Page 1: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Step-by-Step GuideEnterprise Singapore Grant Portal (ESGP)

1

Page 2: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Content Page

1. Login ( Activate CorpPass)2. Applying for PI-Land (Productivity Improvement – Land

Productivity)3. Accepting Letter of Offer4. Cash Advancement via ESGP5. Submission of Amendment via ESGP6. Submitting Claim via ESGP7. Check Grant Status and History8. Project Abort

Page 3: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Application for CDG

Please access the Business Grant Portal to submit your application

Application for Productivity Improvement – Land Productivity will still be processed via Enterprise Singapore Grant Portal

Please also note that all subsequent amendments and claims for CDG will be processed via Enterprise Singapore Grant Portal

Page 4: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

A copy of Step-by-Step Guide is attached here for reference. Please click here to find out on using ESGP.

Copy of ESGP Step-by-Step Guide

Page 5: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Login

Companies can access the ESGP via the following link: https://grantportal.enterprisesg.gov.sg

Companies will need to access ESGP using CorpPass

Click on the “Login with CorpPass “

Applicant will log in to ESGP using CorpPass

Users with CEO/Proxy roles can submit application

Page 6: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Queries on CorpPass

Enter company‘s UEN number and CorpPass Password Users accessing ESGP via CorpPass must be registered users with CorpPass

account To register a CorpPass account, please visit https://www.corppass.gov.sg

Page 7: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Roles Description

CEO This role can create, amend and submit applications, amendments and

claims and accept letters of offer and amendment letters.

Proxy This role acts on behalf of the CEO. Role can create, amend and submit

applications, amendments, claims and accept letters of offer and

amendment letters.

Officer This role can create and amend applications, amendments and

claims. However, officer cannot submit the applications, amendments

and claims.

There are three types of users for ESGP : CEO, Proxy and Officer. Please refer tothe attached table for description of the roles.

Roles for ESGP

1) Log into CorpPass by CorpPass Admin to assign ESGP as e-services

2) Assign the respective roles

Page 8: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Roles for ESGP

Page 9: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Roles for ESGP

Page 10: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

2. Project Application

(Productivity Improvement – Land Productivity)

Back to Content Page

Applying for PI-LandEnterprise Singapore Grant Portal (ESGP)

Page 11: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Company’s Dashboard after logging in

Shows the Actions buttons that can be triggered for “live” projects

Page 12: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Project Application

• Click on the Productivity Improvement – Land Productivity to apply

Page 13: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Project Application

• Under “Eligibility Check” tab, fill in all necessary information.

• All fields denoted with an asterisk are mandatory.

Page 14: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Project Application

• Mouse over the green information icon for more information regarding the field.

Page 15: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Project Application

• Click on the “Next” button to proceed.

Step 1: Fill in all necessary information

Step 2: Click “Next”

Page 16: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Project Application

• Under “Company Information” tab, fill in all necessary information.

• All fields denoted with an asterisk are mandatory.

Page 17: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Project Application

• Details will be auto-populated upon entering the Unique Entity Number.

• All fields denoted with an asterisk are mandatory.

Page 18: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Project Application

• Click on the “Add record” button to attach a soft copy of ACRA document and Financial Statements.

• Users should note the following:

– ACRA document should be the latest and not more than 6 months old.

– Financial statements should be the latest audited and not more than 1 year old.

Page 19: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Project Application

• A pop up window will appear for users to attach documents. Click on “Browse” button to select the document from your computer.

Page 20: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Project Application

• Select the file to be uploaded and click on the “Upload” button to proceed.

Page 21: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Project Application

• Determine the “Attachment Type” for the document selected and click on the “Save” button.

Step 1: Select the attachment type

Step 2: Click “Save”

Page 22: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Project Application

• Documents uploaded will appear. Click “Next” to proceed.

Click “Next” to proceed

Page 23: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Project Application

• Under “Project Information” tab, select an estimated project cost from the dropdown list.

• All fields denoted with an asterisk are mandatory.

Page 24: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Project Application

• Upon selecting estimated project cost “Up to 45,000”, a pop up message will appear to inform users that the application form for grant support of $30,000 or less has been simplified.

• Click on the “OK” button to dismiss the pop-up after reading.

Page 25: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Project Application

• Click on the calendar icon to select the Project Commencement Date and Project Completion Date.

• Do note that the project should commence at least one working day after application submission.

• Project duration is automatically computed, and will be used as a basis for claim submissions.

Page 26: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Project Application• If consultancy is required, do ensure consultancy information is being

entered into this section.

• This information will be populated under Project Cost tab in the later sections.

Page 27: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Project Application

• Consultancy details will appear.

Page 28: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Project Application – For Projects with Costs <$45,000

• In the Quantitative Information (Based on last FY) section, fill in all necessary information.

• All fields denoted with an asterisk are mandatory.

Page 29: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Project Application – For Projects with Costs <$45,000

• Mouse over the green information icon for more information regarding the field.

Page 30: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Project Application – For Projects with Costs <$45,000• In the Project Details section, fill in all necessary information.

• All fields denoted with an asterisk are mandatory.

• It is important to note that each question should be limited to 150-200 words.

• Click “Next” to proceed.

• The steps for filling in Project Costs will be described in details in the later section.

Page 31: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Project Application with Project Costs >$100,000

• For estimated project cost “Up to 100,000 / Up to 150,000 / More than

150,000”, a different form will be populated.

• Fill in all project related information.

• All fields denoted with an asterisk are mandatory.

Page 32: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Project Application

• Click on the calendar icon to select the Project Commencement Date and Project Completion Date.

• Do note that the project should commence at least one working day after application submission.

• Project duration is automatically computed, and will be used as a basis for claim submissions.

Page 33: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Project Application

• Click on “Add record” to upload soft copy of your Project Proposal and Other Supporting Documents.

• A pop up window will appear for users to attach documents. Click on “Browse” button to select the document from your computer. Click “Upload” to upload the documents.

Page 34: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Project Application

• If consultancy is required, do ensure consultancy information is being entered into this section.

• This information will be populated under Project Cost tab in the later sections.Step 1: Select “Yes” if consultancy is required

Step 2: Click “Add record” to upload consultancy details

• To enter details for Land Productivity

Page 35: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Project Application• To enter information under “Project Impact”, click on the wordings to enter

information.• A pop up window will appear for users to enter information.• All fields denoted with an asterisk are mandatory. Please key values for both tables and

click “Save”.

Click on the wordings

Page 36: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Project Application

• Under “Project Costs” tab, select the checkbox with relevant project costs.

• Click the “Add record” button to input information.

Step 1: Select checkbox

Step 2: Click “Add record” button

Page 37: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Project Application

• A pop up window will appear for users to enter information.

• All fields denoted with an asterisk are mandatory.

• Click “Save”.

Step 1: Fill in all necessary information

Step 2: Click “Save”

Page 38: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Project Application

• To input information under “Consultancy” field, select the checkboxbeside it.

• Click the “Add record” button to input information.

Step 1: Select checkbox

Step 2: Click “Add record” button

Page 39: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Project Application

• A pop up window will appear for users to enter information.

• All fields denoted with an asterisk are mandatory.

• It is important to note that users have to enter the consultancy firminformation under “Project Information” tab in order to see theconsultancy firm listed here.

Step 1: Fill in all necessary information

Step 2: Click “Save”

Page 40: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Project Application

• The portal automatically adds up the Total Project Cost for all project cost components entered.

Page 41: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Project Application

• Scroll to the top and click on “Submission Check” to ensure all necessary information has been filled in.

Page 42: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Project Application

• If it indicates that there is no error, users can click on “Submit” to send theapplication through to Enterprise Singapore.

• Alternatively, users can click on “Save” to retain the applicationinformation for submission on a later date.

Step 1: Check if there are errors

Step 2: If there are no errors, click on “Submit” for

SPRING Singapore to process the application

Page 43: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Project Application

• A declaration page will appear. To proceed, ensure that you have agreed to the following and that all checkboxes are checked before clicking on the “Accept” icon.

Page 44: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

2. Project Application

(Productivity Improvement – Land Productivity)

Back to Content Page

Accepting Letter of Offer

Page 45: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Letter of Offer

• Once the project has been approved, the Company Dashboard will display an option to “Accept Letter of Offer”.

Page 46: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Letter of Offer

• Under the “Tasks” panel, a notification will appear to remind users to accept the Letter of Offer.

• To accept, click “Accept Letter of Offer”.

A notification appears to remind

users to accept Letter of Offer

Page 47: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Letter of Offer

• The Letter of Offer would be displayed.

• Users have to select the checkbox to indicate acceptance to terms and conditions stated in this Letter of Offer and all enclosures.

• To proceed, click “Accept”.

Page 48: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Letter of Offer

• A pop up message will appear to confirm acceptance of terms and conditions. Click “Ok” to proceed.

Page 49: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

2. Project Application

(Productivity Improvement – Land Productivity)

Back to Content Page

Cash Advancement via ESGP

Page 50: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Cash Advancement

• Letter of offer is accepted in Business Grant Portal

• For projects with cash advancement components, grant applicant is to log into Enterprise Singapore Grant Portal to submit cash advancement

Page 51: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Cash Advancement

• A tab “Cash Advancement” appears.

• To upload proof of project commencement, click the “Add record” button.

• All fields denoted with an asterisk are mandatory.

Page 52: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Cash Advancement

• After filling in all mandatory fields, click “Submit”.

Page 53: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Cash Advancement

• A pop up message will appear to confirm acceptance of terms and conditions. Click “Ok” to proceed.

Page 54: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

2. Project Application

(Productivity Improvement – Land Productivity)

Back to Content Page

Submission of Amendment via ESGP

Page 55: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Submitting Amendment via ESGP

Amendment can be triggered via the “Request Amendment” link

Page 56: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Submitting Amendment via ESGP

For Coy Info tab, changes can be made to Coy name, Address and Contact Person Details

Page 57: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Amendment of Project Information Coy can provide updates to any changes in the approved parameters accordingly (e.g. project

deliverables, project/claim extensions, revisions to project costs, etc.) under project information tab

Page 58: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

For changes to project period or extension to claim expiry date, applicant may amend accordingly

Applicant is given additional 3 months from claim lapsed date to submit an amendment. Do note that each project’s claim period will be allowed a one-time extension of 6 months (By checking “Yes”)

Amendment of Project Information

Page 59: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Amendment of Project Information

Add Record for new cost items or click on Equipment to input the current cost item

Page 60: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Pop-up dialogue box

Enter the necessary data in the pop-up dialogue box. Changes will be indicated in blue font Requested new grant will be auto-computed based on the same support level as per approved

application

Amendment of Project Information

Page 61: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Amendment of Project Information If there is any changes to consultancy (e.g. new consultant), the consultant table need to

be filled up before coy can make add the new consultancy firm into Consultancy Cost item. This process is similar to application submission

To amend details of consultancy firm

Page 62: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Applicant to indicate “Reasons for Amendment” Applicant may attach supporting documents for Amendment Click “Save” to save the amendment or Click “Submit” to proceed

Click “OK” and amendment is submitted to ESG

Important Note:Only users holding role of Proxy/CEO will be able to see the “Submit” ButtonIf user is holding the role of Officer, there is no “Submit” button, please update CorpPass

Submitting Amendment

Page 63: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Submitting Amendment

For amendment in draft mode click “Edit Draft Amendment” “Edit” User may delete or submit the amendment

Page 64: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

2. Project Application

(Productivity Improvement – Land Productivity)

Back to Content Page

Submitting Claim Via ESGP

Page 65: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Claims Submission

• Identify the claim type that is applicable to you according to Para 3.18 in the Letter of Offer.

• The claim types are:

– Interim claims on declaration

– Claims on reimbursement basis

Page 66: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Claims Submission

• For interim claims on declaration, users are required to click on “Submit Claims” under the “Current Projects” panel.

Page 67: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Claims Submission

• Under “Project Information” tab, fill in all necessary information.

• All fields denoted with an asterisk are mandatory.

Page 68: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Claims Submission

• Under “Claim Information” tab, fill in all necessary information.

• All fields denoted with an asterisk are mandatory.

• Click “Submit”.

Step 2: Click “Submit”

Step 1: Fill in Interim Claim Request

Page 69: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Claims Submission• A declaration page will appear. To proceed, ensure that you have agreed to

the following and that all checkboxes are checked before clicking on the “Accept” icon.

Page 70: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Claims Submission

• For claims on reimbursement basis, it is recommended for users to carry out the following activities before starting the claim submission process:

– Prepare the required documents according to the Claim Submission Checklist

– Engage an auditor from SPRING’s Pre-Qualified Panel to verify claim submission, unless expressly exempted by SPRING.

i. Contact the auditors for quotation

ii. Appoint an auditor

• Send all the claim supporting documents to the auditor

Page 71: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Claims Submission

• Once all relevant documents have been prepared, users can proceed with claim submission by clicking “Submit Claims” under “Current Projects” in the homepage.

Page 72: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Claims Submission

• Under “Project Information” tab, fill in all necessary information.

• All fields denoted with an asterisk are mandatory.

Page 73: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Claims Submission

Coy need to approach Panel of Auditors to get a quotation on audit fees and indicate the appointed auditor in the claims submission

Please indicate claim type (Final or Interim) and Claim period

i. Select the appointed auditorii. If wrong auditor is selected, applicant

will need to withdraw the claim

Page 74: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Claims Submission

• Under “Claim Information” tab, fill in all necessary information.

• All fields denoted with an asterisk are mandatory.

• To edit the table under “Claim Summary”, click on the text.

Page 75: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Claims Submission

• A pop up window will appears for users to enter the actual expenses paid. Click “Save”.

Step 1: Fill in Actual Expenses Paid

Step 2: Click “Save”

Page 76: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Claims Submission

• Claim amount will be reflected under “Claim Summary” table.

Page 77: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Claims Submission

• Scroll to the top and click on “Submit” for Enterprise Singapore to process the claim.

Page 78: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Claims Submission

• Alternatively, users can click on “Save” to retain the application information for later submission.

Page 79: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Claims Submission• After submission, a message will appear to display the claims declaration. To

proceed, ensure that you have agreed to the following and that all checkboxes are checked before clicking on the “Accept” icon.

Page 80: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

2. Project Application

(Productivity Improvement – Land Productivity)

Back to Content Page

Check Grant Status and History

Page 81: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Check Grant Status & History

• At the Company Dashboard, users can view their grant application status under the “Current Projects” panel. A green dot indicates the current project status on the timeline.

Page 82: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Check Grant Status & History

• To view more details about the project grant, click on “View Details”.

Page 83: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Check Grant Status & History

• Click on “Grant History” tab to access all grant history records.

Page 84: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Check Grant Status & History

• All grant records will be displayed.

Page 85: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

2. Project Application

(Productivity Improvement – Land Productivity)

Back to Content Page

Project Abort

Page 86: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Project Abort

Trigger Abort Request

• “Abort Request” is available in company’s dashboard. Click on “View Details” next to theproject timeline to get to the below viewo There should not be any pending amendment/claims entries

Page 87: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Project Abort

Summary of any preceding disbursements

Provide reason for project abortion and relevant supporting docs (such as email correspondences)

• System triggers a warning that refund may be required for any disbursements made• Indicate reasons and supporting docs for project abortion for submission• Click Submit. Note once abort request is submitted, it cannot be withdrawn

Page 88: Step-by-Step Guide Step-by-step User Guide.pdfFor changes to project period or extension to claim expiry date, applicant may amend accordingly Applicant is given additional 3 months

Help and Support

Enterprise Singapore Grant Portal

Helpdesk Support

Handle issues relating to usage andtechnical issues encountered in ESGP

CorpPass Helpdesk Support

Telephone Hotline: +(65) 6643 0577Email: [email protected]

Business Grants Portal Helpdesk Support

Telephone Hotline: +(65) 6898 1800* Managed by SME Infoline

Telephone Hotline: +(65) 6898 1800• Managed by SME InfolineEmail: [email protected]