stormwater pollution prevention plan€¦ · columbia v5g 4g3 g • enginee mwater t way soil t ed...

24
E B Environmen 4400 Domini Burnaby, British Canada tal Consultin Stor DerwePrepar Project N Revision Novemb Suite 320 ion Street Columbia V5G 4G3 ng • Enginee rmwater nt Way Soil red for: SumNo. 12943 n No. 6 er 2017 Te Fa in ering Solutio Pollutio Transfer and mit Earthwor elephone: 604 4 acsimile: 604 43 nfo@keystoneenv ons • Environ on Preve d Barge Facil rks Inc. 30 0671 30 0672 vironmental.ca nmental Plan ention P lity nning Plan

Upload: others

Post on 03-Sep-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Stormwater Pollution Prevention Plan€¦ · Columbia V5G 4G3 g • Enginee mwater t Way Soil T ed for: Summ o. 12943 No. 6 er 2017 Te Fa in ring Solutio Pollutio ransfer and it Earthwor

E

B

Environmen

4400 DominiBurnaby, British

Canada

tal Consultin

Stor Derwen Prepar Project NRevisionNovemb

Suite 320ion StreetColumbiaV5G 4G3

ng • Enginee

rmwaternt Way Soil T

red for: Summ

No. 12943 n No. 6 er 2017

TeFain

ering Solutio

r PollutioTransfer and

mit Earthwor

elephone: 604 4acsimile: 604 43

nfo@keystoneenv

ons • Environ

on Preved Barge Facil

rks Inc.

30 0671 30 0672 vironmental.ca

nmental Plan

ention Plity

nning

Plan

Page 2: Stormwater Pollution Prevention Plan€¦ · Columbia V5G 4G3 g • Enginee mwater t Way Soil T ed for: Summ o. 12943 No. 6 er 2017 Te Fa in ring Solutio Pollutio ransfer and it Earthwor

Stormwater Pollution Prevention Plan (Rev. 6) Derwent Way Soil Transfer and Barge Facility

i Project 12943 / November 2017

PREFACE

This Stormwater Pollution Prevention Plan is designed to conform to the Port Metro Vancouver’s July 2015 Project and Environmental Review Guidelines: Developing Your Stormwater Pollution Prevention Plan in support of the conditions outlined in the Project & Environmental Review (PER No. 16-022) Application Submission Requirements dated February 16, 2015. Revision 6 addresses comments provided by the Vancouver Fraser Port Authority (VFPA) and third-party technical reviewers in September 2017, and incorporates the 90% design drawings for the facility, issued in October/November 2017.

The Barge Loading Facility is a transfer facility for soils that have concentrations less than BC Hazardous Waste Regulation criteria. The transfer station facilitates delivery of contaminated soil to soil treatment facilities in the Lower Mainland and Fraser Valley.

Trucks bring soil to the facility where it is temporarily stored before being transferred to a barge for transport to an approved treatment facility in Mission BC.

Summit Earthworks Inc. (Summit) minimizes any possible impact of its operations by utilizing best available control technologies and operating procedures.

The purpose of this document is to provide stormwater management planning in conjunction with overall site planning, design, and future construction, beginning at the outset of the Project (operation of a Barge Loading Facility at this location by Summit Earthworks Inc.).

Page 3: Stormwater Pollution Prevention Plan€¦ · Columbia V5G 4G3 g • Enginee mwater t Way Soil T ed for: Summ o. 12943 No. 6 er 2017 Te Fa in ring Solutio Pollutio ransfer and it Earthwor

INT1. OV2.

2.12.2

SIT3.3.13.23.3

ISS4.4.14.24.34.44.5

STO5.5.1

IMP6.6.16.26.3

LIM7.

TRODUCTIOVERVIEW ....

BackgrouLocation .

TE INVENTOActivities Materials Desktop H3.3.1 W3.3.2

3.3.3

3.3.4

SUES IDENTApplicablePotential Potential Identified Identified

ORMWATERManagem5.1.1

5.1.2

5.1.3 TPLEMENTAT

ImplemenSite MoniAdaptive

MITATIONS .

ON ..................................

und .................................

ORY ..................................................Hydrologic AWaste StoraGravel StoraBarge RampRemaining STIFICATIONe StandardsPollutant SoSensitive ReIssues .......Pollutant Pa

R POLLUTIOment StrategPrevention .ContainmenTreatment ..TION AND Mntation .........toring .........Managemen...................

TABLE

...................

...................

...................

...................

...................

...................

...................Assessment age Area .....age Bays ....p Area .........Site Area ..... AND RISK

s, Acts and Rources .........eceptors ........................athways ......ON PREVENy ....................................

nt / Reductio...................

MONITORIN......................................nt and Conti...................

iii

OF CONTE

...................

...................

...................

...................

...................

...................

...................and Design ............................................................................ANALYSIS

Regulations ............................................................................NTION PLAN......................................n ...................................

NG ....................................................nuous Impro...................

StormwDerwe

NTS

...................

...................

...................

...................

...................

...................

................... Basis .......................................................................................................................................................................................................N .....................................................................................................................................................ovement ........................

water Pollution Pent Way Soil Tran

Project 12

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

Prevention Plan (nsfer and Barge

2943 / November

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

...................

Rev. 6) Facility

r 2017

Page ...... 1

...... 1

...... 1

...... 1

...... 2

...... 2

...... 2

...... 2

...... 4

...... 5

...... 5

...... 6

...... 6

...... 6

...... 7

...... 7

...... 7

...... 7

...... 9

...... 9

...... 9

...... 9

.... 10

.... 12

.... 12

.... 12

.... 13

.... 14

Page 4: Stormwater Pollution Prevention Plan€¦ · Columbia V5G 4G3 g • Enginee mwater t Way Soil T ed for: Summ o. 12943 No. 6 er 2017 Te Fa in ring Solutio Pollutio ransfer and it Earthwor

Stormwater Pollution Prevention Plan (Rev. 6) Derwent Way Soil Transfer and Barge Facility

iv Project 12943 / November 2017

LIST OF APPENDICES

Appendix A Site Drainage Plan Appendix B Infiltration System Design Appendix C Stormwater Design Calculations

Page 5: Stormwater Pollution Prevention Plan€¦ · Columbia V5G 4G3 g • Enginee mwater t Way Soil T ed for: Summ o. 12943 No. 6 er 2017 Te Fa in ring Solutio Pollutio ransfer and it Earthwor

INTR1.

StormwaStormwabecomesflows overoadwaysnegative

This StorLoading Fraser R

The purppollutantsare consand typeindustry quality ofand eval

OVER2.

2.1 B

The Barghazardoutreatmenwhere it wand trans

The Site Plan is a

2.2 L

The Bargnorthern by a rail storage lthe west on the wapproxim

RODUCTION

ater originateater remainss stormwateer land (vegs); as it flowly impact wa

rmwater PolFacility on

River (“the Sit

pose of the Ss by stormw

sidered sounes of pollutaor pollutantf stormwateruation of the

RVIEW

Background

ge Loading us waste. Tnt facilities inwill be tempsported to an

will be self-vailable for t

Location

ge Loading bank of the right-of-way

ot to the eas(see Drawin

western sidemately 7,100

N

es from precs on the gror runoff, whigetated or bws it accumater quality.

llution PreveDerwent W

te”). The Sit

SPPP is to dwater runoff.nd, relativelyants. Advanct. The BMPr dischargede SPPP.

Facility will The transfen the Lower porarily storen approved t

-contained athis site and

Facility is toFraser Rive

y and pavedst, the Fraseng No. 17-12e of Derwen

m2, and app

cipitation eveound surfacich ultimatelbare soil areulates debri

ention Plan Way in Newe is located

develop a po. Best Manay low in cosced BMPs as discussed

d from the fa

accept contr station wMainland an

ed in a ‘Wasttreatment fa

and will have should be r

o be locateder. The upland access ro

er River to th2943-01). T

nt Way. Theproximately

1

ents (such ace through ply enters neeas, imperviis, soil and

(SPPP) hasw Westminsin an unimp

ollutant contagement Prast, and appliare defined d in this plaacility and to

taminated sowill facilitate nd Fraser Vte Storage A

acility.

e emergencyreviewed in t

d on Derwennd portion ofoad from Sahe south, anhe area is la

e project Sit100 m wide

StormwDerwe

as rainfall) aponding, is arby bodiesious surfacesediment, a

s been devester, BC, onproved indus

trol strategy actices (BMicable to a as those th

an have beeo aid in the d

oils that havdelivery o

Valley. TruckArea’ before

y procedurethe context o

nt Way in Nef the project

alter Street, d a rail rightargely induste area (uplalong the F

water Pollution Pent Way Soil Tran

Project 12

and from snsoaked into

s of water. Ses such as and contam

eloped for a n the northestrial area.

to minimizePs) are thobroad categhat are specen designeddevelopment

ve been conf contamina

ks will bring being trans

es in place. Aof this SPPP

ew Westmint Site is bouna paved sh

t-of-way andstrial, with reland and wa

Fraser River

Prevention Plan (nsfer and Barge

2943 / November

ow and ice o the groun

Stormwater rparking lotsinants that c

proposed Bern bank o

e the discharse practices

gory of induscific to a tyd to improvet, implement

nfirmed not ated soil tosoil to the fa

sferred to a b

A Spill RespP.

nster, BC, onded to the hipping contd Derwent Wesidential hoater lease lbank.

Rev. 6) Facility

r 2017

melt. nd, or runoff s and could

Barge of the

rge of s that stries pe of e the tation

to be o soil acility barge

ponse

n the north tainer

Way to using ot) is

Page 6: Stormwater Pollution Prevention Plan€¦ · Columbia V5G 4G3 g • Enginee mwater t Way Soil T ed for: Summ o. 12943 No. 6 er 2017 Te Fa in ring Solutio Pollutio ransfer and it Earthwor

SITE3.

3.1 A

Over theactivities Drawing

Soil o Barge Refue

3.2 M

The signinclude th

Wast Petro

3.3 D

A desktoProject involumes take intoinfrastruc

For the pareas as

Cove Grave Barge Rema

Trucks hDerwent to the noArea. Finoff-Site.

INVENTOR

Activities

e lifecycle olisted belo

No. 17-1294

off-loading e loading elling of site

Materials

nificant matehe following

te and Indusoleum fuels a

Desktop Hyd

op hydrologin order to esfor various

o account thcture for the

purpose of thfollows:

ered Waste Sel Storage Be Ramp Areaining Site A

hauling soilsWay. Truck

orth, then easnally, trucks

RY

of the Projew that have43-01 shows

equipment

erials expect:

strial Land Uand oils asso

drologic As

c assessmestimate the srainfall evene results ofSite.

he desktop h

Storage AreaBays – 300 ma – 50 m2 (0

Area – 3,730

s will enter ks will travel st of the Wawill drive thr

ect, the Barge the potens the propos

ted to be ex

se Classifiedociated with

sessment a

ent was constormwater rnts. The desf the hydrolo

hydrologic a

a – 2,020 m2

m2 (0.030 he0.005 hectar0 m2 (0.3730

the Site vivia the des

aste Storage rough the W

2

ge Loading ntial to exposed facility pl

xposed to st

d Soils refuelling an

and Design

nducted basrunoff responsign of the sogical asses

ssessment,

2 (0.20 hectaectares) res) 0 hectares)

a the Site ignated trucArea, and d

Wheel and Tr

StormwDerwe

Facility is ose stormwalan.

tormwater a

nd maintaini

Basis

sed on the pnse, includin

site stormwassment to p

the Site was

ares)

Entry Apprck routing padeposit the sruck Wash, t

water Pollution Pent Way Soil Tran

Project 12

expected toater runoff t

at the Barge

ing onsite eq

proposed finng peak flowater manageprovide adeq

s divided int

roach on Saath, through soil inside ththrough the

Prevention Plan (nsfer and Barge

2943 / November

o engage into contamin

e Loading Fa

quipment

nal design ow rates and rement systemquate stormw

to sub-catch

alter Street the weigh s

he Waste Stoweigh scale

Rev. 6) Facility

r 2017

n the nants.

acility

of the runoff m will water

hment

near scale, orage e, and

Page 7: Stormwater Pollution Prevention Plan€¦ · Columbia V5G 4G3 g • Enginee mwater t Way Soil T ed for: Summ o. 12943 No. 6 er 2017 Te Fa in ring Solutio Pollutio ransfer and it Earthwor

Stormwater Pollution Prevention Plan (Rev. 6) Derwent Way Soil Transfer and Barge Facility

3 Project 12943 / November 2017

The Waste Storage Area (refer to Drawing No. 17-12943-01) will be contained by lock-block walls and a high-density polyethylene (HDPE) liner, and covered with a parabolic roof to prevent the majority of precipitation during heavy storm events from coming into contact with the soils temporarily stored on Site. This roof covers the Waste Storage Area and the road immediately south of the Waste Storage Area, minimizing stormwater contact with the stored material and the area before the truck wash where contaminated soils could potentially be tracked. Stormwater and runoff that is generated inside the Waste Storage Area will be collected in a collection sump that will flow by gravity to a pumping station to be pumped to the water storage tank and treatment system. Roof runoff will not come into contact with the stored material, and will infiltrate to the ground via underground infiltration pits to the north and south of the Waste Storage Area.

The Gravel Storage Bays (refer to Drawing No. 17-12943-01) are contained with berms. Water from this area will percolate into the soil or drain to ditches/swales to the north.

The Barge Ramp Area (refer to Drawing No. 17-12943-01) is comprised of the sloped area down to the barge ramp. The runoff in this area will flow to a separate small sump and will be pumped to the water storage tank and treatment system.

The Site area outside of these three areas is referred to as the Remaining Site Area. It is noted that this area contains several small sub-catchments (the small asphalt road area at the northernmost edge of the site that drains northwards, the asphalt road area along the western edge of the Site that drains to ditches/swales to the east, and the unpaved areas surrounding the Gravel Storage Bays and Waste Storage Areas that drains to ditches/swales to the north). These sub-catchments within the Remaining Site Area do not experience traffic from trucks that have recently unloaded soils or entered the Waste Storage Area without having passed through the Wheel Wash. Trucks that move through this area will be exiting with washed wheels or will be entering the Site with ‘clean’ wheels. Site areas excluded by the offset buffer zones (from the railway right-of-way to the west, and the Fraser River to the south) were also included in the Remaining Site Area as they will similarly not experience any traffic or materials impacts from Project operations, and pose a low risk for pollutant entrainment into stormwater.

The Waste Storage Area and Barge Ramp Area have the potential to generate a higher concentration of solids and contaminant runoff while soil is being loaded and/or unloaded during a storm event. Following Port Metro Vancouver’s July 2015 Project and Environmental Review Guidelines: Developing Your Stormwater Pollution Prevention Plan, SPPPs should address two types of rainfall events: Water Quality Events and Storm Drainage Events. Runoff as a result of the first rain after a dry period mobilizes a greater concentration of contaminants in a short period of time. This initial surface water runoff is known as the “first flush” and represents a Water Quality Event. A Storm Drainage Event is defined as a design storm event used to size on Site infrastructure and environmental responses – in this case, storage tank, pumps, treatment system capacity, and containment berms.

Water Quality Events represent small, frequent events, but are large enough as to account for the majority of annual stormwater generated on Site. The “first flush” design event selected as the design basis for this SPPP is a 1-in-2 year storm event. Several mitigation strategies (described further in the sections below) are utilized to address Water Quality Events in this

Page 8: Stormwater Pollution Prevention Plan€¦ · Columbia V5G 4G3 g • Enginee mwater t Way Soil T ed for: Summ o. 12943 No. 6 er 2017 Te Fa in ring Solutio Pollutio ransfer and it Earthwor

Stormwater Pollution Prevention Plan (Rev. 6) Derwent Way Soil Transfer and Barge Facility

4 Project 12943 / November 2017

SPPP. These strategies minimize excess generation of stormwater in areas of concern, and contain and treat runoff from areas where stormwater may come into contact contaminated soils. This minimizes the concentrations of contaminants in runoff and reduces the impact of sediment-laden or contaminant-laden runoff from the “first flush.”

As this Site is relatively small but will temporarily store contaminated materials and occasionally experience elevated volumes of traffic (up to 60 trucks per day, as well as traffic from on Site equipment), this SPPP focusses on addressing Water Quality Events with elevated contaminant levels. Flooding or overflow events are expected to be less of a concern at this relatively small, flat Site with limited up-gradient stormwater inputs.

Storm Drainage Events are mitigated by selecting an appropriate design frequency to develop a stormwater system that can manage variable storm runoff rates and volumes. Design frequencies must be appropriate for the type of structures in question, and should consider the impacts and risk factors associated with flooding or overflow or bypass. The proposed stormwater system at this Site falls under “Minor Systems” listed in the City of New Westminster’s Design Criteria; therefore a 1-in-10 year design storm is sufficient design frequency. Given the industrial nature of the Site and the proposed Project works involving runoff coming into contact with stored soils, a 1-in-25 year storm event has conservatively been selected as the design basis for this SPPP for sizing of infrastructure.

3.3.1 Waste Storage Area

The following hydrological parameters were used to model hydrological properties of the proposed design with respect to the Waste Storage Area:

Waste Storage Area – 0.202 hectares Impervious area – 100% Average slope – 0.2% Time of concentration – 9 min Metro Vancouver Regional IDF Curve Zone 3

Results above are estimated using the City of New Westminster’s Design Criteria for Stormwater Drainage Systems, which is based on the Rational Method proposed in Port Metro Vancouver’s PER Guidelines for Developing Your Stormwater Pollution Prevention Plan.

As the Waste Storage Area has a roof to cover its entire surface area, it is assumed that only 22% of precipitation comes into contact with the waste material (based on approximate estimates of driving rain as a proportion of rainfall) – the remainder drains off the roof to infiltrate to ground via rock pits.

Waste Storage Area – Stormwater to Collection Sump

The peak flow for the Storm Drainage Event was calculated to determine sizing for pumps, tanks, equipment, and piping. The peak flow for the Water Quality Event was calculated to determine runoff volumes requiring retention and treatment on a regular basis. A peak flow of approximately 2.4 L/s (39 GPM) is expected for the Water Quality Event and a peak flow of

Page 9: Stormwater Pollution Prevention Plan€¦ · Columbia V5G 4G3 g • Enginee mwater t Way Soil T ed for: Summ o. 12943 No. 6 er 2017 Te Fa in ring Solutio Pollutio ransfer and it Earthwor

Stormwater Pollution Prevention Plan (Rev. 6) Derwent Way Soil Transfer and Barge Facility

5 Project 12943 / November 2017

approximately 4.7 L/s (74 GPM) is expected for a Storm Drainage Event. The total first flush volume from the Waste Storage Area is estimated to be 4.7 m3 based on a 1 hour, 1-in-2 year design storm, and 8.9 m3 based on a 1 hour, 1-in-25 year design storm.

Waste Storage Area – Roof Runoff to Infiltration Pits

A peak flow of approximately 8.7 L/s (137 GPM) is expected for the Water Quality Event and a peak flow of approximately 16.6 L/s (262 GPM) is expected for a Storm Drainage Event. The total first flush volume from the Waste Storage Area is estimated to be 16.7 m3 based on a 1 hour, 1-in-2 year design storm, and 31.5 m3 based on a 1 hour, 1-in-25 year design storm.

3.3.2 Gravel Storage Bays

The following hydrological parameters were used to model hydrological properties of the proposed design with respect to the Gravel Storage Bays:

Gravel Storage Bays – 0.030 hectares Impervious area – 0% (storage bays expected to be packed gravel) Average slope – 0.7% Time of concentration – 8 min Metro Vancouver Regional IDF Curve Zone 3

A peak flow of approximately 1.0 L/s (16 GPM) is expected for the Water Quality Event and a peak flow of approximately 1.9 L/s (31 GPM) is expected for a Storm Drainage Event. The total first flush volume from the Gravel Storage Bays is estimated to be 3.2 m3 based on a 1 hour,1-in-2 year design storm, and 6.0 m3 based on a 1 hour, 1-in-25 year design storm.

3.3.3 Barge Ramp Area

The following hydrological parameters were used to model hydrological properties of the proposed design with respect to the Barge Ramp Area:

Barge Ramp Area – 0.005 hectares Impervious area – 100% Average slope – 6.7% Time of concentration – 1 min Metro Vancouver Regional IDF Curve Zone 3

A peak flow of approximately 0.3 L/s (4 GPM) is expected for the Water Quality Event and a peak flow of approximately 0.5 L/s (8 GPM) is expected for a Storm Drainage Event. The total first flush volume from the Barge Ramp Area is estimated to be 0.5 m3 based on a 1 hour, 1-in-2 year design storm, and 1.0 m3 based on a 1 hour, 1-in-25 year design storm.

Page 10: Stormwater Pollution Prevention Plan€¦ · Columbia V5G 4G3 g • Enginee mwater t Way Soil T ed for: Summ o. 12943 No. 6 er 2017 Te Fa in ring Solutio Pollutio ransfer and it Earthwor

3.3.4 R

The folloproposed

Rema Impe Avera Time Metro

A peak flpeak flowThe total1-hour, 1This flowthe east

ISSU4.

4.1 A

The follosources

Canaby fis

Canato the

Cana Cana

qualit BC E Corpo

No. 7 Fede

unde

Remaining Si

owing hydrod design with

aining Site Arvious area age slope – of concentro Vancouver

low of approw of approx first flush v

1-in-2 year dw is not being

and west of

UES IDENTIF

Applicable S

owing relevalisted above

ada Fisheriessh ada Shippinge marine envada Environmadian Councty standards

Environmentaoration of th

7746, 2015) eral Interim Gr the Federa

ite Area

ological parah respect to

Area (exclud– 35% 2.7%

ration – 10 mr Regional ID

oximately 12ximately 24volume fromdesign stormg directed tothe Site.

FICATION A

Standards, A

ant legislatioe.

s Act regard

g Act, Natiovironment mental Protecil of Minists al Managemhe City of N

Groundwateal Contamina

ameters wethe Remain

ing offsets)

min DF Curve Zo

.8 L/s (203 G

.9 L/s (395m the Remam, and 74.6 o the on-Site

AND RISK A

Acts and Re

on and stan

ding the dep

nal Spill Re

ection Act reers of the

ment Act, regNew Westm

er Quality Gated Sites A

6

ere used toing Site Are

– 0.3730 he

one 3

GPM) is exp5 GPM) is eining Area im3 based o

e treatment

ANALYSIS

egulations

ndards are

osition of de

sponse Prot

garding pollEnvironmen

arding polluminster Sewe

uidelines foAction Plan (F

StormwDerwe

o model hydea:

ectares

pected for thexpected fois estimatedon a 1-hoursystem, but

applicable g

eleterious su

tocol regard

ution prevennt (CCME) G

tion preventerage and D

or Federal CFCSAP)

water Pollution Pent Way Soil Tran

Project 12

drological p

he Water Quor a Storm d to be 39.5r, 1-in-25 ye

will be direc

given the p

ubstance in

ding the rele

ntion Guidelines

tion Drainage R

Contaminate

Prevention Plan (nsfer and Barge

2943 / November

properties o

uality Event aDrainage E

5 m3 based ear design scted to swal

otential poll

water freque

ease of pollu

relating to w

egulation (B

d Sites (FIG

Rev. 6) Facility

r 2017

of the

and a Event.

on a storm. les to

lutant

ented

utants

water

Bylaw

GQG)

Page 11: Stormwater Pollution Prevention Plan€¦ · Columbia V5G 4G3 g • Enginee mwater t Way Soil T ed for: Summ o. 12943 No. 6 er 2017 Te Fa in ring Solutio Pollutio ransfer and it Earthwor

Stormwater Pollution Prevention Plan (Rev. 6) Derwent Way Soil Transfer and Barge Facility

7 Project 12943 / November 2017

4.2 Potential Pollutant Sources

An assessment was conducted to identify materials and practices that may reasonably be expected to add significant levels of pollutants to stormwater or that may result in the discharge of pollutants during dry weather from separate storm sewers draining from the facility. This section will provide a description of potential sources that may contribute to the presence of contaminants in stormwater runoff.

Soil receiving, handling, transferring, storage, and ship loading could result in soil being spilled onto the ground.

Dust from the temporary soil piles could spread across the Site during dry weather periods. Fuel, oil, or coolant from service vehicles or barges could leak due to damage, normal wear

and tear or during fuelling or preventative maintenance.

4.3 Potential Sensitive Receptors

The Fraser River provides habitat for fish and is a potential sensitive receptor.

4.4 Identified Issues

No outstanding issues have been identified at this time. Section 5.1 outlines the management strategy to address prevention, containment, reduction, and treatment measures.

4.5 Identified Pollutant Pathways

Pollutant pathways identified in the preparation of this SPPP include:

1. Runoff coming in contact with soils stored in the Waste Storage Area; 2. Runoff coming in contact with soils tracked outside the Waste Storage Area by trucks

or equipment. 3. Runoff in contact with fuel or oil from equipment maintenance or refuelling.

The Waste Storage will be isolated from the rest of the Site by a 1.5m high concrete curb, lined with an HDPE liner under an asphalt cover. This design will prevent runoff water from this area from infiltrating into the ground and will inhibit the ability of stormwater runoff from either running into or out of the Waste Storage Area via overland flow. The Waste Storage Area will have a roof over the entire containment area (including the asphalt road directly south of the Waste Storage Area, where trucks unload material), to prevent excess precipitation from coming into contact with the stored soils. The roof will drain to the north and south where runoff that has not come into contact with Site soil handling activities and will infiltrate into the ground via rock pits installed along the northern and southern edges of the Waste Storage Area.

Rainfall and snowmelt that is windblown under the roof structure and falls within the Waste Storage Area will be captured by the containment wall and collected in the collection sump. The pumping station will be arranged such that the first flush water from the Waste Storage Area will be captured and pumped to the onsite water storage tank, upstream of the treatment process.

Page 12: Stormwater Pollution Prevention Plan€¦ · Columbia V5G 4G3 g • Enginee mwater t Way Soil T ed for: Summ o. 12943 No. 6 er 2017 Te Fa in ring Solutio Pollutio ransfer and it Earthwor

Stormwater Pollution Prevention Plan (Rev. 6) Derwent Way Soil Transfer and Barge Facility

8 Project 12943 / November 2017

Trucks and site equipment must manoeuvre around the Site in order to move soil to and from the Waste Storage Area. Trucks are expected to enter the Site with ‘clean’ wheels -- construction/excavation sites in Metro Vancouver (typical generating sites for the type of material accepted) would be equipped with a truck wheel wash. Once trucks have offloaded materials to the Waste Storage Area, they must pass through the truck wheel wash before proceeding through the rest of the site to the exit approach. Loaders will be used on Site to move soils from the Waste Storage Area to the barges.

The areas between where the trucks offload and the wheel wash, and also the paths taken by the loaders to move materials onto barges have the potential to contain tracked soils and contaminants from the Waste Storage Area. This area will be covered and contained to minimize stormwater contact with stored soils and prevent water pollution on Site. Catch basins will capture runoff from these areas during storm events, and convey stormwater to the on-Site treatment system. Effluent from the truck wash will also be pumped to the water storage tank.

A 2,500 litre, above-ground storage tank (AST) may be present on Site for fuelling of site equipment. This storage tank will be a double-walled vacuum-monitored tank placed on a concrete pad. The concrete pad will provide an impervious surface for small drips and leaks during filling and refuelling. The tank and concrete pad will be protected with bollards to provide a visual barrier and prevent impact from trucks and on-Site equipment. Engineered drawings will be produced for the tank and the design will be registered with the Petroleum and Allied Petroleum Products Storage Tanks Regulations. Fuelling will be completed at a minimum distance of 30 m from the high water mark.

Water will be conveyed to the water storage tank from the Waste Storage Area Collection Sump and the Barge Ramp Area via the pumping station indicated on Drawing No. 17-12943-01. Water in the storage tank will be treated as described in Section 5.1.3, prior to discharge to ground. The tank is designed to contain the design storm as defined in the design basis. Following the first flush period, surface water runoff generated within the Waste Storage Area Collection Sump and Barge Ramp Area will be directed to the water storage tank and trigger the treatment system to begin operating. Should the tank continue to fill after the first flush period is over (note that the tank is oversized, even for significant storm events), the runoff will by-pass the water treatment system and be transferred directly to the infiltration system for discharge.

The treatment system will continuously treat water from the tank. Even during periods of inactivity on Site or dry periods, stored water will continue to be processed through the treatment system and discharged to allow space to collect stormwater runoff during the next storm event.

Runoff from the Remaining Site Area will be directed to the swales to the east and west of the Site.

Page 13: Stormwater Pollution Prevention Plan€¦ · Columbia V5G 4G3 g • Enginee mwater t Way Soil T ed for: Summ o. 12943 No. 6 er 2017 Te Fa in ring Solutio Pollutio ransfer and it Earthwor

STOR5.

5.1 M

The BargBMPs toThese pr

5.1.1 P

Maintenaeffective beneficiasafety ancapital co

The Barinspectiowhich co

Leachabgeneratedown thetreatmenthe soil a

The Wascompletefrom the prevent i

Dischargpermittinrespect twithin pe

The ASTtake placbe contaautomatiarea com

5.1.2 C

Trucks awith a dr

RMWATER

Managemen

ge Loading o target thractices will e

Prevention

ance of wormanageme

al in terms ofnd often coosts.

rge Loadingons, testing, ould result in

le toxic wase significant e majority o

nt. The site and rainfall ru

ste Storage ely contained

remaining Snfiltration int

ge from the wg guidelinesto the permitermitting guid

T will be douce on-Site oained withinc shutoff v

mpound.

Containment

and cars parip tray unde

POLLUTIO

t Strategy

Facility storhe potentialencompass

rk areas thent practicef limiting exp

ontribute to

g Facility wmaintenancthe discharg

stes will not contaminan

of soil and will be swe

unoff.

Area will bd within a seSite area. Tto the under

water storags. Where thet criteria, thedelines.

ble-walled ar within the

n the desigvalve and

/ Reduction

ked on Site rneath the m

N PREVENT

rmwater pol pollutant prevention,

at may cone for this Sposure of mareducing lo

will employ ce, and repage of sedime

be acceptents in the stoils accumupt regularly

be constructeparate drai

This includesrlying subgra

ge tank will e water quale water will b

and stored owater lot; onnated refuea spill kit

for more thmotor to prev

9

TION PLAN

lution prevesources idcontainmen

ntribute pollSite. Good aterials to st

osses of pro

a preventivairs of facilityent-laden sto

d at this factockpile runoulated on thduring dry

ted such thanage netwo

s lining the cade.

be continuoity is determbe treated a

ver a concrenly Site equ

elling area.will be lo

an one day vent potentia

StormwDerwe

N

ention strateentified in

nt/reduction,

utants to sthousekeep

tormwater, boducts, ther

ve maintenay equipmenormwater.

cility and thuoff. The firshe Site roadperiods to m

at stormwateork to the sucontainment

ous with watmined to be u

second time

ete pad. Noipment will bThe nozzle

ocated withi

will be parkal oil leaks.

water Pollution Pent Way Soil Tran

Project 12

egy is to imSection 4.and treatme

tormwater wing practicebut they alsoreby lowerin

ance prograt and system

us rainfall isst flush is exds that will minimize inte

er generaterface water t floor with a

ter samplingunsuitable foe, or until th

o barge or trube refuellede will be coin 10 m o

ked within a

Prevention Plan (nsfer and Barge

2943 / November

plement a s.2 of this ent.

will be the es are not o improve wng operation

am that incms, the failu

s not expectxpected to be capture

eraction betw

ed in this arrunoff gene

an HDPE lin

g occurring wor dischargee water qua

uck refuellin, and fuellinomplete witof the refu

designated

Rev. 6) Facility

r 2017

set of plan.

most only

worker nal or

ludes ure of

ted to wash

ed for ween

rea is erated ner to

within e with ality is

ng will ng will th an elling

area

Page 14: Stormwater Pollution Prevention Plan€¦ · Columbia V5G 4G3 g • Enginee mwater t Way Soil T ed for: Summ o. 12943 No. 6 er 2017 Te Fa in ring Solutio Pollutio ransfer and it Earthwor

Stormwater Pollution Prevention Plan (Rev. 6) Derwent Way Soil Transfer and Barge Facility

10 Project 12943 / November 2017

Trucks arriving on Site are considered ‘clean’ and will travel to the Waste Storage Area on a paved Site road. They will deposit their load in the Waste Storage Area and continue in a clockwise direction on the paved road through the wheel and truck wash station, before exiting the Site.

Trucks returning to pick up gravel at the Gravel Loading Bays will deposit their load in the Waste Storage Area and continue in a clockwise direction on the paved road through the wheel and truck wash station, before passing through the weigh scale. These empty trucks will then return to the Site via the South Site Access, loading gravel at the storage bays The loaded trucks will then be weighed a third time on weigh scale before exiting the Site via the North Entry/Exit.

Gravel will be clean fill brought from off-Site by barge and by truck.

A loader will remain on Site as permanent Site equipment and will be used to move soil from the Waste Storage Area to the barge. The loader will be limited to the Site and will travel between the Waste Storage Area and the barge along the paved road except when it requires refuelling or maintenance, both activities taking place on Site. The quality of the storm water runoff will not be impacted by the loader movement as soils that are lost during transfer from the Waste Storage Area to the barge will be addressed by dry cleaning of Site roadways during dry periods and first flush runoff will be captured by the treatment system.

Stormwater on the ramp to the barge is captured by a collection sump at the base of the ramp and is pumped to the treatment system. The ramp itself will have 7.5 cm high impervious barriers along the edge to prevent stormwater from flowing off the ramp.

The barges used for offloading to receiving facilities will not be covered, but will be sealed. The barge will contain runoff from the soil piles placed on the barge in addition to runoff from the barge loading ramp during storm events. During typical rainfall events, the soil placed within the barge is expected to absorb stormwater and rainfall. Water will be then be removed with the soil upon final disposal. Water may accumulate within the barge during heavy rainfall periods. Accumulated water within the barge will be removed either by a vacuum truck for off-Site disposal, or will be pumped up to the permitted treatment facility at Duncan Avenue, Mission BC for treatment prior to discharge.

The truck unloading area south of the Waste Storage Area will have 30 cm high concrete containment berms to the east and south to prevent excess runoff from exiting the site. These berms provide containment of the areas experiencing truck traffic that has recently unloaded contaminated soils.

5.1.3 Treatment

One 19,000 litre (5,000 gallon) water storage tank will be required on Site in order to provide sufficient storage for the first flush runoff volume from the Waste Storage Area and Barge Ramp Area as described above. The tank will be designed to manage the entirety of storm water generated during a 1 hour, 1-in-25 year storm event, with additional capacity to manage wash water from the on-site truck and wheel washing station, if necessary. One tank provides a total of 19 m3 of equalization and storage capacity; Storm Drainage Event calculations indicate that 9 m3 are required to contain the entirety of the 1 hour, 1-in-25 year storm event.

Page 15: Stormwater Pollution Prevention Plan€¦ · Columbia V5G 4G3 g • Enginee mwater t Way Soil T ed for: Summ o. 12943 No. 6 er 2017 Te Fa in ring Solutio Pollutio ransfer and it Earthwor

Stormwater Pollution Prevention Plan (Rev. 6) Derwent Way Soil Transfer and Barge Facility

11 Project 12943 / November 2017

Average peak flow rates are expected to be on the order of 2.7 L/s for the Water Quality Event described in the Design Basis. The storage tank will provide storage and equalization prior to the treatment system, such that the treatment system can be sized for lower flows (which will be encountered more often). The treatment system will be designed to treat 2.7 L/s.

First flush water from the Waste Storage Area and Barge Ramp Area will be directed to the water storage tank and continuously processed through the treatment system. As the treatment system is designed for the 2.7 L/s peak flow, the water storage tank can be drained in approximately 2 hours, allowing for additional storage capacity for ongoing rain events. Stormwater will continuously be directed to the storage tank for subsequent treatment during any rain event (Water Quality Event or otherwise) as long as the storage tank has capacity.

Given that the majority of annual rainfall events in Metro Vancouver are below 10 mm/day (Canadian Climate Normals 1981–2010 for Vancouver indicate that, on average, 86% of days with precipitation experience less than or equal to 10 mm/day, and 98% of days with precipitation experience less than 25 mm/day), the storage provided by the storage tank and treatment capacity of the treatment system is considered sufficient, as the design basis accounts for a 22 mm storm occurring in 1 hour.

Stormwater within the water storage tank will be directed to the water treatment system. The system will include solids settling, flocculent injection to enhance settling, sand filtration, and a granular activated carbon filter. Flocculants designed for environmentally sensitive environments (i.e., polymer-based formulations) will be exclusively used. The dose rate and treatment chemical will be adjusted regularly, and will be based on the different contaminants of potential concern associated with each different delivery of soil material to Site. As required, secondary and tertiary treatment of this collected water will be completed until such time as the water is of a suitable quality such that it can be discharged. Effluent water will be tested prior to discharge for the contaminants of potential concern associated with each delivery of soil. The treated water will be discharged to ground via an infiltration system to the north of the Waste Storage Area.

Details of the infiltration system can be found in Drawing No. 17-12943-02, appended to this plan.

Sludge from the treatment process will be collected in by a vacuum truck and disposed of at an accredited soil treatment facility.

Runoff water from the Remaining Site Area will be collected in the swales to the east and west of the property and flow north. The swales will be designed to passively treat or convey the 1-in-25 year peak flow scenario of 26.8 L/s (divided amongst the 2 swales to the east and west), which exceeds design storm flow for this catchment area.

All trucks exiting the Site will go through the truck and wheel wash. The proposed truck and wheel wash model for this facility is Model TW750, capable of 47 L/s (750 GPM), and washing 400 trucks per day. This model includes capacity for two complete tire revolutions as trucks pass through, providing ample space and time for removal of sediments from truck wheels. Water within the wheel and truck wash will be recycled until sediment load becomes significant, or regular maintenance procedures require discharge of the wash water (at a minimum on a daily basis). Discharged wash water will be sent to the water storage tank. Discharge would not

Page 16: Stormwater Pollution Prevention Plan€¦ · Columbia V5G 4G3 g • Enginee mwater t Way Soil T ed for: Summ o. 12943 No. 6 er 2017 Te Fa in ring Solutio Pollutio ransfer and it Earthwor

occur ducapacity will be coclean wafrom the

Other me

Sedimobse

Good

IMPL6.

6.1 Im

The BargThe mancould imthe manaplan and

All Site sof this presponsiand to re

6.2 S

Regular stormwatconcernsrainfall isoperationtruck andmonths won good

At a minindustriaexposurestorage a

In additiupcomingevents (p

ring first flusin case of e

ollected by aater for the troof structur

easures that

ment barriervations, the

d housekeep

LEMENTATI

mplementat

ge Loading Fnager will ppact stormwagement prathe importa

staff involvedplan at hire bility of all s

eport them to

Site Monitor

site and efter BMPs ous related to s high (Octon of the stod wheel wawhen averaghousekeepi

nimum, the ml materials e to stormwareas, and s

on to the wg storm evepredicted rai

sh or a heavextreme stora vacuum truruck wash dre.

t will be put i

ers such asese will be avping practice

ION AND MO

tion

Facility Site ossess the

water qualityactices. The

ance of adhe

d in regular sorientation

staff to be ao the Site ma

ring

ffluent inspeutlined in this

the qualityber to Marc

ormwater infash, and coge rainfall is ng practices

manager wior activities

water exists. soil load-out

weekly inspents and confall exceed

vy storm evrm events. Suck and sentduring winter

in place are:

s silt fencinvailable on S

es and regula

ONITORING

manager wiknowledge

y at the faciley shall eduering to each

site operatioand annua

able to recoganager.

ections shas plan are be

of stormwach), site and frastructure ntainment blow (April to

s (site sweep

ll conduct ws are expos

Such areaareas.

pections, theonduct inspding 15 mm/d

12

ent, though Sediment cot to a permitr months wi

:

ng or fiberSite to be usar Site clean

G

ll be responand skills t

ity, and whoucate other Sh BMP as de

ns and activally. The tragnize ineffec

all be condueing implemater effluenteffluent ins(swales, pu

berms) and o Septemberping and equ

weekly inspesed to storms specificall

e manager ections befoday).

StormwDerwe

the tank haollected withtted soil treall primarily c

r rolls (as sed if requirenup and mai

nsible for theto assess co can also eSite person

escribed in th

vities will recaining will cctive stormw

ucted by thmented effect

t. During wspections wilumps, catchmonitoring

r), site and euipment mai

ections of almwater andly include th

will monitoore, during,

water Pollution Pent Way Soil Tran

Project 12

as been sizein the truck

atment facilitconsist of ra

needed baed) ntenance

e implementaconditions aevaluate thenel in the ahis documen

ceive traininglearly indica

water manag

he managertively and tointer monthll focus on mh basins, trof effluent.

effluent inspntenance).

ll areas of td/or where he soil rece

or local wea and after

Prevention Plan (nsfer and Barge

2943 / November

ed with additand wheel

ty. The sourinwater colle

ased on on

ation of this nd activities

e effectiveneapplication ont.

g on the conate that it isgement prac

r to confirmo identify poss when avemaintenanceeatment sysDuring sum

ections will f

the facility wthe potentia

eiving areas

ather reportsignificant s

Rev. 6) Facility

r 2017

tional wash rce of ected

n-Site

plan. s that ess of of this

ntents s the ctices

m that ssible erage e and stem, mmer focus

where al for s, soil

ts for storm

Page 17: Stormwater Pollution Prevention Plan€¦ · Columbia V5G 4G3 g • Enginee mwater t Way Soil T ed for: Summ o. 12943 No. 6 er 2017 Te Fa in ring Solutio Pollutio ransfer and it Earthwor

Stormwater Pollution Prevention Plan (Rev. 6) Derwent Way Soil Transfer and Barge Facility

13 Project 12943 / November 2017

The water quality of stormwater within the water storage tank will be tested during discharge. Water will be tested for a specific analytical suite (determined by a qualified environmental professional) based on the contaminants of potential concern associated with the soils stored on Site. Each soil load will be delivered with a soil quality report completed by a qualified environmental professional or certified laboratory. The soil quality report will help to determine the analytical suite for the discharge water which will typically include pH, total suspended solids, heavy metals and hydrocarbons. In addition to the chemical composition of the discharge water, visual signs of contamination such as foam, discoloration, sediment or an oily sheen will be assessed.

Discharge would be stopped if parameters exceed the Federal Interim Groundwater Quality Guidelines for Federal Contaminated Sites (FIGQG), CCME surface water guidelines with a 10x dilution, and the BC Contaminated Sites Regulation standards for the protection of drinking water and aquatic life (BC CSR AWFW, DW) for discharge to ground

All weekly and storm event inspections, as well as water quality sampling events will be documented along with repairs/maintenance of the existing stormwater management works and new stormwater management works proposed. The documentation will include the personnel responsible for maintenance or installation and a timeline for completion of the recommended maintenance or installation.

Triggers for substantial replacement or upgrade of the stormwater infrastructure will be as follows:

Discharge analytical results above the applicable standards will trigger recirculation of the effluent through the treatment system, backwash of the sand filters, and replacement of the granular activated carbon.

Treatment chemical levels below 30% will trigger ordering replacement chemicals Heavy sedimentation of the pumping station, catch basins, or collection sump will trigger

cleanout via vacuum truck. At a minimum this will be conducted annually. Erosion or sedimentation of swales will trigger swale upgrade or maintenance within one

month’s notice of the damage. Cracks, leaks, or otherwise failing infrastructure will be replaced upon documentation of

the defects. Good housekeeping practice and BMP enforcement procedures will be developed if these

practices are not followed on three consecutive weekly inspections.

6.3 Adaptive Management and Continuous Improvement

A key process in the effective implementation of the SPPP is the ability to change mitigation measures or actions as site conditions warrant in order to protect stormwater quality. This approach, generally termed as ‘adaptive management’, is a planned and systematic process for continuously improving environmental management practices by learning about their outcomes.

Page 18: Stormwater Pollution Prevention Plan€¦ · Columbia V5G 4G3 g • Enginee mwater t Way Soil T ed for: Summ o. 12943 No. 6 er 2017 Te Fa in ring Solutio Pollutio ransfer and it Earthwor

The Bargensure cexposureadequatemitigationstormwatare need

LIMIT7.

Findings for the prclimate dCalculatithe work during thhave beeby other similar cintendedenvironm

We trust any ques

SincerelyKeyston

Alice KruEnvironm I:\12900-129 ATTACHM Appen Appen Appen

ge Loading Fcontinuous es have bee. The inspn actions ater manage

ded.

TATIONS

presented iroposed wordata, and (ons and estwas conduc

his investigaten prepared

members oircumstance, nor is it ab

mental condit

this informastions.

y, ne Environm

uchten, EIT mental Engin

999\12943\Storm

MENTS: ndix A: Site Dndix B: Infiltrandix C: Storm

Facility manimprovemenen identifie

pection repond measure

ement proce

n this plan arks on the suiii) a literattimations refcted. Site cotion. Conseq in a manne

of the enviroes in the areble, to providtions. This p

ation meets

mental Ltd.

neer

mwater Pollution

Drainage Planation System mwater Design

nager will revnt for the d, and thatorts will bees. The resedures are

are based uubject site, (ure review flect conditio

onditions maquently, whiler consistenonmental scea at the timde a totally cplan must be

your requir

Prevention Plan\

n Design n Calculations

14

view the constormwater t the mana reviewed

sults of thesworking eff

pon (i) a des(ii) a desktopof applicab

ons expectedy vary from le findings at with that le

cience and eme of the pecomprehensie read and us

rements at t

JasoSen

\12943 171108 S

s

StormwDerwe

ntents of thissystem, th

gement prafor trends

se reviews fectively or

sktop reviewp review of p

ble values fd at the spethat extrapo

and conclusievel of skill engineering erformance ive review osed in its en

this time. Pl

on Christensior Engineer

Stormwater Pollu

water Pollution Pent Way Soil Tran

Project 12

s plan on anhat all poteactices are in effectivemay determadditional m

w of client-prpublicly-avafor hydrologecific site locolated from tions documeand care noprofession

of the workof past, presentirety.

ease contac

sen, P.Eng. r

ution Prevention

Prevention Plan (nsfer and Barge

2943 / November

n annual basential stormw

appropriatee and ineffemine that cumitigation e

rovided drawilable rainfal

gical paramecation at thehe data colleented in thisormally exer

practising uk, this plan ient, or future

ct us if you

Plan-Rev6.docx

Rev. 6) Facility

r 2017

sis to water

e and ective urrent efforts

wings ll and eters.

e time ected

s plan rcised under s not e site

have

Page 19: Stormwater Pollution Prevention Plan€¦ · Columbia V5G 4G3 g • Enginee mwater t Way Soil T ed for: Summ o. 12943 No. 6 er 2017 Te Fa in ring Solutio Pollutio ransfer and it Earthwor

APPENDIX A

SITE DRAINAGE PLAN

Page 20: Stormwater Pollution Prevention Plan€¦ · Columbia V5G 4G3 g • Enginee mwater t Way Soil T ed for: Summ o. 12943 No. 6 er 2017 Te Fa in ring Solutio Pollutio ransfer and it Earthwor
Page 21: Stormwater Pollution Prevention Plan€¦ · Columbia V5G 4G3 g • Enginee mwater t Way Soil T ed for: Summ o. 12943 No. 6 er 2017 Te Fa in ring Solutio Pollutio ransfer and it Earthwor

APPENDIX B

INFILTRATION SYSTEM DESIGN

Page 22: Stormwater Pollution Prevention Plan€¦ · Columbia V5G 4G3 g • Enginee mwater t Way Soil T ed for: Summ o. 12943 No. 6 er 2017 Te Fa in ring Solutio Pollutio ransfer and it Earthwor
Page 23: Stormwater Pollution Prevention Plan€¦ · Columbia V5G 4G3 g • Enginee mwater t Way Soil T ed for: Summ o. 12943 No. 6 er 2017 Te Fa in ring Solutio Pollutio ransfer and it Earthwor

APPENDIX C

STORMWATER DESIGN CALCULATIONS

Page 24: Stormwater Pollution Prevention Plan€¦ · Columbia V5G 4G3 g • Enginee mwater t Way Soil T ed for: Summ o. 12943 No. 6 er 2017 Te Fa in ring Solutio Pollutio ransfer and it Earthwor

Catchment Area Area L H s C Tc Event Type Design Storm Volume Duration Intensity* Q Q Q

(m2) (hectares) (m) (m) (%) Weighted (min)

using 1 hour storm

(m3) (mm/hr) (m

3/s) (L/s) (GPM)

Rational Coef.

2,020 0.2020 60 0% 0% 100% 0.1 0.2 0.90 9 Water Quality 1-in-2 year 4.7 10 min 22.0 0.002 2.4 39

2,020 0.2020 60 0% 0% 100% 0.1 0.2 0.90 9 Storm Drainage 1-in-25 year 8.9 10 min 42.0 0.005 4.7 74

50 0.0050 15 0% 0% 100% 1 6.7 0.90 1 Water Quality 1-in-2 year 0.5 10 min 22.0 0.000 0.3 4

50 0.0050 15 0% 0% 100% 1 6.7 0.90 1 Storm Drainage 1-in-25 year 1.0 10 min 42.0 0.001 0.5 8

Water Quality 1-in-2 year 5.2 0.003 2.7 43

Storm Drainage 1-in-25 year 9.9 0.005 5.2 82

2,020 0.2020 60 0% 0% 100% 0.1 0.2 0.90 9 Water Quality 1-in-2 year 16.7 10 min 22.0 0.009 8.7 137

2,020 0.2020 60 0% 0% 100% 0.1 0.2 0.90 9 Storm Drainage 1-in-25 year 31.5 10 min 42.0 0.017 16.6 262

Water Quality 1-in-2 year 16.7 0.009 8.7 137

Storm Drainage 1-in-25 year 31.5 0.017 16.6 262

300 0.0300 15 100% 0% 0% 0.1 0.7 0.55 8 Water Quality 1-in-2 year 3.2 10 min 22.0 0.001 1.0 16

300 0.0300 15 100% 0% 0% 0.1 0.7 0.55 8 Storm Drainage 1-in-25 year 6.0 10 min 42.0 0.002 1.9 31

3,730 0.3730 75 35% 30% 35% 2 2.7 0.60 10 Water Quality 1-in-2 year 39.5 15 min 20.7 0.013 12.8 203

3,730 0.3730 75 35% 30% 35% 2 2.7 0.60 10 Storm Drainage 1-in-25 year 74.6 15 min 40.2 0.025 24.9 395

Water Quality 1-in-2 year 42.7 0.014 13.8 219

Storm Drainage 1-in-25 year 80.6 0.027 26.8 425

Water Quality 1-in-2 year 64.7 0.025 25.2 400

Storm Drainage 1-in-25 year 122.0 0.049 48.6 770

Definitions: L flow path length

H vertical drop from top of watershed to discharge point

s slope

Tc time of concentration

C runoff coefficient

Q runoff flow

Common Rational Equation Runoff Coefficients for Urban Watersheds (ref: TXDOT)

Runoff

coefficient

Runoff

coefficient

0.70-0.95 0.85-0.95

0.30-0.70 0.90-0.95

0.70-0.85

0.30-0.50 0.75-0.95

0.40-0.60 0.75-0.95

0.60-0.75

0.35-0.40 0.30-0.80

0.30-0.70 0.60-0.90

0.10-0.25

0.30-0.40

0.30-0.40

Reference: Standard Handbook of Environmental Engineering

McGraw-Hill 1990

(used for Tc equation, applying FAA formula, and confirming runoff coefficients)

*IDF Curve: MetroVancouver Regional IDF Curve Zone 3

Time of concentration: FAA equation: Tc = G (1.1 - c) L0.5

/ (100 S)1/3

City of New Westminster: Tc follows FAA equation

Tc (lot size ≤2000 m2) = 10 min

Tc (lot size >2000 m2) = 15 min or as calculated

** Waste Storage Area has roof to prevent infiltration of precipitation to the waste material stored within. Conservatively assume 22% of precipitation reaches waste material

based on estimates of driving rain intensity as a proportion of rainfall intensity.

Asphaltic

Streets:

Type of drainage area

Treated Stormwater

Total

Site Stormwater

Total

Waste Storage Area

Roof Runoff**

Infiltrated

Stormwater Total

Ditch/Swale

Stormwater Total

Railroad yards

Playgrounds

Parks, cemeteries

Heavy areas

Light areas

Apartment dwelling areas

Suburban

Multi-units, attached

Multi-units, detached

Single-family areas

Residential:

Neighborhood

Downtown

Business:

Type of drainage area

Industrial:

Roofs

Drives and walks

Brick

Concrete

Barge Ramp Area

Remaining Site

Area

DERWENT WAY BARGE LOADING FACILITY STORMWATER RUNOFF FLOW

November 8, 2017

Keystone Environmental Ltd. Project 12943

Using the Rational Method, City of New Westminster Design Criteria, Port Metro Vancouver PER Guidelines for SPPPs

Gravel Storage

Bays

% Packed

Gravel

% Coarse

Vegetation

% Paved /

Impermeable

Waste Storage Area

Sump**