stopping distances depend on truck breaking capabilities, road slope and vehicle velocity

• Stopping distance curves can be derived based on SAE service break maximum stopping distances

Page 155: Strategic Open Pit Mine Planning Course.pdf

10

Stopping Distance Characteristics

Sur

face

Min

e D

esig

n

For example, stopping distance characteristics of vehicles of 200,000 to 400,000 pounds GVW

(Kaufman and Ault)

Page 156: Strategic Open Pit Mine Planning Course.pdf

11

Stopping Distances

Sur

face

Min

e D

esig

n

• Prior to final road layout, manufacturers of vehicles that will use the road should be contacted to verify the service brake performance capabilities

Page 157: Strategic Open Pit Mine Planning Course.pdf

12

Vertical Alignment

Sur

face

Min

e D

esig

n

• Establishment of grades and vertical curves that allow adequate stopping distances on all segments of the haul road• Maximum sustained grades

• Reduction in grade significantly increases vehicle uphill speed• Reduction in grade decreases cycle time, fuel consumption, stress

on mechanical components and operating costs• Reduction in grade increases safe descent speeds, increasing

cycle time• The benefits of low grades offset by construction costs associated

with low grades

Page 158: Strategic Open Pit Mine Planning Course.pdf

13

Vehicle Performance Chart

Sur

face

Min

e D

esig

n

Page 159: Strategic Open Pit Mine Planning Course.pdf

14

Vehicle Retarder Chart

Sur

face

Min

e D

esig

n

Page 160: Strategic Open Pit Mine Planning Course.pdf

15

Vertical Alignment

Sur

face

Min

e D

esig

n

• Maximum sustained grades• Some states limit maximum grades to 15 to 20% and

sustained grades of 10%• Most authorities suggest 10% as the maximum safe

sustained grade limitation• Manufacturer studies show 8% grades result in the

lowest cycle time exclusive of construction consideration

Page 161: Strategic Open Pit Mine Planning Course.pdf

16

Vertical Alignment

Sur

face

Min

e D

esig

n

• Maximum sustained grades• Property boundaries, geology, topography, climate

must be considered on a case by case basis. • Lower operating costs must be balanced against higher

capital costs of low grades.• Truck simulators and mine planning studies over the

life of mine should be used to make the determination of the appropriate grades

Page 162: Strategic Open Pit Mine Planning Course.pdf

17

Vertical Curves

Sur

face

Min

e D

esig

n

• Vertical curves smooth transitions from one grade to another

• Minimum vertical curve lengths are based on eye height, object height, and algebraic difference in grade

Page 163: Strategic Open Pit Mine Planning Course.pdf

18

Stopping Distance vs. Vertical Curve

Sur

face

Min

e D

esig

n

For example, vertical curve controls 9 ft eye height (usually minimum height for articulated haulage trucks of 200,000 to 400,000 pound of GVW)

Page 164: Strategic Open Pit Mine Planning Course.pdf

19

Horizontal Alignment

Sur

face

Min

e D

esig

n

• Deals primarily with design of curves and considers previously discussed radius, width, and sight distance in addition tosuperelevation

• Cross slopes also should be considered in the design

Page 165: Strategic Open Pit Mine Planning Course.pdf

20

Curves, Superelevation, and Speed Limits

Sur

face

Min

e D

esig

n

• Superelevation grade recommendations vary but should be limited to 10% or less because of traction limitations

• Depending on magnitude of the side friction forces at low speed, different values are suggested for small radius curves

• Kaufman and Ault suggest .04-.06 fpf(basically the normal cross slope)

Page 166: Strategic Open Pit Mine Planning Course.pdf

21

Curves, Superelevation, and Speed Limits

Sur

face

Min

e D

esig

n

• CAT suggests higher slopes with traction cautions and 10% maximum caution

• Again, where ice, snow, and mud are a problem, there is a practical limit on the degree of superelevation

Page 167: Strategic Open Pit Mine Planning Course.pdf

22

Curve Superelevation

Sur

face

Min

e D

esig

n

(CAT)

Page 168: Strategic Open Pit Mine Planning Course.pdf

23

Recommended SuperelevationRates

Sur

face

Min

e D

esig

n

(Kaufman and Ault)

If superelevation is not used, speed limits should be set on curves.

Page 169: Strategic Open Pit Mine Planning Course.pdf

24

Curves, Superelevation, and Speed Limits

Sur

face

Min

e D

esig

n

• Centrifugal forces of vehicles on curves are counteracted by friction between tire an road and vehicle weight as a result of superelevation

• Theoretically, with superelevation, side friction factors would be zero and centrifugal force is balanced by the vehicle weight component

• To reduce tire wear, superelevation or speed limits on curves are required

Page 170: Strategic Open Pit Mine Planning Course.pdf

25

Combinations of Alignments

Sur

face

Min

e D

esig

n

• Avoid sharp horizontal curvature at or near the crest of a hill

• Avoid sharp horizontal curves near the bottom of sustained downgrades

• Avoid intersections near crest verticals and sharp horizontal curvatures

• Intersections should be made flat as possible• If passing allowed, grades should be constant and

long enough

Page 171: Strategic Open Pit Mine Planning Course.pdf

26

Cross Section

Sur

face

Min

e D

esig

n

• A stable road base is very important• Sufficiently rigid bearing material should be

used beneath the surface• Define the bearing capacity of the material

using the California Bearing Ratio (CBR)

Page 172: Strategic Open Pit Mine Planning Course.pdf

27

California Bearing Ratio

Sur

face

Min

e D

esig

n

Page 173: Strategic Open Pit Mine Planning Course.pdf

28

Subbase Construction

Sur

face

Min

e D

esig

n

Page 174: Strategic Open Pit Mine Planning Course.pdf

29

Sur

face

Min

e D

esig

n

Cross Slopes

• Cross slopes provide adequate drainage and range from ¼ to ½ inch drop per foot of width (approximately .02 to .04 foot per foot)

• Lower cross slopes used on smooth surfaces that dissipate water quickly and when ice or mud is a constant problem

Page 175: Strategic Open Pit Mine Planning Course.pdf

30

Sur

face

Min

e D

esig

n

Cross Slopes

• Higher cross slopes permit rapid drainage, reduce puddles and saturated sub-base, and are used on rough surfaces (gravel and crushed rock) or where mud and snow are not a problem

• High cross slopes can be particularly problematic with ice or snow on high grades (+5%)

Page 176: Strategic Open Pit Mine Planning Course.pdf

31

Sur

face

Min

e D

esig

n

Recommended Rate of Cross-Slope Change

(Kaufman and Ault)

Slope change should be gradual.

Page 177: Strategic Open Pit Mine Planning Course.pdf

32

Sur

face

Min

e D

esig

n

Width

• On straight or tangent segments, width depends on• Vehicle width• Number of lanes• Recommended vehicle clearance, which ranges

from 44 to 50% of vehicle width

Page 178: Strategic Open Pit Mine Planning Course.pdf

33

Sur

face

Min

e D

esig

n

Minimum Road Design Widths for Various Size Dump Trucks

(Couzens, SME Open Pit Planning and Design)

Page 179: Strategic Open Pit Mine Planning Course.pdf

34

Sur

face

Min

e D

esig

n

Typical Design Haul Road Width

(Couzens, SME Open Pit Planning and Design)

Typical design haul-road width for two-way traffic using 77.11-t (85-st) trucks

Page 180: Strategic Open Pit Mine Planning Course.pdf

35

Sur

face

Min

e D

esig

n

(Kaufman and Ault)

Typical Haulageway Sections

Page 181: Strategic Open Pit Mine Planning Course.pdf

36

Sur

face

Min

e D

esig

n

Width

• Berm height and width as a function of vehicle size and material type

• Ditch(es) added to basic recommendations• Runaway provisions may also add to width• Road wider on curves because of overhang• Minimum turning radius considered on

curves (should be exceeded)

Page 182: Strategic Open Pit Mine Planning Course.pdf

37

Sur

face

Min

e D

esig

n

Haulageway Widths on Curves

Page 183: Strategic Open Pit Mine Planning Course.pdf

38

Sur

face

Min

e D

esig

n

Safety Provisions - Berms

• Triangular or trapezoidal made by using local material• Stands at natural angle of repose of construction

material• Redirects vehicle onto roadway• Minimum height at rolling radius of tire

Page 184: Strategic Open Pit Mine Planning Course.pdf

39

Sur

face

Min

e D

esig

n

Berms

• Larger boulders backed with earthen material• Near vertical face deflects vehicle for slight

angles of incidence• Problems with damage and injury and

availability of boulders• Minimum height of boulder at height of tire

allowing chassis impact

Page 185: Strategic Open Pit Mine Planning Course.pdf

40

Sur

face

Min

e D

esig

n

Runaway Provisions

• With adverse grades some safety provision should be integrated to prevent runaway vehicles

• Primary design consideration is required spacing between protective provisions

• Driver must reach a safety provision before truck traveling too fast to maneuver

• Maximum permissible speed depends on truck design conditions and operator

Page 186: Strategic Open Pit Mine Planning Course.pdf

41

Sur

face

Min

e D

esig

n

Runaway Provisions

• Maximum permissible speed, equivalent downgrade, and speed at break failure determine distance between runaway truck safety provisions

• For example, at an equivalent downgrade of 5% and a maximum speed of 40 mph,

Speed at Failure 10 mph 20 mphProvision Spacing 1,000 ft 800 ft

(Kaufman and Ault)

Page 187: Strategic Open Pit Mine Planning Course.pdf

42

Sur

face

Min

e D

esig

n

Runaway Precautions

(Atkinson SME Handbook)

Page 188: Strategic Open Pit Mine Planning Course.pdf

43

Sur

face

Min

e D

esig

n

Median Runaway-Vehicle Provision Berms

• Vehicle straddles collision berm and rides vehicle to stop

• Made of unconsolidated-screened fines• Critical design aspects spacing between

berms and height of berm• Height governed by height of undercarriage

and wheel track governed by largest vehicle

Page 189: Strategic Open Pit Mine Planning Course.pdf

44

Sur

face

Min

e D

esig

n

Median Runaway-Vehicle Provision Berms

• Requires maintenance in freezing conditions • Agitation to prevent damage to vehicle• May cover berm in high rainfall areas

Page 190: Strategic Open Pit Mine Planning Course.pdf

45

Sur

face

Min

e D

esig

n

Escape Lanes

• Good tool for stopping runaway but expensive to construct

• Entrance from road is important; spacing, horizontal, vertical curve and superelevationare all considered in design

• Deceleration mainly by adverse grade and high rolling resistance material

Page 191: Strategic Open Pit Mine Planning Course.pdf

46

Sur

face

Min

e D

esig

n

Escape Lanes

• Length a function of grade and speed at entrance and rolling resistance

• Stopping by level section median berm, sand or gravel or mud pits, road bumps or manual steering

Page 192: Strategic Open Pit Mine Planning Course.pdf

47

Sur

face

Min

e D

esig

n

Escape Lanes

Page 193: Strategic Open Pit Mine Planning Course.pdf

48

Sur

face

Min

e D

esig

n

Maintenance

• The road surface is deformed by the constant pounding of haulage vehicles.

• A good road maintenance program is necessary for safety and economics.

Page 194: Strategic Open Pit Mine Planning Course.pdf

49

Sur

face

Min

e D

esig

n

Safety Considerations

• Dust, potholes, ruts, depressions, bumps, and other conditions can impede vehicular control.

Page 195: Strategic Open Pit Mine Planning Course.pdf

50

Sur

face

Min

e D

esig

n

Economic Considerations

• The wear on every component is increased when a vehicle travels over a rough surface.

• If the vehicle brakes constantly, unnecessary lining wear occurs as well.

Page 196: Strategic Open Pit Mine Planning Course.pdf

51

Sur

face

Min

e D

esig

n

Dust Control

• Dust may infiltrate brakes, air filters, hydraulic lifts, and other components of machinery.

• The abrasive effect of dust will result in costly cleaning or replacement of these items.

Page 197: Strategic Open Pit Mine Planning Course.pdf

52

Sur

face

Min

e D

esig

n

Deterioration Factors

• Weather• Vehicles follow a

similar path• Spillage

Page 198: Strategic Open Pit Mine Planning Course.pdf

53

Sur

face

Min

e D

esig

n

Motor Graders

• A motor grader should be used to maintain cross slopes, remove spills, and to fill and smooth surface depressions as they occur.

Page 199: Strategic Open Pit Mine Planning Course.pdf

54

Sur

face

Min

e D

esig

n

Road Drainage

• To avoid overflow, roadside ditches and culverts should be periodically cleaned.

• Avoid erosion or saturation of subbase materials.

Page 200: Strategic Open Pit Mine Planning Course.pdf

Haul Road Design

Open Pit Contour Maps

Dr. Kadri Dagdelen

Source: Hustrulid and Kuchta

Sur

face

Min

e D

esig

n

Page 201: Strategic Open Pit Mine Planning Course.pdf

2

Sur

face

Min

e D

esig

n

Example of Mapping Procedure

Page 202: Strategic Open Pit Mine Planning Course.pdf

3

Sur

face

Min

e D

esig

n

Plan View of a Portion of the Open Pit

Crests denoted by dashed lines and toes by solid lines.

Page 203: Strategic Open Pit Mine Planning Course.pdf

4

Sur

face

Min

e D

esig

n

Example of Mapping Procedure

Page 204: Strategic Open Pit Mine Planning Course.pdf

5

Sur

face

Min

e D

esig

n

Midbench Elevation

Page 205: Strategic Open Pit Mine Planning Course.pdf

6

Sur

face

Min

e D

esig

n

Plan View of Midbench Elevation

Page 206: Strategic Open Pit Mine Planning Course.pdf

7

Sur

face

Min

e D

esig

n

Map Based on Midbench Contours

Page 207: Strategic Open Pit Mine Planning Course.pdf

8

Sur

face

Min

e D

esig

n

Procedure to Convert Midbench to Toe and Crest Contours

Page 208: Strategic Open Pit Mine Planning Course.pdf

9

Sur

face

Min

e D

esig

n

Representation of Crests and Toes

Page 209: Strategic Open Pit Mine Planning Course.pdf

10

Sur

face

Min

e D

esig

n

Designing a Spiral Ramp Inside the Wall

Page 210: Strategic Open Pit Mine Planning Course.pdf

11

Sur

face

Min

e D

esig

n

Completing the new crest lines

Page 211: Strategic Open Pit Mine Planning Course.pdf

12

Sur

face

Min

e D

esig

n

Pit Layout Including Ramp

Page 212: Strategic Open Pit Mine Planning Course.pdf

13

Sur

face

Min

e D

esig

n

Design of a Spiral Ramp Outside the Wall

Page 213: Strategic Open Pit Mine Planning Course.pdf

14

Sur

face

Min

e D

esig

n

Pit Layout Including Ramp

Page 214: Strategic Open Pit Mine Planning Course.pdf

15

Sur

face

Min

e D

esig

n

Design of a Switchback

Page 215: Strategic Open Pit Mine Planning Course.pdf

16

Sur

face

Min

e D

esig

n

Design of a Switchback

Page 216: Strategic Open Pit Mine Planning Course.pdf

17

Sur

face

Min

e D

esig

n

Design of a Switchback

Page 217: Strategic Open Pit Mine Planning Course.pdf

18

Sur

face

Min

e D

esig

n

Pit Layout Including Ramp

Page 218: Strategic Open Pit Mine Planning Course.pdf

19

Sur

face

Min

e D

esig

n

Example of Two Switchbacks

Page 219: Strategic Open Pit Mine Planning Course.pdf

20

Sur

face

Min

e D

esig

n

Plan and Section Views of Pit Without Ramp

Page 220: Strategic Open Pit Mine Planning Course.pdf

21

Sur

face

Min

e D

esig

n

Plan and Section Views of Pit With Ramp

Page 221: Strategic Open Pit Mine Planning Course.pdf

22

Sur

face

Min

e D

esig

n

Road Volume in the Ramp

Page 222: Strategic Open Pit Mine Planning Course.pdf

1

Block Modeling and Ore Reserves Estimation

Dr. Kadri Dagdelen

Sur

face

Min

e D

esig

n

Page 223: Strategic Open Pit Mine Planning Course.pdf

2

Basic Block Model Information

• Topography Data • Drill Data• Sampling• Assays

Sur

face

Min

e D

esig

n

Page 224: Strategic Open Pit Mine Planning Course.pdf

3

Topography Data

3D Display (Color Coded Elevations)

Sur

face

Min

e D

esig

n

Page 225: Strategic Open Pit Mine Planning Course.pdf

4

Drill Data

Drill Hole Data Sources

•Collar Coordinates•Geologic Logs•Down Hole Surveys•Lab Tests

Sur

face

Min

e D

esig

n

Page 226: Strategic Open Pit Mine Planning Course.pdf

5

Samplings

Sampling Data

•Rock Types•Alteration Types•Metal Grades•Attributes

Sur

face

Min

e D

esig

n

Page 227: Strategic Open Pit Mine Planning Course.pdf

6

Samplings (Cont.)

Data Collections

Sur

face

Min

e D

esig

n

Page 228: Strategic Open Pit Mine Planning Course.pdf

7

Assays

Assay Data for Cu and Mo

Multiple Cutoffs

Rock Types

AlterationsSur

face

Min

e D

esig

n

Page 229: Strategic Open Pit Mine Planning Course.pdf

8

Geological Interpretation

Section View Showing Topography and Alteration Types

Sur

face

Min

e D

esig

n

Page 230: Strategic Open Pit Mine Planning Course.pdf

9

Geological Interpretation

Boundaries for rock types

Sur

face

Min

e D

esig

n

Page 231: Strategic Open Pit Mine Planning Course.pdf

10

Geological Interpretation

Color Filled Display for Alteration Types

Sur

face

Min

e D

esig

n

Page 232: Strategic Open Pit Mine Planning Course.pdf

11

3D Geological View

3D Display of Alteration Type Solids

(With Drill Hole Piercing Points)

Sur

face

Min

e D

esig

n

Page 233: Strategic Open Pit Mine Planning Course.pdf

12

Composites

Composited Grade Data with Corresponding Assay Interval Data

Sur

face

Min

e D

esig

n

Page 234: Strategic Open Pit Mine Planning Course.pdf

13

3D Block Models

3D View of the Block Models

Sur

face

Min

e D

esig

n

Page 235: Strategic Open Pit Mine Planning Course.pdf

14

Block Estimation

Kriging - Geological Interpolation Technique for Ore Reserve Estimation

Sur

face

Min

e D

esig

n

Page 236: Strategic Open Pit Mine Planning Course.pdf

15

Block Values

Block by Block Profit Values in Association with Block Grade Data and Alteration Type Boundaries

Sur

face

Min

e D

esig

n

Page 237: Strategic Open Pit Mine Planning Course.pdf

16

Block Models

Interpolated Grades from Drill Hole Data

Sur

face

Min

e D

esig

n

Page 238: Strategic Open Pit Mine Planning Course.pdf

17

Ore Reserve Estimation

Interpolated Grades from Drill Hole Data

Sur

face

Min

e D

esig

n

Page 239: Strategic Open Pit Mine Planning Course.pdf

18

Economic Pit Limits

Economic Pit Limits for Different Economic Scenarios

Sur

face

Min

e D

esig

n

Page 240: Strategic Open Pit Mine Planning Course.pdf

19

3D View of Economic Pit Limits

3D View of Economic Pit Limits for Different Economic Scenarios

Sur

face

Min

e D

esig

n

Page 241: Strategic Open Pit Mine Planning Course.pdf

20

Mine Planning Application(Open Pit Mine)

Yearly Maps for the Open Pit Mine Scheduling

Sur

face

Min

e D

esig

n

Page 242: Strategic Open Pit Mine Planning Course.pdf

21

Geologic Resource Modeling Techniques

• Exploratory Data Analysis• Variogram Analysis• Search Strategies• Simple Kriging, Ordinary Kriging, Indicator

Kriging, Co-Kriging• Cross Validation• Uncertainty and Risk Evaluation

Sur

face

Min

e D

esig

n

Page 243: Strategic Open Pit Mine Planning Course.pdf

22

Frequency and Cumulative Frequency Plots

•Classical Statistics•Data Posting and Display•Histograms •Cumulative Histograms•Probability Plots

Sur

face

Min

e D

esig

n

Page 244: Strategic Open Pit Mine Planning Course.pdf

23

Inverse Distance Technique

• In general, ∑∑=

=

=n

iin

ip

i

pi v

d

dv

1

1

1

1

ˆ

• Inverse distance technique is the simplest interpolation method.

• Give more weight to the closest samples, and less to those that are farthest away.

∑=

= n

ipi

pi

i

d

dw

1

1

1

∑=

=n

iiivwv

1

ˆ 11

=∑=

n

iiwS

urfa

ce M

ine

Des

ign

Page 245: Strategic Open Pit Mine Planning Course.pdf

24

Inverse Distance Technique (pg257)

v1

v2

d1

d244

1

1

1

34

1

1

1

24

1

1

1

14

1

1

1

2

24

2

23

2

22

2

21ˆ vvvvv

id

d

id

d

id

d

id

d

iiii∑∑∑∑

====

+++=

v̂ Inverse Distance Square

• We can make the weights inversely proportional to any power of the distance.

• If p=2, it is called Inverse Distance Square.

d3

d4

v3

v4

Sur

face

Min

e D

esig

n

Page 246: Strategic Open Pit Mine Planning Course.pdf

25

Inverse Distance Square Example

V1=0.2

V2=0.3

d1=1d2=2

• Estimate the unknown point by using the Inverse Distance Square technique

d3=4

V3=0.5

v1= 0.2 d1 =1

v2= 0.3 d2 =2

v3= 0.5 d3 =4

?ˆ =v

Sur

face

Min

e D

esig

n

Page 247: Strategic Open Pit Mine Planning Course.pdf

26

Inverse Distance Square Example

• First of all, calculate the weights w1, w2, w3

21161

1621

241

221

211

211

1 ==++

=w

214

162141

241

221

211

221

2 ==++

=w

211

1621161

241

221

211

241

3 ==++

=w Note:1321 =++ www

Sur

face

Min

e D

esig

n

Page 248: Strategic Open Pit Mine Planning Course.pdf

27

Inverse Distance Square Example

• Then, calculate

233.05.0211

3.0214

2.02116ˆ =×+×+×=v

Sur

face

Min

e D

esig

n

Page 249: Strategic Open Pit Mine Planning Course.pdf

28

Estimation Error

• Error estimation between estimation (Exploration data) and true value (Blasthole data).

Error = Estimated Grade – True Grade

e.g., Estimation Error for Block 1 = 0.463 – 0.433 = 0.031

Sur

face

Min

e D

esig

n

Page 250: Strategic Open Pit Mine Planning Course.pdf

29

Histogram of Errors

Sur

face

Min

e D

esig

n

Page 251: Strategic Open Pit Mine Planning Course.pdf

30

Scatter Graph

True grades agai n s t E s t i mated grades

0.00

0.10

0.20

0.30

0.40

0.50

0.60

0.70

0.80

0.90

0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80 0.90True (%)

Est

imat

ed (

%)

Sur

face

Min

e D

esig

n

Page 252: Strategic Open Pit Mine Planning Course.pdf

Surface Mine DesignMNGN312 - MNGN512

Sur

face

Min

e D

esig

n

Lecture 5September 14, 2004

InstructorDr. Kadri Dagdelen

Page 253: Strategic Open Pit Mine Planning Course.pdf

2

Geologic Block Modeling

• Assume that a geologic model to be created by using 75ft by 75ft blocks from the exploration data set. Estimate the grade of these blocks using the inverse distance square (IDS) technique.

• Use rectangular search neighborhood of 37.5ft x 37.5ft.

• Assume that the center of the block represents the block grade.

Sur

face

Min

e D

esig

n

Page 254: Strategic Open Pit Mine Planning Course.pdf

3

Geologic Block Modeling

• Estimate the grade of the block (block size 75ft x 75ft) for exploration data set.

75ft

75ft

1̂v2v̂

Estimate the center point

Sur

face

Min

e D

esig

n

Page 255: Strategic Open Pit Mine Planning Course.pdf

4

Geologic Block Modeling

• Rectangular search neighborhood of 37.5ft x 37.5ft.75

ft 37.5ft

37.5ft 37.5ft

37.5ft

Use all the exploration holes within a given block (For this block, use 3 exploration samples)

75ft

Sur

face

Min

e D

esig

n

Page 256: Strategic Open Pit Mine Planning Course.pdf

5

Inverse Distance Technique

• In general,

∑∑=

=

=n

iin

ip

i

pi v

d

dv

1

1

1

1

ˆ

• Inverse distance technique is the simplest interpolation method.

• Give more weight to the closest samples, and less to those that are farthest away.

∑=

= n

ipi

pi

i

d

dw

1

1

1

∑=

=n

iiivwv

1

ˆ 11

=∑=

n

iiw

Unknown pointSampling points

Weights

Sur

face

Min

e D

esig

n

Page 257: Strategic Open Pit Mine Planning Course.pdf

6

Inverse Distance Technique

v1

v2

d1

d244

1

1

1

34

1

1

1

24

1

1

1

14

1

1

1

2

24

2

23

2

22

2

21ˆ vvvvv

id

d

id

d

id

d

id

d

iiii∑∑∑∑

====

+++=

v̂ Inverse Distance Square

• We can make the weights inversely proportional to any power of the distance.

• If p=2, it is called Inverse Distance Square (IDS).

d3

d4

v3

v4

Sur

face

Min

e D

esig

n

Page 258: Strategic Open Pit Mine Planning Course.pdf

7

Inverse Distance Square Example

V1=0.2

V2=0.3

d1=1d2=2

• Estimate the unknown point by using the Inverse Distance Square technique

d3=4

V3=0.5

v1= 0.2 d1 =1

v2= 0.3 d2 =2

v3= 0.5 d3 =4

?ˆ =v

Sur

face

Min

e D

esig

n

Page 259: Strategic Open Pit Mine Planning Course.pdf

8

Inverse Distance Square Example

• First of all, calculate the weights w1, w2, w3

21161

1621

241

221

211

211

1 ==++

=w

214

162141

241

221

211

221

2 ==++

=w

211

1621161

241

221

211

241

3 ==++

=w

Note:

121

1416321 =

++=++ www

• Then, calculate

233.05.0211

3.0214

2.02116ˆ =×+×+×=v

Sur

face

Min

e D

esig

n

Page 260: Strategic Open Pit Mine Planning Course.pdf

9

Geologic Block Modeling

25

25

g1

d1

36.352525 221 =+=d

Sur

face

Min

e D

esig

n

Page 261: Strategic Open Pit Mine Planning Course.pdf

10

Geologic Block Modeling

0032.00008.0

∑=

n

i id12

1

Block1 X Y vi x dist y dist di 1/di2 wi wi*viCentered on 12.5 12.5 0.42 25 25 35.35534 0.0008 0.25 0.105

(X=37.5, Y=37.5) 62.5 12.5 0.24 -25 25 35.35534 0.0008 0.25 0.0637.5 62.5 0.41 0 -25 25 0.0016 0.5 0.205

0.0032 1 0.37(Estimated Grade)

Sur

face

Min

e D

esig

n

Page 262: Strategic Open Pit Mine Planning Course.pdf

11

Geologic Block Modeling

• Using the estimated block values, one normally determines the overall estimated bench average grade of the copper ore at some cutoff, i.e, 0.7%Cu.

Sur

face

Min

e D

esig

n

Page 263: Strategic Open Pit Mine Planning Course.pdf

12

Geologic Block ModelReconciliation

• Determine the average grade of 75ft by 75ft grid blocks for the blasthole data set (blasthole2004.txt) by averaging the grades of 9 blast holes that fall within each block.

Block 1 Grade

= (0.42+0.35+0.24+0.33+ … + 0.46) / 9

=0.35

Sur

face

Min

e D

esig

n

Page 264: Strategic Open Pit Mine Planning Course.pdf

13

Geologic Block ModelReconciliation

• Error estimation between estimation (Exploration data) and true value (Blasthole data).

Error = Estimated Grade – True Grade

e.g., Estimation Error for Block 1

= 0.37 – 0.35 = 0.02

Sur

face

Min

e D

esig

n

Page 265: Strategic Open Pit Mine Planning Course.pdf

14

Geologic Block ModelReconciliation

• Histogram of Error (Example of 100ft x 100ft estimation)

Histogram of Estimation Errors (Estimation - True)

0

0.5

1

1.5

2

2.5

3

3.5

-0.2 -0.15 -0.1 -0.05 0 0.05 0.1 0.15 0.2 0.25 More

Bin

Fre

quen

cy

0.00%

10.00%

20.00%

30.00%

40.00%

50.00%

60.00%

70.00%

80.00%

90.00%

100.00%

Frequency

Cumulative %

Bin FrequencyCumulative %-0.2 0 0.00%

-0.15 0 0.00%-0.1 1 11.11%

-0.05 1 22.22%0 3 55.56%

0.05 3 88.89%0.1 0 88.89%

0.15 0 88.89%0.2 1 100.00%

0.25 0 100.00%More 0 100.00%

Sur

face

Min

e D

esig

n

Page 266: Strategic Open Pit Mine Planning Course.pdf

15

Geologic Block ModelReconciliation

• Scatter Graph (Example of 100ft x 100ft estimation)

True grades agai n s t E s t i mated grades

0.00

0.10

0.20

0.30

0.40

0.50

0.60

0.70

0.80

0.90

0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80 0.90True (%)

Est

imat

ed (

%)

Draw a diagonal line (y=x) to show perfect estimation line.

Sur

face

Min

e D

esig

n

Page 267: Strategic Open Pit Mine Planning Course.pdf

16

Univariate Distribution of Errors

• Error = Estimated Value - True Value• We also refer to these error as residuals.• If error is positive, then we have overestimated the true;

if error is negative, then we have underestimated the true.

If m=0, then Unbiased Estimates

Overestimates and underestimates are balanced.

We typically prefer to have a symmetric distribution.

Sur

face

Min

e D

esig

n

Page 268: Strategic Open Pit Mine Planning Course.pdf

17

Univariate Distribution of Errors

• We would like to see the error distribution has small spread.

• Both distributions are centered on 0 and are symmetric.• The distribution shown in a), however, has error that span

a greater range.• Therefore, b) is better estimation than a).

a) b)

Sur

face

Min

e D

esig

n

Page 269: Strategic Open Pit Mine Planning Course.pdf

18

Over and Under Estimation

• a) Negative mean: A general tendency towards the underestimation.

• b) Positive mean: A general tendency towards the overestimation.

a) b)

Sur

face

Min

e D

esig

n

Page 270: Strategic Open Pit Mine Planning Course.pdf

19

Scatter Diagrams in EstimationE

stim

atio

n

True

Good Estimation

Est

imat

ion

True

Over Estimation at High Grade

Est

imat

ion

True

Under Estimation at Low Grade

Good Estimation: Falling closer to diagonal on which perfect estimates would plot.S

urfa

ce M

ine

Des

ign

Page 271: Strategic Open Pit Mine Planning Course.pdf

20

Scatter Diagrams in EstimationE

stim

atio

n

True

Over Estimation at Low Grade

Est

imat

ion

True

Under Estimation at Low Grade

Sur

face

Min

e D

esig

n

Page 272: Strategic Open Pit Mine Planning Course.pdf

1

Floating Cone Algorithm

Dr. Kadri Dagdelen

Sur

face

Min

e D

esig

n

Page 273: Strategic Open Pit Mine Planning Course.pdf

2

Basic Procedure

Sur

face

Min

e D

esig

n

Top

-1 +1 -1 -1 -1

-1 -1 +3 -1 -1

BottomLeft Right

-1 -1

-1 -1 -1 -1

Heuristic procedure

Page 274: Strategic Open Pit Mine Planning Course.pdf

3

Floating Cone Steps

Sur

face

Min

e D

esig

n

• The cone is floated from left to right along the top row of blocks in the section. If there is a positive block it is removed.

• Move to the second row. Start from the left and search for the first positive block. If the sum of all blocks falling within the cone is positive, the blocks are removed (mined).

• Follow the floating cone process moving from left to right and top to bottom of the section until no more blocks can be removed. Then go back to the top again and repeat the process for a second iteration. If during a given iteration no positive blocks can be mined, stop.

• The profitability of the mined area can be found by adding the values of the blocks that are to be removed.

• Overall stripping ration can be determined by dividing the number of positive blocks by the total number of negative blocks.

Page 275: Strategic Open Pit Mine Planning Course.pdf

4

Example

Sur

face

Min

e D

esig

n

-1 -1 -1 -1 -1 +1 -1 Ore

-2 -2 +4 -2 -2

+7 +1 -3 Waste

Initial Block Model

Page 276: Strategic Open Pit Mine Planning Course.pdf

5

Example

Sur

face

Min

e D

esig

n

-1 -1 -1 -1 -1 +1 -1 Ore

-2 -2 +4 -2 -2 Waste

+7 +1 -3 Mined

Step 1

Page 277: Strategic Open Pit Mine Planning Course.pdf

6

Example

Sur

face

Min

e D

esig

n

-1 -1 -1 -1 -1 +1 -1 Ore

-2 -2 +4 -2 -2 Waste

+7 +1 -3 Mined

Step 2

Page 278: Strategic Open Pit Mine Planning Course.pdf

7

Example

Sur

face

Min

e D

esig

n

-1 -1 -1 -1 -1 +1 -1 Ore

-2 -2 +4 -2 -2 Waste

+7 +1 -3 Mined

Step 3

Page 279: Strategic Open Pit Mine Planning Course.pdf

8

Example

Sur

face

Min

e D

esig

n

-1

-2 -2

+1 -3

Final Pit

Page 280: Strategic Open Pit Mine Planning Course.pdf

9

ShortcomingsMissing Combinations of Profitable Blocks

Sur

face

Min

e D

esig

n

-1 -1 -1 -1 -1 -1 -1 Ore

-2 -2 -2 -2 -2

+10 -3 +10 Waste

Initial Block Model

Page 281: Strategic Open Pit Mine Planning Course.pdf

10

Sur

face

Min

e D

esig

n

Step 1

-1 -1 -1 -1 -1 -1 -1 Ore

-2 -2 -2 -2 -2 Waste

+10 -3 +10 Considered but rejected

ShortcomingsMissing Combinations of Profitable Blocks

Page 282: Strategic Open Pit Mine Planning Course.pdf

11

Sur

face

Min

e D

esig

n

Step 2

-1 -1 -1 -1 -1 -1 -1 Ore

-2 -2 -2 -2 -2 Waste

+10 -3 +10 Considered but rejected

There are no blocks to be mined – wrong solution

ShortcomingsMissing Combinations of Profitable Blocks

Page 283: Strategic Open Pit Mine Planning Course.pdf

12

Sur

face

Min

e D

esig

n

Correct solution

-1 -1 -1 -1 -1 -1 -1 Ore

-2 -2 -2 -2 -2 Waste

+10 -3 +10 Mined (Correct solution)

-3

Final Pit

ShortcomingsMissing Combinations of Profitable Blocks

Page 284: Strategic Open Pit Mine Planning Course.pdf

13

ShortcomingsOver-mining

Sur

face

Min

e D

esig

n

-1 -1 -1 -1 -1 Ore

+5 -2 -2

+5 Waste

Initial Block Model

Page 285: Strategic Open Pit Mine Planning Course.pdf

14

ShortcomingsOver-mining

Sur

face

Min

e D

esig

n

First block analyzed

-1 -1 -1 -1 -1 Ore

+5 -2 -2 Waste

+5 Mined

The search process was started from bottom to top.

Everything is mined out.

Page 286: Strategic Open Pit Mine Planning Course.pdf

15

ShortcomingsOver-mining

Sur

face

Min

e D

esig

n

Correct solution

-1 -1 -1 -1 -1 Ore

+5 -2 -2 Waste

+5 Mined

-1 -1

-2 -2

+5

Final Pit

Page 287: Strategic Open Pit Mine Planning Course.pdf

16

ShortcomingsCombination of problems

Sur

face

Min

e D

esig

n

-1 -1 -4 -1 -1 Ore

+5 -4 +5

+3 Waste

Initial Block Model

Page 288: Strategic Open Pit Mine Planning Course.pdf

17

ShortcomingsCombination of problems

Sur

face

Min

e D

esig

n

First Step

-1 -1 -4 -1 -1 Ore

+5 -4 +5 Waste

+3 Considered but rejected

Page 289: Strategic Open Pit Mine Planning Course.pdf

18

ShortcomingsCombination of problems

Sur

face

Min

e D

esig

n

Second Step

-1 -1 -4 -1 -1 Ore

+5 -4 +5 Waste

+3 Considered but rejected

Page 290: Strategic Open Pit Mine Planning Course.pdf

19

ShortcomingsCombination of problems

Sur

face

Min

e D

esig

n

Wrong Solution

-1 -1 -4 -1 -1 Ore

+5 -4 +5 Waste

+3 Mined

Everything is mined out.

Page 291: Strategic Open Pit Mine Planning Course.pdf

20

ShortcomingsCombination of problems

Sur

face

Min

e D

esig

n

Correct Solution

-1 -1 -4 -1 -1 Ore

+5 -4 +5 Waste

+3 Mined

-4

+3

Final Pit

Page 292: Strategic Open Pit Mine Planning Course.pdf

21

ExampleInitial Data

Sur

face

Min

e D

esig

n

% recovery through mill and smelter 90.00%Value of recovered copper $1.00 per lbStripping and haulage to dump (level 1) $0.50 per tonMining and transportation to plant level $0.80 per tonHaulage cost increase per ton per bench $0.10 per ton/benchProcessing, smelting and refining $1.20 per tonGeneral overhead, administration, etc. $1.20 per tonUltimate Pit Slope 1:1

Page 293: Strategic Open Pit Mine Planning Course.pdf

22

ExampleGeologic Model

Sur

face

Min

e D

esig

n

0.00 1.15 0.08 0.05 0.00 0.00 0.05

0.00 1.25 1.15 1.13 0.00

1.13 1.15 0.50

Copper Grades (%)

Page 294: Strategic Open Pit Mine Planning Course.pdf

23

ExampleBlock Values

Sur

face

Min

e D

esig

n

P = Price

s = Sales Cost

c = Processing Cost

y = Recovery

m = Mining Cost

gB = Block Grade

BV = Block Value

mcygsPBV B −−−= **)(Ore Block:

Waste Block:

mBV −=

Page 295: Strategic Open Pit Mine Planning Course.pdf

24

ExampleEconomic Model

Sur

face

Min

e D

esig

n

-0.50 17.50 -0.50 -0.50 -0.50 -0.50 -0.50

-0.60 19.20 17.40 17.04 -0.60

16.94 17.30 -0.70

Value per block ($/ton)

Page 296: Strategic Open Pit Mine Planning Course.pdf

25

ExampleEconomic Model

Sur

face

Min

e D

esig

n

-0.50 17.50 -0.50 -0.50 -0.50 -0.50 -0.50

-0.60 19.20 17.40 17.04 -0.60

16.94 17.30 -0.70

Value per block ($/ton)

5.178.04.29.0*2000*100/15.1*)01( =−−−=BV

Page 297: Strategic Open Pit Mine Planning Course.pdf

26

ExampleEconomic Model

Sur

face

Min

e D

esig

n

-0.50 17.50 -0.50 -0.50 -0.50 -0.50 -0.50

-0.60 19.20 17.40 17.04 -0.60

16.94 17.30 -0.70

Value per block ($/ton)

2.38.04.29.0*2000*100/0.0*)01()/($ −=−−−=tonBV If mined as ore

6.0)/($ −=tonBV If mined as waste

Page 298: Strategic Open Pit Mine Planning Course.pdf

27

ExampleEconomic Model

Sur

face

Min

e D

esig

n

Value per block ($/ton)Values rounded to the nearest $

-1 18 -1 -1 -1 -1 -1

-1 19 17 17 -1

17 17 -1

Page 299: Strategic Open Pit Mine Planning Course.pdf

28

ExampleFloating Cone Algorithm

Sur

face

Min

e D

esig

n

1st Increment

-1 18 -1 -1 -1 -1 -1

-1 19 17 17 -1

17 17 -1

1

Page 300: Strategic Open Pit Mine Planning Course.pdf

29

ExampleFloating Cone Algorithm

Sur

face

Min

e D

esig

n

2nd Increment

-1 18 -1 -1 -1 -1 -1

-1 19 17 17 -1

17 17 -1

1 22

2

Page 301: Strategic Open Pit Mine Planning Course.pdf

30

ExampleFloating Cone Algorithm

Sur

face

Min

e D

esig

n

3rd Increment

-1 18 -1 -1 -1 -1 -1

-1 19 17 17 -1

17 17 -1

2 2

2

1 3

3

Page 302: Strategic Open Pit Mine Planning Course.pdf

31

ExampleFloating Cone Algorithm

Sur

face

Min

e D

esig

n

4th Increment

-1 18 -1 -1 -1 -1 -1

-1 19 17 17 -1

17 17 -1

3

3

1 2 2

2

4

4

Page 303: Strategic Open Pit Mine Planning Course.pdf

32

ExampleFloating Cone Algorithm

Sur

face

Min

e D

esig

n

5th Increment

-1 18 -1 -1 -1 -1 -1

-1 19 17 17 -1

17 17 -1

3

3

1 2 2

2

4

4

5

5

5

Page 304: Strategic Open Pit Mine Planning Course.pdf

33

ExampleFloating Cone Algorithm

Sur

face

Min

e D

esig

n

6th Increment

-1 18 -1 -1 -1 -1 -1

-1 19 17 17 -1

17 17 -1

3

3

1 2 2

2

4

4

5

5

5 6

Page 305: Strategic Open Pit Mine Planning Course.pdf

34

ExampleFloating Cone Algorithm

Sur

face

Min

e D

esig

n

Ultimate Pit Limit

-1

-1

-1

Page 306: Strategic Open Pit Mine Planning Course.pdf

35

ExampleTotal Economic Value

Sur

face

Min

e D

esig

n

Value Per block considering:

Tonnage/block = 10,000 tons

-5,000 175,000 -5,000 -5,000 -5,000 -5,000

-6,000 192,000 174,000 170,400

169,400 173,000

Page 307: Strategic Open Pit Mine Planning Course.pdf

36

ExamplePit Reserves

Sur

face

Min

e D

esig

n

Bench Ore tons Waste tons S.R. $

1 10,000 50,000 5.00 150,0002 30,000 10,000 0.33 530,4003 20,000 0 0.00 342,400

Total 60,000 60,000 1.00 1,022,800

Page 308: Strategic Open Pit Mine Planning Course.pdf

1

Manual Pit Design

Dr. Kadri Dagdelen

Sur

face

Min

e D

esig

n

Page 309: Strategic Open Pit Mine Planning Course.pdf

2

Manual Pit DesignStripping Ratio

Sur

face

Min

e D

esig

n

)/($)/($Pr)/($covRe).(.

tonCostStrippingtonCostoductionTotaltonValueeredBreakevenRS −=

)/($)/($)/($

tonCostStrippingtonCostMiningSurfacetonCostMiningUG

BreakevendUndergrounorSurface−

=

1:58.6)/66.0$

/70.0$/04.5$ =−=tonwaste

tonoretonoreBreakevendUndergrounorSurface

Page 310: Strategic Open Pit Mine Planning Course.pdf

3

Manual Pit DesignExample

Sur

face

Min

e D

esig

n

Ore Grade (%Cu) 0.90 0.85 0.75 0.70 0.65 0.50 0.40

Conc. Recovery (%) 0.900 0.900 0.900 0.900 0.900 0.900 0.900Smelt. Recovery (%) 0.980 0.980 0.980 0.980 0.980 0.980 0.980Ref. Recovery (%) 0.990 0.990 0.990 0.990 0.990 0.990 0.990

Total Recovery (%) 0.873 0.873 0.873 0.873 0.873 0.873 0.873

Recovered Quantity (lb/ton) 15.7 14.8 13.1 12.2 11.3 8.7 7.0

Costs per ton

Finance 0.62 0.62 0.62 0.62 0.62 0.62 0.62Mining 0.70 0.70 0.70 0.70 0.70 0.70 0.70Concentration 2.68 2.68 2.68 2.68 2.68 2.68 2.68Smelter 1.70 1.48 1.38 1.29 1.21 1.19 1.18Refining 1.80 1.57 1.36 1.27 1.20 1.16 1.12

Total cost ($/ton) 7.50 7.05 6.74 6.56 6.41 6.35 6.30

Stripping cost ($/ton) 0.66 0.66 0.66 0.66 0.66 0.66 0.66

Breakeven stripping ratio

Copper Price ($/lb)0.90 10.07 9.56 7.65 6.73 5.70 2.29 -0.020.75 6.50 6.19 4.67 3.95 3.13 0.30 -1.610.70 5.31 5.06 3.68 3.03 2.27 -0.36 -2.140.65 4.12 3.94 2.69 2.10 1.42 -1.02 -2.67

07.10/66.0$

/5.7$/90.0$7.15=

−∗=

wasteoftonoreoftonlblbs

BESR

Page 311: Strategic Open Pit Mine Planning Course.pdf

4

Manual Pit DesignStripping Ratio – Grade - Price

Sur

face

Min

e D

esig

n

S.R. - Ore Grades - Cu Prices

-4.00

-2.00

0.00

2.00

4.00

6.00

8.00

10.00

12.00

0.40 0.50 0.60 0.70 0.80 0.90

% Cu

Str

ipp

ing

Rat

io

0.90 $/lb0.75 $/lb0.70 $/lb0.65 $/lb

Page 312: Strategic Open Pit Mine Planning Course.pdf

5

X'

SR =

A B

Y'Y

Topo

Orebody

X'Y'

SR = YX

X

Manual Pit DesignHypothetical Cross Section

Sur

face

Min

e D

esig

n

Page 313: Strategic Open Pit Mine Planning Course.pdf

6

Manual Pit DesignS.R. in Section

Sur

face

Min

e D

esig

n

First

X’ = 30

Y’ = 5

S.R. = 6

G = 0.67%

Second

X’ = 39.6

Y’ = 6

S.R. = 6.6 (Breakeven)

G = 0.70%

First

X = 10

Y = 5

S.R. = 2

G = 0.48%

Second

X = 15

Y = 3

S.R. = 5

G = 0.70%

5 : 1 < 6.6 : 1 OK

Current Price = 0.90 $/lb

Page 314: Strategic Open Pit Mine Planning Course.pdf

7

Manual Pit DesignRepeat for All Sections

Sur

face

Min

e D

esig

n Pit contouror Final pit

Page 315: Strategic Open Pit Mine Planning Course.pdf

1

Cutoff Grade Optimization

Dr. Kadri Dagdelen

Sur

face

Min

e D

esig

n

Page 316: Strategic Open Pit Mine Planning Course.pdf

2

Factors Influencing The Cutoff Grades

Sur

face

Min

e D

esig

n

• As the Cutoff Grade increases in a given operation cash flow also increases

• The ultimate adjustment of the dial is influenced by the available capacities in the mining system

• The Cutoff Grade is not only function of economic parameters but also capacities of the mining system with respect to mining,milling and the market (refining)

Page 317: Strategic Open Pit Mine Planning Course.pdf

3

What Is Cutoff Grade

Sur

face

Min

e D

esig

n

1. Cutoff Grade is defined as the grade that is normally used to discriminate between ore and waste within a given deposit

2. Cutoff Grade is the dial that is used to adjust the cash flow coming from the mining operations in a given year

3. The Cutoff Grade policy allows a mining company to fine tune their operation with respect to a given financial objective

4. The Cutoff Grade dial also controls how much ore is available to the mill from a given bench and how much of final product to be produced in a given period

5. The overall influence of Cutoff Grade policy on the economics of an operation is profound

Page 318: Strategic Open Pit Mine Planning Course.pdf

4

Economic Objectives And The Cutoff Grade

Sur

face

Min

e D

esig

n

• The cash costs related to mining, milling and refining along with the commodity price determines the lower limit to cutoff in a given period.

• If the financial objective of the company is to maximize undiscounted profits, the cutoff grade should be lowered all theway down to process breakeven cutoff grade.

• Processing every ton of ore that pays for itself will maximize the undiscounted profits for the operation.

Page 319: Strategic Open Pit Mine Planning Course.pdf

5

Economic Objectives And The Cutoff Grade (Cont.)

Sur

face

Min

e D

esig

n

• If the financial objective of the company is to maximize the discounted profits that is Net Present Value (NPV), the Cutoff Grade in a given period has to be adjusted upwards to pay for the opportunity cost of mining low grade ore now while the higher grades are still available.

• The mining rate, milling rate, the ultimate rate of production for the commodity being sold, and the production costs determine how far the cutoff grade has to be adjusted upwards to maximize the NPV.

Page 320: Strategic Open Pit Mine Planning Course.pdf

6

Ultimate Pit Cutoff

Sur

face

Min

e D

esig

n

• Defined as the breakeven grade that equates cost of mining, milling and refining to the value of the block in terms of recovered metal and the selling price.

• Any administrative overhead expense which would stop if mining were stopped must be included in the cost calculations.

• Overhead costs should be divided between mining and processing.

Page 321: Strategic Open Pit Mine Planning Course.pdf

7

Ultimate Pit Cutoff

Sur

face

Min

e D

esig

n

• Price (P) $400/oz• Sales Cost (s) $5 /oz• Processing Cost (c) $ 10/ ton ore• Recovery (y) 90 %• Mining Cost (m) $ 1.20/ ton• Overhead

(Included in c and m )

Page 322: Strategic Open Pit Mine Planning Course.pdf

8

Ultimate Pit Cutoff

Sur

face

Min

e D

esig

n eryCostSalesiceCostMiningCostMilling

gm covRe*)(Pr −+

=

tonozgm /0315.09.0*)5$400($

2.1$10$=

−+

=

Page 323: Strategic Open Pit Mine Planning Course.pdf

9

Milling Cutoff

Sur

face

Min

e D

esig

n

• Defined as the breakeven grade that equates cost of milling and refining to the value of the block in terms of recovered metal and the selling price.

• Any administrative overhead expense which would stop if mining were stopped must be included in the cost calculations.

Page 324: Strategic Open Pit Mine Planning Course.pdf

10

Milling Cutoff

Sur

face

Min

e D

esig

n eryCostSalesiceCostMilling

gc covRe*)(Pr −=

tonozgc /0281.09.0*)5$400($

10$=

−=

Page 325: Strategic Open Pit Mine Planning Course.pdf

11

Block Value

Sur

face

Min

e D

esig

n

Block Grade = gB

if ggcc < < ggm <m < ggBB thenBlock Value = (P(P--S)* gS)* gBB * y * y –– c c –– mm

Else if ggBB < < ggm <m < ggcc thenBlock Value = Block Value = --mm

Page 326: Strategic Open Pit Mine Planning Course.pdf

12

Block Value

Sur

face

Min

e D

esig

n

Block Grade = gB

if ggcc < < ggB B << ggmm thenBlock contains marginal ore.

• Marginal ore pays for processing cost but not for mining cost.

Page 327: Strategic Open Pit Mine Planning Course.pdf

13

Block Value Calculation Example

Sur

face

Min

e D

esig

n

a) Ore BlockBlock grade = gB = 0.11 oz/tonggc c < < ggm < m < ggBB

0.0281 < 0.0315 < 0.11Block Value = (P(P--S)*S)* ggBB * y * y –– c c –– mm

Block Value = (400 - 5)*0.11*0.9 - 10 - 1.20= $27.9/ton of block

Page 328: Strategic Open Pit Mine Planning Course.pdf

14

Block Value Calculation Example

Sur

face

Min

e D

esig

n

b) Waste BlockBlock Grade = gB = 0.01 oz/tonggB B < < ggc c << ggmm

0.01 < 0.0281 < 0.0315

therefore

Block Value = -- $1.20/ton$1.20/ton= Mining Cost

Page 329: Strategic Open Pit Mine Planning Course.pdf

15

Mine Design Parameters For The Case Study

Sur

face

Min

e D

esig

n

• Price (P) $600/oz• Sales Cost (s) $5 /oz• Processing Cost (c) $ 19/ ton ore• Recovery (y) 90 %• Mining Cost (m) $ 1.20/ ton• Fixed Costs (fa) 8.35 M/year• Mining Capacity (M) Unlimited• Milling Capacity (C) 1.05 M• Capital Costs (CC) 105 M• Discount Rate (d) 15%

Page 330: Strategic Open Pit Mine Planning Course.pdf

16

Calculation of Ultimate Pit Cutoff Grade

Sur

face

Min

e D

esig

n eryCostSalesiceCostMiningCostMilling

gm covRe*)(Pr −+

=

tonozgm /038.09.0*)5$600($

2.1$19$=

−+

=

Page 331: Strategic Open Pit Mine Planning Course.pdf

17

Calculation of Milling Cutoff Grade

Sur

face

Min

e D

esig

n eryCostSalesiceCostMilling

gc covRe*)(Pr −=

tonozgc /035.09.0*)5$600($

19$=

−=

Page 332: Strategic Open Pit Mine Planning Course.pdf

18

Grade Tonnage Distribution

Sur

face

Min

e D

esig

n

Avg. IntervalGrade

0.000 - 0.020 70,000 0.01000.020 - 0.025 7,257 0.02250.025 - 0.030 6,319 0.02750.030 - 0.035 5,591 0.03250.035 - 0.040 4,598 0.03750.040 - 0.045 4,277 0.04250.045 - 0.050 3,465 0.04750.050 - 0.055 2,428 0.05250.055 - 0.060 2,307 0.05750.060 - 0.065 1,747 0.06250.065 - 0.070 1,640 0.06750.070 - 0.075 1,485 0.07250.075 - 0.080 1,227 0.07750.080 - 0.100 3,598 0.09000.100 - 0.358 9,576 0.2290

Cutoff Grade 0.035

KTonsGrade Interval KTons Grade

89,167

36,348

Waste

0.1023

Ore

Oz/ton

Page 333: Strategic Open Pit Mine Planning Course.pdf

19

Constant Cutoff Grades.Yearly Tons and Grade Schedules.

Table 3

Sur

face

Min

e D

esig

n

Year Cutoff Avg QM Qc Qr Profits Grade Grade $M/year

1 0.035 0.102 3.6 1.05 96.3 33.02 0.035 0.102 3.6 1.05 96.3 33.03 0.035 0.102 3.6 1.05 96.3 33.04 0.035 0.102 3.6 1.05 96.3 33.05 0.035 0.102 3.6 1.05 96.3 33.06 0.035 0.102 3.6 1.05 96.3 33.07 0.035 0.102 3.6 1.05 96.3 33.08 0.035 0.102 3.6 1.05 96.3 33.09 0.035 0.102 3.6 1.05 96.3 33.0

10 0.035 0.102 3.6 1.05 96.3 33.0For 11 to 34 0.035 0.102 3.6 1.05 96.3 33.0

35 0.035 0.102 3.4 1.00 91.7 31.4TOTAL 0.035 0.102 125.8 36.70 3365.9 1154.2

NPV $M 218.5

Page 334: Strategic Open Pit Mine Planning Course.pdf

20

Profit

Sur

face

Min

e D

esig

n

Profits ($M) = (P Profits ($M) = (P –– s ) x s ) x QQrr –– QQcc x c x c –– QQmm x mx m

P – Price S – Sales CostQm – Total Material MinedQc – Ore Tonnage Processed By The MillQr – Recovered Ouncesc – Milling Costs ($/ton)m – Mining Costs ($/ton)

Page 335: Strategic Open Pit Mine Planning Course.pdf

21

Shortcomings of the traditional cutoff grades

Sur

face

Min

e D

esig

n

• They are established to satisfy the objective of maximizing the undiscounted profits from a given mining operation.

• They are constant unless the commodity price and the costs change during the life of mine AND

• They do not consider grade distribution of the deposit.

Page 336: Strategic Open Pit Mine Planning Course.pdf

22

Traditional

Sur

face

Min

e D

esig

n

eryCostSalesiceofitMinimumonDepreciatiCostMilling

gc covRe*)(PrPr

−++

=

tonozgc /060.09.0*)5$600($

3$10$19$=

−++

=

Page 337: Strategic Open Pit Mine Planning Course.pdf

23

Nontraditional ????????

Sur

face

Min

e D

esig

n eryCostSalesiceonDepreciatiCostMilling

gc covRe*)(Pr −+

=

tonozgc /054.09.0*)5$600($

10$19$=

−+

=

Page 338: Strategic Open Pit Mine Planning Course.pdf

24

Constant Cutoff GradesYearly Tons and Grade Schedules

Table 4

Sur

face

Min

e D

esig

n

Year Cutoff Avg Qm Qc Qr Profits Grade Grade $M/year

1 0.060 0.153 6.90 1.05 144.60 57.82 0.060 0.153 6.90 1.05 144.60 57.83 0.060 0.153 6.90 1.05 144.60 57.84 0.060 0.153 6.90 1.05 144.60 57.85 0.060 0.153 6.90 1.05 144.60 57.86 0.054 0.141 6.00 1.05 132.80 51.97 0.054 0.141 6.00 1.05 132.80 51.98 0.054 0.141 6.00 1.05 132.80 51.99 0.054 0.141 6.00 1.05 132.80 51.9

10 0.054 0.141 6.00 1.05 132.80 51.9For 11 to 27 0.035 0.102 3.60 1.05 96.30 33.0

28 0.035 0.102 0.30 0.09 8.10 2.8TOTAL 0.035 0.102 125.80 28.44 3032.10 1112.7

NPV $M 355.7

Page 339: Strategic Open Pit Mine Planning Course.pdf

25

Declining Cutoff Grades

Sur

face

Min

e D

esig

n

eryCostSalesiceCostFixedonDepreciatiCostMilling

gc covRe*)(Pr −++

=

tonozgc /069.09.0*)5$600($95.7$10$19$

=−

++=

Page 340: Strategic Open Pit Mine Planning Course.pdf

26

Declining Cutoff Grades

Sur

face

Min

e D

esig

n eryCostSalesiceCostFixedCostMilling

gc covRe*)(Pr −+

=

tonozgc /050.09.0*)5$600($

95.7$19$=

−+

=

Page 341: Strategic Open Pit Mine Planning Course.pdf

27

Declining Cutoff Grades

Sur

face

Min

e D

esig

n

eryCostSalesiceCostFixedofMinimumonDepreciatiCostMilling

gc covRe*)(Pr.Pr

−+++

=

tonozgc /075.09.0*)5$600($

95.7$3$10$19$=

−+++

=

Page 342: Strategic Open Pit Mine Planning Course.pdf

28

Declining Cutoff Grades

Sur

face

Min

e D

esig

n

eryCostSalesiceCostMilling

gc covRe*)(Pr −=

tonozgc /035.09.0*)5$600($

19$=

−=

Page 343: Strategic Open Pit Mine Planning Course.pdf

29

Declining Cutoff GradesYearly Tons and Grade Schedules.

Table 5

Sur

face

Min

e D

esig

n

Year Cutoff Avg QM Qc Qr **Profits Grade Grade $M/year

1 0.075 0.182 9.2 1.05 171.6 62.82 0.075 0.182 9.2 1.05 171.6 62.83 0.075 0.182 9.2 1.05 171.6 62.84 0.075 0.182 9.2 1.05 171.6 62.85 0.075 0.182 9.2 1.05 171.6 62.86 0.069 0.169 8.2 1.05 160.0 57.17 0.069 0.169 8.2 1.05 160.0 57.18 0.069 0.169 8.2 1.05 160.0 57.19 0.069 0.169 8.2 1.05 160.0 57.1

10 0.069 0.169 8.2 1.05 160.0 57.1For 11 to 17 0.050 0.132 5.4 1.05 124.8 39.5

18 0.050 0.132 1.3 0.26 30.5 9.6

TOTAL 125.8 18.11 2562.5 885.6NPV $M 357.7

**Profits ($M)= (PProfits ($M)= (P--s) xs) x QrQr –– Qc x c Qc x c –– QmQm x m x m –– f af a

Page 344: Strategic Open Pit Mine Planning Course.pdf

30

Cutoff Grade Optimization

Determination Of Optimum Cutoff Grades

When The MillIs Bottleneck

Sur

face

Min

e D

esig

n

Page 345: Strategic Open Pit Mine Planning Course.pdf

31

Formula for Optimum Cutoff Grade

Sur

face

Min

e D

esig

n ySPFfc

ig ic *)(

)(−

++=

• Where FFii = d x NPV= d x NPVii /C/Cf = f = ffaa/C /C

and fa is annual fixed costs

Page 346: Strategic Open Pit Mine Planning Course.pdf

32

Optimum Cutoff GradesYearly Tons and Grade Schedules

Table 6

Sur

face

Min

e D

esig

n

Year Cutoff Avg QM Qc Qr **Profits NPV Grade Grade $M $M

1 0.161 0.259 18.0 1.05 245.2 95.9 413.82 0.152 0.255 17.2 1.05 241.0 94.4 380.03 0.142 0.250 16.5 1.05 236.4 92.6 342.64 0.131 0.245 15.7 1.05 231.3 90.5 301.45 0.120 0.239 14.9 1.05 225.7 88.1 256.16 0.107 0.232 14.1 1.05 219.6 85.4 206.47 0.092 0.213 12.1 1.05 200.9 76.7 152.08 0.079 0.188 9.8 1.05 177.9 65.9 98.19 0.065 0.163 7.6 1.05 153.6 53.9 46.9

TOTAL 125.8 9.45 1931.4 743.4NPV $M 413.8

**Profits ($M)= (PProfits ($M)= (P--s) x s) x Qr Qr –– Qc x c Qc x c –– Qm Qm x m x m –– f af a

Page 347: Strategic Open Pit Mine Planning Course.pdf

33

Summary

Sur

face

Min

e D

esig

n

Avg Total Total Strip Profits NPV Life Undiscounted NPV Grade Amount Amount Ratio % Reduction % Increase

mined processed INC CUM INC CUMQm Qr $M $M yrs

Traditional 0.102 125.8 36.70 2.43 4453.4 218.5 35 n/a n/a n/a n/a

Heuristic 0.125 125.8 28.44 3.42 1127.4 355.7 28 3.6 3.6 63.0 63.0(Depr)

Heuristic 0.164 125.8 18.11 5.95 885.6 357.1 18 20.4 23.3 0.3 63.4(Depr and

Fixed Costs)

Lanes's 0.235 125.8 9.45 12.31 743.4 413.8 9 16.0 35.6 15.9 89.0Approach

Page 348: Strategic Open Pit Mine Planning Course.pdf

34

Cutoff Grade Optimization

One Constraint Cutoff Grade

Optimization Algorithm

Sur

face

Min

e D

esig

n

Page 349: Strategic Open Pit Mine Planning Course.pdf

35

Steps Of The Algorithm

Sur

face

Min

e D

esig

n

1. Start with Grade-Tonnage Curve.

2. Define: P - PriceC - Milling Capacity s - Marketing Costsm - Mining Costsc - Milling Costsfa - Fixed Costsd - Discount Rate

Page 350: Strategic Open Pit Mine Planning Course.pdf

36

Steps Of The Algorithm (Cont.)

Sur

face

Min

e D

esig

n

3. Determine the cutoff grade gc for year (i).

ySPFfc

ig ic *)(

)(−

++=

• Where FFii = d x NPV= d x NPVii /C/Cf = f = ffaa/C /C

and fa is annual fixed costs

Page 351: Strategic Open Pit Mine Planning Course.pdf

37

Steps Of The Algorithm (Cont.)

Sur

face

Min

e D

esig

n

4. For Cutoff Grade gmilling (i):

• Determine Ore Tonnage Tc and Grade gc

• Determine the Waste Tonnage Tw

• Stripping Ratio ((srsr) = ) = TTww//TTcc

Page 352: Strategic Open Pit Mine Planning Course.pdf

38

Steps Of The Algorithm (Cont.)

Sur

face

Min

e D

esig

n

5. Set

QQcc = C = C if if TTcc > C> CQQcc = = TTcc if if TTcc < C< C

And

QQmm = Q= Qcc(1+(1+srsr))

Page 353: Strategic Open Pit Mine Planning Course.pdf

39

Steps Of The Algorithm (Cont.)

Sur

face

Min

e D

esig

n

6. Determine the annual profit (Pi) by using the following equationPi =(PPi =(P--s) x Qc x s) x Qc x ggcc x y x y –– Qc x (c + f) Qc x (c + f) –– Qm Qm x mx m

P - Prices - Marketing Costs Qm - Total material minedQc - Ore tonnage processed by the millc - Milling Costs ($/ton)m - Mining Costs ($/ton)gc - Average Grade (Opt)y - Recoveryf - Fixed Cost ($/ton)

Page 354: Strategic Open Pit Mine Planning Course.pdf

40

Steps Of The Algorithm (Cont.)

Sur

face

Min

e D

esig

n

7. Adjust the Grade-Tonnage Curve of the deposit for Qc and QQww = = Qm Qm –– QcQc .

8. If Qc < CQc < C in year (i) go to step 9 otherwise

Set i = i+1i = i+1 and go to Step 3.

Page 355: Strategic Open Pit Mine Planning Course.pdf

41

Steps Of The Algorithm (Cont.)

Sur

face

Min

e D

esig

n

9. Calculate incremental NPV for each year (i)

∑=

+−+=

N

ijij

ji d

PNPV 1)1(

Page 356: Strategic Open Pit Mine Planning Course.pdf

42

Steps Of The Algorithm (Cont.)

Sur

face

Min

e D

esig

n

10. If NPV1 for this iteration is not within some tolerance (say plusplus--minus $500K minus $500K ) on the NPV1 of the previous iteration go to Step 1otherwiseotherwiseStop the cutoff grade gc (i) for years i = 1i = 1, NN is Optimum Policy.

Page 357: Strategic Open Pit Mine Planning Course.pdf

Open Pit Sequencing and Production Scheduling

Dr. Kadri Dagdelen

Sur

face

Min

e D

esig

n

Page 358: Strategic Open Pit Mine Planning Course.pdf

2

Sur

face

Min

e D

esig

n

Open pit production scheduling

• It is a timed sequence of extraction of the ore and waste within the ultimate pit limits from the initial condition of the deposit up to a predetermined stage that mat be referred to as an intermediate of final pit limit.

• It sets the relationship between quantity and quality of the material to be mined, time, geometry of the orebody, and the available resources.

Page 359: Strategic Open Pit Mine Planning Course.pdf

3

Sur

face

Min

e D

esig

n

Time

Stri

ppin

gV

olum

e

Declining Stripping Ratio Method

1

2

3

4

5

67

1

2

76

5

4

3

1

2

3

4

5

67

Orebody

Waste

Page 360: Strategic Open Pit Mine Planning Course.pdf

4

Sur

face

Min

e D

esig

n

Increasing Stripping Ratio Method

Orebody

Waste

Page 361: Strategic Open Pit Mine Planning Course.pdf

5

Sur

face

Min

e D

esig

n

Constant Stripping Ratio Method

Orebody

Waste

Page 362: Strategic Open Pit Mine Planning Course.pdf

6

Sur

face

Min

e D

esig

n

Long Term Production Scheduling

•Long term production scheduling is usually carried out from the initial condition of the deposit (i.e. initial topography) to the ultimate pit limit, in periods of at least one year.

•Its purpose is to determine ore reserves, stripping ratios, future investments, and to conserve and develop owned resources.

•Long term production scheduling takes into account capital availability, geometry and grade distribution of the orebody, metallurgical and physical properties of the material, as well as environmental and legal constraints.

Page 363: Strategic Open Pit Mine Planning Course.pdf

7

Sur

face

Min

e D

esig

n

Short Term Production Scheduling

•Short term production scheduling is concerned with schedules on a daily, weekly or monthly basis.

•Its main objective is to furnish the requirements of the processing plant with ore of uniform quality to ensure operating efficiency.

•To accomplish this objective, short term production scheduling has to comply with restrictions imposed by the long term plan, equipment availability, blending of different materials from different sites within the mine, and the availability of exposed ore.

Page 364: Strategic Open Pit Mine Planning Course.pdf

8

Sur

face

Min

e D

esig

n

Objectives in Open Pit Mine Planning

• To ensure the tonnage required by the processing plant in order to operate efficiently and to produce the expected amount of concentrate per mining period.

• To meet the grade specifications at the processing plant within a given range for each ore parameter that has an effect on the operating costs or the quality of the final product.

Page 365: Strategic Open Pit Mine Planning Course.pdf

9

Sur

face

Min

e D

esig

n

Objectives in Open Pit Mine Planning (cont.)

• To minimize the pre-production stripping volume required to expose enough ore at the beginning of the mine life in order to ensure a continuous operation.

• To defer waste stripping as long as possible to maximize cash flow in the early years of the operation.

Page 366: Strategic Open Pit Mine Planning Course.pdf

10

Sur

face

Min

e D

esig

n

Objectives in Open Pit Mine Planning (cont.)

• To ensure a feasible schedule in terms of mining practice. This implies mining exposed material sequentially, keeping appropriate mining widths, maintaining access to the mining areas, and maintaining stable pit walls.

• To ensure the schedule is compatible with the remaining periods. In other words, the present schedule must ensure the feasibility of the future extraction.

Page 367: Strategic Open Pit Mine Planning Course.pdf

11

Sur

face

Min

e D

esig

n

Objectives in Open Pit Mine Planning (cont.)

• To mine the orebody in such a way that for each year the cost to produce a given kilogram of metal is at minimum.

• To develop an achievable start-up schedule with respect to manpower training, equipment deployment, infrastructure and logistical support in order to ensure positive cash flow as planned.

• To have enough exposed ore at the beginning of each scheduling period to offset any problem that could arise in the case of underestimation of ore tonnages and grades in the reserves model.

Page 368: Strategic Open Pit Mine Planning Course.pdf

12

Sur

face

Min

e D

esig

n

Objectives in Open Pit Mine Planning (Cont.)

• To maximize design pit slope angles in response to adequate geotechnical investigations, and yet through careful planning minimize the adverse impacts of any slope instability, should itoccur.

• To properly examine the economic merits of alternative ore production rate and cutoff grade scenarios.

• To thoroughly subject the proposed mining strategy, equipment selection, and mine development plan to “what if” contingency planning, before a commitment to proceed is made.

Page 369: Strategic Open Pit Mine Planning Course.pdf

13

Sur

face

Min

e D

esig

n

Pit Sequence Planning

• Orebodies are normally mined in stages, so as to defer waste stripping and maximize the net present value of the surface mining venture.

• These stages are commonly called sequences, expansions, phases, working pits, slices, or pushbacks.

• They are the basic building block on which more detailed time period planning is subsequently made.

• Phase planning should commence with mining that portion of the orebody which will yield the maximum cash flow and then proceed to mine other stages of lessening cash flow.

Page 370: Strategic Open Pit Mine Planning Course.pdf

14

Sur

face

Min

e D

esig

n

Procedure to obtain the pushbacks

• Generate nested pits by increasing and/or decreasing the product price.

• According to the size of the deposit, pick a number of phases that allow enough operating room for the equipment.

Page 371: Strategic Open Pit Mine Planning Course.pdf

15

Sur

face

Min

e D

esig

n

Example of how to obtain the pushbacks

•% Recovery through mill and smelter 90%

•Value of recovered copper $1.10/lb

•Stripping and haulage to dump (level 1) $0.50/ton

•Mining and transportation to plant level $0.80/ton

•Haulage costs increase per bench $0.10/ton

•Processing, smelting and refining $1.20/ton

•General overhead, administration, etc. (ore blocks only) $1.20/ton

•Ultimate pit slope 1 : 1

Page 372: Strategic Open Pit Mine Planning Course.pdf

16

Sur

face

Min

e D

esig

n

Example of how to obtain the pushbacks (Cont.)

Block Model showing copper grades in %

Level1 0.00 0.10 0.15 0.08 0.05 0.00 0.00 0.05 0.03 0.00 0.05 0.05 0.05 0.05 0.05 0.052 0.00 0.22 0.08 0.25 0.15 0.13 0.10 0.13 0.45 0.20 0.20 0.32 0.10 0.15 0.24 0.213 0.05 0.05 0.12 0.13 0.02 0.14 0.11 0.08 0.22 0.09 0.08 0.15 0.22 0.20 0.14 0.054 0.04 0.15 0.12 0.45 0.08 0.09 0.25 0.20 0.29 0.14 0.15 0.04 0.24 0.05 0.02 0.045 0.05 0.08 0.15 0.12 0.30 0.21 0.09 0.79 0.10 0.45 0.32 0.23 0.01 0.01 0.01 0.016 0.08 0.10 0.08 0.01 0.05 0.34 0.45 0.02 0.01 0.04 0.38 0.00 0.00 0.00 0.01 0.15

Page 373: Strategic Open Pit Mine Planning Course.pdf

17

Sur

face

Min

e D

esig

n

Example of how to obtain the pushbacks (Cont.)

Economic Model showing block values in $/ton

Original copper price of $1.10/lb1 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.502 -0.60 1.06 -0.60 1.65 -0.60 -0.60 -0.60 -0.60 5.61 0.66 0.66 3.04 -0.60 -0.60 1.45 0.863 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 0.96 -0.70 -0.70 -0.70 0.96 0.56 -0.70 -0.704 -0.80 -0.80 -0.80 5.41 -0.80 -0.80 1.45 0.46 2.24 -0.80 -0.80 -0.80 1.25 -0.80 -0.80 -0.805 -0.90 -0.90 -0.90 -0.90 2.34 0.56 -0.90 12.04 -0.90 5.31 2.74 0.95 -0.90 -0.90 -0.90 -0.906 -1.00 -1.00 -1.00 -1.00 -1.00 3.03 5.21 -1.00 -1.00 -1.00 3.82 -1.00 -1.00 -1.00 -1.00 -1.00

mcygsPBV B −−−= **)(

mBV −=

For ore blocks:

For waste blocks:

Page 374: Strategic Open Pit Mine Planning Course.pdf

18

Sur

face

Min

e D

esig

n

Example of how to obtain the pushbacks (Cont.)

The floating cone algorithm was used to find the ultimate pit limit

Pit1 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 12 -0.60 1.06 -0.60 1.65 -0.60 -0.60 -0.60 -0.60 5.61 0.66 0.66 3.04 -0.60 -0.60 1.45 0.86 23 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 0.96 -0.70 -0.70 -0.70 0.96 0.56 -0.70 -0.70 34 -0.80 -0.80 -0.80 5.41 -0.80 -0.80 1.45 0.46 2.24 -0.80 -0.80 -0.80 1.25 -0.80 -0.80 -0.80 45 -0.90 -0.90 -0.90 -0.90 2.34 0.56 -0.90 12.04 -0.90 5.31 2.74 0.95 -0.90 -0.90 -0.90 -0.90 56 -1.00 -1.00 -1.00 -1.00 -1.00 3.03 5.21 -1.00 -1.00 -1.00 3.82 -1.00 -1.00 -1.00 -1.00 -1.00 6

7The ore block left at the right cannot be mined due to slope constraints. All ore blocks are mined in the first iteration. 8

91 102 113 124 135 146 15

Page 375: Strategic Open Pit Mine Planning Course.pdf

19

Sur

face

Min

e D

esig

n

Example of how to obtain the pushbacks (Cont.)

To find a smaller pit reduce the copper price to 0.60/lb Economic block model

1 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.502 -0.60 -0.60 -0.60 -0.60 -0.60 -0.60 -0.60 -0.60 1.56 -0.60 -0.60 0.16 -0.60 -0.60 -0.60 -0.603 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.704 -0.80 -0.80 -0.80 1.36 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80 -0.805 -0.90 -0.90 -0.90 -0.90 -0.90 -0.90 -0.90 4.93 -0.90 1.26 -0.90 -0.90 -0.90 -0.90 -0.90 -0.906 -1.00 -1.00 -1.00 -1.00 -1.00 -1.00 1.16 -1.00 -1.00 -1.00 0.40 -1.00 -1.00 -1.00 -1.00 -1.00

mcygsPBV B −−−= **)(

mBV −=

For ore blocks:

For waste blocks:

Page 376: Strategic Open Pit Mine Planning Course.pdf

20

Sur

face

Min

e D

esig

n

Example of how to obtain the pushbacks (Cont.)

The floating cone algorithm was used to find the limit of the pit at $0.60/lb

1 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.502 -0.60 -0.60 -0.60 -0.60 -0.60 -0.60 -0.60 -0.60 1.56 -0.60 -0.60 0.16 -0.60 -0.60 -0.60 -0.603 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.704 -0.80 -0.80 -0.80 1.36 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80 -0.80 -0.805 -0.90 -0.90 -0.90 -0.90 -0.90 -0.90 -0.90 4.93 -0.90 1.26 -0.90 -0.90 -0.90 -0.90 -0.90 -0.906 -1.00 -1.00 -1.00 -1.00 -1.00 -1.00 1.16 -1.00 -1.00 -1.00 0.40 -1.00 -1.00 -1.00 -1.00 -1.00

123456

Page 377: Strategic Open Pit Mine Planning Course.pdf

21

Sur

face

Min

e D

esig

n

Example of how to obtain the pushbacks (Cont.)

To find an intermediate pit reduce the copper price to $0.86/lb Economic Block Model

1 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.502 -0.60 0.11 -0.60 0.57 -0.60 -0.60 -0.60 -0.60 3.67 -0.60 -0.60 1.65 -0.60 -0.60 0.42 -0.603 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.704 -0.80 -0.80 -0.80 3.47 -0.80 -0.80 0.37 -0.80 0.99 -0.80 -0.80 -0.80 0.22 -0.80 -0.80 -0.805 -0.90 -0.90 -0.90 -0.90 1.04 -0.90 -0.90 8.63 -0.90 3.37 1.35 -0.90 -0.90 -0.90 -0.90 -0.906 -1.00 -1.00 -1.00 -1.00 -1.00 1.56 3.27 -1.00 -1.00 -1.00 2.18 -1.00 -1.00 -1.00 -1.00 -1.00

Page 378: Strategic Open Pit Mine Planning Course.pdf

22

Sur

face

Min

e D

esig

n

Example of how to obtain the pushbacks (Cont.)

To find an intermediate pit reduce the copper price to $0.86/lb Economic Block Model

1 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 -0.50 Pit2 -0.60 0.11 -0.60 0.57 -0.60 -0.60 -0.60 -0.60 3.67 -0.60 -0.60 1.65 -0.60 -0.60 0.42 -0.60 13 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 -0.70 24 -0.80 -0.80 -0.80 3.47 -0.80 -0.80 0.37 -0.80 0.99 -0.80 -0.80 -0.80 0.22 -0.80 -0.80 -0.80 35 -0.90 -0.90 -0.90 -0.90 1.04 -0.90 -0.90 8.63 -0.90 3.37 1.35 -0.90 -0.90 -0.90 -0.90 -0.906 -1.00 -1.00 -1.00 -1.00 -1.00 1.56 3.27 -1.00 -1.00 -1.00 2.18 -1.00 -1.00 -1.00 -1.00 -1.00

The ore block left at the right cannot be mined due to slope constraints. All ore blocks are mined in the first iteration.

123456

Page 379: Strategic Open Pit Mine Planning Course.pdf

23

Sur

face

Min

e D

esig

n

Example of how to obtain the pushbacks (Cont.)

The three pits shown in together

1 $0.60/lb23456

$1.10/lb$0.86/lb

Page 380: Strategic Open Pit Mine Planning Course.pdf

24

ABCD

EF

Design Phase Limits Ultimate Pit

Ore

Rock Type I

Rock Type II

Sur

face

Min

e D

esig

n

Hypothetical Deposit and Pit Development Sequence

Page 381: Strategic Open Pit Mine Planning Course.pdf

25

Sur

face

Min

e D

esig

n

Tonnage Inventory by Phase

Waste Ore Waste Ore Waste Ore5100 15,0005050 32,0005000 50,000 2,000 4,0004950 38,000 18,000 15,0004900 15,000 20,000 18,0004850 4,000 10,000 15,000 22,0004800 3,000 9,000 4,000 9,000 16,0004750 2,000 8,000 3,000 9,000 3,000 10,0004700 2,000 7,000 5,000 20,0004650 1,000 6,000 8,000 22,0004600 3,000 17,0004550 1,000 7,000

Total 159,000 27,000 65,000 31,000 95,000 76,000

Thousands of tonnes

Phase "A" Phase "B" Phase "C"Bench

Page 382: Strategic Open Pit Mine Planning Course.pdf

26

Sur

face

Min

e D

esig

n

Summary by Phase

Waste above Waste on Ore Cumulativefirst ore ore Ore Life* ore lifebench benches (years) (years)

A 150,000 9,000 27,000 1.08 1.08B 55,000 10,000 31,000 1.24 2.32C 75,000 20,000 76,000 3.04 5.36D 128,000 38,000 125,000 5.00 10.36E 182,000 49,000 151,000 6.04 16.40F 220,000 45,000 130,000 5.20 21.60Total 810,000 171,000 540,000 21.60

*Assuming an annual milling rate 0f 25,000 tonnes

Phase

Thousands of tonnes

Page 383: Strategic Open Pit Mine Planning Course.pdf

27

Sur

face

Min

e D

esig

n

Hypothetical Deposit and Pit Development Sequence

Time (Years)

10

ore deliveriesrequired to sustainMinimum waste stripping

Time (Years)Pre-production

(Mill

ions

of t

onne

s)C

umul

ativ

e St

ripp

ing

250

0

500

750

A

B

C

D

(Mill

ions

of t

onne

s)D

evel

oped

Ore

50

0

1000

100

150

BA

C

D

It requires 128 M tonnes strippingPhase "D" life = 5 yearsPhase "D" ore = 125 M tonnes

-10 -5

200

25050

F

200 M

25 M

75 M50 M

- Pre-production period

A proposed stripping

- Production period50 M tonnes / year

4 yrs. Yr 1

scheduleE

42-3

E

F

2015

stripping scheduledue to the proposedEarlier ore development

25

Period

-10 -5 0 5 10 15 20 25

schedule

4 yrs. Yr 1- Pre-production period

A proposed stripping50 M tonnes / year

- Production period

B

A

C

D

25 M50 M

200 M75 M4

2-3

0

500

250

-10 -5 0 51 2 3 42550

50

75

150

Pre-productionPeriod

200

BA

C

D

0

50

100

-10 -5 0 5

1.08

1.24

3.04

27 31

76

Page 384: Strategic Open Pit Mine Planning Course.pdf

28

Sur

face

Min

e D

esig

nTime (Years)

10

ore deliveriesrequired to sustainMinimum waste stripping

Time (Years)

Pre-production

(Mill

ions

of

tonn

es)

Cum

ulat

ive

Stri

ppin

g

250

0

500

750

A

B

C

D

(Mill

ions

of t

onne

s)D

evel

oped

Ore

50

0

100

150

BA

C

D

It requires 128 M tonnes strippingPhase "D" life = 5 yearsPhase "D" ore = 125 M tonnes

-10 -5 50

200 M

25 M

75 M50 M

- Pre-production period

- Production period50 M tonnes / year

4 yrs. Yr 1

E

42-3

Estripping scheduledue to the proposedEarlier ore development

Period

-10 -5 0 5 101 2 3 4

75

505025

Cushion = 0.66 years

Cushion = 0.80 years

Cushion = 0.34 years

5.003.04

1.241.08

27 31

76

125

Page 385: Strategic Open Pit Mine Planning Course.pdf

($374M)

Period 1$46M

Period 2$42M

Period 3$63M

Period 5$51M

Period 4$65M

Period 6$48M

Period 7 $43MPeriod 8 $16M

Period 1$81M

Period 2$72M

Period 3$63M

Period 5$37M

Period 6$32MPeriod 7

$43M

Period 8$9M

($398M)

Period 4$61M

Period 1$50M

Period 2$37M

Period 3 $60M

Period 4$50M

Period 5 $49M Period 6$50M

($366M)

Period 7 $52M

Period 8 $19M

($372M)

Period 1 $42MPeriod 7 $57MPeriod 8 $11M

Period 2$32M

Period 3$71M

Period 4 $51M

Period 5 $57MPeriod 6 $52M

Page 386: Strategic Open Pit Mine Planning Course.pdf

Long Term Planning and Sequencing

Dr. Kadri Dagdelen

Colorado School of Mines

Sur

face

Min

e D

esig

n

Page 387: Strategic Open Pit Mine Planning Course.pdf

2

Sur

face

Min

e D

esig

n

Long Term Planning and Sequencing

• Objective is to determine the suitability of the limestone resource for the subsequent processing by the cement plant

• Life of mining and reclamation plans• Equipment Selection• Facility layout and Permitting

Page 388: Strategic Open Pit Mine Planning Course.pdf

3

Sur

face

Min

e D

esig

n

Long Term Planning and Sequencing

• Create a geologic model• Define structural domains and stratigraphy• Chemistry• Long and short term variability

• Long term reserves and average chemistry• Estimate the block chemical values• Estimate possible raw mix requirements

• Quarry layout and operational plan yearly mine plans

Page 389: Strategic Open Pit Mine Planning Course.pdf

4

Sur

face

Min

e D

esig

n

Long Term Planning and Sequencing

• Determine mineable resource boundaries• Haul road layout • Define long term reclamation needs

Page 390: Strategic Open Pit Mine Planning Course.pdf

5

Sur

face

Min

e D

esig

n

Midlothian Cement Quarry:Case Study

• Current production 1.8 million tons of limestone• One 50ft to 60ft bench operation • In pit crushing - 1000 ton/per hour capacity• Expand the capacity to 3.6 million tons by bringing

the second bench into production• 50 percent of the production from first 50ft bench

and another 50 percent from the second bench.• %SO3 is not very good for the limestone coming

from the second bench. Blending of these two benches are necessary.

Page 391: Strategic Open Pit Mine Planning Course.pdf

6

Sur

face

Min

e D

esig

n

Midlothian Cement Quarry:Case Study

• Quarry currently operates 10 hours per shift, 5 days per week

• 1000 ton per hour Krubb In Pit Crusher• 2000 ft long main movable belt conveyor

with 500 ft long extension belt• Komatsu 14 and 10 cubic yard loaders

Page 392: Strategic Open Pit Mine Planning Course.pdf

7

Sur

face

Min

e D

esig

n

Midlothian Cement Quarry:Case Study

• Determine next 50 years life of mine plans • Sequencing plan to come up with the right

blend limestone that meets the minimum of %1.3 SO3 requirements

• Determine equipment and capital investment needs for the next 10 years

Page 393: Strategic Open Pit Mine Planning Course.pdf

8

Sur

face

Min

e D

esig

n

Quarry Development and Sequencing

Page 394: Strategic Open Pit Mine Planning Course.pdf

9

Sur

face

Min

e D

esig

n

Holnam Quarry Mining Sequence: First Bench Development

Page 395: Strategic Open Pit Mine Planning Course.pdf

10

Sur

face

Min

e D

esig

nHolnam Quarry Mining Sequence:

Second Bench Development During the First Three Years

Page 396: Strategic Open Pit Mine Planning Course.pdf

11

Sur

face

Min

e D

esig

n

Holnam Quarry Mining Sequence: First and Second Bench Development

Page 397: Strategic Open Pit Mine Planning Course.pdf

12

Sur

face

Min

e D

esig

n

Holnam Quarry Mining Sequence: First and Second Bench Development

Page 398: Strategic Open Pit Mine Planning Course.pdf

13

Sur

face

Min

e D

esig

n

Holnam Quarry Mining Sequence: First and Second Bench Development

Page 399: Strategic Open Pit Mine Planning Course.pdf

14

Sur

face

Min

e D

esig

n

Midlothian North Area Quarry Progress Contours Year1

Page 400: Strategic Open Pit Mine Planning Course.pdf

15

Sur

face

Min

e D

esig

n

Midlothian North Area Quarry Progress Contours Year 2

Page 401: Strategic Open Pit Mine Planning Course.pdf

16

Sur

face

Min

e D

esig

n

Midlothian North Area Quarry Progress Contours Year 3

Page 402: Strategic Open Pit Mine Planning Course.pdf

17

Sur

face

Min

e D

esig

n

Midlothian North Area Quarry Progress Contours Year 4

Page 403: Strategic Open Pit Mine Planning Course.pdf

18

Sur

face

Min

e D

esig

n

Midlothian Quarry Block Model Definition

Page 404: Strategic Open Pit Mine Planning Course.pdf

19

Sur

face

Min

e D

esig

n

Midlothian Quarry Block Model Definition

Page 405: Strategic Open Pit Mine Planning Course.pdf

20

Sur

face

Min

e D

esig

n

Midlothian Quarry Sequence: One Year Increments on Elevation 790

Page 406: Strategic Open Pit Mine Planning Course.pdf

21

Sur

face

Min

e D

esig

n

Midlothian Quarry Sequence: One Year Increments on Elevation 780

Page 407: Strategic Open Pit Mine Planning Course.pdf

22

Sur

face

Min

e D

esig

n

Midlothian Quarry Sequence: One Year Increments on Elevation 770

Page 408: Strategic Open Pit Mine Planning Course.pdf

23

Sur

face

Min

e D

esig

n

Midlothian Quarry Sequence: One Year Increments on Elevation 760

Page 409: Strategic Open Pit Mine Planning Course.pdf

24

Sur

face

Min

e D

esig

n

Midlothian Quarry Sequence: One Year Increments on Elevation 750

Page 410: Strategic Open Pit Mine Planning Course.pdf

25

Sur

face

Min

e D

esig

n

Midlothian Quarry Sequence: One Year Increments on Elevation 750

Page 411: Strategic Open Pit Mine Planning Course.pdf

26

Sur

face

Min

e D

esig

n

Midlothian Quarry Sequence: One Year Increments on Elevation 730

Page 412: Strategic Open Pit Mine Planning Course.pdf

27

Sur

face

Min

e D

esig

n

Midlothian Quarry Sequence: One Year Increments on Elevation 720

Page 413: Strategic Open Pit Mine Planning Course.pdf

28

Sur

face

Min

e D

esig

n

Midlothian Quarry Sequence: One Year Increments on Elevation 700

Page 414: Strategic Open Pit Mine Planning Course.pdf

29

Sur

face

Min

e D

esig

n

Midlothian Quarry Sequence: One Year Increments on Elevation 690

Page 415: Strategic Open Pit Mine Planning Course.pdf

30

Sur

face

Min

e D

esig

n

Equipment Selection

Three Different Options were Evaluated:• One 15 yd3 Caterpillar 992G model loader working

with a 70 ton CAT 775D truck fleet.• One 15 yd3 Caterpillar 992G model loader working

with a 98 ton CAT 777D truck fleet.• One 11 yd3 Caterpillar 990series II model loader

working with a 70 ton CAT 775D truck fleet

Page 416: Strategic Open Pit Mine Planning Course.pdf

31

Sur

face

Min

e D

esig

n

Loader - Truck Fleet Evaluation and Cost Analysis Year 1

Page 417: Strategic Open Pit Mine Planning Course.pdf

32

Sur

face

Min

e D

esig

n

Loader - Truck Fleet Evaluation and Cost Analysis Year 2

Page 418: Strategic Open Pit Mine Planning Course.pdf

33

Sur

face

Min

e D

esig

n

Loader - Truck Fleet Evaluation and Cost Analysis Year 3

Page 419: Strategic Open Pit Mine Planning Course.pdf

34

Sur

face

Min

e D

esig

n

Loader - Truck Fleet Evaluation & Cost Analysis Haul Road Profile

Page 420: Strategic Open Pit Mine Planning Course.pdf

35

Sur

face

Min

e D

esig

n

Loader - Truck Productivity Calculations

Assumptions• 90 % Loader and truck availability resulting

in 81 % fleet availability• 92 % Operator efficiency• 75 % bucket fill factor• 2400 scheduled hrs• 0.55 min. loader cycle time

Page 421: Strategic Open Pit Mine Planning Course.pdf

36

Sur

face

Min

e D

esig

n

Loader - Truck Productivity Calculations

Assumptions (Cont.)• 0.1 min. first bucket dump time• 0.7 min. hauler exchange time• 2492 lbs/yd3 density• 14 ton/pass; 5 passes per truck• 2400 hours per year

Page 422: Strategic Open Pit Mine Planning Course.pdf

37

Sur

face

Min

e D

esig

n

Equipment Productivity & Cost Estimation

• For CAT 992G Loader - 775D Trucks

Page 423: Strategic Open Pit Mine Planning Course.pdf

38

Sur

face

Min

e D

esig

n

Option 1: Cat 992G Loader -775D Trucks

The truck cycle time for four different conditions:

• Year 1: 9.67 minutes• Year 2: 11.05 minutes• Year 3: 10.86 minutes• Year 7: 11.04 minutes

Page 424: Strategic Open Pit Mine Planning Course.pdf

39

Sur

face

Min

e D

esig

n

Option 1: Cat 992G Loader - 775D Trucks Fleet Productivity in Tons

# of 775D's Year 1 Year 2 Year 3 Year 7 1 825,332 808,107 801,532 808,669 2 1,540,565 1,524,899 1,504,316 1,525,959 3 2,111,530 2,108,190 2,070,839 2,109,657 4 2,586,695 2,644,575 2,580,165 2,644,575

Page 425: Strategic Open Pit Mine Planning Course.pdf

40

Sur

face

Min

e D

esig

n

Option 2: Cat 992G Loader -777D Trucks

The truck cycle time for four different conditions

• Year 1: 12.16 minutes• Year 2: 12.63 minutes• Year 3: 12.42 minutes• Year 7: 12.27 minutes

Page 426: Strategic Open Pit Mine Planning Course.pdf

41

Sur

face

Min

e D

esig

n

Option 2: Cat 992G Loader -777D Trucks

# of 777's Year 1 Year 2 Year 3 Year 7 1 945,127 903,286 920,644 934,223 2 1,731,661 1,667,466 1,695,274 1,715,981 3 2,285,652 2,234,289 2,254,834 2,275,379 4 2,737,983 2,714,476 2,724,550 2,731,266

Page 427: Strategic Open Pit Mine Planning Course.pdf

42

Sur

face

Min

e D

esig

n

Operating Cost for the Loader and Trucks

Model Operating CostCAT 992G $125/hrCAT 775 D $63/hrCAT 777 $82/hr

Page 428: Strategic Open Pit Mine Planning Course.pdf

43

Sur

face

Min

e D

esig

n

Operating Cost for the Loader and Trucks

Model Operating CostCAT 992G $125/hrCAT 775 D $63/hrCAT 777 $82/hr

Page 429: Strategic Open Pit Mine Planning Course.pdf

44

Sur

face

Min

e D

esig

n

Loader - Truck Capital Requirements

Model Purchase PriceCAT 992G $1,270,000CAT 775 D $740,000CAT 777 $1,060,000

Page 430: Strategic Open Pit Mine Planning Course.pdf

45

Sur

face

Min

e D

esig

n

Loader - Truck Capital Requirements

• At the start of the production from bench two, $2.1 M is needed to purchase 1 Cat 992G Loader and 775D truck.

• In year 2, additional $1.5M is needed to purchase 2 more Cat 775D trucks.

• For the Cat 992G loader, Cat 777D truck combination, $2.35M and $2.12M would be needed at the start and beginning of year 2.

Page 431: Strategic Open Pit Mine Planning Course.pdf

Sur

face

Min

e D

esig

n

Loaders and Shovels

Comparative Analysis

Dr. Kadri DagdelenColorado School of Mines

Source: J. Wiebmer, Caterpillar Incorporated

Page 432: Strategic Open Pit Mine Planning Course.pdf

2

Sur

face

Min

e D

esig

n

Hydraulic Shovel Applications

• Hard Digging• Poorly shoot material• Selective loading• Wet, jagged floor• Pitching floor• Single face operation

Page 433: Strategic Open Pit Mine Planning Course.pdf

3

Sur

face

Min

e D

esig

n

Hydraulic Shovel Selection Considerations

• Multiple loading fronts• Fast cycle time (25 to 30

seconds)• Low capital costs• Moderate mobility• Highly productive

Page 434: Strategic Open Pit Mine Planning Course.pdf

4

Sur

face

Min

e D

esig

n

Hydraulic ShovelFavorable Site Conditions

• Single loading face• Tight digging materials• Face height equals to stick

length• Some will dig below and

above• Soft floors

Page 435: Strategic Open Pit Mine Planning Course.pdf

5

Sur

face

Min

e D

esig

n

Hydraulic ShovelUnfavorable Site Conditions

• Requires clean-up support• Excessive tramming• High benches

Page 436: Strategic Open Pit Mine Planning Course.pdf

6

Sur

face

Min

e D

esig

n

Wheel Loader Applications

• Mobility and versatility• Well blasted material• Low pile profile• Smooth, level floor• No clean-up support equipment• Short mine life

Page 437: Strategic Open Pit Mine Planning Course.pdf

7

Sur

face

Min

e D

esig

n

Wheel LoaderSelection Considerations

• Highly mobile/versatile• High bucket fill factors• Low capital costs• No clean-up support

Page 438: Strategic Open Pit Mine Planning Course.pdf

8

Sur

face

Min

e D

esig

n

Wheel LoaderFavorable Site Conditions

• Good loading materials• Lower face profile• Multi-face loading

Page 439: Strategic Open Pit Mine Planning Course.pdf

9

Sur

face

Min

e D

esig

n

Wheel LoaderUnfavorable Site Conditions

• Poor underfooting (tire cost)• Soft floor• Tight load area

Page 440: Strategic Open Pit Mine Planning Course.pdf

10

Sur

face

Min

e D

esig

n

Comparison Shovels vs. Loaders

Hydraulic Shovel Wheel Loader

% Operating Weight as bucket payload

8-11% 18-21%

Cost/CY of capacity ($1000)

100-120 60-80

Economic life (1000 hours)

30-60 30-60

Operating Cost/ton 0.07 - 0.12 0.07 - 0.12

Market Share (1980) 15% 85%

Market Share (1990) 30% 70%

Page 441: Strategic Open Pit Mine Planning Course.pdf

11

Sur

face

Min

e D

esig

n

Mobility

0 200 400 600 800 1000 1200 1400

HydraulicShovel

Wheel Loader

Feet Traveled in One Minute

Page 442: Strategic Open Pit Mine Planning Course.pdf

12

Sur

face

Min

e D

esig

n

Breakout Force

• For similar bucket capacities, a hydraulic shovel and a wheel loader will show approximately the same breakout force.

• However, because the difference in bucket shapes, the shovel can apply twice as much force.

• The shovel can apply the force over its reach of the face.

Page 443: Strategic Open Pit Mine Planning Course.pdf

13

Sur

face

Min

e D

esig

n

Bucket Fill Factors

Hydraulic Front Shovels 80-85%

Hydraulic backhoes 100%

Caterpillar wheel loaders 100-115%

Other wheel loaders 85-95%

Page 444: Strategic Open Pit Mine Planning Course.pdf

14

Sur

face

Min

e D

esig

n

Power and Fuel

• Hydraulic shovels burn less fuel per hour than wheel loaders.

• But considering tons moved per gallon burned, wheel loaders and hydraulic shovel compare very favorable to each other.

Page 445: Strategic Open Pit Mine Planning Course.pdf

15

Sur

face

Min

e D

esig

n

Two-to-Three Minute Rule

• A truck does not make money when its tires are not running.

• Truck load times should be in the two to three minute range.

• Loading times are reduced by the use of the right loading tool, better rock fragmentation, operator training, and face supervision.

Page 446: Strategic Open Pit Mine Planning Course.pdf

16

Sur

face

Min

e D

esig

n

Loading Tool Preferences

85% 15%

60% 40%

50% 50%

Region

North & South America

Europe, Africa, Middle East

Australia, Far East

Page 447: Strategic Open Pit Mine Planning Course.pdf

17

Sur

face

Min

e D

esig

n

Hydraulic Shovel Production Range

Operating Weight (Tons)

Production Range (tons/hour)

140 800 - 1,100

230 1,100 - 1,800

340 1,600 - 2,400

620 3,000 - 4,000

Page 448: Strategic Open Pit Mine Planning Course.pdf

18

Sur

face

Min

e D

esig

n

Wheel Loader Production Range

ModelProduction Range

(tons/hour)

Cat 994 2,700 - 3,100

Cat 992D 1,300 - 1,700

Cat 988B 700 - 900

Cat 980F 500 - 700

Cat 966F 300 - 500

Page 449: Strategic Open Pit Mine Planning Course.pdf

19

Sur

face

Min

e D

esig

n

Conclusions

• No two pits are the same.

• There is a wide array of loading tools to meet operational needs.

• Analysis, not luck, will yield the winner for your operation

Page 450: Strategic Open Pit Mine Planning Course.pdf

Types of Mobile Surface Mining Equipment

•Dozers

•Scrapers

•Trucks

•Front-end Loaders

•Hydraulic Excavators

•Electric Shovels

•Draglines

•Bucket Wheel Excavators

•Blast Hole Drills

Page 451: Strategic Open Pit Mine Planning Course.pdf

Other Bulk Material Handling Systems

Surface and Underground Mining

•Belt Conveyors•Rail Haulage

Page 452: Strategic Open Pit Mine Planning Course.pdf

Types of Underground Mining Equipment

•Blast Hole Drills•Roofbolters•Slushers•Overshot Loaders•Load-Haul-Dump Units (LHDs)•Trucks•Belt Conveyors•Rail Transportation•Hoisting Systems

Page 453: Strategic Open Pit Mine Planning Course.pdf

Loading & Hauling EquipmentLoading Hauling Combination Loading Hauling Combination

Rubber WheelFront End

LoaderTrucks

Loader Scrapers

Front End Loader

TrucksLoad Haul

Dump Bulldozers

Back Hoe GradersOver Shot Loaders

CrawlerTrack

LoaderBulldozers

Track Loaders

Hydraulic Shovel

Bucket Wheel Excavator

Hydraulic Shovel s

Cable Shovel

Over Shot Loaders

Drag Line

Back Hoe

RailConventional

Rail Cars Over Shot Loaders

Mine Cars/ Locomotives

OtherWalking

Drag LinePneumatic/ Hydraulic

Pneumatic/ Hydraulic

Slusher

Dredge Conveyer Conveyers

Skips

SURFACE UNDERGROUND

Page 454: Strategic Open Pit Mine Planning Course.pdf

Comparative Equipment Size

Page 455: Strategic Open Pit Mine Planning Course.pdf

Transport Distances

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Page 456: Strategic Open Pit Mine Planning Course.pdf

Dozers

The dozer, or bulldozer is a crawler or wheel driven tractor with a

front mounted blade for digging and pushing material.

It is used to both excavate and transport material over short

distances.

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Page 457: Strategic Open Pit Mine Planning Course.pdf

Dozer Powered Functions

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Page 458: Strategic Open Pit Mine Planning Course.pdf

Typical Dozer Production Cycle

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Page 459: Strategic Open Pit Mine Planning Course.pdf

Applications

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Land clearance: The dozer can be sized to provide sufficient power, and with proper operating techniques can move most obstacles in its path, including boulders, trees, etc. This makes it the primary tool in clearing land prior to mining. Special blades are available for this application.

Stripping overburden: Some mine plans utilize scrapers and dozers for overburden removal. The dozer, in these operations,moves a portion of the overburden by pushing it over the highwall.

Grading and leveling mining benches: Draglines, electric shovels and wheel excavators require a flat work surface free of boulders; dozers are commonly used in this clean-up operation.

Page 460: Strategic Open Pit Mine Planning Course.pdf

Applications

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Feeding a belt conveyor: The dozer can be effectively employed to push material into a "belt loader" which in turn feeds a belt conveyor.

Trapping for loaders: The efficiency of small to medium sized loading equipment can be improved by using a dozer to rip and position material to be loaded.

Reclamation: Dozers are a basic tool for leveling and recontouringmined out land. Special blades and special wheel models are available for this type of work.

Page 461: Strategic Open Pit Mine Planning Course.pdf

Fait-Allis 41B with single shank ripper leveling dragline spoil piles.

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Page 462: Strategic Open Pit Mine Planning Course.pdf

CAT D11, Black Thunder Mine, Wyoming, Spring 2002

Page 463: Strategic Open Pit Mine Planning Course.pdf

CAT D11, Black Thunder Mine, Wyoming, Spring 2002

Page 464: Strategic Open Pit Mine Planning Course.pdf

CAT D11, Black Thunder Mine, Wyoming, Spring 2002

Page 465: Strategic Open Pit Mine Planning Course.pdf

Scrapers

The scraper is a rather unique machine because of its ability to

excavate material in thin horizontal layers, transport the material a

considerable distance, and then discharge it in a spreading action.

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Page 466: Strategic Open Pit Mine Planning Course.pdf

Scrapers

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Page 467: Strategic Open Pit Mine Planning Course.pdf

Scraper Powered Functions

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Page 468: Strategic Open Pit Mine Planning Course.pdf

Scrapers

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Page 469: Strategic Open Pit Mine Planning Course.pdf

Applications

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Topsoil removal: The scraper is broadly used in those activities which involve selective removal of horizontal horizons and transport to storage.

General reclamation: The scraper is applied in the rough leveling and contouring phase and for replacement of the upper horizons prior to revegetation.

Ore/Coal removal (with or without ripping): Scrapers are employed in cases where the seams are thin and other types of excavating equipment are inefficient.

Page 470: Strategic Open Pit Mine Planning Course.pdf

Applications

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Overburden removal (with or without prior ripping): These can be either initial cuts or prebenching operations for other excavating equipment, or complete overburden removal.

The latter case requires a well planned circular operational layout to minimize travel distances and utilize downgrade loading and dumping.

Typically, operations of this type use dozers for preshaping, supplementary material transport and push-pull scraperloading techniques.

Page 471: Strategic Open Pit Mine Planning Course.pdf

x

Terex S-24B tandem scraper self loading overburden.(Source: Surface Mining Equipment, Martin, et. al., 1982)

Page 472: Strategic Open Pit Mine Planning Course.pdf

Trucks

A truck is simply a mobile piece of equipment for hauling material.

It is often an integral part of the material handeling activities in the

mine for either transport of ore from the face to processing or

stockpile, or for transport of overburden to spoil.

Page 473: Strategic Open Pit Mine Planning Course.pdf

Trucks

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Page 474: Strategic Open Pit Mine Planning Course.pdf

Truck Powered Functions

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Page 475: Strategic Open Pit Mine Planning Course.pdf

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Page 476: Strategic Open Pit Mine Planning Course.pdf

Applications

(Source: Surface Mining Equipment, Martin, et. al., 1982)

These trucks are used exclusively for material transport. The material can be just about anything but, in mining, the broad classifications are:

•Overburden•Ore/Coal

When trucks are used to haul overburden, the mine normally has an open pit or area mine plan with dumping off of spoil benches.

Trucks can be used to haul ore/coal to a hopper or stockpile, invirtually any surface mine plan.

Dumping to stockpile is generally done in shallow lifts.

Page 477: Strategic Open Pit Mine Planning Course.pdf

Applications

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Bottom dump units, driving over a grizzly, are used to feed a hopper.

A back-in hopper station is utilized with rear dumps.

In some cases the trucks carrying coal directly to a nearby power plant will on the return trip transport ash back into the pit for burial.

Page 478: Strategic Open Pit Mine Planning Course.pdf

Large Haul Trucks, Cripple Creek –Victor, Colorado, Fall 2002

Page 479: Strategic Open Pit Mine Planning Course.pdf

Large Haul Truck, Cripple Creek –Victor, Colorado, Fall 2002

Page 480: Strategic Open Pit Mine Planning Course.pdf

Wabco 3200B, 250 ton, three axel rear dump.

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Page 481: Strategic Open Pit Mine Planning Course.pdf

Rimpull three axel bottom dump coal hauler.

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Page 482: Strategic Open Pit Mine Planning Course.pdf

(World Mining Equipment, September 2002)

Page 483: Strategic Open Pit Mine Planning Course.pdf

(World Mining Equipment, March 2003)

Page 484: Strategic Open Pit Mine Planning Course.pdf
Page 485: Strategic Open Pit Mine Planning Course.pdf
Page 486: Strategic Open Pit Mine Planning Course.pdf
Page 487: Strategic Open Pit Mine Planning Course.pdf
Page 488: Strategic Open Pit Mine Planning Course.pdf

Front-End Loaders (FEL)The front-end loader is a wheel or crawler mounted tractor with a

front mounted bucket and is utilized in excavating, loading, and

transporting material.

Because of its versatility, the front end loader is found in a wide

variety of mining applications.

Page 489: Strategic Open Pit Mine Planning Course.pdf

FEL Powered Functions

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Page 490: Strategic Open Pit Mine Planning Course.pdf

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Page 491: Strategic Open Pit Mine Planning Course.pdf

Applications

(Source: Surface Mining Equipment, Martin, et. al., 1982)

The wheel loader is a competitive excavator, loader and transporter.

It competes with shovels, dozers and, over short transport distances, with scrapers and trucks.

Being quite fast, mobile, and versatile, it can be used in a number of mine applications.

Because the FEL has generally not been considered to have the digging ability of a shovel in consolidated digging faces, it finds many of its applications in softer formations, coal/ore andstockpile work.

The larger sizes are more rugged and powerful, and are proving themselves in difficult digging.

Page 492: Strategic Open Pit Mine Planning Course.pdf

Applications

(Source: Surface Mining Equipment, Martin, et. al., 1982)

The primary mine applications are the following:

•Loading and/ or transporting topsoil

•Loading and/ or transporting coal/ ore from the digging face

•Loading and/or transporting coal/ore from stockpile

•Loading and/or transporting overburden and waste

In all of the above loading can be into trucks, hoppers, railroad cars, or belt loaders.

Transport can be for distances up to 1000 feet on the level or grades up to 12%.

Page 493: Strategic Open Pit Mine Planning Course.pdf

CAT 994D loading a haul truck

Heavy Equipment, John Tipler, 2000

Page 494: Strategic Open Pit Mine Planning Course.pdf

Hydraulic Excavators

Hydraulic shovels, primarily a European development, have

proven themselves on construction projects.

The have now reached a level of reliability and have increased in size to the point where units are common in surface mining applications.

Page 495: Strategic Open Pit Mine Planning Course.pdf

Digging Profile

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Page 496: Strategic Open Pit Mine Planning Course.pdf

Hydraulic Excavator Powered Functions

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Page 497: Strategic Open Pit Mine Planning Course.pdf

ApplicationsHydraulic machines are employed in overburden removal, coal/ore loading or, in the smaller sizes, for utility work generally related to mine drainage systems.

The hydraulic shovel is primarily an excavating and loading device. While it can swing and/or propel to transport material short distances, it is used almost exclusively to load trucks or, in some cases, hoppers/crushers.

Hoes have similar uses to shovels. However, their below grade digging capability makes them particularly suited to tasks such as trenching or excavating under water.

Hoes are utilized in mining when floor conditions warrant keeping machines off the bottom of the pit.

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Page 498: Strategic Open Pit Mine Planning Course.pdf

Typical Hydraulic Shovel Production Cycle

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Page 499: Strategic Open Pit Mine Planning Course.pdf

Typical Hydraulic Hoe Production Cycle

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Page 500: Strategic Open Pit Mine Planning Course.pdf

Heavy Equipment, John Tipler, 2000

CAT 5230 hydraulic excavator loading a haul truck

Page 501: Strategic Open Pit Mine Planning Course.pdf

Electric ShovelsThe shovel is one of the oldest types of excavating equipment.

With time, the machines grew in capacity , steam power was replaced by gas, then diesel fuel and finally, in the larger units used in mining today, by electricity.

In recent years, smaller shovels below 5 cubic yards in capacity are being replaced by front-end loaders and hydraulic machines.

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Page 502: Strategic Open Pit Mine Planning Course.pdf

Steam Shovel Mining Virginia Minnesota, circa 1910

Page 503: Strategic Open Pit Mine Planning Course.pdf

Electric Shovels

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Page 504: Strategic Open Pit Mine Planning Course.pdf

Electric Shovel Powered Functions

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Page 505: Strategic Open Pit Mine Planning Course.pdf

Applications

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Electric shovels generally have the same applications as hydraulic shovels although the electric units are considered to be particularly suited to more severe digging conditions.

They are available in larger sizes and have a proven service record in multi-shift mining operations. Electric shovels also tend to have longer range capabilities.

These shovels are applied in benching operations in either overburden or coal/ore.

Discharge is commonly into trucks but can also be into mobilehoppers.

The larger models and/or those equipped with long range front ends may be applied in direct spoiling overburden removal operations.

Page 506: Strategic Open Pit Mine Planning Course.pdf

Loading Plans

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Page 507: Strategic Open Pit Mine Planning Course.pdf

The Bucyrus-Erie 1850-B Brutus with 90-yard dipper at Pittsburg and Midway Coal Mining Company in 1961.

This shovel is currently maintained by a preservation group.

Extreme Mining Machines, Keith Haddock, 2001

Page 508: Strategic Open Pit Mine Planning Course.pdf

The last stripping shovel produced was this 105-yard Marion 5900, sold in 1971 to Amax Coal Company’s Leahy Mine in Illinois.

Extreme Mining Machines, Keith Haddock, 2001

Page 509: Strategic Open Pit Mine Planning Course.pdf

Draglines

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Page 510: Strategic Open Pit Mine Planning Course.pdf

Draglines

Through the years, the dragline has remained a unique excavating tool and has experienced a dramatic growth in maximum size.

With its long reach and ability to dig to substantial depths below itself, it has had broad applications on many irrigationprojects and, in more recent years, in surface mining.

The hydraulic hoe has, to some extent, replaced the smaller sized diesel draglines but the larger diesel and/ or electric machinesretain their popularity.

Draglines, along with the bucket wheel excavators, are the largest pieces of mobile equipment currently manufactured.

Page 511: Strategic Open Pit Mine Planning Course.pdf

Draglines

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Page 512: Strategic Open Pit Mine Planning Course.pdf

Dragline Powered Functions

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Page 513: Strategic Open Pit Mine Planning Course.pdf

The world’s largest operating dragline (one of two), the Bucyrus2570-WS with 160 yard bucket at the Black Thunder Mine, WY.

Extreme Mining Machines, Keith Haddock, 2001

Page 514: Strategic Open Pit Mine Planning Course.pdf

The 100 yard Marion 8800 loading in Kentucky

Extreme Mining Machines, Keith Haddock, 2001

Page 515: Strategic Open Pit Mine Planning Course.pdf

Bucyrus International’s Big Muskie’s 220-yard bucket easily accommodates a high school band. Photo taken in 1969.

Extreme Mining Machines, Keith Haddock, 2001

Page 516: Strategic Open Pit Mine Planning Course.pdf

Bucket Wheel ExcavatorsWheel excavators dig with a rotating bucket wheel that discharges the material onto a belt conveyor.

The material is transported on this conveyor or a series of beltconveyors until it is discharged from the machine.

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Page 517: Strategic Open Pit Mine Planning Course.pdf

Bucket Wheel Excavators

Wheel excavators have been used, in limited numbers, for continuous excavation of unconsolidated materials starting back in the mid 1920's.

Interest in the machines has been much greater overseas with theGermans, in particular, performing extensive application studies and machine development.

Overall use within the United States has been very limited.

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Page 518: Strategic Open Pit Mine Planning Course.pdf

Bucket Wheel Excavator Powered Functions

(Source: Surface Mining Equipment, Martin, et. al., 1982)

Page 519: Strategic Open Pit Mine Planning Course.pdf

Applications

(Source: Surface Mining Equipment, Martin, et. al., 1982)

There are currently very few bucket wheel excavators in service in the US. They have been used for:

•Overburden excavation with direct spoiling

•Overburden excavation with conveyor or truck loading, prestripping for a large dragline or stripping shovel

•Large earthmoving projects (medium size or small fixed wheels)

•Coal excavation with conveyor or truck loading(medium size or small fixed wheels)

•Topsoil removal and Reclamation leveling (small fixed wheels)

Page 520: Strategic Open Pit Mine Planning Course.pdf

Rhineland Lignite Mine, Germanywww.mining- technology.com

Page 521: Strategic Open Pit Mine Planning Course.pdf

World Mining Equipment, September 2002

Förderanlagen Magdenburg (FAM) bucket wheel excavator.

Page 522: Strategic Open Pit Mine Planning Course.pdf

Sur

face

Min

e D

esig

n

Loading Equipment

Dr. Kadri Dagdelen

Colorado School of Mines

Page 523: Strategic Open Pit Mine Planning Course.pdf

2

Sur

face

Min

e D

esig

n

Excavators

Page 524: Strategic Open Pit Mine Planning Course.pdf

3

Sur

face

Min

e D

esig

n

Hydraulic Shovels Specifications

Page 525: Strategic Open Pit Mine Planning Course.pdf

4

Sur

face

Min

e D

esig

n

Excavator Specifications

Page 526: Strategic Open Pit Mine Planning Course.pdf

5

Sur

face

Min

e D

esig

n

Digging EnvelopesFront Shovels

Page 527: Strategic Open Pit Mine Planning Course.pdf

6

Sur

face

Min

e D

esig

n

Curl and Crowd ForcesFront Shovels

Page 528: Strategic Open Pit Mine Planning Course.pdf

7

Sur

face

Min

e D

esig

n

Digging EnvelopesExcavators

Page 529: Strategic Open Pit Mine Planning Course.pdf

8

Sur

face

Min

e D

esig

n

Excavators Bucket

Page 530: Strategic Open Pit Mine Planning Course.pdf

9

Sur

face

Min

e D

esig

n

Loaders

Page 531: Strategic Open Pit Mine Planning Course.pdf

10

Sur

face

Min

e D

esig

n

Breakout ForceLoaders

Page 532: Strategic Open Pit Mine Planning Course.pdf

11

Sur

face

Min

e D

esig

n

Breakout Force from RackbackLoaders

Page 533: Strategic Open Pit Mine Planning Course.pdf

12

Sur

face

Min

e D

esig

n

Carry PositionLoaders

Page 534: Strategic Open Pit Mine Planning Course.pdf

13

Sur

face

Min

e D

esig

n

900 Series II – Dimensions Loaders

Page 535: Strategic Open Pit Mine Planning Course.pdf

14

Sur

face

Min

e D

esig

n

900 Series II – Dimensions Loaders

Page 536: Strategic Open Pit Mine Planning Course.pdf

15

Sur

face

Min

e D

esig

n

SpecificationsLoaders

Page 537: Strategic Open Pit Mine Planning Course.pdf

16

Sur

face

Min

e D

esig

n

SpecificationsLoaders

Page 538: Strategic Open Pit Mine Planning Course.pdf

17

Sur

face

Min

e D

esig

n

Travel Time – LoadedLoaders

Page 539: Strategic Open Pit Mine Planning Course.pdf

18

Sur

face

Min

e D

esig

n

Travel Time – EmptyLoaders

Page 540: Strategic Open Pit Mine Planning Course.pdf

19

Sur

face

Min

e D

esig

n

Excavator Production Calculations

A standard formula for cyclic excavators can be employed:

O = B x BF x D x HS x J x A x 3,600 seconds(1+S) C hour

Bucket Load Buckets/Period

Page 541: Strategic Open Pit Mine Planning Course.pdf

20

Sur

face

Min

e D

esig

n

Bucket Load

B x BF x D/(1 + S) < Recommended Operating Capacity

• With wheel loaders:50% of full turn static tipping load fora specific bucket type

• With front shovels:Maximum load

Page 542: Strategic Open Pit Mine Planning Course.pdf

21

Sur

face

Min

e D

esig

n

Bucket Load

• Bucket weight depends on size, duty and ground engaging tools

• Bucket size depends on reach• Bucket size (B) based on 2:1 heap• Bucket fill (BF) decreases with increasing

material consolidation

Page 543: Strategic Open Pit Mine Planning Course.pdf

22

Sur

face

Min

e D

esig

n

(CAT)

Wheel Loader Bucket Fill Factors

Page 544: Strategic Open Pit Mine Planning Course.pdf

23

Sur

face

Min

e D

esig

n

Weight of Materials

(CAT)

Page 545: Strategic Open Pit Mine Planning Course.pdf

24

Sur

face

Min

e D

esig

n

Bucket Load

• % Swell increases and load factor decreases with degree of consolidation

• In place density (D) important and should be a measured number

• Loose density (D/(1 + S)) important and should be a measures number

Page 546: Strategic Open Pit Mine Planning Course.pdf

25

Sur

face

Min

e D

esig

n

Buckets/Period

• Average cycle time (C) based on standard cycle time adjusted for:• Material• Material fragmentation• Material size distribution• Pile configuration

Page 547: Strategic Open Pit Mine Planning Course.pdf

26

Sur

face

Min

e D

esig

n

Buckets/Period

• Average cycle time (C) based on standard cycle time adjusted for:• Consistency of operation• Swing angle (Shovels)• Travel distance (Loaders)• Operator ability

Page 548: Strategic Open Pit Mine Planning Course.pdf

27

Sur

face

Min

e D

esig

n

Wheel Loader Cycle Time

Average cycle time for truck loading increases with machine size

.60-.7015-21

.55-.607.5-11

.50-.555.0-7.5

.45-.501.7-4.5Cycle time (min)Loader Size (cy)

Page 549: Strategic Open Pit Mine Planning Course.pdf

28

Sur

face

Min

e D

esig

n

Cycle Time

• Hours scheduled (HS) usually a given, based on management preferences and required output

• Longer shifts appear to be trend to minimize start-up, shut-down impact

Page 550: Strategic Open Pit Mine Planning Course.pdf

29

Sur

face

Min

e D

esig

n

Cycle Time

• Job factor (J) depends on: • Truck assignment• Management issues• Job layout (Blending, etc.)

Page 551: Strategic Open Pit Mine Planning Course.pdf

30

Sur

face

Min

e D

esig

n

Cycle Time

• Mechanical availability (A) depends on:• Material• Management/suppliers• Age of machine• Schedule

Page 552: Strategic Open Pit Mine Planning Course.pdf

31

Sur

face

Min

e D

esig

n

Loading Methods

• Loading method impacts cycle time and job factor• Wheel loaders

• Y pattern used with machine digging point left to right• Truck spotting location important• With a limited truck fleet and excess loader capacity,

staggered and chain loading can be utilized

Page 553: Strategic Open Pit Mine Planning Course.pdf

32

Sur

face

Min

e D

esig

n

Loading Methods

Page 554: Strategic Open Pit Mine Planning Course.pdf

33

Sur

face

Min

e D

esig

n

Loading Methods

(Mining Magazine)

Page 555: Strategic Open Pit Mine Planning Course.pdf

34

Sur

face

Min

e D

esig

n

Shovels:Double Back-Up

Options include • Double back-up• Single back-up• Drive-by• Modified drive-by

Page 556: Strategic Open Pit Mine Planning Course.pdf

35

Sur

face

Min

e D

esig

n

Shovels:Double Back-Up

• Trucks loaded on both sides• Average swing angle reduces• Clean-up allowed on one side while loading

continues• Moves required as shovel penetrates bank

Page 557: Strategic Open Pit Mine Planning Course.pdf

36

Sur

face

Min

e D

esig

n

Shovels:Double Back-Up

Page 558: Strategic Open Pit Mine Planning Course.pdf

37

Sur

face

Min

e D

esig

n

Shovels:Double Back-Up

Requires balance of move time versus cycle time

(Oslund and Russell)

Page 559: Strategic Open Pit Mine Planning Course.pdf

38

Sur

face

Min

e D

esig

n

Shovels:Single Back-Up

• Truck loaded on one side• Larger swing angle• Potential clean-up delays• Potential spotting delays depending on

excavator first cycle

Page 560: Strategic Open Pit Mine Planning Course.pdf

39

Sur

face

Min

e D

esig

n

Shovels:Single Back-Up

Page 561: Strategic Open Pit Mine Planning Course.pdf

40

Sur

face

Min

e D

esig

n

Shovels:Drive-By

• Used with tractor trailers• Large swing angles• Potential clean-up delays• Minimal amount of shovel moves• Blending problems

Page 562: Strategic Open Pit Mine Planning Course.pdf

41

Sur

face

Min

e D

esig

n

Shovels:Drive-By

Page 563: Strategic Open Pit Mine Planning Course.pdf

42

Sur

face

Min

e D

esig

n

Shovels:Modified Drive-By

• Truck backs in to reduce swing angle• Potential clean-up delays• Minimal amount of shovel moves• Blending problems• Depth of cut effects cycle time and move

time

Page 564: Strategic Open Pit Mine Planning Course.pdf

43

Sur

face

Min

e D

esig

n

Shovels:Modified Drive-By

Page 565: Strategic Open Pit Mine Planning Course.pdf

44

Sur

face

Min

e D

esig

n

Modified Drive-By:Optimum Width

Page 566: Strategic Open Pit Mine Planning Course.pdf

Production Estimating of Material Movement With Earth Moving Equipment

There are five factors which need to be considered in preparing aproduction estimate of earthmoving equipment for any particular job.

These factors include:1. Earthmoving Cycle Components2. Job Efficiency Factors3. Material Weights & Swell Factors4. Vehicle Payloads5. Selection of Equipment

Page 567: Strategic Open Pit Mine Planning Course.pdf

1. Earthmoving Cycle Components

The productivity cycle of any earthmoving job may be separatedinto six components:

1. load, 2. haul or push, 3. dump, 4. return, 5. spot,6. and delay.

Each of these components is responsible for a certain percentage of thetotal cycle time.

The factors affecting these components will determine the time eachcomponent will require.

Page 568: Strategic Open Pit Mine Planning Course.pdf

Load Factors

• Performance ability of unit• Hauling distance• Haul road condition• Grades• Miscellaneous factors affecting haul speed

Haul/Push Factors

• Size and type of loading machine • Type & condition of material to be loaded• Capacity of unit • Skill of the loading operator

Page 569: Strategic Open Pit Mine Planning Course.pdf

Dump Factors

• Performance ability of unit• Return distance• Haul road condition• Grades• Miscellaneous factors affecting return speed

Return Factors

• Destination of material -Hopper, Over Bank, Fill, Stockpile, etc.• Condition of dump area• Type & maneuverability of hauling unit• Type & condition of material

Page 570: Strategic Open Pit Mine Planning Course.pdf

Spot Factors

• Time spent waiting on loading unit or pusher• Time spent waiting to dump –at crusher

Delay Factors

• Maneuverability of unit• Maneuver area available• Type of loading machine• Location of loading equipment

Page 571: Strategic Open Pit Mine Planning Course.pdf

2. Job Efficiency FactorsAn estimate must indicate sustained, or average earthmoving production over a long period of time.

Overly optimistic hourly production estimates will result in failure to maintain forecasted production, and an insufficient number of unitsassigned to the job.

It is necessary to allow for the unavoidable delays encountered on all operations such as night operating, shovel moving, blasting, weather, traffic, shutdowns, or for factors such as management and supervisionefficiency, operator experience, proper balance of auxiliary equipment such as tamping roller, pusher or spreader bulldozers, proper crusher capacity, etc.

Page 572: Strategic Open Pit Mine Planning Course.pdf

2. Job Efficiency FactorsThe maximum productivity of an earthmover should be derated to meet actual conditions. Typical deration factors are found in the following table:

Page 573: Strategic Open Pit Mine Planning Course.pdf

3. Material Weights & Swell FactorsThe weight of material is most often expressed in pounds per cubic yard.

Undisturbed or “in place” material is called a bank cubic yard (BCY).

Material in a loose, broken, or blasted state is called a loose cubic yard (LCY).

Page 574: Strategic Open Pit Mine Planning Course.pdf

3. Material Weights & Swell FactorsThe relationship between bank and loose cubic yards is established by the swell factor or percent swell.

For example, the percent swell of shale is 33% indicating that one bank cubic yard of shale will swell to 1.33 cubic yards in the loosestate.

Shale weighs 2800 pounds per bank cubic yard. At a swell factor of 0.75 (inverse of 1.33) the weight of one loose cubic yard of shale is 2100 pounds (2800 pounds * 0.75).

Note: Earthfill projects employ mechanical means such as rolling, tamping and adding water to compress the deposited loose cubic yard back to the state it was in the bank. This compaction may reduce the volume of the bank cubic yard by as much as 15%.

Page 575: Strategic Open Pit Mine Planning Course.pdf

4. Vehicle PayloadsThe rated payload of hauling units is given on the specification sheets in pounds, struck (water level) capacities and SAE capacities.

For haulers the SAE heaped capacity is for a load at a 2: 1 slope. For scrapers the SAE heaped capacity is for a load at a 1: 1 slope.

For estimating purposes, the payload in pounds should not be exceeded.

Page 576: Strategic Open Pit Mine Planning Course.pdf

Vehicle Payloads Should Not Be Exceeded

Page 577: Strategic Open Pit Mine Planning Course.pdf

4. Vehicle PayloadsLoaders, scrapers and haulers all carry material in the loose condition.

To assure adequate volumetric capacity, the pounds payload should be divided by the weight per loose cubic yard and compared to the heaped capacity as shown below:

Page 578: Strategic Open Pit Mine Planning Course.pdf

5. Selection of Equipment

After the estimator has examined the job requirements and operating conditions and decided to investigate earthmoving equipment, a tentative equipment selection will be made.

The final decision will, of course, depend on which method offers the lowest cost per yard or ton.

In some cases, methods such as draglines, belt conveyors, etc. will also be considered.

Page 579: Strategic Open Pit Mine Planning Course.pdf

Example

Rock density: 11 cubic feet per short tonSwell factor: 1.6

ShovelBucket capacity: 18.8 cubic yardsDigging cycle time: 30 seconds per passBucket fill factor: 0.92

TruckLoad capacity: 62 cubic yards struck

88 cubic yards at 2:1 SAE140 tons payload capacity

a) Calculate the number of passes to load the truck.b) Calculate the total time required to load a truck.

Page 580: Strategic Open Pit Mine Planning Course.pdf

Loading and HaulingFleet Productivity

Dr. Kadri Dagdelen

Source : Hrebar – Lafarge 2000 Presentation

Sur

face

Min

e D

esig

n

Page 581: Strategic Open Pit Mine Planning Course.pdf

2

Truck Selection

• Number and type of trucks selected should be based on overall system economics

• Lowest cost fleet selected considering operating and capital coats

Sur

face

Min

e D

esig

n

Page 582: Strategic Open Pit Mine Planning Course.pdf

3

Truck Selection

• Production requirement and operating schedule

• Material characteristics• Density in place and loose, swell• General size distribution, particularly maximum

and minimum sizes and percentage of total• Hardness and texture• Ease of handling

Sur

face

Min

e D

esig

n

Page 583: Strategic Open Pit Mine Planning Course.pdf

4

Truck Selection

• Physical and climatic conditions• Effect of altitude on engine efficiency• Effect of ambient temperature on engine cooling, tire

performance, and use of lubricants• Effect of rainfall, frost, snow, fog, etc. on road conditions

and travel

• Haul road characteristics• Length, grade, and surface condition of

segment

Sur

face

Min

e D

esig

n

Page 584: Strategic Open Pit Mine Planning Course.pdf

5

Truck Selection

• Loading• Space and ground conditions at loading point• Type and size of loading equipment• Total availability of loading equipment

• Dumping• Dumping arrangements: rear dump into hopper, drive

over hopper, edge of spoil, windrow, etc.• Space and ground condition at dump point• Total availability of down stream equipment

Sur

face

Min

e D

esig

n

Page 585: Strategic Open Pit Mine Planning Course.pdf

6

Truck Selection:Rear Dump

• High horsepower to weight ratio• Deep pits, high grades, maneuverability required

high impact and rough in pit conditions. • Can be used with any type of material ( e.g.,

blocky, free flowing, etc. )• Used for dumping into hoppers or over bank or fill• Economic distance limited

Sur

face

Min

e D

esig

n

Page 586: Strategic Open Pit Mine Planning Course.pdf

7

Truck Selection:Bottom Dump

• Low HP/weight ratio• Free flowing material• Dumping over hopper or in windrow• Operational advantages: Dump on the move,

More favorable tire and axle loading, high speed hauling on level hauls

• Moderate grade and long distance hauls

Sur

face

Min

e D

esig

n

Page 587: Strategic Open Pit Mine Planning Course.pdf

8

Production Calculations

• The prime mover delivers a force that propels the haulage vehicle plus the load

• The force the drive wheels deliver to the ground is referred to as rimpull

• This force is a function of: the torque developed by the engine, the ratio of the gears, and the size of the wheels

Sur

face

Min

e D

esig

n

Page 588: Strategic Open Pit Mine Planning Course.pdf

9

Production Calculations

• Maximum velocity is reached when rimpullis equal to resisting forces of gravity, rolling resistance. etc.

Horsepower x 375 x EfficiencyAvailable Rimpull =

Speed in MPH

Sur

face

Min

e D

esig

n

Page 589: Strategic Open Pit Mine Planning Course.pdf

10

Rimpull vs. Velocity

Sur

face

Min

e D

esig

n

Page 590: Strategic Open Pit Mine Planning Course.pdf

11

Rolling Resistance

• Measure of the force required to overcome internal bearing friction and the retarding effect between the tires and the ground (i.e., tire penetration and tire flexing).

• Expressed in terms of lb/ton vehicle weight or % vehicle weight

• Haul Road Resistance can be estimated by:RR = 2%+1.5% per inch of tire penetration

Sur

face

Min

e D

esig

n

Page 591: Strategic Open Pit Mine Planning Course.pdf

12

Rolling Resistance FactorsTYPICAL ROLLING RESISTANCE FACTORS

Various tire sizes and inflation pressures will greatly reduce or increase the rolling resistance. The values in this table are approximate, particularly for the track and track+ tire machines. These values can be used for estimating purposes when specific performance information on particular equipment and given soil conditions is not available See Mining and Earthmoving Section for more detail:

ROLLING RESISTANCE, PERCENT ̀ Tires Track Track

UNDERFOOTING Bias Radial ** +Tires A very hard, smooth roadway, concrete, cold asphalt or dirt surface, no penetration or flexing 1.5%* 1.2% 0% 1.0% A hard; smooth, stabilized surfaced roadway without penetration under load; watered; maintained 2.0% 1.7% 0% 1.2% A firm, smooth, rolling roadway with dirt or light surfacing, flexing slightly under load or undulating, maintained fairly regularly, watered 3.0% 2.5% 0% 1.8% A dirt roadway, rutted or flexing under load; little maintenance, no water, 25 mm (1”) tire penetration or flexing 4.0% 4.0% 0% 2.4% A dirt roadway; rutted or flexing under load; little maintenance, no water, 50 mm (2”) tire penetration or flexing 5.0% 5.0% 0% 3.0% Rutted dirt roadway, soft under travel, no maintenance, no stabilization 100 mm (4”) tire penetration or flexing 8.0% 8.0% 0% 4.8% Loose sand or gravel 10.0% 10:0% 2% 7.0% Rutted dirt roadway, soft under travel, no maintenance, no stabilization, 200 mm (8”) tire penetration and flexing 14.0% 14.0% 5% 10:0% Very soft, muddy, rutted roadway, 300 mm (12”) tire penetration, no flexing 20.0% 20.0% 8% 15% *Percent of combined machine weight. **Assumes drag load has been subtracted. to give Drawbar Pull for good to moderate conditions. Some resistance added for soft conditions. (CAT)

Sur

face

Min

e D

esig

n

Page 592: Strategic Open Pit Mine Planning Course.pdf

13

Grade Resistance

• Force required to overcome gravity when moving vehicle uphill. Expressed in % vehicle weight (adds power to vehicle downhill).

• Percent Grade = Vertical rise or drop (ft) x 100Horizontal Distance (ft)

e.g., 60 ft rise in 1,000 ft, Grade = 60/ 1,000 x 100 = 6%Horizontal Distance =

(Horizontal distance2 + vertical distance2)1/2

e.g., (1,0002 +602)1/2 = 1,001.8 ft

Sur

face

Min

e D

esig

n

Page 593: Strategic Open Pit Mine Planning Course.pdf

14

Weights and Traction

• Weights: determines the force required to propel vehicle.• Function of vehicle weight, rated capacity (CY), and

density of material hauled, number of passes of excavator

• Traction: force deliverable can be limited by traction conditions• Usable rimpull is a function of road surface and weight

on the drive wheelsUsable Rimpull =

Coefficient of Traction x Weight on Drive Wheels

Sur

face

Min

e D

esig

n

Page 594: Strategic Open Pit Mine Planning Course.pdf

15

Coefficient of Traction Factors

(CAT)

Sur

face

Min

e D

esig

n

Page 595: Strategic Open Pit Mine Planning Course.pdf

16

(CAT)

Altitude Deration

Sur

face

Min

e D

esig

n

Page 596: Strategic Open Pit Mine Planning Course.pdf

17

Speed Limits

• Speed Limits: limits on curves, in pit, and on main haul roads• Curves based on radius and super elevation• In pit, ramp, and main haul roads, the speed limit

depends on haul road width and conditions

Sur

face

Min

e D

esig

n

Page 597: Strategic Open Pit Mine Planning Course.pdf

18

Acceleration, Deceleration, Operator

• Speeds obtained from performance curves indicate maximum velocity under optimum conditions on a given profile.

• These speeds must be corrected for acceleration, deceleration, and operator performance to yield reasonable haul and return times.• F=Ma Simulation utilized to account for acceleration and

deceleration • Time studies indicate that simulated haul times are less

than actual haul times

Sur

face

Min

e D

esig

n

Page 598: Strategic Open Pit Mine Planning Course.pdf

19

Tires

• Limit capability of machine to perform by limiting load and speed

• Ton-mile-per-hour ratings should not be exceeded and depend on:• Weight (Flex/revolution)• Speed (Flexes/period)• Ambient Temperature• Road Surface Temperature

Sur

face

Min

e D

esig

n

Page 599: Strategic Open Pit Mine Planning Course.pdf

20

Tires

TMPH = Average Tire Load x Average Speed for Shift

Average Tire Load = Empty Tire Load + Loaded Tire Load (tons)2

Average Speed = Round Trip (mi) x Trips/ShiftTotal Hours (hr)

Limits by tire type and limits may also include maximumspeed

Sur

face

Min

e D

esig

n

Page 600: Strategic Open Pit Mine Planning Course.pdf

21

Ton-MPH Data

(CAT)

Sur

face

Min

e D

esig

n

Page 601: Strategic Open Pit Mine Planning Course.pdf

22

Estimating Cycle Time

• Limiting factors are considered in developing an estimate of the cycle time. The cycle time consists of variable or travel time (haul and return time) plus the fixed time (load, dump, and spot times).

• Travel time (haul and return times) is a function of payload, vehicle weight, HP/weight ratio, haul road segment lengths, rolling and grade resistance, speed limits, etc.

Sur

face

Min

e D

esig

n

Page 602: Strategic Open Pit Mine Planning Course.pdf

23

Estimating Cycle Time

• Loading time is a function bucket size, fill factor, excavator cycle time, loose material density, and truck capacity

• Other fixed times depend on loading method and dump configuration• Spot and maneuver in loading area (typically .6-.8 min)• Dumping (typically 1-1.2 min)

• Unit production calculated considering truck payload, truck cycle time, hours per shift, and operating efficiencyS

urfa

ce M

ine

Des

ign

Page 603: Strategic Open Pit Mine Planning Course.pdf

24

Unit Production

• Unit Production (Tons/shift)• Truck payload / Truck cycle time x Operating

efficiency x Hours/shift• Units required are a function of total shift tonnage

requirements and unit production and mechanical availability

• Units Required Operating• Tons required/shift / Unit truck production/shift

(Usually rounded up)

Sur

face

Min

e D

esig

n

Page 604: Strategic Open Pit Mine Planning Course.pdf

25

Unit Production

• Units Required Purchased• Units Required Operating (Not rounded) /

Mechanical availability

Sur

face

Min

e D

esig

n

Page 605: Strategic Open Pit Mine Planning Course.pdf

26

Match Factor and System

• Production of the excavator truck system dependent on the number of trucks assigned to the excavator

Sur

face

Min

e D

esig

n

Page 606: Strategic Open Pit Mine Planning Course.pdf

27

Allocations based on at least two approaches:• Number of trucks = Truck cycle time / Load time

(excluding first pass)This calculation approach reduces excavator delays

• Number of trucks = Truck cycle time

Load time (excluding first pass) + Truck exchange time

Match Factor and System

Sur

face

Min

e D

esig

n

Page 607: Strategic Open Pit Mine Planning Course.pdf

28

Match Factor Approach

• Match factor approach reduces truck delays compared to first method. For example:L o a d e r c y c l e t i m e . 5 m i nN o . o f p a s s e s 7E f f e c t i v e l o a d i n g t i m e ( 7 - 1 ) x . 5 3 . 0 0 m i nT r u c k s p o t t i m e ( e x c h a n g e t i m e ) 1 . 3 0 m i nH a u l , d u m p a n d r e t u r n 1 2 . 7 1 m i nT r u c k c y c l e t i m e 1 7 . 0 1 m i n

N o . T r u c k s ( 1 7 . 0 1 / 3 . 0 0 ) 5 . 6 7N o . T r u c k s ( 1 7 . 0 1 / ( 3 . 0 0 + 1 . 3 0 ) ) 3 . 9 6

Sur

face

Min

e D

esig

n

Page 608: Strategic Open Pit Mine Planning Course.pdf

29

System Production

• System production must consider number of trucks, unit production and excavator availability.

• System production• Number of truck/shift x Unit production (Tons/shift)

x Excavator availability

• Complexity of calculations and variability of times leads to use of fleet production simulators such as FPC and TALPAC

Sur

face

Min

e D

esig

n

Page 609: Strategic Open Pit Mine Planning Course.pdf

30

The End

Sur

face

Min

e D

esig

n

Page 610: Strategic Open Pit Mine Planning Course.pdf

TRUCK SELECTION AND PRODUCTION CALCULATIONS

Dr. Kadri Dagdelen

Sur

face

Min

e D

esig

n

Page 611: Strategic Open Pit Mine Planning Course.pdf

2

Wheel Loader Production Calculations

• Example:Calculate the output in tons/hr of a 990 Wheel Loader with a 11cy bucket with .55 min. cycle time and 95% bucket fill factor loading material with 3100 lbs. per LCY. Assume 85% mechanical availability and 83.3% job factor.

Sur

face

Min

e D

esig

n

Page 612: Strategic Open Pit Mine Planning Course.pdf

3

Wheel Loader Production Calculations (Cont.)

• Equation to estimate the production per hour:

O = BC*BF*D*MA*JF*3,600sec(1+SF)*CT hour

Where,O =Production, tons/hrBC =Bucket Size, CY (Usually heaped at 2:1)BF =Bucket Fill Factor, %D =In Place Density, tons/CYMA=Mechanical Availability, %JF =Job Factor, %SF =Material Swell, %100CT =Average cycle time, seconds

Sur

face

Min

e D

esig

n

Page 613: Strategic Open Pit Mine Planning Course.pdf

4

Wheel Loader Production Calculations (Cont.)

• Solution:

O = 11*0.95*1.55*0.85*0.833*3,600sec33sec

= 1252 tons/hr

Sur

face

Min

e D

esig

n

Page 614: Strategic Open Pit Mine Planning Course.pdf

5

Loader-Truck Production Calculations

• Example:CAT775 truck (65ton) is loaded with a 11.0CY 990 loader with 0.55min cycle time with 95% fill factor.For truck cycle time, use the following table. Determine the number of trucks needed for the loader and the total production per hour.

0.6minSpot

1.8minReturn

1.0minDump

3.8minHaul

Truck cycle time

Sur

face

Min

e D

esig

n

Page 615: Strategic Open Pit Mine Planning Course.pdf

6

Loader-Truck Production Calculations (Cont.)

Tons / cycle = 11CY/cycle * 0.95*3100lb/cy / 2000lb= 16.2T/cycle

# of cycles/truck = 65T / truck / 1 cycle/16.2T= 4 cycles

Loading time = (4-1) cycles * 0.55min / cycle = 1.65 min

Sur

face

Min

e D

esig

n

Page 616: Strategic Open Pit Mine Planning Course.pdf

7

Loader-Truck Production Calculations (Cont.)

Cycle time

1.7minLoad

0.6minSpot

1.8minReturn

1.0minDump

3.8minHaul

Total Cycle time 8.9min

Sur

face

Min

e D

esig

n

Page 617: Strategic Open Pit Mine Planning Course.pdf

8

Loader-Truck Production Calculations (Cont.)

• Number of Trucks/ Loader

No. of Trucks = Truck cycle time / Load time= 8.9 min / 1.65 min= 5.4 trucks(Assume 6 trucks)

Sur

face

Min

e D

esig

n

Page 618: Strategic Open Pit Mine Planning Course.pdf

9

Loader-Truck Production Calculations (Cont.)

• Total ProductionAssume – 50 min / hour, and 85% availability

65T/cycle*1cycle/8.9min*50min/hr*0.85/unit = 312T/hr

Total Production = No. of trucks * tons/hr – unit= 5.4 trucks * 312T/hr per truck= 1685 tons/ hr

Sur

face

Min

e D

esig

n

Page 619: Strategic Open Pit Mine Planning Course.pdf

10

Loader-Truck Production Calculations

• Example:

A quarry works with CAT769D flat floor trucks (Max payload 41T, Engine+-450hp) that is loaded by 8cy loader.

The material density is 2800lb/LCY and the quarry is located at the sea level, sending material at 260tons/ hour to the crusher.Calculate truck loading time, productivity, and number or trucks required.

Sur

face

Min

e D

esig

n

Page 620: Strategic Open Pit Mine Planning Course.pdf

11

Loader-Truck Production Calculations (Cont.)

• Example (Cont.):Loader data:

Capacity: 8cyFill factor: 80%Cycle time: 0.5 min/passMechanical availability: 88%

Sur

face

Min

e D

esig

n

Page 621: Strategic Open Pit Mine Planning Course.pdf

12

Loader-Truck Production Calculations (Cont.)

• Example (Cont.):Truck cycle time data:

Spot time: 0.8 minDump time:1.5min

Truck mechanical availability: 85%

Sur

face

Min

e D

esig

n

Page 622: Strategic Open Pit Mine Planning Course.pdf

13

Loader-Truck Production Calculations (Cont.)

• Example (Cont.):Road profile:

4

2

4

Rolling resistance (%)

0

8

0

Grade (%)

45

20

45

Speed limit (km/hr)

1523

7622

1221

Length (m)Segment

Road condition: Firm

Sur

face

Min

e D

esig

n

Page 623: Strategic Open Pit Mine Planning Course.pdf

14

Loader-Truck Production Calculations (Cont.)

Tons / cycle = 8CY/cycle * 0.8*2800lb/cy / 2000lb= 9T/cycle

# of cycles/truck = 41T / truck / 1 cycle / 9T= 4.6 cycles (5 cycles)

Loading time = (5-1) cycles * 0.5min / cycle = 2.0 min

Sur

face

Min

e D

esig

n

Page 624: Strategic Open Pit Mine Planning Course.pdf

15

Loader-Truck Production Calculations (Cont.)

Haul Speed:Segment1

Total Resistance = 4%Max speed = 42km/h

< Speed limit (45km/hr)

42

Sur

face

Min

e D

esig

n

Page 625: Strategic Open Pit Mine Planning Course.pdf

16

Loader-Truck Production Calculations (Cont.)

Conversion of Max Speed to Average Speed

Weights to HP ratio: 75050kg = 165456lb165456lb / 450hp = 368lb/hp

Haul load length: 122m = 401ft

Conversion factor = 0.51

Avg speed = 42km/hr*0.51=21.4km/hr Sur

face

Min

e D

esig

n

Page 626: Strategic Open Pit Mine Planning Course.pdf

17

Loader-Truck Production Calculations (Cont.)

Haul Speed :Segment2

Total Resistance = 10%Max speed = 16km/h

< Speed limit (20km/hr)

Conversion factor = 1Avg speed = 16km/hr

16

Sur

face

Min

e D

esig

n

Page 627: Strategic Open Pit Mine Planning Course.pdf

18

Loader-Truck Production Calculations (Cont.)

Haul Speed :Segment3

Total Resistance = 4%Max speed = 42km/h

< Speed limit (45km/hr)

Conversion factor = 0.68Avg speed

= 42km/hr*0.68=28.6km/hr

42

Sur

face

Min

e D

esig

n

Page 628: Strategic Open Pit Mine Planning Course.pdf

19

Loader-Truck Production Calculations (Cont.)

Haul Time:Segment1:

0.122km / 21.4km/hr * 60min = 0.34 min

Segment2: 0.762km / 16km/hr * 60min = 2.86 min

Segment3: 0.152km / 28.6km/hr * 60min = 0.32 min

Total Haul Time:0.34+2.86+0.32 = 3.52 min

Sur

face

Min

e D

esig

n

Page 629: Strategic Open Pit Mine Planning Course.pdf

20

Loader-Truck Production Calculations (Cont.)

Return Speed:Segment1

Total Resistance = 4%Max speed = 73km/h

> Speed limit (45km/hr)So, choose 45km/hr

Avg speed = 45km/hr*0.68=30.6km/hr

73

Sur

face

Min

e D

esig

n

Page 630: Strategic Open Pit Mine Planning Course.pdf

21

Loader-Truck Production Calculations (Cont.)

Return Speed :Segment2

Total Resistance = -8%+2% = -6%Max speed = 69km/h> Speed limit (20km/h)

Choose 20km/hr

Avg speed = 20*0.95= 19km/h

69

6%

Sur

face

Min

e D

esig

n

Page 631: Strategic Open Pit Mine Planning Course.pdf

22

Loader-Truck Production Calculations (Cont.)

Return Speed :Segment3

Total Resistance = 4%Max speed = 73km/h

> Speed limit (45km/hr)So, choose 45km/hr

Avg speed = 45km/hr*0.54=24.3km/hr

73

Sur

face

Min

e D

esig

n

Page 632: Strategic Open Pit Mine Planning Course.pdf

23

Loader-Truck Production Calculations (Cont.)

Return Time:Segment1:

0.122km / 30.6km/hr * 60min = 0.24 min

Segment2: 0.762km / 19km/hr * 60min = 2.41 min

Segment3: 0.152km / 24.3km/hr * 60min = 0.38 min

Total Return Time:0.24+2.41+0.38 = 3.02 min

Sur

face

Min

e D

esig

n

Page 633: Strategic Open Pit Mine Planning Course.pdf

24

Loader-Truck Production Calculations (Cont.)

Haul and Return Time Summary:

0.3824.30.5445734401523

2.41190.952069-62-87622

0.2430.60.6845734401221

time (min)Avg. Speed

(km/hr)ConversionLimit

(km/hr)Speed (km/hr)

Total Resistance (%)RR (%)Grade(%)

Length(m)Segment

Return

0.3228.560.6845424401523

2.86161201610287622

0.3421.420.5145424401221

time (min)Avg. Speed

(km/hr)ConversionLimit

(km/hr)Speed (km/hr)

Total Resistance (%)RR (%)Grade(%)

Length(m)Segment

Haul

Total time = 3.52min(haul)+3.02(return)=6.54 min

Sur

face

Min

e D

esig

n

Page 634: Strategic Open Pit Mine Planning Course.pdf

25

Loader-Truck Production Calculations (Cont.)

Truck cycle time (min)

0.8minSpot

3.0minReturn

1.5minDump

3.5minHaul

2.0 minLoad

Total 10.8min

Sur

face

Min

e D

esig

n

Page 635: Strategic Open Pit Mine Planning Course.pdf

26

Loader-Truck Production Calculations (Cont.)

• Slip condition check (Segment2):

Available Rimpull=(Grade resistance + Rolling resistance)

* Gross Vehicle Weight = (8% + 2%) * (34050kg + 41000kg)= 10%*75050kg= 7505kg

Sur

face

Min

e D

esig

n

Page 636: Strategic Open Pit Mine Planning Course.pdf

27

Loader-Truck Production Calculations (Cont.)

Usable Rimpull: Function of road surface and weight on the drive wheels

Usable Rimpull = Coefficient of Traction * Weight on Wheel

Sur

face

Min

e D

esig

n

Page 637: Strategic Open Pit Mine Planning Course.pdf

28

Loader-Truck Production Calculations (Cont.)

Typical Coefficient of Traction

Sur

face

Min

e D

esig

n

Page 638: Strategic Open Pit Mine Planning Course.pdf

29

Loader-Truck Production Calculations (Cont.)

Weight of Wheel:

769D: Rear 66.7%, Front 33.3% Distribution (by CAT Performance Book)

Weight on Rear Tire is 75050kg * 0.667 = 50058kg

Then, Usable Rimpull is 0.6*50058kg*Cos(8%) = 29939kg

Sur

face

Min

e D

esig

n

Page 639: Strategic Open Pit Mine Planning Course.pdf

30

Loader-Truck Production Calculations (Cont.)

• CONDITION CHECK

Usable Rimpull > Available Rimpull

There is no slip condition.

Sur

face

Min

e D

esig

n

Page 640: Strategic Open Pit Mine Planning Course.pdf

31

Loader-Truck Production Calculations (Cont.)

• Unit Production

Assuming 50min / hour

Productivity:41T/cycle*1cycle/10.8min*50min/hr*0.85 = 161T/hr

Sur

face

Min

e D

esig

n

Page 641: Strategic Open Pit Mine Planning Course.pdf

32

Loader-Truck Production Calculations (Cont.)

• Number of Trucks/ Loader

For maximum productivity: 10.8min / 2.0min = 5.4 (6trucks)

To achieve 260T/hr: 260 / 161 = 1.61 (2 trucks)

Sur

face

Min

e D

esig

n

Page 642: Strategic Open Pit Mine Planning Course.pdf

Fleet Size Determination Using Binomial Distribution

by

Dr. Kadri Dagdelen

Sur

face

Min

e D

esig

n

Page 643: Strategic Open Pit Mine Planning Course.pdf

2

Sur

face

Min

e D

esig

n

Example

Consider the following fleet:

One loader, 80% mechanical availability and an estimated productivity of 9,000 tons per operating shift.

Three haul trucks, 70 percent mechanical availability and an estimated productivity 0f 4,000 tons per operating shift.

Page 644: Strategic Open Pit Mine Planning Course.pdf

3

Sur

face

Min

e D

esig

n

Example

Assume that the fleet is scheduled 100% of the time and will only be inoperative if either the loader or all the trucks are down for repairs.

Page 645: Strategic Open Pit Mine Planning Course.pdf

4

Sur

face

Min

e D

esig

n

Wrong Assumption

One could incorrectly assume that the average loader production would be 80% of 9,000 tons per shift, or 7,200 tons per shift.

However, since the loader production is dependent on available haul trucks, the truck downtime distribution must be considered.

Page 646: Strategic Open Pit Mine Planning Course.pdf

5

Sur

face

Min

e D

esig

n

Binomial Distribution

xnx ppxnx

n −−⋅−

)1()!(!

!

This formula gives the fraction of time x units are available out of a fleet of n units with a given availability of p.

Page 647: Strategic Open Pit Mine Planning Course.pdf

6

Sur

face

Min

e D

esig

n

Binomial Distribution for Trucks

42.0)7.01(7.0)!12(!1

!2 121 =−⋅−

Availability = 70%

0 1 2 3 4 5 6

1 0.30 0.70

2 0.09 0.42 0.49

3 0.03 0.19 0.44 0.34

4 0.01 0.08 0.26 0.41 0.24

5 0.00 0.03 0.13 0.31 0.36 0.17

6 0.00 0.01 0.06 0.19 0.32 0.30 0.12

Fleet Size (n)

Number of Units Available (x)

Fraction of the time that 1 truck out of a fleet of 2 will be operating

Page 648: Strategic Open Pit Mine Planning Course.pdf

7

Sur

face

Min

e D

esig

n

Fleet Capacity

The fleet capacity can be stated as follows:

The loader operates 80% of the time and during this time, 34% will be at 9,000 tons per shift, 44% will be at 8,000 tons per shift, and 19% will be at only 4,000 tons per shift.

0.80 x 0.34 x 9,000 = 2,448 tons

0.80 x 0.44 x 8,000 = 2,816 tons

0.80 x 0.19 x 4,000 = 608 tons

TOTAL = 5,872 tons

Page 649: Strategic Open Pit Mine Planning Course.pdf

8

Sur

face

Min

e D

esig

n

Fleet Capacity

From this example, it can be seen that production from the loader would be 18% short of the initial estimate of 7,200 tons per shift that was determined without consideration of the haul fleet.

Page 650: Strategic Open Pit Mine Planning Course.pdf

9

Sur

face

Min

e D

esig

n

Haul Truck Requirement Determination

Annual target objective 1,800,000 tons

Shifts scheduled 250 shifts

Tonnage requirements per shift 7,200 tons

Average truck productivity 4,000 tons per shift

Need 1.80 operating trucks per shift

3 trucks at 70% availability will average 2.1 shifts

Page 651: Strategic Open Pit Mine Planning Course.pdf

10

Sur

face

Min

e D

esig

n

Haul Truck Requirement Determination

It could be incorrectly assumed that 3 trucks would be sufficient.

However, if the loading fleet contains only 1 loader , then 20% of the time the haul fleet would be idle waiting for the loader to be repaired.

It is also known that the loader could not keep up with three trucks and production would be limited to 9,000 tons per shift, not the 12,000 tons indicated by the haulage capacity.

Page 652: Strategic Open Pit Mine Planning Course.pdf

11

Sur

face

Min

e D

esig

n

Haul Truck Requirement Determination

250 shifts x 0.80 x 0.34 x 9,000 tons = 612,000 tons

250 shifts x 0.80 x 0.44 x 8,000 tons = 704,000 tons

250 shifts x 0.80 x 0.19 x 4,000 tons = 152,000 tons

TOTAL = 1,468,000 tons per year

The solution in this case would be to purchase another loader or work more shifts.

Page 653: Strategic Open Pit Mine Planning Course.pdf

Estimating Owning and Operating Costs

by

Dr. Kadri Dagdelen

Sur

face

Min

e D

esig

n

Page 654: Strategic Open Pit Mine Planning Course.pdf

2

Sur

face

Min

e D

esig

n

Hourly owning and operating cost estimate

AnalystDate

1 2Machine Designation Track-type Tractor Wheel LoaderEstimated Ownership Period (Years) 7 5Estimated Usage (Hours/Year) 1200 1500Ownership Usage (Total Hours) 8400 7500

1. a. Delivered Price (including attachments) 135,000 1,200,000 b. Less Tire Replacement Cost if Desired 4,000 c. Delivered Price Less Tires 135,000 1,196,000

2. a. Residual Value - % of original deliverd price 35% 48%b. Less Residual Value at replacement 47,250 574,080

3. a. Value to be recovered through work 87,750 621,920 b. Cost per hour 10.45 82.92

4. a. Interest rate 16% 16%b. Interest costs 10.29 76.54

5. a. Insurance rate 1% 1%b. Insurance Costs 0.64 4.78

6. a. Tax rate 1% 1%b. Property tax 0.64 4.78

7. Total hourly owning cost 22.02 169.03

Antonio Peralta11/7/2005

Owning Costs

Page 655: Strategic Open Pit Mine Planning Course.pdf

3

Sur

face

Min

e D

esig

n

Hourly owning and operating cost estimate

8. a. Fuel unit price 2.20 2.20 b. Fuel consumption 5 4 c. Fuel cost 11.00 8.80

9. Lube oils, filters, grease 0.46 0.43 10. a. Life of tires (Hours) 3,500

b. Tires replacement cost 1.14 c. Impact factor 0.20 d. Abrasiveness factor 0.20 e. Z factor 0.30 f. Basic factor 6.20 g. Under carriage 4.34

11. a. Extended use multiplier for repair reserve 1.00 1.00 b. Basic repair factor for repair service 4.50 4.00 c. Repair reserve 4.50 4.00

12. a. Special wear items 1.32 0.60

13. Total hourly operating cost 21.62 14.97

14. Maching Owning plus operating 43.64 184.01

15. Operator's hourly wage (include fringes) 30.00 30.00

16. TOTAL OWNING AND OPERATING COST 73.64 214.01

Operating Costs

Page 656: Strategic Open Pit Mine Planning Course.pdf

4

Sur

face

Min

e D

esig

n

9A. Lube Oils, Filters, Grease

Unit Price Consumption Cost/Hour Unit Price Consumption Cost/HourEngineTransmissionFinal DrivesHydraulicsGreaseFilters

Total 0 Total 0

Track-type tractor Wheel Loader

Page 657: Strategic Open Pit Mine Planning Course.pdf

5

Sur

face

Min

e D

esig

n

12A. Special Wear Items

# Cost Life $/Hour Cost Life $/Hour1 105 150 0.70 50 165 0.302 165 450 0.37 80 450 0.183 125 500 0.25 70 600 0.12456

Total 1.32 Total 0.60

Track-type tractor Wheel Loader

Page 658: Strategic Open Pit Mine Planning Course.pdf

Drilling

Dr. Kadri Dagdelen

Sur

face

Min

e D

esig

n

Page 659: Strategic Open Pit Mine Planning Course.pdf

2

Sur

face

Min

e D

esig

n

Drilling Methods

• Top hammer drilling

Hydraulic self-contained drills

Pneumatic drills with portable air compressors

• Down-the-hole (DTH) drilling

Pneumatically operated carriers with portable air compressors

Hydraulically operated self-contained carriers

• Rotary drilling

Drills for rotary crushing

Drills for rotary cutting

Page 660: Strategic Open Pit Mine Planning Course.pdf

3

Sur

face

Min

e D

esig

n

Surface Drilling Methods and Applications

Page 661: Strategic Open Pit Mine Planning Course.pdf

4

Sur

face

Min

e D

esig

n

Components of Surface Drilling Methods

Page 662: Strategic Open Pit Mine Planning Course.pdf

5

Sur

face

Min

e D

esig

n

Top Hammer Drilling

• Soft to hard rock

• Diameter from 7/8” to 10”

• Top hammer drills can be classified according to their size and principle of operation:

Hydraulic or pneumatic handheld drills

Light hydraulic drills mounted on feeds for mechanized drilling in different types of boom applications

Pneumatic crawler drills operated by a separate portable air compressor

Hydraulic crawler or wheel-based drills operated by a powerpack onboard

Page 663: Strategic Open Pit Mine Planning Course.pdf

6

Sur

face

Min

e D

esig

n

Principle of Top Hammer Drilling

• It can be hydraulic or pneumatic

• It combines four functions

Percussion

Feed

Rotation

Flushing

• Parameters that affect the penetration rate:

Impact energy, impact frequency, rotation speed, feed force, andflushing of the hole

Page 664: Strategic Open Pit Mine Planning Course.pdf

7

Sur

face

Min

e D

esig

n

Relative Penetration Rate as a Function of Percussion Pressure

Page 665: Strategic Open Pit Mine Planning Course.pdf

8

Sur

face

Min

e D

esig

n

The Optimal Adjustment of Drilling Parameters Means Maximum Penetration

Page 666: Strategic Open Pit Mine Planning Course.pdf

9

Sur

face

Min

e D

esig

n

Flushing

Page 667: Strategic Open Pit Mine Planning Course.pdf

10

Sur

face

Min

e D

esig

n

Flushing

Page 668: Strategic Open Pit Mine Planning Course.pdf

11

Sur

face

Min

e D

esig

n

Penetration Rates Between Pneumatic and Hydraulic Top Hammer Drilling

Page 669: Strategic Open Pit Mine Planning Course.pdf

12

Sur

face

Min

e D

esig

n

Bench Drilling Rig

Page 670: Strategic Open Pit Mine Planning Course.pdf

13

Sur

face

Min

e D

esig

n

Bench Drilling Rig

A modern surface crawler drill should fulfill the following requirements, to make the operation economical:

• High penetration rate

• Short cycle times

• High quality holes

• High availability

• Low operating cost

Page 671: Strategic Open Pit Mine Planning Course.pdf

14

Sur

face

Min

e D

esig

n

Choice of Bit Type

Page 672: Strategic Open Pit Mine Planning Course.pdf

15

Sur

face

Min

e D

esig

n

Application Range of Tube Drill Steels

Page 673: Strategic Open Pit Mine Planning Course.pdf

16

Sur

face

Min

e D

esig

n

DTH Drilling

• It is more efficient than top hammer drilling

• A DTH hammer follows immediately behind the bit

• Good drilling accuracy

• DTH drills are used in bench drilling of 3½” to 6½” holes on benches up to 150 feet

• DTH hammer life is dependent on:

Hammer size, operating pressure, rock abrasiveness, and rock drillability

Page 674: Strategic Open Pit Mine Planning Course.pdf

17

Sur

face

Min

e D

esig

n

Principle of DTH Drilling

Page 675: Strategic Open Pit Mine Planning Course.pdf

18

Sur

face

Min

e D

esig

n

A Typical DTH Hammer

Page 676: Strategic Open Pit Mine Planning Course.pdf

19

Sur

face

Min

e D

esig

n

Features of DTH Hammer

Page 677: Strategic Open Pit Mine Planning Course.pdf

20

Sur

face

Min

e D

esig

n

Truck Mounted DTH Drill

Page 678: Strategic Open Pit Mine Planning Course.pdf

21

Sur

face

Min

e D

esig

n

DTH Bit Designs

Page 679: Strategic Open Pit Mine Planning Course.pdf

22

Sur

face

Min

e D

esig

n

Rotary Drilling

• It is used in most major open pit mining operations

• Diameter from 4” to 17½”, depth up to 150 feet

• The key elements in rotary drilling are:

Sufficient torque to turn the bit in any strata encountered

Sufficiently high bit loading capability (pulldown force) for optimum penetration

Sufficient flushing air volume to remove the cuttings during penetration, as well as to provide cool air to the drill bit bearings

Selection of the proper type of bit for the material being drilled

Page 680: Strategic Open Pit Mine Planning Course.pdf

23

Sur

face

Min

e D

esig

n

Principle Rotary Drilling

Page 681: Strategic Open Pit Mine Planning Course.pdf

24

Sur

face

Min

e D

esig

n

Rotary Drills

Page 682: Strategic Open Pit Mine Planning Course.pdf

25

Sur

face

Min

e D

esig

n

Rotary Drills

Page 683: Strategic Open Pit Mine Planning Course.pdf

26

Sur

face

Min

e D

esig

n

Principles of Rotation

Page 684: Strategic Open Pit Mine Planning Course.pdf

27

Sur

face

Min

e D

esig

n

Rotary Power versus Hole Diameter

Page 685: Strategic Open Pit Mine Planning Course.pdf

28

Sur

face

Min

e D

esig

n

Pull Down versus Hole Diameter

Page 686: Strategic Open Pit Mine Planning Course.pdf

29

Sur

face

Min

e D

esig

n

Principles of Feed Systems

Page 687: Strategic Open Pit Mine Planning Course.pdf

30

Sur

face

Min

e D

esig

n

Thrust and Pulldown Force

Page 688: Strategic Open Pit Mine Planning Course.pdf

31

Sur

face

Min

e D

esig

n

Flushing Air Compressor Size

Page 689: Strategic Open Pit Mine Planning Course.pdf

32

Sur

face

Min

e D

esig

n

Carrousel Type Pipe Changer

Page 690: Strategic Open Pit Mine Planning Course.pdf

33

Sur

face

Min

e D

esig

n

Rotary Drilling Accessories

• Drill bits

• Drill pipes

• Shock subs

• Stabilizers

• Saver subs

• Bit subs

Page 691: Strategic Open Pit Mine Planning Course.pdf

34

Sur

face

Min

e D

esig

n

Rotary Drill Bit Components

Page 692: Strategic Open Pit Mine Planning Course.pdf

35

Sur

face

Min

e D

esig

n

Rotary Bit Selection Parameters

Type of ground Tooth or insert spacing Tooth depth Cutting actionSoft formations with low compressive strengths and high drillability: shales, unconsolitaded sands, calcites

HighLarge: Inserts extended chisel shaped

Mostly gouging and scraping by skew cone action, with little chipping and crushing

Medium Formations: harder shales, limestone, sandstones, dolomites

Medium, closeMedium: Inserts short or blunt chisel shaped

Partly by gouging and scraping but with significant chipping and crushing action especially at harder end of type

Hard formations: siliceous limestones, hard sandstones, porphyry copper ores

Close with low intermeshLow: Inserts spherical or conical

Mostly by chipping and crushing by cutter rolling action

Very hard formations: taconites, quartzites

Very close with low intermesh

Very low: Insert hemispherical conical or ovoid

Nearly all excavation by true rolling action of cutters

Page 693: Strategic Open Pit Mine Planning Course.pdf

36

Sur

face

Min

e D

esig

n

Bit Selection for Rotary Drilling

Page 694: Strategic Open Pit Mine Planning Course.pdf

37

Sur

face

Min

e D

esig

n

Insert Shapes for Tricone Bits

Page 695: Strategic Open Pit Mine Planning Course.pdf

38

Sur

face

Min

e D

esig

n

Penetration Rate versus Bit Load

Page 696: Strategic Open Pit Mine Planning Course.pdf

39

Sur

face

Min

e D

esig

n

Principles of Rotary Cutting

Page 697: Strategic Open Pit Mine Planning Course.pdf

Drilling

Dr. Kadri Dagdelen

Sur

face

Min

e D

esig

n

Page 698: Strategic Open Pit Mine Planning Course.pdf

2

Sur

face

Min

e D

esig

n

Penetration Rate

300)log2861( 10

rpmWScP ⋅⋅−=

φ

Where:

P = penetration rate (ft/hr)

Sc = uniaxial compressive strength, in thousands of psi

W/F = Weight per inch of bit diameter, in thousands of pounds

rpm = revolutions of drill pipe per minute

Bauer and Calder, 1967 (Surface Mining Handbook)

Page 699: Strategic Open Pit Mine Planning Course.pdf

3

Sur

face

Min

e D

esig

n

Horse Power

5.15.2 WDrpmKhp ⋅⋅⋅=Where:

D = bit diameter (in.)

W = weight on the bit in thousands of pounds

K = constant that varies with rock type.

As material strength decreases, the value of K increases. This caters for the greater teeth penetration experienced in soft rocks. Values vary from 14 x 10-5 for soft rocks down to 4 x 10-5 for high-strength materials.

Surface Mining Handbook

Page 700: Strategic Open Pit Mine Planning Course.pdf

4

Sur

face

Min

e D

esig

n

Balancing Air Velocity

2/12/1264 dpUm ⋅=Where:

Um =

2420 fpm for 13 mm (1/2 in.) diameter platelets with a density of 2.7 g/cc

d = diameter of the chip in inches

p = density of the chip in lb/ft3

Surface Mining Handbook

Page 701: Strategic Open Pit Mine Planning Course.pdf

5

Sur

face

Min

e D

esig

n

Bailing Velocities

Page 702: Strategic Open Pit Mine Planning Course.pdf

6

Sur

face

Min

e D

esig

n

Bailing Velocities

Page 703: Strategic Open Pit Mine Planning Course.pdf

7

Sur

face

Min

e D

esig

n

Air Requirements Chart

Page 704: Strategic Open Pit Mine Planning Course.pdf

8

Sur

face

Min

e D

esig

n

Optimal Bit Load

5DC

LoadOptimumBit×

=

Where:

C = Rock compressive strength

D = bit diameter in inches

Source: R. Baker, Tamrock

Page 705: Strategic Open Pit Mine Planning Course.pdf

9

Sur

face

Min

e D

esig

n

Total Work

TNRWWTWorkTotal ××××= π2)(

Where:

W = bit load (lbs)

R = penetration rate (feet/min)

N = bit rotation speed

T = torque (foot lbs)

Source: R. Baker, Tamrock

Page 706: Strategic Open Pit Mine Planning Course.pdf

10

Sur

face

Min

e D

esig

n

Rotary Horsepower

CWRD

hpPowerHorse6.1)1000/(95.4

)(×××=

Where:

hp = rotary horsepower

R = bit rotational speed

D = bit diameter (inches)

W = optimum bit load (lbs)

C = rock compressive strength

Source: R. Baker, Tamrock

Page 707: Strategic Open Pit Mine Planning Course.pdf

11

Sur

face

Min

e D

esig

n

Maximum Bit RPM

6.1)1000/(95.4)(

WDChp

RRPMBitMaximum××

×=

Where:

hp = rotary horsepower

R = bit rotational speed

D = bit diameter (inches)

W = optimum bit load (lbs)

C = rock compressive strength

Source: R. Baker, Tamrock

Page 708: Strategic Open Pit Mine Planning Course.pdf

12

Sur

face

Min

e D

esig

n

Volume CFM

×+×

×=

14425.0

14425.0 22 D

PSFD

PCFMVolumeππ

Where:

P = penetration rate

D = bit diameter (inches)

SF = swell factor (0.6 sedimentary or 0.4 Igneous/metamorphic)

Source: R. Baker, Tamrock

Page 709: Strategic Open Pit Mine Planning Course.pdf

13

Sur

face

Min

e D

esig

n

Air Velocity

22

183dD

CFMVelocityAir

−×

=

Where:

d = pipe diameter (inches)

D = bit diameter (inches)

CFM = effective compressor volume (CFM)

Source: R. Baker, Tamrock

Page 710: Strategic Open Pit Mine Planning Course.pdf

14

Sur

face

Min

e D

esig

n

Compressive Strength

9.0)10000/1(2.018.2

)(DP

RWCStrengtheCompressiv

×××××

=

Where:

P = average pure penetration rate (feet/hour)

W = average bit load (lbs)

R = average bit rotation

D = bit diameter (inches)

Source: R. Baker, Tamrock

Page 711: Strategic Open Pit Mine Planning Course.pdf

15

Sur

face

Min

e D

esig

n

Pure Penetration

)10000/(2.018.2

)(9.0 CDC

RWPnPenetratioPure

×××××

=

Where:

P = average pure penetration rate (feet/hour)

W = optimum bit load (lbs)

R = optimum bit rotation speed

D = bit diameter (inches)

C = average compressive strength

Source: R. Baker, Tamrock

Page 712: Strategic Open Pit Mine Planning Course.pdf

Explosives

Definitions

Explosive -A chemical mixture that releases gasses and heat at high velocity, causing very high pressures.

Explosion –Thermochemical process in which mixtures of gasses, solids, or liquids react with almost instantaneous formation of gaseous pressures and heat release.

Detonation – Supersonic explosive reaction which creates a high pressure shock wave, heat, and gasses.

Page 713: Strategic Open Pit Mine Planning Course.pdf

Theory of Blasting

The rock is affected by a detonating explosive in three principal stages.

In the first stage, starting from the initiation point, the blastholeexpands by crushing the blasthole walls. This is due to the high pressure upon detonation.

In the second stage, compressive stress waves emanate in all directions from the blasthole with a velocity equal to the sonic wave velocity in the rock. When these compressive stress waves reflect against a free rock face, they cause tensile stresses in the rock mass between the blasthole and the free face. If the tensile strength of the rock is exceeded, the rock breaks in the burden area, which is the case in a correctly designed blast.

Page 714: Strategic Open Pit Mine Planning Course.pdf

Mechanics of Detonation

Compressive Shock Waves

Tensile Shock Waves

Page 715: Strategic Open Pit Mine Planning Course.pdf

Mechanics of Detonation

In the third stage, the released gas volume "enters" the crackformation under high pressure, expanding the cracks.

If the distance between theblasthole and the free face iscorrectly calculated, the rockmass between the blastholeand the free face will yield andbe thrown forward.

Page 716: Strategic Open Pit Mine Planning Course.pdf

Bench Blast

(Atlas Copco)

Page 717: Strategic Open Pit Mine Planning Course.pdf
Page 718: Strategic Open Pit Mine Planning Course.pdf

History of Explosives Development

1000 -Black Powder•Discovered in China around 1000 A.D.

•Mixture of potassium nitrate (saltpeter), sulfur and charcoal.

•The combustion of charcoal (C) and sulfur (S) is the fuel, and oxygen is contained within the nitrate ion (NO3).

•Marco Polo brought it to Europe where it was originally used for military purposes.

•The first blasting application was in Hungary in 1627 and by the end of the 17th century most of the European miners used black powder to loosen rock.

•The first black powder mills were established in America around the year 1775.

Page 719: Strategic Open Pit Mine Planning Course.pdf

History of Explosives Development

1831-Safety Fuse•William Bickford, an Englishman, patented the “Miners Safety Fuse”, in 1831.

•Safety fuse gave blasters a safe and reliable means of initiating black powder.

1846 -Nitroglycerin•In 1846, Ascanio Sobrero, an Italian, discovered nitroglycerin (C3H5N3O9), but he considered it too unpredictable and hazardous for anyone to use.

Page 720: Strategic Open Pit Mine Planning Course.pdf

History of Explosives Development

1867 -Blasting Caps

•The main problem with nitroglycerin was to get it to shoot consistently.

•Alfred Nobel, a Swede, solved this problem with the invention of the fulminate of mercury blasting cap in 1867.

•Use together with safety fuse, the blasting cap provided an excellent initiating system for nitroglycerin.

Page 721: Strategic Open Pit Mine Planning Course.pdf

History of Explosives Development

1866 –Dynamite

•In his efforts to make nitroglycerin safer to handle, Alfred Nobel in 1866 discovered that Kieselguhr (a diatomaceous earth) not only absorbed three times its own weight of nitroglycerin, but also rendered it less sensitive to shock.

•After kneading and shaping it into a cartridge, it was wrapped in paper and the Dynamite was invented.

Page 722: Strategic Open Pit Mine Planning Course.pdf

History of Explosives Development

1894-PETN•The explosive PETN (C5H8N4O12) was discovered in 1894.

•It was not widely used until the 1940’s and today it is the primary explosive compound in modern initiators and boosters.

1922-Electric Blasting Caps•In the beginning of the 20th century the electric initiation wasintroduced, and by 1922 the first electric delay detonator (with1 sec. delay) came into practical use.

•The introduction of the short delay detonator 10-100 milliseconds) in the late 1940's has had the greatest importancein the development of modern blasting techniques.

Page 723: Strategic Open Pit Mine Planning Course.pdf

History of Explosives Development

1956 –ANFO

•In 1956, ANFO (Ammonium Nitrate and Fuel Oil) was introduced to the U.S. market.

•The success of the ANFO in U.S.A. is indisputable, from a consumption rate of almost nil in 1956, the consumption had increased to over 1,000,000 tons by 1975, the consumption of dynamites has, during the same time, declined from 340,000 tons to 135,000 tons.

Page 724: Strategic Open Pit Mine Planning Course.pdf

History of Explosives Development1960’s -Water gels and slurries

•In the 1960's, we have seen the development of water gels, also called slurries.

•A slurry explosive is a high density aqueous explosive containing ammonium nitrate which is an oxidizer.

•Water gels contain 10 to 30 percent water and are sensitized by carbonaceous fuels, TNT, aluminum, or certain organiccompounds like methylamin nitrate.

•Both cap sensitive and non-cap sensitive water gel explosives are available

Page 725: Strategic Open Pit Mine Planning Course.pdf

History of Explosives Development

1970’s-Nonel•In the late 1970's we saw new non-electrical initiating systems like Nonel being developed.

1970’s -Emulsions•1970's the development of emulsion explosives.

•Emulsion explosives are composed of separate, very small drops of ammonium nitrate solution and other oxidizers, densely dispersed in a continuous phase, which is composed of oil and wax.

•The oil/wax mixture, which is the fuel, is in this way given a very large contact surface to the oxidizer, the ammonium nitratesolution .

Page 726: Strategic Open Pit Mine Planning Course.pdf

Properties of Explosives

In the ideal conditions of dry blastholes a simple explosive can be used, while under wet conditions, more sophisticated products are called for .

The most important characteristics of an explosive are:•velocity of detonation (VOD)•strength•detonation stability•sensitiveness (propagation ability)•density•water resistance•sensitivity•safety in handling•resistance to freezing•oxygen balance•shelf life

Page 727: Strategic Open Pit Mine Planning Course.pdf

Classification of Explosives

The explosives used in civil engineering and mining can nowadaysbe classified as:

•High explosives•Blasting agents

High explosives are characterized by high velocity of detonation (VOD), high pressure shock wave, high density and by being cap sensitive.

Blasting agents are mixtures consisting of a fuel and oxidizer system, where none of the ingredients are classified as an explosive and when unconfined cannot be detonated by means of a #8 test blasting cap (1.0 grams of high explosives). Blasting agents have to be initiated by a primer. ANFO is a typical blasting agent.

Page 728: Strategic Open Pit Mine Planning Course.pdf

Firing Devices

Firing methods can be divided into two main groups:

Non-electric•Safety Fuse and Blasting Cap•Detonating Cord•Nonel system

Electric•Electronic Blasting Caps

Page 729: Strategic Open Pit Mine Planning Course.pdf

Safety Fuse and Blasting Cap

The safety fuse consists of a black powder core that is tightly wrapped with coverings of textile and waterproofing materials.

Safety fuse has a steady well controlled burning speed, usually around 40 seconds per foot.

Page 730: Strategic Open Pit Mine Planning Course.pdf

Safety Fuse and Blasting Cap

To initiate the explosive, a plain detonator has to be attached to the safety fuse.

Detonators of different strengths expressed as a number are available, currently #6 or #8 caps.

The #8 detonator contains approximately 1.0 grams of high explosives, and the #6 about 0.8 grams.

Page 731: Strategic Open Pit Mine Planning Course.pdf

Detonating Cord

Detonating cord consists of a PETN core which is wrapped in coverings of textiles and waterproofing materials.

Detonating cord may be initiated with a #6 detonator and detonates along its entire length at about 7000 meters/second.

It initiates most explosives.

Does not work well with ANFO in small to medium sized blastholes, (incomplete detonation).

Firing pattern for detonating cord blast.

Page 732: Strategic Open Pit Mine Planning Course.pdf

Electric Blasting Caps

Electric detonators can be divided into three different classes according to their timing properties:

•instantaneous•millisecond delays•half second delays

The millisecond delay detonator has a built-in millisecond delay element. Delays are usually available in 25 ms delay intervals.

Page 733: Strategic Open Pit Mine Planning Course.pdf

Electric Blasting Caps

Electric detonators may be connected in series or parallel depending on the number of detonators in the round, and the current available in the blasting machine.

Parallel series circuit.

Page 734: Strategic Open Pit Mine Planning Course.pdf

Electric Blasting Caps

The testing instruments for blasting circuits have to be specially designed for their purpose and be approved by the authorities concerned.

An Ohm-meter is used to control the resistance of single electric detonators, detonators in series and in parallel-series and for the final check before firing.

Page 735: Strategic Open Pit Mine Planning Course.pdf

Electric Blasting CapsThe series are connected in parallel and subsequently measured.

The resistance of the parallel connection is in accordance with Kirckhoffs law:

As the difference in resistance between the series must not exceed ± 5 percent, the resistance of the parallel connection will be:

series ofNumber /seriesResistance

R =

Rn1

...R1

R1

R1

21

+++=

Page 736: Strategic Open Pit Mine Planning Course.pdf

ExampleAssume a blast of 250 V A-detonators with a resistance of 3.6 Ohms each. (The resistance is always 3.6 Ohms independent of legwire length.) The firing cable has a resistance of 5 Ohms and a CID 330 V A blasting machine is used.

In accordance with the instructions on the blasting machine, the round may be connected in 5 parallel series.

Number of detonators in each series: 50.

Resistance per series: 50x3.6=180 Ohms.

Resistance after parallel connection :

Resistance at the firing point is the resistance of the parallel-series connection plus the resistance of the firing cable.36 + 5 = 41 Ohms.

Ohms 365

180series ofNumber

/seriesResistanceR ===

Page 737: Strategic Open Pit Mine Planning Course.pdf

Possible errors during measuring:Resistance too high:

* Larger number of detonators than calculated.* Sub-division into series wrongly carried out.* Poor contact ill some connection or detonator .

Resistance too low:* All detonators are not connected into the circuit.* Sub-division into series wrongly carried out.* Some part of the round not connected into the circuit.

Infinite resistance:* Interruption in series through incomplete connection.* Faulty detonator (usually torn off legwire).

Page 738: Strategic Open Pit Mine Planning Course.pdf

Electric Blasting Caps

Blasting machines of various types are used to fire the rounds.

Shown is the model CI 50 which is designed for firing a maximum of 50 conventional detonators.

Page 739: Strategic Open Pit Mine Planning Course.pdf

Nonel systemThe NONEL detonator functions as an electric delay detonator, but the legwires and the fuse head have been replaced by a plastic tube through which a shock wave is transmitted.

The endsplit of of the shockwave from the plastic tube initiates the delay element in the detonator.

The 3mm diameter plastic tube is coated on the inside with a thin layer of reactive material which transmits the shockwave with a velocity of about 2000 meters per second.

Page 740: Strategic Open Pit Mine Planning Course.pdf

Non-Electric vs. Electric

Tubing Air Space

Shell

Non Electric Cap

Electric Cap

CrimpsPlug

IgnitionCharge Fuse

Powder

FuseElement

PrimingCharge

BaseCharge

ClosureBridgeWire

Page 741: Strategic Open Pit Mine Planning Course.pdf

Nonel systemA connector with a strength of 1/3 a #8 cap is used to connect and initiate the detonators.

Page 742: Strategic Open Pit Mine Planning Course.pdf

Nonel system

NONEL connected for bench blasting.

Page 743: Strategic Open Pit Mine Planning Course.pdf

Nonel system

NONEL detonators may also be connected to a detonating cord using a specially designed clip if noise is not a problem.

Page 744: Strategic Open Pit Mine Planning Course.pdf

Nonel system

A NONEL round may be fired using a plain detonator and safety fuse, or by using a specially designed NONEL system blasting machine.

Page 745: Strategic Open Pit Mine Planning Course.pdf

Bench BlastingBench blasting is the most common kind of blasting work.

It can be defined as blasting of vertical or nearly vertical blastholes in one or more rows towards a free surface.

The blastholes can have free breakage of fixed bottom.

Free breakageFixed bottom

Page 746: Strategic Open Pit Mine Planning Course.pdf

Bench Blasting

The tensile, compressive and shearing strengths of a rock mass vary with different kinds of rock and may vary within the same blast.

As the rock's tensile strength has to be exceeded in order to break therock, its geological properties will affect its blastability.

Faults and dirt-seams may change the effect of the explosive in the blast.

Faulty rock containing voids, where the gases penetrate without giving full effect, may be difficult to blast even though the rock may have a relatively low tensile strength.

Page 747: Strategic Open Pit Mine Planning Course.pdf

Bench BlastingThe requisite specific charge, (kg/m3 ) provides a first-rate measure of the blastability of the rock.

By using the specific charge as a basis for the calculation, it is possible to calculate the charge which is suitable for the rock concerned.

The distribution of the explosives in the rock is of the utmost importance. A closely spaced round with small diameter blastholes gives much better fragmentation of the rock than a round of widely spaced large diameter blastholes, provided that the same specific charge is used.

Page 748: Strategic Open Pit Mine Planning Course.pdf

Burden -the distance between the drill hole and the nearest parallel free face.

Spacing - the distance between holes along rows that are parallel to the face.

Stemming -non-explosive material that is placed in the bore hole to confine the explosives (usually placed near the collar of the hole).

Sub-drilling is the amount of hole that is drilled below the intended new bench level.

Basic Definitions

Page 749: Strategic Open Pit Mine Planning Course.pdf

Blasting Theory

When hole depth equals the bench height masses of rock are oftenleft at the toe of the bench because of lack of reflected tension energy from the free face. The solution for this is either sub-drilling or inclined holes.

Partial Reflected

WaveUn-reflectedCompression

Wave

Leaves Un-fractured Toe

Bef

ore

Bla

stin

g

Aft

er B

last

ing

Page 750: Strategic Open Pit Mine Planning Course.pdf

Blasting Theory

Inclined holes cause total reflective tensile waves at the toe of the bench. This causes a flat lower bench and is a more efficient use of explosives.

Total ReflectedTensile Waves

Page 751: Strategic Open Pit Mine Planning Course.pdf

Vertical Holes vs. Inclined Holes

Vertical Holes• Easier to drill• Avoids difficulties in

fractured rock

Inclined Holes• Commonly drilled between 10 &

15 degrees• Causes more productive

reflected shock wave in toe of bench

Page 752: Strategic Open Pit Mine Planning Course.pdf

Bench Height Factors

Research indicates that bore hole length should

be approximately 3 times the burden

distance.-Ash & Smith, Society of

Explosives Engineers, 1976

Bench Height is a function of both hole diameter and burden distance.

Zone of optimal fragmentation

Page 753: Strategic Open Pit Mine Planning Course.pdf

Burden Spacing Equations

Page 754: Strategic Open Pit Mine Planning Course.pdf

Burden Spacing EquationsAndersonB = K(d*L)**2

Pearse B = K*d*(P/T)**2

AshB = K*d/12

Fraenkel (meters & mm)((R*L)**0.3)*(l**0.3)*(d**0.8)

B =50 B burden distance (inches)

d hole diameter (inches)L hole length (feet)T ultimate tensile strength of rock (pounds per square inch)P stability pressure of explosive (pounds per square inch)K constants (empirically determined)

Rock characteristics are difficulty to mathematically model since rock is never really homogeneous.

Page 755: Strategic Open Pit Mine Planning Course.pdf

Burden Spacing Equations

S/B*f*cs*p

33d

Bmax =

Langefors/Kihlström

Bmax = maximum burden (m)d = diameter in the bottom of the blasthole (mm)p = packing degree (loading density) (kg/liter or g/c3 )s = weight strength of the explosive (ANFO = 1)c = rock constant, 0.3 to 0.5c = c + 0.05 for Bmax between 1.4 and 15.0 metersf = degree of fixation, 1.0 for vertical holes

and 0:95 for holes with inclination 3:1S/B = ratio of spacing to burden

Page 756: Strategic Open Pit Mine Planning Course.pdf

Terminology

Page 757: Strategic Open Pit Mine Planning Course.pdf

Charge Calculations

The maximum burden in the bottom of the blasthole depends on:

•weight strength of the actual explosive (s)•charge concentration (lb)•rock constant (c)•constriction of the blasthole (R1)

Page 758: Strategic Open Pit Mine Planning Course.pdf
Page 759: Strategic Open Pit Mine Planning Course.pdf

Table 1a.

Page 760: Strategic Open Pit Mine Planning Course.pdf
Page 761: Strategic Open Pit Mine Planning Course.pdf
Page 762: Strategic Open Pit Mine Planning Course.pdf
Page 763: Strategic Open Pit Mine Planning Course.pdf
Page 764: Strategic Open Pit Mine Planning Course.pdf
Page 765: Strategic Open Pit Mine Planning Course.pdf
Page 766: Strategic Open Pit Mine Planning Course.pdf
Page 767: Strategic Open Pit Mine Planning Course.pdf
Page 768: Strategic Open Pit Mine Planning Course.pdf
Page 769: Strategic Open Pit Mine Planning Course.pdf
Page 770: Strategic Open Pit Mine Planning Course.pdf
Page 771: Strategic Open Pit Mine Planning Course.pdf
Page 772: Strategic Open Pit Mine Planning Course.pdf
Page 773: Strategic Open Pit Mine Planning Course.pdf
Page 774: Strategic Open Pit Mine Planning Course.pdf
Page 775: Strategic Open Pit Mine Planning Course.pdf

Kadri DagdelenFuat Bilgin

Mining Engineering DepartmentColorado Shool of MInes

RECENT DEVELOPMENTS IN VEHICLE PROXIMITY WARNING AND COLLISION AVOIDANCE SYSTEMS

USING GPS AND WIRELESS NETWORKS

Page 776: Strategic Open Pit Mine Planning Course.pdf

10/29/2006

COLORADO SCHOOL OF MINES

2

OUTLINE

INTRODUCTION

PREVIOS WORK

CURRENT WORK

FUTURE WORK

CONCLUSIONS

MAIN

Page 777: Strategic Open Pit Mine Planning Course.pdf

10/29/2006

COLORADO SCHOOL OF MINES

3

INTRODUCTION Surface Mining Safety Research Program

• Safety Issues• Truck Proximity Warning• Collision Avoidance

• Global Positioning System (GPS)• Wireless Network Technology

Page 778: Strategic Open Pit Mine Planning Course.pdf

10/29/2006

COLORADO SCHOOL OF MINES

4

EE--Mail Requesting Help Mail Requesting Help

Jim:Jim:

You may or may not be aware that at couple of You may or may not be aware that at couple of weeks ago El Abra suffered a fatal accident weeks ago El Abra suffered a fatal accident when a truck driver backed through the berm. when a truck driver backed through the berm. Shortly after that happened, I was asked by Shortly after that happened, I was asked by Dennis Barlett and Hunter White to lead a team Dennis Barlett and Hunter White to lead a team of representatives from North American of representatives from North American operations to make sure that this was the last operations to make sure that this was the last accident of this type that we had to suffer. ….accident of this type that we had to suffer. ….

…………..…………..

Thanks,Thanks,

FerolFerol

The Problem We Face

Page 779: Strategic Open Pit Mine Planning Course.pdf

10/29/2006

COLORADO SCHOOL OF MINES

5

CONCEPTUALIZED SYSTEM

• Software for dump edge recognition

• Trimble GPS

• Trimble 900 MHz radios

• Introduction to 802.11b

Page 780: Strategic Open Pit Mine Planning Course.pdf

10/29/2006

COLORADO SCHOOL OF MINES

6

Field Tests at the Morenci Field Tests at the Morenci Copper Mine Copper Mine -- ArizonaArizona

MORENCI TEST PREVIOUS WORK

Page 781: Strategic Open Pit Mine Planning Course.pdf

10/29/2006

COLORADO SCHOOL OF MINES

7

CURRENT WORK

• LAFARGE QUARRY IMPLEMENTATIONOptiTrack

• Real Time

• Design of the System

• Hardware Development

• Software Development

• Robustness of the System

Page 782: Strategic Open Pit Mine Planning Course.pdf

10/29/2006

COLORADO SCHOOL OF MINES

8

OptiTrack SYSTEM CURRENT WORK

Page 783: Strategic Open Pit Mine Planning Course.pdf

10/29/2006

COLORADO SCHOOL OF MINES

9

Description of the System (Infrastructure)

GPS Differential Correction Service

Data, DTM

GPS data

GPS Differential

GPS

Control Base

OptiTrack Network at Lafarge Quarry

Wireless CommunicationTransmitting Truck Position

Wireless Communication Between Lafarge Quarry and CSM

DTM

Page 784: Strategic Open Pit Mine Planning Course.pdf

10/29/2006

COLORADO SCHOOL OF MINES

10

OptiTrack (Lafarge) CURRENT WORK

• Mobile Clients• Haul Trucks• Manager Trucks• PDAs

• Central Points• Repeaters• Trailer

Page 785: Strategic Open Pit Mine Planning Course.pdf

10/29/2006

COLORADO SCHOOL OF MINES

11

OptiTrack Mobile Clients CURRENT WORK

Page 786: Strategic Open Pit Mine Planning Course.pdf

10/29/2006

COLORADO SCHOOL OF MINES

12

OptiTrack Haul Trucks CURRENT WORK

DC Injector N-Female N-Female

Amplifier 1wt WAF2400-1000

N-Female N -Female

Barrel Adapter N-Male N -Male

Lighting Arrestor WRLA-1.2/1.8 N-Female N -Female

Jumper Cable

N-Male RPTNC-Female

LMR600

N-Male N-Male

Omni Antenna

RS 232

GPS SatellitesGPS Device & Antenna

Wireless PCMCI Card Cisco LMC 352

Page 787: Strategic Open Pit Mine Planning Course.pdf

10/29/2006

COLORADO SCHOOL OF MINES

13

OptiTrack Central Points CURRENT WORK

• Repeater at Mechanic House

• Repeater on the Trailer

Page 788: Strategic Open Pit Mine Planning Course.pdf

10/29/2006

COLORADO SCHOOL OF MINES

14

OptiTrack Repeater CURRENT WORK

Page 789: Strategic Open Pit Mine Planning Course.pdf

10/29/2006

COLORADO SCHOOL OF MINES

15

OptiTrack Trailer CURRENT WORK

Page 790: Strategic Open Pit Mine Planning Course.pdf

10/29/2006

COLORADO SCHOOL OF MINES

16

OptiTrack Trailer CURRENT WORK

Page 791: Strategic Open Pit Mine Planning Course.pdf

10/29/2006

COLORADO SCHOOL OF MINES

17

Schematic Representation of OptiTrack TrailerCURRENT WORK

Power Supplies Solar Panels

Cisco AP 350

DC Injector N-Female N-Female

Amplifier 1wt WAF2400-1000

N-Female N-Female

Barrel Adapter N-Male N-Male

Lighting Arrestor WRLA-1.2/1.8 N-Female N-Female

Jumper Cable

N-Male RPTNC-Female

LMR600

N-Male N-Male

Coax Cable

LMR600 N-Male N-Male

Coax Cable

LMR600 N-Male N-Male

Coax Cable LMR600

N-Male N-Male

Directional Antennas WRPA2400 11-AM

V Pol N-Male

Point to Point Antenna WR2400-24M H Pol

N-Female

RPTNC-male

Page 792: Strategic Open Pit Mine Planning Course.pdf

10/29/2006

COLORADO SCHOOL OF MINES

18

OptiTrack (CSM) CURRENT WORK

OptiTrack at CSM GPS Laboratory

Server

Page 793: Strategic Open Pit Mine Planning Course.pdf

10/29/2006

COLORADO SCHOOL OF MINES

19

OptiTrack Antenna CURRENT WORK

Point to Point Antenna (Brown Building)

Page 794: Strategic Open Pit Mine Planning Course.pdf

10/29/2006

COLORADO SCHOOL OF MINES

20

Schematic Representation of OptiTrack (CSM)CURRENT WORK

Cisco AP 350

RPTNC-male

Jumper Cable N-Male RPTNC-Female

DC Injector N-Female N-Female

LMR600 N-Male N-Male

Amplifier 1wt WAF2400-1000 N-Female N-Female

Barrel Adapter N-Male N-Male

Lighting Arrestor WRLA-1.2/1.8 N-Female N-Female

RF Coax Cable N-Male N-Male

Antenna on the roof of Brown Building

Page 795: Strategic Open Pit Mine Planning Course.pdf

10/29/2006

COLORADO SCHOOL OF MINES

21

OptiTrack Software CURRENT WORK

Page 796: Strategic Open Pit Mine Planning Course.pdf

10/29/2006

COLORADO SCHOOL OF MINES

22

Future Work

• New Mobile Clients• PDAs• Sensors

• Radar Implementation

• Mobile Adhoc Network(MANET)

Page 797: Strategic Open Pit Mine Planning Course.pdf

10/29/2006

COLORADO SCHOOL OF MINES

23

Description of the System (Ad Hoc)

GPS Differential Correction Service

Data, DTM

GPS data

GPS Differential

GPS

Control Base

OptiTrack Network at Lafarge Quarry

Wireless CommunicationTransmitting Truck Position

Wireless Communication Between Lafarge Quarry and CSM

DTM

Page 798: Strategic Open Pit Mine Planning Course.pdf

10/29/2006

COLORADO SCHOOL OF MINES

24

Broadcast Protocols Future Work

Existing Protocols• Flooding• Adaptive-SBA• AHBP-EX

OptiTrack Protocols• Naive Bayes• Adaptive Boosting (AdaBoost)

Page 799: Strategic Open Pit Mine Planning Course.pdf

10/29/2006

COLORADO SCHOOL OF MINES

25

Existing Protocols Future Work

Page 800: Strategic Open Pit Mine Planning Course.pdf

10/29/2006

COLORADO SCHOOL OF MINES

26

Machine Learning Approach Future Work

Classification

Rebroadcast

Discard

Incoming Packet

Page 801: Strategic Open Pit Mine Planning Course.pdf

10/29/2006

COLORADO SCHOOL OF MINES

27

OptiTrack Protocols Future Work

Page 802: Strategic Open Pit Mine Planning Course.pdf

10/29/2006

COLORADO SCHOOL OF MINES

28

Simulation Comparison Future Work

95 %Confidence Interval

10Number of Trials

100 secondsSimulation Time

50Node Max. IFQ Length

64 bytes payloadData Packet Size

100 meterNode Tx Distance

350 x 350 meterNetwork Area

NS-2 (1b7a)Simulator

ValueSimulation Parameter

8060402010Pkt. Src. Rate (pkts/sec)

20151051Average Speed (m/sec)

9070605040Number of Nodes

54321Trial

Page 803: Strategic Open Pit Mine Planning Course.pdf

10/29/2006

COLORADO SCHOOL OF MINES

29

Delivery Ratio of the Protocols

Delivery Ratio

60

65

70

75

80

85

90

95

100

1 2 3 4 5

Trial

Deliver

y R

atio

Adaptive SBA

AHBP-EX

Flooding

AdaBoost

Naive Bayes

Future Work

Page 804: Strategic Open Pit Mine Planning Course.pdf

10/29/2006

COLORADO SCHOOL OF MINES

30

Number of Retransmitting Nodes

Number of Retransmitting Nodes

0

10

20

30

40

50

60

1 2 3 4 5

Trial

Num

ber

of R

etra

nsm

ittin

g N

odes

Adaptive SBA

AHBP-EX

Flooding

AdaBoost

Naive Bayes

Future Work

Page 805: Strategic Open Pit Mine Planning Course.pdf

10/29/2006

COLORADO SCHOOL OF MINES

31

End-to-End Delay Future Work

End-to-End Delay

0

0,5

1

1,5

2

2,5

3

1 2 3 4 5

Trial

End-to

-End D

elay Adaptive SBA

AHBP-EX

Flooding

AdaBoost

Naive Bayes

Page 806: Strategic Open Pit Mine Planning Course.pdf

10/29/2006

COLORADO SCHOOL OF MINES

32

ADHOC & INFRASTRUCTURE Future Work

ADHOC

Infrastructure

Page 807: Strategic Open Pit Mine Planning Course.pdf

10/29/2006

COLORADO SCHOOL OF MINES

33

1.1. The tests that are being carried out at CSM as well The tests that are being carried out at CSM as well as in Lafarge Quarry indicate that as in Lafarge Quarry indicate that ““OptiTrackOptiTrack”” softsoftware system can be used as a proximity warning dware system can be used as a proximity warning device to avoid collisions between off highway truckevice to avoid collisions between off highway trucks and the other vehicles as well as to monitor truck s and the other vehicles as well as to monitor truck positions with respect to dump edge on a 3positions with respect to dump edge on a 3--D topoD topography map.graphy map.

2.2. Integration of the developed GPS based system witIntegration of the developed GPS based system with other systems based on concepts such as RFID, rh other systems based on concepts such as RFID, radar, and video cameras need to be pursued to havadar, and video cameras need to be pursued to have a complete and reliable collision avoidance systee a complete and reliable collision avoidance system.m.

Conclusions

Page 808: Strategic Open Pit Mine Planning Course.pdf

Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512

Sustainability Issues in Mining

Antonio Peralta

by

Source: Rozgonyi and Ramirez, January 2003

Page 809: Strategic Open Pit Mine Planning Course.pdf

Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512

What is Sustainable Development?Sustainable development is:

• A concept of needs;

• Idea of limitations;

• Future oriented paradigm, and;

• A process of change.

This concept reflects a compromise between the world’s tripartite aspirations:

• ECONOMICAL: Promoting economic betterment but preserving of options for future generations.

• ECOLOGICAL: Protecting, maintaining and restoring of environmental quality.

• SOCIAL: Promoting and improving social and community stability and values.

SUSTAINABLEDEVELOPMENT

ECONOMICAL

ECOLOGICALSOCIAL

SUSTAINABLEDEVELOPMENT

ECONOMICAL

ECOLOGICALSOCIAL

Page 810: Strategic Open Pit Mine Planning Course.pdf

Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512

Sustainable Development in Mining

§ Applying the concepts of sustainable development and sustainable natural resource management to energy and mineral resources is not an oxymoron.

§ Energy and mineral resources are mostly not renewable; sustaining any given deposit or mine is not possible. However, SD involves designing, developing and managing resources in a way that is conducive to long-term wealth creation. Minerals are a form of natural capital and thus of endowed wealth.

§ Therefore, mining projects can serve sustainability objectives if they are designed and implemented in ways that build viable long-term capacities, strengthen communities and rehabilitate damaged ecosystems.

Page 811: Strategic Open Pit Mine Planning Course.pdf

Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512

Global Mining and Mineral Industry Trends

• International mergers, and globalization,

• Shifts in supply availability and recycling,

• Consumer demand (responsibility for the whole life cycle of the minerals, metals),

• Political restructuring,

• Economic transformations,

• Social and cultural developments,

• Public attitudes about mining and minerals,

• The new paradigm of “sustainable development”,

• An era of increasing regulations affecting all phases of activity from exploration and extraction to processing and products.

Page 812: Strategic Open Pit Mine Planning Course.pdf

Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512

Principal Mining and Environmental Actions During Each Phase of Mine Development

Environmental assessment

Rehabilitation planExploration permit application

Exploration road construction

Rock core drillingGeochemical analysisGeostatistical analysisOrebody evaluation

Exploration

Comprehensive EIA and reviewMitigation planningReclamation and closure planningConceptual design for closureReclamation and closure costing

Closure fund design

Plan of operationsTechnology selection

Conceptual to final designsCosting and cost benefit analysisInvestment brokerage

Feasibility study

Environmental baseline studyEnvironmental assessment“Fatal Flaw” analysis

Initiation of permitting process

Initial mine and minerals process planningFacilities sitingSchedulingEconometric analysisInitial technology selection

Pre-feasibility study

PRINCIPAL ENVIRONMENTAL MANAGEMENT ACTION

PRINCIPAL MINE PLANNING ACTIONPHASE IN MINE PROJECT DEVELOPMENT

Page 813: Strategic Open Pit Mine Planning Course.pdf

Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512

Principal Mining and Environmental Actions During Each Phase of Mine Development (cont.)

Implementation of closure planSite cleanupFinal reclamationFinal impact assessmentPost closure planning

Facilities decommissioningDismantlingDecontaminationBurialRemovalAsset recoveryRecycling

Closure

Installation of pollution control facilitiesGeneral environmental management (air,

water, land)Construction phase reclamation and

closure

Access and haul road developmentSite clearing and grubbingEarth moving and surface water managementMine dewateringUtilities installationBuilding and infrastructure construction

Construction

TreatmentMaintenanceMonitoringFinal bond release

Post closure

General environmental managementPerformance assessment/auditMonitoringConcurrent reclamationFinal closure designPartial closurePartial bond release

Ore extractionSize reductionMinerals processingSmelting and refiningMaintenance and upgrade

Production

PRINCIPAL ENVIRONMENTAL MANAGEMENT ACTION

PRINCIPAL MINE PLANNING ACTIONPHASE IN MINE PROJECT DEVELOPMENT

Page 814: Strategic Open Pit Mine Planning Course.pdf

Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512

Elements of Environmental Planning

A). INITIAL PROJECT EVALUATION

B). THE STRATEGIC PLAN

C). THE ENVIRONMENTAL PLANNING TEAM

Page 815: Strategic Open Pit Mine Planning Course.pdf

Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512

Environmental Planning Procedures (EPP)A). INITIAL PROJECT EVALUATION:

1. Prepare a detailed outline of the proposed action.

2. Identify permit requirements.

3. Identify major environmental concerns.

4. Evaluate the opportunity for and likelihood of public participation in the decision making process.

5. Consider the amount and effect of delay possibly resulting from public participation during each stage of the project.

6. Evaluate the organization and effectiveness of local citizens groups.

7. Determine the attitudes and experiences of governmental agencies.

8. Consider previous industry experience in the area.

9. Consider recent experience of other companies.

10. Identify possible local consultants and evaluate their ability and experience.

11. Consider having a local consultant check the conclusions of the initial evaluation.

Page 816: Strategic Open Pit Mine Planning Course.pdf

Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512

Environmental Planning Procedures (EPP) (cont.)

B). THE STRATEGIC PLAN:

1. Outline of technical information needed to obtain permits and to address legitimate environmental, land use and socio-economic concerns. Permitting process is quite long and complex.

2. Categorically assign responsibilities for the acquisition of the technical information and hire necessary consultants.

3. Prepare a schedule for obtaining information and data and for submitting permit applications to the appropriate agencies.

4. Select local legal, technical and public relations consultants.

5. Avoid hostile confrontations with environmental groups.

6. Develop a consistent program for the generation of credible factual information.

7. Perform risk assessment.

8. Perform cost analysis.

9. Prepare mine reclamation plan.

Page 817: Strategic Open Pit Mine Planning Course.pdf

Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512

Environmental Planning Procedures (EPP) (cont.)

C). THE ENVIRONMENTAL PLANNING TEAM

The team shall be multidisciplinary:

Ø Mining engineers

Ø Metallurgical engineers

Ø Biologists

Ø Environmentalists

Ø Toxicologists

Ø etc.

Page 818: Strategic Open Pit Mine Planning Course.pdf

Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512

Risk Assessment

1. Data collection and hazard evaluation.

2. Toxicity assessment.

3. Exposure assessment.

4. Risk characterization.

a). Non carcinogenic risks.

b). Carcinogenic risks.

5. Risk assessment / management by considering:

a). What types of problems or failures could occur, and what is the probability that each one will occur?

b). What types of environmental impacts could result?

c). What types of compliance-related retrofits or remediation methods could be required?

d). What are the possible fines or remediation costs?

Page 819: Strategic Open Pit Mine Planning Course.pdf

Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512

Cost Analysis

By considering:

Ø Capital costs

Ø Operating costs

Ø Closure costs

Ø Potential costs for retrofits associated with regulatory compliance

Ø Potential cost for remediation

Ø Life-cycle environmental costs

Page 820: Strategic Open Pit Mine Planning Course.pdf

Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512

Mine Reclamation

i. Surface and groundwater management

ii. Mine waste management

iii. Tailings management

iv. Cyanide heap and vat leach systems

v. Acid Mine Drainage Control

vi. Landform reclamation

vii. Revegetation

viii. Site stability

ix. Subsurface stabilization

x. Erosion prevention

Page 821: Strategic Open Pit Mine Planning Course.pdf

Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512

Mine Reclamation

i. Surface and groundwater management

ii. Mine waste management

iii. Tailings management

iv. Cyanide heap and vat leach systems

v. Acid Mine Drainage Control

vi. Landform reclamation

vii. Revegetation

viii. Site stability

ix. Subsurface stabilization

x. Erosion prevention

Page 822: Strategic Open Pit Mine Planning Course.pdf

Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512

Location of the McLaughlin Mine in California

Page 823: Strategic Open Pit Mine Planning Course.pdf

Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512

Facilities map of the McLaughlin Mine

Page 824: Strategic Open Pit Mine Planning Course.pdf

Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512

Mine waste management

1) 2)

3) 4)

M

c

L

a

u

g

h

l

i

n

Early stage for waste disposal & AMD control facilities Advance of the waste disposal works

Final limit of the waste dump Erosion control by revegetating is started

Page 825: Strategic Open Pit Mine Planning Course.pdf

Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512

5) 6)

7) 8)

Mine waste management (cont.)

M

c

L

a

u

g

h

l

i

n

Advance on the erosion control & and pit backfilling

South pit is backfilled & west dump is almost covered

East waste dump is completely covered

Waste dumps encapsulation is finished

06/14/ 98

05/04/ 92 05/04/ 93

05/10/ 93

Page 826: Strategic Open Pit Mine Planning Course.pdf

Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512

Acid Mine Drainage Control

AMD control facilities at the west waste dump

Page 827: Strategic Open Pit Mine Planning Course.pdf

Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512

Revegetation

Supervising the revegetation works on the west waste dump

(notice the AMD control facilities on the right side)

Page 828: Strategic Open Pit Mine Planning Course.pdf

Surface Mine Design Surface Mine Design –– MNGN312/512MNGN312/512

Minimizing AMD in open pit mining through mine planning

Antonio Peralta

by

Page 829: Strategic Open Pit Mine Planning Course.pdf

Acid Mine Drainage (AMD)Acid Mine Drainage (AMD)

q It encompasses all issues associated with the environmental effects of sulphide oxidation resulting from mining activities.

q Its significant potential for long-term environmental degradation makes it one of the biggest environmental issues facing the mining industry.

Page 830: Strategic Open Pit Mine Planning Course.pdf

Acid Mine Drainage ExamplesAcid Mine Drainage Examples

Page 831: Strategic Open Pit Mine Planning Course.pdf

Contributing FactorsContributing Factors

q Primary factors are directly involved in the generation of sulphide oxidation products.

q Secondary factors consume or alter those products.

q Tertiary factors are the physical conditions that influence the process.

Page 832: Strategic Open Pit Mine Planning Course.pdf

Problems for Mine OperatorsProblems for Mine Operators

q Impact on mine water quality.

q Impact on aquatic ecosystems.

q Impact on riparian communities.

q Impact on groundwater quality.

q Impairment of the use of waterways.

q Revegetating and stabilizing mine wastes.

q Long term liability.

Page 833: Strategic Open Pit Mine Planning Course.pdf

Acid Mine Drainage ControlAcid Mine Drainage Control

q There is a number of well established principles for minimizing AMD.

q Mine planning to minimize AMD is the most cost effective and desirable solution to the problem.

q Treatment is less desirable due to the long term nature of AMD and associated high treatment costs.

Page 834: Strategic Open Pit Mine Planning Course.pdf

Principles to Prevent Acid Mine DrainagePrinciples to Prevent Acid Mine Drainage

q Exclusion of oxygen from wastes.

q Control of water flux within wastes.

q Minimize transport of oxidation products.

q Neutralization of AMD with alkaline materials.

q Monitoring to determine the effectiveness of remediation measures.

Page 835: Strategic Open Pit Mine Planning Course.pdf

11stst Step Step –– Characterization of Rock TypesCharacterization of Rock Types

q Geological assessment.

q Geochemical tests, classified as static and kinetic tests.

q Static testing evaluates the acid generating and acid neutralizing processes.

q Kinetic testing evaluates the rate of sulphide oxidation, AMD characteristics, and assess potential management techniques.

Page 836: Strategic Open Pit Mine Planning Course.pdf

Geological Assessment Geological Assessment –– Information SourcesInformation Sources

q Acid generation characteristics of similar ore bodies and host rocks.

q Relevant information should be logged and recorded from drill core during the exploration stage.

q Core samples must be retained for further testing.

Page 837: Strategic Open Pit Mine Planning Course.pdf

Geological Assessment Geological Assessment –– SamplingSampling

q Sampling should be representative, based on accepted statistical procedures.

q Representative profiles of all geological units should be sampled.

q The number of samples will depend on geological variability, complexity of rock types, and level of confidence required.

Page 838: Strategic Open Pit Mine Planning Course.pdf

Geological Assessment Geological Assessment –– Handling of SamplesHandling of Samples

q Samples should be stored in a cool, dry environment to minimize sulphide oxidation prior to testing.

q Static tests may require as little as 2 grams of sample.

q Kinetic tests require a minimum of 500 grams of sample.

Page 839: Strategic Open Pit Mine Planning Course.pdf

Geological Assessment Geological Assessment –– InterpretationInterpretation

q Topography and drillholes

Page 840: Strategic Open Pit Mine Planning Course.pdf

Geological Assessment Geological Assessment –– InterpretationInterpretation

q Cross section of the drillholes

Page 841: Strategic Open Pit Mine Planning Course.pdf

Geological Assessment Geological Assessment –– InterpretationInterpretation

q Interpretation of rock types

Page 842: Strategic Open Pit Mine Planning Course.pdf

Geological Assessment Geological Assessment –– InterpretationInterpretation

q 3D view of two interpreted sections

Page 843: Strategic Open Pit Mine Planning Course.pdf

Geological Assessment Geological Assessment –– InterpretationInterpretation

q 3D view of two interpreted sections

Page 844: Strategic Open Pit Mine Planning Course.pdf

Geochemical Tests Geochemical Tests –– Static TestsStatic Tests

q Acid base accounting or net acid producing potential (NAPP) test.

q Net acid generation (NAG) test.

q Saturated paste pH and conductivity (EC).

q Total and soluble metal analysis

Page 845: Strategic Open Pit Mine Planning Course.pdf

Net Acid Producing PotentialNet Acid Producing Potential

q NAPP is determined by subtracting the estimated acid neutralizing capacity of a sample from the estimated potential acidity of the sample.

q It has three components:Maximum potential acidity (MPA)Acid neutralizing capacity (ANC)Sample classification.

Page 846: Strategic Open Pit Mine Planning Course.pdf

Net Acid Generation TestNet Acid Generation Test

q NAG comprises the addition of a strong oxidizing agent such hydrogen peroxide to a prepared sample and the measurement of the solution pH and acidity after the oxidation reaction is complete.

q This test can provide and indication of sulphide reactivity and available neutralizing potential within 24 hours.

Page 847: Strategic Open Pit Mine Planning Course.pdf

Saturated paste pH and conductivitySaturated paste pH and conductivity

q The test gives a preliminary indication of the in situpH and the reactivity of the materials present in the sample.

q A crushed sample (<1 mm) is saturated to create a paste and the pH and EC is determined after a period of equilibration.

Page 848: Strategic Open Pit Mine Planning Course.pdf

Total and soluble metal analysisTotal and soluble metal analysis

q Initial screening should compare metal concentration in the solids with that of the background soils and country rocks in the area.

q Statistical methods are available to determine whether any enrichment is significant.

Page 849: Strategic Open Pit Mine Planning Course.pdf

Geochemical Tests Geochemical Tests –– Kinetic TestsKinetic Tests

q They simulate weathering and oxidation of rock over time under exposure to moisture and air.

q They provide an indication of the oxidation rate and time periods for onset of acid generation (lag time).

q Columns and humidity cells are the most used kinetic test techniques.

Page 850: Strategic Open Pit Mine Planning Course.pdf

Rock ClassificationRock Classification

q Acid Generating (AG)

q Potentially acid generating (PAG)

q Potentially acid consuming (PAC)

q Potentially neutral (PN)

Classification for regulatory and permitting purposes.

Page 851: Strategic Open Pit Mine Planning Course.pdf

22ndnd Step Step –– Quantifying the Materials to be disposedQuantifying the Materials to be disposed

q AMD waste materials includes overburden, waste rock, pit walls, pit floor and tailings.

q A database of the AMD parameters determined in the tests is required.

q A predictive AMD block model should be created using the information available in the database.

Page 852: Strategic Open Pit Mine Planning Course.pdf

Block Modeling Block Modeling

q A block model is a three-dimensional spatial representation of an ore body.

q It is used to quantify the geology an economics of the deposit.

q It is developed by dividing the ore body and the host rock into regularly shaped blocks representing the smallest mineable unit.

Page 853: Strategic Open Pit Mine Planning Course.pdf

Information in the Block Model Information in the Block Model

q Ore grades.

q Contaminants.

q Metallurgical recoveries.

q Physical parameters of the ore.

q Economic parameters.

q Environmental parameters.

Page 854: Strategic Open Pit Mine Planning Course.pdf

Steps to create a block modelSteps to create a block model

q Produce a detailed geologic interpretation.

q Create drill hole composites per material type.

q Perform statistical analysis.

q Perform spatial analysis if sufficient data exist.

q Interpolate a value into each block, for each of the required variables.

Page 855: Strategic Open Pit Mine Planning Course.pdf

Complete Block ModelComplete Block Model

q Block model includes waste and ore blocks.

Page 856: Strategic Open Pit Mine Planning Course.pdf

Constrained Block ModelConstrained Block Model

q Block model includes only ore blocks.

Page 857: Strategic Open Pit Mine Planning Course.pdf

Block Model and Mine DesignBlock Model and Mine Design

q Blocks inside and outside the final pit limit.

Page 858: Strategic Open Pit Mine Planning Course.pdf

33rdrd Step Step -- Mining DevelopmentMining Development

q Site potential and reserves

éExpected pit development

q Development phasing

éPeriod of development

éAreas of extractionby phase

Page 859: Strategic Open Pit Mine Planning Course.pdf

2005

2035

2020

2050

Maps for different time periodsMaps for different time periods

Page 860: Strategic Open Pit Mine Planning Course.pdf

Coordination with ReclamationCoordination with Reclamation

q Clearing / Vegetation removal

q Topsoil management

q Overburden / Waste rockmanagement

q Grading principles

q Erosion control

q Revegetation

Page 861: Strategic Open Pit Mine Planning Course.pdf

Isolation Strategy Isolation Strategy

q The objective is to isolate reactive wastes for selective disposal either separately or within non-reactive materials.

q In some cases, it may be preferable to segregate highly reactive wastes within a separate facility to permit intensive treatment and control strategies.

Page 862: Strategic Open Pit Mine Planning Course.pdf

Waste EncapsulationWaste Encapsulation

q AMD waste is selectively handled and surrounded with non-acid producing materials to limit flow of air and water into waste and AMD flow out.

q A cell structure is formed. The surface is covered with compacted benign material, usually clay.

Page 863: Strategic Open Pit Mine Planning Course.pdf

InIn--Pit DisposalPit Disposal

q Similar in concept to encapsulation. Method is useful where a mined out pit of sufficient size is available.

q With effective mine planning an early closure of one of a series of mined pits allows for in-pit disposal of AMD wastes.

Page 864: Strategic Open Pit Mine Planning Course.pdf

CoCo--disposal and Blending of Wastedisposal and Blending of Waste

q Involves the blending/mixing and co-disposal of AMD wastes with benign non-acid producing materials or even acid neutralizing materials.

q Small cells within a waste dump are rapidly filled and covered to reduce AMD generation and water ingress.

Page 865: Strategic Open Pit Mine Planning Course.pdf

CoversCovers

q A low permeability cover is constructed over an existing waste dump, mainly using locally available borrow or benign waste, to reduce the infiltration of surface water and infusion of air into the dump.

Page 866: Strategic Open Pit Mine Planning Course.pdf

Recovery and TreatmentRecovery and Treatment

q Option for marginal acid producing wastes where subsequent acid drainage is recovered and treated downstream.

q Collection/recovery systems can include catchment ponds, drains, trenches and groundwater bores.

Page 867: Strategic Open Pit Mine Planning Course.pdf

ConclusionsConclusions

qMine planning can be a cost effective method to control AMD in open pit mines.

q There are three basic steps to achieve AMD control: characterize the rock types, quantify the amount and content of the rocks, and develop a mine plan according to the previous steps.

q The mine plan should include waste management strategies to minimize AMD: isolation, encapsulation, in-pit disposal, co-disposal, blending, covers, and treatment.

q A combination of these strategies could be highly effective to control AMD.

Page 868: Strategic Open Pit Mine Planning Course.pdf

Questions and comments???????Questions and comments???????

Page 869: Strategic Open Pit Mine Planning Course.pdf

Summitville, ColoradoSummitville, Colorado

Page 870: Strategic Open Pit Mine Planning Course.pdf

Summitville, ColoradoSummitville, Colorado

According to the United States Environmental Protection Agency (US EPA), mining generates twice as much waste as all other American industries put together.

So-called "hard rock" mining wastes are acidic and contaminated with toxic heavy metals which have poisoned more than 12,000 miles of streams and rivers and 180,000 acres of lakes.

EPA estimates the public cost to clean up the more than 550,000 abandoned mines in America at between $32-72 billion.

The very scale of today's massive open-pit mining operations means that sometimes cleanup costs will outstrip the value of the metals pulled out of the ground, as happened with the $232 million cleanup of the Summitville mine in southern Colorado.

Page 871: Strategic Open Pit Mine Planning Course.pdf

Examples, ColoradoExamples, Colorado

At Eagle mine, a zinc, copper and silver operation, ten million tons of mine waste and mine tailings were left along the banks of theEagle River in Gilman Colorado.

Cleanup costs exceeded $55 million which totaled more than $5.50per ton of mine waste.

A zinc, lead and silver mine at Smuggler Mountain in PitkinColorado. The estimated cost for environmental recovery is $7.2 million. This equals $2.40 per ton of waste.

Page 872: Strategic Open Pit Mine Planning Course.pdf

Feasibility StudiesThe formal feasibility study includes an economic analysis of the rate of return that can be expected from the mine at a certain rate of production.

Some of the factors considered during such an economic analysis are:

Tons in the depositGrade of the mine productMill recoverySale price of the metal or mineralCost of mining per tonCost of milling per tonRoyaltiesCapital cost of the mine

Capital Cost of the millExploration and development costMining rate, tons per dayDepreciation method usedDepletion allowanceWorking capital necessaryMiscellaneous costs of operationTax rate

Page 873: Strategic Open Pit Mine Planning Course.pdf

Risk

Mining is a very risky business.

The most serious risks in any mining project are those associated with:

•Geology: the actual size and grade of the minable portion of the deposit,

•metallurgical factors: how much of the orebody can be recovered, and

•Economics: metal markets, interest rates, mining, processing,ect.

Page 874: Strategic Open Pit Mine Planning Course.pdf

Return on Investment

In order to compensate for risk, a mining organization will require a minimum acceptable rate of return on investment.

The cost of borrowing capital for the mine or of generating the needed capital internally within the company must be considered.

If a company has a number of attractive investment opportunities, the rate of return from the proposed mine venture may be compared with the rate expected on a different mining venture elsewhere, or with some other business opportunity unrelated to mining.

Management has an obligation to its stockholders or investors toselect projects with the best rate of return.

Page 875: Strategic Open Pit Mine Planning Course.pdf

As a general rule of thumb, a project must have better than a 15-percent rate of return to be considered by a major company.

An individual commonly expects a 30- to 50 percent rate of return to consider investing in a mining venture.

Among other uses of the cash flow generated by the mine, these funds must finance:

•continuing exploration elsewhere, •pay for past failures, and •contribute to the mine's portion of main office and general overhead.

Page 876: Strategic Open Pit Mine Planning Course.pdf

Time Value of MoneyMoney has a time value. The future value of an investment can be calculated by:

where:P = Present value of investmentF = Future value of investmenti = interest rateN = number of years

For example $100 invested at 10% interest for 1, 2, and 3 years would yield:

F = 100(1 + .10)1 = $110.00F = 100(1 + .10)2 = $121.00F = 100(1 + .10)3 = $133.10

Ni)P(1F +=

Page 877: Strategic Open Pit Mine Planning Course.pdf

Time Value of MoneyConversely money received in the future is not as valuable as money received today. If money is received in the future:

Using the same example:

P = 110.00/(1 + .10)1 = $100.00P = 121.00/(1 + .10)2 = $100.00P = 133.10/(1 + .10)3 = $100.00

Ni)(1/FP +=

Page 878: Strategic Open Pit Mine Planning Course.pdf

DCF-ROR

The criterion most commonly employed in the minerals industry when evaluating the rate of return on an investment proposal is called the discounted cash flow rate of return (DCF-ROR).

The term is a special version of the more generic term, internal rate of return (IRR).

The internal rate of return is defined a that interest rate which equates the sum of the present value in cash inflows with the sum of the present value of cash outflows for a project:

ΣPV cash inflows = ΣPV cash outflows (3)

Page 879: Strategic Open Pit Mine Planning Course.pdf

DCF-RORThe DCF-ROR can be calculated by:

(4)

where:CFn = Amount of cash in or out in a given yearn = YearN = Project lifei = DCF-ROR

Once the cash flows for a project have been determined, the interest rate i can be solved for using an iterative process, i.e. guess at an initial value for i and then solve Equation 4 until a result of 0 is obtained.

0i)(1

CFN

0nn

n =+∑

=

Page 880: Strategic Open Pit Mine Planning Course.pdf

Steps Involved in Cash Flow Analysis

The evaluation of a mining project is usually an iterative process using the following steps:

1. Select a mining method2. Select a production rate3. Calculate Capital and Operating Costs4. Select cutoff grade and tonnage5. Calculate cash flow and return

Change steps 4, 2, and 1 and select the alternative that gives thehighest return.

Page 881: Strategic Open Pit Mine Planning Course.pdf

Steps Involved in Cash Flow AnalysisIn a feasibility study, attempt to quantify all geologic, technical,marketing, environmental, political, etc. factors. Many of thesevariables are dependent on each other. A feasibility study are usually divided into the pre-production, production, and post-production phases:

1. Preproduction PeriodExploration

Water and land acquisitionMine and mill capital

Working capital, etc2. Production Period

Revenue less costsCalculation Of Annual Cash Flow

3. Postproduction PeriodEquipment salvage

Working capital liquidation

Page 882: Strategic Open Pit Mine Planning Course.pdf

Steps Involved in Cash Flow Analysis

Page 883: Strategic Open Pit Mine Planning Course.pdf

DepletionOne of the features that distinguish a mining enterprise from many other businesses is that during production, the company’s assets, i.e. the ore, is consumed.

The percentage depletion allowance is based on the idea that as minerals are extracted, the mine is worth less.

The percentage depletion allowance permits mining companies to deduct a certain percentage from their gross income to reflect the mine's reduced value over time.

Page 884: Strategic Open Pit Mine Planning Course.pdf

DepreciationDepreciation is an allowable deduction when computing taxable income that represents the exhaustion, wear, and tear of property used in a trade or business, or of property held for the production of income.

The purpose of the depreciation deduction is to provide a means by which a business or trade can recapture the capital needed to keep itself in business.

Therefore depreciation allowances for capital assets are deducted from taxable income in an orderly manner such that the property owner has deducted the initial investment in the asset by the time it wears out or becomes exhausted.

Having recaptured the initial asset cost from the annual tax deductions, the owner can, in theory, replace the worn-out piece of equipment with a new one and keep himself in business.

Page 885: Strategic Open Pit Mine Planning Course.pdf

Case StudyThe calculation of the cash flow and DCF-ROR is illustrated using a bedded zinc deposit, producing 6000 tons per day, with total reserves of 22.5 MM Tons @ 14% zinc.

Simplifying and other assumptions:1. No royalty2. No investment tax credits3. Straight line depreciation and depreciation life equal to life of property4. Federal, state, and local taxes equal to 40% net after depletion5. No replacement or additional equipment requirements 6. No start-up costs or learning curve 7. Uniform grade mined over mine life 8. Uniform production rate over mine life 9. Operating costs constant over mine life 10. Mine would be division of large profitable corporation with 100% of exploration

and development expensed11. No consideration of cost depletion12. Price/cost differential constant over life of mine with no consideration of escalation

and inflation

Page 886: Strategic Open Pit Mine Planning Course.pdf

Cash Flow Calculations

Pre-Production PeriodYear 1 2 3 4 5 6 7 TotalExploration *1 2,000 4000 4000 0 0 0 0 10,000Development *2 0 0 0 4000 8000 8000 0 20,000Mine/Mill 0 0 0 15000 36000 36000 0 87,000Working Capital 0 0 0 0 0 2600 9,300 11,900Total Investment (2,000) (4,000) (4,000) (19,000) (44,000) (46,600) (9,300) (128,900)Tax Savings *3 800 1600 1600 1600 3200 3200 0 12,000Net Cash Flow (1,200) (2,400) (2,400) (17,400) (40,800) (43,400) (9,300) (116,900)

*1 Expensed under Section 617 of IRS Code*2 Expensed*3 Assume federal, state, and local tax rate = 40% of net after depletion

Cash Flow Calculations ($1,000)

Page 887: Strategic Open Pit Mine Planning Course.pdf

Zinc Smelter Schedule

PaymentsSilver: Deduct 2 Troy oz., pay for 80% of remainder at

Handy & Harman quotation for refined silver inMetals Week, averaged for the calendar monthfollowing delivery, less $.055 per oz.

Lead: No payment.

zinc: Pay for 85% of zinc content at delivery price for prime western zinc published in Metals Week, averaged for the calendar month following delivery,less $.015 per pound.

Page 888: Strategic Open Pit Mine Planning Course.pdf

Zinc Smelter Schedule

DeductionsSmelter Charge:

$170/dry ton

Price Adjustment: Increase by $3.00 per ton for each $.01 that the zincquotation exceeds $.40 per pound. Fractions in proportion.

Decrease by $2.00 per ton for each $.01 that the zinc quotation decreases below $.40 per pound. Fractions in proportion.

Page 889: Strategic Open Pit Mine Planning Course.pdf

Smelter Schedule CalculationsConcentrate Grade = 55%zinc Price = $0.47/lb

Payments:2,000 lb/ton * 0.55 * 0.85 * $(0.47- 0.015)/lb = $425.43/ton

Deductions:Base Charge 170.00Price Adjustment(47- 40)c * $3.00/c = 21.00Total Deductions: (191.00)

Freight:Truck 5.00Rail 15.00Total Freight: (20.00)

Net Smelter Return/Ton Concentrate (NSR/T) $214.43/ton

Page 890: Strategic Open Pit Mine Planning Course.pdf

Revenue and Operating CalculationsRevenue/year = Tons/year Concentrate * NSR/ton

Tons/year Concentrate = (Tons/year Ore * Grade * Mill Recovery)/(Conc. Grade)Mine Schedule = 250 Days/yearMill Recovery = 90%

Tons/year Concentrate = 6,000 T/D * 250 D/Y * 0.14 * 0.9/0.55 = 343,636 Tons/year Concentrate .

Revenue/year ($1,000) = 343,636 T/Y * $214.43/1,000 = $73,684/Year

Direct Operating cost/Year = Tons/year Ore * Operating Costs/Ton OreDirect Operating Costs

Mining $15.00 /Ton OreMilling 5.00Overhead 3.00

Total 23.00 /Ton Ore

Operating Cost/Year ($1,000) = 6,000 T/D * 250 D/Y * $23.00/T/1,000 = $34,500/Year

Page 891: Strategic Open Pit Mine Planning Course.pdf

Production PeriodYear 7 8 9 10 11 12-21Revenues 73,684 73,684 73,684 73,684 73,684 73,684Operating Costs (34,500) (34,500) (34,500) (34,500) (34,500) (34,500)Net Before D & D 39,184 39,184 39,184 39,184 39,184 39,184Depreciation (5,800) (5,800) (5,800) (5,800) (5,800) (5,800)Net After Depr. 33,384 33,384 33,384 33,384 33,384 33,384Depletion (6,211) (16,211) (16,211) (16,211) (16,211) (16,211)Taxable Income 27,173 17,173 17,173 17,173 17,173 17,173Tax @ 40% (10,869) (6,869) (6,869) (6,869) (6,869) (6,869)Net After Tax 16,304 10,304 10,304 10,304 10,304 10,304Depreciation 5,800 5,800 5,800 5,800 5,800 5,800Depletion 6,211 16,211 16,211 16,211 16,211 16,211Cash Flow 28,315 32,315 32,315 32,315 32,315 32,315Working Capital (9,300) 0 0 0 0 0Net Cash Flow 19,015 32,315 32,315 32,315 32,315 32,315

Depletion Calculation: 7 8 9 10 11 12-21Initial Recapture 10,00022% Revenue 16,211 16,211 16,211 16,211 16,211 16,21150% Net After Depr. 16,692 16,692 16,692 16,692 16,692 16,692Depletion Earned 16,211 16,211 16,211 16,211 16,211 16,211Depletion Recaptured 10,000 0 0 0 0 0Recapture Balance 0 0 0 0 0 0Depletion Claimed 6,211 16,211 16,211 16,211 16,211 16,211

Page 892: Strategic Open Pit Mine Planning Course.pdf

Depreciation and Depletion

Depreciation/Year = (Mine & Mill capital)/Mine Life

Mine Life = Reserves/Annual Production= 22,500,000 Tons/(6,000 T/D * 250 D/Y) = 15 years

Depreciation/Year ($1,000) = $87,000,000/15 Yr/1,000 = $5,800/Year

Depletion ($1,000):

Statutory % * Revenue or 50% Net after Depreciation, Select Smaller

zinc Depletion Rate = 22%

22% * $73,684 = $16,211 <=== Select SmallerOR

50% * $33,384 = $16,692

Page 893: Strategic Open Pit Mine Planning Course.pdf

Production PeriodYear 7 8 9 10 11 12-21Revenues 73,684 73,684 73,684 73,684 73,684 73,684Operating Costs (34,500) (34,500) (34,500) (34,500) (34,500) (34,500)Net Before D & D 39,184 39,184 39,184 39,184 39,184 39,184Depreciation (5,800) (5,800) (5,800) (5,800) (5,800) (5,800)Net After Depr. 33,384 33,384 33,384 33,384 33,384 33,384Depletion (6,211) (16,211) (16,211) (16,211) (16,211) (16,211)Taxable Income 27,173 17,173 17,173 17,173 17,173 17,173Tax @ 40% (10,869) (6,869) (6,869) (6,869) (6,869) (6,869)Net After Tax 16,304 10,304 10,304 10,304 10,304 10,304Depreciation 5,800 5,800 5,800 5,800 5,800 5,800Depletion 6,211 16,211 16,211 16,211 16,211 16,211Cash Flow 28,315 32,315 32,315 32,315 32,315 32,315Working Capital (9,300) 0 0 0 0 0Net Cash Flow 19,015 32,315 32,315 32,315 32,315 32,315

Depletion Calculation: 7 8 9 10 11 12-21Initial Recapture 10,00022% Revenue 16,211 16,211 16,211 16,211 16,211 16,21150% Net After Depr. 16,692 16,692 16,692 16,692 16,692 16,692Depletion Earned 16,211 16,211 16,211 16,211 16,211 16,211Depletion Recaptured 10,000 0 0 0 0 0Recapture Balance 0 0 0 0 0 0Depletion Claimed 6,211 16,211 16,211 16,211 16,211 16,211

Page 894: Strategic Open Pit Mine Planning Course.pdf

Post-Production PeriodYear 22Working Capital 11,900After-Tax Reclam. -8,000Net Cash Flow 3,900

Page 895: Strategic Open Pit Mine Planning Course.pdf

DCF-ROR or Internal Rate of ReturnPresent Value Present Value Present Value

Year (j) Net CF 1/(1+.20)^j CF @ 20% 1/(1+.25)^j CF @ 25% 0.21509 CF @ 21.509%1 (1,200) 0.833 (1,000) 0.800 (960) 0.823 (988)2 (2,400) 0.694 (1,667) 0.640 (1,536) 0.677 (1,626)3 (2,400) 0.579 (1,389) 0.512 (1,229) 0.557 (1,338)4 (17,400) 0.482 (8,391) 0.410 (7,127) 0.459 (7,982)5 (40,800) 0.402 (16,397) 0.328 (13,369) 0.378 (15,403)6 (43,400) 0.335 (14,535) 0.262 (11,377) 0.311 (13,485)7 19,015 0.279 5,307 0.210 3,988 0.256 4,8628 32,315 0.233 7,515 0.168 5,422 0.210 6,8009 32,315 0.194 6,263 0.134 4,337 0.173 5,597

10 32,315 0.162 5,219 0.107 3,470 0.143 4,60611 32,315 0.135 4,349 0.086 2,776 0.117 3,79112 32,315 0.112 3,624 0.069 2,221 0.097 3,12013 32,315 0.093 3,020 0.055 1,777 0.079 2,56714 32,315 0.078 2,517 0.044 1,421 0.065 2,11315 32,315 0.065 2,097 0.035 1,137 0.054 1,73916 32,315 0.054 1,748 0.028 910 0.044 1,43117 32,315 0.045 1,457 0.023 728 0.036 1,17818 32,315 0.038 1,214 0.018 582 0.030 96919 32,315 0.031 1,011 0.014 466 0.025 79820 32,315 0.026 843 0.012 373 0.020 65721 32,315 0.022 702 0.009 298 0.017 54022 3,900 0.018 71 0.007 29 0.014 54

367,726 3,580 (5,666) 0

By Linear Interpolation

DCF-ROR = 20% + 3580/(3580+5666)*(25-20)% = 21.9%

Exact Solution 21.5090%

Page 896: Strategic Open Pit Mine Planning Course.pdf

Present Value of Cash Flows at 21.5% Discount Rate

(20,000)

(15,000)

(10,000)

(5,000)

0

5,000

10,000

1 3 5 7 9 11 13 15 17 19 21

Year

$ *1

000

Projected Cash Flows For Bedded Zinc Deposit

-50000-40000-30000-20000-10000

010000200003000040000

1 3 5 7 9 11 13 15 17 19 21

Year

$ *1

000

Page 897: Strategic Open Pit Mine Planning Course.pdf

Definitions of troy ounce on the Web:

ounce: a unit of apothecary weight equal to 480 grains or one twelfth of a pound

he traditional unit of weight for gold is the troy ounce, named, it is thought, after a weight used at the annual fair at Troyes in France in the Middle Ages.

Although the metric system is used increasingly in mining and the gold business, the troy ounce remains the basic unit in which the price of 995 gold is quoted.

One troy ounce = 31.1034807 grams, 32.15 troy ounces = 1 kilogram, 1 troy ounce = 480 grains,

Page 898: Strategic Open Pit Mine Planning Course.pdf

Mine Production Scheduling Mine Production Scheduling OptimizationOptimization

-- The State of Art The State of Art --

K. Dagdelen

ProfessorMining Engineering Department

Colorado School of MinesGolden, Colorado 80401

Page 899: Strategic Open Pit Mine Planning Course.pdf

AP

CO

M 2

005

OPEN PIT OPTIMIZATIONOPEN PIT OPTIMIZATION

For Each Block in The For Each Block in The ModelModel

ll If a given block of If a given block of material should be material should be mined?mined?

ll When it Should be When it Should be mined?mined?

ll Once it is mined what to Once it is mined what to do with the block of do with the block of MaterialMaterial

Page 900: Strategic Open Pit Mine Planning Course.pdf

AP

CO

M 2

005

OPEN PIT OPTIMIZATIONOPEN PIT OPTIMIZATIONStart

Physical Capacities

Ultimate pit

Design Of Cuts

Cutoff Grade

Steps of Traditional Planning by Circular Analysis

ExtractionScheduling

ProductionCosts

Page 901: Strategic Open Pit Mine Planning Course.pdf

AP

CO

M 2

005

OPEN PIT OPTIMIZATIONOPEN PIT OPTIMIZATIONULTIMATE PIT LIMITS

Page 902: Strategic Open Pit Mine Planning Course.pdf

AP

CO

M 2

005

OPEN PIT OPTIMIZATIONOPEN PIT OPTIMIZATIONULTIMATE PIT LIMITS

l Identifies What blocks should be mined and which ones should be left in the ground.

l Defines the lateral and vertical extent to which a given deposit can economically be mined to

l 3-D Breakeven Analysis l Moving Cone algorithm gives sub-optimum resultsl Lerchs and Grossmann algorithm gives true

breakeven pit that maximizes the undiscounted profits

Page 903: Strategic Open Pit Mine Planning Course.pdf

AP

CO

M 2

005

OPEN PIT OPTIMIZATIONOPEN PIT OPTIMIZATIONULTIMATE PIT LIMITS

The Lerchs and Grossmann Algorithml Only finds the maximum profit pit boundary l No time value of money is consideredl The pit that maximizes discounted profits (NPV) by

taking into account time value of money is much smaller than the ultimate pit found by this technique

Page 904: Strategic Open Pit Mine Planning Course.pdf

AP

CO

M 2

005

OPEN PIT OPTIMIZATIONOPEN PIT OPTIMIZATIONULTIMATE PIT LIMITS

l Common practice is to apply Lerchs and Grossmann’s algorithm to the economic block model that is generated to discounted block values

l Economic block model is generated by discounting block values based on a rough initial production schedule

Page 905: Strategic Open Pit Mine Planning Course.pdf

AP

CO

M 2

005

OPEN PIT OPTIMIZATIONOPEN PIT OPTIMIZATIONULTIMATE PIT LIMITS

l If the schedule is not defined by identifying effect of waste stripping on the overall cash flows then the ultimate pit limit may not be correct

l NPV analysis on the last incremental pushbacksalways results in elimination of non-contributing incremental pits

Page 906: Strategic Open Pit Mine Planning Course.pdf

AP

CO

M 2

005

OPEN PIT OPTIMIZATIONOPEN PIT OPTIMIZATIONStart

Physical Capacities

Ultimate pit

Design Of Cuts

Cutoff Grade

Steps of Traditional Planning by Circular Analysis

ExtractionScheduling

ProductionCosts

Page 907: Strategic Open Pit Mine Planning Course.pdf

AP

CO

M 2

005

OPEN PIT OPTIMIZATIONOPEN PIT OPTIMIZATIONDESIGN OF PUSHBACKS

Economic block models are developed by varying eitherl Metal Price l Cutoff Grade l Minimum profits required per ton of orel Some ratio in block evaluation equationl As these variables change the pit outline also changesl Each outline is then used as pushbacks

Page 908: Strategic Open Pit Mine Planning Course.pdf

AP

CO

M 2

005

OPEN PIT OPTIMIZATIONOPEN PIT OPTIMIZATIONDESIGN OF PUSHBACKS

PHASE 2

PHASE 1

PHASE 3

Page 909: Strategic Open Pit Mine Planning Course.pdf

AP

CO

M 2

005

OPEN PIT OPTIMIZATIONOPEN PIT OPTIMIZATIONDESIGN OF PUSHBACKS

l The concept is based on mining “next best ore” without considering impact of stripping to be done ahead of time

l First incremental pit contains the ore that has the highest average overall value per ton. The subsequent pits have lower and lower average value per ton of ore

l The push back designs do not take into account effect of timing of waste stripping on the NPV

l Blending requirements can not be taken into account

Page 910: Strategic Open Pit Mine Planning Course.pdf

AP

CO

M 2

005

OPEN PIT OPTIMIZATIONOPEN PIT OPTIMIZATIONDESIGN OF PUSHBACKS

Page 911: Strategic Open Pit Mine Planning Course.pdf

AP

CO

M 2

005

OPEN PIT OPTIMIZATIONOPEN PIT OPTIMIZATIONStart

Physical Capacities

Ultimate pit

Design Of Cuts

Cutoff Grade

Steps of Traditional Planning by Circular Analysis

ExtractionScheduling

ProductionCosts

Page 912: Strategic Open Pit Mine Planning Course.pdf

AP

CO

M 2

005

OPEN PIT OPTIMIZATIONOPEN PIT OPTIMIZATIONCUTOFF GRADES

Page 913: Strategic Open Pit Mine Planning Course.pdf

2005

SM

E A

nnua

l Mee

ting

Cutoff GradesCutoff Gradesl A cutoff grade is the grade that is used to

differentiate between ore and waste in a given mining environment. Although the definition of cutoff grade is straight forward, the determination of it is not.

l To determine if a block of material should be milled or taken to the waste dump, breakeven mill cutoff may be used.

Milling cutoff grade

Page 914: Strategic Open Pit Mine Planning Course.pdf

2005

SM

E A

nnua

l Mee

ting

McLaughlin Gold MineMcLaughlin Gold MineCalifornia, USACalifornia, USA

Waste dumps

Autoclave Mill

Pit

Waste Ore and waste discrimination

Cutoff grade

Stockpiles

Ore

Page 915: Strategic Open Pit Mine Planning Course.pdf

2005

SM

E A

nnua

l Mee

ting

Round Mountain Gold MineRound Mountain Gold Mine

Waste dumps

Leach Pads

Stockpiles

Low grade stockpiles

Crusher

WasteOxide

Sulfide

CIP Mill

Ore

Page 916: Strategic Open Pit Mine Planning Course.pdf

Breakeven Mill Cutoff GradeBreakeven Mill Cutoff Grade

l The lowest economic grade where mining, milling, and administration cost are equal to revenues obtained from the metal produced.

Breakeven cutoff grade = Milling Cost

(Price – Refining Cost - Sales Cost) * Recovery

l Traditionally, this breakeven cutoff grade has been widely used in a production scheduling.

2005

SM

E A

nnua

l Mee

ting

Page 917: Strategic Open Pit Mine Planning Course.pdf

McLaughlin Mine Case StudyMcLaughlin Mine Case Study20

05 S

ME

Ann

ual M

eetin

g

l The economic and operational parameters:

Price (P) 600 $/oz

Sales Cost (s) 5 $/oz

Processing Cost (c) 19 $/ton ore

Recovery (y) 0.9

Mining Cost (m) 1.2 $/ton

Fixed Cost (fa) 8.35M $/year

Mining Capacity (M) Unlimited

Processing Capacity (C) 1.05M tons

Discount Rate (d) 15 %

Page 918: Strategic Open Pit Mine Planning Course.pdf

Production Scheduling By Production Scheduling By Breakeven Cutoff Grade (Case1)Breakeven Cutoff Grade (Case1)

2005

SM

E A

nnua

l Mee

ting

l If one uses breakeven cutoff grade for a production scheduling:

$19/ton

($600/oz - $5.0/oz) * 0.90Breakeven cutoff grade =

= 0.035 oz/ton

l All the materials above 0.035oz/ton goes to process, and below goes to waste dump.

Page 919: Strategic Open Pit Mine Planning Course.pdf

McLaughlin Case StudyMcLaughlin Case Study20

05 S

ME

Ann

ual M

eetin

g

l Consider a case study from McLaughlin Mine in California where an epithermal gold deposit was mined by an open pit.

l The grade distribution within the ultimate pit limit is:

Grade CategoryFrom To midpoint Ktons

0 0.02 0.0100 70,0000.02 0.025 0.0225 7,257

0.025 0.03 0.0275 6,3190.03 0.035 0.0325 5,591

0.035 0.04 0.0375 4,5980.04 0.045 0.0425 4,277

0.045 0.05 0.0475 3,4650.05 0.055 0.0525 2,428

0.055 0.06 0.0575 2,3070.06 0.065 0.0625 1,747

0.065 0.07 0.0675 1,6400.07 0.075 0.0725 1,485

0.075 0.08 0.0775 1,2270.08 0.1 0.0900 3,5980.1 0.358 0.2290 9,576

125,515

Ton

s

Grade intervals36,346 [email protected]/ton

89,167 tons

SR=2.45

COG

Page 920: Strategic Open Pit Mine Planning Course.pdf

Yearly Mining and Milling RatesYearly Mining and Milling Rates20

05 S

ME

Ann

ual M

eetin

g

l Assuming the deposit is homogeneously distributed, yearly mining rate is given as follows:

l Yearly ore tons: 1.05Mtons (Limited by process capacity)l Yearly ounces recovered: 1.05Mtons x 0.102 oz/ton x 0.9

= 96.3kozl Yearly waste tons: 1.05Mtons x 2.45 (SR) = 2.58Mtonsl Yearly mining rates: 1.05M + 2.58M = 3.62Mtons

Page 921: Strategic Open Pit Mine Planning Course.pdf

Yearly Schedules by Breakeven Yearly Schedules by Breakeven Cutoff Grade (Cont.)Cutoff Grade (Cont.)

2005

SM

E A

nnua

l Mee

ting

l Mining the deposit with breakeven cutoff grade of 0.035oz/ton at 1.05M tons process capacity:

Avg Qm Qc Qr Profits

Year (i) COG Ore Grade (Mtons) (Mtons) (ktons) ($M)

1 0.035 0.102 3.6 1.05 96.3 33.0

2 0.035 0.102 3.6 1.05 96.3 33.0

3 0.035 0.102 3.6 1.05 96.3 33.0

4 0.035 0.102 3.6 1.05 96.3 33.0

5 0.035 0.102 3.6 1.05 96.3 33.0

6 0.035 0.102 3.6 1.05 96.3 33.0

7 0.035 0.102 3.6 1.05 96.3 33.0

8 0.035 0.102 3.6 1.05 96.3 33.0

9 0.035 0.102 3.6 1.05 96.3 33.0

10 0.035 0.102 3.6 1.05 96.3 33.0

11 to 34 0.035 0.102 3.6 1.05 96.3 33.0

35 0.035 0.102 3.4 1.00 91.7 31.4

Total 125.8 36.7 3,365.9 1,154.2

(NPV@15%)

$218.5

Page 922: Strategic Open Pit Mine Planning Course.pdf

Shortcomings of the Traditional Shortcomings of the Traditional Cutoff GradesCutoff Grades

l They are established to maximizing the undiscounted profits from a given mining operation.

l They are constant unless the commodity price and the costs change during the life of the mine.

l They do not consider grade distribution of the deposit.

2005

SM

E A

nnua

l Mee

ting

Page 923: Strategic Open Pit Mine Planning Course.pdf

AP

CO

M 2

005

OPEN PIT OPTIMIZATIONOPEN PIT OPTIMIZATIONCUTOFF GRADES

l Many open pit mines are still designed and operated using cutoff grades based on breakeven economic analysis which maximizes undiscounted profits

l The cutoff grades should be set to much higher levels than the breakeven cutoff during the initial years of the operation

Page 924: Strategic Open Pit Mine Planning Course.pdf

AP

CO

M 2

005

OPEN PIT OPTIMIZATIONOPEN PIT OPTIMIZATIONCUTOFF GRADES

l The heuristic algorithm to define optimum declining cutoff grades that maximize the NPV of a given project was developed by Kenneth Lane in 1965

l Applying this method to a given project results in higher NPV for a project specially if capacities are not in harmony with the grade distribution of the deposit

Page 925: Strategic Open Pit Mine Planning Course.pdf

Declining Cutoff GradeDeclining Cutoff Grade20

05 S

ME

Ann

ual M

eetin

g

l Traditional cutoff grade (constant cutoff grade) does not maximize the NPV.

l Many approaches have been suggested to improve NPV of the project.

l K. F Lane in 1964 suggested an heuristic algorithm to obtain cutoff grades higher than breakeven grades during the early years that maximize the Net Present Value (NPV) of a project

Page 926: Strategic Open Pit Mine Planning Course.pdf

Optimum Cutoff Grades by Lane’s Optimum Cutoff Grades by Lane’s Algorithm Algorithm

2005

SM

E A

nnua

l Mee

ting

l Lane’s approach considers the mining operation to be constrained by the capacities of mine, mill, and refinery.

l The cutoff grades are optimized by considering the grade distribution of the deposit in providing highest quality of ore to the mill subject to three capacity constraints.

l This approach has been successfully used in the mining industry for many years.

Page 927: Strategic Open Pit Mine Planning Course.pdf

Optimum Cutoff Grades by OptiPit Optimum Cutoff Grades by OptiPit ®®20

05 S

ME

Ann

ual M

eetin

g

l Linear Programming (LP) based algorithm and software is being developed to optimize cutoff grades under complex mining and process constraints.

l Mathematical programming approach is very powerful and provides complete flexibility in modeling complex operating environments.

l This approach will be described and demonstrated using four case studies coming from gold mines in Western United States.

Page 928: Strategic Open Pit Mine Planning Course.pdf

Round Mountain Gold MineRound Mountain Gold Mine

Waste dumps

Leach Pads

Stockpiles

Low grade stockpiles

Crusher

WasteOxide

Sulfide

CIP Mill

Ore

AP

CO

M 2

005

Page 929: Strategic Open Pit Mine Planning Course.pdf

COMPLICATED PROCESSES AND COMPLICATED PROCESSES AND CAPACITIESCAPACITIES

Dump

ROM Leach

Cr Leach

Cr

Flot.

10M tons/yr

limited by crusher

5M tons/yr

1.05M tons/yr

2M tons/yr

Proc 1

Proc 2

Proc 3

Proc 4

Tailings

80%

20%

Autoclave

Mine

Phase1

Phase2

Mining Capacity: 12M tons/yr

Refining Capacity: 350 koz/yr

Stockpile available

AP

CO

M 2

005

Page 930: Strategic Open Pit Mine Planning Course.pdf

AP

CO

M 2

005

OPEN PIT OPTIMIZATIONOPEN PIT OPTIMIZATIONCUTOFF GRADES

l Linear Programming (LP) based algorithm and software is being developed to optimize cutoff grades under complex mining and process constraints.

l Mathematical programming approach is very powerful and provides complete flexibility in modeling complex operating environments.

Page 931: Strategic Open Pit Mine Planning Course.pdf

CUTOFF GRADE FORMULATION CUTOFF GRADE FORMULATION

McLaughlin mine

Mine

Dump MillCutoff Grade

Index i

Index g

Index d

Index t: YearsT

ons

Grade intervals

igdtX

l Decision variables:

AP

CO

M 2

005

Page 932: Strategic Open Pit Mine Planning Course.pdf

AP

CO

M 2

005

OPEN PIT OPTIMIZATIONOPEN PIT OPTIMIZATIONFUTURE

l NO scheduler in the market that incorporates shortcomings discussed

l There are efforts to develop methods that will overcome these shortcomings

l The advancements in hardware and software technology in recent years is providing an unique opportunity to solve this problem by way of “Linear –Integer Programming” techniques

l In the mean time, the use of computer programs that optimizes sub-problems will give you higher NPV for a given project if not the optimum.

Page 933: Strategic Open Pit Mine Planning Course.pdf

1

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Push Backs or Phases

• Defines how the pit will evolve with time.

• Defines ore tons and its quality for different time periods.

• Defines waste tons for removal schedules.

• Defines the cash flows and overall project economics.

Page 934: Strategic Open Pit Mine Planning Course.pdf

2

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Push Backs or Phases Example

Phase 1 Phase 2

Page 935: Strategic Open Pit Mine Planning Course.pdf

3

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Push Backs or Phases Example (Cont.)

Phase 3 Phase 4

Page 936: Strategic Open Pit Mine Planning Course.pdf

4

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Push Backs or Phases Example (Cont.)

Cross Section

Page 937: Strategic Open Pit Mine Planning Course.pdf

5

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Cutoff Grade

• Minimum grade of the material for processing.

• Normally used to discriminate between ore and waste within a given orebody.

• Cutoff grade is Dynamic.

Read “Cutoff Grade Optimization” by Dr. Dagdelen

Page 938: Strategic Open Pit Mine Planning Course.pdf

6

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Breakeven Cutoff Grade

• The lowest economic grade where mining, milling, and administration cost are equal to revenues obtained from the metal produced.

• Cutoff grades in the pit are normally much higher than the breakeven cutoff grade.

• Cutoff grades decline as the mine matures, and approaches the breakeven cutoff.

Page 939: Strategic Open Pit Mine Planning Course.pdf

7

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Hypothetical Case Study

• Consider a hypothetical case study where an epithermal gold deposit will be mined by an open pit.

• The grade distribution within the ultimate pit limit is:Grade Category

From To midpoint Ktons0 0.02 0.0100 70,000

0.02 0.025 0.0225 7,2570.025 0.03 0.0275 6,3190.03 0.035 0.0325 5,591

0.035 0.04 0.0375 4,5980.04 0.045 0.0425 4,277

0.045 0.05 0.0475 3,4650.05 0.055 0.0525 2,428

0.055 0.06 0.0575 2,3070.06 0.065 0.0625 1,747

0.065 0.07 0.0675 1,6400.07 0.075 0.0725 1,485

0.075 0.08 0.0775 1,2270.08 0.1 0.0900 3,5980.1 0.358 0.2290 9,576

125,515

Page 940: Strategic Open Pit Mine Planning Course.pdf

8

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Mine Design Parameters

• Capacities and Costs are:

Price (P) 600 $/oz

Sales Cost (s) 5.00 $/oz

Processing Cost (c) 19.0 $/ton ore

Recovery (y) 90 %

Mining Cost (m) 1.2 $/ton

Fixed Costs (fa) 8.35 $M/yr

Mining Capacity (M) Unlimited

Milling Capacity (C) 1.05 M

Capital Costs (CC) 105 $M

Discount Rate (d) 15 %

Page 941: Strategic Open Pit Mine Planning Course.pdf

9

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Traditional Cutoff Grades

• Traditionally, a cutoff grade is used to determine if a block of material should be mined or not.

• And, another cutoff is used to determine whether or not it should be milled or taken to the waste dump.

Ultimate pit cutoff grade

Milling cutoff grade

Page 942: Strategic Open Pit Mine Planning Course.pdf

10

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Ultimate Pit Cutoff Grade

• Ultimate pit cutoff grade is defined as the breakeven grade that equates cost of mining, milling, refining and marketingto the value of the block in terms of recovering metal and the selling price.

Ultimate pit cutoff grade = Milling Cost + Mining Cost

(Price – Refining Cost - Sales Cost) * Recovery

$19/ton + $1.2/ton

($600/oz - $5.0/oz) * 0.90Ultimate pit cutoff grade =

= 0.038 oz/ton

Page 943: Strategic Open Pit Mine Planning Course.pdf

11

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Milling Cutoff Grade

• Milling cutoff grade is defined as the breakeven grade that equates cost of milling, refining and marketing to the value of the block in terms of recovering metal and the selling price.

Milling cutoff grade = Milling Cost

(Price – Refining Cost - Sales Cost) * Recovery

$19/ton

($600/oz - $5.0/oz) * 0.90Milling cutoff grade =

= 0.035 oz/ton

Page 944: Strategic Open Pit Mine Planning Course.pdf

12

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Milling Cutoff Grade (Cont.)

• In the milling cutoff grade, no mining cost is included since this cutoff is basically applied to those blocks that are already selected for mining.

• The depreciation costs, general and administrative costs (G & A) and the opportunity costs are not included in the cutoff grade.

• The basic assumption is that all of these costs including fixed costs defined as G & A will be paid by the material whose grade is much higher than the established cutoff grades.

Page 945: Strategic Open Pit Mine Planning Course.pdf

13

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Summary of the Traditional Cutoff Grades

• The ultimate pit limit cutoff is used to ensure that no material (unless they are in the way of other high grade blocks) is taken out of the ground unless all of the direct costs associated with gaining the metal can be recovered. (This assurance is automatically built into the ultimate pit limit determination algorithms like Learchs – Grossmann and Moving Cone)

• The milling cutoff is used to ensure that any material that provides positive contribution beyond the direct milling, refining and marketing costs will be milled.

Page 946: Strategic Open Pit Mine Planning Course.pdf

14

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Shortcomings of the Traditional Cutoff Grades

• They are established to satisfy the objective of maximizing the undiscounted profits from given mining operation.

• They are constant unless the commodity price and the costs change during the life of the mine.

• They do not consider grade distribution of the deposit.

Page 947: Strategic Open Pit Mine Planning Course.pdf

15

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Yearly Tons and Grades Schedules by Constant Cutoff Grades

• Define:Qm: Amount of total material mined in a given year (Mtons)

Qc: The ore tonnage processed by the mill (Mtons)

Qr: The recovered gold (koz)

• The annual cash flows:

Profits ($M) = (P - s) * Qr – Qc * c – Qm * m

Page 948: Strategic Open Pit Mine Planning Course.pdf

16

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Yearly Tons and Grade Schedules by Constant Cutoff Grades

• Mining the deposit with traditional milling cutoff grade of 0.035oz/ton at 1.05M tons milling capacity (Table3):

Avg Qm Qc Qr Profits

Year (i) COG Ore Grade (Mtons) (Mtons) (ktons) ($M)

1 0.035 0.102 3.6 1.05 96.3 33.0

2 0.035 0.102 3.6 1.05 96.3 33.0

3 0.035 0.102 3.6 1.05 96.3 33.0

4 0.035 0.102 3.6 1.05 96.3 33.0

5 0.035 0.102 3.6 1.05 96.3 33.0

6 0.035 0.102 3.6 1.05 96.3 33.0

7 0.035 0.102 3.6 1.05 96.3 33.0

8 0.035 0.102 3.6 1.05 96.3 33.0

9 0.035 0.102 3.6 1.05 96.3 33.0

10 0.035 0.102 3.6 1.05 96.3 33.0

11 to 34 0.035 0.102 3.6 1.05 96.3 33.0

35 0.035 0.102 3.4 1.00 91.7 31.4

Total 125.8 36.7 3,365.9 1,154.2

(NPV@15%)

$218.5

Page 949: Strategic Open Pit Mine Planning Course.pdf

17

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Yearly Tons and Grades Schedules by Constant Cutoff Grades (NPV Calculation)

• NPV of the project:

NPV = 33.0(1 + 0.15)1

33.0(1 + 0.15)2

+ 33.0(1 + 0.15)3

+

33.0(1 + 0.15)4

+ 33.0(1 + 0.15)5

+ …

33.0(1 + 0.15)34

+

= $218.5M

31.4(1 + 0.15)35

+

Page 950: Strategic Open Pit Mine Planning Course.pdf

18

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Summary of Constant Cutoff Grade

• Total 28.44M tons is mined (Avg. grade 0.102 oz/ton)

• Overall stripping ratio: 1: 2.42

• Mine life: 35 years

• Undiscounted profits: $1154.2M

• NPV: $218.5M

Page 951: Strategic Open Pit Mine Planning Course.pdf

19

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Declining Cutoff Grade

• Traditional cutoff grade (constant cutoff grade) does not maximize the NPV.

• Many approaches have been suggested such that NPV is improved.

• Using cutoff grade higher than breakeven grades during the early years for a faster recovery of capital investments and using breakeven grades during the later stages has been practiced in the industry.

Page 952: Strategic Open Pit Mine Planning Course.pdf

20

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Heuristic Cutoff Grade

• The traditional cutoff grade is modified so that they include depreciation, fixed costs and minimum profit per ton required for a period of time to obtain a much higher cutoff grade during the early years.

• After the end of the initial period, minimum profit requirement is removed from the equation to lower the cutoff grades further until the plant is paid off.

• At that point, the depreciation charges are also removed.

Page 953: Strategic Open Pit Mine Planning Course.pdf

21

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Concept of Heuristic Cutoff Grade

• The concept is demonstrated pictorially as follows:

Idealized cross section of a series of pits for various cutoff grades

Page 954: Strategic Open Pit Mine Planning Course.pdf

22

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Capital Cost

• Assume:

Capital Cost: $105M (Depreciated during the first 10 years)

• Depreciation cost per year

$105M / 10 yrs = $10.5M / yr

• Depreciation cost per ton

$10.5M / 1.05M tons = $10 / ton of ore

Page 955: Strategic Open Pit Mine Planning Course.pdf

23

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Minimum Profit

• Assume:

Minimum profit of $3.0 per ton will be imposed to increase the cash flows further during the first five years

Page 956: Strategic Open Pit Mine Planning Course.pdf

24

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Heuristic Cutoff Grade Calculation

• The milling cutoff grades will be:

g milling = Milling Cost + Depreciation + Minimum Prof.

(Price – Refining Cost - Sales Cost) * Recovery

$19/ton + $10/ton + $3/ton

($600/oz - $5.0/oz) * 0.90Ultimate pit cutoff grade =

= 0.060 oz/ton

Yr 1 to 5

Page 957: Strategic Open Pit Mine Planning Course.pdf

25

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Heuristic Cutoff Grade Calculation (Cont.)

g milling = Milling Cost + Depreciation

(Price – Refining Cost - Sales Cost) * Recovery

$19/ton + $10/ton

($600/oz - $5.0/oz) * 0.90Ultimate pit cutoff grade =

= 0.054 oz/ton

Yr 6 to 10

Page 958: Strategic Open Pit Mine Planning Course.pdf

26

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Heuristic Cutoff Grade Calculation (Cont.)

g milling = Milling Cost

(Price – Refining Cost - Sales Cost) * Recovery

$19/ton

($600/oz - $5.0/oz) * 0.90Ultimate pit cutoff grade =

= 0.035 oz/ton

Yr 11 to Depletion

Page 959: Strategic Open Pit Mine Planning Course.pdf

27

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Yearly Tons and Grade Schedules

• The year by year tons and grade schedule obtained modified cutoff grade policy (Table4):

Avg Qm Qc Qr Profits

Year (i) COG Ore Grade (Mtons) (Mtons) (ktons) ($M)

1 0.060 0.153 6.9 1.05 144.6 57.8

2 0.060 0.153 6.9 1.05 144.6 57.8

3 0.060 0.153 6.9 1.05 144.6 57.8

4 0.060 0.153 6.9 1.05 144.6 57.8

5 0.060 0.153 6.9 1.05 144.6 57.8

6 0.054 0.141 6.0 1.05 132.8 51.9

7 0.054 0.141 6.0 1.05 132.8 51.9

8 0.054 0.141 6.0 1.05 132.8 51.9

9 0.054 0.141 6.0 1.05 132.8 51.9

10 0.054 0.141 6.0 1.05 132.8 51.9

11 to 27 0.035 0.102 3.6 1.05 96.3 33.0

28 0.035 0.102 0.3 0.09 8.1 2.8

Total 125.8 28.44 3,032.1 1,112.7

(NPV@15%)

$355.7

Page 960: Strategic Open Pit Mine Planning Course.pdf

28

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Summary of Modified Cutoff Grade

• Again, a total 28.44M tons is mined (Avg. grade 0.106 oz/ton)

• Overall stripping ratio: 1: 3.88

• Mine life: 25 years

• Undiscounted profits: $1112.7M (3.6% reduction from Table3)

• NPV: $355.7M (63% increase from Table3)

Page 961: Strategic Open Pit Mine Planning Course.pdf

29

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Heuristic Cutoff Grade (Including G & A)

• Assume:

Fixed Costs per year: $8.35M / year

Fixed Costs per ton: ($8.35M/year) / (1.05Mtons/year)

= $7.95 / ton

• In the previous calculations, the G & A costs were not included in the cutoff grade and profit calculations.

Page 962: Strategic Open Pit Mine Planning Course.pdf

30

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Heuristic Cutoff Grade Calculation (With G & A)

• The milling cutoff grades will be:

g milling = Milling Cost + Depreciation + Minimum Prof. + Fixed cost

(Price – Refining Cost - Sales Cost) * Recovery

$19/ton + $10/ton + $3/ton + $7.95/ton

($600/oz - $5.0/oz) * 0.90Ultimate pit cutoff grade =

= 0.075 oz/ton

Yr 1 to 5

Page 963: Strategic Open Pit Mine Planning Course.pdf

31

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Heuristic Cutoff Grade Calculation (With G & A) (Cont.)

g milling = Milling Cost + Depreciation + Fixed cost

(Price – Refining Cost - Sales Cost) * Recovery

$19/ton + $10/ton + $7.95/ton

($600/oz - $5.0/oz) * 0.90Ultimate pit cutoff grade =

= 0.069 oz/ton

Yr 6 to 10

Page 964: Strategic Open Pit Mine Planning Course.pdf

32

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Heuristic Cutoff Grade Calculation (With G & A) (Cont.)

g milling = Milling Cost + Fixed cost

(Price – Refining Cost - Sales Cost) * Recovery

$19/ton + $7.95/ton

($600/oz - $5.0/oz) * 0.90Ultimate pit cutoff grade =

= 0.050 oz/ton

Yr 11 to Depletion

Page 965: Strategic Open Pit Mine Planning Course.pdf

33

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Yearly Tons and Grades Schedules

• The year by year tons and grade schedule obtained modified cutoff grade policy that includes fixed costs (Table5):

Avg Qm Qc Qr Profits

Year (i) COG Ore Grade (Mtons) (Mtons) (ktons) ($M)

1 0.075 0.182 9.2 1.05 171.6 62.8

2 0.075 0.182 9.2 1.05 171.6 62.8

3 0.075 0.182 9.2 1.05 171.6 62.8

4 0.075 0.182 9.2 1.05 171.6 62.8

5 0.075 0.182 9.2 1.05 171.6 62.8

6 0.069 0.169 8.2 1.05 160.0 57.1

7 0.069 0.169 8.2 1.05 160.0 57.1

8 0.069 0.169 8.2 1.05 160.0 57.1

9 0.069 0.169 8.2 1.05 160.0 57.1

10 0.069 0.169 8.2 1.05 160.0 57.1

11 to 17 0.050 0.132 5.4 1.05 124.8 39.5

18 0.050 0.132 1.3 0.26 30.5 9.6

Total 125.8 18.11 2,562.5 885.6

(NPV@15%)

$357.1

Page 966: Strategic Open Pit Mine Planning Course.pdf

34

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Summary of Modified Cutoff Grade with Fixed Cost Included

• The policy of declining cutoff grades calculated with depreciation, minimum profit, and the G & A cost further improved the NPV of the deposit by 1% ($355.7M vs. $357.5M)

• Overall undiscounted profits were adversely reduced by 20% ($1112.7M vs. $885.6M)

Page 967: Strategic Open Pit Mine Planning Course.pdf

35

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Lane’s Approach

• Declining cutoff grades throughout the mine life gives higher NPV.

• The question is, “How should the cutoff grades be determined to obtain the highest NPV?”

• K. F. Lane discussed the theoretical background, a general formulation, and a solution algorithm.

Read “Choosing the Optimum Cutoff Grade” by K.F. Lane

Page 968: Strategic Open Pit Mine Planning Course.pdf

36

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Lane’s Approach (Cont.)

• Lane showed that cutoff grade calculations that maximize NPV have to include the fixed costs associated with not receiving the future cash flow quicker due to the cutoff grade decision taken now.

• Underlying philosophy in inclusion of the opportunity cost is that every deposit has a given NPV associated with it at a given point in time and that every ton of material processed by the mill during a given year should pay for the cost of not receiving the future cash flows by one year sooner.

Page 969: Strategic Open Pit Mine Planning Course.pdf

37

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Cutoff Grade Equation for Lane’s Approach

• The cutoff grade equation that maximizes the NPV of the deposit constrained by the mill capacity is:

g milling (i) = c + f + Fi

(P - s) * y

Where i = 1, …, N (mine life), gmilling(i) is the cutoff grade to be used in Year i.

Page 970: Strategic Open Pit Mine Planning Course.pdf

38

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Cutoff Grade Equation for Lane’s Approach (Cont.)

• Fi is the opportunity cost per ton of ore in Year i and it is defined as:

Fi = d * NPVi / C

• f is defined as:f = fa / C

Where d is the discount rate; NPVi is the NPV of the future cash flows of the years (i) to the endof mine life;fa is the annual fixed costs

Page 971: Strategic Open Pit Mine Planning Course.pdf

39

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Yearly Tons and Grades Schedules

• The year by year tons and grade schedule resulted from Lane’s approach (Table6):

Avg Qm Qc Qr Profits NPV

Year (i) COG Ore Grade (Mtons) (Mtons) (ktons) ($M) ($M)

1 0.161 0.259 18.0 1.05 245.2 95.9 413.8

2 0.152 0.255 17.2 1.05 241.0 94.4 380.0

3 0.142 0.25 16.5 1.05 236.4 92.6 342.6

4 0.131 0.245 15.7 1.05 231.3 90.5 301.4

5 0.120 0.239 14.9 1.05 225.7 88.1 256.1

6 0.107 0.232 14.1 1.05 219.6 85.4 206.4

7 0.092 0.213 12.1 1.05 200.9 76.7 152.0

8 0.079 0.188 9.8 1.05 177.9 65.9 98.1

9 0.065 0.163 7.6 1.05 153.6 53.9 46.9

Total 125.8 9.45 1,931.4 743.4

(NPV@15%)

$413.8

Page 972: Strategic Open Pit Mine Planning Course.pdf

40

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Steps to Obtain Table 6 (1st Iteration)

Avg Waste Ore SR Qm Qc Qr Profits NPV Year (i) NPVi Cog Ore Grade (Mtons) (Mtons) (Mtons) (Mtons) (ktons) ($M) ($M)

1 0 0.050 0.133 101.5 24.0 4.2 5.5 1.05 125.7 39.9 $255.02 0 0.050 0.133 97.1 23.0 4.2 5.5 1.05 125.7 39.9 $253.43 0 0.050 0.133 92.6 21.9 4.2 5.5 1.05 125.7 39.9 $251.54 0 0.050 0.133 88.2 20.9 4.2 5.5 1.05 125.7 39.9 $249.35 0 0.050 0.133 83.7 19.8 4.2 5.5 1.05 125.7 39.9 $246.86 0 0.050 0.133 79.3 18.8 4.2 5.5 1.05 125.7 39.9 $243.97 0 0.050 0.133 74.9 17.7 4.2 5.5 1.05 125.7 39.9 $240.6…21 0 0.050 0.133 12.7 3.0 4.2 5.5 1.05 125.7 39.9 $86.622 0 0.050 0.133 8.3 2.0 4.2 5.5 1.05 125.7 39.9 $59.723 0 0.050 0.133 3.8 0.9 4.2 5.1 0.91 108.9 33.1 $28.7

Total 125.8 24.0 2,874.0 910.8 (NPV@15%)

$255.0

Year 1: Cog= 19+8.35/1.05+(0*0.15)/1.05 = 0.050(600-5)*0.9

Year 2: Cog= 19+8.35/1.05+(0*0.15)/1.05 = 0.050(600-5)*0.9

Page 973: Strategic Open Pit Mine Planning Course.pdf

41

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Steps to Obtain Table 6 (2nd Iteration)

2nd iterationAvg Waste Ore SR Qm Qc Qr Profits NPV

Year (i) NPVi Cog Ore Grade (Mtons) (Mtons) (Mtons) (Mtons) (ktons) ($M) ($M)1 $255.0 0.118 0.238 116.6 8.9 13.1 14.8 1.05 224.9 87.8 $399.52 $253.4 0.118 0.238 102.9 7.9 13.1 14.8 1.05 224.9 87.8 $371.73 $251.5 0.117 0.236 89.1 6.8 13.1 14.8 1.05 223.0 86.6 $339.74 $249.3 0.117 0.236 74.5 5.7 13.1 14.8 1.05 223.0 86.7 $304.05 $246.8 0.116 0.236 61.6 4.8 12.9 14.6 1.05 223.0 86.8 $262.96 $243.9 0.115 0.236 48.2 3.8 12.9 14.5 1.05 223.0 86.9 $215.57 $240.6 0.115 0.236 34.8 2.7 12.9 14.6 1.05 223.0 86.9 $160.98 $236.8 0.114 0.235 20.0 1.6 12.9 14.6 1.05 222.1 86.3 $98.29 $232.4 0.112 0.234 7.0 0.5 15.6 7.5 0.45 94.8 30.5 $26.6

Total 125.0 8.9 1,881.8 726.4 (NPV@15%)

$399.5

Year 1: Cog= 19+8.35/1.05+(255*0.15)/1.05 = 0.118(600-5)*0.9

Year 2: Cog= 19+8.35/1.05+(253.4*0.15)/1.05 = 0.118(600-5)*0.9

Page 974: Strategic Open Pit Mine Planning Course.pdf

42

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Steps to Obtain Table 6 (3rd Iteration)

3rd iterationAvg Waste Ore SR Qm Qc Qr Profits NPV

Year (i) NPVi Cog Ore Grade (Mtons) (Mtons) (Mtons) (Mtons) (ktons) ($M) ($M)1 $399.5 0.157 0.257 118.1 7.4 15.9 17.7 1.05 242.9 94.9 $411.82 $371.7 0.149 0.253 101.2 6.6 15.4 17.3 1.05 239.1 93.2 $378.73 $339.7 0.141 0.250 84.8 5.9 14.4 16.2 1.05 236.3 92.8 $342.24 $304.0 0.131 0.245 69.0 4.9 14.1 15.8 1.05 231.5 90.5 $300.75 $262.9 0.120 0.238 54.7 4.2 13.2 14.9 1.05 224.9 87.7 $255.46 $215.5 0.108 0.232 40.7 3.3 12.3 14.0 1.05 219.2 85.3 $206.07 $160.9 0.093 0.215 27.5 2.5 11.1 11.7 1.05 203.2 78.6 $151.68 $98.2 0.077 0.189 15.3 1.7 9.0 9.5 1.05 178.6 66.6 $95.79 $26.6 0.057 0.158 7.1 0.9 8.4 8.8 1.05 149.3 50.0 $43.5

Total 125.8 9.5 1,925.0 739.7 (NPV@15%)

$411.81

Year 1: Cog= 19+8.35/1.05+(399.5*0.15)/1.05 = 0.157(600-5)*0.9

Year 2: Cog= 19+8.35/1.05+(371.7*0.15)/1.05 = 0.149(600-5)*0.9

Page 975: Strategic Open Pit Mine Planning Course.pdf

43

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Steps to Obtain Table 6 (4th Iteration)

4th iterationAvg Waste Ore SR Qm Qc Qr Profits NPV

Year (i) NPVi Cog Ore Grade (Mtons) (Mtons) (Mtons) (Mtons) (ktons) ($M) ($M)1 $411.8 0.160 0.259 117.0 7.8 15.0 17.8 1.05 244.8 96.0 $412.32 $378.7 0.151 0.255 101.4 6.7 15.1 17.0 1.05 241.0 94.7 $378.23 $342.2 0.142 0.250 85.2 5.9 14.4 16.2 1.05 236.3 92.8 $340.24 $300.7 0.131 0.245 70.0 5.1 13.7 15.6 1.05 231.5 90.7 $298.45 $255.4 0.118 0.238 55.9 4.2 13.3 14.6 1.05 224.9 88.0 $252.46 $206.0 0.105 0.230 41.8 3.3 12.7 13.9 1.05 217.4 84.3 $202.37 $151.6 0.091 0.213 28.0 2.7 10.4 12.0 1.05 201.3 77.1 $148.38 $95.7 0.076 0.182 16.5 2.0 8.3 10.2 1.05 172.0 61.8 $93.59 $43.5 0.062 0.162 8.0 1.2 6.7 8.5 1.05 153.1 52.6 $45.7

Total 125.8 9.5 1,922.1 738.0 (NPV@15%)

$412.30

Year 1: Cog= 19+8.35/1.05+(411.8*0.15)/1.05 = 0.160(600-5)*0.9

Year 2: Cog= 19+8.35/1.05+(378.7*0.15)/1.05 = 0.151(600-5)*0.9

Page 976: Strategic Open Pit Mine Planning Course.pdf

44

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Table 6

Table 6Avg Waste Ore SR Qm Qc Qr Profits NPV

Year (i) NPVi Cog Ore Grade (Mtons) (Mtons) (Mtons) (Mtons) (ktons) ($M) ($M)1 $413.8 0.161 0.259 18.0 1.05 244.8 95.7 $413.82 $380.0 0.152 0.255 17.2 1.05 241.0 94.4 $380.23 $342.6 0.142 0.250 16.5 1.05 236.3 92.5 $342.84 $301.4 0.131 0.245 15.7 1.05 231.5 90.6 $301.75 $256.1 0.119 0.239 14.9 1.05 225.9 88.2 $256.36 $206.4 0.105 0.232 14.1 1.05 219.2 85.2 $206.67 $152.0 0.091 0.2131 12.1 1.05 201.4 77.0 $152.38 $98.1 0.077 0.188 9.8 1.05 177.7 65.7 $98.29 $46.9 0.063 0.163 7.6 1.05 154.0 54.3 $47.2

Total 125.8 9.5 1,931.7 743.7 (NPV@15%)

$413.82

Year 1: Cog= 19+8.35/1.05+(413.8*0.15)/1.05 = 0.161(600-5)*0.9

Year 2: Cog= 19+8.35/1.05+(380.0*0.15)/1.05 = 0.152(600-5)*0.9

Page 977: Strategic Open Pit Mine Planning Course.pdf

45

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Summary of Lane’s Approach

• Lane’s approach gives 90% higher NPV and 35% lower undiscounted profits than constant cutoff grade (Table3).

• Total tons mined are the same.

• Tons milled is lower (36.7Mtons vs. 9.45Mtons)

• Ounces of gold recovered is lower (3.37Moz vs. 1.93Moz)

• Mine life is significantly shorter (36yrs vs. 10yrs)

Page 978: Strategic Open Pit Mine Planning Course.pdf

1

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Cutoff Grade Optimization 2

• How to determine a cutoff grade policy where

Mining capacity, milling capacity, and refining capacity may be limited,AndMaximizing NPV of the projects

Read “An NPV Maximization Algorithm For Open PitMine Design” by Dr. Dagdelen

Page 979: Strategic Open Pit Mine Planning Course.pdf

2

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Definition of the Problem

• The problem is to maximize the NPV subject to production constraints:Maximize ∑

=+

=N

id iiprofitNPV

1)1(

1*)(

Subject to MiQm ≤)( for i = 1,…N

CiQc ≤)( for i = 1,…N

RiQr ≤)( for i = 1,…N Where

i: Year indicator

N: Mine life in yearsQm: Amount of total metal mined in a given year (Ore + Waste)

Qc: Ore tonnage processed in a given year

Qr: Recovered metal (in tons) in a given year

M: Annual mining capacity in tonsC: Annual milling capacity in tonsR: Annual refinery capacity in tons

Page 980: Strategic Open Pit Mine Planning Course.pdf

3

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Derivation of Opportunity Costs of Mining Low Grades

• Define:

V: Maximum possible present value of future profits (cash flows) from the operation (NPV of total operation)

Profits ($M): Profits (Cash flow) from mining Qm amount of material

Vq: Maximum possible present value of future profits (cash flows) after the next Qm amount of material has been mined

v=V-Vq: Marginal increase in present value to be achieved by mining next Qm of material

Page 981: Strategic Open Pit Mine Planning Course.pdf

4

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Derivation of Opportunity Costs of Mining Low Grades (Cont.)

TdVqMprofits

V)1(

))($(+

+=

))($()1(* VqMprofitsdV T +=+

If i is relatively small, then )*1()1( Tdd i +=+

VqMprofitsTdV +=+ )($)*1(*

VqMprofitsTdVV +=+ )($**

TdVMprofitsVqV **)($ −=−

Page 982: Strategic Open Pit Mine Planning Course.pdf

5

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Derivation of Opportunity Costs of Mining Low Grades (Cont.)

Let v=V-Vq then

TVdMprofitsv **)($ −=

The opportunity cost of taking low grades now when higher grades are still available

We need to set cutoff grade so that we do not delay high grade

Page 983: Strategic Open Pit Mine Planning Course.pdf

6

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Basic Present Value Expression

• Annual profits can be calculated as follows:

TVdTfQmQcQsrPv mcr ******)( −−−−−−=

WhereP: Metal price per ton of productr: Marketing cost per ton of product

c: Processing cost per ton of orem: Mining cost per ton of ore

f: Annual fixed administrative costs

s: Sales cost per ton of product

T: Number of time periods that will take to mine, concentrate and refine Qm amount of material from the pit (i.e. years)

Page 984: Strategic Open Pit Mine Planning Course.pdf

7

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Mine Limiting Case

• When the mining capacity is the bottleneck in the system:

MQ

T m=

mcrm QM

VdfmQcQsrPv *

)*(**)(

+

+−−−−=

COG

vm

vm is a function of cutoff grades

Page 985: Strategic Open Pit Mine Planning Course.pdf

8

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

COG of Mine Limiting Case

• Cutoff grade of mine limiting case is:

ysrPc

gm *)( −−=

where

y: Metallurgical recovery

Page 986: Strategic Open Pit Mine Planning Course.pdf

9

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Concentrator Limiting Case

• When the concentrator capacity is the bottleneck in the system:

CQ

T c=

mcrc QmQC

VdfcQsrPv **

)*(*)( −

+

+−−−=

• Cutoff grade of concentrator limiting case is:

ysrPC

Vdfc

gc *)(

)*(

−−

++

=

Page 987: Strategic Open Pit Mine Planning Course.pdf

10

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Refinery Limiting Case

• When the refinery capacity is the bottleneck in the system:

RQ

T r=

mcrr QmQcQR

VdfsrPv ***)

)*(( −−

+−−−=

• Cutoff grade of refinery limiting case is:

yR

VdfsrP

cg r

*)*(

+−−−

=

Page 988: Strategic Open Pit Mine Planning Course.pdf

11

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Balancing Cutoff Grade (Cont.) Mine - Mill

C/M

g mc

Page 989: Strategic Open Pit Mine Planning Course.pdf

12

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Balancing Cutoff Grade (Cont.)Mine - Refinery

R/M

g mr

Page 990: Strategic Open Pit Mine Planning Course.pdf

13

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Balancing Cutoff Grade (Cont.)Mill - Refinery

R/C

g rc

Page 991: Strategic Open Pit Mine Planning Course.pdf

14

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Open Pit Copper Case StudyDeposit Reserves

(Mtons)(%Cu)

Page 992: Strategic Open Pit Mine Planning Course.pdf

15

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

First Year Production Reserves

(Mtons)(%Cu)

Page 993: Strategic Open Pit Mine Planning Course.pdf

16

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Open Pit Copper Case Study Unit of mining: ton

Price (P): $25/ 1%Cu of one unit of mining

(=$25/1%Cu*1ton = $25/0.01tonCu = $25/20lbsCu

= $1.25/lbCu)

Mining Cost (m): $1/ one unit of mining = $1/ton

Concentrator Cost (c): $2/ one unit of mining = $2/ton

Refinery Cost (s): $5/ 1%Cu of one unit of mining

Fixed Cost (f): $300M /yr

Mine capacity (M): 100M one unit of mining /yr = 100Mtons/yr

Concentrator capacity (C): 50M one unit of mining /yr = 50Mtons/yr

Refinery capacity (R): 40M of 1%Cu of one unit of mining /yr

(=40M*0.01tonCu /yr = 400k tons Cu /yr)

Recovery (y): 100%

Discount rate (d): 15%

Page 994: Strategic Open Pit Mine Planning Course.pdf

17

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Mine Limited Case

(V=0) (V=1174)

Page 995: Strategic Open Pit Mine Planning Course.pdf

18

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Concentrator Limited Case

(V=0) (V=1174)

Page 996: Strategic Open Pit Mine Planning Course.pdf

19

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Refinery Limited Case

(V=0) (V=1174)

Page 997: Strategic Open Pit Mine Planning Course.pdf

20

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Balancing Cutoff Grade

Balancing Cutoff Grades (V=0)

-300

-200

-100

0

100

200

300

400

500

0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9

COG

Pro

fit vm

vc

vr

gm gr

gc

Gopt

Feasible Region

Page 998: Strategic Open Pit Mine Planning Course.pdf

21

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Balancing Cutoff Grade

Balancing Cutoff Grades (V=1174)

-250

-200

-150

-100

-50

0

50

100

150

200

250

300

0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9

COG

Pro

fit vm

vc

vr

Gopt

Page 999: Strategic Open Pit Mine Planning Course.pdf

22

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Limiting Economic Cutoff Grades

CuCutonCu

tonysP

cg m %10.0%

1*)525(2

1*)1*%1/)($525()/($2

*)(=

−=

−=

−=

• Cutoff grade of mine limiting case is (V=0):

• Cutoff grade of concentrator limiting case is (V=0):

CuCutonCu

yrtonMyrM

ton

ysPC

Vdfc

g c %40.0%1*)525(

50300

2

1*)1*%1/)($525()/(50)/($300

)/($2

*)(

)*(

=−

+=

+=

++

=

Page 1000: Strategic Open Pit Mine Planning Course.pdf

23

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Limiting Economic Cutoff Grades (Cont.)

• Cutoff grade of refinery limiting case is (V=0):

( ) 1*))/1*%1(40

)/($300)1*%1/($525

)/($2

*)*(

−−

=

+

−−=

yrtonCuMyrM

tonCu

ton

yR

VdfsP

cg r

CuCu %16.0%1*

40300

525

2=

−−

=

Page 1001: Strategic Open Pit Mine Planning Course.pdf

24

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Grade – Tonnage Curve

Page 1002: Strategic Open Pit Mine Planning Course.pdf

25

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Average Grade Above Cutoff

Page 1003: Strategic Open Pit Mine Planning Course.pdf

26

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Ore : Material Ratio

Page 1004: Strategic Open Pit Mine Planning Course.pdf

27

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Product : Material Ratio

Page 1005: Strategic Open Pit Mine Planning Course.pdf

28

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Product : Ore Ratio

Page 1006: Strategic Open Pit Mine Planning Course.pdf

29

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Grade – Tonnage Relationship

Cutoff Quantity Tons Below Tons Above Avg Grade Cu Produced Ore to Product to Product to Ore to(%Cu) (Mtons) Cutoff Cutoff Above Cutoff (%Cu of Material Material Ore Waste

(Mtons) (Mtons) (%Cu) 1ton of Material) Ratio Ratio Ratio Ratio(C ) ( R) (C/M) (R/M) (R/C)

0.00 100 0 1000 0.500 500 1.0 0.500 0.500 0.00

0.10 100 100 900 0.550 495 0.9 0.495 0.550 0.11

0.20 100 200 800 0.600 480 0.8 0.480 0.600 0.25

0.30 100 300 700 0.650 455 0.7 0.455 0.650 0.43

0.40 100 400 600 0.700 420 0.6 0.420 0.700 0.67

0.50 100 500 500 0.750 375 0.5 0.375 0.750 1.00

0.60 100 600 400 0.800 320 0.4 0.320 0.800 1.50

0.70 100 700 300 0.850 255 0.3 0.255 0.850 2.33

0.80 100 800 200 0.900 180 0.2 0.180 0.900 4.00

0.90 100 900 100 0.950 95 0.1 0.095 0.950 9.00

Page 1007: Strategic Open Pit Mine Planning Course.pdf

30

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Balancing Economic Cutoffs

gmc: Ore : Material = C:M = 50M/100M =0.5

Then, from the table above gmc= 0.50 %Cu

gmr: Product : Material = R:M = 40M/100M =0.4

Then, from the table above gmr= 0.45 %Cu

grc: Product : Ore = R:C = 40M/50M =0.8

Then, from the table above grc= 0.60 %Cu

Page 1008: Strategic Open Pit Mine Planning Course.pdf

31

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Choosing Optimum Cutoff Grade

Page 1009: Strategic Open Pit Mine Planning Course.pdf

32

MN

GN

433

Min

e S

yste

ms

Ana

lysi

s

Choosing Optimum Cutoff Grade

Gmc = 0.40%Cu Grc = 0.40%Cu Gmr = 0.16%Cu Then, Gopt = 0.40%Cu