stormwater management report - garden district, toronto · 2016. 10. 18. · stormwater management...
TRANSCRIPT
June 2016
Stormwater Management Report
Queen Developments Inc. 88 Queen Street East Phase 2 City of Toronto
10-15087-001-SW3
Stormwater Management Report | 88 Queen Street East Phase 2
WSP/MMM Group Limited | June 2016 | 10-15087-001-SW3 i
TABLE OF CONTENTS
1.0 INTRODUCTION ............................................................................................ 1
1.1 Scope of the Stormwater Management Report ................................................................... 1
1.2 Site Location ........................................................................................................................... 1
1.3 Stormwater Management Plan Objectives .......................................................................... 1
1.4 Design Criteria ........................................................................................................................ 1
2.0 EXISTING CONDITIONS ............................................................................... 3
2.1 General..................................................................................................................................... 3
2.2 Rainfall Information ................................................................................................................ 3
2.3 Allowable Flow Rates ............................................................................................................. 3
3.0 POST-DEVELOPMENT CONDITIONS .......................................................... 5
3.1 General..................................................................................................................................... 5
3.2 Water Balance ........................................................................................................................ 6
3.3 Water Quality Control............................................................................................................. 7
3.4 Erosion Control ...................................................................................................................... 7
3.5 Water Quantity Control .......................................................................................................... 7
4.0 CONCLUSIONS ............................................................................................. 9
LIST OF FIGURES
Figure 1 Site Location ..................................................................................................... 1 Figure 2 Existing Conditions ........................................................................................... 3 Figure 3 Proposed Conditions ........................................................................................ 5
LIST OF TABLES
Table 1 Rainfall Parameters .......................................................................................... 3 Table 2 Pre-Development Peak Flow Rate Calculations ............................................... 4 Table 3 Proposed Land-Use Area Breakdown .............................................................. 5 Table 4 Water Balance Calculation Summary ............................................................... 6 Table 5 Post-Development Peak Flow and Storage Rates ............................................ 7
LIST OF APPENDICES
Appendix A – Stormwater Management Calculations
Stormwater Management Report | 88 Queen Street East Phase 2
WSP/ MMM Group Limited | June 2016 | 10-15087-001-SW3
1
1.0 INTRODUCTION
1.1 Scope of the Stormwater Management Report
MMM Group has been retained by Queen Developments Inc. to prepare a Stormwater Management
Report for the proposed residential/commercial development at 88 Queen Street East—Phase 2, in the
City of Toronto. This site is immediately south of the Phase 1 development, known as 88 North, at 30
Mutual Street. 88 North is currently under Site Plan Application stage under SPA No. 15 270190 STE 27
SA. This report is to be read in conjunction with the Phase 1 Stormwater Management Report for the
assessment of the Zoning By-Law Amendment Application for the entire 88 Queen Street East site. This
stormwater management report examines the potential water quality, quantity and water balance impacts
of the proposed development and summarizes how each will be addressed in accordance with the City of
Toronto’s Wet Weather Flow Management Guidelines (WWFMG).
1.2 Site Location
The 88 Queen Street East—Phase 2 development is bounded by Queen St. E. to the south, Mutual Street
to the east and Dalhousie Street to the west, and immediately south of the Phase 1 development, 88 North
at 30 Mutual St. The second phase of the development, 88 Queen Street East, is in the southern portion of
the development area. The location of 88 Queen Street East is shown in Figure 1, and has an area of 0.70
ha.
1.3 Stormwater Management Plan Objectives
The objectives of the stormwater management plan are as follows:
► Determine site specific stormwater management requirements to ensure that the development project
is in conformance with the ‘Wet Weather Flow Management Guidelines’ (WWFMG) issued by the City
of Toronto;
► Evaluate various stormwater management practices that meet the requirements of the City and
recommend a preferred strategy; and
► Prepare a preliminary stormwater management report documenting the strategy along with the
technical information necessary for the sizing of the proposed stormwater management practices.
1.4 Design Criteria
The City of Toronto has issued the Wet Weather Flow Management Guidelines (WWFMG, November
2006) to provide direction on how to manage rainfall and runoff inside the City’s jurisdiction. A summary of
the stormwater management criteria applicable to this project is as follows:
Stormwater Management Report | 88 Queen Street East Phase 2
WSP/ MMM Group Limited | June 2016 | 10-15087-001-SW3
2
► Water Balance – The WWFMG requires a site to ‘retain stormwater on-site, to the extent practicable,
to achieve the same level of annual volume of overland runoff allowable from the development site
under pre-development conditions’. According to the guidelines, if the allowable annual runoff volume
from the development site under post-development conditions is less than the pre-development
conditions, then the maximum allowable annual runoff is 50% of the total average annual rainfall
depth. The WWFMG shows that 50% of the average annual rainfall in the City of Toronto falls in
events of 5 mm or less. For the proposed project site, all runoff from a 5 mm or smaller storm event
must be retained onsite through infiltration, evapotranspiration or rainwater reuse.
► Water Quality – Under the Wet Weather Flow Management Guidelines, the site is required to provide
a long-term removal of 80% of total suspended solids (TSS) on an average annual basis.
► Erosion Control – As indicated in WWFMG, ‘For small infill/redevelopment sites < 2 ha, erosion control
in the form of stormwater detention is normally not required, provided the on-site minimum runoff
retention from a small design rainfall event (typically 5 mm) is achieved under the Water Balance
Criteria.’
► Water Quantity Control and Discharge to Municipal Infrastructure – Runoff from the 2-year to 100-year
design storms must not exceed the peak runoff rate from the site under pre-development conditions.
Because the imperviousness of the site under pre-development is higher than the maximum allowable
runoff coefficient value of 0.5, the allowable release rate to the municipal storm sewer system from the
development site is the 2-year pre-development flow rate based on a runoff coefficient value of 0.50.
Stormwater Management Report | 88 Queen Street East Phase 2
WSP/ MMM Group Limited | June 2016 | 10-15087-001-SW3
3
2.0 EXISTING CONDITIONS
2.1 General
Phase 2 of the development is currently an existing impervious parking lot with a total area of
0.70 hectares. In existing conditions, the site drains towards Mutual Street, to the southeast. A runoff
coefficient of 0.90 is applicable for an impervious area under existing conditions. Figure 2 illustrates the
existing conditions for the subject site.
2.2 Rainfall Information
The rainfall intensity for the site was calculated using the following equation:
I = ATC
Where; I = rainfall intensity in mm/hr,
T = time of concentration in hours,
A, C = constant parameters (see below)
The parameters (A and C) recommended for use in the City of Toronto are defined in section 3.1 of the
WWFMG, and are summarized below in Table 1.
TABLE 1: RAINFALL PARAMETERS
Return Period
(years) 2 5 10 25 50 100
A 21.8 32.0 38.7 45.2 53.5 59.7
C -0.78 -0.79 -0.80 -0.80 -0.80 -0.80
An initial time of concentration, TC, of 10 minutes (or 0.167 hours) is recommended in the WWFMG
document.
2.3 Allowable Flow Rates
Phase 2 of the site is an impervious parcel located in a highly urbanized area. Relevant policies from the
WWFMG restrict flow rates on this site to the allowable flow rates for discharge to municipal sewers.
According to the WWFMG, Section 2.2.3.8, the allowable release rate to the municipal storm sewer
system from the existing site is 85.9 L/s, based on the 2-year pre-development flow rate calculated with a
Stormwater Management Report | 88 Queen Street East Phase 2
WSP/ MMM Group Limited | June 2016 | 10-15087-001-SW3
4
runoff coefficient value of 0.50. This release rate applies to the entire site, since it will drain to one storm
sewer.
The calculated pre-development peak flow rates for the existing site for 2 to 100-year storm events are
summarized in Table 2. Detailed calculations are provided in Appendix A.
TABLE 2: PRE-DEVELOPMENT PEAK FLOW RATE CALCULATIONS
(Based on a runoff coefficient of 0.50 and Tc = 10 minutes)
Return Period
(years)
Rainfall Intensity, I
(mm/hour)
Peak Flow Rate
(L/s)
Allowable
Release Rate
(L/s)
2 88 85.9
85.9
5 132 128.3
10 162 158.0
25 190 184.5
50 224 218.4
100 250 243.7
Stormwater Management Report | 88 Queen Street East Phase 2
WSP/ MMM Group Limited | June 2016 | 10-15087-001-SW3
5
3.0 POST-DEVELOPMENT CONDITIONS
3.1 General
Phase 2 of the proposed development includes 3 separate towers and 3 podiums, a small park area, and
a P.O.P.S. (privately owned public space). The development proposes an underground parking garage,
green roof, and an open space. The perimeter area located on west side of the development site will
include lane widening on Dalhousie. A runoff coefficient of 0.90 is applicable for runoff generated from the
hard surface rooftop and at-grade impervious areas of the proposed development. Figure 3 shows the
proposed conditions of the development site. The land use area breakdown is shown in Table 3.
To address stormwater management at the proposed site, runoff from roof and at-grade areas will be
directed to one of two underground SWM tanks, one for the north buildings and at-grade areas, and one
for the south buildings and at-grade areas. No at-grade areas within the site limits are uncontrolled in the
current design. In addition, the proposed lane widening area will flow uncontrolled to the Dalhousie Street
storm sewer. To account for uncontrolled flow from this lane-widening area, the remaining site will be over-
controlled to meet allowable release rate requirements.
TABLE 3: PROPOSED LAND-USE AREA BREAKDOWN
Land-use Area (m2) % Coverage
Runoff Coefficient
North Cistern
Impervious Roof 1289 18% 0.9
Green Roof 1201 17% 0.5
At-grade Impervious
1078 15% 0.9
Park 247 4% 0.25
Lane Widening 42 1% 0.9
South Cistern
Impervious Roof 1585 23% 0.9
Green Roof 515 7% 0.5
At-Grade Impervious
1009 14% 0.9
Tree Cells 8 0% 0.25
Lane Widening 31 0% 0.9
Total Site Area 7004 100% 0.78
Stormwater Management Report | 88 Queen Street East Phase 2
WSP/ MMM Group Limited | June 2016 | 10-15087-001-SW3
6
3.2 Water Balance
The WWFMG requires the post-development annual runoff volume to be less than the pre-development
volume. The WWFMG requires the proponent to retain all runoff from a 5 mm storm event through
infiltration, evapotranspiration or rainwater reuse. For the proposed development, the underground parking
garage covers a majority of the area, so infiltration is not an option to satisfy the water balance
requirement. To address this, two rainwater SWM cisterns located in the underground parking garage will
be the primary mechanism to capture rainwater.
A sump provided in the tank serving the north towers will be sized to capture a total runoff volume of 9.6
m3 for re-use purposes (assuming 1 mm initial abstraction for impervious surfaces, and 5 mm abstraction
from pervious surfaces). A sump provided in the tank serving the south tower will be sized to capture a
total runoff volume of 10.5 m3 for re-use purposes (assuming 1 mm initial abstraction for impervious
surfaces, and 5 mm abstraction from pervious surfaces). This retained water could be used for building
purposes including car washes, cooling towers, or toilet flushing purposes. The final cistern reuse volume
sizing will vary, depending on the reuse strategy selected. A summary of the required retention volume to
satisfy the water balance requirement is provided in Table 4.
TABLE 4: REQUIRED WATER BALANCE VOLUME
Land-use Area (m2) Initial
Abstraction (mm)
Water Balance Volume (m3)
North Cistern
Impervious Roof 1289 1 5.2
Green Roof 1201 5 0.0
Open Space 1078 1 4.3
Park 247 5 0.0
Lane Widening 42 1 0.2
Total 3856 9.6
South Cistern
Impervious Roof 1585 1 6.3
Green Roof 515 5 0.0
Open Space 1009 1 4.0
Tree Cells 8 5 0.0
Lane Widening 31 1 0.1
Total 3148 10.5
Stormwater Management Report | 88 Queen Street East Phase 2
WSP/ MMM Group Limited | June 2016 | 10-15087-001-SW3
7
3.3 Water Quality Control
Phase 2 of the development proposes impervious roof, green roof, and at-grade open space and
landscaped areas where only pedestrian traffic is permitted. All garage entrances will be covered by roof
areas. Thus, site areas are not prone to any sediment generation so runoff from these areas will be
considered clean for the purposes of water quality. No additional water quality treatment is recommended
for this site.
3.4 Erosion Control
As mentioned in section 1.4, the Phase 2 site is an overall small footprint development. According to the
WWFMG, ‘For small infill/redevelopment sites < 2.0 ha, erosion control in the form of stormwater detention
is normally not required, provided the on-site minimum runoff retention from a small design rainfall event
(typically 5 mm) is achieved under the Water Balance Criteria.’
The total site area for consideration under this application is 0.70 ha, which is well below the 2.0 ha
guideline. The water balance requirement for the proposed development is satisfied by providing a 5 mm
runoff volume retention concerns as addressed in Section 3.2. Therefore, additional erosion control
measures are not recommended.
3.5 Water Quantity Control
As noted in section 2.3, the allowable discharge rate to the municipal sewer system from the site under
post-development condition is 85.9 L/s based on a runoff coefficient of 0.50 as summarized in Table 2.
The SWM strategy described in detail above, and as shown in Figure 3, includes a number of elements
which contribute to a reduction in peak flow rates. This includes:
► Green roof and landscaped areas to reduce peak flow rate;
► Two stormwater tanks located in the underground parking garage to provide detention and control of
runoff from impervious areas.
The tank serving the mid-block tower areas will have a footprint of 58.5 m2, with a maximum height of 3 m,
providing 176 m3 of available storage for the water balance and quantity control. The post-development
flow will be controlled with a 100 mm orifice tube to the prescribed flow rate. The outlet invert will be 0.17
m above the bottom of the tank. This provides 9.9 m3 of storage in the sump, which exceeds the required
water balance reuse volume of 9.6 m3. The tank will also be fitted with an overflow pipe. This will prevent
flow back-up into the building when the primary outlet is blocked, or if a storm event is in excess of the
100-year return period, as well as alert the owner in the event of an obstruction.
The tank serving the south tower areas will have a footprint of 57.2 m2, with a maximum height of 3 m,
providing 172 m3 of available storage for the water balance and quantity control. The post-development
flow will be controlled with a 100 mm orifice tube to the prescribed flow rate. The outlet invert will be 0.19
Stormwater Management Report | 88 Queen Street East Phase 2
WSP/ MMM Group Limited | June 2016 | 10-15087-001-SW3
8
m above the bottom of the tank. This provides 10.9 m3 of storage in the sump, which exceeds the required
water balance reuse volume of 10.5 m3. The tank will also be fitted with an overflow pipe. This will prevent
flow back-up into the building when the primary outlet is blocked, or if a storm event is in excess of the
100-year return period, as well as alert the owner in the event of an obstruction.
The ‘HydroCAD’ software package has been used to model the behaviour of the proposed SWM system,
and determine its response under various storm events. This software utilizes the Modified Rational
Method to calculate flow rates and related storage values. Detailed output from the modelling for the
proposed condition is included in Appendix A. Table 5 summarizes the generated peak flow rates for
proposed conditions and storage volumes required.
TABLE 5: POST-DEVELOPMENT PEAK FLOW AND STORAGE RATES
Return
Period
(years)
Allowable
Release
Rate (L/s)
Flow from
North
Stormwater
Tank (L/s)
Flow from
South
Stormwater
Tank (L/s)
Uncontrolled
Flow from
North Lane
Widening
(L/s)
Uncontrolled
Flow from
South Lane
Widening
(L/s)
North Tank
Storage
Utilized
(m3, 176 m3
available)
South
Tank
Storage
Utilized
(m3, 172
m3
available)
Total Post-
Development
Peak Flow
(L/s)
2
85.9
16.7 15.7 0.5 0.4 34.0 32.0 32.9
5 22.4 21.3 0.8 0.6 50.8 47.1 44.2
10 25.7 24.5 0.9 0.7 62.8 58.1 50.8
25 28.5 27.2 1.1 0.8 74.2 68.5 56.4
50 31.7 30.4 1.3 1.0 89.0 82.1 63.0
100 34.0 32.6 1.5 1.1 100.4 92.4 67.6
As shown in Table 5, the minimum required storage in the north tank is 100.4 m3 and the minimum
required storage in the south tank is 92.4 m3 to control the 100-year post-development flow to the
allowable release rate without overland flow. These numbers should be updated once a full site design
and water balance reuse solution is determined.
AP
PE
ND
IX A
– S
torm
wa
ter M
an
ag
em
en
t Ca
lcu
latio
ns
Project:88 Queen Phase 2
No.:10-15087
By:Margaret Olson
Date:03/06/2016
Page:
Checked:Maggie Ding
Checked:1
Subject:
Stormwater Management Calculations - Predevelopment Allowable Runoff Rate
Calculation of existing runoff rate is undertaken using the Rational Method:
Where: Q = Peak flow rate (litres/second)
C = Runoff coefficient
I = Rainfall intensity (mm/hour)
A = Catchment area (hectares)
Site Area, A 0.70 hectares
Post-Development
Runoff Coefficient, C0.50
Rainfall Intensity is calculated based on City of Toronto Intensity-Duration-Frequency (IDF) Equations: I=A(T)B
Where: I = Rainfall Intensity in mm/hr
T = Time of Concentration in minutes, use 10min
A, B = Rainfall Parameters used by the City of Toronto
Return Period (Years) 2 5 10 25 50 100
A 21.8 32.0 38.7 45.2 53.5 59.7
B -0.780 -0.790 -0.800 -0.800 -0.800 -0.800
T (mins) ** 10 10 10 10 10 10
T (hrs) 0.167 0.167 0.167 0.167 0.167 0.167
I (mm/hr) 88.2 131.8 162.3 189.5 224.3 250.3
Q (litres/sec) 85.9 128.3 158.0 184.5 218.4 243.7
Q (m3/sec) 0.086 0.128 0.158 0.185 0.218 0.244
** Note recommended minimum value for time of concentration for small sites (<2.0ha) is 10 minutes.
Allowable release rate to municipal storm sewer system is therefore 85.9 litres/second.
(As per City of Toronto Guidelines)
CIAQ 78.2=
1S
Existing Conditions
3S
Proposed Site North
4S
Lane Widening
10S
Proposed Site
11S
Green Roof North
Buildings
12S
Impervious Roof Area
13S
Lane Widening
15S
Green Roof
16S
Impervious Roof Area6P
Stormwater Cistern
17P
Stormwater Cistern
2L
Outflow
7L
Total Outflow
9L
Total North Uncontrolled
Flow
18L
Total Outflow
19L
Total South Uncontrolled
Flow
20L
Total Site Outflow
Drainage Diagram for Phase 2 Site Runoffs V_02Prepared by MMM Group Limited, Printed 03/06/2016
HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Subcat Reach Pond Link
Toronto 2-Year Duration=21 min, Inten=49.4 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 2HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Time span=0.00-4.00 hrs, dt=0.01 hrs, 401 pointsRunoff by Rational method, Rise/Fall=1.0/1.0 xTc
Reach routing by Stor-Ind+Trans method - Pond routing by Stor-Ind method
Runoff Area=7,004.0 m² 0.00% Impervious Runoff Depth=9 mmSubcatchment 1S: Existing Conditions Tc=10.0 min C=0.50 Runoff=0.0481 m³/s 60.6 m³
Runoff Area=1,325.0 m² 0.00% Impervious Runoff Depth=13 mmSubcatchment 3S: Proposed Site North Tc=10.0 min C=0.78 Runoff=0.0142 m³/s 17.9 m³
Runoff Area=42.0 m² 0.00% Impervious Runoff Depth=16 mmSubcatchment 4S: Lane Widening Tc=10.0 min C=0.90 Runoff=0.0005 m³/s 0.7 m³
Runoff Area=1,018.0 m² 0.00% Impervious Runoff Depth=15 mmSubcatchment 10S: Proposed Site Tc=10.0 min C=0.89 Runoff=0.0124 m³/s 15.7 m³
Runoff Area=1,201.0 m² 0.00% Impervious Runoff Depth=9 mmSubcatchment 11S: Green Roof North Tc=10.0 min C=0.50 Runoff=0.0082 m³/s 10.4 m³
Runoff Area=1,289.0 m² 0.00% Impervious Runoff Depth=16 mmSubcatchment 12S: Impervious Roof Tc=10.0 min C=0.90 Runoff=0.0159 m³/s 20.1 m³
Runoff Area=31.0 m² 0.00% Impervious Runoff Depth=16 mmSubcatchment 13S: Lane Widening Tc=10.0 min C=0.90 Runoff=0.0004 m³/s 0.5 m³
Runoff Area=515.0 m² 0.00% Impervious Runoff Depth=9 mmSubcatchment 15S: Green Roof Tc=10.0 min C=0.50 Runoff=0.0035 m³/s 4.5 m³
Runoff Area=1,585.0 m² 0.00% Impervious Runoff Depth=16 mmSubcatchment 16S: Impervious Roof Tc=10.0 min C=0.90 Runoff=0.0196 m³/s 24.7 m³
Peak Elev=0.580 m Storage=34.0 m³ Inflow=0.0384 m³/s 48.3 m³Pond 6P: Stormwater Cistern Outflow=0.0167 m³/s 38.3 m³
Peak Elev=0.559 m Storage=32.0 m³ Inflow=0.0356 m³/s 44.8 m³Pond 17P: Stormwater Cistern Outflow=0.0157 m³/s 33.9 m³
Inflow=0.0481 m³/s 60.6 m³Link 2L: Outflow Primary=0.0481 m³/s 60.6 m³
Inflow=0.0170 m³/s 39.0 m³Link 7L: Total Outflow Primary=0.0170 m³/s 39.0 m³
Inflow=0.0005 m³/s 0.7 m³Link 9L: Total North Uncontrolled Flow Primary=0.0005 m³/s 0.7 m³
Inflow=0.0159 m³/s 34.4 m³Link 18L: Total Outflow Primary=0.0159 m³/s 34.4 m³
Inflow=0.0004 m³/s 0.5 m³Link 19L: Total South Uncontrolled Flow Primary=0.0004 m³/s 0.5 m³
Toronto 2-Year Duration=21 min, Inten=49.4 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 3HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Inflow=0.0329 m³/s 73.4 m³Link 20L: Total Site Outflow Primary=0.0329 m³/s 73.4 m³
Total Runoff Area = 14,010.0 m² Runoff Volume = 154.9 m³ Average Runoff Depth = 11 mm100.00% Pervious = 14,010.0 m² 0.00% Impervious = 0.0 m²
Toronto 2-Year Duration=21 min, Inten=49.4 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 4HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 1S: Existing Conditions
Runoff = 0.0481 m³/s @ 0.17 hrs, Volume= 60.6 m³, Depth= 9 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 2-Year Duration=21 min, Inten=49.4 mm/hr
Area (m²) C Description
7,004.0 0.50
7,004.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 1S: Existing Conditions
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.05
0.045
0.04
0.035
0.03
0.025
0.02
0.015
0.01
0.005
0
Toronto 2-Year
Duration=21 min,
Inten=49.4 mm/hr
Runoff Area=7,004.0 m²
Runoff Volume=60.6 m³
Runoff Depth=9 mm
Tc=10.0 min
C=0.50
0.0481 m³/s
Toronto 2-Year Duration=21 min, Inten=49.4 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 5HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 3S: Proposed Site North
Runoff = 0.0142 m³/s @ 0.17 hrs, Volume= 17.9 m³, Depth= 13 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 2-Year Duration=21 min, Inten=49.4 mm/hr
Area (m²) C Description
247.0 0.25 Park1,078.0 0.90 At-grade
1,325.0 0.78 Weighted Average1,325.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 3S: Proposed Site North
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.014
0.012
0.01
0.008
0.006
0.004
0.002
0
Toronto 2-Year
Duration=21 min,
Inten=49.4 mm/hr
Runoff Area=1,325.0 m²
Runoff Volume=17.9 m³
Runoff Depth=13 mm
Tc=10.0 min
C=0.78
0.0142 m³/s
Toronto 2-Year Duration=21 min, Inten=49.4 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 6HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 4S: Lane Widening
Runoff = 0.0005 m³/s @ 0.17 hrs, Volume= 0.7 m³, Depth= 16 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 2-Year Duration=21 min, Inten=49.4 mm/hr
Area (m²) C Description
42.0 0.90 Lane Widening
42.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 4S: Lane Widening
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.001
0.001
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0
0
0
Toronto 2-Year
Duration=21 min,
Inten=49.4 mm/hr
Runoff Area=42.0 m²
Runoff Volume=0.7 m³
Runoff Depth=16 mm
Tc=10.0 min
C=0.90
0.0005 m³/s
Toronto 2-Year Duration=21 min, Inten=49.4 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 7HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 10S: Proposed Site
Runoff = 0.0124 m³/s @ 0.17 hrs, Volume= 15.7 m³, Depth= 15 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 2-Year Duration=21 min, Inten=49.4 mm/hr
Area (m²) C Description
9.0 0.25 Tree Boxes1,009.0 0.90 At-Grade
1,018.0 0.89 Weighted Average1,018.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 10S: Proposed Site
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.0130.0120.011
0.010.0090.0080.0070.0060.0050.0040.0030.0020.001
0
Toronto 2-Year
Duration=21 min,
Inten=49.4 mm/hr
Runoff Area=1,018.0 m²
Runoff Volume=15.7 m³
Runoff Depth=15 mm
Tc=10.0 min
C=0.89
0.0124 m³/s
Toronto 2-Year Duration=21 min, Inten=49.4 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 8HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 11S: Green Roof North Buildings
Runoff = 0.0082 m³/s @ 0.17 hrs, Volume= 10.4 m³, Depth= 9 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 2-Year Duration=21 min, Inten=49.4 mm/hr
Area (m²) C Description
1,201.0 0.50 Green Roof W
1,201.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 11S: Green Roof North Buildings
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.009
0.008
0.007
0.006
0.005
0.004
0.003
0.002
0.001
0
Toronto 2-Year
Duration=21 min,
Inten=49.4 mm/hr
Runoff Area=1,201.0 m²
Runoff Volume=10.4 m³
Runoff Depth=9 mm
Tc=10.0 min
C=0.50
0.0082 m³/s
Toronto 2-Year Duration=21 min, Inten=49.4 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 9HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 12S: Impervious Roof Area
Runoff = 0.0159 m³/s @ 0.17 hrs, Volume= 20.1 m³, Depth= 16 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 2-Year Duration=21 min, Inten=49.4 mm/hr
Area (m²) C Description
1,289.0 0.90 Impervious Roof W
1,289.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 12S: Impervious Roof Area
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.016
0.014
0.012
0.01
0.008
0.006
0.004
0.002
0
Toronto 2-Year
Duration=21 min,
Inten=49.4 mm/hr
Runoff Area=1,289.0 m²
Runoff Volume=20.1 m³
Runoff Depth=16 mm
Tc=10.0 min
C=0.90
0.0159 m³/s
Toronto 2-Year Duration=21 min, Inten=49.4 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 10HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 13S: Lane Widening
Runoff = 0.0004 m³/s @ 0.17 hrs, Volume= 0.5 m³, Depth= 16 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 2-Year Duration=21 min, Inten=49.4 mm/hr
Area (m²) C Description
31.0 0.90 Lane Widening
31.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 13S: Lane Widening
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.000
0.000
0.000
0.000
0.000
0.000
0
0
0
Toronto 2-Year
Duration=21 min,
Inten=49.4 mm/hr
Runoff Area=31.0 m²
Runoff Volume=0.5 m³
Runoff Depth=16 mm
Tc=10.0 min
C=0.90
0.0004 m³/s
Toronto 2-Year Duration=21 min, Inten=49.4 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 11HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 15S: Green Roof
Runoff = 0.0035 m³/s @ 0.17 hrs, Volume= 4.5 m³, Depth= 9 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 2-Year Duration=21 min, Inten=49.4 mm/hr
Area (m²) C Description
515.0 0.50 Green Roof
515.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 15S: Green Roof
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.004
0.003
0.003
0.002
0.002
0.001
0.001
0
Toronto 2-Year
Duration=21 min,
Inten=49.4 mm/hr
Runoff Area=515.0 m²
Runoff Volume=4.5 m³
Runoff Depth=9 mm
Tc=10.0 min
C=0.50
0.0035 m³/s
Toronto 2-Year Duration=21 min, Inten=49.4 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 12HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 16S: Impervious Roof Area
Runoff = 0.0196 m³/s @ 0.17 hrs, Volume= 24.7 m³, Depth= 16 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 2-Year Duration=21 min, Inten=49.4 mm/hr
Area (m²) C Description
1,585.0 0.90 Impervious Roof
1,585.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 16S: Impervious Roof Area
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.02
0.018
0.016
0.014
0.012
0.01
0.008
0.006
0.004
0.002
0
Toronto 2-Year
Duration=21 min,
Inten=49.4 mm/hr
Runoff Area=1,585.0 m²
Runoff Volume=24.7 m³
Runoff Depth=16 mm
Tc=10.0 min
C=0.90
0.0196 m³/s
Toronto 2-Year Duration=21 min, Inten=49.4 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 13HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Pond 6P: Stormwater Cistern
Inflow Area = 3,815.0 m², 0.00% Impervious, Inflow Depth = 13 mm for 2-Year eventInflow = 0.0384 m³/s @ 0.17 hrs, Volume= 48.3 m³Outflow = 0.0167 m³/s @ 0.44 hrs, Volume= 38.3 m³, Atten= 56%, Lag= 16.4 minPrimary = 0.0167 m³/s @ 0.44 hrs, Volume= 38.3 m³
Routing by Stor-Ind method, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsPeak Elev= 0.580 m @ 0.44 hrs Surf.Area= 58.7 m² Storage= 34.0 m³
Plug-Flow detention time= 25.4 min calculated for 38.2 m³ (79% of inflow)Center-of-Mass det. time= 23.4 min ( 38.9 - 15.5 )
Volume Invert Avail.Storage Storage Description
#1 0.000 m 176.1 m³ 10.00 mW x 5.87 mL x 3.00 mH Prismatoid
Device Routing Invert Outlet Devices
#1 Primary 0.168 m 100 mm Vert. Orifice/Grate C= 0.800
Primary OutFlow Max=0.0167 m³/s @ 0.44 hrs HW=0.579 m (Free Discharge)1=Orifice/Grate (Orifice Controls 0.0167 m³/s @ 2.13 m/s)
Pond 6P: Stormwater Cistern
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.04
0.035
0.03
0.025
0.02
0.015
0.01
0.005
0
Inflow Area=3,815.0 m²
Peak Elev=0.580 m
Storage=34.0 m³
0.0384 m³/s
0.0167 m³/s
Toronto 2-Year Duration=21 min, Inten=49.4 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 14HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Pond 17P: Stormwater Cistern
Inflow Area = 3,118.0 m², 0.00% Impervious, Inflow Depth = 14 mm for 2-Year eventInflow = 0.0356 m³/s @ 0.17 hrs, Volume= 44.8 m³Outflow = 0.0157 m³/s @ 0.44 hrs, Volume= 33.9 m³, Atten= 56%, Lag= 16.4 minPrimary = 0.0157 m³/s @ 0.44 hrs, Volume= 33.9 m³
Routing by Stor-Ind method, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsPeak Elev= 0.559 m @ 0.44 hrs Surf.Area= 57.2 m² Storage= 32.0 m³
Plug-Flow detention time= 25.5 min calculated for 33.8 m³ (75% of inflow)Center-of-Mass det. time= 23.1 min ( 38.6 - 15.5 )
Volume Invert Avail.Storage Storage Description
#1 0.000 m 171.6 m³ 10.00 mW x 5.72 mL x 3.00 mH Prismatoid
Device Routing Invert Outlet Devices
#1 Primary 0.190 m 100 mm Vert. Orifice/Grate C= 0.800
Primary OutFlow Max=0.0157 m³/s @ 0.44 hrs HW=0.558 m (Free Discharge)1=Orifice/Grate (Orifice Controls 0.0157 m³/s @ 2.00 m/s)
Pond 17P: Stormwater Cistern
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.035
0.03
0.025
0.02
0.015
0.01
0.005
0
Inflow Area=3,118.0 m²
Peak Elev=0.559 m
Storage=32.0 m³
0.0356 m³/s
0.0157 m³/s
Toronto 2-Year Duration=21 min, Inten=49.4 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 15HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Link 2L: Outflow
Inflow Area = 7,004.0 m², 0.00% Impervious, Inflow Depth = 9 mm for 2-Year eventInflow = 0.0481 m³/s @ 0.17 hrs, Volume= 60.6 m³Primary = 0.0481 m³/s @ 0.17 hrs, Volume= 60.6 m³, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 0.00-4.00 hrs, dt= 0.01 hrs
Link 2L: Outflow
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.05
0.045
0.04
0.035
0.03
0.025
0.02
0.015
0.01
0.005
0
Inflow Area=7,004.0 m²
0.0481 m³/s0.0481 m³/s
Toronto 2-Year Duration=21 min, Inten=49.4 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 16HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Link 7L: Total Outflow
Inflow Area = 3,857.0 m², 0.00% Impervious, Inflow Depth > 10 mm for 2-Year eventInflow = 0.0170 m³/s @ 0.43 hrs, Volume= 39.0 m³Primary = 0.0170 m³/s @ 0.43 hrs, Volume= 39.0 m³, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 0.00-4.00 hrs, dt= 0.01 hrs
Link 7L: Total Outflow
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.018
0.016
0.014
0.012
0.01
0.008
0.006
0.004
0.002
0
Inflow Area=3,857.0 m²
0.0170 m³/s0.0170 m³/s
Toronto 2-Year Duration=21 min, Inten=49.4 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 17HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Link 9L: Total North Uncontrolled Flow
Inflow Area = 42.0 m², 0.00% Impervious, Inflow Depth = 16 mm for 2-Year eventInflow = 0.0005 m³/s @ 0.17 hrs, Volume= 0.7 m³Primary = 0.0005 m³/s @ 0.17 hrs, Volume= 0.7 m³, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 0.00-4.00 hrs, dt= 0.01 hrs
Link 9L: Total North Uncontrolled Flow
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.001
0.001
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0
0
0
Inflow Area=42.0 m²
0.0005 m³/s0.0005 m³/s
Toronto 2-Year Duration=21 min, Inten=49.4 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 18HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Link 18L: Total Outflow
Inflow Area = 3,149.0 m², 0.00% Impervious, Inflow Depth > 11 mm for 2-Year eventInflow = 0.0159 m³/s @ 0.44 hrs, Volume= 34.4 m³Primary = 0.0159 m³/s @ 0.44 hrs, Volume= 34.4 m³, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 0.00-4.00 hrs, dt= 0.01 hrs
Link 18L: Total Outflow
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.016
0.014
0.012
0.01
0.008
0.006
0.004
0.002
0
Inflow Area=3,149.0 m²
0.0159 m³/s0.0159 m³/s
Toronto 2-Year Duration=21 min, Inten=49.4 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 19HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Link 19L: Total South Uncontrolled Flow
Inflow Area = 31.0 m², 0.00% Impervious, Inflow Depth = 16 mm for 2-Year eventInflow = 0.0004 m³/s @ 0.17 hrs, Volume= 0.5 m³Primary = 0.0004 m³/s @ 0.17 hrs, Volume= 0.5 m³, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 0.00-4.00 hrs, dt= 0.01 hrs
Link 19L: Total South Uncontrolled Flow
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.000
0.000
0.000
0.000
0.000
0.000
0
0
0
Inflow Area=31.0 m²
0.0004 m³/s0.0004 m³/s
Toronto 2-Year Duration=21 min, Inten=49.4 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 20HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Link 20L: Total Site Outflow
Inflow Area = 7,006.0 m², 0.00% Impervious, Inflow Depth > 10 mm for 2-Year eventInflow = 0.0329 m³/s @ 0.44 hrs, Volume= 73.4 m³Primary = 0.0329 m³/s @ 0.44 hrs, Volume= 73.4 m³, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 0.00-4.00 hrs, dt= 0.01 hrs
Link 20L: Total Site Outflow
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.035
0.03
0.025
0.02
0.015
0.01
0.005
0
Inflow Area=7,006.0 m²
0.0329 m³/s0.0329 m³/s
Toronto 5-Year Duration=21 min, Inten=73.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 21HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Time span=0.00-4.00 hrs, dt=0.01 hrs, 401 pointsRunoff by Rational method, Rise/Fall=1.0/1.0 xTc
Reach routing by Stor-Ind+Trans method - Pond routing by Stor-Ind method
Runoff Area=7,004.0 m² 0.00% Impervious Runoff Depth=13 mmSubcatchment 1S: Existing Conditions Tc=10.0 min C=0.50 Runoff=0.0713 m³/s 89.9 m³
Runoff Area=1,325.0 m² 0.00% Impervious Runoff Depth=20 mmSubcatchment 3S: Proposed Site North Tc=10.0 min C=0.78 Runoff=0.0211 m³/s 26.5 m³
Runoff Area=42.0 m² 0.00% Impervious Runoff Depth=23 mmSubcatchment 4S: Lane Widening Tc=10.0 min C=0.90 Runoff=0.0008 m³/s 1.0 m³
Runoff Area=1,018.0 m² 0.00% Impervious Runoff Depth=23 mmSubcatchment 10S: Proposed Site Tc=10.0 min C=0.89 Runoff=0.0185 m³/s 23.3 m³
Runoff Area=1,201.0 m² 0.00% Impervious Runoff Depth=13 mmSubcatchment 11S: Green Roof North Tc=10.0 min C=0.50 Runoff=0.0122 m³/s 15.4 m³
Runoff Area=1,289.0 m² 0.00% Impervious Runoff Depth=23 mmSubcatchment 12S: Impervious Roof Tc=10.0 min C=0.90 Runoff=0.0236 m³/s 29.8 m³
Runoff Area=31.0 m² 0.00% Impervious Runoff Depth=23 mmSubcatchment 13S: Lane Widening Tc=10.0 min C=0.90 Runoff=0.0006 m³/s 0.7 m³
Runoff Area=515.0 m² 0.00% Impervious Runoff Depth=13 mmSubcatchment 15S: Green Roof Tc=10.0 min C=0.50 Runoff=0.0052 m³/s 6.6 m³
Runoff Area=1,585.0 m² 0.00% Impervious Runoff Depth=23 mmSubcatchment 16S: Impervious Roof Tc=10.0 min C=0.90 Runoff=0.0291 m³/s 36.6 m³
Peak Elev=0.865 m Storage=50.8 m³ Inflow=0.0569 m³/s 71.7 m³Pond 6P: Stormwater Cistern Outflow=0.0224 m³/s 61.7 m³
Peak Elev=0.824 m Storage=47.1 m³ Inflow=0.0528 m³/s 66.5 m³Pond 17P: Stormwater Cistern Outflow=0.0213 m³/s 55.5 m³
Inflow=0.0713 m³/s 89.9 m³Link 2L: Outflow Primary=0.0713 m³/s 89.9 m³
Inflow=0.0227 m³/s 62.6 m³Link 7L: Total Outflow Primary=0.0227 m³/s 62.6 m³
Inflow=0.0008 m³/s 1.0 m³Link 9L: Total North Uncontrolled Flow Primary=0.0008 m³/s 1.0 m³
Inflow=0.0215 m³/s 56.3 m³Link 18L: Total Outflow Primary=0.0215 m³/s 56.3 m³
Inflow=0.0006 m³/s 0.7 m³Link 19L: Total South Uncontrolled Flow Primary=0.0006 m³/s 0.7 m³
Toronto 5-Year Duration=21 min, Inten=73.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 22HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Inflow=0.0442 m³/s 118.9 m³Link 20L: Total Site Outflow Primary=0.0442 m³/s 118.9 m³
Total Runoff Area = 14,010.0 m² Runoff Volume = 229.8 m³ Average Runoff Depth = 16 mm100.00% Pervious = 14,010.0 m² 0.00% Impervious = 0.0 m²
Toronto 5-Year Duration=21 min, Inten=73.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 23HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 1S: Existing Conditions
Runoff = 0.0713 m³/s @ 0.17 hrs, Volume= 89.9 m³, Depth= 13 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 5-Year Duration=21 min, Inten=73.3 mm/hr
Area (m²) C Description
7,004.0 0.50
7,004.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 1S: Existing Conditions
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.07
0.06
0.05
0.04
0.03
0.02
0.01
0
Toronto 5-Year
Duration=21 min,
Inten=73.3 mm/hr
Runoff Area=7,004.0 m²
Runoff Volume=89.9 m³
Runoff Depth=13 mm
Tc=10.0 min
C=0.50
0.0713 m³/s
Toronto 5-Year Duration=21 min, Inten=73.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 24HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 3S: Proposed Site North
Runoff = 0.0211 m³/s @ 0.17 hrs, Volume= 26.5 m³, Depth= 20 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 5-Year Duration=21 min, Inten=73.3 mm/hr
Area (m²) C Description
247.0 0.25 Park1,078.0 0.90 At-grade
1,325.0 0.78 Weighted Average1,325.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 3S: Proposed Site North
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.022
0.02
0.018
0.016
0.014
0.012
0.01
0.008
0.006
0.004
0.002
0
Toronto 5-Year
Duration=21 min,
Inten=73.3 mm/hr
Runoff Area=1,325.0 m²
Runoff Volume=26.5 m³
Runoff Depth=20 mm
Tc=10.0 min
C=0.78
0.0211 m³/s
Toronto 5-Year Duration=21 min, Inten=73.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 25HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 4S: Lane Widening
Runoff = 0.0008 m³/s @ 0.17 hrs, Volume= 1.0 m³, Depth= 23 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 5-Year Duration=21 min, Inten=73.3 mm/hr
Area (m²) C Description
42.0 0.90 Lane Widening
42.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 4S: Lane Widening
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.001
0.001
0.001
0.000
0.000
0.000
0.000
0
0
Toronto 5-Year
Duration=21 min,
Inten=73.3 mm/hr
Runoff Area=42.0 m²
Runoff Volume=1.0 m³
Runoff Depth=23 mm
Tc=10.0 min
C=0.90
0.0008 m³/s
Toronto 5-Year Duration=21 min, Inten=73.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 26HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 10S: Proposed Site
Runoff = 0.0185 m³/s @ 0.17 hrs, Volume= 23.3 m³, Depth= 23 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 5-Year Duration=21 min, Inten=73.3 mm/hr
Area (m²) C Description
9.0 0.25 Tree Boxes1,009.0 0.90 At-Grade
1,018.0 0.89 Weighted Average1,018.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 10S: Proposed Site
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.02
0.018
0.016
0.014
0.012
0.01
0.008
0.006
0.004
0.002
0
Toronto 5-Year
Duration=21 min,
Inten=73.3 mm/hr
Runoff Area=1,018.0 m²
Runoff Volume=23.3 m³
Runoff Depth=23 mm
Tc=10.0 min
C=0.89
0.0185 m³/s
Toronto 5-Year Duration=21 min, Inten=73.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 27HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 11S: Green Roof North Buildings
Runoff = 0.0122 m³/s @ 0.17 hrs, Volume= 15.4 m³, Depth= 13 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 5-Year Duration=21 min, Inten=73.3 mm/hr
Area (m²) C Description
1,201.0 0.50 Green Roof W
1,201.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 11S: Green Roof North Buildings
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.0130.0120.011
0.010.0090.0080.0070.0060.0050.0040.0030.0020.001
0
Toronto 5-Year
Duration=21 min,
Inten=73.3 mm/hr
Runoff Area=1,201.0 m²
Runoff Volume=15.4 m³
Runoff Depth=13 mm
Tc=10.0 min
C=0.50
0.0122 m³/s
Toronto 5-Year Duration=21 min, Inten=73.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 28HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 12S: Impervious Roof Area
Runoff = 0.0236 m³/s @ 0.17 hrs, Volume= 29.8 m³, Depth= 23 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 5-Year Duration=21 min, Inten=73.3 mm/hr
Area (m²) C Description
1,289.0 0.90 Impervious Roof W
1,289.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 12S: Impervious Roof Area
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.0260.0240.022
0.020.018
0.0160.014
0.0120.01
0.008
0.0060.004
0.0020
Toronto 5-Year
Duration=21 min,
Inten=73.3 mm/hr
Runoff Area=1,289.0 m²
Runoff Volume=29.8 m³
Runoff Depth=23 mm
Tc=10.0 min
C=0.90
0.0236 m³/s
Toronto 5-Year Duration=21 min, Inten=73.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 29HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 13S: Lane Widening
Runoff = 0.0006 m³/s @ 0.17 hrs, Volume= 0.7 m³, Depth= 23 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 5-Year Duration=21 min, Inten=73.3 mm/hr
Area (m²) C Description
31.0 0.90 Lane Widening
31.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 13S: Lane Widening
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.001
0.001
0.001
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0
0
0
Toronto 5-Year
Duration=21 min,
Inten=73.3 mm/hr
Runoff Area=31.0 m²
Runoff Volume=0.7 m³
Runoff Depth=23 mm
Tc=10.0 min
C=0.90
0.0006 m³/s
Toronto 5-Year Duration=21 min, Inten=73.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 30HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 15S: Green Roof
Runoff = 0.0052 m³/s @ 0.17 hrs, Volume= 6.6 m³, Depth= 13 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 5-Year Duration=21 min, Inten=73.3 mm/hr
Area (m²) C Description
515.0 0.50 Green Roof
515.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 15S: Green Roof
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.005
0.005
0.004
0.004
0.003
0.003
0.002
0.002
0.001
0.001
0.000
0
Toronto 5-Year
Duration=21 min,
Inten=73.3 mm/hr
Runoff Area=515.0 m²
Runoff Volume=6.6 m³
Runoff Depth=13 mm
Tc=10.0 min
C=0.50
0.0052 m³/s
Toronto 5-Year Duration=21 min, Inten=73.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 31HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 16S: Impervious Roof Area
Runoff = 0.0291 m³/s @ 0.17 hrs, Volume= 36.6 m³, Depth= 23 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 5-Year Duration=21 min, Inten=73.3 mm/hr
Area (m²) C Description
1,585.0 0.90 Impervious Roof
1,585.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 16S: Impervious Roof Area
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.03
0.025
0.02
0.015
0.01
0.005
0
Toronto 5-Year
Duration=21 min,
Inten=73.3 mm/hr
Runoff Area=1,585.0 m²
Runoff Volume=36.6 m³
Runoff Depth=23 mm
Tc=10.0 min
C=0.90
0.0291 m³/s
Toronto 5-Year Duration=21 min, Inten=73.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 32HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Pond 6P: Stormwater Cistern
Inflow Area = 3,815.0 m², 0.00% Impervious, Inflow Depth = 19 mm for 5-Year eventInflow = 0.0569 m³/s @ 0.17 hrs, Volume= 71.7 m³Outflow = 0.0224 m³/s @ 0.45 hrs, Volume= 61.7 m³, Atten= 61%, Lag= 16.9 minPrimary = 0.0224 m³/s @ 0.45 hrs, Volume= 61.7 m³
Routing by Stor-Ind method, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsPeak Elev= 0.865 m @ 0.45 hrs Surf.Area= 58.7 m² Storage= 50.8 m³
Plug-Flow detention time= 27.7 min calculated for 61.7 m³ (86% of inflow)Center-of-Mass det. time= 26.0 min ( 41.5 - 15.5 )
Volume Invert Avail.Storage Storage Description
#1 0.000 m 176.1 m³ 10.00 mW x 5.87 mL x 3.00 mH Prismatoid
Device Routing Invert Outlet Devices
#1 Primary 0.168 m 100 mm Vert. Orifice/Grate C= 0.800
Primary OutFlow Max=0.0224 m³/s @ 0.45 hrs HW=0.864 m (Free Discharge)1=Orifice/Grate (Orifice Controls 0.0224 m³/s @ 2.85 m/s)
Pond 6P: Stormwater Cistern
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.06
0.0550.05
0.045
0.040.035
0.03
0.0250.02
0.0150.01
0.0050
Inflow Area=3,815.0 m²
Peak Elev=0.865 m
Storage=50.8 m³
0.0569 m³/s
0.0224 m³/s
Toronto 5-Year Duration=21 min, Inten=73.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 33HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Pond 17P: Stormwater Cistern
Inflow Area = 3,118.0 m², 0.00% Impervious, Inflow Depth = 21 mm for 5-Year eventInflow = 0.0528 m³/s @ 0.17 hrs, Volume= 66.5 m³Outflow = 0.0213 m³/s @ 0.45 hrs, Volume= 55.5 m³, Atten= 60%, Lag= 16.8 minPrimary = 0.0213 m³/s @ 0.45 hrs, Volume= 55.5 m³
Routing by Stor-Ind method, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsPeak Elev= 0.824 m @ 0.45 hrs Surf.Area= 57.2 m² Storage= 47.1 m³
Plug-Flow detention time= 26.7 min calculated for 55.4 m³ (83% of inflow)Center-of-Mass det. time= 25.2 min ( 40.7 - 15.5 )
Volume Invert Avail.Storage Storage Description
#1 0.000 m 171.6 m³ 10.00 mW x 5.72 mL x 3.00 mH Prismatoid
Device Routing Invert Outlet Devices
#1 Primary 0.190 m 100 mm Vert. Orifice/Grate C= 0.800
Primary OutFlow Max=0.0213 m³/s @ 0.45 hrs HW=0.824 m (Free Discharge)1=Orifice/Grate (Orifice Controls 0.0213 m³/s @ 2.71 m/s)
Pond 17P: Stormwater Cistern
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.055
0.05
0.045
0.04
0.035
0.03
0.025
0.02
0.015
0.01
0.005
0
Inflow Area=3,118.0 m²
Peak Elev=0.824 m
Storage=47.1 m³
0.0528 m³/s
0.0213 m³/s
Toronto 5-Year Duration=21 min, Inten=73.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 34HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Link 2L: Outflow
Inflow Area = 7,004.0 m², 0.00% Impervious, Inflow Depth = 13 mm for 5-Year eventInflow = 0.0713 m³/s @ 0.17 hrs, Volume= 89.9 m³Primary = 0.0713 m³/s @ 0.17 hrs, Volume= 89.9 m³, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 0.00-4.00 hrs, dt= 0.01 hrs
Link 2L: Outflow
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.07
0.06
0.05
0.04
0.03
0.02
0.01
0
Inflow Area=7,004.0 m²
0.0713 m³/s0.0713 m³/s
Toronto 5-Year Duration=21 min, Inten=73.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 35HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Link 7L: Total Outflow
Inflow Area = 3,857.0 m², 0.00% Impervious, Inflow Depth > 16 mm for 5-Year eventInflow = 0.0227 m³/s @ 0.44 hrs, Volume= 62.6 m³Primary = 0.0227 m³/s @ 0.44 hrs, Volume= 62.6 m³, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 0.00-4.00 hrs, dt= 0.01 hrs
Link 7L: Total Outflow
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.0240.022
0.020.0180.016
0.0140.012
0.01
0.0080.0060.004
0.0020
Inflow Area=3,857.0 m²
0.0227 m³/s0.0227 m³/s
Toronto 5-Year Duration=21 min, Inten=73.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 36HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Link 9L: Total North Uncontrolled Flow
Inflow Area = 42.0 m², 0.00% Impervious, Inflow Depth = 23 mm for 5-Year eventInflow = 0.0008 m³/s @ 0.17 hrs, Volume= 1.0 m³Primary = 0.0008 m³/s @ 0.17 hrs, Volume= 1.0 m³, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 0.00-4.00 hrs, dt= 0.01 hrs
Link 9L: Total North Uncontrolled Flow
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.001
0.001
0.001
0.000
0.000
0.000
0.000
0
0
Inflow Area=42.0 m²
0.0008 m³/s0.0008 m³/s
Toronto 5-Year Duration=21 min, Inten=73.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 37HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Link 18L: Total Outflow
Inflow Area = 3,149.0 m², 0.00% Impervious, Inflow Depth > 18 mm for 5-Year eventInflow = 0.0215 m³/s @ 0.44 hrs, Volume= 56.3 m³Primary = 0.0215 m³/s @ 0.44 hrs, Volume= 56.3 m³, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 0.00-4.00 hrs, dt= 0.01 hrs
Link 18L: Total Outflow
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.024
0.022
0.02
0.018
0.016
0.014
0.012
0.01
0.008
0.006
0.004
0.002
0
Inflow Area=3,149.0 m²
0.0215 m³/s0.0215 m³/s
Toronto 5-Year Duration=21 min, Inten=73.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 38HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Link 19L: Total South Uncontrolled Flow
Inflow Area = 31.0 m², 0.00% Impervious, Inflow Depth = 23 mm for 5-Year eventInflow = 0.0006 m³/s @ 0.17 hrs, Volume= 0.7 m³Primary = 0.0006 m³/s @ 0.17 hrs, Volume= 0.7 m³, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 0.00-4.00 hrs, dt= 0.01 hrs
Link 19L: Total South Uncontrolled Flow
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.001
0.0010.0010.0000.000
0.0000.0000.000
0.0000.000
0
00
Inflow Area=31.0 m²
0.0006 m³/s0.0006 m³/s
Toronto 5-Year Duration=21 min, Inten=73.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 39HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Link 20L: Total Site Outflow
Inflow Area = 7,006.0 m², 0.00% Impervious, Inflow Depth > 17 mm for 5-Year eventInflow = 0.0442 m³/s @ 0.44 hrs, Volume= 118.9 m³Primary = 0.0442 m³/s @ 0.44 hrs, Volume= 118.9 m³, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 0.00-4.00 hrs, dt= 0.01 hrs
Link 20L: Total Site Outflow
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.045
0.04
0.035
0.03
0.025
0.02
0.015
0.01
0.005
0
Inflow Area=7,006.0 m²
0.0442 m³/s0.0442 m³/s
Toronto 10-Year Duration=21 min, Inten=89.6 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 40HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Time span=0.00-4.00 hrs, dt=0.01 hrs, 401 pointsRunoff by Rational method, Rise/Fall=1.0/1.0 xTc
Reach routing by Stor-Ind+Trans method - Pond routing by Stor-Ind method
Runoff Area=7,004.0 m² 0.00% Impervious Runoff Depth=16 mmSubcatchment 1S: Existing Conditions Tc=10.0 min C=0.50 Runoff=0.0872 m³/s 109.9 m³
Runoff Area=1,325.0 m² 0.00% Impervious Runoff Depth=24 mmSubcatchment 3S: Proposed Site North Tc=10.0 min C=0.78 Runoff=0.0257 m³/s 32.4 m³
Runoff Area=42.0 m² 0.00% Impervious Runoff Depth=28 mmSubcatchment 4S: Lane Widening Tc=10.0 min C=0.90 Runoff=0.0009 m³/s 1.2 m³
Runoff Area=1,018.0 m² 0.00% Impervious Runoff Depth=28 mmSubcatchment 10S: Proposed Site Tc=10.0 min C=0.89 Runoff=0.0226 m³/s 28.4 m³
Runoff Area=1,201.0 m² 0.00% Impervious Runoff Depth=16 mmSubcatchment 11S: Green Roof North Tc=10.0 min C=0.50 Runoff=0.0150 m³/s 18.8 m³
Runoff Area=1,289.0 m² 0.00% Impervious Runoff Depth=28 mmSubcatchment 12S: Impervious Roof Tc=10.0 min C=0.90 Runoff=0.0289 m³/s 36.4 m³
Runoff Area=31.0 m² 0.00% Impervious Runoff Depth=28 mmSubcatchment 13S: Lane Widening Tc=10.0 min C=0.90 Runoff=0.0007 m³/s 0.9 m³
Runoff Area=515.0 m² 0.00% Impervious Runoff Depth=16 mmSubcatchment 15S: Green Roof Tc=10.0 min C=0.50 Runoff=0.0064 m³/s 8.1 m³
Runoff Area=1,585.0 m² 0.00% Impervious Runoff Depth=28 mmSubcatchment 16S: Impervious Roof Tc=10.0 min C=0.90 Runoff=0.0355 m³/s 44.8 m³
Peak Elev=1.069 m Storage=62.8 m³ Inflow=0.0696 m³/s 87.7 m³Pond 6P: Stormwater Cistern Outflow=0.0257 m³/s 77.6 m³
Peak Elev=1.015 m Storage=58.1 m³ Inflow=0.0645 m³/s 81.3 m³Pond 17P: Stormwater Cistern Outflow=0.0245 m³/s 70.3 m³
Inflow=0.0872 m³/s 109.9 m³Link 2L: Outflow Primary=0.0872 m³/s 109.9 m³
Inflow=0.0261 m³/s 78.8 m³Link 7L: Total Outflow Primary=0.0261 m³/s 78.8 m³
Inflow=0.0009 m³/s 1.2 m³Link 9L: Total North Uncontrolled Flow Primary=0.0009 m³/s 1.2 m³
Inflow=0.0248 m³/s 71.2 m³Link 18L: Total Outflow Primary=0.0248 m³/s 71.2 m³
Inflow=0.0007 m³/s 0.9 m³Link 19L: Total South Uncontrolled Flow Primary=0.0007 m³/s 0.9 m³
Toronto 10-Year Duration=21 min, Inten=89.6 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 41HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Inflow=0.0508 m³/s 149.9 m³Link 20L: Total Site Outflow Primary=0.0508 m³/s 149.9 m³
Total Runoff Area = 14,010.0 m² Runoff Volume = 280.8 m³ Average Runoff Depth = 20 mm100.00% Pervious = 14,010.0 m² 0.00% Impervious = 0.0 m²
Toronto 10-Year Duration=21 min, Inten=89.6 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 42HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 1S: Existing Conditions
Runoff = 0.0872 m³/s @ 0.17 hrs, Volume= 109.9 m³, Depth= 16 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 10-Year Duration=21 min, Inten=89.6 mm/hr
Area (m²) C Description
7,004.0 0.50
7,004.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 1S: Existing Conditions
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.09
0.08
0.07
0.06
0.05
0.04
0.03
0.02
0.01
0
Toronto 10-Year
Duration=21 min,
Inten=89.6 mm/hr
Runoff Area=7,004.0 m²
Runoff Volume=109.9 m³
Runoff Depth=16 mm
Tc=10.0 min
C=0.50
0.0872 m³/s
Toronto 10-Year Duration=21 min, Inten=89.6 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 43HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 3S: Proposed Site North
Runoff = 0.0257 m³/s @ 0.17 hrs, Volume= 32.4 m³, Depth= 24 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 10-Year Duration=21 min, Inten=89.6 mm/hr
Area (m²) C Description
247.0 0.25 Park1,078.0 0.90 At-grade
1,325.0 0.78 Weighted Average1,325.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 3S: Proposed Site North
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.0280.0260.0240.022
0.020.0180.0160.0140.012
0.010.0080.0060.0040.002
0
Toronto 10-Year
Duration=21 min,
Inten=89.6 mm/hr
Runoff Area=1,325.0 m²
Runoff Volume=32.4 m³
Runoff Depth=24 mm
Tc=10.0 min
C=0.78
0.0257 m³/s
Toronto 10-Year Duration=21 min, Inten=89.6 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 44HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 4S: Lane Widening
Runoff = 0.0009 m³/s @ 0.17 hrs, Volume= 1.2 m³, Depth= 28 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 10-Year Duration=21 min, Inten=89.6 mm/hr
Area (m²) C Description
42.0 0.90 Lane Widening
42.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 4S: Lane Widening
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.001
0.001
0.001
0.001
0.001
0.000
0.000
0.000
0.000
0
0
Toronto 10-Year
Duration=21 min,
Inten=89.6 mm/hr
Runoff Area=42.0 m²
Runoff Volume=1.2 m³
Runoff Depth=28 mm
Tc=10.0 min
C=0.90
0.0009 m³/s
Toronto 10-Year Duration=21 min, Inten=89.6 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 45HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 10S: Proposed Site
Runoff = 0.0226 m³/s @ 0.17 hrs, Volume= 28.4 m³, Depth= 28 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 10-Year Duration=21 min, Inten=89.6 mm/hr
Area (m²) C Description
9.0 0.25 Tree Boxes1,009.0 0.90 At-Grade
1,018.0 0.89 Weighted Average1,018.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 10S: Proposed Site
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.024
0.022
0.02
0.018
0.016
0.014
0.012
0.01
0.008
0.006
0.004
0.002
0
Toronto 10-Year
Duration=21 min,
Inten=89.6 mm/hr
Runoff Area=1,018.0 m²
Runoff Volume=28.4 m³
Runoff Depth=28 mm
Tc=10.0 min
C=0.89
0.0226 m³/s
Toronto 10-Year Duration=21 min, Inten=89.6 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 46HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 11S: Green Roof North Buildings
Runoff = 0.0150 m³/s @ 0.17 hrs, Volume= 18.8 m³, Depth= 16 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 10-Year Duration=21 min, Inten=89.6 mm/hr
Area (m²) C Description
1,201.0 0.50 Green Roof W
1,201.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 11S: Green Roof North Buildings
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.016
0.014
0.012
0.01
0.008
0.006
0.004
0.002
0
Toronto 10-Year
Duration=21 min,
Inten=89.6 mm/hr
Runoff Area=1,201.0 m²
Runoff Volume=18.8 m³
Runoff Depth=16 mm
Tc=10.0 min
C=0.50
0.0150 m³/s
Toronto 10-Year Duration=21 min, Inten=89.6 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 47HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 12S: Impervious Roof Area
Runoff = 0.0289 m³/s @ 0.17 hrs, Volume= 36.4 m³, Depth= 28 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 10-Year Duration=21 min, Inten=89.6 mm/hr
Area (m²) C Description
1,289.0 0.90 Impervious Roof W
1,289.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 12S: Impervious Roof Area
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.03
0.025
0.02
0.015
0.01
0.005
0
Toronto 10-Year
Duration=21 min,
Inten=89.6 mm/hr
Runoff Area=1,289.0 m²
Runoff Volume=36.4 m³
Runoff Depth=28 mm
Tc=10.0 min
C=0.90
0.0289 m³/s
Toronto 10-Year Duration=21 min, Inten=89.6 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 48HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 13S: Lane Widening
Runoff = 0.0007 m³/s @ 0.17 hrs, Volume= 0.9 m³, Depth= 28 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 10-Year Duration=21 min, Inten=89.6 mm/hr
Area (m²) C Description
31.0 0.90 Lane Widening
31.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 13S: Lane Widening
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.001
0.001
0.000
0.000
0.000
0.000
0
0
Toronto 10-Year
Duration=21 min,
Inten=89.6 mm/hr
Runoff Area=31.0 m²
Runoff Volume=0.9 m³
Runoff Depth=28 mm
Tc=10.0 min
C=0.90
0.0007 m³/s
Toronto 10-Year Duration=21 min, Inten=89.6 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 49HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 15S: Green Roof
Runoff = 0.0064 m³/s @ 0.17 hrs, Volume= 8.1 m³, Depth= 16 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 10-Year Duration=21 min, Inten=89.6 mm/hr
Area (m²) C Description
515.0 0.50 Green Roof
515.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 15S: Green Roof
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.0070.0070.0060.0050.0050.0040.0040.0030.0030.0020.0020.0010.0010.000
0
Toronto 10-Year
Duration=21 min,
Inten=89.6 mm/hr
Runoff Area=515.0 m²
Runoff Volume=8.1 m³
Runoff Depth=16 mm
Tc=10.0 min
C=0.50
0.0064 m³/s
Toronto 10-Year Duration=21 min, Inten=89.6 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 50HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 16S: Impervious Roof Area
Runoff = 0.0355 m³/s @ 0.17 hrs, Volume= 44.8 m³, Depth= 28 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 10-Year Duration=21 min, Inten=89.6 mm/hr
Area (m²) C Description
1,585.0 0.90 Impervious Roof
1,585.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 16S: Impervious Roof Area
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.035
0.03
0.025
0.02
0.015
0.01
0.005
0
Toronto 10-Year
Duration=21 min,
Inten=89.6 mm/hr
Runoff Area=1,585.0 m²
Runoff Volume=44.8 m³
Runoff Depth=28 mm
Tc=10.0 min
C=0.90
0.0355 m³/s
Toronto 10-Year Duration=21 min, Inten=89.6 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 51HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Pond 6P: Stormwater Cistern
Inflow Area = 3,815.0 m², 0.00% Impervious, Inflow Depth = 23 mm for 10-Year eventInflow = 0.0696 m³/s @ 0.17 hrs, Volume= 87.7 m³Outflow = 0.0257 m³/s @ 0.46 hrs, Volume= 77.6 m³, Atten= 63%, Lag= 17.1 minPrimary = 0.0257 m³/s @ 0.46 hrs, Volume= 77.6 m³
Routing by Stor-Ind method, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsPeak Elev= 1.069 m @ 0.46 hrs Surf.Area= 58.7 m² Storage= 62.8 m³
Plug-Flow detention time= 29.4 min calculated for 77.6 m³ (89% of inflow)Center-of-Mass det. time= 28.0 min ( 43.5 - 15.5 )
Volume Invert Avail.Storage Storage Description
#1 0.000 m 176.1 m³ 10.00 mW x 5.87 mL x 3.00 mH Prismatoid
Device Routing Invert Outlet Devices
#1 Primary 0.168 m 100 mm Vert. Orifice/Grate C= 0.800
Primary OutFlow Max=0.0257 m³/s @ 0.46 hrs HW=1.069 m (Free Discharge)1=Orifice/Grate (Orifice Controls 0.0257 m³/s @ 3.27 m/s)
Pond 6P: Stormwater Cistern
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.07
0.06
0.05
0.04
0.03
0.02
0.01
0
Inflow Area=3,815.0 m²
Peak Elev=1.069 m
Storage=62.8 m³
0.0696 m³/s
0.0257 m³/s
Toronto 10-Year Duration=21 min, Inten=89.6 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 52HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Pond 17P: Stormwater Cistern
Inflow Area = 3,118.0 m², 0.00% Impervious, Inflow Depth = 26 mm for 10-Year eventInflow = 0.0645 m³/s @ 0.17 hrs, Volume= 81.3 m³Outflow = 0.0245 m³/s @ 0.45 hrs, Volume= 70.3 m³, Atten= 62%, Lag= 17.0 minPrimary = 0.0245 m³/s @ 0.45 hrs, Volume= 70.3 m³
Routing by Stor-Ind method, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsPeak Elev= 1.015 m @ 0.45 hrs Surf.Area= 57.2 m² Storage= 58.1 m³
Plug-Flow detention time= 28.6 min calculated for 70.3 m³ (87% of inflow)Center-of-Mass det. time= 26.9 min ( 42.4 - 15.5 )
Volume Invert Avail.Storage Storage Description
#1 0.000 m 171.6 m³ 10.00 mW x 5.72 mL x 3.00 mH Prismatoid
Device Routing Invert Outlet Devices
#1 Primary 0.190 m 100 mm Vert. Orifice/Grate C= 0.800
Primary OutFlow Max=0.0245 m³/s @ 0.45 hrs HW=1.015 m (Free Discharge)1=Orifice/Grate (Orifice Controls 0.0245 m³/s @ 3.12 m/s)
Pond 17P: Stormwater Cistern
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.07
0.06
0.05
0.04
0.03
0.02
0.01
0
Inflow Area=3,118.0 m²
Peak Elev=1.015 m
Storage=58.1 m³
0.0645 m³/s
0.0245 m³/s
Toronto 10-Year Duration=21 min, Inten=89.6 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 53HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Link 2L: Outflow
Inflow Area = 7,004.0 m², 0.00% Impervious, Inflow Depth = 16 mm for 10-Year eventInflow = 0.0872 m³/s @ 0.17 hrs, Volume= 109.9 m³Primary = 0.0872 m³/s @ 0.17 hrs, Volume= 109.9 m³, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 0.00-4.00 hrs, dt= 0.01 hrs
Link 2L: Outflow
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.09
0.08
0.07
0.06
0.05
0.04
0.03
0.02
0.01
0
Inflow Area=7,004.0 m²
0.0872 m³/s0.0872 m³/s
Toronto 10-Year Duration=21 min, Inten=89.6 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 54HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Link 7L: Total Outflow
Inflow Area = 3,857.0 m², 0.00% Impervious, Inflow Depth > 20 mm for 10-Year eventInflow = 0.0261 m³/s @ 0.44 hrs, Volume= 78.8 m³Primary = 0.0261 m³/s @ 0.44 hrs, Volume= 78.8 m³, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 0.00-4.00 hrs, dt= 0.01 hrs
Link 7L: Total Outflow
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.025
0.02
0.015
0.01
0.005
0
Inflow Area=3,857.0 m²
0.0261 m³/s0.0261 m³/s
Toronto 10-Year Duration=21 min, Inten=89.6 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 55HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Link 9L: Total North Uncontrolled Flow
Inflow Area = 42.0 m², 0.00% Impervious, Inflow Depth = 28 mm for 10-Year eventInflow = 0.0009 m³/s @ 0.17 hrs, Volume= 1.2 m³Primary = 0.0009 m³/s @ 0.17 hrs, Volume= 1.2 m³, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 0.00-4.00 hrs, dt= 0.01 hrs
Link 9L: Total North Uncontrolled Flow
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.001
0.001
0.001
0.001
0.001
0.000
0.000
0.000
0.000
0
0
Inflow Area=42.0 m²
0.0009 m³/s0.0009 m³/s
Toronto 10-Year Duration=21 min, Inten=89.6 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 56HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Link 18L: Total Outflow
Inflow Area = 3,149.0 m², 0.00% Impervious, Inflow Depth > 23 mm for 10-Year eventInflow = 0.0248 m³/s @ 0.44 hrs, Volume= 71.2 m³Primary = 0.0248 m³/s @ 0.44 hrs, Volume= 71.2 m³, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 0.00-4.00 hrs, dt= 0.01 hrs
Link 18L: Total Outflow
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.025
0.02
0.015
0.01
0.005
0
Inflow Area=3,149.0 m²
0.0248 m³/s0.0248 m³/s
Toronto 10-Year Duration=21 min, Inten=89.6 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 57HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Link 19L: Total South Uncontrolled Flow
Inflow Area = 31.0 m², 0.00% Impervious, Inflow Depth = 28 mm for 10-Year eventInflow = 0.0007 m³/s @ 0.17 hrs, Volume= 0.9 m³Primary = 0.0007 m³/s @ 0.17 hrs, Volume= 0.9 m³, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 0.00-4.00 hrs, dt= 0.01 hrs
Link 19L: Total South Uncontrolled Flow
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.001
0.001
0.000
0.000
0.000
0.000
0
0
Inflow Area=31.0 m²
0.0007 m³/s0.0007 m³/s
Toronto 10-Year Duration=21 min, Inten=89.6 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 58HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Link 20L: Total Site Outflow
Inflow Area = 7,006.0 m², 0.00% Impervious, Inflow Depth > 21 mm for 10-Year eventInflow = 0.0508 m³/s @ 0.44 hrs, Volume= 149.9 m³Primary = 0.0508 m³/s @ 0.44 hrs, Volume= 149.9 m³, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 0.00-4.00 hrs, dt= 0.01 hrs
Link 20L: Total Site Outflow
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.055
0.05
0.045
0.04
0.035
0.03
0.025
0.02
0.015
0.01
0.005
0
Inflow Area=7,006.0 m²
0.0508 m³/s0.0508 m³/s
Toronto 25-Year Duration=21 min, Inten=104.7 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 59HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Time span=0.00-4.00 hrs, dt=0.01 hrs, 401 pointsRunoff by Rational method, Rise/Fall=1.0/1.0 xTc
Reach routing by Stor-Ind+Trans method - Pond routing by Stor-Ind method
Runoff Area=7,004.0 m² 0.00% Impervious Runoff Depth=18 mmSubcatchment 1S: Existing Conditions Tc=10.0 min C=0.50 Runoff=0.1018 m³/s 128.3 m³
Runoff Area=1,325.0 m² 0.00% Impervious Runoff Depth=29 mmSubcatchment 3S: Proposed Site North Tc=10.0 min C=0.78 Runoff=0.0301 m³/s 37.9 m³
Runoff Area=42.0 m² 0.00% Impervious Runoff Depth=33 mmSubcatchment 4S: Lane Widening Tc=10.0 min C=0.90 Runoff=0.0011 m³/s 1.4 m³
Runoff Area=1,018.0 m² 0.00% Impervious Runoff Depth=33 mmSubcatchment 10S: Proposed Site Tc=10.0 min C=0.89 Runoff=0.0263 m³/s 33.2 m³
Runoff Area=1,201.0 m² 0.00% Impervious Runoff Depth=18 mmSubcatchment 11S: Green Roof North Tc=10.0 min C=0.50 Runoff=0.0175 m³/s 22.0 m³
Runoff Area=1,289.0 m² 0.00% Impervious Runoff Depth=33 mmSubcatchment 12S: Impervious Roof Tc=10.0 min C=0.90 Runoff=0.0337 m³/s 42.5 m³
Runoff Area=31.0 m² 0.00% Impervious Runoff Depth=33 mmSubcatchment 13S: Lane Widening Tc=10.0 min C=0.90 Runoff=0.0008 m³/s 1.0 m³
Runoff Area=515.0 m² 0.00% Impervious Runoff Depth=18 mmSubcatchment 15S: Green Roof Tc=10.0 min C=0.50 Runoff=0.0075 m³/s 9.4 m³
Runoff Area=1,585.0 m² 0.00% Impervious Runoff Depth=33 mmSubcatchment 16S: Impervious Roof Tc=10.0 min C=0.90 Runoff=0.0415 m³/s 52.3 m³
Peak Elev=1.263 m Storage=74.2 m³ Inflow=0.0813 m³/s 102.4 m³Pond 6P: Stormwater Cistern Outflow=0.0285 m³/s 92.3 m³
Peak Elev=1.197 m Storage=68.5 m³ Inflow=0.0753 m³/s 94.9 m³Pond 17P: Stormwater Cistern Outflow=0.0272 m³/s 83.9 m³
Inflow=0.1018 m³/s 128.3 m³Link 2L: Outflow Primary=0.1018 m³/s 128.3 m³
Inflow=0.0289 m³/s 93.7 m³Link 7L: Total Outflow Primary=0.0289 m³/s 93.7 m³
Inflow=0.0011 m³/s 1.4 m³Link 9L: Total North Uncontrolled Flow Primary=0.0011 m³/s 1.4 m³
Inflow=0.0275 m³/s 85.0 m³Link 18L: Total Outflow Primary=0.0275 m³/s 85.0 m³
Inflow=0.0008 m³/s 1.0 m³Link 19L: Total South Uncontrolled Flow Primary=0.0008 m³/s 1.0 m³
Toronto 25-Year Duration=21 min, Inten=104.7 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 60HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Inflow=0.0564 m³/s 178.6 m³Link 20L: Total Site Outflow Primary=0.0564 m³/s 178.6 m³
Total Runoff Area = 14,010.0 m² Runoff Volume = 328.0 m³ Average Runoff Depth = 23 mm100.00% Pervious = 14,010.0 m² 0.00% Impervious = 0.0 m²
Toronto 25-Year Duration=21 min, Inten=104.7 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 61HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 1S: Existing Conditions
Runoff = 0.1018 m³/s @ 0.17 hrs, Volume= 128.3 m³, Depth= 18 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 25-Year Duration=21 min, Inten=104.7 mm/hr
Area (m²) C Description
7,004.0 0.50
7,004.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 1S: Existing Conditions
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.11
0.1
0.09
0.08
0.07
0.06
0.05
0.04
0.03
0.02
0.01
0
Toronto 25-Year
Duration=21 min,
Inten=104.7 mm/hr
Runoff Area=7,004.0 m²
Runoff Volume=128.3 m³
Runoff Depth=18 mm
Tc=10.0 min
C=0.50
0.1018 m³/s
Toronto 25-Year Duration=21 min, Inten=104.7 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 62HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 3S: Proposed Site North
Runoff = 0.0301 m³/s @ 0.17 hrs, Volume= 37.9 m³, Depth= 29 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 25-Year Duration=21 min, Inten=104.7 mm/hr
Area (m²) C Description
247.0 0.25 Park1,078.0 0.90 At-grade
1,325.0 0.78 Weighted Average1,325.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 3S: Proposed Site North
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.03
0.025
0.02
0.015
0.01
0.005
0
Toronto 25-Year
Duration=21 min,
Inten=104.7 mm/hr
Runoff Area=1,325.0 m²
Runoff Volume=37.9 m³
Runoff Depth=29 mm
Tc=10.0 min
C=0.78
0.0301 m³/s
Toronto 25-Year Duration=21 min, Inten=104.7 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 63HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 4S: Lane Widening
Runoff = 0.0011 m³/s @ 0.17 hrs, Volume= 1.4 m³, Depth= 33 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 25-Year Duration=21 min, Inten=104.7 mm/hr
Area (m²) C Description
42.0 0.90 Lane Widening
42.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 4S: Lane Widening
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.001
0.001
0.001
0.001
0.001
0.001
0.001
0.000
0.000
0.000
0.000
0
0
Toronto 25-Year
Duration=21 min,
Inten=104.7 mm/hr
Runoff Area=42.0 m²
Runoff Volume=1.4 m³
Runoff Depth=33 mm
Tc=10.0 min
C=0.90
0.0011 m³/s
Toronto 25-Year Duration=21 min, Inten=104.7 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 64HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 10S: Proposed Site
Runoff = 0.0263 m³/s @ 0.17 hrs, Volume= 33.2 m³, Depth= 33 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 25-Year Duration=21 min, Inten=104.7 mm/hr
Area (m²) C Description
9.0 0.25 Tree Boxes1,009.0 0.90 At-Grade
1,018.0 0.89 Weighted Average1,018.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 10S: Proposed Site
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.025
0.02
0.015
0.01
0.005
0
Toronto 25-Year
Duration=21 min,
Inten=104.7 mm/hr
Runoff Area=1,018.0 m²
Runoff Volume=33.2 m³
Runoff Depth=33 mm
Tc=10.0 min
C=0.89
0.0263 m³/s
Toronto 25-Year Duration=21 min, Inten=104.7 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 65HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 11S: Green Roof North Buildings
Runoff = 0.0175 m³/s @ 0.17 hrs, Volume= 22.0 m³, Depth= 18 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 25-Year Duration=21 min, Inten=104.7 mm/hr
Area (m²) C Description
1,201.0 0.50 Green Roof W
1,201.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 11S: Green Roof North Buildings
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.018
0.016
0.014
0.012
0.01
0.008
0.006
0.004
0.002
0
Toronto 25-Year
Duration=21 min,
Inten=104.7 mm/hr
Runoff Area=1,201.0 m²
Runoff Volume=22.0 m³
Runoff Depth=18 mm
Tc=10.0 min
C=0.50
0.0175 m³/s
Toronto 25-Year Duration=21 min, Inten=104.7 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 66HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 12S: Impervious Roof Area
Runoff = 0.0337 m³/s @ 0.17 hrs, Volume= 42.5 m³, Depth= 33 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 25-Year Duration=21 min, Inten=104.7 mm/hr
Area (m²) C Description
1,289.0 0.90 Impervious Roof W
1,289.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 12S: Impervious Roof Area
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.035
0.03
0.025
0.02
0.015
0.01
0.005
0
Toronto 25-Year
Duration=21 min,
Inten=104.7 mm/hr
Runoff Area=1,289.0 m²
Runoff Volume=42.5 m³
Runoff Depth=33 mm
Tc=10.0 min
C=0.90
0.0337 m³/s
Toronto 25-Year Duration=21 min, Inten=104.7 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 67HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 13S: Lane Widening
Runoff = 0.0008 m³/s @ 0.17 hrs, Volume= 1.0 m³, Depth= 33 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 25-Year Duration=21 min, Inten=104.7 mm/hr
Area (m²) C Description
31.0 0.90 Lane Widening
31.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 13S: Lane Widening
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.001
0.001
0.001
0.001
0.000
0.000
0.000
0.000
0
0
Toronto 25-Year
Duration=21 min,
Inten=104.7 mm/hr
Runoff Area=31.0 m²
Runoff Volume=1.0 m³
Runoff Depth=33 mm
Tc=10.0 min
C=0.90
0.0008 m³/s
Toronto 25-Year Duration=21 min, Inten=104.7 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 68HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 15S: Green Roof
Runoff = 0.0075 m³/s @ 0.17 hrs, Volume= 9.4 m³, Depth= 18 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 25-Year Duration=21 min, Inten=104.7 mm/hr
Area (m²) C Description
515.0 0.50 Green Roof
515.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 15S: Green Roof
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.008
0.007
0.006
0.005
0.004
0.003
0.002
0.001
0
Toronto 25-Year
Duration=21 min,
Inten=104.7 mm/hr
Runoff Area=515.0 m²
Runoff Volume=9.4 m³
Runoff Depth=18 mm
Tc=10.0 min
C=0.50
0.0075 m³/s
Toronto 25-Year Duration=21 min, Inten=104.7 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 69HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 16S: Impervious Roof Area
Runoff = 0.0415 m³/s @ 0.17 hrs, Volume= 52.3 m³, Depth= 33 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 25-Year Duration=21 min, Inten=104.7 mm/hr
Area (m²) C Description
1,585.0 0.90 Impervious Roof
1,585.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 16S: Impervious Roof Area
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.045
0.04
0.035
0.03
0.025
0.02
0.015
0.01
0.005
0
Toronto 25-Year
Duration=21 min,
Inten=104.7 mm/hr
Runoff Area=1,585.0 m²
Runoff Volume=52.3 m³
Runoff Depth=33 mm
Tc=10.0 min
C=0.90
0.0415 m³/s
Toronto 25-Year Duration=21 min, Inten=104.7 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 70HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Pond 6P: Stormwater Cistern
Inflow Area = 3,815.0 m², 0.00% Impervious, Inflow Depth = 27 mm for 25-Year eventInflow = 0.0813 m³/s @ 0.17 hrs, Volume= 102.4 m³Outflow = 0.0285 m³/s @ 0.46 hrs, Volume= 92.3 m³, Atten= 65%, Lag= 17.3 minPrimary = 0.0285 m³/s @ 0.46 hrs, Volume= 92.3 m³
Routing by Stor-Ind method, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsPeak Elev= 1.263 m @ 0.46 hrs Surf.Area= 58.7 m² Storage= 74.2 m³
Plug-Flow detention time= 31.0 min calculated for 92.3 m³ (90% of inflow)Center-of-Mass det. time= 29.8 min ( 45.3 - 15.5 )
Volume Invert Avail.Storage Storage Description
#1 0.000 m 176.1 m³ 10.00 mW x 5.87 mL x 3.00 mH Prismatoid
Device Routing Invert Outlet Devices
#1 Primary 0.168 m 100 mm Vert. Orifice/Grate C= 0.800
Primary OutFlow Max=0.0285 m³/s @ 0.46 hrs HW=1.263 m (Free Discharge)1=Orifice/Grate (Orifice Controls 0.0285 m³/s @ 3.62 m/s)
Pond 6P: Stormwater Cistern
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.09
0.08
0.07
0.06
0.05
0.04
0.03
0.02
0.01
0
Inflow Area=3,815.0 m²
Peak Elev=1.263 m
Storage=74.2 m³
0.0813 m³/s
0.0285 m³/s
Toronto 25-Year Duration=21 min, Inten=104.7 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 71HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Pond 17P: Stormwater Cistern
Inflow Area = 3,118.0 m², 0.00% Impervious, Inflow Depth = 30 mm for 25-Year eventInflow = 0.0753 m³/s @ 0.17 hrs, Volume= 94.9 m³Outflow = 0.0272 m³/s @ 0.46 hrs, Volume= 83.9 m³, Atten= 64%, Lag= 17.2 minPrimary = 0.0272 m³/s @ 0.46 hrs, Volume= 83.9 m³
Routing by Stor-Ind method, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsPeak Elev= 1.197 m @ 0.46 hrs Surf.Area= 57.2 m² Storage= 68.5 m³
Plug-Flow detention time= 30.0 min calculated for 83.9 m³ (88% of inflow)Center-of-Mass det. time= 28.6 min ( 44.1 - 15.5 )
Volume Invert Avail.Storage Storage Description
#1 0.000 m 171.6 m³ 10.00 mW x 5.72 mL x 3.00 mH Prismatoid
Device Routing Invert Outlet Devices
#1 Primary 0.190 m 100 mm Vert. Orifice/Grate C= 0.800
Primary OutFlow Max=0.0272 m³/s @ 0.46 hrs HW=1.196 m (Free Discharge)1=Orifice/Grate (Orifice Controls 0.0272 m³/s @ 3.47 m/s)
Pond 17P: Stormwater Cistern
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.08
0.07
0.06
0.05
0.04
0.03
0.02
0.01
0
Inflow Area=3,118.0 m²
Peak Elev=1.197 m
Storage=68.5 m³
0.0753 m³/s
0.0272 m³/s
Toronto 25-Year Duration=21 min, Inten=104.7 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 72HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Link 2L: Outflow
Inflow Area = 7,004.0 m², 0.00% Impervious, Inflow Depth = 18 mm for 25-Year eventInflow = 0.1018 m³/s @ 0.17 hrs, Volume= 128.3 m³Primary = 0.1018 m³/s @ 0.17 hrs, Volume= 128.3 m³, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 0.00-4.00 hrs, dt= 0.01 hrs
Link 2L: Outflow
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.11
0.1
0.09
0.08
0.07
0.06
0.05
0.04
0.03
0.02
0.01
0
Inflow Area=7,004.0 m²
0.1018 m³/s0.1018 m³/s
Toronto 25-Year Duration=21 min, Inten=104.7 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 73HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Link 7L: Total Outflow
Inflow Area = 3,857.0 m², 0.00% Impervious, Inflow Depth > 24 mm for 25-Year eventInflow = 0.0289 m³/s @ 0.44 hrs, Volume= 93.7 m³Primary = 0.0289 m³/s @ 0.44 hrs, Volume= 93.7 m³, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 0.00-4.00 hrs, dt= 0.01 hrs
Link 7L: Total Outflow
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.03
0.025
0.02
0.015
0.01
0.005
0
Inflow Area=3,857.0 m²
0.0289 m³/s0.0289 m³/s
Toronto 25-Year Duration=21 min, Inten=104.7 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 74HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Link 9L: Total North Uncontrolled Flow
Inflow Area = 42.0 m², 0.00% Impervious, Inflow Depth = 33 mm for 25-Year eventInflow = 0.0011 m³/s @ 0.17 hrs, Volume= 1.4 m³Primary = 0.0011 m³/s @ 0.17 hrs, Volume= 1.4 m³, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 0.00-4.00 hrs, dt= 0.01 hrs
Link 9L: Total North Uncontrolled Flow
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.001
0.001
0.0010.001
0.001
0.001
0.001
0.000
0.0000.000
0.000
0
0
Inflow Area=42.0 m²
0.0011 m³/s0.0011 m³/s
Toronto 25-Year Duration=21 min, Inten=104.7 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 75HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Link 18L: Total Outflow
Inflow Area = 3,149.0 m², 0.00% Impervious, Inflow Depth > 27 mm for 25-Year eventInflow = 0.0275 m³/s @ 0.44 hrs, Volume= 85.0 m³Primary = 0.0275 m³/s @ 0.44 hrs, Volume= 85.0 m³, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 0.00-4.00 hrs, dt= 0.01 hrs
Link 18L: Total Outflow
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.03
0.025
0.02
0.015
0.01
0.005
0
Inflow Area=3,149.0 m²
0.0275 m³/s0.0275 m³/s
Toronto 25-Year Duration=21 min, Inten=104.7 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 76HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Link 19L: Total South Uncontrolled Flow
Inflow Area = 31.0 m², 0.00% Impervious, Inflow Depth = 33 mm for 25-Year eventInflow = 0.0008 m³/s @ 0.17 hrs, Volume= 1.0 m³Primary = 0.0008 m³/s @ 0.17 hrs, Volume= 1.0 m³, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 0.00-4.00 hrs, dt= 0.01 hrs
Link 19L: Total South Uncontrolled Flow
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.001
0.001
0.001
0.001
0.000
0.000
0.000
0.000
0
0
Inflow Area=31.0 m²
0.0008 m³/s0.0008 m³/s
Toronto 25-Year Duration=21 min, Inten=104.7 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 77HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Link 20L: Total Site Outflow
Inflow Area = 7,006.0 m², 0.00% Impervious, Inflow Depth > 25 mm for 25-Year eventInflow = 0.0564 m³/s @ 0.44 hrs, Volume= 178.6 m³Primary = 0.0564 m³/s @ 0.44 hrs, Volume= 178.6 m³, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 0.00-4.00 hrs, dt= 0.01 hrs
Link 20L: Total Site Outflow
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.060.055
0.050.045
0.040.035
0.03
0.0250.02
0.0150.01
0.0050
Inflow Area=7,006.0 m²
0.0564 m³/s0.0564 m³/s
Toronto 50-Year Duration=21 min, Inten=123.9 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 78HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Time span=0.00-4.00 hrs, dt=0.01 hrs, 401 pointsRunoff by Rational method, Rise/Fall=1.0/1.0 xTc
Reach routing by Stor-Ind+Trans method - Pond routing by Stor-Ind method
Runoff Area=7,004.0 m² 0.00% Impervious Runoff Depth=22 mmSubcatchment 1S: Existing Conditions Tc=10.0 min C=0.50 Runoff=0.1205 m³/s 151.9 m³
Runoff Area=1,325.0 m² 0.00% Impervious Runoff Depth=34 mmSubcatchment 3S: Proposed Site North Tc=10.0 min C=0.78 Runoff=0.0356 m³/s 44.8 m³
Runoff Area=42.0 m² 0.00% Impervious Runoff Depth=39 mmSubcatchment 4S: Lane Widening Tc=10.0 min C=0.90 Runoff=0.0013 m³/s 1.6 m³
Runoff Area=1,018.0 m² 0.00% Impervious Runoff Depth=39 mmSubcatchment 10S: Proposed Site Tc=10.0 min C=0.89 Runoff=0.0312 m³/s 39.3 m³
Runoff Area=1,201.0 m² 0.00% Impervious Runoff Depth=22 mmSubcatchment 11S: Green Roof North Tc=10.0 min C=0.50 Runoff=0.0207 m³/s 26.0 m³
Runoff Area=1,289.0 m² 0.00% Impervious Runoff Depth=39 mmSubcatchment 12S: Impervious Roof Tc=10.0 min C=0.90 Runoff=0.0399 m³/s 50.3 m³
Runoff Area=31.0 m² 0.00% Impervious Runoff Depth=39 mmSubcatchment 13S: Lane Widening Tc=10.0 min C=0.90 Runoff=0.0010 m³/s 1.2 m³
Runoff Area=515.0 m² 0.00% Impervious Runoff Depth=22 mmSubcatchment 15S: Green Roof Tc=10.0 min C=0.50 Runoff=0.0089 m³/s 11.2 m³
Runoff Area=1,585.0 m² 0.00% Impervious Runoff Depth=39 mmSubcatchment 16S: Impervious Roof Tc=10.0 min C=0.90 Runoff=0.0491 m³/s 61.9 m³
Peak Elev=1.517 m Storage=89.0 m³ Inflow=0.0962 m³/s 121.2 m³Pond 6P: Stormwater Cistern Outflow=0.0317 m³/s 111.1 m³
Peak Elev=1.435 m Storage=82.1 m³ Inflow=0.0891 m³/s 112.3 m³Pond 17P: Stormwater Cistern Outflow=0.0304 m³/s 101.3 m³
Inflow=0.1205 m³/s 151.9 m³Link 2L: Outflow Primary=0.1205 m³/s 151.9 m³
Inflow=0.0322 m³/s 112.7 m³Link 7L: Total Outflow Primary=0.0322 m³/s 112.7 m³
Inflow=0.0013 m³/s 1.6 m³Link 9L: Total North Uncontrolled Flow Primary=0.0013 m³/s 1.6 m³
Inflow=0.0308 m³/s 102.6 m³Link 18L: Total Outflow Primary=0.0308 m³/s 102.6 m³
Inflow=0.0010 m³/s 1.2 m³Link 19L: Total South Uncontrolled Flow Primary=0.0010 m³/s 1.2 m³
Toronto 50-Year Duration=21 min, Inten=123.9 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 79HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Inflow=0.0630 m³/s 215.3 m³Link 20L: Total Site Outflow Primary=0.0630 m³/s 215.3 m³
Total Runoff Area = 14,010.0 m² Runoff Volume = 388.2 m³ Average Runoff Depth = 28 mm100.00% Pervious = 14,010.0 m² 0.00% Impervious = 0.0 m²
Toronto 50-Year Duration=21 min, Inten=123.9 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 80HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 1S: Existing Conditions
Runoff = 0.1205 m³/s @ 0.17 hrs, Volume= 151.9 m³, Depth= 22 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 50-Year Duration=21 min, Inten=123.9 mm/hr
Area (m²) C Description
7,004.0 0.50
7,004.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 1S: Existing Conditions
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.130.120.11
0.10.090.080.070.060.05
0.040.030.020.01
0
Toronto 50-Year
Duration=21 min,
Inten=123.9 mm/hr
Runoff Area=7,004.0 m²
Runoff Volume=151.9 m³
Runoff Depth=22 mm
Tc=10.0 min
C=0.50
0.1205 m³/s
Toronto 50-Year Duration=21 min, Inten=123.9 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 81HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 3S: Proposed Site North
Runoff = 0.0356 m³/s @ 0.17 hrs, Volume= 44.8 m³, Depth= 34 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 50-Year Duration=21 min, Inten=123.9 mm/hr
Area (m²) C Description
247.0 0.25 Park1,078.0 0.90 At-grade
1,325.0 0.78 Weighted Average1,325.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 3S: Proposed Site North
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.035
0.03
0.025
0.02
0.015
0.01
0.005
0
Toronto 50-Year
Duration=21 min,
Inten=123.9 mm/hr
Runoff Area=1,325.0 m²
Runoff Volume=44.8 m³
Runoff Depth=34 mm
Tc=10.0 min
C=0.78
0.0356 m³/s
Toronto 50-Year Duration=21 min, Inten=123.9 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 82HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 4S: Lane Widening
Runoff = 0.0013 m³/s @ 0.17 hrs, Volume= 1.6 m³, Depth= 39 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 50-Year Duration=21 min, Inten=123.9 mm/hr
Area (m²) C Description
42.0 0.90 Lane Widening
42.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 4S: Lane Widening
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.001
0.001
0.001
0.001
0.001
0.000
0.000
0
Toronto 50-Year
Duration=21 min,
Inten=123.9 mm/hr
Runoff Area=42.0 m²
Runoff Volume=1.6 m³
Runoff Depth=39 mm
Tc=10.0 min
C=0.90
0.0013 m³/s
Toronto 50-Year Duration=21 min, Inten=123.9 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 83HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 10S: Proposed Site
Runoff = 0.0312 m³/s @ 0.17 hrs, Volume= 39.3 m³, Depth= 39 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 50-Year Duration=21 min, Inten=123.9 mm/hr
Area (m²) C Description
9.0 0.25 Tree Boxes1,009.0 0.90 At-Grade
1,018.0 0.89 Weighted Average1,018.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 10S: Proposed Site
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.03
0.025
0.02
0.015
0.01
0.005
0
Toronto 50-Year
Duration=21 min,
Inten=123.9 mm/hr
Runoff Area=1,018.0 m²
Runoff Volume=39.3 m³
Runoff Depth=39 mm
Tc=10.0 min
C=0.89
0.0312 m³/s
Toronto 50-Year Duration=21 min, Inten=123.9 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 84HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 11S: Green Roof North Buildings
Runoff = 0.0207 m³/s @ 0.17 hrs, Volume= 26.0 m³, Depth= 22 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 50-Year Duration=21 min, Inten=123.9 mm/hr
Area (m²) C Description
1,201.0 0.50 Green Roof W
1,201.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 11S: Green Roof North Buildings
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.022
0.02
0.018
0.016
0.014
0.012
0.01
0.008
0.006
0.004
0.002
0
Toronto 50-Year
Duration=21 min,
Inten=123.9 mm/hr
Runoff Area=1,201.0 m²
Runoff Volume=26.0 m³
Runoff Depth=22 mm
Tc=10.0 min
C=0.50
0.0207 m³/s
Toronto 50-Year Duration=21 min, Inten=123.9 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 85HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 12S: Impervious Roof Area
Runoff = 0.0399 m³/s @ 0.17 hrs, Volume= 50.3 m³, Depth= 39 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 50-Year Duration=21 min, Inten=123.9 mm/hr
Area (m²) C Description
1,289.0 0.90 Impervious Roof W
1,289.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 12S: Impervious Roof Area
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.04
0.035
0.03
0.025
0.02
0.015
0.01
0.005
0
Toronto 50-Year
Duration=21 min,
Inten=123.9 mm/hr
Runoff Area=1,289.0 m²
Runoff Volume=50.3 m³
Runoff Depth=39 mm
Tc=10.0 min
C=0.90
0.0399 m³/s
Toronto 50-Year Duration=21 min, Inten=123.9 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 86HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 13S: Lane Widening
Runoff = 0.0010 m³/s @ 0.17 hrs, Volume= 1.2 m³, Depth= 39 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 50-Year Duration=21 min, Inten=123.9 mm/hr
Area (m²) C Description
31.0 0.90 Lane Widening
31.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 13S: Lane Widening
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.001
0.001
0.001
0.001
0.001
0.000
0.000
0.000
0.000
0
0
Toronto 50-Year
Duration=21 min,
Inten=123.9 mm/hr
Runoff Area=31.0 m²
Runoff Volume=1.2 m³
Runoff Depth=39 mm
Tc=10.0 min
C=0.90
0.0010 m³/s
Toronto 50-Year Duration=21 min, Inten=123.9 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 87HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 15S: Green Roof
Runoff = 0.0089 m³/s @ 0.17 hrs, Volume= 11.2 m³, Depth= 22 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 50-Year Duration=21 min, Inten=123.9 mm/hr
Area (m²) C Description
515.0 0.50 Green Roof
515.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 15S: Green Roof
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.009
0.008
0.007
0.006
0.005
0.004
0.003
0.002
0.001
0
Toronto 50-Year
Duration=21 min,
Inten=123.9 mm/hr
Runoff Area=515.0 m²
Runoff Volume=11.2 m³
Runoff Depth=22 mm
Tc=10.0 min
C=0.50
0.0089 m³/s
Toronto 50-Year Duration=21 min, Inten=123.9 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 88HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 16S: Impervious Roof Area
Runoff = 0.0491 m³/s @ 0.17 hrs, Volume= 61.9 m³, Depth= 39 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 50-Year Duration=21 min, Inten=123.9 mm/hr
Area (m²) C Description
1,585.0 0.90 Impervious Roof
1,585.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 16S: Impervious Roof Area
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.05
0.045
0.04
0.035
0.03
0.025
0.02
0.015
0.01
0.005
0
Toronto 50-Year
Duration=21 min,
Inten=123.9 mm/hr
Runoff Area=1,585.0 m²
Runoff Volume=61.9 m³
Runoff Depth=39 mm
Tc=10.0 min
C=0.90
0.0491 m³/s
Toronto 50-Year Duration=21 min, Inten=123.9 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 89HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Pond 6P: Stormwater Cistern
Inflow Area = 3,815.0 m², 0.00% Impervious, Inflow Depth = 32 mm for 50-Year eventInflow = 0.0962 m³/s @ 0.17 hrs, Volume= 121.2 m³Outflow = 0.0317 m³/s @ 0.46 hrs, Volume= 111.1 m³, Atten= 67%, Lag= 17.5 minPrimary = 0.0317 m³/s @ 0.46 hrs, Volume= 111.1 m³
Routing by Stor-Ind method, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsPeak Elev= 1.517 m @ 0.46 hrs Surf.Area= 58.7 m² Storage= 89.0 m³
Plug-Flow detention time= 33.1 min calculated for 111.1 m³ (92% of inflow)Center-of-Mass det. time= 32.0 min ( 47.5 - 15.5 )
Volume Invert Avail.Storage Storage Description
#1 0.000 m 176.1 m³ 10.00 mW x 5.87 mL x 3.00 mH Prismatoid
Device Routing Invert Outlet Devices
#1 Primary 0.168 m 100 mm Vert. Orifice/Grate C= 0.800
Primary OutFlow Max=0.0317 m³/s @ 0.46 hrs HW=1.517 m (Free Discharge)1=Orifice/Grate (Orifice Controls 0.0317 m³/s @ 4.04 m/s)
Pond 6P: Stormwater Cistern
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.1
0.09
0.08
0.07
0.06
0.05
0.04
0.03
0.02
0.01
0
Inflow Area=3,815.0 m²
Peak Elev=1.517 m
Storage=89.0 m³
0.0962 m³/s
0.0317 m³/s
Toronto 50-Year Duration=21 min, Inten=123.9 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 90HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Pond 17P: Stormwater Cistern
Inflow Area = 3,118.0 m², 0.00% Impervious, Inflow Depth = 36 mm for 50-Year eventInflow = 0.0891 m³/s @ 0.17 hrs, Volume= 112.3 m³Outflow = 0.0304 m³/s @ 0.46 hrs, Volume= 101.3 m³, Atten= 66%, Lag= 17.4 minPrimary = 0.0304 m³/s @ 0.46 hrs, Volume= 101.3 m³
Routing by Stor-Ind method, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsPeak Elev= 1.435 m @ 0.46 hrs Surf.Area= 57.2 m² Storage= 82.1 m³
Plug-Flow detention time= 31.5 min calculated for 101.1 m³ (90% of inflow)Center-of-Mass det. time= 30.7 min ( 46.2 - 15.5 )
Volume Invert Avail.Storage Storage Description
#1 0.000 m 171.6 m³ 10.00 mW x 5.72 mL x 3.00 mH Prismatoid
Device Routing Invert Outlet Devices
#1 Primary 0.190 m 100 mm Vert. Orifice/Grate C= 0.800
Primary OutFlow Max=0.0304 m³/s @ 0.46 hrs HW=1.434 m (Free Discharge)1=Orifice/Grate (Orifice Controls 0.0304 m³/s @ 3.87 m/s)
Pond 17P: Stormwater Cistern
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.09
0.08
0.07
0.06
0.05
0.04
0.03
0.02
0.01
0
Inflow Area=3,118.0 m²
Peak Elev=1.435 m
Storage=82.1 m³
0.0891 m³/s
0.0304 m³/s
Toronto 50-Year Duration=21 min, Inten=123.9 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 91HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Link 2L: Outflow
Inflow Area = 7,004.0 m², 0.00% Impervious, Inflow Depth = 22 mm for 50-Year eventInflow = 0.1205 m³/s @ 0.17 hrs, Volume= 151.9 m³Primary = 0.1205 m³/s @ 0.17 hrs, Volume= 151.9 m³, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 0.00-4.00 hrs, dt= 0.01 hrs
Link 2L: Outflow
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.130.120.11
0.10.090.080.070.060.050.040.030.020.01
0
Inflow Area=7,004.0 m²
0.1205 m³/s0.1205 m³/s
Toronto 50-Year Duration=21 min, Inten=123.9 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 92HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Link 7L: Total Outflow
Inflow Area = 3,857.0 m², 0.00% Impervious, Inflow Depth > 29 mm for 50-Year eventInflow = 0.0322 m³/s @ 0.44 hrs, Volume= 112.7 m³Primary = 0.0322 m³/s @ 0.44 hrs, Volume= 112.7 m³, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 0.00-4.00 hrs, dt= 0.01 hrs
Link 7L: Total Outflow
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.035
0.03
0.025
0.02
0.015
0.01
0.005
0
Inflow Area=3,857.0 m²
0.0322 m³/s0.0322 m³/s
Toronto 50-Year Duration=21 min, Inten=123.9 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 93HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Link 9L: Total North Uncontrolled Flow
Inflow Area = 42.0 m², 0.00% Impervious, Inflow Depth = 39 mm for 50-Year eventInflow = 0.0013 m³/s @ 0.17 hrs, Volume= 1.6 m³Primary = 0.0013 m³/s @ 0.17 hrs, Volume= 1.6 m³, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 0.00-4.00 hrs, dt= 0.01 hrs
Link 9L: Total North Uncontrolled Flow
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.001
0.001
0.001
0.001
0.001
0.000
0.000
0
Inflow Area=42.0 m²
0.0013 m³/s0.0013 m³/s
Toronto 50-Year Duration=21 min, Inten=123.9 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 94HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Link 18L: Total Outflow
Inflow Area = 3,149.0 m², 0.00% Impervious, Inflow Depth > 33 mm for 50-Year eventInflow = 0.0308 m³/s @ 0.45 hrs, Volume= 102.6 m³Primary = 0.0308 m³/s @ 0.45 hrs, Volume= 102.6 m³, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 0.00-4.00 hrs, dt= 0.01 hrs
Link 18L: Total Outflow
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.03
0.025
0.02
0.015
0.01
0.005
0
Inflow Area=3,149.0 m²
0.0308 m³/s0.0308 m³/s
Toronto 50-Year Duration=21 min, Inten=123.9 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 95HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Link 19L: Total South Uncontrolled Flow
Inflow Area = 31.0 m², 0.00% Impervious, Inflow Depth = 39 mm for 50-Year eventInflow = 0.0010 m³/s @ 0.17 hrs, Volume= 1.2 m³Primary = 0.0010 m³/s @ 0.17 hrs, Volume= 1.2 m³, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 0.00-4.00 hrs, dt= 0.01 hrs
Link 19L: Total South Uncontrolled Flow
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.001
0.001
0.001
0.001
0.001
0.000
0.000
0.000
0.000
0
0
Inflow Area=31.0 m²
0.0010 m³/s0.0010 m³/s
Toronto 50-Year Duration=21 min, Inten=123.9 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 96HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Link 20L: Total Site Outflow
Inflow Area = 7,006.0 m², 0.00% Impervious, Inflow Depth > 31 mm for 50-Year eventInflow = 0.0630 m³/s @ 0.45 hrs, Volume= 215.3 m³Primary = 0.0630 m³/s @ 0.45 hrs, Volume= 215.3 m³, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 0.00-4.00 hrs, dt= 0.01 hrs
Link 20L: Total Site Outflow
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.07
0.06
0.05
0.04
0.03
0.02
0.01
0
Inflow Area=7,006.0 m²
0.0630 m³/s0.0630 m³/s
Toronto 100-Year Duration=21 min, Inten=138.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 97HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Time span=0.00-4.00 hrs, dt=0.01 hrs, 401 pointsRunoff by Rational method, Rise/Fall=1.0/1.0 xTc
Reach routing by Stor-Ind+Trans method - Pond routing by Stor-Ind method
Runoff Area=7,004.0 m² 0.00% Impervious Runoff Depth=24 mmSubcatchment 1S: Existing Conditions Tc=10.0 min C=0.50 Runoff=0.1345 m³/s 169.5 m³
Runoff Area=1,325.0 m² 0.00% Impervious Runoff Depth=38 mmSubcatchment 3S: Proposed Site North Tc=10.0 min C=0.78 Runoff=0.0397 m³/s 50.0 m³
Runoff Area=42.0 m² 0.00% Impervious Runoff Depth=44 mmSubcatchment 4S: Lane Widening Tc=10.0 min C=0.90 Runoff=0.0015 m³/s 1.8 m³
Runoff Area=1,018.0 m² 0.00% Impervious Runoff Depth=43 mmSubcatchment 10S: Proposed Site Tc=10.0 min C=0.89 Runoff=0.0348 m³/s 43.8 m³
Runoff Area=1,201.0 m² 0.00% Impervious Runoff Depth=24 mmSubcatchment 11S: Green Roof North Tc=10.0 min C=0.50 Runoff=0.0231 m³/s 29.1 m³
Runoff Area=1,289.0 m² 0.00% Impervious Runoff Depth=44 mmSubcatchment 12S: Impervious Roof Tc=10.0 min C=0.90 Runoff=0.0446 m³/s 56.1 m³
Runoff Area=31.0 m² 0.00% Impervious Runoff Depth=44 mmSubcatchment 13S: Lane Widening Tc=10.0 min C=0.90 Runoff=0.0011 m³/s 1.4 m³
Runoff Area=515.0 m² 0.00% Impervious Runoff Depth=24 mmSubcatchment 15S: Green Roof Tc=10.0 min C=0.50 Runoff=0.0099 m³/s 12.5 m³
Runoff Area=1,585.0 m² 0.00% Impervious Runoff Depth=44 mmSubcatchment 16S: Impervious Roof Tc=10.0 min C=0.90 Runoff=0.0548 m³/s 69.0 m³
Peak Elev=1.710 m Storage=100.4 m³ Inflow=0.1073 m³/s 135.2 m³Pond 6P: Stormwater Cistern Outflow=0.0340 m³/s 125.1 m³
Peak Elev=1.615 m Storage=92.4 m³ Inflow=0.0995 m³/s 125.3 m³Pond 17P: Stormwater Cistern Outflow=0.0326 m³/s 114.3 m³
Inflow=0.1345 m³/s 169.5 m³Link 2L: Outflow Primary=0.1345 m³/s 169.5 m³
Inflow=0.0345 m³/s 126.9 m³Link 7L: Total Outflow Primary=0.0345 m³/s 126.9 m³
Inflow=0.0015 m³/s 1.8 m³Link 9L: Total North Uncontrolled Flow Primary=0.0015 m³/s 1.8 m³
Inflow=0.0330 m³/s 115.7 m³Link 18L: Total Outflow Primary=0.0330 m³/s 115.7 m³
Inflow=0.0011 m³/s 1.4 m³Link 19L: Total South Uncontrolled Flow Primary=0.0011 m³/s 1.4 m³
Toronto 100-Year Duration=21 min, Inten=138.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 98HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Inflow=0.0676 m³/s 242.6 m³Link 20L: Total Site Outflow Primary=0.0676 m³/s 242.6 m³
Total Runoff Area = 14,010.0 m² Runoff Volume = 433.2 m³ Average Runoff Depth = 31 mm100.00% Pervious = 14,010.0 m² 0.00% Impervious = 0.0 m²
Toronto 100-Year Duration=21 min, Inten=138.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 99HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 1S: Existing Conditions
Runoff = 0.1345 m³/s @ 0.17 hrs, Volume= 169.5 m³, Depth= 24 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 100-Year Duration=21 min, Inten=138.3 mm/hr
Area (m²) C Description
7,004.0 0.50
7,004.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 1S: Existing Conditions
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.14
0.12
0.1
0.08
0.06
0.04
0.02
0
Toronto 100-Year
Duration=21 min,
Inten=138.3 mm/hr
Runoff Area=7,004.0 m²
Runoff Volume=169.5 m³
Runoff Depth=24 mm
Tc=10.0 min
C=0.50
0.1345 m³/s
Toronto 100-Year Duration=21 min, Inten=138.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 100HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 3S: Proposed Site North
Runoff = 0.0397 m³/s @ 0.17 hrs, Volume= 50.0 m³, Depth= 38 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 100-Year Duration=21 min, Inten=138.3 mm/hr
Area (m²) C Description
247.0 0.25 Park1,078.0 0.90 At-grade
1,325.0 0.78 Weighted Average1,325.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 3S: Proposed Site North
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.04
0.035
0.03
0.025
0.02
0.015
0.01
0.005
0
Toronto 100-Year
Duration=21 min,
Inten=138.3 mm/hr
Runoff Area=1,325.0 m²
Runoff Volume=50.0 m³
Runoff Depth=38 mm
Tc=10.0 min
C=0.78
0.0397 m³/s
Toronto 100-Year Duration=21 min, Inten=138.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 101HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 4S: Lane Widening
Runoff = 0.0015 m³/s @ 0.17 hrs, Volume= 1.8 m³, Depth= 44 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 100-Year Duration=21 min, Inten=138.3 mm/hr
Area (m²) C Description
42.0 0.90 Lane Widening
42.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 4S: Lane Widening
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.002
0.001
0.001
0.001
0.001
0.001
0.000
0.000
0
Toronto 100-Year
Duration=21 min,
Inten=138.3 mm/hr
Runoff Area=42.0 m²
Runoff Volume=1.8 m³
Runoff Depth=44 mm
Tc=10.0 min
C=0.90
0.0015 m³/s
Toronto 100-Year Duration=21 min, Inten=138.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 102HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 10S: Proposed Site
Runoff = 0.0348 m³/s @ 0.17 hrs, Volume= 43.8 m³, Depth= 43 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 100-Year Duration=21 min, Inten=138.3 mm/hr
Area (m²) C Description
9.0 0.25 Tree Boxes1,009.0 0.90 At-Grade
1,018.0 0.89 Weighted Average1,018.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 10S: Proposed Site
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.035
0.03
0.025
0.02
0.015
0.01
0.005
0
Toronto 100-Year
Duration=21 min,
Inten=138.3 mm/hr
Runoff Area=1,018.0 m²
Runoff Volume=43.8 m³
Runoff Depth=43 mm
Tc=10.0 min
C=0.89
0.0348 m³/s
Toronto 100-Year Duration=21 min, Inten=138.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 103HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 11S: Green Roof North Buildings
Runoff = 0.0231 m³/s @ 0.17 hrs, Volume= 29.1 m³, Depth= 24 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 100-Year Duration=21 min, Inten=138.3 mm/hr
Area (m²) C Description
1,201.0 0.50 Green Roof W
1,201.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 11S: Green Roof North Buildings
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.024
0.022
0.02
0.018
0.0160.014
0.012
0.01
0.008
0.0060.004
0.002
0
Toronto 100-Year
Duration=21 min,
Inten=138.3 mm/hr
Runoff Area=1,201.0 m²
Runoff Volume=29.1 m³
Runoff Depth=24 mm
Tc=10.0 min
C=0.50
0.0231 m³/s
Toronto 100-Year Duration=21 min, Inten=138.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 104HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 12S: Impervious Roof Area
Runoff = 0.0446 m³/s @ 0.17 hrs, Volume= 56.1 m³, Depth= 44 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 100-Year Duration=21 min, Inten=138.3 mm/hr
Area (m²) C Description
1,289.0 0.90 Impervious Roof W
1,289.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 12S: Impervious Roof Area
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.045
0.04
0.035
0.03
0.025
0.02
0.015
0.01
0.005
0
Toronto 100-Year
Duration=21 min,
Inten=138.3 mm/hr
Runoff Area=1,289.0 m²
Runoff Volume=56.1 m³
Runoff Depth=44 mm
Tc=10.0 min
C=0.90
0.0446 m³/s
Toronto 100-Year Duration=21 min, Inten=138.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 105HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 13S: Lane Widening
Runoff = 0.0011 m³/s @ 0.17 hrs, Volume= 1.4 m³, Depth= 44 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 100-Year Duration=21 min, Inten=138.3 mm/hr
Area (m²) C Description
31.0 0.90 Lane Widening
31.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 13S: Lane Widening
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.001
0.001
0.001
0.001
0.001
0.001
0.001
0.000
0.000
0.000
0.000
0
0
Toronto 100-Year
Duration=21 min,
Inten=138.3 mm/hr
Runoff Area=31.0 m²
Runoff Volume=1.4 m³
Runoff Depth=44 mm
Tc=10.0 min
C=0.90
0.0011 m³/s
Toronto 100-Year Duration=21 min, Inten=138.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 106HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 15S: Green Roof
Runoff = 0.0099 m³/s @ 0.17 hrs, Volume= 12.5 m³, Depth= 24 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 100-Year Duration=21 min, Inten=138.3 mm/hr
Area (m²) C Description
515.0 0.50 Green Roof
515.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 15S: Green Roof
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.011
0.01
0.009
0.008
0.007
0.006
0.005
0.004
0.003
0.002
0.001
0
Toronto 100-Year
Duration=21 min,
Inten=138.3 mm/hr
Runoff Area=515.0 m²
Runoff Volume=12.5 m³
Runoff Depth=24 mm
Tc=10.0 min
C=0.50
0.0099 m³/s
Toronto 100-Year Duration=21 min, Inten=138.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 107HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Subcatchment 16S: Impervious Roof Area
Runoff = 0.0548 m³/s @ 0.17 hrs, Volume= 69.0 m³, Depth= 44 mm
Runoff by Rational method, Rise/Fall=1.0/1.0 xTc, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsToronto 100-Year Duration=21 min, Inten=138.3 mm/hr
Area (m²) C Description
1,585.0 0.90 Impervious Roof
1,585.0 100.00% Pervious Area
Tc Length Slope Velocity Capacity Description(min) (meters) (m/m) (m/sec) (m³/s)
10.0 Direct Entry,
Subcatchment 16S: Impervious Roof Area
Runoff
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.06
0.055
0.05
0.045
0.04
0.035
0.03
0.025
0.02
0.015
0.01
0.005
0
Toronto 100-Year
Duration=21 min,
Inten=138.3 mm/hr
Runoff Area=1,585.0 m²
Runoff Volume=69.0 m³
Runoff Depth=44 mm
Tc=10.0 min
C=0.90
0.0548 m³/s
Toronto 100-Year Duration=21 min, Inten=138.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 108HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Pond 6P: Stormwater Cistern
Inflow Area = 3,815.0 m², 0.00% Impervious, Inflow Depth = 35 mm for 100-Year eventInflow = 0.1073 m³/s @ 0.17 hrs, Volume= 135.2 m³Outflow = 0.0340 m³/s @ 0.46 hrs, Volume= 125.1 m³, Atten= 68%, Lag= 17.6 minPrimary = 0.0340 m³/s @ 0.46 hrs, Volume= 125.1 m³
Routing by Stor-Ind method, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsPeak Elev= 1.710 m @ 0.46 hrs Surf.Area= 58.7 m² Storage= 100.4 m³
Plug-Flow detention time= 34.3 min calculated for 124.8 m³ (92% of inflow)Center-of-Mass det. time= 33.7 min ( 49.2 - 15.5 )
Volume Invert Avail.Storage Storage Description
#1 0.000 m 176.1 m³ 10.00 mW x 5.87 mL x 3.00 mH Prismatoid
Device Routing Invert Outlet Devices
#1 Primary 0.168 m 100 mm Vert. Orifice/Grate C= 0.800
Primary OutFlow Max=0.0340 m³/s @ 0.46 hrs HW=1.709 m (Free Discharge)1=Orifice/Grate (Orifice Controls 0.0340 m³/s @ 4.33 m/s)
Pond 6P: Stormwater Cistern
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.12
0.11
0.1
0.09
0.08
0.07
0.06
0.05
0.04
0.03
0.02
0.01
0
Inflow Area=3,815.0 m²
Peak Elev=1.710 m
Storage=100.4 m³
0.1073 m³/s
0.0340 m³/s
Toronto 100-Year Duration=21 min, Inten=138.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 109HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Pond 17P: Stormwater Cistern
Inflow Area = 3,118.0 m², 0.00% Impervious, Inflow Depth = 40 mm for 100-Year eventInflow = 0.0995 m³/s @ 0.17 hrs, Volume= 125.3 m³Outflow = 0.0326 m³/s @ 0.46 hrs, Volume= 114.3 m³, Atten= 67%, Lag= 17.5 minPrimary = 0.0326 m³/s @ 0.46 hrs, Volume= 114.3 m³
Routing by Stor-Ind method, Time Span= 0.00-4.00 hrs, dt= 0.01 hrsPeak Elev= 1.615 m @ 0.46 hrs Surf.Area= 57.2 m² Storage= 92.4 m³
Plug-Flow detention time= 32.9 min calculated for 114.1 m³ (91% of inflow)Center-of-Mass det. time= 32.2 min ( 47.7 - 15.5 )
Volume Invert Avail.Storage Storage Description
#1 0.000 m 171.6 m³ 10.00 mW x 5.72 mL x 3.00 mH Prismatoid
Device Routing Invert Outlet Devices
#1 Primary 0.190 m 100 mm Vert. Orifice/Grate C= 0.800
Primary OutFlow Max=0.0326 m³/s @ 0.46 hrs HW=1.615 m (Free Discharge)1=Orifice/Grate (Orifice Controls 0.0326 m³/s @ 4.16 m/s)
Pond 17P: Stormwater Cistern
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.11
0.1
0.09
0.08
0.07
0.06
0.05
0.04
0.03
0.02
0.01
0
Inflow Area=3,118.0 m²
Peak Elev=1.615 m
Storage=92.4 m³
0.0995 m³/s
0.0326 m³/s
Toronto 100-Year Duration=21 min, Inten=138.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 110HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Link 2L: Outflow
Inflow Area = 7,004.0 m², 0.00% Impervious, Inflow Depth = 24 mm for 100-Year eventInflow = 0.1345 m³/s @ 0.17 hrs, Volume= 169.5 m³Primary = 0.1345 m³/s @ 0.17 hrs, Volume= 169.5 m³, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 0.00-4.00 hrs, dt= 0.01 hrs
Link 2L: Outflow
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.14
0.12
0.1
0.08
0.06
0.04
0.02
0
Inflow Area=7,004.0 m²
0.1345 m³/s0.1345 m³/s
Toronto 100-Year Duration=21 min, Inten=138.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 111HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Link 7L: Total Outflow
Inflow Area = 3,857.0 m², 0.00% Impervious, Inflow Depth > 33 mm for 100-Year eventInflow = 0.0345 m³/s @ 0.44 hrs, Volume= 126.9 m³Primary = 0.0345 m³/s @ 0.44 hrs, Volume= 126.9 m³, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 0.00-4.00 hrs, dt= 0.01 hrs
Link 7L: Total Outflow
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.035
0.03
0.025
0.02
0.015
0.01
0.005
0
Inflow Area=3,857.0 m²
0.0345 m³/s0.0345 m³/s
Toronto 100-Year Duration=21 min, Inten=138.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 112HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Link 9L: Total North Uncontrolled Flow
Inflow Area = 42.0 m², 0.00% Impervious, Inflow Depth = 44 mm for 100-Year eventInflow = 0.0015 m³/s @ 0.17 hrs, Volume= 1.8 m³Primary = 0.0015 m³/s @ 0.17 hrs, Volume= 1.8 m³, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 0.00-4.00 hrs, dt= 0.01 hrs
Link 9L: Total North Uncontrolled Flow
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.002
0.001
0.001
0.001
0.001
0.001
0.000
0.000
0
Inflow Area=42.0 m²
0.0015 m³/s0.0015 m³/s
Toronto 100-Year Duration=21 min, Inten=138.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 113HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Link 18L: Total Outflow
Inflow Area = 3,149.0 m², 0.00% Impervious, Inflow Depth > 37 mm for 100-Year eventInflow = 0.0330 m³/s @ 0.45 hrs, Volume= 115.7 m³Primary = 0.0330 m³/s @ 0.45 hrs, Volume= 115.7 m³, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 0.00-4.00 hrs, dt= 0.01 hrs
Link 18L: Total Outflow
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.035
0.03
0.025
0.02
0.015
0.01
0.005
0
Inflow Area=3,149.0 m²
0.0330 m³/s0.0330 m³/s
Toronto 100-Year Duration=21 min, Inten=138.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 114HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Link 19L: Total South Uncontrolled Flow
Inflow Area = 31.0 m², 0.00% Impervious, Inflow Depth = 44 mm for 100-Year eventInflow = 0.0011 m³/s @ 0.17 hrs, Volume= 1.4 m³Primary = 0.0011 m³/s @ 0.17 hrs, Volume= 1.4 m³, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 0.00-4.00 hrs, dt= 0.01 hrs
Link 19L: Total South Uncontrolled Flow
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.001
0.001
0.001
0.001
0.001
0.001
0.001
0.000
0.000
0.000
0.000
0
0
Inflow Area=31.0 m²
0.0011 m³/s0.0011 m³/s
Toronto 100-Year Duration=21 min, Inten=138.3 mm/hrPhase 2 Site Runoffs V_02 Printed 03/06/2016Prepared by MMM Group Limited
Page 115HydroCAD® 9.10 s/n 06627 © 2009 HydroCAD Software Solutions LLC
Summary for Link 20L: Total Site Outflow
Inflow Area = 7,006.0 m², 0.00% Impervious, Inflow Depth > 35 mm for 100-Year eventInflow = 0.0676 m³/s @ 0.45 hrs, Volume= 242.6 m³Primary = 0.0676 m³/s @ 0.45 hrs, Volume= 242.6 m³, Atten= 0%, Lag= 0.0 min
Primary outflow = Inflow, Time Span= 0.00-4.00 hrs, dt= 0.01 hrs
Link 20L: Total Site Outflow
InflowPrimary
Hydrograph
Time (hours)43210
Flo
w (m
³/s
)
0.07
0.06
0.05
0.04
0.03
0.02
0.01
0
Inflow Area=7,006.0 m²
0.0676 m³/s0.0676 m³/s