Qila Energy’s Design of AD plant

Page 2: Step by step powerpoint presentation
Page 3: Step by step powerpoint presentation

The biogas process

Page 4: Step by step powerpoint presentation

Benefits of our pre-treatment Turbo Tank

Hydrolysis – 50C - acid environment

Methanogenesis – 40C neutral PH

Harvest biogas faster – in just 4 weeks

Feed 20% less feedstock

Greater biogas yields,15–30% more

Page 5: Step by step powerpoint presentation

1 - Feedstock is taken from the clamps and loaded into the feeder

Page 6: Step by step powerpoint presentation

2 - The feedstock is moved to the Vogelsang energy jet and RotaCut

Page 7: Step by step powerpoint presentation

3 - The liquid feedstock is moved to the Turbo Tank

2-3 days

Hydrolysis50-55

°C

Page 8: Step by step powerpoint presentation

4. The liquid feedstock is then transferred to the main digester tank – Biogas production

15-20 days

Methanogenesis

41-44oC

Page 9: Step by step powerpoint presentation

5. Some of the biogas is used to generate electricity using a Combined Heat and Power (CHP) unit.

The AD plant will run on self-generating power

Each year the CHP will prodce - 4,000,000 kWh/a

electricity

4,700,000 kWh of thermal energy

Page 10: Step by step powerpoint presentation

6. Biogas is moved to the upgrader, where it is cleaned to generate Biomethane

The biomethane should contain at least 97% methane to be entered into the grid. Need to ensure consistency on 97/98%.

Page 11: Step by step powerpoint presentation

7. Biomethane is moved to the Grid Entry unit

This unit monitors the quality of the gas and ensures that it conforms to the specifications and pressure required within the grid.

To bring the biomethane up to the same energy content, the Grid Entry Unit adds propane (approximately 4%) must be added at the point of injection. An odorant must also be added for health and safety reasons.

Page 12: Step by step powerpoint presentation

8. Biomethane enters the National Gas Grid and reaches the end user

Once in the grid, it is easy to arrange to sell the gas to residential and industrial customers

Page 13: Step by step powerpoint presentation

9. Digestate is removed from the main digester tank, separated and returned to farm land

Page 14: Step by step powerpoint presentation

For more information about Qila Energy’s design in AD plant, please contact 020 3603 3016, email us on

[email protected] or visit our website Qilaenergy.com